KR20170111858A - The construction method precast prestressed concrete parking buildings with precast concrete wall panels - Google Patents

The construction method precast prestressed concrete parking buildings with precast concrete wall panels Download PDF

Info

Publication number
KR20170111858A
KR20170111858A KR1020160038058A KR20160038058A KR20170111858A KR 20170111858 A KR20170111858 A KR 20170111858A KR 1020160038058 A KR1020160038058 A KR 1020160038058A KR 20160038058 A KR20160038058 A KR 20160038058A KR 20170111858 A KR20170111858 A KR 20170111858A
Authority
KR
South Korea
Prior art keywords
wall panel
panel member
wall
slab
parking lot
Prior art date
Application number
KR1020160038058A
Other languages
Korean (ko)
Other versions
KR102507299B1 (en
Inventor
유승룡
Original Assignee
동국대학교 산학협력단
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 동국대학교 산학협력단 filed Critical 동국대학교 산학협력단
Priority to KR1020160038058A priority Critical patent/KR102507299B1/en
Publication of KR20170111858A publication Critical patent/KR20170111858A/en
Application granted granted Critical
Publication of KR102507299B1 publication Critical patent/KR102507299B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H6/00Buildings for parking cars, rolling-stock, aircraft, vessels or like vehicles, e.g. garages
    • E04H6/08Garages for many vehicles
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • E04B1/34315Structures characterised by movable, separable, or collapsible parts, e.g. for transport characterised by separable parts
    • E04B1/34321Structures characterised by movable, separable, or collapsible parts, e.g. for transport characterised by separable parts mainly constituted by panels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • E04B1/34384Assembling details for foldable, separable, collapsible or retractable structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

본 발명은 보와 기둥을 일체형으로 하나의 PC벽 패널부재로 제작하여 지상 PC 주차장을 시공할 수 있도록 함으로서, 보와 기둥이 일체형으로 된 PC 벽 패널부재와; 상기 바닥에 설치되어 PC 벽 패널부재를 고정할 수 있도록 된 받침부재와; 상기 PC 벽 패널부재에 일체로 형성된 상단 보 양측에 다수의 슬래브가 설치되도록 형성된 걸림부를 구성한 것으로 본 발명은 주차장 건물 시공시 PC 부재의 개수를 최소화하고 공기를 단축하여 최소한의 공사비용으로 PC 주차장을 시공할 수 있도록 하는 동시에 지진에 대한 횡 지지능력을 증가시킬 수 있도록 하여 내진설계가 적용되도록 한 프리캐스트 프리스트레스 콘크리트 벽 패널을 이용한 지상 PC 주차장 및 그 시공방법에 관한 것이다.The present invention relates to a PC wall panel member in which a beam and a pillar are integrally formed into a single PC wall panel member so that a ground PC park can be constructed, A support member installed on the floor so as to fix the PC wall panel member; The present invention minimizes the number of PC members and shortens the air at the time of constructing a parking lot, thereby minimizing the construction cost of the PC parking lot at a minimum construction cost. The present invention relates to a ground PC parking lot using precast prestressed concrete wall panels and a method of constructing the precast concrete park walls using earthquake resistant design so that the earthquake resistance can be increased.

Description

프리캐스트 프리스트레스 콘크리트 벽 패널을 이용한 지상 PC 주차장 및 그 시공방법{ THE CONSTRUCTION METHOD PRECAST PRESTRESSED CONCRETE PARKING BUILDINGS WITH PRECAST CONCRETE WALL PANELS} TECHNICAL FIELD [0001] The present invention relates to a precast concrete wall panel and a precast concrete wall panel,

본 발명은 보와 기둥을 일체형으로 하나의 PC 벽 패널부재로 제작하여 지상 PC 주차장을 시공할 수 있도록 함으로서, 주차장 건물 시공시 PC 부재의 개수를 최소화하고 공기를 단축하여 최소한의 공사비용으로 PC 주차장을 시공할 수 있도록 하고, 지진에 대한 횡 지지능력을 증가시킬 수 있도록 하여 내진설계가 적용되도록 한 프리캐스트 프리스트레스 콘크리트 벽 패널을 활용한 지상 PC 주차장 및 그 시공방법에 관한 것이다.The present invention minimizes the number of PC members and shortens the air during construction of a parking lot by constructing a PC wall panel member by integrally forming a beam and a pillar to construct a ground PC parking lot, The present invention relates to a ground PC parking lot utilizing precast prestressed concrete wall panels, and a construction method thereof, in which seismic design is applied so as to increase lateral supportability against earthquakes.

일반적인 지상 주차장은 철골 빔을 이용하여 타공된 철판을 슬래브로 설치하여 사용함으로 차량 운행시 시끄러운 소음이 발생되고, 장기간 사용시 용접부위가 노출된 상태이므로 녹이나 부식이 발생되고, 우천시 누수가 발생되어 주기적으로 보수 공사가 필요할 뿐만 아니라 외관상 고급스럽지 못한 문제점이 있다.In general, the ground parking lot is constructed by using slabs installed by using iron steel beams with steel beams, so there is a loud noise when the vehicle is driven, and the welds are exposed during long-term use, so rust and corrosion occur, And there is a problem in that it is not luxurious in appearance.

또한 콘크리트 구조물의 지상 주차장은 진동을 방지하고, 누수가 없으며, 주기적으로 보수공사가 필요 없으나, 공사기간이 많이 소요되고 공사비용이 상승되는 문제점이 있다. Also, the ground parking lot of the concrete structure prevents vibration, does not leak, and periodically requires no repair work, but it takes a long period of construction and increases the construction cost.

상기와 같은 철골 빔과 철판을 이용한 지상주차장의 문제점과 콘크리트를 이용한 지상주차장의 문제점을 해소하기 위해 최근에는 PC 패널을 이용한 지상구조물을 시공함으로써 공사기간을 단축하고 공사비용을 줄이는 사례가 많아지고 있다. Recently, in order to solve the problems of the ground parking lot using the steel beam and the steel plate and the problem of the ground parking lot using the concrete as described above, there have been many cases of shortening the construction period and reducing the construction cost by constructing the ground structure using the PC panel .

공장에서 제작되는 콘크리트 부재 중 프리스트레스를 도입한 콘크리트를 PS콘크리트 또는 PSC라 하고, 보통 콘크리트로 하는 것을 PC콘크리트라 하는데, 본 명세서에서는 이들을 통칭하여 PC(Precast Concrete)라 한다.Among the concrete members manufactured in the factory, the concrete in which the prestress is introduced is referred to as PS concrete or PSC, and the concrete made in ordinary concrete is referred to as PC concrete. In the present specification, these are collectively referred to as PC (Precast Concrete).

따라서 공장에서 제작하고 현장 조립 시공하는 PC 제품은 구조물의 품질이 좋고 시공이 간편하며, 공사를 조기에 완료할 수 있어 공사기간이 단축되며, 특히 인력 및 가설재 투입이 적어 재해 발생 우려가 적은 장점이 있다.Therefore, PC products manufactured at the factory and assembled on-site are good in structure quality, easy to construct, can be completed early, shortening the construction period, and having less risk of disasters due to fewer manpower and temporary inputs have.

이 분야의 선행기술을 살펴 보면 공개특허공보 제10-2005-0090970호(이하 "선행기술 1"이라 한다)의 조립식 주차장치는 상하 좌우로 조립이 가능한 주차블럭(100)과, 상기 대향하는 주차블럭(100)에 지지되어 차량(C)의 통로 기능을 하는 판상의 슬래브(200)를 철근콘크리트로 구성하여, 다양한 크기와 디자인의 주차장치의 시공이 가능하고, 부식에 의한 고장이나 내구력 상실의 문제가 발생하지 않아 안정성이 확보되고, 공기가 짧고, 시공비가 적게 소요되며, 분리한 후 이송하여 재활용이 가능하도록된 구성이 개시되었다 .[0005] In view of the prior art in this field, the prefabricated parking lot of the Japanese Patent Application Laid-Open No. 10-2005-0090970 (hereinafter referred to as "Prior Art 1") has a parking block 100 that can be assembled up and down and right and left, The slab 200 of the plate shape supported by the railway car 100 is constructed of reinforced concrete to enable construction of parking apparatuses of various sizes and designs and a problem of failure due to corrosion or loss of durability So that stability is ensured, air is short, the construction cost is low, and the recycling can be performed by separating and transporting the separator.

또 다른 선행기술로는 등록특허공보 제10-1385556호(이하 "선행기술 2"이라한다) PC를 이용한 지하구조물 및 그 조립공법 지하구조물이 시공될 바닥에 타설되어서 지하구조물의 베이스를 이루는 기초콘크리트(10); 직사각형을 이루도록 기초콘크리트(10)의 상부면에 배열되고 지하구조물의 네 측벽을 이루며 내부에 철근(28)이 배근되고 철근(28)의 상하단이 상하부에 노출되며 지하구조물의 중량에 의한 수직압 및 토압의 수평압을 지지하는 다수의 외부벽체(20);다수 배열된 외부벽체들 중 최외측의 외부벽체에 결합되고 지하구조물의 측벽 모서리의 한 부분을 이루며 내부에 철근(38)이 배근되며 철근(38)의 상하단이 상하부에 노출되고 지하구조물의 중량에 의한 수직압 및 토압의 수평압을 지지하는 제1코너벽체(30); 외부벽체 및 제1코너벽체 사이에 결합되고 지하구조물의 측벽 모서리의 나머지 부분을 이루며 내부에 철근(48)이 배근되고 철근(48)의 상하단이 상하부에 노출되며 지하구조물의 중량에 의한 수직압 및 토압의 수평압을 지지하는 제2코너벽체(40); 외부벽체(20) 및 제1코너벽체(30), 제2코너벽체(40)의 하부에 노출된 철근에 연결되는 바닥철근(50); 바닥철근(50)의 상부의 기초콘크리트(10) 상부면에 타설되어서 지하구조물의 바닥을 이루는 바닥콘크리트(60); 외부벽체(20) 및 제1코너벽체(30), 제2코너벽체(40)의 상부면에 안착되고 외부벽체(20) 및 제1코너벽체(30), 제2코너벽체(40)의 상부로 노출된 철근(28)(38)(48)에 연결되는 하프슬라브(70); 하프슬라브(70)의 상부에 타설되는 토핑콘크리트(80)를 포함하여 이루어지고; 외부벽체(20)는, 기초콘크리트(10)의 상부면에 안착되고 지하구조물의 벽체 두께보다 더 두꺼운 수평폭을 가지며 지하구조물의 벽체보다 더 내측으로 돌출되어 있고 토압의 수평압을 지지하는 수평압지지부(21)와, 수평압지지부(21)의 외측단부에 수직으로 형성되어 있어 수평압지지부(21)와 함께 ㄴ자 형태를 이루고 상부에 하프슬라브(70) 단부가 안착되도록 상부단턱(24)이 형성되어 있으며 일측면에 측면결합홈(25)이 형성되어 있고 타측면에 측면결합돌기(26)가 돌출되어 있으며 지하구조물의 수직하중을 지지하는 수직압지지부(22)와, 수평압지지부(21) 및 수직압지지부(22)의 이음부위에 형성되어서 이음부위에 집중되는 응력을 분산시키는 보강부(23)로 이루어지며;As another prior art, an underground structure using a PC (registered trademark) No. 10-1385556 (hereinafter referred to as "Prior Art 2") and an assembly method thereof are placed on the floor where the underground structure is to be installed, (10); The upper and lower ends of the reinforcing bars 28 are exposed at the upper and lower portions of the reinforcing bars 28 and the vertical pressure due to the weight of the underground structure A plurality of outer walls 20 for supporting the horizontal pressure of the earth pressure, a plurality of outer walls formed on the outermost wall of the plurality of outer walls, A first corner wall 30 exposing the upper and lower ends of the upper and lower walls 38 and supporting the horizontal pressure of the vertical pressure and the earth pressure by the weight of the underground structure; The reinforcing bars 48 are inserted between the outer wall and the first corner wall to form the remainder of the side wall edges of the underground structure and the upper and lower ends of the reinforcing bars 48 are exposed to the upper and lower portions. A second corner wall (40) supporting a horizontal pressure of the earth pressure; An outer wall 20 and a first corner wall 30, a bottom reinforcing bar 50 connected to a reinforcing bar exposed at a lower portion of the second corner wall 40; A bottom concrete 60 placed on the upper surface of the foundation concrete 10 at the upper part of the bottom steel bar 50 and forming the bottom of the underground structure; The outer wall 20 and the first corner wall 30 are positioned on the upper surface of the second corner wall 40 and the outer wall 20 and the first corner wall 30, A half slab 70 connected to the exposed reinforcing bars 28, 38, 48; And topping concrete (80) laid on top of the half slab (70); The outer wall 20 has a horizontal width that is greater than the wall thickness of the underground structure and is projected inwardly from the wall of the underground structure and is supported on the upper surface of the foundation concrete 10, And an upper step 24 is formed on the upper end of the horizontal slit 70 so that the upper half of the half slab 70 is seated on the upper side with the horizontal slit 21, A vertical pressure receiving portion 22 for supporting a vertical load of the underground structure and having a lateral coupling groove 25 formed on one side thereof and a side coupling protrusion 26 protruded on the other side thereof, And a reinforcing part (23) formed at a joint part of the vertical pressure receiving part (22) and dispersing stress concentrated on the joint part;

제1코너벽체(30)는, 기초콘크리트(10)의 상부면에 안착되고 지하구조물의 벽체 두께보다 더 두꺼운 수평폭을 가지며 지하구조물의 벽체보다 더 내측으로 돌출되어 있고 토압의 수평압을 지지하는 제1코너수평압지지부(31)와, 제1코너수평압지지부(31)의 외측 단부에 수직으로 형성되어 있어 제1코너수평압지지부(31)와 함께 ㄴ자 형태를 이루고 상부에 하프슬라브(70) 단부가 안착되도록 제1 코너 상부단턱(34)이 형성되어 있으며 일측면에 외부벽체(20)의 측면결합돌기(26)가 삽입되도록 외부벽체결합홈(35)이 형성되어 있고 타측면에 코너벽체결합돌기(36)가 형성되어 있으며지하구조물의 수직하중을 지지하는 제1코너수직압지지부(32)와, 제1코너수평압지지부(31) 및 제1코너수직압지지부(32)의 이음부위에 형성되어서 이음부위에 집중되는 응력을 분산시키는 제1코너보강부(33)로 이루어지고;The first corner wall 30 is mounted on the upper surface of the foundation concrete 10 and has a horizontal width that is thicker than the wall thickness of the underground structure and protrudes more inward than the wall of the underground structure and supports the horizontal pressure of the earth pressure The first corner horizontal pressure receiving portion 31 and the first corner horizontal pressure receiving portion 31 are formed perpendicular to the outer end of the first corner horizontal pressure receiving portion 31 and are formed in the form of a square with the first corner horizontal pressure receiving portion 31, And a first corner upper step 34 is formed on the other corner so that the end portion of the outer wall 20 is seated on the outer wall 20. An outer wall engaging groove 35 is formed on one side of the outer wall 20 so as to insert the side wall engaging projection 26, A first corner vertical pressure support portion 32 for supporting a vertical load of the underground structure and a joint of the first corner horizontal pressure support portion 31 and the first corner vertical pressure support portion 32, To disperse the stress concentrated at the joint site First corner is made of a reinforcement (33);

제2코너벽체(40)는, 기초콘크리트(10)의 상부면에 안착되고 지하구조물의 벽체 두께보다 더 두꺼운 수평폭을 가지며 지하구조물의 벽체보다 더 내측으로 돌출되어 있고 토압의 수평압을 지지하는 제2코너수평압지지부(41)와, 제2코너수평압지지The second corner wall 40 is mounted on the upper surface of the foundation concrete 10 and has a horizontal width that is thicker than the wall thickness of the underground structure and protrudes more inward than the wall of the underground structure and supports the horizontal pressure of the earth pressure A second corner horizontal pressing portion 41, a second corner horizontal pressing portion 41,

부(41)의 외측 단부에 수직으로 형성되어 있어 제2코너수평압지지부(41)와 함께 ㄴ자 형태를 이루고 상부에 하프슬라브(70) 단부가 안착되도록 제2코너상부단턱(44)이 형성되어 있으며 일측면에 코너벽체결합홈(45)이 형성되어 있고 타측면에 외부벽체(20)의 측면결합홈(25)에 삽입되도록 외부벽체결합돌기(46)가 형성되어 있으며 지하구조물의 수직하중을 지지하는 제2코너수직압지지부(42)와, 제2코너수평압지지부(41) 및 제2코너수직압지지부(42)의 이음부위에 형성되어서 이음부위에 집중되는 응력을 분산시키는 제2코너보강부(43)로 이루어지고; 외부벽체(20), 제1코너벽체(30), 제2코너벽체(40)에는, 각각 강선홀(27)(37)(47)이 형성되되,A second corner upper step 44 is formed so as to be in the form of a square with the second corner horizontal pressure receiving part 41 and to have an end of the half slab 70 mounted on the upper part thereof, And an outer wall coupling protrusion 46 is formed on the other side of the outer wall 20 so as to be inserted into the side coupling groove 25 of the outer wall 20 and a vertical load of the underground structure A second corner vertical pressure support portion 42 for supporting the second corner vertical pressure support portion 42 and a second corner vertical pressure support portion 42 formed on the joint portion between the second corner horizontal pressure support portion 41 and the second corner vertical pressure support portion 42, A reinforcing portion 43; Steel wire holes 27, 37 and 47 are formed in the outer wall 20, the first corner wall 30 and the second corner wall 40, respectively,

외부벽체(20), 제1코너벽체(30), 제2코너벽체(40)를 직사각틀 형태로 배열시킬 시, 건축구조물의 각 벽면에 형성된 강선홀(27)(37)(47)들이 동일 수평선상에 위치되고, 동일 수평선상에 위치된 강선홀(27)(37)(47)들에는 강선(90)이 통과되며, 강선(90)의 양단을 인장시켜서 각 벽면들을 이루는 외부벽체(20)들, 제1코너벽체(30), 제2코너벽체(40)를 하나의 블록으로 결속시키도록 된 것을 특징으로 하는 PC를 이용한 지하구조물이 개시되었다.When the outer wall 20, the first corner wall 30 and the second corner wall 40 are arranged in a rectangular frame shape, the steel wire holes 27, 37 and 47 formed on the wall surfaces of the building structure are the same The steel wire 90 is passed through the steel wire holes 27, 37 and 47 positioned on the same horizontal line and the both ends of the steel wire 90 are stretched to form the outer wall 20 , The first corner wall 30, and the second corner wall 40 are bound to one block.

상기 선행기술 1은 ∩자 형의 암거형태로 주차블럭(100)을 형성하고 주차블럭과 주차블럭 사이에 슬래부(200)설치하여 이루어진 구성으로서, 이러한 구성은 건축형태의 주차장이 아니라 차량 1대만 주차할 수 있는 공간부를 형성활 수 있도록된 구조물로서 다수의 주차블럭을 븍럭 쌓듯이 적층하는 것으로 주차공간을 형성한다 하더라도 각각의 주차블럭 측벽이 겹쳐 설치됨으로 필요 이상의 공간부를 차지하게 됨으로 공간활용을 효율적으로 하지 못화는 문제점이 있다.In the prior art 1, a parking block 100 is formed in a cube-shaped culvert shape, and a slab part 200 is installed between a parking block and a parking block. The parking space is formed by stacking a plurality of parking blocks such that the parking spaces can be formed by overlapping the side wall of each parking block, There is a problem with the problem.

또한 상기 선행기술 2는 PC를 이용한 지하구조물은, 기초콘크리트(10), 외부벽체(20), 제1코너벽체(30), 제2코너벽체(40), 바닥철근(50), 바닥콘크리트(60), 하프슬라브(70), 토핑콘크리트(80)로 형화된 PC를 이용하여서 우수저류조, 지하주차장 등의 지하구조물의 조립공수를 단축시킬 수 있도록 한 PC를 이용한 지하구조물에 관한 것으로 자하의 토압을 지지하도록 구성된 것으로 선행기술 2는 바닥에 콘크리트 타설작업을 시행하여야 하는 점과 상부 주차장을 형성하기 위한 연속적인 구성이 없는 것으로 지하 주차장에 한정된 구성으로 지상주차장으로는 시공할 수 없는 구조로 이루어진 문제점이 있다. In the prior art 2, an underground structure using a PC is composed of a base concrete 10, an outer wall 20, a first corner wall 30, a second corner wall 40, a bottom reinforcing bar 50, The present invention relates to an underground structure using a PC capable of shortening the number of assemblies of an underground structure such as a storeroom tank and an underground parking lot by using a PC typified by a half slab 70, a top slab 70, and a topping concrete 80, The prior art 2 has a problem that the concrete should be poured on the floor and there is no continuous structure for forming the upper parking lot, and the construction is limited to the underground parking lot, .

대한민국 공개특허공보 제10-2005-0090970호Korean Patent Publication No. 10-2005-0090970 대한민국 등록특허공보 제10-1385556호Korean Patent Publication No. 10-1385556

본 발명은 보와 기둥을 일체형으로 하나의 PC벽 패널부재로 제작하여 지상 PC 주차장의 시공할 수 있도록 한 것으로 주차장 건물 시공시 PC 부재의 개수를 최소화하고 공기를 단축하여 최소한의 공사비용으로 PC 주차장을 시공할 수 있도록 하는 목적과, 또 다른 목적으로는 보와 기둥을 일체형으로 하나의 PC벽 패널부재를 사용함으로 수직선상 층간을 연속적으로 조림시공 함으로 협소한 면적에서 다수의 지상 주차장 공간을 제공할 수 있도록 한 목적과, 또한 본 발명은 지진에 대한 횡 지지능력을 증가시킬 수 있도록 하여 내진설계가 적용되도록 한 프리캐스트 프리스트레스 콘크리트 벽 패널을 활용한 지상 PC 주차장 및 그 시공방법에 관한 것이다.The present invention minimizes the number of PC members and shortens the air at the construction of a parking lot by constructing a single PC wall panel member with a beam and a column, And another purpose is to provide a plurality of ground parking spaces in a narrow area by continuously stowing the vertical line layers by using one PC wall panel member integrally with beams and pillars The present invention also relates to a terrestrial PC parking lot utilizing a precast concrete wall panel to which seismic design is applied so as to increase lateral supportability against an earthquake, and a construction method thereof.

본 발명은 상기와 같은 목적을 달성하기 위한 해결 수단으로서, 조립식 PC 주차장에 있어서,According to another aspect of the present invention, there is provided a prefabricated PC parking lot,

보와 기둥이 일체형으로 이루어지며 높이보다 횡 방향의 길이가 더 길게 제작된 PC 벽 패널부재와; A PC wall panel member having a beam and a pillar integrally formed and having a longer length in a transverse direction than a height;

상기 바닥에 설치되어 PC 벽 패널부재를 고정할 수 있도록 된 받침부재와;A support member installed on the floor so as to fix the PC wall panel member;

상기 PC 벽 패널부재에 일체로 형성된 상단 보 양측에 다수의 슬래브가 설치되도록 형성된 걸림부를 구성하는 것을 특징으로 한다.And a plurality of slabs are formed on both sides of the upper beam formed integrally with the PC wall panel member.

상기 PC 벽 패널부재는 상단과 하단에 일체로 상부보와 하부보를 구성하고, 상부보와 하부보 사이에 소정의 간격으로 패널형 기둥이 일체로 형성된 것을 특징으로 한다.The PC wall panel member integrally includes an upper beam and a lower beam integrally formed at an upper end and a lower end thereof, and a panel column is integrally formed at a predetermined interval between the upper beam and the lower beam.

상기 PC 벽 패널부재 상단에 일체로 형성된 상부 보는 양측에 걸림부가 형성되어 다수의 슬래브가 설치될 수 있도록 된 것을 특징으로 한다.And a plurality of slabs can be installed on both sides of the top view integrally formed on the top of the PC wall panel member.

상기 PC 벽 패널부재 하단에 일체로 형성된 하부 보는 양측에 소정의 간격으로 다수의 요홈이 형성되고, 상부보 상면과 양측단부 및 하부보 양측 단부에 철근이 돌출되어 PC 벽 패널부재을 상하 복수 고정할 수 있도록 된 것을 특징으로 한다.A plurality of recesses are formed at predetermined intervals on both sides of the lower view integrally formed at the lower end of the PC wall panel member. Reinforcing bars protrude from both the upper and lower ends of the upper and lower beams, .

상기 슬래브는 다수의 중공부가 형성되어 PC 벽 패널부재에 설치시 PC강선이 끼워져 고정할 수 있도록 된 것을 특징으로 한다.The slab is formed with a plurality of hollow portions so that a PC steel wire can be inserted and fixed when installed on the PC wall panel member.

상기 PC 벽 패널부재는 다수의 층을 형성할 수 있는 길이로 형성하고 층간을 형성하는 슬래브가 설치되는 위치에 걸림부가 소정의 간격으로 다수 형성된 것을 특징으로 한다.The PC wall panel member is formed to have a length capable of forming a plurality of layers, and a plurality of latching portions are formed at predetermined intervals at positions where slabs forming the interlayer are installed.

상기 PC 벽 패널부재를 고정할 수 있도록 된 받침부재는 PC 벽 패널부재의 하단 보에 형성된 요홈과 대응되는 위치에 철근이 돌출되도록 형성된 것을 특징으로 한다.The supporting member adapted to fix the PC wall panel member is formed such that a reinforcing bar protrudes at a position corresponding to the groove formed in the lower end beam of the PC wall panel member.

본 발명은 보와 기둥을 일체형으로 하나의 PC벽 패널부재로 제작하여 지상 PC 주차장을 시공할 수 있도록 함으로서, 첫째, 주차장 건물 시공시 PC 부재의 개수를 PC벽 패널부재와 슬래브 만으로 구성 함으로 건축부재를 최소화할 수 있으며,In the present invention, the ground and the pillar are integrally formed as one PC wall panel member so that the ground PC parking lot can be constructed. First, since the number of the PC members is made only by the PC wall panel member and the slab, Can be minimized,

둘째, PC 부재를 이용하여 시공함으로 별도의 콘크리트 타설 시간, 콘크리트 양생시간이 요구되지 않으므로 공기를 단축하는 효과를 가지며,Second, because it is constructed by using PC member, there is no need for extra concrete pouring time and concrete curing time,

셋째, 지장 주차장을 최소한의 건축부재와 최소한의 공사기간에 시공이 완료됨으로 공사비용을 줄일 수 있는 효과를 가지며,Third, it has the effect of reducing the construction cost by completing construction of the parking lot with minimum construction material and minimum construction period,

넷째, 보와 기둥이 일체형으로 이루어지며 높이보다 횡 방향의 길이가 더 길게 PC 벽 패널부재가 제작 설치됨으로 지진에 대한 횡 지지능력을 증가시킬 수 있도록 하여 내진설계가 적용되도록 한 프리캐스트 프리스트레스 콘크리트 벽 패널을 활용한 지상 PC 주차장 및 그 시공방법에 관한 것이다.Fourth, precast prestressed concrete wall with seismic design is applied so that the horizontal and vertical lengths of the beam and column are integrated and the length of the lateral wall is longer than that of the PC wall panel member. The present invention relates to a ground PC parking lot utilizing a panel and a construction method thereof.

도1은 종래의 PC 주차블럭을 이용하여 조립된 주차장의 조립도를 나타낸 것이며,
도2는 종래의 PC를 이용한 지하 구조물의 조립도를 나타낸 것이며,
도3은 본 발명에 PC 벽 패널부재로서 상부 보와 하부보 및 기둥이 일체화 된 것을 나타낸 것이며,
도4는 본 발명의 PC 벽 패널부재 상단에 설치되는 PC 슬래브를 나타낸 것이며,
도5는 본 발명의 PC 벽 패널부재를 소정의 간격으로 배열된 받침부재에 설치한 상태를 나타낸 것이며,
도6은 본 발명의 PC 벽 패널부재를 소정의 간격으로 배열된 받침부재에 설치하고 상단부에 PC슬래부를 설치한 상태를 나타낸 것이며,
도7은 상기 도6을 사공한 후 2층 주차장을 조립하기 위해 PC 벽 패널부재를 수직으로 설치한 상태를 나타낸 것이며,
도8은 상기 도7과 같이 PC 벽 패널부재를 설치한 후 PC 벽 패널부재와 PC 벽 패널부재 사이에 PC 슬래브를 설치한 상태를 나타낸 것이며,
도9는 도7 및 도8의 시공 방법으로 3층 주차장을 시공한 상태를 나타낸 것이며,
도10은 본 발명의 다른 실시례로서 PC 벽 패널부재를 상부보와 기둥을호 만 이루어진 상태 를 나타낸 것이며,
도11은 본 발명의 시공방법에 따른 시공순서를 나타낸 것이다.
FIG. 1 shows an assembled view of a parking lot assembled using a conventional PC parking block,
FIG. 2 shows an assembled view of an underground structure using a conventional PC,
Fig. 3 is a view showing that the upper beam, the lower beam and the column are integrated as the PC wall panel member in the present invention,
4 shows a PC slab installed at the top of the PC wall panel member of the present invention,
Fig. 5 shows a state in which the PC wall panel members of the present invention are installed on a receiving member arranged at a predetermined interval,
6 shows a state in which the PC wall panel members of the present invention are provided on a receiving member arranged at predetermined intervals and a PC slat portion is provided on the upper end thereof,
7 is a view illustrating a state in which the PC wall panel member is vertically installed to assemble the two-storey car park after draining the FIG. 6,
8 is a view showing a state where a PC slab is installed between a PC wall panel member and a PC wall panel member after the PC wall panel member is installed as shown in FIG. 7,
FIG. 9 shows a state in which a three-storey car park is constructed by the construction method of FIGS. 7 and 8,
10 shows another embodiment of the present invention in which the PC wall panel member is formed only of the upper beam and the column,
11 shows a construction procedure according to the construction method of the present invention.

이하 본 발명을 첨부 도면에 의거하여 시공방법을 상세히 설명하면 다음과 같다Hereinafter, a method of constructing the present invention will be described in detail with reference to the accompanying drawings.

도3은 본 발명에 PC 벽 패널부재로서 상부 보와 하부보 및 기둥이 일체화 된 것을 나타낸 것으로서, PC 벽 패널부재(10)는 상 하부 보(11)(12)와 기둥(13)이 일체형으로 형성된다.3 shows the PC wall panel member in which the upper beam, the lower beam and the column are integrated. In the PC wall panel member 10, the upper and lower beams 11 and 12 and the column 13 are integrally formed .

상기 PC 벽 패널부재(10)는 상부 보(11)와 하부 보(12) 사이에 일체로 형성되는 패널 형태의 기둥(13)과 기둥(13)이 소정의 간격으로 이격되도록 형성되고 기둥과 기둥 사이에는 공간부(16)가 형성된다.The PC wall panel member 10 is formed such that a column-shaped column 13 integrally formed between the upper beam 11 and the lower beam 12 and the column 13 are spaced apart from each other by a predetermined distance, A space portion 16 is formed.

또한 PC 벽 패널부재(10)의 상부 보(11) 양 측면에는 PC 슬래브(30)가 걸쳐지도록 단턱으로 된 걸림부(14)가 형성된다.On both side surfaces of the upper beam 11 of the PC wall panel member 10, a locking portion 14 having a stepped portion is formed so that the PC slab 30 is spanned.

상기 PC 벽 패널부재(10)의 상부 보(11) 양측 단부 및 상부에 다수의 철근(40)이 돌출되도록 하고, 하부 보(12) 양측 단부에 철근(40)이 돌출되도록 형성된다.A plurality of reinforcing bars 40 protrude from both ends and upper portions of the upper beam 11 of the PC wall panel member 10 and the reinforcing bars 40 protrude from both ends of the lower beam 12.

상기 상부 보(11)와 하부 보(12)에 돌출되도록 형성되는 철근(40)에 PC 벽 패널부재(10)의 강도를 증진시키기 위해 매설되는 철근(40) 단부가 돌출되도록 한 것이다.The ends of the reinforcing bars 40 embedded in the reinforcing bars 40 protruding from the upper and lower beams 11 and 12 to increase the strength of the PC wall panel member 10 are protruded.

또한 PC 벽 패널부재(10)의 하부 보(12) 양측면에는 소정의 간격으로 다수의 요홈(15)이 형성되어 차 후 시공시 접합부를 형성하게 된다.In addition, a plurality of grooves 15 are formed on both side surfaces of the lower beam 12 of the PC wall panel member 10 at predetermined intervals to form a joint at the time of post-installation.

본 발명의 PC 벽 패널부재는 보와 기둥이 일체형으로 이루어지며 높이보다 횡 방향의 길이가 더 길게 PC 벽 패널부재가 제작 설치됨으로 지진에 대한 횡 지지능력을 증가시킬 수 있도록 하여 내진설계가 적용되도록 한 것이다.The PC wall panel member of the present invention is constructed such that the beam and the pillar are integrally formed and the length of the lateral direction is longer than that of the PC wall panel member so that the seismic protection capability can be increased so that the seismic design is applied It is.

도4는 본 발명의 PC 벽 패널부재 상단에 설치되는 PC 슬래브를 나타낸 것으로서 주차장 시공시 PC 벽 패널부재와 PC 벽 패널부재의 상단에 걸쳐지도록 설치된다.FIG. 4 shows a PC slab installed on the top of the PC wall panel member of the present invention, and is installed to cover the tops of the PC wall panel member and the PC wall panel member when the parking lot is installed.

상기 PC 벽 패널부재(10)와 PC 벽 패널부재(10)의 상단 상이에 설치되는 PC 슬래브(30)는 단부가 PC 벽 패널부재(10)의 상부 보(11) 양측에 형성된 단턱의 걸림부(14)에 걸쳐지도록 설치된다.The PC slabs 30 provided on the tops of the PC wall panel members 10 and the PC wall panel members 10 have end portions which are formed at both sides of the upper beam 11 of the PC wall panel member 10, (14).

또한 상기 PC 슬래브(30)는 길이 방향으로 양측에 제1연결부(33)와 제2연결부(34)가 형성되어 PC 슬래브(30)가 맞물림으로 수평연결되도록 구성된다.In addition, the PC slabs 30 are configured such that a first connecting portion 33 and a second connecting portion 34 are formed on both sides in the longitudinal direction so that the PC slabs 30 are coupled to each other in a horizontal direction.

즉, PC 슬래브(30)의 제1연결부(33)는 오목부로 형성하고 제2 연결부(34)는 볼록부로 형성할 수 있으며, 또는 제1 연결부(33)는 볼록부로 형성하고 제2 연결부(34)는 오목부로 형성하여 PC 슬래브(30)와 PC 슬래브(30)가 수평적으로 맞물려 밀착 설치되도록 한 것이다. That is, the first connecting portion 33 of the PC slab 30 may be formed as a concave portion, the second connecting portion 34 may be formed as a convex portion, or the first connecting portion 33 may be formed as a convex portion and the second connecting portion 34 Is formed as a concave portion so that the PC slab 30 and the PC slab 30 are horizontally engaged and closely installed.

도5는 본 발명의 PC 벽 패널부재를 소정의 간격으로 배열된 받침부재에 설치한 상태를 나타낸 것으로서, 바닥에 받침부재(20)를 설치하여 PC 벽 패널부재(10)를 기둥 역할 을 할 수 있도록 받침부재(20) 위에 세워 설치하게 된다.FIG. 5 shows a state in which the PC wall panel members according to the present invention are installed on the support members arranged at predetermined intervals. The support member 20 is provided on the floor, and the PC wall panel member 10 can serve as a pillar So that it is installed on the receiving member 20.

본 발명의 받침부재(20)는 지면에 PC 슬래브(30)의 길이 간격으로 설치하게 되는데 지면은 받침부재(20)를 고정할 수 있는 수단으로 형성된다.The support member 20 of the present invention is installed at intervals of the length of the PC slabs 30 on the ground, and the ground surface is formed by means that can fix the support member 20.

즉, 주차장으로 사용될 장소의 지면에 콘크리트를 타설하여 받침부재(20)를 고정할 수 있고, 지반을 판판하게 다짐을 한 후 받침부재(20)를 기타 도구를 이용하여 고정할 수 있다.That is, the support member 20 can be fixed by placing concrete on the floor of a place to be used as a parking lot, and the support member 20 can be fixed using other tools after the ground is plastered.

상기 받침부재(20)는 상부에 PC 벽 패널부재(10)가 올려져 고정될 수 있도록 PC 벽 패널부재(10)의 저면과 대응 밀착된 구조로 이루어졌다.The supporting member 20 has a structure in which the bottom surface of the PC wall panel member 10 is brought into close contact with the bottom surface of the PC wall panel member 10 so that the PC wall panel member 10 can be raised and fixed.

또한 받침부재(20)는 강도를 높이기 위해 내부에 철근이 매설되며 수직철근 단부는 받침부재 상부로 돌출되어 상부에 설치되는 PC 벽 패널부재(10)의 하부 보(12) 양측에 형성된 요홈(15)에 끼워져 접합부를 구성할 수 있다.In order to increase the strength of the support member 20, reinforcing bars are embedded therein, and the end portions of the vertical reinforcing bars are protruded to the upper portion of the support member, and the recesses 15 formed on both sides of the lower beam 12 of the PC wall panel member 10, To form a joint portion.

또한 본 발명의 받침부재(20)는 철근(40)이 돌출되지 않도록 형성한 후 받침부재(20)와 PC 벽 패널부재(10)의 하부 보(12) 양측에 형성된 요홈(15)을 이용하여 앵커볼트로 접합부를 구성할 수 있다.The support member 20 of the present invention is formed by using the support member 20 and the groove 15 formed on both sides of the lower beam 12 of the PC wall panel member 10 after the reinforcing bars 40 are formed so as not to protrude An anchor bolt can be used to form the joint.

상기 받침부재(20)의 요홈(15)은 ∪자형 금속금구를 설치하되 금속금구 바닥의 외측방향으로 볼트 또는 철근이 인입출되도록 개구부를 형성하여 설치하여 앵커볼트를 설치하거나 받침부재(20)에서 돌출되어 금속금구에 끼워진 철근(40)을 용접하여 접합부를 형성할 수 있다.The recess 15 of the receiving member 20 is provided with a U-shaped metal fitting, and an opening is formed to install a bolt or a reinforcing bar in an outward direction of the bottom of the metal fitting to provide an anchor bolt, It is possible to form the joint by welding the reinforcing bars 40 projected and inserted into the metal fittings.

본 발명의 받침부재(20)는 시공되는 주차장의 부지 면적에 따라서 일정한 간격으로 설치하여 PC 벽 패널부재(10)를 도5와 같이 설치할 수 있다.The support members 20 of the present invention can be installed at regular intervals according to the area of the parking lot to be installed so that the PC wall panel member 10 can be installed as shown in FIG.

도6은 본 발명의 PC 벽 패널부재를 소정의 간격으로 배열된 받침부재에 설치하고 상단부에 PC슬래브를 설치한 상태를 나타낸 것으로서, 지면에 배열된 받침부재(20)를 고정하고 그 상면에 PC 벽 패널부재(10)를 설치한 후 PC 벽 패널부재(10)와 PC 벽 패널부재(10) 사이의 상단에 PC 슬래브(30)를 설치 한다.6 shows a state in which a PC wall panel member of the present invention is installed on a support member arranged at a predetermined interval and a PC slab is installed at an upper end thereof. The support member 20 arranged on the ground is fixed, The PC slab 30 is installed at the upper end between the PC wall panel member 10 and the PC wall panel member 10 after the wall panel member 10 is installed.

상기 PC 슬래브(30)는 PC 벽 패널부재(10)의 상단에 형성된 상부 보(11) 양측 길이방향으로 형성된 걸림부(14)에 PC 슬래부(30) 양단부가 걸쳐지도록 설치된다.The PC slabs 30 are installed in such a manner that both ends of the PC slabs 30 are stuck on the engaging portions 14 formed on both sides of the upper beam 11 formed on the upper end of the PC wall panel member 10.

상기 걸림부(14)는 도3에 도시된 바와 같이 PC 벽 패널부재(10)의 상부 보(11) 양측에 단턱이 형성되어 PC 슬래브(30)가 걸쳐지도록 할 수 있다.As shown in FIG. 3, the locking portions 14 may be formed on both sides of the upper beam 11 of the PC wall panel member 10 so that the PC slabs 30 may be staggered.

상기 걸림부(14)에 걸쳐진 PC 슬래브(30)의 양단부는 앵커볼트, ㄱ자형 앵글, 기타 고정부재로 고정할 수 있다. Both ends of the PC slab 30 extending over the locking part 14 can be fixed by anchor bolts, angled angles, and other fixing members.

또한 PC 슬래브(30)는 주차장의 바닥으로 사용될 수 있도록 하중에 대한 인장강도와 압축강도는 사전에 계산되어 PC 슬래브(30)가 제작된다.Also, the tensile strength and the compressive strength with respect to the load are calculated in advance so that the PC slab 30 can be used as the floor of the parking lot, and the PC slab 30 is manufactured.

상기 PC 슬래브는 내부에 가로세로로 철근(40)이 배열되어 매설된 상태이며 필요에 따라서 도4와 같이 길이 발향으로 다수의 중공부(31)를 형성하고 이의 중공부(31)에 강선을 끼워 PC 슬래브(30)가 상부 보(11)의 걸림부(14)에 걸쳐진 후 양측에서 강선을 당겨 고정할 수 있다.As shown in FIG. 4, the PC slab has a plurality of hollow portions 31 formed in a lengthwise direction as shown in FIG. 4, and a steel wire is inserted into the hollow portion 31 of the PC slab The PC slabs 30 can be pulled over the fastening portions 14 of the upper beam 11 and then pulled from both sides to fix them.

상기 PC 슬래브(30)는 길이 방향으로 양측에 제1연결부(33)와 제2연결부(34)가 형성되어 PC 슬래브(30)가 좌우에서 맞물림으로 수평 연결되도록 형성된다.The PC slabs 30 are formed such that a first connecting portion 33 and a second connecting portion 34 are formed on both sides of the PC slab 30 in the longitudinal direction so that the PC slabs 30 are horizontally connected to each other in the right and left directions.

상기 PC 슬래브(30)의 제1연결부(33)와 제2 연결부(34)는 볼록부 또는 오목부로 형성되어 서로 대응되는 측면이 맞물림으로 밀착 결합 될 수 있도록 구성한다.The first connecting portion 33 and the second connecting portion 34 of the PC slab 30 are formed as convex portions or concave portions so that the side surfaces corresponding to each other can be tightly engaged with each other.

도7은 상기 도6을 사공한 후 2층 주차장을 조립하기 위해 PC 벽 패널부재를 수직으로 설치한 상태를 나타낸 것이고, 도8은 상기 도7과 같이 PC 벽 패널부재를 설치한 후 PC 벽 패널부재와 PC 벽 패널부재 사이에 PC 슬래브를 설치한 상태를 나타낸 것이다.7 is a view illustrating a state in which a PC wall panel member is vertically installed to assemble a two-storey car park after draining the FIG. 6, FIG. 8 is a perspective view of the PC wall panel member after the PC wall panel member is installed, And a PC slab is installed between the member and the PC wall panel member.

상기 도5와 도6과 같이 받침부재(20)와 PC 벽 패널부재(10) 및 PC 슬래브(30) 를 이용하여 1층 주차장을 시공한 후에는 설치된 PC 벽 패널부재(10)의 상부 보(11) 상면에 PC 벽 패널부재(10)를 좌우 연속적으로 설치한다.5 and 6, after the one-storey car park is constructed by using the support member 20, the PC wall panel member 10 and the PC slab 30, the upper wall of the PC wall panel member 10 11, the PC wall panel member 10 is continuously installed laterally.

이때 PC 벽 패널부재(10)의 상부 보(11) 상면에 설치되는 PC 벽 패널부재(10)의 하부 보(12) 양측에 형성된 요홈(15)에 하부에 위치한 PC 벽 패널부재(10)의 상부 보(11) 상면으로 돌출된 철근(40)이 끼워져 접합부를 구성하여 도7과 같이 2층을 형성하기 위한 PC 벽 패널부재(10)를 설치하여 기둥과 보 역활을 할 수 있도록 한다.The PC wall panel member 10 installed on the upper side of the PC wall panel member 10 has a groove 15 formed on both sides of the lower side beam 12 of the PC wall panel member 10, A reinforcing bar 40 protruding from the upper surface of the upper beam 11 is fitted to form a joint so that a PC wall panel member 10 for forming two layers as shown in Fig.

상기와 같이 PC 벽 패널부재(10)의 상부 보(11) 상면에 PC 벽 패널부재(10)를 설치한 후에는 도8과 같이 PC 벽 패널부재(10)와 PC 벽 패널부재(10) 사이의 상단 걸림부(14)에 PC 슬래브(30)를 걸쳐지도록 설치하면 2층 주차장이 시공된다.8, after the PC wall panel member 10 is installed on the upper surface of the upper beam 11 of the PC wall panel member 10 as described above, there is a gap between the PC wall panel member 10 and the PC wall panel member 10 The PC slab 30 is installed on the top securing portion 14 of the vehicle.

도9는 도7 및 도8의 시공 방법으로 3층 주차장을 시공한 상태를 나타낸 것이다. 도9는 상기 2층 주차장 시공 방법과 동일한 시공방법으로 3층 주차장을 시공한다.FIG. 9 shows a state in which a three-storey car park is constructed by the construction method of FIGS. 7 and 8. FIG. FIG. 9 shows a three-storey car park constructed by the same construction method as the two-storey parking lot construction method.

본 발명에서는 받침부재(20)와, PC 벽 패널부재(10), PC 슬래브(30)를 이용하여 지상주차장을 PC로 조립 건축시공하는 것을 설명한 것이며, 1층에서 2층, 2츨에서 3층으로 올라가거나 내려오는 주차로는 층간 사이에 경사로를 설치하여 차량이 이동될 수 있도록 하는 것으로 이는 통상의 다양한 방법으로 설치될 수 있는 것으로 본 발명에서는 발명의 요지가 아니므로 이의 설명을 생략한다.In the present invention, it is described that a ground parking lot is constructed and assembled with a PC by using the support member 20, the PC wall panel member 10, and the PC slab 30, and the construction is carried out from the first floor to the second floor, A parking space for raising or lowering the vehicle can be installed by installing a ramp between the layers so that the vehicle can be moved. This can be installed by various conventional methods, and therefore, the present invention is not a gist of the present invention.

도10은 본 발명의 다른 실시 예로서 PC 벽 패널부재를 상부보와 기둥으로 만 이루어진 상태를 나타낸 것으로서, PC 벽 패널부재(10a) 제작시 걸림부를 갖는 상부 보(11)와 기둥(13) 만을 일체 형으로 형성하고 하부 보(12)는 생략하였다.10 shows a state in which the PC wall panel member is formed only of the upper beam and the column as another embodiment of the present invention. In manufacturing the PC wall panel member 10a, only the upper beam 11 and the column 13 And the lower beam 12 is omitted.

따라서 도10의 PC벽 패널부재(10a)는 기둥(13) 하단부 모서리 4곳에 요홈(15)를 형성하여 바닥에 설치된 받침부재(20) 또는 PC 벽 패널부재(10a)의 상부 보(11) 상면에 돌출된 철근(40)이 연결되어 접합부를 구성할 수 있도록 하였다.The PC wall panel member 10a of Figure 10 is formed with four grooves 15 at the lower edge corners of the column 13 so that the top surface 11a of the support member 20 or the PC wall panel member 10a, The reinforcing bars 40 protruding from the reinforcing bars 40 are connected to constitute the joints.

즉, 상기 도10은 하부 보를 생략한 대신에 기둥(13)의 하단부가 받침부재(20)에 올려져 고정되거나 또는 PC 벽 패널부재(10a) 상단면과 연결되도록 구성된다.10, the lower end of the column 13 may be fixed on the support member 20 or may be connected to the upper end surface of the PC wall panel member 10a.

이상에서 설명된 본 발명은 PC 부재를 이용하여 지상 주차장을 간단 용이하게 조립 시공할 수 있도록 한 것으로서, 받침부재(20), PC 벽 패널부재(10)(10a) PC 슬래브(30)를 조립하여 시공되는 것으로 설명하였으나, 접합부는 용접, 앵커볼트, 기타 방법으로 접합부를 구성할 수 있으며, PC와 PC가 연결되는 부분은 콘크리트 또는 마감재로 시공할 수 있다.  The present invention described above can easily and easily assemble a ground parking lot by using a PC member. The PC slab 30 of the support member 20, the PC wall panel member 10, 10a, However, the joint may be formed by welding, anchor bolts, or other methods, and the portion where the PC and the PC are connected may be constructed of concrete or a finishing material.

도 11은 본 발명의 시공방법에 따른 시공순서를 나타낸 것으로서, PC 주차장으로 시공되는 바닥의 지반공사 후 PC 슬래브(30)가 설치되는 길이 간격으로 받침부재(20)를 설치하는 단계와,11 is a view showing a construction procedure according to a construction method of the present invention. The construction step includes the steps of installing a support member 20 at a length of a PC slab 30,

상기 설치된 받침부재(20)의 돌출된 철근(40)이 PC 벽 패널부재(10)의 하부 보(12)에 형성된 요홈(15)에 끼워지도록 PC 벽 패널부재(10)를 다수 세워 설치하는 단계와,A step of installing a plurality of PC wall panel members 10 so that the projected reinforcing bars 40 of the installed support members 20 fit into the recesses 15 formed in the lower beam 12 of the PC wall panel member 10 Wow,

상기 PC 벽 패널부재(10)를 받침부재(20)에 설치한 후에는 PC 벽 패널부재(10)와 PC 벽 패널부재(10) 사이의 상부 보에 형성된 걸림부(14)에 단부가 걸쳐지도록 PC 슬래브(30)를 설치하는 단계와,After the PC wall panel member 10 is installed on the receiving member 20, the end portion of the PC wall panel member 10 is stuck on the engaging portion 14 formed on the upper beam between the PC wall panel member 10 and the PC wall panel member 10 Installing a PC slab (30)

상기 받침부재(20)에 설치된 PC 벽 패널부재(10)의 상부 보(11)에 다른 PC 벽 패널부재(10)를 2단으로 설치하는 단계와, Installing two different PC wall panel members (10) on the upper beam (11) of the PC wall panel member (10) provided on the receiving member (20)

상기 2단으로 설치된 PC 벽 패널부재(10)와 PC 벽 패널부재(10) 사이에 PC 슬래브(30)를 설치하여 2층 주차장을 시공하는 단계와,Installing a PC slab (30) between the PC wall panel member (10) and the PC wall panel member (10) installed at the two stages to construct a two - storey car park,

상기 2층 주차장 시공 단계 방법으로 3층 주차장을 시공하는 단계로 프리캐스트 프리스트레스 콘크리트 벽 패널을 이용한 지상 PC 주차장 시공방법이 이루어진다.As a step of constructing the three-storey parking lot by the above-mentioned two-storey parking lot construction method, a method of constructing a terrestrial PC parking lot using a precast concrete wall panel is performed.

또한 본 발명의 첨부도면 11을 간략히 설명하면 ① 받침부재 설치→ ② 받침부재에 PC 벽 패널부재 설치 → ③ PC 벽 패널부재와 PC 벽 패널부재 사이에 PC 슬래브설치 → ④ 1층 주차장 완성 → ⑤ PC 슬래브가 설치된 PC 벽 패널부 상부에 PC 벽 패널부재 설치 ⑥ PC 벽 패널부재와 PC 벽 패널부재 상단 사이에 PC 슬래브 설치 → ⑦ 2층 주차장 완성 → ⑧ 완성된 2층 주차장의 PC 벽 패널부재 상단에 다른 PC 벽 패널부재를 각각 설치한 후 PC 슬래브를 설치 → ⑨ 3층 주차장 완성의 순서로 PC 벽 패널부재를 이용한 주차장 건축물 시공이 완료된다. In addition, referring to the accompanying drawing 11 of the present invention, a brief description of the present invention will be given. (1) Mounting of a support member, (2) Installation of a PC wall panel member to a supporting member, (3) Installation of a PC slab between a PC wall panel member and a PC wall panel member, Install PC wall panel member on top of PC wall panel part with slab installed ⑥ Install PC slab between PC wall panel member and PC wall panel member top → ⑦ Complete 2-storey parking lot → ⑧ On top of PC wall panel member of completed 2-story parking lot Installation of other PC wall panel members, installation of PC slabs → ⑨ Completion of parking lot construction using PC wall panel members in the order of completion of 3-story parking lots.

이와 같이 된 본 발명은 보와 기둥을 일체형으로 하나의 PC 벽 패널부재로 구성하되 전체의 크기가 높이보다 횡 방향의 길이가 더 길게 PC 벽 패널부재를 제작함으로서 내진 설계되도록한 것이다.According to the present invention, the beam and the column are integrally formed as one PC wall panel member, and the PC wall panel member is manufactured so that the whole length is longer than the height.

즉, 지진은 횡방향으로 지진파가 전해지므로 PC 벽 패널부재를 높이보다 길이를 더 길게 형성함으로 지진의 횡 지지능력을 증가시킬 수 있도록 하여 내진설계가 적용되도록 한 것이다. In other words, the earthquake is caused by the seismic waves transmitted in the lateral direction, so that the PC wall panel member is formed longer than the height, so that the lateral support capability of the earthquake can be increased, so that the seismic design is applied.

이와 같이 된 본 발명의 PC 벽 패널부재를 이용하여 지상 PC 주차장을 시공할 수 있도록 함으로서, ①주차장 건물 시공시 건축부재를 최소화할 수 있으며, ②시공시 별도의 콘크리트 타설 시간, 콘크리트 양생 시간이 요구되지 않으므로 공기를 단축하는 이점이 있으며, ③지장 주차장 시공시 최소한의 부재와 최소한의 공사기간에 시공이 완료됨으로 공사비용을 줄일 수 있는 이점이 있으며, ④주변의 환경조건에 따라 디자인의 변화를 줄 수 있으며, 특히 콘크리트 건물 주차장과 같은 견고함과 외견상 미려함을 제공할 수 있는 이점이 있다.By using the PC wall panel member of the present invention as described above, it is possible to construct a ground PC parking lot, thereby making it possible to minimize the construction members when constructing parking garages, and to provide concrete concrete placement time and concrete curing time ③ There is an advantage that construction cost is reduced because the installation is completed in minimum construction time and minimum absence when construction of parking lot is done. ④ There is an advantage to reduce the design change according to the surrounding environmental conditions. And can provide the ruggedness and apparently beautifulness of a concrete building parking lot, in particular.

10:PC 벽 패널부재 11:상부 보
12:하부 보 13: 기둥
14:걸림부 15:요홈
16:공간부 17: 걸림공
20:받침부재 30: PC 슬래브
31: 중공부
33: 제1 연결부 34:제2 연결부
40:철근
10: PC wall panel member 11: upper beam
12: Lower beam 13: Column
14: latch 15: groove
16: space part 17:
20: support member 30: PC slab
31: hollow
33: first connection part 34: second connection part
40: Rebar

Claims (10)

조립식 PC 주차장 시공방법에 있어서,
보와 기둥이 일체형으로 이루어지며 높이보다 횡 방향의 길이가 더 길게 제작된 PC 벽 패널부재(10)와;
상기 바닥에 설치되어 PC 벽 패널부재(10)를 고정할 수 있도록 된 받침부재(20)와;
상기 PC 벽 패널부재(10)에 일체로 형성된 상단 보(11) 양측에 다수의 PC 슬래브(30)가 설치되도록 형성된 걸림부(14)를 포함하는 것을 특징으로 하는 프리캐스트 프리스트레스 콘크리트 벽 패널을 이용한 지상 PC 주차장.
In a method of constructing a prefabricated PC parking lot,
A PC wall panel member 10 formed integrally with the beam and the column and having a longer length in the transverse direction than the height;
A supporting member 20 installed on the floor and capable of fixing the PC wall panel member 10;
And a plurality of PC slabs (30) formed on both sides of the upper beam (11) formed integrally with the PC wall panel member (10), characterized in that the pre-cast prestressed concrete wall panel Ground PC parking.
제1항에 있어서,
상기 PC 벽 패널부재(10)는 상단과 하단에 일체로 상부 보(11)와 하부 보(12)를 구성하고, 상부 보(11)와 하부 보(12) 사이에 소정의 간격으로 패널형 기둥(13)이 일체로 형성된 것을 특징으로 하는 프리캐스트 프리스트레스 콘크리트 벽 패널을 이용한 지상 PC 주차장.
The method according to claim 1,
The PC wall panel member 10 integrally includes an upper beam 11 and a lower beam 12 integrally formed at an upper end and a lower end of the PC wall panel member 10, (13) are formed integrally with each other, and a ground PC garage using the precast concrete wall panel.
제1항에 있어서,
상기 PC 벽 패널부재(10) 상단에 일체로 형성된 상부 보(11)는 양측에 걸림부(14)가 형성되어 다수의 PC 슬래브(30)가 설치될 수 있도록 된 것을 특징으로 하는 프리캐스트 프리스트레스 콘크리트 벽 패널을 이용한 지상 PC 주차장.
The method according to claim 1,
Wherein a plurality of PC slabs (30) can be installed on both sides of the upper beam (11) integrally formed on the upper end of the PC wall panel member (10) Ground PC parking lot using wall panel.
제1항에 있어서,
상기 PC 벽 패널부재(10) 하단에 일체로 형성된 하부 보(12)는 양측에 소정의 간격으로 다수의 요홈(15)이 형성되고, 상부 보(11) 상면과 양측 단부 및 하부 보(12) 양측 단부에 철근(40)이 돌출되어 PC 벽 패널부재(10)을 상하 복수 고정할 수 있도록 된 것을 특징으로 하는 프리캐스트 프리스트레스 콘크리트 벽 패널을 이용한 지상 PC 주차장.
The method according to claim 1,
The bottom wall 12 integrally formed at the lower end of the PC wall panel member 10 is formed with a plurality of grooves 15 at predetermined intervals on both sides thereof and is provided with an upper surface and upper and lower ends 12, And reinforcing bars (40) protrude from both ends of the PC wall panel member (10) so that the PC wall panel member (10) can be fixed vertically and vertically.
제1항에 있어서,
상기 PC 슬래부는 다수의 중공부(31)가 형성되어 PC 벽 패널부재(10)에 설치시 PC 강선이 끼워져 고정할 수 있도록 된 것을 특징으로 하는 프리캐스트 프리스트레스 콘크리트 벽 패널을 이용한 지상 PC 주차장.
The method according to claim 1,
Wherein the PC slabs are formed with a plurality of hollow portions (31) so that a PC steel wire can be inserted and fixed when installed in the PC wall panel member (10).
제1항에 있어서.
상기 PC 벽 패널부재(10)는 걸림부(14)를 갖는 상부 보(11)와 벽 형태의 기둥(13) 만을 일체로 형성하고 상기 벽 형태의 기둥 하단 모서리 4곳에 요홈(15)이 형성된 PC 벽 패널부재(10a)로 형성된 것을 특징으로 하는 프리캐스트 프리스트레스 콘크리트 벽 패널을 이용한 지상 PC 주차장.
The method of claim 1,
The PC wall panel member 10 is formed by integrally forming only the upper beam 11 and the wall-shaped column 13 having the engaging portion 14 and forming the groove 15 at the bottom corner of the column- Wherein the wall panel member (10a) is formed of a pre-cast concrete wall panel.
제1항에 있어서,
상기 PC 벽 패널부재는 다수의 층을 형성할 수 있는 길이로 형성하고 층간을 형성하는 PC 슬래브(30a)가 설치되는 위치에 각각 걸림공(17)이 형성된 PC 벽 패널부재(10a)을 포하는 것을 특징으로 하는 프리캐스트 프리스트레스 콘크리트 벽 패널을 이용한 지상 PC 주차장.
The method according to claim 1,
The PC wall panel member includes a PC wall panel member 10a having a length capable of forming a plurality of layers and each having a locking hole 17 at a position where a PC slab 30a forming an interlayer is formed A ground PC garage using precast prestressed concrete wall panels.
제1항에 있어서
상기 PC 벽 패널부재(10)(10')를 고정할 수 있도록 된 받침부재(20)는 PC 벽 패널부재(10)(10')의 하단 보(12)에 형성된 요홈(15)과 대응되는 위치에 철근(40)이 돌출되도록 형성된 것을 특징으로 하는 프리캐스트 프리스트레스 콘크리트 벽 패널을 이용한 지상 PC 주차장.
The method of claim 1, wherein
The supporting member 20 capable of fixing the PC wall panel members 10 and 10 'corresponds to the groove 15 formed in the lower beam 12 of the PC wall panel members 10 and 10' And the reinforcing bars (40) are formed to protrude from the pre-cast prestressed concrete wall panels.
제항에 있어서,
상기 받침부재는 PC 받침부재 또는 금속 받침부재로 형성된 것을 특징으로 하는 프리캐스트 프리스트레스 콘크리트 벽 패널을 이용한 지상 PC 주차장.
In the provision,
Wherein the support member is formed of a PC support member or a metal support member.
PC 주차장으로 시공되는 바닥의 지반공사 후 PC 슬래브가 설치되는 길이 간격으로 받침부재를 설치하는 단계;
상기 설치된 받침부재의 돌출된 철근이 PC 벽 패널부재의 하부 보에 형성된 요홈에 끼워지도록 PC 벽 패널부재를 다수 세워 설치하는 단계;
상기 PC 벽 패널부재를 받침부재에 설치한 후에는 PC 벽 패널부재와 PC 벽 패널부재 사이의 상부 보에 형성된 걸림부에 단부가 걸쳐지도록 PC 슬래브를 설치하는 단계;
상기 받침부재에 설치된 PC 벽 패널부재의 상부 보에 다른 PC 벽 패널부재를 2단으로 설치하는 단계;
상기 2단으로 설치된 PC 벽 패널부재와 PC 벽 패널부재 사이에 PC 슬래브를 설치하여 2층 주차장을 시공하는 단계;
상기 2층 주차장 시공 단계 방법으로 3층 주차장을 시공하는 단계를 포함하는 프리캐스트 프리스트레스 콘크리트 벽 패널을 이용한 지상 PC 주차장 시공방법.
Installing a supporting member at a length of a length at which a PC slab is installed after a floor construction of a floor installed in a PC parking lot;
Installing a plurality of PC wall panel members so that protruded reinforcing bars of the installed supporting members fit into recesses formed in a lower beam of the PC wall panel member;
Installing a PC slab so that an end portion of the PC slab is stuck on a hook formed on an upper beam between the PC wall panel member and the PC wall panel member after the PC wall panel member is installed on the receiving member;
Installing two different PC wall panel members on the upper beam of the PC wall panel member provided on the receiving member;
Installing a PC slab between the PC wall panel member and the PC wall panel member installed in the two stages to construct a two-storey car park;
And constructing a three-storey car park by the two-storey car park construction step.
KR1020160038058A 2016-03-30 2016-03-30 The construction method precast prestressed concrete parking buildings with precast concrete wall panels KR102507299B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160038058A KR102507299B1 (en) 2016-03-30 2016-03-30 The construction method precast prestressed concrete parking buildings with precast concrete wall panels

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160038058A KR102507299B1 (en) 2016-03-30 2016-03-30 The construction method precast prestressed concrete parking buildings with precast concrete wall panels

Publications (2)

Publication Number Publication Date
KR20170111858A true KR20170111858A (en) 2017-10-12
KR102507299B1 KR102507299B1 (en) 2023-03-08

Family

ID=60140490

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160038058A KR102507299B1 (en) 2016-03-30 2016-03-30 The construction method precast prestressed concrete parking buildings with precast concrete wall panels

Country Status (1)

Country Link
KR (1) KR102507299B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20220133627A (en) 2021-03-25 2022-10-05 주식회사 신장흥 Culvert-type parking structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050090970A (en) 2005-08-25 2005-09-14 김연진 A sectional parking lot installation
KR101041229B1 (en) * 2011-01-03 2011-06-13 주식회사 한국그린피아 Toilet wall constructing structure using precast concrete panel
KR20120135565A (en) * 2011-06-07 2012-12-17 한국건설기술연구원 None module correspondence and horizontal shear performance enhanced hollow core slab and construction method using the same
KR101385556B1 (en) 2012-05-21 2014-04-15 김현욱 Ground structure and the built-up construction method that use precast concrete
KR101389203B1 (en) * 2013-03-06 2014-04-24 도시구조안전(주) Method for constructing residential building using precast concrete and modular unit

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050090970A (en) 2005-08-25 2005-09-14 김연진 A sectional parking lot installation
KR101041229B1 (en) * 2011-01-03 2011-06-13 주식회사 한국그린피아 Toilet wall constructing structure using precast concrete panel
KR20120135565A (en) * 2011-06-07 2012-12-17 한국건설기술연구원 None module correspondence and horizontal shear performance enhanced hollow core slab and construction method using the same
KR101385556B1 (en) 2012-05-21 2014-04-15 김현욱 Ground structure and the built-up construction method that use precast concrete
KR101389203B1 (en) * 2013-03-06 2014-04-24 도시구조안전(주) Method for constructing residential building using precast concrete and modular unit

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20220133627A (en) 2021-03-25 2022-10-05 주식회사 신장흥 Culvert-type parking structure

Also Published As

Publication number Publication date
KR102507299B1 (en) 2023-03-08

Similar Documents

Publication Publication Date Title
KR101030419B1 (en) Joint structure of vertical member and horizontal member
JP4823790B2 (en) Column unit and method of building building using column unit
KR101346814B1 (en) The remodeling earthquake resistant connection details by using precast concrete member for old reinforced beam-column building structures and the remodeling construction method using the same
KR20090019490A (en) Structure for using precast members and construction method thereof
KR102243984B1 (en) Non-supporting formwork system for retaining wall using self-supporting form and construction method thereof
JP6553442B2 (en) Reinforcement structure and reinforcement method for existing columns
KR102197689B1 (en) Vertical core structure horizontally assembled and construction method therewith
KR101998579B1 (en) Steel Built Up Beam And Column-Beam Joint Construction Method Using Thereof
KR102154095B1 (en) Modular prefabricated house using precast concrete segment and construction method thereof
KR101414254B1 (en) Structure and method for construction using PC column and PC flat plate slab and PC girder
KR101385558B1 (en) Prefabricated construction using half slab
JP2011006849A (en) Method for constructing foundation
KR20170111858A (en) The construction method precast prestressed concrete parking buildings with precast concrete wall panels
KR101908943B1 (en) RC WALL STRUCTURE FOR TOP-DOWN AND METHOD FOR CONSTRUCTING THE STRUCTUREa
KR20130133423A (en) The building slab structure and the constructing method thereof
KR20100121865A (en) Method for constructing building using prc integrating method
KR20090093524A (en) Connecting structure for form-less column and steel beams, and constructing method thereof
JP6214102B2 (en) Reinforcement structure and reinforcement method for existing columns
KR102174760B1 (en) Roof structure for culvert houses
KR101385554B1 (en) Prefabricated construction using half slab
KR102247787B1 (en) Partial reinforced concrete permanent Cement Mortar form and method of constructing the same
KR101466683B1 (en) The remodeling earthquake resistant connection details by using precast concrete member for old reinforced beam-column building structures and the remodeling construction method using the same
KR100456192B1 (en) Composition of precast concrete wall and precast concrete column for outdoor to sustain external force
KR102289243B1 (en) Underground Parking Lot Construction Method Using Pre-assembled bar column, U-shaped beam, Corrugated deck
KR102464866B1 (en) Constructing method for soundproof wall foundation and soundproof wall foundation constructed by the same

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant