KR20180047337A - A drilling equipment transfer apparatus of drilling ship - Google Patents

A drilling equipment transfer apparatus of drilling ship Download PDF

Info

Publication number
KR20180047337A
KR20180047337A KR1020160143321A KR20160143321A KR20180047337A KR 20180047337 A KR20180047337 A KR 20180047337A KR 1020160143321 A KR1020160143321 A KR 1020160143321A KR 20160143321 A KR20160143321 A KR 20160143321A KR 20180047337 A KR20180047337 A KR 20180047337A
Authority
KR
South Korea
Prior art keywords
drill
trolley
deck
horizontal section
bop
Prior art date
Application number
KR1020160143321A
Other languages
Korean (ko)
Inventor
김건호
Original Assignee
대우조선해양 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대우조선해양 주식회사 filed Critical 대우조선해양 주식회사
Priority to KR1020160143321A priority Critical patent/KR20180047337A/en
Publication of KR20180047337A publication Critical patent/KR20180047337A/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B27/00Arrangement of ship-based loading or unloading equipment for cargo or passengers
    • B63B27/22Arrangement of ship-based loading or unloading equipment for cargo or passengers of conveyers, e.g. of endless-belt or screw-type
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/44Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
    • B63B35/4413Floating drilling platforms, e.g. carrying water-oil separating devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • E21B15/02Supports for the drilling machine, e.g. derricks or masts specially adapted for underwater drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B19/00Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables
    • E21B19/02Rod or cable suspensions
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/02Surface sealing or packing
    • E21B33/03Well heads; Setting-up thereof
    • E21B33/06Blow-out preventers, i.e. apparatus closing around a drill pipe, e.g. annular blow-out preventers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B3/00Hulls characterised by their structure or component parts
    • B63B3/14Hull parts
    • B63B2003/147Moon-pools, e.g. for offshore drilling vessels

Abstract

The present invention relates to a drilling equipment transfer apparatus of a drilling ship, wherein when installing BOP equipment and Christmas tree equipment, a trolley is slantingly moved along a guide rail to be moved to a drilling well of a moon pool placed in a lower direction of a drill floor. Therefore, a height of the drill floor and an upper deck can be lowered to secure stability in movement and drilling work.

Description

시추선의 장비 운반장치{A DRILLING EQUIPMENT TRANSFER APPARATUS OF DRILLING SHIP}BACKGROUND OF THE INVENTION 1. Field of the Invention [0001] The present invention relates to an equipment handling apparatus for a drilling rig,

본 발명은 시추선의 장비 운반장치에 관한 것으로, 더욱 상세하게는 BOP 장비 및 크리스마스트리 장비 설치시 트롤리가 가이드 레일을 따라 경사지게 이동되어, 드릴 플로워의 하방에 위치된 문풀의 시추공으로 이동되도록 함으로써, 드릴 플로워 및 상부 데크의 높이를 낮출 수 있어 이동 및 시추 작업시 안정성을 확보할 수 있고, 트롤리가 이동시 장비와 드릴 플로워의 간섭을 방지할 수 있는 시추선의 장비 운반장치에 관한 것이다.The present invention relates to a device for transporting a drill ship, more particularly, a trolley is moved obliquely along a guide rail at the time of installation of a BOP equipment and a Christmas tree equipment, and is moved to a borehole of a doorway located below the drill traveler, The height of the floor and the upper deck can be reduced to ensure stability in moving and drilling operations and to prevent the interference of the trolley with the equipment and the drill through when the trolley moves.

일반적으로, 시추선은 리그선(rig ship), 고정형 플랫폼(stationary platform), 시추선(drill ship) 등의 다양한 종류가 있으며, 해당 선박의 특징에 따라 다양한 형태로 운용되고 있다.Generally, there are various types of drill ships, such as rig ships, stationary platforms, drill ships, etc., and they are operated in various forms according to characteristics of the ship.

이러한 시추선들 중, 시추선(drill ship)은 기존의 고정형 시추 장비와는 달리 시추 장비가 구비된 선박으로, 시추선의 중앙 영역에는 문풀(moonpool)이라는 대규모의 개구부(open area)를 포함한 공간이 형성된다.Among these drill ships, the drill ship is a ship equipped with drilling equipment unlike the existing fixed drilling equipment, and a space including a large open space called a moonpool is formed in the center area of the drill ship .

그리고, 문풀의 상부에는 시추 작업을 위한 데릭 구조물 및 드릴 플로워(Drillfloor) 등이 구성되며, 문풀을 통해 시추 장비에 대한 설치, 테스트, 유지보수 등의 전반적인 작업이 진행된다.In addition, the upper part of the platform has a derrick structure for drilling and a drillfloor. Through the portal, installation, testing, and maintenance of the drilling equipment are performed.

한편, 해저 시추 작업은 시추공(drilling well) 내로 제어되지 않은 지질층 유체(formation fluid)의 유동인 블로 아웃(blow out) 현상이 수반될 수 있는데, 블로 아웃 현상은 위험하고, 시추 장비의 수명 단축, 오염, 손상 및 유정(well) 생산의 손실 등을 유발할 수 있다.On the other hand, submarine drilling can be accompanied by blowout, which is the flow of formation fluid that is not controlled into the drilling well. The blowout phenomenon is dangerous, shortening the life of drilling equipment, , Damage and loss of well production.

이를 방지하기 위해, 시추선에는 블로 아웃 방지장비(blowout preventor, BOP)가 설치되는데, 블로 아웃 방지 장비(BOP)는 시추 위치(drilling site)에서 지질층 압력(formation presure) 및 유체를 안전하게 격리하여 제어한다.To prevent this, a blowout preventor (BOP) is installed at the drill ship. BOP (blowout prevention equipment) is used to safely isolate and control the formation presure and fluid at the drilling site .

그리고, 시추선에는 블로아웃 방지 장비(BOP)를 일정 위치로 이동시키기 위한 가이드 시스템이 구성되는데, 종래의 가이드 시스템에는 일정 이동경로를 형성하는 가이드 레일과, 일정 유압력에 의해 레일을 따라 이동하면서 블로아웃 방지 장비(BOP)를 특정 위치로 이동시키기 위한 트롤리(Trolley)가 설치된다.A guide system for moving the blow-out preventing device (BOP) to a predetermined position is formed on the drill ship. The conventional guide system includes a guide rail for forming a constant movement path, A trolley for moving the out-of-control equipment (BOP) to a specific location is installed.

또한, 시추선에는 유압력을 제공하기 위한 유압 공급유닛(Hydraulic Power Unit: HPU) 및, 유정 자체 압력에 의해 분출이 끝나면 가스 등을 공급해 시추공 압력을 높이기 위한 크리스마트 트리(Christmas Tree) 등이 구성된다.Hydraulic power unit (HPU) for providing hydraulic pressure to the drill ship and a Christmas tree for increasing the borehole pressure by supplying gas or the like after the spray is completed by the oil well self pressure .

그런데, 종래의 시추선은 드릴 플로워의 높이를 낮춰야 시추선의 이동 및 시추 작업시의 안정성을 확보할 수 있지만, 드릴 플로워의 높이를 낮추는 경우, 트롤리에 의해 설치 위치로 이동되는 장비(BOP 및 크리스마스트리)와 드릴 플로워 간의 간섭이 발생할 수 있어, 시추선의 안정성과 장비 이동시 드릴 플로워와의 간섭을 방지할 수 있는 구조가 요구된다.However, when the height of the drill follower is lowered, the equipment (BOP and Christmas tree) which is moved to the installation position by the trolley can not be used, And the drill follower may occur, and a structure capable of preventing the stability of the drill ship and the interference with the drill follower when moving the equipment is required.

본 발명과 관련된 선행 문헌으로는 대한민국 공개특허 제20-2014-0002900호(2014년 05월 16일)가 있으며, 상기 선행 문헌에는 BOP 작동라인 가이드장치 및 해양 구조물이 개시되어 있다.Prior art related to the present invention is Korean Patent Laid-Open Publication No. 20-2014-0002900 (May 16, 2014), which discloses a BOP operating line guide device and an offshore structure.

본 발명의 목적은 BOP 장비 및 크리스마스트리 장비 설치시 트롤리가 가이드 레일을 따라 경사지게 이동되어, 드릴 플로워의 하방에 위치된 문풀의 시추공으로 이동되도록 함으로써, 드릴 플로워 및 상부 데크의 높이를 낮출 수 있어 이동 및 시추 작업시 안정성을 확보할 수 있고, 트롤리가 이동시 장비와 드릴 플로워의 간섭을 방지할 수 있는 시추선의 장비 운반장치를 제공하는데 있다.It is an object of the present invention to reduce the height of the drill floors and the upper deck by moving the trolley to be inclined along the guide rails when the BOP equipment and the Christmas tree equipment are installed, And it is an object of the present invention to provide an apparatus and a device for transporting a drill ship which can secure stability in drilling operation and prevent the interference of equipment and a drill follower when a trolley moves.

본 발명에 따른 BOP 트롤리는 드릴 플로워의 하부에 위치된 데크로부터 오목하게 형성되며, 장비가 설치될 수 있도록 문풀이 형성되는 레일 설치공간과, 상기 레일 설치공간을 따라 이동 경로를 형성하며, 종 방향 양단이 상기 테크의 상면으로 상향 경사지게 연결되는 가이드 레일 및, 상기 가이드 레일을 따라 이동 가능하게 장착되어, 상기 장비를 상기 데크 및 상기 데크의 하방에 위치된 문풀로 이동시키는 트롤리를 포함하는 것을 특징으로 한다.A BOP trolley according to the present invention includes: a rail installation space formed concavely from a deck positioned at a lower portion of a drill floor and having a door pool for installation of equipment; And a trolley mounted movably along the guide rail and adapted to move the equipment to the deck and a platform positioned below the deck. do.

여기서, 상기 가이드 레일은 상기 레일 설치공간의 하부에 수평하게 설치되며, 상기 드릴 플로워의 하방에 위치된 상태에서 상기 데크의 양 방향으로 길이를 갖는 수평 구간 및, 상기 수평 구간의 종 방향 양단으로부터 상기 데크의 상면으로 상향 경사지게 연결되어, 상기 트롤리가 상기 수평 구간과 상기 데릭의 상면으로 이동 가능하도록 하는 한 쌍의 경사 구간이 형성되는 것이 바람직하다.Here, the guide rail is installed horizontally below the rail installation space, and includes a horizontal section having a length in both directions of the deck in a state of being positioned below the drill traveler, and a horizontal section extending from both longitudinal ends of the horizontal section, And a pair of inclined sections connected to the upper surface of the deck so as to be upwardly inclined so that the trolley can be moved to the horizontal section and the upper surface of the derrick.

또한, 상기 수평 구간의 종 방향 양단과 상기 경사 구간의 일단은 하부로 오목한 곡선 구간에 의해 연결되는 것이 바람직하다.In addition, it is preferable that the both longitudinal ends of the horizontal section and one end of the inclined section are connected by a concave curved section downward.

또한, 상기 수평 구간은 상기 드릴 플로워와 설정 간격을 유지하며, 상기 드릴 플로워의 높이에 따라 상기 설정 간격을 유지하도록 깊이가 가변적으로 적용되는 것이 바람직하다.In addition, it is preferable that the horizontal interval maintains a set interval with the drill follower, and the depth is variably applied to maintain the set interval according to the height of the drill traveler.

또한, 상기 문풀에는 상기 장비가 설치될 수 있도록 시추공이 형성되며, 상기 시추공은 상기 수평 구간의 이동 경로 내에 위치되는 것이 바람직하다.In addition, a borehole may be formed in the doorpath so that the equipment can be installed, and the borehole is positioned in the movement path of the horizontal section.

또한, 상기 트롤리는 상기 경사 구간을 따라 이동시 상부 장착면이 수평하게 유지되는 것이 바람직하다.In addition, it is preferable that the upper mounting surface of the trolley is held horizontally when the trolley moves along the inclined section.

또한, 상기 데크의 상면에는 상기 레일 설치공간을 기준으로 양 방향에 BOP 적재공간 및 크리스마스트리 적재공간이 각각 형성되며, 상기 경사 구간들의 상단은 상기 BOP 적재공간 및 크리스마스트리 적재공간으로 각각 연결되는 것이 바람직하다.The BOP loading space and the Christmas tree loading space are formed on the upper surface of the deck on both sides of the rail installation space, and the upper ends of the slope sections are connected to the BOP loading space and the Christmas tree loading space desirable.

본 발명은 BOP 장비 및 크리스마스트리 장비 설치시 트롤리가 가이드 레일을 따라 경사지게 이동되어, 드릴 플로워의 하방에 위치된 문풀의 시추공으로 이동되도록 함으로써, 드릴 플로워 및 상부 데크의 높이를 낮출 수 있어 이동 및 시추 작업시 안정성을 확보할 수 있고, 트롤리가 이동시 장비와 드릴 플로워의 간섭을 방지할 수 있는 효과를 갖는다.In the present invention, when the BOP equipment and the Christmas tree equipment are installed, the trolley is moved obliquely along the guide rail to be moved to the borehole of the door located below the drill traveler, thereby lowering the height of the drill floor and the upper deck. It is possible to secure stability during operation and to prevent the trolley from interfering with the equipment and the drill follower when moving.

도 1은 본 발명에 따른 시추선의 장비 운반장치를 보여주기 위한 정단면도이다.
도 2는 본 발명에 따른 시추선의 장비 운반장치에서 수평 구간과 경사 구간의 연결부에 곡선 구간을 적용시킨 상태를 보여주기 위한 정단면도이다.
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a front sectional view showing a device for transporting a drill rig according to the present invention; FIG.
FIG. 2 is a front sectional view showing a state in which a curve section is applied to a connecting portion between a horizontal section and a slope section in a rig transporting apparatus according to the present invention.

이하 첨부된 도면을 참조하면서 본 발명에 따른 바람직한 실시 예를 상세히 설명하기로 한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명의 이점 및 특징, 그리고 그것을 달성하는 방법은 첨부된 도면과 함께 상세하게 후술되어 있는 실시예들을 참조하면 명확해질 것이다.BRIEF DESCRIPTION OF THE DRAWINGS The advantages and features of the present invention and the manner of achieving it will become apparent with reference to the embodiments described in detail below with reference to the accompanying drawings.

그러나 본 발명은 이하에 개시되는 실시예들에 의해 한정되는 것이 아니라 서로 다른 다양한 형태로 구현될 것이며, 단지 본 실시예들은 본 발명의 개시가 완전하도록 하며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 발명의 범주를 완전하게 알려주기 위해 제공되는 것이며, 본 발명은 청구항의 범주에 의해 정의될 뿐이다.The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the invention to those skilled in the art. To fully disclose the scope of the invention to those skilled in the art, and the invention is only defined by the scope of the claims.

또한, 본 발명을 설명함에 있어 관련된 공지 기술 등이 본 발명의 요지를 흐리게 할 수 있다고 판단되는 경우 그에 관한 자세한 설명은 생략하기로 한다.In the following description, well-known functions or constructions are not described in detail since they would obscure the invention in unnecessary detail.

도 1은 본 발명에 따른 시추선의 장비 운반장치를 보여주기 위한 정단면도이고, 도 2는 본 발명에 따른 시추선의 장비 운반장치에서 수평 구간과 경사 구간의 연결부에 곡선 구간을 적용시킨 상태를 보여주기 위한 정단면도이다.FIG. 1 is a front sectional view showing a device for conveying a drill rig according to the present invention, and FIG. 2 shows a state in which a curve section is applied to a connection portion between a horizontal section and a slope section in a device for transporting a drill rig according to the present invention Fig.

도 1과 2를 참조하면, 본 발명에 따른 시추선의 장비 운반장치는 레일 설치공간(100)과, 가이드 레일(200) 및, 트롤리(Trolley, 300)를 포함한다.Referring to FIGS. 1 and 2, the apparatus for transporting a drill rig according to the present invention includes a rail installation space 100, a guide rail 200, and a trolley 300.

먼저, 상기 레일 설치공간(100)은 선체의 데크로부터 하부로 오목하게 형성되어, 후술 될 트롤리(300)가 문풀(20)의 시추공(21)으로 이동할 수 있는 공간이다.First, the rail installation space 100 is recessed downward from the deck of the ship hull so that the trolley 300, which will be described later, can move to the borehole 21 of the doorpost 20.

여기서, 상기 레일 설치공간(100)은 문풀(20)의 영역 내에 위치될 수 있고, 상기 문풀(20)에는 장비를 설치하기 위한 시추공(well center)이 형성된다.Here, the rail installation space 100 may be located within the area of the door 20, and a well center for installing the equipment may be formed in the door 20.

그리고, 상기 문풀(20)의 상부에는 데릭(derrick, 30)이 일정 높이로 설치되는데, 상기 데릭(30)의 일정 높이에는 시추 작업을 위한 드릴 플로워(31)가 일정 넓이로 설치된다.A derrick 30 is installed at a predetermined height on the upper portion of the door pile 20. A drill follower 31 for drilling is installed at a predetermined height of the derrick 30 to a predetermined width.

이때, 레일 설치공간(100)은 드릴 플로워(31)의 하부 데크로부터 하부로 오목하게 형성되며, 상기 레일 설치공간(100)은 문풀(20) 영역에 형성된다.At this time, the rail installation space 100 is formed to be concave downward from the lower deck of the drill follower 31, and the rail installation space 100 is formed in the area of the door frame 20.

예를 들어, 선체의 안정성을 높이기 위해 상기 드릴 플로워(31)의 높이를 낮추는 경우, 상기 레일 설치공간(100)의 깊이도 증가시켜 상기 드릴 플로워(31)와 상기 레일 설치공간(100)의 간격을 일정하게 유지시킬 수 있다.For example, when the height of the drill follower 31 is lowered to increase the stability of the hull, the depth of the rail installation space 100 is increased so that the distance between the drill follower 31 and the rail installation space 100 Can be kept constant.

그리고, 데크의 상면에는 레일 설치공간(100)을 기준으로 양 방향에 BOP 적재공간(A) 및 크리스마스트리(X-mas tree) 적재공간(B)이 각각 형성된다.A BOP loading space A and a X-mas tree loading space B are formed on the upper surface of the deck with respect to the rail installation space 100 in both directions.

즉, 레일 설치공간(100)은 드릴 플로워(31)의 하부와 일정 간격을 유지하게 되므로, 후술 될 트롤리(300)가 BOP(40) 및 크리스마스트리(50) 장비를 문풀(20)의 시추공(21)으로 이동시키는 경우, BOP(40) 및 크리스마스트리(50) 장비와 드릴 플로워(31)와의 간섭이 발생하지 않도록 한다.That is, the rail installation space 100 maintains a certain distance from the lower portion of the drill follower 31, so that the trolley 300, which will be described later, can install the BOP 40 and the Christmas tree 50 equipment in the borehole 21, the interference between the BOP 40 and the Christmas tree 50 equipment and the drill follower 31 does not occur.

가이드 레일(200)은, 후술 될 트롤리(300)가 이동하는 이동 경로를 제공하기 위한 것으로, 상기 가이드 레일(200)은 레일 설치공간(10)을 따라 이동 경로를 형성한다.The guide rail 200 provides a movement path for moving the trolley 300, which will be described later, and the guide rail 200 forms a movement path along the rail installation space 10.

여기서, 상기 가이드 레일(200)의 종 방향 양단이 데크의 상면으로 상향 경사지게 연결되어, BOP(40) 절재공간(A) 및 크리스마스트리(50) 적재공간(B)으로 연결된다.The longitudinal ends of the guide rail 200 are connected to the upper surface of the deck at an upward slope so as to be connected to the BOP 40 storage space A and the loading space B of the Christmas tree 50.

더 상세히 설명하면, 상기 가이드 레일(200)은 도 1에서처럼 수평 구간(210) 및, 한 쌍의 경사 구간(220)로 구비될 수 있다.More specifically, the guide rail 200 may include a horizontal section 210 and a pair of inclined sections 220 as shown in FIG.

상기 수평 구간(210)은, 후술 될 트롤리(300)가 레일 설치공간(100)의 하부에서 수평하게 이동될 수 있도록 이동 경로를 형성한다.The horizontal section 210 forms a movement path so that the trolley 300, which will be described later, can be horizontally moved in a lower portion of the rail installation space 100.

여기서, 상기 수평 구간(210)은 레일 설치공간(100)의 양측 벽면에 각각 설치되어 후술 될 트롤리(300)의 양단이 각각 연결됨으로써, 트레이(300)가 BOP 적재공간(A) 및 크리스마스트리(X-mas tree) 적재공간(B) 방향으로 이동될 수 있도록 한다.The horizontal section 210 is installed on both side walls of the rail installation space 100 and both ends of the trolley 300 to be described later are connected to each other so that the tray 300 is installed in the BOP loading space A and the Christmas tree X-mas tree) in the loading space (B) direction.

이와 같은 상기 수평 구간(210)은, 드릴 플로워(31)와 설정 간격을 유지하며, 상기 수평 구간(210)은 드릴 플로워(31)의 높이에 따라 설정 간격을 유지하도록 깊이가 가변적으로 적용될 수 있다.The horizontal section 210 maintains the set interval with the drill follower 31 and the horizontal section 210 can be varied in depth to maintain the set interval according to the height of the drill follower 31 .

한 쌍의 경사 구간(220)은, 수평 구간(210)의 종 방향 양단으로부터 데크의 상면으로 상향 경사지게 연결되어, 후술 될 트롤리(300)가 수평 구간(210)과 데릭(30)의 상면으로 이동 가능하도록 한다.The pair of slope sections 220 are sloped upward from the longitudinal ends of the horizontal section 210 to the upper surface of the deck so that the trolley 300 to be described later moves to the upper surface of the horizontal section 210 and the derrick 30 .

여기서, 상기 한 쌍의 경사 구간(220)는 레일 설치공간(100)의 양측 벽면에 각각 설치되어 후술 될 트롤리(300)의 양단이 각각 연결됨으로써, 트레이(300)가 BOP 적재공간(A) 및 크리스마스트리(X-mas tree) 적재공간(B) 방향으로 이동될 수 있도록 한다.The pair of slope sections 220 are installed on both side walls of the rail installation space 100 and are connected to both ends of a trolley 300 to be described later so that the tray 300 can be installed in the BOP loading space A and / The X-mas tree can be moved in the loading space (B) direction.

이와 같은 상기 한 쌍의 경사 구간(220)은, 수평 구간(210)과 하나의 이동 경로를 형성하며, 상기 경사 구간(220)들의 상단은 BOP 적재공간(A) 및 크리스마스트리 적재공간(B)으로 각각 연결된다.The pair of slope sections 220 form one movement path with the horizontal section 210 and the upper ends of the slope sections 220 form a BOP stacking space A and a Christmas tree stacking space B, Respectively.

그리고, 상기 경사 구간(220)들의 각도는 후술 될 트롤리(300)가 이동될 수 있는 적정 각도를 갖는 것으로, 상기 경사 구간(220)는 다양한 각도로 적용이 가능하다.The angle of the slope sections 220 has an appropriate angle at which the trolley 300 to be described later can be moved, and the slope section 220 can be applied at various angles.

한편, 도 2에서처럼 수평 구간(210)의 종 방향 양단과 경사 구간(220)들의 일단은 하부로 오목한 곡선 구간(230)에 의해 연결될 수 있다.2, one longitudinal end of the horizontal section 210 and one end of the inclined section 220 may be connected to each other by a concave curved section 230.

상기 곡선 구간(230)은, 레일 설치공간(100)의 양측 벽면에 각각 설치되어 수평 구간(210)와 하나의 이동 경로를 형성하는 것으로, 후술 될 트레이(300)가 수평 구간(210)와 경사 구간(220)로 이동될 수 있도록 한다.The curved section 230 is provided on both side walls of the rail installation space 100 to form a movement path with the horizontal section 210 so that the tray 300 to be described later is inclined with respect to the horizontal section 210, Section 220. [0034] FIG.

여기서, 상기 곡선 구간(230)은 수평 구간(210) 및 경사 구간(220)과 하나의 이동 경로를 형성하는 것으로, 상기 곡선 구간(230)는 곡률은 다양하게 적용이 가능하다.Here, the curved section 230 forms one movement path with the horizontal section 210 and the inclined section 220, and the curvature of the curved section 230 can be variously applied.

트롤리(300)는, 가이드 레일(200)을 따라 이동 가능하게 장착되는 것으로, 상기 트롤리(300)의 상부에는 BOP(40) 장비와 크리스마스트리(50) 장비가 장착될 수 있다.The trolley 300 is mounted movably along the guide rail 200. The BOP 40 and the Christmas tree 50 can be mounted on the trolley 300.

여기서, 상기 트롤리(300)는 BOP(40) 장비와 크리스마스트리(50) 장비를 장착한 상태에서 문풀(20)의 시추공(21)로 이동되거나, BOP 적재공간(A) 및 크리스마스트리 적재공간(B)으로 이동될 수 있다.The trolley 300 may be moved to the borehole 21 of the doorpane 20 in the state that the BOP 40 and the Christmas tree 50 are mounted or the BOP loading space A and the Christmas tree loading space B).

그리고, 상기 트롤리(300)는 BOP 적재공간(A) 방향의 가이드 레일(200) 상에 설치되어 BOP(40) 장비를 이동시키는 트롤리와, 크리스마스트리 적재공간(B) 방향의 가이드 레일(200) 상에 설치되어 크리스마스트리(50) 장비를 이동시키는 트롤리로 각각 구분될 수 있다.The trolley 300 is installed on the guide rail 200 in the direction of the BOP loading space A and is mounted on the trolley for moving the BOP 40 and the guide rail 200 in the direction of the Christmas tree loading space B. [ And a trolley for moving the Christmas tree 50 equipment.

또한, 상기 트롤리(300)는 구동유닛(미도시)에 의해 가이드 레일(200)을 따라 이동될 수 있으며, 상기 트롤리(300)에는 BOP(40) 장비와 크리스마스트리(50) 장비를 고정 및 고정 해지시키기 위한 구성(미도시)이 설치될 수 있다.The trolley 300 can be moved along a guide rail 200 by a driving unit and the trolley 300 is fixedly and fixed to the BOP 40 and the Christmas tree 50 A configuration (not shown) for canceling the image can be provided.

이와 같은 상기 트롤리(300)의 상부 장착면은, BOP 적재공간(A) 및 크리스마스트리 적재공간(B)에 위치시와 수평 구간(210) 및 경사 구간(220)를 따라 이동하는 과정에서 수평하게 위치될 수 있다.The upper mounting surface of the trolley 300 is horizontally positioned in the BOP loading space A and the Christmas tree loading space B during the movement along the horizontal section 210 and the slope section 220 Lt; / RTI >

즉, 상기 트롤리(300)는 문풀(20)의 시추공(21)로 이동시키거나, 원래의 적재 위치로 이동 위치되는 경우, BOP(40) 장비와 크리스마스트리(50) 장비가 안정적으로 위치될 수 있도록 한다.That is, when the trolley 300 is moved to the borehole 21 of the door frame 20 or is moved to the original loading position, the BOP 40 and the Christmas tree 50 equipment can be stably positioned .

그리고, 트롤리(300)는 경사 구간(220)를 통해 레일 설치공간(100)의 하부에 위치된 수평 구간(210)로 이동되므로, 문풀(20) 내에서의 설치 작업시 드릴 플로워(31)와의 간섭을 없앨 수 있다.Since the trolley 300 is moved to the horizontal section 210 located below the rail installation space 100 through the inclined section 220, Interference can be eliminated.

결과적으로, 본 발명은 BOP(40) 장비 및 크리스마스트리(50) 장비 설치시 트롤리(300)가 가이드 레일(100)을 따라 경사지게 이동되어, 드릴 플로워(31)의 하방에 위치된 문풀(20)의 시추공(21)으로 이동되도록 할 수 있다.As a result, the present invention allows the trolley 300 to be inclined along the guide rail 100 when the BOP 40 and the Christmas tree 50 are installed, To the borehole 21 of the borehole.

이로써, 본발명은 드릴 플로워(31) 및 상부 데크의 높이를 낮출 수 있어 이동 및 시추 작업시 안정성을 확보할 수 있으며, 트롤리(300)가 이동시 장비와 드릴 플로워의 간섭을 방지할 수 있다.Thus, the present invention can lower the height of the drill follower 31 and the upper deck, thereby ensuring stability in moving and drilling operations, and preventing the trolley 300 from interfering with equipment and the drill follower when moving.

지금까지 본 발명의 시추선의 장비 운반장치에 관한 구체적인 실시예에 관하여 설명하였으나, 본 발명의 범위에서 벗어나지 않는 한도 내에서는 여러 가지 실시 변형이 가능함은 자명하다.It is apparent that various modifications are possible within the scope of the present invention without departing from the scope of the present invention.

그러므로 본 발명의 범위에는 설명된 실시예에 국한되어 전해져서는 안되며, 후술하는 특허 청구범위뿐만 아니라 이 특허 청구범위와 균등한 것들에 의해 정해져야 한다.Therefore, the scope of the present invention should not be limited to the embodiments described, but should be determined by the equivalents of the claims and the claims.

즉, 전술된 실시예는 모든 면에서 예시적인 것이며, 한정적인 것이 아닌 것으로 이해되어야 하며, 본 발명의 범위는 상세한 설명보다는 후술될 특허 청구범위에 의하여 나타내어지며, 그 특허 청구범위의 의미 및 범위 그리고 그 등가 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.It is to be understood that the foregoing embodiments are illustrative and not restrictive in all respects and that the scope of the present invention is indicated by the appended claims rather than the foregoing description, It is intended that all changes and modifications derived from the equivalent concept be included within the scope of the present invention.

10: 선체 20: 문풀(moonpool)
21: 시추공(main well center) 30: 데릭(derrick)
31: 드릴 플로워(drillfloor) 40: BOP(blowout Preventer)
50: 크리스마스 트리(X-mas tree)100: 가이드 레일
110: 수평 구간 120: 경사 구간
130: 곡선 구간 200: 트롤리
A: BOP 적재공간 B: 크리스마스트리 적재공간
10: Hull 20: moonpool
21: main well center 30: derrick
31: Drillfloor 40: BOP (blowout preventer)
50: X-mas tree 100: guide rail
110: horizontal section 120: slope section
130: Curved section 200: Trolley
A: BOP loading space B: Christmas tree loading space

Claims (7)

드릴 플로워의 하부에 위치된 데크로부터 오목하게 형성되며, 장비가 설치될 수 있도록 문풀이 형성되는 레일 설치공간;
상기 레일 설치공간을 따라 이동 경로를 형성하며, 종 방향 양단이 상기 테크의 상면으로 상향 경사지게 연결되는 가이드 레일; 및
상기 가이드 레일을 따라 이동 가능하게 장착되어, 상기 장비를 상기 데크 및 상기 데크의 하방에 위치된 문풀로 이동시키는 트롤리;를 포함하는 것을 특징으로 하는 시추선의 장비 운반장치.
A rail installation space formed concavely from a deck located at a lower portion of the drill floor and having a door pool for installation of the equipment;
A guide rail forming a movement path along the rail installation space and having both longitudinal ends thereof connected to the upper surface of the tuck upwardly; And
And a trolley movably mounted along the guide rail for moving the equipment to the deck and a door positioned below the deck.
청구항 1에 있어서,
상기 가이드 레일은,
상기 레일 설치공간의 하부에 수평하게 설치되며, 상기 드릴 플로워의 하방에 위치된 상태에서 상기 데크의 양 방향으로 길이를 갖는 수평 구간 및,
상기 수평 구간의 종 방향 양단으로부터 상기 데크의 상면으로 상향 경사지게 연결되어, 상기 트롤리가 상기 수평 구간과 상기 데릭의 상면으로 이동 가능하도록 하는 한 쌍의 경사 구간이 형성되는 것을 특징으로 하는 시추선의 장비 운반장치.
The method according to claim 1,
The guide rails
A horizontal section which is installed horizontally below the rail installation space and has a length in both directions of the deck in a state of being positioned below the drill traveler,
And a pair of inclined sections connected to the upper surface of the deck at both longitudinal ends of the horizontal section so as to be sloped upward so that the trolley can move to the upper surface of the derrick and the horizontal section. Device.
청구항 2에 있어서,
상기 수평 구간의 종 방향 양단과 상기 경사 구간의 일단은,
하부로 오목한 곡선 구간에 의해 연결되는 것을 특징으로 하는 시추선의 장비 운반장치.
The method of claim 2,
The longitudinal ends of the horizontal section and one end of the slant section are connected to each other,
And the lower portion is connected by a concave curved section.
청구항 2에 있어서,
상기 수평 구간은,
상기 드릴 플로워와 설정 간격을 유지하며, 상기 드릴 플로워의 높이에 따라 상기 설정 간격을 유지하도록 깊이가 가변적으로 적용되는 것을 특징으로 하는 시추선의 장비 운반장치.
The method of claim 2,
In the horizontal section,
Wherein a depth of the drill follow is varied to maintain the set interval according to a height of the drill follow, while maintaining a predetermined interval with the drill follow.
청구항 1 또는 2에 있어서,
상기 문풀에는,
상기 장비가 설치될 수 있도록 시추공이 형성되며,
상기 시추공은,
상기 수평 구간의 이동 경로 내에 위치되는 것을 특징으로 하는 시추선의 장비 운반장치.
The method according to claim 1 or 2,
In the above-
A borehole is formed so that the equipment can be installed,
The borehole includes:
And wherein the device is located within a travel path of the horizontal section.
청구항 2에 있어서,
상기 트롤리는,
상기 경사 구간을 따라 이동시 상부 장착면이 수평하게 유지되는 것을 특징으로 하는 시추선의 장비 운반장치.
The method of claim 2,
The trolley,
And the upper mounting surface is held horizontally when moving along the slope section.
청구항 2에 있어서,
상기 데크의 상면에는,
상기 레일 설치공간을 기준으로 양 방향에 BOP 적재공간 및 크리스마스트리 적재공간이 각각 형성되며,
상기 경사 구간들의 상단은,
상기 BOP 적재공간 및 크리스마스트리 적재공간으로 각각 연결되는 것을 특징으로 하는 시추선의 장비 운반장치.
The method of claim 2,
On the upper surface of the deck,
A BOP loading space and a Christmas tree loading space are formed on both sides of the rail installation space,
The upper end of the slope sections,
Wherein the BOP loading space and the Christmas tree loading space are connected to the BOP loading space and the Christmas tree loading space, respectively.
KR1020160143321A 2016-10-31 2016-10-31 A drilling equipment transfer apparatus of drilling ship KR20180047337A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160143321A KR20180047337A (en) 2016-10-31 2016-10-31 A drilling equipment transfer apparatus of drilling ship

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160143321A KR20180047337A (en) 2016-10-31 2016-10-31 A drilling equipment transfer apparatus of drilling ship

Publications (1)

Publication Number Publication Date
KR20180047337A true KR20180047337A (en) 2018-05-10

Family

ID=62184912

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160143321A KR20180047337A (en) 2016-10-31 2016-10-31 A drilling equipment transfer apparatus of drilling ship

Country Status (1)

Country Link
KR (1) KR20180047337A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112814587A (en) * 2019-11-15 2021-05-18 四川宏华石油设备有限公司 Formula of sinking christmas tree moves fortune dolly

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112814587A (en) * 2019-11-15 2021-05-18 四川宏华石油设备有限公司 Formula of sinking christmas tree moves fortune dolly
CN112814587B (en) * 2019-11-15 2024-04-09 四川宏华石油设备有限公司 Sinking type christmas tree transporting trolley

Similar Documents

Publication Publication Date Title
US9458680B2 (en) Drilling rig
CN107654192B (en) Method and apparatus for drilling a plurality of subsea wells from an offshore platform at a single site
US20180155995A1 (en) Drilling installation; handling system, method for independent operations
CN111491857B (en) Vessel and method for performing subsea wellbore related activities
KR20180047337A (en) A drilling equipment transfer apparatus of drilling ship
KR101222205B1 (en) Device for guiding blow out preventer
EP3755618B1 (en) Vessel and method for performing subsea wellbore related activities, e.g. workover activities, well maintenance, installing an object on a subsea well bore
KR20190009613A (en) Riser Handling System and Oil Prospection offshore rig Including The Same
KR200484424Y1 (en) Parking structure of cradle and cradle with the structure in drillship
KR101379429B1 (en) Ship having movable guide bridge
KR101400145B1 (en) Floating offshore platform
KR101707517B1 (en) Install structure of blow out preventer and drilling offshore structure having the same
KR101468533B1 (en) Moonpool recess door for pipe layer vessel
KR101681718B1 (en) Riser Transfer System
US11808096B2 (en) Offshore drilling system, vessel and method
KR20150033763A (en) Drillfloorless drill system
KR200490626Y1 (en) Riser Handling System
KR20180077562A (en) Drillship
KR102242211B1 (en) Riser Handling System and Oil Prospection offshore rig Including The Same
US20220274676A1 (en) Semi-submersible floating offshore vessel
KR101956677B1 (en) Transporter having blowout preventer guide apparatus and guide system in offshore
CN110914145B (en) Vessel and method for performing subsea wellbore related operations
KR200492738Y1 (en) Bop trolley of drillship
KR101835286B1 (en) Bridge with crane and drillship including the same
KR20160036263A (en) Drill pipe handling method