KR20090058062A - New diaphragm wall used trench excavation with double sheetpile system : dss diaphragm wall method - Google Patents
New diaphragm wall used trench excavation with double sheetpile system : dss diaphragm wall method Download PDFInfo
- Publication number
- KR20090058062A KR20090058062A KR1020070124676A KR20070124676A KR20090058062A KR 20090058062 A KR20090058062 A KR 20090058062A KR 1020070124676 A KR1020070124676 A KR 1020070124676A KR 20070124676 A KR20070124676 A KR 20070124676A KR 20090058062 A KR20090058062 A KR 20090058062A
- Authority
- KR
- South Korea
- Prior art keywords
- wall
- underground
- sheet pile
- continuous
- excavation
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/20—Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
The present invention relates to the structure and construction method of the continuous underground wall to resist external forces such as earth pressure and water pressure during construction of underground excavation and to minimize damage to adjacent ground or structures.
The present invention relates to the structure and construction method of the continuous underground wall to resist external forces such as earth pressure and water pressure during construction of underground excavation and to minimize damage to adjacent ground or structures.
In general, underground continuous wall construction method is to install the guide wall (Guide Wall), filling the stabilizer (Bentonite) to the excavation ground to form a hollow wall and then excavation using the equipment such as hang grab, hydro mill. After the excavation, the fabricated reinforcement net is introduced into the hollow wall, and the concrete is poured to form a continuous reinforced concrete wall in the ground.
Underground continuous wall construction method is more rigid than other earthquake construction methods. Therefore, it is structurally safe for long-term construction, and can be used as sidewall of structure.
The conventional underground continuous wall construction method uses bentonite stabilizer to maintain the hollow walls, which causes contamination of groundwater and soil, and requires a large plant and equipment to secure a construction site of a certain size or more. In addition, concrete placing work is performed by using tremi tube in stabilizer mixed with fine soil inside the hollow wall, which causes problems such as deterioration of concrete strength and poor quality, and it contains stabilizer and soil powder used after completion of excavation and concrete placing. It is accompanied by problems in the construction process, such as the treatment of tofu after sludge treatment and concrete curing, difficulty in treating waste generated by wall cleaning during the removal of guide wall, removal of guide wall and underground excavation.
The present invention can form a stable hollow wall that can support the earth pressure and water pressure even in a narrow site without using a stabilizer when trench excavation work for the construction of underground continuous wall, environmentally friendly, shortening the construction period and construction cost It is to provide a structure and construction method of the continuous wall to reduce the cost.
(Solution of problem)
The present invention uses the structure and construction method of the following continuous underground wall to solve the above problems.
Underground continuous walls that support loads such as earth pressure and water pressure during excavation; In the underground continuous wall support structure to be constructed including the external support material to be installed toward the underground continuous wall, the underground continuous wall is an inner support material for supporting the sheet pile and the sheet pile to be installed on the outer side of the underground structural wall and the sheet Reinforcing reinforcing steel and concrete is constructed inside the pile, and forms the structure of the continuous continuous wall of the role of the retaining wall during the excavation and finally acts as the underground structural wall of the structure,
(a) installing a sheet pile on an outer side of an underground structural wall to be formed;
(b) installing an internal support while excavating a trench inside the sheet pile;
(c) reinforcing reinforcement and concrete in the trench after completion of the excavation;
(d) drawing and withdrawing the sheet pile;
(e) installing an external support on the base continuous wall;
(f) repeating step (e) to complete the underground continuous wall support structure; using the method of constructing the continuous underground wall, characterized in that it comprises a.
In the present invention, since the hollow wall is formed by the
First, it is possible to work on a small site because it does not require large equipment, and by installing underground structure walls directly, it maximizes the use of the site and uses a small number of large equipment through simultaneous input of appropriate manpower for excavation scale. Air shortening is possible.
Second, since the sheetpile itself is ordered, the degree of ordering is assured during excavation, and concrete is poured after all the trenches are excavated.
third. Since the gap between the sheets can be arbitrarily adjusted, various building plan designs can be accommodated and separate formwork can be installed inside the hollow walls, allowing the wall thickness of specific parts to be arbitrarily adjusted.
Fourth, there is no soil pollution because it does not use a stable solution (Bentonite), environmentally friendly, concrete strength and quality of the underground wall is sure.
Fifth, the sheetpile can be used as a formwork as it is, and at this time, the economical efficiency can be improved because the sheetpile is recovered by applying a release agent or installing a spacer. Also, the sheetpile installed on the back side can be used as a waterproof wall.
Sixth, guide wall removal, tofu cleanup and wall cleanup are not necessary, so the process is simplified and construction waste is not generated.
Hereinafter, the configuration of the present invention through the specific embodiments shown in the accompanying drawings in detail as follows.
The present invention comprises the steps of installing the sheet pile (1) to the outside of the underground structural wall to be constructed, drilling and installing the H-pile for the excavation of the lower rock layer, while digging the trench inside the sheet pile (1) while supporting the internal support ( 2) installing, after the excavation is completed, forming an underground structural wall by reinforcing reinforcement and concrete placing in the trench, drawing and collecting sheet piles, installing an
Figure 1 is an embodiment of the step of installing the sheet pile (1) on the outside of the underground structural wall. Sheet pile (1) primarily supports earth pressure and water pressure during underground excavation. The shape of the
Figure 2 is an embodiment of the drilling and installation step of the H-pile for excavation of the lower rock bed. This step is to form a structure of a general earth wall to be applied to the rock layer in order to maximize the workability and economics of the present invention. If the lower ground is not a rock layer, it is easy to install the sheet pile (1), or this step is not necessary if the sheet pile (1) is installed to the rock layer.
3 is one embodiment of the step of installing the inner support material (2) while excavating the trench inside the sheet pile (1). The
Trench excavation can use small equipment for the efficiency of excavation, but mainly manpower is used, so it is not necessary to use large equipment like the conventional construction method, so it is possible to work on small land, and through the simultaneous input of appropriate manpower suitable for the excavation scale It is possible to shorten the air and reduce the construction cost compared to the conventional construction method using large equipment.
Figure 4 is an embodiment of the step of forming the underground structural wall by reinforcement and concrete placement in the trench after the end of the excavation. In the embodiment of FIG. 4, the width of the hollow wall by the
5 is one embodiment of the drawing and withdrawal step of the sheet pile (1). In order to facilitate the recovery of the sheet pile (1), a release agent is applied or a spacer is installed, and the economic efficiency is improved through the recycling of the sheet pile (1).
Figure 6 is an embodiment of the step of installing the
(Effects of the Invention)
As described above, since the present invention forms an empty wall by the sheet pile (1) and the internal support member (2), the following effects are expected as compared with the conventional underground continuous wall construction method.
First, it is possible to work on a small site because it does not require large equipment, and by installing underground structure walls directly, it maximizes the use of the site and uses a small number of large equipment through simultaneous input of appropriate manpower for excavation scale. Air shortening is possible.
Second, since the sheetpile itself is ordered, the degree of ordering is assured during excavation, and concrete is poured after all the trenches are excavated.
third. Since the gap between the sheets can be arbitrarily adjusted, various building plan designs can be accommodated and separate formwork can be installed inside the hollow walls, allowing the wall thickness of specific parts to be arbitrarily adjusted.
Fourth, there is no soil pollution because it does not use a stable solution (Bentonite), environmentally friendly, concrete strength and quality of the underground wall is sure.
Fifth, the sheetpile can be used as a formwork as it is, and at this time, the economical efficiency can be improved because the sheetpile is recovered by applying a release agent or installing a spacer. Also, the sheetpile installed on the back side can be used as a waterproof wall.
Sixth, guide wall removal, tofu cleanup and wall cleanup are not necessary, so the process is simplified and construction waste is not generated.
Figure 1 is an embodiment of the step of installing the sheet pile (1) on the outside of the underground structural wall.
2 is one embodiment of the drilling and installation steps of the H-
Figure 3 is one embodiment of the step of installing the
Figure 4 is an embodiment of the step of forming the underground structural wall by reinforcement and concrete placement in the trench after the end of the excavation.
5 is one embodiment of the drawing and recovery step of the sheet pile.
Figure 6 is an embodiment of the step of installing the
<Description of the symbols for the main parts of the drawings>
1: Sheet pile 2: Internal support material
61: h-pile 62: External support
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020070124676A KR20090058062A (en) | 2007-12-04 | 2007-12-04 | New diaphragm wall used trench excavation with double sheetpile system : dss diaphragm wall method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020070124676A KR20090058062A (en) | 2007-12-04 | 2007-12-04 | New diaphragm wall used trench excavation with double sheetpile system : dss diaphragm wall method |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20090058062A true KR20090058062A (en) | 2009-06-09 |
Family
ID=40988597
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020070124676A KR20090058062A (en) | 2007-12-04 | 2007-12-04 | New diaphragm wall used trench excavation with double sheetpile system : dss diaphragm wall method |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20090058062A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101864764A (en) * | 2010-05-04 | 2010-10-20 | 中交第二航务工程局有限公司 | Retaining wall structure of Y-shaped rock-inlaid trough section of diaphgram wall and trough-forming construction method thereof |
CN108844684A (en) * | 2018-04-17 | 2018-11-20 | 中国矿业大学 | A method of monitoring diaphram wall seam crossing leakage scenarios |
CN111997044A (en) * | 2020-08-25 | 2020-11-27 | 徐州工业职业技术学院 | Diaphragm wall construction process based on BIM technology |
-
2007
- 2007-12-04 KR KR1020070124676A patent/KR20090058062A/en not_active Application Discontinuation
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101864764A (en) * | 2010-05-04 | 2010-10-20 | 中交第二航务工程局有限公司 | Retaining wall structure of Y-shaped rock-inlaid trough section of diaphgram wall and trough-forming construction method thereof |
CN108844684A (en) * | 2018-04-17 | 2018-11-20 | 中国矿业大学 | A method of monitoring diaphram wall seam crossing leakage scenarios |
CN111997044A (en) * | 2020-08-25 | 2020-11-27 | 徐州工业职业技术学院 | Diaphragm wall construction process based on BIM technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108086343B (en) | Cantilever type single-side wall body mixed reinforcement and replacement structure and construction method thereof | |
KR100884289B1 (en) | Composite type steel temporary construction and construction method thereof | |
KR20100068597A (en) | A shoring method using arch plate pile and h-pile | |
CN101560771A (en) | Reclaimable foundation pit bracing system and construction method thereof | |
KR101341679B1 (en) | Device for constructing an underground structure and method thereof | |
KR100722665B1 (en) | Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same | |
KR101176592B1 (en) | Earth retaining wall structure constructing method using prestressed tendon | |
CN101560766B (en) | Grid-like underground continuous wall plate and production method thereof | |
CN113216213B (en) | Basement waterproof foundation pit structure and construction method | |
JP5351125B2 (en) | Open shield machine start method of open shield method | |
KR20090058062A (en) | New diaphragm wall used trench excavation with double sheetpile system : dss diaphragm wall method | |
CN212294747U (en) | Pipe jacking well structure | |
CN206428707U (en) | A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation | |
CN102418348A (en) | Construction technology of using occlusive pile to form underground continuous wall | |
KR101041264B1 (en) | Displacement control tunnelling reinforcing structure using pressurizing support | |
CN112854198B (en) | Construction method for treating old foundation of underground diaphragm wall | |
KR101221084B1 (en) | Temporary pile using bending restoring force and temporary structure construction method therewith | |
KR200403694Y1 (en) | Guide pipe for sheet pile | |
JP3682704B2 (en) | Built-in column construction method without casing | |
CN208023591U (en) | A kind of foundation pit supporting construction of steel sheet pile combined deposited pile | |
JP6691831B2 (en) | Underground construction method for existing buildings | |
CN111456029B (en) | Foundation pit supporting structure and construction method thereof | |
CN214738100U (en) | Go up and stride existing underground structure's foundation ditch envelope and newly-built structure | |
JP2015108262A (en) | Reaction receiving member and positioning method for upper surface of permanent steel column | |
CN204401648U (en) | Circular Pit inwall reinforcing cage binding stand |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
WITN | Withdrawal due to no request for examination |