AU2017903344A0 - A methodology during the process of constructing a reinforced concrete building, which allows prefabricated volumetric bathroom modules to be installed on the level of the latest slab pour on the same working day upon which the pouring of columns and erection of slab falsework is commenced for construction of the concrete structure above that particular slab pour. - Google Patents

A methodology during the process of constructing a reinforced concrete building, which allows prefabricated volumetric bathroom modules to be installed on the level of the latest slab pour on the same working day upon which the pouring of columns and erection of slab falsework is commenced for construction of the concrete structure above that particular slab pour.

Info

Publication number
AU2017903344A0
AU2017903344A0 AU2017903344A AU2017903344A AU2017903344A0 AU 2017903344 A0 AU2017903344 A0 AU 2017903344A0 AU 2017903344 A AU2017903344 A AU 2017903344A AU 2017903344 A AU2017903344 A AU 2017903344A AU 2017903344 A0 AU2017903344 A0 AU 2017903344A0
Authority
AU
Australia
Prior art keywords
slab
pour
falsework
commenced
erection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
AU2017903344A
Inventor
David Anthony Wheeler
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Project Initiation and Facilitation Pty Ltd
Original Assignee
Project Initiation and Facilitation Pty Ltd
Filing date
Publication date
Application filed by Project Initiation and Facilitation Pty Ltd filed Critical Project Initiation and Facilitation Pty Ltd
Publication of AU2017903344A0 publication Critical patent/AU2017903344A0/en
Abandoned legal-status Critical Current

Links

AU2017903344A 2017-08-18 A methodology during the process of constructing a reinforced concrete building, which allows prefabricated volumetric bathroom modules to be installed on the level of the latest slab pour on the same working day upon which the pouring of columns and erection of slab falsework is commenced for construction of the concrete structure above that particular slab pour. Abandoned AU2017903344A0 (en)

Publications (1)

Publication Number Publication Date
AU2017903344A0 true AU2017903344A0 (en) 2017-08-31

Family

ID=

Similar Documents

Publication Publication Date Title
WO2013009529A3 (en) Foundation system for bridges
MX2015015447A (en) Method and system for rapid construction of structurally reinforced concrete structures using prefabricated assemblies and method of making the same.
GB2570578B (en) Precast concrete formwork, floor system and a method of construction
CN102094525A (en) Method for constructing reinforced concrete lintel
WO2016020932A3 (en) Deployable pre-fabricated reinforcement cage system
AU2017903344A0 (en) A methodology during the process of constructing a reinforced concrete building, which allows prefabricated volumetric bathroom modules to be installed on the level of the latest slab pour on the same working day upon which the pouring of columns and erection of slab falsework is commenced for construction of the concrete structure above that particular slab pour.
KR101715359B9 (en) Method of aseismic reinforcement for existing building structure using concrete filled steel tube
WO2012123964A3 (en) Casting designer walls for building by using moulds
CN203668894U (en) Concrete prefabricated form structure allowing rapid installation
EP4273344A3 (en) Reinforcing framework and slab design
KR102213088B9 (en) Precast concrete girder for used by continuous construction method
PL3121350T3 (en) Prefabricated formwork element, formwork obtained and method for manufacturing a slab of a construction with a pass through opening delimited by said formwork
GB201807023D0 (en) Method of casting a textured concrete walling slab
CN204552090U (en) Accommodation stairway joint plate
CN209339301U (en) A kind of quick partition wall of structure containing water and pipe culvert
PH22017000941Y1 (en) A panel wall structure construction system
AU2019904251A0 (en) An innovative methodology undertaken during the process of constructing a reinforced concrete building, which allows Table-form false-work to be transported across a recently poured concrete slab on the second calendar day after that particular pour had been undertaken. The methodology is specifically applicable to that type of Table-Form false-work, which is assembled using Table-Heads into which the top plates of its props can be so securely locked that said props do not require to have any cross-bracing between them.
HU5558U (en) Prefabricated concrete building components especially for footing construction
FR3001484B1 (en) METHOD FOR PRODUCING A WATER BASIN, ESPECIALLY SWIMMING POOL, FROM PREFABRICATED CONCRETE MODULES
PH22014000325Y1 (en) A method of installing a jointless prefabricated slab and means of producing thereof
MY193242A (en) A formwork panel assembly
CN204311347U (en) Discharge structure
HUP1900090A1 (en) Method for constructing wall structure using hemp concrete bricks
HU5573U (en) Prefabricated reinforced concrete building unit, in particular for retaining wall building
AU2018902742A0 (en) Advanced Formwork System D.E.B Dropped Edge Beam. Is a far superior system used in the construction of concrete slabs that require a D.E.B. Dropped Edge Beams as a method of that construction