KR20160099150A - Bridge construction method using anchorage device for tendon axis displacement control - Google Patents

Bridge construction method using anchorage device for tendon axis displacement control Download PDF

Info

Publication number
KR20160099150A
KR20160099150A KR1020150020895A KR20150020895A KR20160099150A KR 20160099150 A KR20160099150 A KR 20160099150A KR 1020150020895 A KR1020150020895 A KR 1020150020895A KR 20150020895 A KR20150020895 A KR 20150020895A KR 20160099150 A KR20160099150 A KR 20160099150A
Authority
KR
South Korea
Prior art keywords
girder
anchor head
fixing
tension member
horizontal block
Prior art date
Application number
KR1020150020895A
Other languages
Korean (ko)
Other versions
KR101674471B1 (en
Inventor
추태석
추태헌
김지현
김현진
김성진
조윤영
Original Assignee
(주)성환이앤씨
추태헌
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)성환이앤씨, 추태헌 filed Critical (주)성환이앤씨
Priority to KR1020150020895A priority Critical patent/KR101674471B1/en
Publication of KR20160099150A publication Critical patent/KR20160099150A/en
Application granted granted Critical
Publication of KR101674471B1 publication Critical patent/KR101674471B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • E04C5/12Anchoring devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention provides a method to construct a girder bridge by using an anchorage apparatus for tendon axis adjustment, to easily match axes of anchor heads which are anchored in an anchorage device buried in the inside of a girder after tension to improve a pre-stress introduction effect. According to the present invention, the anchorage apparatus for tendon axis adjustment comprises: an anchorage device including an anchoring plate; an anchor head supported by the anchoring plate; and an anchor head support block which includes a horizontal block where the anchor head and the anchor head support block come in point or surface contact with each other, and an extended horizontal block integrally formed with the horizontal block to be fixed and installed in the anchoring plate.

Description

긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법{BRIDGE CONSTRUCTION METHOD USING ANCHORAGE DEVICE FOR TENDON AXIS DISPLACEMENT CONTROL}TECHNICAL FIELD [0001] The present invention relates to a girder bridge construction method using a fixing device for a torsional rigid frame,

본 발명은 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법에 관한 것이다. 더욱 구체적으로 거더 내부에 설치되는 정착장치에 긴장 후 정착되는 앵커헤드의 중심축을 서로 용이하게 일치시킬 수 있도록 하여 프리스트레스 도입효과를 증진시킬 수 있는 단경간 및 다경간용 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법에 관한 것이다.The present invention relates to a method of constructing a girder bridge using a fixing device for a tension member center-tune adjustment. More specifically, it is possible to easily adjust the center axis of the anchor head to be fixed after the tension to the fixing device installed in the girder, thereby improving the effect of introducing the prestress. Girder bridge construction method.

일반적으로 거더교는 교대와 교각 또는 교각과 교각 사이에 거더를 길이방향(종방향)으로 설치하고, 상기 거더의 상면에 바닥판(슬래브)을 설치하는 방식으로 교량을 시공하게 된다.Generally, the girder bridges are constructed in such a manner that a girder is installed in a longitudinal direction (longitudinal direction) between an alternation and a pier or a pier and a pier, and a bottom plate (slab) is installed on the upper surface of the girder.

또한, 교각(교대)과 교각 사이를 경간(Span)이라고 하는데 각 경간의 주형이 분리된 교량을 단순교라 하고, 각 경간의 주형이 연속된 것을 연속교라 한다.Also, the bridge between the piers (alternating) and the piers is called a span, and the bridges in which the bridges of the bridges are separated are simple bridges.

이때, 단경간 거더교는 교대와 교대 사이에 거더를 거치하고, 상기 거더 상부에 슬래브를 시공하는 방식으로 시공하게 된다.At this time, the single span girder bridges are constructed in such a manner that a girder is interposed between the alternation and alternation, and a slab is installed on the girder.

다경간 거더교는 교대와 교각을 다수 설치하고 교대, 교각 사이에 거더를 거치하여 상기 거더 상부에 슬래브를 시공하는 방식으로 시공하게 된다.The multi span girder bridges are constructed by installing a plurality of alternating and pier angles, alternately installing the slab between the piers and placing the girders on the girders.

도 1a는 상기 거더를 도시한 것이다.Fig. 1A shows the girder.

이러한 거더(50)는 상부플랜지(51), 복부(52) 및 하부플랜지(53)를 포함하며, 상기 복부(52) 양 외측면에 측면정착블록(60)을 형성시키고, 상기 측면정착블록(60)에 긴장용 정착부(61)와 보수보강용 정착부(62)를 함께 설치하고 있음을 알 수 있다.The girder 50 includes an upper flange 51, an abdomen 52 and a lower flange 53. The girder 50 forms a side fixing block 60 on both outer sides of the abdomen 52, 60 are provided together with the tension fixing part 61 and the fixing part 62 for repair and reinforcement.

이에 상기 긴장용 정착부와 보수보강용 정착부가 함께 형성되다 보니 긴장재들(54,55)을 긴장 및 정착시킴에 있어 협소한 작업 공간과 교량 시공을 함에 있어 고소작업의 어려움 때문에 시공성이 불량하고 안전사고가 빈번하다는 문제점이 있었다.Accordingly, the tension fixation unit and the repair and fixing fixture unit are formed together to tighten and fix the tensile members 54 and 55. As a result, the construction work is poor and safety There was a problem that accidents were frequent.

또한, 상기 거더로서 PSC 거더를 이용하는 경우, 상기 PSC 거더에 사용되는 긴장장치의 경우 정착장치(정착구, 앵커헤드 및 쐐기 등 포함)와 긴장재를 이용하게 된다.In the case of using the PSC girder as the girder, the tension device used in the PSC girder uses a fixing device (including an anchorage hole, an anchor head, and a wedge) and a tension member.

하지만 이러한 정착장치에 긴장재가 긴장 후 정착될 때, 재 긴장하거나 긴장력을 유지하면서도 간편하게 긴장력을 유지 및 조정할 수 있는 장치가 없어 현장에서 이를 조절하는 방법이 용이하지 않을 수 있다는 문제점이 있었다.However, there is a problem that when the tension member is fixed after the tension is applied to such a fixing apparatus, there is no device that can easily maintain and adjust the tension force while maintaining the tension or tension.

구체적으로는 종래 PSC 거더용 정착구(10)는 도 1b와 같이 프리스트레스 도입을 위해 사용되는 긴장재(30)가 관통되도록 설치된 일종의 하우징(Housing)이라 할 수 있다.Specifically, the conventional fixing port 10 for the PSC girder is a kind of housing which is installed to penetrate the prestressing member 30 used for introducing the prestress, as shown in FIG. 1B.

이러한 정착구(10)의 우측 단부는 주름관 형태로서 거더 내부에 설치되는 긴장재용 쉬스(40)가 연결되도록 하고, 상기 주름관에 주물등으로 제작된 정착헤드(11) 및 정착헤드(11)를 거더 표면에 위치하도록 하면서 국부응력을 분산시키는 정착판(13)을 포함하여 설치된다.The right end of the fixing port 10 is formed in the form of a corrugated pipe so as to connect the sheath 40 for tension material installed inside the girder and fix the fixing head 11 and the fixing head 11 made of casting or the like to the corrugated pipe, And a fusing plate 13 for dispersing local stress while being located at a predetermined position.

이에 정착구(10) 내부를 관통하는 긴장재(30)는 정착구(10) 외부로 인출되며 앵커헤드(20)를 관통하도록 하고, 상기 앵커헤드(20)를 관통하는 긴장재(30)를 긴장 후, 쐐기(50)를 이용하여 앵커헤드(20)에 긴장재를 쐐기(Wedge)를 이용하여 정착시키게 된다.The tension member 30 passing through the fixing hole 10 is drawn out of the fixing hole 10 and passes through the anchor head 20. After the tension member 30 passing through the anchor head 20 is tensed, The tension member is fixed to the anchor head 20 using a wedge by using the wedge 50.

이때, 상기 앵커헤드(20)는 프리스트레스에 의하여 정착헤드(11)의 정착판(13)에 지지되도록 하게 된다.At this time, the anchor head 20 is supported by the fusing plate 13 of the fixing head 11 by the prestress.

하지만 다수의 긴장재(30)를 개별적으로 혹은 한꺼번에 긴장 후 정착시키는 과정에서 앵커헤드(20)가 정착판(13)상에서 상,하,좌,우로 이동이 발생하여 정착구(10)의 중심축과 앵커헤드(20)의 중심축이 실제로는 일치하지 않은 경우가 발생하게 되고, 이는 긴장재가 포물선 형태로 거더 내부에 배치되는 경우 등에 있어 더욱 많이 발생하게 된다.However, in the process of fixing a plurality of the tension members 30 individually or after tensioning, the anchor head 20 moves upward, downward, leftward, and rightward on the fixing plate 13 so that the center axis of the fixing port 10, The center axes of the heads 20 do not actually coincide with each other, which is more likely to occur when the tension members are disposed inside the girders in the form of a parabola.

이에 긴장재에 의하여 도입되는 프리스트레스가 거더에 제대로 도입되지 못하는 문제점이 발생하게 되므로 상기 정착구(10)의 중심축과 앵커헤드(20)의 중심축이 서로 일치하도록 긴장재(30)를 긴장 및 정착시키는 작업이 매우 중요하게 되는데 현장에서의 품질관리는 기대에 못 미치는 경우가 많았다.The prestress introduced by the tension member can not be properly introduced into the girder, so that the tension member 30 is tensioned and fixed so that the central axis of the fixation port 10 and the central axis of the anchor head 20 coincide with each other The quality control in the field was often less than expected.

이에 본 발명은 거더에 설치되는 정착구와 앵커헤드의 중심축을 현장에서 용이하게 일치시킨 상태에서 긴장재를 긴장 및 정착시킬 수 있어, 보다 효율적인 프리스트레스 도입이 가능한 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법 제공을 해결하고자 하는 기술적 과제로 한다.Accordingly, the present invention provides a method of constructing a girder bridge using a fixing device for a prestressing core structure capable of tensioning and fixing a tension member in a state in which a center axis of an anchor head and an anchor head installed on a girder are easily aligned in a field. To solve the problem.

상기 과제를 달성하기 위하여 본 발명은In order to achieve the above object,

긴장재 및 긴장재 중심축조정용 정착장치를 이용한 단경간 교량시공방법에 있어서,A method for constructing a short-span bridge using a fixing device for a tie-rod and a tie-

(a) 제 1긴장재를 거더 제작 시 거더 양 단부면에 긴장재 중심축조정용 정착장치를 이용하여 긴장 후 정착되도록 함으로써 거더에 압축 프리스트레스가 초기 도입되도록 하고, 상기 긴장재 중심축조정용 정착장치의 정착판을 거더의 양 단부면에 매입 설치되도록 거더를 제작하는 단계; 및 (a) a first prestress is first introduced into a girder by causing the first prestressing material to be fixed after being strained by using a fixing device for a prismatic tie-rod adjusting device at both ends of the girder when the girder is manufactured, Fabricating a girder so as to be embedded in both end faces of the girder; And

(b) 상기 거더를 교대 사이에 설치한 후, 상기 거더 상부에 슬래브를 시공하는 단계;를 포함하며, 상기 긴장재 중심축조정용 정착장치는 정착헤드와 일체로 형성되어 긴장재가 거더 표면에 위치하도록 하면서 국부응력을 분산시키는 상기 정착판을 포함하는 정착구; 상기 정착구를 관통하는 긴장재가 긴장재홀을 통해 긴장 후 정착되어 상기 정착판에 지지되는 앵커헤드; 및 앵커헤드와 앵커헤드지지블록이 서로 점 접촉 또는 면 접촉되는 수평블록 및 상기 수평블록과 일체로 형성되어 정착판에 고정 설치되는 확장수평블록을 포함하여 구성된 앵커헤드지지블록;을 포함하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법을 제공한다.(b) installing a slab on the upper part of the girder after the girders are installed alternately, wherein the fixing device for a center member for adjusting a torsion member is integrally formed with a fixing head so that a tension member is positioned on the surface of the girder A fixture including the fixation plate for dispersing local stress; An anchor head fixed to the fixation plate through a tension member hole after being strained through the fixation hole; And an anchor head supporting block including a horizontal block in which the anchor head and the anchor head supporting block are in point contact or surface contact with each other, and an enlarged horizontal block integrally formed with the horizontal block and fixed to the fixing plate. A girder bridge construction method using a fixing device for a building fixation is provided.

또한 긴장재 및 긴장재 중심축조정용 정착장치를 이용한 다경간 교량시공방법에 있어서,Also, in a method of constructing a multi-span bridge using a fixing device for a tensional material and a tension member,

(a) 제 1긴장재를 거더 제작 시 거더 양 단부면에 긴장재 중심축조정용 정착장치(100)를 이용하여 긴장 후 정착되도록 함으로써 거더에 압축 프리스트레스가 초기 도입되도록 하고, 상기 긴장재 중심축조정용 정착장치의 정착판을 거더의 양 단부면에 매입 설치되도록 거더를 제작하는 단계; (a) a first prestress is first introduced into a girder by causing the first prestressing material to be fixed after being strained by using a fixing device 100 for a prismatic central structural unit on both end faces of the girder when the girder is manufactured, Fabricating the girder so that the fixing plate is embedded in both end surfaces of the girder;

(b) 상기 거더의 일측 단부에서 중앙쪽으로 이격되어 위치한 상부면을 절취하여 일정깊이를 구비한 거더 상면 긴장부가 형성되도록 하며, 연속지점부에 위치하게 될 타측 단부는 단부에서 상단을 절취하여 거더 지점부 상단공간부(B)가 형성되도록 하여, 상기 거더 상면 긴장부와 거더 지점부 상단공간부에 연통되도록 제 2긴장재용 쉬스가 설치되도록 거더를 제작하는 단계;(b) a girder upper surface tension portion having a predetermined depth is cut off at an upper surface spaced apart from the center at one end of the girder, and the other end portion to be positioned at the continuous point portion is cut off at the upper end of the girder, Forming a girder so that a sheath for a second tension material is provided so as to communicate with the upper surface tension portion of the girder and the upper space portion at the upper end of the girder portion so as to form the lower end space portion B;

(c) 상기 제작된 거더를 상기 단부 지점부와 연속지점부에 걸쳐지도록 설치하여 연속지점부에서 상기 거더 지점부 상단공간부가 서로 마주보도록 하여 연속지점부에 확장된 지점부 연결공간(E)이 형성되도록 하는 단계; 및(c) The girder is installed so as to extend over the end portion and the continuous portion so that the girder portion upper end space portion is opposed to each other at the successive portion so that the extended portion connecting space (E) ; And

(d) 상기 연속지점부에서 마주보는 제 2긴장재용 쉬스를 상기 확장된 지점부 연결공간을 활용하여 교량의 종방향 선형곡률과 일치되게 하고 수직 편심을 최대화 할 수 있도록 연속지점부연결관으로 연결한 후, 거더 상부에 슬래브를 시공하는 단계;를 포함하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법을 제공한다.(d) connecting the sheath for the second tension member facing the continuous point portion to the continuous point portion connection pipe so as to match the longitudinal linear curvature of the bridge utilizing the expanded focal point connection space and maximize the vertical eccentricity And a step of placing the slab on the upper part of the girder after the girder bridge construction.

이때 상기 긴장재 중심축조정용 정착장치(100)는At this time, the fixing device 100 for a tenter material center-

첫째, 앵커헤드의 위치를 구속시킬 수 있는 앵커헤드지지블록을 정착판에 미리 위치를 세팅시켜 놓고, 앵커헤드지지블록에 앵커헤드가 접하도록 위치시키는 것만으로도 간단하게 앵커헤드와 정착구의 중심축을 일치하도록 하게 되며, 긴장재에 의한 프리스트레스가 도입될 때, 앵커헤드가 앵커헤드지지블록에 지지되어 이동이 구속되도록 하게 된다. 따라서 작업자가 앵커헤드와 정착구의 중심축을 일치시키기 위한 노력이 필요 없도록 하게 된다. First, by setting the anchor head supporting block capable of restraining the position of the anchor head in advance on the fixing plate, and positioning the anchor head in contact with the anchor head supporting block, it is possible to easily set the center axis of the anchor head and the anchor head And when the prestress by the tension member is introduced, the anchor head is supported by the anchor head support block to restrain the movement. Thus, the operator does not need to make efforts to align the center axis of the anchor head with the anchor hole.

둘째, 상기 앵커헤드지지블록은 정착판의 표면에 앵커헤드의 일측 외주면이 지지될 수 있도록 고정되도록 하면 되고, 일종의 지지블록으로 형성시키면 된다. 이에 앵커헤드와 앵커헤드지지블록은 서로 1점 접촉에 의한 지지상태가 되도록 하게 된다.Second, the anchor head support block may be fixed to the surface of the anchor head so that one side of the anchor head can be supported, and may be formed as a kind of support block. Thus, the anchor head and the anchor head supporting block are brought into a supported state by one point contact with each other.

이때 상기 1점 접촉에 의한 앵커헤드지지블록은 일방향으로만 앵커헤드의 이동을 구속하므로 상기 앵커헤드지지블록을 수용홈을 가지는 형태 예컨대 U형 수용부로 형성시키고, 상기 U형 수용부에 앵커헤드의 일부가 삽입 지지되도록 하게 되면 서로 다른 방향으로 점접촉이 발생하기 때문에 3점 접촉으로도 앵커헤드를 구속시킬 수 있게 된다.At this time, since the anchor head supporting block by the one-point contact restrains movement of the anchor head only in one direction, the anchor head supporting block is formed into a shape having a receiving groove, for example, a U-shaped receiving portion, When the part is inserted and supported, point contact occurs in different directions, so that the anchor head can be restrained even by three-point contact.

또한, 상기 점접촉이 아닌 면접촉이 되도록 앵커헤드의 접촉면과 동일한 형태로 앵커헤드지지블록의 접촉면을 곡면부(S)로 형성시키게 되면 보다 안정적인 앵커헤드 지지가 가능하게 되며 구속도 용이하게 된다.Further, if the contact surface of the anchor head supporting block is formed of the curved surface portion S in the same shape as the contact surface of the anchor head so that the surface contact is not the point contact, more stable anchor head support is possible and restraint becomes easy.

본 발명에 의한 중심축조정용 정착장치를 이용한 거더교는 제 1,2,3 긴장재를 모두 사용할 수 있음에 따른 긴장재 도입 효과를 증진시킬 수 있어 유지관리에 유리한 단경간 또는 다경간 거더교 시공이 가능하게 된다.Since the girder bridges using the fixing device for central axis adjustment according to the present invention can use all of the first, second and third tensions, it is possible to improve the effect of introducing the tensions, thereby enabling the construction of a short span or multi span girder bridge favorable for maintenance .

본 발명에 의하여 작업자는 간단하게 정착구에 앵커헤드의 중심축을 일치시켜 거더에 프리스트레스를 도입시킬 수 있으며, 앵커헤드의 위치가 구속된 상태에서 PT작업이 가능하여 작업성 효율이 크게 증진될 수 있게 된다.According to the present invention, the operator can easily introduce the prestress into the girder by aligning the center axis of the anchor head with the fixture, and PT work is possible in a state where the position of the anchor head is constrained, .

또한, 정착구에 앵커헤드의 중심축을 일치시킴에 있어 긴장재의 종류에 따른 스페이서를 제공하여 보다 긴장재 품질관리에 매우 유리하게 된다.Further, in providing the spacer according to the kind of the tension member in matching the center axis of the anchor head with the fixture, it is very advantageous in quality control of the tension member.

도 1a는 종래 측면정착블록을 이용한 거더 구성도,
도 1b는 종래 정착구와 앵커헤드의 설치도,
도 2a, 도 2b 및 도 2c는 본 발명에 의한 긴장재 중심축조정용 정착장치의 예시도,
도 2d는 본 발명에 사용되는 앵커헤드의 사용도,
도 3a 및 도 3b는 본 발명에 의한 긴장재 중심축조정용 정착장치를 이용한 거더 및 이를 이용한 단경간 거더교의 시공순서도,
도 4a 및 도 4b는 본 발명에 의한 긴장재 중심축조정용 정착장치를 이용한 거더 연결도 및 이를 이용한 다경간 거더교의 시공순서도이다.
FIG. 1A is a girder construction diagram using a conventional side fusing block,
FIG. 1B is a view showing the installation of the conventional anchorage head and anchor head,
FIGS. 2A, 2B, and 2C are diagrams illustrating an example of a fixing device for adjusting a center member of a tension member according to the present invention;
FIG. 2d is a view showing the use of the anchor head used in the present invention,
FIG. 3A and FIG. 3B are views showing a construction procedure of a girder using a fixing device for a center member of a tie member according to the present invention, and a single span girder bridge using the same.
FIGS. 4A and 4B are a view illustrating a girder connection using a fixing device for a tentative core adjustment according to the present invention, and a construction sequence of a multi-span girder bridge using the same.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings, which will be readily apparent to those skilled in the art. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In order to clearly illustrate the present invention, parts not related to the description are omitted, and similar parts are denoted by like reference characters throughout the specification.

명세서 전체에서, 어떤 부분이 어떤 구성요소를 "포함"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다.Throughout the specification, when an element is referred to as "comprising ", it means that it can include other elements as well, without excluding other elements unless specifically stated otherwise.

[ 본 발명에 의한 긴장재 중심축조정용 정착장치(100) ][Fixing Apparatus (100) for Tension Material Center Tune Adjustment According to the Present Invention)

도 2a, 도 2b 및 도 2c는 본 발명에 의한 긴장재 중심축조정용 정착장치(100)의 예시도이다. 이러한 각각의 긴장재 중심축조정용 정착장치(100)는 앵커헤드지지블록(200)과 긴장재 중심축조정용 정착장치(100)를 구성하는 정착판(113)의 지지방식에 따라 구분된다.FIGS. 2A, 2B and 2C are views illustrating an example of a fixing device 100 for a tenter material center-tune adjustment according to the present invention. Each of the fixing devices 100 for a torsion centering unit is divided in accordance with the supporting method of the fixing plate 113 constituting the anchor head supporting block 200 and the fixing device 100 for adjusting the center of the tension member.

[실시예 1][Example 1]

도 2a는 본 발명의 실시예 1에 의한 긴장재 중심축조정용 정착장치(100)의 예시도이다.FIG. 2A is an exemplary view of a fixing device 100 for a tenter material center-tune adjustment according to a first embodiment of the present invention.

먼저 긴장재 중심축조정용 정착장치(100)는 미리 기성제품으로 구입이 가능하고 본 발명을 위한 별도의 생산설비가 필요하다면 긴장재 중심축조정용 정착장치(100)의 구입단가가 올라 갈 수 있다.First, the fixing device 100 for the tie member center-tie fixation can be purchased as a prefabricated product, and if the separate production facility for the present invention is required, the purchase price of the fixing device 100 for the tie member center-

이에 본 발명은 긴장재 중심축조정용 정착장치(100)를 구성하는 정착구(110)에 앵커헤드(120)를 지지할 수 있는 블록형태의 앵커헤드지지블록(200)만을 부가적으로 설치하게 된다.Accordingly, only the anchor head supporting block 200 in the form of a block capable of supporting the anchor head 120 is additionally installed in the fixing hole 110 constituting the fixing device 100 for a center member for adjusting tensions.

이에 상기 긴장재 중심축조정용 정착장치(100)는 거더에 매립 설치되는 정착구(110)와 앵커헤드(120)를 포함한다.The fixing device 100 for a tenter material central axis adjustment includes an anchor head 120 and a fixing hole 110 embedded in a girder.

먼저 거더는 PSC 거더와 같이, 프리스트레스를 도입하기 위한 빔 부재를 의미하며 기타 정착장치가 설치되는 부재라면 달리 제한되지는 않을 것이다.First, the girder is a beam member for introducing a prestress like a PSC girder, and is not limited to a member provided with other fixing devices.

이러한 정착구(110)의 단부는 주름관 형태로서 거더 내부에 설치되는 긴장재용 쉬스가 연결되도록 하고, 상기 주름관에 일체로 형성된 정착헤드(111), 상기 정착헤드(111)를 감싸 거더에 매립 설치되는 보강철근(112) 및 정착헤드(111)와 일체로 형성되어 거더 표면에 위치하도록 하면서 국부응력을 분산시키는 정착판(113)을 포함하도록 구성된다.The end of the fixing port 110 is formed as a corrugated pipe type and has a fixing head 111 formed integrally with the corrugated tube so as to connect the sheath for the tension member installed in the inside of the girder, And a fusing plate 113 formed integrally with the reinforcing bar 112 and the fixing head 111 to disperse local stress while being positioned on the surface of the girder.

이때 상기 정착판(113)은 예컨대, 사각판 형태로 거더 일면에 매립 또는 돌출되도록 형성시킬 수 있는데 이러한 정착판(113)에 앵커헤드지지블록(200)을 고정 설치시키게 된다.At this time, the fusing plate 113 may be formed to be embedded or protruded on one side of the girder, for example, in the form of a rectangular plate. The anchor head supporting block 200 is fixed to the fusing plate 113.

실시예 1에 의한 앵커헤드지지블록(200)은 앵커헤드(120)와 앵커헤드지지블록(200)이 서로 1점 접촉 되도록 하는 형태(도 2a에서 1개의 점으로 표시됨)로서 통상 원형판 형태의 앵커헤드 외주면과 1점 접촉하는 직육면체 블록인 수평블록(210)을 구비하도록 형성된 것임을 알 수 있다.The anchor head supporting block 200 according to the first embodiment is configured such that the anchor head 120 and the anchor head supporting block 200 are in contact with each other at one point (indicated by one point in FIG. 2A) And a horizontal block 210, which is a rectangular parallelepiped block that is in one-point contact with the outer peripheral surface of the head.

이때, 상기 수평블록(210)을 직접 정착판(113)에 고정시키는 경우 수평블록과 정착판이 서로 접하는 부위에 응력집중이 될 수 있고, 정착판(113)에 앵커헤드지지블록(200)을 고정시키기 위한 체결구(260)를 체결시킬 경우 수평블록(210)의 단면손실이 발생할 수 있다.In this case, when the horizontal block 210 is directly fixed to the fixing plate 113, stress can be concentrated on a portion where the horizontal block and the fixing plate are in contact with each other, and the anchor head supporting block 200 is fixed A cross-sectional loss of the horizontal block 210 may occur when the fastener 260 is fastened.

이에 상기 수평블록(210) 보다 큰 단면을 가진 확장수평블록(220)을 수평블록(210)과 일체로 형성시키고, 상기 확장수평블록(220)을 정착판(113)에 앵커볼트와 같은 체결구(260)로 고정되도록 하게 된다.An extended horizontal block 220 having a larger cross section than the horizontal block 210 is integrally formed with the horizontal block 210. The extended horizontal block 220 is fixed to the fixing plate 113 by a fastener such as an anchor bolt (260).

이에 2개의 직사각형 단면을 가진 수평블록(210)과 확장수평블록(220)으로 구성된 앵커헤드지지블록(200)은 정착판(113)에 고정 형성되어 있고, 이러한 앵커헤드지지블록(200)에 1점 접촉에 의하여 앵커헤드(120)가 지지되도록 하게 됨을 알 수 있다.The anchor head supporting block 200 composed of the horizontal block 210 having the two rectangular cross sections and the extended horizontal block 220 is fixed to the fixing plate 113 and is fixed to the anchor head supporting block 200 It can be seen that the anchor head 120 is supported by the point contact.

이로서 상기 앵커헤드(120)의 자중과 프리스트레스에 대한 응력분산을 부담하는 앵커헤드지지블록(200)의 설치로 인해 작업자는 긴장재의 긴장 및 정착에 의한 앵커헤드(120)의 이동을 효과적으로 구속시켜 효율적인 거더에 프리스트레스 도입이 가능하게 된다.Accordingly, the anchor head supporting block 200, which imposes stress dispersion on the anchor head 120 and the prestress, effectively restrains the movement of the anchor head 120 due to the tension and fixation of the tension member, It becomes possible to introduce the prestress into the girder.

이로서 긴장재의 긴장 및 정착시 정착판(113)에서 앵커헤드(120)의 상,하,좌,우 이동을 앵커헤드(120)의 하부에 접하여 지지하는 상기 앵커헤드지지블록(200)이 구속하여 긴장재의 긴장 및 정착 시 정착구(110)의 중심축과 앵커헤드(20)의 중심축이 서로 일치시킬 수 있어 긴장재에 의한 프리스트레스 도입효과를 증진시킬 수 있게 된다.The anchor head supporting block 200 which supports the anchor head 120 in contact with the lower portion of the anchor head 120 restrains the upward, downward, leftward and rightward movement of the anchor head 120 in the fixing plate 113 when the tension member is tensed and fixed The center axis of the fixing member 110 and the center axis of the anchor head 20 can be aligned with each other when the tension member is tensed and fixed, thereby enhancing the effect of introducing the prestress by the tension member.

[실시예 2][Example 2]

도 2b는 본 발명의 실시예 2에 의한 긴장재 중심축조정용 정착장치(100)의 예시도이다.FIG. 2B is an exemplary view of a fixing device 100 for a tenter material center-tune adjustment according to a second embodiment of the present invention.

상기 실시예 2의 경우 실시예 1과 다른 점은 앵커헤드지지블록(200)의 수평블록(210)이 실시예 1은 직사각형 단면의 블록인 반면 실시예 2의 경우에는 U형 수평블록을 채택하고 있다는 점에 차이가 있다. The second embodiment differs from the first embodiment in that the horizontal block 210 of the anchor head supporting block 200 is a block having a rectangular cross section in the first embodiment, while a U-shaped horizontal block is adopted in the second embodiment There is a difference.

구체적으로 살펴보면, 도 2b와 같이 상기 실시예 2에 의한 긴장재 중심축조정용 정착장치(100)도 역시 거더에 매립 설치되는 정착구(110)와 앵커헤드(120)를 포함한다.Specifically, as shown in FIG. 2B, the fixing device 100 for a center member for adjusting a tension member according to the second embodiment also includes a fixing hole 110 and an anchor head 120, which are embedded in a girder.

이에 상기 정착구(110)도 단부는 주름관 형태로서 거더 내부에 설치되는 긴장재용 쉬스가 연결되도록 하고, 상기 주름관에 주물 등으로 제작된 정착헤드(111), 상기 정착헤드(111)를 감싸 거더에 매립 설치되는 보강철근(112), 정착헤드(111)를 거더 표면에 위치하도록 하면서 국부응력을 분산시키는 정착판(113)을 포함한다.The fixture 110 is also formed in the shape of a corrugated tube so that the sheath for the tension member installed inside the girder is connected to the fixture head 110. The fixation head 111 made of cast iron or the like is embedded in the corrugated tube, And a fusing plate 113 for dispersing local stress while positioning the fixing head 111 on the surface of the girder.

이때 상기 정착판(113)은 역시 사각판 형태로 거더 일면에 매립 또는 돌출되도록 형성시킬 수 있는데 이러한 정착판(113)에 앵커헤드지지블록(200)을 고정 설치시키게 된다.At this time, the fusing plate 113 may be formed to be embedded or protruded on one side of the girder in the form of a rectangular plate. The anchor head supporting block 200 is fixed to the fusing plate 113.

실시예 2에 의한 앵커헤드지지블록(200)은 앵커헤드(120)와 앵커헤드지지블록(200)이 서로 3점 접촉 되도록 하는 형태(도 2b에서 3개의 점으로 표시됨)로서 통상 원형판 형태의 앵커헤드 외주면과 3점 접촉하는 U형 수평블록(230)을 가지도록 형성된 것임을 알 수 있다.The anchor head supporting block 200 according to the second embodiment is configured such that the anchor head 120 and the anchor head supporting block 200 are in contact with each other at three points (indicated by three dots in FIG. 2B) And a U-shaped horizontal block 230 contacting the outer peripheral surface of the head at three points.

즉, 앵커헤드(120)의 외주면은 U형 수평블록(230)의 내측면 3점에 각각 지지되도록 하고 있으며, 결국 앵커헤드(120)가 U형 수평블록(230) 내측에 삽입되어 지지되도록 하는 것임을 알 수 있다.That is, the outer circumferential surface of the anchor head 120 is supported at three points on the inner side of the U-shaped horizontal block 230, so that the anchor head 120 is inserted and supported inside the U-shaped horizontal block 230 .

이때, 상기 U형 수평블록(230)을 직접 정착판(113)에 고정시키는 경우 역시 U형 수평블록(230)과 U형 수평블록(230)과 정착판이 서로 접하는 부위에 응력집중이 될 수 있고, 정착판(113)에 앵커헤드지지블록(200)을 고정시키기 위한 체결구(260)를 체결시킬 경우 U형 수평블록(230)의 단면손실이 발생할 수 있다.When the U-shaped horizontal block 230 is directly fixed to the fusing plate 113, the stress may be concentrated on a portion where the U-shaped horizontal block 230 and the U-shaped horizontal block 230 contact with the fixing plate , A cross-sectional loss of the U-shaped horizontal block 230 may occur when a fastener 260 for fixing the anchor head supporting block 200 to the fixing plate 113 is fastened.

이에 상기 U형 수평블록(230) 보다 큰 단면을 가진 확장수평블록(220)을 U형 수평블록(230)과 일체로 형성시키고, 상기 확장수평블록(220)을 정착판(113)에 앵커볼트와 같은 체결구(260)로 고정되도록 하게 된다.An extended horizontal block 220 having a larger cross section than the U-shaped horizontal block 230 is integrally formed with the U-shaped horizontal block 230. The extended horizontal block 220 is fixed to the anchor bolt As shown in FIG.

이로서 앵커헤드지지블록(200)은 정착판(113)에 고정되어 있고, 이러한 앵커헤드지지블록(200)에 3점 접촉에 의하여 앵커헤드(120)가 세팅되도록 하게 됨을 알 수 있다.The anchor head supporting block 200 is fixed to the fixing plate 113 and the anchor head 120 is set by three-point contact with the anchor head supporting block 200.

역시 상기 앵커헤드(120)의 자중과 프리스트레스에 대한 응력분산을 부담하는 앵커헤드지지블록(200)의 설치로 인해 작업자는 긴장재의 긴장 및 정착에 의한 앵커헤드(120)의 이동을 구속시켜 효율적인 거더에 프리스트레스 도입이 가능하게 된다.The anchor head supporting block 200 which imposes stress dispersion on the anchor head 120 and the prestress also restrains the movement of the anchor head 120 due to the tension and fixation of the tension member, It is possible to introduce a prestress into the system.

[실시예 3][Example 3]

도 2c는 본 발명의 실시예 3에 의한 긴장재 중심축조정용 정착장치(100)의 예시도이다.FIG. 2C is an exemplary view of a fixing device 100 for a tenter material center-tune adjustment according to a third embodiment of the present invention.

상기 실시예 3의 경우 실시예 1과 다른 점은 앵커헤드지지블록(200)의 수평블록(210)이 실시예 1의 경우에는 직사각형 단면의 블록인 반면 실시예 3의 경우에는 곡선형 수평블록이라는 점에 차이가 있다. The third embodiment differs from the first embodiment in that the horizontal block 210 of the anchor head supporting block 200 is a rectangular cross-section block in the first embodiment, while the horizontal block 210 in the third embodiment is a curved horizontal block There are differences in points.

구체적으로 살펴보면, 도 2c와 같이 상기 실시예 3에 의한 긴장재 중심축조정용 정착장치(100)도 역시 거더에 매립 설치되는 정착구(110)와 앵커헤드(120)를 포함한다.Specifically, as shown in FIG. 2C, the fixing device 100 for a center member for adjusting a tenter material according to the third embodiment also includes a fixing hole 110 and an anchor head 120, which are embedded in a girder.

이러한 정착구(110)도 역시 단부는 주름관 형태로서 거더 내부에 설치되는 긴장재용 쉬스가 연결되도록 하고, 상기 주름관에 주물 등으로 제작된 정착헤드(111), 상기 정착헤드(111)를 감싸 거더에 매립 설치되는 보강철근(112), 정착헤드(111)를 거더 표면에 위치하도록 하면서 국부응력을 분산시키는 정착판(113)을 포함한다.The fixation port 110 also has a corrugated pipe shape at the end thereof to connect the sheath for the tension member installed inside the girder. The fixation head 111, which is made of cast iron or the like, and the fixing head 111 are wrapped around the corrugated pipe, And a fusing plate 113 for dispersing local stress while positioning the fixing head 111 on the surface of the girder.

이때 상기 정착판(113) 역시 사각판 형태로 거더 일면에 매립 또는 돌출되도록 형성시킬 수 있는데 이러한 정착판(113)에 앵커헤드지지블록(200)을 고정 설치시키는 것도 동일하다.At this time, the fusing plate 113 may also be formed in a rectangular plate shape so as to be embedded or protruded on one side of the girder, and the anchor head supporting block 200 is fixedly installed on the fusing plate 113.

실시예 3에 의한 앵커헤드지지블록(200)은 앵커헤드(120)와 앵커헤드지지블록(200)이 서로 면 접촉 되도록 하는 형태로서 통상 원형판 형태의 앵커헤드 외주면과 면 접촉하는 곡선형 수평블록(240)을 가지도록 형성된 것임을 알 수 있다.The anchor head supporting block 200 according to the third embodiment is a type in which the anchor head 120 and the anchor head supporting block 200 are brought into surface contact with each other and is a curved horizontal block which is in surface contact with the outer peripheral surface of the anchor head, 240, respectively.

즉, 앵커헤드(120)의 외주면 일부는 곡선형 수평블록(240)의 곡면부(C)에 지지되도록 하는 것임을 알 수 있다.That is, it can be seen that a part of the outer circumferential surface of the anchor head 120 is supported by the curved surface portion C of the curved horizontal block 240.

이로서 앵커헤드와 앵커헤드지지블록(200)의 접촉면적이 증대하므로 보다 안정적인 앵커헤드 지지가 가능하게 된다.As a result, the contact area between the anchor head and the anchor head support block 200 is increased, which makes it possible to more stably support the anchor head.

이때, 상기 곡선형 수평블록(240)을 직접 정착판(113)에 고정시키는 경우 역시 곡선형 수평블록(240)과 곡선형 수평블록(240)과 정착판이 접하는 부위에 응력집중이 될 수 있고, 정착판(113)에 앵커헤드지지블록(200)을 고정시키기 위한 체결구(260)를 체결시킬 경우 곡선형 수평블록(240)의 단면손실이 발생할 수 있다.In this case, when the curved horizontal block 240 is directly fixed to the fixing plate 113, stress can be concentrated on the portion where the curved horizontal block 240 and the curved horizontal block 240 contact with the fixing plate, When the fastener 260 for fixing the anchor head supporting block 200 is fastened to the fixing plate 113, a sectional loss of the curved horizontal block 240 may occur.

이에 상기 곡선형 수평블록(240) 보다 큰 단면을 가진 확장수평블록(220)을 곡선형 수평블록(240)과 일체로 형성시키고, 상기 확장수평블록(220)을 정착판(113)에 앵커볼트와 같은 체결구(260)로 고정되도록 하게 된다.An extended horizontal block 220 having a larger cross section than the curved horizontal block 240 is integrally formed with the curved horizontal block 240 and the extended horizontal block 220 is fixed to the fixing plate 113 by an anchor bolt As shown in FIG.

이로서 앵커헤드지지블록(200)은 정착판(113)에 고정되어 있고, 이러한 앵커헤드지지블록(200)에 면 접촉에 의하여 앵커헤드(120)가 세팅되도록 하게 됨을 알 수 있다.As a result, the anchor head supporting block 200 is fixed to the fixing plate 113, and the anchor head 120 is set by surface contact with the anchor head supporting block 200.

결국 상기 앵커헤드(120)의 자중과 프리스트레스에 대한 응력분산을 부담하는 앵커헤드지지블록(200)의 설치로 인해 역시 작업자는 긴장재의 긴장 및 정착에 의한 앵커헤드(120)의 이동을 구속시켜 효율적인 거더에 프리스트레스 도입이 가능하게 된다.As a result, the anchor head supporting block 200, which imposes stress dispersion on the anchor head 120 and the prestress, also restrains the movement of the anchor head 120 due to the tension and fixation of the tension member, It becomes possible to introduce the prestress into the girder.

도 2d는 본 발명에 사용되는 앵커헤드(120)의 사용도로서, 상기 정착구(110)와 앵커헤드(120)의 설치예가 도시되어 있다.FIG. 2D is a view showing the use of the anchor head 120 used in the present invention, and shows an example of the installation of the anchor head 110 and the anchor head 120. FIG.

즉, 거더에 먼저 정착판(113)이 설치되도록 하되, 정착판(113)은 사각 판재 형태로 형성될 수 있으며, 정착헤드(111)와 일체로 형성되도록 함을 알 수 있으며, 보강철근(112)도 형성되어 있음을 알 수 있다.That is, it can be seen that the fixing plate 113 is first installed on the girder, and the fixing plate 113 can be formed in the form of a rectangular plate, and is formed integrally with the fixing head 111. The reinforcing bars 112 ) Is also formed.

이에 긴장재를 준비하고, 상기 긴장재를 긴장재용 쉬스에 삽입시키게 되며, 그 양 단부가 정착판(113)을 통해 인출되도록 배치하게 된다.The tension member is prepared, the tension member is inserted into the sheath for tension member, and the both ends of the tension member are arranged to be pulled out through the fixing plate 113.

이에 상기 정착판(113)으로부터 인출된 긴장재를 내부앵커헤드(121)를 이용하여 정착판(113)에 초기 세팅하게 된다.The tension member drawn from the fusing plate 113 is initially set on the fusing plate 113 by using the inner anchor head 121.

이때 상기 내부앵커헤드(121)는 도 2d와 같이 다수의 긴장재관통공이 형성되며 외주면에 나사산에 형성된 것을 이용하되, 상기 내부앵커헤드(121)는 긴장재가 관통하여 물려지도록 쐐기(웨지)에 의하여 긴장재가 세팅되도록 하게 된다.As shown in FIG. 2d, the inner anchor head 121 has a plurality of through-holes formed therein, and the inner anchor head 121 is formed by threading on the outer periphery of the inner anchor head 121, Is set.

또한 상기 나사산에는 링너트형 앵커헤드(120)가 체결되어 있음을 알 수 있는데, 이러한 링너트형 앵커헤드(120)가 정착판(113)에 앵커헤드지지블록(200)에 의하여 The ring nut type anchor head 120 is fastened to the fixing plate 113 by an anchor head supporting block 200. The ring nut type anchor head 120 is fastened to the fixing plate 113

지지되도록 함을 알 수 있다.As shown in FIG.

즉, 긴장재의 단부에 미도시된 유압잭 등을 이용하여 긴장시키게 되면, 긴장재가 긴장되어 좌측으로 위치가 이동(화살표 표시)되게 되는데, 이에 따라 링너트형 앵커헤드(120)도 내부앵커헤드(121)와 함께 좌측으로 이동하게 된다.In other words, when the tension member is tensed using a hydraulic jack (not shown) at the end of the tension member, the tension member is tensed and the position is shifted to the left (indicated by an arrow mark). Accordingly, the ring nut type anchor head 120 is also moved to the inner anchor head 121 To the left.

이에 상기 위치 이동된 링너트형 앵커헤드(120)를 회전시켜 다시 내부앵커헤드(121)가 정착판(113)에 지지 안착되도록 하여 긴장재에 도입된 긴장력이 유지될 수 있도록 하게 된다.Then, the position-shifted ring nut type anchor head 120 is rotated so that the inner anchor head 121 is supported on the fusing plate 113 so that the tension force introduced into the tension member can be maintained.

이로서 상기 링너트형 앵커헤드(120)의 회전량을 조정하여 도입된 긴장력을 미세 조정할 수 있도록 하는 효과를 가지게 된다.Thereby, the amount of rotation of the ring nut type anchor head 120 can be adjusted to fine tune the introduced tension force.

[ 본 발명의 긴장재 중심축조정용 정착장치(100)를 이용한 거더교 시공방법 ][Method of constructing a girder bridge using the fixing device 100 for a center member of a tension member of the present invention]

도 3a 및 도 3b는 본 발명에 의한 중심축조정용 정착장치를 이용한 거더 및 이를 이용한 단경간 거더교의 시공순서도,FIG. 3A and FIG. 3B are views showing a construction sequence of a girder using a fixing device for a central axis adjustment according to the present invention and a single span girder bridge using the same.

도 4a 및 도 4b는 본 발명에 의한 중심축조정용 정착장치를 이용한 거더 연결도 및 이를 이용한 다경간 거더교의 시공순서도이다.FIGS. 4A and 4B are views showing a girder connection using a fixing apparatus for a central axis adjustment according to the present invention and a construction sequence of a multi-span girder bridge using the same.

[단경간용 거더 및 이를 이용한 거더교 시공방법][Single span girder and girder bridge construction method using it]

먼저, 도 3a와 같이 단경간용 PSC 거더의 예를 살펴본다.First, an example of a short-span PSC girder as shown in FIG. 3A will be described.

상기 단경간용 PSC 거더(A)는 통상의 I형 단면의 프리스트레스 철근 콘크리트로써 내부에 긴장재가 쉬스에 의하여 배치되도록 제작하되, 상기 긴장재(300)는 크게 제1 긴장재(310), 제2 긴장재(320) 및 제3 긴장재(330)로 배치되도록 하게 된다.The PSC girder (A) for short span is manufactured from a prestressed reinforced concrete having an I-shaped cross section, and a prestressing material is disposed inside the prestressing prestressing sheath. The prestressing material 300 is mainly composed of a first prestressing material 310, a second prestressing material 320 and the third tensional element 330, respectively.

이때, 상기 제1 긴장재(310)는 철근 콘크리트 거더로써, 보다 낮은 형고에 의한 PSC 거더를 제작하기 위하여 즉, PSC 거더의 자중 및 슬래브의 자중 전부 또는 일부에 의한 휨 강성을 충분히 확보하기 위하여 설치되는 긴장재라 할 수 있고,At this time, the first tensional material 310 is installed as a reinforced concrete girder in order to sufficiently secure the flexural rigidity of the self weight of the PSC girder and all or a part of the self weight of the slab It can be said to be tense,

상기 제2 긴장재(320)는 PSC 거더를 교대에 거치 후 슬래브가 형성된 이후에 작용하는 활하중(공용하중 등)에 저항하기 위하여 설치되는 긴장재라 할 수 있고,The second tensional material 320 may be a tension material installed to resist a live load (common load, etc.) acting after the slab is formed after the PSC girder is alternately placed,

상기 제3 긴장재(330)는 교량 시공 완성 후, PSC 거더 및 연속 지점부에 형성된 연결 콘크리트 등 교량을 유지, 보강하기 위하여 추가로 설치되는 긴장재라 할 수 있다.The third prestressing material 330 may be a tensile material that is additionally installed to maintain and reinforce the bridge such as the PSC girder and the connecting concrete formed at the continuous point portion after completion of the bridge construction.

먼저, 상기 제1 긴장재(310)는 도 3b와 같이 긴장재 중심축조정용 정착장치(100)를 PSC 거더의 양 단부면에 배치되도록 한 상태에서 상기 정착장치 사이에 예컨대 포물선 형태로 배치되도록 한 후, 긴장 및 정착된다.3B, the first tensions 310 are arranged in a parabolic shape between the fixing devices in a state where they are disposed on both end surfaces of the PSC girder, Tense and settled.

물론 이러한 제1 긴장재(310)는 거더 내부에 배치된 긴장재용 쉬스에 의하여 배치되도록 하며 PS 강연선이 이용될 수 있다.Of course, such a first tensional element 310 is arranged by the sheath for tension material arranged inside the girder, and a PS strand can be used.

이때, 상기 제1 긴장재(310)는 PSC 거더의 자중과, 추후 상부에 형성되는 슬래브의 자중 전부 또는 일부에 충분히 저항할 수 있을 정도로 그 설치량이 조정되도록 정해지게 된다.At this time, the first tensional element 310 is determined such that its installation amount is adjusted so as to sufficiently resist the self weight of the PSC girder and all or a part of the self weight of the slab formed at the upper portion.

다음으로 상기 제2 긴장재(320)는 도 3b와 같이 거더 상면에 노출된 긴장재 중심축조정용 정착장치(100) 사이에 배치되도록 한 후, 긴장 및 정착된다.Next, the second tensions 320 are disposed between the fixing devices 100 for torsion centering structures exposed on the upper surface of the girder as shown in FIG. 3B, and then they are tensioned and fixed.

이러한 상기 제2 긴장재(320)는 비록 제1 긴장재(310)의 설치량 보다는 작은 설치량을 가지게 되지만, 최대한 낮은 형고로 제작된 PSC 거더의 단부면에서 긴장 및 정착시킬 경우 긴장재의 긴장 및 정착공간을 충분히 확보할 수 없게 된다.Although the second tensional element 320 has a smaller installation amount than the first tensional element 310, if the torsion and settlement of the end surface of the PSC girder manufactured to have a low profile are minimized, It can not be ensured.

나아가 PSC 거더를 교대, 교각에 거치한 후 긴장 및 정착되기 때문에 고소작업에 의한 안전 문제가 있고, PSC 거더 단부 주위에서 긴장 및 정착작업이 이루어질 경우 시공성이 떨어질 수밖에 없다는 문제점이 있다.Furthermore, since the PSC girder is alternately tilted and fixed after being mounted on the pier, there is a safety problem due to the complicated work and there is a problem that the workability is inevitably lowered when the tension and fixing work are performed around the end of the PSC girder.

이에 상기 제2 긴장재(320)의 긴장 및 정착작업은 거더 상면(슬래브 시공 이후에는 슬래브 상면)에서 이루어질 수 있도록 제2 긴장재(320)의 단부를 PSC 거더의 상부면으로부터 인출되도록 하는데, 이를 위하여 도 3a 및 도 3b와 같이 PSC 거더의 양 단부로부터 중앙부 쪽으로 이격된 위치에 거더 상면을 일부만 절취하여 형성시킨 거더상면긴장부(B)를 형성시키게 된다.The tensioning and fixing operation of the second tensional material 320 is carried out from the upper surface of the PSC girder so that the second tensional material 320 can be formed on the upper surface of the girder (the slab upper surface after the slab is installed) 3a and 3b, a girder upper surface tension portion B is formed by cutting a part of the upper surface of the girder at a position spaced apart from both ends of the PSC girder toward the center.

이에 제2 긴장재(320)는 PSC 거더의 양 단부면으로부터 중앙부쪽으로 이격된 위치의 상기 거더상면긴장부(B)에서 긴장 및 정착작업이 이루어지도록 하게 된다.Thus, the second tensional element 320 is tensioned and fixed at the upper surface tension portion B of the girder at a position spaced from the both end surfaces of the PSC girder toward the central portion.

이러한 거더상면긴장부(B)의 크기는 정착장치를 수용할 수 있을 정도로 최소화 시켜 PSC 거더의 단면 손실을 최소화 할 수 있도록 한다.The size of the upper surface tension portion B of the girder is minimized to such an extent that the fixing device can be accommodated, thereby minimizing the cross-sectional loss of the PSC girder.

상기 제2 긴장재(320)도 PSC 거더의 내부에서 긴장재용 쉬스에 의하여 배치되도록 하는데, 이러한 제2 긴장재(320)는 PSC 거더의 내부를 통상 포물선 형태로 배치하게 되며, 시공 순서 상 거더 설치 이후 슬래브가 완성된 이후에 긴장, 정착시키게 된다.The second tensional material 320 is also disposed inside the PSC girder by sheath for the tensional material. The second tensional material 320 is disposed inside the PSC girder in the form of a parabola, After the completion, tension is settled.

상기 제3 긴장재(330)는 PSC 거더를 교대에 거치한 후, 슬래브를 시공한 후에, 시간이 경과함에 따라 도입된 긴장력(프리스트레스)이 손실되는 문제점을 해결하기 위하여 설치된다.The third prestressing member 330 is installed to solve the problem that the introduced prestress is lost as the time passes after the PSC girder is alternately mounted and the slab is installed.

이에 먼저 PSC 거더에 제3 긴장재(330)가 설치될 긴장재용 쉬스를 미리 배치만 하고, 상기 제3 긴장재(330)는 추후 필요 시 긴장재용 쉬스에 삽입되어 설치되도록 하게 된다.First, the PSC girder is provided with a sheath for a tension material to be installed in advance, and the third prong material 330 is inserted into a sheath for tension material at a later stage if necessary.

이로서 상기 제3 긴장재(330)가 설치될 쉬스는 추후 교량이 완성된 이후에 손쉽게 접근할 수 있도록 하는 위치에 설치되어야 한다.Thus, the sheath to which the third tensional material 330 is to be installed must be installed at a position where the sheath can be easily accessed after completion of the bridge.

이에 긴장재용 쉬스는 도 3a 및 도 3b와 같이 거더의 양 단부로부터 거더 중앙부 쪽으로 이격된 위치의 거더 하부플랜지와 복부 사이에 형성시킨 제 3긴장재용 정착부(D)에 설치된다.As shown in FIGS. 3A and 3B, the sheath for tensioning is installed in the fixing portion D for the third tension member formed between the girder lower flange and the abdomen at a position spaced from both ends of the girder toward the center of the girder.

이에 교량 완성 후 사용 중에, 상기 긴장재용 쉬스에 제3 긴장재(330)를 삽입하여 삽입된 제3 긴장재(330)를 앞서 살펴본 긴장재 중심축조정용 정착장치(100)를 이용하여 긴장 및 정착함으로써 거더에 압축 프리스트레스가 추가 도입될 수 있도록 하게 된다.During the use of the bridges, the third tensions (330) inserted by inserting the third tensions (330) into the sheath for the ties are tensed and fixed by using the fixing device (100) So that a compression prestress can be additionally introduced.

이때 상기 제1긴장재, 제2긴장재 및 제3 긴장재에 사용되는 긴장재 중심축조정용 정착장치(100) 도 2a 내지 도 2c에 의한 긴장재 중심축조정용 정착장치(100)중 어느 하나를 이용하면 된다.In this case, any one of the fusing device 100 for a torsion centering device used for the first torsion material, the second torsion material and the third torsion material may be used.

도 3b의 경우에는 도 3a에 의한 단경간용 거더를 이용한 거더교 시공방법을 도시한 것이다.3B illustrates a girder bridge construction method using the single span girder according to FIG. 3A.

즉, 긴장재 중심축조정용 정착장치(100)가 형성된 거더(500)를 이용하여 단경간 거더교를 시공하는 경우로서, 상기 거더는 PSC 거더이다.That is, in the case where a girder 500 having a fixing device 100 for a tie member center-tie adjustment is formed, a single span girder bridge is constructed, and the girder is a PSC girder.

이때 상기 거더(500)는 내부를 관통하여 설치된 쉬스에 삽입되어 배치되는 단부긴장재인 제1 긴장재(310), 상면긴장재인 제2 긴장재(320), 측면긴장재인 제3 긴장재(330)를 포함하도록 제작되어 상기 긴장재들(310,320,330)과 앞서 살펴본 긴장재 중심축조정용 정착장치(100)를 이용하여 단경간 거더교 시공이 이루어지게 된다.The girder 500 includes a first torsion material 310, an upper torsion material second torsion material 320, and a third torsion material 330, which are inserted into the sheath through which the girder 500 is inserted, Span girder bridges are constructed by using the tension members 310, 320, and 330 and the fixing device 100 for a tie center adjustment.

상기 거더(500)에는 제 1긴장재(310)가 설치되도록 하되, 상기 제 1긴장재는 거더 제작 시 거더 양 단부면에서 긴장재 중심축조정용 정착장치(100)를 이용하여 긴장 후 정착되도록 함으로써 거더에 압축 프리스트레스가 초기 도입되도록 하게 된다.The first tension member 310 may be installed on the girder 500. The first tension member may be fixed to the girder at both ends of the girder by using the fixing device 100 for adjusting the center member of the tension member, So that the prestress is introduced at an early stage.

이때 제 1긴장재(310)용 긴장재 중심축조정용 정착장치(100)는 앞서 살펴본 도 4a, 도 4b 또는 도 4c에 의한 앵커헤드지지블록(200)이 정착판(113)에 형성된 것을 이용하면 된다.The anchor head supporting block 200 according to the above-described FIG. 4A, FIG. 4B or FIG. 4C may be formed in the fixing plate 113 for the first tension member 310 for the tension member.

이때 제 3긴장재용 정착부(D)에 긴장재 중심축조정용 정착장치(100)가 설치되도록 하되, 거더 내부에 제 3긴장재용 쉬스를 상기 긴장재 중심축조정용 정착장치(100) 사이에 연결되도록 하고, 상기 정착판(113)을 먼저 제 3긴장재용 정착부에 매입 설치되도록 거더(500)를 제작하게 된다.At this time, the fixing device 100 for the center member for the adjustment of tension is installed in the fixing part D for the third tension member, and the sheath for the third member for tensioning is connected between the fixing device 100 for the center member for adjusting the tension member, The girder 500 is manufactured so that the fusing plate 113 is first embedded in the fusing unit for the third tension member.

역시 상기 긴장재 중심축조정용 정착장치(100)는 앞서 살펴본 도 4a, 도 4b 또는 도 4c에 의한 앵커헤드지지블록(200)이 정착판(113)에 형성된 것을 이용하면 된다.In the fixing device 100 for a tentative core adjustment, the anchor head supporting block 200 according to the above-described FIG. 4A, FIG. 4B or FIG. 4C may be formed on the fixing plate 113.

다음으로는 상기 거더(500)를 교대(600) 사이에 설치한 후, 상기 거더 상부에 슬래브(700)를 시공하게 된다.Next, after the girders 500 are installed between the shifts 600, the slabs 700 are installed on the girders.

이때, 상기 거더(500)는 제작 시 양 단부에서 중앙쪽으로 이격되어 위치한 상부면을 절취하여 일정깊이를 구비한 거더상면긴장부(B)가 형성되도록 하되, 상기 거더 상면긴장부(B)로 연장되는 제 2긴장재용 쉬스가 설치되도록 하게 된다.At this time, the upper part of the girder 500, which is spaced from the both ends of the upper part of the girder 500 at the time of fabrication, is cut to form a girder upper surface tension part B having a predetermined depth. The sheath for the second tension material is installed.

상기 슬래브 시공 이후에, 상기 제 2긴장재용 쉬스에 제 2긴장재(320)를 삽입하여 거더 상면 긴장부에서 긴장재 중심축조정용 정착장치(100)에 의하여 상기 제 2긴장재가 긴장 및 정착되도록 하여 거더(500) 및 슬래브(700)에 압축 프리스트레스가 함께 도입되도록 하게 된다.After the slab is installed, the second tension member 320 is inserted into the sheath for the second tension member, so that the second tension member is tensioned and fixed by the fixing device 100 for adjusting the center member of the tension member at the upper surface tension portion of the girder, 500 and the slab 700 together with a compressive prestress.

이때 역시 제 2긴장재(320)용 긴장재 중심축조정용 정착장치(100)는 앞서 살펴본 도 4a, 도 4b 또는 도 4c에 의한 앵커헤드지지블록(200)이 정착판(113)에 형성된 것을 이용하면 된다.In this case, the fixing device 100 for the tension member centering structure for the second tension member 320 may be formed by using the anchor head supporting block 200 according to the above-described FIG. 4A, FIG. 4B or FIG. 4C formed in the fixing plate 113 .

이로서 교량완성 이후에, 상기 제 3긴장재용 정착부(D)에 제 3긴장재(330)를 긴장재 중심축조정용 정착장치(100)를 관통하여 앵커헤드(120)를 역시 관통하도록 한 후, 제 3긴장재(330)를 긴장 후, 상기 앵커헤드(120)에 쐐기를 이용하여 정착시키게 된다.After the completion of the bridge, the third tension member 330 is passed through the fixing device 100 for the center member for adjusting the tensions and the anchor head 120 is passed through the fixing member D for the third tension member. After straining the tension member 330, the tension member 330 is fixed to the anchor head 120 by using a wedge.

이때 앵커헤드(120)는 내부앵커헤드(121)가 구비된 링너트형 앵커헤드를 이용할 수 있을 것이다.At this time, the anchor head 120 may use a ring-nut type anchor head having an inner anchor head 121.

[다경간용 거더 및 이를 이용한 거더교 시공방법][Multi span girder and girder bridge construction method using it]

먼저, 도 4a와 같이 다경간용 PSC 거더의 연결구성을 살펴본다.First, a connection structure of a PSC girder for multiple spans will be described with reference to FIG. 4A.

상기 다경간용 PSC 거더의 경우에도 기본적으로 단경간용 PSC 거더와 크게 다를 바 없다.In the case of the above-described multi-span PSC girder, it is basically not much different from that of the single span PSC girder.

이에 다경간용 PSC 거더도 통상의 I형 단면의 프리스트레스 철근 콘크리트로써 내부에 긴장재가 쉬스에 의하여 배치되도록 제작하되, 상기 긴장재는 크게 제1 긴장재(310), 제2 긴장재(320) 및 제3 긴장재(330)로 배치되도록 하게 된다.Also, the PSC girder for span type is a prestressed reinforced concrete having an I-shaped cross section, and is constructed such that a sheath is used to arrange the sheath in the sheath. The sheath is mainly composed of the first prestressing material 310, the second prestressing material 320, (330).

역시 상기 제1 긴장재(310)도 PSC 거더의 자중 및 슬래브의 자중 전부 또는 일부에 의한 휨 강성을 충분히 확보하기 위하여 각 거더에 설치되며,The first tensional elements 310 are also installed on the respective girders in order to sufficiently secure the flexural rigidity of the self weight of the PSC girder and all or part of the self weight of the slab,

상기 제2 긴장재(320)도 PSC 거더를 교대에 거치 후 슬래브가 형성된 이후에 작용하는 활하중(공용하중 등)에 저항하기 위하여 설치된다. The second tensions 320 are also installed to resist live loads (common loads, etc.) acting after the slab is formed after the PSC girders are alternately mounted.

이러한 다경간용 PSC 거더와 단경간용 PSC 거더(A)와 차이는 이러한 제2 긴장재가 각 거더를 경유하여 연속지점부에 연속하여 설치되도록 한다는 점이다.The difference between this multi-span PSC girder and the single span PSC girder (A) is that these second tensions are installed continuously to the continuous focal points via each girder.

이는 거더가 연속지점부를 기준으로 양 측으로 서로 연결되도록 설치하는 것이 다경간 연속교량에 있어 요구되기 때문이다.This is because it is necessary to install the girder so that the girders are connected to each other with respect to the continuous point portion.

나아가 상기 제3 긴장재(330)도 교량 시공 완성 후, PSC 거더 및 연속 지점부에 형성된 연결 콘크리트 등 교량을 유지, 보강하기 위하여 추가로 설치되며, 역시 단경간용 PSC 거더(A)와 차이는 이러한 제3 긴장재가 각 거더를 경유하여 연속지점부에 연속하여 설치하게 된다.Further, the third tensional element 330 is further provided to maintain and reinforce the bridge such as the PSC girder and the connecting concrete formed at the continuous point portion after completion of the bridge construction, and the difference from the PSC girder (A) The third tensional material is continuously installed on the continuous focal point via each girder.

이에 상기 제2 긴장재와 제 3긴장재는 연속지점부를 모두 연속하여 경유하도록 하게 되며, 제1 긴장재만이 각 거더의 양 단부면에 긴장 후 정착되도록 하는 것임을 알 수 있다.The second tensional material and the third tensional material are continuously passed through the continuous focal point portion, and only the first tensional material is fixed after the tension on both end surfaces of each girder.

구체적으로, 상기 제1 긴장재(310)는 긴장재 중심축조정용 정착장치(100)를 PSC 거더의 양 단부면에 배치되도록 한 상태에서 상기 정착장치 사이에 예컨대 포물선 형태로 배치되도록 한 후, 긴장 및 정착되며, 거더 내부에 배치된 쉬스(미도시)에 의하여 배치되도록 하게 된다.Specifically, the first tension member 310 is disposed in the form of, for example, a parabolic line between the fixing devices in a state where the fixing device 100 for tension member center-tune adjustment is disposed on both end surfaces of the PSC girder, (Not shown) arranged inside the girder.

상기 제2 긴장재(320)도 긴장재 중심축조정용 정착장치(100)를 사용하여 정착장치 사이에 배치되도록 한 후, 긴장 및 정착되도록 하되, 역시 상기 제2 긴장재(320)의 긴장 및 정착작업이 거더 상면(슬래브 시공 이후에는 슬래브 상면)에서 이루어질 수 있도록 거더 상면을 절취하여 형성시킨 거더 상면 긴장부(B)를 형성시키게 된다.The second tension member 320 is also tensioned and fixed after being disposed between the fixing apparatuses by using the fixing apparatus 100 for tension member central axis adjustment. And the girder upper surface tension portion B formed by cutting the upper surface of the girder so as to be formed on the upper surface (the upper surface of the slab after the slab construction).

이러한 제2 긴장재(320)도 시공 순서 상 거더 설치 이후 슬래브가 완성된 이후에 긴장, 정착시키게 된다.Such a second tensional material 320 is also tensioned and fixed after the slab is completed after the installation of the girder in the order of construction.

또한, 상기 제3 긴장재(330)도 PSC 거더에 제3 긴장재(330)가 설치될 긴장재용 쉬스를 미리 배치만 하고, 상기 제3 긴장재(330)는 추후 필요 시 상기 긴장재용 쉬스에 삽입되어 설치되도록 하고, 상기 긴장재용 쉬스는 거더의 양 단부로부터 거더 중앙부 쪽으로 이격된 위치의 거더 하부플랜지와 복부 사이에 형성시킨 제 3긴장재용 정착부(D)에 설치하게 된다.Also, the third tensional element 330 may be disposed in the PSC girder in advance, and the third tensional element 330 may be inserted into the sheath for the tensional element 330, if necessary, And the sheath for tensioning is installed in the fixing part D for the third tension member formed between the girder lower flange and the abdomen at a position spaced from both ends of the girder toward the center of the girder.

도 4b와 같이, 교각(800)이 시공되는 위치는 휨 부모멘트가 발생되는 연속 지점부라 할 수 있는데, 이러한 연속 지점부에서 인접하게 설치된 다경간용 PSC 거더가 서로 구조적으로 연결되도록 하게 된다.As shown in FIG. 4B, the position where the bridge pillar 800 is installed can be referred to as a continuous point portion where a bending moment is generated. In such a continuous point portion, the adjacent multi-span PSC girders are structurally connected to each other.

이는 특히 제2 긴장재(320)를 연속시키는 방식으로 이루어지게 되는데, 상기 연속 지점부는 경제적인 이유에 의하여 종래 거더 단부의 인접거리가 30cm 내외였다.This is accomplished in particular by the way of continuing the second tensions 320, where the adjacent distance of the end of the conventional girders is about 30 cm for economical reasons.

이에 제2 긴장재(320)를 서로 연결시켜줄 작업공간이 협소하여 작업성이 매우 떨어질 수밖에 없었으며, 서로 인접한 거더의 단부 상면의 높이가 서로 일치하지 않아 종방향 선형곡률을 일치시기가 용이하지 않았다.Accordingly, the working space for connecting the second tensions 320 to each other is narrow and the workability is very poor. Also, since the height of the tops of the end portions of the adjacent girders do not coincide with each other, it is not easy to match the longitudinal linear curvatures.

또한 곡선교에 있어서는 제2 긴장재가 서로 연속지점부에서 곡률반경을 가지고 배치되도록 하는데 협소한 공간에서 제2 긴장재를 곡선 배치하는 것은 매우 힘든 일이 된다.Further, in the curved bridge, it is very difficult to arrange the second tensions in a narrow space so that the second tensions are arranged with a radius of curvature at successive fulcrums.

이에 도 4b와 같이 본 발명의 다경간용 거더의 경우에는 교대와 같은 단부 지점부에서는 거더의 일측 단부 상부면에 일정깊이를 형성시킨 거더 상면 긴장부(B)가 형성되도록 하고, 교각과 같은 연속 지점부에 위치하게 될 타측 단부는 상단을 절취하여 거더 지점부 상단공간부(F)가 형성되도록 하게 된다.As shown in FIG. 4B, in the case of the multi-span girder according to the present invention, a girder upper surface tension portion B having a certain depth is formed on the upper surface of one end portion of the girder at an end portion such as an alternating portion, And the other end portion to be positioned at the fulcrum portion is cut off to form the space portion F at the upper end of the girder fulcrum portion.

이에 연속 지점부에서 서로 인접한 다경간용 PSC 거더는 상기 거더 지점부 상단공간부(F)에 의하여 확장된 지점부 연결공간(E)이 형성하게 됨을 알 수 있다.Thus, it can be seen that the multi-span PSC girder adjacent to each other at the consecutive point portion forms a focal point connection space E extended by the upper end space portion F of the girder point portion.

이에 다경간용 PSC 거더의 경우, 특히 제2 긴장재는 단부 지점부에 형성된 거더 상면 긴장부(B)와 연속지점부에 형성된 거더 지점부 상단공간부(F)에 제2 긴장재용 쉬스(310)의 양 단부가 연장되도록 하게 되며,In the case of the multi-span PSC girder, in particular, the second tensional element is formed by a girder upper surface tension portion B formed at the end portion portion and a girder tip portion upper space portion F formed at the continuous point portion, So that both end portions of the first and second protrusions are extended,

일측 거더로부터 연속지점부를 거쳐 타측 거더에 제2 긴장재가 연속으로 배치되도록 하게 되며,The second tension members are continuously arranged from the one side girder to the other side girder via the continuous point portion,

긴장재용 쉬스도 일측 거더로부터 연속지점부를 거처 타측 거더에 제3 긴장재가 연속으로 배치되도록 하게 된다.The third tension member is continuously disposed on the other girder through the continuous fulcrum portion from one side girder of the sheath for tensioning material.

이러한 연속 지점부를 경유하는 제 2긴장재 긴장재용 쉬스와 제3 긴장재 긴장재용 쉬스는 연속 지점부 연결관(900)에 의하여 서로 연결되도록 하게 된다.The sheath for the second tensional tension member and the sheath for the third tensional tension member via the continuous focal point portion are connected to each other by the continuous focal point connection tube 900.

나아가 도 4a와 같이 거더 지점부 상단공간부(F)에 연장되는 제2 긴장재용 쉬스의 노출 된 단부는 지름이 확장된 단면확장부(G)로 형성되도록 하여 상기 단면확장부에 연속 지점부 연결관의 단부가 삽입되어 연결되도록 하여 연속 지점부에서 제2 긴장재의 곡선배치가 용이하도록 하도록 하게 된다.Further, as shown in FIG. 4A, the exposed end of the sheath for the second tensional material extending in the space portion F at the upper end of the girder portion is formed by the enlarged sectional enlarged portion G, The ends of the tube are inserted and connected so as to facilitate the arrangement of the curves of the second tensions at the successive fulcrums.

다음으로 도 4b의 경우에는 다경간 거더교의 경우를 도시한 것이다. 즉 교대(600) 사이에 교각(800)이 적어도 1개 이상 형성되도록 하여 거더(500)를 연속지점부에서 2개의 교량받침으로 서로 연속화 시키게 된다.4B shows a case of a multi-span girder bridge. That is, at least one bridge 800 is formed between the alternations 600, so that the girders 500 are successively connected to each other by the two bridge supports at the continuous focal point.

이때, 긴장재 중심축조정용 정착장치(100)가 형성된 거더(500)를 이용하여 다경간 거더교를 시공하는 경우로서, 상기 거더는 역시 PSC 거더이다.At this time, when a multi-span girder bridge is constructed by using the girder 500 formed with the fixing device 100 for a center member for adjusting a tie, the girder is also a PSC girder.

이때 상기 거더(500)는 내부를 관통하여 설치된 쉬스에 삽입되어 배치되는 단부긴장재인 제1 긴장재(310), 상면긴장재인 제2 긴장재(320), 측면긴장재인 제3 긴장재(330)를 포함하는 긴장재(300) 및 긴장재 중심축조정용 정착장치(100)를 이용하여 교대와 같은 단부 지점부와 교각과 같은 연속지점부에 상기 거더(500)를 설치하여 교량을 완성하는 다경간 교량시공이 이루어지게 된다.The girder 500 includes a first tensional element 310, an upper tensional element, a second tensional element 320, and a third tensional element 330, which are end tensions inserted into the sheath installed through the inside of the girder 500 Span bridge construction in which the girder 500 is installed at a continuous point portion such as an alternate long end point portion and a pier bridge by using the tension member 300 and the fixing device 100 for adjusting the center member of the tension member, do.

먼저, 상기 거더(500)의 일측 단부로부터 거더 중앙부 쪽으로 이격된 위치의 거더 하부플랜지 상면과 복부 하부의 측면에 접하도록 형성시킨 제 3긴장재용 정착부에 긴장재 중심축조정용 정착장치(100)가 설치되도록 하되, First, a fixing device 100 for a tension member center-tune adjustment is installed in a fixing part for a third tension member which is formed so as to be in contact with the upper surface of the lower flange of the girder and the side surface of the lower part of the abdomen at a position spaced from one end of the girder 500 toward the center of the girder. However,

거더 내부에 제 3긴장재용 쉬스를 상기 긴장재 중심축조정용 정착장치(100) 사이에 연결되도록 하고, 상기 정착판(113)을 먼저 제 3긴장재용 정착부(D)에 매입 설치되도록 하게 된다. The sheath for the third tension material is connected between the fixing device 100 for the center member for adjusting the tension member and the fixing plate 113 is first embedded in the fixing part D for the third tension member.

나아가 상기 거더(500)의 일측 단부에서 중앙쪽으로 이격되어 위치한 상부면을 절취하여 일정깊이를 구비한 거더 상면 긴장부(B)가 형성되도록 하며, 연속지점부에 위치하게 될 타측 단부는 단부에서 상단을 절취하여 거더 지점부 상단공간부(B)가 형성되도록 하여, 상기 거더 상면 긴장부와 거더 지점부 상단공간부(B)에 연통되도록 제 2긴장재용 쉬스가 설치되도록 거더를 제작하게 된다.Further, the girder upper surface tension portion B having a predetermined depth is formed by cutting the upper surface spaced apart from the one side end portion of the girder 500, and the other end portion to be positioned at the continuous point portion is cut from the upper The girder upper end space portion B is formed so that the sheath for the second tension material is provided so as to communicate with the girder upper surface tension portion and the girder end portion upper end space portion B.

다음으로는 상기 제작된 거더(500)를 상기 단부 지점부와 연속지점부에 걸쳐지도록 설치하여 연속지점부에서 상기 거더 지점부 상단공간부가 서로 마주보도록 하여 연속지점부에 확장된 지점부 연결공간(E)이 형성되도록 하게 된다.Next, the manufactured girder 500 is installed so as to extend over the end portion and the continuous portion, so that the girder portion upper end space portion is opposed to each other at the continuous point portion, E) are formed.

다음으로는 상기 연속지점부에서 마주보는 제 2긴장재용 쉬스를 상기 확장된 지점부 연결공간을 활용하여 교량의 종방향 선형곡률과 일치되게 하고 수직 편심을 최대화 할 수 있도록 관 부재와 같은 연속지점부연결관(900)으로 연결한 후, 거더(500) 상부에 슬래브(700)를 시공하게 된다.Next, the sheath for the second tension member facing the continuous point portion is made to coincide with the longitudinal linear curvature of the bridge by utilizing the extended fulcrum connection space, and a continuous fulcrum portion such as a pipe member After connecting to the connecting pipe 900, the slab 700 is installed on the girder 500.

다음으로는 교량 완성 후, 제 3긴장재가 연속지점부를 경유하여 제 3긴장재용 정착부에 상기 긴장재 중심축조정용 정착장치(100)를 이용하여 긴장 및 정착시키게 된다. 즉, 상기 제 3긴장재용 정착부에 제 3긴장재(330)를 긴장재 중심축조정용 정착장치(100)를 관통하여 앵커헤드(120)를 역시 관통하도록 한 후, 제 3긴장재(330)를 긴장 후, 상기 앵커헤드(120)에 쐐기를 이용하여 정착시키게 된다.Next, after the completion of the bridge, the third tensional material is tensioned and fixed to the third tensional material fixing portion via the continuous focal point portion by using the fixing device 100 for adjusting the tensional material central axis. That is, after the third tension member 330 is passed through the anchor head 120 through the fixing device 100 for the center member for adjusting the tension member, the third tension member 330 is tensioned , And fixed to the anchor head 120 using a wedge.

이때 역시 앞서 살펴본 도 4a, 도 4b 및 도 4c에 의한 앵커헤드지지블록(200)이 정착판(113)에 형성된 것을 이용하게 된다.At this time, the anchor head supporting block 200 according to the above-described FIGS. 4A, 4B and 4C is formed on the fixing plate 113. FIG.

이때 상기 거더 연속지점부 상단공간부에 연장되는 제 2긴장재용 정착부의 노출된 단부는 지름이 확장된 단면확장부(G)로 형성되도록 하여 상기 단면확장부에 연속지점부 연결관의 단부가 삽입되어 연결되도록 하여 연속지점부에서 제 2긴장재의 곡선배치가 용이하도록 하고,At this time, the exposed end of the second tension member extending in the upper space portion of the girder continuous fulcrum portion is formed of the enlarged cross-sectional enlarged portion G so that the end portion of the continuous fulcrum connecting tube is inserted So as to facilitate the arrangement of the curves of the second tensions at the continuous fulcrum portion,

상기 제 2긴장재용 쉬스에는 제 2긴장재(320)가 거더의 일측 거더 상면 긴장부로부터 거더 지점부 상단공간부를 거쳐 인접한 거더의 거더 상면 긴장부를 경유하도록 하고, 슬래브를 시공한 이후에 상기 거더 상면 긴장부에서 정착장치에 의하여 긴장 후 정착되도록 함으로써 거더 전체 및 슬래브에 압축프리스트레스가 도입되도록 하고,The second tension member 320 is caused to pass through the girder upper surface tension portion of one side of the girder and the upper side girder upper surface tension portion of the adjacent girder through the girder upper portion space portion, So that the compression prestress is introduced into the entire girder and the slab,

상기 거더에는 제 2긴장재(320)와 더불어 제 1긴장재(310)가 설치되도록 하되, 상기 제 1긴장재는 거더 제작 시 거더 양 단부면에서 긴장재 중심축조정용 정착장치(100)를 이용하여 긴장 후 정착되도록 함으로써 거더에 압축 프리스트레스가 초기 도입되도록 하고,The first tension member 310 may be installed on the girder along with the second tension member 320. The first tension member may be fixed at both ends of the girder during the manufacture of the girder by using a fixing device 100 for adjusting the center member of the tension member, So that the compression prestress is introduced into the girder at an early stage,

상기 연속지점부에서 마주보는 제 2긴장재용 쉬스를 상기 연속지점부연결관(900)으로 연결되도록 함과 더불어 연속지점부에서 마주보는 제 3긴장재용 쉬스도 별도의 연속지점부 연결관으로 연결되도록 한 후, 거더 상부에 슬래브가 형성되도록 하여, 제 3긴장재(330)가 연속지점부를 경유하도록 하게 됨을 알 수 있다.The sheath for the second tension member facing the continuous point portion is connected to the continuous point portion connection pipe 900 and the sheath for the third tension member facing the continuous point portion is also connected to the separate continuous point portion connection pipe And then the slab is formed on the upper portion of the girder so that the third tensional material 330 passes through the continuous focal point portion.

전술한 본 발명의 설명은 예시를 위한 것이며, 본 발명이 속하는 기술분야의 통상의 지식을 가진 자는 본 발명의 기술적 사상이나 필수적인 특징을 변경하지 않고서 다른 구체적인 형태로 쉽게 변형이 가능하다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시예들은 모든 면에서 예시적인 것이며 한정적이 아닌 것으로 이해해야만 한다. 예를 들어, 단일형으로 설명되어 있는 각 구성 요소는 분산되어 실시될 수도 있으며, 마찬가지로 분산된 것으로 설명되어 있는 구성 요소들도 결합된 형태로 실시될 수 있다.It will be understood by those skilled in the art that the foregoing description of the present invention is for illustrative purposes only and that those of ordinary skill in the art can readily understand that various changes and modifications may be made without departing from the spirit or essential characteristics of the present invention. will be. It is therefore to be understood that the above-described embodiments are illustrative in all aspects and not restrictive. For example, each component described as a single entity may be distributed and implemented, and components described as being distributed may also be implemented in a combined form.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is defined by the appended claims rather than the detailed description and all changes or modifications derived from the meaning and scope of the claims and their equivalents are to be construed as being included within the scope of the present invention do.

100: 중심축조정용 정착장치
110: 정착구
111: 정착헤드 112: 보강철근
113: 정착판 120: 앵커헤드
200: 앵커헤드지지블록
210: 수평블록 220: 확장수평블록
230: U형 수평블록 240: 곡선형 수평블록
300: 긴장재
310: 제1 긴장재 320: 제2 긴장재
330: 제3 긴장재
500: 거더 600: 교대
700: 슬래브 800: 교각
900: 연속지점부연결관 S: 곡면부
100: Fixing device for central axis adjustment
110: anchorage
111: Fixing head 112: Rebar
113: Fusing plate 120: Anchor head
200: Anchor head supporting block
210: horizontal block 220: extended horizontal block
230: U-shaped horizontal block 240: Curved horizontal block
300: Tension material
310: first tension member 320: second tension member
330: Third tension member
500: Girder 600: Shift
700: Slab 800: Pier
900: continuous connection part connection tube S: curved part

Claims (15)

긴장재(300) 및 긴장재 중심축조정용 정착장치(100)를 이용한 단경간 교량시공방법에 있어서,
(a) 제 1긴장재(310)를 거더 제작 시 거더 양 단부면에 긴장재 중심축조정용 정착장치(100)를 이용하여 긴장 후 정착되도록 함으로써 거더에 압축 프리스트레스가 초기 도입되도록 하고, 상기 긴장재 중심축조정용 정착장치(100)의 정착판(113)을 거더의 양 단부면에 설치되도록 거더(500)를 제작하는 단계; 및
(b) 상기 거더(500)를 교대(600) 사이에 설치한 후, 상기 거더 상부에 슬래브(700)를 시공하는 단계;를 포함하며,
상기 긴장재 중심축조정용 정착장치(100)는 정착헤드(111)와 일체로 형성되어 긴장재(300)가 설치된 거더(500) 표면에 위치하도록 하면서 국부응력을 분산시키는 정착판(113)을 포함하는 정착구(110); 상기 정착구(110)를 관통하는 긴장재(300)가 긴장재홀을 통해 긴장 후 정착되어 상기 정착판(113)에 지지되는 앵커헤드(120); 및 앵커헤드(120)와 앵커헤드지지블록(200)이 서로 점 접촉 또는 면 접촉되는 수평블록(210) 및 상기 수평블록과 일체로 형성되어 정착판에 고정 설치되는 확장수평블록(220)을 포함하여 구성된 앵커헤드지지블록(200);을 포함하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
A method of constructing a short span bridge using a tension member (300) and a fixing device (100) for a center member of a tension member,
(a) the first prestressing member 310 is fixed to both end surfaces of the girder by using the fixing device 100 for the prismatic center-tune adjustment when the first prestressing member 310 is manufactured, Fabricating the girder 500 so that the fixing plate 113 of the fixing apparatus 100 is installed on both end surfaces of the girder; And
(b) installing the slabs (700) on the girders after the girders (500) are installed between the alternating (600)
The fixing device 100 for a center member for adjusting a center member for a torsion fixture includes a fixation plate 113 integrally formed with a fixation head 111 and having a fixation plate 113 for dispersing a local stress while being positioned on a surface of a girder 500, (110); An anchor head 120 which is fixed to the fixing plate 113 after the tension member 300 penetrating the fixing hole 110 through the tension member hole and is supported by the fixing plate 113; And a horizontal block 210 in which the anchor head 120 and the anchor head supporting block 200 are in point contact or face contact with each other and an extended horizontal block 220 integrally formed with the horizontal block and fixed to the fixing plate And an anchor head support block (200) configured to support the girder bridge structure.
제 1항에 있어서,
상기 (a) 단계에서, 거더(500)는 제작 시 양 단부에서 중앙쪽으로 이격되어 위치한 상부면을 절취하여 일정깊이를 구비한 거더 상면 긴장부(B)가 형성되도록 하되, 상기 거더 상면 긴장부(B)로 연장되는 제 2긴장재용 쉬스가 설치되도록 하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
The method according to claim 1,
In the step (a), the upper surface of the girder 500 spaced from the both ends of the girder 500 at the center is cut so that a girder upper surface tension portion B having a predetermined depth is formed. The girder upper surface tension portion B) of the second tension member is provided on the lower portion of the girder bridge.
제 2항에 있어서,
상기 (b)단계의 슬래브 시공 이후에, 상기 제 2긴장재용 쉬스에 제 2긴장재(320)를 삽입하여 거더 상면 긴장부에서 긴장재 중심축조정용 정착장치(100)에 의하여 상기 제 2긴장재가 긴장 및 정착되도록 하여 거더 및 슬래브에 압축 프리스트레스가 함께 도입되도록 하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
3. The method of claim 2,
After the slab installation in the step (b), the second tensional material 320 is inserted into the sheath for the second tensional material to cause the second tensional material to be tensed and deformed by the fixing device 100 for adjusting the center- And a compression prestress is introduced into the girder and the slab so as to fix the girder and the slab.
제 3항에 있어서,
상기 (b) 단계의 슬래브(700) 시공 이후에, 상기 거더 중앙부 쪽으로 이격된 위치의 거더 하부플랜지 상면과 복부 하부의 측면에 접하도록 형성시킨 제 3긴장재용 정착부(D)에 제 3긴장재(330)를 상기 긴장재 중심축조정용 정착장치(100)를 관통하여 앵커헤드(120)를 관통하도록 한 후, 제 3긴장재(330)를 긴장 후, 상기 앵커헤드(120)에 정착시키는 단계를 포함하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
The method of claim 3,
After the installation of the slab 700 in the step (b), the third tension member (D) for the third tension member formed to contact the upper surface of the lower flange of the girder and the side surface of the lower abdomen at a position spaced toward the center of the girder 330) through the anchor head (120) through the fixing device (100) for the adjustment of the central member for adjusting the tensions and then fixing the third tensions (330) to the anchor head (120) Construction method of girder bridges using a fixing device for center - of - gravity tie fixation.
제 1항에 있어서,
상기 수평블록(210)은 직육면체 블록으로서 앵커헤드의 외주면이 수평블록과 1점 접촉에 의하여 앵케헤드지지블록이 정착판에 지지되도록 하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
The method according to claim 1,
Wherein the horizontal block (210) is a rectangular parallelepiped block, and the anchor head supporting block is supported on the fixing plate by the one-point contact of the outer peripheral surface of the anchor head with the horizontal block.
제 1항에 있어서,
상기 수평블록(210)은 U형 수평블록으로서 앵커헤드의 외주면이 U형 수평블록의 U형 수용부에 삽입되어 3점 접촉에 의하여 앵케헤드지지블록이 정착판에 지지되도록 하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
The method according to claim 1,
The horizontal block 210 is a U-shaped horizontal block, and the outer peripheral surface of the anchor head is inserted into the U-shaped receiving portion of the U-shaped horizontal block so that the anchor head supporting block is supported on the fixing plate by three- A method of girder bridge construction using the apparatus.
제 1항에 있어서,
상기 수평블록(210)은 곡선형 수평블록으로서 앵커헤드의 외주면이 곡선형 수평블록의 곡면부에 면 접촉에 의하여 앵케헤드지지블록이 정착판에 지지되도록 하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
The method according to claim 1,
The horizontal block 210 is a curved horizontal block, and the anchor head is supported on the fixing plate by the surface contact of the outer circumferential surface of the anchor head with the curved surface of the curved horizontal block. In the girder bridge construction Way.
제 1항에 있어서,
상기 앵커헤드(120)는
정착판(113)으로부터 연장된 긴장재를 내부앵커헤드(121)를 이용하여 정착판(113)에 초기 세팅하도록 하되, 상기 내부앵커헤드(121)는 외주면에 나사산에 형성된 것을 이용하고 내부앵커헤드(121)는 긴장재가 관통하여 물려지도록 쐐기(웨지)에 의하여 긴장재가 세팅되도록 하고, 상기 나사산에는 링너트형 앵커헤드(120)가 체결되어 있어 링너트형 앵커헤드(120)를 회전시켜 내부앵커헤드(121)가 정착판(113)에 지지 안착되도록 하여 긴장재에 도입된 긴장력이 유지될 수 있도록 하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
The method according to claim 1,
The anchor head (120)
The tension member extending from the fixing plate 113 is initially set in the fixing plate 113 by using the inner anchor head 121. The inner anchor head 121 is formed by threading the outer anchor head 121, 121 are fixed by a wedge so that the tension member is passed through and a ring nut type anchor head 120 is fastened to the threads to rotate the ring nut type anchor head 120, (121) is supported on the fixing plate (113) so that the tension applied to the tension member can be maintained.
긴장재(300) 및 긴장재 중심축조정용 정착장치(100)를 이용한 다경간 교량시공방법에 있어서,
(a) 제 1긴장재(310)를 거더 제작 시 거더 양 단부면에 긴장재 중심축조정용 정착장치(100)를 이용하여 긴장 후 정착되도록 함으로써 거더에 압축 프리스트레스가 초기 도입되도록 하고, 상기 긴장재 중심축조정용 정착장치(100)의 정착판(113)을 거더의 양 단부면에 매입 설치되도록 거더(500)를 제작하는 단계;
(b) 상기 거더(500)의 일측 단부에서 중앙쪽으로 이격되어 위치한 상부면을 절취하여 일정깊이를 구비한 거더 상면 긴장부가 형성되도록 하며, 연속지점부에 위치하게 될 타측 단부는 단부에서 상단을 절취하여 거더 지점부 상단공간부(B)가 형성되도록 하여, 상기 거더 상면 긴장부와 거더 지점부 상단공간부에 연통되도록 제 2긴장재용 쉬스가 설치되도록 거더를 제작하는 단계;
(c) 상기 제작된 거더(500)를 상기 단부 지점부와 연속지점부에 걸쳐지도록 설치하여 연속지점부에서 상기 거더 지점부 상단공간부가 서로 마주보도록 하여 연속지점부에 확장된 지점부 연결공간(E)이 형성되도록 하는 단계; 및
(d) 상기 연속지점부에서 마주보는 제 2긴장재용 쉬스를 상기 확장된 지점부 연결공간을 활용하여 교량의 종방향 선형곡률과 일치되게 하고 수직 편심을 최대화 할 수 있도록 연속지점부연결관(900)으로 연결한 후, 거더 상부에 슬래브를 시공하는 단계;를 포함하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
In a multi-span bridge construction method using a tension member (300) and a fixing device (100)
(a) the first prestressing member 310 is fixed to both end surfaces of the girder by using the fixing device 100 for the prismatic center-tune adjustment when the first prestressing member 310 is manufactured, Fabricating the girder 500 so that the fixing plate 113 of the fixing apparatus 100 is embedded in both end surfaces of the girder;
(b) a girder upper surface tension portion having a predetermined depth is cut by cutting the upper surface spaced apart from the center at one end of the girder (500), and the other end portion to be positioned at the continuous point portion is cut Thereby forming a girder upper end space portion B so that a sheath for a second tension material is provided so as to communicate with the girder upper surface tension portion and the upper end space portion of the girder post portion;
(c) The manufactured girder 500 is installed so as to span the end portion and the continuous fulcrum portion so that the girder fulcrum upper portion space portion is opposed to each other at the successive fulcrums, E) < / RTI > And
(d) a sheath for the second tension member facing the continuous point portion is made to coincide with the longitudinal linear curvature of the bridge utilizing the extended fulcrum connection space and the vertical fulcrum is maximized, And a step of placing the slab on the upper part of the girder.
제 9항에 있어서,
상기 (b)단계에서, 거더 연속지점부 상단공간부에 연장되는 제 2긴장재용 정착부의 노출된 단부는 지름이 확장된 단면확장부로 형성되도록 하여 상기 단면확장부에 연속지점부연결관(900)의 단부가 삽입되어 연결되도록 하여 연속지점부에서 제 2긴장재의 곡선배치가 용이하도록 하고,
상기 제 2긴장재용 쉬스에는 제 2긴장재가 거더의 일측 거더 상면 긴장부로부터 거더 지점부 상단공간부를 거쳐 인접한 거더의 거더 상면 긴장부를 경유하도록 하고, 슬래브를 시공한 이후에 상기 거더 상면 긴장부에서 정착장치에 의하여 긴장 후 정착되도록 함으로써 거더 전체 및 슬래브에 압축프리스트레스가 도입되도록 하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
10. The method of claim 9,
In the step (b), the exposed end of the fusing unit for the second tension member, which is extended to the space at the upper end of the girder continuous fulcrum, is formed as the enlarged cross-sectional enlargement unit, So that the curvilinear arrangement of the second tensions can be facilitated at the continuous fulcrum portion,
The second tensional material is passed through the upper surface of the girder upper surface space portion from the upper surface girder upper surface space portion of the girder so as to go through the upper surface portion of the girder of the adjacent girder and after the slab is constructed, Wherein the compression prestress is introduced into the entire girder and the slab by tensioning after the tensioning by the device.
제 9항에 있어서,
상기 (d) 단계의 슬래브(700) 시공 이후에, 상기 거더 중앙부 쪽으로 이격된 위치의 거더 하부플랜지 상면과 복부 하부의 측면에 접하도록 형성시킨 제 3긴장재용 정착부(D)에 제 3긴장재(330)를 상기 긴장재 중심축조정용 정착장치(100)를 관통하여 앵커헤드(120)를 관통하도록 한 후, 제 3긴장재(330)를 긴장 후, 상기 앵커헤드(120)에 정착시키는 단계를 포함하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
10. The method of claim 9,
After the installation of the slab 700 in the step (d), the third tension member (D) for the third tension member formed to contact the upper surface of the lower flange of the girder and the lower surface of the lower abdomen at a position spaced toward the center of the girder 330) through the anchor head (120) through the fixing device (100) for the adjustment of the central member for adjusting the tensions and then fixing the third tensions (330) to the anchor head (120) Construction method of girder bridges using a fixing device for center - of - gravity tie fixation.
제 9항에 있어서,
상기 수평블록(210)은 직육면체 블록으로서 앵커헤드의 외주면이 수평블록과 1점 접촉에 의하여 앵케헤드지지블록이 정착판에 지지되도록 하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
10. The method of claim 9,
Wherein the horizontal block (210) is a rectangular parallelepiped block, and the anchor head supporting block is supported on the fixing plate by the one-point contact of the outer peripheral surface of the anchor head with the horizontal block.
제 9항에 있어서,
상기 수평블록(210)은 U형 수평블록으로서 앵커헤드의 외주면이 U형 수평블록의 U형 수용부에 삽입되어 3점 접촉에 의하여 앵케헤드지지블록이 정착판에 지지되도록 하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
10. The method of claim 9,
The horizontal block 210 is a U-shaped horizontal block, and the outer peripheral surface of the anchor head is inserted into the U-shaped receiving portion of the U-shaped horizontal block so that the anchor head supporting block is supported on the fixing plate by three- A method of girder bridge construction using the apparatus.
제 9항에 있어서,
상기 수평블록(210)은 곡선형 수평블록으로서 앵커헤드의 외주면이 곡선형 수평블록의 곡면부에 면 접촉에 의하여 앵케헤드지지블록이 정착판에 지지되도록 하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
10. The method of claim 9,
The horizontal block 210 is a curved horizontal block, and the anchor head is supported on the fixing plate by the surface contact of the outer circumferential surface of the anchor head with the curved surface of the curved horizontal block. In the girder bridge construction Way.
제 9항에 있어서,
상기 앵커헤드(120)는
정착헤드(130)와 링너트를 이용하여 설치되는 것으로서, 상기 정착헤드는 다수의 긴장재관통공이 형성되며 외주면에 나사산에 형성된 것을 이용하되 상기 정착헤드는 긴장재가 관통하여 물려지도록 하고, 상기 링너트는 상기 정착헤드의 나사산에 체결되도록 하여 정착판에 지지되도록 설치하여 긴장재가 정착판, 정착헤드 및 링너트에 의하여 세칭되도록 한 후에, 상기 긴장재가 긴장되어 정착헤드가 정착판으로부터 이격되었을 때, 링너트를 회전시켜 정착판에 상기 링너트가 안착되도록 하는 긴장재 중심축조정용 정착장치를 이용한 거더교 시공방법.
10. The method of claim 9,
The anchor head (120)
The fixing head is formed by using a fixing head 130 and a ring nut. The fixing head is formed with a plurality of through holes, and the fixing head is formed on the outer circumference surface of the fixing head. The fixing head penetrates through the fixing head, The fixing member is fixed to the fixing screw so that the fixing member is supported by the fixing plate so that the tension member is caused to be squeezed by the fixing plate, the fixing head and the ring nut. Then, when the fixing member is strained and the fixing head is separated from the fixing plate, Wherein the ring nut is mounted on the fixing plate by rotating the fixing nut.
KR1020150020895A 2015-02-11 2015-02-11 Bridge construction method using anchorage device for tendon axis displacement control KR101674471B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020150020895A KR101674471B1 (en) 2015-02-11 2015-02-11 Bridge construction method using anchorage device for tendon axis displacement control

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020150020895A KR101674471B1 (en) 2015-02-11 2015-02-11 Bridge construction method using anchorage device for tendon axis displacement control

Publications (2)

Publication Number Publication Date
KR20160099150A true KR20160099150A (en) 2016-08-22
KR101674471B1 KR101674471B1 (en) 2016-11-10

Family

ID=56854689

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150020895A KR101674471B1 (en) 2015-02-11 2015-02-11 Bridge construction method using anchorage device for tendon axis displacement control

Country Status (1)

Country Link
KR (1) KR101674471B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107514097A (en) * 2017-10-13 2017-12-26 柳州欧维姆机械股份有限公司 Prestressing force bellows component and its construction method of installation
CN110273360A (en) * 2019-06-15 2019-09-24 江阴法尔胜住电新材料有限公司 A kind of self-locking prestress anchorage system and construction method
CN114197335A (en) * 2021-12-28 2022-03-18 中交鹭建有限公司 External prestress reinforcing structure of hollow slab beam bridge and construction method
CN114876126A (en) * 2022-06-27 2022-08-09 中冶建工集团有限公司 Prestressed beam corrugated pipe fixing device and construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006090065A (en) * 2004-09-27 2006-04-06 Sumitomo Denko Steel Wire Kk Anchorage device for pc tendon
KR100991869B1 (en) * 2010-02-09 2010-11-04 추태헌 Single and continuous prestressed concrete girder bridge and the construction method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006090065A (en) * 2004-09-27 2006-04-06 Sumitomo Denko Steel Wire Kk Anchorage device for pc tendon
KR100991869B1 (en) * 2010-02-09 2010-11-04 추태헌 Single and continuous prestressed concrete girder bridge and the construction method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107514097A (en) * 2017-10-13 2017-12-26 柳州欧维姆机械股份有限公司 Prestressing force bellows component and its construction method of installation
CN107514097B (en) * 2017-10-13 2023-08-01 柳州欧维姆机械股份有限公司 Prestressed corrugated pipe assembly and installation and construction method thereof
CN110273360A (en) * 2019-06-15 2019-09-24 江阴法尔胜住电新材料有限公司 A kind of self-locking prestress anchorage system and construction method
CN114197335A (en) * 2021-12-28 2022-03-18 中交鹭建有限公司 External prestress reinforcing structure of hollow slab beam bridge and construction method
CN114197335B (en) * 2021-12-28 2024-05-03 中交鹭建有限公司 Construction method of external prestress reinforcing structure of hollow slab beam bridge
CN114876126A (en) * 2022-06-27 2022-08-09 中冶建工集团有限公司 Prestressed beam corrugated pipe fixing device and construction method

Also Published As

Publication number Publication date
KR101674471B1 (en) 2016-11-10

Similar Documents

Publication Publication Date Title
KR100991869B1 (en) Single and continuous prestressed concrete girder bridge and the construction method
KR101674471B1 (en) Bridge construction method using anchorage device for tendon axis displacement control
KR101222620B1 (en) Prestressed concrete girder and it's manufacture and construction method which used pretensioning steel plate
KR101108788B1 (en) Method of manufacturing multi stage prestressed composite beam which composes precast concrete panel and steel girder and correction device used therein
KR101655330B1 (en) Rahmem structure using composite steel beam and the construction method therefor
KR20100025161A (en) Girder bridge connected to abutment and the construction method thereof
KR100823448B1 (en) The improved seismic resistant continuation structure of prestressed concrete composite beam bridge and method thereof
KR101203815B1 (en) Method for strengthening girder using prestressed steel plate
JP2002038421A (en) Erection method of structure
KR20130005928A (en) A composite steel box girder using prestressed concrete for a positive moment area of a bridge
JP4336659B2 (en) Construction method of upper-floor type suspension floor slab bridge
KR101458088B1 (en) Construction method for rahmen bridge using transverse prestressed girder
KR101119050B1 (en) structure for filling-up a steel reinforced concrete on H shaped section steel in slab bridge
KR101660888B1 (en) Girder with pressing embed ahchorage apparatus and the girder construction method therewith
KR20100057446A (en) Apparatus for preventing vertical structure from falling sideward
JP3877995B2 (en) How to build a string string bridge
KR20100025160A (en) Apparatus having a girder connection anchor plate and the continuous construction method for a psc girder bridge by using the same apparatus
KR101483173B1 (en) Corrugated steel plate web-PSC composite beam and Construction method of corrugated steel plate web-PSC composite beam
KR102315988B1 (en) pressing plate and method of manufacturing steel composite girder using thereof
KR101589063B1 (en) Psc girder with end blockout beam and construction method therefor
KR20110019623A (en) Process for producing prestressed concrete girder and concrete girder structure
KR100506573B1 (en) Steel beam constructed prestressing segmental component and construction method thereof
KR20010068055A (en) PSC Girder having Anchoring Sleeves and Strengthening Method
KR101080945B1 (en) Continuous prestressed concrete girder bridge construction method using end-anchorage block and end blockot space
JP4493245B2 (en) Suspended floor slab bridge and method for reinforcing suspended floor slab

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20191031

Year of fee payment: 4