KR20130003868A - Tention typed cable-stayed bridge construction method - Google Patents

Tention typed cable-stayed bridge construction method Download PDF

Info

Publication number
KR20130003868A
KR20130003868A KR1020110065482A KR20110065482A KR20130003868A KR 20130003868 A KR20130003868 A KR 20130003868A KR 1020110065482 A KR1020110065482 A KR 1020110065482A KR 20110065482 A KR20110065482 A KR 20110065482A KR 20130003868 A KR20130003868 A KR 20130003868A
Authority
KR
South Korea
Prior art keywords
deck
segment
main
span
cable
Prior art date
Application number
KR1020110065482A
Other languages
Korean (ko)
Other versions
KR101308992B1 (en
Inventor
노정휘
이상훈
박종헌
이재형
조재영
김병탁
김재범
김도학
Original Assignee
지에스건설 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 지에스건설 주식회사 filed Critical 지에스건설 주식회사
Priority to KR1020110065482A priority Critical patent/KR101308992B1/en
Priority to PCT/KR2011/004957 priority patent/WO2013005877A1/en
Publication of KR20130003868A publication Critical patent/KR20130003868A/en
Application granted granted Critical
Publication of KR101308992B1 publication Critical patent/KR101308992B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: A construction method of a tension type single span cable-stayed bridge is provided to cost-efficiently construct a cable-stayed bridge by changing compressive force applied to a girder into tensile force. CONSTITUTION: A construction method of a tension type single span cable-stayed bridge is as follows. First deck segments are installed to be directly supported to two towers(110) separated from each other using inclined cables. Multiple deck segments are consecutively installed on the first deck segments using additional inclined cables. When the deck segments to be connected to each other are adjacent to each other, jacks(200) are installed between the towers and the first deck segments. Key segments(400) are arranged between the deck segments to be connected to each other, and the installed jacks are powered to continuously connect the deck segments to each other. Tensile force is applied to the connected deck segments. [Reference numerals] (AA) First step; (BB) Second step; (CC) Third step; (DD) Fourth step

Description

단경간 인장형 사장교 시공방법{TENTION TYPED CABLE-STAYED BRIDGE CONSTRUCTION METHOD}Construction method for short span tensile cable-stayed bridge {TENTION TYPED CABLE-STAYED BRIDGE CONSTRUCTION METHOD}

본 발명은 단경간 인장형 사장교 시공방법에 관한 것으로써, 더욱 구체적으로는 양 주탑 사이(주경간)에 거더를 경사케이블로 매달아 설치하는 단경간 사장교에 있어서 거더에 작용하는 압축력을 인장력으로 변환되도록 하는 시공과정을 거쳐 보다 경제적으로 사장교를 시공할 수 있도록 한 단경간 인장형 사장교 시공방법에 관한 것이다.The present invention relates to a method for constructing a short span cable-stayed bridge, and more specifically, to convert the compressive force acting on the girder into a tensile force in a short span cable-stayed bridge in which a girder is suspended by an inclined cable between both main towers (main span). The present invention relates to a short span tensile cable-stayed bridge construction method that enables the construction of a cable-stayed bridge more economically.

일반적으로, 사장교는 주탑에서 경사진 방향으로 설치된 경사케이블을 이용하여 주경간을 지지하는 교량이다.In general, the cable-stayed bridge is a bridge that supports the main span by using the inclined cable installed in the inclined direction from the pylon.

사장교는 주경간의 길이를 길게 할 수 있기 때문에 최근에는 넓은 폭을 가지는 강이나 바다에도 시공되고 있다.Since the cable-stayed bridge can lengthen the main span, it is recently installed in rivers and seas with wide widths.

사장교는 양측 주탑에 데크세그먼트(Deck Segment)를 각각 순차적으로 설치하여 주경간(Main Span)과 측경간(Side Span)을 만들되, 경사케이블을 이용하여 상기 주경간과 측경간의 데크세그먼트가 서로 연결되도록 한다.The cable-stayed bridge is installed on both sides of the sequential deck (segment) in order to make the main span (Span) and side span (Side Span), but using the inclined cable so that the deck segment between the main span and the side span are connected to each other.

이에 따라, 서로 연결된 양측의 데크세그먼트에는 수평 방향으로 압축력이 작용하게 된다.Accordingly, the compressive force acts in the horizontal direction on the deck segments on both sides connected to each other.

즉, 도 1a와 같이, 경사케이블(1)이 주탑(3) 양쪽의 데크세그먼트(2)를 서로 연결하기 때문에 경사케이블(1)이 작용하는 힘 중에서 수평방향 분력(F21)은 데크세그먼트(2)에 압축력으로써 작용하고 수직방향 분력(F11)은 상측으로 작용하게 된다.That is, as shown in FIG. 1A, since the inclined cable 1 connects the deck segments 2 on both sides of the main column 3 to each other, the horizontal component F21 is the deck segment 2 among the forces acting on the inclined cable 1. ) Acts as a compressive force and the vertical component force F11 acts upward.

상기 압축력은 주탑(3)이 설치된 곳(M)에서 최대로 되고 주경간(Main Span)의 중앙 지점(C)에서 제로(힌지연결)가 된다.The compressive force is maximized at the place (M) where the main tower (3) is installed and zero (hinge connection) at the center point (C) of the main span (Main Span).

이는 주탑으로부터 데크세그먼트(2)의 설치가 시작됨에 따라 작용하는 압축력이 데크세그먼트(2)에 누적되어 증가되기 때문이다.This is because the compressive force acting as the installation of the deck segment 2 from the pylon starts to accumulate and increase in the deck segment 2.

이에 상기 데크세그먼트(2)에 작용하는 최대 압축력은 주경간의 길이(L) 즉, 주탑(3) 사이의 거리에 비례하여 커진다.Accordingly, the maximum compressive force acting on the deck segment 2 increases in proportion to the length L between the main spans, that is, the distance between the main towers 3.

도 1b는 상기 최대 압축력과 주경간 길이(L) 사이의 관계를 보여주는 그래프로서, 주경간의 데크세그먼트(2)의 단면적이 일정하다는 가정(Assumption)하에 만들어진 것이다.1B is a graph showing the relationship between the maximum compressive force and the main span length L, and is made under the assumption that the cross-sectional area of the deck segment 2 between the main spans is constant.

즉, 예컨대 주경간의 길이(L)가 1000m인 경우에 160MPa이던 최대 압축력이 주경간의 길이(L)가 2000m가 되면 500MPa이 됨을 알 수 있다.That is, for example, it can be seen that the maximum compressive force of 160 MPa when the length L of the main span is 1000 m is 500 MPa when the length L of the main span becomes 2000 m.

이에 이러한 압축력의 증가에 대응하기 위해서 데크세그먼트(2)는 고강도 강(Higher Strength Steel)을 사용하거나 단면적을 증가시켜야 한다는 문제점이 있었다.Accordingly, in order to cope with such an increase in compressive force, the deck segment 2 has a problem of using high strength steel or increasing the cross-sectional area.

또한 강재로 제작되는 데크세그먼트는 압축력에 의한 좌굴 및/또는 뒤틀림을 보완하기 위하여 스티프너 형태 등의 국부좌굴방지재가 많이 소요되는데 이러한 국부좌굴방지재의 사용으로 인하여 데크세그먼트의 자중이 증가할 수 밖에 없고, 그 제작 및 설치비용에 의하여 사장교의 공사비가 증가되는 문제점이 있었다.In addition, the deck segment made of steel requires a lot of local buckling materials such as stiffeners to compensate for buckling and / or twisting due to compressive force, and the weight of the deck segment must increase due to the use of such local buckling materials. There was a problem that the construction cost of the cable-stayed bridge is increased by the manufacturing and installation costs.

도 1c는 종래 단경간 사장교의 예를 도시한 것이다.Figure 1c shows an example of a conventional short span cable-stayed bridge.

즉, 단경간 사장교(10)의 경우에는 통상의 사장교과 비교할 때 도 1a와 같은 측경간이 없으므로 주탑(11)의 양쪽이 비대칭이 된다.That is, in the case of the short span cable-stayed bridge 10, both sides of the main column 11 are asymmetrical as there is no side span as shown in FIG.

따라서 종래의 기술에 따르면 거더(12,데크세그먼트가 서로 연결되어 완성된 것)의 수직방향 분력(F11)에 해당하는 하중은 경사케이블(13)에 의하여 지지되며, 거더(12)의 축력(F1)은 거더(12)가 강결되는 주탑(11)이 지지하도록 시공된다.Therefore, according to the prior art, the load corresponding to the vertical component force F11 of the girder 12 (the deck segments connected to each other) is supported by the inclined cable 13, and the axial force F1 of the girder 12 ) Is constructed so that the main column 11 to which the girder 12 is rigid is supported.

이로써 주탑(11)은 상부에 걸쳐지는 다수의 경사케이블(13)에 의한 하방 연직력(F2)을 받으면서 동시에 하부에 강결되는 거더(12)로부터의 수평방향 축력(F1)을 동시에 받게 된다.As a result, the main tower 11 receives the vertical vertical force F2 by the plurality of inclined cables 13 across the top, and simultaneously receives the horizontal axial force F1 from the girder 12 that is rigidly tightened to the lower portion.

이에 종래의 기술에 따른 단경간 사장교(10)에서 주탑(11)은 경사케이블(13)이 걸쳐진 상부에서 발생되는 수평방향의 축력(F3)과, 거더가 강결된 하부에서의 축력(F1)으로 인하여 휨 모멘트를 받게 되어 활 모양으로 휘게 되어 불안전한 구조를 갖게 되므로 거더의 축력(F1)들에 의하여 발생되는 휨 모멘트에 저항 하기위하여 주탑하부의 기초(14)를 매우 크도록 설계하여야 하고, 이에 따라 경제성이 떨어지는 단점이 있었다.In the short span cable-stayed bridge 10 according to the prior art, the main column 11 has a horizontal axial force (F3) generated in the upper portion over which the inclined cable 13 spans, and an axial force (F1) in the lower portion where the girder is hardened. Due to the bending moment is bent in a bow shape to have an unstable structure, the base 14 of the pylon should be designed to be very large to resist the bending moment caused by the axial forces (F1) of the girder, so As a result, the economy was inferior.

이러한 단경간 사장교의 단점을 극복하기 위한 단경간 사장교가 도 1d 및 도 1e에 소개되어 있다.Short span cable stayed bridges for overcoming the shortcomings of the short span cable stayed bridges are introduced in FIGS. 1D and 1E.

즉, 주탑(11)의 일측으로 연장된 거더(12)를 경사케이블(13)로 지지하는 단경간 사장교에 있어서, 상기 주탑(11)과 상기 거더(12)는 서로 분리되어 있고, 상기 거더의 축력(F1)은 앵커리지블럭(15)에 설치되는 것으로서 거더의 단부를 지지하는 반력벽(16)에 지지되도록 한 것이다(반력 작용).That is, in the short span cable-stayed bridge supporting the girder 12 extending to one side of the main column 11 with the inclined cable 13, the main column 11 and the girder 12 are separated from each other, The axial force F1 is provided in the anchorage block 15 so as to be supported by the reaction wall 16 supporting the end of the girder (reaction action).

이에 거더와 주탑을 분리함으로써 거더에서 전달되는 축력(F1)을 배제하여, 주탑에 발생하는 휨 모멘트를 줄여 주탑의 안전성이 증대되는 효과를 가지도록 한 것이다.Thus, by separating the girder and the pylon to remove the axial force (F1) transmitted from the girder, to reduce the bending moment generated in the pylon to have the effect of increasing the safety of the pylon.

이에 주탑의 기초블록(14)을 과대하게 크게 시공할 필요가 없게 되어 경제성을 확보할 수 있게 되는 효과도 갖는다.Therefore, the foundation block 14 of the pylon does not need to be excessively large, so that economic efficiency may be obtained.

한편, 거더의 축력(F1)을 받는 반력벽(16)을 앵커리지블록(15)에 형성하는 경우에 거더의 측력과 앵커리지블록의 축력이 상쇄됨으로써 단경간 사장교의 안전성이 더욱 증대되는 효과도 가지게 된다.On the other hand, when the reaction force wall 16 receiving the axial force (F1) of the girder is formed in the anchorage block 15, the side force of the girder and the axial force of the anchorage block are canceled to have an effect of further increasing the safety of the short span cable-stayed bridge. .

하지만 이러한 단경간 사장교에 있어서 근본적인 문제점은 거더에 역시 압축력이 누적되면서 거더의 단면이 커짐과 더불어 이에 따른 국부좌굴방지재의 많은 사용으로 인하여 데크세그먼트의 자중이 증가할 수 밖에 없고, 그 제작 및 설치비용에 의하여 사장교의 공사비가 증가된다는 점이다.However, the fundamental problem in the short-span cable-stayed bridge is that as the compressive force accumulates in the girders, the cross section of the girders increases and the weight of the deck segment increases due to the use of local buckling prevention materials. The construction cost of the cable-stayed bridge is increased.

따라서 종래 단경간 사장교에 있어 거더에 작용하는 압축력인 축력을 감소시키는 것은 매우 중요한 의미를 가지게 됨을 알 수 있다.Therefore, it can be seen that reducing the axial force, which is a compressive force acting on the girder, has a very important meaning in the conventional short span cable-stayed bridge.

이에 상기 종래 단경간 사장교의 거더에 있어 작용하는 압축력(F1)의 분포를 도 1f를 기준으로 살펴보면 다음과 같다.Thus, the distribution of the compressive force (F1) acting on the girder of the conventional short span cable-stayed bridge is as follows with reference to Figure 1f.

즉, 상기 도 1f에 의하면 주경간에 걸쳐 양 단부는 매우 압축력이 커지고 중앙부는 힌지연결에 의하여 압축력이 발생하지 않음을 알 수 있다.That is, according to FIG. 1f, it can be seen that the compressive force is very large at both ends over the main span and the compressive force is not generated by the hinge connection at the center portion.

이에 종래 단경간 사장교도 역시 다경간 사장교와 마찬가지로 주경간에 걸쳐 압축력이 거더 단면을 지배하는 구조로 되어 있음을 알 수 있으며, 이로서 주경간이 커지게 되면 압축력에 지배되는 거더의 단면적이 커질 수 밖에 없어 거더의 국부좌굴방지를 위한 보강문제가 항상 대두될 수 밖에 없다는 문제점이 여전히 지적되었다.Therefore, the conventional short span cable-stayed bridge also has a structure in which the compressive force dominates the cross section of the girder over the main span, similarly to the multi-span cable-stayed bridge, and as the main span increases, the cross-sectional area of the girder which is governed by the compressive force becomes large. It is still pointed out that reinforcement problems to prevent local buckling always arise.

본 발명은 상기 문제점들을 해결하기 위해 고안된 것으로서The present invention is designed to solve the above problems.

본 발명의 목적은 단경간 사장교를 시공함에 있어 주경간에 경사케이블에 의하여 매달려 지지되는 데크세그먼트를 제작함에 있어 데크세그먼트 단면설계의 최적화를 유도함으로서 상기 압축력에 의한 국부좌굴에 저항하기 위한 국부좌굴방지재의 최소화를 통해 보다 경제적인 단경간 사장교를 시공하기 위한 것이라 할 수 있다.An object of the present invention is to provide a local buckling prevention material for resisting local buckling by the compressive force by inducing the optimization of the deck segment cross-sectional design in the manufacture of the deck segment that is supported by the inclined cable in the main span in the construction of the short span cable-stayed bridge It can be said to build a more economical short span cable-stayed bridge through minimization.

이에 본 발명에 의한 단경간 사장교는 동일한 데크세그먼트 단면이라면 보다 장경간(주경간의 길이가 길어짐)의 사장교를 시공할 수 있게 되며, 동일한 경간장(주경간)이라면 보다 경제적인 데크세그먼트 단면 설계가 가능하여 경제적인 단경간 인장형 사장교 제공이 가능하도록 하는 것을 그 해결하고자 하는 기술적 과제로 한다.Therefore, the short span cable-stayed bridge according to the present invention can be constructed with a longer span (longer length) cable stayed bridge if the same deck segment cross section, and the economical deck segment cross section can be more economical if the same span length (main span) is possible. It is a technical problem to be solved that it is possible to provide a short span tensile cable-stayed bridge.

전술한 바와 같이, 기존의 단경간 사장교는 주탑이 있는 곳에서 최대 압축력이 발생하고 상기 최대 압축력은 주경간의 길이가 길어질수록 커진다. As described above, in the existing short span cable-stayed bridge, the maximum compressive force is generated where the pylon is located, and the maximum compressive force increases as the length of the main span becomes longer.

이에 따라 주경간의 길이가 길어질수록 주경간의 데크세그먼트의 단면을 보강하기 위해서 주경간의 데크세그먼트의 단면이 커지거나 국부좌굴방지를 위한 고강도 강(Higher Strength Steel)이 사용되어야 하기 때문에 주경간의 길이가 길어지게 되면 사장교의 경제성이 떨어질 수 밖에 없다.Accordingly, as the length of the main span increases, the cross section of the main segment between the main span increases in order to reinforce the cross section of the deck segment between the main span, or the length of the main span increases due to the use of high strength steel to prevent local buckling. If the economics of the cable-stayed bridge will fall.

이에 본 발명은 The present invention

교축방향으로 서로 이격되어 설치된 양 주탑에 직접 지지되도록 최초 데크세그먼트를 경사케이블을 이용하여 설치하는 제 1단계;A first step of installing the first deck segment by using an inclined cable so as to be directly supported by both main towers spaced apart from each other in the axial direction;

상기 최초 데크세그먼트에 다수의 데크세그먼트들을 주경간 중앙부(C)로 다수 연속하여 추가 경사케이블을 이용하여 설치하는 제 2단계;A second step of installing a plurality of deck segments in the first deck segment by using a plurality of consecutively inclined cables to a central portion C of the main span;

상기 주경간 중앙부(C)에서 서로 연결될 데크세그먼트가 인접하면 상기 주탑과 최초 데크세그먼트 사이에 잭을 설치한 후 상기 서로 연결될 데크세그먼트 사이에 키세그를 배치하고, 상기 잭을 작동시켜 연결될 데크세그먼트에 키세그가 접근하면 서로 강결 연결시켜 데크세그먼트를 연속화시키는 제 3단계; 및When the deck segments to be connected to each other in the main span center portion C are adjacent to each other, a jack is installed between the main tower and the first deck segment, and a key segment is disposed between the deck segments to be connected to each other, and the jack is operated to be connected to the deck segment to be connected. A third step of sequencing the deck segment by tightly connecting each other when the segment approaches; And

상기 주탑과 최초 데크세그먼트 사이에 설치된 잭을 작동전 상태로 서서히 복원시켜 주경간 중앙부 반대방향으로 벌어진 주탑이 주경간 중앙부쪽으로 이동하면서 연결된 데크세그먼트에 인장력이 도입되도록 하는 제 4단계를 포함하는 인장형 단경간 사장교 시공방법을 제공하게 된다.Tensile type short span including a fourth step to gradually restore the jack installed between the main tower and the first deck segment to the state before operation so that the main tower opened in the opposite direction to the center of the main span is moved toward the center of the main span, the tensile force is introduced to the connected deck segment. It will provide the construction method of the cable-stayed bridge.

즉, 본 발명은 데크세그먼트에 작용하는 누적된 압축력을 데크세그먼트와 주탑 사이에 설치된 잭을 통해 주탑이 직접 저항하도록 하여 주경간 중앙부 반대방향으로 주탑이 벌어지도록 하고, 상기 잭을 서서히 복원시킴에 따라 벌어진 주탑이 다시 주경간 중앙부쪽으로 이동하면서 잭을 통해 데크세그먼트에 인장력이 도입되도록 하여 상기 압축력이 상쇄되도록 한 것이다.That is, the present invention allows the main tower directly resists the accumulated compressive force acting on the deck segment through the jack installed between the deck segment and the main tower so that the main tower is opened in the opposite direction to the center of the main span, and the jack is gradually restored. As the pylon moves back toward the center of the main span, the compressive force is canceled by introducing a tension force into the deck segment through the jack.

또한 데크세그먼트와 주탑 사이에 추가로 설치되는 교축방향 댐퍼를 이용하여 시공과정 등에 있어 데크세그먼트의 안전성 및 지진하중에 대한 저항능력을 확보하도록 하고,In addition, by using the axial damper additionally installed between the deck segment and the main column to ensure the safety of the deck segment and resistance to earthquake loads in the construction process,

상기 데크세그먼트의 종방향 거동을 제어하면서 부반력을 제어하도록 링크슈를 설치함으로서, 장경간의 단경간 인장형 사장교를 시공함에 있어 안전성과 경제성을 충분히 확보할 수 있도록 하였다.By installing a link shoe to control the side reaction force while controlling the longitudinal behavior of the deck segment, it was possible to secure sufficient safety and economics in the construction of a short span long cable-stayed bridge between long spans.

본 발명에 의한 단경간 인장형 사장교는Short span tensile cable-stayed bridge according to the present invention

첫째, 종래 단경간 사장교의 경우 주경간에 설치되는 데크세그먼트는 압축력(일종의 축력)이 지배적이기 때문에 이러한 지배적인 압축력에 대응하는 단부세그먼트의 단면 설계가 필요하게 되고, 나아가 압축력에 취약한 단부세그먼트 내부에 다수의 국부좌굴방지재를 설치해야 했지만, 본 발명의 단경간 사장교에 있어서는 시공과정에서 단부세그먼트에 압축력을 상쇄하는 인장력이 발생하게 되므로 발생하는 압축력이 크기가 감소하여 단부세그먼트의 단면을 최적화(단부세그먼트를 구성하는 상부,하부플랜지 양 측벽부의 강재 사용량 절감 등)하여 강재로 제작하는 단부세그먼트의 제작비용 및 시공비용을 절감할 수 있을 뿐만 아니라, 상기 단부세그먼트에 설치해야 하는 국부과굴방지재의 사용량을 현저하게 감소시킬 수 있어 매우 경제적인 단경간 사장교 시공이 가능하게 된다.First, in the case of the conventional short span cable-stayed bridge, since the deck segment installed in the main span is dominant in compression force (a kind of axial force), it is necessary to design a cross section of the end segment corresponding to the dominant compression force, and moreover in the end segment that is vulnerable to the compression force. Although the local buckling prevention material of the present invention had to be installed, in the short span cable-stayed bridge of the present invention, since the tensile force to cancel the compressive force is generated in the end segment during the construction process, the compressive force generated is reduced in size to optimize the cross-section of the end segment (end segment). To reduce the amount of steel used in the upper and lower flanges of both sidewalls, and to reduce the manufacturing cost and construction cost of the end segment manufactured from steel, as well as to significantly reduce the amount of local anti-fogging material to be installed in the end segment. Very economical This construction is made possible between the cable-stayed bridge.

둘째, 단경간 사장교의 시공 이후 교통하중, 풍하중 등의 활하중에 의해서 사장교에는 추가 압축력이 발생하게 되는데 이러한 추가 압축력도 단부세그먼트에 단면설계에 반영되어 결국 데크세그먼트의 자중을 증가시키는 요인이 된다. 하지만 본 발명의 경우에는 상기 추가 압축력도 본 발명에 의한 인장력에 의하여 상쇄될 수 있어 시공과정에서 발생하는 압축력 뿐만 아니라 시공후 과정에서 발생하는 활하중에 의한 압축력도 제어할 수 있어 보다 효율적이고 경제적인 사장교 시공이 가능하게 된다.Second, after the construction of the short span cable-stayed bridge, additional compressive force is generated in the cable-stayed bridge due to live loads such as traffic load and wind load. This additional compressive force is also reflected in the cross-sectional design of the end segment, which eventually increases the weight of the deck segment. However, in the case of the present invention, the additional compressive force may be offset by the tensile force according to the present invention to control not only the compressive force generated in the construction process but also the compressive force due to the live load generated in the post-construction process. Construction is possible.

셋째, 결국 본 발명에 의한 단경간 사장교는 단부세그먼트의 최적화 단면설계로 동일 경간 기준이라면 단부세그먼트 제작비용 및 시공비용이 절감될 수 있어 보다 경제적인 사장교 시공이 가능하게 되며, 동일 단부세그먼트라면 보다 장경화된 장경간 사장교 시공이 가능하게 된다.Third, the short span cable-stayed bridge according to the present invention can reduce the end segment production cost and construction cost if it is the same span standard by optimizing the sectional design of the end segment, so that the construction of the cable-stayed bridge can be more economical. The construction of the long span cable-stayed bridge will be possible.

도 1a는 종래 기술에 따른 사장교의 정면도 및 작용하는 압축력의 형태를 보여주는 력도,
도 1b는 사장교에서 주경간의 길이(L)와 주경간의 데크세그먼트에 발생하는 최대 압축력의 관계를 보여주는 그래프,
도 1c는 종래 단경간 사장교의 힘 분력도,
도 1d 및 도 1e는 종래 개량 단경간 사장교의 시공도,
도 1f는 종래 개량 단경간 사장교의 하중작용도,
도 2는 본 발명의 단경간 인장형 사장교의 시공도,
도 3a, 도 3b, 도 3c 및 도 3d는 본 발명에 의한 단경간 인장형 사장교의 시공순서도 및 이에 따른 축력도,
도 4a 및 도 4b는 본 발명의 주탑 주두부 시공도이다.
Figure 1a is a force diagram showing the front view of the cable-stayed bridge according to the prior art and the form of the acting compression force,
Figure 1b is a graph showing the relationship between the length (L) of the major span in the cable-stayed bridge and the maximum compressive force generated in the deck segment between the main span,
1c is a force component diagram of a conventional short span cable-stayed bridge,
1D and 1E are construction drawings of a conventional improved short span cable-stayed bridge,
1f is a load action diagram of a conventional improved short span cable-stayed bridge,
2 is a construction of the short span tensile cable-stayed bridge of the present invention,
3a, 3b, 3c and 3d is a construction sequence diagram of the short-span tensile cable-stayed bridge according to the present invention and the resulting axial force diagram,
4a and 4b is a construction of the main column head tofu of the present invention.

이하, 첨부된 도면들을 참조로 본 발명에 대해서 상세히 설명하기로 한다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정해서 해석되어서는 아니되며, 발명자는 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다. 따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 실시예들에 불과할 뿐이고 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들을 대체할 수 있는 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings. Prior to this, terms or words used in the specification and claims should not be construed as having a conventional or dictionary meaning, and the inventors should properly explain the concept of terms in order to best explain their own invention. Based on the principle that can be defined, it should be interpreted as meaning and concept corresponding to the technical idea of the present invention. Therefore, the embodiments described in the present specification and the configurations shown in the drawings are merely examples of the present invention and are not intended to represent all of the technical ideas of the present invention, so that various equivalents And variations are possible.

도 2는 본 발명에 의한 단경간 인장형 사장교의 축력도 및 단부세그먼트의 횡단면도를 도시한 것이다.Figure 2 shows the axial force diagram and the cross-sectional view of the end segment of the short span tensile cable-stayed bridge according to the present invention.

먼저, 본 발명에 의한 사장교(100)는 종래 단경간 사장교와 같이 주탑(110)이 교축방향(종방향)으로 서로 이격되어 설치되며 주탑 사이의 이격거리가 주경간이 된다.First, the cable-stayed bridge 100 according to the present invention is installed with the main towers 110 spaced apart from each other in the axial direction (longitudinal direction), as in the conventional short span cable-stayed bridge, and the separation distance between the main towers is the main span.

이러한 주경간 사이에 데크세그먼트(120)가 설치되는데 이러한 데크세그먼트는 주탑 외측으로 각각 설치된 앵커리지블럭(130)에 경사케이블(300)의 일 단부가 고정되며 주탑(110) 상단을 경유하여 타 단부는 데크세그먼트(120)에 연결되도록 설치됨을 종래 단경간 사장교와 동일하다.Deck segments 120 are installed between the main spans. The deck segments are fixed to one end of the inclined cable 300 to the anchorage blocks 130 installed to the outside of the main tower, and the other ends of the decks are passed through the top of the main tower 110. Installed to connect to the segment 120 is the same as the conventional short span cable-stayed bridge.

이때 주탑(110)에 하부에 설치되는 데크세그먼트(120)는 세그먼트를 각 주탑으로부터 경사케이블(300)로 지지하면서 주경간 중앙부(C)로 연속하여 연결 설치하게 되며 이는 FCM(Free Cantilever Method) 공법과 같은 종래 시공방법에 의하여 서로 연속 연결 설치할 수 있을 것이다.At this time, the deck segment 120 installed at the lower part of the main tower 110 is connected to the main section (C) of the main span continuously while supporting the segments with the inclined cable 300 from each main tower, which is the FCM (Free Cantilever Method) method. By the same conventional construction method it will be possible to install continuously connected to each other.

이에 경사케이블(300)에 의하여 주경간 중앙부(C)에서 서로 데크세그먼트가 서로 키세그에 의하여 강결되어 연결되기 이전까지는 데크세그먼트(120)에 압축력이 누적되어 발생하게 된다.Accordingly, the compressive force accumulates in the deck segment 120 until the deck segments are rigidly connected to each other by the key segments in the central span C by the inclined cable 300.

하지만 도 3d와 같이 주탑과 최초 데크세그먼트 사이에 설치된 잭을 작동전 상태로 서서히 복원시키는 과정(제 4단계)에서 주경간 중앙부 반대방향으로 벌어진 주탑이 주경간 중앙부쪽으로 이동하면서 연결된 데크세그먼트에 인장력(T)이 도입된다.However, in the process of gradually restoring the jack installed between the pylon and the initial deck segment to its pre-operation state as shown in FIG. 3d (step 4), the pylon, which is opened in the opposite direction to the center of the main span, moves toward the center of the main span, while the tension (T) is connected to the connected deck segment. This is introduced.

이러한 인장력(T)은 동일한 조건의 종래 단경간 사장교에 작용하는 압축력과 대비하여 절대값이 개략 20%정도 감소하여 데크세그먼트의 단면을 최적화시킬 수 있을 뿐만 아니라, 압축력이 발생하는 데크세그먼트에는 좌굴 및 뒤틀림이 발생하게 되는데 이러한 좌굴 및 뒤틀림에 저항하는 국부좌굴방지재를 데크세그먼트 내부에 설치해야 한다.This tensile force (T) is approximately 20% of the absolute value is reduced compared to the compressive force acting on the conventional short-span cable-stayed bridge under the same conditions as well as to optimize the cross section of the deck segment, the buckling and Twisting occurs, and local buckling resistant materials that resist this buckling and twisting must be installed inside the deck segment.

하지만 본 발명은 상기 압축력이 감소함으로서 도 2와 같이 데크세그먼트를 구성하는 예먼대 상부,하부플랜지, 양측벽부의 두께를 줄일 수 있으며, 국부좌굴방지재(D)의 사용량을 현저하게 절감시킬 수 있어 특히 장경간의 단순 사장교를 시공함에 있어 매우 경제적인 사장교 시공이 가능하게 된다.However, the present invention can reduce the thickness of the upper and lower flanges, both side wall portion constituting the deck segment as shown in Figure 2 by reducing the compressive force, can significantly reduce the amount of local buckling prevention material (D) In particular, it is possible to construct a very economical cable-stayed bridge when constructing a simple cable-stayed bridge between long spans.

이에 어떠한 시공과정을 거처 본 발명의 단경간 인장형 사장교를 시공할 수 있는지 도 3a, 도 3b, 도 3c 및 도 3d를 기준으로 살펴보도록 한다.Therefore, the construction process of the present invention will be described based on FIGS. 3A, 3B, 3C, and 3D to construct the short-span tensile cable-stayed bridge of the present invention.

[제 1단계][Step 1]

먼저, 도 3a 및 도 3c와 같이 양 주탑(110)을 설치하게 되는데 이러한 주탑(110)은 전체적으로 상단으로부터 하부로 내려가면서 양 측벽부(111)로 횡방향으로 벌어지는 형태(예컨대 다이아몬드형)로 형성시키고, 양 측벽부(111)의 하부는 기초(140)에 지지되도록 설치하게 된다.First, both main towers 110 are installed as shown in FIGS. 3A and 3C. The main towers 110 are formed in a shape (for example, diamond type) that is laterally expanded to both side wall portions 111 while descending from the top to the bottom as a whole. And, the lower portion of both side wall portion 111 is installed to be supported on the base 140.

이러한 양 주탑(110)과 기초(140)는 모두 철근콘크리트 구조물로 설치하게 된다.Both main tower 110 and the base 140 are both installed as a reinforced concrete structure.

이에 주탑(110,LEG)은 서로 교축방향으로 서로 이격되어 설치되며 주탑 사이의 간격이 주경간이 됨을 알 수 있다.The main tower (110, LEG) is installed spaced apart from each other in the axial direction and it can be seen that the interval between the main tower is the main span.

이러한 주탑(110)의 양 측벽부(111) 사이에는 최초 데크세그먼트(121)가 교축방향으로 관통하도록 설치되는데 이러한 최초 데크세그먼트(121)는 교량받침(160)에 의하여 지지되도록 가로보(150)를 설치하게 된다.Between the side wall portions 111 of the main tower 110, the first deck segment 121 is installed to penetrate in the axial direction. The first deck segment 121 supports the cross beam 150 to be supported by the bridge support 160. Will be installed.

즉, 서로 횡방향으로 이격된 주탑(110)의 양 측벽부(111) 사이에 횡방향(교축직각방향)으로 가로보(150)를 설치하여 최초 데크세그먼트(121)의 양 단부가 교량받침(160)에 의하여 지지되도록 하고, 상기 가로보(150)에 접속도로용 상판(170)의 거더가 역시 교량받침(160)에 의하여 지지되도록 하게 된다.That is, the horizontal beam 150 is installed in the horizontal direction (orthogonal direction) between both sidewall portions 111 of the main tower 110 spaced apart from each other in the transverse direction so that both ends of the first deck segment 121 are bridged 160. ) And the girder of the upper plate 170 for the road to the cross beam 150 is also supported by the bridge support 160.

이러한 가로보(150)가 설치되는 부위를 지점부 또는 주두부로 지칭하게 된다.The area where the cross beam 150 is installed will be referred to as a point or head.

이때, 상기 최초 데크세그먼트(120)가 관통하는 부위의 양 주탑(110) 정확하게는 양 측벽부(111)의 주경간 중앙부쪽 외측면(I)에는 지지대(180)가 설치된다.At this time, the support column 180 is installed on both sides of the main column 110 of the portion through which the first deck segment 120 penetrates.

이러한 지지대(180)는 강재프레임으로 제작되는 일종의 스트럿(Strut)으로 탈착이 가능하도록 설치하게 된다.The support 180 is installed to be detachable as a kind of strut (Strut) made of a steel frame.

상기 스트럿은 단면이 U형으로 제작되도록 하여 내부에 후술되는 잭(200,Jack)을 안착할 수 있도록 하게 된다.The struts are made to have a U-shaped cross section so that the jack 200 to be described later can be seated therein.

이에 상기 지지대(180)가 설치되면 인접한 최초 데크세그먼트(121)의 양 외측면에 형성시킨 반력대(190)의 단부면에 지지대(180)가 접하도록 하게 된다.Accordingly, when the support 180 is installed, the support 180 is in contact with the end surface of the reaction force 190 formed on both outer surfaces of the adjacent first deck segment 121.

이러한 반력대(190) 역시 강재프레임(또는 강재박스)으로 제작할 수 있으며 주두부에 설치되는 최초 데크세그먼트(121)에만 설치하면 된다.The reaction table 190 may also be manufactured as a steel frame (or steel box) and may be installed only on the first deck segment 121 installed on the main head.

이로서 반력대(190)가 양 외측면에 설치된 최초 데크세그먼트(121)는 앵커리지 블럭(130)에 일단부가 고정되고 주탑(110)의 상단을 경유하여 타단부가 상기 최초 데크세그먼트(121)에 연결되는 경사케이크블(300)에 결국 매달려 설치되도록 있음을 알 수 있다.Thus, the first deck segment 121 having the reaction table 190 installed on both outer surfaces thereof has one end fixed to the anchorage block 130 and the other end connected to the first deck segment 121 via the top of the main tower 110. It can be seen that the inclined cable 300 is finally suspended to be installed.

이 상태에서는 상기 경사케이블(300)에 의하여 최초 데크세그먼트(121)에 축력으로서 압축력이 발생하게 되며, 이러한 압축력은 반력대(190)를 거쳐 지지대(180)를 거쳐 주탑(110)에 의하여 지지된다.In this state, a compressive force is generated as the axial force in the first deck segment 121 by the inclined cable 300, and this compressive force is supported by the main tower 110 via the support 180 through the reaction force 190. .

[제 2단계][Step 2]

다음으로는 도 3b와 같이 상기 주두부에 설치된 최초 데크세그먼트(121)에 추가 경사케이블(300)을 이용하여 주경간 중앙부(C)에 추가 데크세그먼트들(122,123)이 인접할 때까지 연속하여 연결 설치하게 되며 이때까지는 최초 데크세그먼트(121)와 다른 추가 데크세그먼트들(122,123)에 계속해서 압축력이 발생하여 주탑(110)에 전달된다.Next, as shown in FIG. 3b, the additional deck segments 121 and 123 are continuously connected to the central section C by using the additional inclined cable 300 to the first deck segment 121 installed in the main head. Until this time, the compressive force is continuously generated in the initial deck segment 121 and other additional deck segments 122 and 123 and transmitted to the main column 110.

물론 최초 데크세그먼트 이외의 추가 데크세그먼트(122,123)들은 2개로 구분되어 있으나 주경간의 연장길이에 따라 설치개수가 증가될 수 있을 것이며 이에 데크세그먼트들(121,122,123)이 동일한 연장길이를 가지도록 제작되기 때문에 주경간의 연장길이에 맞추어 2개 이상의 다수가 서로 설치될 수 있을 것이다.Of course, the additional deck segments (122,123) other than the initial deck segment is divided into two, but the number of installation may increase according to the extension length of the main span, and the main segments because the deck segments (121, 122, 123) are made to have the same extension length Two or more of the plurality may be installed with each other according to the extension length of.

본 발명에서는 최초 데크세그먼트(121)를 제외하고 연속하여 주경간 중앙부로 연속하여 설치되는 단부세그먼트들(122,123)을 추가 단부세그먼트로 지칭하기로 한다.In the present invention, except for the first deck segment 121, the end segments 122 and 123 which are continuously installed in the center portion of the main span will be referred to as additional end segments.

[제 3단계][Step 3]

다음으로 도 3c와 같이 주경간 중앙부(C)에서 추가 데크세그먼트(123)가 서로 인접하게 되면 서로 강결시켜 연결시키게 되는데 이를 위하여 키세그(400,KEY SEG)가 이용된다.Next, when the additional deck segments 123 are adjacent to each other in the main span center portion C as shown in FIG. 3C, the additional deck segments 123 are firmly connected to each other. For this purpose, a key segment 400 (KEY SEG) is used.

이러한 키세그(400)는 데크세그먼트와 동일한 단면형태로 제작하는 것으로서 서로 인접한 추가 데크세그먼트들(123)를 연결시키기 위한 것이다.The key segment 400 is formed in the same cross-sectional shape as the deck segment and is for connecting additional deck segments 123 adjacent to each other.

상기 키세그(400)는 별도로 사장교 주경간 중앙부 하부에서 미도시된 인양장치로 인양하여 인접한 추가 데크세그먼트(123) 사이에 끼워지도록 세팅하게 된다.The key segment 400 is set to be separately lifted by a lifting device not shown in the lower portion of the main span of the cable-stayed bridge to be inserted between adjacent additional deck segments 123.

이에 상기 키세그(400)와 인접한 추가 데크세그먼트들(123)과 서로 강결 연결시키게 된다.Thus, the key segment 400 and the additional deck segments 123 adjacent to each other are firmly connected to each other.

여기서 강결의 의미는 최초 및 추가 데크세그먼트들이 서로 구조적으로 연속하여 연결되도록 한다는 의미이며, 강재로 제작되는 데크세그먼트들의 연결은 용접, 긴장재에 의한 압착 등의 의미를 모두 포함한다.Here, the meaning of hardening means that the first and additional deck segments are connected to each other structurally in succession, and the connection of the deck segments made of steel includes both the welding and the pressing by the tension material.

하지만 상기 키세그(400)와 인접한 추가 데크세그먼트(123)들은 동일선상에서 서로 정확하게 접하도록 하면서 서로 강결 연결시키기 쉽지 않기 때문에 셋백(SET BACK) 작업을 통해 이격 간격을 조정하게 된다.However, since the key segment 400 and the additional deck segment 123 adjacent to each other are not easily connected to each other while being in exact contact with each other on the same line, the spacing is adjusted through a set back operation.

이를 위해 잭(200)을 설치하게 된다.To this end, the jack 200 is installed.

즉, 상긱 잭(200)의 양 단부를 지지대(180)와 반력대(190) 사이에 탈착이 가능하도록 고정시킨 후, 잭(200)을 작동시켜 셋백(SET BACK)시키게 된다.That is, after fixing both ends of the Sangik jack 200 to be detachable between the support 180 and the reaction force 190, the jack 200 is operated to set back.

즉, 셋백(SET BACK)작업은 잭(200)의 연장길이를 신장시키는 것이 아니라 연장길이를 축소시키는 방향으로 작동시켜 인접한 추가 데크세그먼트(123) 이격 간격을 일시적으로 약간 더 벌어지도록 하여 상기 추가 데크세그먼트 사이에 키세그(400)가 용이하게 끼워져 설치되도록 하기 위함이며 키세그를 설치할 수 있는 정도로 이격 간격을 확보할 수 있으면 셋백은 수행하지 않아도 상관은 없다.That is, the set back operation does not increase the extension length of the jack 200, but operates in the direction of reducing the extension length so that the additional additional deck segment 123 is spaced slightly further apart to temporarily open the additional deck. The key segment 400 is easily inserted between the segments. If the key segment 400 can be secured to a sufficient distance to install the key segment, the setback may not be performed.

이에 상기 셋백(SET BACK) 작업에 의하여 키세그(400)의 위치를 정확하게 세팅되도록 한 이후에는 잭(200)을 셋포워드(SET FOWARD) 작업을 통해 키세그(400)와 추가 데크세그먼트(123)이 동일선상으로 서로 접하도록 한 상태에서 앞서 살펴본 것과 같이 서로 강결시켜 구조적으로 데그세그먼트들이 연속하여 연결되도록 하게 된다.Accordingly, after the position of the key segment 400 is accurately set by the SET BACK operation, the key segment 400 and the additional deck segment 123 are set through the SET FOWARD operation of the jack 200. In the state in which they are in contact with each other in the same line, as shown above, the rigid segments are connected to each other so that the segment segments are continuously connected.

이러한 셋포워드(SET FOWARD) 작업에 의하여 지지대(180)는 도 3d와 같이(제 3단계) 주탑(110)과 반력대(190)로부터 분리된다.The support 180 is separated from the main tower 110 and the reaction table 190 as shown in FIG. 3D by the set forward operation.

상기 셋포워드(SET FOWARD) 작업은 셋백(SET BACK) 작업에 의하여 추가 세그먼트들의 이격 간격이 벌어진 것을 다시 원상 복귀시키면서 키세그(400)와 인접한 데크세그먼트(123)들을 압착되도록 하는 것을 의미한다.The SET FOWARD operation means to compress the deck segment 123 adjacent to the key segment 400 while returning to the original space that the separation interval of the additional segments is opened by the SET BACK operation.

이로서 양 주탑(110)의 주두부로부터 주경간 중앙부로 연장된 데크세그먼트들(120)은 서로 구조적으로 강결되어 연결됨을 알 수 있다.As a result, it can be seen that the deck segments 120 extending from the main heads of both main towers 110 to the main span center portion are structurally rigid and connected to each other.

이러한 제 3단계까지는 데크세그먼트(120)에 압축력(P)이 계속해서 발생되어 단부세그먼트(120)의 반력대(190)을 경유하여, 잭(200)을 통해 주탑(110)에 전달되어 결국 압축력은 주탑(110)이 저항하도록 함을 알 수 있다.Until this third step, the compressive force P is continuously generated in the deck segment 120 and transmitted to the main tower 110 through the jack 200 through the reaction force 190 of the end segment 120, and finally the compressive force. It can be seen that the main column 110 to resist.

[제 4단계][Step 4]

이에 도 3d와 같이 제 3단계에 이후에 설치된 잭(200)을 제거하게 되는데 이러한 잭(200)의 제거는 시간당 개략 1-5CM정도 진행시켜 데크세그먼트들의 안정성을 확보하면서 서서히 셋포워드(SET FOWARD)된 잭을 원상으로 복원시키게 된다.Accordingly, the jack 200 installed after the third step is removed as shown in FIG. 3D. The removal of the jack 200 proceeds approximately 1-5CM per hour, while gradually securing the stability of the deck segments (SET FOWARD). The original jack is restored.

즉, 본 발명은 데크세그먼트(120)에 작용하는 누적된 압축력을 데크세그먼트(120)의 반력대(190)과 주탑(110) 사이에 설치된 잭(200)을 통해 주탑이 직접 저항하도록 하여 주경간 중앙부(C) 반대방향으로 주탑이 벌어지도록 하고,That is, the present invention allows the main tower directly resists the accumulated compressive force acting on the deck segment 120 through the jack 200 installed between the reaction force 190 of the deck segment 120 and the main tower 110. (C) Let the pylons open in the opposite direction,

상기 잭(200)을 서서히 복원시킴에 따라 벌어진 주탑(110)이 다시 주경간 중앙부쪽으로 이동하면서 잭(200)을 통해 데크세그먼트(120)에 인장력(T)이 도입되도록 하여 상기 압축력이 상쇄되도록 한 것이다.By gradually restoring the jack 200, the main column 110, which is opened, moves toward the center portion of the main span again, so that the tensile force T is introduced into the deck segment 120 through the jack 200 so that the compression force is offset. .

이때 도 3d를 기준으로 하면, 주탑(110)은 벌어진 상태에서 주경간 중앙부(C)쪽으로 L1에 대항하는 변위만큼 이동함을 알 수 있다.In this case, based on FIG. 3D, it can be seen that the main tower 110 moves by a displacement against L1 toward the center portion C of the main span in the open state.

이로서 최종 잭(200)은 주탑(110)과 단부세그먼트(120)의 반력대(190) 사이가 충분히 벌어짐에 따라 자연스럽게 분리되게 된다.As a result, the final jack 200 is naturally separated as the gap between the main tower 110 and the reaction table 190 of the end segment 120 is sufficiently widened.

이 과정에서 주탑(110)과 데크세그먼트(120)의 반력대 사이는 이격되면서 안정화 되며, 후술되는 바와 같이 주두부에 설치된 가로보(150)의 교량받침(160)에 최초 데크세그먼트가 지지되어 설치되도록 하게 된다.In this process, the main tower 110 and the reaction force of the deck segment 120 is stabilized while being spaced apart, so that the first deck segment is supported and installed on the bridge support 160 of the cross beam 150 installed in the head as described below. Done.

상기 제 4단계에 의하여 경사케이블(300)에 의하여 매달려 설치되어 서로 강결 연결된 데크세그먼트(120)에는 압축력이 상쇄되도록 하는 인장력(T)의 크기는 주경간에 설치되는 데크세그먼트(120)의 설치개수, 경사케이블(300)의 설치 각도 등 여러 요인에 의해서 조절될 수 있는데 압축력의 크기를 개략 20%정도 상쇄될 수 있을 정도로 세팅하는 경우를 기준으로 할 경우 데크세그먼트(120)의 최적화가 가능하여 매우 경제적인 사장교 시공이 가능하게 됨을 알 수 있었다.The number of installation of the deck segment 120 installed in the main span is the magnitude of the tensile force (T) to be installed in the fourth segment to be suspended by the inclined cable 300 and the rigidly connected deck segment 120 to cancel the compressive force, It can be adjusted by various factors such as the installation angle of the inclined cable 300, but based on the case of setting the size of the compressive force to be offset by approximately 20%, the deck segment 120 can be optimized and very economical Construction of the cable-stayed bridge was realized.

이로서, 본 발명은 데크세그먼트 설치 초기에는 데크세그먼트에 압축력이 발생하게 되지만 주경간 중앙부에서 데크세그먼트를 서로 강결 연결시키고 설치된 잭을 복원시키는 과정에서 데크세그먼트에 압축력을 상쇄하는 인장력이 발생하는 형태가 되기 때문에 종래 최대 압축력에 지배되어 단면설계되는 데크세그먼트와 대비하여 보다 경제적인 단면의 데크세그먼트를 제작할 수 있어 특히 장경간의 단경간 사장교에 매우 유리하게 된다.As such, the present invention is a compression force is generated in the deck segment at the beginning of the deck segment installation, but in the process of restoring the jack installed in the center of the main span between the deck segments and restoring the installed jack, so that the compressive force to the deck segment is generated Compared to the deck segment that is designed to be cross-sectional design dominated by the maximum compressive force in the prior art, it is possible to manufacture a more economical cross-section deck segment is particularly advantageous for long span cable-stayed bridge between long spans.

또한, 사장교 시공 이후에는 차량이 통과하게 되고, 풍하중 등에 의하여 사장교의 강결 연결된 데크세그먼트(120)에는 추가로 압축력이 발생하게 된다.In addition, after the construction of the cable-stayed bridge, the vehicle passes, and additional compressive force is generated in the rigidly connected deck segment 120 of the cable-stayed bridge due to wind load.

이러한 추가 압축력은 데크세그먼트 단면 설계 시 고려되어 데크세그먼트 단면크기에 반영되는데 본 발명은 이러한 추가 압축력을 구속인장력에 의하여 제어할 수 있어 매우 효율적인 사장교 설계 및 시공이 가능하게 된다.This additional compressive force is considered in the deck segment cross-sectional design is reflected in the deck segment cross-sectional size, the present invention can control this additional compressive force by the restraint tensile force it is possible to design and construct a very efficient cable-stayed bridge.

도 4a는 특히 상기 주탑의 주두부에서의 데크세그먼트 설치 상세를 확인할 수 있는데 경사케이블에 의하여 서로 연결된 최초 데크세그먼트(121)는 주두부에 설치된 가로보(150)의 교량받침(160)에 의하여 안착되도록 하고 있음을 알 수 있으며, 접속도로의 상판(170)에 설치된 거더도 역시 가로보(150)의 교량받침(160)에 의하여 안착되어 상기 최초 데크세그먼트(120)와 접속도로의 거더는 서로 신축이음장치(B)에 의하여 서로 연결되어 있음을 알 수 있다.Figure 4a can be confirmed in particular the installation of the deck segment in the main head of the pylon, the first deck segment 121 connected to each other by the inclined cable to be seated by the bridge support 160 of the cross beam 150 installed in the main head. It can be seen that, the girder installed on the upper plate 170 of the access road is also seated by the bridge support 160 of the cross beam 150 so that the first deck segment 120 and the girder of the access road is stretched each other It can be seen that (B) is connected to each other.

이에 본 발명의 데크세그먼트(120)는 잭(200)이 제거 됨에 따라 가로보(150)에 안착되어 안전된 세팅상태를 유지할 수 있게 된다.Thus, the deck segment 120 of the present invention is able to maintain a safe setting state is seated on the cross beam 150 as the jack 200 is removed.

이에 시공 과정에서 풍압 등을 고려할 경우 주탑이 종방향으로 이동이 가능하고 교량이 완성된 이후라도 종방향으로 온도에 의한 이동이 가능하여 다소 불안정해질 수 있다.Therefore, when considering wind pressure in the construction process, the main tower can be moved in the longitudinal direction, and even after the bridge is completed, movement by the temperature in the longitudinal direction can be somewhat unstable.

이에 본 발명은 도 4a와 같이 주탑 주두부의 가로보(150) 상면에 댐퍼(510)를 설치하고 상기 댐퍼(510)는 가로보(150)와 데크세그먼트(120)의 저면에 설치된 지지프레임(520)에 연결되도록 하여 댐퍼(510)가 교축방향으로의 데크세그먼트(120) 이동을 제어할 수 있도록 하게 된다.Thus, the present invention, as shown in Figure 4a, the damper 510 is installed on the upper surface of the main beam main head 150, the damper 510 is the support frame 520 installed on the lower surface of the horizontal beam 150 and the deck segment 120 The damper 510 may be connected to the deck segment 120 to control the movement of the deck segment 120 in the axial direction.

이러한 댐퍼는 상시에는 온도하중, 풍하중, 통과차량에 의한 영향을 흡수하고, 지진시에 발생하는 순간적인 충격에 저항하여 교량전체의 안정성을 확보할 수 있도록 하게 된다.This damper is to always absorb the effects of temperature load, wind load, passing vehicle, and to ensure the stability of the entire bridge by resisting the instantaneous shock generated during the earthquake.

또한 주탑 주두부 외측면에는 브라켓형태로 지지구(530)를 설치하고 상기 지지구(530)에 링크부재(540)의 하단부를 연결하고, 상단부를 데크세그먼트(120)의 외측면에 링크슈(550)로 연결하여 링크부재(540)가 상하방향으로 데크세그먼트(120)와 주탑(110)을 연결하여 링크부재(540) 상단부의 링크슈(550)에 의하여 주두부에서 발생하는 데크세그먼트(120)의 부반력을 제어하도록 하게 된다.In addition, the main column head outer surface is provided with a support 530 in the form of a bracket, the lower end of the link member 540 is connected to the support 530, the upper end of the link shoe (120) on the outer surface of the deck segment (120) Link segment 540 is connected to the 550, the deck segment 120 and the main tower 110 in the vertical direction connected to the deck segment 120 generated from the head by the link shoe 550 of the upper end of the link member 540 To control the negative reaction force.

또한 상기 링크부재(540)는 교축방향으로 회전이 가능하여 데크세그먼트(120)의 종방향 변위도 함께 제어되도록 하게 된다.In addition, the link member 540 is rotatable in the axial direction so that the longitudinal displacement of the deck segment 120 is also controlled.

나아가 도 4b와 같이 상기 주두부에 있어 데크세그먼트의 양 측면과 주탑의 횡방향 내측면에는 풍력에 의한 데크세그먼트의 이동을 제어하기 위하여 윈드슈(560)를 설치하는 것이 바람직하다.Furthermore, as shown in FIG. 4B, the wind shoe 560 may be installed at both side surfaces of the deck segment and the transverse inner surface of the main column in order to control the movement of the deck segment by the wind.

또한 앵커리지블럭(130)은 경사케이블(300)의 일단부가 고정되도록 주탑 외측으로부터 이격된 위치에 콘크리트 블럭 형태로 시공하게 되며 경사케이블이 정착되어 고정될 수 있도록 내부중공이 형성된 구조로 시공하게 된다.In addition, the anchorage block 130 is constructed in the form of a concrete block at a position spaced apart from the outside of the main tower so that one end of the inclined cable 300 is fixed, and is constructed in a structure in which the internal hollow is formed so that the inclined cable is fixed and fixed.

이에 경사케이블(300)은 앵커리지블럭(130)에 일단부가 고정되어 주탑의 상단을 경유하여 데크세그먼트에 다수가 연결되어 있음을 알 수 있다.The inclined cable 300 has one end fixed to the anchorage block 130, it can be seen that a large number is connected to the deck segment via the top of the main tower.

100: 단경간 사장교
110: 주탑 111: 양 측벽부(주탑)
120: 데크세그먼트 121: 최초 데크세그먼트
122.123: 추가 데크세그먼트 130: 앵커리지 블럭
140: 기초 150: 가로보
160: 교량받침 170: 접속도로용 상판
180: 지지대(스트럿) 190: 반력대
200: 잭(Jack) 300: 경사케이블
400: 키세그(KEY SEG) 510: 댐퍼
520: 지지프레임 530: 지지구
540: 링크부재 550: 링크슈
560: 윈드슈
B: 신축이음장치 C: 주경간 중앙부
D: 국부좌굴방지재
100: short span cable stayed bridge
110: pylon 111: both side walls (main tower)
120: deck segment 121: first deck segment
122.123: Additional Deck Segment 130: Anchorage Block
140: base 150: crossbeam
160: bridge support 170: access road deck
180: support (strut) 190: reaction force
200: Jack 300: inclined cable
400: KEY SEG 510: damper
520: support frame 530: support
540: link member 550: link shoe
560 windshoe
B: Expansion joint C: Center of main span
D: Local buckling prevention material

Claims (10)

교축방향으로 서로 이격되어 설치된 양 주탑(110)에 직접 지지되도록 최초 데크세그먼트(121)를 경사케이블(300)을 이용하여 설치하는 제 1단계;
상기 최초 데크세그먼트(121)에 다수의 데크세그먼트들을 주경간 중앙부(C)로 다수 연속하여 추가 경사케이블(300)을 이용하여 설치하는 제 2단계;
상기 주경간 중앙부(C)에서 서로 연결될 데크세그먼트가 인접하면 상기 주탑과 최초 데크세그먼트 사이에 잭(200)을 설치한 후 상기 서로 연결될 데크세그먼트 사이에 키세그(400)를 배치하고, 상기 잭(200)을 작동시켜 연결될 데크세그먼트에 키세그가 접근하면 서로 강결 연결시켜 데크세그먼트를 연속화시키는 제 3단계; 및
상기 주탑(110)과 최초 데크세그먼트(121) 사이에 설치된 잭(200)을 작동전 상태로 서서히 복원시켜 주경간 중앙부 반대방향으로 벌어진 주탑(110)이 주경간 중앙부쪽으로 이동하면서 연결된 데크세그먼트에 인장력(T)이 도입되도록 하는 제 4단계;를 포함하는 것을 특징으로 하는 단경간 인장형 사장교 시공방법.
A first step of installing the first deck segment 121 using the inclined cable 300 to be directly supported by both main towers 110 spaced apart from each other in the axial direction;
A second step of installing a plurality of deck segments in the initial deck segment 121 by using a plurality of additional inclined cables 300 in a row in the center of the main span C;
When the deck segments to be connected to each other in the main span center portion (C) are adjacent to each other, the jack 200 is installed between the main tower and the first deck segment, and then the key segments 400 are disposed between the deck segments to be connected to each other, and the jack 200 is provided. A third step of continually connecting the deck segments to be connected to each other by connecting the deck segments to be connected to each other, thereby continuing the deck segments; And
Tensile force (T) to the deck segment connected to the main tower 110 and the first deck segment 121 is gradually restored to the pre-operation state by moving the main tower 110 opened in the opposite direction to the center of the main span while moving toward the center of the main span. 4) step to be introduced; Short-span tensile type cable-stayed bridge construction method comprising a.
제 1항에 있어서, 상기 주탑(110)과 최초 단부세그먼트(121)은 주탑에 탈착이 가능하도록 설치된 지지대(180)와 최초 단부세그먼트(121)에 설치된 반력대(190)에 의하여 서로 직접 접하도록 하고, 상기 지지대(180)는 잭(200)을 작동전 상태로 서서히 복원시키는 과정에서 주탑(110)과 최초 단부세그먼트의 반력대(190)로부터 분리되도록 하는 것을 특징으로 하는 단경간 인장형 사장교 시공방법.According to claim 1, wherein the main tower 110 and the first end segment 121 is in direct contact with each other by the support 180 is installed to be detachable to the main tower 180 and the reaction table 190 installed on the first end segment 121. And, the support 180 is a short-span tension cable-stayed bridge construction characterized in that to be separated from the main tower 110 and the reaction table 190 of the first end segment in the process of gradually restoring the jack 200 to the pre-operation state Way. 제 2항에 있어서, 상기 지지대(180)는 양 측벽부 내측면에 설치된 U형 강재프레임으로 제작되도록 하고 지지대 내측에는 잭(200)이 안착되어 설치될 수 있도록 하는 것을 특징으로 하는 단경간 인장형 사장교 시공방법.The method of claim 2, wherein the support 180 is made of a U-shaped steel frame is installed on the inner side surface of both side walls and the short-span tensile type characterized in that the jack 200 can be seated and installed inside the support. Construction method of cable-stayed bridge. 제 1항에 있어서, 상기 양 주탑(110)은 상단부로부터 하부로 내려갈 수록 서로 횡방향으로 벌어지는 양 측벽부(111)로 형성되도록 하고, 상기 양 측벽부 하부는 기초에 의하여 지지되어 설치되도록 하며, 서로 연속화된 단부세그먼트가 양 측벽부 사이를 교축방향으로 관통하도록 하는 것을 특징으로 하는 단경간 인장형 사장교 시공방법.The method according to claim 1, wherein the two main towers 110 are formed as both sidewalls 111 extending laterally from each other from the top to the bottom, and the bottom of both sidewalls are supported and installed by a base. Short span tension cable-stayed bridge construction method characterized in that the end segments continuously connected to each other penetrate between the side wall portions in the axial direction. 제 2항에 있어서, 상기 양 측벽부 사이에는 가로보(150)를 더 설치하고, 상기 가로보 상면에 교량받침(160)을 설치하여 교량받침에 연속화된 단부세그먼트의 단부가 지지되도록 하고, 상기 가로보(150)에는 접속도로용 상판의 거더가 지지되도록 교량받침을 더 설치하고, 상기 교량받침에 의하여 지지된 접속도로용 상판의 거더와 연속화된 단부세그먼트가 신축이음장치(B)에 의하여 서로 연결되도록 하는 것을 특징으로 하는 단경간 인장형 사장교 시공방법.According to claim 2, Between the side wall portion is further provided with a cross beam 150, the bridge support 160 is installed on the upper surface of the cross beam to support the end of the end segment continuous to the bridge support, the cross beam ( 150, the bridge support is further installed to support the girder of the access road top plate, and the girder of the access road top plate supported by the bridge support and the continuous end segment are connected to each other by the expansion joint (B). Short span tensile cable-stayed bridge construction method characterized in that. 제 5항에 있어서, 상기 가로보(150) 상면에 댐퍼(510)를 설치하고 상기 댐퍼(510)는 가로보(150)와 연속하된 데크세그먼트의 저면에 설치된 지지프레임(520)에 연결되도록 하여 댐퍼(510)가 교축방향으로의 데크세그먼트(120) 이동을 제어할 수 있도록 하는 것을 특징으로 하는 단경간 인장형 사장교 시공방법.The damper 510 is installed on the upper surface of the cross beam 150, and the damper 510 is connected to the support frame 520 installed on the bottom of the deck segment continuous with the cross beam 150. Short span tension cable-stayed bridge construction method characterized in that the 510 can control the movement of the deck segment 120 in the axial direction. 제 6항에 있어서, 상기 주탑 외측면에는 브라켓형태로 지지구(530)를 설치하고 상기 지지구(530)에 링크부재(540)의 하단부를 연결하고, 상단부를 연속화된 데크세그먼트의 외측면에 링크슈(550)로 연결하여 링크부재(540)가 상하방향으로 연속화된 데크세그먼트와 주탑(110)을 연결하여 링크부재(540) 상단부의 교축방향(종방향) 이동을 제어하는 링크슈(550)에 의하여 상기 연속화된 데크세그먼트(120)의 부반력을 제어하도록 하는 것을 특징으로 하는 단경간 인장형 사장교 시공방법.According to claim 6, wherein the main tower outer surface is provided with a support 530 in the form of a bracket, the lower end of the link member 540 connected to the support 530, the upper end on the outer surface of the continuous deck segment Link shoe 550 to control the axial direction (longitudinal) movement of the upper end of the link member 540 by connecting to the link shoe 550, the link member 540 is connected to the deck segment and the main tower 110 continuous in the vertical direction. Short span tension cable-stayed bridge construction method characterized in that to control the side reaction force of the continuous deck segment (120) by. 제 6항에 있어서, 상기 연속화된 데크세그먼트의 양 외측면과 주탑의 횡방향 내측면에는 풍력에 의한 데크세그먼트의 이동을 제어하기 위하여 윈드슈를 설치하는 것을 특징으로 하는 단경간 인장형 사장교 시공방법.The method of claim 6, wherein the windshield is installed on both outer surfaces of the continuous deck segment and the transverse inner surface of the main column to control the movement of the deck segment by wind power. . 제 1항에 있어서, 상기 연속화된 데크세그먼트는 강재로 제작된 중공박스 형태로 제작된 것을 이용하도록 하고, 상기 반력대(190)는 강재프레임으로 제작된 것을 이용하는 것을 특징으로 하는 단경간 인장형 사장교 시공방법.The short-span tension cable-stayed bridge of claim 1, wherein the continuous deck segment is made of a hollow box made of steel, and the reaction force 190 is made of a steel frame. Construction method. 제 9항에 있어서, 상기 키세그는 강재로 제작된 중공박스 형태로 제작된 것을 이용하여 데크세그먼트와 서로 구조적으로 강결되어 연결되도록 하는 것을 특징으로 하는 단경간 인장형 사장교 시공방법.10. The method of claim 9, wherein the key segment is structurally rigid and connected to the deck segment by using a hollow box made of steel.
KR1020110065482A 2011-07-01 2011-07-01 Tention typed cable-stayed bridge construction method KR101308992B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
KR1020110065482A KR101308992B1 (en) 2011-07-01 2011-07-01 Tention typed cable-stayed bridge construction method
PCT/KR2011/004957 WO2013005877A1 (en) 2011-07-01 2011-07-02 Method for constructing an extendable cable-stayed girder bridge having a single span

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110065482A KR101308992B1 (en) 2011-07-01 2011-07-01 Tention typed cable-stayed bridge construction method

Publications (2)

Publication Number Publication Date
KR20130003868A true KR20130003868A (en) 2013-01-09
KR101308992B1 KR101308992B1 (en) 2013-09-17

Family

ID=47437209

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110065482A KR101308992B1 (en) 2011-07-01 2011-07-01 Tention typed cable-stayed bridge construction method

Country Status (2)

Country Link
KR (1) KR101308992B1 (en)
WO (1) WO2013005877A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113216004A (en) * 2021-05-31 2021-08-06 中交路桥建设有限公司 Construction method of cast-in-place beam support of cable-stayed bridge for meeting flood fighting
CN113356064A (en) * 2021-06-11 2021-09-07 中交二公局第二工程有限公司 Mid-span closure-section-free pushing closure construction method for three-tower cable-stayed bridge
CN115897399A (en) * 2022-11-21 2023-04-04 中交建筑集团有限公司 Construction method for inclined main tower of lute-shaped cable-stayed bridge

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105354386B (en) * 2015-11-13 2018-08-17 西南石油大学 A kind of displacement computational methods in natural gas line suspension cable Oil pipeline pigging process
CN108547226B (en) * 2018-05-25 2024-02-27 中交第二公路勘察设计研究院有限公司 Tower column support for determining cable-free zone of inclined tower of cable-stayed bridge
CN110258344A (en) * 2019-07-03 2019-09-20 中交路桥华南工程有限公司 Inclined guy cable stretching construction method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000234311A (en) * 1999-02-17 2000-08-29 Otaki Yuatsu:Kk Side moving method for bridge beam, etc., and side moving device therefor
KR100603638B1 (en) * 2003-12-18 2006-07-24 김찬녕 Structural beam using a loading system for a beam and bridge construction method using the same
KR101124514B1 (en) * 2009-04-17 2012-03-15 홍석희 Scaffolding girder introducing prestress using a device generating tension in steel wire and prestress introducing method thereof
US8266751B2 (en) * 2009-12-10 2012-09-18 Yidong He Method to compress prefabricated deck units by tensioning supporting girders

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113216004A (en) * 2021-05-31 2021-08-06 中交路桥建设有限公司 Construction method of cast-in-place beam support of cable-stayed bridge for meeting flood fighting
CN113356064A (en) * 2021-06-11 2021-09-07 中交二公局第二工程有限公司 Mid-span closure-section-free pushing closure construction method for three-tower cable-stayed bridge
CN115897399A (en) * 2022-11-21 2023-04-04 中交建筑集团有限公司 Construction method for inclined main tower of lute-shaped cable-stayed bridge
CN115897399B (en) * 2022-11-21 2024-05-31 中交建筑集团有限公司 Construction method of lute-shaped cable-stayed bridge inclined main tower

Also Published As

Publication number Publication date
WO2013005877A1 (en) 2013-01-10
KR101308992B1 (en) 2013-09-17

Similar Documents

Publication Publication Date Title
KR101308992B1 (en) Tention typed cable-stayed bridge construction method
CN109736206B (en) Cast-in-situ bracket structure for bridge side span closure of corrugated steel web continuous beam and construction method
KR20120023907A (en) Partially and fully earth-anchored cable-stayed bridge using main span prestressing appratus and construction method for the same
KR101373169B1 (en) Tention typed cable-stayed bridge construction method using hybrid decksegment
KR100974305B1 (en) Continuous beam bridge construction method using girder for multi-span
CN109487674A (en) Assembling tank-shaped composite beam bridge
KR101387595B1 (en) Tention typed multi-span cable-stayed bridge construction method using hybrid decksegment
CN104562944B (en) Long span steel-concrete composite beam cable-stayed bridge limit steel case anchoring temporarily system
KR101161644B1 (en) Partially earth-anchored cable-stayed bridge using hinge connection parts and construction method for the same
CN209907208U (en) Wave form steel web continuous beam bridge side span folds cast-in-place supporting structure
CN104847016A (en) Suspending transfer layer of stayed cable beam
CN112982139A (en) Wide-width large-span hybrid beam and short-tower cable-stayed bridge system and construction method thereof
KR101347555B1 (en) Method for continuous supporting structure of Corrugated steel plate web-PSC composite beam
KR101688517B1 (en) Continuous bridge construction method using support pier girder and continuous tendon of pier
KR100592196B1 (en) large number bracket in which supporter was installed is used and it is a bridge, multiplex point installed so that support might be carried out support bracket and its installation method
CN210636294U (en) Cable-stayed bridge of semi-floating truss type bridge tower
KR100974306B1 (en) Bridge construction method using node structure hanged with girder
KR20140106861A (en) Temporary bridge and construction method using pile and fabricated girder
CN112227216B (en) Triangular area cable buckling and sling combined construction method for steel diagonal bracing continuous rigid frame bridge
KR20050095049A (en) Continuous bridge construction method using a psc girder
KR101298569B1 (en) Bridge construction method using hybrid psc girder
KR101121725B1 (en) Construction method for psc girder and slab with precast deck and bridge construction method using the same
KR101123935B1 (en) Girder with patial-anchorage apppratus for tension rebar and bridge construction methd using the same
KR101352956B1 (en) Cable-stayed bridge construction method
JP6586305B2 (en) Replacement method for existing bridges

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160927

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170905

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20180911

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20190903

Year of fee payment: 7