KR940002426A - Bridge deck construction method that moves the formwork along the rail - Google Patents

Bridge deck construction method that moves the formwork along the rail Download PDF

Info

Publication number
KR940002426A
KR940002426A KR1019920012713A KR920012713A KR940002426A KR 940002426 A KR940002426 A KR 940002426A KR 1019920012713 A KR1019920012713 A KR 1019920012713A KR 920012713 A KR920012713 A KR 920012713A KR 940002426 A KR940002426 A KR 940002426A
Authority
KR
South Korea
Prior art keywords
bridge deck
construction method
moves
construction
work section
Prior art date
Application number
KR1019920012713A
Other languages
Korean (ko)
Inventor
김성남
Original Assignee
김성남
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김성남 filed Critical 김성남
Priority to KR1019920012713A priority Critical patent/KR940002426A/en
Publication of KR940002426A publication Critical patent/KR940002426A/en

Links

Abstract

교량상판을 타설하는 공사에서 한개의 작업구간에 필요한 지보공을 현장 조립하여 제작하는 공지한 것에 있어서 그 상부에 설치되는 교량상판 거푸집 지보공을 유압작키를 이용하여 들어올리면서 고임틀로 고여설치하고 탈형시에는 유압작키로 지지시키면서 고임틀을 제거한후 하단의 로울러를 레일위에 얹혀놓고 한개의 작업구간에서 인접작업구간으로 직접이동할 수 있게 함을 특징으로 한 교량상판 시공방법임.In the well-known work of assembling the support work required for one work section in the construction of placing the bridge deck, the bridge deck formwork installed on the upper part is lifted up by using a hydraulic working key, It is a bridge deck construction method that can be moved directly from one work section to adjacent work section by removing rollers and supporting them with hydraulic operation keys.

Description

거푸집 지보공을 레일을 따라 이동케한 교량상판 시공방법Bridge deck construction method that moves the formwork along the rail

본 내용은 요부공개 건이므로 전문내용을 수록하지 않았음Since this is an open matter, no full text was included.

제1도는 본 발명에서 사용되는 고정식 지보공의 상부에 레일을 설치한 상태의 사시도.1 is a perspective view of a state in which a rail is installed on the top of the fixed supporter used in the present invention.

제2도는 본 발명 거푸집 지보공의 설치상태도.2 is an installation state of the present invention formwork.

제3도는 제2도의 A-A선 종단면도.3 is a longitudinal cross-sectional view taken along the line A-A of FIG.

제4도는 본 발명 거푸집 지보공의 확대도.4 is an enlarged view of the present invention formwork.

Claims (1)

본 발명은 교량상판을 타설하는 공사에서 한개의 작업구간에 필요한 지보공을 현장 조립하여 제작하는 것에 있어서 그 상부에 설치되는 교량상판 거푸집 지보공을 유압작키를 이용하여 들어올리면서 고임틀로 고여설치하고 탈형시에는 유압작키로 지지시키면서 고임틀을 제거한 후 하단의 로울러를 레일위에 얹혀놓고 한개의 작업구간에서 인접작업구간으로 직접이동할수 있게 함을 특징으로 하는 거푸집 지보공을 레일을 따라 이동케한 교량상판 시공방법.The present invention in the construction of assembling the support work required for one work section in the construction of the bridge top plate in the construction of the bridge deck formwork to be installed on the upper portion by using a hydraulic working key while lifting up and demolishing The bridge deck construction method which moves the formwork to move along the rails is characterized in that the rollers at the bottom are placed on the rails and supported by the hydraulic operation keys, and then the direct moving from one work section to the adjacent work section is carried out. . ※ 참고사항 : 최초출원 내용에 의하여 공개하는 것임.※ Note: The disclosure is based on the initial application.
KR1019920012713A 1992-07-16 1992-07-16 Bridge deck construction method that moves the formwork along the rail KR940002426A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019920012713A KR940002426A (en) 1992-07-16 1992-07-16 Bridge deck construction method that moves the formwork along the rail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019920012713A KR940002426A (en) 1992-07-16 1992-07-16 Bridge deck construction method that moves the formwork along the rail

Publications (1)

Publication Number Publication Date
KR940002426A true KR940002426A (en) 1994-02-17

Family

ID=67147396

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019920012713A KR940002426A (en) 1992-07-16 1992-07-16 Bridge deck construction method that moves the formwork along the rail

Country Status (1)

Country Link
KR (1) KR940002426A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200020182A (en) 2018-08-16 2020-02-26 이준식 Diluting apparatus of chlorine dioxide

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200020182A (en) 2018-08-16 2020-02-26 이준식 Diluting apparatus of chlorine dioxide

Similar Documents

Publication Publication Date Title
KR910006579A (en) Truss and this reinforced precast concrete slab
ES2047251T3 (en) STEREOSTRUCTURE.
GB1229044A (en)
ATE218655T1 (en) IMPROVEMENTS TO THE FRAME OF A MANHOLE COVER
DE69503806D1 (en) BRIDGE CONSTRUCTION SYSTEM IN CONTINUOUS DESIGN
KR940002426A (en) Bridge deck construction method that moves the formwork along the rail
SE8105655L (en) PROCEDURE FOR ASSEMBLY AND REMOVAL OF CONSUMPTION FOR THE CONCENTRATION WORK AS WELL AS A CONSUMPTION FOR IMPLEMENTATION OF THE PROCEDURE
ATE99375T1 (en) PULLER RAIL.
ATE72001T1 (en) CONNECTING DEVICE FOR CONNECTING A CONCRETE COVER TO A SUPPORT AND STRUCTURE.
FR2796095B1 (en) WAITING BOX BOX AND WAITING BOX INCLUDING SUCH A BOX
ATE145027T1 (en) PREFABRICATED COVER PLATE AND METHOD FOR MAKING A BRIDGE USING SUCH PLATES
FR2426131A1 (en) SLIDING FORMWORK CONSTRUCTION DEVICE
ATE221607T1 (en) FORMWORK DEVICE WITH ADJUSTABLE CURVATURE
DE69516469T2 (en) Lifting ring for lifting side loads
SU1447963A1 (en) Method of dismantling a bridge span structure
SU1650888A1 (en) Sliding formwork of bridge pier
SU688589A1 (en) Device for temporary attachment of panel to pillar
SU1406289A1 (en) Bridge structure
GB1100039A (en) Apparatus for constructing bridge spans of ordinary or prestressed reinforced concrete in situ
DE59809256D1 (en) Stone, especially formwork or block stone
KR830004500A (en) Assembling and testing method of vertical movable platform structure with groundable support frame
DE68908699D1 (en) MACHINE FOR CIVIL WORK, IN PARTICULAR APPLICABLE FOR THE INSTALLATION OF VERTICAL DRAINAGE BODIES.
KR100223443B1 (en) The moving method of the slab
KR940002427A (en) Bridge deck construction method using movable supporter and formwork supporter
KR200256842Y1 (en) A movable working pulley of bridge

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application