KR20090013554A - Constructing method of top-down type retaining wall - Google Patents

Constructing method of top-down type retaining wall Download PDF

Info

Publication number
KR20090013554A
KR20090013554A KR1020070077796A KR20070077796A KR20090013554A KR 20090013554 A KR20090013554 A KR 20090013554A KR 1020070077796 A KR1020070077796 A KR 1020070077796A KR 20070077796 A KR20070077796 A KR 20070077796A KR 20090013554 A KR20090013554 A KR 20090013554A
Authority
KR
South Korea
Prior art keywords
thumb pile
panel
retaining wall
ground
pile
Prior art date
Application number
KR1020070077796A
Other languages
Korean (ko)
Inventor
홍성영
Original Assignee
주식회사 스마텍엔지니어링
주식회사 이산
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 스마텍엔지니어링, 주식회사 이산 filed Critical 주식회사 스마텍엔지니어링
Priority to KR1020070077796A priority Critical patent/KR20090013554A/en
Publication of KR20090013554A publication Critical patent/KR20090013554A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0216Cribbing walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Soil Sciences (AREA)
  • Retaining Walls (AREA)

Abstract

A construction method of a top-down type vertical cutting slope reinforcement retaining wall is provided to construct a vertical cutting slope reinforcement retaining wall safely, rapidly and economically without installing a temporary structure, etc. A construction method of a top-down type vertical cutting slope reinforcement retaining wall comprises the steps of installing a soldier pile(20) to the ground to be deeper than the planned height of the bottom of a retaining wall, excavating the front ground of the soldier pile, installing a panel(1) to the front of the soldier pile and placing filler(2) in a space between the front of the soldier pile and the rear of the panel, and repeating above mentioned steps downward by states, thereby forming a retaining wall to have the planned height, wherein a tension reinforcement(40) is installed to the ground to apply bearing capacity to the rear of the soldier pile to prevent the solider pile from turning over toward the front by rear earth pressure by excavating the ground toward the front of the solider pile.

Description

Constructing Method of Top-down Type Retaining Wall

The present invention relates to a construction method of a reversing vertical cut slope reinforcing retaining wall, and more particularly, in installing the retaining wall on the front surface of a vertically cut slope, after cutting the slope downward with a cutting plan and moving upwards from below. Unlike the conventional method of installing the retaining wall by sequentially constructing the cutouts at the top of the slope, the excavation is performed by digging down the slope downward, and the wall of the retaining wall is sequentially constructed, thereby quickly retaining the retaining wall for the reinforcement of the vertical cutout slope. It relates to a construction method of a retaining wall of a new structure that can be constructed economically and economically.

Due to the nature of Korea, which has a lot of mountainous terrain, many slopes are cut off during the construction of roads, railways, industrial complexes and residential lands, and retaining walls are often installed at the bottom of the cut slopes. However, as land prices increase and civil complaints increase due to environmental damage, it is increasingly necessary to construct retaining walls by vertically cutting slopes when installing such retaining walls.

As a method of constructing such a cut slope retaining wall, conventionally, a method of installing the retaining wall sequentially from the bottom after cutting the slope inclinedly has been used. However, when the slant is cut in such a manner, the amount of cut soil and the backfill after the retaining wall construction increase, resulting in an increase in the amount of earthwork, which causes the cost of construction and an increase in the construction period. In addition, problems such as collapse of the slope may occur at the time of cutting, or at the stage before the retaining wall construction after cutting.

In particular, when there is a facility such as a building on the back of the retaining wall installation position, there is a limit that it is impossible to cut it inclined itself. In this case, it is necessary to cut vertically for the protection of the facility. To ensure safety when cutting, a separate provision for preventing the collapse of the vertical cutting surface is to be installed separately, and after the cutting is completed, the retaining wall must be constructed upward from the bottom. Therefore, the cost according to the installation of the cut-away collapsed temporary installation is increased, and since the retaining wall is constructed only from the bottom of the cut-out surface, the increase in construction period cannot be avoided.

In addition, in the case of the retaining wall installed on the front of the cut slope, a retaining wall having an aesthetic appearance that can be harmonized with the surrounding environment is required. In the conventional construction method, the retaining wall exterior is beautiful because the wall of the retaining wall is constructed using site-cast concrete. There is a limit that is difficult to achieve. It is also possible to use a method of attaching the stone to the front of the retaining wall, but in this case, it is very disadvantageous in terms of cost and time because the stone must be manually attached by hand, and in the case of the high retaining wall, a separate work scaffold and scaffolding must be installed. In addition to the increase, the risk of a safety accident is high.

The present invention was developed to solve the above problems, and in the construction of the retaining wall by cutting the slope vertically or almost vertically, unlike the conventional method of constructing the retaining wall from below after vertical cutting, vertical cutting is possible. It aims to be able to construct vertical cut slope reinforcement retaining wall safely, quickly and inexpensively without installing any temporary equipment to prevent the collapse of the slope at the stage before or after the cutting.

In addition, the present invention in the construction of the retaining wall by cutting the slope vertically or almost close to the vertical, by applying a factory-made panel of the retaining wall wall to give a pattern to the panel itself or to the front panel The object of the present invention is to attach decorative materials such as stones, tiles, etc. to have a beautiful appearance, and to efficiently construct a vertical cut slope reinforcing retaining wall having excellent aesthetic appearance.

In order to achieve the above object, in the present invention, the thumb pile is installed on the ground to a depth greater than the planned height of the retaining wall; Excavating the front ground of the thumb pile and installing the panel on the front of the thumb pile in a stepwise manner to construct a wall of the retaining wall having a plan; Excavating the ground in the front direction of the thumb pile so that the thumb pile is not conducted in the front direction by the back earth pressure, so that the ground is provided with a tension reinforcement to force the tension reinforcement to support the rear of the thumb pile A retaining wall construction method is provided.

In the retaining wall construction method of the present invention as described above, for the installation of the tensile reinforcement, when the ground vertically cut above the height that can be installed one panel to the front of the thumb pile, for the tension reinforcement to the rear of the thumb pile Drill holes; Inserting and placing the tensile reinforcing member into the hole for the tensile reinforcing material so as to be installed on the rear ground through the thumb pile, and injecting a grouting material into the hole for the tensile reinforcing material to fix one end of the tensile reinforcing material in the ground; Disposing the panel at intervals from the thumb pile to the front of the thumb pile, and fixing the other end of the tensile reinforcement to the front of the panel while the other end of the tensile reinforcement penetrates the panel; Placing a filler in the gap between the front of the thumb pile and the back of the panel; The wall of the retaining wall is constructed by repeating the above operation to the plan of the retaining wall wall, the front vertical ground cutting operation of the thumb pile, the tension reinforcing material installation work, the panel installation work, the fixing work of the tension reinforcement material, The wall of the retaining wall may be constructed by repeating the filling of the filling material to the plan of the retaining wall.

In this case, it is preferable that a recess is formed on the front surface of the panel so that the fixed end of the tensile reinforcement does not protrude outward so that the other end of the tensile reinforcement is located in the recess.

In addition, in the retaining wall construction method of the present invention, in order to install the tensile reinforcement member, when the ground is vertically cut to a height higher than the height at which one panel can be installed in front of the thumb pile, the hole for the tension reinforcement member is located behind the thumb pile. Perforating; The tensile reinforcing member is inserted into the tensile reinforcing material hole so as to be installed on the rear ground through the thumb pile, and the grouting material is injected into the hole for the tensile reinforcing material to fix one end of the tensile reinforcing material in the ground. Fixing the other end of the to the thumb pile; Disposing a panel at a distance from the thumb pile to the front of the thumb pile; Placing a filler in the gap between the front of the thumb pile and the back of the panel; The wall of the retaining wall may be constructed by repeating the front vertical ground cutting of the thumb pile, installing and fixing the tension reinforcement member, installing the panel, and placing the filler material up to the plan of the retaining wall wall. .

In addition, in the retaining wall construction method of the present invention, in order to install the tensile reinforcement member, when the ground is vertically cut to a height higher than the height at which one panel can be installed in front of the thumb pile, the hole for the tension reinforcement member is located behind the thumb pile. Perforating; The tensile reinforcing member is inserted into the tensile reinforcing material hole so as to be installed on the rear ground through the thumb pile, and the grouting material is injected into the hole for the tensile reinforcing material to fix one end of the tensile reinforcing material in the ground. Fixing the other end of the tension reinforcement to the thumb pile in a tensioned state; Disposing a panel at a distance from the thumb pile to the front of the thumb pile; Placing a filler in the gap between the front of the thumb pile and the back of the panel; The wall of the retaining wall may be constructed by repeating the front ground vertical cutting of the thumb pile, the installation of the panel, and the placing of the filler material up to the plan of the retaining wall wall.

In particular, in the present invention as described above, by filling the filling material inlet on the front top of the panel and injecting the filling material in the gap between the front of the thumb pile and the back of the panel through the filling material inlet; After the filling of the filling material is completed, it may have a configuration to close the filling material inlet using a stopper, and may be provided on the ground front between the neighboring thumb piles to install a porous drain for draining the water flowing from the back soil.

According to the present invention, in constructing the retaining wall by cutting the slope vertically or almost close to vertical, unlike the conventional method of constructing the wall of the retaining wall from below after the vertical cutting, the retaining wall wall is cut off when the ground is vertically cut. It is possible to construct a vertical cut slope reinforcement retaining wall safely, quickly and at low cost without installing a temporary facility to prevent the collapse of the slope before the construction stage.

In addition, according to the present invention, when constructing the retaining wall by cutting the slope vertically or almost vertically, by applying the factory manufactured panel in the precast method to construct the wall of the retaining wall, the panel itself is provided with a pattern or the panel By attaching a decorative material such as stone, tile on the front to have a beautiful appearance, it is possible to efficiently construct a vertical cut slope reinforcement retaining wall with excellent aesthetics.

Next, a detailed configuration of the present invention will be described with reference to the drawings showing an embodiment of the present invention.

Figures 1a to 7b is a view showing each step of constructing a vertical cut slope reinforcement retaining wall according to the present invention, Figures 1a, 2a, 3a, 4a, 5a, 6a and 7a 1B, 2B, 3B, 4B, 5B, 6B, and 7B are plan views of slopes, that is, views viewed from above.

First, as shown in Figs. 1A to 3B, the thumb pile 20 is inserted into the ground for constructing the retaining wall. The thumb pile 20 is to be constructed to a depth greater than the bottom plan (計劃 高) of the retaining wall, first, as shown in Figures 1a and 1b to drill the hole 10 for installing the thumb pile 20 in the ground and Figure 2a 2b, after the thumb pile 20 is inserted into the hole 10 and installed therein, the filler 10 such as concrete, mortar, etc. is formed in the hole 10 as shown in FIGS. 3a and 3b. Fill and fill. As will be described later, since the tension reinforcement 40 must be installed past the thumb pile 20, as illustrated in the figure, the thumb pile 20 having the "c" cross-section with the "c" cross-section positioned to face each other combined It is preferable to use a thumb pile. In the case of the thumb pile 20 having such a configuration, it is very easy to allow the tension reinforcing material 40 to pass through the thumb pile 20 as described later. However, in the present invention, the thumb pile 20 is not necessarily limited to the thumb pile combined by placing the c-shaped thumb piles facing each other as described above, as long as the thumb pile having any configuration as long as the tensile reinforcement can pass through. It is available. For example, a thumb pile may be used that has a cross section and is horizontally perforated with holes through which tension reinforcement can pass.

In the drawing, the reference numeral 50 briefly shows a facility 50 such as a building located on the back of the retaining wall installation position.

As described above, in the present invention, the thumb pile 20 may be excavated in a downward step while supporting the ground of the back surface by using the self-supporting force of the thumb pile 20 in the state where the thumb pile 20 is installed on the ground.

On the other hand, when excavating the ground step by step downward, in order to further strengthen the self-supporting force of the pile 20 in the present invention by installing a tension reinforcing material 40, such as earth bolts, earth anchors on the ground, the tensile reinforcing material 40 By applying a supporting force to the rear of the thumb pile 20, the thumb pile 20 is prevented from falling in the front direction by the earth pressure of the back ground.

Referring to Figure 4a to 8, according to an embodiment of the present invention, looking at each step of installing a plurality of tensile reinforcing material 40, the front of the thumb pile 20 in the state where the thumb pile 20 is installed After cutting the ground vertically above the height at which more than one panel 1 can be installed, the hole 41 for tension reinforcement is drilled to the rear of the thumb pile 20. That is, through the thumb pile 20 to the perforations of the tensile reinforcing material 41 so that the tensile reinforcing material 40 can be embedded in the back ground. Although two panels 1 are shown in the drawing, the vertical cutting height is not limited thereto and may be cut to a height of one panel according to a site situation.

When the tensile reinforcing material hole 41 is drilled in this manner, the tensile reinforcing material 40 inserted and disposed in the tensile reinforcing material hole 41 and fixed at one end thereof in the ground is the thumb toward the front of the thumb pile 20. To penetrate the panel (1) arranged at intervals with the pile 20, the other end of the tension reinforcement (40) is fixed to the panel (1).

Specifically, the tensile reinforcing material 40 is inserted into the tensile reinforcing material hole 41 so as to be installed on the rear ground after passing through the thumb pile 20, and the grouting material 42 is disposed in the tensile reinforcing material hole 41. Injection to allow the tension reinforcement 40 to be secured in the ground (see FIGS. 5A and 5B). As described above, one end of the tension reinforcement 40 is fixed to the ground, and the other end of the tension reinforcement 40 is fixed to the front of the thumb pile 20 or penetrates the panel 1 to the front of the panel 1. It can be fixed to.

6A shows an embodiment in which the other end of the tension reinforcement 40 is fixed to the front side of the panel 1, in which the panel 1 is spaced apart from the thumb pile 20 toward the front of the thumb pile 20. The other end of the tensile reinforcing material 40 can be fixed to the front surface of the panel 1 in a state in which the other end of the tensile reinforcing material 40 is penetrated through the panel 1. At this time, a spacer (not shown) may be disposed to maintain a gap between the thumb pile 20 and the panel 1.

On the other hand, prior to installing the tension reinforcement 40, the panel 1 is placed in advance in the state of the thumb pile 20 to the front of the thumb pile 20, the tension reinforcement to penetrate the panel (1) After the 40 is inserted, one end thereof may be fixed in the tension reinforcing material hole 41 and the other end may be fixed in front of the panel 1.

As such, after the panel 1 is installed, the filler 2 such as backfill concrete or mortar is placed in the gap between the front of the thumb pile 20 and the rear surface of the panel 1 as shown in FIGS. 7A and 7B. Pour.

9 is a perspective view showing a panel 1 is installed on the front of the thumb pile 20, the tension reinforcing material 40 is fixed to the front of the panel 1, the panel (1) In the installation on the front of the pile 20, the panel 1 may be installed using the ground, but as shown in the figure, after installing the base 21 on the front of the thumb pile 20, the panel (1) It may be placed thereon, the gap between the front of the thumb pile 20 and the back of the panel 1 through the filler inlet (3) by forming a filler inlet 3 in the upper front of the panel (1) It is also possible to easily inject the filler 2 into the pouring. In this case, after the filling of the filling material 2 is completed, it is preferable to close the filling material injection hole 3 using the stopper 4 in view of aesthetics and the like.

As described above, after the panel 1 is installed on the front of the thumb pile 20, the ground is further vertically cut in the downward direction of the installed panel 1, and the above work is repeated until the planned height is reached. You will build a retaining wall. That is, the vertical ground cutting operation of the pile 20, the tension reinforcing material 40 and the panel 1 installation work, the tension reinforcing material 40 fixed work, the filling material (2) placing work By repeating the bottom plan of the retaining wall wall, the wall of the retaining wall is constructed. In FIG. 8, a state in which the retaining wall is constructed by sequentially carrying out the construction steps from the top to the bottom is shown in side view.

On the other hand, as described above, unlike the embodiment shown in Figures 6a and 6b, the other end of the tension reinforcement 40 can also be fixed to the thumb pile 20, 10a, 10b, 11a and FIG. In FIG. 11B, an embodiment in which the other end of the tension reinforcement 40 is fixed to the front of the thumb pile 20 is shown in a side view and a plan view, respectively. As shown in the figure, the grouting material 42 is injected into the hole for tension reinforcing material 42, and the other end of the tension reinforcing material 40 is fixed in the ground while the one end of the tensile reinforcing material 40 is the thumb pile 20. After fixing to the front () 10a and 10b, it is possible to install the panel 1 on the front of the thumb pile 20 (Figs. 11a and 11b).

Subsequently, the vertical ground cutting operation of the pile 20 in the front direction, the installation and fixing of the tension reinforcing material 40, the installation of the panel 1, and the pouring of the filler material 2 are performed at the bottom of the retaining wall. By repeating the plan, the walls of the retaining wall are constructed.

There are various methods of attaching and attaching the panel 1 to the front of the thumb pile 20. A coupling member such as a coupling bolt is installed through the panel 1 so that an end of the coupling member is connected to the thumb pile 20. The front panel may be coupled to the front panel, and the panel 1 may be installed on the front of the thumb pile 20 in various other ways.

After the panel 1 is installed at intervals on the front of the thumb pile 20, the front panel and the panel (the front of the thumb pile 20, similar to the embodiment shown in Figures 6a, 6b, 7a and 7b) Fill the filling material (2) such as backfill concrete or mortar in the gap between the back of 1).

On the other hand, the other end portion of the tensile reinforcing material 40 is fixed through the panel 1 in the front of the panel 1 may be modified as follows. 12 shows a part of the retaining wall constructed according to the modified embodiment of the present invention in a plan view, in which a recess 5 is formed on the front surface of the panel 1 so that the fixing end of the tension reinforcement 40 is recessed. By being located in the part 5, it is possible to prevent the fixing end of the tensile reinforcing material 40 from protruding to the outside.

Meanwhile, a porous drain 23 may be installed on the ground front between neighboring thumb piles 20 so that water flowing from the rear soil may be easily drained.

On the other hand, in the present invention, when the support force to the rear acting on the thumb pile 20 by the tension reinforcing material 40 is sufficient, for example, when the tension is applied to the tension reinforcing material 40, the tension is settled The number of reinforcement 40 can be reduced.

Meanwhile, in the present invention, the panel 1 may have a beautiful appearance by giving a pattern on the front surface or by attaching a decoration such as a stone or a tile. Therefore, according to the present invention, there is an advantage that the aesthetics of the retaining wall can be easily improved.

Figures 1a to 7b is a view showing each step of constructing a vertical cut slope reinforcement retaining wall according to the present invention, Figures 1a, 2a, 3a, 4a, 5a, 6a and 7a is a side view of the slope 1B, 2B, 3B, 4B, 5B, 6B, and 7B are plan views of slopes.

8 is a schematic side view showing a state in which a retaining wall is constructed by sequentially performing a construction step from the top of the ground to the bottom according to one embodiment of the construction method according to the present invention.

Figure 9 is a schematic perspective view showing the shape of the panel installed on the front of the thumb pile in the present invention.

10a, 10b, 11a and 11b is another embodiment of the construction method according to the present invention, respectively, a schematic side view showing the construction step according to the embodiment in which the other end of the tension reinforcement is fixed to the front of the thumb pile And plan view.

12 is a plan sectional view showing a part of the retaining wall constructed by the modified embodiment of the present invention.

* Description of the symbols for the main parts of the drawings *

1: Panel

10: hole

20: thumb pile

Claims (8)

The thumb pile 20 is installed in the ground to a depth greater than the bottom plan of the retaining wall; Excavating the front ground of the thumb pile 20 and installing the panel (1) on the front of the thumb pile 20, the filling material (2) in the gap between the front of the thumb pile 20 and the back surface of the panel (1) Constructing the wall of the retaining wall so as to have a plan by repeating the work of pouring the step by step downwardly; Due to the excavation of the ground in the front direction of the thumb pile 20, the thumb pile 20 is not conducted in the front direction by the back earth pressure, and the ground is provided with a tensile reinforcement 40 to the tensile reinforcement 40 Retaining wall construction method characterized in that to apply a supporting force to the rear of the thumb pile (20). The method of claim 1, In order to install the tensile reinforcement 40, when the ground is vertically cut above the height that can be installed one panel (1) to the front of the thumb pile 20, the tension reinforcement to the rear of the thumb pile 20 Drilling holes 41;  The panel 1 having a tension reinforcement 40 inserted and disposed in the tension reinforcement hole 41 and having one end fixed in the ground at a distance from the thumb pile 20 to the front of the thumb pile 20. Retaining wall construction method characterized in that the other end is fixed to the panel (1) so as to pass through. The method of claim 2, Drilling the hole 41 for the tension reinforcement, and installing the tension reinforcement 40 in the tension reinforcing hole (41) to fix the panel (1), the front ground excavation work of the thumb pile 20 , The step of repeating stepwise downward with the installation of the panel (1) of the front of the thumb pile 20 and the filling material (2) of the gap between the front of the pile 20 and the back of the panel (1). Retaining wall construction method. The method of claim 2, The recess 5 is formed on the front surface of the panel 1 so that the other end of the tensile reinforcement 40 does not protrude to the outside so that the other end of the tensile reinforcement 40 is located in the recess 5. Retaining wall construction method characterized in that. The method of claim 1, In order to install the tensile reinforcement 40, when the ground is vertically cut above the height that can be installed one panel (1) to the front of the thumb pile 20, the tension reinforcement to the rear of the thumb pile 20 Drilling holes 41;  The other end of the tensile reinforcing member 40 inserted and disposed in the tensile reinforcing member hole 41 and having one end fixed in the ground, to be fixed to the thumb pile 20; Retaining wall construction method, characterized in that the panel (1) is arranged at a distance from the thumb pile 20 to the front of the thumb pile (20). The method of claim 4, wherein Drilling the hole 41 for the tension reinforcement, and installing the tension reinforcement 40 in the hole 41 for the tension reinforcement to secure the thumb pile 20, excavating the front ground of the thumb pile 20 Work, the installation of the panel (1) in the front of the thumb pile 20 and the step of placing the filling material (2) of the gap between the front of the pile 20 and the back of the panel (1) characterized in that it is repeated step by step downward. Retaining wall construction method. The method according to any one of claims 1 to 6, Filler 2 is formed at the top of the front surface of the panel 1, and the filler 2 is injected into the gap between the front surface of the thumb pile 20 and the rear surface of the panel 1 through the filler material opening 3. To; Retaining wall construction method characterized in that after the injection of the filler material (2) is completed, the filler inlet (3) is closed using a stopper (4). The method according to any one of claims 1 to 6, Retaining wall construction method characterized in that a porous drainage material for draining the water flowing from the back soil is installed on the ground front between the adjacent thumb pile (20).
KR1020070077796A 2007-08-02 2007-08-02 Constructing method of top-down type retaining wall KR20090013554A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020070077796A KR20090013554A (en) 2007-08-02 2007-08-02 Constructing method of top-down type retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020070077796A KR20090013554A (en) 2007-08-02 2007-08-02 Constructing method of top-down type retaining wall

Publications (1)

Publication Number Publication Date
KR20090013554A true KR20090013554A (en) 2009-02-05

Family

ID=40683975

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020070077796A KR20090013554A (en) 2007-08-02 2007-08-02 Constructing method of top-down type retaining wall

Country Status (1)

Country Link
KR (1) KR20090013554A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101147459B1 (en) * 2011-08-04 2012-05-21 이평우 Construction method of cutting the ground retaining wall using the pole
KR101147460B1 (en) * 2011-07-19 2012-05-21 이평우 Cutting the ground retaining wall using the pole and construction method of the same
KR101599931B1 (en) * 2015-03-23 2016-03-04 이상현 Retaining Wall using Precast Panels and PHC Piles having Steel Bands, and Constructing Method of such Retaining Wall
CN111235989A (en) * 2020-03-09 2020-06-05 中铁二院工程集团有限责任公司 Soil cutting pre-reinforcing structure and construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101147460B1 (en) * 2011-07-19 2012-05-21 이평우 Cutting the ground retaining wall using the pole and construction method of the same
KR101147459B1 (en) * 2011-08-04 2012-05-21 이평우 Construction method of cutting the ground retaining wall using the pole
KR101599931B1 (en) * 2015-03-23 2016-03-04 이상현 Retaining Wall using Precast Panels and PHC Piles having Steel Bands, and Constructing Method of such Retaining Wall
CN111235989A (en) * 2020-03-09 2020-06-05 中铁二院工程集团有限责任公司 Soil cutting pre-reinforcing structure and construction method
CN111235989B (en) * 2020-03-09 2024-03-12 中铁二院工程集团有限责任公司 Construction method of soil cutting pre-reinforcement structure

Similar Documents

Publication Publication Date Title
EP3521514B1 (en) Permanent prefabricated braced wall
KR101612521B1 (en) Method for constructing underground structures restraining transformation and using external wall
KR20130056725A (en) Retaining wall with the function of angle adjustmetnt for precast panel
KR100468035B1 (en) A Precast Concrete Block for Retaining-Wall and Construction Method of Retaining-Wall for using Top-down Method
KR101843023B1 (en) Shear connector for temporary retaining wall file and building outer wall, and method for constructing an underground structure using thereof
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
JP6632028B2 (en) Concrete assembly retaining wall
KR20090013554A (en) Constructing method of top-down type retaining wall
CN108035360B (en) A method of for pattern foundation pit supporting structure
KR20080025219A (en) Underground outer wall construction method using deck-plate and deck-plate for constructing underground outer wall
KR102111153B1 (en) Retaining Wall Panel Structure using PC Strand
KR101052363B1 (en) Freestanding Digging Method for Deep Excavation
CN114263187A (en) Foundation pit bottom plate force transmission structure and construction method thereof
KR100948492B1 (en) Constructing Method of Top-down type Retaining Wall
KR101328027B1 (en) Cutting the ground area breast wall and slant safe-guard structure
KR100515789B1 (en) Shoring structure of concrete base slab for prefabricate structure
JP2011157719A (en) Earth retaining method
KR20110034831A (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
KR101524302B1 (en) Construction method for underground structure without temporary structure
KR20200088659A (en) Top-down type underground structure construction method using earth support plate
KR100990820B1 (en) Constructing Method of Top-down type Retaining Wall
KR100638841B1 (en) Method for constructing cellar
KR102322702B1 (en) Construction method of ground-penetrating concrete building
KR102312126B1 (en) Temporary retaining wall structure and method construturing the same
KR100958251B1 (en) Constructing Method of Top-down type Retaining Wall

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
E902 Notification of reason for refusal
E601 Decision to refuse application