KR20160041281A - Construction work management system based on BIM and management method of the same - Google Patents

Construction work management system based on BIM and management method of the same Download PDF

Info

Publication number
KR20160041281A
KR20160041281A KR1020140134887A KR20140134887A KR20160041281A KR 20160041281 A KR20160041281 A KR 20160041281A KR 1020140134887 A KR1020140134887 A KR 1020140134887A KR 20140134887 A KR20140134887 A KR 20140134887A KR 20160041281 A KR20160041281 A KR 20160041281A
Authority
KR
South Korea
Prior art keywords
construction
information
bim
construction information
plan
Prior art date
Application number
KR1020140134887A
Other languages
Korean (ko)
Other versions
KR101662651B1 (en
Inventor
최태일
김진우
나호준
Original Assignee
현대건설주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 현대건설주식회사 filed Critical 현대건설주식회사
Priority to KR1020140134887A priority Critical patent/KR101662651B1/en
Publication of KR20160041281A publication Critical patent/KR20160041281A/en
Application granted granted Critical
Publication of KR101662651B1 publication Critical patent/KR101662651B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/109Time management, e.g. calendars, reminders, meetings or time accounting
    • G06Q10/1091Recording time for administrative or management purposes

Abstract

The present invention provides a construction work management method based on building information modeling (BIM). The construction work management method comprises the steps of: constructing a construction information library module for construction of a building; executing a construction information planning module through a construction information library in a BIM model of the building; executing a construction information input module inputting construction information regarding each construction plan and each construction performance carried out based on the construction information planning module; and outputting construction information including a construction plan and a construction performance generated by the input of the construction information. Thus, the constructed construction information library module can be connected to each module for use to manage construction work more efficiently, the construction information library module can be reused later to lay foundation for the reuse of the construction information, and when a method of construction is selected, activities can be automatically generated and arranged by the construction information library module, so the construction of a building can be planned and managed more efficiently.

Description

BIM기반 건설공사 관리 시스템 및 관리 방법 {Construction work management system based on BIM and management method of the same}[0001] The present invention relates to a BIM-based construction management system and a management method thereof,

본 발명은 BIM기반 건설공사 관리 시스템 및 관리 방법에 관한 것으로서, 보다 상세하게는 BIM과 연계하고 축적된 공사정보를 기반으로 건설공사를 효율적으로 통합관리할 수 있는 BIM기반 건설공사 관리 시스템 및 관리 방법에 관한 것이다.The present invention relates to a BIM-based construction management system and method, and more particularly, to a BIM-based construction management system and management method capable of efficiently and integrally managing construction work based on accumulated construction information in connection with BIM .

일반적으로 건설공사의 일정관리란, 건설공사계약을 위한 공사내역을 실제 시행할 작업(Activity)들로 분류, 정의하고 그 정의된 작업들이 주어진 기간 내에 주어진 목표를 달성할 수 있도록 관리하는 기법으로서 PERT/CPM기법의 일정관리를 지칭하며 이러한 일정관리를 쉽게 할 수 있도록 지원해주는 상용패키지가 많이 개발, 보급되고 있는 추세이다.In general, the schedule management of construction works is a technique to classify and define the construction details for construction contracts as real activities and manage the defined tasks to achieve the given goal within a given period. / CPM technique. It is a tendency that many commercial packages that support the schedule management are developed and popular.

이러한 건설공사의 관리방법의 기술의 예로 종래에는 인터넷을 이용하여 건설사업을 관리하는 방법 및 그 방법을 실행하기 위한 시스템으로 특허공개 제10-2002-0041390호의 인터넷을 이용한 건설사업관리방법 및 그 시스템이 개시된 바 있다. 그런데, 상기 건설사업관리방법 및 그 시스템은 각각의 관리모듈 별로 건설정보를 저장함에 따라 관리모듈 상호간의 연결관계가 미흡하여 모듈별 입력 실적 및 결론에 대한 배경 및 타 모듈에 미치는 영향을 파악하기는 불가능한 문제점이 있었다.As an example of the technique of management method of construction work, conventionally, a method of managing a construction business using the Internet and a system for implementing the method are disclosed in Patent Publication No. 10-2002-0041390, Have been disclosed. However, since the construction management method and the system store construction information for each management module, the connection relation between the management modules is insufficient, so that it is necessary to grasp the background of the module input results and the influence on conclusion and other modules There was an impossible problem.

다른 예로, 특허공개 제10-2012-0121634호는 웹 기반의 3차원 모델링을 통한 공정 및 비용관리 시스템 및 그의 운용 방법이 개시된 바 있는데, 이러한 경우에는 BIM기반 공정정보 및 비용정보를 연계관리하기는 하나 공정 및 비용정보로 한정하여 외부에서 작성된 정보를 불러들여와 연계하는 방식이기 때문에 시스템 내 공사계획 및 정보관리체계 표준화가 불가능한 문제점이 있었다.In another example, Patent Publication No. 10-2012-0121634 discloses a process and cost management system and its operating method through web-based three-dimensional modeling. In this case, linking BIM-based process information and cost information There is a problem that it is impossible to standardize the construction planning and information management system in the system because it is a method of importing and linking the information created externally only to one process and cost information.

또 다른 기술의 예로 특허공개 제10-2012-0122189호는 스마트폰 기반 건설사업관리 시스템 및 건설사업관리방법이 개시된 바 있으며, 이러한 경우에는 검측에 제한적으로 사용되며 검측을 위한 체크리스트 및 부접합 사항에 대한 관리 기록이 불가능하며 공사정보를 작업자가 매번 입력하는 방식으로 구성되어 표준화된 공사정보관리체계를 가질 수 없을 뿐만 아니라, 도면 또는 BIM모델링과의 연계가 없으므로 위치적 정보 확인이 불가능한 문제점이 있었다.As another example of technology, Patent Publication No. 10-2012-0122189 discloses a smartphone-based construction project management system and a construction project management method. In such a case, limited use is made for the inspection, and a checklist for inspection and a non- It is not possible to have a management information record for the construction work. Therefore, it is not possible to have a standardized construction information management system composed of the construction information input by the worker every time, and there is no linkage with the drawing or BIM modeling, .

본 발명은, 관리모듈 상호간의 공사정보 및 공사실적 등을 연계하기 위한 공사정보 라이브러리를 구축하고 및 이를 통하여 공사계획 및 공사관리의 체계화 및 표준화를 가능하게 함은 물론, BIM을 활용하여 건물공사를 효과적으로 계획 및 관리할 수 있는 BIM기반 건설공사 관리 시스템 및 관리 방법을 제공하는데 목적이 있다.The present invention establishes a construction information library for linking construction information and construction results between management modules, and enables systematization and standardization of construction planning and construction management, And to provide a BIM-based construction management system and method that can be effectively planned and managed.

본 발명의 일 측면에 의하면, 본 발명은 건설하고자 하는 해당건물의 공사정보가 축적된 공사정보 라이브러리모듈; 상기 공사정보 라이브러리모듈과 연계되어 상기 해당건물의 BIM(Building information modeling)모델에서 설정된 구역에 대한 공사정보를 계획하는 공사정보 계획모듈; 상기 공사정보 계획모듈을 토대로 공사를 실시하되, 각 공사계획과 공사실적에 대한 공사정보를 입력하기 위한 공사정보 입력모듈; 및 상기 공사정보 입력에 의해 생성된 상기 공사계획과 상기 공사실적을 포함하는 공사정보를 출력하는 공사정보 출력모듈을 포함하는 BIM기반 건설 공사 관리 시스템.을 제공한다.According to an aspect of the present invention, there is provided a construction information library module in which construction information of a building to be constructed is stored. A construction information planning module for linking the construction information library module and planning construction information for a zone set in a building information modeling (BIM) model of the building; A construction information input module for performing construction based on the construction information planning module and inputting construction information for each construction plan and construction results; And a construction information output module for outputting construction information including the construction plan and the construction results generated by the construction information input.

본 발명의 다른 실시예에 의하면, 본 발명은 해당건물의 공사를 위한 공사정보 라이브러리모듈을 구축하는 단계; 상기 해당건물의 BIM(Building information modeling)모델에서 상기 공사정보 라이브러리를 통하여 공사정보 계획모듈을 수행하는 단계; 상기 공사정보 계획모듈을 토대로 실시된 각 공사계획과 공사실적에 대한 공사정보를 입력하는 공사정보 입력모듈을 수행하는 단계; 및 상기 공사정보 입력에 의해 생성된 상기 공사계획과 상기 공사실적을 포함하는 공사정보를 출력하는 공사정보 출력모듈을 수행하는 단계를 포함하는 BIM기반 건설 공사 관리 방법을 제공한다. According to another embodiment of the present invention, there is provided a method for constructing a construction information library module for building a building, Performing a construction information planning module through the construction information library in a building information modeling (BIM) model of the building; Performing a construction information input module for inputting construction information on each construction plan and construction results based on the construction information planning module; And a construction information output module for outputting construction information including the construction plan and the construction result generated by the construction information input.

본 발명에 따른 BIM기반 건설공사 관리 시스템 및 관리 방법은 다음과 같은 효과를 제공한다. The BIM-based construction management system and management method according to the present invention provides the following effects.

첫째, 구축된 공사정보 라이브러리모듈을 각 모듈과 연계하고 이를 활용함으로써 보다 효율적으로 건설공사 관리를 수행할 수 있으며, 공사정보 라이브러리모듈을 향 후 재활용할 수 있어 공사정보 재활용의 기반을 다질 수 있다.First, by linking the built construction information library module with each module, it is possible to perform construction management more efficiently by utilizing it, and the construction information library module can be recycled and reused so that the foundation of construction information recycling can be improved.

둘째, 공법을 선택하면 공사정보 라이브러리모듈에서 자동으로 액티비티가 생성 및 배열되어 보다 효율적으로 건물공사를 계획 및 관리할 수 있다.Second, if the construction method is selected, the activity information is automatically generated and arranged in the construction information library module, so that the construction work can be planned and managed more efficiently.

셋째, 관리모듈 상호간의 공사정보 및 공사실적 등을 연계하고, 각각의 관리모듈 별로 공사정보를 저장 및 축적하여 모듈별 입력 실적 및 결론에 대한 배경 및 타 모듈에 미치는 영향을 파악하기가 용이하다. Third, it is easy to correlate construction information and construction results between management modules, and to store and accumulate construction information for each management module, so it is easy to grasp the input results per module and the effect on background and other modules of conclusion.

넷째, 공사정보 라이브러리를 구축하여 공사계획 및 공사정보관리를 체계화 및 표준화를 가능하게 할 수 있다. Fourth, the construction information library can be constructed to systematize and standardize the construction plan and construction information management.

다섯째, 도면 또는 BIM모델과 연계하여 객체에 대한 위치적 정보 확인이 용이하고, 건물공사 계획 및 관리를 용이하게 할 수 있다. Fifth, it is easy to confirm the positional information about the object in connection with the drawing or the BIM model, and it is possible to facilitate planning and management of the building work.

도 1은 본 발명의 실시예에 따른 BIM기반 건설공사 관리 시스템의 구성을 개략적으로 나타낸 블록도이다.
도 2는 본 발명의 실시예에 따른 BIM기반 건설공사 관리 방법을 나타내는 절차도이다.
도 3은 도 2의 공사정보 라이브러리모듈 구축과정을 나타내는 절차도이다.
도 4는 도 2의 공사정보 계획모듈을 수행하는 절차를 나타내는 절차도이다.
도 5는 도 2의 공사정보 입력모듈을 수행하는 절차를 나타내는 절차도이다.
도 6은 도 2의 공사정보 출력모듈을 수행하는 과정을 나타내는 절차도이다.
1 is a block diagram schematically illustrating a configuration of a BIM-based construction management system according to an embodiment of the present invention.
2 is a flowchart illustrating a BIM-based construction management method according to an embodiment of the present invention.
FIG. 3 is a flowchart illustrating a process of constructing the construction information library module of FIG.
4 is a flowchart illustrating a procedure for executing the construction information planning module of FIG.
5 is a flowchart illustrating a procedure for executing the construction information input module of FIG.
6 is a flowchart illustrating a process of performing the construction information output module of FIG.

이하 첨부된 도면을 참조하면서 본 발명에 따른 바람직한 실시예를 상세히 설명하기로 한다.
Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

먼저, 도 1을 참조하면, 본 발명의 실시예에 따른 BIM기반 건설공사 관리 시스템은, BIM과 건설프로세스 접목을 통하여 건설공사를 통합 관리할 수 있는 것으로 공사정보 라이브러리모듈(100)과, 공사정보 계획모듈(200)과, 공사정보 입력모듈(300)과, 공사정보 출력모듈(400)을 포함한다.Referring to FIG. 1, a BIM-based construction management system according to an embodiment of the present invention can integrally manage a construction through a BIM and a construction process, and includes a construction information library module 100, A planning module 200, a construction information input module 300, and a construction information output module 400.

상기 공사정보 라이브러리모듈(100)은, 상기 공사정보 계획모듈(200)과 연계되어 공사계획 수립 시 사용되는 것으로서, 공사계획 및 실적입력과 같은 공사 관리에 필요한 라이브러리 생성, 수정, 삭제를 통한 표준화 관리가 가능하게 하며, 프로젝트 BIM 객체 기반의 공사정보관리 프로세스 연계를 통한 공사정보(계획/실적)가 축적된다. The construction information library module 100 is used in establishing a construction plan in connection with the construction information planning module 200. The construction information library module 100 is used for standardization management by creating, , And construction information (plan / performance) is accumulated through linkage of project information management process based on project BIM object.

상세하게, 상기 공사정보 라이브러리모듈(100)은, 공법 라이브러리(S21)와, 품질 라이브러리(S22)와, 자원라이브러리(S23)를 포함한다. 상기 공법 라이브러리(S21)는, 공법의 특성에 따른 대/중/소 공종(작업)별 작업 명명 및 작업 순서를 생성 및 관리하며, 해당건물의 골조부와 마감부를 포함하는 각 객체 종류에 따른 액티비티와, 공법별 액티비티 순서를 포함하고 있다. 여기서, 상기 객체는 건물의 수직부재와 수평부재와 슬래브를 포함하는 골조부와, 마감재와 창호를 포함하는 마감부 등을 포함할 수 있다.In detail, the construction information library module 100 includes a construction library S21, a quality library S22, and a resource library S23. The construction library (S21) generates and manages a job naming and a work order for each large / small / small type (work) according to the characteristics of the construction method, and performs activities related to each object type including a frame part and a finishing part of the building And an activity sequence for each construction method. Here, the object may include a framing part including a vertical member of the building, a horizontal member and a slab, and a finishing part including a finishing material and a window.

상기 품질 라이브러리(S22)는, 생성된 공법단위의 대/중/소 공종 단위 품질관리 체크리스트를 생성 또는 상기 품질 체크리스트를 불러오고, 생성된 상기 액티비티와 상기 품질 체크리스트를 맵핑할 수 있도록 한다.The quality library S22 generates a large / medium / small-sized unit quality control check list of the generated construction method or invokes the quality check list and maps the generated activity and the quality check list .

상기 자원 라이브러리(S23)는, 공종별 공사에 투입되는 자원인 인력과 장비를 생성하는 것으로, 인력업체 및 장비관련 라이브러리를 생성 및 축적한다.The resource library (S23) generates manpower and equipment, which are resources to be put into construction by type of work, and generates and stores labor-related companies and equipment-related libraries.

상기 공사정보 계획모듈(200)은, 상기 공사정보 라이브러리모듈(100)과 연계되어 초기 공사계획을 수립하는 것으로서, 해당건물의 BIM(Building information modeling)모델에서 설정된 구역에 대한 공사정보를 계획한다. 여기서, 상기 BIM모델(10)은 3D모델(OBS)와 속성정보를 관리하고, 상기 공사정보 계획모듈(200)에서 BIM의 OBS/WBS/CBS를 맵핑한다. 한편, 상기 BIM모델과 뷰어 등에 관한 상세한 설명은 공지의 건설사업관리분야의 BIM과 관련된 내용과 유사하므로 생략하기로 한다.The construction information planning module 200 establishes an initial construction plan in connection with the construction information library module 100 and plans construction information for a zone set in a building information modeling (BIM) model of the building. Here, the BIM model 10 manages the 3D model (OBS) and attribute information, and maps the OBS / WBS / CBS of the BIM in the construction information planning module 200. The detailed description of the BIM model, the viewer, and the like is similar to that related to the BIM in the field of construction management.

상기 공사정보 계획모듈(200)은, 상기 BIM모델(10)에서 상기 설정된 구역의 객체에 대한 공사정보를 작업자가 선택하면 상기 공사정보 라이브러리를 통하여 선택된 객체에 대한 액티비티(Activity)가 자동생성 및 배열된다. .The construction information planning module 200 automatically generates and arranges activities for selected objects through the construction information library when the operator selects construction information for the objects in the set area in the BIM model 10 do. .

상기한 바에 따르면, 상기 공사정보 계획모듈(200)은 공사계획 기반 공사정보관리 BIM 모델링 명명 체계화 및 BIM 모델링 물량현황을 시각화할 수 있는데, 즉 설계 BIM모델링 명명체계와 공사계획 BIM 모델링 명명 체계(수직조닝,수평조닝; 도3참조)연계로 새로운 공사정보관리 BIM 명명체계가 생성되고, 변화하는 공사계획에 따라 공사정보관리 BIM 명명 체계 반영 및 이에 따른 물량현황을 시각화할 수 있다. 또한, 상기 공사정보 계획모듈(200)은 선택된 BIM 모델링 속성정보를 활용하여 공사정보 라이브러리모듈(100) 공법 연계 자동화 및 액티비티를 생성하는데, BIM모델링 속성정보 중 객체의 종류를 활용, 공사정보 라이브러리모듈(100)과 연계하여 공법에 따른 작업순서에 따라 대/중/소 공종을 포함한 액티비티를 생성하고, BIM 모델링의 객체 부위정보와 연계한다.According to the above description, the construction information planning module 200 can visualize the BIM modeling naming system and the BIM modeling quantity status of the construction plan-based construction information management BIM modeling naming system and the construction plan BIM modeling naming system 3), a new construction information management BIM naming system is created, and the construction information management BIM nomenclature system can be reflected and the quantity status according to the changed construction plan can be visualized. In addition, the construction information planning module 200 generates automation and activity related to the construction method library module 100 using the selected BIM modeling property information. The construction information planning module 200 utilizes the types of objects in the BIM modeling property information, (100), the activity including the large / medium / small type work is generated according to the work order according to the construction method, and is linked with the object part information of the BIM modeling.

상기 공사정보 입력모듈(300)은, 상기 초기 공사계획에 기반하여 실제 공사 계획 및 실적을 입력하는 것으로서, 상기 공사정보 계획모듈(200)을 토대로 공사를 실시하되, 각 공사계획과 공사실적에 대한 공사정보를 입력한다. 상게하게, 상기 공사정보 입력모듈(300)은, 공사계획 입력모듈(S31;도 5참조)과, 공사실적 입력모듈(S32)을 포함한다. The construction information input module 300 inputs actual construction plans and performances based on the initial construction plan and performs construction based on the construction information planning module 200, Enter the construction information. The construction information input module 300 includes a construction plan input module S31 (see FIG. 5) and a construction performance input module S32.

상기 공사계획 입력모듈(S31)은, 사무실에서 웹시스템을 기반으로 하여 공사계획을 입력하도록 되어 있다. 여기서, 상기 공사정보 입력모듈(300)은, 상기 공사계획에 따른 각 액티비티에 대한 전체 공사 일정 계획과, 상기 액티비티 단위 계획에 따른 주간별 일별 단기 공사 일정 계획과, 당일 공사 실적 확인을 각각 입력할 수 있도록 되어 있다.The construction plan input module (S31) is configured to input the construction plan based on the web system in the office. Here, the construction information input module 300 inputs the total construction schedule for each activity according to the construction plan, the daily schedule for each week according to the activity unit plan, and the performance confirmation on the day .

상기 공사실적 입력모듈(S32)은, 모바일기기를 기반으로 하여 현장에서 현장 실적을 실시간으로 입력하도록 되어 있다. 여기서, 상기 공사실적 입력모듈(S32)은, 단위 시간에 대한 공사계획 및 시공체크리스트 입력과, 액티비티 단위별 시작시간 및 종료시간 입력과, BIM뷰어에서 작업 객체부위 선택 입력과, 상기 액티비티 단위별 품질 체크리스트를 확인 후 적합여부를 입력하도록 되어 있다.The construction result input module (S32) is configured to input, in real time, field performance on the basis of a mobile device. Here, the work performance input module (S32) inputs a construction plan and a construction check list for a unit time, inputs a start time and an end time for each activity unit, a work object part selection input in the BIM viewer, After confirming the quality check list, it is required to enter the conformity.

상기 공사정보 출력모듈(400)은, 상기 공사정보 입력에 의해 생성된 상기 공사계획과 상기 공사실적을 포함하여 공사정보를 출력하며, 공사 계획, 입력 및 품질 실적 보고서를 생성하여 출력하고, 공사계획 및 입력 실적 정보 자료를 출력하도록 되어 있다.The construction information output module 400 outputs construction information including the construction plan and the construction results generated by the construction information input, generates and outputs a construction plan, input and quality performance report, And input result information data.

상기한 바에 따르면, 상기 BIM기반 건설공사 관리 시스템은 기존 개별 실적/결과 단위로 공정/품질 등이 관리되어 온 PMIS 공사정보관리와는 달리 BIM과 상기 공사정보 계획모듈(200)과, 공사정보 라이브러리모듈(100)과, 공사정보 입력모듈(300)을 연계하여 공사정보 통합관리가 가능하다. 또한, BIM 모델링의 객체 별로 공사정보 계획모듈(200)에서 생성되는 초기공사계획과 공사정보 라이브러리모듈(100)에서의 공법/품질/자원 정보가 연계되어, 이를 바탕으로 공사정보 입력모듈(300) 수행 시 단위 계획 및 실적이 입력되어 공사정보를 축적하고 축적된 공사정보 등의 결과물은 공사정보 출력모듈(400)을 통해 보고서 및 데이터 형식으로 추출된다.Unlike the PMIS construction information management, which is managed by the BIM-based construction management system, the BIM, the construction information planning module 200, the construction information library The module 100 and the construction information input module 300 are linked with each other so that the construction information integration management is possible. In addition, the initial construction plan generated by the construction information planning module 200 and the construction method / quality / resource information in the construction information library module 100 are linked with each other in the BIM modeling object, The unit plan and the performance are inputted at the time of execution and the construction information is accumulated and the result of the accumulated construction information and the like is extracted as a report and data format through the construction information output module 400.

즉, 상기 BIM기반 건설공사 관리시스템은, BIM기반 공사정보 라이브러리모듈(100)을 통하여 공사정보를 통합 관리할 수 있으며, BIM객체기반의 공사정보관리 프로세스 연계를 통하여 공사정보(계획/실적)을 축적하여 효율적으로 공사관리를 할 수 있음은 물론 공사정보를 향후 재사용할 수 있는 기반을 마련함으로써 공사기간감축을 비롯한 공사계획과 공사정보관리를 보다 체계적이고 표준화 시킬 수 있다. 또한, 공사정보를 BIM의 3차원 객체 기반으로 맵핑함으로써 건설 프로세스와 생성되는 공사정보를 상호 연계하고 이를 PC기반의 공사계획모듈(200) 및 실시간 현장 시공 및 품질 공사정보를 효율적으로 입력하는 모바일 모듈을 통하여 작업성을 용이하게 하고 실적 자원화를 통한 향후 공사정보 재활용 기반을 다질 수 있다.
That is, the BIM-based construction management system can integrally manage the construction information through the BIM-based construction information library module 100. The BIM-based construction management system can manage the construction information (plan / performance) It is possible to accumulate and manage the construction efficiently, and it is possible to systematically standardize the construction plan and construction information management including construction period reduction by establishing the basis for reusing construction information in the future. Also, by mapping the construction information on the basis of the three-dimensional object of the BIM, the construction process and the generated construction information are linked with each other, and the construction planning module 200 based on the PC and the mobile module for efficiently inputting the real- , It is possible to improve the workability and to improve the recycling base of the construction information in the future through the recycling of the actual resources.

이하에서는, 상기한 BIM기반 건설공사 관리 시스템을 통하여 본 발명의 실시예에 따른 BIM기반 건설공사 관리방법에 대하여 도 2 내지 도 6을 참조하여 살펴보기로 한다. Hereinafter, a BIM-based construction management method according to an embodiment of the present invention will be described with reference to FIGS. 2 to 6 through the BIM-based construction management system.

먼저, 도 2를 참조하면, 본 발명의 실시예에 따른 BIM기반 건설공사 관리방법은, 공사정보 라이브러리모듈(100)을 구축하는 단계(S200)와, 공사정보 계획모듈(200)을 수행하는 단계(S100)와, 공사정보 입력모듈(300)을 수행하는 단계(S300)와, 공사정보 출력모듈(400)을 수행하는 단계(S400)를 포함한다. Referring to FIG. 2, a BIM-based construction management method according to an embodiment of the present invention includes constructing a construction information library module 100 (S200), performing a construction information planning module 200 A step S300 of executing the construction information input module 300, and a step S400 of performing the construction information output module 400. [

도 3을 참조하면, 상기 공사정보 라이브러리모듈(100)을 구축하는 단계(S200)는, 시스템상으로 해당건물의 공사를 위한 공사정보 라이브러리모듈(100)을 구축하는 단계로서, 공법 라이브러리를 생성하는 단계(S21)와, 품질 라이브러리를 생성하는 단계(S22)와, 자원 라이브러리를 생성하는 단계(S23)를 포함한다. Referring to FIG. 3, the step of constructing the construction information library module 100 (S200) includes building a construction information library module 100 for construction of the building on the system, A step S21 of generating a quality library, a step S22 of creating a quality library, and a step S23 of creating a resource library.

상기 공법 라이브러리를 생성하는 단계(S21)는, 객체 종류에 따른 액티비티 대/중/소분류를 생성하고(S210), 공법별 상기 액티비티 순서를 정의한다(S220).In step S21, the activity library is generated. In step S220, activity groups are generated according to the object types. In step S220, the activity groups are defined in step S220.

상기 품질 라이브러리를 생성하는 단계(S22)는, 품질 체크리스트 생성 또는 상기 품질 체크리스트를 불러오는 단계(S230)와, 생성된 상기 액티비티와 상기 품질 체크리스트를 맵핑하는 단계(S240)를 포함하여 생성된다.The step S22 of generating the quality library is generated by including a step of creating a quality check list or loading the quality check list S230 and mapping the generated activity and the quality check list S240 .

상기 자원 라이브러리를 생성하는 단계(S23)는, 인력관련 전문업체명, 공종(공종, 인력담당자) 및 이름을 추가하는 단계(S250)와, 장비관련 장비명 및 규격을 추가하는 단계(S260)를 포함한다. The step of creating the resource library (S23) includes a step (S250) of adding a name of a professional company, a type of work (a type of worker, a person in charge) and a name, and a step S260 of adding an equipment- do.

도 4를 참조하면, 상기 공사정보 계획모듈(200)을 수행하는 단계(S200)는, 상기 해당건물의 BIM(Building information modeling)모델에서 상기 공사정보 라이브러리를 통하여 수행하는데, 세부적으로 상기 BIM모델(10)의 뷰어(Viewer)에서 공간별과 부재별에 대한 필터링에 따른 BIM모델(10) 물량현황을 확인(S110)한 뒤, 작업자에 의하여 상기 BIM모델(10)에서 같은 시공을 하는 것으로 복수개의 층단위로 수직 조닝(S120)을 실시한다. Referring to FIG. 4, the step S200 of performing the construction information planning module 200 is performed through the construction information library in a building information modeling (BIM) model of the building, 10 in the BIM model 10 according to the filtering by the space and the member in step S 110 and then the same construction is performed by the operator in the BIM model 10, A vertical zoning (S120) is performed in units of layers.

그런 다음, 수직 조닝에 의하여 복수개의 층으로 이루어진 수직존으로 필터링 된 BIM 뷰어에서 수평 조닝을 위한 하나 또는 복수개의 객체를 선택(S130)하여 구역설정과 부재선택을 한 뒤 수평 조닝명을 선택(S140)한다.Then, one or a plurality of objects for horizontal zoning are selected (S130) in the BIM viewer filtered by vertical zones composed of a plurality of layers by vertical zoning, and a horizontal zoning name is selected )do.

다음으로, 선택된 수평조닝에서 상기 객체의 속성정보에 따른 존의 공사종류에 따른 공법종류와 존별, 층별 공사선행여부를 작업자가 선택(S150)하는데 이때, 선택된 공법종류는 존 단위 같은 공사를 실시한다. 이러한 과정을 거친 다음에는, 상기 수평조닝별 인력 및 장비를 선택(S160)하는데, 그 세부내용은 업체명, 작업자, 장비규격, 장비 대수 등과 관련된 사항으로 할 수 있다. Next, in step S150, the operator selects the type of construction method, zone type, and construction precedence according to the construction type of the zone according to the attribute information of the object in the selected horizontal zoning (S150). At this time, . After this process, the manpower and equipment for each horizontal zoning are selected (S160). The details may be related to the company name, worker, equipment specifications, equipment number, and the like.

상기한 객체의 공법종류와 상기 공사선행여부 및 상기 객체에 대한 인력 및 장비가 작업자에 의하여 선택되면, 시스템상에서 자동으로 상기 공사정보 라이브러리를 통하여 층/수평 조닝별 액티비티(Activity)가 대/중/소분류별로 자동생성 및 배열되고 해당 객체부위, 인력 및 장비가 자동 연계(S170)된다. 여기서, 상기 액티비티 대/중/소분류의 예로, 골조공사의 경우 액티비티 대분류는 수직존 층별 철근콘크리트공사를 포함할 수 있으며, 중분류는 수직 수평부재 철근공사, 거푸집공사, 콘크리트공사, 마무리공사를 포함할 수 있으며, 소분류는 수직부재 수평부재 철근공사에 대해서는 먹매김, 철근양중, 철근설치를 포함하고, 수직부재 수평부재 거푸집공사에 대해서는 먹매김, 거푸집양중, 거푸집설치를 포함하고, 수직부재 수평부재 콘크리트공사는 콘크리트 타설을, 수직부재 수평부재 마무리는 거푸집해체를 포함할 수 있다.When the type of the object, the precedence of the construction, and the manpower and equipment for the object are selected by the operator, the activity for each layer / horizontal zoning is automatically / And the object part, manpower and equipment are automatically linked (S170). Here, in the case of the activity large / medium / small classification, in the case of the frame construction, the activity major classification may include the reinforced concrete construction by the vertical zone floor, and the middle class includes vertical and horizontal member reinforcing work, formwork, concrete work, For the vertical member horizontal member reinforcing steel work, the sub-category includes installation of reinforcing bars, reinforcing bars and reinforcing bars. For vertical member horizontal member formwork, it includes feeding, formwork and formwork. Vertical member horizontal member concrete Construction may include concrete pouring, vertical member horizontal member finishing, and form dismantling.

도 5를 참조하면, 상기 공사정보 입력모듈(300)을 수행하는 단계는, 상기 공사정보 계획모듈(200)을 토대로 실시된 각 공사계획과 공사실적에 대한 공사정보를 입력하는 공사정보 입력모듈(300)을 수행하며, 사무실에서 웹시스템 기반 공사계획을 입력하는 단계(S31)와, 상기 웹시스템 기반 공사계획 입력에 따라 현장에서 모바일기기 기반 현장실적을 실시간으로 입력하는 단계(S32)를 포함한다.Referring to FIG. 5, the step of performing the construction information input module 300 includes a construction information input module 300 for inputting construction information on each construction plan and construction performance based on the construction information planning module 200 300), inputting a web system-based construction plan in the office (S31), and inputting a real-time field performance based on the mobile device in the field according to the web system-based construction plan input (S32) .

상기 웹시스템 기반 공사계획을 입력하는 단계(S31)는, 중분류 액티비티 단위 순서 및 인력/장비 부분을 수정 및 공사 시작일과 종료일을 수정하여 전체 공사 일정 계획을 입력하는 단계(S310)와, 소분류 액티비티 단위 계획에 의하여 주간별 일별 계획을 입력하는 단계(S320)와, 당일 실적 확인을 포함하여 일일 계획을 입력하는 단계(S330)를 포함한다.The step S31 of inputting the web system-based construction plan includes a step S310 of inputting the overall construction schedule by modifying the order of divisional activity unit, the manpower / equipment part, and the construction start date and the ending date, A step S320 of inputting a weekly day-by-day plan according to the plan, and a step S330 of entering a daily plan including confirmation of the same day's performance.

상기 모바일기기 기반 현장실적을 실시간으로 입력하는 단계(S32)는, 상기 일일 계획과 시공체크리스트를 확인하는 단계(S340)와, 소분류 액티비티 단위 시작시간을 확인하는 단계(S350)와, 상기 소분류 액티비티 단위 종료시간 확인 및 BIM뷰어에서 작업 객체부위를 선택하는 단계(S360)와, 중분류 액티비티 단위 품질 체크리스트를 확인(S370)하여 적합여부를 판단하는 단계(S380)를 포함한다. 여기서, 상기한 과정을 거쳐 적합여부 판단 시 부적합 사항이 없을 시 부적합 보고서 작성 및 조치를 확인(S390)한다. The step S32 of inputting the mobile device-based field performances in real time includes a step S340 of checking the daily plan and a construction check list, a step S350 of checking the start time of the sub-activity unit, Step S360 of checking the unit end time and selecting a job object part in the BIM viewer, and S360 checking the middle division activity unit quality check list S360 to determine whether it is suitable or not (step S380). If there is no inconsistency in the determination of conformity through the process described above, the nonconformity report preparation and measures are confirmed (S390).

도 6을 참조하면, 상기 공사정보를 출력하는 단계는, 상기 공사정보 입력에 의해 생성된 상기 공사계획과 상기 공사실적을 포함하는 공사정보를 출력한다.Referring to FIG. 6, the step of outputting the construction information may include outputting the construction information including the construction plan generated by the construction information input and the construction results.

상세하게, 상기 공사정보 출력모듈(400)을 수행하는 단계는, 공사 계획, 입력 및 품질 실적 보고서 생성 및 출력하는 단계(S410)와, 공사계획 및 입력 실적 정보 원자료를 출력하는 단계(S420)를 포함한다.In detail, the step of performing the construction information output module 400 includes a step S410 of generating and outputting a construction plan, an input and a quality performance report, a step S420 of outputting a construction plan and an input result information source data, .

상기한 바에 따르면, 상기 BIM기반 건설공사 관리시스템 및 관리방법은, 결과 중심의 오프라인(Off-line) 공사관리 방식에서 과정 중심의 온라인(On-line) 공사관리 방식의 실시간 공사정보관리를 할 수 있으며, 건축공사가 점차 대형화, 복잡화가 되는 요즘 이에 효율적으로 대응할 수 있는 공사정보를 분석 및 활용할 수 있다. 또한, 구축된 공사정보 라이브러리모듈을 각 모듈과 연계하고 이를 활용함으로써 보다 효율적으로 건설공사 관리를 수행할 수 있으며, 공사정보 라이브러리모듈을 향 후 재활용할 수 있어 공사정보 재활용의 기반을 다질 수 있고, 작업자가 공법을 선택하면 시스템상으로 공사정보 라이브러리모듈을 통하여 자동으로 액티비티가 생성 및 배열되어 보다 효율적으로 건물공사를 계획 및 관리할 수 있다.
According to the above description, the BIM-based construction management system and management method can perform real-time construction information management on the basis of a process-oriented on-line construction management method in an off-line construction management method based on results As the construction work becomes larger and more complicated, it is possible to analyze and utilize the construction information that can cope efficiently. In addition, by linking the constructed construction information library module with each module and utilizing it, it is possible to perform construction construction management more efficiently, and the construction information library module can be recycled, so that the foundation of construction information recycling can be improved, When the operator selects the construction method, the activity is automatically generated and arranged through the construction information library module on the system, so that the construction work can be more efficiently planned and managed.

본 발명은 도면에 도시된 실시예를 참고로 설명되었으나 이는 예시적인 것에 불과하며, 본 기술 분야의 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 다른 실시예가 가능하다는 점을 이해할 것이다. 따라서, 본 발명의 진정한 기술적 보호 범위는 첨부된 특허청구범위의 기술적 사상에 의하여 정해져야 할 것이다.While the present invention has been described with reference to exemplary embodiments, it is to be understood that the invention is not limited to the disclosed exemplary embodiments, but, on the contrary, is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the appended claims. Accordingly, the true scope of the present invention should be determined by the technical idea of the appended claims.

100... 공사정보 라이브러리모듈 200... 공사정보 계획모듈
300... 공사정보 입력모듈 400... 공사정보 출력모듈
100 ... construction information library module 200 ... construction information planning module
300 ... construction information input module 400 ... construction information output module

Claims (14)

건설하고자 하는 해당건물의 공사정보가 축적된 공사정보 라이브러리모듈;
상기 공사정보 라이브러리모듈과 연계되어 상기 해당건물의 BIM(Building information modeling)모델에서 설정된 구역에 대한 공사정보를 계획하는 공사정보 계획모듈;
상기 공사정보 계획모듈을 토대로 공사를 실시하되, 각 공사계획과 공사실적에 대한 공사정보를 입력하기 위한 공사정보 입력모듈; 및
상기 공사정보 입력에 의해 생성된 상기 공사계획과 상기 공사실적을 포함하는 공사정보를 출력하는 공사정보 출력모듈을 포함하는 BIM기반 건설 공사 관리 시스템.
A construction information library module in which construction information of a building to be constructed is accumulated;
A construction information planning module for linking the construction information library module and planning construction information for a zone set in a building information modeling (BIM) model of the building;
A construction information input module for performing construction based on the construction information planning module and inputting construction information for each construction plan and construction results; And
And a construction information output module for outputting the construction information including the construction plan and the construction result generated by the construction information input.
청구항 1에 있어서,
상기 공사정보 라이브러리모듈은,
해당건물의 골조부와 마감부를 포함하는 각 객체 종류에 따른 액티비티와, 공법별 액티비티 순서를 포함하는 공법 라이브러리와,
품질 체크리스트 생성 또는 상기 품질 체크리스트를 불러오고, 생성된 상기 액티비티와 상기 품질 체크리스트를 맵핑하는 품질 라이브러리와,
인력업체 및 장비관련 라이브러리를 생성하는 자원 라이브러리를 포함하는 BIM기반 건설 공사 관리 시스템.
The method according to claim 1,
The construction information library module includes:
A construction library including an activity according to each object type including a frame part and a finishing part of the building and an activity sequence for each construction method,
A quality library that generates a quality check list or invokes the quality check list, maps the generated activity and the quality check list,
A BIM-based construction management system that includes a resource library that generates worker vendors and equipment-related libraries.
청구항 1에 있어서,
상기 공사정보 계획모듈은,
상기 BIM모델에서 상기 설정된 구역의 객체에 대한 공사정보를 상기 공사정보 라이브러리를 통하여 액티비티(Activity)가 자동생성 및 배열되는 BIM기반 건설 공사 관리 시스템.
The method according to claim 1,
The construction information planning module comprises:
And a BIM-based construction management system in which activity information is automatically generated and arranged through the construction information library in the BIM model.
청구항 1에 있어서,
상기 공사정보 입력모듈은,
웹시스템을 기반으로 하여 공사계획을 입력하는 공사계획 입력모듈과,
모바일기기를 기반으로 하여 현장에서 현장실적을 입력하는 공사실적 입력모듈을 포함하는 BIM기반 건설 공사 관리 시스템.
The method according to claim 1,
The construction information input module includes:
A construction plan input module for inputting a construction plan based on the web system,
BIM-based construction management system that includes construction performance input module for inputting site performance on site based on mobile device.
청구항 4에 있어서,
상기 공사계획 입력모듈은,
상기 공사계획에 따른 각 액티비티에 대한 전체 공사 일정 계획과, 상기 액티비티 단위 계획에 따른 주간별 일별 단기 공사 일정 계획과, 당일 공사 실적 확인을 각각 입력하는 BIM기반 건설 공사 관리 시스템.
The method of claim 4,
The construction schedule input module includes:
A BIM-based construction management system that inputs a total construction schedule for each activity based on the construction plan, a daily schedule for each week according to the activity unit plan, and a confirmation of the performance on that day.
청구항 4에 있어서,
상기 공사실적 입력모듈은,
단위 시간에 대한 공사계획 및 시공체크리스트 입력과, 액티비티 단위별 시작시간 및 종료시간 입력과, BIM뷰어에서 작업 객체부위 선택 입력과, 상기 액티비티 단위별 품질 체크리스트를 확인 후 적합여부를 입력하는 것을 포함하는 BIM기반 건설 공사 관리 시스템.
The method of claim 4,
The construction result input module includes:
Inputting a construction plan and construction checklist for unit time, inputting a start time and an ending time for each activity unit, inputting a work object part selection input in the BIM viewer, and confirming the quality check list for each activity unit, Including BIM - based construction management system.
청구항 1에 있어서,
상기 공사정보 출력모듈은,
공사 계획, 입력 및 품질 실적 보고서를 생성하여 출력하고, 공사계획 및 입력 실적 정보 자료를 출력하는 BIM기반 건설 공사 관리 시스템.
The method according to claim 1,
The construction information output module includes:
A BIM-based construction management system that generates and outputs construction plans, inputs and quality performance reports, and outputs construction plans and input performance data.
해당건물의 공사를 위한 공사정보 라이브러리모듈을 구축하는 단계;
상기 해당건물의 BIM(Building information modeling)모델에서 상기 공사정보 라이브러리를 통하여 공사정보 계획모듈을 수행하는 단계;
상기 공사정보 계획모듈을 토대로 실시된 각 공사계획과 공사실적에 대한 공사정보를 입력하는 공사정보 입력모듈을 수행하는 단계; 및
상기 공사정보 입력에 의해 생성된 상기 공사계획과 상기 공사실적을 포함하는 공사정보를 출력하는 공사정보 출력모듈을 수행하는 단계를 포함하는 BIM기반 건설 공사 관리 방법.
Building a construction information library module for construction of the building;
Performing a construction information planning module through the construction information library in a building information modeling (BIM) model of the building;
Performing a construction information input module for inputting construction information on each construction plan and construction results based on the construction information planning module; And
And performing a construction information output module for outputting construction information including the construction plan and the construction result generated by the construction information input.
청구항 8에 있어서,
상기 공사정보 라이브러리모듈을 구축하는 단계는,
객체 종류에 따른 액티비티를 생성하는 단계와, 공법별 상기 액티비티 순서를 정의하는 단계를 포함하는 공법 라이브러리를 생성단계와,
품질 체크리스트 생성 또는 상기 품질 체크리스트를 불러오는 단계와, 생성된 상기 액티비티와 상기 품질 체크리스트를 맵핑하는 단계를 포함하는 품질 라이브러리를 생성하는 단계와,
인력업체 및 장비관련 라이브러리를 생성하는 자원 라이브러리를 생성하는 단계를 포함하는 BIM기반 건설 공사 관리 방법.
The method of claim 8,
The step of constructing the construction information library module comprises:
Generating an activity according to an object type, and defining a sequence of activities for each method;
Generating a quality check list or invoking the quality check list; generating a quality library including mapping the generated activity and the quality check list;
And creating a resource library that creates a library of worker companies and equipment.
청구항 8에 있어서,
상기 공사정보 계획모듈을 수행하는 단계는,
상기 BIM모델에서 공간별과 부재별에 대한 필터링에 따른 BIM모델 물량현황을 확인하는 단계;
상기 BIM모델에서 복수개의 층단위로 수직조닝하는 단계;
수직조닝 된 상기 복수개의 층으로 필터링 된 상기 BIM모델에서 하나 또는 복수개의 객체를 선택하여 수평조닝을 수행하는 단계;
선택된 수평조닝에서 상기 객체의 공사종류에 따른 공법종류와 공사선행여부를 선택하는 단계;
상기 수평조닝별 인력 및 장비를 선택하는 단계; 및
상기 객체의 공법종류와 상기 공사선행여부 및 상기 객체에 대한 인력 및 장비가 선택되면 상기 공사정보 라이브러리를 통하여 액티비티(Activity)가 자동생성 및 배열되고 인력 및 장비가 자동 연계되는 단계를 포함하는 BIM기반 건설 공사 관리 방법.
The method of claim 8,
Wherein the step of performing the construction information planning module comprises:
Checking the status of the BIM model according to the filtering by the space and the member in the BIM model;
Vertically zoning a plurality of layers in the BIM model;
Performing horizontal zoning by selecting one or a plurality of objects in the BIM model filtered with the vertically zoned multiple layers;
Selecting a type of construction method and a construction precedence according to a construction type of the object in the selected horizontal zoning;
Selecting the attracting force and equipment for each horizontal zoning; And
A BIM-based system including an automatic generation and arrangement of activities through the construction information library and automatically associating manpower and equipment when the type of construction method of the object, the construction precedence, and the manpower and equipment for the object are selected; How to manage construction work.
청구항 8에 있어서,
상기 공사정보 입력모듈을 수행하는 단계는,
웹시스템 기반 공사계획을 입력하는 단계와,
상기 웹시스템 기반 공사계획 입력에 따라 모바일기기 기반 현장실적을 실시간으로 입력하는 단계를 포함하는 BIM기반 건설 공사 관리 방법.
The method of claim 8,
The step of performing the construction information input module includes:
Inputting a web system-based construction plan,
And inputting a mobile device-based field performance in real time in accordance with the input of the web system-based construction plan.
청구항 11에 있어서,
상기 웹시스템 기반 공사계획을 입력하는 단계는,
중분류 액티비티 단위 순서 및 인력/장비 부분을 수정 및 공사 시작일과 종료일을 수정하여 전체 공사 일정 계획을 입력하는 단계와,
소분류 액티비티 단위 계획에 의하여 주간별 일별 계획을 입력하는 단계와,
당일 실적 확인을 포함하여 일일 계획을 입력하는 단계를 포함하는 BIM기반 건설 공사 관리 방법.
The method of claim 11,
Wherein the step of inputting the web system-
Inputting an overall construction schedule by modifying the order of divisional activity unit and manpower / equipment part and correcting construction start and end dates;
Inputting a day-by-day daily plan according to the small-category activity unit plan,
A method for managing a BIM-based construction work including a step of inputting a daily plan including confirming a day's performance.
청구항 12에 있어서,
상기 모바일기기 기반 현장실적을 실시간으로 입력하는 단계는,
상기 일일 계획과 시공체크리스트를 확인하는 단계와,
소분류 액티비티 단위 시작시간을 확인하는 단계와,
상기 소분류 액티비티 단위 종료시간 확인 및 BIM뷰어에서 작업 객체부위를 선택하는 단계와,
중분류 액티비티 단위 품질 체크리스트를 확인하여 적합여부를 판단하는 단계를 포함하는 BIM기반 건설 공사 관리 방법.
The method of claim 12,
The step of inputting the mobile device-based field performance in real-
Confirming the daily plan and the construction check list;
Confirming the sub-activity unit start time,
Checking the sub-activity unit end time and selecting a work object part in the BIM viewer;
And a step of verifying the conformity of the divisional activity unit quality check list.
청구항 8에 있어서,
상기 공사정보 출력모듈을 수행하는 단계는,
공사 계획, 입력 및 품질 실적 보고서 생성 및 출력하는 단계와,
공사계획 및 입력 실적 정보 원자료를 출력하는 단계를 포함하는 BIM기반 건설 공사 관리 방법.
The method of claim 8,
The step of performing the construction information output module includes:
Generating and outputting a construction plan, an input and a quality performance report,
A method for managing a BIM-based construction work including a step of outputting a construction plan and input result information source data.
KR1020140134887A 2014-10-07 2014-10-07 Construction work management system based on BIM and management method of the same KR101662651B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020140134887A KR101662651B1 (en) 2014-10-07 2014-10-07 Construction work management system based on BIM and management method of the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020140134887A KR101662651B1 (en) 2014-10-07 2014-10-07 Construction work management system based on BIM and management method of the same

Publications (2)

Publication Number Publication Date
KR20160041281A true KR20160041281A (en) 2016-04-18
KR101662651B1 KR101662651B1 (en) 2016-10-05

Family

ID=55916424

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020140134887A KR101662651B1 (en) 2014-10-07 2014-10-07 Construction work management system based on BIM and management method of the same

Country Status (1)

Country Link
KR (1) KR101662651B1 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101695914B1 (en) 2016-06-23 2017-01-16 부산대학교산학협력단 Excavator 3-dimensional earthwork bim system for providing realtime shape information of excavator in executing earthwork construction
KR20180055130A (en) * 2016-11-16 2018-05-25 현대건설주식회사 Heavy equipment management system based on BIM and heavy equipment management method of the same
CN109360123A (en) * 2018-10-22 2019-02-19 上海建工四建集团有限公司 A kind of multi-specialized execution management method therefor and system based on room
KR102112749B1 (en) * 2018-11-28 2020-05-21 주식회사 대림코퍼레이션 Method for managing of the tower crane using construction management plan and computer readable media thereof
KR102112748B1 (en) * 2018-11-28 2020-05-21 주식회사 대림코퍼레이션 Method for managing of Earth-volume and frame-volume resource using construction management plan and computer readable media thereof
KR102112747B1 (en) * 2018-11-28 2020-05-21 주식회사 대림코퍼레이션 Method for planning of construction management using vertical relation and horizontal relation and program and computer readable media thereof
CN111877760A (en) * 2020-06-16 2020-11-03 中交第三公路工程局有限公司 BIM-based construction method in super high-rise building construction
CN112241770A (en) * 2020-08-05 2021-01-19 上海建工一建集团有限公司 Building block splitting and reconstructing method based on BIM and RFID
KR20210032744A (en) 2019-09-17 2021-03-25 현대건설주식회사 Construction management system and method based on bim
CN113706086A (en) * 2020-05-22 2021-11-26 成晟 Bridge construction quality measurement change progress plan management data structure design

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102153531B1 (en) 2019-11-26 2020-09-09 한국건설기술연구원 the 3D printing design and construction method based on BIM
KR20240016734A (en) 2022-07-29 2024-02-06 서울대학교산학협력단 System and method for managing modular construction project schedule
KR102561303B1 (en) 2023-02-21 2023-07-28 (주)원빔그룹 Method, device and system for providing construction management solution through linkage between architectural design bim data and construction schedule

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070004162A (en) * 2005-07-04 2007-01-09 심영호 Project management information system
KR20130016620A (en) * 2011-08-08 2013-02-18 삼성물산 주식회사 3d process management method for bim(building information modeling)

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20070004162A (en) * 2005-07-04 2007-01-09 심영호 Project management information system
KR20130016620A (en) * 2011-08-08 2013-02-18 삼성물산 주식회사 3d process management method for bim(building information modeling)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
송성열 외 2인, "4D 시뮬레이션을 위한 공법 템플릿 기반의 건설공정 자동 생성", 산업공학(IE interfaces) 제25권 제2호, 2012년6월, pp. 216 ~ 228* *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101695914B1 (en) 2016-06-23 2017-01-16 부산대학교산학협력단 Excavator 3-dimensional earthwork bim system for providing realtime shape information of excavator in executing earthwork construction
KR20180055130A (en) * 2016-11-16 2018-05-25 현대건설주식회사 Heavy equipment management system based on BIM and heavy equipment management method of the same
CN109360123A (en) * 2018-10-22 2019-02-19 上海建工四建集团有限公司 A kind of multi-specialized execution management method therefor and system based on room
CN109360123B (en) * 2018-10-22 2021-07-27 上海建工四建集团有限公司 Multi-professional construction management method and system based on room
KR102112749B1 (en) * 2018-11-28 2020-05-21 주식회사 대림코퍼레이션 Method for managing of the tower crane using construction management plan and computer readable media thereof
KR102112748B1 (en) * 2018-11-28 2020-05-21 주식회사 대림코퍼레이션 Method for managing of Earth-volume and frame-volume resource using construction management plan and computer readable media thereof
KR102112747B1 (en) * 2018-11-28 2020-05-21 주식회사 대림코퍼레이션 Method for planning of construction management using vertical relation and horizontal relation and program and computer readable media thereof
KR20210032744A (en) 2019-09-17 2021-03-25 현대건설주식회사 Construction management system and method based on bim
CN113706086A (en) * 2020-05-22 2021-11-26 成晟 Bridge construction quality measurement change progress plan management data structure design
CN111877760A (en) * 2020-06-16 2020-11-03 中交第三公路工程局有限公司 BIM-based construction method in super high-rise building construction
CN112241770A (en) * 2020-08-05 2021-01-19 上海建工一建集团有限公司 Building block splitting and reconstructing method based on BIM and RFID

Also Published As

Publication number Publication date
KR101662651B1 (en) 2016-10-05

Similar Documents

Publication Publication Date Title
KR101662651B1 (en) Construction work management system based on BIM and management method of the same
KR101754328B1 (en) Construction work management system based on BIM and management method of the same
Wu et al. Bridge construction schedule generation with pattern-based construction methods and constraint-based simulation
Getuli et al. A BIM-based construction supply chain framework for monitoring progress and coordination of site activities
Larsson et al. Discrete event simulation analysis of product and process platforms: A bridge construction case study
KR101717766B1 (en) Labor-based Progress Measurement for Cost and Schedule Control System in Construction Programs
Li et al. SWP-enabled constraints modeling for on-site assembly process of prefabrication housing production
Si et al. A dynamic just-in-time component delivery framework for off-site construction
Brinda et al. Developments of facility management using building information modelling
Porwal Construction waste management at source: a Building Information Modeling based system dynamic approach
Krepp et al. BIMsite-towards a BIM-based generation and evaluation of realization variants comprising construction methods, site layouts and schedules
Khanh et al. Exploring productivity of concrete truck for multistory building projects using discrete event simulation
Alsudairi Simulation as a tool for assessing the economical aspects of construction processes
Ghammad et al. Transforming building renovation: A holistic, strategic approach with construction robot management
Leifgen et al. Integrated digital and model-based construction logistics management based on lean thinking approaches
Prasertrungruang et al. System dynamics modelling of machine downtime for small to medium highway contractors
Nguyen Process-based cost modeling to support target value design
Taha et al. Overall Cost Overrun Estimate in Residential Projects: A Hybrid Dynamics Approach
Weber et al. Rule-Based Generation of Assembly Sequences for Simulation in Large-Scale Plant Construction
Agostinelli et al. 4D Bim-Oriented Digital Project Construction Management for the Aec Industry
Sacks et al. System Design–Requirements and Specifications for Simulation and Prediction
Igwe et al. Using lean construction tools and 4D modelling for equipment workspace planning
Handayani et al. A Proposal for Implementing Building Information Modeling (BIM) to Manage the Prerequisite Activities in Construction Projects
Hindmarch et al. A support tool for assessing the impact of design changes during built environment projects
Khataei et al. 4D BIM integrated productivity estimation of construction projects

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20190903

Year of fee payment: 4