KR20160002620A - Soil retaining wall and construction method thereof - Google Patents
Soil retaining wall and construction method thereof Download PDFInfo
- Publication number
- KR20160002620A KR20160002620A KR1020150179175A KR20150179175A KR20160002620A KR 20160002620 A KR20160002620 A KR 20160002620A KR 1020150179175 A KR1020150179175 A KR 1020150179175A KR 20150179175 A KR20150179175 A KR 20150179175A KR 20160002620 A KR20160002620 A KR 20160002620A
- Authority
- KR
- South Korea
- Prior art keywords
- pile
- retaining structure
- ground
- support pile
- earth
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
BACKGROUND OF THE
The term "retaining structure" means a temporary structure or permanent structure which is installed to protect the construction area by supporting the earth pressure of the back soil in the construction work to secure the construction area of the structure.
Examples of the construction method for forming the wall in such a retaining structure include a thumb pile method, a CIP (Cast-In-Place) method, a SCW (Soil Cement Wall) method, a sheet file method, a slurry wall method, have.
As a method for preventing collapse of the wall in the retaining structure, there are a stratified construction method, an earth anchor construction method, a soil nail construction method, and the earth anchor and the soil nail construction method are a method of supporting a tensile material on the back soil side.
1 shows a conventional soil retaining structure in which a
However, in the conventional earth anchor method, since the penetration depth D of the
If the inclination angle? Formed by the
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and it is an object of the present invention to provide a retaining structure capable of stably installing an earth anchor or soil nail even when it is difficult to secure sufficient space on the back surface, and a construction method thereof do.
In order to solve the above problems, the present invention provides a retaining structure supported by a plurality of piles (10), in which all or a part of the plurality of piles (10) are formed and a lower end is formed as a fixed end A supporting pile 100 inserted so as to have a penetration depth D of 3 times (3 /?) Or more of the
It is preferable that the virtual fixed point (1 /?) Is calculated by the following equation (1).
[Equation 1]
k H : horizontal soil reaction force coefficient
D: Diameter of the support pile 100
EI: Flexural Stiffness of Support Pile (100)
The
The inclination angle? Formed by the
The
The upper portion of the
The method of constructing the earth retaining structure according to the present invention is characterized in that the lower end of the supporting pile 100 is inserted at least three times (3 / β) of the virtual fixing point (1 / β) on the basis of the maximum excavation depth (H) Calculating a penetration depth (D) of the support pile (100); (100) on the ground to satisfy the penetration depth (D); Forming the hinge part (200) on the upper end of the supporting pile (100); A step of attaching the
The method of constructing the earth retaining structure according to the present invention is characterized in that the lower end of the supporting pile 100 is inserted at least three times (3 / β) of the virtual fixing point (1 / β) on the basis of the maximum excavation depth (H) Calculating a penetration depth (D) of the support pile (100); (100) on the ground to satisfy the penetration depth (D); Installing the cap beam (210) on the upper end of the support pile (100); The upper end of the
The present invention proposes a retaining structure capable of stably installing an earth anchor or soil nail even when it is difficult to secure sufficient space on the back surface, and a construction method thereof.
1 is a cross-sectional view of a retaining structure according to a conventional earth anchor method.
2 is a sectional view of a retaining structure according to the present invention.
3 is a schematic diagram of a virtual fixed point model of a pile.
Fig. 4 is a view showing a bending moment of a conventional earth retaining wall. Fig.
5 is a load distribution diagram of a conventional retaining structure.
6 is a view showing bending moments of the earth retaining wall according to the present invention.
7 is a load distribution diagram of the earth retaining structure according to the present invention.
8 is a sectional view of an embodiment of a hinge portion of a retaining structure according to the present invention.
Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
As shown in FIG. 2 and subsequent drawings, the retaining structure supported by a plurality of
Here, the earth retaining structure supported by the plurality of
The
Hereinafter, the virtual fixed point theory (model) will be described.
The virtual fixed-point model, which is mainly used for the foundation pile design, is an equivalent fixed-bed model. The virtual fixed point in the ground is generated so that the reaction force and the bending moment of the pile head are the same as those calculated by replacing the ground with the elastic spring It is a theory to decide.
As shown in FIG. 3, it is assumed that the virtual fixed point is located at 1 / β below the ground surface. Considering that the ground displacement does not occur any longer than the virtual fixed point, the lateral resistance design method of the pile The pile is designed by applying.
Here, β is the lateral resistance characteristic value of the pile, which can be obtained by the following equation (1).
k H : horizontal soil reaction force coefficient
D: Diameter of the support pile 100
EI: Flexural Stiffness of Support Pile (100)
In this way, the virtual fixed point model is proposed for the design of general pile (foundation structure) irrespective of the original retaining structure, and the depth of penetration (D) of the pile is 3 times (3 / β) or more of the virtual fixed point In the case of a pile of finite length, the error can be ignored even if the pile is calculated as an infinite length.
It is developed that the depth of penetration depth (D) of the pile becomes 3 times (3 / β) or more of the virtual fixed point, it can be interpreted as a fixed end, and it is applied to find the lateral resistance of the foundation design.
The present invention applies the virtual fixed point theory of such a pile (foundation structure) to a retaining structure.
Hereinafter, the effect of the retaining structure according to the present invention will be described with reference to FIGS.
FIG. 4 is a view showing a bending moment diagram of a retaining structure supported by an earth anchor at one point without satisfying a fixed end condition, and FIG. 5 is a view showing a design earth pressure distribution diagram of a conventional retaining structure supported by a plurality of anchors It is.
Since the penetration depth (D) of the supporting pile is not more than 3 times (3 / β) of the virtual fixing point in the conventional retaining structure, the bottom of the pile is designed and analyzed as a hinge end instead of a fixed end.
In addition to the conventional retaining structure is applied in view of the large bending moment generated on the support peg because of the support of a number of anchors, the proposed pack earth pressure Terzaghi and Peck as shown in Fig. 5 (P Peck) to design earth pressure, which equation 2. ≪ / RTI >
P peck : Pack earth pressure
K a : Main earth pressure factor
γ: Unit weight of soil
H: Excavation depth
FIG. 6 shows a bending moment diagram of the earth retaining structure according to the present invention, and FIG. 7 shows a design earth pressure distribution diagram of the earth retaining structure to which the present invention is applied.
The support pile of the retaining structure according to the present invention is designed and designed not as a hinge but as a fixed end because the penetration depth (D) of the pile is 3 times (3 /?) Or more of the virtual fixed point.
In the present invention, since the
Taken together, the
In addition, in the conventional retaining structure, since the penetration portion of the pile is analyzed as a hinge structure, only a positive (+) moment is generated in the supporting pile, so that it is required that the resistance of the wall and the tensile member is large (FIG. 4) (+) Moment generated by main-side earth pressure is compensated by the negative moment generated at the virtual fixed point because a small design load is applied as described above and a virtual fixed point is formed in the near portion of the support pile. So that the resistance of the wall and the tensile member may be relatively small (Fig. 6).
As described above, since the present invention minimizes the force acting on the
Therefore, even when it is difficult to secure a sufficient space on the back surface of the wall, it is possible to stably install a tensile material such as an earth anchor or a soil nail.
The
The upper end of the
Since the conventional earth anchor method is a method of supporting through the
Here, it is advantageous in terms of structural stability that the center line of the support pile 100 and the
Hereinafter, an embodiment of a method of constructing the earth retaining structure according to the present invention will be described.
The support pile 100 is formed by the
The support pile 100 is inserted into the ground so as to satisfy the penetration depth D.
A hinge part (200) is formed at the upper end of the supporting pile (100).
In the case of the above embodiment, the
The
The upper end of the earth anchor or the soil nail passes through the
The soil retaining structure is installed to be supported by the support pile 100, and the ground in the inner area is excavated.
It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention as defined in the appended claims. It is to be understood that both the technical idea and the technical spirit of the invention are included in the scope of the present invention.
10: pile 20: anchorage
30: Earth anchor 40: Wale
100: Support pile 200: Hinge section
210: Cap beam 211: Insertion hole
220: fixing part 300: tensile material
H: maximum excavation depth D: penetration depth
Claims (8)
(3/3) of the virtual fixed point (1 /?) Based on the maximum excavation depth (H) of the ground in order to form all or a part of the plurality of piles (10) / [beta]) or more at a penetration depth (D);
A hinge part 200 formed at the upper end of the supporting pile 100 so as to form a hinged end;
A tensile material 300 inserted into the hinge portion 200 such that the upper end thereof is engaged and the lower end thereof is inclined downward to the backside gravel-
Wherein the retaining structure comprises:
Wherein the virtual fixed point (1 /?) Is calculated by the following equation (1).
[Equation 1]
k H : horizontal soil reaction force coefficient
D: Diameter of the support pile 100
EI: Flexural Stiffness of Support Pile (100)
Wherein the tensile material (300) is an earth anchor or a soil nail.
Wherein an angle of inclination (θ) between the tension member (300) and the horizontal plane is 50 to 80 °.
The hinge unit (200)
A cap beam 210 coupled to an upper end of the support pile 100 and having an opposite end extending in the horizontal direction of the back side of the support pile 100 and coupled with an upper end of the tension member 300;
Wherein the retaining structure comprises:
An insertion hole 211 is formed in the cap beam 210 so as to be inclined to insert the tensile material 300,
Wherein an upper end of the tensile material is passed through the insertion hole and is fixed to the cap beam by a fixing unit.
(3 /?) Of the virtual fixing point (1 /?) With respect to the maximum excavation depth (H) of the ground, the lower end of the supporting pile (100) (D);
(100) on the ground to satisfy the penetration depth (D);
Forming the hinge part (200) on the upper end of the supporting pile (100);
A step of attaching the tensile material 300 such that the upper end of the hinge unit 200 is engaged and the lower end of the hinge unit 200 has a downwardly inclined structure toward the rear surface soil material side;
Installing the earth retaining structure to be supported by the support pile (100), and excavating the ground in the inner region;
Wherein the method comprises the steps of:
(3 /?) Of the virtual fixing point (1 /?) With respect to the maximum excavation depth (H) of the ground, the lower end of the supporting pile (100) (D);
(100) on the ground to satisfy the penetration depth (D);
Installing the cap beam (210) on the upper end of the support pile (100);
The upper end of the tensile material 300 passes through the insertion hole 211 of the cap beam 210 and is fixed to the cap beam 210 by the fixing unit 220, (300) so as to have a downwardly inclined structure toward the back surface gravel side;
Installing the earth retaining structure to be supported by the support pile (100), and excavating the ground in the inner region;
Wherein the method comprises the steps of:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150179175A KR20160002620A (en) | 2015-12-15 | 2015-12-15 | Soil retaining wall and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150179175A KR20160002620A (en) | 2015-12-15 | 2015-12-15 | Soil retaining wall and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20160002620A true KR20160002620A (en) | 2016-01-08 |
Family
ID=55170504
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020150179175A KR20160002620A (en) | 2015-12-15 | 2015-12-15 | Soil retaining wall and construction method thereof |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20160002620A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2017119775A1 (en) | 2016-01-08 | 2017-07-13 | 주식회사 엘지화학 | Battery pack |
WO2020021294A1 (en) * | 2018-07-26 | 2020-01-30 | Sepac Zvonimir | Retaining engineering structure and design method for stabilizing deep excavations or earth slope instability near existing civil objects |
CN111199070A (en) * | 2020-01-27 | 2020-05-26 | 贵州星隆迪岩土工程有限公司 | Design method of pile-supported two-layer retaining wall |
KR102267289B1 (en) * | 2020-09-09 | 2021-06-18 | 이태곤 | Head-Fixed Retaining Wall and Construction Method Thereof |
KR102636650B1 (en) | 2023-03-22 | 2024-02-15 | 주식회사 지오불스 | Construction method of earth retaining wall with adjustable anchor angle |
-
2015
- 2015-12-15 KR KR1020150179175A patent/KR20160002620A/en not_active Application Discontinuation
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2017119775A1 (en) | 2016-01-08 | 2017-07-13 | 주식회사 엘지화학 | Battery pack |
WO2020021294A1 (en) * | 2018-07-26 | 2020-01-30 | Sepac Zvonimir | Retaining engineering structure and design method for stabilizing deep excavations or earth slope instability near existing civil objects |
CN111199070A (en) * | 2020-01-27 | 2020-05-26 | 贵州星隆迪岩土工程有限公司 | Design method of pile-supported two-layer retaining wall |
CN111199070B (en) * | 2020-01-27 | 2024-04-26 | 贵州星隆迪岩土工程有限公司 | Design method of pile support two-layer retaining wall |
KR102267289B1 (en) * | 2020-09-09 | 2021-06-18 | 이태곤 | Head-Fixed Retaining Wall and Construction Method Thereof |
KR102636650B1 (en) | 2023-03-22 | 2024-02-15 | 주식회사 지오불스 | Construction method of earth retaining wall with adjustable anchor angle |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20160002620A (en) | Soil retaining wall and construction method thereof | |
KR100969996B1 (en) | Soil retaining method for two rows pile using earth anchor | |
KR100964995B1 (en) | Soil retaining method for two rows pile using raker | |
JP4998646B2 (en) | Connection structure of steel pipe sheet pile and steel sheet pile and its construction method | |
KR20130046061A (en) | Earth retaining wall and method of construction retaining wall using thereof | |
KR101506880B1 (en) | Shoring apparatus | |
JP5031463B2 (en) | Earth retaining wall reinforcement structure and method | |
KR100926300B1 (en) | Foundation structure reinfoeced by pile and the construction method for the same | |
KR20120132818A (en) | Reinforcement structure for soil retaining wall using raker and reinforcement method thereof | |
KR20140015019A (en) | Arch wall shoring structure | |
KR100789209B1 (en) | Land-side protection wall using composite pile connected two piles in a body | |
JP6476095B2 (en) | Reinforced soil integrated precast lattice frame method | |
KR101705785B1 (en) | Apparatus for Supporting Anchor box for Tie-Back Anchor of H-Pipe Pile used in the Panel Retaining Wall Method without Wale and Method for Installing Tie-Back Anchor of H-Pipe Pile without Wale | |
JP2015055085A (en) | Earthquake strengthening method for bridge for preventing bridge fall | |
JP2005213977A (en) | Slope stabilizing technique | |
KR101406865B1 (en) | Extension of foundation structure and constructing method for extension of foundaion structure using the same | |
JP5800765B2 (en) | Rock fall prevention structure | |
KR101212732B1 (en) | Arch tunnel using geometric reaction force block and arch tunnel construction method therefor | |
KR20240022083A (en) | Construction Method of EARTH RETAINING STRUCTURE Supported by Multiple Piles | |
KR101732133B1 (en) | Reinforcement structure for pile and construction method of reinforcement structure for pile using the same | |
KR101690641B1 (en) | Method for constructing retaining wall using precast retaining wall-block having curved surface | |
JP5641563B2 (en) | Reinforced earth wall structure construction method and anchor plate with L-shaped cross section used for reinforcement earth wall structure construction method | |
JP5021049B2 (en) | Reaction device for bottom plate and method for constructing bottom plate | |
JP2010163818A (en) | Method of reinforcing concrete structure | |
JP2017025678A (en) | Reinforcement structure for earth retaining wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
G15R | Request for early opening | ||
E902 | Notification of reason for refusal | ||
E601 | Decision to refuse application |