KR20170133035A - Prefabricated retaining device for building the pipeline easy to install and dismantle - Google Patents

Prefabricated retaining device for building the pipeline easy to install and dismantle Download PDF

Info

Publication number
KR20170133035A
KR20170133035A KR1020160063971A KR20160063971A KR20170133035A KR 20170133035 A KR20170133035 A KR 20170133035A KR 1020160063971 A KR1020160063971 A KR 1020160063971A KR 20160063971 A KR20160063971 A KR 20160063971A KR 20170133035 A KR20170133035 A KR 20170133035A
Authority
KR
South Korea
Prior art keywords
steel plate
vertical
horizontal
sides
web
Prior art date
Application number
KR1020160063971A
Other languages
Korean (ko)
Inventor
금영석
김영길
Original Assignee
주식회사 금원건설
금영석
김영길
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 금원건설, 금영석, 김영길 filed Critical 주식회사 금원건설
Priority to KR1020160063971A priority Critical patent/KR20170133035A/en
Publication of KR20170133035A publication Critical patent/KR20170133035A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0032Steel; Iron in sheet form, i.e. bent or deformed plate-material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/40Miscellaneous comprising stabilising elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The present invention relates to a prefabricated earth retaining device for pipe construction that is easy to be installed and dismantled while preventing lateral collapse during pipe construction. To this end, the present invention includes: a body portion in which a vertical portion and a horizontal portion are formed as welded or bolt-engaged with each other, wherein the vertical portion includes vertical H beams that are vertically arranged at regular intervals spaced from both sides of the tube to be installed, wherein the horizontal portions include horizontal H beams that are horizontally laid between webs between the vertical H beams, and steel plate insertion holes that are formed in a longitudinal direction with respect to the web of the horizontal H beam; a steel plate portion coupled between the steel plate insertion holes formed in the horizontal portion so as to support an earth wall to prevent the earth from collapsing; and a strut portion positioned between the vertical H beams facing each other with the tube interposed therebetween, and supporting the steel plate so as not to collapse.

Description

설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치{PREFABRICATED RETAINING DEVICE FOR BUILDING THE PIPELINE EASY TO INSTALL AND DISMANTLE}TECHNICAL FIELD [0001] The present invention relates to a prefabricated retreading device for building a pipeline for easy installation and disassembly,

본 발명은 설치 및 해체가 용이한 관로공사용 조립식 흙막이 장치에 관한 것으로, 더욱 상세하게는 굴토 벽면이 붕괴되는 것을 방지하면서 설치 및 해체가 용이한 관로공사용 조립식 흙막이 장치에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a prefabricated earthmoving apparatus for construction of a pipeline which is easy to install and disassemble, and more particularly, to a prefabricated earthmoving apparatus for a pipeline construction which is easy to install and disassemble while preventing collapse of a wall surface of a crud.

통상 지하철, 관로, 대형 지하구조물 등을 시공하는 경우의 굴착에 있어서 주변의 토사나 지하수가 굴착지반 내에 칩입하지 않도록 흙막이용 가설구조물을 설치한다.In general, when constructing subways, pipelines, and large underground structures, temporary structures for earthworks are installed so that the surrounding soil or groundwater does not enter into the excavation ground.

이러한 가설구조물은 일시적으로 사용하고 제거하기 때문에 안전성과 시공성은 물론 경제성도 동시에 요구된다.Since these temporary structures are temporarily used and removed, safety and construction as well as economic efficiency are required at the same time.

종래의 토사방지 패널 버팀대는 일측에 고정부를 반대측에 가동부를 형성한 신축형 버팀대를 만들어 토사방지 패널사이에 넣어 버팀작용을 하도록 하고 있으나 가동부가 볼트와 너트로 구성되어 일측에 형성되어 있으므로 버팀대를 신축시킬 때 신속한 조정이 이루어지지 않아 작업시간이 느려져서 비능률적인 문제가 있었다.The conventional anti-earth-sandwich panel brace is constructed such that a stretch brace having a movable portion formed on one side thereof and a movable portion on the opposite side thereof is formed between the anti-slip panels so as to support it. However, since the movable portion is formed by bolts and nuts, And there was an inefficiency problem because the operation time was slowed because quick adjustment was not made when the new construction was carried out.

한국등록특허공보 제1034260호(등록일: 2011.05.03., 명칭: 장경간프리스트레스 토류판넬과 띠장으로 지지되는 흙막이 가시설장치 및 이의 시공방법)Korean Registered Patent No. 1034260 (Registered: May 3, 2011, entitled: Long-span prestressed soil panel and temporary retaining device supported by wale and its construction method)

본 발명은 관로 공사를 위해 터파기를 진행 한 후 관을 설치하기 전 양측면에 있는 토사가 흘러 내려 무너지지 않도록 하는 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치를 제공하기 위한 것이다.An object of the present invention is to provide a prefabricated earth moving device for pipeline construction which is easy to install and disassemble so that the gravel on both sides of the pipe does not fall down before the pipe is installed after the wave for the channel construction.

또한, 본 발명은 토사가 흘러내리지 않도록 관을 설치하는 양측 벽면에 흙막이를 설치하되, 본체부, 강판부, 및 버팀부의 끼움결합으로 설치함으로써 나사와 같은 결합부재를 사용하지 않아 시공시간을 단축시키는 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치를 제공하기 위한 것이다. In addition, the present invention provides a soil retaining structure on both side walls for installing a pipe so that the soil does not flow down, but it is provided with a main body portion, a steel plate portion, and a supporting portion, And to provide a prefabricated earthmoving device for a pipeline construction that is easy to install and dismantle.

본 발명이 이루고자 하는 기술적 과제들은 이상에서 언급한 기술적 과제들로 제한되지 않는다.The technical objects to be achieved by the present invention are not limited to the above-mentioned technical problems.

상기 과제를 달성하기 위한 본 발명의 설치 및 해체가 용이한 관로공사용 조립식 흙막이 장치는 관로 공사시 측면 붕괴를 방지하기 위한 관로공사용 조립식 흙막이 장치에 있어서, 관이 설치될 위치 양 측면으로 일정간격 이격하여 수직으로 수직 H빔이 나열되어 설치되는 수직부 및 상기 수직 H빔과 수직 H빔 사이의 웨브와 웨브 사이에 가로로 뉘어진 수평 H빔이 위치되되, 상기 수평 H빔의 웨브에 길이 방향으로 강판 삽입홀이 형성된 수평부가 용접 또는 볼트 결합되어 형성된 본체부; 상기 수평부에 형성된 상기 강판 삽입홀 사이에 결합하여, 흙이 붕괴되는 것을 방지하도록 흙벽을 지지하는 강판부; 및 상기 관을 사이에 두고 서로 마주보는 상기 수직 H빔 사이에 위치하여 상기 강판부가 붕괴되지 않도록 지지하는 버팀부;를 포함하는 것을 특징으로 한다.In order to accomplish the above object, the present invention provides a prefabricated earthmoving device for pipeline construction that is easy to install and disassemble, and is configured to prevent lateral collapse at the time of pipeline construction, A horizontal H beam is disposed between the vertical H beam and the vertical H beam and between the vertical H beam and the vertical H beam and between the web and the web, A body portion formed by welding or bolting a horizontal portion having an insertion hole; A steel plate portion coupled between the steel plate insertion holes formed in the horizontal portion and supporting the earth wall to prevent the earth from collapsing; And a brace part positioned between the vertical H beams facing each other with the tube therebetween to support the steel plate so as not to collapse.

구체적으로, 상기 버팀부는 상부 지지부 및 하부 지지부를 포함하며, 양측면으로 상부 지지부 및 하부 지지부를 연결하는 연결부를 포함하되, 상기 상부 지지부의 양측과 하부 지지부의 양측은 연결부와 결합되되, 상기 연결부의 결합축에 의해 상하로 회동되는 것을 특징으로 한다.Specifically, the supporting portion includes an upper supporting portion and a lower supporting portion, and includes a connecting portion connecting both the upper supporting portion and the lower supporting portion on both sides thereof. The both sides of the upper supporting portion and both sides of the lower supporting portion are coupled with the connecting portion, And is vertically rotated by an axis.

또한, 상기 수직부는 내측 플랜지에 상기 버팀부가 일직선으로 끼워져 결합될 수 있도록 가이드부; 및 상기 가이드부의 하부 방향에 일정간격 이격되어 상기 버팀부가 일정깊이 이상 인입되는 것을 막아주는 걸림부;를 더 포함하는 것을 특징으로 한다.Further, the vertical portion may include a guide portion to be engaged with the inner flange so as to be linearly fitted to the support portion; And a locking part spaced apart from the guide part by a predetermined distance in order to prevent the locking part from being inserted in a predetermined depth or more.

또한, 상기 수평부인 수평 H빔의 웨브는 양측으로 상기 수직 H빔의 일측 플랜지 폭만큼 더 돌출되는 것을 특징으로 한다.Further, the horizontal H-beam web, which is the horizontal portion, is further projected to both sides by a flange width of one side of the vertical H-beam.

또한, 상기 수평부에 형성된 홀에 상기 강판부가 용이하게 인입될 수 있도록, 상기 홀 주변에 강판 인입 가이드부;를 더 포함하는 것을 특징으로 한다.In addition, the steel plate further includes a steel plate guiding guide portion around the hole so that the steel plate portion can be easily inserted into the hole formed in the horizontal portion.

또한, 상기 강판부는 이동장비로 용이하게 이동시킬 수 있도록 이동장비와 결합시킬 수 있는 고리 형태의 이동결합부를 더 포함하는 것을 특징으로 한다.In addition, the steel plate may further include a ring-shaped moving coupling unit that can be coupled with the mobile equipment so that the steel plate unit can be easily moved to the mobile equipment.

또한, 상기 상부 지지부 및 하부 지지부의 상하 회전 동작에 제한을 두기 위해 상기 상부 지지부 및 하부 지지부의 하단에 회동제한수단을 구비하는 것을 특징으로 한다.Further, in order to limit the upward and downward rotation of the upper support portion and the lower support portion, rotation restricting means is provided at the lower ends of the upper support portion and the lower support portion.

또한, 상기 수평부는 상기 수평 H빔이 두 개 이상 구비되는 것을 특징으로 한다. The horizontal portion may include two or more horizontal H beams.

이상에서 설명한 바와 같이,As described above,

본 발명은 비교적 구조가 간단하고, 동일규격으로 일체화되어 있어 설치 및 해체가 용이한 효과가 있다. INDUSTRIAL APPLICABILITY The present invention is relatively simple in structure and integrated with the same standard, so that it is easy to install and dismantle.

또한, 본 발명은 설치 및 해체가 용이함에 따라 공사기간을 대폭 단축할 수 있어 공사비를 절감하는 효과가 있다. In addition, since the present invention is easy to install and dismantle, the construction period can be greatly shortened and the construction cost can be reduced.

또한, 본 발명은 이미 설치된 관로 부위의 조립식 흙막이 장치를 분리하여 연장될 위치에 재 설치함으로써 관로 공사 현장의 전체 길이에 해당하는 조립식 흙막이 장치를 구비하지 않아도 되는 장점이 있다. Further, according to the present invention, there is an advantage that the prefabricated earthmoving device of the channel region already installed is separated and re-installed at the extended position, so that the prefabricated earthmoving device corresponding to the entire length of the pipeline construction site is not required.

도 1은 본 발명의 실시예에 따른 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치를 설치한 평면도이다.
도 2는 본 발명의 실시예에 따른 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치를 설치한 사시도이다.
도 3은 본 발명의 실시예에 따른 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치를 설치한 단면도이다.
도 4는 본 발명의 실시예에 따른 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치의 수직부 및 수평부를 나타낸 도면이다.
도 5는 본 발명의 실시예에 따른 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치의 강판부를 나타낸 도면이다.
도 6은 본 발명의 실시예에 따른 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치의 버팀부를 나타낸 도면이다.
FIG. 1 is a plan view of a prefabricated earthmoving apparatus for a pipeline construction that is easy to install and dismantle according to an embodiment of the present invention.
FIG. 2 is a perspective view of a prefabricated earthmoving apparatus for pipeline construction, which is easy to install and dismantle according to an embodiment of the present invention.
FIG. 3 is a cross-sectional view of a prefabricated earthmoving apparatus for pipeline construction that is easy to install and dismantle according to an embodiment of the present invention.
4 is a view showing a vertical part and a horizontal part of the assembled earthmoving device for pipeline construction which is easy to install and disassemble according to the embodiment of the present invention.
FIG. 5 is a view illustrating a steel plate portion of a prefabricated earthmoving apparatus for a pipeline construction that is easy to install and disassemble according to an embodiment of the present invention.
FIG. 6 is a view showing a strut part of the assembled earthmoving apparatus for a pipeline construction which is easy to install and dismantle according to an embodiment of the present invention.

이하, 첨부된 도면을 참조하여 본 발명의 바람직한 실시예를 상세하게 설명한다. 도면들 중 동일한 구성요소들은 가능한 어느 곳에서든지 동일한 부호로 표시한다. 또한 본 발명의 요지를 불필요하게 흐릴 수 있는 공지 기능 및 구성에 대한 상세한 설명은 생략한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the drawings, the same components are denoted by the same reference symbols whenever possible. In the following description, well-known functions or constructions are not described in detail since they would obscure the invention in unnecessary detail.

도 1 내지 도 6은 본 발명의 실시예에 따른 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치를 나타낸 도면으로서, 관로 공사용 조립식 흙막이 장치는 본체부(100), 강판부(130), 및 버팀부(140)를 포함한다.FIG. 1 is a perspective view of a conventional earthworking apparatus for pipeline construction according to an embodiment of the present invention. FIG. 1 is a perspective view of a conventional earthworking apparatus for a pipeline construction, (140).

본체부(100)는 수직부(110) 및 수평부(120)를 포함하며, 수직부(110)는 관(10)이 설치될 위치 양 측면으로 일정간격 이격하여 수직 H빔(111)이 나열되어 설치되고, 수평부(120)는 수직부(110)인 수직 H빔(111)과 수직 H빔(111) 사이의 웨브(112)와 웨브(112) 사이에 가로로 뉘어진 수평 H빔(121)이 위치되어 용접 또는 볼트 결합으로 형성된다. The body part 100 includes a vertical part 110 and a horizontal part 120. The vertical parts 110 are separated from each other at positions where the pipe 10 is to be installed, And the horizontal portion 120 is a vertical H beam 111 and a horizontal H beam 111 horizontally laid between the web 112 and the web 112 between the vertical H beam 111 and the vertical H beam 111, 121 are positioned and formed by welding or bolting.

여기서, 수직부(110)의 수직 H빔(111)은 도 4와 같이, 일측 플랜지(113)에 상기 버팀부(140)가 일직선으로 끼워져 결합될 수 있도록 하는 가이드부(114) 및 상기 가이드부(114)의 하부 방향에 일정간격 이격되어 상기 버팀부(140)가 일정깊이 이상 인입되는 것을 막아주는 걸림부(115)를 형성한다. 4, the vertical H beam 111 of the vertical part 110 includes a guide part 114 that allows the one of the flanges 113 to be coupled to the one of the flanges 113 by being fitted in a straight line, (115) spaced at a predetermined distance in the lower direction of the protrusion (114) to prevent the stretching part (140) from being drawn over a certain depth.

이때, 이와 같이 가이드부(114)와 걸림부(115)가 형성된 플랜지(113)는 관(10)이 위치될 방향으로 위치시키는 것이 바람직하다. 즉, 관(10)을 사이에 두고 위치한 양측의 수직 H빔(111)에 형성된 가이드부(114)와 걸림부(115)가 서로 마주보도록 형성된다. At this time, it is preferable that the flange 113 formed with the guide part 114 and the engaging part 115 is positioned in the direction in which the pipe 10 is positioned. That is, the guide portion 114 and the engaging portion 115 formed on the vertical H beams 111 located on both sides of the tube 10 are formed to face each other.

또한, 수평부(120)는 수평 H빔(121)의 웨브(122)에 길이 방향으로 강판 삽입홀(124)이 형성되고, 강판 삽입홀(124) 주변으로는 수평부(120)에 형성된 강판 삽입홀(124)에 강판부(130)가 용이하게 인입될 수 있도록 강판 인입 가이드부(125)를 더 형성한다.The horizontal part 120 has a steel plate insertion hole 124 formed in the longitudinal direction of the web 122 of the horizontal H beam 121 and a steel plate insertion hole 124 formed in the horizontal part 120 around the steel plate insertion hole 124. [ The steel plate pull-in guide portion 125 is further formed so that the steel plate portion 130 can be easily inserted into the insertion hole 124.

이때, 강판 인입 가이드부(125)는 인입되는 강판부(130)가 강판 삽입홀(124)에 인입되도록 강판 삽입홀(124)을 기준으로 웨브(122)의 외측 상단에 구비하여 외측으로 일정 각도를 주어 강판 삽입홀(124)이 형성된 내측으로 안내 될 수 있도록 형성한다. At this time, the steel plate pull-in guide portion 125 is provided at the outer upper end of the web 122 with respect to the steel plate insertion hole 124 so that the steel plate portion 130 to be drawn into the steel plate insertion hole 124 is guided outward at a predetermined angle So that the steel plate insertion hole 124 can be guided to the inside.

여기서, 수평부(120)인 수평 H빔(121)의 웨브(122)는 양측으로 수직 H빔(111)의 일측 플랜지(113) 폭만큼 더 돌출되어 수직 H빔(111)의 플랜지(113)와 플랜지(113) 사이의 웨브(112)에 용이하게 결합될 수 있도록 한다. The web 122 of the horizontal H beam 121 which is the horizontal part 120 is further projected to both sides by the width of the one flange 113 of the vertical H beam 111 to form the flange 113 of the vertical H beam 111, To the web 112 between the flange 113 and the flange 113.

이때, 수직부(110)과 수평부(120)는 용접 또는 볼트 결합하여 하나의 본체부(100)로 형성된다. At this time, the vertical portion 110 and the horizontal portion 120 are welded or bolted to form one body portion 100.

강판부(130)는 수평부(120)에 형성된 강판 삽입홀(124) 사이에 결합하여, 흙이 붕괴되는 것을 방지하도록 흙벽을 지지한다. The steel plate part 130 is coupled between the steel plate insertion holes 124 formed in the horizontal part 120 to support the earth wall to prevent the soil from collapsing.

일반적으로 공사현장에서 사용되는 강판부(130)는 안전을 위해 내구성이 뛰어나며 무게가 상당하여 사람의 힘으로 들어 올리거나 이동하는 것이 쉽지 않다. 그래서 강판부(130)는 도 5에 나타낸 바와 같이, 이동장비로 용이하게 이동시킬 수 있도록 이동장비와 결합시킬 수 있도록 강판부(130) 상단에 고리 형태의 이동결합부(131)를 형성한다. Generally, the steel plate 130 used in a construction site is excellent in durability for safety, and is heavy in weight, so it is not easy to lift or move by the force of a person. Therefore, as shown in FIG. 5, the steel plate part 130 is formed with a ring-shaped moving part 131 at the upper end of the steel plate part 130 so that the steel plate part 130 can be coupled with the mobile equipment so as to be easily moved to the mobile equipment.

본 발명의 실시예에서 강판부(130)는 두께가 6mm 이상인 후판(厚板)인 것이 바람직하며, 강판부(130)의 두께는 수평 H빔(121)에 형성된 강판 삽입홀(124)의 두께와 같거나 작은 것이 바람직하다. The thickness of the steel plate portion 130 is preferably set to be a thickness of the steel plate insertion hole 124 formed in the horizontal H beam 121, Is preferable.

또한, 강판부(130)의 폭은 수평 H빔(121)에 형성된 강판 삽입홀(124)의 길이와 같거나 작은 것이 바람직하다. The width of the steel plate part 130 is preferably equal to or smaller than the length of the steel plate insertion hole 124 formed in the horizontal H beam 121. [

버팀부(140)는 관(10)을 사이에 두고 서로 마주보는 수직 H빔(111) 사이에 위치시켜 강판부(130)가 붕괴되지 않도록 지지한다.The stretching part 140 is positioned between the vertical H beams 111 facing each other with the tube 10 interposed therebetween to support the steel plate part 130 so as not to collapse.

상기 버팀부(140)는 상부 지지부(141) 및 하부 지지부(142)를 포함하며, 양측면으로 상부 지지부(141) 및 하부 지지부(142)를 연결하는 연결부(143)를 포함하고, 상부 지지부(141)의 양측과 하부 지지부(142)의 양측은 연결부(143)와 결합되되, 상기 연결부(143)의 결합축(144)에 의해 상하로 회전 동작한다. The supporting portion 140 includes an upper supporting portion 141 and a lower supporting portion 142 and includes a connecting portion 143 for connecting the upper supporting portion 141 and the lower supporting portion 142 on both sides thereof, And both sides of the lower support part 142 and the lower support part 142 are coupled with the connection part 143 and rotated up and down by the coupling shaft 144 of the connection part 143. [

도 6과 같이, 상부 지지부(141) 및 하부 지지부(142)는 상하로 회전 동작을 함으로써 서로 대향하는 수직 H빔(111)과 수직 H빔(111) 사이에 삽입이 원활하게 이루어질 수 있다. As shown in FIG. 6, the upper support portion 141 and the lower support portion 142 are rotated up and down, so that insertion can be smoothly performed between the vertical H beam 111 and the vertical H beam 111, which are opposed to each other.

상부 지지부(141)와 하부 지지부(142)의 회전 각도는 상부 지지부(141) 및 하부 지지부(142) 하단에 각각 위치한 회동제한수단(145)이 닿는 각도까지만 가능하고, 버팀부(140)가 가이드부(114)를 따라 수직 H빔(111)과 수직 H빔(111) 사이에 안착되어 걸림부(115)까지 인입되면 버팀부(140)의 상부 지지부(141) 및 하부 지지부(142)는 수평을 이루게 된다. The rotation angle of the upper support portion 141 and the lower support portion 142 can be limited up to an angle that the rotation limiting means 145 located at the lower end of the upper support portion 141 and the lower end of the lower support portion 142, The upper supporting part 141 and the lower supporting part 142 of the supporting part 140 are positioned horizontally between the vertical H beam 111 and the vertical H beam 111 along the part 114, .

여기서, 상부 지지부(141), 하부 지지부(142), 및 연결부(143)는 사다리형상의 일체형으로 형성된다. Here, the upper support portion 141, the lower support portion 142, and the connection portion 143 are integrally formed in a ladder shape.

또한, 상부 지지부(141) 및 하부 지지부(142)가 연결부(143)에 의해 일체형으로 형성되지 않고, 개별적으로 상부 지지부(141) 및 하부 지지부(142)가 구비된다면, 동일한 작업을 두 번 반복해서 수행해야 하는 단점이 있을 뿐만 아니라, 나사 결합에 의해 결합되지 않으면 수평을 맞추기 위해 많은 시간이 소요되는 단점이 있다. Also, if the upper support 141 and the lower support 142 are not integrally formed by the connection 143 but are separately provided with the upper support 141 and the lower support 142, There is a disadvantage in that it takes a lot of time to adjust the level if it is not coupled by screw coupling.

관로 공사 시 설치되는 관(10)의 크기는 규격으로 정하고 있고, 터파기시 사용되는 장비로 터파기를 진행 할 때, 항상 일정한 폭을 유지하면서 터파기를 진행하기 때문에 일정한 규격의 버팀부(140)를 통해 수평으로 양측의 강판부(130)를 지지할 수 있다. The size of the pipe (10) to be installed at the time of pipe line construction is set as a standard, and when the treader is operated with the equipment used in the tearing operation, the treading operation is continued while maintaining a constant width. So that the steel plate portions 130 on both sides can be horizontally supported.

또한, 본 발명의 실시예에 따른 조립식 흙막이 장치는 복잡한 구조로 결합된 방법이 아니라 쉽게 설치 및 해체가 용이하여 관로 공사 시 이미 설치가 완료된 관로 부위는 흙이 메워져야 하므로 설치가 완료된 관로 부위의 본체부(100), 강판부(130), 및 버팀부(140)를 분리하여 관로가 연장될 위치에 재설치하여 관로공사를 진행할 수 있기 때문에 많은 자재가 필요치 않아 공사비를 대폭 절감할 수 있다.In addition, the prefabricated earth moving device according to the embodiment of the present invention is not a method combined with a complicated structure, but is easy to install and disassemble. Therefore, Since the pipe 100 can be separated from the steel plate part 130 and the brace part 140 and can be reinstalled at a position where the pipe line is extended, the piping work can be performed.

따라서, 본 발명은 비교적 구조가 간단하고, 동일규격으로 일체화되어있어 설치 및 해체가 용이한 효과가 있다. Therefore, the present invention is relatively simple in structure and integrated with the same standard, which facilitates installation and disassembly.

또한, 본 발명은 설치 및 해체가 용이함에 따라 공사기간을 대폭 단축할 수 있어 공사비를 절감하는 효과가 있다. In addition, since the present invention is easy to install and dismantle, the construction period can be greatly shortened and the construction cost can be reduced.

상기와 같은 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치는 위에서 설명된 실시예들의 구성과 작동 방식에 한정되는 것이 아니다. 상기 실시예들은 각 실시예들의 전부 또는 일부가 선택적으로 조합되어 다양한 변형이 이루어질 수 있도록 구성될 수도 있다. The assembled earth moving device for pipeline construction which is easy to install and disassemble as described above is not limited to the configuration and the operation method of the embodiments described above. The embodiments may be configured so that all or some of the embodiments may be selectively combined so that various modifications may be made.

10 : 관 100 : 본체부
110 : 수직부 111 : 수직 H빔
112 : 웨브 113 : 플랜지
114 : 가이드부 115 : 걸림부
120 : 수평부 121 : 수평 H빔
122 : 웨브 123 : 플랜지
124 : 강판 삽입홀 125 : 강판 인입 가이드부
130 : 강판부 131 : 이동결합부
140 : 버팀부 141 : 상부 지지부
142 : 하부 지지부 143 : 연결부
144 : 결합축 145 : 회동제한수단
10: tube 100:
110: vertical part 111: vertical H beam
112: web 113: flange
114: guide portion 115:
120: Horizontal part 121: Horizontal H beam
122: web 123: flange
124: steel plate insertion hole 125: steel plate insertion guide part
130: steel plate part 131:
140: Support part 141: Upper support
142: lower support portion 143:
144: coupling shaft 145: rotation restricting means

Claims (8)

관로 공사시 측면 붕괴를 방지하기 위한 관로공사용 조립식 흙막이 장치에 있어서,
관이 설치될 위치 양 측면으로 일정간격 이격하여 수직으로 수직 H빔이 나열되어 설치되는 수직부 및 상기 수직 H빔과 수직 H빔 사이의 웨브와 웨브 사이에 가로로 뉘어진 수평 H빔이 위치되되, 상기 수평 H빔의 웨브에 길이 방향으로 강판 삽입홀이 형성된 수평부가 용접 또는 볼트 결합되어 형성된 본체부;
상기 수평부에 형성된 상기 강판 삽입홀 사이에 결합하여, 흙이 붕괴되는 것을 방지하도록 흙벽을 지지하는 강판부; 및
상기 관을 사이에 두고 서로 마주보는 상기 수직 H빔 사이에 위치하여 상기 강판부가 붕괴되지 않도록 지지하는 버팀부;를 포함하는 것을 특징으로 하는 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치.
A prefabricated earthmoving apparatus for pipeline construction for preventing lateral collapse during pipeline construction,
A vertical H beam is vertically arranged at regular intervals spaced from both sides of the pipe where the pipe is to be installed, and a horizontal H beam horizontally laid between the web and the web between the vertical H beam and the vertical H beam is positioned A body portion formed by welding or bolting a horizontal portion formed with a steel plate insertion hole in the longitudinal direction in the web of the horizontal H beam;
A steel plate portion coupled between the steel plate insertion holes formed in the horizontal portion and supporting the earth wall to prevent the earth from collapsing; And
And a brace part positioned between the vertical H beams facing each other with the pipe therebetween to prevent the steel plate from being collapsed.
청구항 1에 있어서,
상기 버팀부는 상부 지지부 및 하부 지지부를 포함하며, 양측면으로 상부 지지부 및 하부 지지부를 연결하는 연결부를 포함하되,
상기 상부 지지부의 양측과 하부 지지부의 양측은 연결부와 결합되되, 상기 연결부의 결합축에 의해 상하로 회동되는 것을 특징으로 하는 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치.
The method according to claim 1,
The supporting part includes an upper supporting part and a lower supporting part, and a connecting part connecting both the upper supporting part and the lower supporting part on both sides,
Wherein both sides of the upper support part and both sides of the lower support part are coupled with the connection part and are vertically rotated by the coupling shaft of the connection part.
청구항 1에 있어서,
상기 수직부는 내측 플랜지에 상기 버팀부가 일직선으로 끼워져 결합될 수 있도록 가이드부; 및
상기 가이드부의 하부 방향에 일정간격 이격되어 상기 버팀부가 일정깊이 이상 인입되는 것을 막아주는 걸림부;를 더 포함하는 것을 특징으로 하는 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치.
The method according to claim 1,
The vertical portion may include a guide portion to be engaged with the inner flange in a straight line, And
And a locking part spaced apart from the guide part by a predetermined distance to prevent the supporting part from being inserted to a predetermined depth or more.
청구항 1에 있어서,
상기 수평부인 수평 H빔의 웨브는 양측으로 상기 수직 H빔의 일측 플랜지 폭만큼 더 돌출되는 것을 특징으로 하는 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치.
The method according to claim 1,
Wherein the web of the horizontal H beam is further protruded to both sides of the vertical H beam by one flange width of the vertical H beam.
청구항 1에 있어서,
상기 수평부에 형성된 홀에 상기 강판부가 용이하게 인입될 수 있도록, 상기 홀 주변에 강판 인입 가이드부;를 더 포함하는 것을 특징으로 하는 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치.
The method according to claim 1,
Further comprising a steel plate pull-in guide portion around the hole so that the steel plate portion can be easily inserted into the hole formed in the horizontal portion.
청구항 1에 있어서,
상기 강판부는 이동장비로 용이하게 이동시킬 수 있도록 이동장비와 결합시킬 수 있는 고리 형태의 이동결합부를 더 포함하는 것을 특징으로 하는 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치.
The method according to claim 1,
Wherein the steel plate part further comprises a ring-shaped moving coupling part that can be coupled with the mobile equipment so that the steel plate part can be easily moved to the mobile equipment.
청구항 2에 있어서,
상기 상부 지지부 및 하부 지지부의 상하 회전동작에 제한을 두기 위해 상기 상부 지지부 및 하부 지지부의 하단에 회동제한수단을 구비하는 것을 특징으로 하는 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치.
The method of claim 2,
Wherein the upper supporting portion and the lower supporting portion are provided with rotation restricting means at the lower ends of the upper supporting portion and the lower supporting portion so as to limit the upward and downward rotational movements of the upper supporting portion and the lower supporting portion.
청구항 1에 있어서,
상기 수평부는 상기 수평 H빔이 두 개 이상 구비되는 것을 특징으로 하는 설치 및 해체가 용이한 관로 공사용 조립식 흙막이 장치.

The method according to claim 1,
Wherein the horizontal portion includes at least two horizontal H beams.

KR1020160063971A 2016-05-25 2016-05-25 Prefabricated retaining device for building the pipeline easy to install and dismantle KR20170133035A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160063971A KR20170133035A (en) 2016-05-25 2016-05-25 Prefabricated retaining device for building the pipeline easy to install and dismantle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160063971A KR20170133035A (en) 2016-05-25 2016-05-25 Prefabricated retaining device for building the pipeline easy to install and dismantle

Publications (1)

Publication Number Publication Date
KR20170133035A true KR20170133035A (en) 2017-12-05

Family

ID=60920971

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160063971A KR20170133035A (en) 2016-05-25 2016-05-25 Prefabricated retaining device for building the pipeline easy to install and dismantle

Country Status (1)

Country Link
KR (1) KR20170133035A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3043674U (en) * 1997-05-22 1997-11-28 佐九郎 佐藤 Frame for assembly and disassembly of seating plate

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3043674U (en) * 1997-05-22 1997-11-28 佐九郎 佐藤 Frame for assembly and disassembly of seating plate

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
일본 등록실용신안공보 실용신안등록 제 3043674호(1997.11.28.) 1부. *

Similar Documents

Publication Publication Date Title
KR101640971B1 (en) Connecting a sheet pile for retaining wall
KR100575420B1 (en) A shoring structure using concrete member
KR101656367B1 (en) Temporary Construction Method of Soil Arresting Structure for Laying Pipe Below Rood
CN108755706B (en) Movable foundation pit inner support system and foundation pit construction method
KR100812722B1 (en) Bracket and Support for Prestressed Scaffolding System
KR100753021B1 (en) The subterranean soil flow wall construction method which formed the institution thing installation space part using main girder compression reaction
KR20140042132A (en) Construction method of the underground tunnel and, structure for the slab construction
JP2017137688A (en) Earth retaining method and supporting system
KR101619330B1 (en) Horizontal Beam Supporting Bracket for Temporary Soil Retaining Work
KR101182820B1 (en) Self-sustaining earth retaining panel for pipe conduit construction
KR20170133035A (en) Prefabricated retaining device for building the pipeline easy to install and dismantle
KR20100001516A (en) Joint structure for connecting slant supporter and square steel strut for temporary soil sheathing work
KR200389266Y1 (en) Slide rail type shoring apparatus
KR101221084B1 (en) Temporary pile using bending restoring force and temporary structure construction method therewith
KR101664668B1 (en) Structure for connecting earth retaining wall
KR20190142547A (en) Improved earth soil pre-stress method
KR102185246B1 (en) Temporary retaining wall system and construction method thereof
JP7301203B1 (en) Earth retaining device for shallow excavated trenches
KR101899859B1 (en) Temporary retaining wall structure
KR102172119B1 (en) Extendable panel for retainer wall and retainer wall thereof
KR20210098162A (en) Under ground structure using column steel pipe wall and construction method thereof
KR101042556B1 (en) Fence supporting device for water works
KR102633792B1 (en) The moving type shoring apparatus
KR200416567Y1 (en) Pile chamber type trench shoring apparatus
KR200416514Y1 (en) Length Control Type Steel Pipe Strut

Legal Events

Date Code Title Description
A201 Request for examination