KR20190130745A - Under ground structure construction method using concrete wall with upper, under column and under ground structure therewith - Google Patents

Under ground structure construction method using concrete wall with upper, under column and under ground structure therewith Download PDF

Info

Publication number
KR20190130745A
KR20190130745A KR1020180055233A KR20180055233A KR20190130745A KR 20190130745 A KR20190130745 A KR 20190130745A KR 1020180055233 A KR1020180055233 A KR 1020180055233A KR 20180055233 A KR20180055233 A KR 20180055233A KR 20190130745 A KR20190130745 A KR 20190130745A
Authority
KR
South Korea
Prior art keywords
wall
plate structure
ground
upper plate
excavation
Prior art date
Application number
KR1020180055233A
Other languages
Korean (ko)
Inventor
유병훈
Original Assignee
유병훈
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 유병훈 filed Critical 유병훈
Priority to KR1020180055233A priority Critical patent/KR20190130745A/en
Publication of KR20190130745A publication Critical patent/KR20190130745A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Abstract

The present invention relates to an underground structure construction method using a retaining wall, which excavates an inner ground of a retaining wall and constructs an underground structure after inserting the retaining wall into an excavation hole in a trench shape formed on the ground, thereby being possible to minimize vehicle passage control, and an underground structure constructed by using the same. The retaining wall is possible to construct the underground structure having wide width in a lateral direction by using manufacture so as to allow a lower beam extended to a lower portion from a wall part to be integrated to be supported on a front end of the excavation hole formed to be spaced apart from each other in a lateral direction and allow an upper beam extended to an upper portion from the wall to be integrated to be positioned on a ground surface.

Description

흙막이벽체를 이용한 지중구조물 시공방법 및 이를 이용하여 시공된 지중구조물{UNDER GROUND STRUCTURE CONSTRUCTION METHOD USING CONCRETE WALL WITH UPPER, UNDER COLUMN AND UNDER GROUND STRUCTURE THEREWITH}Construction method of underground structures using earthquake walls and construction of underground structures using the same {UNDER GROUND STRUCTURE CONSTRUCTION METHOD USING CONCRETE WALL WITH UPPER, UNDER COLUMN AND UNDER GROUND STRUCTURE THEREWITH}

본 발명은 흙막이벽체를 이용한 지중구조물 시공방법 및 이를 이용하여 시공된 지중구조물에 관한 것이다. 더욱 구체적으로 지반에 형성시킨 트렌치 형태의 굴착공에 흙막이벽체를 삽입 삽입한 후, 흙막이벽체 내측지반을 굴착하여 지중구조물을 시공하되 지상의 차량통행 통제를 최소화시킬 수 있는 흙막이벽체를 이용한 지중구조물 시공방법 및 이를 이용하여 시공된 지중구조물에 관한 것이다.The present invention relates to an underground structure construction method using a retaining wall and an underground structure constructed using the same. More specifically, after inserting the retaining wall into the trench-shaped excavation hole formed in the ground, construct the underground structure by excavating the inner ground of the retaining wall, but construct the underground structure using the retaining wall to minimize the control of vehicle traffic on the ground. It relates to a method and underground structures constructed using the same.

도 1은 종래 지하차도 등을 프리캐스트 벽체를 이용하여 시공하는 종래 SLIT 공법(슬릿공법)의 시공도를 도시한 것이다.FIG. 1 shows a construction diagram of a conventional SLIT method (slit method) for constructing a conventional underground roadway using a precast wall.

이러한 슬릿공법은 프리캐스트 부재인 측벽 부재(40)를 제작한 이후에 프리캐스트 상판구조물(50)을 먼저 설치하여 개착식 지하 구조물 시공과 대비하여 복공판을 설치하지 않고 지상부를 조기에 완성하고 내부를 굴착 및 구축하는 개착 지하 구조물 구축 기술이라 할 수 있다.In this slit method, after fabricating the sidewall member 40 which is a precast member, the precast upper plate structure 50 is installed first, and the ground part is completed early without installing a perforated plate in preparation for the construction of a detachable underground structure. It can be referred to as a technology for constructing underground structures for excavation and construction.

이러한 슬릿공법에 사용되는 측벽 부재(40)는 프리캐스트 부재(41)의 바닥 면에 시공 시의 지지 말뚝 및 측방 토압에 저항하는 H빔(42)을 서로 연결한 것을 지중에 서로 연결하여 지하 구조물의 측벽을 시공하게 되는데, 이는 지하 구조물 측벽 전부를 프리캐스트 부재로 시공하는 경우와 비교하여 운반과 시공이 상대적으로 용이하고 이로서 비용 절감이 가능하다는 장점이 있게 된다.The side wall member 40 used in the slit method is connected to the ground by connecting the support pile and the H-beam 42 resisting the lateral earth pressure at the bottom of the precast member 41 to each other in the underground structure The side wall of the construction is to be constructed, which is relatively easy to transport and construction compared to the case of constructing all the side wall of the underground structure as a precast member, which has the advantage that the cost can be reduced.

하지만 프리캐스트 부재(41)와 H빔(42)을 서로 앵커볼트와 연결강판을 이용하여 서로 각각 제작하여 연결하는 방식을 취하고 있는데, 실제 이러한 연결작업은 품질관리에 한계가 있고, 프리캐스트 부재(41)의 크기가 커지는 경우에는 장비의 대형화로 인하여 역시 시공성이 저하될 수밖에 없다는 문제가 있게 된다.However, the precast member 41 and the H beam 42 are made to connect to each other by using an anchor bolt and a connecting steel sheet, respectively, in practice, such a connection is limited in quality control, the precast member ( In the case of increasing the size of 41), there is a problem that the workability is inevitably deteriorated due to the enlargement of the equipment.

또한 프리캐스트 상판구조물(50)을 시공하기 전에는 상부의 교통을 통제할 수밖에 없기 때문에 광폭 지하구조물(예컨대 2 차선 이상의 지하차도 구조물)을 시공함에 있어서는 한계가 있고, 프리캐스트 상판구조물(50)의 크기가 커지는 경우 제작, 운반 및 시공 상 불리하다는 문제가 발생하게 된다.In addition, there is a limit in constructing wide underground structures (for example, two-lane or more underground roadway structures) because the traffic of the upper part cannot be controlled before the precast roofing structure 50 is constructed, and the size of the precast roofing structure 50 is limited. If it becomes large, there is a problem that disadvantages in manufacturing, transportation and construction.

대한민국 특허 제 10-1379305호(발명의 명칭: 프리캐스트 전면벽체 및 프리캐스트 배면벽체를 이용한 벽체구조물 제작방법, 공개일자: 2014년03월28일)Korean Patent No. 10-1379305 (Invention name: Method of manufacturing wall structure using precast front wall and precast back wall, published date: March 28, 2014) 대한민국 등록특허 10-1568194(발명의 명칭: PC부재 연결방법 및 이를 이용하여 시공된 PC구조물)Republic of Korea Patent Registration 10-1568194 (Name of the invention: PC member connection method and PC structure constructed using it) 대한민국 공개특허 10-2010-0106274(발명의 명칭: 조립식 보-기둥 구조물을 위한 건식 접합구조 및 이에 따른 시공방법)Republic of Korea Patent Application Publication No. 10-2010-0106274 (Invention name: dry joint structure for the prefabricated beam-column structure and construction method according thereto)

이에 본 발명은 광폭 지중구조물을 교통통제를 최소화 하면서 탑-다운방식으로 시공할 수 있도록 흙막이벽체를 이용할 수 있도록 하여 보다 효율적인 광폭 지중구조물 시공이 가능하고, 흙막이벽체는 공장에서 제작한 것을 현장에서 형성시킨 트렌치홀에 바로 삽입 시공할 수 있도록 하여 신속하고 경제적인 시공이 가능한 흙막이벽체를 이용한 지중구조물 시공방법 및 이를 이용하여 시공된 지중구조물 제공을 해결하고자 하는 기술적 과제로 한다.Accordingly, the present invention enables the construction of wide wall structures so that the wide ground structures can be constructed in a top-down manner while minimizing traffic control, so that the wide ground structures can be constructed more efficiently. The construction of underground structures using the earthquake walls that can be quickly and economically constructed by inserting them directly into the trench holes, and the technical problem to solve the provision of the underground structures constructed using the same.

상기 과제를 달성하기 위하여 본 발명은 The present invention to achieve the above object

(a) 횡방향으로 서로 이격되도록 형성된 굴착공 선단에, 벽체부로부터 하부로 연장되어 일체화된 하부빔이 지지되도록 하고, 벽체로부터 상부로 연장되어 일체화된 상부빔이 지반 표면에 위치하도록 흙막이벽체를 인양하여 삽입 시공하는 단계; (b) 흙막이벽체 사이의 지반에 중간파일을 하방으로 시공하여 중간파일 상단과 흙막이벽체의 상부빔 상단 사이에 타이로드를 설치하는 단계; (c) 상기 타이로드가 설치되지 않은 중간파일과 흙막이벽체의 상부빔 사이의 지반을 하방으로 굴착하면서, 굴착에 의하여 형성되는 굴착공간(S1)쪽으로 지반이 붕괴되지 않도록 중간파일과 흙막이벽체의 상부빔에 토류판을 설치하는 단계; 및 (d) 상기 굴착공간(S1)에서 흙막이벽체의 벽체부 상단이 노출되면 상기 벽체부 상단에 상판구조물을 일부 시공하는 단계;를 포함하여, 상기 타이로드가 설치되는 지반은 차량통행이 통제되지 않은 상태에서 상판구조물 일부를 시공할 수 있도록 하는 흙막이벽체를 이용한 지중구조물 시공방법을 제공하게 된다.(a) At the tip of the excavation hole formed so as to be spaced apart from each other in the transverse direction, the bottom wall extending from the wall portion to support the integrated lower beam, and extending from the wall to the top so that the integrated upper beam is located on the ground surface. Lifting and inserting construction; (b) installing a tie rod between the upper end of the intermediate pile and the upper beam of the retaining wall by constructing an intermediate pile downward in the ground between the retaining walls; (c) while excavating the ground between the intermediate pile and the upper beam of the retaining wall without the tie rods downward, the upper portion of the intermediate pile and the retaining wall so that the ground does not collapse toward the excavation space (S1) formed by excavation Installing an earth plate on the beam; And (d) constructing a part of the upper plate structure on the top of the wall part when the top of the wall part of the retaining wall is exposed in the excavation space S1. The ground on which the tie rod is installed is not controlled by vehicle traffic. It provides a method of construction of underground structures using the earth wall to allow the construction of a portion of the top plate structure in the absence.

또한 바람직하게는 Also preferably

(a) 횡방향으로 서로 이격되도록 형성된 3개의 굴착공 선단에, 벽체부로부터 하부로 연장되어 일체화된 하부빔이 지지되도록 하고, 벽체로부터 상부로 연장되어 일체화된 상부빔이 지반 표면에 위치하도록 흙막이벽체를 인양하여 삽입 시공하는 단계; (b) 흙막이벽체 사이사이의 지반에 양 중간파일을 하방으로 시공하여 양 중간파일 상단과 중간 흙막이벽체의 상부빔 상단 사이에 타이로드를 설치하는 단계; (c) 상기 타이로드가 설치되지 않은 중간파일과 흙막이벽체의 상부빔 사이의 지반을 하방으로 굴착하면서, 굴착에 의하여 형성되는 굴착공간(S1)쪽으로 지반이 붕괴되지 않도록 중간파일과 흙막이벽체의 상부빔에 토류판을 설치하는 단계; 및 (d) 상기 굴착공간(S1)에서 흙막이벽체의 벽체부 상단이 노출되면 상기 벽체부 상단에 상판구조물을 일부 시공하는 단계;를 포함하여, 상기 타이로드가 설치되는 지반은 차량통행이 통제되지 않은 상태에서 상판구조물 일부를 시공할 수 있도록 하는 흙막이벽체를 이용한 지중구조물 시공방법을 제공하게 된다.(a) At the tip of the three excavation holes formed to be spaced apart from each other in the transverse direction, the earth film is extended so as to support the integrated lower beam extending downward from the wall portion and the upper beam integrated from the wall upward to be located on the ground surface. Lifting and inserting the wall; (b) constructing both intermediate piles downwards on the ground between the barrier walls to install tie rods between the upper ends of both intermediate piles and the upper beams of the intermediate barrier walls; (c) while excavating the ground between the intermediate pile and the upper beam of the retaining wall without the tie rods downward, the upper portion of the intermediate pile and the retaining wall so that the ground does not collapse toward the excavation space (S1) formed by excavation Installing an earth plate on the beam; And (d) constructing a part of the upper plate structure on the top of the wall part when the top of the wall part of the retaining wall is exposed in the excavation space S1. The ground on which the tie rod is installed is not controlled by vehicle traffic. It provides a method of construction of underground structures using the earth wall to allow the construction of a portion of the top plate structure in the absence.

본 발명에 의한 지중구조물은 횡방향으로 서로 이격되도록 형성된 굴착공 선단에, 벽체부로부터 하부로 연장되어 일체화된 하부빔이 지지되도록 하고, 벽체로부터 상부로 연장되어 일체화된 상부빔이 지반 표면에 위치하도록 흙막이벽체를 이용하여 시공하고, 토류판을 이용하여 차량통행을 최소한으로 통제하도록 하여 광폭의 지중구조물 시공이 가능하게 된다.The underground structure according to the present invention is supported by the lower end of the excavation hole formed to be spaced apart from each other in the transverse direction, so that the lower beam is integrated from the wall to the lower portion, and the upper beam is extended from the wall to the upper portion and is located on the ground surface. It is possible to construct by using mud wall, and to control the traffic to a minimum by using earth plate, so that the construction of wide underground structures is possible.

도 1은 종래 슬릿공법(SLIT공법)의 시공도,
도 2는 본 발명의 흙막이벽체를 이용한 지중구조물 시공도,
도 3a 및 도 3b는 본 발명의 실시예 1에 의한 흙막이벽체를 이용한 지중구조물 시공방법의 순서도,
도 4a 및 도 4b는 본 발명의 실시예 2에 의한 흙막이벽체를 이용한 지중구조물 시공방법의 순서도이다.
1 is a construction of the conventional slit method (SLIT method),
Figure 2 is a construction of the underground structure using the wall of the invention,
Figure 3a and Figure 3b is a flow chart of the construction method for underground structures using the earth wall according to the first embodiment of the present invention,
Figures 4a and 4b is a flow chart of the construction method for underground structures using the earth retaining wall according to the second embodiment of the present invention.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art may easily implement the present invention. As those skilled in the art would realize, the described embodiments may be modified in various different ways, all without departing from the spirit or scope of the present invention. In the drawings, parts irrelevant to the description are omitted in order to clearly describe the present invention, and like reference numerals designate like parts throughout the specification.

명세서 전체에서, 어떤 부분이 어떤 구성요소를 "포함"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다.Throughout the specification, when a part is said to "include" a certain component, it means that it can further include other components, without excluding other components unless specifically stated otherwise.

[본 발명의 흙막이벽체(100)를 이용한 지중구조물(A)][Underground structure (A) using earth retaining wall 100 of the present invention]

본 발명의 흙막이벽체(100)를 이용한 지중구조물(A)은 도 2를 참조하면 먼저 지반을 일정 깊이 터파기 하여 확보한 작업공간에 트렌치 굴착(일정한 폭으로 종방향으로 연속하여 수직홀을 형성시키는 굴착)을 하고, 트렌치 굴착된 굴착공(310)에 본 발명의 흙막이벽체(100)를 삽입 하고, Underground structure (A) using the earth retaining wall 100 of the present invention is to refer to Figure 2 first trenches excavated in the work space secured by digging a certain depth (to form a vertical hole continuously in the longitudinal direction with a predetermined width) Excavation), and insert the earthwall wall 100 of the present invention into the trench excavated excavation hole 310,

흙막이벽체(100)의 상부 지반을 굴착하면서 흙막이벽체(100) 상부에 토류판(140)을 설치하여 확보한 굴착공간(S1,S2)에 상판구조물(200)을 시공하고, Construction of the upper plate structure 200 in the excavation space (S1, S2) secured by installing the earth plate 140 on the top of the earth wall wall 100 while excavating the upper ground of the earth wall wall 100,

상기 굴착공간(S1,S2)을 되메움하여 차량을 통행시킨 후, After filling the excavation space (S1, S2) to pass the vehicle,

상판구조물(200)의 하부 지반을 추가 굴착하여 최종 지중구조물(A) 시공을 완성시키게 된다.Further excavation of the lower ground of the upper plate structure 200 will complete the final underground structure (A) construction.

이와 같은 본 발명의 흙막이벽체(100)는 종래 SLIT 공법과 대비하여 하부빔(120)은 흙막이벽체(100)와 제작 시 부터 일체화되도록 하여 종래 SLIT 공법과 달리 H빔(12)을 프리캐스트 부재(41)에 별도로 연결시킴에 따른 품질관리의 문제점을 해결할 수 있도록 하고, As compared with the conventional SLIT method, the earthwall wall 100 of the present invention allows the lower beam 120 to be integrated with the earthwall wall 100 from the time of manufacture so that the H beam 12 is precast member ( 41) to solve the problem of quality control by connecting separately to,

흙막이벽체(100)의 상면에도 흙막이용 토류판(140)을 설치할 수 있는 엄지말뚝 기능을 가진 상부빔(130)을 역시 일체로 제작하게 된다.The upper beam 130 having the thumb pile function that can be installed on the top surface of the retaining wall (100) for the earth retaining plate 140 is also made integrally.

이에 도 2와 같이, 본 발명의 흙막이벽체(100)는 벽체부(110) 하부로부터 연장된 하부빔(120)이 일체로 합성되어 있고, 상부빔(130)이 벽체부(110) 상부로부터 연장되어 일체로 합성된 것을 이용하게 되며, Accordingly, as shown in FIG. 2, in the barrier wall 100 of the present invention, the lower beam 120 extending from the lower portion of the wall portion 110 is integrally synthesized, and the upper beam 130 extends from the upper portion of the wall portion 110. To use the synthesized one,

상기 하부빔(120)은 벽체부(110)를 굴착공(310)에 삽입되어 고정되도록 하는 역할을 하게 되고, The lower beam 120 serves to fix the wall portion 110 is inserted into the excavation hole 310,

상기 상부빔(130)은 흙막이의 토류판을 사이사이에 끼워 설치할 수 있는 엄지말뚝의 역할을 하게 된다.The upper beam 130 serves as a thumb pile that can be installed between the earth plate of the earthen membrane between.

이에 굴착으로 노출된 벽체부(110) 상단 사이에 상판구조물(200)을 시공하고, 상판구조물(200) 하부 지반을 굴착하면서 저판구조물(300)을 시공하여 최종 본 발명의 흙막이벽체를 이용한 지중구조물을 시공하게 된다.The construction of the top plate 200 between the top of the wall portion 110 exposed by the excavation, and by constructing the bottom plate structure 300 while excavating the lower ground of the top structure 200 underground structure using the earth wall of the final invention Will be constructed.

이로서 도 2에 의하면 본 발명의 흙막이벽체를 이용한 지중구조물(A)은 지중에 상부빔과 하부빔이 일체로 형성된 양 흙막이벽체(100), 상판구조물(200)과 저판구조물(300)로 시공되도록 하고 있음을 알 수 있다.Thus, according to Figure 2 underground structure (A) using the earth wall of the present invention is to be constructed as both earth wall 100, the upper plate structure 200 and the bottom plate structure 300, the upper and lower beams are integrally formed in the ground It can be seen that.

[ 본 발명의 흙막이벽체를 이용한 지중구조물(A) 시공방법: 실시예 1][Method for constructing underground structure (A) using earthwall of the present invention: Example 1]

도 3a 및 도 3b는 본 발명의 실시예 1에 의한 흙막이벽체를 이용한 지중구조물(A) 시공방법의 순서도를 도시한 것이다.Figure 3a and Figure 3b shows a flow chart of the construction method of the underground structure (A) using the earth retaining wall according to the first embodiment of the present invention.

먼저, 도 3a와 같이, First, as shown in Figure 3a,

양 흙막이벽체(100)가 수직으로 삽입될 수 있는 굴착공(310)을 형성시키게 된다. 이러한 굴착공(310)은 트렌치용 굴착기를 사용하여 트렌치(Trench) 굴착을 통해 형성시키면 된다. Both retaining wall 100 is to form an excavation hole 310 that can be inserted vertically. The excavation hole 310 may be formed through trench excavation using a trench excavator.

이러한 트렌치 굴착에 의한 굴착공(310)은 공벽유지를 위하여 시멘트밀크등과 같은 충진재를 채워 넣어 공벽유지가 가능하도록 하는 것이 바람직하다.The excavation hole 310 by the trench excavation is preferably filled with a filler such as cement milk for maintaining the empty wall to enable the empty wall maintenance.

도 3a의 경우에는 2개의 굴착공(310)을 횡방향으로 이격시켜 시공하고 있음을 알 수 있으며, 종방향으로 연속해서 지중구조물(A)에 따라 연장 시공하게 된다.In the case of FIG. 3A, it can be seen that the two drilling holes 310 are spaced apart in the lateral direction, and are continuously extended in the longitudinal direction along the underground structure A.

이러한 굴착공(310)에 미리 제작하여 운반된 흙막이벽체(100)를 인양하여 수직으로 삽입하여 종방향으로 측면들이 접하도록 설치하게 되면 측면들에 형성시킨 전단키, 전단홈등을 이용하여 일체화시키면 된다.If it is installed in such excavation hole 310 in advance by lifting and inserting the vertical wall wall 100 is transported in the vertical direction to install the side in contact with the longitudinal direction by using the shear key formed in the side, shear grooves, etc. .

이러한 흙막이벽체(100)는 상단에 상부빔(130)이 일체로 형성되어 있고, 하단에도 하부빔(120)이 일체로 형성되어 있으므로 Since the top wall 130 is integrally formed at the upper end and the lower beam 120 is integrally formed at the lower end of the retaining wall 100.

굴착공(310)에 삽입되어 하부빔(120)은 굴착공(310)의 선단에 지지되도록 하고, 싱부빔(130)은 지반 표면까지 연장되어 있음을 알 수 있고, 벽체부(110)는 지중에 위치하도록 굴착공(310)이 형성되어 있음을 알 수 있으며, The lower beam 120 is inserted into the excavation hole 310 to be supported at the tip of the excavation hole 310, and the single beam 130 extends to the ground surface, and the wall part 110 is underground. It can be seen that the excavation hole 310 is formed to be located in,

이때 양 굴착공(310) 사이에서는 교통이 통제되지 않으므로 차량통행이 통제되지 않게 됨을 알 수 있다.At this time, the traffic is not controlled between the two excavation holes 310, it can be seen that the vehicle traffic is not controlled.

다음으로는 양 흙막이벽체(100) 사이에 H파일과 같은 중간파일(160)을 추가 시공하고 중간파일(160) 상부와 우측 상부빔(130) 사이에는 와이어, 철근 등의 우측 타이로드(150a)를 연결시키게 된다.Next, the intermediate pile 160, such as the H pile, is additionally installed between the two wall walls 100, and the right tie rod 150a, such as a wire or rebar, is disposed between the upper portion of the intermediate pile 160 and the upper right beam 130. Will be connected.

이러한 중간파일(160)은 토류판을 설치할 엄지말뚝의 역할을 하고, 우측 타이로드(150a)는 중간파일(160)과 좌측 흙막이벽체(100) 사이를 굴착할 때, 지반이 좌측으로 붕괴되지 않도록 하는 역할을 하게 된다.The intermediate pile 160 serves as a thumb pile for installing the earth plate, and the right tie rod 150a prevents the ground from collapsing to the left side when excavating between the intermediate pile 160 and the left retaining wall 100. It will play a role.

도 3a에 의하면, 우측 타이로드(150a)는 우측 흙막이벽체(100)의 상부빔(130) 상단과 중간파일(160) 상단 사이에 설치되어 좌측 지반은 차량통행이 통제되지 않도록 하고 있음을 알 수 있다.According to Figure 3a, the right tie rod 150a is installed between the upper end of the upper beam 130 and the upper end of the intermediate pile 160 of the right retaining wall 100, it can be seen that the left ground does not control the traffic of the vehicle have.

이러한 중간파일(160)은 우측 상부빔(130)과 연결되므로 우측 상부빔(130)에 대응하여 지반을 천공 후 삽입 시공하는 방식을 이용하여 설치하면 되고, 깊이는 상부빔 길이보다는 약간 긴 것을 이용함을 알 수 있으며 추후 제거된다.Since the intermediate pile 160 is connected to the upper right beam 130, the intermediate pile 160 may be installed using a method of inserting the ground after drilling to correspond to the upper right beam 130, and the depth is slightly longer than the length of the upper beam. It can be seen and removed later.

다음으로 좌측 상부빔(130)과 중간파일(160) 사이 지반을 하방으로 굴착하여 형성된 굴착공간(S1)에서 좌측 상판구조물(200a)을 노출된 벽체부(110) 상단에 시공하고, Next, in the excavation space S1 formed by excavating the ground between the upper left beam 130 and the intermediate pile 160 downward, construct the upper left structure 200a on the exposed wall portion 110,

다시 굴착공간(S1)을 되메움한 후, After filling the excavation space (S1) again,

우측 상부빔(130)과 좌측 상판구조물(200a) 단부에 새로이 설치된 상판중간파일(170) 사이를 굴착하여 굴착공간(S2)을 형성시키게 된다.Excavation space (S2) is formed by excavating between the upper plate middle pile 170 newly installed at the upper end of the upper right beam 130 and the left upper plate structure (200a).

이때 좌측 상부빔(130)과 중간파일(160)에는 토류판(140)을 설치하여 하방 굴착된 굴착공간(S1)으로 지반이 붕괴되지 않도록 하게 된다. At this time, the earth plate 140 is installed on the upper left beam 130 and the intermediate pile 160 so that the ground does not collapse into the excavation space S1 which is excavated downward.

상기 토류판(140)은 통상적인 흙막이구조물에서 사용되는 것을 이용하면 되고, 하방으로 굴착하면서 종방향으로 이격된 상부빔(130) 사이, 종방향으로 이격된 중간파일(160)의 사이에 끼워 설치하게 된다.The earth plate 140 may be used to be used in a conventional masonry structure, to be installed between the upper beam 130 spaced in the longitudinal direction while being excavated downward, sandwiched between the intermediate pile 160 spaced in the longitudinal direction do.

이에 좌측 벽체부(110) 상단이 노출되는 깊이까지 하방굴착하게 되면 좌측상판구조물(200a)을 좌측 벽체부(110) 상단에 연결되도록 수평 설치하게 된다.Accordingly, when the bottom wall portion 110 is excavated downward to the exposed depth, the left upper plate structure 200a is horizontally installed to be connected to the upper side of the left wall portion 110.

신속한 시공을 위해서 프리캐스트 방식의 좌측상판구조물(200a)을 이용할 수도 있지만 현장타설 콘크리트로 시공하는 것이 일체화에 효과적이며, 좌측상판구조물(200a)의 우측 단부는 저면지지블록(210)을 통해 수평을 유지하면서 지지 설치되도록 하게 된다.Although the left top plate structure 200a of the precast method may be used for rapid construction, it is effective to integrate with the site-casting concrete, and the right end of the left top structure 200a is horizontal through the bottom support block 210. It will be installed while supporting.

또한 상기 좌측상판구조물(200a)의 우측 상단에는 상판중간파일(170)을 추가로 세워 설치하게 된다.In addition, the upper plate middle pile 170 is additionally installed on the upper right side of the left upper plate structure 200a.

이러한 상판중간파일(170)을 별도로 설치하는 이유는 좌측의 상부빔(130)과의 사이에 좌측 타이로드(150b)를 설치하여 굴착공간(S2) 형성 후 좌측상판구조물(200a)과 우측상판구조물(200b)을 서로 일체화시키기 위한 공간을 확보하기 어렵기 때문이다.The reason why the upper plate intermediate pile 170 is installed separately is to install the left tie rod 150b between the upper beam 130 on the left side to form the excavation space S2 and to form the left top structure 200a and the right top structure. This is because it is difficult to secure a space for integrating the 200b with each other.

이에 좌측상판구조물(200a) 상부의 굴착공간(S1)을 되메움하고, 좌측 타이로드(150b)를 좌측 상부빔(130)과 상판중간파일(170) 상단 사이에 설치하게 된다.Thus, the excavation space (S1) of the upper left upper plate structure 200a is backfilled, and the left tie rod 150b is installed between the upper left upper beam 130 and the upper middle plate pile (170).

이로서 되메움토는 상판중간파일(170)에 설치된 토류판(140)에 의하여 우측으로 붕괴되지 않도록 하면서 좌측 차량통행이 가능하도록 할 수 있게 된다.As a result, the backfill soil can be allowed to pass on the left side of the vehicle while not collapsing to the right side by the earth plate 140 installed on the upper plate middle pile 170.

이에 중간파일(160)을 인발시킴과 더불어 우측타이로드(150a)를 제거하고, 우측 지반을 하방으로 굴착하여 우측상판구조물(200b)을 시공할 수 있도록 지표면으로부터 하방으로 굴착하여 굴착공간(S2)을 형성시키게 된다.In addition, the intermediate pile 160 is pulled out and the right tie rod 150a is removed, and the right ground is excavated downward to excavate downward from the ground surface so that the right upper plate structure 200b can be constructed. Will form.

이로서 도 3b와 같이, 굴착공간(S2)에서 좌측상판구조물(200a)이 노출되어 우측상판구조물(200b)을 서로 일체화시켜 상판구조물(200) 시공을 할 수 있게 됨을 알 수 있다.Thus, as shown in Figure 3b, the excavation space (S2) is exposed to the left top structure 200a it can be seen that the right top structure 200b can be integrated with each other to construct the top plate structure 200.

이에 상판구조물(200) 시공이 완료되면 굴착공간(S2)을 다시 되메움시키게 되는데 전면 차량통행이 가능하도록 상부빔(130), 상판중간파일(170)의 상단은 일부 커팅 되어 잔존될 수도 있음을 알 수 있으며 필요하다면 모두 제거도 가능할 것이다.When the construction of the upper plate structure 200 is completed, the excavation space (S2) is backfilled. The upper beam 130 and the upper end of the upper plate middle pile 170 may be partially cut to remain in order to allow front vehicle traffic. It can be known and removed if necessary.

이에 다음으로는 상판구조물(200) 하부의 지반을 추가 굴착하여 굴착공간(S3)이 확보되면 저판구조물(300)을 벽체부(110) 하단 사이에 형성시키게 되면 현장타설콘크리트를 이용하여 시공할 수 있을 것이다.Next, if the excavation space (S3) is secured by additional excavation of the ground under the upper plate structure 200, the bottom plate structure 300 may be formed between the bottom of the wall part 110, and the construction may be performed by using the site casting concrete. There will be.

[ 본 발명의 흙막이벽체를 이용한 지중구조물(A) 시공방법: 실시예 2][Method for constructing underground structure (A) using earthwall of the present invention: Example 2]

도 4a 및 도 4b는 본 발명의 실시예 2에 의한 흙막이벽체를 이용한 지중구조물(A) 시공방법의 순서도를 도시한 것이다.Figures 4a and 4b shows a flow chart of the construction method of underground structure (A) using the earth retaining wall according to the second embodiment of the present invention.

실시예 1과 다른 점은 지중구조물(A)의 횡방향 폭이 큰 경우에 양 흙막이벽체(100) 사이에 추가 흙막이벽체(100)를 시공하는 것에 차이가 있다.The difference from the first embodiment is that when the horizontal width of the underground structure (A) is large, there is a difference in the construction of the additional retaining wall 100 between the two retaining wall (100).

이에 도 4a와 같이, As shown in Figure 4a,

양 흙막이벽체(100)와 중간 흙막이벽체(100)가 수직으로 삽입될 수 있는 굴착공(310)을 형성시키게 된다. 이러한 굴착공(310)은 트렌치용 굴착기를 사용하여 트렌치(Trench) 굴착을 통해 형성시키면 된다.Both retaining wall 100 and the middle retaining wall 100 is to form an excavation hole 310 that can be inserted vertically. The excavation hole 310 may be formed through trench excavation using a trench excavator.

도 4a의 경우에는 3개의 굴착공(310)을 횡방향으로 이격시켜 시공하고 있음을 알 수 있으며, 종방향으로 연속해서 지중구조물(A)에 따라 연장 시공하게 된다.In the case of Figure 4a it can be seen that the three excavation holes 310 are spaced apart in the transverse direction, the construction is extended in accordance with the underground structure (A) continuously in the longitudinal direction.

이러한 굴착공(310)에 미리 제작하여 운반된 흙막이벽체(100)를 인양하여 수직으로 삽입하여 종방향으로 측면들이 접하도록 설치하게 되면 측면들에 형성시킨 전단키, 전단홈등을 이용하여 일체화시키면 된다.If it is installed in such excavation hole 310 in advance by lifting and inserting the vertical wall wall 100 is transported in the vertical direction to install the side in contact with the longitudinal direction by using the shear key formed in the side, shear grooves, etc. .

이러한 흙막이벽체(100)는 상단에 상부빔(130)이 일체로 형성되어 있고, 하단에도 하부빔(120)이 일체로 형성되어 있으므로 Since the top wall 130 is integrally formed at the upper end and the lower beam 120 is integrally formed at the lower end of the retaining wall 100.

굴착공(310)에 삽입되어 하부빔(120)은 굴착공(310)의 선단에 지지되도록 하고, 싱부빔(130)은 지반 표면까지 연장되어 있음을 알 수 있고, 벽체부(110)는 지중에 위치하도록 굴착공(310)이 형성되어 있음을 알 수 있으며, 이때 양 굴착공(310) 사이에서는 교통이 통제되지 않으므로 차량통행이 전면 통제되지 않게 됨을 알 수 있으며 실시예 1과 대비하여 중간 흙막이벽체(100)를 위한 굴착공(310)을 더 형성시켜 중간 흙막이벽체(100)가 추가 설치되고 있음을 알 수 있다.The lower beam 120 is inserted into the excavation hole 310 to be supported at the tip of the excavation hole 310, and the single beam 130 extends to the ground surface, and the wall part 110 is underground. It can be seen that the excavation hole 310 is formed so as to be located in this case, since traffic is not controlled between the two excavation holes 310, it can be seen that the vehicle traffic is not controlled entirely. It can be seen that the intermediate retaining wall 100 is further installed by further forming an excavation hole 310 for the wall 100.

다음으로는 흙막이벽체(100)들 사이사이에 H파일과 같은 양 중간파일(160)을 추가 시공하고 양 중간파일(160) 상부와 중간 흙막이벽체(100)의 상부빔(130) 사이에는 와이어, 철근 등의 양 중간 타이로드(150c)를 연결시키게 된다.Next, the construction between the intermediate pile 160, such as the H pile between the soil barrier wall 100, and additionally between the upper beam 130 of the upper middle intermediate pile 160 and the middle barrier wall 100, Both intermediate tie rods 150c, such as rebar, are connected.

이러한 양 중간파일(160)은 토류판을 설치할 엄지말뚝의 역할을 하고, 양 중간 타이로드(150c)는 양 중간파일(160)과 좌측 및 우측 흙막이벽체(100) 사이를 굴착할 때, 양 중간파일(160) 사이의 지반이 붕괴되지 않도록 하는 역할을 하게 된다.Both of the intermediate pile 160 serves as a thumb pile to install the earth plate, both intermediate tie rods 150c when the two intermediate piles 160 and the left and right soil wall wall 100 when excavating, both intermediate piles The ground between the 160 to prevent the collapse.

도 4a에 의하면, 중간 타이로드(150c)는 좌측 및 우측 흙막이벽체(100)의 상부빔(130) 상단과 양 중간파일(160) 상단 사이에 설치되어 차량통행이 통제되지 않도록 하고 있음을 알 수 있다.According to Figure 4a, the intermediate tie rod 150c is installed between the upper end of the upper beam 130 and the upper end of both the intermediate pile 160 of the left and right retaining wall 100, so that the vehicle traffic is not controlled. have.

이러한 양 중간파일(160)은 좌측 및 우측 상부빔(130)과 연결되므로 좌측 및 우측 상부빔(130)에 대응하여 지반을 천공 후 삽입 시공하는 방식을 이용하여 설치하면 되고, 깊이는 양 상부빔 길이보다는 약간 긴 것을 이용함을 알 수 있으며 추후 제거된다.Since the two intermediate piles 160 are connected to the left and right upper beams 130, the intermediate piles 160 may be installed using a method of inserting and drilling the ground to correspond to the left and right upper beams 130, and the depth of both upper beams 130. It can be seen that it is slightly longer than the length and will be removed later.

다음으로 좌측 및 우측 상부빔(130)과 양 중간파일(160) 사이 지반을 하방으로 굴착하여 형성된 굴착공간(S1)에서 좌측 및 우측 상판구조물(200a,200b)을 노출된 벽체부(110) 상단에 시공하고, Next, in the excavation space S1 formed by digging the ground between the left and right upper beams 130 and both intermediate piles 160 downward, the upper and lower wall structures 200a and 200b expose the upper part of the wall 110. Construction on,

다시 굴착공간(S1)을 되메움한 후, After filling the excavation space (S1) again,

좌측 및 우측 상판구조물(200a,200b)에 새로이 설치된 양 상판중간파일(170) 사이를 굴착하여 굴착공간(S2)을 형성시키게 된다.Excavation space (S2) is formed by excavating between the two upper plate intermediate piles 170 newly installed on the left and right upper plate structures (200a, 200b).

이때 좌측 및 우측 상부빔(130), 양 중간파일(160)에는 토류판(140)을 설치하여 하방 굴착된 굴착공간(S1)으로 지반이 붕괴되지 않도록 하게 된다. At this time, the ground plate 140 is installed on the left and right upper beams 130 and both intermediate piles 160 so that the ground does not collapse into the excavation space S1 which is excavated downward.

상기 토류판(140)은 통상적인 흙막이구조물에서 사용되는 것을 이용하면 되고, 하방으로 굴착하면서 종방향으로 이격된 좌측 및 우측 상부빔(130), 종방향으로 이격된 양 중간파일(160)에 끼워 설치하게 된다.The earth plate 140 may be used to be used in a conventional masonry structure, and installed in the left and right upper beam 130 spaced in the longitudinal direction while being excavated downward, fitted to both intermediate piles 160 spaced in the longitudinal direction Done.

이에 좌측 및 우측 벽체부(110) 상단이 노출되는 깊이까지 하방굴착하게 되면 좌측 및 우측 상판구조물(200a,200b)을 좌측 및 우측 벽체부(110) 상단에 연결되도록 수평 설치하게 된다.When the left and right wall portion 110 is excavated downward to the depth that is exposed, the left and right upper plate structure (200a, 200b) is installed horizontally so as to be connected to the upper left and right wall portion (110).

신속한 시공을 위해서 프리캐스트 방식의 좌측상판구조물(200a)을 이용할 수도 있지만 현장타설 콘크리트로 시공하는 것이 일체화에 효과적이며, 좌측 및 우측 상판구조물(200a,200b) 양 단부는 저면지지블록(210)을 통해 수평을 유지하면서 지지 설치되도록 하게 된다.For the rapid construction, the precast type left top structure 200a may be used, but it is effective to integrate it with site-cast concrete, and both ends of the left and right top structure 200a and 200b may have the bottom support block 210. It is to be installed while maintaining the horizontal through.

또한 상기 좌측 및 우측 상판구조물(200a,200b)의 상기 단부 상단에는 양 상판중간파일(170)을 추가로 세워 설치하게 된다.In addition, the upper end of the upper left and right upper plate structure (200a, 200b) both upper plate intermediate piles 170 are installed upright.

이러한 양 상판중간파일(170)을 별도로 설치하는 이유는 좌측 및 우측의 상부빔(130)과의 사이에 좌측 및 우측 타이로드(150a, 150b)를 설치하여 굴착공간(S2) 형성 후 중간 상판구조물(200c)을 설치하기 위한 공간을 확보하기 위함이다.The reason why the upper plate intermediate pile 170 is installed separately is to install the left and right tie rods 150a and 150b between the upper and lower beams 130 on the left and right sides to form the excavation space S2 and then form the intermediate upper plate structure. This is to secure a space for installing the 200c.

이에 좌측 및 우측 상판구조물(200a,200b) 상부의 굴착공간(S1)을 되메움하고, 좌측 및 우측 타이로드(150a, 150b)를 좌측 및 우측 상부빔(130)과 양 상판중간파일(170) 상단 사이에 설치하게 된다.The back and the top of the excavation space (S1) of the upper plate structure (200a, 200b), and the left and right tie rods (150a, 150b) to the left and right upper beam 130 and the upper plate intermediate pile 170 It will be installed between the tops.

이로서 되메움토는 상판중간파일(170)에 설치된 토류판에 의하여 중간으로 붕괴되지 않도록 하면서 좌측 및 우측 차량 통행이 가능하도록 할 수 있게 된다.As a result, the backfill is able to allow left and right vehicle traffic while not being collapsed in the middle by the earth plate installed in the upper plate intermediate pile 170.

이에 양 중간파일(160)을 인발시킴과 더불어 중간타이로드(150c)를 제거하고, 중간 지반을 하방으로 굴착하여 중간 상판구조물(200c)을 시공할 수 있도록 지표면으로부터 하방으로 굴착하여 굴착공간(S2)을 형성시키게 된다.Thus, both the intermediate pile 160 is pulled out and the intermediate tie rod 150c is removed, and the excavation space is excavated downward from the ground surface so that the intermediate ground structure 200c can be constructed by digging the intermediate ground downward. ).

이로서 도 4b와 같이, 좌측 및 우측 상판구조물(200a,200b)이 노출되어 중간상판구조물(200c)을 좌측 및 우측 상판구조물(200a,200b)과 서로 일체화시켜 상판구조물(200) 시공을 할 수 있게 됨을 알 수 있다.Thus, as shown in FIG. 4B, the left and right top structures 200a and 200b are exposed to integrate the middle top structure 200c with the left and right top structures 200a and 200b so that the top structure 200 can be constructed. It can be seen that.

이에 상판구조물(200) 시공이 완료되면 굴착공간(S2)을 다시 되메움 시키게 되는데 전면 차량통행이 가능하도록 좌측 및 우측 상부빔(130), 양 상판중간파일(170)의 상단은 일부 커팅 되어 잔존될 수도 있음을 알 수 있으며 필요하다면 모두 제거도 가능할 것이다.When the construction of the upper plate structure 200 is completed, the excavation space (S2) is backfilled. The upper left and right upper beams 130 and the upper ends of both upper plate intermediate piles 170 are partially cut so that the front vehicle can pass. It can be seen that it can be removed and, if necessary, all can be removed.

이에 도 4d와 같이, 상판구조물(200) 하부의 지반을 추가 굴착하여 굴착공간(S3)이 확보되면 저판구조물(300)을 벽체부(110) 하단 사이에 형성시키게 되면 현장타설콘크리트를 이용하여 시공할 수 있을 것이다.Thus, as shown in Figure 4d, when the excavation space (S3) is secured by additional excavation of the ground of the bottom of the upper plate structure 200 when the bottom plate structure 300 is formed between the bottom of the wall portion 110, the construction using the site casting concrete You can do it.

전술한 본 발명의 설명은 예시를 위한 것이며, 본 발명이 속하는 기술분야의 통상의 지식을 가진 자는 본 발명의 기술적 사상이나 필수적인 특징을 변경하지 않고서 다른 구체적인 형태로 쉽게 변형이 가능하다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시예들은 모든 면에서 예시적인 것이며 한정적이 아닌 것으로 이해해야만 한다. 예를 들어, 단일형으로 설명되어 있는 각 구성 요소는 분산되어 실시될 수도 있으며, 마찬가지로 분산된 것으로 설명되어 있는 구성 요소들도 결합된 형태로 실시될 수 있다.The foregoing description of the present invention is intended for illustration, and it will be understood by those skilled in the art that the present invention may be easily modified in other specific forms without changing the technical spirit or essential features of the present invention. will be. Therefore, it should be understood that the embodiments described above are exemplary in all respects and not restrictive. For example, each component described as a single type may be implemented in a distributed manner, and similarly, components described as distributed may be implemented in a combined form.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is shown by the following claims rather than the above description, and all changes or modifications derived from the meaning and scope of the claims and their equivalents should be construed as being included in the scope of the present invention. do.

100: 흙막이벽체 110: 벽체부
120: 하부빔 130: 상부빔
140: 토류판 150a: 우측 타이로드
150b: 좌측 타이로드 150c: 중간 타이로드
160: 중간파일 170: 상판중간파일
200a,200b: 좌측 상판구조물, 우측 상판구조물
200: 상판구조물 300: 저판구조물
100: wall wall 110: wall portion
120: lower beam 130: upper beam
140: earth plate 150a: right tie rod
150b: left tie rod 150c: middle tie rod
160: intermediate file 170: the upper intermediate file
200a, 200b: left top structure, right top structure
200: top plate structure 300: bottom plate structure

Claims (10)

(a) 횡방향으로 서로 이격되도록 형성된 굴착공(310) 선단에, 벽체부(110)로부터 하부로 연장되어 일체화된 하부빔(120)이 지지되도록 하고, 벽체부(110)로부터 상부로 연장되어 일체화된 상부빔(130)이 지반 표면에 위치하도록 흙막이벽체(100)를 인양하여 삽입 시공하는 단계;
(b) 흙막이벽체(100) 사이의 지반에 중간파일(160)을 하방으로 시공하여 중간파일 (160) 상단과 흙막이벽체(100)의 상부빔(130) 상단 사이에 타이로드(150)를 설치하는 단계;
(c) 상기 타이로드(150)가 설치되지 않은 중간파일(160)과 흙막이벽체(100)의 상부빔(130) 사이의 지반을 하방으로 굴착하면서, 굴착에 의하여 형성되는 굴착공간(S1)쪽으로 지반이 붕괴되지 않도록 중간파일(160)과 흙막이벽체(100)의 상부빔(130)에 토류판(140)을 설치하는 단계; 및
(d) 상기 굴착공간(S1)에서 흙막이벽체의 벽체부 상단이 노출되면 상기 벽체부 상단에 상판구조물(200a)을 일부 시공하는 단계;를 포함하여,
상기 타이로드가 설치되는 지반은 차량통행이 통제되지 않은 상태에서 상판구조물 일부를 시공할 수 있도록 하는 흙막이벽체를 이용한 지중구조물 시공방법.
(a) extends downward from the wall portion 110 to support the integrated lower beam 120 at the tip of the excavation hole 310 formed to be spaced apart from each other in the lateral direction, and extends upward from the wall portion 110. Lifting and inserting the retaining wall 100 so that the integrated upper beam 130 is positioned on the ground surface;
(b) installing the tie rod 150 between the upper end of the intermediate pile 160 and the top of the upper beam 130 of the retaining wall 100 by constructing the intermediate pile 160 downward on the ground between the retaining wall 100. Doing;
(c) while excavating the ground between the intermediate pile 160 and the upper beam 130 of the retaining wall 100, the tie rod 150 is not installed, toward the excavation space (S1) formed by excavation Installing the earth plate 140 on the upper beam 130 of the intermediate pile 160 and the retaining wall 100 so that the ground does not collapse; And
(d) when the top of the wall portion of the earth wall in the excavation space (S1) is exposed, the step of constructing a part of the upper plate structure (200a) on the top of the wall; including,
The ground on which the tie rod is installed is an underground structure construction method using an earth retaining wall to allow construction of a portion of a top plate structure in a state where vehicle traffic is not controlled.
제 1항에 있어서,
상기 (d) 단계이후에,
(e) 상기 일부 시공된 상판구조물(200a) 단부 상면으로부터 상방으로 상판중간파일(170)을 더 형성시킨 후, 상판중간파일(170)에 토류판을 설치하여 굴착공간(S1)을 되메움하는 단계; 및
(f) 상기 되메움된 굴착공간(S1)에 의하여 차량통행이 가능하도록 하면서 타이로드(150)가 설치된 지반을 하방으로 굴착하여 시공된 중간파일(160)과 타이로드(150)를 함께 제거하여 굴착공간(S2)에서 먼저 시공된 상판구조물(200a)이 노출되도록 하는 단계;를 더 포함하는 흙막이벽체를 이용한 지중구조물 시공방법.
The method of claim 1,
After step (d),
(e) further forming a top plate middle pile 170 upward from the upper surface of the end of the partially structured top plate structure 200a, and installing a earth plate on the top plate middle pile 170 to backfill the excavation space (S1). ; And
(f) excavating the ground where the tie rod 150 is installed while allowing the vehicle to pass by the backfilled excavation space (S1) to remove the intermediate pile 160 and the tie rod 150 installed together The construction of the underground structure using the earthwall wall further comprises; exposing the top plate structure (200a) first constructed in the excavation space (S2).
제 2항에 있어서,
상기 (f) 단계 이후에,
(g) 상기 노출된 상판구조물(200a)에 상판구조물(200b)을 더 형성시켜 상판구조물(200) 시공을 완료하는 단계;
(h) 상기 더 형성시킨 상판구조물(200b) 상부를 되메움하여 차량통행이 가능하도록 하는 단계; 및
(i) 상기 상판구조물(200) 하방을 굴착하여 지중구조물의 저판구조물(300)을 시공하는 단계;를 더 포함하는 흙막이벽체를 이용한 지중구조물 시공방법.
The method of claim 2,
After step (f),
(g) completing the construction of the upper plate structure 200 by further forming the upper plate structure 200b on the exposed upper plate structure 200a;
(h) backfilling the upper plate structure 200b further formed to enable vehicle traffic; And
(i) excavating the upper plate structure 200 below to construct the bottom plate structure 300 of the underground structure.
제 3항에 있어서,
상기 (g) 단계에서,
상기 벽체부 상단에 일부 시공된 상판구조물(200a)은 저면지지블록(210)을 통해 수평을 유지하면서 지지 설치되어 중간파일(160)을 제거하여 형성된 굴착공간(S2)를 이용하여 상판구조물(200b)을 더 형성시켜 상판구조물(200) 시공을 완료하도록 하는 흙막이벽체를 이용한 지중구조물 시공방법.
The method of claim 3,
In the step (g),
The upper plate structure 200a partially installed on the top of the wall portion is supported while being horizontally maintained through the bottom support block 210 to remove the intermediate pile 160, and thus, the upper plate structure 200b. The underground structure construction method using the earth wall to complete the construction of the upper plate structure 200 by further forming a).
제 1 항 내지 제 4항 중 어느 한항에 의하여 시공된 흙막이벽체를 이용한 지중구조물.An underground structure using an earth wall constructed according to any one of claims 1 to 4. (a) 횡방향으로 서로 이격되도록 형성된 3개의 굴착공 선단에, 벽체부로부터 하부로 연장되어 일체화된 하부빔이 지지되도록 하고, 벽체로부터 상부로 연장되어 일체화된 상부빔이 지반 표면에 위치하도록 흙막이벽체를 인양하여 삽입 시공하는 단계;
(b) 흙막이벽체 사이사이의 지반에 양 중간파일을 하방으로 시공하여 양 중간파일 상단과 중간 흙막이벽체의 상부빔 상단 사이에 타이로드를 설치하는 단계;
(c) 상기 타이로드가 설치되지 않은 중간파일과 흙막이벽체의 상부빔 사이의 지반을 하방으로 굴착하면서, 굴착에 의하여 형성되는 굴착공간(S1)쪽으로 지반이 붕괴되지 않도록 중간파일과 흙막이벽체의 상부빔에 토류판을 설치하는 단계; 및
(d) 상기 굴착공간(S1)에서 흙막이벽체의 벽체부 상단이 노출되면 상기 벽체부 상단에 상판구조물(200a,200b)을 일부 시공하는 단계;를 포함하여,
상기 타이로드가 설치되는 지반은 차량통행이 통제되지 않은 상태에서 상판구조물 일부를 시공할 수 있도록 하는 흙막이벽체를 이용한 지중구조물 시공방법.
(a) At the tip of the three excavation holes formed to be spaced apart from each other in the transverse direction, the bottom of the wall is extended so as to support the integrated lower beam, and from the wall upwards so that the integrated upper beam is located on the ground surface. Lifting and inserting the wall;
(b) constructing both intermediate piles downwards on the ground between the barrier walls to install tie rods between the upper ends of both intermediate piles and the upper beams of the intermediate barrier walls;
(c) while excavating the ground between the intermediate pile and the upper beam of the retaining wall without the tie rods downward, the upper part of the intermediate pile and the retaining wall so that the ground does not collapse toward the excavation space (S1) formed by the excavation. Installing an earth plate on the beam; And
(d) when the top of the wall portion of the earth wall in the excavation space (S1) is exposed, the step of constructing a part of the upper plate structure (200a, 200b) on the top of the wall;
The ground on which the tie rod is installed is an underground structure construction method using an earth retaining wall to allow construction of a portion of a top plate structure in a state where vehicle traffic is not controlled.
제 6항에 있어서,
상기 (d) 단계이후에,
(e) 상기 일부 시공된 상판구조물(200a,200b) 단부 상면으로부터 상방으로 상판중간파일(170)을 더 형성시킨 후, 상판중간파일(170)에 토류판을 설치하여 굴착공간(S1)을 되메움하는 단계; 및
(f) 상기 되메움된 굴착공간(S1)에 의하여 차량통행이 가능하도록 하면서 타이로드(150)가 설치된 지반을 하방으로 굴착하여 시공된 중간파일(160)과 타이로드(150)를 함께 제거하여 굴착공간(S2)에서 먼저 시공된 상판구조물(200a,200b)이 노출되도록 하는 단계;를 더 포함하는 흙막이벽체를 이용한 지중구조물 시공방법.
The method of claim 6,
After step (d),
(e) After further forming the upper plate intermediate pile 170 upward from the upper surface of the upper part of the structure (200a, 200b) of the partially constructed, the earth plate is installed in the upper plate intermediate pile 170 to fill the excavation space (S1) Doing; And
(f) excavating the ground where the tie rod 150 is installed while allowing the vehicle to pass by the backfilled excavation space (S1) to remove the intermediate pile 160 and the tie rod 150 installed together Method for constructing the underground structure using the earthwall wall further comprises; exposing the top plate structure (200a, 200b) first constructed in the excavation space (S2).
제 7항에 있어서,
상기 (f) 단계 이후에,
(g) 상기 노출된 상판구조물(200a,200b)에 상판구조물(200c)을 더 형성시켜 상판구조물(200) 시공을 완료하는 단계;
(h) 상기 더 형성시킨 상판구조물(200) 상부를 되메움하여 차량통행이 가능하도록 하는 단계; 및
(i) 상기 상판구조물(200) 하방을 굴착하여 지중구조물의 저판구조물(300)을 시공하는 단계;를 더 포함하는 흙막이벽체를 이용한 지중구조물 시공방법.
The method of claim 7, wherein
After step (f),
(g) further forming the upper plate structure 200c on the exposed upper plate structures 200a and 200b to complete construction of the upper plate structure 200;
(h) backfilling the upper plate structure 200 further formed to enable vehicle traffic; And
(i) excavating the upper plate structure 200 below to construct the bottom plate structure 300 of the underground structure; underground construction method using a mud wall.
제 8항에 있어서,
상기 (g) 단계에서,
상기 벽체부 상단에 일부 시공된 상판구조물(200a,200b)은 저면지지블록(210)을 통해 수평을 유지하면서 지지 설치되어 중간파일(160)을 제거하여 형성된 굴착공간(S2)을 이용하여 상판구조물(200c)을 더 형성시켜 상판구조물(200) 시공을 완료하도록 하는 흙막이벽체를 이용한 지중구조물 시공방법.
The method of claim 8,
In the step (g),
The upper plate structures 200a and 200b partially constructed on the top of the wall part are installed while supporting the horizontal structure through the bottom support block 210 to remove the intermediate pile 160 to form the upper plate structure using the excavation space S2. Underground structure construction method using the earth wall to complete the construction of the upper plate structure 200 by further forming (200c).
제 6 항 내지 제 9항 중 어느 한항에 의하여 시공된 흙막이벽체를 이용한 지중구조물.An underground structure using a retaining wall constructed according to any one of claims 6 to 9.
KR1020180055233A 2018-05-15 2018-05-15 Under ground structure construction method using concrete wall with upper, under column and under ground structure therewith KR20190130745A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020180055233A KR20190130745A (en) 2018-05-15 2018-05-15 Under ground structure construction method using concrete wall with upper, under column and under ground structure therewith

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020180055233A KR20190130745A (en) 2018-05-15 2018-05-15 Under ground structure construction method using concrete wall with upper, under column and under ground structure therewith

Publications (1)

Publication Number Publication Date
KR20190130745A true KR20190130745A (en) 2019-11-25

Family

ID=68730525

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020180055233A KR20190130745A (en) 2018-05-15 2018-05-15 Under ground structure construction method using concrete wall with upper, under column and under ground structure therewith

Country Status (1)

Country Link
KR (1) KR20190130745A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100106274A (en) 2010-09-07 2010-10-01 동국대학교 산학협력단 Dry connection for a prefabricated beam-column structures and construction method by that connection
KR101379305B1 (en) 2013-08-21 2014-03-28 안창일 Wall structure manufacturing method using precast front wall panel and precast back wall panel
KR101568194B1 (en) 2014-12-15 2015-11-12 (주)서현컨스텍 Pc member connection method using pc connector and pc structure therewith

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100106274A (en) 2010-09-07 2010-10-01 동국대학교 산학협력단 Dry connection for a prefabricated beam-column structures and construction method by that connection
KR101379305B1 (en) 2013-08-21 2014-03-28 안창일 Wall structure manufacturing method using precast front wall panel and precast back wall panel
KR101568194B1 (en) 2014-12-15 2015-11-12 (주)서현컨스텍 Pc member connection method using pc connector and pc structure therewith

Similar Documents

Publication Publication Date Title
KR101652163B1 (en) Concrerte pannel for retaining wall and method for constructing retaining wall using the same
KR102195504B1 (en) Construction method for Eearth self-retaining wall using reinforcing member and CIP construction method
KR20110077334A (en) Retaining wall structure and construction method of the retaining wall structure
KR101843023B1 (en) Shear connector for temporary retaining wall file and building outer wall, and method for constructing an underground structure using thereof
KR101792844B1 (en) Under ground structure construction method using underground column wall and under ground structure therewith
KR102196532B1 (en) Under ground structure construction method using composite steel pile underground column wall and top-down under ground structure therewith
KR102195510B1 (en) Construction method for earth self-retaining wall using reinforcing member and PHC pile
KR101902791B1 (en) Under ground structure construction method using composite steel pile and under ground structure therewith
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR101902786B1 (en) Under ground structure construction method using composite sheet pile and under ground structure therewith
JP2013015015A (en) Structure and construction method for earth retaining wall
KR102362257B1 (en) Top-down construction method
KR101282770B1 (en) Precast straight wall foundation and construction method therefor
KR101599931B1 (en) Retaining Wall using Precast Panels and PHC Piles having Steel Bands, and Constructing Method of such Retaining Wall
JP3829319B2 (en) Construction method of underground hollow structure and its underground hollow structure
KR20190084633A (en) Top-down construction method for concrete building structure using steel pile underground wall and shear support plate
KR102277470B1 (en) Basement Composite Wall Using Retaing Wall And Method for Constructing the Same
KR20190130745A (en) Under ground structure construction method using concrete wall with upper, under column and under ground structure therewith
KR102195496B1 (en) Pile for earth self-retaining wall using cast in place concrete pile with double I beam
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
KR20110034831A (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
JP2017119953A (en) Building method using reverse out method
JPH11190024A (en) Earth retaining work
KR102649959B1 (en) Longitudinal and lateral integration structure of pile and structure manufactured using the same
JP2004132124A (en) Pneumatic caisson and pneumatic caisson constructing method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right