MA34864B1 - METHOD FOR BUILDING DOCK CORONY BEAM WITH FALSE DOOR - Google Patents

METHOD FOR BUILDING DOCK CORONY BEAM WITH FALSE DOOR

Info

Publication number
MA34864B1
MA34864B1 MA35096A MA35096A MA34864B1 MA 34864 B1 MA34864 B1 MA 34864B1 MA 35096 A MA35096 A MA 35096A MA 35096 A MA35096 A MA 35096A MA 34864 B1 MA34864 B1 MA 34864B1
Authority
MA
Morocco
Prior art keywords
corony
false door
building dock
prefabricated elements
dock
Prior art date
Application number
MA35096A
Other languages
Arabic (ar)
French (fr)
Inventor
Serge Michel Paloumet-Bourda
Original Assignee
Serge Michel Paloumet-Bourda
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Serge Michel Paloumet-Bourda filed Critical Serge Michel Paloumet-Bourda
Priority to MA35096A priority Critical patent/MA34864B1/en
Priority to PCT/MA2013/000021 priority patent/WO2014017891A1/en
Publication of MA34864B1 publication Critical patent/MA34864B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/066Quays
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/365Stop-end shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/06Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Collating Specific Patterns (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

POUTRE DE COURONNEMENT DE QUAI BETONNEE SUR ELEMENTS PREFABRIQUES FORMANT COFFRAGELE PRINCIPE REPOSE SUR LA CONCEPTION D'ÉLÉMENTS PRÉFABRIQUÉS INCORPORÉS POSÉS ET RÉGLÉS PARFAITEMENT AVANT BÉTONNAGE PERMETTANT UNE MAÎTRISE PARFAITE DE LA QUALITÉ DU BÉTON IMMERGÉ RESPECTANT LA FISSURATION DE RETRAIT DU MASQUE AVANT EN AUTORISANT UN QUAI DE TEMPS GLOBAL DE RÉALISATION DE 60 %.BEAM CROWN BEAM BETWEEN PREFABRICATED ELEMENTS FORMING FORMWORK THE PRINCIPLE IS BASED ON THE DESIGN OF PREFABRICATED ELEMENTS INCORPORATED AND SET PERFECTLY BEFORE CONCRETING FOR PERFECT CONTROL OF THE QUALITY OF SUBMERGED CONCRETE RESPECTING THE CRACKING OF FRONT MASK REMOVAL BY AUTHORIZING A WHARF GLOBAL TIME OF REALIZATION OF 60%.

MA35096A 2012-07-23 2012-07-23 METHOD FOR BUILDING DOCK CORONY BEAM WITH FALSE DOOR MA34864B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
MA35096A MA34864B1 (en) 2012-07-23 2012-07-23 METHOD FOR BUILDING DOCK CORONY BEAM WITH FALSE DOOR
PCT/MA2013/000021 WO2014017891A1 (en) 2012-07-23 2013-07-16 Quay capping beam that is concreted on prefabricated formwork-forming elements

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
MA35096A MA34864B1 (en) 2012-07-23 2012-07-23 METHOD FOR BUILDING DOCK CORONY BEAM WITH FALSE DOOR

Publications (1)

Publication Number Publication Date
MA34864B1 true MA34864B1 (en) 2014-02-01

Family

ID=49182471

Family Applications (1)

Application Number Title Priority Date Filing Date
MA35096A MA34864B1 (en) 2012-07-23 2012-07-23 METHOD FOR BUILDING DOCK CORONY BEAM WITH FALSE DOOR

Country Status (2)

Country Link
MA (1) MA34864B1 (en)
WO (1) WO2014017891A1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111005323A (en) * 2020-01-02 2020-04-14 中铁十九局集团第六工程有限公司 Supporting method and device for variable-slope cover beam end mold of highway bridge engineering
CN112049024A (en) * 2020-09-29 2020-12-08 山东双端数字科技有限公司 Standardized structure for bridge lower cover beam template
CN113106873A (en) * 2021-04-14 2021-07-13 中铁二局第一工程有限公司 Standardized construction system of large-span steel trestle
CN114232484B (en) * 2021-12-13 2024-04-12 上海绿地建设(集团)有限公司 Construction method of municipal viaduct bridge crossing heavy traffic road section

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE8417175U1 (en) * 1984-06-06 1984-08-30 Weru Gmbh & Co Kg, 7062 Rudersberg CEILING EDGE
CH675891A5 (en) * 1988-07-25 1990-11-15 Giulio Albanese
DE19758238A1 (en) * 1997-12-30 1999-07-29 Giulio Albanese Formwork system
US6902353B2 (en) * 2001-04-19 2005-06-07 Ned H. Nelson Top block for retaining wall

Also Published As

Publication number Publication date
WO2014017891A1 (en) 2014-01-30

Similar Documents

Publication Publication Date Title
MA34864B1 (en) METHOD FOR BUILDING DOCK CORONY BEAM WITH FALSE DOOR
MY197748A (en) Self-climbing system, self-climbing unit and method for moving such a self-climbing unit on a concrete building structure
ZA201908153B (en) Construction method for high-ductility masonry wall having reinforced joint mortar layer
EP3851618A4 (en) Device for alternately jacking added storey of building with high-strength concrete columns and steel slideways and construction method therefor
PH12015500913A1 (en) Method for constructing cylindrical tank
SG10201805031TA (en) Hollow cylindrical pier for fixing offshore platform structure to bed and method of installing and constructing same
DK3259405T3 (en) PROCESS FOR BUILDING A FOUNDATION INCLUDING A STEEL MONTH AND A BETONDEL AND AN ASSOCIATED FOUNDATION FOR BUILDING WORK
MA38552A1 (en) Method for installing a hollow concrete tower consisting of more than one segment and corresponding hollow concrete tower
MX366797B (en) Prefabricated footing for wind turbines.
WO2016020932A3 (en) Deployable pre-fabricated reinforcement cage system
PH12017501962A1 (en) Scour protection for an underwater bottom alongside a quay wall, and method for providing the same
KR101715359B9 (en) Method of aseismic reinforcement for existing building structure using concrete filled steel tube
WO2016209067A3 (en) Method for repairing an intake for a storage dam
FR3050474B1 (en) DEVICE FOR ACCESSING A BASIN OF A SWIMMING POOL
KR102213088B9 (en) Precast concrete girder for used by continuous construction method
HUP1700206A1 (en) Portable structure for prefabrication of prestressed reinforced concrete beams
RU2014151563A (en) INSTALLATION FOR THE PRODUCTION OF THE CONCRETE PANEL EQUIPPED WITH FACING ELEMENTS
AU2012101774A4 (en) Revised design innovation of transportable slab, that will eliminate the need to use concrete disks(donoughnuts) on site, reduce slab weight, increase slab installation speed, eliminate the need to swap jacks during the process of installing slab, eliminate the risk of coring through ring beam and reducing slab structural integrity. Revised design innovation will reduce manual handling of concrete disks on site.
FR3024187B1 (en) DEVICE FOR THE INSTALLATION OF A SENSOR, PARTICULARLY OPTICAL, THROUGH A THIN WALL
AU2017903344A0 (en) A methodology during the process of constructing a reinforced concrete building, which allows prefabricated volumetric bathroom modules to be installed on the level of the latest slab pour on the same working day upon which the pouring of columns and erection of slab falsework is commenced for construction of the concrete structure above that particular slab pour.
FR2994205B1 (en) METHOD FOR PRODUCING WALLS OF A SWIMMING POOL, AND CONSTRUCTION DEVICE FOR CARRYING OUT SAID METHOD
Langdon F31 Precast Concrete Sills/Lintels/Copings/Features
ES1308222Y (en) Floating platform for the construction of large concrete structures.
PL3730263T3 (en) Method for producing a plurality of cast elements made of prestressed concrete
Allaix et al. Random fields for the modeling of deteriorated structures