KR20170016897A - Tunnel construction method with support walls - Google Patents

Tunnel construction method with support walls Download PDF

Info

Publication number
KR20170016897A
KR20170016897A KR1020170008448A KR20170008448A KR20170016897A KR 20170016897 A KR20170016897 A KR 20170016897A KR 1020170008448 A KR1020170008448 A KR 1020170008448A KR 20170008448 A KR20170008448 A KR 20170008448A KR 20170016897 A KR20170016897 A KR 20170016897A
Authority
KR
South Korea
Prior art keywords
steel
steel material
wall
tunnel
joining
Prior art date
Application number
KR1020170008448A
Other languages
Korean (ko)
Other versions
KR101819494B1 (en
Inventor
조현
임재승
최재호
박동인
정덕교
정헌철
Original Assignee
쌍용건설 주식회사
주식회사 비엠에스이앤씨
주식회사 성우지오텍
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 쌍용건설 주식회사, 주식회사 비엠에스이앤씨, 주식회사 성우지오텍 filed Critical 쌍용건설 주식회사
Priority to KR1020170008448A priority Critical patent/KR101819494B1/en
Publication of KR20170016897A publication Critical patent/KR20170016897A/en
Application granted granted Critical
Publication of KR101819494B1 publication Critical patent/KR101819494B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches

Abstract

The present invention relates to a non-excavation type tunnel construction method, comprising: a step of installing a reinforcement wall; a step of excavating a tunnel of a unit section; a step of installing a steel rib (108); and a step of coupling the steel rib. The present invention reduces a construction period.

Description

보강벽체를 이용한 터널시공방법{TUNNEL CONSTRUCTION METHOD WITH SUPPORT WALLS}[0001] TUNNEL CONSTRUCTION METHOD WITH SUPPORT WALLS [0002]

본 발명은 토목 분야에 관한 것으로서, 상세하게는 터널시공방법에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a civil engineering field, and more particularly, to a tunnel construction method.

저토피 토사구간에서의 구조물시공을 위한 굴착공법은 상부 지반을 개착한 후 시공되는 개착공법을 적용하는 경우가 많았는데 지상에 도심지가 있는 경우 긴 시간동안 교통을 통제해야 하는 불편을 초래하였다. The excavation method for the construction of the structure in the low toe - to - tothos section is often applied to the construction method after the installation of the upper ground, which causes the inconvenience to control the traffic for a long time when there is a downtown area.

따라서, 종래에는 터널의 상부 지반을 개착하지 않고 시공하기 위해 일반적으로, 터널 갱내에서 레그파일, 엘리펀트 풋, 측벽보강 등을 적용하여 터널을 완성 하는 방법이 사용되고 있다.Therefore, conventionally, a method of completing a tunnel by applying a leg file, an elephant foot, a sidewall reinforcement, or the like in a tunnel mine is generally used for constructing without opening the upper ground of the tunnel.

종래의 저토피 토사구간의 터널시공 과정은, 도 1에 도시된 바와 같이, 터널 굴착 전 아치(arch) 형태의 대구경 강관(110)을 터널의 진행방향(X축 방향)을 따라 압입하는 단계, 강지보재(108) 또는 격자지보재(이하 강지보재로 통칭함)를 설치하고 엘리펀트 풋을 형성하는 단계, 숏크리트타설, 록볼트 시공 단계 및 레그파일 시공, 측벽보강 단계를 포함하여 시공되어 왔다.Conventionally, as shown in FIG. 1, a tunnel construction process of a low-to-fatigue zone is performed by inserting a large-diameter steel pipe 110 in the form of an arch in the direction of travel (X-axis direction) A step of installing a steel support material 108 or a grid support material (hereinafter, referred to as a steel support material) and forming an elevator foot, a shotcrete installation, a rock bolt construction step, a leg file construction, and a side wall reinforcement step.

종래 공법에 따라 갱내를 보강하려면 강지보재(108)의 지지력 및 침하에 대한 안정성 확보를 위하여 엘리펀트 풋(elephant foot), 레그 파일(leg pile)을 추가로 설치하는 작업이 필요하며, 굴착 중 상부하중 및 측벽부 하중에 대한 안정성 확보를 위하여 측벽 파일 및 가인버트 등을 설치하는 공정이 필요하여 공사기간이 길어지며, 터널 구조물의 변위가 크게 발생되는 문제점을 가지고 있다.In order to reinforce the mine according to the conventional method, it is necessary to additionally provide an elephant foot and a leg pile for securing the stability of the steel support material 108 and the stability of settlement, And a step of installing a side wall pile and a girder butt for securing the stability against the side wall load is required, so that the construction period is lengthened and the displacement of the tunnel structure is largely generated.

이러한 문제를 해결하고자, 본원의 출원인은 제10-2010-0080286호로 특허출원(보강벽체를 이용한 터널시공방법)을 하여 제10-1254608호로 등록을 받은바 있다.In order to solve such a problem, the applicant of the present application has filed a patent application (tunnel construction method using a reinforced wall) with No. 10-2010-0080286 and has been registered as No. 10-1254608.

위 종래특허에 따른 비개착식 터널시공방법은, 도 2에 도시된 바와 같이, 굴착될 터널의 양측에 보강벽체(100)를 형성하는 단계, 상기 보강벽체(100)사이에 터널의 루프를 형성하는 단계, 터널의 루프와 상기 보강벽체(100)를 연결하는 단계 및 터널 내부를 마감하는 단계를 포함하여 구성된다.As shown in FIG. 2, the method for constructing a non-detachable tunnel according to the prior art includes forming a reinforcing wall 100 on both sides of a tunnel to be excavated, forming a tunnel loop between the reinforcing walls 100, , Connecting the loop of the tunnel to the reinforced wall (100), and closing the inside of the tunnel.

터널의 양측에 보강벽체(100)를 형성하는 단계는, 터널의 굴착방향(X축 방향)을 따라 상기 터널 굴착방향을 기준으로 적어도 일 측에 소정 깊이까지 상기 굴착될 터널의 상부지반 하중을 지탱하기 위한 복수의 보강벽체(100)를 설치하는 단계를 포함한다.The step of forming the reinforcing wall 100 on both sides of the tunnel includes supporting the upper ground load of the tunnel to be excavated at least on one side to a predetermined depth based on the tunnel excavation direction along the tunnel excavation direction And installing a plurality of reinforced wall members (100).

터널의 루프를 형성하는 단계는, 터널의 작업구에서 수평방향(X방향)으로 대구경강관(110)을 압입하고 상기 대구경강관(110) 내부를 그라우팅 한 후, 터널 상반을 굴착하여 강지보재(108)를 설치하는 단계를 포함한다.In the step of forming the loop of the tunnel, the large-diameter steel pipe 110 is press-fitted in the horizontal direction (X direction) in the work hole of the tunnel, and the inside of the large-diameter steel pipe 110 is grouted, ).

상기 루프와 상기 보강벽체(100)를 연결하는 단계는, 상기 루프의 상기 강지보재(108)를 상기 보강벽체(100)와 고정 및 연결하여 상기 루프에 작용하는 하중을 상기 보강벽체(100)로 전달하는 단계를 포함한다.The step of connecting the loop and the reinforced wall 100 may include the step of fixing and connecting the reinforcing wall 100 with the reinforcing wall 100 so that a load acting on the loop is transmitted to the reinforcing wall 100 .

터널내부를 마감하는 단계는, 상기 보강벽체(100)와 상기 강지보재(108)를 고정 및 연결한 후 터널내부 숏크리트 타설 단계를 포함한다.The step of finishing the interior of the tunnel includes a step of placing a shotcrete in a tunnel after fixing and connecting the reinforced wall 100 and the steel support material 108.

따라서, 보강벽체(100)를 선 시공한 후 상기 강지보재(108)와 고정하여 연결함으로써 터널상부의 하중을 상기 보강벽체(100)가 전달받을 수 있게 하는 것이다.Therefore, the reinforcement wall 100 can be received by the upper portion of the tunnel by connecting the reinforcement wall 100 to the steel support 108 after fixing the reinforcement wall 100.

한편, 보강벽체(100)와 강지보재(108)를 결합하는 공정은 도 3,4에 도시된 바와 같다.The process of joining the reinforcing wall 100 and the steel material support 108 is as shown in FIGS.

터널의 상반을 굴착한 뒤 터널내부에서 보강벽체(100)의 측면을 일부 절삭하여 강지보재(108)의 양끝부분이 거치될 수 있는 거치부(201)를 마련하고, 앵커(105)를 설치한 후, 강지보재(108)를 거치부(201)에 거치하고 앵커(105)로 고정한다.After the upper part of the tunnel is excavated, the side wall of the reinforced wall 100 is partially cut inside the tunnel to provide a mounting part 201 where both ends of the steel supporting material 108 can be mounted, and an anchor 105 is installed Then, the steel support material 108 is fixed to the mounting part 201 and fixed with the anchor 105.

그런데 이러한 종래의 공법은, 보강벽체(100)의 절삭작업 및 앵커의 설치와 고정작업이 어렵고 공사기간이 과도하게 장기화한다는 문제가 있었다.However, such a conventional method has a problem that it is difficult to perform the cutting operation and the anchor installation and fixing work of the reinforced wall 100, and the construction period is prolonged for an excessively long period of time.

본 발명은 상기와 같은 문제점을 해결하기 위하여 도출된 것으로서, 시공성이 우수하고 공사기간을 단축할 수 있도록 하는 보강벽체를 이용한 터널시공방법을 제시하는 것을 그 목적으로 한다.It is an object of the present invention to provide a tunnel construction method using a reinforced wall which is excellent in workability and can shorten a construction period.

상기 과제의 해결을 위하여, 본 발명은 굴착 터널의 적어도 어느 일측벽에 인접하도록 터널 굴착방향을 따라 지중에 소정 깊이까지 보강벽체(100)를 설치하는 보강벽체 설치단계; 상기 터널 굴착방향을 따라 지중에 단위 구간의 터널을 굴착하는 단계와; 상기 단위 구간 터널 굴착부의 천단보강을 위해 강지보재(108)를 설치하는 단계; 상기 보강벽체(100)와 상기 강지보재(108)를 결합시키는 강지보재 결합단계;를 포함하는 비개착식 터널시공방법에 있어서, 상기 보강벽체 설치단계는, 상하방향을 따라 심부에 상기 강재(510)가 삽입된 콘크리트 말뚝(500) 다수를 열지어 지중에 설치함으로써 상기 보강벽체(100)를 형성하는 단계;를 포함하고, 상기 강지보재 결합단계는, 상기 보강벽체(100)의 표면 일부를 제거하여 상기 강재(510)의 결합부를 노출시키는 단계; 상기 강재(510)의 결합부에 상기 강지보재(108)를 결합하는 단계;를 포함하는 것을 특징으로 하는 보강벽체를 이용한 터널시공방법을 제시한다.According to an aspect of the present invention, there is provided a method for installing a reinforced-wall structure, the method comprising: installing a reinforced-wall structure to a depth of a ground along a tunnel excavation direction so as to be adjacent to at least one side wall of the tunnel; Drilling a unit section tunnel in the ground along the tunnel excavation direction; Installing a steel material support (108) for reinforcing the ceiling of the unit section tunnel excavation part; And a steel support material joining step of joining the reinforcing wall body 100 and the steel support material 108. In the non-installation type tunnel construction method, the reinforcing wall installation step may include the steps of: And a step of forming the reinforcing wall body 100 by installing a plurality of concrete piles 500 into which the reinforcing wall pile 500 is inserted by inserting a plurality of concrete piles 500 into the ground, Thereby exposing an engaging portion of the steel material 510; And joining the steel support material (108) to a joint portion of the steel material (510).

상기 강재(510)는 H 빔이고, 상기 H 빔의 플랜지 표면이 상기 강지보재(108)와 결합하도록 상기 콘크리트 말뚝(500)에 삽입설치되는 것이 바람직하다.The steel material 510 is an H beam, and the flange surface of the H beam is inserted into the concrete pile 500 so as to engage with the steel support material 108.

상기 강재(510)는 상기 콘크리트 말뚝(500)의 내측에 치우치도록 삽입설치되는 것이 바람직하다.The steel material 510 may be inserted into the concrete pile 500 so as to be offset.

상기 보강벽체 설치단계는, 지반에 천공 홀을 형성하고, 상기 강재(510)를 삽입하는 단계; 상기 천공 홀에 대하여 콘크리트를 타설하는 단계;를 포함하는 것이 바람직하다.The step of installing the reinforcing wall includes the steps of forming a perforation hole in the ground and inserting the steel material 510; And pouring concrete onto the perforation hole.

상기 보강벽체 설치단계는, 상하방향을 따라 심부에 상기 강재(510)가 삽입된 프리캐스트 말뚝을 제조하는 단계; 지반에 상기 프리캐스트 말뚝을 삽입하는 단계;를 포함하는 것이 바람직하다.The step of installing the reinforcing wall includes the steps of: preparing a precast pile in which the steel material 510 is inserted in a vertical portion along a vertical direction; And inserting the precast pile into the ground.

상기 강지보재(108)는 아치형 구조이고, 상기 강지보재(108)의 단부는 횡방향을 따라 편평하게 가공되어 횡방향 접합부(108a)를 형성하며, 상기 강지보재(108)의 횡방향 접합부(108a)는 상기 강재(510)의 결합부에 결합하는 것이 바람직하다.The steel support material 108 has an arcuate structure and the end portion of the steel support material 108 is processed to be flat along the lateral direction to form the lateral joining portion 108a and the lateral joining portions 108a Is coupled to the coupling portion of the steel material 510.

상기 강지보재(108)는 아치형 구조이고, 상기 강지보재(108)의 단부는 종방향을 따라 편평하게 가공되어 종방향 접합부(108b)를 형성하며, 상기 강재(510)의 결합부에는 브라켓(520)이 결합하고, 상기 강지보재(108)의 종방향 접합부(108b)는 상기 브라켓(520)에 결합한 것이 바람직하다.The end portion of the steel support member 108 is flattened along the longitudinal direction to form a longitudinal joint portion 108b and a bracket 520 And the longitudinal joint portion 108b of the steel support member 108 is coupled to the bracket 520. [

상기 보강벽체 설치단계는, 이탈이 용이한 재질에 의한 임시부재(530)를 상기 강재(510)의 결합부에 설치하고, 상하방향을 따라 심부에 상기 강재(510)가 삽입된 콘크리트 말뚝(500) 다수를 열지어 지중에 설치함으로써 상기 보강벽체(100)를 형성하는 단계;를 포함하고, 상기 강지보재 결합단계는, 상기 보강벽체(100)에서 상기 임시부재(530)를 제거하여 상기 강재(510)의 결합부를 노출시키는 단계; 상기 강재(510)의 결합부에 상기 강지보재(108)를 결합하는 단계;를 포함하는 것이 바람직하다.The provision of the reinforcing wall may include installing a provisional member 530 made of a material that can be easily separated in a joint portion of the steel material 510 and a concrete pile 500 having the steel material 510 inserted in a vertically- And forming the reinforcing wall body 100 by installing a plurality of the reinforcing wall bodies 100 in the ground, wherein the step of joining the steel reinforcing material 100 removes the temporary member 530 from the reinforcing wall body 100, 510); < / RTI > And joining the steel support material (108) to the joining portion of the steel material (510).

상기 강재(510)는 H 빔이고, 상기 임시부재(530)는 스티로폼이며, 상기 스티로폼은 상기 H 빔의 플랜지 표면에 설치하는 것이 바람직하다.Preferably, the steel material 510 is an H beam, the temporary member 530 is a styrofoam, and the styrofoam is disposed on a flange surface of the H beam.

본 발명은 시공성이 우수하고 공사기간을 단축할 수 있도록 하는 보강벽체를 이용한 터널시공방법을 제시한다.The present invention proposes a tunnel construction method using a reinforced wall which is excellent in workability and can shorten a construction period.

도 1 내지 4는 종래기술의 공정도.
도 5 이하는 본 발명의 실시예를 도시한 것으로서,
도 5,6은 제1 실시예의 공정도.
도 7은 제2 실시예의 공정도.
도 8은 제3 실시예의 공정도.
도 9는 제4 실시예의 공정도.
도 10,11은 제5 실시예의 공정도.
도 12,13은 제6 실시예의 공정도.
Figures 1 to 4 are process drawings of the prior art.
5 shows an embodiment of the present invention,
5 and 6 are process drawings of the first embodiment.
7 is a process chart of the second embodiment.
8 is a process chart of the third embodiment.
9 is a process chart of the fourth embodiment.
10 and 11 are process drawings of the fifth embodiment.
12 and 13 are process drawings of the sixth embodiment.

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 5 이하에 도시된 바와 같이, 본 발명에 의한 보강벽체를 이용한 터널시공방법은 기본적으로, 굴착 터널의 적어도 어느 일측벽에 인접하도록 터널 굴착방향을 따라 지중에 소정 깊이까지 보강벽체(100)를 설치하는 보강벽체 설치단계; 터널 굴착방향을 따라 지중에 단위 구간의 터널을 굴착하는 단계; 단위 구간 터널 굴착부의 천단보강을 위해 강지보재(108)를 설치하는 단계; 보강벽체(100)와 강지보재(108)를 결합시키는 강지보재 결합단계;를 포함하는 구성을 취한다.5, a tunnel construction method using a reinforced wall according to the present invention basically includes a step of reinforcing a wall 100 to a predetermined depth in the ground along a tunnel excavation direction so as to be adjacent to at least one side wall of the tunnel Installing a reinforced wall; Excavating a unit section tunnel in the ground along a tunnel excavation direction; Installing a steel support material (108) for reinforcing the ceiling of the unit section tunnel excavation part; And a steel reinforcing material joining step of joining the reinforcing wall body (100) and the steel reinforcing material (108).

여기서 상기 보강벽체 설치단계는, 상하방향을 따라 심부에 강재(510)가 삽입된 콘크리트 말뚝(500) 다수를 열지어 지중에 설치함으로써 보강벽체(100)를 형성하는 구성을 취한다.In the step of installing the reinforcing wall, a plurality of concrete piles 500, in which the steel material 510 is inserted in the vertical direction along the vertical direction, is installed in the ground to form the reinforced wall 100.

또한 상기 강지보재 결합단계는, 보강벽체(100)의 표면 일부를 제거하여 강재(510)의 결합부를 노출시키는 단계; 강재(510)의 결합부에 강지보재(108)를 용접, 볼팅 등에 의해 결합하는 단계;를 포함하는 구성을 취한다.In addition, the step of joining the steel support material may include the steps of exposing a joint portion of the steel material 510 by removing a part of the surface of the reinforcement wall body 100; And joining the steel material support (108) to the joining portion of the steel material (510) by welding, bolting, or the like.

즉, 보강벽체의 설치공정에서 미리 강재(510)가 삽입된 콘크리트 말뚝(500) 다수를 열지어 지중에 설치하여 두고, 터널의 굴착 후, 보강벽체(100)의 표면 일부를 절삭작업 등에 의해 제거하여 강재(510)의 결합부(표면)를 노출시킨 후, 그 강재(510)의 결합부에 강지보재(108)를 결합하는 것이다.That is, a large number of concrete piles 500, in which the steel material 510 is inserted in advance, are installed in the ground in the step of installing the reinforced wall, and after the tunnel is excavated, a part of the surface of the reinforced wall 100 is removed (Surface) of the steel material 510 is exposed, and then the steel material support member 108 is joined to the joining portion of the steel material 510.

이는 종래공법과 같이 콘크리트 일부의 절삭작업이 필요하기는 하지만, 강재(510)의 표면이 노출될 정도로만 절삭작업을 수행하면 되고, 별도의 앵커 설치작업이 필요 없이 강재(510)와 강지보재(108)를 결합하면 되므로, 시공성이 우수하여 공사기간을 단축할 수 있다는 효과가 있다.Although cutting work of a part of concrete is required as in the conventional method, the cutting operation can be performed only to the extent that the surface of the steel material 510 is exposed, and the steel material 510 and the steel material support 108 ), It is possible to shorten the construction period because of excellent workability.

강재(510)로는 H 빔을 적용하여 콘크리트 말뚝(500)에 삽입설치함으로써, H 빔의 플랜지 표면이 강지보재(108)와 결합하도록 하는 것이 시공성을 위하여 바람직하다(도 5).It is preferable for the steel 510 to have the flange surface of the H beam to be coupled with the steel support 108 by applying H beams to the concrete pile 500 (FIG. 5).

강재(510)는 콘크리트 말뚝(500)의 중앙부에 위치하도록 삽입설치할 수도 있으나, 콘크리트 말뚝(500)의 내측(터널 측)에 치우치도록 삽입설치하는 경우, 강재(510)의 표면을 노출시키기 위한 절삭작업의 양이 줄어들어 공사기간을 더욱 단축할 수 있다는 장점이 추가된다(도 8,9).The steel material 510 may be inserted to be positioned at the center of the concrete pile 500 but may be inserted into the concrete pile 500 such that the steel material 510 is disposed in the inner side The amount of cutting work is reduced and the construction period can be further shortened (Figs. 8 and 9).

강재(510)가 삽입된 콘크리트 말뚝(500) 다수를 열지어 지중에 설치함으로써 보강벽체(100)를 형성하는 방식은 현장타설 방식, 프리캐스트 방식 등이 모두 가능하다.The method of forming the reinforced wall 100 by installing a plurality of concrete piles 500 in which the steel material 510 is inserted is installed in the ground so that it is possible to place the concrete piles 500 in a field installation method or a precast method.

현장타설 방식의 경우에는, 지반에 천공 홀을 형성하고, 강재(510)를 삽입한 후, 그 천공 홀에 대하여 콘크리트를 타설하는 공정에 의해 보강벽체(100)를 형성할 수 있다.In the field installation method, the reinforced wall 100 can be formed by forming a perforation hole in the ground, inserting the steel material 510, and pouring concrete into the perforation hole.

*프리캐스트 방식의 경우에는, 상하방향을 따라 심부에 강재(510)가 삽입된 프리캐스트 말뚝을 제조하고, 그 프리캐스트 말뚝을 지반에 천공 후 삽입방식, 항타방식 또는 이들의 조합방식에 의해 삽입하는 공정에 의해 보강벽체(100)를 형성할 수 있다.In the case of the pre-cast method, a precast pile in which a steel material 510 is inserted along the vertical direction is manufactured, and the pre-cast pile is inserted into the ground by an insertion method, The reinforced wall 100 can be formed.

강지보재(108)는 아치형 구조를 취하는데, 이러한 구조의 강지보재(108)와 강재(510)의 결합은 다음과 같은 실시예에 의해 구현될 수 있다.The steel support member 108 has an arcuate structure. The steel support member 108 having such a structure and the steel member 510 can be combined by the following embodiments.

*첫째, 강지보재(108)의 단부를 횡방향을 따라 편평하게 가공하여 횡방향 접합부(108a)를 형성하고, 그 강지보재(108)의 횡방향 접합부(108a)를 강재(510)의 결합부에 용접, 볼팅 등에 의해 결합할 수 있다(도 6).First, the end portion of the steel support member 108 is formed to be flat along the lateral direction to form the lateral joint portion 108a, and the lateral joint portion 108a of the steel support member 108 is joined to the joint portion 108a of the steel member 108 By welding, bolting or the like (Fig. 6).

이는 별도의 결합부재 없이, 강지보재(108)와 강재(510)를 결합할 수 있다는 장점이 있다.This has the advantage that the steel support member 108 and the steel member 510 can be joined without a separate joining member.

둘째, 강지보재(108)의 단부를 종방향을 따라 편평하게 가공하여 종방향 접합부(108b)를 형성하고, 강재(510)의 결합부에 브라켓(520)을 결합한 후, 위 강지보재(108)의 종방향 접합부(108b)를 브라켓(520)에 용접, 볼팅 등에 의해 결합할 수 있다(도 7).Second, the end portion of the steel support member 108 is flattened along the longitudinal direction to form the longitudinally joined portion 108b. After the bracket 520 is joined to the joint portion of the steel member 510, The longitudinally joined portion 108b of the bracket 520 can be joined to the bracket 520 by welding, bolting, or the like (Fig. 7).

이는 별도의 브라켓이 필요하지만, 강지보재(108)의 종방향 접합부(108b)의 가공을 위한 수고가 위 횡방향 접합부(108a)의 가공을 위한 수고에 비해 적게 소요된다는 장점이 있다.This requires an additional bracket, but has an advantage in that the labor for machining the longitudinal joint 108b of the steel support member 108 is less than that required for machining the transverse joint 108a.

한편, 이탈이 용이한 재질(스티로폼 등)에 의한 임시부재(530)를 강재(510)의 결합부에 미리 설치하고, 상하방향을 따라 심부에 위 임시부재 및 강재(510)가 삽입된 콘크리트 말뚝(500) 다수를 열지어 지중에 설치함으로써 보강벽체(100)를 형성하며, 터널의 굴착 후, 보강벽체(100)에서 임시부재(530)를 제거하여 강재(510)의 결합부(표면)를 노출시키고, 그 강재(510)의 결합부에 강지보재(108)를 결합하는 방식을 취하는 경우, 더욱 우수한 시공성을 얻을 수 있다(도 10 내지 13).On the other hand, a provisional member 530 made of a material (styrofoam or the like) which is easy to release is provided in advance in the joint portion of the steel material 510, and a concrete pile having the upper temporary member and the steel material 510 inserted in the vertical direction along the vertical direction The reinforcing wall 100 is formed by installing a plurality of the reinforcing walls 500 in the reinforcing wall 100 and the provisional member 530 is removed from the reinforcing wall 100 after the tunnel is excavated, And a method of bonding the steel support material 108 to the joining portion of the steel material 510 is employed, more excellent workability can be obtained (Figs. 10 to 13).

이 경우에도, 강재(510)로는 H 빔을 적용하고, 그 H 빔의 플랜지 표면에 스티로폼 등의 임시부재(530)를 설치하는 경우, 더욱 우수한 시공성을 얻을 수 있다.Even in this case, when the H beam is applied to the steel material 510 and the provisional member 530 such as styrofoam is provided on the flange surface of the H beam, more excellent workability can be obtained.

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention as defined in the appended claims. It is to be understood that both the technical idea and the technical spirit of the invention are included in the scope of the present invention.

100 : 보강벽체 108 : 강지보재
108a : 횡방향 접합부 108b : 종방향 접합부
500 : 콘크리트 말뚝 510 : 강재
520 : 브라켓 530 : 임시부재
100: reinforced wall member 108: steel support member
108a: transverse bonding portion 108b: longitudinal bonding portion
500: Concrete pile 510: Steel
520: Bracket 530: Temporary member

Claims (3)

굴착 터널의 적어도 어느 일측벽에 인접하도록 터널 굴착방향을 따라 지중에 소정 깊이까지 보강벽체(100)를 설치하는 보강벽체 설치단계;
상기 터널 굴착방향을 따라 지중에 단위 구간의 터널을 굴착하는 단계와;
상기 단위 구간 터널 굴착부의 천단보강을 위해 강지보재(108)를 설치하는 단계;
상기 보강벽체(100)와 상기 강지보재(108)를 결합시키는 강지보재 결합단계;를 포함하는 비개착식 터널시공방법에 있어서,
상기 보강벽체 설치단계는,
상하방향을 따라 심부에 상기 강재(510)가 삽입된 콘크리트 말뚝(500) 다수를 열지어 지중에 설치함으로써 상기 보강벽체(100)를 형성하기 위하여, 지반에 천공 홀을 형성하고, 상기 강재(510)를 삽입하는 단계;
상기 천공 홀에 대하여 콘크리트를 타설하는 단계;를 포함하고,
상기 강지보재 결합단계는,
상기 보강벽체(100)의 표면 일부를 제거하여 상기 강재(510)의 결합부를 노출시키는 단계;
상기 강재(510)의 결합부에 상기 강지보재(108)를 결합하는 단계;를 포함하고,
상기 강재(510)는 H 빔이고, 상기 H 빔의 플랜지 표면이 상기 강지보재(108)와 결합하도록 상기 콘크리트 말뚝(500)에 삽입설치되고,
상기 강재(510)는 상기 콘크리트 말뚝(500)의 내측에 치우치도록 삽입설치되고,
상기 강지보재(108)는 아치형 구조이고,
상기 강지보재(108)의 단부는 횡방향을 따라 편평하게 가공되어 횡방향 접합부(108a)를 형성하며,
상기 강지보재(108)의 횡방향 접합부(108a)는 상기 강재(510)의 결합부에 결합하는 것을 특징으로 하는 보강벽체를 이용한 터널시공방법.
Installing a reinforced wall (100) to a predetermined depth in the ground along a tunnel excavation direction so as to be adjacent to at least one side wall of the excavation tunnel;
Drilling a unit section tunnel in the ground along the tunnel excavation direction;
Installing a steel material support (108) for reinforcing the ceiling of the unit section tunnel excavation part;
And a steel slab joining step of joining the reinforcing wall body (100) and the steel slab (108), the method comprising:
In the reinforcing wall installing step,
A plurality of concrete piles 500 in which the steel material 510 is inserted in the vertical direction along the vertical direction are installed in the ground to form a perforation hole in the ground to form the reinforcing wall body 100, );
And pouring concrete against the perforation hole,
The method of claim 1,
Removing a portion of the surface of the reinforced wall (100) to expose an engaging portion of the steel material (510);
And joining the steel support member (108) to a joining portion of the steel material (510)
The steel material 510 is an H beam and the flange surface of the H beam is inserted into the concrete pile 500 so as to engage with the steel support material 108,
The steel material 510 is inserted into the concrete pile 500 so as to be offset from the concrete pile 500,
The steel material support (108) has an arcuate structure,
The ends of the steel support members 108 are flattened along the transverse direction to form the transverse joints 108a,
Wherein the transverse joint portion (108a) of the steel support (108) is coupled to the joint portion of the steel (510).
제1항에 있어서,
상기 보강벽체 설치단계는,
이탈이 용이한 재질에 의한 임시부재(530)를 상기 강재(510)의 결합부에 설치하고, 상하방향을 따라 심부에 상기 강재(510)가 삽입된 콘크리트 말뚝(500) 다수를 열지어 지중에 설치함으로써 상기 보강벽체(100)를 형성하는 단계;를 포함하고,
상기 강지보재 결합단계는,
상기 보강벽체(100)에서 상기 임시부재(530)를 제거하여 상기 강재(510)의 결합부를 노출시키는 단계;
상기 강재(510)의 결합부에 상기 강지보재(108)를 결합하는 단계;를
포함하는 것을 특징으로 하는 보강벽체를 이용한 터널시공방법.
The method according to claim 1,
In the reinforcing wall installing step,
A temporary member 530 made of a material easily detachable is installed in the joint portion of the steel material 510 and a large number of concrete piles 500 having the steel material 510 inserted in the center portion along the vertical direction are opened, And forming the reinforced wall (100) by installing the reinforcement wall (100)
The method of claim 1,
Removing the provisional member (530) from the reinforced wall (100) to expose an engaging portion of the steel material (510);
Joining the steel support material (108) to the joining portion of the steel material (510);
Wherein the reinforcing wall is formed of a reinforcing material.
제2항에 있어서,
상기 강재(510)는 H 빔이고,
상기 임시부재(530)는 스티로폼이며,
상기 스티로폼은 상기 H 빔의 플랜지 표면에 설치하는 것을 특징으로 하는 보강벽체를 이용한 터널시공방법.
3. The method of claim 2,
The steel material 510 is an H beam,
The temporary member 530 is made of styrofoam,
Wherein the styrofoam is installed on a flange surface of the H beam.
KR1020170008448A 2017-01-18 2017-01-18 Tunnel construction method with support walls KR101819494B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170008448A KR101819494B1 (en) 2017-01-18 2017-01-18 Tunnel construction method with support walls

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170008448A KR101819494B1 (en) 2017-01-18 2017-01-18 Tunnel construction method with support walls

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020150088198A Division KR20170000008A (en) 2015-06-22 2015-06-22 Tunnel construction method with support walls

Publications (2)

Publication Number Publication Date
KR20170016897A true KR20170016897A (en) 2017-02-14
KR101819494B1 KR101819494B1 (en) 2018-01-18

Family

ID=58121302

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170008448A KR101819494B1 (en) 2017-01-18 2017-01-18 Tunnel construction method with support walls

Country Status (1)

Country Link
KR (1) KR101819494B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035733A (en) * 2017-11-01 2018-05-15 中铁四局集团有限公司 A kind of perpendicular support partial excavation method of rock matter large section tunnel steelframe dike combination
CN109113747A (en) * 2018-08-24 2019-01-01 江苏翰烽美筑工程技术有限公司 A kind of tunnel excavation engineering method
CN109404004A (en) * 2018-11-30 2019-03-01 中铁隧道集团二处有限公司 Cavern and its construction method for being assembled in push pipe auger
CN110985002A (en) * 2019-11-11 2020-04-10 中铁十九局集团第五工程有限公司 Tunnel construction method for horizontal semi-soft semi-hard section stratum
CN113685202A (en) * 2021-08-19 2021-11-23 中铁四局集团第四工程有限公司 Reaction wall structure for jacking cohesive soil layer pipe curtain and construction method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101169462B1 (en) * 2012-03-08 2012-07-30 (주)엠씨에스에스티기술사사무소 Top-down construction method using post member

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035733A (en) * 2017-11-01 2018-05-15 中铁四局集团有限公司 A kind of perpendicular support partial excavation method of rock matter large section tunnel steelframe dike combination
CN108035733B (en) * 2017-11-01 2019-10-25 中铁四局集团有限公司 A kind of perpendicular support partial excavation method of rock matter large section tunnel steelframe dike combination
CN109113747A (en) * 2018-08-24 2019-01-01 江苏翰烽美筑工程技术有限公司 A kind of tunnel excavation engineering method
CN109113747B (en) * 2018-08-24 2020-08-11 江苏华设远州交通科技有限公司 Tunnel excavation construction method
CN109404004A (en) * 2018-11-30 2019-03-01 中铁隧道集团二处有限公司 Cavern and its construction method for being assembled in push pipe auger
CN109404004B (en) * 2018-11-30 2024-02-20 中铁隧道集团二处有限公司 Cave for assembling in tunnel of pipe jacking machine and construction method of cave
CN110985002A (en) * 2019-11-11 2020-04-10 中铁十九局集团第五工程有限公司 Tunnel construction method for horizontal semi-soft semi-hard section stratum
CN110985002B (en) * 2019-11-11 2021-03-23 中铁十九局集团第五工程有限公司 Tunnel construction method for horizontal semi-soft semi-hard section stratum
CN113685202A (en) * 2021-08-19 2021-11-23 中铁四局集团第四工程有限公司 Reaction wall structure for jacking cohesive soil layer pipe curtain and construction method
CN113685202B (en) * 2021-08-19 2023-08-18 中铁四局集团第四工程有限公司 Counterforce wall structure for jacking cohesive soil layer pipe curtain and construction method

Also Published As

Publication number Publication date
KR101819494B1 (en) 2018-01-18

Similar Documents

Publication Publication Date Title
KR101819494B1 (en) Tunnel construction method with support walls
KR101324173B1 (en) Construction method for underground tunnel using guiding shape steel
KR100794609B1 (en) Construction method of underground structure using concrete filled pipe roof and concrete wall
JP2019127692A (en) Joint structure of concrete members
KR102149474B1 (en) Installation method and Steel structure with non-opening steel composite concrete support
KR20070076553A (en) Construction method of underground structure using concrete filled pipe roof and concrete wall
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
KR20050092881A (en) Steel pipe roof construction method for building underground structure, roof structure therefor, and structure of steel pipe therefor
KR100383268B1 (en) method for underground construction of building by using permanent structural member as strut for support retaining wall
KR20170000008A (en) Tunnel construction method with support walls
KR102129608B1 (en) Semi open cut type tunnel construction method at low overburden
KR101479267B1 (en) Method for constructing tunnel by using pipe
KR20080034424A (en) A constructing method of underground structure with supporting beam for steel pipe
KR20030065963A (en) A method of constrution method for tunnel of structure pipe
KR101234270B1 (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
KR101612522B1 (en) Construction method for tunneling
KR200354467Y1 (en) Steel pipe roof structure for building underground structure
KR20220028563A (en) Method for forming a two-way girder using press-fit steel pipes in underground structure construction
JP6022729B1 (en) Cut beam support and bridge pier reinforcement method using it
KR101671806B1 (en) Construction method for tunneling
JP2005325556A (en) Concrete sheet pile
JP2009102804A (en) Earth retaining construction method
TWI790741B (en) Retaining wall and its construction method
KR101254608B1 (en) Tunnel construction method with support walls
KR101524302B1 (en) Construction method for underground structure without temporary structure

Legal Events

Date Code Title Description
A107 Divisional application of patent
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant