KR20130011450A - Top pile construction method and its construction mat - Google Patents
Top pile construction method and its construction mat Download PDFInfo
- Publication number
- KR20130011450A KR20130011450A KR1020110072608A KR20110072608A KR20130011450A KR 20130011450 A KR20130011450 A KR 20130011450A KR 1020110072608 A KR1020110072608 A KR 1020110072608A KR 20110072608 A KR20110072608 A KR 20110072608A KR 20130011450 A KR20130011450 A KR 20130011450A
- Authority
- KR
- South Korea
- Prior art keywords
- nonwoven fabric
- top pile
- fixing
- pile
- construction
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
- E02D27/14—Pile framings, i.e. piles assembled to form the substructure
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/48—Piles varying in construction along their length, i.e. along the body between head and shoe, e.g. made of different materials along their length
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0075—Textiles
- E02D2300/0076—Textiles non-woven
Abstract
The present invention is excavated to a predetermined depth for reinforcing the soft ground step of installing the top pile left and right adjacent to the soft ground on which the nonwoven fabric is installed; And filling the quarry through the spaces between the top piles, wherein the top of the nonwoven fabric is provided with a stator to allow the quarry to be filled only inside the nonwoven fabric. It further comprises the step of fixing by using a fixing nail on the upper outer surface of the top of the top pile in the state of raising the edge of the installed nonwoven fabric.
Description
It relates to the construction method of the top pile of the present invention and the finishing member for the construction, more specifically, so that the quarry can be filled only inside the non-woven fabric installed on the bottom surface of the soft ground to install the top pile on the soft ground The present invention relates to a construction method of a top pile that can reduce the use of quarrying and a finishing member for the construction.
In general, the top pile made of concrete is mainly installed on the soft ground to have a stress distribution effect on the ground, and at the same time, it distributes the load and smoothly transfers the ground to reinforce the soft ground.
The top pile used for the purpose of reinforcing the soft ground is to reinforce the soft ground by arranging a plurality of top piles in the plane on the ground, filling the space with aggregates such as gravel (crushed stone), and compacting them. Since the effect appears immediately, it can be easily used as the foundation ground of a building, and thus has the advantage of excellent efficiency and economic efficiency of the ground reinforcement.
On the other hand, the concrete top pile used for this purpose is to pour concrete into a mold (top-type pile) molded in the factory, and then transported to the site for construction, which is very inconvenient in construction.
Therefore, in recent years, instead of manufacturing a top pile in a factory, a construction method that can be manufactured on-site and immediately constructed has been implemented. That is, by first manufacturing the top pile mold in a factory made of synthetic resin, and then placing the mold on the soft ground of the construction site, by pouring concrete to the mold to form the top pile, the production and construction of the file at the same time made It was to lose.
In this way, when installing the cured top pile directly on the soft ground or installing the top pile mold on the soft ground, the surface of the soft ground is uniformly processed (ground leveling process), and then civil engineering such as nonwoven fabric is placed on the ground. Apply the mat for civil engineering (final mat (finishing member) installation process), and install the top or pile pile on the mat so as to be continuously arranged adjacent to the left and right (top pile or pile pile installation process). . At this time, when the top pile mold is provided, concrete is poured into the top pile mold and cured.
Subsequently, by filling the aggregate such as crushed stone through the space formed between each top pile and between the top pile mold, and after the compaction process, by laying concrete on top of the top pile or top pile mold, the foundation concrete layer Form the to complete the construction.
However, in the conventional construction method, when filling aggregates such as crushed stone through spaces formed between top piles or top pile types, as shown in FIG. 6, crushed stone filled at edges S of the soft ground should be used. There is a disadvantage. That is, in the case of the ground leveling process for installing the
Therefore, there is a problem that the amount of use of the crushed
The purpose of the present invention is to vertically erect the edge portion of the nonwoven fabric installed on the bottom surface of the soft ground to install the top pile on the soft ground, so that the quarry can be filled only inside the nonwoven fabric to use the quarry The present invention provides a method for constructing a top pile that can be reduced and a finishing member for the construction.
The construction method of the present invention for achieving the above object, the step of installing the pile pile left and right adjacent to the soft ground excavated to a predetermined depth for the reinforcement of the soft ground is installed nonwoven fabric; And filling the quarry through the spaces between the top piles, wherein the top of the nonwoven fabric is provided with a stator to allow the quarry to be filled only inside the nonwoven fabric. It characterized in that it further comprises the step of fixing by using a fixing nail on the upper outer surface of the top of the top pile in the state of raising the edge of the installed nonwoven fabric.
In addition, the structure of the present invention for achieving the above object, non-woven fabric installed on the bottom of the soft ground excavated to a predetermined depth so as to install the top pile left and right adjacent; And fixing means configured to be fixed to the upper outer surface of the top of the top of the nonwoven fabric in a state in which the edge of the nonwoven fabric is raised so that the quarry can be filled only through the space between the tops of the nonwoven fabric. It is done.
The fixing means is characterized in that consisting of a fixing member installed along the edge of the nonwoven fabric and a fixing nail for fixing the nonwoven fabric provided with the fixing member to the upper outer surface of the top pile.
The present invention by fixing the vertical edge of the nonwoven fabric installed on the bottom surface of the soft ground to install the top pile on the soft ground, so that the quarry can be filled only inside the nonwoven fabric to reduce the amount of quarrying construction cost By saving it has an economic advantage.
1 is a perspective view showing a top pile,
2 is a view showing the construction state of the top pile in plan view,
3 is a view showing a construction state of the top pile,
4 is a view showing the edge portion at the time of construction of the top pile,
5 is an enlarged view of a portion “A” of FIG. 4;
6 is a view showing a construction state of the top pile by the conventional structure.
Hereinafter, with reference to the accompanying drawings will be described more preferred embodiments of the present invention.
As shown, the construction method of the top pile according to the present invention is to excavate to a predetermined depth for the reinforcement of the soft ground to install the top pile (1) adjacent to the left and right adjacent to the soft ground on which the
The fixing step of the top pile (1) in a state in which the
Therefore, the edge portion of the
As shown, the finishing member for the construction of the top pile according to the present invention consists of a
The
The fixing means 20 is a fixing nail (22) for fixing the
According to the present invention, by fixing the edge portion of the nonwoven fabric installed on the bottom surface of the soft ground vertically, the quarry can be filled only to the inside of the nonwoven fabric to reduce the waste of quarrying has an economic advantage.
1-top pile 2-quarrying
10-nonwoven fabric 20-fasteners
22-holder 24-nail
Claims (3)
Using a fixing nail on the top outer surface of the top pile in a state in which a fixing stand is installed at the edge of the nonwoven fabric so that the quarry can be filled only inside the nonwoven fabric, and the edge of the nonwoven fabric provided with the fixing stand is raised. Construction method of the top pile further comprising the step of fixing.
And fastening means configured to be fixed to the top outer surface of the top of the top of the nonwoven fabric in a state in which the edge of the nonwoven is raised so that the quarry can be filled only through the space between the tops of the nonwoven fabric. Finishing member for the construction of the top pile.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020110072608A KR20130011450A (en) | 2011-07-21 | 2011-07-21 | Top pile construction method and its construction mat |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020110072608A KR20130011450A (en) | 2011-07-21 | 2011-07-21 | Top pile construction method and its construction mat |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20130011450A true KR20130011450A (en) | 2013-01-30 |
Family
ID=47840404
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020110072608A KR20130011450A (en) | 2011-07-21 | 2011-07-21 | Top pile construction method and its construction mat |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20130011450A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20170025329A (en) | 2015-08-28 | 2017-03-08 | 이정엽 | Pile having height adjustment function and construction method thereof |
-
2011
- 2011-07-21 KR KR1020110072608A patent/KR20130011450A/en not_active Application Discontinuation
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20170025329A (en) | 2015-08-28 | 2017-03-08 | 이정엽 | Pile having height adjustment function and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101787710B (en) | Integrally-assembled buttressed retaining wall and construction method thereof | |
CN105926803B (en) | A kind of 3D printing reinforced masonry shear wall structure with concave convex texture | |
CN101787708A (en) | Integrally-assembled cantilever-type retaining wall and construction method thereof | |
KR101105092B1 (en) | A precast retaining panel and construction method of the same with half pc type backfill | |
KR100787178B1 (en) | Light weight steel frame foundation flooring material and method for construction | |
CN106164380B (en) | Wind-driven generator fabricated base | |
KR101370102B1 (en) | Cast-in-place type top-pile and construction process of the same | |
CN209907429U (en) | Industrialized dense rib plate type retaining wall | |
CN201746850U (en) | Assembled monolithic cantilever retaining wall | |
CN205669211U (en) | A kind of prefabricated Gravity Retaining Wall | |
KR101021475B1 (en) | Construction method for prefabricated type concrete road using precasted concrete panel | |
CN204940700U (en) | Reverse construction prefabricated post and underground structure | |
KR101111655B1 (en) | method for reinforced of soft ground by using top pile | |
CN207878440U (en) | A kind of reinforcement composite foundation structure suitable for soft soil foundation | |
KR20130011450A (en) | Top pile construction method and its construction mat | |
JP2020197015A (en) | Construction method of foundation | |
CN105133630A (en) | Prefabricated part for constructing foundation forming molds | |
CN106917396B (en) | A kind of taper foundation reinforcement method | |
CN206512546U (en) | A kind of anti-settling pervious surface | |
KR100920688B1 (en) | Structure for reinforced of soft ground by using top pile | |
KR101808833B1 (en) | Floor structure of underground floor with reduced floor height using shear reinforcement and the construction method thereof | |
CN109667278B (en) | Anti-cracking and anti-seepage construction method for arranging tower crane foundation under independent foundation of underground garage | |
CN104131578A (en) | Inverted construction method and structure of bearing platform and base plate of basement under current-formed soils | |
KR100780216B1 (en) | Method for constructing a honeycomb-shaped mat | |
CN103255872A (en) | Hollow building block |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
AMND | Amendment | ||
E601 | Decision to refuse application | ||
AMND | Amendment | ||
E902 | Notification of reason for refusal |