KR20190052284A - Self reliance earth retaining construction method having prestress introduced of Double I Beam - Google Patents

Self reliance earth retaining construction method having prestress introduced of Double I Beam Download PDF

Info

Publication number
KR20190052284A
KR20190052284A KR1020170147835A KR20170147835A KR20190052284A KR 20190052284 A KR20190052284 A KR 20190052284A KR 1020170147835 A KR1020170147835 A KR 1020170147835A KR 20170147835 A KR20170147835 A KR 20170147835A KR 20190052284 A KR20190052284 A KR 20190052284A
Authority
KR
South Korea
Prior art keywords
pile
ground
thumb pile
thumb
tension member
Prior art date
Application number
KR1020170147835A
Other languages
Korean (ko)
Other versions
KR102097855B1 (en
Inventor
백진명
이종범
Original Assignee
백진명
이종범
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 백진명, 이종범 filed Critical 백진명
Priority to KR1020170147835A priority Critical patent/KR102097855B1/en
Publication of KR20190052284A publication Critical patent/KR20190052284A/en
Application granted granted Critical
Publication of KR102097855B1 publication Critical patent/KR102097855B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a self-reliance earth retaining construction method, and more particular, to a self-reliance earth retaining construction method for applying compression stress to a double I-beam, which applies compression stress to an H-pile formed as a double I-beam, thereby effectively suppressing the displacement of the ground behind earth retaining by the increased rigidity thereof and reducing the construction period and improving economic efficiency with no need for a support material. A self-reliance earth retaining construction method for applying compression stress to a double I-beam, according to an appropriate embodiment of the present invention, comprises the steps of: boring holes to a required depth at intervals to embed, at predetermined intervals, H-piles in the ground for which earth retaining is required; respectively embedding the H-piles, each having a tendon for fixing a lower end thereof, in the holes bored in a row; filling the holes, in which the H-piles are embedded, with soil or sand; primarily excavating the ground on a front side of the H-piles to install a wale and tension the tendon; installing the wale on an upper end of the H-pile on an excavation side, passing an upper end of the tendon through the wale, and tensioning the tendon to be seated on the wale, applying compression stress to the H-pile; and excavating the ground to a required excavation depth while installing earth plates between the H-piles installed in the row.

Description

더블 아이 빔에 압축응력이 도입된 자립식 흙막이 공법{Self reliance earth retaining construction method having prestress introduced of Double I Beam}BACKGROUND OF THE INVENTION 1. Field of the Invention [0001] The present invention relates to a self-supporting earth retaining construction method having a double-

본 발명은 자립식 흙막이 공법에 관한 것으로, 특히 더블 아이 빔으로 구성된 엄지말뚝에 압축응력이 도입되도록 하여 증가된 강성에 의해 흙막이 배면지반의 변위를 효과적으로 억제시킬 수 있고, 지보재의 불필요로 공기의 단축과 경제성이 우수한 더블 아이 빔에 압축응력이 도입된 자립식 흙막이 공법에 관한 것이다.In particular, the present invention relates to a self-supporting earth retaining method, and more particularly, it relates to a self-supporting earth retaining method capable of effectively introducing compressive stress into a thumb pile composed of a double eye beam to effectively suppress displacement of the earth retaining back ground by an increased rigidity, And a self-sustaining type earth retaining method in which compressive stress is introduced into a double eye beam excellent in economy.

기존의 자립식 흙막이 공법은 1열 벽체나 2열 벽체로 흙막이 토류벽을 형성하여 사용되어 왔으나 1열 벽체로 흙막이토류벽을 형성할 경우 토압에 의해 배면에 변위가 크게 발생하므로 굴착심도가 매우 낮고 지반이 양호한 조건에 극히 제한적으로 사용되었다. 이를 보완하기 위하여 2열 벽체에 의해 흙막이토류벽을 형성하여 자립식벽체로 사용하는 다양한 공법이 개발되어 사용되고 있으나 2열 벽체를 형성하기 위하여 배면의 여유부지를 필요로 함에 따라 사용에 제약이 따르고 공사기간과 공사비가 증가하는 문제점이 있다.The existing self-retaining retaining method has been used to form the earth retaining wall with 1-row wall or 2-wall wall. However, when the wall of the retaining wall is formed with the 1-wall wall, displacement occurs greatly on the backside due to earth pressure, It has been used very limitedly under good conditions. In order to compensate this, a variety of construction methods have been developed and used as self-sustaining wall by forming the earth retaining wall by the two-row wall. However, since it requires a backing site to form the two-wall wall, And the construction cost is increased.

따라서 기존의 자립식 흙막이 공법의 단점을 극복하기 위하여 변위억제와 휨저항성을 증대시킬 수 있는 흙막이 공법이 요구된다.Therefore, a retention method that can increase displacement and bending resistance is required to overcome the disadvantages of existing self - retaining retention method.

본 발명의 배경이 되는 기술로는 한국 등록실용신안 등록번호 제20-0293048호로서, '프리스트레스가 도입된 지하벽을 이용한 흙막이 구조'가 제안되어 있다. 이는 대지경계선을 따라 소정의 심도까지 굴착된 굴착공에 형성되며, 프리스트레스가 도입된 지하벽; 및 상기 지하벽에 형성된 스트러트 와 띠장과 같은 지보재;를 포함하여 흙막이 구조를 제공한다. 그런데 이 배경기술은, 철근콘크리트 벽체에 매설된 긴장재에 인장을 도입시켜 흙막이를 시공하는 구조로서, 콘크리트의 양생과정을 필요로 하므로 현장에서의 공기가 길어질 수 밖에 없다.As a background of the present invention, Korean Registered Utility Model Registration No. 20-0293048 has proposed a 'retaining structure using a prestressed underground wall'. This is formed in a drilling hole excavated up to a predetermined depth along a site boundary line, and includes a prestressed underground wall; And a support such as a strut and a wale formed on the underground wall. However, this background technique is a structure for applying a tension to a tensional material embedded in a reinforced concrete wall to form a retaining wall, which requires a curing process of the concrete, so that the air in the field is inevitably lengthened.

본 발명의 다른 배경기술로는 한국 등록특허 등록번호 제10-1729117호로서, '프리스트레스가 도입된 엄지말뚝과 스트러트를 이용한 자립식 가설 흙막이 시공방법'이 제안되어 있다. 이는 엄지말뚝 전면부 일정길이에 1차로 프리스트레스를 가하여 엄지말뚝을 제작하고, 상기 프리스트레스가 도입된 엄지말뚝을 굴착저면 근입부에 충분히 고정될 수 있는 근입장으로 지반을 천공 후, 상기 엄지말뚝을 근입한 후, 1단계로 지반의 얕은 굴착 후, 엄지말뚝 최상부에 띠장과 스트러트를 설치한 후, 상기 엄지말뚝에 2차로 프리스트레스를 가하여 소요압축력을 확보하고, 굴착면 진행시 점점 증가하는 배면토압을 프리스트레스가 도입된 엄지말뚝이 받도록 한 것이다. 그러나 이 배경기술은 매 굴착단계마다 엄지말뚝에 브라켓을 설치해가면서 인장재를 여러번 인장 및 정착시켜야 하는 과정을 필요로 하므로 작업이 번거로울 뿐만 아니라 H빔을 엄지말뚝으로 사용하므로 강성을 증가시키는데 한계가 있다.As another background art of the present invention, Korean Patent Registration No. 10-1729117 proposes a 'self-supporting type permanent earth retaining construction method using a prestressed stiff pile and strut'. This makes it possible to form a thumb pile by first applying a prestress to a predetermined length of the front surface of the pile of the pile and to puncture the ground with a near position where the pile having the prestress introduced therein can be sufficiently fixed to the bottom of the excavation bottom, After a shallow excavation of the ground in the first stage, a welt and a strut are installed at the top of the pile of the thumb, a required compressive force is secured by applying a second prestress to the thumb pile, and the back earth pressure, To receive the thumb peg introduced. However, this background technique requires a process of tensioning and fixing the tensile material several times while installing a bracket on the thumb pile at each excavation step, so that it is not only troublesome to work but also uses the H beam as a thumb pile, so there is a limit to increase rigidity.

한국 등록실용신안 등록번호 제20-0293048호Korean Registered Utility Model Registration No. 20-0293048 한국 등록특허 등록번호 제10-1729117호Korean Patent Registration No. 10-1729117

본 발명은 더블 아이 빔으로 구성된 엄지말뚝에 압축응력이 도입되도록 하여 증가된 강성에 의해 흙막이 배면지반의 변위를 효과적으로 억제시킬 수 있고, 지보재의 불필요로 공기가 단축되고 경제성이 우수하도록 한 더블 아이 빔에 압축응력이 도입된 자립식 흙막이 공법을 제공함에 그 목적이 있다.The present invention relates to a double-eye type pile-type double-eye pile which is capable of introducing compressive stress into a thumb pile composed of a double eye beam, thereby effectively suppressing displacement of the earth retaining pavement ground due to increased rigidity, The present invention has been made to solve the above-mentioned problems occurring in the prior art.

본 발명의 적절한 일 실시 형태에 의한 더블 아이 빔에 압축응력이 도입된 자립식 흙막이 공법은, 흙막이가 필요한 지반에 엄지말뚝을 일정 간격마다 근입하기 위해 해당 간격마다 필요 깊이까지 천공하는 단계와; 하단을 고정시킨 긴장재가 배치된 엄지말뚝을 지반에 1열로 천공된 천공홀에 각기 근입하는 단계와; 엄지말뚝이 근입된 천공홀에 토사 또는 모래를 채움하는 단계와; 띠장의 설치와 긴장재의 인장을 위해 엄지말뚝의 전면측 지반에 1단계 굴착을 실시하는 단계와; 엄지말뚝의 상단에 굴착측에서 띠장을 지지되게 설치하고, 긴장재의 상단을 띠장에 통과시킨 후 긴장재를 인장하여 띠장에 정착시켜서 엄지말뚝에 압축응력을 도입시켜 놓는 단계와; 토류판을 1열로 설치된 엄지말뚝의 사이에 설치해가면서 지반에 소요 굴착심도까지 굴착하는 단계;를 포함하여 시공되는 것을 특징으로 한다.According to a preferred embodiment of the present invention, a self-supporting type earth retaining method in which a compressive stress is introduced into a double eye beam includes the steps of puncturing the pile to a required depth every interval to insert a thumb pile at predetermined intervals on a ground requiring soil retention; A step of placing a thumb pile having a lower fixed end disposed thereon in a perforated hole perforated in the ground; Filling the perforation hole into which the thumb peg is inserted with soil or sand; A step of performing a first stage excavation on the front side ground of the thumb pile for the installation of the belt and the tensioning of the tension member; Placing a wrist strap at the upper end of the thumb pile so as to support the wrist strap, passing the upper end of the strap through a wrist strap, tensioning the strained strap and fixing it to the wrist strap to introduce compressive stress into the thumb pile; And installing the soil plate between the thumb piles installed in one row to excavate the ground to a required depth of excavation.

또한, 본 발명의 적절한 다른 실시 형태에 의한 더블 아이 빔에 압축응력이 도입된 자립식 흙막이 공법은, 흙막이가 필요한 지반에 후열의 엄지말뚝을 일정 간격마다 근입하기 위해 해당 간격마다 필요 깊이까지 천공하는 단계와; 하단을 고정시킨 긴장재가 배치된 후열의 엄지말뚝을 지반에 1열로 천공된 후열의 천공홀에 각기 근입하는 단계와; 엄지말뚝이 근입된 후열의 천공홀에 토사 또는 모래를 채움하는 단계와; 후열의 천공홀로부터 굴착될 영역쪽으로 일정 거리 떨어진 위치에 전열의 엄지말뚝을 지반에 근입하기 위한 천공을 실시하는 단계와; 전열측 천공홀에 전열의 엄지말뚝을 근입하는 단계와; 전열의 엄지말뚝이 근입된 천공홀에 토사 또는 모래를 채움하는 단계와; 후열의 엄지말뚝의 상단부 전면에 후열의 띠장 설치하고, 후열의 띠장과 전열의 엄지말뚝의 사이에 연결강관을 설치하는 단계와; 전열의 띠장 설치와 긴장재의 인장을 위한 1단계 굴착을 실시하고, 전열의 엄지말뚝의 상단에 전열의 띠장을 설치하고, 긴장재의 상단을 후열의 띠장과 연결강관 및 전열의 띠장을 통과시킨 후, 긴장재를 인장하여 전열의 띠장에 정착시켜서 후열의 엄지말뚝에 압축응력을 도입시켜 놓는 단계와; 토류판을 전열의 엄지말뚝에 설치해가면서 지반에 소요 굴착심도까지 굴착하는 단계;를 포함하여 시공되는 것을 특징으로 한다.In the self-supporting earth retaining method in which a compressive stress is introduced into a double eye beam according to another preferred embodiment of the present invention, in order to insert a rear pile of thumb piles at a predetermined interval in a soil requiring soil retention, ; A step of locating a posterior heat-induced pile having a lower end fixed therein in a perforation hole in a row of perforated holes in the ground; Filling the perforation hole of the rear row into which the thumb pile is inserted with soil or sand; Performing perforation to insert a heat-induced thumb pile into the ground at a position spaced a certain distance from the perforation hole of the rear row toward the area to be excavated; A step of placing a heat-induced thumb pile on the heat-transferring perforation hole; Filling the perforation hole into which the thumb peg with the heat is inserted, with gravel or sand; A step of installing a welt of a rear row on the entire upper end of the thumb pile of the rear row and a connecting steel pipe between the welt of the rear row and the thumb pile of the heat row; And the first stage excavation for tensioning of the tension member is carried out, and a wale band of the electric heat is installed at the upper end of the heat pile pile. After passing the upper end of the tension member through the wale cord of the rear row, Tensioning the tensile material and fixing it to the wristband of the heat transfer to introduce compressive stress into the thumb pile of the subsequent row; And a step of excavating the earth plate to a depth of a required excavation depth while installing the earth plate on a heat pile.

또한, 엄지말뚝은 강재로 제작된 더블 아이 빔이 적용된 것을 특징으로 한다.Further, the thumb pile is characterized in that a double eye beam made of a steel material is applied.

또한, 엄지말뚝의 하단에는 긴장재의 하단부를 걸침하기 위한 긴장재 가이드 걸침홈을 갖는 하부 긴장재 가이드 걸침블럭이 설치되고, 엄지말뚝의 상단에는 긴장재의 상단부를 걸침하기 위한 긴장재 가이드 걸침홈을 갖는 상부 긴장재 가이드 걸침블럭이 설치되어져 있는 것을 특징으로 한다.In addition, a lower tensioner guide fastening block is provided at the lower end of the thumb pile, and a lower tensioner guide fastening block having a fastener guide hook fastening block for fastening the lower end of the fastener is installed. At the upper end of the thumb pile, And a stepping block is provided.

또한, 긴장재는 2개가 한 쌍을 이루어 나란하게 엄지말뚝에 배치되고, 한 쌍의 긴장재는 더블 아이 빔의 단면 도심에서 편심거리를 가지고 굴착영역의 반대쪽에 위치되는 플랜지측에 가까이 배치된 것을 특징으로 한다.In addition, the two tension members are disposed in parallel to each other in a pair of thumb piles, and a pair of the tension members are disposed close to the flange side located on the opposite side of the excavation region with an eccentric distance from the center of the cross section of the double eye beam do.

또한, 띠장은 강재로 제작된 더블 아이 빔이 적용되어 플랜지에 긴장재를 삽통시키기 위한 슬롯이 형성된 것을 특징으로 한다.In addition, the band is characterized in that a slot for allowing the tension member to be inserted into the flange is formed by applying a double eye beam made of a steel material.

또한, 긴장재는 PC 강선 또는 PC 강연선인 것을 특징으로 한다.Further, the tension member is characterized by being a PC steel wire or a PC steel wire.

본 발명의 더블 아이 빔에 압축응력이 도입된 자립식 흙막이 공법에 따르면, 더블 아이 빔으로 구성된 엄지말뚝에 압축응력이 도입되도록 하여 증가된 강성에 의해 흙막이 배면지반의 변위를 효과적으로 억제시킬 수 있다. 또한 지보재가 불필요하여 공기를 단축시킬 수 있어 경제성 우수하다. 또한 배면의 부지여유에 제약을 받지 않고 깊은 심도까지 자립이 가능하다. 또한, 2열 자립식 흙막이를 시공할 수 있어 배면에 부지여유가 있고 굴착심도가 깊어지는 경우에도 적용될 수 있다.According to the self-supporting earth retaining method in which the compressive stress is introduced into the double eye beam of the present invention, compressive stress is introduced into the thumb pile composed of the double eye beam, thereby effectively suppressing the displacement of the earth retaining back ground due to the increased rigidity. Also, it is economical because it can shorten the air because the support material is unnecessary. In addition, it can be self-supporting up to a deep depth without being restricted by the ground margin of the back side. In addition, it can be applied to the case where two rows of self-standing earthmoving can be constructed, so that there is a lot of ground on the back and depth of drilling is deepened.

본 명세서에서 첨부되는 다음의 도면들은 본 발명의 바람직한 실시 예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 첨부한 도면에 기재된 사항에만 한정되어서 해석되어서는 아니 된다.
도 1 내지 도 6은 본 발명의 제1 실시예에 따른 1열 자립식 흙막이 공법의 시공순서도.
도 7의 (가) 및 (나)는 본 발명의 제1 실시예에 따라 긴장재가 배치된 엄지말뚝의 사시도 및 A-A선 단면도.
도 8의 (가) 및 (나)는 엄지말뚝 하부 및 상부측 부분 절취상태도.
도 9는 본 발명에 따른 엄지말뚝의 이음부측 사시도.
도 10은 본 발명의 제1 실시예에 따른 1열 자립식 흙막이가 완공된 상태에서의 평면도.
도 11 내지 도 17은 본 발명의 제2 실시예에 따른 2열 자립식 흙막이 공법의 시공순서도.
도 18은 도 14에서의 긴장재 상부측 정착 상태를 나타낸 사시도.
도 19는 본 발명의 제2 실시예에 따른 2열 자립식 흙막이가 완공된 상태에서의 평면도.
BRIEF DESCRIPTION OF THE DRAWINGS The accompanying drawings, which are incorporated in and constitute a part of the specification, illustrate exemplary embodiments of the invention and, together with the description, serve to explain the principles of the invention, Shall not be construed as limiting.
1 to 6 are views showing a construction sequence of a one-row self-standing earthmoving method according to a first embodiment of the present invention.
7 (a) and 7 (b) are a perspective view and a cross-sectional view taken along the line AA of a thumb pile in which a tensile material is disposed according to a first embodiment of the present invention.
8 (a) and 8 (b) are partial cut-away diagrams of the lower and upper parts of the thumb pile.
9 is a perspective view of a joint part of a thumb pile according to the present invention.
FIG. 10 is a plan view of a single-row self-standing earthmoving according to the first embodiment of the present invention in a completed state; FIG.
FIGS. 11 to 17 are flowcharts showing a construction sequence of a two-row self-standing earthmoving method according to a second embodiment of the present invention.
Fig. 18 is a perspective view showing the upper side of the tension member in Fig. 14; Fig.
19 is a plan view of a two-row self-standing earthmoving according to a second embodiment of the present invention in a completed state;

아래에서 본 발명은 첨부된 도면에 제시된 실시 예를 참조하여 상세하게 설명이 되지만 제시된 실시 예는 본 발명의 명확한 이해를 위한 예시적인 것으로 본 발명은 이에 제한되지 않는다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described in detail below with reference to the embodiments shown in the accompanying drawings, but the present invention is not limited thereto.

<제1 실시예>&Lt; Embodiment 1 >

먼저, 1열 자립식 흙막이 공법에 대하여 설명한다.First, the one-row self-standing type earth retaining method will be described.

우선, 도 1과 같이 흙막이가 필요한 지반(10)에 후술할 엄지말뚝(20)을 일정 간격마다 근입하기 위해 해당 간격마다 필요 깊이까지 천공이 이루어진다. 천공은 천공기(200)를 통해 이루어질 수 있다. 여기서 천공의 간격은 후설치되는 토류판(50)의 길이에 따라 결정될 수 있다. 따라서 천공홀(101)은 1열로 일정 간격을 가지고 배열되게 된다.First, as shown in FIG. 1, perforation is carried out to a required depth at each interval to insert a thumb pile 20, which will be described later, at a predetermined interval on a ground 10 requiring soil retention. The perforation can be made through the perforator (200). Here, the interval of the perforations may be determined according to the length of the soil plate 50 to be installed later. Therefore, the perforation holes 101 are arranged at regular intervals in one row.

다음, 도 2와 같이 엄지말뚝(20)을 지반에 1열로 천공된 천공홀(101)에 각기 근입하여 놓는다. 이는 엄지말뚝(20)을 크레인(300)으로 인양한 후 천공홀(101)에 삽입시켜서 이루어질 수 있다. Next, as shown in FIG. 2, the thumb pile 20 is inserted into the perforation hole 101 formed in one row on the ground. This can be accomplished by lifting the thumb pile 20 to the crane 300 and then inserting it into the perforation hole 101.

엄지말뚝(20)은 본 실시 예에서 강재로 제작된 더블 아이 빔이 적용된다. 따라서 엄지말뚝(20)은 2열의 웨브(201)와 웨브(201)의 양단에 각기 접합된 플랜지(202)를 갖는다. 더블 아이 빔으로 제작된 엄지말뚝(20)은 근입하기 전에 긴장재(30)가 엄지말뚝(20)에 배치된다. 따라서 도 10과 같이 엄지말뚝(20)은 1열로 시공된다.The thumb pile 20 is a double eye beam made of steel in this embodiment. Thus, the thumb pile 20 has two rows of webs 201 and flanges 202 that are joined to opposite ends of the webs 201, respectively. The thumb pile 20 made of double eyepieces is placed on the thumb pile 20 before the tension member 30 is inserted. Therefore, the thumb pile 20 is constructed in a single row as shown in FIG.

도 7과 같이 긴장재(30)는 2개가 한쌍을 이루어 나란하게 엄지말뚝(20)에 배치되고, 한 쌍의 긴장재(30)는 더블 아이 빔의 단면 도심(C)에서 편심거리(S)를 가지고 굴착영역의 반대쪽에 위치되는 플랜지(202)측에 가까이 배치됨이 바람직하다. 긴장재(30)는 PC 강선 또는 PC 강연선이 될 수 있다.As shown in FIG. 7, the two tensile members 30 are arranged on the thumb pile 20 in a pair, and the pair of tensile members 30 have an eccentric distance S on the cross-sectional center C of the double eye beam And is disposed close to the side of the flange 202 located on the opposite side of the excavation area. The tensile member 30 may be a PC steel wire or a PC steel wire.

이때 도 7 및 도 8과 같이 엄지말뚝(20)의 하단에는 긴장재(30)의 하단부를 걸침하기 위한 긴장재 가이드 걸침홈(22a)을 갖는 하부 긴장재 가이드 걸침블럭(22)이 설치되고, 엄지말뚝(20)의 상단에는 긴장재(30)의 상단부를 걸침하기 위한 긴장재 가이드 걸침홈(24a)을 갖는 상부 긴장재 가이드 걸침블럭(24)이 설치되어진다. 긴장재(30)의 하단은 하부 긴장재 가이드 걸침블럭(22)에 걸침되어져 주지의 하부 정착구(26)에 정착되어 있고, 긴장재(30)의 상단은 상부 긴장재 가이드 걸침블럭(24)에 걸침된 후 엄지말뚝(20)의 플랜지(202)를 삽통하여 일정 길이가 늘어져 있게 배치된다.7 and 8, at the lower end of the thumb pile 20, a lower tension member guide block 22 having a tension member guide groove 22a for receiving the lower end portion of the tension member 30 is installed, 20 is provided with an upper tension guide guide block 24 having a tension member guide groove 24a for receiving the upper end of the tension member 30. [ The lower end of the tension member 30 is fixed to the lower fixing member 26 by being stuck on the lower tension member guide fastening block 22 and the upper end of the tension member 30 is stuck on the upper tension member guide fastening block 24, And the flange 202 of the pile 20 is inserted and arranged so as to have a predetermined length.

한편, 엄지말뚝(20)을 길게 제작해야 하는 경우, 도 9와 같이 플랜지 커버플레이트(5)와 웨브 커버플레이트(6)를 볼트와 너트를 사용하여 이음부에 결합시켜 엄지말뚝(20)을 길게 구성할 수 있다. 플랜지 커버플레이트(5)는 평판형으로 구성되며, 웨브 커버플레이트(6)는 ] 형 단면을 갖는 판형으로 구성된다.9, the flange cover plate 5 and the web cover plate 6 are coupled to the joint using bolts and nuts so that the thumb pile 20 is elongated Can be configured. The flange cover plate 5 is formed in a flat plate shape, and the web cover plate 6 is formed in a plate shape having a] shaped cross section.

그 다음, 도 3과 같이 엄지말뚝(20)이 근입된 천공홀(101)에 토사 또는 모래를 채움한다. 이같이 천공홀(101)에 토사 또는 모래를 채움되면, 엄지말뚝(20)과 천공홀(101)의 사이에 틈새가 없어진다. Then, as shown in FIG. 3, the perforation hole 101 into which the thumb pile 20 is inserted is filled with sand or sand. When the perforation hole 101 is filled with sand or sand, the gap between the thumb pile 20 and the perforation hole 101 disappears.

그 다음, 도 4와 같이 후술할 띠장(40)의 설치와 긴장재(30)의 인장을 위해 엄지말뚝(20)의 전면측 지반에 굴삭기(400)를 사용하여 1단계 굴착을 실시한다.Next, as shown in FIG. 4, the excavator 400 is used to perform a one-step excavation on the front surface side ground of the thumb pile 20 for the installation of the wale band 40 and the tensioning of the tension member 30.

그 다음, 도 5와 같이 엄지말뚝(20)의 상단에 굴착측에서 띠장(40)을 지지되게 설치하고, 긴장재(30)의 상단을 띠장(40)에 통과시킨 후 긴장재(30)를 도시안된 유압잭으로 인장하여 도 6의 띠장(40)에 정착시켜 놓는다. 이때 긴장재(30)의 정착은 띠장(40)의 배면에 배치된 주지의 상부 정착구(28)를 통해 이루어질 수 있다.5, the wrist strap 40 is supported on the upper end of the thumb pile 20 and the upper end of the strap 30 is passed through the wrist strap 40, Tensioned by the hydraulic jack, and fixed to the wristband 40 of Fig. At this time, the fixing of the tension member 30 may be performed through a known upper fixing hole 28 disposed on the back surface of the wristband 40.

띠장(40)은 도 6과 같이 강재로 제작된 더블 아이 빔이 적용되어 플랜지에 긴장재(30)를 삽통시키기 위한 슬롯(401)을 갖는다.The wrist strap 40 has a slot 401 for inserting the straining material 30 into the flange by applying a double eye beam made of a steel material as shown in Fig.

이같이 긴장재(30)에 인장력이 부여되어져 정착되면, 긴장재(30)에 긴장력이 작용하여 엄지말뚝(20)에 압축응력이 도입된다. 따라서 압축응력이 도입된 엄지말뚝(20)은 휨내력이 증가된다.When the tensile force is applied to the tensile member 30, the tensile force is applied to the tensile member 30 and compressive stress is introduced into the thumbed pile 20. Therefore, the bending strength of the thumb pile 20 to which compression stress is introduced increases.

그 다음, 도 6과 같이 토류판(50)을 1열로 설치된 엄지말뚝(20)에 설치해가면서 지반에 소요 굴착심도까지 굴착하여 1열 자립식 흙막이의 시공이 완료된다.Then, as shown in FIG. 6, the soil plate 50 is installed on the thumb pile 20 installed in one row, and the soil is excavated up to the required excavation depth to complete the construction of the one-row self-standing earthmoving.

이같이 제1 실시 예의 공법으로 시공된 1열 자립식 흙막이에 적용된 엄지말뚝(20)은 고강도 강재로 제작된 더블 아이 빔으로 2열의 웨브(201)를 갖기 때문에 강성을 증대시킬 수 있다. 또한, 긴장재(30)에 프리스트레스가 도입되어 엄지말뚝(20)의 강성이 증대됨으로서 1열 자립식 흙막이는 배면지반의 변위를 효과적으로 억제시킬 수 있다.As described above, the thumb pile 20 applied to the self-supporting single-row retaining structure constructed by the method of the first embodiment has two rows of webs 201 with a double eye beam made of a high-strength steel, which can increase the rigidity. Also, since the prestress is introduced into the prestressing material 30 to increase the rigidity of the thumb pile 20, the one-row self-standing earthmoving can effectively suppress the displacement of the back ground.

이로 인해 본 공법은 1열 벽체에 의한 지보재가 불필요하여 공기를 단축시킬 수 있어 경제성이 우수하다. 또한 배면의 부지여유에 제약을 받지 않고 깊은 심도까지 자립이 가능하다. As a result, this method is economical because it can shorten the air because it does not require the support material by the one-row wall. In addition, it can be self-supporting up to a deep depth without being restricted by the ground margin of the back side.

<제2 실시예>&Lt; Embodiment 2 >

한편, 본 발명은 배면에 부지여유가 있고 굴착심도가 깊어질 경우 2열 자립식 흙막이를 도 11 내지 도 17과 같은 작업공정을 거쳐 시공할 수 있다. 도 11 내지 도 17에서 제1실시 예와 동일 또는 동등한 부분은 동일 부호를 사용하여 설명한다.On the other hand, in the present invention, when there is a site margin on the backside and a depth of excavation is deep, the two-row self-standing earthmoving can be applied through the work process as shown in FIG. 11 to FIG. 11 to 17, the same or equivalent parts to those of the first embodiment will be described using the same reference numerals.

먼저, 도 11과 같이 흙막이가 필요한 지반(10)에 후열의 엄지말뚝(20)을 일정 간격마다 근입하기 위해 해당 간격마다 필요 깊이까지 천공기(200)를 통해 천공한 후, 후열의 엄지말뚝(20)을 지반에 1열로 천공된 후열의 천공홀(101)에 크레인(300)을 이용하여 각기 근입하여 놓는다. 이때 엄지말뚝(20)에는 제1 실시예와 동일하게 하단을 고정시킨 긴장재(30)가 배치되어 있다. 물론 긴장재(30)는 상부 긴장재 가이드 걸침블럭(24)과 하부 긴장재 가이드 걸침블럭(22)에 걸침되어 있고, 긴장재(30)의 하단은 하부 긴장재 가이드 걸침블럭(22)에 상기와 동일한 정착구를 통해 정착되어 있다. 또한 긴장재(30)는 도 7과 같이 2개가 한쌍을 이루어 나란하게 후열의 엄지말뚝(20)에 배치되고, 한 쌍의 긴장재(30)는 더블 아이 빔의 단면 도심에서 편심거리(S)를 가지고 굴착영역의 반대쪽에 위치되는 플랜지(202)측에 가까이 배치됨이 바람직하다.First, as shown in FIG. 11, in order to insert the rear-end thumb pile 20 at a predetermined interval in the ground 10 requiring soil retention, the perforation is pierced through the perforator 200 to the required depth every interval, Are inserted into the perforation holes 101 of the rear row, which have been drilled in one row in the ground, by using the crane 300, respectively. At this time, the thrust pile (20) is provided with a tensile material (30) having its lower end fixed in the same manner as in the first embodiment. Of course, the tension member 30 is stuck to the upper tension member guide block 24 and the lower tension member guide block 22, and the lower end of the tension member 30 is fixed to the lower tension member guide fastening block 22 through the same fixing hole Has been established. 7, the two tensile members 30 are arranged in a row of the thumb piles 20 in a row, and the pair of tensile members 30 have an eccentric distance S in the center of the cross section of the double eye beam And is disposed close to the side of the flange 202 located on the opposite side of the excavation area.

그 다음, 도 12와 같이 엄지말뚝(20)이 근입된 후열의 천공홀(101)에 토사 또는 모래를 채움한다.Then, as shown in FIG. 12, the perforation hole 101 of the rear row in which the thumb pile 20 is inserted is filled with sand or sand.

그 다음, 도 13과 같이 후열의 천공홀(101)로부터 굴착될 영역쪽으로 일정 거리 떨어진 위치에 전열의 엄지말뚝(20a)을 지반에 근입하기 위한 천공을 실시한다. 따라서 후열의 엄지말뚝(20)의 전방으로 전열측 천공홀(102)이 1열로 배열된다.Next, as shown in FIG. 13, drilling is performed to insert the heat-induced thumb pile 20a into the ground at a position a certain distance away from the drilling hole 101 in the rear row toward the area to be excavated. Therefore, the heat-transfer perforation holes 102 are arranged in one row in front of the thumb pile 20 in the rear row.

그 다음, 도 14와 같이 전열측 천공홀(102)에 전열의 엄지말뚝(20a)을 근입하여 놓고, 전열의 엄지말뚝(20a)이 근입된 천공홀(102)에 토사 또는 모래를 채움한다. 물론 전열의 엄지말뚝(20a)도 크레인을 통해 근입이 이루어질 수 있다.Subsequently, as shown in FIG. 14, a heat-transferring thumb pile 20a is inserted into the heat transferring perforation hole 102, and the perforation hole 102 into which the heat-transferring thumb pile 20a is inserted is filled with gravel or sand. Of course, the thumb pile 20a of the heat transfer type can be inserted through the crane.

그 다음, 도 15와 같이 후열의 엄지말뚝(20)의 상단부 전면에 후열의 띠장(40a)을 설치하고, 후열의 띠장(40a)과 전열의 엄지말뚝(20a)의 사이에 연결강관(44)을 설치한다. 이때 도 18과 같이 연결강관(44)은 내부로 긴장재(30)가 통과될 수 있는 위치에 설치된다.15, a wristband 40a of the rear row is provided on the entire upper end of the rear-end thumb pile 20, and a connecting steel pipe 44 is provided between the wristband 40a of the rear row and the thumb pile 20a of the rear row, . 18, the connecting steel pipe 44 is installed at a position where the tension member 30 can pass through.

그 다음, 도 16과 같이 전열의 띠장(40) 설치와 긴장재(30)의 인장을 위한 1단계 굴착을 실시하고, 전열의 엄지말뚝(20a)의 상단에 전열의 띠장(40)을 설치하고, 긴장재(30)의 상단을 후열의 띠장(40a)과 연결강관(44) 및 전열의 띠장(40)을 통과시킨 후, 긴장재(30)를 도시안된 유압잭으로 인장하여 전열의 띠장(40)에 정착시켜 놓는다. 이때 긴장재(30)의 정착은 전열의 띠장(40)의 배면에 배치된 주지의 정착구를 통해 이루어질 수 있다.Thereafter, as shown in FIG. 16, a wale 40 is installed and a first stage excavation is performed for tensile strength of the tensile material 30. The wale 40 is provided at the upper end of the heat-induced thumb pile 20a, The upper end of the tension member 30 is passed through the wrist strap 40a of the rear welt 40 and the connecting steel pipe 44 and the wrist strap 40 of the heat train. Thereafter, the tension member 30 is tensioned by the unshown hydraulic jack, . At this time, the fixing of the tension member 30 may be performed through a well-known fixing member disposed on the back surface of the wrist strap 40.

이같이 긴장재(30)에 인장력이 부여되어져 정착되면, 긴장재(30)에 긴장력이 작용하여 후열의 엄지말뚝(20)에 압축응력이 도입된다. 따라서 압축응력이 도입된 후열의 엄지말뚝(20)은 휨내력이 증가된다.When the tensile force is applied to the tensile member 30, the tensile force is applied to the tensile member 30, and the compressive stress is introduced into the thumb pile 20. Therefore, the bending force of the thumb pile 20 after the compression stress is introduced.

그 다음, 도 19와 같이 토류판(50)을 전열의 엄지말뚝(20a)에 설치해가면서 지반에 소요 굴착심도까지 굴착하여 흙막이 시공이 완료된다.Then, as shown in FIG. 19, the soil plate 50 is installed on the heat-driven thumb pile 20a and is excavated to the ground with a required depth of excavation to complete the earth retaining construction.

이와 같이 제2 실시예에서는 전열의 엄지말뚝(20a)의 후방으로 후열의 엄지말뚝(20)이 압축 응력(프리스트레스)이 도입되어 시공되어져 있어, 2열 자립식 흙막이를 이루면서 배면지반의 변위를 더욱 효과적으로 억제시킬 수 있다. 따라서 배면에 부지여유가 있고 굴착심도가 깊어질 경우 2열 자립식 흙막이를 시공할 수 있다.As described above, in the second embodiment, the rear-end thumb pile 20 is introduced to the rear of the heat-induced thumb pile 20a by introducing compressive stress (prestress), and the displacement of the back ground becomes more Can be effectively suppressed. Therefore, if there is a lot of land on the back and depth of excavation is deep, a two row self-supporting type earth retaining wall can be constructed.

지금까지 본 발명은 제시된 실시 예를 참조하여 상세하게 설명이 되었지만 이 분야에서 통상의 지식을 가진 자는 제시된 실시 예를 참조하여 본 발명의 기술적 사상을 벗어나지 않는 범위에서 다양한 변형 및 수정 발명을 만들 수 있을 것이다. 본 발명은 이와 같은 변형 및 수정 발명에 의하여 제한되지 않으며 다만 아래에 첨부된 청구범위에 의하여 제한된다. While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is evident that many alternatives, modifications and variations will be apparent to those skilled in the art in light of the above teachings. will be. The invention is not limited by these variations and modifications, but is limited only by the claims appended hereto.

20, 20a: 엄지말뚝
22: 하부 긴장재 가이드 걸침블럭
24: 상부 긴장재 가이드 걸침블럭
30: 긴장재
40,40a: 띠장
50: 토류판
20, 20a: thumb pile
22: Lower tensioning guide guide block
24: upper tensioning guide guide block
30: Tension material
40,40a: Wale
50: Circulation plate

Claims (7)

흙막이가 필요한 지반(10)에 엄지말뚝(20)을 일정 간격마다 근입하기 위해 해당 간격마다 필요 깊이까지 천공하는 단계와;
하단을 고정시킨 긴장재(30)가 배치된 엄지말뚝(20)을 지반에 1열로 천공된 천공홀(101)에 각기 근입하는 단계와;
엄지말뚝(20)이 근입된 천공홀(101)에 토사 또는 모래를 채움하는 단계와;
띠장(40)의 설치와 긴장재(30)의 인장을 위해 엄지말뚝(20)의 전면측 지반에 1단계 굴착을 실시하는 단계와;
엄지말뚝(20)의 상단에 굴착측에서 띠장(40)을 지지되게 설치하고, 긴장재(30)의 상단을 띠장(40)에 통과시킨 후 긴장재(30)를 인장하여 띠장(40)에 정착시켜서 엄지말뚝(20)에 압축응력을 도입시켜 놓는 단계와;
토류판(50)을 1열로 설치된 엄지말뚝(20)의 사이에 설치해가면서 지반에 소요 굴착심도까지 굴착하는 단계;를 포함하여 시공되는 것을 특징으로 하는 더블 아이 빔에 압축응력이 도입된 자립식 흙막이 공법.
Piercing the ground pile (20) to a necessary depth at every interval to insert the ground pile (20) at predetermined intervals on the ground (10) where the pile is required;
Placing each of the thumb piles (20) having the lower end fixedly arranged therein in a perforation hole (101) perforated in one row on the ground;
Filling the perforation hole 101 into which the thumb pile 20 is inserted with gravel or sand;
A step of performing a first stage excavation on the front side ground of the thumb pile (20) for the installation of the wale band (40) and the tensioning of the tension member (30);
The wrist strap 40 is supported on the upper end of the thumb pile 20 and the upper end of the strap 30 is passed through the wrist strap 40 and then the strap 30 is tensioned and fixed on the wrist strap 40 Introducing compressive stress into the thumb pile 20;
And installing the soil plate (50) between the thumb piles (20) installed in one row to the depth of the excavation to a required depth of the excavation. [3] The method according to claim 1, .
흙막이가 필요한 지반(10)에 후열의 엄지말뚝(20)을 일정 간격마다 근입하기 위해 해당 간격마다 필요 깊이까지 천공하는 단계와;
하단을 고정시킨 긴장재(30)가 배치된 후열의 엄지말뚝(20)을 지반에 1열로 천공된 후열의 천공홀(101)에 각기 근입하는 단계와;
엄지말뚝(20)이 근입된 후열의 천공홀(101)에 토사 또는 모래를 채움하는 단계와;
후열의 천공홀(101)로부터 굴착될 영역쪽으로 일정 거리 떨어진 위치에 전열의 엄지말뚝(20a)을 지반에 근입하기 위한 천공을 실시하는 단계와;
전열측 천공홀(102)에 전열의 엄지말뚝(20a)을 근입하는 단계와;
전열의 엄지말뚝(20a)이 근입된 천공홀(102)에 토사 또는 모래를 채움하는 단계와;
후열의 엄지말뚝(20)의 상단부 전면에 후열의 띠장(40a)을 설치하고, 후열의 띠장(40a)과 전열의 엄지말뚝(20a)의 사이에 연결강관(44)을 설치하는 단계와;
전열의 띠장(40) 설치와 긴장재(30)의 인장을 위한 1단계 굴착을 실시하고, 전열의 엄지말뚝(20a)의 상단에 전열의 띠장(40)을 설치하고, 긴장재(30)의 상단을 후열의 띠장(40a)과 연결강관(44) 및 전열의 띠장(40)을 통과시킨 후, 긴장재(30)를 인장하여 전열의 띠장(40)에 정착시켜서 후열의 엄지말뚝(20)에 압축응력을 도입시켜 놓는 단계와;
토류판(50)을 전열의 엄지말뚝(20a)에 설치해가면서 지반에 소요 굴착심도까지 굴착하는 단계;를 포함하여 시공되는 것을 특징으로 하는 더블 아이 빔에 압축응력이 도입된 자립식 흙막이 공법.
Piercing the soil pile (20) of the rear row to the required depth at every interval to insert the soil pile (20) in the ground (10) requiring soil retention at regular intervals;
Placing a thumb pile (20) of a rear row in which a lower end fixed stationary material (30) is disposed, into the perforation hole (101) of the rear row perforated in the ground;
Filling the perforation hole 101 of the rear row into which the thumb pile 20 is inserted with soil or sand;
Punching a thump pile (20a) of heat transfer into the ground at a position a certain distance away from the drilling hole (101) of the rear row toward the area to be drilled;
A step of placing a heat-generating thumb pile 20a in the heat-transferring perforation hole 102;
Filling the perforation hole 102 into which the thumb pile 20a with heat is inserted, with gravel or sand;
Installing a wristband 40a in the rear row on the entire upper end of the stem pad 20 of the rear row and installing a connecting steel tube 44 between the wristband 40a in the rear row and the thumb pile 20a in the rear row;
The wristband 40 of the heat conduction is installed and the first stage excavation is performed for the tensioning of the tensile material 30. The wristband 40 of the heat conduction is installed at the upper end of the heat pumped pile 20a, After passing through the wristband 40a of the rear row, the connecting steel pipe 44 and the wristband 40 of the heat conduction, the tension member 30 is tensioned and fixed to the wristband 40 of the heat conduction, Introducing into the chamber;
And a step of excavating the earth plate (50) to a depth of a desired excavation depth while installing the soil plate (50) on the heat-driven thumb pile (20a).
제1항 또는 제2항에 있어서,
엄지말뚝(20)은 강재로 제작된 더블 아이 빔이 적용된 것을 특징으로 하는 더블 아이 빔에 압축응력이 도입된 자립식 흙막이 공법.
3. The method according to claim 1 or 2,
The thumb pile (20) is characterized in that a double eye beam made of steel is applied, and a self-supporting earth retaining method in which a compressive stress is introduced into a double eye beam.
제 3항에 있어서,
엄지말뚝(20)의 하단에는 긴장재(30)의 하단부를 걸침하기 위한 긴장재 가이드 걸침홈(22a)을 갖는 하부 긴장재 가이드 걸침블럭(22)이 설치되고, 엄지말뚝(20)의 상단에는 긴장재(30)의 상단부를 걸침하기 위한 긴장재 가이드 걸침홈(24a)을 갖는 상부 긴장재 가이드 걸침블럭(24)이 설치되어져 있는 것을 특징으로 하는 더블 아이 빔에 압축응력이 도입된 자립식 흙막이 공법.
The method of claim 3,
A lower tension member guide block 22 having a tension member guide groove 22a for receiving a lower end portion of the tensile member 30 is provided at the lower end of the thumb pile 20 and a tensile member 30 The upper tension member guide block 24 having a tension member guide groove 24a for receiving the upper end of the upper tension member guide groove 24a.
제 3항에 있어서,
긴장재(30)는 2개가 한 쌍을 이루어 나란하게 엄지말뚝(20)에 배치되고, 한 쌍의 긴장재(30)는 더블 아이 빔의 단면 도심에서 편심거리(S)를 가지고 굴착영역의 반대쪽에 위치되는 플랜지(202)측에 가까이 배치된 것을 특징으로 하는 더블 아이 빔에 압축응력이 도입된 자립식 흙막이 공법.
The method of claim 3,
The two tension members 30 are arranged in a pair in the thumb pile 20 in a pair and the pair of the tension members 30 are located on the opposite side of the excavation region with the eccentric distance S in the center of the double- And the flange (202) side of the double eye beam.
제1항 또는 제2항에 있어서,
띠장(40)은 강재로 제작된 더블 아이 빔이 적용되어 플랜지(402)에 긴장재(30)를 삽통시키기 위한 슬롯(401)이 형성된 것을 특징으로 하는 더블 아이 빔에 압축응력이 도입된 자립식 흙막이 공법.
3. The method according to claim 1 or 2,
Wherein the wale band (40) is formed with a slot (401) for inserting the tension member (30) into the flange (402) by applying a double eye beam made of a steel material. Method.
제 1항에 있어서,
긴장재(30)는 PC 강선 또는 PC 강연선인 것을 특징으로 하는 더블 아이 빔에 압축응력이 도입된 자립식 흙막이 공법.
The method according to claim 1,
Characterized in that the tensile member (30) is a PC steel wire or a PC stranded wire, and a self-supporting type earth retaining method in which a compressive stress is introduced into a double eye beam.
KR1020170147835A 2017-11-08 2017-11-08 Self reliance earth retaining construction method having prestress introduced of Double I Beam KR102097855B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170147835A KR102097855B1 (en) 2017-11-08 2017-11-08 Self reliance earth retaining construction method having prestress introduced of Double I Beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170147835A KR102097855B1 (en) 2017-11-08 2017-11-08 Self reliance earth retaining construction method having prestress introduced of Double I Beam

Publications (2)

Publication Number Publication Date
KR20190052284A true KR20190052284A (en) 2019-05-16
KR102097855B1 KR102097855B1 (en) 2020-04-06

Family

ID=66672201

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170147835A KR102097855B1 (en) 2017-11-08 2017-11-08 Self reliance earth retaining construction method having prestress introduced of Double I Beam

Country Status (1)

Country Link
KR (1) KR102097855B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456027A (en) * 2020-04-15 2020-07-28 机械工业勘察设计研究院有限公司 Connecting device and connecting method for assembly type supporting and retaining structure
CN112323822A (en) * 2020-11-30 2021-02-05 中国电建集团福建省电力勘测设计院有限公司 Pipe gallery foundation pit with tension and compression support
KR20210015490A (en) * 2019-08-02 2021-02-10 백진명 Two Rows type Self reliance retaining wall construction method Using the Prestressed pile
KR20230030596A (en) * 2023-01-11 2023-03-06 오용환 Temporary earth retaining facility using guide bracket and ground anchor and its construction method
KR20230030562A (en) * 2022-12-09 2023-03-06 오용환 Temporary retaining facility using guide bracket and ground anchor for step-by-step support of deep excavation and its construction method
KR20230030595A (en) * 2023-01-11 2023-03-06 오용환 Temporary earth retaining facility using guide bracket and ground anchor and its construction method
KR20230032048A (en) * 2021-08-30 2023-03-07 오용환 Prestressed thumb piles for suppression of displacement and construction method for self-supporting temporary retainers using the same

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200293048Y1 (en) 2002-08-03 2002-10-25 삼성물산 주식회사 shoring structure using prestressed retaining wall
JP2009013611A (en) * 2007-07-02 2009-01-22 Nippon Steel Corp Reinforcement structure and method for earth retaining wall
KR101729117B1 (en) 2016-04-21 2017-04-24 오용환 Its construction method and using a temporary retaining piles and the prestressed struts are introduced
JP2017122358A (en) * 2016-01-08 2017-07-13 大成建設株式会社 Earth retaining frame
KR20170100322A (en) * 2016-02-25 2017-09-04 백진명 Double independent type retaining wall temporary structure for elimnating back row pile and tie anker and construction method of the same

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200293048Y1 (en) 2002-08-03 2002-10-25 삼성물산 주식회사 shoring structure using prestressed retaining wall
JP2009013611A (en) * 2007-07-02 2009-01-22 Nippon Steel Corp Reinforcement structure and method for earth retaining wall
JP2017122358A (en) * 2016-01-08 2017-07-13 大成建設株式会社 Earth retaining frame
KR20170100322A (en) * 2016-02-25 2017-09-04 백진명 Double independent type retaining wall temporary structure for elimnating back row pile and tie anker and construction method of the same
KR101729117B1 (en) 2016-04-21 2017-04-24 오용환 Its construction method and using a temporary retaining piles and the prestressed struts are introduced

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20210015490A (en) * 2019-08-02 2021-02-10 백진명 Two Rows type Self reliance retaining wall construction method Using the Prestressed pile
CN111456027A (en) * 2020-04-15 2020-07-28 机械工业勘察设计研究院有限公司 Connecting device and connecting method for assembly type supporting and retaining structure
CN112323822A (en) * 2020-11-30 2021-02-05 中国电建集团福建省电力勘测设计院有限公司 Pipe gallery foundation pit with tension and compression support
CN112323822B (en) * 2020-11-30 2024-04-02 中国电建集团福建省电力勘测设计院有限公司 Piping lane foundation ditch with pull-press support
KR20230032048A (en) * 2021-08-30 2023-03-07 오용환 Prestressed thumb piles for suppression of displacement and construction method for self-supporting temporary retainers using the same
KR20230030562A (en) * 2022-12-09 2023-03-06 오용환 Temporary retaining facility using guide bracket and ground anchor for step-by-step support of deep excavation and its construction method
KR20230030596A (en) * 2023-01-11 2023-03-06 오용환 Temporary earth retaining facility using guide bracket and ground anchor and its construction method
KR20230030595A (en) * 2023-01-11 2023-03-06 오용환 Temporary earth retaining facility using guide bracket and ground anchor and its construction method

Also Published As

Publication number Publication date
KR102097855B1 (en) 2020-04-06

Similar Documents

Publication Publication Date Title
KR20190052284A (en) Self reliance earth retaining construction method having prestress introduced of Double I Beam
KR101691139B1 (en) Construction method using soil retaining wall
KR101949086B1 (en) Self reliance pile and Self reliance retaining wall construction method using the same
US9422687B2 (en) Flat plate foundation supports
KR102312008B1 (en) Two Rows type Self reliance retaining wall construction method Using the Prestressed pile
KR20170005991A (en) soil retaining wall using PHC pile and its construction method
KR100913569B1 (en) Phc pile for retaining wall
KR100807810B1 (en) Structure lifting method by foundation strengthening
KR101641293B1 (en) Double line retaining wall self-reliance composite wall construction method for reinforcement pile wall
KR101743758B1 (en) Downward construction method for vertical extension of building using base block
KR100989853B1 (en) piling location fixing apparatus for cast in place concrete pile wall
KR101568956B1 (en) Excavation method for sluice on soft ground using front h-pile with multi-wire
KR20170100322A (en) Double independent type retaining wall temporary structure for elimnating back row pile and tie anker and construction method of the same
KR101065017B1 (en) A shoring method using arch plate pile and H-Pile
KR101822175B1 (en) Retaining Wall using Precast Piles and Constructing Method thereof
KR20180106156A (en) Reinforced solider pile apparatus of long span&#39;s soil retaining wall
KR101061516B1 (en) Temporary wall structure using arched steel pile
KR100691890B1 (en) Method for constructing retaining wall having h-beam
KR20190012368A (en) Smallcaliber composite pile wall using small drilling rig at adjacent building proximity section and construction method of the same
KR101692541B1 (en) Structure of before and after pile connection for two rows pile construction
KR101891069B1 (en) A steel pipe for non-excavation construction method and a non-excavation construction method using the same
KR100989023B1 (en) Supporting apparatus having in between two belts and constructing method thereof
KR20230057054A (en) Soil retaning structure for two rows pile using prestressed wale
KR20180101986A (en) Methods for constructing retaining wall using fastening unit for stiffener
KR101623342B1 (en) Earth retaining structure utilizing in-situ soil and earth retaining structure construction Method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant