KR100691890B1 - Method for constructing retaining wall having h-beam - Google Patents

Method for constructing retaining wall having h-beam Download PDF

Info

Publication number
KR100691890B1
KR100691890B1 KR1020060000678A KR20060000678A KR100691890B1 KR 100691890 B1 KR100691890 B1 KR 100691890B1 KR 1020060000678 A KR1020060000678 A KR 1020060000678A KR 20060000678 A KR20060000678 A KR 20060000678A KR 100691890 B1 KR100691890 B1 KR 100691890B1
Authority
KR
South Korea
Prior art keywords
pile
pipe member
hole
filler
unit
Prior art date
Application number
KR1020060000678A
Other languages
Korean (ko)
Inventor
홍성영
오성남
전덕찬
남현우
Original Assignee
주식회사 스마텍엔지니어링
주식회사 서영엔지니어링
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 스마텍엔지니어링, 주식회사 서영엔지니어링 filed Critical 주식회사 스마텍엔지니어링
Priority to KR1020060000678A priority Critical patent/KR100691890B1/en
Application granted granted Critical
Publication of KR100691890B1 publication Critical patent/KR100691890B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1685Shapes cylindrical

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

A construction method for a pile unit provided with an H-beam is provided to increase the cost required and to reduce the use of unnecessary filler by drilling holes continuously and installing H-beam piles to the holes. The construction method for a pile unit provided with an H-beam comprises the steps of: executing primary casing work by forming a primary hole(50) on the ground to the appointed depth using a drilling machine such as an auger, etc. and inserting a primary pipe member to the primary hole; executing secondary casing work by inserting a secondary member(52) to the inside of the primary pipe member and pulling out the primary pipe member; executing third casing work by forming a secondary hole(60) adjacently to the primary hole and inserting a third pipe member to the secondary hole; executing fourth casing work by inserting a fourth pipe member to the inside of the third pipe member and pulling out the third pipe member; forming a slit of the fourth pipe member and a slit of the secondary pipe member to connect with each other and inserting an H-beam pile(10) over the primary hole and the secondary hole; placing filler such as soil cement or concrete to the secondary pipe member and the fourth pipe member to make the whole H-beam pile buried under the filler; and pulling out the secondary pipe member and the fourth pipe member before the filler is cured.

Description

엄지말뚝 매립형 말뚝 유닛의 시공방법 및 이를 이용한 주열식 흙막이 벽체의 시공방법{Method for Constructing Retaining Wall having H-Beam} Construction Method of Thumb Pile Recessed Pile Unit and Construction Method of Rowing Soil Wall Using the Same {Method for Constructing Retaining Wall having H-Beam}

도 1은 본 발명의 일실시예에 따라 시공된 주열식 흙막이 벽체의 개략적인 평면도이다. 1 is a schematic plan view of a columnar wall structure constructed according to an embodiment of the present invention.

도 2a 내지 도 2f는 각각 본 발명에 따라 말뚝 유닛용 구멍을 연속 천공하여 H빔 엄지말뚝을 배치하여 말뚝 유닛을 시공하는 방법의 각 시공단계를 보여주는 도면이다. Figure 2a to 2f is a view showing each construction step of the method for constructing the pile unit by arranging the H-beam thumb pile by continuously drilling holes for the pile unit according to the present invention, respectively.

도 3은 제1공 및 제2공에 모두 충진재를 채운 후 제2 관부재와 제4 관부재를 모두 인발하여 제거한 상태를 보여주는 평면도이다. 3 is a plan view showing a state in which both the second tube member and the fourth tube member are drawn and removed after filling the filler in both the first and second holes.

도 4는 도 3에 도시된 구성의 말뚝 유닛을 이용하여 시공된 주열식 흙막이 벽체와 콘크리트 지하 벽체가 합성된 상태의 일예를 보여주는 개략적인 평면도이다. FIG. 4 is a schematic plan view showing an example of a state in which the columnar wall and the concrete underground wall constructed by using the pile unit having the configuration shown in FIG.

도 5는 제1공에만 충진재를 채운 후 제2 관부재와 제4 관부재를 모두 인발하여 제거한 상태를 보여주는 평면도이다. 5 is a plan view showing a state in which both the second pipe member and the fourth pipe member are removed by filling only the first hole and then removed.

도 6은 도 5에 도시된 구성의 말뚝 유닛을 이용하여 시공된 주열식 흙막이 벽체의 개략적인 평면도이다. FIG. 6 is a schematic plan view of a columnar wall structure constructed using a pile unit having the configuration shown in FIG. 5. FIG.

도 7a 내지 도 7c는 각각 도 6에 도시된 주열식 흙막이 벽체에 접하여 콘크 리트 지하 벽체가 시공될 때, H빔 엄지말뚝의 일부분이 상기 충진재 내에 매립되어 있는 구조의 말뚝 유닛을 포함하는 주열식 흙막이 벽체에서 H빔 엄지말뚝의 활용 방법 예를 보여주는 평면도이다. 7A to 7C show a sequential mudstone including a pile unit having a structure in which a portion of the H-beam thumb pile is embedded in the filler when the concrete basement wall is constructed in contact with the sequential mud wall shown in FIG. 6, respectively. This is a plan view showing an example of the use of the H beam thumb pile in the wall.

도 8은 종래의 일반적인 엄지말뚝 매립형 말뚝 유닛의 개략적인 평면도이다, 8 is a schematic plan view of a conventional general pile pile buried pile unit,

도 9는 종래의 엄지말뚝 매립형 말뚝 유닛을 이용한 주열식 흙막이 벽체의 개략적인 평면도이다. FIG. 9 is a schematic plan view of a main row soil wall using a conventional thumb pile embedded pile unit. FIG.

도 10은 종래의 엄지말뚝 매립형 말뚝 유닛을 이용한 주열식 흙막이 벽체에 콘크리트 지하 벽체가 합성되어 있는 형태를 보여주는 평면도가 도시되어 있는데,FIG. 10 is a plan view showing a form in which a concrete underground wall is synthesized in a main row wall using a conventional pile pile pile unit.

<도면의 주요 부분에 대한 부호의 설명> <Explanation of symbols for the main parts of the drawings>

2, 3 : 말뚝 유닛2, 3: pile unit

10 : H빔 엄지말뚝10: H beam thumb pile

본 발명은 엄지말뚝 매립형 말뚝 유닛의 시공방법 및 이를 이용한 주열식 흙막이 벽체의 시공방법에 관한 것으로서, 구체적으로는 지반에 말뚝 유닛용 구멍을 천공할 때 2개의 구멍을 일부 겹치게 천공하고 상기 구멍에 걸쳐서 종전 보다 더 큰 엄지말뚝을 설치함으로써 말뚝의 강성을 증가시킬 수 있으며, 주열식 흙막이 벽 체에 사용될 때 엄지말뚝이 지하 벽체의 구조재 등으로 활용될 수 있도록 시공하는 엄지말뚝 매립형 말뚝 유닛의 시공방법 및 이를 이용한 주열식 흙막이 벽체의 시공방법에 관한 것이다. The present invention relates to a method of constructing a pile pile buried pile unit and a method of constructing a heat-retaining wall using the same, and more specifically, when drilling a hole for a pile unit in the ground, two holes are partially overlapped and over the holes. By installing a larger thumb pile than before, the rigidity of the pile can be increased, and the construction method of the thumb pile buried pile unit, which is constructed so that the thumb pile can be used as a structural material of the underground wall when used in the heat-stacking wall, and the same It relates to a construction method of the column-style soil wall used.

도 8에는 종래의 일반적인 엄지말뚝 매립형 말뚝 유닛(120)의 개략적인 평면도가 도시되어 있는데, 도면에 도시된 것처럼 엄지말뚝 매립형 말뚝 유닛(120)은 지중에 수직하게 천공한 후 그 천공된 구멍에 엄지말뚝(101)을 설치하고, 천공된 구멍 내에 위치한 상기 엄지말뚝(101) 주위에 소일 시멘트나 콘크리트, 또는 토사 등의 충진재(102)로 채우는 구조로 이루어져 있다. 엄지말뚝(101)으로는 H빔이 주로 사용된다. FIG. 8 is a schematic plan view of a conventional general thumb pile embedded pile unit 120. As shown in the drawing, the thumb pile embedded pile unit 120 is drilled perpendicularly to the ground and then the thumb is formed in the drilled hole. The pile 101 is installed and filled with a filler 102 such as soil cement, concrete, or earth and sand around the thumb pile 101 located in the perforated hole. As the thumb pile 101, an H beam is mainly used.

이와 같은 엄지말뚝 매립형 말뚝 유닛(120)은 다양한 용도로 사용될 수 있는데, 대표적으로는 주열식 흙막이 벽체에 사용된다. 도 9에는 위와 같은 엄지말뚝 매립형 말뚝 유닛(120)을 이용한 종래의 주열식 흙막이 벽체(103)의 개략적인 평면도가 도시되어 있다. 도면에 도시된 것처럼, 일반적으로 주열식 흙막이 벽체(103)는, 구조물의 지하 벽체 시공 위치 측면에서 지반을 천공한 후 엄지말뚝(101)을 소정 간격으로 설치하고 상기 엄지말뚝(101)의 주위에 소일 시멘트 또는 콘크리트 등의 충진재(102)를 타설하여 형성되는 말뚝 유닛(120)과, 엄지말뚝(101) 없이 충진재(102) 만을 타설하여 형성되는 말뚝 유닛(130)을 이웃하게 일정간격으로 연속 배치하여 주열식 흙막이 벽체(103)를 형성하는 구조를 가지고 있다. Such a pile pile buried pile unit 120 may be used for a variety of purposes, typically used in the main column wall. FIG. 9 is a schematic plan view of a conventional columnar retaining wall 103 using the thumb pile embedded pile unit 120 as described above. As shown in the figure, the heat-staining wall (103) is generally installed after the drilling of the ground at the side of the construction site of the underground wall of the structure, the thumb pile 101 is installed at a predetermined interval and around the thumb pile 101 The pile unit 120 formed by pouring the filler 102 such as soil cement or concrete and the pile unit 130 formed by pouring only the filler 102 without the thumb pile 101 are continuously disposed at a predetermined interval adjacent to each other. It has a structure to form the columnar soil wall (103).

그런데 이러한 종래의 주열식 흙막이 벽체(103)에 있어서, 말뚝 유닛(120, 130)의 천공직경은 모두 일정하며 그 크기가 작기 때문에 흙막이 벽체의 강성이 충 분하지 아니하다는 것이 문제점으로 지적되어 왔다. 따라서 종래의 주열식 흙막이 벽체에 있어서는 지보공의 수직 간격을 넓히는데 한계가 있다. However, it has been pointed out that in such a conventional heat-staining wall 103, the perforation diameters of the pile units 120 and 130 are all constant and their sizes are small so that the rigidity of the wall is not sufficient. Therefore, in the conventional columnar wall, there is a limit to widening the vertical gap of the support.

이와 같은 주열식 흙막이 벽체(103)로서 사용할 경우뿐만 아니라, 다른 용도로 엄지말뚝 매립형 말뚝 유닛(120)을 사용할 때에도, 엄지말뚝(101)을 더 크게 하는 것이 바람직한 경우가 많다. 더 큰 엄지말뚝(101)을 사용하기 위해서는 지중에 천공하는 구멍의 지름이 커질 수밖에 없는데, 단순히 구멍의 지름만을 더 증가시켜 천공 구멍을 크게 하게 되면 천공에 따른 공사비가 과도하게 되어 경제성이 저하되며, 더 나아가 충진재(102)를 채워야 하는 엄지말뚝(101) 주변의 공간이 불필요하게 커지게 되는 단점이 있다. It is often desirable to make the thumb pile 101 larger when not only using it as the main heating wall 103, but also when using the thumb pile embedded pile unit 120 for other purposes. In order to use a larger thumb pile 101, the diameter of a hole to be drilled in the ground is inevitably increased, but if the diameter of the hole is increased by simply increasing the diameter of the hole, the construction cost due to drilling is excessive, and the economical efficiency is lowered. Furthermore, there is a disadvantage in that the space around the thumb pile 101 to fill the filler 102 becomes unnecessarily large.

한편, 이러한 주열식 흙막이 벽체(103)에서, 충진재(102)로 소일 시멘트 또는 콘크리트를 사용하는 경우, 충진재(102) 내에 매립되어 있는 상기 H빔 엄지말뚝(101)을 인발하여 재활용하는 것이 극히 어렵다. 반면에 H빔은 주로 강재로 만들어지고 고가이기 때문에 H빔 엄지말뚝(101)을 충진재(102) 속에 매립하여 사장시키는 것은 경제적으로도 매우 불리하다. 흙막이 벽체(103)에 바로 인접하여 지하 벽체를 시공하는 경우가 많은데, 종전에는 위와 같이 H빔 엄지말뚝(101)이 아깝게 사장되는 것을 고려하여 H빔 엄지말뚝(101)을 콘크리트 지하 벽체(100)의 강성을 증가시키는 구조 부재로 활용하려는 노력이 시도가 있다. On the other hand, in such a heat-staining wall 103, when using the cement or concrete as the filler 102, it is extremely difficult to draw and recycle the H-beam thumb pile 101 embedded in the filler 102 . On the other hand, since the H-beam is mainly made of steel and expensive, it is very economically disadvantageous to embed the H-beam thumb pile 101 in the filling material 102. There are many cases where the underground wall is directly adjacent to the earth wall (103), but in the past, the H-beam thumb pile (101) is concretely confined to the H-beam thumb pile (101) as mentioned above. Efforts have been made to utilize the structural member to increase the rigidity.

도 10에는 종래의 주열식 흙막이 벽체(103)에 콘크리트 지하 벽체(100)가 합성되어 있는 형태를 보여주는 평면도가 도시되어 있는데, 도 10에 도시된 것처럼 H빔 엄지말뚝(101)의 일측 플랜지 전면에 커넥션 볼트(110)를 미리 고정 설치해놓 고, 상기 커넥션 볼트(110)가 콘크리트 지하 벽체(100) 속에 매립되도록 함으로써, H빔 엄지말뚝(101)과 콘크리트 지하 벽체(100)를 일체로 만드는 것이 제안되고 있다. 그런데 위와 같은 종래 기술의 경우, H빔 엄지말뚝(101) 주변으로 충진재(102)가 타설되어 있으므로 H빔 엄지말뚝(101) 주변의 충진재(102)를 제거하는 과정에서 커넥션 볼트(110)가 손상될 가능성이 높아 터파기 공사가 완료되거나 또는 진행 중인 상태에서는 H빔 엄지말뚝(101)에 설치된 커넥션 볼트(110)를 노출시키는 것이 용이하지 아니하며, 그에 따라 작업성이 저하되는 문제가 생기게 된다. 이와 같이 H빔 엄지말뚝(101)을 지하 벽체(100)와 일체화시켜 지하 벽체(100)의 강성 보강용 구조 부재로 사용하려는 종전의 시도는 H빔 엄지말뚝(101)이 말뚝 유닛에서 충진재(102) 속에 완전히 매립되어 있기 때문에 실용화되기 어려운 상황이다. FIG. 10 is a plan view showing a structure in which a concrete underground wall 100 is synthesized in a conventional columnar retaining wall 103. As shown in FIG. 10, a front surface of one flange of an H beam thumb pile 101 is shown. It is proposed that the connection bolt 110 is fixed in advance and the connection bolt 110 is embedded in the concrete underground wall 100 so that the H beam thumb pile 101 and the concrete underground wall 100 are integrally formed. It is becoming. However, in the prior art as described above, since the filler 102 is poured around the H beam thumb pile 101, the connection bolt 110 is damaged in the process of removing the filler 102 around the H beam thumb pile 101. It is not easy to expose the connection bolt 110 installed in the H-beam thumb pile 101 in the state that the trench construction is completed or in progress because it is likely to be a problem, the workability is deteriorated accordingly. As described above, previous attempts to integrate the H beam thumb pile 101 with the underground wall 100 and use it as a structural member for rigid reinforcement of the underground wall 100 have been performed by the H beam thumb pile 101 in the pile unit. It is difficult to put into practical use because it is completely buried inside.

본 발명은 상기한 것처럼 엄지말뚝 매립형 말뚝 유닛을 시공함에 있어서, 단순히 천공 지름을 크게 하는 것이 아니라, 신규한 구성을 통하여 말뚝 유닛용 구멍을 서로 이웃하도록 연속하여 천공하고, H빔 엄지말뚝을 연속 천공된 2개의 구멍에 걸쳐서 설치할 수 있도록 함으로써, 더 큰 크기의 엄지말뚝을 설치할 수 있으면서도 천공 지름 확대에 따른 천공비의 증가를 방지할 수 있고 불필요한 충진재의 사용을 줄일 수 있도록 하는 말뚝 유닛의 시공방법을 제공하는 것을 목적으로 한다. In the present invention, when constructing the pile pile embedded pile unit as described above, not only to increase the diameter of the drilling, but also to continuously drill holes for the pile unit adjacent to each other through a novel configuration, and to continuously drill the H-beam thumb pile By installing over two holes, the pile unit can be installed to prevent the increase of the drilling cost due to the expansion of the drilling diameter and to reduce the use of unnecessary fillers. It aims to provide.

또한, 본 발명에서는 주열식 흙막이 벽체에서 말뚝 유닛을 시공함에 있어서, 위와 같은 본 발명의 말뚝 유닛 시공방법을 적용함으로써, 엄지말뚝이 말뚝 유닛에 서 소일 시멘트 또는 콘크리트 등의 충진재 속에 완전히 매립됨으로 인하여 고가의 엄지말뚝이 사장되는 등의 종래 기술이 가지고 있는 문제점들을 해결하는 것을 목적으로 한다. 구체적으로 본 발명에서는 말뚝 유닛에 포함된 엄지말뚝의 일부가 말뚝 유닛의 외부로 노출될 수 있도록 하여, 엄지말뚝을 사장시키지 아니하고 흙막이 벽체에 접하여 시공되는 구조물의 강성을 보강하는 구조 부재로서도 용이하게 활용될 수 있도록 하는 것을 목적으로 한다. In addition, in the present invention in the construction of the pile unit in the heat-stacking wall, by applying the pile unit construction method of the present invention as described above, the thumb pile is completely embedded in the filling material, such as soil cement or concrete in the pile unit, expensive An object of the present invention is to solve problems with the prior art, such as a thumb pile. Specifically, in the present invention, a part of the thumb pile included in the pile unit may be exposed to the outside of the pile unit, so that the thumb pile may be easily used as a structural member that reinforces the stiffness of the structure that is in contact with the earth wall without the thumb pile. The purpose is to make it possible.

또한, 본 발명은 주열식 흙막이 벽체를 시공함에 있어서 말뚝 유닛의 천공직경은 모두 일정하며 그 크기가 작기 때문에 충분한 강성의 흙막이 벽체를 이룰 수 없으며, 그에 따라 지보공의 수직 간격을 넓힐 수 없게 되는 종래 기술의 단점과 한계를 해결하는 것을 목적으로 한다. 구체적으로 본 발명은, 신규한 구성을 통하여 말뚝 유닛용 구멍을 연속하여 일부 겹치게 천공하고, 상기 연속 천공된 구멍에 걸쳐서 크기가 큰 H빔 엄지말뚝을 설치하여 말뚝 유닛을 형성하고, 이러한 말뚝 유닛을 포함한 구조로 흙막이 벽체를 시공함으로써, 큰 강성의 흙막이 벽체를 이루게 되며, 그에 따라 지보공의 수직 간격도 증대시켜 경제적인 시공을 이룰 수 있도록 하는 엄지말뚝 매립형 말뚝 유닛을 이용한 주열식 흙막이 벽체의 시공방법을 제공함을 목적으로 한다. In addition, the present invention is a conventional technology that can not form a sufficient rigid soil wall wall because the drilling diameter of the pile unit is all constant and small in the construction of the column-style soil wall wall, and thus can not widen the vertical gap of the jibo It aims to solve the shortcomings and limitations of the. Specifically, the present invention, through a novel configuration, the hole for the pile unit in succession partially overlapped, install a large H-beam thumb pile over the continuous perforated holes to form a pile unit, such a pile unit By constructing the retaining wall with the included structure, a large rigid retaining wall is formed, and accordingly, the vertical gap of the jibo is also increased to achieve economical construction. For the purpose of providing it.

상술한 목적을 위하여 본 발명에서는 지중에 천공된 구멍에 엄지말뚝이 삽입 설치되는 구조를 가지는 말뚝 유닛의 시공방법으로서, 지반에 소정 깊이로 제1공을 천공하고 상기 제1공에 제1 관부재를 삽입하여 1차 케이싱 작업을 수행하는 단계; 일측이 오목한 오목부를 가지는 반월형 단면 구조로 이루어져 있으며 H빔 엄지말뚝이 삽입될 때 그 웨브가 지나면서 개방되는 슬릿이 종방향(관부재의 길이방향)으로 상기 오목부에 형성되어 있는 제2 관부재를 상기 제1 관부재의 내부에 삽입하고 상기 제1 관부재는 인발하여 제거하는 2차 케이싱 작업을 수행하는 단계; 상기 제1공에 바로 인접하여 제2공을 천공하고 상기 제2공에 제3 관부재를 삽입하는 3차 케이싱 작업을 수행하는 단계; H빔 엄지말뚝이 삽입될 때 그 웨브가 지날 수 있도록 측면에 길이 방향으로 슬릿이 형성되어 있는 제4 관부재를 제3 관부재의 내부에 삽입하는 4차 케이싱 작업을 수행하는 단계; 및 상기 제4 관부재의 슬릿과 상기 제2 관부재의 슬릿이 서로 마주보아 연통되도록 한 상태에서 상기 제1공과 제2공에 걸쳐서 H빔 엄지말뚝을 삽입하는 단계를 포함함으로써 2개의 구멍을 그 일부가 서로 겹치게 연속하여 천공하고 그 천공된 구멍에 H빔 엄지말뚝이 걸쳐져서 배치되는 구조를 가지도록 말뚝 유닛을 시공하는 것을 특징으로 하는 엄지말뚝 매립형 말뚝 유닛의 시공방법이 제공된다. In the present invention for the above purpose, in the construction method of the pile unit having a structure in which the thumb pile is inserted into the hole drilled in the ground, the first hole is drilled to a predetermined depth in the ground and the first pipe member in the first hole Inserting to perform a primary casing operation; It consists of a half-wall-shaped cross-sectional structure having a concave portion on one side, and when the H-beam thumb pile is inserted, a slit which is opened as the web passes through is formed in the recess in the longitudinal direction (the longitudinal direction of the tube member). Inserting the inside of the first pipe member and performing a second casing operation to draw and remove the first pipe member; Performing a third casing operation of drilling a second hole immediately adjacent to the first hole and inserting a third pipe member into the second hole; Performing a fourth casing operation of inserting a fourth pipe member having a slit in the longitudinal direction to the inside of the third pipe member so that the web can pass when the H beam thumb pile is inserted; And inserting an H beam thumb pile over the first hole and the second hole with the slit of the fourth pipe member and the slit of the second pipe member facing each other. There is provided a method of constructing a pile pile buried pile unit, characterized in that the pile unit is constructed so that a portion is drilled continuously overlapping each other and the H-beam thumb pile is disposed in the drilled hole.

또한, 본 발명에서는 제1공과 제2공에 걸쳐서 H빔 엄지말뚝을 설치한 후에, 제2 관부재 내부에 충진재를 타설하고, 상기 충진재가 양생되기 전에 제2 관부재를 인발하여 제거하는 단계; 및 상기 충진재가 소정 강도 이상으로 양생된 후 제4 관부재를 인발하여 제거하는 단계를 포함함으로써 H빔 엄지말뚝의 일부분만이 말뚝 유닛의 충진재 내에 매립되는 구조를 가지도록 말뚝 유닛을 시공하는 것을 특징으로 하는 엄지말뚝 매립형 말뚝 유닛의 시공방법이 제공된다. In addition, in the present invention, after installing the H-beam thumb pile over the first hole and the second hole, the filler is placed inside the second pipe member, and the second pipe member is drawn and removed before the filler is cured; And drawing out and removing the fourth pipe member after the filler is cured to a predetermined strength or more, thereby constructing the pile unit such that only a portion of the H-beam thumb pile is embedded in the filler of the pile unit. Provided is a construction method of a thumb pile embedded pile unit.

또한 본 발명에서는, 제1공과 제2공에 걸쳐서 H빔 엄지말뚝을 설치한 후에, 제2 관부재 및 제4 관부재에 충진재를 타설하고 제2 관부재 및 제4 관부재를 인발하여 제거하는 단계를 포함함으로써 H빔 엄지말뚝의 전부가 말뚝 유닛의 충진재 내에 매립되는 구조를 가지도록 말뚝 유닛을 시공하는 것을 특징으로 하는 엄지말뚝 매립형 말뚝 유닛의 시공방법이 제공된다. In addition, in the present invention, after installing the H-beam thumb pile over the first hole and the second hole, the filler is poured into the second tube member and the fourth tube member, and the second tube member and the fourth tube member are drawn and removed. The method of constructing the pile pile buried pile unit, characterized in that the pile unit is constructed so that the whole of the H-beam thumb pile is embedded in the filler of the pile unit.

상기한 본 발명에 있어서, 제2 관부재는 오목부 내측으로 가이드 런을 형성하고 상기 가이드를 사이에 유입방지판을 삽입하여 상기 슬릿을 임시로 폐쇄하는 구성을 가지며; 상기 제1공과 제2공에 걸쳐서 H빔 엄지말뚝을 삽입하기에 앞서 상기 유입방지판을 제거하여 상기 슬릿을 개방하는 구조를 가질 수 있다. In the present invention described above, the second pipe member has a configuration in which a guide run is formed inside the recess, and the guide is inserted between the guides to temporarily close the slit; Prior to inserting the H beam thumb pile over the first hole and the second hole, the inlet preventing plate may be removed to open the slit.

또한 본 발명에서는, 지반에 천공된 소정 깊이의 구멍에 H빔 엄지말뚝을 설치하고 그 주변으로 충진재를 채워서 형성한 말뚝 유닛과, 단지 천공된 구멍에 충진재만을 채워서 형성한 말뚝 유닛을 이웃하게 일정간격으로 연속 배치하여 주열식 흙막이 벽체를 시공하는 방법으로서, 상기한 방법에 의하여 H빔 엄지말뚝의 일부분만이 충진재 내에 매립되는 구조를 가지도록 말뚝 유닛을 시공하고, 상기 말뚝 유닛을, H빔 엄지말뚝이 포함되어 있지 아니한 말뚝 유닛의 소정 간격 사이에 배치하는 것을 특징으로 하는 주열식 흙막이 벽체 시공방법이 제공된다.In addition, in the present invention, the pile unit is formed by installing the H-beam thumb pile in the hole of the predetermined depth perforated in the ground and filled the filler material around, and the pile unit formed by filling only the filler material in the perforated hole adjacent to a certain interval As a method of constructing a main heat-retaining wall by successive arrangement, the pile unit is constructed so that only a part of the H-beam thumb pile is embedded in the filler by the above-described method, and the pile unit is formed by the H-beam thumb pile. There is provided a method of constructing a staggered wall structure, which is arranged between predetermined intervals of a pile unit which is not included.

또한 본 발명에서는, 지반에 천공된 소정 깊이의 구멍에 H빔 엄지말뚝을 설치하고 그 주변으로 충진재를 채워서 형성한 말뚝 유닛과, 단지 천공된 구멍에 충진재만을 채워서 형성한 말뚝 유닛을 이웃하게 일정간격으로 연속 배치하여 주열식 흙막이 벽체를 시공하는 방법으로서, 상기한 방법에 의하여 일부가 겹쳐진 채로 연 속 천공된 구멍에 H빔 엄지말뚝이 걸쳐진 형태로 배치되어 H빔 엄지말뚝 전체가 충진재 내에 매립되는 구조를 가지도록 말뚝 유닛을 시공하고, 상기 말뚝 유닛을, H빔 엄지말뚝이 포함되어 있지 아니한 말뚝 유닛의 소정 간격 사이에 배치하는 것을 특징으로 하는 주열식 흙막이 벽체 시공방법이 제공된다.In addition, in the present invention, the pile unit is formed by installing the H-beam thumb pile in the hole of the predetermined depth perforated in the ground and filled the filler material around, and the pile unit formed by filling only the filler material in the perforated hole adjacent to a certain interval As a method of constructing a heat-retaining wall structure by continuously arranging the structure, the H-beam thumb pile is disposed in the form of the H-beam thumb pile in a continuous perforated hole with a part overlapped by the above method, so that the entire H-beam pile is embedded in the filler. A piling unit wall construction method is provided, wherein the pile unit is installed to be provided, and the pile unit is disposed between predetermined intervals of the pile unit not including the H beam thumb pile.

이하, 첨부된 예시도면을 참조하여 본 발명에 따른 엄지말뚝 매립형 말뚝 유닛의 시공방법과, 이를 이용한 주열식 흙막이 벽체의 시공방법에 대하여 상세히 설명한다. 아래의 설명에서 상기 엄지말뚝의 일예로서 "H빔 엄지말뚝"을 예시하고 있으나, 본 발명의 엄지말뚝은 "H빔" 형상에 한정되는 것은 아니다. 또한, 아래에서는 본 발명에 따라 시공된 말뚝 유닛의 사용예로서, 주열식 흙막이 벽체를 예시하고 있고, 이에 대하여 특허청구하고 있으나, 본 발명에 따른 말뚝 유닛의 시공방법에 의하여 시공된 말뚝 유닛이 사용되는 예는 반드시 주열식 흙막이 벽체에만 한정되는 것은 아니다. Hereinafter, with reference to the accompanying drawings will be described in detail the construction method of the pile pile buried pile unit according to the present invention, and the construction method of the column-type mud wall using the same. In the following description, but one example of the thumb pile "H beam thumb pile" is illustrated, but the thumb pile of the present invention is not limited to the "H beam" shape. In addition, below, as an example of the use of the pile unit constructed in accordance with the present invention, it is illustrated that the main heat-sucking wall, the patent claim for this, but the pile unit constructed by the construction method of the pile unit according to the present invention is used Examples are not necessarily limited to staggered wall.

도 1에는 본 발명의 일실시예에 따라 시공된 주열식 흙막이 벽체(1)의 개략적인 평면도가 도시되어 있다. 도면에 도시된 본 발명의 일실시예에 따른 주열식 흙막이 벽체(1)는 다수개의 말뚝 유닛(2, 3)이 연속적으로 배치되어 형성되는데, H빔 엄지말뚝(10)이 삽입되지 않고 단순히 충진재(31)만으로 이루어진 말뚝 유닛(3)의 사이에 소정 간격으로 상기 말뚝 유닛(3)의 경우보다 더 큰 H빔 엄지말뚝(10)이 충진재(31)에 매립되어 있는 구조의 말뚝 유닛(2)이 배치되는 구조를 가진다. 즉, 도면에 도시된 것처럼, H빔 엄지말뚝(10)이 충진재(31)에 매립되어 있는 구조의 말 뚝 유닛(2)은 제1공과 제2공이 말뚝 유닛 배치면에 수직한 방향으로 구멍의 일부가 겹치도록 천공되어 상기 제1공과 제2공에 걸쳐서 H빔 엄지말뚝(10)이 배치되는 구조를 가지는 것이다. FIG. 1 is a schematic plan view of a columnar retaining wall 1 constructed in accordance with one embodiment of the present invention. In the main column wall 1 according to an embodiment of the present invention shown in the drawing is formed by a plurality of pile units (2, 3) are arranged in succession, H beam thumb pile 10 is not inserted simply filling material The pile unit 2 of the structure in which the H beam thumb pile 10 which is larger than the case of the said pile unit 3 is embedded in the filler 31 at predetermined intervals between the pile units 3 which consist only of 31. It has a structure that is arranged. That is, as shown in the figure, the pile unit 2 of the structure in which the H-beam thumb pile 10 is embedded in the filler 31, the first hole and the second hole of the hole in the direction perpendicular to the pile unit arrangement surface Perforated to overlap a portion has a structure in which the H beam thumb pile 10 is disposed over the first hole and the second hole.

이와 같이, 단순히 충진재(31)만으로 이루어진 말뚝 유닛(3)보다 더 큰 구멍을 가지도록 천공하고 종전에 상기 말뚝 유닛(3)에 삽입되던 것보다 더 큰 H빔 엄지말뚝(10)을 삽입하여 말뚝 유닛(2)을 형성하게 되면, 더 커진 H빔 엄지말뚝(10)의 강성에 의하여 주열식 흙막이 벽체(1)의 강성을 더욱 증가시킬 수 있는 효과가 있다. 또한 큰 강성의 흙막이 벽체를 이루게 됨에 따라 지보공의 수직 간격도 증대시켜 경제적인 시공을 이룰 수 있게 된다. 아울러 말뚝 유닛(2)에 매립된 상기 H빔 엄지말뚝(10)을, 주열식 흙막이 벽체(1)에 인접하여 시공되는 콘크리트 지하 벽체(100)의 구조 부재로서 활용하는 경우에는, 더 커진 H빔 엄지말뚝(10)의 증가된 강성만큼 콘크리트 지하 벽체(100)의 두께 등을 줄일 수 있게 되어 더욱 경제적인 시공이 가능하게 된다. As such, it is simply perforated to have a larger hole than the pile unit 3 consisting of only the filler 31 and inserting the H beam thumb pile 10 larger than the one previously inserted into the pile unit 3 When the unit 2 is formed, the rigidity of the main heating wall 1 can be further increased by the rigidity of the larger H-beam thumb pile 10. In addition, as the large stiff soil wall forms a wall, the vertical spacing of jibo is also increased to achieve economic construction. In addition, when the H beam thumb pile 10 embedded in the pile unit 2 is utilized as a structural member of the concrete underground wall 100 constructed adjacent to the main thermal wall 1, the larger H beam By increasing the rigidity of the thumb pile 10 it is possible to reduce the thickness and the like of the concrete basement wall 100 it becomes more economical construction is possible.

그런데 위와 같이 더 커진 H빔 엄지말뚝(10)을 가진 말뚝 유닛(2)을 시공하기 위해서는 그만큼 천공단면도 커야 하는데, 만일 단순히 오거의 직경을 크게 하여 천공하는 것은 결코 바람직하지 않다. 왜냐하면 단순히 오거의 직경을 키워 천공단면을 증가시키게 되면 지반 천공에 소요되는 비용이 급격하게 증가하게 되기 때문이다. 또한 위와 같은 경우 H빔 엄지말뚝(10) 주위에 채워질 충진재(31)의 양도 과도하게 증가하게 되고 그에 따라 시공비가 상승하는 문제점도 있다. 그 뿐만 아니라, H빔 엄지말뚝(10)이 설치되지 아니하는 말뚝 유닛(3)의 시공을 위한 오 거와는 다른 크기의 직경을 가지는 오거를 별도로 준비하여야 하고 서로 다른 크기의 오거를 번갈아 투입하여야 하므로, 그 만큼 비용이 증가하게 될 뿐만 아니라 천공작업도 번거롭게 되어 작업성이 매우 저하되는 문제점이 발생하게 된다. However, in order to construct the pile unit 2 having the larger H-beam thumb pile 10 as described above, the perforation cross-section should be large, but it is never desirable to perforate simply by increasing the diameter of the auger. Because simply increasing the diameter of the auger to increase the perforated section will increase the cost of drilling the ground rapidly. In addition, in the above case, the amount of the filler 31 to be filled around the H-beam thumb pile 10 is also excessively increased, thereby increasing the construction cost. In addition, an auger having a diameter different from that of the auger for the construction of the pile unit 3 in which the H-beam thumb pile 10 is not installed must be separately prepared, and the augers of different sizes must be alternated. Therefore, not only the cost increases, but also the boring work is cumbersome, the workability is very poorly generated.

이러한 문제점을 해결하기 위하여 본 발명에서는 다음과 같은 방법 단계에 의하여 더 커진 H빔 엄지말뚝(10)을 구비한 말뚝 유닛(2)을 시공한다. 도 2a 내지 도 2f에는 본 발명에 따른 말뚝 유닛의 시공단계에 포함된 각 단계를 설명하기 위한 측면도 내지 평면도가 도시되어 있다. In order to solve this problem, the present invention constructs a pile unit 2 having a larger H-beam thumb pile 10 by the following method steps. 2A to 2F are side views to plan views for explaining each step included in the construction step of the pile unit according to the present invention.

우선 도 2a의 수직 단면도에 도시된 것처럼 오거 등의 천공기(70)를 이용하여 지반을 소정 깊이로 천공하여 제1공(50)을 형성한다. 천공기(70)가 지반 내로 굴진할 때 제1공(50)에는 제1 관부재(51)를 삽입하여 1차 케이싱 작업을 하게 된다. 천공이 종료되어 제1공(50)에 제1 관부재(51)가 삽입 설치되면 도 2b의 수직 단면도에 도시된 것처럼 제1 관부재(51)의 내부에 또다른 제2 관부재(52)를 삽입하고 제1 관부재(51)를 인발하여 제거하는 2차 케이싱 작업을 하게 된다. 도 2c에는 2차 케이싱 작업을 완료하여 제1공(50)에 제2 관부재(52)만이 설치되어 있는 상태의 평면도가 도시되어 있다. First, as shown in the vertical cross-sectional view of FIG. 2A, the ground is drilled to a predetermined depth by using a boring machine 70 such as auger to form the first hole 50. When the drilling machine 70 excavates into the ground, the first casing 50 is inserted into the first hole 50 to perform the first casing operation. When the drilling is completed and the first pipe member 51 is inserted and installed in the first hole 50, another second pipe member 52 is formed inside the first pipe member 51 as shown in a vertical cross-sectional view of FIG. 2B. Insert the second casing to remove the first pipe member 51 is removed. 2C is a plan view of a state in which only the second pipe member 52 is installed in the first hole 50 by completing the secondary casing operation.

본 발명에 있어서 제2 관부재(52)는 도 2c에 도시된 것과 같이 그 일측이 오목한 오목부(53)를 가지는 반월형 단면 구조로 이루어져 있다. 예를 들면 관부재 일측에서 소정 길이의 원호 부분을 종방향(관부재의 길이방향)으로 절단한 후 이를 뒤집어서 다시 붙이는 방법 등을 통하여 오목부(53)를 가지는 반월형 단면의 관부재를 용이하게 제작할 수 있다. 후술하는 것처럼 H빔 엄지말뚝(10)을 삽입할 때 엄지말뚝(10)의 웨브(11)가 제2 관부재(51)를 관통할 수 있도록 상기 오목부(53)의 중간에는 종방향으로 슬릿(54)이 형성되어 있다. 경우에 따라서는 후술하는 것처럼 제1공에 접하여 제2공을 천공할 때 토사가 상기 슬릿(54)을 통하여 제2 관부재(52)의 내부로 유입될 수 있는데, 이를 방지하기 위한 유입방지판(55)을 임시로 설치할 수도 있다. 도면에 도시된 실시예에는 상기 유입방지판(55)을 위로 뽑아서 제거하기 용이하도록 오목부(53) 내측으로 가이드 런(56)을 형성하고 상기 가이드 런(56) 사이에 유입방지판(55)을 삽입하여, 유입방지판(55)을 가이드 런(56)으로부터 슬라이딩시켜 제거할 수 있도록 구성되어 있다. In the present invention, the second pipe member 52 has a half-month cross-sectional structure having a concave portion 53 having one side concave as shown in FIG. 2C. For example, it is easy to manufacture a half-walled cross section having a concave portion 53 by cutting a circular arc portion of a predetermined length in the longitudinal direction (the longitudinal direction of the tubular member) from one side of the tube member and then inverting and reattaching it. Can be. As will be described later, when inserting the H beam thumb pile 10, the slits in the longitudinal direction in the middle of the concave portion 53 are formed so that the web 11 of the thumb pile 10 can penetrate through the second pipe member 51. 54 is formed. In some cases, when the second hole is in contact with the first hole as described below, the earth and sand may flow into the second pipe member 52 through the slit 54. It is also possible to temporarily install 55. In the embodiment shown in the drawing to form a guide run 56 to the inside of the concave portion 53 to facilitate the removal by removing the inflow preventing plate 55 and the inflow preventing plate 55 between the guide run (56). It is configured to be removed by sliding the inflow preventing plate 55 from the guide run 56 by insertion.

이후 제2 관부재(52)의 오목부(53)에 인접하여 천공기(70)를 이용하여 지반에 제2공(60)을 천공한다. 종래에는 지반에 구멍을 연속적으로 천공할 수가 없었다. 즉, 위와 같이 제1공(50)을 천공한 후에 바로 인접하여 제2공(60)을 천공하는 것이 가능하지 아니하였다. 왜냐하면 제2공을 천공하는 과정에서 지반의 토사가 무너져서 제1공으로 유입되기 때문이다. 그러나 본 발명에서는 제1공(50)에 미리 제2 관부재(52)를 설치해둔 상태이고, 특히 제2 관부재(52)의 측면에는 제2공을 천공할 수 있는 공간을 확보하도록 오목부(53)가 형성되어 있으므로 천공과정에서 지반 토사가 무너져서 제1공으로 유입되는 것이 방지되므로 제1공(50)에 바로 인접하여 제2공(60)을 천공할 수 있게 된다. 이와 같이 천공기가 제1공(50)에 이웃한 위치에서 지반 내로 굴진하여 제2공(60)을 형성할 때에는 도 2d의 평면도에 도시된 것처럼 제2공(60)에는 제3 관부재(61)를 삽입하는 3차 케이싱 작업을 병행하게 된다. Thereafter, the second hole 60 is drilled in the ground by using the puncher 70 adjacent to the recess 53 of the second pipe member 52. Conventionally, it was not possible to continuously drill holes in the ground. That is, it was not possible to puncture the second hole 60 immediately adjacent to the first hole 50 as described above. This is because soil in the ground collapses in the process of drilling the second hole and flows into the first hole. However, in the present invention, the second pipe member 52 is installed in the first hole 50 in advance, and in particular, the concave portion is provided on the side surface of the second pipe member 52 to secure a space for drilling the second hole. Since 53 is formed, it is possible to drill the second hole 60 immediately adjacent to the first hole 50 because the ground soil is prevented from falling into the first hole during the drilling process. As such, when the perforator drills into the ground at a position adjacent to the first hole 50 to form the second hole 60, the third pipe member 61 is disposed in the second hole 60 as shown in the plan view of FIG. 2D. The third casing work to insert) will be performed in parallel.

이와 같이 제3 관부재(61)가 제2공(60)에 삽입 설치된 상태에서 후속하여 제3 관부재(61)의 내부에 제4 관부재(62)를 삽입하고, 제3 관부재(61)는 인발하여 제거하는 4차 케이싱 작업을 수행한다. 도 2e에는 제4 관부재(62)를 설치한 후 제3 관부재(61)를 인발한 상태를 보여주는 평면도가 도시되어 있다. 도면에 도시된 것처럼 제4 관부재(62)에서 상기 제1공(50)의 제2 관부재(52) 방향 측면에는 상기 제2 관부재(52)와 마찬가지로 종방향으로 길게 슬릿(64)이 형성되며, 상기 제4 관부재(62)는 그 슬릿(64)과 상기 제2 관부재(52)의 슬릿(54)이 서로 마주보아 연통되도록 배치된다. 상기 제4 관부재(62)를 설치한 후에는 도 2f의 평면도에 도시된 것처럼 상기 제1공(50)과 제2공(60)에 걸쳐서 H빔 엄지말뚝(10)을 삽입한다. 본 발명에서는 상기한 것처럼 제2 관부재(52)와 제4 관부재(62)의 측면에 각각 슬릿(54, 64)이 마주보도록 형성되어 있으므로 H빔 엄지말뚝(10)의 웨브(11)가 상기 슬릿(54, 64)을 통과하여 양측의 제1공(50)과 제2공(60)에 걸쳐서 배치될 수 있다. 앞서 설명한 것처럼 제2 관부재(52)의 슬릿(54)이 유입방지판(55)에 의하여 막혀 있는 경우에는 유입방지판(55)을 제거하여 슬릿(54, 64)이 서로 연통되도록 한 후에 H빔 엄지말뚝(10)을 삽입 설치한다. In this way, while the third pipe member 61 is inserted into the second hole 60, the fourth pipe member 62 is subsequently inserted into the third pipe member 61, and the third pipe member 61 is inserted therein. ) Performs the fourth casing operation to draw and remove. 2E is a plan view showing a state in which the third pipe member 61 is drawn after the fourth pipe member 62 is installed. As shown in the drawing, the slit 64 is elongated in the longitudinal direction in the fourth tube member 62 in the lateral side of the first tube 50 in the direction of the second tube member 52, similarly to the second tube member 52. The fourth tube member 62 is disposed such that the slit 64 and the slit 54 of the second tube member 52 face each other to communicate with each other. After installing the fourth pipe member 62, the H beam thumb pile 10 is inserted over the first hole 50 and the second hole 60, as shown in the plan view of FIG. 2F. In the present invention, since the slits 54 and 64 face each other on the side surfaces of the second pipe member 52 and the fourth pipe member 62 as described above, the web 11 of the H-beam thumb pile 10 is Passing through the slits 54 and 64 may be disposed over the first hole 50 and the second hole 60 on both sides. As described above, when the slit 54 of the second pipe member 52 is blocked by the inflow preventing plate 55, the inflow preventing plate 55 is removed to allow the slits 54 and 64 to communicate with each other. Insert and install the beam thumb pile (10).

이와 같은 구성을 통하여, 말뚝 유닛의 천공지름을 키우지 않고서도, 2개의 구멍을 연속하여 천공하여 종전보다 더 큰 크기의 H빔 엄지말뚝(10)을 설치할 수 있게 된다. Through such a configuration, it is possible to install the H-beam thumb pile 10 having a larger size than before by drilling two holes in succession without increasing the drilling diameter of the pile unit.

이미 기술하였지만, 본 발명에 따른 말뚝 유닛의 시공방법에 의하여 시공된 말뚝 유닛이 사용되는 예가 반드시 주열식 흙막이 벽체에 한정되는 것은 아니다. 즉, 도 2f에 도시된 상태에서 제1공(50)과 제2공(60)에 충진재로서 토사를 채우고 제2 관부재(52) 및 제4 관부재(62)를 각각 인발하여 제거하여 사용할 수 있다. 이 경우 추후 H빔 엄지말뚝(10)을 인발하여 재활용하기가 용이하게 된다. Although already described, the example in which the pile unit constructed by the construction method of the pile unit according to the present invention is used is not necessarily limited to the main heating wall. That is, in the state shown in Figure 2f to fill the earth and sand as the filling material in the first hole 50 and the second hole 60, the second pipe member 52 and the fourth pipe member 62 is used to remove and remove, respectively. Can be. In this case, it is easy to draw and recycle the H-beam thumb pile 10 later.

만일 도 1에 도시된 것과 같은 주열식 흙막이 벽체(1)를 시공하는 경우에는 후속하여 다음과 같은 단계들을 진행한다. In the case of constructing the columnar wall 1 as shown in FIG. 1, the following steps are subsequently performed.

H빔 엄지말뚝(10)이 설치되면 제2 관부재(52) 및 제4 관부재(62) 내에 각각 소일 시멘트 또는 콘크리트와 같은 충진재(31)를 타설하여 H빔 엄지말뚝(10) 전체가 충진재(31) 속에 매립되도록 한다. 후속하여 상기 충진재(31)가 양생되기 전에 제2 관부재(52) 및 제4 관부재(62)를 각각 인발하여 제거한다. 도 3에는 위와 같은 과정을 통해 제2 관부재(52)와 제4 관부재(62)를 모두 인발하여 제거한 상태를 보여주는 평면도가 도시되어 있다. When the H beam thumb pile 10 is installed, the filling material 31 such as soil cement or concrete is poured into the second pipe member 52 and the fourth pipe member 62, respectively, so that the entire H beam thumb pile 10 is filled. (31) to be buried in. Subsequently, before the filler 31 is cured, the second pipe member 52 and the fourth pipe member 62 are drawn and removed, respectively. 3 is a plan view showing a state in which both the second pipe member 52 and the fourth pipe member 62 are removed by the above-described process.

이와 같은 방법으로 말뚝 유닛(2)을 시공한 후에는 종래의 방법을 이용하여 상기 제1공(50)의 좌우측으로는 H빔 엄지말뚝(10)이 없는 통상의 말뚝 유닛(3)을 시공하여 말뚝 유닛(2, 3)이 연속하여 배치하도록 한다. 즉, 도 1에 도시된 것처럼 제1공(50)과 제2공(60)이 겹치게 천공되어 그 내부의 충진재(31) 내에 H빔 엄지말뚝(10)이 상기 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)과, 그 좌우측으로는 H빔 엄지말뚝(10)이 충진재(31) 내에 매립되어 있지 아니한 구조의 말뚝 유닛(3)이 연속적으로 배치되어 본 발명에 따른 주열식 흙막이 벽체(1)를 형성하게 된다. 이와 같이, H빔 엄지말뚝(10)의 전부가 상기 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)을 포함하는 본 발명의 주열식 흙막이 벽체(1)는 다양한 구성 을 이용하여 상기 H빔 엄지말뚝(10)을 구조재로서 활용할 수 있게 된다. After the pile unit 2 is constructed in this manner, the conventional pile unit 3 without the H beam thumb pile 10 is installed on the left and right sides of the first hole 50 by using a conventional method. The pile units 2 and 3 are arranged continuously. That is, as shown in FIG. 1, the first hole 50 and the second hole 60 are overlapped and the H beam thumb pile 10 is embedded in the filler 31 in the filler 31 therein. The pile unit 2 of the structure and the pile unit 3 of the structure in which the H-beam thumb pile 10 is not embedded in the filler 31 on the left and right sides thereof are arranged in succession, and the main heating wall according to the present invention is arranged. (1) is formed. As described above, the main heat-stacking wall 1 of the present invention including the pile unit 2 having the structure in which all of the H-beam thumb piles 10 are embedded in the filling material 31 is used in various ways. The beam thumb pile 10 can be utilized as a structural member.

도 4에는 본 발명에 따라 시공된 주열식 흙막이 벽체(1)에 접하여 콘크리트 지하 벽체(100)가 시공될 때, 도 3에 도시된 것과 같이 H빔 엄지말뚝(10)이 상기 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)에 전단연결재(110)를 설치하여 상기 전단연결재(110)를 콘크리트 지하 벽체(100)에 매립되도록 함으로써, 주열식 흙막이 벽체(1)와 콘크리트 지하 벽체(100)가 일체로 합성되도록 하는 실시예를 보여주는 평면도가 도시되어 있다. 4 shows the H-beam thumb pile 10 as shown in FIG. 3 when the concrete underground wall 100 is constructed in contact with the main thermal wall 1 constructed in accordance with the present invention. By installing the shear connector 110 in the pile unit (2) of the buried structure so that the shear connector 110 is embedded in the concrete underground wall (100), the main heat-retaining wall (1) and concrete underground wall (100) A plan view is shown showing an embodiment in which) is integrally synthesized.

지하 구조물을 시공하기 위해서는 도 1의 상태에서 말뚝 유닛(30, 31)의 전면 부분의 지반을 굴착하여 주열식 흙막이 벽체(1)에 접하여 콘크리트 지하 벽체(100)를 시공하게 된다. H빔 엄지말뚝(10)이 매립되어 있는 말뚝 유닛(2)의 경우, H빔 엄지말뚝(10)의 외면이 노출되고 그 노출면에는 전단연결재(110)가 설치된다. 후속하여 도 4에 도시된 것처럼 콘크리트 지하 벽체(100)가 시공될 때 H빔 엄지말뚝(10)의 노출 외면에 설치된 전단연결재(110)가 콘크리트 지하 벽체(100) 속에 매립되도록 콘크리트 지하 벽체(100)를 형성하게 되는 것이다. In order to construct an underground structure, the ground of the front part of the pile units 30 and 31 is excavated in the state of FIG. 1 to be in contact with the main thermal wall 1 to construct the concrete underground wall 100. In the case of the pile unit 2 in which the H-beam thumb pile 10 is embedded, the outer surface of the H-beam thumb pile 10 is exposed, and the shear connecting member 110 is installed on the exposed surface. Subsequently, when the concrete underground wall 100 is constructed as shown in FIG. 4, the shear connection material 110 installed on the exposed outer surface of the H-beam thumb pile 10 is embedded in the concrete underground wall 100 so that the concrete underground wall 100 is embedded. ) Will be formed.

한편, 도 2a 내지 도 2f에 도시된 단계에 후속하여 아래에 설명하는 단계를 더 수행함으로써, 제1공(50)과 제2공(60) 중의 어느 한 곳에만 충진재를 채우고 H빔 엄지말뚝(10)의 일부를 충진재 외부로 노출시켜 이를 지하 구조물의 벽체에 매립시키는 등과 같이 다른 용도로 사용할 수도 있다. Meanwhile, by further performing the steps described below after the steps shown in FIGS. 2A to 2F, the filler is filled in only one of the first hole 50 and the second hole 60, and the H beam thumb pile 10 is filled. It can also be used for other purposes, such as exposing a portion of) to the outside of the filler and embedding it in the walls of the underground structure.

즉, 도 2f에 도시된 단계를 통해 H빔 엄지말뚝(10)이 설치된 상태에서 제2 관부재(52)에는 충진재(31)를 타설하고, 충진재(31)가 양생되기 전에 제2 관부재 (52)를 인발하여 제거하고, 충진재(31)의 양생이 완료되면 제4 관부재(62) 역시 인발하여 제거한다. 도 5에는 위와 같은 과정을 통해 제2 관부재(52)와 제4 관부재(62)를 모두 인발하여 제거한 상태를 보여주는 평면도가 도시되어 있다. 제4 관부재(62)를 인발할 때, 충진재(31)가 제4 관부재(62)의 외면에 붙어 제4 관부재(62)의 인발이 어려워지는 것을 방지하기 위하여 미리 제4 관부재(62) 외면에 이탈제 등을 도포하는 것이 바람직하며, 도면에 도시되지 아니하였지만, 경우에 따라서는 제1공(50)에 채워진 충진재(31)가 양생되면서 붙게 되는 영역의 경계면을 따라 제4 관부재(62)의 외부에 플라스틱 판재 등의 판부재를 미리 붙여 두고, 추후 제1공(50)의 충진재(31)가 양생되어 상기 판부재가 충진재(31)와 붙게 되면, 제4 관부재(62)를 비트는 등의 방법을 통해 상기 판부재가 충진재(31)에 붙어 있는 채로 제4 관부재(62)와는 분리되어 제4 관부재(62)만을 인발하도록 하는 방법도 취할 수 있다. That is, the filler 31 is poured into the second tube member 52 in the state where the H beam thumb pile 10 is installed through the step shown in FIG. 2F, and the second tube member (before the filler 31 is cured). 52) is removed by drawing, and when the curing of the filler 31 is completed, the fourth pipe member 62 is also removed by drawing. FIG. 5 is a plan view showing a state in which both the second pipe member 52 and the fourth pipe member 62 are removed by the above-described process. When drawing out the fourth pipe member 62, the filler 31 is attached to the outer surface of the fourth pipe member 62 to prevent the drawing of the fourth pipe member 62 from becoming difficult. 62) It is preferable to apply a releasing agent to the outer surface, and although not shown in the drawing, in some cases, the fourth pipe along the boundary of the region where the filler 31 filled in the first hole 50 is attached while curing. If a plate member such as a plastic plate is pasted on the outside of the member 62 and the filler 31 of the first hole 50 is cured later, and the plate member is stuck with the filler 31, the fourth tube member ( By twisting 62, the plate member may be separated from the fourth tube member 62 while being attached to the filler 31 to draw only the fourth tube member 62.

제4 관부재(62)까지 인발하여 제거하여 말뚝 유닛(2)을 시공한 후에는 종래의 방법을 이용하여 상기 제1공(50)의 좌우측으로는 H빔 엄지말뚝(10)이 없는 통상의 말뚝 유닛(3)을 시공하여 말뚝 유닛(2, 3)이 연속하여 배치하도록 한다. 도 6에는 H빔 엄지말뚝(10)의 일부분이 상기 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)과, 그 좌우측으로는 H빔 엄지말뚝(10)이 충진재(31) 내에 매립되어 있지 아니한 구조의 말뚝 유닛(3)이 연속적으로 배치되어 본 발명의 일실시예에 따른 주열식 흙막이 벽체(1)를 형성한 상태의 평면도가 도시되어 있다. 도면에 도시된 실시예와 같이 H빔 엄지말뚝(10)의 일부분이 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)이, H빔 엄지말뚝(10)을 전혀 포함하고 있지 아니한 말뚝 유닛(3) 몇 개를 사이에 두고 반복하여 배치될 수 있다. After drawing up and removing the fourth pipe member 62 and constructing the pile unit 2, the H beam thumb pile 10 is not disposed on the left and right sides of the first hole 50 using a conventional method. The pile unit 3 is constructed so that the pile units 2 and 3 are continuously arranged. 6, a pile unit 2 having a structure in which a portion of the H beam thumb pile 10 is embedded in the filler 31, and an H beam thumb pile 10 is embedded in the filler 31 on the left and right sides thereof. The top view of the state in which the pile unit 3 of the structure which is not provided is continuously arrange | positioned and the main column type wall wall 1 which concerns on one Embodiment of this invention is formed is shown. Pile unit 2 having a structure in which a portion of H beam thumb pile 10 is embedded in filler 31, as shown in the figure, does not include H beam thumb pile 10 at all. (3) It may be repeatedly arranged with several pieces in between.

이와 같이, H빔 엄지말뚝(10)의 일부분이 상기 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)을 포함하는 주열식 흙막이 벽체(1)는 다양한 구성을 이용하여 상기 H빔 엄지말뚝(10)을 구조재로서 활용할 수 있게 된다. As described above, the main column type wall 1 including a pile unit 2 having a structure in which a portion of the H beam thumb pile 10 is embedded in the filler 31 is formed using various configurations. (10) can be utilized as a structural material.

도 7a 내지 도 7c에는 주열식 흙막이 벽체(1)에 접하여 콘크리트 지하 벽체(100)가 시공될 때, H빔 엄지말뚝(10)의 일부분이 상기 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)을 포함하는 주열식 흙막이 벽체(10)에서 H빔 엄지말뚝(10)의 활용 방법의 다양한 실시예를 보여주는 평면도가 도시되어 있다. 7A to 7C, a pile unit having a structure in which a portion of the H-beam thumb pile 10 is embedded in the filler 31 when the concrete underground wall 100 is constructed in contact with the main thermal wall 1 is constructed. A plan view showing various embodiments of the utilization method of the H-beam thumb pile 10 in the columnar retaining wall 10 including 2) is shown.

지하 구조물을 시공하기 위해서는 도 6의 상태에서 제2공(61) 부분을 포함하여 말뚝 유닛(30, 31)의 전면 부분의 지반을 굴착한 후 주열식 흙막이 벽체(1)에 접하여 콘크리트 지하 벽체(100)를 시공하게 된다. H빔 엄지말뚝(10)의 일부분이 충진재(31) 외부로 노출된 말뚝 유닛(2)의 경우, 도 7a 및 도 7b에 도시된 것처럼 콘크리트 지하 벽체(100)가 시공될 때 H빔 엄지말뚝(10)의 노출된 부분이 콘크리트 지하 벽체(100) 속에 매립되도록 할 수 있다. 이와 같은 경우, 콘크리트 지하 벽체(100) 속에 매립된 H빔 엄지말뚝(10) 부분은 콘크리트 지하 벽체(100) 자체의 강성을 보강하는 구조 부재로서 기능하게 되므로, 그에 맞추어 콘크리트 지하 벽체(100)의 두께를 줄이거나 그 내부에 배근되는 철근 등의 보강부재를 줄일 수 있어 경제적인 시공을 할 수 있게 된다. 특히 콘크리트 지하 벽체(100)의 두께가 감소되면 더 넓은 지하 공간을 확보할 수 있게 되는 장점이 발휘된다. 또한 H빔 엄지 말뚝(10)이 매립된 말뚝 유닛과 콘크리트 지하 벽체(100) 즉, 흙막이 벽체(1)와 콘크리트 지하 벽체(100)가 일체로 결합되어 합성효과를 발휘하게 되므로, 말뚝 유닛의 충진재(31) 속에 매립된 H빔 엄지말뚝(10) 부분도 사장되지 아니하고 콘크리트 지하 벽체(100)의 강성을 높여주는 유리한 기능을 가지게 된다. In order to construct the underground structure, the ground of the front part of the pile unit 30, 31 including the second hole 61 in the state of FIG. 100) will be installed. In the case of the pile unit 2 in which a portion of the H beam thumb pile 10 is exposed to the outside of the filler 31, the H beam thumb pile (when the concrete underground wall 100 is constructed, as shown in FIGS. 7A and 7B). The exposed portion of 10 may be embedded in the concrete underground wall 100. In this case, since the portion of the H-beam thumb pile 10 embedded in the concrete underground wall 100 functions as a structural member to reinforce the rigidity of the concrete underground wall 100 itself, the concrete underground wall 100 accordingly It is possible to reduce the thickness or to reduce the reinforcing members such as reinforcing bars in the interior can be economical construction. In particular, when the thickness of the concrete underground wall 100 is reduced, the advantage that it is possible to secure a wider underground space. In addition, since the pile unit and the concrete underground wall 100 that is embedded with the H-beam thumb pile 10, that is, the soil wall 1 and the concrete underground wall 100 are integrally combined to exert a synthetic effect, the filler of the pile unit The portion of the H-beam thumb pile 10 embedded in the 31 is not dead but has an advantageous function of increasing the rigidity of the concrete underground wall 100.

또한 도 7c에 도시된 것처럼, 말뚝 유닛(2)의 충진재(31) 외부로 노출된 H빔 엄지말뚝(10)의 플랜지 내측으로 콘크리트 지하 벽체(100)를 시공할 수도 있는데, 이 경우 충진재(31) 외부로 노출된 H빔 엄지말뚝(10)의 일부분은 콘크리트 지하 벽체(100) 시공을 위한 거푸집을 설치하기 위한 지지대로도 사용할 수 있으므로 콘크리트 지하 벽체(100)의 시공이 더욱 용이하게 될 수 있다. In addition, as shown in FIG. 7C, the concrete underground wall 100 may be constructed inside the flange of the H beam thumb pile 10 exposed to the outside of the filler 31 of the pile unit 2, in which case the filler 31. A part of the H-beam thumb pile 10 exposed to the outside may be used as a support for installing the formwork for the construction of the concrete underground wall 100, so that the construction of the concrete underground wall 100 may be more easily performed. .

이상 살펴본 바와 같이, 본 발명에 있어서는 엄지말뚝 매립형 말뚝 유닛을 시공함에 있어서 단순히 천공 지름을 크게 하는 것이 아니라, 구멍을 서로 이웃하도록 연속하여 천공하고, H빔 엄지말뚝을 연속 천공된 2개의 구멍에 걸쳐서 설치할 수 있도록 함으로써, 더 큰 크기의 엄지말뚝을 설치할 수 있으면서도 천공 지름 확대에 따른 천공비의 증가를 방지할 수 있고 불필요한 충진재의 사용을 줄일 수 있게 된다. As described above, in the present invention, in constructing the thumb pile embedded pile unit, instead of simply increasing the punching diameter, the holes are continuously drilled so as to be adjacent to each other, and the H beam thumb pile is continuously spread over the two holes which are continuously punched. By making it possible to install a larger sized pile, it is possible to prevent an increase in the drilling rate due to the expansion of the drilling diameter and to reduce the use of unnecessary fillers.

특히, 주열식 흙막이 벽체의 말뚝 유닛을 시공할 때, 위와 같은 본 발명에 따른 말뚝 유닛의 시공방법을 적용할 수 있는데, 상기 H빔 엄지말뚝(10)이 삽입되지 아니한 소 직경의 말뚝 유닛(3)들 사이에 본 발명에 따라 H빔 엄지말뚝(10)이 삽입된 대 직경의 말뚝 유닛(2)을 소정 간격으로 혼합 배치하여 전체 흙막이 벽체를 구성하게 된다. 이러한 구조에서는 H빔 엄지말뚝(10)이 삽입된 대 직경의 말뚝 유닛(2)이 큰 강성을 발휘하게 때문에 지보공의 수직 방향 간격을 큰 폭으로 형성할 수 있으며, 그에 따라 시공을 용이하고 빠르게 진행할 수 있게 되는 장점이 있다. 특히, 큰 강성을 가지는 H빔 엄지말뚝(10)이 삽입된 대 직경의 말뚝 유닛(2)이 콘크리트 지하 벽체(100)에 대하여 큰 지지력을 발휘하기 때문에 콘크리트 지하 벽체(100)의 두께를 줄일 수 있으며, 그에 따라 콘크리트 지하 벽체(100) 시공비가 절감되고, 콘크리트 지하 벽체(100)가 차지하고 있던 면적이 줄어들어 더 넓은 지하 면적을 확보할 수 있게 되는 장점이 있다. In particular, when constructing the pile unit of the heat-stacking wall, it is possible to apply the construction method of the pile unit according to the present invention as above, the small diameter pile unit (3) is not inserted into the H-beam thumb pile (10) In accordance with the present invention, a large diameter pile unit 2 having the H-beam thumb pile 10 inserted therebetween is mixed and arranged at predetermined intervals so as to constitute the entire wall of walls. In such a structure, since the large diameter pile unit 2 into which the H-beam thumb pile 10 is inserted exhibits great rigidity, the vertical gap of the support beam can be formed with a large width, thereby making construction easier and faster. It has the advantage of being able to. In particular, since the large diameter pile unit 2 into which the H-beam thumb pile 10 having large rigidity is inserted exerts a large bearing force against the concrete underground wall 100, the thickness of the concrete underground wall 100 can be reduced. In this case, the construction cost of the concrete underground wall 100 is reduced, and the area occupied by the concrete underground wall 100 is reduced, thereby securing a wider underground area.

또한, 본 발명에 의하면 제1 관부재(51), 반월형 단면 구조를 가지는 제2 관부재(52), 제3 관부재(61), 및 제4 관부재(62)를 이용하여 제1공(50)과 제2공(60)을 인접한 상태로 연속 천공하여 H빔 엄지말뚝(10)의 일부분만이 충진재(31)에 매립되어 있고 나머지 일부는 충진재(31) 외부로 노출되는 구조의 말뚝 유닛(2)을 경제적인 방법으로 용이하게 시공할 수 있게 된다. In addition, according to the present invention, the first tube (51), the second tube member 52 having a half-wall-shaped cross-sectional structure, the third tube member 61, and the fourth tube member 62 using the first hole ( 50) and the second hole 60 is continuously drilled in a state adjacent to only the portion of the H beam thumb pile 10 is embedded in the filler 31 and the remaining pile unit of the structure exposed to the outside of the filler 31 (2) can be easily installed in an economic way.

이러한 구조의 말뚝 유닛(2)을 포함하여 주열식 흙막이 벽체(1)를 시공하게 되면 자칫 사장될 수 있는 고가의 H빔 엄지말뚝(10)을 콘크리트 지하 벽체(100)의 강성을 증가시키는 구조부재로서 활용할 수 있게 되어 콘크리트 지하 벽체(100)를 경제적으로 시공할 수 있게 된다. 구체적으로 H빔 엄지말뚝(10)이 구조부재로서 활용되어 콘크리트 지하 벽체(100)에 대하여 큰 지지력을 발휘하기 때문에 콘크리트 지하 벽체(100)의 두께를 줄일 수 있으며, 그에 따라 콘크리트 지하 벽체(100) 시공비가 절감되고, 콘크리트 지하 벽체(100)가 차지하고 있던 면적이 줄어들어 더 넓은 지하 면적을 확보할 수 있게 되는 장점이 있다. Including the pile unit 2 of such a structure, the construction of the main thermal wall 1 to increase the rigidity of the concrete underground wall 100 to the expensive H-beam thumb pile 10 can be easily It can be utilized as a concrete basement wall 100 can be economically constructed. Specifically, since the H beam thumb pile 10 is utilized as a structural member to exert great support for the concrete underground wall 100, the thickness of the concrete underground wall 100 can be reduced, and accordingly, the concrete underground wall 100 The construction cost is reduced, the area occupied by the concrete underground wall 100 is reduced, there is an advantage that can secure a wider underground area.

특히 H빔 엄지말뚝(10)의 일부분만이 충진재(31)에 매립되어 있고 나머지 일부는 충진재(31) 외부로 노출되는 구조의 말뚝 유닛(2)을 이용하면 다양한 합성 구조를 형성할 수 있게 되는 장점이 있다. In particular, only a portion of the H-beam thumb pile 10 is embedded in the filler 31 and the other part can be formed using a pile unit 2 having a structure exposed to the outside of the filler 31 There is an advantage.

Claims (6)

지중에 천공된 구멍에 엄지말뚝이 삽입 설치되는 구조를 가지는 말뚝 유닛의 시공방법으로서,As a construction method of a pile unit having a structure in which a thumb pile is inserted into a hole drilled in the ground, 지반에 소정 깊이로 제1공(50)을 천공하고 상기 제1공(50)에 제1 관부재(51)를 삽입하여 1차 케이싱 작업을 수행하는 단계; Drilling a first hole (50) to a predetermined depth in the ground and inserting a first pipe member (51) into the first hole (50) to perform a primary casing operation; 일측에 오목한 오목부(53)를 가지는 반월형 단면 구조로 이루어져 있으며 H빔 엄지말뚝(10)이 삽입될 때 H빔 엄지말뚝(10)의 웨브가 지나면서 개방되는 슬릿(54)이 종방향으로 상기 오목부(53)에 형성되어 있는 제2 관부재(52)를 상기 제1 관부재(51)의 내부에 삽입하고 상기 제1 관부재(51)는 인발하여 제거하는 2차 케이싱 작업을 수행하는 단계; The slit 54 is made of a half-wall-shaped cross-sectional structure having a concave concave portion 53 on one side, and the slit 54 is opened while the web of the H-beam thumb pile 10 passes through when the H-beam thumb pile 10 is inserted. The second tube member 52 formed in the recess 53 is inserted into the first tube member 51 and the first tube member 51 performs a secondary casing operation of drawing and removing the first tube member 51. step; 상기 제1공(50)에 바로 인접하여 제2공(60)을 천공하고 상기 제2공(60)에 제3 관부재(61)를 삽입하는 3차 케이싱 작업을 수행하는 단계; Performing a third casing operation of drilling the second hole 60 immediately adjacent to the first hole 50 and inserting a third pipe member 61 into the second hole 60; H빔 엄지말뚝(10)이 삽입될 때 그 웨브가 지날 수 있도록 측면에 종방향으로 슬릿(64)이 형성되어 있는 제4 관부재(62)를 제3 관부재(61)의 내부에 삽입하고 제3 관부재(61)는 인발하여 제거하는 4차 케이싱 작업을 수행하는 단계; 및 When the H-beam thumb pile 10 is inserted, the fourth pipe member 62 having the slits 64 formed in the longitudinal direction on the side thereof is inserted into the third pipe member 61 so that the web can pass therethrough. The third pipe member 61 is a step of performing the fourth casing to remove the draw; And 상기 제4 관부재(62)의 슬릿(64)과 상기 제2 관부재(52)의 슬릿(54)이 서로 마주보아 연통되도록 한 상태에서 상기 제2 관부재(52) 내부의 제1공(50)과 상기 제4 관부재(62) 내부의 제2공(60)에 걸쳐서 H빔 엄지말뚝(10)을 삽입하는 단계를 포함함으로써, 2개의 구멍을 그 일부가 서로 겹치게 연속하여 천공하고 그 천공된 구멍에 H빔 엄지말뚝(10)이 걸쳐져서 배치되는 구조를 가지도록 말뚝 유닛(2)을 시공하는 것을 특징으로 하는 엄지말뚝 매립형 말뚝 유닛의 시공방법.The first hole inside the second pipe member 52 in a state in which the slit 64 of the fourth pipe member 62 and the slit 54 of the second pipe member 52 communicate with each other. 50) and inserting the H-beam thumb pile 10 over the second hole 60 in the fourth pipe member 62 so that the two holes are successively drilled in such a manner that their portions overlap each other. Construction method of the pile pile buried pile unit, characterized in that the pile unit (2) is constructed so as to have a structure in which the H-beam thumb pile (10) is placed over the perforated hole. 제1항에 있어서, The method of claim 1, 제1공(50)과 제2공(60)에 걸쳐서 H빔 엄지말뚝(10)을 설치한 후에, 제2 관부재(52)에 충진재(31)를 타설하는 단계; After installing the H beam thumb pile 10 over the first hole 50 and the second hole 60, placing the filler 31 in the second pipe member 52; 상기 충진재(31)가 양생되기 전에 제2 관부재(52)를 인발하여 제거하는 단계; 및 Drawing and removing the second pipe member (52) before the filler (31) is cured; And 상기 충진재(31)가 소정 강도 이상으로 양생된 후 제4 관부재(62)를 인발하여 제거하는 단계를 포함함으로써 H빔 엄지말뚝(10)의 일부분만이 말뚝 유닛(2)의 충진재(31) 내에 매립되는 구조를 가지도록 말뚝 유닛(2)을 시공하는 것을 특징으로 하는 엄지말뚝 매립형 말뚝 유닛의 시공방법.After the filler 31 is hardened to a predetermined strength or more, the fourth pipe member 62 may be drawn and removed, so that only a portion of the H beam thumb pile 10 is filled in the pile unit 2. Construction method of the pile pile buried pile unit, characterized in that to construct the pile unit (2) to have a structure embedded in the inside. 제1항에 있어서, The method of claim 1, 제1공(50)과 제2공(60)에 걸쳐서 H빔 엄지말뚝(10)을 설치한 후에, 제2 관부재(52) 및 제4 관부재(62)에 충진재(31)를 타설하는 단계; 및After installing the H beam thumb pile 10 over the first hole 50 and the second hole 60, the filler 31 is poured into the second pipe member 52 and the fourth pipe member 62. step; And 상기 충진재(31)가 양생되기 전에 제2 관부재(52) 및 제4 관부재(62)를 인발하여 제거하는 단계를 포함함으로써 H빔 엄지말뚝(10)의 전부가 말뚝 유닛(2)의 충 진재(31) 내에 매립되는 구조를 가지도록 말뚝 유닛(2)을 시공하는 것을 특징으로 하는 엄지말뚝 매립형 말뚝 유닛의 시공방법.And removing the second pipe member 52 and the fourth pipe member 62 before the filler 31 is cured so that all of the H-beam thumb pile 10 is filled in the pile unit 2. Construction method of the pile pile buried pile unit, characterized in that to construct the pile unit (2) to have a structure embedded in the true material (31). 제1항 내지 제3항 중 어느 한 항에 있어서, The method according to any one of claims 1 to 3, 제2 관부재(52)는 오목부(53) 내측으로 가이드 런(56)을 형성하고 상기 가이드 런(56) 사이에 유입방지판(55)을 삽입하여 상기 슬릿(54)을 임시로 폐쇄하는 구성을 가지며; The second pipe member 52 forms a guide run 56 inside the recess 53 and inserts the inflow preventing plate 55 between the guide runs 56 to temporarily close the slit 54. Has a configuration; 상기 제1공(50)과 제2공(60)에 걸쳐서 H빔 엄지말뚝(10)을 삽입하기에 앞서 상기 유입방지판(55)을 제거하여 상기 슬릿(54)을 개방하는 것을 특징으로 하는 엄지말뚝 매립형 말뚝 유닛의 시공방법. Before the insertion of the H-beam thumb pile 10 over the first hole 50 and the second hole 60, the inflow preventing plate 55 is removed to open the slit 54. Construction method of thumb pile embedded pile unit. 지반에 천공된 소정 깊이의 구멍에 H빔 엄지말뚝을 설치하고 그 주변으로 충진재(31)를 채워서 형성한 말뚝 유닛(2)과, 천공된 구멍에 충진재만을 채워서 형성한 말뚝 유닛(3)을 이웃하게 일정간격으로 연속 배치하여 주열식 흙막이 벽체(1)를 시공하는 방법으로서, The pile unit 2 formed by installing the H-beam thumb pile in a hole having a predetermined depth drilled into the ground and filling the filler 31 around the pile, and the pile unit 3 formed by filling only the filler in the drilled hole As a method of constructing the main heat-resisting wall (1) by arranging continuously at regular intervals, 지반에 소정 깊이로 제1공(50)을 천공하고 상기 제1공(50)에 제1 관부재(51)를 삽입하여 1차 케이싱 작업을 수행하는 단계; Drilling a first hole (50) to a predetermined depth in the ground and inserting a first pipe member (51) into the first hole (50) to perform a primary casing operation; 일측에 오목한 오목부(53)를 가지는 반월형 단면 구조로 이루어져 있으며 H 빔 엄지말뚝(10)이 삽입될 때 그 웨브가 지나면서 개방되는 슬릿(54)이 종방향으로 상기 오목부(53)에 형성되어 있는 제2 관부재(52)를 상기 제1 관부재(51)의 내부에 삽입하고 상기 제1 관부재(51)는 인발하여 제거하는 2차 케이싱 작업을 수행하는 단계; It consists of a half-wall-shaped cross-sectional structure having a concave concave part 53 on one side, and when the H beam thumb pile 10 is inserted, a slit 54 is formed in the concave part 53 in the longitudinal direction. Inserting a second pipe member (52) into the first pipe member (51) and performing a second casing operation to draw and remove the first pipe member (51); 상기 제1공(50)에 바로 인접하여 제2공(60)을 천공하고 상기 제2공(60)에 제3 관부재(61)를 삽입하는 3차 케이싱 작업을 수행하는 단계; Performing a third casing operation of drilling the second hole 60 immediately adjacent to the first hole 50 and inserting a third pipe member 61 into the second hole 60; H빔 엄지말뚝(10)이 삽입될 때 그 웨브가 지날 수 있도록 측면에 길이 방향으로 슬릿(64)이 형성되어 있는 제4 관부재(62)를 제3 관부재(61)의 내부에 삽입하고 상기 제3 관부재(61)를 인발하여 제거하는 4차 케이싱 작업을 수행하는 단계; When the H-beam thumb pile 10 is inserted, a fourth pipe member 62 having a slit 64 formed in the longitudinal direction is inserted into the third pipe member 61 so that the web can pass therethrough. Performing a fourth casing operation to draw and remove the third pipe member (61); 상기 제4 관부재(62)의 슬릿(64)과 상기 제2 관부재(52)의 슬릿(54)이 서로 마주보아 연통되도록 한 상태에서 상기 제1공(50)과 제2공(60)에 걸쳐서 H빔 엄지말뚝(10)을 삽입하는 단계; The first hole 50 and the second hole 60 in a state in which the slit 64 of the fourth pipe member 62 and the slit 54 of the second pipe member 52 face each other and communicate with each other. Inserting the H-beam thumb pile 10 over; 제2 관부재(52)에 충진재(31)를 타설하고 양생되기 전에 제2 관부재(52)를 인발하여 제거하는 단계; 및 Pouring the filler 31 onto the second pipe member 52 and drawing and removing the second pipe member 52 before curing; And 상기 충진재(31)가 소정 강도 이상으로 양생된 후 제4 관부재(62)를 인발하여 제거하는 단계를 포함함으로써 H빔 엄지말뚝(10)의 일부분만이 충진재(31) 내에 매립되는 구조를 가지도록 말뚝 유닛(2)을 시공하고, After the filler 31 is hardened to a predetermined strength or more, a step of drawing and removing the fourth pipe member 62 has a structure in which only a part of the H beam thumb pile 10 is embedded in the filler 31. Construction pile unit (2), 상기 말뚝 유닛(2)을, H빔 엄지말뚝이 포함되어 있지 아니한 말뚝 유닛(3)의 소정 간격 사이에 배치하는 것을 특징으로 하는 주열식 흙막이 벽체 시공방법.The pile unit (2) is arranged between the predetermined intervals of the pile unit (3) that does not contain the H-beam thumb piles. 지반에 천공된 소정 깊이의 구멍에 H빔 엄지말뚝을 설치하고 그 주변으로 충진재(31)를 채워서 형성한 말뚝 유닛(2)과, 천공된 구멍에 충진재만을 채워서 형성한 말뚝 유닛(3)을 이웃하게 일정간격으로 연속 배치하여 주열식 흙막이 벽체(1)를 시공하는 방법으로서, The pile unit 2 formed by installing the H-beam thumb pile in a hole having a predetermined depth drilled into the ground and filling the filler 31 around the pile, and the pile unit 3 formed by filling only the filler in the drilled hole As a method of constructing the main heat-resisting wall (1) by arranging continuously at regular intervals, 지반에 소정 깊이로 제1공(50)을 천공하고 상기 제1공(50)에 제1 관부재(51)를 삽입하여 1차 케이싱 작업을 수행하는 단계; Drilling a first hole (50) to a predetermined depth in the ground and inserting a first pipe member (51) into the first hole (50) to perform a primary casing operation; 일측에 오목한 오목부(53)를 가지는 반월형 단면 구조로 이루어져 있으며 H빔 엄지말뚝(10)이 삽입될 때 그 웨브가 지나면서 개방되는 슬릿(54)이 종방향으로 상기 오목부(53)에 형성되어 있는 제2 관부재(52)를 상기 제1 관부재(51)의 내부에 삽입하고 상기 제1 관부재(51)는 인발하여 제거하는 2차 케이싱 작업을 수행하는 단계; It consists of a half-wall-shaped cross-sectional structure having a concave concave portion 53 on one side, and when the H-beam thumb pile 10 is inserted, a slit 54 is formed in the concave portion 53 in the longitudinal direction. Inserting a second pipe member (52) into the first pipe member (51) and performing a second casing operation to draw and remove the first pipe member (51); 상기 제1공(50)에 바로 인접하여 제2공(60)을 천공하고 상기 제2공(60)에 제3 관부재(61)를 삽입하는 3차 케이싱 작업을 수행하는 단계; Performing a third casing operation of drilling the second hole 60 immediately adjacent to the first hole 50 and inserting a third pipe member 61 into the second hole 60; H빔 엄지말뚝(10)이 삽입될 때 그 웨브가 지날 수 있도록 측면에 길이 방향으로 슬릿(64)이 형성되어 있는 제4 관부재(62)를 제3 관부재(61)의 내부에 삽입하고 상기 제3 관부재(61)를 인발하여 제거하는 4차 케이싱 작업을 수행하는 단계; When the H-beam thumb pile 10 is inserted, a fourth pipe member 62 having a slit 64 formed in the longitudinal direction is inserted into the third pipe member 61 so that the web can pass therethrough. Performing a fourth casing operation to draw and remove the third pipe member (61); 상기 제4 관부재(62)의 슬릿(64)과 상기 제2 관부재(52)의 슬릿(54)이 서로 마주보아 연통되도록 한 상태에서 상기 제1공(50)과 제2공(60)에 걸쳐서 H빔 엄지말뚝(10)을 삽입하는 단계; The first hole 50 and the second hole 60 in a state in which the slit 64 of the fourth pipe member 62 and the slit 54 of the second pipe member 52 face each other and communicate with each other. Inserting the H-beam thumb pile 10 over; 제2 관부재(52) 및 제4 관부재(62)에 충진재(31)를 타설하고, 상기 충진재(31)가 양생되기 전에 제2 관부재(52) 및 제4 관부재(62)를 인발하여 제거하는 단계를 포함함으로써 2개의 구멍을 그 일부가 서로 겹치게 연속하여 천공하고 그 천공된 구멍에 H빔 엄지말뚝(10)이 걸쳐져서 배치되어 충진재(31) 내에 매립되는 구조를 가지도록 말뚝 유닛(2)을 시공하고, The filler 31 is poured into the second pipe member 52 and the fourth pipe member 62, and the second pipe member 52 and the fourth pipe member 62 are drawn out before the filler 31 is cured. And a step of drilling two holes so that a part thereof overlaps each other continuously, and the H-beam thumb pile 10 is disposed in the perforated hole so as to have a structure embedded in the filler 31. (2) construction, 상기 말뚝 유닛(2)을, H빔 엄지말뚝이 포함되어 있지 아니한 말뚝 유닛(3)의 소정 간격 사이에 배치하는 것을 특징으로 하는 주열식 흙막이 벽체 시공방법. The pile unit (2) is arranged between the predetermined intervals of the pile unit (3) that does not contain the H-beam thumb piles.
KR1020060000678A 2006-01-03 2006-01-03 Method for constructing retaining wall having h-beam KR100691890B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060000678A KR100691890B1 (en) 2006-01-03 2006-01-03 Method for constructing retaining wall having h-beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060000678A KR100691890B1 (en) 2006-01-03 2006-01-03 Method for constructing retaining wall having h-beam

Publications (1)

Publication Number Publication Date
KR100691890B1 true KR100691890B1 (en) 2007-03-09

Family

ID=38102892

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060000678A KR100691890B1 (en) 2006-01-03 2006-01-03 Method for constructing retaining wall having h-beam

Country Status (1)

Country Link
KR (1) KR100691890B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101190877B1 (en) 2011-02-09 2012-10-15 무풍건설주식회사 The ground improvement device for cutoff wall and earths wall
KR20170018524A (en) * 2015-08-10 2017-02-20 주식회사 스틸텍 A method of construction for retaining wall
CN107882211A (en) * 2017-12-15 2018-04-06 赵建敏 Constraint compound wall structure for building
KR20180093358A (en) 2017-02-13 2018-08-22 주식회사 스틸텍 Slot casing with spacer and a method of construction for retaining wall using slot casing
KR20190092355A (en) * 2019-07-29 2019-08-07 박강호 An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101190877B1 (en) 2011-02-09 2012-10-15 무풍건설주식회사 The ground improvement device for cutoff wall and earths wall
KR20170018524A (en) * 2015-08-10 2017-02-20 주식회사 스틸텍 A method of construction for retaining wall
KR101711393B1 (en) * 2015-08-10 2017-03-02 황문삼 A method of construction for retaining wall
KR20180093358A (en) 2017-02-13 2018-08-22 주식회사 스틸텍 Slot casing with spacer and a method of construction for retaining wall using slot casing
CN107882211A (en) * 2017-12-15 2018-04-06 赵建敏 Constraint compound wall structure for building
KR20190092355A (en) * 2019-07-29 2019-08-07 박강호 An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same
KR102078794B1 (en) * 2019-07-29 2020-02-18 박강호 An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same

Similar Documents

Publication Publication Date Title
KR100782007B1 (en) Construction method of a earth-protection walls
KR200424432Y1 (en) Direct punching simultaneous poruing equipment
KR102097855B1 (en) Self reliance earth retaining construction method having prestress introduced of Double I Beam
KR101750273B1 (en) Tunnel Reinforcement structure and Tunnel Reinforcement methods using the same
KR100691890B1 (en) Method for constructing retaining wall having h-beam
KR101676814B1 (en) CFT pile Construction Method and the Shoring Method using the same file
KR101812265B1 (en) A Foundation Method Of Continuous and Cut Off wall By Overlap Casing
KR102003448B1 (en) Reinforced solider pile apparatus of long span&#39;s soil retaining wall
KR20140055639A (en) A execution method of architecture beam
KR100989853B1 (en) piling location fixing apparatus for cast in place concrete pile wall
KR20180124795A (en) An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same
KR101674656B1 (en) CIP retaining wall with steel tube
KR102325623B1 (en) Construction method of retaining wall
KR20080076015A (en) Retaining wall using pier unit having big h-beam
KR102233572B1 (en) Inverse casing for perforating ground bore and inverse casing manufacturing method thereof
KR101506163B1 (en) the improved cast injected concrete pile structure using automatic expanded rebar and quick-gelled injection and the reinforced steel withdrawal method using the same
KR101807366B1 (en) A Foundation Method Of Continuous and Cut Off wall By Overlap Casing
KR102239089B1 (en) Underaround continued wall structure using casing and pile continuous connection and method therefor
KR101254189B1 (en) Directional grouting method and device
KR20190137432A (en) Soil retaining wall for phc pile
KR101517884B1 (en) Construction method for wall structure of underground using the semicircular sheet pile
KR20080076013A (en) Method for constructing pier unit having h-beam
KR101025179B1 (en) Reinforcement assembly and c.i.p. construction method
KR20120049602A (en) Temporary retaining wall and constructing method thereof
KR102342510B1 (en) Overlap cylindrical member for construction of continuous and cut off wall

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120113

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20130115

Year of fee payment: 7

LAPS Lapse due to unpaid annual fee