KR20160067056A - The tower crane reinforced concrete lower support structure and construction method - Google Patents

The tower crane reinforced concrete lower support structure and construction method Download PDF

Info

Publication number
KR20160067056A
KR20160067056A KR1020150171516A KR20150171516A KR20160067056A KR 20160067056 A KR20160067056 A KR 20160067056A KR 1020150171516 A KR1020150171516 A KR 1020150171516A KR 20150171516 A KR20150171516 A KR 20150171516A KR 20160067056 A KR20160067056 A KR 20160067056A
Authority
KR
South Korea
Prior art keywords
tower crane
base
frame
ground
support structure
Prior art date
Application number
KR1020150171516A
Other languages
Korean (ko)
Other versions
KR101910844B1 (en
Inventor
최동섭
Original Assignee
주식회사 씨에스콘텍
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 씨에스콘텍 filed Critical 주식회사 씨에스콘텍
Publication of KR20160067056A publication Critical patent/KR20160067056A/en
Application granted granted Critical
Publication of KR101910844B1 publication Critical patent/KR101910844B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Jib Cranes (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

본 발명은 타워크레인의 하부를 지지하기 위한 지지대를 설치하기 위한 시공방법에 관한 것으로서, 보다 상세하게는 고중량의 타워크레인을 지지하기 위하여 타워크레인이 설치되는 하부에 철근콘크리트(이하 RC라 함)를 시공하여 구축함으로서 타워크레인의 설치가 용이하고 고강도 지지가 가능한 타워크레인 RC 하부 지지대 시공방법에 관한 것이다.
또한 타워크레인의 하중을 분산하며 설치 및 유지보수를 용이하게 함으로써, 타워크레인과 맞닿는 지면의 안정성을 향상시키며 장기간 사용하는 타워크레인의 수명을 증가시켜 안전하게 유지할 수 있는 효과가 있다.
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for installing a support for supporting a lower portion of a tower crane, and more particularly, to a construction method for installing a support crane for supporting a tower crane, The present invention relates to a method of constructing a tower crane RC lower support which can easily install a tower crane by constructing and constructing a tower crane.
In addition, by distributing the load of the tower crane and facilitating installation and maintenance, stability of the ground contacting with the tower crane can be improved, and the lifetime of the tower crane used for a long period of time can be increased.

Description

타워크레인 RC 하부 지지대 구조물 및 시공방법{THE TOWER CRANE REINFORCED CONCRETE LOWER SUPPORT STRUCTURE AND CONSTRUCTION METHOD}BACKGROUND OF THE INVENTION 1. Field of the Invention [0001] The present invention relates to a tower crane RC lower support structure,

본 발명은 타워크레인의 하부에 가해지는 하중을 분산하기 위한 지지대 구조물을 시공하기 위한 시공방법에 관한 것으로서, 보다 상세하게는 고중량의 타워크레인을 지지하기 위하여 타워크레인이 설치되는 하부에 철근콘크리트(이하 RC라 함)를 시공하여 구축함으로서 타워크레인의 설치가 용이하고 하중이 분산되어 고강도 지지가 가능한 타워크레인 RC 하부 지지대 구조물 및 시공방법에 관한 것이다.
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for constructing a support structure for dispersing a load applied to a lower portion of a tower crane, RC) to construct a tower crane RC lower support structure which can easily install a tower crane and distribute loads to support high strength.

일반적으로 타워크레인은 빌딩 등의 건설현장에서 작업물을 들어옮기며 필요한 위치로 이동시킬 수 있는 장비로서, 고층건물을 건설하기 위해 필수적으로 사용되고 있다.
In general, tower cranes are used as a means to lift and move workpieces from a construction site, such as a building, to a required location, and are used to construct high-rise buildings.

이러한 타워크레인은 건축물의 층수보다 더 높게 설치하여 사용하는 것이 일반적이며, 건출물의 층수가 증가할수록 타워크레인 또한 지지프레임이 계속 추가되어 그 높이가 높아지게 됨에 따라 타워크레인의 중량 또한 증가하게 되는 상황이 발생하게 된다.
These tower cranes are generally installed higher than the number of buildings, and as the number of floors increases, the weight of the tower crane also increases as the height of the tower crane is increased. .

도 1은 종래의 타워크레인 기초의 평면부분을 도시한 도면으로, 기초부분의 상측단부가 평평하게 형성되어있어 지지프레임의 증가에 따라 타워크레인의 중량 또한 증가하여 타워크레인의 하측단부와 맞닿게 되는 지면부나 슬래브는 타워크레인의 하중을 집중적으로 받게 되어, 타워크레인과 맞닿는 면이 피로누적에 따라 내구성이 하락하게 되며 지면의 안정성 또한 저하되는 문제점이 있다.
FIG. 1 is a plan view of a conventional tower crane foundation, in which the upper end of the base portion is flattened so that the weight of the tower crane also increases with the increase of the support frame to come into contact with the lower end of the tower crane The floor or slab receives the load of the tower crane intensively, so that the durability of the surface contacting the tower crane decreases with the accumulation of fatigue, and the stability of the ground is also lowered.

또한 종래의 타워크레인은 지면에 파워크레인의 하부프레임을 삽입하여 설치하게 됨으로써 지면의 지지부의 강도가 약해지는 문제점이 여전히 존재하고 있다.
Further, the conventional tower crane has a problem that the strength of the supporting portion of the ground is weakened by installing the lower frame of the power crane on the ground.

본 발명은 상기한 바와 같은 문제점을 해결하기 위하여 창안된 것으로서, 더욱 상세하게는 타워크레인의 하측단부에 발생하게되는 하중을 분산시켜 지면과의 안정성을 향상시키며, 타워크레인 지지부의 지지대 구조개선을 통하여 설치 및 유지보수가 용이하도록 하기 위한 타워크레인 RC 하부 지지대 구조물 및 시공방법을 제공하는 것을 그 목적으로 한다.
The present invention has been devised in order to solve the above-described problems, and more particularly, it is an object of the present invention to improve the stability with the ground by dispersing the load generated at the lower end of the tower crane, And an object of the present invention is to provide a tower crane RC lower support structure and a construction method for facilitating installation and maintenance.

상기한 목적을 달성하기 위한 본 발명은, 고층건축물의 시공을 위해 설치되어지는 타워크레인(T)의 지지부에 가해지는 자중을 분산시키고 지지부와의 안정성을 향상시키기 위한 RC 하부 지지대 구조물의 시공방법에 있어서, 상기 시공방법은 (a) 상기 타워크레인(T)이 설치되어지는 시공현장의 지면에는 소정의 깊이가 형성되며 터파기 되어지는 단계, (b) 상기 터파기가 완료되어지면 소정의 위치에 복수개의 매입말뚝 기둥(C)이 수직으로 타설되어지며, 터파기 자리에는 기초부(100)가 형성되어지도록 철근이 격자로 형성되어 배근되어지는 단계, (c) 상기 기초부(100)의 상측단면에는 지면으로부터 소정의 높이만큼 돌출되어 복수개의 돌출부(300)가 형성되어지도록 철근이 배근되어지는 단계, (d) 상기 복수개의 돌출부(300)에는 타워크레인(T)의 하측단부와 결합되어지도록 복수개의 결합부(400)가 수직되어 형성되어지는 단계, (e) 상기 돌출부(300)가 형성되어지며 배근되어지는 철근의 둘레에 현장콘크리트가 타설되어지기 위해 격판이 설치되어지는 단계, (f) 상기 (e)단계가 완료되어지면 현장콘크리트가 타설되어지는 단계, (g) 상기 현장콘크리트와 철근이 일체로 양생되어지면 상기 격판이 해체되어지는 단계, (h) 상기 (g)단계가 완료되어지면 상기 복수개의 결합부(400)에 타워크레인의 프레임이 설치되어지는 단계를 포함하는 것을 특징으로 한다.
In order to achieve the above object, the present invention provides a method of constructing an RC lower support structure for dispersing a weight applied to a support portion of a tower crane T installed for high-rise building construction and improving stability with the support portion (A) a step of forming a predetermined depth on a ground surface of a construction site where the tower crane (T) is installed, and (b) a step of forming a plurality of (C) a step in which reinforcing rods are formed and laid so that the embedded pile columns C are laid vertically and the foundation part 100 is formed at the terra cotta site; (c) (D) the plurality of protrusions 300 are provided with a lower end portion of the tower crane T and a lower end portion of the tower crane T, (E) a step in which the diaphragm is installed to place the concrete in the periphery of the reinforcing bars to which the projecting portion 300 is formed and to be laid around; (g) disassembling the diaphragm when the concrete and the concrete are cured in an integrated manner, (h) dismantling the diaphragm when the concrete and the concrete are cured together, (h) A step of installing a frame of the tower crane in the plurality of coupling parts 400 is completed.

본 발명의 다른 선호적인 실시예에 따르면, 상기 기초부(100)는 격자형상으로 형성되어지는 기초지지부(110)와, 상기 기초지지부(110)의 소정의 위치에는 기초지지부(110)의 구조보강을 위해 설치되어지는 복수개의 연결보강부(120)와, 상기 기초지지부(110)의 일측단부에는 지면과 수직되어지며 소정의 높이만큼 돌출되어 형성되어지는 수직기초부(130)를 포함하는 것을 특징으로 한다.
According to another preferred embodiment of the present invention, the base portion 100 includes a base support portion 110 to be formed in a lattice shape, and a reinforcing structure of the base support portion 110 at a predetermined position of the base support portion 110 And a vertical base part 130 formed at one end of the base supporting part 110 so as to be perpendicular to the ground and protruding by a predetermined height. .

본 발명의 다른 선호적인 실시예에 따르면, 상기 기초부(100)의 상측단부에는 상기 기초부(100)가 지면으로 노출되어지는 것이 방지되어지도록 하기위해 소정의 두께로 형성되어지는 지면부(200)를 포함하는 것을 특징으로 한다.
According to another preferred embodiment of the present invention, an upper end portion of the base portion 100 is provided with a ground portion 200 (see FIG. 1) formed to have a predetermined thickness so as to prevent the base portion 100 from being exposed to the ground. ).

본 발명의 다른 선호적인 실시예에 따르면, 상기 돌출부(300)의 내부에는 타워크레인(T)의 하중이 흡수되어지도록 하기 위한 탄성프레임(F)이 더 포함되어지는 것을 특징으로 한다.
According to another preferred embodiment of the present invention, the protrusion 300 further includes an elastic frame F for absorbing a load of the tower crane T.

본 발명의 다른 선호적인 실시예에 따르면, 상기 탄성프레임(F)은 상부 프레임과 하부 프레임이 소정의 간격을 형성하며 평행하게 배치되어지며, 상부 프레임과 하부 프레임의 사이에는 상하로 지그재그 형상으로 형성되어지는 탄성부로 구성되어지는 것을 특징으로 한다.
According to another preferred embodiment of the present invention, the elastic frame (F) is arranged in parallel and forms an interval between the upper frame and the lower frame, and is formed in a zigzag fashion between the upper frame and the lower frame And an elastic portion to which the elastic member is attached.

한편 본 명세서에 개시된 기술에 관한 설명은 단지 구조적 내지 기능적 설명을 위한 실시예에 불과하므로, 개시된 기술의 권리범위는 본문에 설명된 실시예에 의하여 제한되는 것으로 해석되어서는 아니 된다. 즉, 실시예는 다양한 변경이 가능하고 여러 가지 형태를 가질 수 있으므로 개시된 기술의 권리범위는 기술적 사상을 실현할 수 있는 균등물들을 포함하는 것으로 이해되어야 한다. 또한, 개시된 기술에서 제시된 목적 또는 효과는 특정 실시예가 이를 전부 포함하여야 한다거나 그러한 효과만을 포함하여야 한다는 의미는 아니므로, 개시된 기술의 권리범위는 이에 의하여 제한되는 것으로 이해되어서는 아니 될 것이다.
On the other hand, the description of the technology disclosed herein is merely an example for structural or functional explanation, and the scope of the right of the disclosed technology should not be construed as being limited by the embodiments described in the text. That is, the embodiments are to be construed as being variously embodied and having various forms, so that the scope of the disclosed technology should be understood to include equivalents capable of realizing technical ideas. Also, the purpose or effect of the disclosed technology should not be construed as being limited thereby, as it does not mean that a particular embodiment must include all such effects or merely include such effects.

또한 본 발명에서 서술되는 용어의 의미는 다음과 같이 이해되어야 할 것이다. "제1", "제2" 등의 용어는 하나의 구성요소를 다른 구성요소로부터 구별하기 위한 것으로, 이들 용어들에 의해 권리범위가 한정되어서는 아니 된다. 예를 들어, 제1 구성요소는 제2 구성요소로 명명될 수 있고, 유사하게 제2 구성요소로 제1 구성요소로 명명될 수 있다.
Also, the meaning of the terms described in the present invention should be understood as follows. The terms "first "," second ", and the like are intended to distinguish one element from another, and the scope of the right should not be limited by these terms. For example, the first component may be referred to as a second component, and similarly, the second component may be referred to as a first component.

나아가 어떤 구성요소가 다른 구성요소에 "연결되어"있다고 언급된 때에는, 그 다른 구성요소에 직접적으로 연결될 수도 있지만, 중간에 다른 구성요소가 존재할 수도 있다고 이해되어야 할 것이다. 반면에, 어떤 구성요소가 다른 구성요소에 "직접 연결되어"있다고 언급된 때에는 중간에 다른 구성요소가 존재하지 않는 것으로 이해되어야 할 것이다. 한편, 구성요소들 간의 관계를 설명하는 다른 표현들, 즉 "~사이에"와 "~사이에" 또는 "~에 이웃하는"과 "~에 직접 이웃하는" 등도 마찬가지로 해석되어야 한다.
Further, when an element is referred to as being "connected" to another element, it should be understood that other elements may also be present in the middle, although it may be directly connected to the other element. On the other hand, when an element is referred to as being "directly connected" to another element, it should be understood that there are no other elements in between. On the other hand, other expressions describing the relationship between components, such as "between", "between" or "neighboring to" and "directly adjacent to" should be interpreted as well.

단수의 표현은 문맥상 명백하게 다르게 뜻하지 않는 한 복수의 표현을 포함하는 것으로 이해되어야 하고, "포함하다" 또는 "가지다" 등의 용어는 설시된 특징, 숫자, 단계, 동작, 구성요소, 부분품 또는 이들을 조합한 것이 존재함을 지정하려는 것이며, 하나 또는 그 이상의 다른 특징이나 숫자, 단계, 동작, 구성요소, 부분품 또는 이들을 조합한 것들의 존재 또는 부가 가능성을 미리 배제하지 않는 것으로 이해되어야 한다.
It should be understood that the singular " include "or" have "are to be construed as including a stated feature, number, step, operation, component, It is to be understood that the combination is intended to specify that it does not preclude the presence or addition of one or more other features, integers, steps, operations, elements, components, or combinations thereof.

본 발명은 따른 타워크레인 RC 하부 지지대 구조물 및 시공방법은 타워크레인의 지지부에 가해지는 하중을 분산하며 설치 및 유지보수가 용이하게 함으로써, 타워크레인과 맞닿는 지면의 안정성을 향상시키고 장기간 사용하는 타워크레인의 수명을 증가시켜 안전하게 유지할 수 있는 효과가 있다.
According to the present invention, the lower crane supporting structure and the construction method of the tower crane disperse the load applied to the supporting portion of the crane and facilitate the installation and maintenance, thereby improving the stability of the ground contacting the crane, The lifetime can be increased and the safety can be maintained.

도 1은 종래의 타워크레인 기초의 평면부분을 도시한 도면
도 2는 본 발명에 따른 타워크레인 RC 하부 지지대 구조물의 시공방법를 나타내는 도면대응 시공순서 사진
도 3은 본 발명에 따른 타워크레인 RC 하부 지지대 구조물의 돌출부의 구성요소를 나타내는 도면대응 사진
도 4는 본 발명에 따른 타워크레인 RC 하부 지지대 구조물의 사시부분을 도시한 도면
도 5는 본 발명에 따른 타워크레인 RC 하부 지지대 구조물의 기초부분을 도시한 도면
도 6은 본 발명에 따른 타워크레인 RC 하부 지지대 구조물의 평면부분을 도시한 도면
도 7은 본 발명에 따른 타워크레인 RC 하부 지지대 구조물의 도 5 A의 단면부분을 도시한 도면
도 8은 본 발명의 다른 실시예에 따른 타워크레인 RC 하부 지지대 구조물의 사시부분을 도시한 도면
1 shows a plan view of a conventional tower crane foundation
FIG. 2 is a view showing a construction method of a tower crane RC lower support structure according to the present invention.
Figure 3 is a corresponding illustration of the components of the protrusion of the tower crane RC lower support structure according to the invention
Figure 4 shows a perspective view of a tower crane RC lower support structure according to the present invention;
5 is a view showing a foundation portion of a tower crane RC lower support structure according to the present invention
Figure 6 is a plan view of a tower crane RC lower support structure in accordance with the present invention;
Figure 7 is a cross-sectional view of Figure 5 A of a tower crane RC lower support structure in accordance with the present invention;
8 is a perspective view of a tower crane RC lower support structure according to another embodiment of the present invention;

이하, 본 발명이 속하는 선호적인 실시예를 참고로 하여 더욱 상세하게 설명한다.
Hereinafter, the present invention will be described in more detail with reference to the preferred embodiments to which the present invention belongs.

먼저 도 2는 본 발명에 따른 타워크레인 RC 하부 지지대 구조물의 시공순서를 나타내는 사진으로, 고층건축물의 시공을 위해 설치되어지는 타워크레인(T)의 지지부에 가해지는 자중을 분산시키고 지지부와의 안정성을 향상시키기 위한 RC 하부 지지대의 시공방법에 있어서, 상기 시공방법은 (a) 상기 타워크레인(T)이 설치되어지는 시공현장의 지면에는 소정의 깊이가 형성되며 터파기 되어지는 단계, (b) 상기 터파기가 완료되어지면 소정의 위치에 복수개의 매입말뚝 기둥(C)이 수직으로 타설되어지며, 터파기 자리에는 기초부(100)가 형성되어지도록 철근이 격자로 형성되어 배근되어지는 단계, (c) 상기 기초부(100)의 상측단면에는 지면으로부터 소정의 높이만큼 돌출되어 복수개의 돌출부(300)가 형성되어지도록 철근이 배근되어지는 단계, (d) 상기 복수개의 돌출부(300)에는 타워크레인(T)의 하측단부와 결합되어지도록 복수개의 결합부(400)가 수직되어 형성되어지는 단계, (e) 상기 돌출부(300)가 형성되어지며 배근되어지는 철근의 둘레에 현장콘크리트가 타설되어지기 위해 격판이 설치되어지는 단계, (f) 상기 (e)단계가 완료되어지면 현장콘크리트가 타설되어지는 단계, (g) 상기 현장콘크리트와 철근이 일체로 양생되어지면 상기 격판이 해체되어지는 단계, (h) 상기 (g)단계가 완료되어지면 상기 복수개의 결합부(400)에 타워크레인의 프레임이 설치되어지는 단계를 거쳐 시공이 이루어지게 된다.
FIG. 2 is a photograph showing a construction procedure of a tower crane RC lower support structure according to the present invention. In FIG. 2, (A) a step of forming a predetermined depth on a ground surface of a construction site where the tower crane (T) is installed, and (b) A step of vertically placing a plurality of embedded piles C at a predetermined position when the trenching is completed and forming a reinforcing bar in a grid so that the foundation 100 is formed at the trenching site; A step of projecting a reinforcing bar so that a plurality of projections 300 are formed by projecting a predetermined height from the ground on an upper end surface of the base part 100; A step of vertically forming a plurality of engaging portions 400 so as to be coupled with a lower end of the tower crane T in the projecting portion 300, (e) a step of forming the projecting portion 300, (C) installing a diaphragm so that the site concrete is poured into the concrete, (c) installing the diaphragm so that the site concrete is poured into the concrete, (e) (H) When the step (g) is completed, the frame is installed on the plurality of coupling parts 400, and the construction is performed.

이하 본 발명에 따른 상기 구성요소에 대해서 구체적으로 설명한다.
Hereinafter, the constituent elements according to the present invention will be described in detail.

도 3은 상기 돌출부(300)의 내부에 포함되어지는 탄성프레임(F)을 나타내는 사진으로 타워크레인(T)의 하중이 발생되어지면, 상기 탄성프레임(F)이 상하로 압축되어지거나 이완되어져 하중이 흡수되어지게 된다.
3 is a photograph showing an elastic frame F included in the protrusion 300. When a load of the tower crane T is generated, the elastic frame F is compressed or relaxed upward and downward, Is absorbed.

상기 탄성프레임(F)은 상부 프레임과 하부 프레임으로 구성되어지며, 상부 프레임과 하부 프레임은 얇은 판 형상으로 형성되며, 소정의 간격을 형성하며 지면과 평행하도록 배치되어진다.
The elastic frame (F) is composed of an upper frame and a lower frame. The upper frame and the lower frame are formed in a thin plate shape, and are arranged so as to be parallel to the ground.

상기 상부 프레임과 하부 프레임의 사이에는 상하로 지그재그 형상으로 형성되어지며 탄성을 가지는 탄성부가 형성되어지며, 일반적으로는 금소재의 철근을 이용하여 구성되어지는 것이 선호되지만, 동일한 목적과 기능을 달성할 수 있는 범위 내에서 다른 재질로 구성되어지는 것을 배제하는 것은 아니다.
Generally, it is preferable to use a reinforcing bar made of a gold material. However, it is preferable to use a reinforcing bar made of a gold material to achieve the same purpose and function But it does not exclude that it is composed of different materials within the range that can be achieved.

도 4는 본 발명에 따른 타워크레인 RC 하부 지지대 구조물의 사시부분을 도시한 도면으로, 격자형상으로 형성되어지며 소정의 두께를 가지는 상기 기초부(100)의 상측단부에는 상기 기초부(100)가 외부로 노출되어지는 것이 방지되어지도록 소정의 두께를 가지는 지면부(200)가 현성되어진다.
FIG. 4 is a perspective view of a tower crane RC lower support structure according to the present invention, in which a base portion 100 is formed at an upper end of a base portion 100 having a predetermined thickness, The ground portion 200 having a predetermined thickness is formed so as to be prevented from being exposed to the outside.

상기 지면부(200)의 상측단부 소정의 위치에는 소정의 길이만큼 상부방향으로 돌출되어 형성되어지며 복수개로 이루어지는 복수개의 돌출부(300)가 형성되어진다.
A plurality of protrusions 300 are formed at predetermined positions on the upper surface of the ground section 200 so as to protrude upward by a predetermined length.

상기 돌출부(300)에는 타워크레인(T)과 결합되어지도록 하기 위한 결합부(400)가 형성되어지며, 상기 결합부(400)는 타워크레인(T)과 결합되어지도록 관통홀이 형성되어진다.
The projecting portion 300 is formed with a coupling portion 400 for coupling with a tower crane T. The coupling portion 400 is formed with a through hole to be coupled with the tower crane T. [

상기 기초부(100)는 철근이 격자로 형성되어지도록 배근되며 현장콘크리트가 타설되어지게 되면, 도 5에 도시된 바와 같이 격자형상의 기초지지부(11)가 형성되어진다.
The base portion 100 is laid so that the reinforcing bars are formed into a lattice, and when the site concrete is laid, the lattice-shaped foundation supporting portion 11 is formed as shown in FIG.

상기 기초지지부(110)의 소정의 위치에는 기초지지부(110)의 구조보강을 위하여 복수개의 연결보강부(120)가 설치되어지며, 상기 연결보강부(120)는 일반적으로 H형강이 사용되어지는 것이 선호되지만, 동일한 목적과 기능을 달성할 수 있는 범위 내에서 다른 형상의 형강을 사용하는 것을 배제하는 것은 아니다.
A plurality of connection reinforcing parts 120 are installed at predetermined positions of the base supporting part 110 to reinforce the structure of the base supporting part 110. The connection reinforcing part 120 is generally made of H- However, it is not excluded to use sections of different shapes within the scope of achieving the same purpose and function.

또한 상기 기초지지부(110)의 일측단부에는 지면과 수직되어지며 소정의 높이만큼 상측으로 돌출되어 형성되어지는 수직기초부(130)가 형성되어진다.
A vertical base part 130 is formed at one end of the base supporting part 110 so as to be perpendicular to the ground surface and protruded upward by a predetermined height.

다음으로 도 6은 타워크레인 RC 하부 지지대 구조물의 평면도를 도시한 도면이며, 도 7은 도 6의 A부분에 대한 단면도를 도시한 도면으로, 상기 결합부(400)는 상기 돌출부(300)의 상측단부에 형성되어지며, 상기 결합부(400)의 중심부에는 타워크레인(T)과 결합되어지도록 관통홀이 형성되어진다.
6 is a cross-sectional view taken along the line A of FIG. 6. Referring to FIG. 6, the coupling portion 400 is disposed on the upper side of the protrusion 300 And a through hole is formed at a central portion of the coupling portion 400 so as to be coupled to the tower crane T.

도 8은 본 발명의 다른 실시예를 도시한 도면으로, 상기 돌출부(300)의 상측단부에는 상기 타워크레인(T)의 하측단부에 발생하게 되는 하중을 실시간으로 측정하기 위하여 복수개의 감지센서부(500)가 추가적으로 형성되어진다.
8 is a view illustrating another embodiment of the present invention. In the upper end of the protrusion 300, a plurality of sensing sensor units (not shown) are installed at the lower end of the tower crane T 500 are additionally formed.

상기 복수개의 감지센서부(500)는 타워크레인(T)의 기울어짐 또는 발생되는 하중이 실시간으로 측정되어짐에 따라, 상기 감지센서부(500)를 통하여 측정된 데이터를 주변의 위험감지 장치, 예를 들면 조명 또는 소리발생이 가능한 알람장치를 통해 타워크레인(T)에 이상이 발생하게 되면 이를 즉각적으로 알람장치로 전달하여 현장 근로자들에게 위험상황을 알려 시공현장에서 타워크레인(T)이 쓰러져 발생하게되는 인명피해를 최소화할 수 있는 장점이 있다.
The plurality of detection sensor units 500 detect data that has been measured through the detection sensor unit 500 as surrounding dangerous devices, for example, If an abnormality occurs in the tower crane (T) through an alarm device capable of generating light or sound, it is instantly transmitted to the alarm device to inform the field workers of the dangerous situation and the tower crane (T) It is possible to minimize the damage caused by human life.

상기 감지센서부(500)는 입력된 수치를 초과하게되면, 이를 위험감지 장치로 전달하도록 구성되어지게 된다.
When the detection sensor unit 500 exceeds the input value, the detection sensor unit 500 is configured to transmit the detected value to the danger detection device.

한편, 상기 (c)단계에 형성되어지는 복수개의 돌출부(300)는 소정의 간격으로 형성되어지며 상부방향으로 돌출되어 형성되어지며, 일반적으로 사각형상의 블록형상으로 형성되는 것이 선호되지만 동일한 목적과 기능을 달성할 수 있는 범위 내에서 다른 형상의 사용을 배제하는 것은 아니다.
Meanwhile, the plurality of protrusions 300 formed at the step (c) are formed at predetermined intervals and protrude upward, and it is preferable that the protrusions 300 are formed in a generally rectangular block shape. However, The use of other shapes is not excluded to the extent that it is possible to achieve the above.

상기와 같은 구성의 타워크레인(T)을 이용해 고층건물의 시공을 진행하게 되며, 타워크레인의 지면에 발생하는 하중을 복수개의 돌출부(300)가 분산시켜 지면을 안정적으로 유지할 수 있으며, 복수개의 결합부(400)를 이용하여 타워크레인의 프레임을 결합하기 때문에 타워크레인 프레임의 교체 및 유지보수가 쉽다는 장점이 있다.
The construction of the high-rise building is progressed by using the tower crane T having the above-described structure. The load generated on the ground of the tower crane can be stably maintained by dispersing the plurality of projections 300, Since the frame of the tower crane is coupled using the unit 400, it is easy to replace and maintain the tower crane frame.

상기에서는 본 발명의 바람직한 실시예를 참조하여 설명하였지만, 해당 기술 분야의 숙련된 당업자는 하기의 특허 청구의 범위에 기재된 본 발명의 사상 및 영역으로부터 벗어나지 않는 범위 내에서 본 발명을 다양하게 수정 및 변경시킬 수 있음을 이행할 수 있을 것이다.
It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the present invention as defined by the following claims It will be possible to do so.

100: 기초부 200: 지면부
300: 돌출부 400: 결합부
500: 감지센서부
100: base part 200: ground part
300: protrusion 400:
500: detection sensor unit

Claims (5)

고층건축물의 시공을 위해 설치되어지는 타워크레인(T)의 지지부에 가해지는 자중을 분산시키고 지지부와의 안정성을 향상시키기 위한 RC 하부 지지대 구조물의 시공방법에 있어서, 상기 시공방법은
(a) 상기 타워크레인(T)이 설치되어지는 시공현장의 지면에는 소정의 깊이가 형성되며 터파기 되어지는 단계,
(b) 상기 터파기가 완료되어지면 소정의 위치에 복수개의 매입말뚝 기둥(C)이 수직으로 타설되어지며, 터파기 자리에는 기초부(100)가 형성되어지도록 철근이 격자로 형성되어 배근되어지는 단계,
(c) 상기 기초부(100)의 상측단면에는 지면으로부터 소정의 높이만큼 돌출되어 복수개의 돌출부(300)가 형성되어지도록 철근이 배근되어지는 단계,
(d) 상기 복수개의 돌출부(300)에는 타워크레인(T)의 하측단부와 결합되어지도록 복수개의 결합부(400)가 수직되어 형성되어지는 단계,
(e) 상기 돌출부(300)가 형성되어지며 배근되어지는 철근의 둘레에 현장콘크리트가 타설되어지기 위해 격판이 설치되어지는 단계,
(f) 상기 (e)단계가 완료되어지면 현장콘크리트가 타설되어지는 단계,
(g) 상기 현장콘크리트와 철근이 일체로 양생되어지면 상기 격판이 해체되어지는 단계,
(h) 상기 (g)단계가 완료되어지면 상기 복수개의 결합부(400)에 타워크레인의 프레임이 설치되어지는 단계를 포함하는 것을 특징으로 하는 타워크레인 RC 하부 지지대 구조물의 시공방법
A method of constructing an RC lower support structure for dispersing a weight applied to a support portion of a tower crane (T) installed for the construction of a high-rise building and improving stability with the support portion,
(a) a step of forming a predetermined depth on a ground surface of a construction site where the tower crane (T) is installed,
(b) a plurality of embedded piles C are vertically laid at a predetermined position when the treading is completed, and a reinforcing bar is formed in a lattice such that the foundation 100 is formed at the tearing place step,
(c) placing a reinforcing bar on the upper end surface of the base part 100 so as to protrude from the ground by a predetermined height to form a plurality of protrusions 300,
(d) vertically forming a plurality of engaging portions 400 on the plurality of protrusions 300 so as to be engaged with a lower end of the tower crane T,
(e) installing a diaphragm in order to place the concrete in the periphery of the reinforcing bars to which the protrusions 300 are formed,
(f) a step in which the on-site concrete is laid when the step (e) is completed,
(g) disassembling the diaphragm when the field concrete and the reinforcing bar are cured together,
(h) installing the frame of the tower crane on the plurality of coupling portions (400) when the step (g) is completed.
제 1 항에 있어서
상기 기초부(100)는 격자형상으로 형성되어지는 기초지지부(110)와, 상기 기초지지부(110)의 소정의 위치에는 기초지지부(110)의 구조보강을 위해 설치되어지는 복수개의 연결보강부(120)와, 상기 기초지지부(110)의 일측단부에는 지면과 수직되어지며 소정의 높이만큼 돌출되어 형성되어지는 수직기초부(130)를 포함하는 것을 특징으로 하는 타워크레인 RC 하부 지지대 구조물
The method of claim 1, wherein
The base portion 100 includes a base support portion 110 formed in a lattice shape and a plurality of connection reinforcing portions 110a and 120b provided at predetermined positions of the base support portion 110 to reinforce the structure of the base support portion 110 And a vertical base part (130) formed at one side of the base supporting part (110) perpendicular to the ground and protruding by a predetermined height.
제 2 항에 있어서,
상기 기초부(100)의 상측단부에는 상기 기초부(100)가 지면으로 노출되어지는 것이 방지되어지도록 하기위해 소정의 두께로 형성되어지는 지면부(200)를 포함하는 것을 특징으로 하는 타워크레인 RC 하부 지지대 구조물
3. The method of claim 2,
And a ground portion 200 formed at an upper end of the base portion 100 to have a predetermined thickness so as to prevent the base portion 100 from being exposed to the ground. Lower support structure
제 1 항에 있어서,
상기 돌출부(300)의 내부에는 타워크레인(T)의 하중이 흡수되어지도록 하기 위한 탄성프레임(F)이 더 포함되어지는 것을 특징으로 하는 타워크레인 RC 하부 지지대 구조물
The method according to claim 1,
The tower crane lower support structure (300) further comprises an elastic frame (F) for absorbing the load of the tower crane (T)
제 4 항에 있어서,
상기 탄성프레임(F)은 상부 프레임과 하부 프레임이 소정의 간격을 형성하며 평행하게 배치되어지며, 상부 프레임과 하부 프레임의 사이에는 상하로 지그재그 형상으로 형성되어지는 탄성부로 구성되어지는 것을 특징으로 하는 타워크레인 RC 하부 지지대 구조물
5. The method of claim 4,
The elastic frame (F) is constituted by an elastic portion formed in parallel between the upper frame and the lower frame and spaced vertically between the upper frame and the lower frame. Tower crane RC lower support structure
KR1020150171516A 2014-12-03 2015-12-03 The tower crane reinforced concrete lower support structure and construction method KR101910844B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020140172516 2014-12-03
KR20140172516 2014-12-03

Publications (2)

Publication Number Publication Date
KR20160067056A true KR20160067056A (en) 2016-06-13
KR101910844B1 KR101910844B1 (en) 2018-10-24

Family

ID=56191276

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150171516A KR101910844B1 (en) 2014-12-03 2015-12-03 The tower crane reinforced concrete lower support structure and construction method

Country Status (1)

Country Link
KR (1) KR101910844B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106223358A (en) * 2016-07-19 2016-12-14 中国化学工程第三建设有限公司 A kind of construction method serving as a contrast casing metal sheet cold box foundation
CN109577360A (en) * 2018-12-04 2019-04-05 江苏兴厦建设工程集团有限公司 A kind of derrick crane is inverse to make steel lattice column foundation construction method
CN110004969A (en) * 2019-04-22 2019-07-12 上海建工一建集团有限公司 A kind of tower-crane foundation structure
CN111058473A (en) * 2019-12-30 2020-04-24 朱夏武 Anti-seepage structure for tower crane foundation in basement bottom plate of building and construction method

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200291983Y1 (en) * 2002-07-24 2002-10-12 (주) 통일전력 Foundation structure for steel tower
KR200400845Y1 (en) * 2005-08-25 2005-11-09 주식회사 호주 목조주택 A double truss type binders for reduce floor noise sounds

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106223358A (en) * 2016-07-19 2016-12-14 中国化学工程第三建设有限公司 A kind of construction method serving as a contrast casing metal sheet cold box foundation
CN109577360A (en) * 2018-12-04 2019-04-05 江苏兴厦建设工程集团有限公司 A kind of derrick crane is inverse to make steel lattice column foundation construction method
CN110004969A (en) * 2019-04-22 2019-07-12 上海建工一建集团有限公司 A kind of tower-crane foundation structure
CN111058473A (en) * 2019-12-30 2020-04-24 朱夏武 Anti-seepage structure for tower crane foundation in basement bottom plate of building and construction method
CN111058473B (en) * 2019-12-30 2021-05-07 朱夏武 Anti-seepage structure for tower crane foundation in basement bottom plate of building and construction method

Also Published As

Publication number Publication date
KR101910844B1 (en) 2018-10-24

Similar Documents

Publication Publication Date Title
KR101910844B1 (en) The tower crane reinforced concrete lower support structure and construction method
US9249593B2 (en) Systems for elevating a building structure above grade, and related methods
KR101288683B1 (en) Guide rail device for climbing gang forms
KR101928332B1 (en) Temporary Structure Failure Detection Monitoring Device
KR20130043765A (en) Safety apparatus for lift gang form
JP6147621B2 (en) Tower crane support structure and tower crane equipment
JP6177151B2 (en) Independent foundation reinforcement structure and independent foundation
JP6177150B2 (en) Independent foundation reinforcement structure and independent foundation
JP2008175036A (en) Concrete foundation beam member and method for constructing mat foundation by connecting concrete foundation beam connecting members
KR102019693B1 (en) Intake tower earthquake proofing and reinforcing method using cable
KR20120025945A (en) Reinforcement assembly of concrete file and building foundation
KR101772468B1 (en) The modular support member for construction precast member and construction method
JP5749620B2 (en) Seismic isolation method for existing buildings
KR100519072B1 (en) A measuring apparatus of a retaining wall structures for safety diagnostic
US20230062533A1 (en) Shallow foundation bollard structures
KR101265139B1 (en) Bridge safe experience apparatus in the construction field
KR101193470B1 (en) Bearing and constructing method for bridge
KR101408781B1 (en) Strut including Lug for mounting wedge and chainblock for drawing strand
KR100660426B1 (en) Gangform Fall Protection
Su et al. Development of the IoT-based monitoring system for scaffold shoring system of concrete formwork
JP6562544B2 (en) Cylindrical caisson scaffolding
CN211183281U (en) Detachable suspender
JP5322214B2 (en) Foundation reinforcement method for existing wooden houses
CN106968376A (en) A kind of assembled hanging platform structure and its construction method
KR20220035709A (en) Safety reinforcement retaining system equipped with buckling detection and buckling reinforcement means

Legal Events

Date Code Title Description
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20151203

A201 Request for examination
PA0201 Request for examination

Patent event code: PA02012R01D

Patent event date: 20151204

Comment text: Request for Examination of Application

Patent event code: PA02011R01I

Patent event date: 20151203

Comment text: Patent Application

PG1501 Laying open of application
E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20170313

Patent event code: PE09021S01D

E90F Notification of reason for final refusal
PE0902 Notice of grounds for rejection

Comment text: Final Notice of Reason for Refusal

Patent event date: 20171116

Patent event code: PE09021S02D

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

Patent event code: PE07011S01D

Comment text: Decision to Grant Registration

Patent event date: 20180723

GRNT Written decision to grant
PR0701 Registration of establishment

Comment text: Registration of Establishment

Patent event date: 20181017

Patent event code: PR07011E01D

PR1002 Payment of registration fee

Payment date: 20181018

End annual number: 3

Start annual number: 1

PG1601 Publication of registration
PR1001 Payment of annual fee

Payment date: 20211007

Start annual number: 4

End annual number: 4

PR1001 Payment of annual fee

Payment date: 20220913

Start annual number: 5

End annual number: 5

PR1001 Payment of annual fee

Payment date: 20241007

Start annual number: 7

End annual number: 7