KR20100092847A - Construction method of basement wall using the precast concrete member - Google Patents

Construction method of basement wall using the precast concrete member Download PDF

Info

Publication number
KR20100092847A
KR20100092847A KR1020090023501A KR20090023501A KR20100092847A KR 20100092847 A KR20100092847 A KR 20100092847A KR 1020090023501 A KR1020090023501 A KR 1020090023501A KR 20090023501 A KR20090023501 A KR 20090023501A KR 20100092847 A KR20100092847 A KR 20100092847A
Authority
KR
South Korea
Prior art keywords
wall
vertical
underground
support
constructing
Prior art date
Application number
KR1020090023501A
Other languages
Korean (ko)
Other versions
KR101101927B1 (en
Inventor
유원석
전금석
Original Assignee
유원석
전금석
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 유원석, 전금석 filed Critical 유원석
Publication of KR20100092847A publication Critical patent/KR20100092847A/en
Application granted granted Critical
Publication of KR101101927B1 publication Critical patent/KR101101927B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Geology (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE: A construction method of a basement wall using a precast concrete member is provided to improve construction performance by appropriately using a PC member. CONSTITUTION: A construction method of a basement wall using a precast concrete member is as follows. A retaining wall(100) is formed. Inner columns are formed inside the retaining wall. The inner ground of the retaining wall is excavated. A mounting bracket is installed in the retaining wall. PC members(200) are placed on the mounting bracket are continuously installed along the retaining wall. A support(300) connects the retaining wall and the inner columns. Vertical reinforcing bars(410) are arranged through a vertical connecting key(210) of the PC members. A basement wall is formed by integrally placing wall concrete(420) in the PC members.

Description

일부분을 PC화한 지하외벽 시공방법{Construction method of basement wall using the precast concrete member}Construction method of basement wall using the precast concrete member}

본 발명은 건물의 지하부분 시공에서 지하외벽의 일부분을 PC화한 지하외벽 시공방법에 관한 것으로, 더욱 상세하게는 공장 제작된 PC부재를 초기에는 흙막이벽을 지지하기 위한 토압전달체로 이용하는 한편 최종적으로는 지하외벽의 일부분이 되도록 함으로써 일정의 시공품질과 경제성 및 시공성을 확보할 수 있도록 한 지하외벽 시공방법에 관한 것이다.The present invention relates to a method for constructing an underground exterior wall in which a part of the underground exterior wall is constructed in the underground construction of a building. More specifically, the factory-made PC member is initially used as a earth pressure carrier for supporting a retaining wall. The present invention relates to a method for constructing an underground exterior wall to secure a certain construction quality, economic feasibility and constructability by being part of the underground exterior wall.

일반적으로 건물의 지하외벽은, 흙막이벽을 시공한 후 흙막이벽 내측을 굴착한 다음 가설 지지체(수평버팀대 등)를 설치하여 토압을 지지하게 한 상태에서 건물 지하부분의 층간 구조체(보와 슬래브)와 함께 또는 독립적으로 하향식 또는 상향식으로 시공하거나(이하, '가설 지지공법'이라 칭함), 흙막이벽을 시공한 후 흙막이벽 내측을 굴착한 다음 건물 지하부분의 층간 구조체(보 또는 슬래브)를 시공하여 그 층간 구조체(보 또는 슬래브)가 토압을 직접 지지하는 영구 지지체가 되도 록 한 상태에서 건물 지하부분의 층간 구조체(보 또는 슬래브)와 함께 하향식으로 또는 건물 지하부분의 층간 구조체(보 또는 슬래브)와는 독립적으로 상향식으로 시공한다(이하, '영구 지지공법'이라 칭함). 특히, 영구 지지공법은 건물 지하부분의 일부인 층간 구조체(보 또는 슬래브)가 흙막이벽을 지지하게 하면서 하향식으로 시공하는 방법이기 때문에 역타공법이라 할 수 있는데, 이는 다시 지하부분의 층간 구조체(보 또는 슬래브)의 구조형식에 따라 철골구조에 의한 철골역타공법(일명 SPS공법), 철근콘크리트구조에 의한 RC역타공법, 합성부재(PC, PC+철골, RC+철골 등)에 의한 합성역타공법으로 구분할 수 있다.In general, the basement outer wall of a building is constructed with an earthquake wall, excavated inside the earthen wall, and then installed a temporary support (horizontal brace, etc.) to support the earth pressure. Work together or independently from the top down or from the bottom up (hereinafter referred to as 'the temporary support method'), or construct the wall and excavate the inside of the wall, then construct the interlayer structure (beam or slab) in the basement of the building. Top down with the interlayer structure (beam or slab) in the basement of the building, independent of the interlayer structure (beam or slab) in the basement of the building, with the interlayer structure (beam or slab) being a permanent support that directly supports the earth pressure. Construction from the bottom up (hereinafter referred to as 'permanent support method'). In particular, the permanent support method is a reverse drilling method because the interlayer structure (beam or slab), which is part of the basement of the building, is supported by the top-down construction while supporting the retaining wall. According to the structural type of), it can be divided into steel reverse drilling method (also called SPS method) by steel structure, RC reverse drilling method by reinforced concrete structure, and synthetic reverse drilling method by composite member (PC, PC + steel, RC + steel, etc.).

가설 지지공법은 통상 가설 지지체를 시공하기에 앞서 철골띠장을 따라 설치하여 토압을 안정적으로 지지할 수 있게 하는데, 철골띠장은 지하외벽 시공과정에서 제거해야 하는 가설부재이기 때문에 전반적으로 시공성과 경제성을 떨어뜨리는 요소가 된다. 또한, 영구 지지공법은 통상 건물 지하부분의 층간 구조체(보 또는 슬래브)를 시공하는 과정에서 테두리보를 함께 시공하여 토압을 안정적으로 지지할 수 있게 하는데, 테두리보는 거푸집작업과 철근배근작업 등의 복잡한 작업을 수반하기 때문에 전반적으로 시공성과 경제성을 떨어뜨리는 요소가 된다.Temporary support method is usually installed along the steel frame length before the construction of the temporary support, so that the earth pressure can be stably supported. Since the steel frame length is a temporary member that needs to be removed during the construction of the basement wall, the construction and economical efficiency are generally low. It becomes a floating element. In addition, the permanent support method is to support the earth pressure stably by constructing the rim beam together in the process of constructing the interlayer structure (beam or slab) of the basement of the building, and the rim beam is complicated work such as formwork and reinforcement work It is a factor that degrades overall construction and economic feasibility.

본 발명은 상기한 종래 지하외벽 시공방법에 있어 시공성과 경제성에 관련한 문제를 개선하고자 개발된 것으로서, 공장 제작된 PC부재를 적절히 이용함으로써 가설작업을 최소화하여 시공성을 향상시킴은 물론 일정의 시공품질과 경제성을 확보할 수 있는 지하외벽 시공방법을 제공하는데 기술적 과제가 있다.The present invention was developed to improve the problems related to the construction and economical efficiency in the above-described conventional underground exterior wall construction method, by minimizing the construction work by appropriately using the factory-produced PC members, as well as to improve the construction performance of a certain construction quality and There is a technical problem in providing an underground exterior wall construction method that can secure economic feasibility.

또한, 본 발명은 가설 지지공법과 영구 지지공법 모두에 유연하게 적용할 수 있는 지하외벽 시공방법을 제공하는데 기술적 과제가 있다.In addition, the present invention has a technical problem to provide a method for the construction of the basement outer wall that can be flexibly applied to both the temporary support method and the permanent support method.

나아가, 본 발명은 지하외벽의 일부분을 PC화함에도 PC부분과 현장시공 RC부분의 일체성을 향상시킬 수 있는 지하외벽 시공방법을 제공하는데 기술적 과제가 있다.Furthermore, the present invention has a technical problem to provide a method for constructing an underground exterior wall that can improve the integrity of the PC portion and the site construction RC portion even when the PC of a part of the underground exterior wall.

상기한 기술적 과제를 해결하기 위해 본 발명은 건물의 지하부분 시공에서 지하외벽의 일부분을 PC화한 지하외벽 시공방법으로서, (a)흙막이벽을 시공하고 흙막이벽 내부로 내부기둥을 시공하는 단계; (b)흙막이벽 내측 지반을 굴토하는 단계; (c)흙막이벽에 거치브라켓을 설치하는 단계; (d)길이방향 상·하부면에 상하연결키를 구비함과 동시에 길이방향 일측면에 측면연결키를 구비하도록 제작된 PC부재를 준비하고, 상기 PC부재를 거치브라켓 위에 거치시키면서 흙막이벽을 따라 연속하게 설치하되 PC부재의 길이방향 타측면이 흙막이벽에 대면하게 설치하는 단계; (e)상기 PC부재의 측면연결키에 구속시키면서 흙막이벽과 내부기둥을 연결하는 지지체를 시공함으로써, 상기 PC부재와 지지체가 흙막이벽을 지지하도록 시공하는 단계; 그리고, (f)상기 PC부재의 상하연결키를 통해 벽체수직철근을 배근한 후 벽체콘크리트를 타설하면서 상기 PC부재와 일체화되도록 지하외벽을 시공하는 단계;를 포함하여 이루어지는 것을 특징으로 하는 일부분을 PC화한 지하외벽 시공방법을 제공한다.In order to solve the above technical problem, the present invention provides a method for constructing an underground exterior wall in which a part of an underground exterior wall is constructed in a basement construction of a building, the method comprising: (a) constructing an earth wall and constructing an inner column into the earth wall; (b) excavating the inner ground of the retaining wall; (c) installing a mounting bracket on the wall; (d) preparing a PC member having upper and lower connecting keys on the upper and lower surfaces of the longitudinal direction and having a side connecting key on one side of the longitudinal direction, and mounting the PC member on the mounting bracket along the earth wall. Installing continuously but installing the other side in the longitudinal direction of the PC member facing the earth wall; (e) constructing the support for connecting the retaining wall and the inner pillar while constraining the side connection key of the PC member, thereby constructing the support for supporting the retaining wall with the PC member; And (f) constructing the basement outer wall to be integrated with the PC member while placing the wall concrete after placing the vertical wall reinforcement through the vertical connecting keys of the PC member. Provides a method of constructing a subterranean exterior wall.

본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention, the following effects can be expected.

첫째, 건물의 지하부분을 시공함에 있어 지하외벽의 일부분을 PC화하여 토압전달체로서 선시공함으로써 흙막이벽을 지지하게 하기 때문에 흙막이벽을 지지하기 위한 지지체의 시공에서 가설작업을 생략하거나 최소화할 수 있으며, 이에 따라 전반적으로 시공성과 경제성을 향상시킬 수 있다.First, in constructing the underground part of the building, a part of the basement outer wall is made into a PC and installed as a earth pressure carrier to support the retaining wall. Therefore, the construction of the support for supporting the retaining wall can be omitted or minimized. As a result, overall construction and economics can be improved.

둘째, 지하외벽의 일부분을 PC화하여 토압전달체로 이용하기 때문에 흙막이벽을 지지하기 위한 지지체 시공과정에서 공장생산된 PC부재의 장점인 구조적인 안정성과 시공품질을 확보할 수 있으며, 나아가 가설 지지공법과 영구 지지공법 모두에 유연하게 적용할 수 있다.Second, since part of the underground wall is made into PC and used as earth pressure carrier, structural stability and construction quality, which are the advantages of the PC member produced in the support construction process for supporting the retaining wall, can be secured. It can be flexibly applied to both and permanent support methods.

셋째, PC부재를 적절히 이용하면 영구 지지체에 의한 역타공법으로 건물의 지하부분을 시공하면서도 지하외벽을 상향식 또는 하향식으로 일체성을 향상시키면서 시공할 수 있다.Third, if the PC member is properly used, it can be installed while improving the integrity of the basement outer wall in a bottom-up or top-down manner while constructing the underground part of the building by a reverse boring method using a permanent support.

이하, 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 상세히 설명한다. Hereinafter, the present invention will be described in detail with reference to the accompanying drawings and preferred embodiments.

도 1과 도 2는 본 발명에 따른 지하외벽 시공방법에 대한 시공순서를 보여주며, 도 3a 내지 도 3c는 본 발명에 따른 지하외벽 시공방법에 바람직하게 이용할 수 있는 PC부재를 도시하며, 도 4 내지 도 9는 본 발명에 따른 지하외벽 시공방법에서 단계별 시공상세를 도시한다.Figures 1 and 2 show the construction sequence for the construction method for the underground exterior wall according to the present invention, Figures 3a to 3c shows a PC member that can be preferably used in the construction method for the underground exterior wall according to the present invention, Figure 4 9 to 9 show the construction details for each step in the construction method of the basement outer wall according to the present invention.

본 발명에 따른 지하외벽 시공방법은 건물의 지하부분을 시공함에 있어, 길이방향 상·하부면에 상하연결키(210)를 구비함과 동시에 길이방향 일측면에 측면연결키(220)를 구비하도록 제작된 PC부재(200)를, 굴토 중의 흙막이벽(100) 지지과정에서는 가설 지지체(310) 또는 영구 지지체(건물 지하부분의 층간 구조체로서 보 또는 슬래브, 320, 330)와 연결하여 토압전달체로 이용하고, 지하외벽(400) 시공과정에서는 벽체수직철근(410) 및 벽체콘크리트(420)의 현장시공 RC부분과 일체화시켜 지하외벽(400)의 일부분으로 구성되게 한다는데 기술적 특징이 있다. 이하부터는 상기한 기술적 특징이 구현된 기술적 구성을 도 1 내지 도 9를 참고하여 단계적으로 설명한다. According to the present invention, the method for constructing the outer wall of the basement includes the upper and lower connecting keys 210 on the upper and lower surfaces in the longitudinal direction, and the side connecting keys 220 on the one side in the longitudinal direction. The fabricated PC member 200 is used as a earth pressure carrier in connection with a temporary support 310 or a permanent support (beam or slab, 320, 330 as an interlayer structure of the building basement part) in the process of supporting the retaining wall 100 in oyster soil. In addition, in the construction process of the basement outer wall 400, there is a technical feature to be integrated with the site construction RC portion of the wall vertical reinforcement 410 and the wall concrete 420 to be configured as a part of the basement outer wall 400. Hereinafter, a technical configuration in which the above technical features are implemented will be described step by step with reference to FIGS. 1 to 9.

(a)단계 : 흙막이벽 및 내부기둥 시공- 도 1(a), 2(a) 참고Step (a): construction of the retaining wall and the inner pillar-see Fig. 1 (a), 2 (a)

건축선에 맞춰 흙막이벽(100)을 시공한다. 흙막이벽(100)은 H말뚝과 토류판, CIP, SCW, 시트파일 등은 물론 지하연속벽(슬러리월)으로 시공 가능하다.Construct the earth wall 100 according to the construction line. The barrier wall 100 may be constructed as an H continuous pile, earth plate, CIP, SCW, sheet pile, etc., as well as underground continuous wall (slurry wall).

흙막이벽(100)을 시공한 후에는 흙막이벽(100) 내부로 내부기둥(110)을 시공한다. 본 발명을 가설 지지공법을 적용하면서 실시한다면 본 단계에서 내부기둥(110)은 가설 기둥 또는 건물 지하부분의 구조체를 구성하는 영구 기둥이 되고, 본 발명을 영구 지지공법을 적용하면서 실시한다면 본 단계에서 내부기둥(110)은 건물 지하부분의 구조체를 구성하는 영구 기둥이 된다. After constructing the retaining wall 100, the inner pillar 110 is constructed into the retaining wall 100. If the present invention is carried out while applying the temporary support method in this step the inner pillar 110 is a permanent column constituting the structure of the temporary pillar or the basement of the building, and in this step if the present invention is carried out while applying the permanent support method The inner pillar 110 becomes a permanent column constituting the structure of the basement of the building.

(b)단계 : 굴토- 도 1(b), 2(b) 참고(b) step: gulto-see Fig. 1 (b), 2 (b)

흙막이벽(100) 내측 지반을 굴토한다. 굴토깊이는 흙막이벽(100)의 안정적인 지지상태를 고려하면서 실시한다. It excavates the ground inside the retaining wall 100. The pit depth is carried out while considering the stable support state of the retaining wall (100).

(c)단계 : 브라켓 설치- 도 1(c), 2(c) 참고Step (c): Bracket Installation-Refer to Figures 1 (c) and 2 (c)

흙막이벽(100)에 접합하여 거치브라켓(120)을 설치한다. 다만, 거치브라켓(120)은 후술하는 (d)단계에서 설치되는 PC부재(200)와 (e)단계에서 시공되는 지지체(300)의 하중을 충분히 견딜 수 있도록 적절한 규격을 정하도록 한다.It is attached to the earth wall 100 to install the mounting bracket (120). However, the mounting bracket 120 is to determine the appropriate size to sufficiently withstand the load of the support member 300 and the PC member 200 is installed in step (d) to be described later (e).

(d)단계 : PC부재 설치- 도 1(d), 2(d), 3a, 3b, 3c, 4 참고Step (d): PC member installation-see Fig. 1 (d), 2 (d), 3a, 3b, 3c, 4

PC부재(200)를 거치브라켓(120) 위에 거치시키면서 흙막이벽(100)을 따라 연속하게 설치한다. PC부재(200)는 기본적으로 길이방향 상·하부면에 상하연결키(210)를 구비함과 동시에 길이방향 일측면에 측면연결키(220)를 구비하도록 제작된 것이어야 한다. 또한 PC부재(200)는 흙막이벽(100)에서 지지체(300)로 토압을 전달하는 토압전달체로서 역할해야 하므로 안정적인 토압전달체로서 충분한 내력을 발휘할 수 있도록 제작되어야 할 것이며, 다만 그 크기(두께와 너비항향 폭)는 현장상황 또는 구조설계에 따라 다양하게 제작될 수 있다. While mounting the PC member 200 on the mounting bracket 120 is installed continuously along the earth wall (100). PC member 200 should be made to be provided with a side connection key 220 on one side of the longitudinal direction at the same time having a vertical connection key 210 on the upper and lower surfaces in the longitudinal direction. In addition, since the PC member 200 should serve as a earth pressure carrier that delivers earth pressure from the retaining wall 100 to the support 300, it should be manufactured to exhibit sufficient strength as a stable earth pressure carrier, but its size (thickness and width). Deflection width) can be manufactured in various ways depending on the site situation or structural design.

본 단계는 상기와 같은 PC부재(200)를 그 길이방향 타측면(측면연결키가 마련된 측면의 반대 편)이 흙막이벽(100)에 대면하게 설치하는 방식으로 이루어지는데, 그 결과로서 PC부재(200)는 측면연결키(220)가 노출된 상태로 흙막이벽(100)에서 내민 형태가 된다. 본 발명을 영구 지지공법을 적용하면서 실시한다면 본 단계에서 PC부재(200)는 영구 지지체(320, 330)로서 건물 지하부분의 층간 구조체(보 또는 슬래브)의 시공위치에 맞춰 설치해야 하나, 가설 지지공법을 적용하면서 실시하는 경우라면 PC부재(200)의 설치위치는 건물 지하부분의 층간 구조체(보 또는 슬래브)의 시공위치에는 무관하게 가설 지지체(310)의 설치위치만을 고려하면 된다.This step is made in such a way that the other side of the PC member 200 as described above (the opposite side of the side on which the side connection key is provided) is installed facing the retaining wall 100. As a result, the PC member ( 200 is a form extruded from the retaining wall 100 in a state in which the side connection key 220 is exposed. If the present invention is carried out while applying the permanent support method in this step, the PC member 200 as permanent support (320, 330) should be installed in accordance with the construction position of the interlayer structure (beam or slab) in the basement of the building, the temporary support If the method is implemented while applying the method, the installation position of the PC member 200 may only consider the installation position of the temporary support 310 regardless of the construction position of the interlayer structure (beam or slab) in the basement of the building.

본 단계에서 이용되는 PC부재(200)는 길이방향 상·하부면에 상하연결키(210)를 구비함과 동시에 길이방향 일측면에 측면연결키(220)를 구비하도록 제작된 것인데, 상기 상하연결키(210)는 지하외벽(400)의 일체성을 위해 벽체수직철근(410)을 연속 배근시키기 위한 구성이고, 측면연결키(220)는 지지체(300)를 PC부재(200)에 연결 결속시키기 위한 구성이다. 본 발명에서는 도 3a 내지 도 3c를 통해 상하연결키(210)로 수직돌출매입철근(211), 수직관통개구부(212) 및 커플러노출매입철근의 형태를 제안하고 측면연결키(220)로 엔드플레이트(221), 수평돌출매입철근(222) 및 커플러노출매입철근(223)의 형태를 제안하고 있는데, 이들 상하연결키(210)와 측면연결키(220)는 다양한 조합으로 구성시킬 수 있다., The PC member 200 used in this step is manufactured to have a side connection key 220 on one side of the longitudinal direction at the same time having a vertical connection key 210 on the upper and lower surfaces in the longitudinal direction, the vertical connection The key 210 is configured to continuously reinforce the vertical wall reinforcement 410 for the integrity of the basement outer wall 400, the side connection key 220 is to bind the support 300 to the PC member 200 It is for the configuration. The present invention proposes the shape of the vertical protrusion purchase reinforcing bar 211, the vertical through-opening opening 212 and the coupler exposure buying rebar as the vertical connection key 210 through Figure 3a to 3c and end plate with the side connection key 220 221, horizontal protruding buried rebar 222 and coupler exposed buried reinforcing bar 223 are proposed, these up and down connection key 210 and side connection key 220 can be configured in various combinations,

도 3a는 상하연결키(210)가 수직돌출매입철근(211)으로 마련되는 한편 측면연결키(220)가 엔드플레이트(221)로 마련된 형태로서, 복근으로 배근되는 벽체수직철근(410) 모두를 연속 배근시킬 수 있도록 상하연결키(210)가 복근의 수직돌출매 입철근(211)으로 마련된 PC부재(200)를 보여준다. 상하연결키(210)로서 수직돌출매입철근(211)은 철근이 상하 수직하게 돌출하도록 PC부재(200)에 매입됨에 따라 마련되며, 측면연결키(220)로서 엔드플레이트(221)는 플레이트가 그 판면이 노출하도록 PC부재(200)에 매입됨에 따라 마련된다. 이와 같은 PC부재(200)는 도시하지 않았지만 벽체콘크리트(420) 타설을 고려하여 콘크리트 타설관이 삽입되거나 공기가 배출되기 위한 개구부가 별도 형성되도록 마련할 수도 있다.3A shows that the vertical connecting key 210 is provided as a vertical protruding reinforcing bar 211 while the side connecting key 220 is provided as an end plate 221. The vertical connection key 210 shows the PC member 200 provided with the vertical protruding media reinforcing bar 211 of the abdominal muscle so as to be continuously placed. The vertical protrusion embedded reinforcing bar 211 as the vertical connection key 210 is provided as the reinforcing bar is embedded in the PC member 200 so as to project vertically vertically, and the end plate 221 as the side connection key 220 is a plate thereof. It is provided as the plate surface is embedded in the PC member 200 to expose. Although not illustrated, the PC member 200 may be provided so that an opening for inserting a concrete pouring pipe or discharging air may be separately formed in consideration of placing the wall concrete 420.

도 3b는 상하연결키(210)가 수직관통개구부(212)로 마련되는 한편 측면연결키(220)가 커플러노출매입철근(223)으로 마련된 형태로서, 복근으로 배근되는 벽체수직철근(410) 모두를 수용하여 연속 배근시킬 수 있도록 상하연결키(210)가 2열의 수직관통개구부(212)로 마련된 PC부재(200)를 보여준다. 이와 같은 PC부재(200)는 수직관통개구부(212)에 의해 경량성을 가지는 점에서 유리한 형태이다. 상하연결키(210)로서 수직관통개구부(212)는 PC부재(200)가 상하 수직 관통하게 개구됨에 따라 마련되며, 측면연결키(220)로서 커플러노출매입철근(223)은 철근 단부에 철근이음용 커플러가 장치된 것으로 커플러의 입구가 노출되게 철근이 PC부재(200)에 매입됨에 따라 마련된다. 특히, 상하연결키로서 수직관통개구부(212)는 다양한 크기와 모양으로 형성되는 것은 물론, 다양한 배치(2열은 물론 1열도 가능)로 형성될 수 있다.3B shows that the vertical connecting key 210 is provided as a vertical through opening 212, while the side connecting key 220 is provided as a coupler-exposed reinforcing bar 223. The upper and lower connection keys 210 show the PC member 200 provided with two rows of vertical through-openings 212 to accommodate the continuous reinforcement. Such PC member 200 is advantageous in that it has a light weight by the vertical through opening 212. The vertical through opening 212 as the vertical connection key 210 is provided as the PC member 200 is vertically penetrated through the vertical opening, the coupler exposure embedded reinforcing bar 223 as the side connection key 220 is a rebar at the end of the reinforcing bar The drinking coupler is provided and is provided as the rebar is embedded in the PC member 200 so that the inlet of the coupler is exposed. In particular, the vertical through opening 212 as the vertical connection key may be formed in various sizes and shapes, as well as in various arrangements (two rows as well as one column).

도 3c는 상하연결키(210)가 수직관통개구부(212)로 마련되는 한편 측면연결키(220)가 수평돌출매입철근(222)으로 마련된 형태로서, 복근으로 배근되는 벽체수직철근(410) 중 하나만을 수용하여 연속 배근시킬 수 있도록 상하연결키(210)가 1 열의 수직관통개구부(212)로 마련된 PC부재(200)를 보여준다. 이와 같은 PC부재(200)는 상당히 짧은 너비로 제작될 수 있기 때문에 도 3b의 PC부재보다도 경량화에 더 유리한 형태라 할 수 있다. 측면연결키(220)로서 수평돌출매입철근(222)은 철근이 수평으로 돌출하도록 PC부재(200)에 매입됨에 따라 마련된다.3c shows that the vertical connecting key 210 is provided as a vertical through opening 212 while the side connecting key 220 is provided as a horizontal protruding recessed reinforcing bar 222, and the vertical vertical reinforcing bar 410 is reinforced with abs. The upper and lower connection keys 210 show a PC member 200 provided with vertical rows of openings 212 in one row so as to accommodate only one. Since the PC member 200 can be manufactured with a considerably short width, it can be said to be more advantageous in weight reduction than the PC member of FIG. 3B. The horizontal protruding embedded rebar 222 as the side connection key 220 is provided as the reinforcing bar is embedded in the PC member 200 to protrude horizontally.

나아가, 본 단계에서는 도 3a,3b,3c에서와 같이 오목홈(224), 측면요철(241), 양중고리(251)가 더 마련된 PC부재(200)를 이용할 수 있다. 오목홈(224)은 측면연결키(220)를 보완하여 PC부재(200)와 영구 지지체(보와 슬래브의 콘크리트, 320, 330)의 일체화를 강화하기 위해 PC부재(200)의 길이방향 일측면(측면연결키가 마련된 면)에 마련된 구성인데, 오목홈(224)은 볼록돌기나 와이어메쉬 마감 등에 의한 울퉁불퉁한 비평탄면으로 대체할 수 있다. 측면요철(241)은 일정 길이로 제작되는 PC부재(200)의 연속 설치를 감안하여 PC부재(200)의 너비방향 양 측면이 돌기와 홈으로 처리됨에 따라 마련된 구성인데, 측면요철(241)은 일정 길이의 PC부재(200) 상호 간을 길이방향으로 연속하도록 너비방향으로 맞대게 설치할 때 개구부를 형성시키는 역할(돌기는 돌기끼리 홈은 홈끼리 서로 맞대면 측면요철에 의해 개구부가 형성됨)을 하거나 서로 맞춤연결하게 하는 역할(돌기와 홈의 맞춤연결)을 하며, 특히 측면요철(241)의 맞댄 설치에 의해 형성된 개구부는 상하연결키(210)로서 수직관통개구부(212)나 콘크리트 타설 또는 공기 배출을 위한 개구부로 이용할 수 있다. 아울러 도 3a와 도 3b에서는 PC부재(200) 상호 간을 길이방향으로 매입되는 길이방향철근(242)끼리 커플러 등으로 연결할 수 있음을 확인알 수 있다. 양중고리(251)는 PC부재(200)의 길이방향 상부면에 마련되어 PC부재(200)의 양중을 가능케 한다.In addition, in this step, as shown in FIGS. 3A, 3B, and 3C, the PC member 200 may further include a concave groove 224, a side unevenness 241, and a double ring 251. The concave groove 224 complements the side connection key 220 so as to reinforce the integration of the PC member 200 and the permanent support (concrete of the beam and slab, 320, 330) in one longitudinal direction of the PC member 200. The concave groove 224 may be replaced with a rugged non-planar surface due to convex protrusions or wire mesh finishes. Side concave-convex 241 is a configuration provided as both sides of the width direction of the PC member 200 is treated with protrusions and grooves in consideration of the continuous installation of the PC member 200 to a certain length, the side concave-convex 241 is a constant When the PC members 200 of the length 200 are installed in the width direction so as to be continuous to each other in the longitudinal direction to form an opening (protrusions are formed between the grooves are formed by the side irregularities when the grooves are opposed to each other grooves) or fit each other It serves to make a connection (custom connection of the projection and groove), in particular, the opening formed by the buttocks of the side concave-convex (241) is an up and down connection key 210, the vertical opening opening 212 or the opening for concrete pouring or air discharge Can be used as 3A and 3B, it can be seen that the longitudinal reinforcing bars 242 embedded in the longitudinal direction of the PC members 200 can be connected to each other by a coupler or the like. Both ring 251 is provided on the longitudinal upper surface of the PC member 200 to enable the lifting of the PC member 200.

한편, 본 단계는 채택되는 PC부재(200)에 따라 다르게 진행하게 된다. 도 3a 및 도 3b와 같은 PC부재(200)는 상하연결키(210)가 복근 배근되는 벽체수직철근(410) 모두를 연속 배근할 수 있게 마련되기 때문에 시공할 지하외벽(400)의 두께에 상당하는 너비를 가지게 될 것이므로, 이에 따라 이러한 PC부재(200)는 흙막이벽(100)에 근접하게 설치하게 된다. 다만, 흙막이벽(100)은 불균일한 면으로 처리되는 것이 일반적이므로 PC부재(200)를 흙막이벽(100)에 밀착하게 설치하는 것이 곤란할 수 있는 바, 본 발명에서는 도 4(a)(b)에서와 같이 PC부재(200)와 흙막이벽(100)의 일체화를 위해 PC부재(200)와 흙막이벽(100) 사이에 그라우팅하여 뒷채움재(130)를 시공할 것을 제안한다. 이와 같은 그라우팅을 통한 뒷채움재(130) 시공을 감안하면, PC부재(200)를 길이방향 타측면(측면연결키가 마련된 측면의 반대 편)에 하부돌출턱(231)이 형성되게 제작 준비하고, 나아가 도 4(a)에서와 같이 하부돌출턱(231) 위의 흙막이벽(100)에 스터드(140)를 접합하거나 도 4(b)에서와 같이 PC부재(200)를 하부돌출턱(231) 위로 수평돌출매입철근(232)이 더 마련되도록 제작 준비하는 것이 바람직한데, 이는 스터드(140) 내지 수평돌출매입철근(232)이 그라우팅에 의한 뒷채움재(130)에 매입되게 함으로써 PC부재(200)와 흙막이벽(100)의 일체화를 강화하기 위함이다. 또한, 도 3a 및 도 3b와 같은 PC부재(200)는 흙막이벽(100)에 근접하게 설치되는 관계로 지하외벽(400)을 완성한 후에 PC부재(100)에 의한 시공조인트가 형성될 우려가 있는데, 이를 고려한다면 PC부재(200)는 길이방향 상부면 또는 하부면에 길이방향홈(251)이 형성되도록 제작 준비하고 PC부재의 길이방향홈(251)에는 수팽창지수재(250)를 장치하도록 한다. On the other hand, this step will proceed differently depending on the PC member 200 is adopted. PC member 200 as shown in Figures 3a and 3b corresponds to the thickness of the basement outer wall 400 to be constructed because the vertical connection key 210 is provided to be able to continuously all of the vertical wall reinforcement 410 that is abs abs Since it will have a width, such a PC member 200 is to be installed close to the retaining wall (100). However, since the barrier wall 100 is generally treated with an uneven surface, it may be difficult to install the PC member 200 in close contact with the barrier wall 100. In the present invention, FIG. 4 (a) (b) It is proposed to construct the backfill material 130 by grouting between the PC member 200 and the retaining wall 100 for the integration of the PC member 200 and the retaining wall 100 as in. In consideration of the construction of the back filling material 130 through the grouting, and preparing the PC member 200 to be formed so that the lower projection jaw 231 is formed on the other side in the longitudinal direction (the opposite side of the side provided with the side connection key), Furthermore, as shown in FIG. 4 (a), the stud 140 is bonded to the earth wall 100 on the lower protrusion jaw 231, or the PC protrusion 200 is attached to the lower protrusion jaw 231 as shown in FIG. 4 (b). It is preferable to prepare the production so that the horizontal protrusion embedded reinforcing bar 232 is further provided, which allows the stud 140 to the horizontal protrusion embedded reinforcing bar 232 to be embedded in the back-filling material 130 by grouting. This is to reinforce the integration of the retaining wall 100 with. In addition, since the PC member 200 as shown in FIGS. 3A and 3B is installed close to the retaining wall 100, a construction joint may be formed by the PC member 100 after completing the basement outer wall 400. , Considering this, the PC member 200 is prepared to be formed so that the longitudinal groove 251 is formed in the longitudinal upper surface or the lower surface and to install the water-expandable index 250 in the longitudinal groove 251 of the PC member. do.

도 3c와 같은 PC부재(200)는 상하연결키(210)가 복근 배근되는 벽체수직철근(410) 중 하나만을 연속 배근할 수 있게 마련되기 때문에 시공할 지하외벽(400)의 두께보다 작은 너비를 가지게 될 것이므로, 이에 따라 이러한 PC부재(200)는 복근 배근되는 벽체수직철근(410) 중 나머지 하나를 배근하기 위한 공간을 남겨둔 채 흙막이벽(100)에서 이격하게 설치하게 된다. 이와 같이 PC부재(200)가 흙막이벽(100)에서 이격하게 설치되므로, 도 3c와 같은 PC부재(200)를 이용함에 있어서는 PC부재(200)와 흙막이벽(100) 사이에는 반드시 뒷채움재(130)를 시공해야 한다. 그래야 흙막이벽(100)에서 뒷채움재(130) 및 PC부재(200)로 연속적으로 이어져 흙막이벽(100)을 안정적으로 지지할 수 있다. 도 3c와 같은 PC부재(200)를 설치함에 있어 뒷채움재(130) 시공은, 도 5(a)에서와 같이 흙막이벽(100)과 PC부재(200)를 연결하는 거푸집(131)을 설치한 후 거푸집(131) 위에 몰탈, 콘크리트 등의 습식재료를 충진하는 방식으로 진행하거나, 도 5(b)(c)에서와 같이 길이방향 타측면(측면연결키가 마련된 측면의 반대 편으로 흙막이벽에 대면하는 면)에 접합철물(233)이 노출되게 장치된 PC부재(200)를 채택하여 연결강재(132)를 흙막이벽(100, 노출된 H형강의 플랜지)과 PC부재(200, 노출된 접합철물)에 동시에 접합 설치하는 방식으로 진행하거나, 도 5(d)에서와 같이 수나사편(133a)과 암사나편(133b)으로 구성된 길이조절형 뒷채움재 조립체(133)를 흙막이벽(100)과 PC부재(200) 사이에 위치시킨 후 상기 조립체(133)의 체결위치를 조절하여 흙막이벽(100)과 PC부재(200)를 압착하게 설치하는 방식으로 진행한다. 다만, 뒷채움재(130)가 시공되는 흙막이 벽(100)과 PC부재(200) 사이 공간은 벽체수직철근(410)이 배근되는 공간이기도 하므로, 벽체수직철근(410)의 연속 배근이 가능하도록 벽체수직철근(410)의 배근계획을 고려하면서 뒷채움재(130)를 시공해야 할 것이다.PC member 200 as shown in Figure 3c has a width smaller than the thickness of the basement outer wall 400 to be installed because the vertical connection key 210 is provided so that only one of the vertical wall reinforcement 410 that is abs abs Therefore, the PC member 200 will be spaced apart from the retaining wall 100 while leaving a space for reinforcing the other one of the wall vertical rebars 410 that are abs abs. As described above, since the PC member 200 is spaced apart from the retaining wall 100, when using the PC member 200 as shown in FIG. 3C, the back filling material 130 must be formed between the PC member 200 and the retaining wall 100. Should be installed. So that it can be continuously connected to the back-filling material 130 and the PC member 200 in the retaining wall 100 can stably support the retaining wall 100. In installing the PC member 200 as shown in FIG. 3C, the construction of the back filling material 130 is provided with a formwork 131 connecting the earth wall 100 and the PC member 200 as shown in FIG. 5 (a). After filling the mold 131 with a wet material such as mortar, concrete, or the like, or as shown in Fig. 5 (b) (c) to the other side of the longitudinal wall (side connection key is provided on the opposite side of the earth wall Adopting the PC member 200 is installed to expose the joining hardware 233 on the facing surface) connecting the connecting steel 132 to the retaining wall (100, exposed H-shaped steel flange) and PC member 200, exposed bonding Hardware), or the length-adjustable backfill material assembly 133 consisting of a male thread piece 133a and a female thread piece 133b as shown in FIG. 5 (d). After placing between the members 200 to adjust the fastening position of the assembly 133 to install the crimping wall 100 and the PC member 200 to compress. Proceed in this way. However, since the space between the wall wall 100 and the PC member 200 on which the backfill material 130 is constructed is also a space in which the wall vertical rebar 410 is reinforced, the wall to allow continuous reinforcement of the wall vertical rebar 410 is possible. Considering the reinforcement plan of the vertical reinforcing bars (410) will have to construct the backfill material (130).

도 5(a)에서와 같은 습식재료에 의한 뒷채움재(130) 시공에는 도 6(a)와 같은 형상변형 거푸집(131)을 이용하는 것이 바람직한데, 형상변형 거푸집(131)은 흙막이벽(100)이 불균일한 면으로 시공되는 경우에 대비하여 불균일한 흙막이벽(100)에 유연하게 대응하면서 형상이 변형될 수 있게 제안된 형태이다. 형상변형 거푸집(131)은 도 6(a)에서와 같이 팬플룻(panflute)처럼 형성된 것으로, 외부틀(131a);과, 다수개가 병렬로 밀착 배치된 채 상기 외부틀(131a)을 관통 돌출하게 장치되는 이동파이프(131b);를 포함하여 구성된 것인데, 상기 다수개의 이동파이프(131b)는 각각이 개별적으로 밀리고 당겨지면서 외부틀(131a)에서의 돌출길이가 자유롭게 신축하는 구조를 가지며, 이에 따라 형상변형 거푸집(131)은 그 형상을 자유자재로 변형시킬 수 있게 된다. 이와 같은 형상변형 거푸집(131)은 도 6(b)에서와 같이 이동파이프(131b)의 자유로운 신축으로 흙막이벽(110)의 울퉁불퉁한 표면에 유연하게 대응하게 하면서 설치되며, 습식재료가 경화되어 뒷채움재(130)가 완성된 후에는 도 6(c)에서와 같이 제거될 수 있다.For the construction of the backfill material 130 by the wet material as shown in Figure 5 (a), it is preferable to use the shape deformation formwork 131 as shown in Figure 6 (a), the shape deformation formwork 131 is earthen wall 100 It is a form that can be deformed while flexibly responding to the uneven earth wall 100 in case of being constructed with this uneven surface. Shape-forming die 131 is formed as a pan flute (panflute), as shown in Figure 6 (a), the outer frame (131a); and a plurality of devices to protrude through the outer frame (131a) in close contact with each other in parallel The moving pipe 131b is configured to include, The plurality of moving pipes 131b has a structure in which the protruding length in the outer frame (131a) is freely stretched while being individually pushed and pulled, thereby deforming the shape The formwork 131 can freely deform the shape. Such a shape-forming formwork 131 is installed while flexibly responding to the bumpy surface of the retaining wall 110 by free expansion and contraction of the moving pipe 131b, as shown in FIG. After the ash 130 is completed, it can be removed as in Figure 6 (c).

도 5(b)(c)에서와 같이 연결강재(132)에 의한 뒷채움재(130) 시공을 위해서는 길이방향 타측면(측면연결키가 형성된 측면의 반대 편)에 접합철물(233)이 노출되게 장치된 PC부재(200)를 채택하여야 하는데, 접합철물(233)은 철근, 플레이트, 앵글, 채널이 PC부재(200)에 노출 매입되는 형태로 장치되거나(도 3a 및 도 5(b) 참조) 채널이 PC부재(200)에 끼워지는 형태(도 5(c) 참조)로 장치될 수 있다. 또한, 접합철물(233)은 PC부재(200)의 길이방향 타측면 전체에 걸쳐 장치되는 것은 물론 연결강재(132)에 의한 뒷채움재(130) 시공 위치에만 위치하게 PC부재(200)의 길이방향 타측면에 부분적으로 장치되는 것도 가능하다.As shown in FIG. 5 (b) (c), for the construction of the backfill material 130 by the connecting steel 132, the joining hardware 233 is exposed on the other longitudinal side (the opposite side of the side on which the side connecting key is formed). Adopted PC member 200, the joining hardware 233 is installed in the form that the reinforcing bars, plates, angles, channels are embedded in the PC member 200 (see Figs. 3a and 5b). The channel may be installed in the form of being fitted to the PC member 200 (see Fig. 5 (c)). In addition, the joining hardware 233 is installed throughout the entire length of the other side surface of the PC member 200, as well as the longitudinal direction of the PC member 200 to be located only at the construction position of the backfill material 130 by the connecting steel 132. It is also possible to be partially mounted on the other side.

도 5(d)에서와 같이 흙막이벽(100)과 PC부재(200)를 동시에 압착하는 뒷채움재(130) 시공을 위해서는 도 7과 같은 길이조절형 뒷채움재 조립체(133)를 이용함이 바람직하다. 길이조절형 뒷채움재 조립체(133)는, 수나사봉 단부에 넓게 확장된 확장지지판(133c)이 마련되는 수나사편(133a);과, 암나사봉 단부에 넓게 확장된 확장지지판(133c)이 마련되는 것으로 암나사봉이 상기 수나사편(133a)의 수나사봉과 체결하게 되는 암나사편(133b);을 포함하여 구성되며, 나아가 수나사편(133a)과 암나사편(133b)의 체결을 용이하게 하기 위해 손잡이(133d)를 더 포함하도록 구성할 수 있다. 이와 같은 길이조절형 뒷채움재 조립체(133)는 수나사편(133a)과 암나사편(133b)의 체결정도로 길이조절이 가능하며, 또한 길이조절을 통해 양 단부의 확장지지판(133c)을 흙막이벽(100)과 PC부재(200) 각각에 압착시키면서 설치할 수 있다.As shown in Figure 5 (d) for the construction of the back-filling material 130 to compress the retaining wall 100 and the PC member 200 at the same time, it is preferable to use the length-adjustable back-filling material assembly 133 as shown in FIG. The length-adjustable backfill material assembly 133 may include: a male thread piece 133a having an extended support plate 133c extended to the male threaded rod end; and an extended support plate 133c extended to the female threaded rod end. A female threaded rod is a female threaded piece 133b to be fastened to the male threaded rod of the male threaded piece 133a; and is configured to further include a handle 133d to facilitate the engagement of the male threaded piece 133a and the female threaded piece 133b. It can be configured to include more. The length-adjustable backfill material assembly 133 is capable of adjusting the length of the male thread piece 133a and the female thread piece 133b, and furthermore, the expansion support plate 133c at both ends through the length adjustment of the earth wall 100 ) And the PC member 200 can be installed while pressing.

(e)단계: 지지체 시공- 도 1(e), 2(e), 4 참고Step (e): support construction-see Figs. 1 (e), 2 (e), 4

PC부재의 측면연결키(220)에 구속시키면서 흙막이벽(100)과 내부기둥(110)을 연결하는 지지체(300)를 시공한다. 상기 지지체(300)는 적용하는 지지공법에 따라 구분하면서 가설 지지체(310) 또는 영구 지지체(320, 330)로 시공하면 된다.Restraining the side connection key 220 of the PC member constructs a support 300 for connecting the earth wall 100 and the inner pillar 110. The support 300 may be constructed as a temporary support 310 or a permanent support 320, 330 while being divided according to the support method applied.

본 발명을 가설 지지공법을 적용하면서 실시한다면 지지체(300)는 가설 지지체(310)로 시공하게 되고, 다만 이 경우에 본 단계는 도 4(a)에서와 같이 측면연결키(220)가 엔드플레이트(221)로 마련된 PC부재(200)를 채택하면서 수행해야 한다. 그래야만 가설 지지체(310)를 PC부재의 엔드플레이트(221)에 접합하여 설치한 후에 지하부분 시공과정에서 용이하게 제거할 수 있게 된다.If the present invention is carried out while applying the temporary support method, the support 300 is constructed as a temporary support 310, but in this case, the side connection key 220 is an end plate as shown in FIG. It should be performed while adopting the PC member 200 provided with (221). Only then, the temporary support 310 is attached to the end plate 221 of the PC member to be installed and then easily removed in the underground construction process.

한편, 본 발명을 영구 지지공법을 적용하면서 실시한다면 지지체(300)는 영구 지지체(320, 330), 즉 건물 지하부분의 층간 구조체(보 또는 슬래브)로 시공하게 되며, 이때 영구 지지체(320, 330)는 철골, 철근콘크리트, 합성구조 중에서 어떠한 구조형식이라도 무방하다. 영구 지지공법을 적용함에 있어서는 가설 지지공법을 적용하는 경우와는 달리 PC부재(200)는 측면연결키(220)의 구성에 제한이 없다. 다시 말해, PC부재(200)가 엔드플레이트(221) 형태의 측면연결키(220)를 구비한 경우라면 도 4(a)에서와 같이 영구 지지체(320, 330)의 강재(철골보 내지 철근)를 PC부재의 엔드플레이트(221)와 접합하여 설치하면 되고, PC부재(200)가 수평돌출매입철근(222) 혹은 커플러노출매입철근(223) 형태의 측면연결키(220)를 구비한 경우라면 도 4(b)(c)에서와 같이 영구 지지체(320, 330)의 철근(건물 지하부분의 층간 구조체로서 보 내지 슬래브의 수평철근)을 수평돌출매입철근(222)이나 커플러노출매입철근(223)에 연결한 후 콘크리트를 타설하면서 시공하면 된다.On the other hand, if the present invention is carried out while applying the permanent support method, the support 300 is constructed as a permanent support (320, 330), that is, the interlayer structure (beam or slab) of the basement of the building, wherein the permanent support (320, 330) ) Can be any type of steel frame, reinforced concrete, or composite structure. In applying the permanent support method, unlike the case of applying the temporary support method, the PC member 200 is not limited to the configuration of the side connection key 220. In other words, if the PC member 200 is provided with a side connection key 220 in the form of the end plate 221, as shown in Figure 4 (a) of the steel (steel ball to steel) of the permanent support (320, 330) If the PC member 200 is provided with a side connection key 220 in the form of a horizontal protruding buried rebar 222 or a coupler exposed buried rebar 223, the PC member 200 may be attached to the end plate 221 of the PC member. As shown in 4 (b) and (c), the reinforcing bars (horizontal reinforcing beams and slabs as interlayer structures in the basement of the building) of the permanent supports 320 and 330 are horizontal protruding buried rebar 222 or coupler exposed buried rebar 223. After connecting to the construction, the concrete is poured.

본 단계의 진행으로 흙막이벽(100)과 PC부재(200) 및 지지체(300)에 의한 토압 지지구조가 완성되며, 이에 따라 PC부재(200)는 흙막이벽(100)에서 지지체(300)로 토압을 전달하는 토압전달체로서 역할하면서 지지체(300)와 함께 흙막이벽(100) 을 지지하게 된다.The earth pressure support structure by the barrier wall 100, the PC member 200, and the support 300 is completed by the progress of this step, and thus the PC member 200 is the earth pressure from the barrier wall 100 to the support 300. It serves as a earth pressure carrier to deliver the support wall 300 together with the support 300.

(f)단계 : 지하외벽 시공- 도 1(f1)(f2), 2(f), 8, 9 참고Step (f): Underground wall construction-see Fig. 1 (f1) (f2), 2 (f), 8, 9

PC부재의 상하연결키(210)를 통해 벽체수직철근(410)을 배근한 후 벽체콘크리트(420)를 타설하면서 상기 PC부재(200)와 일체화되도록 지하외벽(400)을 시공한다. 지하외벽(400)의 시공은 적용하는 지지공법에 따라 하향식 또는 상향식으로 진행하며, 경우에 따라 하향식과 상향식을 적절히 조합하여 혼용식으로 진행하는 것도 가능하다. 또한, 지하외벽(400)의 시공은 상기 (d)단계에서 채택된 PC부재(200)에 적절하게 대응하면서 진행한다.After reinforcing the wall vertical reinforcing bar 410 through the vertical connection key 210 of the PC member, while laying the concrete wall 420, the underground outer wall 400 is constructed to be integrated with the PC member 200. Construction of the basement outer wall 400 proceeds from top to bottom or bottom-up according to the supporting method applied, it is also possible to proceed in a mixed manner by combining the top-down and bottom-up as appropriate. In addition, the construction of the basement outer wall 400 proceeds while appropriately corresponding to the PC member 200 adopted in step (d).

본 발명을 가설 지지공법을 적용하면서 실시한다면 본 단계는 도 1(f1)에서와 같이 건물의 지하부분 층간 구조체(보, 슬래브)의 시공과 병행하면서 상향식으로 진행할 수 있으며, 다만 이 경우에 해당 시공위치의 가설 지지체(310)는 제거하여 병행 시공한 건물의 지하부분 층간 구조체가 곧 영구 지지체가 되게 한다. 물론 도 1(f2)에서 보는 바와 같이 건물의 지하부분 층간 구조체(보, 슬래브)의 시공과 별개로 지하외벽(400)을 상향식 내지 하향식으로 시공할 수도 있으며, 특히 지하외벽(400)을 하향식으로 시공한다면 상기 (d)단계를 상하연결키(210)가 수직돌출매입철근(211)으로 마련된 도 3a와 같은 PC부재(200)를 채택하여 도 9(a)에서와 같이 시공함이 바람직하고 아울러 건물의 지하부분 층간 구조체(보, 슬래브)는 지하외벽(400)을 시공한 후에 상향식으로 시공하면 되며, 다만 이와 같이 지하외벽(400)을 건물의 지하부분 층간 구조체(보, 슬래브)와 별개로 시공하는 경우에는 가설 지지체(310)는 건물의 지하부분 층간 구조체(보, 슬래브)의 시공 상황을 고려하면서 존치 또는 제거하도록 한다. If the present invention is carried out while applying the hypothesis supporting method, this step can be carried out from the bottom up in parallel with the construction of the interlayer structure (beam, slab) of the basement of the building as shown in Figure 1 (f1), but only in this case The temporary support 310 of the location is removed so that the underground interlayer structure of the building constructed in parallel becomes a permanent support. Of course, as shown in FIG. 1 (f2), the basement outer wall 400 may be constructed in a bottom-up or top-down manner apart from the construction of the inter-floor interlayer structure (beam, slab) of the building, in particular, the basement outer wall 400 in a top-down manner. If the construction step (d) adopts the PC member 200 as shown in Figure 3a, the upper and lower connection key 210 is provided with a vertical protruding reinforcing bar 211 is preferably constructed as in Figure 9 (a) The basement interlayer structure (beam, slab) of the building may be constructed in a bottom-up manner after the construction of the basement outer wall 400, but in this way, the basement exterior wall 400 is separated from the basement interlayer structure (beam, slab) of the building. In the case of construction, the temporary support 310 is to be maintained or removed while considering the construction situation of the underground structure interlayer structure (beam, slab) of the building.

본 발명을 영구 지지공법을 적용하면서 실시한다면 본 단계는 하향식 내지 상향식으로 진행할 수 있다. 영구 지지공법이 적용된 경우에서 지하외벽(400)의 하향식 시공은 상기 (b)단계 내지 (e)단계와 함께 하나의 시공사이클을 구성하여 건물 지하부분의 최하층까지 반복 실시하는 방식이다. 다만 이 경우에는 상기 (d)단계를 상하연결키(210)가 수직돌출매입철근(211)으로 마련된 도 3a와 같은 PC부재(200)를 채택하여 실시함이 바람직한데, 그래야 도 9(a)에서와 같이 PC부재(200)가 설치된 상태에서 PC부재(200) 위로만 벽체콘크리트(420)를 타설할 수 있다. 영구 지지공법이 적용된 경우에서 지하외벽(400)의 상향식 시공은 도 1(f)에서와 같이 건물 지하부분의 최하층까지 상기 (b)단계 내지 (e)단계를 반복 실시한 후에 비로소 지하외벽(400)을 상향식으로 시공하는 방식이다. 다만 이 경우에는 상기 (d)단계를 상하연결키(210)가 수직관통개구부(212)로 마련된 도 3b 및 도 3c의 같은 PC부재(200)나 상하연결키가 수직돌출매입철근(211)으로 마련된 경우라도 별도 개구부(콘크리트 타설용 개구부)가 형성된 PC부재를 채택하여 실시하는 것이 바람직한데, 그래야 도 9(b)(c)에서와 같이 PC부재(200)가 설치된 상태에서 PC부재(200)를 통과시키면서 벽체콘크리트(420)를 원활하게 타설할 수 있다. 이와 같이 영구 지지공법이 적용된 경우에서 지하외벽(400)의 하향식 내지 상향식 시공은 지하외벽(400) 시공과정에서 지하외벽(400)과 건물의 지하부분 구조체(기둥, 보, 슬래브)가 일체화되게 된다.If the present invention is carried out while applying the permanent support method, this step may proceed from the top to bottom. When the permanent support method is applied, the top-down construction of the basement outer wall 400 is a method of constructing one construction cycle together with the steps (b) to (e) and repeatedly performing the construction to the lowest floor of the basement part of the building. However, in this case, the step (d) is preferably carried out by adopting the PC member 200 as shown in FIG. 3A provided with the vertical connection key 210 as the vertical protruding reinforcing bar 211, so that FIG. 9 (a) In the state in which the PC member 200 is installed as in the wall concrete 420 can be poured only onto the PC member 200. When the permanent support method is applied, the bottom-up construction of the basement outer wall 400 is performed only after the steps (b) to (e) are repeated to the lowest floor of the basement part of the building as shown in FIG. 1 (f). It is a way of constructing from the bottom up. In this case, however, the step (d) may be performed by the same PC member 200 or the vertical connecting key of FIG. 3B and FIG. 3C having the vertical connecting key 210 provided as the vertical through opening 212 to the vertical protruding reinforcing bar 211. Even if it is provided, it is preferable to adopt a PC member formed with a separate opening (concrete pouring opening), so that the PC member 200 in the state where the PC member 200 is installed as shown in Fig. 9 (b) (c) While passing the wall concrete 420 can be poured smoothly. When the permanent support method is applied as described above, the top-down and bottom-up construction of the basement outer wall 400 is integrated with the basement outer wall 400 and the basement structure (pillar, beam, slab) of the building during the construction of the basement outer wall 400. .

한편, 본 단계는 상기 (d)단계에서 채택된 PC부재(200)에 따라 벽체수직철근 배근에서 조금의 차이가 있다. 도 3a와 같이 상하연결키(210)가 복근의 수직돌출매입철근(211)으로 마련된 PC부재(200)를 채택하여 본 발명을 실시하는 경우라면, 본 단계는 도 8(a)에서와 같이 PC부재의 복근의 수직돌출매입철근(211) 각각에 벽체수직철근(410)을 연결 복근 배근한 후 도 9(a)에서와 같이 벽체콘크리트(420)를 타설하면서 진행한다. 도 3b와 같이 상하연결키(210)가 복근의 벽체수직철근(410) 모두를 수용할 수 있는 수직관통개구부(212)로 마련된 PC부재(200)를 채택하여 본 발명을 실시하는 경우라면, 본 단계는 도 8(b)에서와 같이 PC부재의 수직관통개구부(212)를 통해 벽체수직철근(410)을 복근 배근한 후 도 9(b)에서와 같이 벽체콘크리트(420)를 타설하면서 진행한다. 도 3c와 같이 상하연결키(210)가 벽체수직철근(410) 하나만을 수용할 수 있는 수직관통개구부(212)이 마련된 PC부재(200)를 채택하여 본 발명을 실시하는 경우라면, 본 단계는 도 8(c)에서와 같이 PC부재의 수직관통개구부(212)를 통해 벽체수직철근(410)을 배근함과 아울러 흙막이벽(100)과 PC부재(200) 사이에 벽체수직철근(410)을 배근함으로써 벽체수직철근(410)을 복근 배근한 후 도 9(c)에서와 같이 벽체콘크리트(420)를 타설하면서 진행한다.On the other hand, this step has a slight difference in the wall vertical reinforcement according to the PC member 200 adopted in step (d). If the up and down connecting key 210 adopts the PC member 200 provided with the vertical protruding reinforcing bar 211 of the abdominal muscle as shown in Figure 3a, this step is performed as shown in Figure 8 (a) The wall vertical reinforcing bar 410 is connected to each of the vertical protruding reinforcing bars 211 of the abs of the member, and the wall concrete 420 is poured as shown in FIG. 9 (a). If the upper and lower connection key 210 adopts a PC member 200 provided with a vertical through opening 212 that can accommodate all the vertical wall reinforcement 410 of the abs, as shown in Figure 3b, the present invention, The step is performed by placing the wall vertical reinforcement 410 abs through the vertical through opening 212 of the PC member as shown in Figure 8 (b) and then pouring the wall concrete 420 as shown in Figure 9 (b) . If the upper and lower connection key 210 adopts a PC member 200 provided with a vertical through opening 212 that can accommodate only one wall vertical rebar 410 as shown in FIG. As shown in FIG. 8 (c), the wall vertical rebar 410 is reinforced through the vertical through opening 212 of the PC member, and the wall vertical rebar 410 is disposed between the wall wall 100 and the PC member 200. After the abdominal muscles of the vertical wall reinforcement 410 by the reinforcement proceeds while placing the wall concrete 420 as shown in Figure 9 (c).

본 단계의 진행으로 지하외벽(400)이 완성되며, PC부재(200)는 지하외벽(400)의 일부분이 되어 지하외벽(400)의 현장시공 RC부분과 일체화된다. As the progress of this step, the basement outer wall 400 is completed, the PC member 200 becomes part of the basement outer wall 400 is integrated with the site construction RC portion of the basement outer wall 400.

이상에서 본 발명은 구체적인 실시예를 참조하여 상세히 설명되었으나, 실시예는 본 발명을 예시하기 위한 것일 뿐이므로, 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 치환, 부가 및 변형된 실시 형태들 역시 아래에 첨부한 특허청구범위에 의하여 정하여지는 본 발명의 보호범위에 속한다고 할 것이다.The present invention has been described in detail above with reference to specific embodiments, but the embodiments are only for illustrating the present invention, and thus the embodiments substituted, added, and modified within the scope without departing from the spirit of the present invention are also described below. It will be said to belong to the protection scope of the present invention as defined by the claims appended hereto.

도 1은 본 발명에 따른 '일부분을 PC화한 지하외벽 시공방법'을 가설 지지공법을 적용하면서 실시하는 과정을 도시한다. Figure 1 shows a process of applying the hypothesis support method 'construction of the underground outer wall construction of a part PC in accordance with the present invention.

도 2는 본 발명에 따른 '일부분을 PC화한 지하외벽 시공방법'을 영구 지지공법을 적용하면서 실시하는 과정을 도시한다. Figure 2 shows a process of applying a permanent support method to the 'underground outer wall construction method of a part PC in accordance with the present invention.

도 3a 내지 도 3c는 본 발명에 따른 지하외벽 시공방법에 바람직하게 이용할 수 있는 다양한 PC부재를 도시한다.3A to 3C show various PC members which can be preferably used in the method for constructing the outer wall of the underground according to the present invention.

도 4는 본 발명에 따른 지하외벽 시공방법에서 PC부재 설치단계와 지지체 시공단계를 도시한다.Figure 4 shows the PC member installation step and the support construction step in the underground outer wall construction method according to the present invention.

도 5는 도 4(c)의 PC부재 설치단계에서 뒷채움재 시공상세를 도시한다.Figure 5 shows the backfill construction details in the PC member installation step of Figure 4 (c).

도 6은 도 5(a)의 뒷채움재 시공에서 바람직하게 이용할 수 있는 형상변형 거푸집과 그 이용 상세를 도시한다.FIG. 6 shows the formwork and its use details which can be preferably used in the backfill construction of FIG. 5 (a).

도 7은 도 5(c)의 뒷채움재 시공에서 바람직하게 이용할 수 있는 길이조절형 뒷채움재 조립체를 도시한다.FIG. 7 shows the adjustable backfill assembly that may be preferably used in the backfill construction of FIG. 5 (c).

도 8은 본 발명에 따른 지하외벽 시공방법에서 벽체수직철근 배근단계를 도시한다.8 illustrates a wall vertical reinforcement step in the method for constructing an exterior exterior wall according to the present invention.

도 9는 본 발명에 따른 지하외벽 시공방법에서 벽체콘크리트 타설단계를 도시한다.Figure 9 shows the wall concrete pouring step in the method for constructing the outer exterior wall according to the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

100: 흙막이벽100: retaining wall

110: 내부기둥110: inner pillar

120: 거치브라켓120: mounting bracket

130: 뒷채움재130: backfill

200: PC부재200: PC member

210: 상하연결키210: up-down link key

211: 수직돌출매입철근211: vertical protruding rebar

212: 수직관통개구부212: vertical through opening

220: 측면연결키220: side connection key

221: 엔드플레이트221: end plate

222, 232: 수평돌출매입철근222, 232: horizontal protruding rebar

223: 커플러노출매입철근223: coupler exposure purchase rebar

300: 지지체300: support

310: 가설 지지체310: temporary support

320: 영구 지지체(보)320: permanent support (beam)

330: 영구 지지체(슬래브)330: permanent support (slab)

400: 지하외벽400: outer wall

410: 벽체수직철근410: wall vertical rebar

420: 벽체콘크리트420: concrete wall

Claims (14)

건물의 지하부분 시공에서 지하외벽(400)의 일부분을 PC화한 지하외벽 시공방법으로서,As the underground outer wall construction method of a part of the underground outer wall 400 in the construction of the underground part of the building, (a)흙막이벽(100)을 시공하고 흙막이벽(100) 내부로 내부기둥(110)을 시공하는 단계;(a) constructing the mud wall 100 and constructing the inner pillar 110 into the mud wall 100; (b)흙막이벽(100) 내측 지반을 굴토하는 단계;(b) excavating the inner ground of the mud wall 100; (c)흙막이벽(100)에 거치브라켓(120)을 설치하는 단계;(c) installing the mounting bracket 120 on the earth wall (100); (d)길이방향 상·하부면에 상하연결키(210)를 구비함과 동시에 길이방향 일측면에 측면연결키(220)를 구비하도록 제작된 PC부재(200)를 준비하고, 상기 PC부재(200)를 거치브라켓(120) 위에 거치시키면서 흙막이벽(100)을 따라 연속하게 설치하되 PC부재(200)의 길이방향 타측면이 흙막이벽(100)에 대면하게 설치하는 단계;(d) preparing the PC member 200 manufactured to have the vertical connection key 210 on the upper and lower surfaces of the longitudinal direction and the side connection key 220 on one side of the longitudinal direction, and the PC member ( Step 200 is installed on the mounting bracket 120 while being continuously installed along the retaining wall 100, the other side in the longitudinal direction of the PC member 200 is installed facing the retaining wall 100; (e)상기 PC부재의 측면연결키(220)에 구속시키면서 흙막이벽(100)과 내부기둥(110)을 연결하는 지지체(300)를 시공함으로써, 상기 PC부재(200)와 지지체(300)가 흙막이벽(100)을 지지하도록 시공하는 단계; 그리고,(e) The PC member 200 and the support 300 are constructed by constructing a support 300 connecting the retaining wall 100 and the inner pillar 110 while constraining the side connection key 220 of the PC member. Constructing to support the retaining wall 100; And, (f)상기 PC부재의 상하연결키(210)를 통해 벽체수직철근(410)을 배근한 후 벽체콘크리트(420)를 타설하면서 상기 PC부재(200)와 일체화되도록 지하외벽(400)을 시공하는 단계;(f) constructing the basement outer wall 400 so as to be integrated with the PC member 200 while placing the wall concrete 420 after reinforcing the wall vertical reinforcement 410 through the vertical connection key 210 of the PC member. step; 를 포함하여 이루어지는 것을 특징으로 하는 일부분을 PC화한 지하외벽 시공 방법.PC underground construction method of a portion of the portion comprising a. 제1항에서,In claim 1, 상기 (d)단계는 PC부재를 흙막이벽(100)과 이격하게 위치하도록 설치함과 아울러 흙막이벽(100)과 PC부재(200) 사이에 흙막이벽(100)과 PC부재(200)를 연결하는 뒷채움재(130)를 시공하면서 이루어지며,In the step (d), the PC member is installed to be spaced apart from the barrier wall 100, and the barrier wall 100 and the PC member 200 are connected between the barrier wall 100 and the PC member 200. It is made while constructing the backfill material 130, 상기 (f)단계는 흙막이벽(100)과 PC부재(200) 사이에 벽체수직철근(410)을 배근함과 아울러 상기 PC부재의 상하연결키(210)를 통해 벽체수직철근(410)을 배근함으로써 벽체수직철근(410)을 복근 배근한 후 벽체콘크리트(420)를 타설하면서 이루어지는 것을 특징으로 하는 일부분을 PC화한 지하외벽 시공방법.The step (f) reinforces the wall vertical rebar 410 between the retaining wall 100 and the PC member 200 and reinforces the wall vertical rebar 410 through the vertical connection key 210 of the PC member. By the wall vertical reinforcing bar 410 abs absent by placing a concrete wall 420, a part of the underground outer wall construction method of the PC. 제2항에서,In claim 2, 상기 (d)단계는,In step (d), 흙막이벽(100)과 PC부재(200)를 연결하는 거푸집(131)을 설치한 후 거푸집(131)에 습식재료를 충진하는 방식으로 뒷채움재(130)를 시공하면서 이루어지거나,After installing the formwork 131 connecting the earth wall 100 and the PC member 200 is made while constructing the back-filling material 130 by filling the formwork 131 with a wet material, 길이방향 타측면에 접합철물(233)이 노출되게 장치된 PC부재(200)를 채택하는 한편 연결강재(132)를 흙막이벽(100)과 PC부재(200)에 동시에 접합 설치하는 방 식으로 뒷채움재(130)를 시공하면서 이루어지거나,The PC member 200 is equipped with the joining hardware 233 exposed on the other side in the longitudinal direction, while the connecting steel 132 is joined to the retaining wall 100 and the PC member 200 at the same time. Is made while constructing the ashes 130, 수나사봉 단부에 넓게 확장된 확장지지판(133c)이 마련되는 수나사편(133a);과 암나사봉 단부에 넓게 확장된 확장지지판(133c)이 마련되는 암사나편(133b);으로 구성된 조립체(133)를 흙막이벽(100)과 PC부재(200) 사이에 위치시킨 후 상기 조립체(133)의 체결위치를 조절하여 수나사편과 암나사편의 확장지지판(133c)을 흙막이벽(100)과 PC부재(200)에 압착시키는 방식으로 뒷채움재(130)를 시공하면서 이루어지는 것을 특징으로 하는 일부분을 PC화한 지하외벽 시공방법.An assembly 133 consisting of a male screw piece 133a having an extended support plate 133c extended at the male threaded rod end; and a female screw piece 133b having an extended support plate 133c extended at the female threaded rod end. After positioning between the retaining wall 100 and the PC member 200, by adjusting the fastening position of the assembly 133, the expansion support plate 133c of the male screw piece and the female screw piece to the retaining wall 100 and the PC member 200. The underground outer wall construction method of the PC portion, characterized in that the construction is made while constructing the back-filling material 130 in a pressing manner. 제1항에서,In claim 1, 상기 (f)단계는 상기 PC부재의 상하연결키(210)를 통해 벽체수직철근(410)을 복근 배근한 후 벽체콘크리트(420)를 타설하면서 이루어지는 것을 특징으로 하는 일부분을 PC화한 지하외벽 시공방법.The step (f) is a PC-based underground exterior wall construction method, characterized in that the wall concrete 420 is placed after placing the abs vertically reinforced wall 410 through the vertical connection key 210 of the PC member . 제4항에서,In claim 4, 상기 (d)단계는 길이방향 타측면에 하부돌출턱(231)이 형성된 PC부재(200)를 채택하는 한편 상기 PC부재의 하부돌출턱(231) 위로 그라우팅하여 뒷채움재(130)를 시공하면서 이루어지는 것을 특징으로 하는 일부분을 PC화한 지하외벽 시공방법.The step (d) is performed while constructing the back-filling material 130 by adopting the PC member 200 having the lower projection jaw 231 formed on the other side in the longitudinal direction and grouting the lower projection jaw 231 of the PC member. Underground wall construction method using a part of the PC. 제4항에서,In claim 4, 상기 (d)단계는 길이방향 상부면 또는 하부면에 길이방향홈(251)이 형성된 PC부재(200)를 채택하여 상기 길이방향홈(251)에 수팽창지수재(250)를 장치한 상태에서 이루어지는 것을 특징으로 하는 일부분을 PC화한 지하외벽 시공방법.In the step (d), the PC member 200 having the longitudinal grooves 251 formed in the longitudinal upper surface or the lower surface is adopted to install the water-expandable index member 250 in the longitudinal grooves 251. Underground wall construction method in which the PC part is characterized in that the made. 제1항 내지 제6항 중 어느 한 항에서,In any one of claims 1 to 6, 상기 (d)단계는 상하연결키(210)가 수직돌출매입철근(211) 또는 커플러노출매입철근으로 마련된 PC부재(200)를 채택하면서 이루어지며,The step (d) is made while the vertical connection key 210 adopts a PC member 200 provided with a vertical protruding embedded reinforcing bar 211 or a coupler exposed embedded reinforcing bar, 상기 (f)단계는 벽체수직철근(410)을 상기 PC부재의 수직돌출매입철근(211) 또는 커플러노출매입철근과 연결 배근하면서 이루어지는 것을 특징으로 하는 일부분을 PC화한 지하외벽 시공방법.Wherein the step (f) is the construction of a PC-based underground exterior wall, characterized in that the wall vertical reinforcement (410) is connected to the vertical protrusion embedded reinforcement (211) or coupler exposed embedded reinforcement of the PC member. 제1항 내지 제6항 중 어느 한 항에서,In any one of claims 1 to 6, 상기 (d)단계는 상하연결키(210)가 수직관통개구부(212)로 마련된 PC부재(200)를 채택하면서 이루어지며,The step (d) is made while adopting the PC member 200 is provided with a vertical connection opening 210, the vertical connection opening 212, 상기 (f)단계는 벽체수직철근(410)을 상기 PC부재의 수직관통개구부(212)를 통과하도록 배근하면서 이루어지는 것을 특징으로 하는 일부분을 PC화한 지하외벽 시공방법.Wherein the step (f) is a wall of the reinforcing bar reinforcement 410, the underground outer wall construction method of the PC part, characterized in that the reinforcement to pass through the vertical through the opening 212 of the PC member. 제1항 내지 제6항 중 어느 한 항에서,In any one of claims 1 to 6, 상기 (d)단계는 측면연결키(220)가 엔드플레이트(221)로 마련된 PC부재(200)를 채택하면서 이루어지며, The step (d) is made while the side connection key 220 adopts the PC member 200 provided with the end plate 221, 상기 (e)단계는 지지체(300)를 가설 지지체(310) 또는 영구 지지체(320, 330)로 계획하여 상기 지지체(300)를 상기 PC부재의 엔드플레이트(221)에 접합하면서 이루어지는 것을 특징으로 하는 일부분을 PC화한 지하외벽 시공방법.In the step (e), the support 300 is designed as a temporary support 310 or a permanent support 320 or 330, and the support 300 is bonded to the end plate 221 of the PC member. Underground wall construction method using part of PC. 제1항 내지 제6항 중 어느 한 항에서,In any one of claims 1 to 6, 상기 (d)단계는 측면연결키(220)가 수평돌출매입철근(222) 또는 커플러노출매입철근(223)으로 마련된 PC부재(200)를 채택하면서 이루어지며,The step (d) is made while the side connection key 220 adopts the PC member 200 provided with a horizontal protruding reinforcement reinforcing bar 222 or a coupler exposure reinforcing bar 223, 상기 (e)단계는 지지체(300)를 영구 지지체(320, 330)로 계획하여 상기 영구 지지체(320, 330)의 수평철근을 상기 PC부재의 수평돌출매입철근(222) 또는 커플러노출매입철근(223)과 연결 배근함과 아울러 콘크리트를 타설하면서 이루어지는 것을 특징으로 하는 일부분을 PC화한 지하외벽 시공방법.The step (e) is to plan the support 300 as a permanent support (320, 330) so that the horizontal reinforcement of the permanent support (320, 330) of the horizontal projection embedded reinforcement 222 or coupler exposure embedded reinforcement ( 223) and underground reinforcing wall construction method of the PC portion, characterized in that the connection is made in addition to placing concrete. 제10항에서,In claim 10, 상기 (d)단계는 길이방향 일측면이 울퉁불퉁한 비평탄면으로 처리되도록 제작된 PC부재(200)를 채택하면서 이루어지는 것을 특징으로 하는 일부분을 PC화한 지하외벽 시공방법.Wherein step (d) is a PC-based underground exterior wall construction method, characterized in that the longitudinal one side is made while adopting a PC member (200) made to be treated as an uneven flat surface. 제1항 내지 제6항 중 어느 한 항에서,In any one of claims 1 to 6, 상기 (d)단계는 너비방향 양 측면이 홈과 돌기에 의한 측면요철(241)로 처리되게 제작된 PC부재(200)를 채택하여 PC부재(200) 상호 간을 길이방향으로 연속하게 너비방향으로 맞대게 설치하면서 이루어지는 것을 특징으로 하는 일부분을 PC화한 지하외벽 시공방법.The step (d) adopts the PC member 200, which is made to be treated with the side surface irregularities 241 by the grooves and the projections in both width directions, so that the PC members 200 are continuously in the width direction in the longitudinal direction. A method of constructing a basement outer wall using a part of a PC characterized in that it is installed while facing each other. 지하외벽 시공에서 뒷채움재 시공을 위한 거푸집으로,From the basement wall construction to the formwork for backfill, 외부틀(131a);과, Outer frame 131a; And, 다수개가 병렬로 밀착 배치된 채 상기 외부틀(131a)을 관통 돌출하게 장치되는 이동파이프(131b);를 포함하여 구성되되,And a plurality of moving pipes (131b) are arranged to protrude through the outer frame (131a) in close contact with each other in parallel; 상기 다수개의 이동파이프(131b)는 각각이 개별적으로 밀리고 당겨지면서 외부틀(131a)에서의 돌출길이가 신축하는 것임을 특징으로 하는 형상변형 거푸집.The plurality of moving pipes (131b) is a shape-forming die, characterized in that the protruding length in the outer frame (131a) is stretched while being individually pushed and pulled. 지하외벽 시공에 이용되는 뒷채움재로,As a backfill material used for the construction of underground walls, 수나사봉 단부에 넓게 확장된 확장지지판(133c)이 마련되는 수나사편(133a);과,A male thread piece 133a having an extended support plate 133c wider at the male threaded rod end; And, 암나사봉 단부에 넓게 확장된 확장지지판(133c)이 마련되는 것으로, 암나사봉이 상기 수나사편(133a)의 수나사봉과 체결하게 되는 암나사편(133b);을 포함하여 구성되는 것을 특징으로 하는 길이조절형 뒷채움재 조립체.Widely extended support plate 133c is provided at the end of the female threaded rod, the female threaded rod is a female threaded piece (133b) to be engaged with the male threaded rod of the male threaded piece (133a); adjustable length backfill Reassembly.
KR1020090023501A 2009-02-13 2009-03-19 Construction method of basement wall using the precast concrete member KR101101927B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020090011975 2009-02-13
KR20090011975 2009-02-13

Publications (2)

Publication Number Publication Date
KR20100092847A true KR20100092847A (en) 2010-08-23
KR101101927B1 KR101101927B1 (en) 2012-01-02

Family

ID=42757556

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090023501A KR101101927B1 (en) 2009-02-13 2009-03-19 Construction method of basement wall using the precast concrete member

Country Status (1)

Country Link
KR (1) KR101101927B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101215764B1 (en) * 2011-05-13 2013-01-09 삼성중공업 주식회사 A burial slab structure of an outer wall of an underground construction
CN103899012A (en) * 2014-03-27 2014-07-02 湖南顺天建设集团有限公司 Embedded member of filler wall binding rebar and filler wall binding rebar construction method
CN110185026A (en) * 2019-05-09 2019-08-30 中建八局第一建设有限公司 A kind of diaphram wall and its construction method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101169462B1 (en) 2012-03-08 2012-07-30 (주)엠씨에스에스티기술사사무소 Top-down construction method using post member
KR101415867B1 (en) 2013-04-22 2014-07-09 (주) 에센스 Precast concrete structure construction method for downward construction of underground structures

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100346622B1 (en) 1999-10-30 2002-08-03 삼성중공업 주식회사 Underground construction method using permanent structural members as temporary struts
KR100383268B1 (en) * 2000-07-14 2003-05-12 조재형 method for underground construction of building by using permanent structural member as strut for support retaining wall
KR100766956B1 (en) * 2005-04-11 2007-10-15 (주)에스피에스 Strut system of temporary retaining wall and subgrade external wall construction method utilizing the same system:SRS

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101215764B1 (en) * 2011-05-13 2013-01-09 삼성중공업 주식회사 A burial slab structure of an outer wall of an underground construction
CN103899012A (en) * 2014-03-27 2014-07-02 湖南顺天建设集团有限公司 Embedded member of filler wall binding rebar and filler wall binding rebar construction method
CN110185026A (en) * 2019-05-09 2019-08-30 中建八局第一建设有限公司 A kind of diaphram wall and its construction method
CN110185026B (en) * 2019-05-09 2024-03-22 中建八局第一建设有限公司 Underground diaphragm wall and construction method thereof

Also Published As

Publication number Publication date
KR101101927B1 (en) 2012-01-02

Similar Documents

Publication Publication Date Title
KR100938918B1 (en) Top-down construction method using steel frame by channel
KR100788623B1 (en) Top-down method using precast-concrete colum
KR101301081B1 (en) Wall structure and the construction method therefor
JP5023219B2 (en) Precast temporary structure and construction method thereof
KR101419863B1 (en) Pc panel needless of concrete forms using construction method of cast-in-place step retaining wall for slope reinforcement
KR101772939B1 (en) Non-abutment bridge structure using precast concrete retaining wall and pile, and method for constructing this same
KR20100095986A (en) Construction method of basement wall by combining the precast concrete member with the reinforced concrete member
KR101973565B1 (en) Sheathing method for constructing both sheathing wall and cutoff collar by welding cutoff plate to phc pile with longitudinal plate
KR101193896B1 (en) Pc wall with ancher wire for structrue
KR101101927B1 (en) Construction method of basement wall using the precast concrete member
KR101118263B1 (en) Rain retaining facility and constructing method thereof using precast concrete block
KR102196532B1 (en) Under ground structure construction method using composite steel pile underground column wall and top-down under ground structure therewith
KR101734026B1 (en) Retaining Wal1 Construction Method Using PHC Pile
JP2000265484A (en) CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE BY PCa PILE UNDERGROUND WALL
KR101054696B1 (en) Top-down construction method for underground structure with slurry wall retained by slab diaphragm effect
KR101679727B1 (en) Retaining wall with panel type frictional plate anchor and construction method thereof
KR102079570B1 (en) Soil nailing slope reinforcement system to panel
KR101054718B1 (en) Rahmen bridge using butress and enlarged tendon and rahmen bridge construction method thterefor
KR20100113957A (en) Joint structure and method for constructing slab of underground structures using the same
KR102113291B1 (en) Soil retaining wall using phc pile and construction method thererof
KR20090043625A (en) Method for constructing underground slabs using asymmetric girder
KR101880014B1 (en) Variable filler for supporting column-type wall
KR101271290B1 (en) Underground reclamation type water storage tank having a assembling structure
KR100767953B1 (en) Separating method of Monowall with spandrel girders
KR101664668B1 (en) Structure for connecting earth retaining wall

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20141226

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20151111

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20161227

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20171226

Year of fee payment: 7

LAPS Lapse due to unpaid annual fee