KR100691890B1 - Method for constructing retaining wall having h-beam - Google Patents
Method for constructing retaining wall having h-beam Download PDFInfo
- Publication number
- KR100691890B1 KR100691890B1 KR1020060000678A KR20060000678A KR100691890B1 KR 100691890 B1 KR100691890 B1 KR 100691890B1 KR 1020060000678 A KR1020060000678 A KR 1020060000678A KR 20060000678 A KR20060000678 A KR 20060000678A KR 100691890 B1 KR100691890 B1 KR 100691890B1
- Authority
- KR
- South Korea
- Prior art keywords
- pile
- pipe member
- hole
- filler
- unit
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/20—Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2200/00—Geometrical or physical properties
- E02D2200/16—Shapes
- E02D2200/1685—Shapes cylindrical
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
도 1은 본 발명의 일실시예에 따라 시공된 주열식 흙막이 벽체의 개략적인 평면도이다. 1 is a schematic plan view of a columnar wall structure constructed according to an embodiment of the present invention.
도 2a 내지 도 2f는 각각 본 발명에 따라 말뚝 유닛용 구멍을 연속 천공하여 H빔 엄지말뚝을 배치하여 말뚝 유닛을 시공하는 방법의 각 시공단계를 보여주는 도면이다. Figure 2a to 2f is a view showing each construction step of the method for constructing the pile unit by arranging the H-beam thumb pile by continuously drilling holes for the pile unit according to the present invention, respectively.
도 3은 제1공 및 제2공에 모두 충진재를 채운 후 제2 관부재와 제4 관부재를 모두 인발하여 제거한 상태를 보여주는 평면도이다. 3 is a plan view showing a state in which both the second tube member and the fourth tube member are drawn and removed after filling the filler in both the first and second holes.
도 4는 도 3에 도시된 구성의 말뚝 유닛을 이용하여 시공된 주열식 흙막이 벽체와 콘크리트 지하 벽체가 합성된 상태의 일예를 보여주는 개략적인 평면도이다. FIG. 4 is a schematic plan view showing an example of a state in which the columnar wall and the concrete underground wall constructed by using the pile unit having the configuration shown in FIG.
도 5는 제1공에만 충진재를 채운 후 제2 관부재와 제4 관부재를 모두 인발하여 제거한 상태를 보여주는 평면도이다. 5 is a plan view showing a state in which both the second pipe member and the fourth pipe member are removed by filling only the first hole and then removed.
도 6은 도 5에 도시된 구성의 말뚝 유닛을 이용하여 시공된 주열식 흙막이 벽체의 개략적인 평면도이다. FIG. 6 is a schematic plan view of a columnar wall structure constructed using a pile unit having the configuration shown in FIG. 5. FIG.
도 7a 내지 도 7c는 각각 도 6에 도시된 주열식 흙막이 벽체에 접하여 콘크 리트 지하 벽체가 시공될 때, H빔 엄지말뚝의 일부분이 상기 충진재 내에 매립되어 있는 구조의 말뚝 유닛을 포함하는 주열식 흙막이 벽체에서 H빔 엄지말뚝의 활용 방법 예를 보여주는 평면도이다. 7A to 7C show a sequential mudstone including a pile unit having a structure in which a portion of the H-beam thumb pile is embedded in the filler when the concrete basement wall is constructed in contact with the sequential mud wall shown in FIG. 6, respectively. This is a plan view showing an example of the use of the H beam thumb pile in the wall.
도 8은 종래의 일반적인 엄지말뚝 매립형 말뚝 유닛의 개략적인 평면도이다, 8 is a schematic plan view of a conventional general pile pile buried pile unit,
도 9는 종래의 엄지말뚝 매립형 말뚝 유닛을 이용한 주열식 흙막이 벽체의 개략적인 평면도이다. FIG. 9 is a schematic plan view of a main row soil wall using a conventional thumb pile embedded pile unit. FIG.
도 10은 종래의 엄지말뚝 매립형 말뚝 유닛을 이용한 주열식 흙막이 벽체에 콘크리트 지하 벽체가 합성되어 있는 형태를 보여주는 평면도가 도시되어 있는데,FIG. 10 is a plan view showing a form in which a concrete underground wall is synthesized in a main row wall using a conventional pile pile pile unit.
<도면의 주요 부분에 대한 부호의 설명> <Explanation of symbols for the main parts of the drawings>
2, 3 : 말뚝 유닛2, 3: pile unit
10 : H빔 엄지말뚝10: H beam thumb pile
본 발명은 엄지말뚝 매립형 말뚝 유닛의 시공방법 및 이를 이용한 주열식 흙막이 벽체의 시공방법에 관한 것으로서, 구체적으로는 지반에 말뚝 유닛용 구멍을 천공할 때 2개의 구멍을 일부 겹치게 천공하고 상기 구멍에 걸쳐서 종전 보다 더 큰 엄지말뚝을 설치함으로써 말뚝의 강성을 증가시킬 수 있으며, 주열식 흙막이 벽 체에 사용될 때 엄지말뚝이 지하 벽체의 구조재 등으로 활용될 수 있도록 시공하는 엄지말뚝 매립형 말뚝 유닛의 시공방법 및 이를 이용한 주열식 흙막이 벽체의 시공방법에 관한 것이다. The present invention relates to a method of constructing a pile pile buried pile unit and a method of constructing a heat-retaining wall using the same, and more specifically, when drilling a hole for a pile unit in the ground, two holes are partially overlapped and over the holes. By installing a larger thumb pile than before, the rigidity of the pile can be increased, and the construction method of the thumb pile buried pile unit, which is constructed so that the thumb pile can be used as a structural material of the underground wall when used in the heat-stacking wall, and the same It relates to a construction method of the column-style soil wall used.
도 8에는 종래의 일반적인 엄지말뚝 매립형 말뚝 유닛(120)의 개략적인 평면도가 도시되어 있는데, 도면에 도시된 것처럼 엄지말뚝 매립형 말뚝 유닛(120)은 지중에 수직하게 천공한 후 그 천공된 구멍에 엄지말뚝(101)을 설치하고, 천공된 구멍 내에 위치한 상기 엄지말뚝(101) 주위에 소일 시멘트나 콘크리트, 또는 토사 등의 충진재(102)로 채우는 구조로 이루어져 있다. 엄지말뚝(101)으로는 H빔이 주로 사용된다. FIG. 8 is a schematic plan view of a conventional general thumb pile embedded
이와 같은 엄지말뚝 매립형 말뚝 유닛(120)은 다양한 용도로 사용될 수 있는데, 대표적으로는 주열식 흙막이 벽체에 사용된다. 도 9에는 위와 같은 엄지말뚝 매립형 말뚝 유닛(120)을 이용한 종래의 주열식 흙막이 벽체(103)의 개략적인 평면도가 도시되어 있다. 도면에 도시된 것처럼, 일반적으로 주열식 흙막이 벽체(103)는, 구조물의 지하 벽체 시공 위치 측면에서 지반을 천공한 후 엄지말뚝(101)을 소정 간격으로 설치하고 상기 엄지말뚝(101)의 주위에 소일 시멘트 또는 콘크리트 등의 충진재(102)를 타설하여 형성되는 말뚝 유닛(120)과, 엄지말뚝(101) 없이 충진재(102) 만을 타설하여 형성되는 말뚝 유닛(130)을 이웃하게 일정간격으로 연속 배치하여 주열식 흙막이 벽체(103)를 형성하는 구조를 가지고 있다. Such a pile pile buried
그런데 이러한 종래의 주열식 흙막이 벽체(103)에 있어서, 말뚝 유닛(120, 130)의 천공직경은 모두 일정하며 그 크기가 작기 때문에 흙막이 벽체의 강성이 충 분하지 아니하다는 것이 문제점으로 지적되어 왔다. 따라서 종래의 주열식 흙막이 벽체에 있어서는 지보공의 수직 간격을 넓히는데 한계가 있다. However, it has been pointed out that in such a conventional heat-
이와 같은 주열식 흙막이 벽체(103)로서 사용할 경우뿐만 아니라, 다른 용도로 엄지말뚝 매립형 말뚝 유닛(120)을 사용할 때에도, 엄지말뚝(101)을 더 크게 하는 것이 바람직한 경우가 많다. 더 큰 엄지말뚝(101)을 사용하기 위해서는 지중에 천공하는 구멍의 지름이 커질 수밖에 없는데, 단순히 구멍의 지름만을 더 증가시켜 천공 구멍을 크게 하게 되면 천공에 따른 공사비가 과도하게 되어 경제성이 저하되며, 더 나아가 충진재(102)를 채워야 하는 엄지말뚝(101) 주변의 공간이 불필요하게 커지게 되는 단점이 있다. It is often desirable to make the
한편, 이러한 주열식 흙막이 벽체(103)에서, 충진재(102)로 소일 시멘트 또는 콘크리트를 사용하는 경우, 충진재(102) 내에 매립되어 있는 상기 H빔 엄지말뚝(101)을 인발하여 재활용하는 것이 극히 어렵다. 반면에 H빔은 주로 강재로 만들어지고 고가이기 때문에 H빔 엄지말뚝(101)을 충진재(102) 속에 매립하여 사장시키는 것은 경제적으로도 매우 불리하다. 흙막이 벽체(103)에 바로 인접하여 지하 벽체를 시공하는 경우가 많은데, 종전에는 위와 같이 H빔 엄지말뚝(101)이 아깝게 사장되는 것을 고려하여 H빔 엄지말뚝(101)을 콘크리트 지하 벽체(100)의 강성을 증가시키는 구조 부재로 활용하려는 노력이 시도가 있다. On the other hand, in such a heat-
도 10에는 종래의 주열식 흙막이 벽체(103)에 콘크리트 지하 벽체(100)가 합성되어 있는 형태를 보여주는 평면도가 도시되어 있는데, 도 10에 도시된 것처럼 H빔 엄지말뚝(101)의 일측 플랜지 전면에 커넥션 볼트(110)를 미리 고정 설치해놓 고, 상기 커넥션 볼트(110)가 콘크리트 지하 벽체(100) 속에 매립되도록 함으로써, H빔 엄지말뚝(101)과 콘크리트 지하 벽체(100)를 일체로 만드는 것이 제안되고 있다. 그런데 위와 같은 종래 기술의 경우, H빔 엄지말뚝(101) 주변으로 충진재(102)가 타설되어 있으므로 H빔 엄지말뚝(101) 주변의 충진재(102)를 제거하는 과정에서 커넥션 볼트(110)가 손상될 가능성이 높아 터파기 공사가 완료되거나 또는 진행 중인 상태에서는 H빔 엄지말뚝(101)에 설치된 커넥션 볼트(110)를 노출시키는 것이 용이하지 아니하며, 그에 따라 작업성이 저하되는 문제가 생기게 된다. 이와 같이 H빔 엄지말뚝(101)을 지하 벽체(100)와 일체화시켜 지하 벽체(100)의 강성 보강용 구조 부재로 사용하려는 종전의 시도는 H빔 엄지말뚝(101)이 말뚝 유닛에서 충진재(102) 속에 완전히 매립되어 있기 때문에 실용화되기 어려운 상황이다. FIG. 10 is a plan view showing a structure in which a concrete
본 발명은 상기한 것처럼 엄지말뚝 매립형 말뚝 유닛을 시공함에 있어서, 단순히 천공 지름을 크게 하는 것이 아니라, 신규한 구성을 통하여 말뚝 유닛용 구멍을 서로 이웃하도록 연속하여 천공하고, H빔 엄지말뚝을 연속 천공된 2개의 구멍에 걸쳐서 설치할 수 있도록 함으로써, 더 큰 크기의 엄지말뚝을 설치할 수 있으면서도 천공 지름 확대에 따른 천공비의 증가를 방지할 수 있고 불필요한 충진재의 사용을 줄일 수 있도록 하는 말뚝 유닛의 시공방법을 제공하는 것을 목적으로 한다. In the present invention, when constructing the pile pile embedded pile unit as described above, not only to increase the diameter of the drilling, but also to continuously drill holes for the pile unit adjacent to each other through a novel configuration, and to continuously drill the H-beam thumb pile By installing over two holes, the pile unit can be installed to prevent the increase of the drilling cost due to the expansion of the drilling diameter and to reduce the use of unnecessary fillers. It aims to provide.
또한, 본 발명에서는 주열식 흙막이 벽체에서 말뚝 유닛을 시공함에 있어서, 위와 같은 본 발명의 말뚝 유닛 시공방법을 적용함으로써, 엄지말뚝이 말뚝 유닛에 서 소일 시멘트 또는 콘크리트 등의 충진재 속에 완전히 매립됨으로 인하여 고가의 엄지말뚝이 사장되는 등의 종래 기술이 가지고 있는 문제점들을 해결하는 것을 목적으로 한다. 구체적으로 본 발명에서는 말뚝 유닛에 포함된 엄지말뚝의 일부가 말뚝 유닛의 외부로 노출될 수 있도록 하여, 엄지말뚝을 사장시키지 아니하고 흙막이 벽체에 접하여 시공되는 구조물의 강성을 보강하는 구조 부재로서도 용이하게 활용될 수 있도록 하는 것을 목적으로 한다. In addition, in the present invention in the construction of the pile unit in the heat-stacking wall, by applying the pile unit construction method of the present invention as described above, the thumb pile is completely embedded in the filling material, such as soil cement or concrete in the pile unit, expensive An object of the present invention is to solve problems with the prior art, such as a thumb pile. Specifically, in the present invention, a part of the thumb pile included in the pile unit may be exposed to the outside of the pile unit, so that the thumb pile may be easily used as a structural member that reinforces the stiffness of the structure that is in contact with the earth wall without the thumb pile. The purpose is to make it possible.
또한, 본 발명은 주열식 흙막이 벽체를 시공함에 있어서 말뚝 유닛의 천공직경은 모두 일정하며 그 크기가 작기 때문에 충분한 강성의 흙막이 벽체를 이룰 수 없으며, 그에 따라 지보공의 수직 간격을 넓힐 수 없게 되는 종래 기술의 단점과 한계를 해결하는 것을 목적으로 한다. 구체적으로 본 발명은, 신규한 구성을 통하여 말뚝 유닛용 구멍을 연속하여 일부 겹치게 천공하고, 상기 연속 천공된 구멍에 걸쳐서 크기가 큰 H빔 엄지말뚝을 설치하여 말뚝 유닛을 형성하고, 이러한 말뚝 유닛을 포함한 구조로 흙막이 벽체를 시공함으로써, 큰 강성의 흙막이 벽체를 이루게 되며, 그에 따라 지보공의 수직 간격도 증대시켜 경제적인 시공을 이룰 수 있도록 하는 엄지말뚝 매립형 말뚝 유닛을 이용한 주열식 흙막이 벽체의 시공방법을 제공함을 목적으로 한다. In addition, the present invention is a conventional technology that can not form a sufficient rigid soil wall wall because the drilling diameter of the pile unit is all constant and small in the construction of the column-style soil wall wall, and thus can not widen the vertical gap of the jibo It aims to solve the shortcomings and limitations of the. Specifically, the present invention, through a novel configuration, the hole for the pile unit in succession partially overlapped, install a large H-beam thumb pile over the continuous perforated holes to form a pile unit, such a pile unit By constructing the retaining wall with the included structure, a large rigid retaining wall is formed, and accordingly, the vertical gap of the jibo is also increased to achieve economical construction. For the purpose of providing it.
상술한 목적을 위하여 본 발명에서는 지중에 천공된 구멍에 엄지말뚝이 삽입 설치되는 구조를 가지는 말뚝 유닛의 시공방법으로서, 지반에 소정 깊이로 제1공을 천공하고 상기 제1공에 제1 관부재를 삽입하여 1차 케이싱 작업을 수행하는 단계; 일측이 오목한 오목부를 가지는 반월형 단면 구조로 이루어져 있으며 H빔 엄지말뚝이 삽입될 때 그 웨브가 지나면서 개방되는 슬릿이 종방향(관부재의 길이방향)으로 상기 오목부에 형성되어 있는 제2 관부재를 상기 제1 관부재의 내부에 삽입하고 상기 제1 관부재는 인발하여 제거하는 2차 케이싱 작업을 수행하는 단계; 상기 제1공에 바로 인접하여 제2공을 천공하고 상기 제2공에 제3 관부재를 삽입하는 3차 케이싱 작업을 수행하는 단계; H빔 엄지말뚝이 삽입될 때 그 웨브가 지날 수 있도록 측면에 길이 방향으로 슬릿이 형성되어 있는 제4 관부재를 제3 관부재의 내부에 삽입하는 4차 케이싱 작업을 수행하는 단계; 및 상기 제4 관부재의 슬릿과 상기 제2 관부재의 슬릿이 서로 마주보아 연통되도록 한 상태에서 상기 제1공과 제2공에 걸쳐서 H빔 엄지말뚝을 삽입하는 단계를 포함함으로써 2개의 구멍을 그 일부가 서로 겹치게 연속하여 천공하고 그 천공된 구멍에 H빔 엄지말뚝이 걸쳐져서 배치되는 구조를 가지도록 말뚝 유닛을 시공하는 것을 특징으로 하는 엄지말뚝 매립형 말뚝 유닛의 시공방법이 제공된다. In the present invention for the above purpose, in the construction method of the pile unit having a structure in which the thumb pile is inserted into the hole drilled in the ground, the first hole is drilled to a predetermined depth in the ground and the first pipe member in the first hole Inserting to perform a primary casing operation; It consists of a half-wall-shaped cross-sectional structure having a concave portion on one side, and when the H-beam thumb pile is inserted, a slit which is opened as the web passes through is formed in the recess in the longitudinal direction (the longitudinal direction of the tube member). Inserting the inside of the first pipe member and performing a second casing operation to draw and remove the first pipe member; Performing a third casing operation of drilling a second hole immediately adjacent to the first hole and inserting a third pipe member into the second hole; Performing a fourth casing operation of inserting a fourth pipe member having a slit in the longitudinal direction to the inside of the third pipe member so that the web can pass when the H beam thumb pile is inserted; And inserting an H beam thumb pile over the first hole and the second hole with the slit of the fourth pipe member and the slit of the second pipe member facing each other. There is provided a method of constructing a pile pile buried pile unit, characterized in that the pile unit is constructed so that a portion is drilled continuously overlapping each other and the H-beam thumb pile is disposed in the drilled hole.
또한, 본 발명에서는 제1공과 제2공에 걸쳐서 H빔 엄지말뚝을 설치한 후에, 제2 관부재 내부에 충진재를 타설하고, 상기 충진재가 양생되기 전에 제2 관부재를 인발하여 제거하는 단계; 및 상기 충진재가 소정 강도 이상으로 양생된 후 제4 관부재를 인발하여 제거하는 단계를 포함함으로써 H빔 엄지말뚝의 일부분만이 말뚝 유닛의 충진재 내에 매립되는 구조를 가지도록 말뚝 유닛을 시공하는 것을 특징으로 하는 엄지말뚝 매립형 말뚝 유닛의 시공방법이 제공된다. In addition, in the present invention, after installing the H-beam thumb pile over the first hole and the second hole, the filler is placed inside the second pipe member, and the second pipe member is drawn and removed before the filler is cured; And drawing out and removing the fourth pipe member after the filler is cured to a predetermined strength or more, thereby constructing the pile unit such that only a portion of the H-beam thumb pile is embedded in the filler of the pile unit. Provided is a construction method of a thumb pile embedded pile unit.
또한 본 발명에서는, 제1공과 제2공에 걸쳐서 H빔 엄지말뚝을 설치한 후에, 제2 관부재 및 제4 관부재에 충진재를 타설하고 제2 관부재 및 제4 관부재를 인발하여 제거하는 단계를 포함함으로써 H빔 엄지말뚝의 전부가 말뚝 유닛의 충진재 내에 매립되는 구조를 가지도록 말뚝 유닛을 시공하는 것을 특징으로 하는 엄지말뚝 매립형 말뚝 유닛의 시공방법이 제공된다. In addition, in the present invention, after installing the H-beam thumb pile over the first hole and the second hole, the filler is poured into the second tube member and the fourth tube member, and the second tube member and the fourth tube member are drawn and removed. The method of constructing the pile pile buried pile unit, characterized in that the pile unit is constructed so that the whole of the H-beam thumb pile is embedded in the filler of the pile unit.
상기한 본 발명에 있어서, 제2 관부재는 오목부 내측으로 가이드 런을 형성하고 상기 가이드를 사이에 유입방지판을 삽입하여 상기 슬릿을 임시로 폐쇄하는 구성을 가지며; 상기 제1공과 제2공에 걸쳐서 H빔 엄지말뚝을 삽입하기에 앞서 상기 유입방지판을 제거하여 상기 슬릿을 개방하는 구조를 가질 수 있다. In the present invention described above, the second pipe member has a configuration in which a guide run is formed inside the recess, and the guide is inserted between the guides to temporarily close the slit; Prior to inserting the H beam thumb pile over the first hole and the second hole, the inlet preventing plate may be removed to open the slit.
또한 본 발명에서는, 지반에 천공된 소정 깊이의 구멍에 H빔 엄지말뚝을 설치하고 그 주변으로 충진재를 채워서 형성한 말뚝 유닛과, 단지 천공된 구멍에 충진재만을 채워서 형성한 말뚝 유닛을 이웃하게 일정간격으로 연속 배치하여 주열식 흙막이 벽체를 시공하는 방법으로서, 상기한 방법에 의하여 H빔 엄지말뚝의 일부분만이 충진재 내에 매립되는 구조를 가지도록 말뚝 유닛을 시공하고, 상기 말뚝 유닛을, H빔 엄지말뚝이 포함되어 있지 아니한 말뚝 유닛의 소정 간격 사이에 배치하는 것을 특징으로 하는 주열식 흙막이 벽체 시공방법이 제공된다.In addition, in the present invention, the pile unit is formed by installing the H-beam thumb pile in the hole of the predetermined depth perforated in the ground and filled the filler material around, and the pile unit formed by filling only the filler material in the perforated hole adjacent to a certain interval As a method of constructing a main heat-retaining wall by successive arrangement, the pile unit is constructed so that only a part of the H-beam thumb pile is embedded in the filler by the above-described method, and the pile unit is formed by the H-beam thumb pile. There is provided a method of constructing a staggered wall structure, which is arranged between predetermined intervals of a pile unit which is not included.
또한 본 발명에서는, 지반에 천공된 소정 깊이의 구멍에 H빔 엄지말뚝을 설치하고 그 주변으로 충진재를 채워서 형성한 말뚝 유닛과, 단지 천공된 구멍에 충진재만을 채워서 형성한 말뚝 유닛을 이웃하게 일정간격으로 연속 배치하여 주열식 흙막이 벽체를 시공하는 방법으로서, 상기한 방법에 의하여 일부가 겹쳐진 채로 연 속 천공된 구멍에 H빔 엄지말뚝이 걸쳐진 형태로 배치되어 H빔 엄지말뚝 전체가 충진재 내에 매립되는 구조를 가지도록 말뚝 유닛을 시공하고, 상기 말뚝 유닛을, H빔 엄지말뚝이 포함되어 있지 아니한 말뚝 유닛의 소정 간격 사이에 배치하는 것을 특징으로 하는 주열식 흙막이 벽체 시공방법이 제공된다.In addition, in the present invention, the pile unit is formed by installing the H-beam thumb pile in the hole of the predetermined depth perforated in the ground and filled the filler material around, and the pile unit formed by filling only the filler material in the perforated hole adjacent to a certain interval As a method of constructing a heat-retaining wall structure by continuously arranging the structure, the H-beam thumb pile is disposed in the form of the H-beam thumb pile in a continuous perforated hole with a part overlapped by the above method, so that the entire H-beam pile is embedded in the filler. A piling unit wall construction method is provided, wherein the pile unit is installed to be provided, and the pile unit is disposed between predetermined intervals of the pile unit not including the H beam thumb pile.
이하, 첨부된 예시도면을 참조하여 본 발명에 따른 엄지말뚝 매립형 말뚝 유닛의 시공방법과, 이를 이용한 주열식 흙막이 벽체의 시공방법에 대하여 상세히 설명한다. 아래의 설명에서 상기 엄지말뚝의 일예로서 "H빔 엄지말뚝"을 예시하고 있으나, 본 발명의 엄지말뚝은 "H빔" 형상에 한정되는 것은 아니다. 또한, 아래에서는 본 발명에 따라 시공된 말뚝 유닛의 사용예로서, 주열식 흙막이 벽체를 예시하고 있고, 이에 대하여 특허청구하고 있으나, 본 발명에 따른 말뚝 유닛의 시공방법에 의하여 시공된 말뚝 유닛이 사용되는 예는 반드시 주열식 흙막이 벽체에만 한정되는 것은 아니다. Hereinafter, with reference to the accompanying drawings will be described in detail the construction method of the pile pile buried pile unit according to the present invention, and the construction method of the column-type mud wall using the same. In the following description, but one example of the thumb pile "H beam thumb pile" is illustrated, but the thumb pile of the present invention is not limited to the "H beam" shape. In addition, below, as an example of the use of the pile unit constructed in accordance with the present invention, it is illustrated that the main heat-sucking wall, the patent claim for this, but the pile unit constructed by the construction method of the pile unit according to the present invention is used Examples are not necessarily limited to staggered wall.
도 1에는 본 발명의 일실시예에 따라 시공된 주열식 흙막이 벽체(1)의 개략적인 평면도가 도시되어 있다. 도면에 도시된 본 발명의 일실시예에 따른 주열식 흙막이 벽체(1)는 다수개의 말뚝 유닛(2, 3)이 연속적으로 배치되어 형성되는데, H빔 엄지말뚝(10)이 삽입되지 않고 단순히 충진재(31)만으로 이루어진 말뚝 유닛(3)의 사이에 소정 간격으로 상기 말뚝 유닛(3)의 경우보다 더 큰 H빔 엄지말뚝(10)이 충진재(31)에 매립되어 있는 구조의 말뚝 유닛(2)이 배치되는 구조를 가진다. 즉, 도면에 도시된 것처럼, H빔 엄지말뚝(10)이 충진재(31)에 매립되어 있는 구조의 말 뚝 유닛(2)은 제1공과 제2공이 말뚝 유닛 배치면에 수직한 방향으로 구멍의 일부가 겹치도록 천공되어 상기 제1공과 제2공에 걸쳐서 H빔 엄지말뚝(10)이 배치되는 구조를 가지는 것이다. FIG. 1 is a schematic plan view of a
이와 같이, 단순히 충진재(31)만으로 이루어진 말뚝 유닛(3)보다 더 큰 구멍을 가지도록 천공하고 종전에 상기 말뚝 유닛(3)에 삽입되던 것보다 더 큰 H빔 엄지말뚝(10)을 삽입하여 말뚝 유닛(2)을 형성하게 되면, 더 커진 H빔 엄지말뚝(10)의 강성에 의하여 주열식 흙막이 벽체(1)의 강성을 더욱 증가시킬 수 있는 효과가 있다. 또한 큰 강성의 흙막이 벽체를 이루게 됨에 따라 지보공의 수직 간격도 증대시켜 경제적인 시공을 이룰 수 있게 된다. 아울러 말뚝 유닛(2)에 매립된 상기 H빔 엄지말뚝(10)을, 주열식 흙막이 벽체(1)에 인접하여 시공되는 콘크리트 지하 벽체(100)의 구조 부재로서 활용하는 경우에는, 더 커진 H빔 엄지말뚝(10)의 증가된 강성만큼 콘크리트 지하 벽체(100)의 두께 등을 줄일 수 있게 되어 더욱 경제적인 시공이 가능하게 된다. As such, it is simply perforated to have a larger hole than the
그런데 위와 같이 더 커진 H빔 엄지말뚝(10)을 가진 말뚝 유닛(2)을 시공하기 위해서는 그만큼 천공단면도 커야 하는데, 만일 단순히 오거의 직경을 크게 하여 천공하는 것은 결코 바람직하지 않다. 왜냐하면 단순히 오거의 직경을 키워 천공단면을 증가시키게 되면 지반 천공에 소요되는 비용이 급격하게 증가하게 되기 때문이다. 또한 위와 같은 경우 H빔 엄지말뚝(10) 주위에 채워질 충진재(31)의 양도 과도하게 증가하게 되고 그에 따라 시공비가 상승하는 문제점도 있다. 그 뿐만 아니라, H빔 엄지말뚝(10)이 설치되지 아니하는 말뚝 유닛(3)의 시공을 위한 오 거와는 다른 크기의 직경을 가지는 오거를 별도로 준비하여야 하고 서로 다른 크기의 오거를 번갈아 투입하여야 하므로, 그 만큼 비용이 증가하게 될 뿐만 아니라 천공작업도 번거롭게 되어 작업성이 매우 저하되는 문제점이 발생하게 된다. However, in order to construct the
이러한 문제점을 해결하기 위하여 본 발명에서는 다음과 같은 방법 단계에 의하여 더 커진 H빔 엄지말뚝(10)을 구비한 말뚝 유닛(2)을 시공한다. 도 2a 내지 도 2f에는 본 발명에 따른 말뚝 유닛의 시공단계에 포함된 각 단계를 설명하기 위한 측면도 내지 평면도가 도시되어 있다. In order to solve this problem, the present invention constructs a
우선 도 2a의 수직 단면도에 도시된 것처럼 오거 등의 천공기(70)를 이용하여 지반을 소정 깊이로 천공하여 제1공(50)을 형성한다. 천공기(70)가 지반 내로 굴진할 때 제1공(50)에는 제1 관부재(51)를 삽입하여 1차 케이싱 작업을 하게 된다. 천공이 종료되어 제1공(50)에 제1 관부재(51)가 삽입 설치되면 도 2b의 수직 단면도에 도시된 것처럼 제1 관부재(51)의 내부에 또다른 제2 관부재(52)를 삽입하고 제1 관부재(51)를 인발하여 제거하는 2차 케이싱 작업을 하게 된다. 도 2c에는 2차 케이싱 작업을 완료하여 제1공(50)에 제2 관부재(52)만이 설치되어 있는 상태의 평면도가 도시되어 있다. First, as shown in the vertical cross-sectional view of FIG. 2A, the ground is drilled to a predetermined depth by using a
본 발명에 있어서 제2 관부재(52)는 도 2c에 도시된 것과 같이 그 일측이 오목한 오목부(53)를 가지는 반월형 단면 구조로 이루어져 있다. 예를 들면 관부재 일측에서 소정 길이의 원호 부분을 종방향(관부재의 길이방향)으로 절단한 후 이를 뒤집어서 다시 붙이는 방법 등을 통하여 오목부(53)를 가지는 반월형 단면의 관부재를 용이하게 제작할 수 있다. 후술하는 것처럼 H빔 엄지말뚝(10)을 삽입할 때 엄지말뚝(10)의 웨브(11)가 제2 관부재(51)를 관통할 수 있도록 상기 오목부(53)의 중간에는 종방향으로 슬릿(54)이 형성되어 있다. 경우에 따라서는 후술하는 것처럼 제1공에 접하여 제2공을 천공할 때 토사가 상기 슬릿(54)을 통하여 제2 관부재(52)의 내부로 유입될 수 있는데, 이를 방지하기 위한 유입방지판(55)을 임시로 설치할 수도 있다. 도면에 도시된 실시예에는 상기 유입방지판(55)을 위로 뽑아서 제거하기 용이하도록 오목부(53) 내측으로 가이드 런(56)을 형성하고 상기 가이드 런(56) 사이에 유입방지판(55)을 삽입하여, 유입방지판(55)을 가이드 런(56)으로부터 슬라이딩시켜 제거할 수 있도록 구성되어 있다. In the present invention, the
이후 제2 관부재(52)의 오목부(53)에 인접하여 천공기(70)를 이용하여 지반에 제2공(60)을 천공한다. 종래에는 지반에 구멍을 연속적으로 천공할 수가 없었다. 즉, 위와 같이 제1공(50)을 천공한 후에 바로 인접하여 제2공(60)을 천공하는 것이 가능하지 아니하였다. 왜냐하면 제2공을 천공하는 과정에서 지반의 토사가 무너져서 제1공으로 유입되기 때문이다. 그러나 본 발명에서는 제1공(50)에 미리 제2 관부재(52)를 설치해둔 상태이고, 특히 제2 관부재(52)의 측면에는 제2공을 천공할 수 있는 공간을 확보하도록 오목부(53)가 형성되어 있으므로 천공과정에서 지반 토사가 무너져서 제1공으로 유입되는 것이 방지되므로 제1공(50)에 바로 인접하여 제2공(60)을 천공할 수 있게 된다. 이와 같이 천공기가 제1공(50)에 이웃한 위치에서 지반 내로 굴진하여 제2공(60)을 형성할 때에는 도 2d의 평면도에 도시된 것처럼 제2공(60)에는 제3 관부재(61)를 삽입하는 3차 케이싱 작업을 병행하게 된다. Thereafter, the
이와 같이 제3 관부재(61)가 제2공(60)에 삽입 설치된 상태에서 후속하여 제3 관부재(61)의 내부에 제4 관부재(62)를 삽입하고, 제3 관부재(61)는 인발하여 제거하는 4차 케이싱 작업을 수행한다. 도 2e에는 제4 관부재(62)를 설치한 후 제3 관부재(61)를 인발한 상태를 보여주는 평면도가 도시되어 있다. 도면에 도시된 것처럼 제4 관부재(62)에서 상기 제1공(50)의 제2 관부재(52) 방향 측면에는 상기 제2 관부재(52)와 마찬가지로 종방향으로 길게 슬릿(64)이 형성되며, 상기 제4 관부재(62)는 그 슬릿(64)과 상기 제2 관부재(52)의 슬릿(54)이 서로 마주보아 연통되도록 배치된다. 상기 제4 관부재(62)를 설치한 후에는 도 2f의 평면도에 도시된 것처럼 상기 제1공(50)과 제2공(60)에 걸쳐서 H빔 엄지말뚝(10)을 삽입한다. 본 발명에서는 상기한 것처럼 제2 관부재(52)와 제4 관부재(62)의 측면에 각각 슬릿(54, 64)이 마주보도록 형성되어 있으므로 H빔 엄지말뚝(10)의 웨브(11)가 상기 슬릿(54, 64)을 통과하여 양측의 제1공(50)과 제2공(60)에 걸쳐서 배치될 수 있다. 앞서 설명한 것처럼 제2 관부재(52)의 슬릿(54)이 유입방지판(55)에 의하여 막혀 있는 경우에는 유입방지판(55)을 제거하여 슬릿(54, 64)이 서로 연통되도록 한 후에 H빔 엄지말뚝(10)을 삽입 설치한다. In this way, while the
이와 같은 구성을 통하여, 말뚝 유닛의 천공지름을 키우지 않고서도, 2개의 구멍을 연속하여 천공하여 종전보다 더 큰 크기의 H빔 엄지말뚝(10)을 설치할 수 있게 된다. Through such a configuration, it is possible to install the H-
이미 기술하였지만, 본 발명에 따른 말뚝 유닛의 시공방법에 의하여 시공된 말뚝 유닛이 사용되는 예가 반드시 주열식 흙막이 벽체에 한정되는 것은 아니다. 즉, 도 2f에 도시된 상태에서 제1공(50)과 제2공(60)에 충진재로서 토사를 채우고 제2 관부재(52) 및 제4 관부재(62)를 각각 인발하여 제거하여 사용할 수 있다. 이 경우 추후 H빔 엄지말뚝(10)을 인발하여 재활용하기가 용이하게 된다. Although already described, the example in which the pile unit constructed by the construction method of the pile unit according to the present invention is used is not necessarily limited to the main heating wall. That is, in the state shown in Figure 2f to fill the earth and sand as the filling material in the
만일 도 1에 도시된 것과 같은 주열식 흙막이 벽체(1)를 시공하는 경우에는 후속하여 다음과 같은 단계들을 진행한다. In the case of constructing the
H빔 엄지말뚝(10)이 설치되면 제2 관부재(52) 및 제4 관부재(62) 내에 각각 소일 시멘트 또는 콘크리트와 같은 충진재(31)를 타설하여 H빔 엄지말뚝(10) 전체가 충진재(31) 속에 매립되도록 한다. 후속하여 상기 충진재(31)가 양생되기 전에 제2 관부재(52) 및 제4 관부재(62)를 각각 인발하여 제거한다. 도 3에는 위와 같은 과정을 통해 제2 관부재(52)와 제4 관부재(62)를 모두 인발하여 제거한 상태를 보여주는 평면도가 도시되어 있다. When the H
이와 같은 방법으로 말뚝 유닛(2)을 시공한 후에는 종래의 방법을 이용하여 상기 제1공(50)의 좌우측으로는 H빔 엄지말뚝(10)이 없는 통상의 말뚝 유닛(3)을 시공하여 말뚝 유닛(2, 3)이 연속하여 배치하도록 한다. 즉, 도 1에 도시된 것처럼 제1공(50)과 제2공(60)이 겹치게 천공되어 그 내부의 충진재(31) 내에 H빔 엄지말뚝(10)이 상기 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)과, 그 좌우측으로는 H빔 엄지말뚝(10)이 충진재(31) 내에 매립되어 있지 아니한 구조의 말뚝 유닛(3)이 연속적으로 배치되어 본 발명에 따른 주열식 흙막이 벽체(1)를 형성하게 된다. 이와 같이, H빔 엄지말뚝(10)의 전부가 상기 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)을 포함하는 본 발명의 주열식 흙막이 벽체(1)는 다양한 구성 을 이용하여 상기 H빔 엄지말뚝(10)을 구조재로서 활용할 수 있게 된다. After the
도 4에는 본 발명에 따라 시공된 주열식 흙막이 벽체(1)에 접하여 콘크리트 지하 벽체(100)가 시공될 때, 도 3에 도시된 것과 같이 H빔 엄지말뚝(10)이 상기 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)에 전단연결재(110)를 설치하여 상기 전단연결재(110)를 콘크리트 지하 벽체(100)에 매립되도록 함으로써, 주열식 흙막이 벽체(1)와 콘크리트 지하 벽체(100)가 일체로 합성되도록 하는 실시예를 보여주는 평면도가 도시되어 있다. 4 shows the H-
지하 구조물을 시공하기 위해서는 도 1의 상태에서 말뚝 유닛(30, 31)의 전면 부분의 지반을 굴착하여 주열식 흙막이 벽체(1)에 접하여 콘크리트 지하 벽체(100)를 시공하게 된다. H빔 엄지말뚝(10)이 매립되어 있는 말뚝 유닛(2)의 경우, H빔 엄지말뚝(10)의 외면이 노출되고 그 노출면에는 전단연결재(110)가 설치된다. 후속하여 도 4에 도시된 것처럼 콘크리트 지하 벽체(100)가 시공될 때 H빔 엄지말뚝(10)의 노출 외면에 설치된 전단연결재(110)가 콘크리트 지하 벽체(100) 속에 매립되도록 콘크리트 지하 벽체(100)를 형성하게 되는 것이다. In order to construct an underground structure, the ground of the front part of the
한편, 도 2a 내지 도 2f에 도시된 단계에 후속하여 아래에 설명하는 단계를 더 수행함으로써, 제1공(50)과 제2공(60) 중의 어느 한 곳에만 충진재를 채우고 H빔 엄지말뚝(10)의 일부를 충진재 외부로 노출시켜 이를 지하 구조물의 벽체에 매립시키는 등과 같이 다른 용도로 사용할 수도 있다. Meanwhile, by further performing the steps described below after the steps shown in FIGS. 2A to 2F, the filler is filled in only one of the
즉, 도 2f에 도시된 단계를 통해 H빔 엄지말뚝(10)이 설치된 상태에서 제2 관부재(52)에는 충진재(31)를 타설하고, 충진재(31)가 양생되기 전에 제2 관부재 (52)를 인발하여 제거하고, 충진재(31)의 양생이 완료되면 제4 관부재(62) 역시 인발하여 제거한다. 도 5에는 위와 같은 과정을 통해 제2 관부재(52)와 제4 관부재(62)를 모두 인발하여 제거한 상태를 보여주는 평면도가 도시되어 있다. 제4 관부재(62)를 인발할 때, 충진재(31)가 제4 관부재(62)의 외면에 붙어 제4 관부재(62)의 인발이 어려워지는 것을 방지하기 위하여 미리 제4 관부재(62) 외면에 이탈제 등을 도포하는 것이 바람직하며, 도면에 도시되지 아니하였지만, 경우에 따라서는 제1공(50)에 채워진 충진재(31)가 양생되면서 붙게 되는 영역의 경계면을 따라 제4 관부재(62)의 외부에 플라스틱 판재 등의 판부재를 미리 붙여 두고, 추후 제1공(50)의 충진재(31)가 양생되어 상기 판부재가 충진재(31)와 붙게 되면, 제4 관부재(62)를 비트는 등의 방법을 통해 상기 판부재가 충진재(31)에 붙어 있는 채로 제4 관부재(62)와는 분리되어 제4 관부재(62)만을 인발하도록 하는 방법도 취할 수 있다. That is, the
제4 관부재(62)까지 인발하여 제거하여 말뚝 유닛(2)을 시공한 후에는 종래의 방법을 이용하여 상기 제1공(50)의 좌우측으로는 H빔 엄지말뚝(10)이 없는 통상의 말뚝 유닛(3)을 시공하여 말뚝 유닛(2, 3)이 연속하여 배치하도록 한다. 도 6에는 H빔 엄지말뚝(10)의 일부분이 상기 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)과, 그 좌우측으로는 H빔 엄지말뚝(10)이 충진재(31) 내에 매립되어 있지 아니한 구조의 말뚝 유닛(3)이 연속적으로 배치되어 본 발명의 일실시예에 따른 주열식 흙막이 벽체(1)를 형성한 상태의 평면도가 도시되어 있다. 도면에 도시된 실시예와 같이 H빔 엄지말뚝(10)의 일부분이 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)이, H빔 엄지말뚝(10)을 전혀 포함하고 있지 아니한 말뚝 유닛(3) 몇 개를 사이에 두고 반복하여 배치될 수 있다. After drawing up and removing the
이와 같이, H빔 엄지말뚝(10)의 일부분이 상기 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)을 포함하는 주열식 흙막이 벽체(1)는 다양한 구성을 이용하여 상기 H빔 엄지말뚝(10)을 구조재로서 활용할 수 있게 된다. As described above, the main
도 7a 내지 도 7c에는 주열식 흙막이 벽체(1)에 접하여 콘크리트 지하 벽체(100)가 시공될 때, H빔 엄지말뚝(10)의 일부분이 상기 충진재(31)내에 매립되어 있는 구조의 말뚝 유닛(2)을 포함하는 주열식 흙막이 벽체(10)에서 H빔 엄지말뚝(10)의 활용 방법의 다양한 실시예를 보여주는 평면도가 도시되어 있다. 7A to 7C, a pile unit having a structure in which a portion of the H-
지하 구조물을 시공하기 위해서는 도 6의 상태에서 제2공(61) 부분을 포함하여 말뚝 유닛(30, 31)의 전면 부분의 지반을 굴착한 후 주열식 흙막이 벽체(1)에 접하여 콘크리트 지하 벽체(100)를 시공하게 된다. H빔 엄지말뚝(10)의 일부분이 충진재(31) 외부로 노출된 말뚝 유닛(2)의 경우, 도 7a 및 도 7b에 도시된 것처럼 콘크리트 지하 벽체(100)가 시공될 때 H빔 엄지말뚝(10)의 노출된 부분이 콘크리트 지하 벽체(100) 속에 매립되도록 할 수 있다. 이와 같은 경우, 콘크리트 지하 벽체(100) 속에 매립된 H빔 엄지말뚝(10) 부분은 콘크리트 지하 벽체(100) 자체의 강성을 보강하는 구조 부재로서 기능하게 되므로, 그에 맞추어 콘크리트 지하 벽체(100)의 두께를 줄이거나 그 내부에 배근되는 철근 등의 보강부재를 줄일 수 있어 경제적인 시공을 할 수 있게 된다. 특히 콘크리트 지하 벽체(100)의 두께가 감소되면 더 넓은 지하 공간을 확보할 수 있게 되는 장점이 발휘된다. 또한 H빔 엄지 말뚝(10)이 매립된 말뚝 유닛과 콘크리트 지하 벽체(100) 즉, 흙막이 벽체(1)와 콘크리트 지하 벽체(100)가 일체로 결합되어 합성효과를 발휘하게 되므로, 말뚝 유닛의 충진재(31) 속에 매립된 H빔 엄지말뚝(10) 부분도 사장되지 아니하고 콘크리트 지하 벽체(100)의 강성을 높여주는 유리한 기능을 가지게 된다. In order to construct the underground structure, the ground of the front part of the
또한 도 7c에 도시된 것처럼, 말뚝 유닛(2)의 충진재(31) 외부로 노출된 H빔 엄지말뚝(10)의 플랜지 내측으로 콘크리트 지하 벽체(100)를 시공할 수도 있는데, 이 경우 충진재(31) 외부로 노출된 H빔 엄지말뚝(10)의 일부분은 콘크리트 지하 벽체(100) 시공을 위한 거푸집을 설치하기 위한 지지대로도 사용할 수 있으므로 콘크리트 지하 벽체(100)의 시공이 더욱 용이하게 될 수 있다. In addition, as shown in FIG. 7C, the concrete
이상 살펴본 바와 같이, 본 발명에 있어서는 엄지말뚝 매립형 말뚝 유닛을 시공함에 있어서 단순히 천공 지름을 크게 하는 것이 아니라, 구멍을 서로 이웃하도록 연속하여 천공하고, H빔 엄지말뚝을 연속 천공된 2개의 구멍에 걸쳐서 설치할 수 있도록 함으로써, 더 큰 크기의 엄지말뚝을 설치할 수 있으면서도 천공 지름 확대에 따른 천공비의 증가를 방지할 수 있고 불필요한 충진재의 사용을 줄일 수 있게 된다. As described above, in the present invention, in constructing the thumb pile embedded pile unit, instead of simply increasing the punching diameter, the holes are continuously drilled so as to be adjacent to each other, and the H beam thumb pile is continuously spread over the two holes which are continuously punched. By making it possible to install a larger sized pile, it is possible to prevent an increase in the drilling rate due to the expansion of the drilling diameter and to reduce the use of unnecessary fillers.
특히, 주열식 흙막이 벽체의 말뚝 유닛을 시공할 때, 위와 같은 본 발명에 따른 말뚝 유닛의 시공방법을 적용할 수 있는데, 상기 H빔 엄지말뚝(10)이 삽입되지 아니한 소 직경의 말뚝 유닛(3)들 사이에 본 발명에 따라 H빔 엄지말뚝(10)이 삽입된 대 직경의 말뚝 유닛(2)을 소정 간격으로 혼합 배치하여 전체 흙막이 벽체를 구성하게 된다. 이러한 구조에서는 H빔 엄지말뚝(10)이 삽입된 대 직경의 말뚝 유닛(2)이 큰 강성을 발휘하게 때문에 지보공의 수직 방향 간격을 큰 폭으로 형성할 수 있으며, 그에 따라 시공을 용이하고 빠르게 진행할 수 있게 되는 장점이 있다. 특히, 큰 강성을 가지는 H빔 엄지말뚝(10)이 삽입된 대 직경의 말뚝 유닛(2)이 콘크리트 지하 벽체(100)에 대하여 큰 지지력을 발휘하기 때문에 콘크리트 지하 벽체(100)의 두께를 줄일 수 있으며, 그에 따라 콘크리트 지하 벽체(100) 시공비가 절감되고, 콘크리트 지하 벽체(100)가 차지하고 있던 면적이 줄어들어 더 넓은 지하 면적을 확보할 수 있게 되는 장점이 있다. In particular, when constructing the pile unit of the heat-stacking wall, it is possible to apply the construction method of the pile unit according to the present invention as above, the small diameter pile unit (3) is not inserted into the H-beam thumb pile (10) In accordance with the present invention, a large
또한, 본 발명에 의하면 제1 관부재(51), 반월형 단면 구조를 가지는 제2 관부재(52), 제3 관부재(61), 및 제4 관부재(62)를 이용하여 제1공(50)과 제2공(60)을 인접한 상태로 연속 천공하여 H빔 엄지말뚝(10)의 일부분만이 충진재(31)에 매립되어 있고 나머지 일부는 충진재(31) 외부로 노출되는 구조의 말뚝 유닛(2)을 경제적인 방법으로 용이하게 시공할 수 있게 된다. In addition, according to the present invention, the first tube (51), the
이러한 구조의 말뚝 유닛(2)을 포함하여 주열식 흙막이 벽체(1)를 시공하게 되면 자칫 사장될 수 있는 고가의 H빔 엄지말뚝(10)을 콘크리트 지하 벽체(100)의 강성을 증가시키는 구조부재로서 활용할 수 있게 되어 콘크리트 지하 벽체(100)를 경제적으로 시공할 수 있게 된다. 구체적으로 H빔 엄지말뚝(10)이 구조부재로서 활용되어 콘크리트 지하 벽체(100)에 대하여 큰 지지력을 발휘하기 때문에 콘크리트 지하 벽체(100)의 두께를 줄일 수 있으며, 그에 따라 콘크리트 지하 벽체(100) 시공비가 절감되고, 콘크리트 지하 벽체(100)가 차지하고 있던 면적이 줄어들어 더 넓은 지하 면적을 확보할 수 있게 되는 장점이 있다. Including the
특히 H빔 엄지말뚝(10)의 일부분만이 충진재(31)에 매립되어 있고 나머지 일부는 충진재(31) 외부로 노출되는 구조의 말뚝 유닛(2)을 이용하면 다양한 합성 구조를 형성할 수 있게 되는 장점이 있다. In particular, only a portion of the H-
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020060000678A KR100691890B1 (en) | 2006-01-03 | 2006-01-03 | Method for constructing retaining wall having h-beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020060000678A KR100691890B1 (en) | 2006-01-03 | 2006-01-03 | Method for constructing retaining wall having h-beam |
Publications (1)
Publication Number | Publication Date |
---|---|
KR100691890B1 true KR100691890B1 (en) | 2007-03-09 |
Family
ID=38102892
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020060000678A KR100691890B1 (en) | 2006-01-03 | 2006-01-03 | Method for constructing retaining wall having h-beam |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100691890B1 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101190877B1 (en) | 2011-02-09 | 2012-10-15 | 무풍건설주식회사 | The ground improvement device for cutoff wall and earths wall |
KR20170018524A (en) * | 2015-08-10 | 2017-02-20 | 주식회사 스틸텍 | A method of construction for retaining wall |
CN107882211A (en) * | 2017-12-15 | 2018-04-06 | 赵建敏 | Constraint compound wall structure for building |
KR20180093358A (en) | 2017-02-13 | 2018-08-22 | 주식회사 스틸텍 | Slot casing with spacer and a method of construction for retaining wall using slot casing |
KR20190092355A (en) * | 2019-07-29 | 2019-08-07 | 박강호 | An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same |
-
2006
- 2006-01-03 KR KR1020060000678A patent/KR100691890B1/en not_active IP Right Cessation
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101190877B1 (en) | 2011-02-09 | 2012-10-15 | 무풍건설주식회사 | The ground improvement device for cutoff wall and earths wall |
KR20170018524A (en) * | 2015-08-10 | 2017-02-20 | 주식회사 스틸텍 | A method of construction for retaining wall |
KR101711393B1 (en) * | 2015-08-10 | 2017-03-02 | 황문삼 | A method of construction for retaining wall |
KR20180093358A (en) | 2017-02-13 | 2018-08-22 | 주식회사 스틸텍 | Slot casing with spacer and a method of construction for retaining wall using slot casing |
CN107882211A (en) * | 2017-12-15 | 2018-04-06 | 赵建敏 | Constraint compound wall structure for building |
KR20190092355A (en) * | 2019-07-29 | 2019-08-07 | 박강호 | An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same |
KR102078794B1 (en) * | 2019-07-29 | 2020-02-18 | 박강호 | An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100782007B1 (en) | Construction method of a earth-protection walls | |
KR200424432Y1 (en) | Direct punching simultaneous poruing equipment | |
KR102097855B1 (en) | Self reliance earth retaining construction method having prestress introduced of Double I Beam | |
KR101750273B1 (en) | Tunnel Reinforcement structure and Tunnel Reinforcement methods using the same | |
KR100691890B1 (en) | Method for constructing retaining wall having h-beam | |
KR101676814B1 (en) | CFT pile Construction Method and the Shoring Method using the same file | |
KR101812265B1 (en) | A Foundation Method Of Continuous and Cut Off wall By Overlap Casing | |
KR102003448B1 (en) | Reinforced solider pile apparatus of long span's soil retaining wall | |
KR20140055639A (en) | A execution method of architecture beam | |
KR100989853B1 (en) | piling location fixing apparatus for cast in place concrete pile wall | |
KR20180124795A (en) | An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same | |
KR101674656B1 (en) | CIP retaining wall with steel tube | |
KR102325623B1 (en) | Construction method of retaining wall | |
KR20080076015A (en) | Retaining wall using pier unit having big h-beam | |
KR102233572B1 (en) | Inverse casing for perforating ground bore and inverse casing manufacturing method thereof | |
KR101506163B1 (en) | the improved cast injected concrete pile structure using automatic expanded rebar and quick-gelled injection and the reinforced steel withdrawal method using the same | |
KR101807366B1 (en) | A Foundation Method Of Continuous and Cut Off wall By Overlap Casing | |
KR102239089B1 (en) | Underaround continued wall structure using casing and pile continuous connection and method therefor | |
KR101254189B1 (en) | Directional grouting method and device | |
KR20190137432A (en) | Soil retaining wall for phc pile | |
KR101517884B1 (en) | Construction method for wall structure of underground using the semicircular sheet pile | |
KR20080076013A (en) | Method for constructing pier unit having h-beam | |
KR101025179B1 (en) | Reinforcement assembly and c.i.p. construction method | |
KR20120049602A (en) | Temporary retaining wall and constructing method thereof | |
KR102342510B1 (en) | Overlap cylindrical member for construction of continuous and cut off wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20120113 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20130115 Year of fee payment: 7 |
|
LAPS | Lapse due to unpaid annual fee |