KR20120132743A - Structure of beam for drop down of slab form - Google Patents

Structure of beam for drop down of slab form Download PDF

Info

Publication number
KR20120132743A
KR20120132743A KR1020110051053A KR20110051053A KR20120132743A KR 20120132743 A KR20120132743 A KR 20120132743A KR 1020110051053 A KR1020110051053 A KR 1020110051053A KR 20110051053 A KR20110051053 A KR 20110051053A KR 20120132743 A KR20120132743 A KR 20120132743A
Authority
KR
South Korea
Prior art keywords
yoke
pillar
slab
yoke beam
supporter
Prior art date
Application number
KR1020110051053A
Other languages
Korean (ko)
Other versions
KR101310845B1 (en
Inventor
안호중
Original Assignee
(주)에이원알폼
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)에이원알폼 filed Critical (주)에이원알폼
Priority to KR1020110051053A priority Critical patent/KR101310845B1/en
Publication of KR20120132743A publication Critical patent/KR20120132743A/en
Application granted granted Critical
Publication of KR101310845B1 publication Critical patent/KR101310845B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • E04G11/486Dropheads supporting the concrete after removal of the shuttering; Connecting means on beams specially adapted for dropheads
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • E04G11/50Girders, beams, or the like as supporting members for forms

Abstract

PURPOSE: A beam structure for a drop-down of a slab mold is provided to minimize the impact to a yoke beam, a slab form, and a filler beam when the yoke beam is fallen, and to improve the recycling ability of materials. CONSTITUTION: A beam structure for a drop-down of a slab mold includes a supporter(10), yoke beams(20), a fixing member(30), slab forms, and a falling prevention unit. The supporter includes a pillar beam(11) on the upper side. The yoke beams are arranged on the front and rear longitudinal directions of the pillar beam. The fixing member connects the pillar beam to the yoke beams. The slab forms are arranged on both ends of the pillar beam and the yoke beams, and are filled with concrete. The falling prevention unit includes a jamming protrusion and a support body.

Description

슬래브거푸집의 드롭다운을 위한 빔 구조{STRUCTURE OF BEAM FOR DROP DOWN OF SLAB FORM}STRUCTURE OF BEAM FOR DROP DOWN OF SLAB FORM}

본 발명은 슬래브거푸집의 드롭다운을 위한 빔 구조에 관한 것으로, 슬래브거푸집의 해체 시, 서포터(Supporter)에 의해 지지되던 멍에빔을 드롭다운(Drop Down)시킨 후에 슬래브폼과 멍에빔을 각각 분리 해체하게 되는데, 이때 분리 해체되는 슬래브폼, 멍에빔이 시공현장의 바닥면에 떨어지지 않도록 하여 건축자재의 손상 및 파손을 방지하고, 안전사고를 방지하기 위해 추락방지수단이 도입된다. 본 발명에 따른 추락방지수단은 멍에빔의 낙하(드롭다운 작업) 시에, 멍에빔이나 슬래브폼과, 필러빔이나 서포터(Supporter) 상호간의 충격을 최소화하여 부재의 손상이나 파손을 방지할 수 있도록 구성됨으로써, 건축자재의 재활용성을 높이는 것을 특징으로 한다. 또한 본 발명에 따른 추락방지수단은 기존의 필러빔이나 멍에빔에 추가 구성요소를 부가하는 것만으로도 제작이 가능하므로, 별도의 전용 멍에빔이나 필러빔을 따로 제작할 필요 없이 기존의 필러빔이나 멍에빔을 개량하여 제작할 수 있기 때문에 드롭다운용 빔의 제작비용이나 설계비용을 절감하여 경제성을 높일 수 있도록 하는 것을 특징으로 한다.
The present invention relates to a beam structure for dropping down a slab formwork, and when dismantling the slab formwork, the slab form and the yoke beam are separately separated and dismantled after dropping down the yoke beam supported by the supporter. In this case, the slab form and the yoke beam to be dismantled are not dropped on the floor of the construction site to prevent damage and damage to building materials, and fall prevention means are introduced to prevent safety accidents. The fall prevention means according to the present invention minimizes the impact between the yoke beam or the slab form and the filler beam or the supporter when the yoke beam falls (drop-down operation) to prevent damage or damage to the member. It is characterized by improving the recyclability of building materials. In addition, the fall prevention means according to the present invention can be produced by simply adding additional components to the existing filler beam or yoke beam, without having to make a separate dedicated yoke beam or filler beam separately existing filler beam or yoke Since the beam can be manufactured by improving, the manufacturing cost and design cost of the drop-down beam can be reduced to increase the economic efficiency.

건축물의 슬래브 시공에서 드롭빔, 미들빔, 서포트 등의 골조를 토대로 슬래브폼들을 설치하고, 그 상부로 콘크리트를 타설하게 되며, 타설된 콘크리트가 양생 완료되면, 미들빔 및 슬래브폼들을 해체하게 된다.
In slab construction of the building, slab forms are installed based on the frame of drop beams, middle beams, supports, etc., and concrete is poured on top of them. When the cast concrete is cured, the middle beams and slab forms are dismantled.

이러한 슬래브 시공에 따른 골조 구조에 대한 기술로는, 미국특허 제5,643,487호 "BEAM AND PROP SYSTEM FOR SUPPORTING CONCRETE FORMWORK"가 제시되고,As a technology for the frame structure according to the construction of the slab, US Patent No. 5,643,487 "BEAM AND PROP SYSTEM FOR SUPPORTING CONCRETE FORMWORK" is presented,

상기 미국특허는 미들빔 및 슬래브폼들을 해체하게 될 때에 양생된 콘크리트면에서 이탈됨과 동시에 자유 낙하하여 그대로 바닥면에 나뒹굴게 됨으로써 안전사고를 유발할 수 있고,The US patent may cause safety accidents as the middle beam and the slab form are separated from the cured concrete surface at the same time as they are dismantled and then fall freely and fall on the floor.

또한 바닥면과의 충격으로 인하여 발생하는 소음뿐만 아니라, 미들빔 및 슬래브폼들이 파손되어 재이용할 수 없게 되고, 이러한 요인에 의해 자재비가 상승하게 되는 문제점이 있었다.
In addition, as well as the noise generated by the impact with the floor surface, the middle beam and the slab foams are damaged and can not be reused, there is a problem that the material cost is increased by these factors.

이를 해결하기 위한 기술로는, 대한민국등록실용신안 제20-0326555호 "드롭헤드 서포트"가 제시되어 있는바,As a technology to solve this problem, Korean Utility Model Registration No. 20-0326555 "Drophead support" is proposed,

상기 등록실용신안은 설치와 해체가 용이하여 시공능률을 향상시킬 수 있는 드롭헤드 서포트를 제공하기 위한 것이다.
The utility model is to provide a drophead support that can be easily installed and dismantled to improve the construction efficiency.

상기 등록실용신안은 지지부와, 전후에 배열되는 멍에재가 삽입되는 상하부 플레이트와, 상기 상하부 플레이트를 관통하는 나선공과, 상기 나선공에 체결되되 상기 하부플레이트 저면에 위치하는 링형너트와, 서포트를 지지하기 위한 접지플레이트로 이루어져 있어,The utility model is a support portion, the upper and lower plates into which the yoke material arranged before and after is inserted, the spiral hole penetrating the upper and lower plates, and the ring-shaped nut fastened to the spiral hole but located on the bottom of the lower plate, to support the support Consisting of a grounding plate for

상하부 플레이트에 삽입된 멍에재를 고정하기 위하여 상기 하부플레이트 저면에 위치한 링형너트를 회전시켜 상기 하부플레이트를 상승시킴으로써 상기 멍에재를 가압하여 고정하게 된다.
In order to fix the yoke member inserted into the upper and lower plates, the yoke member is pressed and fixed by rotating the ring-shaped nut located at the bottom of the lower plate to raise the lower plate.

이때 상기 링형너트를 회전시키기 위하여 별도의 장비가 요구되며, 또 상기 링형너트를 체결/해제하기 위한 시간이 많이 소요되어 공기(工期)가 증가하게 되고,At this time, separate equipment is required to rotate the ring nut, and the time required for fastening / release of the ring nut is increased, resulting in increased air.

또 상기 링형너트를 체결/해제하는 동작을 반복하게 됨으로 인하여 체결부위가 손상되고, 이러한 손상으로 인해 제기능을 기대할 수 없어 나선공, 링형너트 및 접지플레이트로 이루어진 구성품을 폐기 처리해야 함을 물론, 새로이 제작함으로써 자재비가 증가하게 된다.
In addition, the fastening part is damaged by repeating the operation of fastening / release of the ring nut, and it is impossible to expect a proper function due to such damage. Therefore, a component consisting of a spiral hole, a ring nut, and a ground plate must be disposed of. New production increases material costs.

상기 문제점을 해결하기 위한 종래의 기술로는 등록권리자 박종역에 의한 등록특허 제10-0985865호(2010.09.30. 등록) "해체 시공이 향상된 드롭헤드 기능을 갖는 서포터 및 이를 이용한 슬래브 시공방법"이 개시되어 있다.
Conventional technology for solving the above problems is registered Patent No. 10-0985865 (registered on September 30, 2010) by the registered right holder Park Jong- station "Supporter having a drop head function with improved dismantling construction and slab construction method using the same" Is disclosed.

상기 종래기술은 현재 사용되고 있는 드롭빔, 미들빔, 서포트 그리고 연결부재를 그대로 이용하여 드롭다운 기능을 가지도록 하고,The prior art has a drop down function by using the drop beam, the middle beam, the support and the connection member as it is currently used,

미들빔의 추락을 방지하기 위해, 서포트에 형성된 제2 삽입공에 삽입되는 삽탈지지부재가 낙하하는 미들빔이 연결된 연결부재를 지지하게 된다.
In order to prevent the middle beam from falling, the insertion / removing support member inserted into the second insertion hole formed in the support supports the connecting member to which the falling middle beam is connected.

그러나 종래기술의 쐐기 형태의 삽탈지지부재만으로 낙하하는 미들빔들의 무게를 지탱하는 데에는 한계가 있고,However, there is a limit in supporting the weight of the middle beams falling by only the wedge-shaped insert-and-release member of the prior art,

또한 삽탈지지부재와 미들빔들이 연결된 연결부재의 충돌 시 발생하는 진동이나 유동에 의하여 연결부재가 삽탈지지부재에 거치되지 않고 이탈하는 문제가 발생할 수 있다.
In addition, a problem may arise in that the connecting member is separated from the insertion support member by vibration or flow generated when the insertion member and the middle beam are connected to each other.

본 발명은 상기한 바와 같은 문제점을 해결하기 위해 안출된 것으로,The present invention has been made to solve the above problems,

슬래브거푸집의 해체 작업 과정에서 많이 발생되고 있는 건축자재(슬래브폼, 멍에빔)의 추락 파손이나 시공현장의 바닥면 손상 등을 방지하고, 안전사고를 미연에 방지하기 위해 추락방지수단을 도입하되,In order to prevent the fall or damage of building materials (slab form, yoke beam), or the floor surface of the construction site, which are frequently generated during the dismantling of slab formwork, fall prevention measures are introduced to prevent safety accidents.

본 발명에 따른 추락방지수단은 멍에빔의 낙하(드롭다운 작업) 시에, 멍에빔이나 슬래브폼과, 필러빔이나 서포터(Supporter) 상호간의 충격을 최소화하여 부재의 손상이나 파손을 방지함으로써 자재의 재활용성을 높일 수 있고,The fall prevention means according to the present invention minimizes the impact between the yoke beam or the slab form and the filler beam or the supporter when the yoke beam falls (drops down), thereby preventing the member from being damaged or broken. Improve recyclability,

또한 본 발명에 따른 추락방지수단은 기존의 필러빔이나 멍에빔에 추가 구성요소를 부가하는 것만으로도 제작이 가능하므로, 별도로 제작할 필요 없어 드롭다운용 빔의 제작비용이나 설계비용을 절감하여 경제성을 높일 수 있는 것을 하나의 목적으로 한다.
In addition, the fall prevention means according to the present invention can be manufactured by simply adding additional components to the existing filler beam or yoke beam, and thus, there is no need to manufacture separately, thereby reducing the manufacturing cost or design cost of the drop-down beam, thereby improving economic efficiency. It is one purpose to be able to increase.

본 발명은 추락방지수단이 구조가 단순하고 샘플하여 제작이 용이하고, 또한 멍에빔의 낙하 시 발생하는 충격에 의해 멍에빔이 필러빔에서 분리 이탈되는 것을 원천적으로 차단하여 제품의 신뢰성 및 안전성을 보장할 수 있는 것을 또 하나의 목적으로 한다.
The present invention is a simple structure of the fall prevention means, the sample is easy to manufacture, and also ensures the reliability and safety of the product by blocking the separation of the yoke beam from the filler beam by the impact generated when the yoke beam falls. We can do it for another purpose.

본 발명에 따른 슬래브거푸집의 드롭다운을 위한 빔 구조는 필러빔(11)이 상단부에 구비된 서포터(Supporter)(10)와; 상기 필러빔의 길이방향을 기준으로 전후방에 배열되는 멍에빔(20)과; 상기 필러빔과 상기 멍에빔을 연결하기 위한 고정부재(30)와; 상기 필러빔과 상기 멍에빔의 양측부에 길이방향을 따라 배열되고, 콘크리트가 타설되는 슬래브폼(40)과; 및 상기 멍에빔의 각 단부에 형성되고, 상기 필러빔을 향해 돌출된 걸림돌기(51)와, 상기 필러빔의 양단부에 형성되어 상기 걸림돌기가 삽입되고, 상기 멍에빔의 낙하 시 상기 걸림돌기가 안내되어 거치되는 지지체(53)를 포함하는 추락방지수단(50);을 포함하여 이루어진다.
Beam structure for the drop down of the slab formwork according to the present invention comprises a supporter (Supporter) 10 having a filler beam 11 is provided at the upper end; A yoke beam (20) arranged in front and rear with respect to the longitudinal direction of the pillar beam; A fixing member 30 for connecting the pillar beam and the yoke beam; A slab form (40) arranged along both lengths of the pillar beam and the yoke beam, in which concrete is poured; And a locking protrusion 51 formed at each end of the yoke beam, protruding toward the pillar beam, and formed at both ends of the pillar beam to insert the locking protrusion, and the locking protrusion is guided when the yoke beam falls. Falling prevention means 50 including the support 53 is mounted;

본 발명에 따른 상기 추락방지수단의 지지체는 상기 필러빔의 상단면과 하단면에 연결된 한 쌍의 가이드부와, 상기 가이드부의 하단부를 연결하는 추락방지턱을 포함하여 이루어진 것을 특징으로 한다.
The support of the fall preventing means according to the invention is characterized in that it comprises a pair of guide parts connected to the top and bottom surfaces of the pillar beam, and the fall prevention jaw connecting the lower end of the guide portion.

본 발명에 따른 상기 지지체의 일측 가이드부 또는 양측 가이드부에는 상기 걸림돌기를 분리 배출시키기 위한 배출홈이 더 구비되어 있는 것을 특징으로 한다.
One side guide portion or both side guide portion of the support according to the invention is characterized in that it is further provided with a discharge groove for separating and discharging the locking projection.

본 발명에 따른 상기 필러빔의 양단부와 상기 각 멍에빔의 단부에는 상기 고정부재의 제거 시, 상기 멍에빔의 자유 낙하가 가능하도록 경사부가 형성되고,At both ends of the filler beam and the end of each yoke beam according to the present invention, the inclined portion is formed to allow the free fall of the yoke beam when the fixing member is removed.

상기 경사부의 경계사면은 상기 필러빔을 향해 하부방향으로 형성되어 있으며,Boundary slopes of the inclined portion are formed in a downward direction toward the pillar beam,

상기 지지체는 상기 경사부에 겹쳐지도록 형성되어 있는 것을 특징으로 한다.
The support is formed so as to overlap the inclined portion.

본 발명에 따른 슬래브거푸집의 드롭다운을 위한 빔 구조는 슬래브거푸집의 해체 시 분리 해체되는 슬래브폼, 멍에빔이나 시공현장의 바닥면 등의 손상 및 파손을 방지하고, 안전사고를 미연에 방지하기 위해 추락방지수단이 도입되되,Beam structure for the drop down of the slab formwork according to the present invention is to prevent the damage and breakage of the slab form, yoke beam or the floor of the construction site, etc., which are separated and dismantled when dismantling the slab formwork, and to prevent safety accidents in advance. Fall prevention measures are introduced,

추락방지수단이 멍에빔의 드롭다운 작업 시에 멍에빔이나 슬래브폼과, 필러빔 상호간의 충격을 최소화하여 부재의 손상이나 파손을 방지함으로써 건축자재의 재활용성을 높이고,Fall prevention means improves the recyclability of building materials by minimizing the impact between the yoke beam, slab form and filler beam during the drop-down operation of the yoke beam, preventing damage or damage to the members.

또한 추락방지수단을 별도로 제작할 필요 없이 기존의 필러빔이나 멍에빔에 그대로 적용함으로써 빔의 제작비용이나 설계비용을 절감하여 경제성을 높일 수 있는 것을 하나의 목적으로 한다.
In addition, it is an object of the present invention to improve the economics by reducing the production cost or design cost of the beam by applying it to the existing filler beam or the yoke beam without having to separately manufacture the fall prevention means.

본 발명은 추락방지수단이 구조가 단순하고 샘플하여 제작이 용이하고,The present invention is the fall prevention means is simple to manufacture and easy to sample,

또한 멍에빔의 낙하 시 발생하는 충격에 의해 멍에빔이 필러빔에서 분리 이탈되는 것을 원천적으로 차단하여 제품의 신뢰성 및 안전성을 보장할 수 있는 것을 또 하나의 목적으로 한다.
In addition, it is another object to ensure the reliability and safety of the product by blocking the yoke beam from being separated and separated from the filler beam by the impact generated when the yoke beam falls.

도 1은 본 발명에 따른 빔 구조를 나타내는 사시도,
도 2는 본 발명에 따른 빔 구조의 필러빔과 멍에빔을 나타내는 사시도,
도 3은 본 발명에 따른 빔 구조를 나타내는 분해사시도,
도 4는 본 발명에 따른 빔 구조에서 드롭다운 상태를 나타내는 단면도,
도 5a 및 도 5b는 본 발명에 따른 멍에빔을 필러빔에서 분리하는 것을 나타내는 작동도,
도 6은 본 발명에 따른 빔 구조에 슬래브폼이 연결된 상태를 나타내는 사시도.
1 is a perspective view showing a beam structure according to the present invention,
2 is a perspective view showing a filler beam and a yoke beam of a beam structure according to the present invention;
3 is an exploded perspective view showing a beam structure according to the present invention;
4 is a cross-sectional view showing a drop down state in a beam structure according to the present invention;
5a and 5b is an operation diagram showing the separation of the yoke beam from the filler beam according to the present invention,
Figure 6 is a perspective view showing a state in which the slab form is connected to the beam structure according to the present invention.

본 발명에 따른 본 발명에 따른 슬래브거푸집의 드롭다운을 위한 빔 구조를 첨부된 도면을 참조하여 상세하게 설명하기로 한다.
A beam structure for dropping down a slab formwork according to the present invention according to the present invention will be described in detail with reference to the accompanying drawings.

도 1 내지 도 3에 도시된 바와 같이 본 발명에 따른 슬래브거푸집의 드롭다운을 위한 빔 구조는As shown in Figures 1 to 3 the beam structure for the drop down of the slab formwork according to the invention

필러빔(11)이 상단부에 구비된 서포터(10)와; 상기 필러빔(11)의 길이방향으로 전후방에 배열되는 멍에빔(20)과; 상기 필럽러빔(11)과 상기 멍에빔(20)을 연결하기 위한 고정부재(30)와; 상기 필러빔(11)과 상기 멍에빔(20)의 양측부에 길이방향을 따라 배열되고, 콘크리트가 타설되는 슬래브폼(40)과; 및 상기 멍에빔(20)의 각 단부에 형성되고, 상기 필러빔(11)을 향해 돌출된 걸림돌기(51)와, 상기 필러빔(11)의 양단부에 형성되어 상기 걸림돌기(51)가 삽입되고, 상기 멍에빔(20)의 낙하 시 상기 걸림돌기(51)가 안내되어 거치되는 지지체(53)를 포함하는 추락방지수단(50);을 포함하여 이루어진다.
A supporter 10 having a pillar beam 11 provided at an upper end thereof; A yoke beam (20) arranged in front and rear in the longitudinal direction of the pillar beam (11); A fixing member 30 for connecting the filler beam 11 and the yoke beam 20; A slab form (40) arranged along both lengths of the pillar beam (11) and the yoke beam (20) along which the concrete is poured; And engaging protrusions 51 formed at each end of the yoke beam 20, protruding toward the pillar beam 11, and formed at both ends of the pillar beam 11 to insert the engaging protrusions 51. And fall prevention means 50 including a support 53 on which the locking projection 51 is guided and mounted when the yoke beam 20 falls.

도 1 내지 도 3에 도시된 바와 같이 본 발명에 따른 슬래브거푸집의 드롭다운을 위한 빔 구조에서, 상기 서포터(Supporter)(10)는,1 to 3, in the beam structure for the drop down of the slab formwork according to the present invention, the supporter (Supporter) 10,

상단부에는 필러빔(11)이 구비되고, 필러빔의 하부에는 바닥면이 지지되는 지주(支柱)로 구성되는데, 상기 서포터(10)는 상기 필러빔(11)에 연결되는 멍에빔(20)과, 상기 필러빔(11)과 멍에빔(20)에 배열된 슬래브폼(40)으로 이루어진 거푸집을 지지하는 역할을 하게 된다.
A filler beam 11 is provided at an upper end, and a pillar is supported at a lower part of the pillar beam. The supporter 10 includes a yoke beam 20 connected to the pillar beam 11. In addition, the pillar beam 11 and the yoke beam 20 serve to support the formwork formed of the slab form 40 arranged.

상기 서포터(10)는 상기 거푸집을 지지하기 위해 다수 구비되고, 상기 서포터(10)의 상단부에는 상기 필러빔(11)이 연결되는데,The supporter 10 is provided a plurality to support the formwork, the pillar beam 11 is connected to the upper end of the supporter 10,

상기 서포터(10)의 상단부에는 복수의 볼트(미도시)가 일체로 고정되어 있고,A plurality of bolts (not shown) are integrally fixed to the upper end of the supporter 10,

상기 필러빔(11)의 하면부에는 상기 볼트가 관통 삽입되는 볼트공(미도시)이 형성되어 상기 볼트공의 상부로 돌출된 볼트에 너트(미도시)를 체결하여 상기 서포터(10)의 지주 상단에 필러빔(11)을 결합 고정시키게 된다.
A bolt hole (not shown) is formed in the lower surface of the pillar beam 11 to insert the bolt therethrough, and fastens a nut (not shown) to the bolt protruding to the upper portion of the bolt hole to support the supporter 10. The pillar beam 11 is fixed to the top.

아울러 상기 필러빔(11)은 양단부가 개방된 형태로 중공(12)이 형성되고,In addition, the pillar beam 11 has a hollow 12 is formed in the form that both ends are open,

상기 필러빔(11)의 양측벽면 하부에는 제1 안치홈(13)이 길이방향을 따라 형성되어 고정부재(30)가 수용되며,First fixing grooves 13 are formed along the longitudinal direction under both side walls of the pillar beam 11 to accommodate the fixing member 30.

상기 필러빔(11)의 양측벽면 상부에는 제2 안치홈(14)이 길이방향을 따라 형성되어 슬래브폼(40)이 안착된다.
The second settling groove 14 is formed along the longitudinal direction on both side wall surfaces of the pillar beam 11 so that the slab foam 40 is seated.

도 1 내지 도 3에 도시된 바와 같이 본 발명에 따른 슬래브거푸집의 드롭다운을 위한 빔 구조에서, 상기 멍에빔(20)은1 to 3, in the beam structure for the drop down of the slab formwork according to the present invention, the yoke beam 20 is

상기 필러빔(11)의 전후단에 연결되고, 양측면부에 슬래브폼(40)을 길이방향을 따라 연결시키는 역할을 하게 된다.It is connected to the front and rear ends of the pillar beam 11, and serves to connect the slab form 40 in the longitudinal direction on both side surfaces.

상기 멍에빔(20)은 양단부가 개방된 형태로 중공이 형성되고,The yoke beam 20 is hollow is formed in the form that both ends are open,

상기 멍에빔(20)의 양측벽면 하부에는 상기 필러빔(11)의 제1 안치홈(13)과 이어지는 제1 안착홈(21)에 형성되어 고정부재(30)가 수용되며,Both sides of the yoke beam 20 are formed in the first seating groove 21 which is connected to the first settling groove 13 of the pillar beam 11 and is fixed to the bottom of both side walls.

상기 멍에빔(20)의 양측벽면 상부에는 상기 필러빔(11)의 제2 안치홈(14)와 이어지는 제2 안착홈(23)이 형성되어 슬래브폼(40)이 안치된다.
A second seating groove 23 is formed on both side walls of the yoke beam 20 to be connected to the second settling groove 14 of the pillar beam 11 so that the slab form 40 is seated.

또한 상기 제1 안착홈(21)이 형성된 멍에빔(20)의 양측면벽에는 길이방향을 따라 다수의 제1 수용홀(21a)이 형성되고,In addition, a plurality of first receiving holes 21a are formed in both side walls of the yoke beam 20 in which the first seating grooves 21 are formed along the longitudinal direction.

상기 제2 안착홈(23)이 형성된 멍에빔(20)의 양측벽면에는 길이방향을 따라 다수의 제2 수용홀(23a)이 형성된다.
A plurality of second accommodating holes 23a are formed on both side walls of the yoke beam 20 in which the second seating grooves 23 are formed along the longitudinal direction.

도 1 내지 도 3에 도시된 바와 같이 본 발명에 따른 슬래브거푸집의 드롭다운을 위한 빔 구조에서, 상기 고정부재(30)는1 to 3, in the beam structure for dropping down the slab formwork according to the present invention, the fixing member 30 is

상기 필러빔(11)과 멍에빔(20)을 연결하고 고정시키는 역할을 하게 된다.
The pillar beam 11 and the yoke beam 20 is connected and fixed.

상기 고정부재(30)는 일정한 길이로 갖도록 막대형상을 이루어져 상기 필러빔(11)의 제1 안치홈(13)과 상기 멍에빔(20)의 제1 안착홈(21)에 수용되는데,The fixing member 30 has a rod shape to have a predetermined length and is accommodated in the first settling groove 13 of the pillar beam 11 and the first seating groove 21 of the yoke beam 20.

상기 고정부재(30)에는 상기 멍에빔(20)의 제1 수용홀(21a)에 상응하도록 관통홀(31)이 형성된다.
Through-holes 31 are formed in the fixing member 30 to correspond to the first receiving holes 21a of the yoke beam 20.

따라서 상기 고정부재(30)를 상기 필러빔(11)과 멍에빔(20)의 양측벽면(상기 고정부재(30)는 상기 필러빔(11)의 양측벽면과, 상기 필러빔(11)의 양단부에 인접한 각 멍에빔(20)의 단부 양측벽면의 일정 부분을 덧대어진 상태), 즉 상기 제1 안치홈(13)과 제1 안착홈(21)에 삽입하게 된다.
Therefore, the fixing member 30 is formed on both side wall surfaces of the pillar beam 11 and the yoke beam 20 (the fixing member 30 is formed on both side wall surfaces of the filler beam 11 and both ends of the pillar beam 11). A portion of both side wall surfaces of the yoke beams 20 adjacent to each other is padded), that is, the first settling groove 13 and the first seating groove 21 are inserted.

그리고 일측 방향에서 상기 멍에빔(20)의 제1 수용홀(21a)과 고정부재(30)의 관통홀(31)을 통하여 고정쐐기(33)를 삽입하게 되면 타측 방향의 제1 수용홀(21a)과 관통홀(31)을 통하여 고정쐐기(33)가 노출되고,In addition, when the fixing wedge 33 is inserted through the first receiving hole 21a of the yoke beam 20 and the through hole 31 of the fixing member 30 in one direction, the first receiving hole 21a in the other direction. ) And the fixing wedge 33 is exposed through the through hole 31,

이때 고정쐐기(33) 단부에 형성된 고정홀(33a)에 고정핀(33b)을 삽입하여 상기 고정부재(30)를 필러빔(11)과 멍에빔(20)에 고정시켜 필러빔(11)과 멍에빔(20)을 연결시키게 된다.
At this time, the fixing pin 33b is inserted into the fixing hole 33a formed at the end of the fixing wedge 33 to fix the fixing member 30 to the pillar beam 11 and the yoke beam 20 so that the pillar beam 11 and The yoke beam 20 is to be connected.

반대로 상기 고정부재(30)를 필러빔(11)과 멍에빔(20)에서 제거하게 되면, 상기 필러빔(11)은 서포터(10) 지주에 의해 그대로 슬래브를 지지하게 되는 반면, 상기 멍에빔(20)은 타설된 콘크리트에 부착되어 있어 이들을 떼거나, 또는 자중에 의하여 낙하를 하게 된다.
On the contrary, when the fixing member 30 is removed from the pillar beam 11 and the yoke beam 20, the pillar beam 11 supports the slab as it is by the supporter 10 support, while the yoke beam ( 20) is attached to the cast concrete, either to detach them or to fall by their own weight.

도 1 내지 도 3 및 도 6에 도시된 바와 같이 본 발명에 따른 슬래브거푸집의 드롭다운을 위한 빔 구조에서, 상기 슬래브폼(40)은1 to 3 and 6, in the beam structure for the drop down of the slab formwork according to the present invention, the slab form 40 is

상기 필러빔(11)과 멍에빔(20)의 양측부에 다수 연결되어 천정 거푸집을 형성하여 그 상면 콘크리트를 타설하고 양생하는 것을 가능하게 한다.
It is connected to both sides of the pillar beam 11 and the yoke beam 20 to form a ceiling formwork, which makes it possible to pour and cure the upper concrete.

상기 슬래브폼(40)(또는 거푸집 패널)은 다양한 사이즈와 재질로 구성될 수 있고,The slab foam 40 (or formwork panel) may be composed of various sizes and materials,

상기 슬래브폼(40)에는 상기 멍에빔(20)의 제2 수용홀(23a)에 대응하는 홀들이 형성되어 있어 고정쐐기나 고정핀을 이용하여 상기 필러빔(11)과 멍에빔(20)의 양측면에 고정하여 연속적으로 연결하여 슬래브거푸집을 형성하게 된다.
Holes corresponding to the second receiving hole 23a of the yoke beam 20 are formed in the slab form 40 so that the pillar beam 11 and the yoke beam 20 may be formed using a fixing wedge or a fixing pin. It is fixed to both sides to connect continuously to form a slab formwork.

그리고 상기 슬래브폼(40)은 상기 고정부재(30)를 제거하게 되면 상기 멍에빔(20)과 함께 낙하한 후, 이들을 분리수거하여 재사용하게 된다.
The slab foam 40 is dropped together with the yoke beam 20 when the fixing member 30 is removed, and the slab foam 40 is separately collected and reused.

도 1 내지 도 5b에 도시된 바와 같이 본 발명에 따른 슬래브거푸집의 드롭다운을 위한 빔 구조에서, 상기 추락방지수단(50)은1 to 5b, in the beam structure for dropping down the slab formwork according to the present invention, the fall preventing means 50 is

상기 필러빔(11)과 멍에빔(20)을 연결 고정하는 고정부재(30)의 제거 시, 멍에빔(20)과 슬래브폼(40)이 낙하게 되는데, 이때 상기 멍에빔(20)과 슬래브폼(40)이 그대로 구조물의 바닥면을 추락하는 것을 방지하는 역할을 하게 된다.
The yoke beam 20 and the slab form 40 fall when the fixing member 30 for connecting and fixing the pillar beam 11 and the yoke beam 20 falls, wherein the yoke beam 20 and the slab are dropped. The foam 40 serves to prevent the bottom surface of the structure to fall as it is.

상기 추락방지수단(50)은 상기 멍에빔(20)의 각 단부에 형성되고, 상기 필러빔(11)을 향해 돌출된 걸림돌기(51)와,The fall preventing means 50 is formed at each end of the yoke beam 20, the engaging projection 51 protruding toward the pillar beam 11,

상기 필러빔(11)의 양단부에 형성되어 상기 걸림돌기(51)가 삽입되고, 상기 멍에빔(20)의 드롭다운 작업 시에, 상기 걸림돌기(51)가 안내되어 거치되는 지지체(53)를 포함하여 이루어진다.
The support protrusions 53 are formed at both ends of the pillar beam 11 so that the locking protrusion 51 is inserted, and the locking protrusion 51 is guided and mounted when the yoke beam 20 is dropped down. It is made to include.

즉 상기 걸림돌기(51)는 상기 멍에빔(20)의 각 단부, 즉 상기 필러빔(11)의 양단부에 인접한 인접 단부에 구비되고,That is, the engaging projection 51 is provided at each end of the yoke beam 20, that is, adjacent ends adjacent to both ends of the pillar beam 11,

그리고 상기 걸림돌기(51)는 상기 각 멍에빔(20)의 상부벽면 하면부에 용접이나 볼트체결 방식으로 고정된다.
In addition, the locking protrusion 51 is fixed to the lower surface of the upper wall surface of each yoke beam 20 by welding or bolting.

아울러 상기 지지체(53)는 상기 필러빔(11)의 상단면과 하단면에 연결되어 서로 마주하는 한 쌍의 가이드부(53a)와,In addition, the support 53 is connected to the upper and lower surfaces of the pillar beam 11 and a pair of guide portions 53a facing each other,

상기 가이드부(53a)의 하단부를 연결하는 추락방지턱(53b)을 포함하여 이루어진다.
It includes a fall prevention jaw (53b) for connecting the lower end of the guide portion (53a).

또한 상기 필러빔(11)의 양단부와 상기 각 멍에빔(20)의 단부에는 상기 고정부재(30)의 제거 시, 상기 멍에빔(20)의 자유 낙하가 가능하도록 경사부(55)가 형성되고,In addition, the inclined portion 55 is formed at both ends of the pillar beam 11 and the end of each yoke beam 20 to allow the yoke beam 20 to fall freely when the fixing member 30 is removed. ,

이때 상기 필러빔(11)에 형성된 경사부(55)가 제1 경사부(55a), 상기 각 멍에빔(20)에 형성된 경사부(55)가 제2 경사부(55b)이다.
At this time, the inclined portion 55 formed on the pillar beam 11 is the first inclined portion 55a, and the inclined portion 55 formed on the yoke beams 20 is the second inclined portion 55b.

그리고 상기 경사부(55)의 경계사면, 즉 상기 제1 및 제2 경사부(55b)의 경계사면은 상기 서포터(10)를 향해 하부방향으로 비스듬히 형성되어 있어And the boundary slope of the inclined portion 55, that is, the boundary slope of the first and second inclined portion 55b is formed obliquely downward toward the supporter 10.

상기 고정부재(30)를 제거하는 경우 상기 필러빔(11)에서 상기 멍에빔(20)이 자연스럽게 분리될 수 있다.
When the fixing member 30 is removed, the yoke beam 20 may be naturally separated from the pillar beam 11.

즉 상기 고정부재(30)를 상기 필러빔(11)과 각 멍에빔(20)에서 제거하게 되면 상기 경사부(55)에 의하여 멍에빔(20)이 필러빔(11)에서 분리되어 하부방향으로 자유 낙하를 하게 되는데,That is, when the fixing member 30 is removed from the filler beam 11 and each yoke beam 20, the yoke beam 20 is separated from the filler beam 11 by the inclined portion 55 and downwards. Free fall,

이때 상기 걸림돌기(51)도 상기 지지체(53)의 가이드부(53a)를 따라 낙하게 된다.
At this time, the locking projection 51 also falls along the guide portion 53a of the support 53.

그리고 상기 걸림돌기(51)는 상기 지지체(53)의 추락방지턱(53b)에 거치됨으로써 상기 멍에빔(20)과 슬래브폼(40)이 구조물의 바닥면으로 직접 추락하는 것을 방지할 수 있고,And the locking projection 51 is mounted on the fall prevention jaw (53b) of the support 53 can prevent the yoke beam 20 and the slab form 40 fall directly to the bottom surface of the structure,

또한 각 멍에빔(20)과 슬래브폼(40)의 낙하 이동거리가 짧아 부재에 가해지는 충격이 종래의 드롭다운을 위한 빔 구조물보다 적어 부재에 손상이나 파손을 최소화할 수 있게 된다.
In addition, the yoke beam 20 and the slab form 40, the fall movement distance is short, so that the impact on the member is less than the beam structure for the conventional drop down to minimize damage or damage to the member.

더 나아가 도 5a 및 도 5b에 도시된 바와 같이 상기 추락방지수단(50)에 의하여 상기 각 멍에빔(20)과 슬래브폼(40)이 낙하하여 필러빔(11)으로부터 분리한 후에는 상기 추락방지수단(50)에서 상기 각 멍에빔(20)을 분리 및 해체하는 작업을 수행하게 되는데,Furthermore, as shown in FIGS. 5A and 5B, the fall prevention means 50 prevents the yoke beam 20 and the slab form 40 from falling by separating them from the filler beam 11 after falling. In the means 50 is performed to separate and dismantle each yoke beam 20,

이때 상기 지지체(53)의 일측 가이드부(53a) 또는 양측 가이드부(53a)에는 상기 걸림돌기(51)를 분리 배출시키기 위한 배출홈(53c)이 구비된다.
At this time, one side guide portion 53a or both side guide portions 53a of the support 53 is provided with a discharge groove 53c for separating and discharging the locking protrusion 51.

그리고 상기 배출홈(53c)은 상기 가이드부(53a)의 중간 부분에 형성되는 것이 바람직한데,And the discharge groove 53c is preferably formed in the middle portion of the guide portion 53a,

이는 상기 배출홈(53c)이 상기 가이드부(53a)의 하부 부분에 형성되는 경우에는 상기 각 멍에빔(20)이 낙하하게 되면 상기 걸림돌기(51)와 추락방지턱(53b)이 충돌을 하게 되고,This is because when the discharge groove (53c) is formed in the lower portion of the guide portion (53a) when the yoke beams 20 fall, the engaging projection 51 and the fall prevention jaw (53b) collide with ,

이때 그 충돌에 의하여 상기 걸림돌기(51)가 좌우측 방향으로 이동을 하게 되면 하부에 형성된 배출홈(53c)을 통하여 걸림돌기(51)가 이탈하여 멍에빔(20)이 추락하는 것을 방지하기 위함이다.
At this time, when the locking protrusion 51 is moved in the left and right directions due to the collision, the locking protrusion 51 is separated through the discharge groove 53c formed at the bottom to prevent the yoke beam 20 from falling. .

즉 상기 배출홈(53c)을 상기 가이드부(53a)의 중간 부분 정도에 형성하게 되면 상기 걸림돌기(51)가 배출홈(53c)에서 이탈되는 것을 방지할 수 있게 되는데,That is, when the discharge groove 53c is formed in the middle portion of the guide portion 53a, the locking protrusion 51 can be prevented from being separated from the discharge groove 53c.

다만 상기 배출홈(53c)을 상기 가이드부(53a)의 상부 부분에 형성하는 것도 가능하나, 이 경우에는 상기 걸림돌기(51)를 분리 배출시키기 위해 멍에빔(20)을 상부까지 들어 올려야하는 불편함이 있다.
However, it is also possible to form the discharge groove (53c) in the upper portion of the guide portion (53a), in this case, it is inconvenient to lift the yoke beam 20 to the upper portion in order to separate and discharge the locking projection (51) There is a ham.

상기 배출홈(53c)에 상기 걸림돌기(51)를 분리 배출하는 방식은 상기 멍에빔(20)에 낙하여 상기 걸림돌기(51)가 상기 추락방지턱(53b)에 거치된 상태에서The method of separating and discharging the locking projections 51 into the discharge grooves 53c falls on the yoke beam 20 in a state where the locking projections 51 are mounted on the fall prevention jaw 53b.

상기 멍에빔(20)의 일단부 측을 약간 들어 올려 상기 걸림돌기(51)를 상기 배출홈(53c)의 위치에 맞춘 후, 상기 멍에빔(20)을 측방향으로 이동시켜 상기 배출홈(53c)에 상기 걸림돌기(51)를 분리해내게 된다.
After slightly lifting one end side of the yoke beam 20 to align the locking projection 51 with the position of the discharge groove 53c, the yoke beam 20 is moved laterally so that the discharge groove 53c. ) To separate the engaging projection (51).

이 경우 상기 배출홈(53c)은 상기 일측 가이드부(53a)에 형성되는 것보다, 양측 가이드부(53a)에 형성하여 어느 방향에서든지 상기 걸림돌기(51)를 배출홈(53c)에 분리할 수 있도록 하는 것이 바람직하다.
In this case, the discharge groove 53c may be formed in both guide parts 53a rather than formed in the one guide part 53a so that the catching protrusion 51 may be separated from the discharge groove 53c in any direction. It is desirable to.

한편 도 4에 도시된 바와 같이 본 발명에 따른 슬래브거푸집에서 가장자리에는 수직지지대(3)가 설치되고,On the other hand, as shown in Figure 4 in the slab formwork according to the present invention is provided with a vertical support (3) at the edge,

상기 수직지지대(3)의 상단부에는 인코너(1)가 연결되어 상기 멍에빔(20)의 단부에 연결되는데,The upper portion of the vertical support (3) is connected to the end of the yoke beam 20 is connected to the corner (1),

이 경우 상기 인코너(1)의 하부에는 상기 걸림돌기(51)가 멍에빔(20) 쪽을 향해 돌출 형성되고, 상기 멍에빔(20)의 단부에는 상기 수용체(53)가 형성된다.
In this case, the locking protrusion 51 protrudes toward the yoke beam 20 toward the lower portion of the inconor 1, and the receptor 53 is formed at the end of the yoke beam 20.

따라서 상기 멍에빔(20)이 필러빔(11)으로부터 분리되어 낙하하는 경우 상기 멍에빔(20)의 수용체(53)도 하강하게 되고, 이때 상기 인코너(1)의 걸림돌기(51)가 상기 수용체(53)의 상단면 걸쳐지면 상기 멍에빔(20)이 인코너(1)의 걸림돌기(51)에 거치된다.Therefore, when the yoke beam 20 is separated from the filler beam 11 and falls, the receptor 53 of the yoke beam 20 is also lowered, and at this time, the catching protrusion 51 of the corner 1 is the receptor The yoke beam 20 is mounted on the engaging projection 51 of the inconor 1 when the upper surface of the 53 is spread over.

그리고 상기 멍에빔(20)을 분리해내는 작업은 상기 필러빔(11) 쪽에서 먼저 멍에빔(20)을 분리한 상태에서 상기 멍에빔(20)을 필러빔(11) 쪽으로 이동시켜 상기 수용체(53)에서 상기 걸림돌기(51)를 빼내면 상기 멍에빔(20)은 완전히 분리 배출된다.
The yoke beam 20 is separated from the yoke beam 20 by moving the yoke beam 20 toward the pillar beam 11 while the yoke beam 20 is separated from the filler beam 11. The yoke beam 20 is completely separated and discharged.

이상에서 첨부된 도면을 참조하여 본 발명인 슬래브거푸집의 드롭다운을 위한 빔 구조를 설명함에 있어 특정 형상 및 방향을 위주로 설명하였으나, 본 발명은 당업자에 의하여 다양한 변형 및 변경이 가능하고, 이러한 변형 및 변경은 본 발명의 권리범위에 포함되는 것으로 해석되어야 한다.
In the above description with reference to the accompanying drawings, the beam structure for the drop-down of the slab formwork of the present invention mainly described in a specific shape and direction, the present invention is capable of various modifications and changes by those skilled in the art, such variations and modifications Should be construed as being included in the scope of the invention.

1 : 인코너 3 : 수직지지대
10 : 서포터 11 : 필러빔
12 : 중공 13 : 제1 안치홈
14 : 제2 안치홈
20 : 멍에빔 21 : 제1 안착홈
21a : 제1 수용홀 23 : 제2 안착홈
23a : 제2 수용홀
30 : 고정부재 31 : 관통홀
33 : 고정쐐기 33a : 고정홀
33b : 고정핀
40 : 슬래브폼
50 : 추락방지수단 51 : 걸림돌기
53 : 지지체 53a : 가이드부
53b : 추락방지턱 53c : 배출홈
55 : 경사부 55a : 제1 경사부
55b : 제2 경사부
1: Inner corner 3: Vertical support
10 supporter 11: pillar beam
12: hollow 13: the first settle groove
14: second settling groove
20: yoke beam 21: first seating groove
21a: first receiving hole 23: second seating groove
23a: second accommodation hole
30: fixing member 31: through hole
33: fixing wedge 33a: fixing hole
33b: fixed pin
40: slab foam
50: fall prevention means 51: locking projection
53 support 53a: guide part
53b: fall prevention jaw 53c: discharge groove
55 inclined portion 55a first inclined portion
55b: second inclined portion

Claims (4)

필러빔(11)이 상단부에 구비된 서포터(10);
상기 필러빔 전후방에 배열되는 멍에빔(20);
상기 필러빔과 상기 멍에빔의 양측부를 연결하는 고정부재(30);
상기 필러빔과 상기 멍에빔의 양측부에 길이방향을 따라 배열되고, 콘크리트가 타설되는 슬래브폼(40); 및
상기 멍에빔(20)의 각 단부에 형성되고 상기 필러빔(11)을 향해 돌출된 걸림돌기(51)와,
상기 필러빔의 양단부에 형성되어 상기 걸림돌기가 삽입되고, 상기 멍에빔을 드롭다운할 때, 상기 걸림돌기가 안내되어 거치되는 지지체(53)를 포함하는 추락방지수단(50);
을 포함하여 이루어진 슬래브거푸집의 드롭다운을 위한 빔 구조.
A supporter 10 having a pillar beam 11 provided at an upper end thereof;
A yoke beam (20) arranged in front and rear of the pillar beam;
A fixing member 30 connecting both sides of the pillar beam and the yoke beam;
Slab form 40 is arranged along the longitudinal direction on both sides of the pillar beam and the yoke beam, the concrete is poured; And
A locking protrusion 51 formed at each end of the yoke beam 20 and protruding toward the pillar beam 11;
Fall prevention means (50) formed at both ends of the pillar beam to include the support protrusion (53) guided and mounted when the locking protrusion is inserted and the yoke beam is dropped down;
Beam structure for the drop down of the slab formwork, including.
제 1 항에 있어서, 상기 추락방지수단의 지지체는
상기 필러빔의 상단면과 하단면에 연결된 한 쌍의 가이드부와,
상기 가이드부의 하단부를 연결하는 추락방지턱을 포함하여 이루어진 것을 특징으로 하는 슬래브거푸집의 드롭다운을 위한 빔 구조.
According to claim 1, wherein the support of the fall prevention means
A pair of guide parts connected to the top and bottom surfaces of the pillar beam,
Beam structure for the drop down of the slab formwork, characterized in that it comprises a fall prevention jaw connecting the lower end of the guide portion.
제 2 항에 있어서,
상기 지지체의 일측 가이드부 또는 양측 가이드부에는 상기 걸림돌기를 분리 배출시키기 위한 배출홈이 더 구비되어 있는 것을 특징으로 하는 슬래브거푸집의 드롭다운을 위한 빔 구조.
The method of claim 2,
One side guide portion or both side guide portion of the support beam structure for the drop down of the slab formwork, characterized in that further provided with a discharge groove for separating and discharging the locking projection.
제 1 항 내지 제 3 항 중 어느 한 항에 있어서,
상기 필러빔의 양단부와 상기 각 멍에빔의 단부에는 상기 고정부재의 제거 시, 상기 멍에빔의 자유 낙하가 가능하도록 경사부가 형성되고,
상기 경사부의 경계사면은 상기 서포터를 향해 하부방향으로 형성되어 있는 것을 특징으로 하는 슬래브거푸집의 드롭다운을 위한 빔 구조.
The method according to any one of claims 1 to 3,
At both ends of the filler beam and at each end of the yoke beam, an inclined portion is formed to allow the yoke beam to fall freely when the fixing member is removed.
The boundary surface of the inclined portion is a beam structure for the drop down of the slab formwork, characterized in that formed in the downward direction toward the supporter.
KR1020110051053A 2011-05-30 2011-05-30 Structure of beam for drop down of slab form KR101310845B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110051053A KR101310845B1 (en) 2011-05-30 2011-05-30 Structure of beam for drop down of slab form

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110051053A KR101310845B1 (en) 2011-05-30 2011-05-30 Structure of beam for drop down of slab form

Publications (2)

Publication Number Publication Date
KR20120132743A true KR20120132743A (en) 2012-12-10
KR101310845B1 KR101310845B1 (en) 2013-09-25

Family

ID=47516209

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110051053A KR101310845B1 (en) 2011-05-30 2011-05-30 Structure of beam for drop down of slab form

Country Status (1)

Country Link
KR (1) KR101310845B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101514395B1 (en) * 2013-12-30 2015-04-23 주식회사 주신산업개발 Supporting device of slab form

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103866975B (en) * 2014-02-28 2016-02-03 苏鸿飞 The mounting method of construction formwork and the aluminum alloy pattern plate connector used

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050029967A (en) * 2003-09-24 2005-03-29 고려개발 주식회사 Support frame assembly for supporting concrete slab form and form setting method using the same
KR100985865B1 (en) * 2008-06-17 2010-10-08 박종역 Supporter where has drop-head function where the dissolution construction is improved and slab construction methods which use this

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101514395B1 (en) * 2013-12-30 2015-04-23 주식회사 주신산업개발 Supporting device of slab form

Also Published As

Publication number Publication date
KR101310845B1 (en) 2013-09-25

Similar Documents

Publication Publication Date Title
US10590665B2 (en) Adjustable support device and shoring system
KR100985865B1 (en) Supporter where has drop-head function where the dissolution construction is improved and slab construction methods which use this
CA2879761C (en) Interlocking highway barrier structure
KR101011417B1 (en) System Formwork for FSM
US10480211B2 (en) Handrail assembly, system and method of installation
KR100893765B1 (en) Supporting structure of slab form
KR101207580B1 (en) Slab Form Device using Drophead Separable Head And Using Method Thereof
KR101310845B1 (en) Structure of beam for drop down of slab form
KR101076562B1 (en) Supporting structure of slab form
KR101180845B1 (en) Supporting System for Slab Form and Construction Method Using the Same
KR101940859B1 (en) Beam structure and slim floor using the same
KR20160106879A (en) Bottom frameform panel supporting apparatus by which bottom frameform is early detatchable
KR102102214B1 (en) Safety handrail for beam table form
KR101527564B1 (en) Supporting apparatus for slab formwork
KR101653940B1 (en) Yoke beam of drop type having forms system
KR100655243B1 (en) structure for supporting concreat mold on ceiling
KR101341864B1 (en) Slab Form Girder Beam Coupling Device
KR101673907B1 (en) Roof building construction methods and construction materials used him
KR101278686B1 (en) Device for support slab formwork and its using the same slab construction method
KR101819196B1 (en) Form system
FI128216B (en) Barrier to be placed by a road or to separate traffic lanes, and methods for attaching barrier units to and detaching them from each other
CN113015833A (en) ALPHADECK-Large area Flat Panel template System
KR101163022B1 (en) Support bracket for preventing fall gang form and concreat structure crack
KR20190000607U (en) Safety railing for Form Meong-yeoi
KR101594961B1 (en) Connecting device for slab wall form

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E90F Notification of reason for final refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160906

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170822

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20180906

Year of fee payment: 6