KR20070046378A - Temporary retaining wall structure for water works - Google Patents

Temporary retaining wall structure for water works Download PDF

Info

Publication number
KR20070046378A
KR20070046378A KR1020050103032A KR20050103032A KR20070046378A KR 20070046378 A KR20070046378 A KR 20070046378A KR 1020050103032 A KR1020050103032 A KR 1020050103032A KR 20050103032 A KR20050103032 A KR 20050103032A KR 20070046378 A KR20070046378 A KR 20070046378A
Authority
KR
South Korea
Prior art keywords
thumb pile
guide member
guide
thumb
earth
Prior art date
Application number
KR1020050103032A
Other languages
Korean (ko)
Other versions
KR100744192B1 (en
Inventor
윤은중
Original Assignee
윤은중
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 윤은중 filed Critical 윤은중
Priority to KR1020050103032A priority Critical patent/KR100744192B1/en
Publication of KR20070046378A publication Critical patent/KR20070046378A/en
Application granted granted Critical
Publication of KR100744192B1 publication Critical patent/KR100744192B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • E02D17/083Shoring struts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

본 발명은 지반(1)의 터파기 작업에 의해 형성된 관로공사용 굴토부(2)의 측면붕괴를 방지하기 위하여 설치되는 관로공사용 간이 흙막이 구조물에 관한 것으로서, 심부에 상하방향으로 엄지말뚝 가이드용 관통공(101)이 형성되고, 측부에 상부 흙막이부재 결합부(110)가 형성됨과 아울러, 굴토부(2)의 측면에 인접하여 소정 간격을 두고 설치되는 복수의 엄지말뚝 가이드부재(100)와; 엄지말뚝 가이드용 관통공(101)에 삽입되어 하측 토체에 근입되도록 설치됨과 아울러, 측부에 하부 흙막이부재 결합부(210)가 형성된 복수의 엄지말뚝(200)과; 복수의 엄지말뚝 가이드부재(100)의 상부 흙막이부재 결합부(110) 및 복수의 엄지말뚝(200)의 하부 흙막이부재 결합부(210) 사이에 결합되는 흙막이부재(300)를; 포함하는 관로공사용 간이 흙막이 구조물을 제시함으로써, 시공이 용이하고 안전하게 하면서도, 자재의 재활용률을 증대시킬 수 있도록 한다.The present invention relates to a simple earth block structure for the pipe liner is installed to prevent the side collapse of the pipe liner's oyster excavation (2) formed by the excavation of the ground (1), the through-hole for the thumb pile guide in the vertical direction A plurality of thumb pile guide members 100 formed at a side, and having an upper retaining member coupling part 110 formed at a side thereof, and installed at predetermined intervals adjacent to the side surface of the pit part 2; A plurality of thumb piles 200 inserted into the through-holes 101 for the thumb pile guide and installed in the lower soil body, and having a lower retaining member coupling part 210 formed at a side thereof; An earth retaining member 300 coupled between the upper earth retaining member engaging portion 110 of the plurality of thumb pile guide members 100 and the lower earth retaining member engaging portion 210 of the plurality of thumb stakes 200; By presenting a simple earth block structure for use by the pipeline, it is possible to increase the recycling rate of the material while making the construction easier and safer.

흙막이, 토류판 Earth Block, Earth Plate

Description

관로공사용 간이 흙막이 구조물{TEMPORARY RETAINING WALL STRUCTURE FOR WATER WORKS}TEMPORARY RETAINING WALL STRUCTURE FOR WATER WORKS}

도 1 내지 도 14는 본 발명에 의한 관로공사용 간이 흙막이 구조물의 실시예를 도시한 것으로서,1 to 14 are shown as an embodiment of a simple earth block structure for use in pipeline construction according to the present invention,

도 1은 평면도.1 is a plan view.

도 2는 제1실시예의 부분사시도.2 is a partial perspective view of the first embodiment;

도 3a 및 3b는 제1실시예의 시공과정을 나타낸 사시도.3a and 3b are perspective views showing the construction process of the first embodiment.

도 4는 제2실시예의 단면도.4 is a sectional view of a second embodiment;

도 5는 제3실시예의 단면도.5 is a sectional view of a third embodiment.

도 6은 제4실시예의 단면도.6 is a sectional view of a fourth embodiment.

도 7은 제5실시예의 단면도.7 is a sectional view of a fifth embodiment.

도 8은 제5실시예의 사시도.8 is a perspective view of a fifth embodiment;

도 9는 제6실시예의 단면도.9 is a sectional view of a sixth embodiment;

도 10은 제7실시예의 부분사시도.10 is a partial perspective view of a seventh embodiment.

도 11은 제7실시예의 단면도.11 is a sectional view of a seventh embodiment.

도 12a 및 12b는 제7실시예의 시공과정을 나타낸 단면도.12A and 12B are sectional views showing the construction process of the seventh embodiment;

도 13은 제8실시예의 분해사시도.13 is an exploded perspective view of the eighth embodiment;

도 14는 제8실시예의 사시도.14 is a perspective view of an eighth embodiment.

도 15 내지 도 17은 종래의 관로공사용 간이 흙막이 구조물을 도시한 것으로서,15 to 17 is a view showing a conventional simple earthen construction structure for pipeline use,

도 15는 사시도.15 is a perspective view.

도 16a 내지 도 16j는 시공과정을 나타낸 단면도.16A to 16J are sectional views showing a construction process.

도 17은 단면도.17 is a sectional view.

**도면의 주요부분에 대한 부호의 설명**** Description of the symbols for the main parts of the drawings **

1 : 지반 2 : 굴토부1: Ground 2: Gulto part

100 : 엄지말뚝 가이드부재 101 : 엄지말뚝 가이드용 관통공100: thumb pile guide member 101: through-hole for thumb pile guide

110 : 상부 흙막이부재 결합부 111 : 흙막이부재 가이드홈110: upper portion of the earth member engaging portion 111: earth member member guide groove

200 : 엄지말뚝 210 : 하부 흙막이부재 결합부200: thumb pile 210: the lower soil member coupling portion

211 : 흙막이부재 가이드홈 300 : 흙막이부재211: retaining member guide groove 300: retaining member

300a,300b : 조각흙막이부재 310 : 자유이탈방지수단300a, 300b: piece earthenware member 310: free release prevention means

311 : 장공 312 : 돌부311: long 312: stone

400 : 마찰저감수단 410 : 롤러부재400: friction reducing means 410: roller member

420 : 롤러부재 압박수단 421 : 볼트 삽입공420: roller member pressing means 421: bolt insertion hole

422 : 볼트 500 : 흙막이부재용 가이드부재422: bolt 500: guide member for the earth retaining member

501 : 흙막이부재 가이드용 관통공 510 : 가이드부재 결합수단501: through hole for guiding member 510: guide member coupling means

511 : 가이드레일 512 : 가이드홈511: guide rail 512: guide groove

600 : 간격유지부재 700 : 간격유지부재 결합용부재600: spacing member 700: spacing member coupling member

710 : 결합용부재 고정수단 711a,711b : 관통공710: fastening member fastening means 711a, 711b: through hole

712 : 볼트 800 : 간격유지부재 마찰저감수단712: bolt 800: friction reducing means for the space keeping member

810 : 롤러부재810: roller member

본 발명은 흙막이 구조물에 관한 것으로서, 상세하게는, 수도관 등의 관로를 형성하기 위한 공사에 사용되는 간이 흙막이 구조물(일명 SK 판넬)에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an earthquake structure, and more particularly, to a simple earthquake structure (aka SK panel) used in construction for forming a pipeline such as a water pipe.

도 15 내지 도 17은 종래의 관로공사용 간이 흙막이 구조물의 구조 및 시공방법을 나타낸 것이다.15 to 17 show the structure and construction method of a conventional simple earthenware construction using a pipeline.

도시된 바와 같이, 관로공사용 간이 흙막이 구조물은 지반(1)의 터파기 작업에 의해 형성된 관로공사용 굴토부(2)의 측면붕괴를 방지하기 위하여 설치되는데, 기본적으로 H-pile 등에 의한 복수의 엄지말뚝(20)과, 그 엄지말뚝(20) 사이에 장착되는 흙막이부재(일명 토류판)(30)와, 굴토부(2)를 사이에 두고 엄지말뚝(20) 사이의 간격을 유지하기 위한 간격유지부재(40)에 의해 구성되며, 이에 의해 보강된 굴토부(2)의 저면에 수도 파이프(10) 등의 구조물이 설치된다.As shown in the figure, the simple earth block structure for the pipeline is installed to prevent the side collapse of the pipeline oyster portion 2 formed by the excavation of the ground (1), basically a plurality of piles by the H-pile 20 and a retaining member (aka earth plate) 30 mounted between the thumb pile 20 and a gap holding member for maintaining a gap between the thumb pile 20 with the oyster portion 2 interposed therebetween. It is comprised by 40, and structures, such as a water pipe 10, are installed in the bottom face of the oyster part 2 reinforced by this.

관로공사에서 이루어지는 터파기 공사는 일반적인 구조물의 경우에 비해, 굴토 심도가 낮고 굴토부의 길이가 매우 길다는 특징을 가지므로, 조립과 해체가 용이한 구조를 갖는 SK 판넬과 같은 조립식 흙막이 구조물을 적용하는 것이 바람직하다.The trench work in the pipeline construction has a feature that the depth of the excavation depth is very long and the length of the excavation portion is very long, compared to the general structure, so that a prefabricated earth block structure such as SK panel has a structure that is easy to assemble and dismantle. It is desirable to.

도 16 및 도 17을 참조하여 종래의 관로공사용 간이 흙막이 구조물의 시공방법을 보다 상세히 설명하면 다음과 같다.Referring to Figure 16 and 17 will be described in more detail the construction method of a conventional simple earthenware construction using a pipeline.

관로가 형성될 지반(1)에 1차 굴토 작업에 의해 굴토부(2)를 형성하고, 굴토부(2) 저면 위에 엄지말뚝(20) 및 흙막이부재(30)를 위치시킨다.(도 16a,16b,16c)Forming the pit pit 2 by the first pit pit operation on the ground (1) where the pipeline is to be formed, and places the thumb pile 20 and the retaining member 30 on the bottom of the pit pit (2) (Fig. 16a, 16b, 16c)

2차 굴토 작업을 수행하면서, 엄지말뚝(20) 및 흙막이부재(30)를 점진적으로 타입하고, 하부 흙막이부재가 소정 깊이에 도달하면, 그 위에 상부 흙막이부재를 끼워 넣는다.(도 16d,16e,16f)While performing the secondary excavation operation, the thumb pile 20 and the retaining member 30 are gradually typed, and when the lower retaining member reaches a predetermined depth, the upper retaining member is inserted thereon. (FIGS. 16D and 16E, 16f)

일반적으로 1차 굴토 작업의 심도(L1)는 2m 정도이고, 2차 굴토 작업의 총심도(L2)는 4m 정도인데, 이와 같이 굴토 작업을 2차에 걸쳐 진행하는 이유는, 저심도의 굴토부가 빠른 속도로 전진되어야 한다는 관로공사의 특성상, 일단 흙막이 구조물 없이 굴토 작업을 진행할 수 있는 한계 심도(2m 정도)까지 1차 작업을 한 후, 그 상태에서 흙막이 구조물의 시공과 2차 굴토 작업을 병행하는 것이 효율적이기 때문이다.In general, the depth of the first gulto work (L1) is about 2m, the total depth (L2) of the second gulto work is about 4m, the reason for proceeding the gulto work in two steps, the low depth pit Due to the nature of the pipeline construction that the engine should be advanced at a high speed, the first work is performed up to the limit depth (about 2m) to allow the pit work to work without the masonry structure, and then the construction of the masonry structure and the second pit work are performed simultaneously. Because it is efficient.

간이 흙막이 구조물이 완성되면, 그 내부공간에 파이프(10)를 매설하고, 되메움 작업 후 엄지말뚝(20) 및 흙막이부재(30)를 해체하여, 이를 전진 위치의 굴토부에 다시 시공한다.(도 16g,16h,16i,16j)When the simple earthquake structure is completed, the pipe 10 is embedded in the inner space, and after the backfilling work to dismantle the thumb pile 20 and the earth retaining member 30, it is re-installed in the pit of the forward position. 16g, 16h, 16i, 16j)

그런데, 이와 같은 구성을 갖는 종래의 관로공사용 간이 흙막이 구조물은 다음과 같은 점에서 문제점으로 지적되어 왔다.By the way, the conventional duct construction simple structure having such a configuration has been pointed out as a problem in the following points.

도 17에 도시된 바와 같이, 일단 1차 심도(L1)까지 굴토 작업을 한 후, 2차 심도(L2)까지의 굴토 및 흙막이 구조물 타입 작업을 진행하다 보면, 엄지말뚝(20) 이 굴토부(2)의 내측을 향하여 어느 정도 휘게 되는 것을 피할 수 없으며, 이는 다음과 같은 문제를 야기한다.As shown in FIG. 17, once the burrowing work is carried out to the first depth L1 and the burrowing and clogging structures are performed up to the second depth L2, the thumb pile 20 is the burrow part ( It can not be avoided to some extent towards the inside of 2), which causes the following problems.

첫째, 흙막이부재(30)는 엄지말뚝(20)인 H-pile의 양측 홈부에 의해 가이드되면서 설치되는데, 그 설치의 기준이 되는 엄지말뚝(20)이 휘어져 있으므로, 흙막이부재(30)의 설치작업이 곤란을 겪을 수밖에 없다.First, the retaining member 30 is installed while being guided by both side grooves of the H-pile that is the thumb pile 20. Since the thumb pile 20, which is a reference of the installation, is bent, the installation work of the retaining member 30 is performed. There is no choice but to suffer from this difficulty.

둘째, 전체적으로 흙막이 구조물이 휘어질 수밖에 없는 상황임에도 불구하고 강제로 타입에 의한 시공이 이루어지므로, 엄지말뚝(20) 및 흙막이부재(30)의 많은 변형을 피할 수 없고, 이는 자재의 해체 후 재활용을 곤란하게 만드는 요인이 된다.Second, despite the situation that the earthen structure is forced to be bent as a whole, because the construction by force is made, many deformations of the thumb pile 20 and the earthing member 30 can not be avoided, which can be recycled after dismantling the material It is a factor that makes it difficult.

셋째, 흙막이 구조물이 제대로 시공되지 않은 상태에서 관로의 설치작업이 진행되므로, 안전사고의 위험이 높다.Third, because the installation process of the pipeline proceeds in the state that the earth block structure is not properly constructed, the risk of safety accident is high.

본 발명은 상기와 같은 문제점을 해결하기 위하여 안출된 것으로서, 시공이 용이하고 안전하면서도, 자재의 재활용률을 증대시킬 수 있도록 하는 효율적인 구조의 관로공사용 간이 흙막이 구조물을 제공하는 것을 그 목적으로 한다.The present invention has been made in order to solve the above problems, it is an object of the present invention to provide a simple earthquake structure for the pipeline construction of an efficient structure to increase the recycling rate of the material while easy and safe construction.

본 발명은 상술한 바와 같은 목적을 달성하기 위하여, 지반의 터파기 작업에 의해 형성된 관로공사용 굴토부의 측면붕괴를 방지하기 위하여 설치되는 관로공사용 간이 흙막이 구조물에 있어서, 심부에 상하방향으로 엄지말뚝 가이드용 관통공이 형성되고, 측부에 상부 흙막이부재 결합부가 형성됨과 아울러, 상기 굴토부의 측면에 인접하여 소정 간격을 두고 설치되는 복수의 엄지말뚝 가이드부재와; 상기 엄지말뚝 가이드용 관통공에 삽입되어 하측 토체에 근입되도록 설치됨과 아울러, 측부에 하부 흙막이부재 결합부가 형성된 복수의 엄지말뚝과; 상기 복수의 엄지말뚝 가이드부재의 상부 흙막이부재 결합부 및 상기 복수의 엄지말뚝의 하부 흙막이부재 결합부 사이에 결합되는 흙막이부재를; 포함하는 관로공사용 간이 흙막이 구조물을 제시한다.In order to achieve the object described above, the present invention, in the pipeline construction simple earthquake structure is installed to prevent the side collapse of the pipeline construction oyster excavation formed by the excavation work of the ground, guide the pile pile up and down in the core A plurality of thumb pile guide members having a through hole formed therein, and having an upper mud member engaging portion formed at a side thereof, and installed at predetermined intervals adjacent to the side surface of the gul soil; A plurality of thumb piles inserted into the through-holes for the thumb pile guide and installed in the lower soil body, and having a lower mud member coupling portion formed at a side thereof; An earth retaining member coupled between an upper retaining member engaging portion of the plurality of thumb pile guide members and a lower retaining member engaging portion of the plurality of thumb piles; Present a simple earthquake structure for the pipeline.

상기 엄지말뚝 및 엄지말뚝 가이드부재는 H형 구조이고, 상기 상부 흙막이부재 결합부 및 하부 흙막이부재 결합부는 상기 H형 구조의 측부에 형성된 흙막이부재 가이드홈인 구조를 취할 수 있다.The thumb pile and the thumb pile guide member may have an H-type structure, and the upper soil member coupling portion and the lower soil member coupling portion may have a structure of a housing member guide groove formed at the side of the H structure.

상기 엄지말뚝 가이드부재의 엄지말뚝 가이드용 관통공에는 상기 엄지말뚝 가이드부재와 상기 엄지말뚝 사이의 마찰을 저감하기 위한 마찰저감수단이 더 구비된 구조를 취하는 것이 바람직하다.The thumb pile guide through-hole of the thumb pile guide member preferably takes a structure further provided with friction reducing means for reducing friction between the thumb pile guide member and the thumb pile.

상기 마찰저감수단은 상기 엄지말뚝 가이드부재의 내면에 설치된 롤러부재에 의해 구현될 수 있다.The friction reducing means may be implemented by a roller member installed on the inner surface of the thumb pile guide member.

상기 롤러부재를 상기 엄지말뚝 측으로 압박하기 위한 롤러부재 압박수단이 더 구비된 구조를 취하는 것이 바람직하다.It is preferable to take a structure further provided with a roller member pressing means for pressing the roller member toward the thumb pile side.

상기 롤러부재 압박수단은 상기 엄지말뚝 가이드부재에 형성된 볼트 삽입공과; 상기 볼트 삽입공에 결합되어 상기 롤러부재를 상기 엄지말뚝 측으로 압박하는 볼트를; 포함하여 구성될 수 있다.The roller member pressing means and the bolt insertion hole formed in the thumb pile guide member; A bolt coupled to the bolt insertion hole to press the roller member toward the thumb pile; It can be configured to include.

상기 엄지말뚝 가이드부재의 측부에는 심부에 상하방향으로 흙막이부재 가이 드용 관통공이 형성된 흙막이부재용 가이드부재가 결합된 구조를 취하는 것이 바람직하다.It is preferable that the side of the thumb pile guide member has a structure in which the guide member for the earth retaining member having a through hole for the earth retaining member guide is formed in the core portion in the vertical direction.

상기 흙막이부재용 가이드부재가 상기 엄지말뚝 가이드부재에 착탈가능하게 장착되도록, 상호 대향하는 상기 엄지말뚝 가이드부재의 측부와 상기 흙막이부재용 가이드부재의 측부에는 가이드부재 결합수단이 형성된 구조를 취하는 것이 바람직하다.It is preferable to take a structure in which the guide member coupling means is formed on the side portions of the thumb pile guide member and the side portions of the guide member for the masonry member that face each other so that the guide member for the masonry member is detachably mounted to the thumb pile guide member. Do.

상기 가이드부재 결합수단은 상기 엄지말뚝 가이드부재의 측부에 돌출형성된 가이드레일과; 상기 가이드레일이 삽입되도록, 상기 흙막이부재용 가이드부재의 측부에 형성된 가이드홈을; 포함하는 구조에 의해 구현될 수 있다.The guide member coupling means includes a guide rail protruding from the side of the thumb pile guide member; Guide grooves formed on the side of the guide member for the earth retaining member so that the guide rail is inserted; It may be implemented by a structure containing.

상기 엄지말뚝 가이드부재와 흙막이부재용 가이드부재의 상호간 절곡 구동이 가능하도록, 상기 가이드레일 및 가이드홈의 단면이 원형인 구조를 취하는 것이 바람직하다.It is preferable to take a structure having a circular cross section of the guide rail and the guide groove so that the thumb pile guide member and the guide member for the earth retaining member can be mutually bent.

상기 흙막이부재용 가이드부재의 흙막이부재 가이드용 관통공에는 상기 흙막이부재용 가이드부재와 상기 흙막이부재 사이의 마찰을 저감하기 위한 마찰저감수단이 더 구비된 구조를 취하는 것이 바람직하다.It is preferable that the through-holes for guiding members of the guiding member guide member further include a friction reducing means for reducing friction between the guiding member guide member and the holding member.

상기 굴토부의 양측면에 상호 대향하도록 설치된 한 쌍의 상기 엄지말뚝 가이드부재 또는 상기 엄지말뚝 사이에는 간격유지부재가 더 구비된 구조를 취하는 것이 바람직하다.It is preferable to take a structure in which a gap maintaining member is further provided between the pair of thumb pile guide members or the thumb piles installed to oppose each other on both sides of the pit part.

상기 엄지말뚝 가이드부재 심부의 엄지말뚝 가이드용 관통공에 상하방향 구동이 가능하도록 상기 엄지말뚝과 함께 삽입됨과 아울러, 상기 간격유지부재의 단 부와 결합되도록 설치된 간격유지부재 결합용부재가 더 구비된 구조를 취하는 것이 바람직하다.Inserted together with the thumb pile so as to enable the vertical driving in the thumb pile guide through hole of the core portion of the thumb pile guide member, and is further provided with a gap holding member coupling member installed to be coupled to the end of the gap holding member It is desirable to take the structure.

상기 엄지말뚝 가이드부재의 엄지말뚝 가이드용 관통공에는 상기 엄지말뚝 가이드부재와 상기 간격유지부재 결합용부재 사이의 마찰을 저감하기 위한 마찰저감수단이 더 구비된 구조를 취하는 것이 바람직하다.It is preferable that the thumb pile guide through-hole of the thumb pile guide member has a structure further provided with friction reducing means for reducing friction between the thumb pile guide member and the spacing member coupling member.

상기 간격유지부재 결합용부재를 상기 엄지말뚝에 고정하는 결합용부재 고정수단이 더 구비된 구조를 취하는 것이 바람직하다.It is preferable to take a structure that is further provided with a coupling member fixing means for fixing the spacing member coupling member to the thumb pile.

상기 결합용부재 고정수단은 상기 엄지말뚝 및 간격유지부재 결합용부재에 각각 형성된 관통공과; 상기 복수의 관통공에 함께 체결되는 볼트를; 포함하는 구조에 의해 구현될 수 있다.The coupling member fixing means includes a through hole formed in each of the thumb pile and the space maintaining member coupling member; Bolts fastened together to the plurality of through holes; It may be implemented by a structure containing.

상기 엄지말뚝과 간격유지부재 결합용부재 사이의 마찰을 저감하기 위한 간격유지부재 마찰저감수단이 더 구비된 구조를 취하는 것이 바람직하다.It is preferable to take a structure further comprising a gap holding member friction reducing means for reducing the friction between the thumb pile and the gap holding member coupling member.

상기 간격유지부재 마찰저감수단은 상기 엄지말뚝 또는 상기 간격유지부재 결합용부재의 상호 대향면에 설치된 롤러부재에 의해 구현될 수 있다.The gap holding member friction reducing means may be implemented by a roller member provided on the mutually opposite surfaces of the thumb pile or the gap holding member coupling member.

상기 흙막이부재는 상하방향으로 상대구동이 가능하도록 형성된 복수의 조각흙막이부재와; 상기 복수의 조각흙막이부재의 상호 결합면에 형성된 자유이탈방지수단을; 포함하는 구조를 취하는 것이 바람직하다.The earth blocking member may include a plurality of pieces of earth blocking members formed to be relative to each other in a vertical direction; Free separation preventing means formed on the mutual coupling surface of the plurality of pieces of mud member; It is desirable to take a structure that includes.

상기 자유이탈방지수단은 상기 조각흙막이부재의 측면에 상하방향으로 형성된 장공과; 상기 장공에 삽입되도록, 상기 조각흙막이부재의 측면에 형성된 돌부를; 포함하는 구성을 취할 수 있다.The free leaving prevention means and the long hole formed in the vertical direction on the side of the piece earthenware member; A protrusion formed on a side surface of the piece earthenware member to be inserted into the long hole; It can take the structure containing.

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1 내지 도 3에 도시된 바와 같이, 본 발명은 기본적으로 지반(1)의 터파기 작업에 의해 형성된 관로공사용 굴토부(2)의 측면붕괴를 방지하기 위하여 설치되는 관로공사용 간이 흙막이 구조물에 관한 것으로서, 심부에 상하방향으로 엄지말뚝 가이드용 관통공(101)이 형성되고, 측부에 상부 흙막이부재 결합부(110)가 형성됨과 아울러, 상기 굴토부의 측면에 인접하여 소정 간격을 두고 설치되는 복수의 엄지말뚝 가이드부재(100)와; 상기 엄지말뚝 가이드용 관통공(101)에 삽입되어 하측 토체에 근입되도록 설치됨과 아울러, 측부에 하부 흙막이부재 결합부(210)가 형성된 복수의 엄지말뚝(200)과; 상기 복수의 엄지말뚝 가이드부재(100)의 상부 흙막이부재 결합부(110) 및 상기 복수의 엄지말뚝(200)의 하부 흙막이부재 결합부(210) 사이에 결합되는 흙막이부재(300)를; 포함하여 구성된다.As shown in Figures 1 to 3, the present invention basically relates to a pipeline construction simple earthquake structure that is installed to prevent the side collapse of the pipeline oyster pit 2 formed by the excavation of the ground (1) As, the through-hole 101 for the thumb pile guide is formed in the core portion in the vertical direction, the upper retaining member engaging portion 110 is formed on the side, and a plurality of which is installed at a predetermined interval adjacent to the side surface of the pit portion Thumb pile guide member 100 and; A plurality of thumb piles 200 which are inserted into the through-holes 101 for the thumb pile guide so as to be inclined to the lower soil body, and have a lower retaining member coupling part 210 formed at a side thereof; An earth retaining member 300 coupled between an upper earth retaining member engaging portion 110 of the plurality of thumb pile guide members 100 and a lower earth retaining member engaging portion 210 of the plurality of thumb stakes 200; It is configured to include.

즉, 엄지말뚝으로서 단지 하나의 부재만이 사용되던 종래의 구성와 달리, 엄지말뚝 가이드부재(100)와 엄지말뚝(200)의 이중구조를 취하고, 엄지말뚝(200)의 타입 작업시 가이드부재(100)에 의해 가이드되는 구성을 취함으로써, 2차 굴토 및 타입 작업에 의해 엄지말뚝(200)이 굴토부(2) 내측으로 휘어지는 것을 방지할 수 있도록 한 것이다.That is, unlike the conventional configuration in which only one member is used as the thumb pile, it takes the dual structure of the thumb pile guide member 100 and the thumb pile 200, and guide member 100 when working the type of thumb pile 200 By taking the configuration guided by), it is to be able to prevent the thumb pile 200 to bend to the inside of the pit 2 by the secondary pit and type work.

따라서, 1차 심도(L1)까지의 굴토 작업에 의한 굴토부(2)의 저면 위에 엄지말뚝 가이드부재(100)가 설치된 후(도 3a), 2차 심도(L2)까지의 굴토 작업과 함께 수행되는 엄지말뚝(200)의 타입 작업시 엄지말뚝(200)이 가이드부재(100)에 의해 가이드되면서 근입되므로 변형이 방지되고(도 3b), 흙막이부재(300)는 이와 같이 변형되지 않은 상태의 엄지말뚝(200) 및 가이드부재(100)를 기준으로 설치되므로 그 설치 작업이 용이하며, 자재의 재활용률을 증대시킬 수 있을 뿐만 아니라, 전체적으로 흙막이 구조물 시공의 안전을 담보할 수 있다.Therefore, after the thumb pile guide member 100 is installed on the bottom surface of the pit part 2 by the pit work up to the first depth L1 (FIG. 3A), the pit work up to the second depth L2 is performed. When the thumb pile 200 is guided by the guide member 100 while the type of the thumb pile 200 is deformed, the deformation is prevented (FIG. 3B), and the earth blocking member 300 has the thumb in the undeformed state. Since it is installed based on the pile 200 and the guide member 100, the installation work is easy, and not only can increase the recycling rate of the material, but also can ensure the safety of the construction of the earthquake structure as a whole.

여기서, 엄지말뚝(200) 및 엄지말뚝 가이드부재(100)는 엄지말뚝(200)이 가이드부재(100)에 의해 가이드될 수 있고, 측부에 흙막이부재 결합부가 형성된 구조이면 어떠한 구조를 취하더라도 관계없으며, 엄지말뚝(200)으로서 통상 사용되는 H-pile을 적용하는 경우에는 그 가이드부재(100)도 H형 구조를 취하는 것이 바람직하고, 이때 상부 흙막이부재 결합부(110) 및 하부 흙막이부재 결합부(210)는 H형 구조의 측부에 형성되는 흙막이부재 가이드홈(111,211)에 의해 구현된다.Here, the thumb pile 200 and the thumb pile guide member 100 may be guided by the thumb member 200 by the guide member 100, and may take any structure as long as it has a structure formed with a coupling member at the side. In the case of applying the H-pile, which is usually used as the thumb pile 200, the guide member 100 also preferably takes the H-type structure, and at this time, the upper mud member engaging portion 110 and the lower mud member engaging portion ( 210 is implemented by the retaining member guide grooves 111 and 211 formed on the side of the H-shaped structure.

엄지말뚝 가이드부재(100)의 엄지말뚝 가이드용 관통공(101)에 삽입되어 가이드되는 엄지말뚝(200)의 상하방향 구동이 원활하게 이루어지도록 하기 위해서는, 엄지말뚝 가이드부재(100)와 엄지말뚝(200) 사이의 마찰을 저감하기 위한 마찰저감수단(400)이 더 구비된 구조를 취하는 것이 바람직하다.In order to smoothly drive up and down the thumb pile 200 inserted and guided into the thumb pile guide through hole 101 of the thumb pile guide member 100, the thumb pile guide member 100 and the thumb pile ( It is preferable to take the structure further provided with friction reducing means 400 for reducing the friction between the 200.

여기서, 마찰저감수단(400)은 양 부재 사이의 접촉에 의해 발생하는 마찰을 줄일 수 있는 구성이면, 오일 도포 방식, 표면 처리 방식 기타 어떠한 구성을 취하더라도 관계없으며, 도 4에서는 엄지말뚝 가이드부재(100)의 내면에 롤러부재(410)가 설치된 실시예를 도시하고 있다.Here, if the friction reducing means 400 is configured to reduce the friction generated by the contact between the two members, it may be any oil coating method, surface treatment method or any other configuration, in Figure 4 thumb pile guide member ( An embodiment in which the roller member 410 is installed on the inner surface of 100 is illustrated.

엄지말뚝(200)의 타입 작업시, 엄지말뚝(200)이 휨변형을 일으키지 않도록 가이드부재(100)에 의해 견고하게 지지되도록 하기 위해서는, 롤러부재(410)를 엄지말뚝(200) 측으로 압박하기 위한 롤러부재 압박수단(420)이 더 구비된 구조를 취 하는 것이 바람직하다.In the type work of the thumb pile 200, in order to ensure that the thumb pile 200 is firmly supported by the guide member 100 so as not to cause bending deformation, for pressing the roller member 410 toward the thumb pile 200 side It is preferable to take the structure that the roller member pressing means 420 is further provided.

이러한 롤러부재 압박수단(420)은 롤러부재(410)를 엄지말뚝(200) 측으로 압박할 수 있는 구조이면 어느 것이나 관계없으며, 도 5에서는 엄지말뚝 가이드부재(100)에 형성된 볼트 삽입공(421)과; 그 볼트 삽입공(421)에 결합되어 롤러부재(410)를 엄지말뚝(200) 측으로 압박하는 볼트(422)를; 포함하는 실시예를 도시하고 있다.The roller member pressing means 420 may be any structure as long as it can press the roller member 410 toward the thumb pile 200. In FIG. 5, the bolt insertion hole 421 formed in the thumb pile guide member 100 is used. and; A bolt 422 coupled to the bolt insertion hole 421 to press the roller member 410 toward the thumb pile 200 side; An example embodiment is shown.

한편, 도 6 내지 도 8에 도시된 바와 같이, 엄지말뚝 가이드부재(100)의 측부에는, 심부에 상하방향으로 흙막이부재 가이드용 관통공(501)이 형성된 흙막이부재용 가이드부재(500)가 결합된 구조를 취할 수 있다.On the other hand, as shown in Figures 6 to 8, the side of the thumb pile guide member 100, the guide member 500 for the earthquake member formed with a through hole 501 for the earthquake member guide in the vertical direction in the core portion is coupled Structure can be taken.

이러한 구조를 취하는 경우, 1차 굴토 작업에 의해 형성된 굴토부(2)의 저면에 엄지말뚝 가이드부재(100) 및 흙막이부재용 가이드부재(500) 결합체를 위치시키고, 2차 굴토 작업시 그 가이드부재 각각의 관통공(101,501)을 통해 엄지말뚝(200) 및 흙막이부재(300)를 가이드하면서 타입하는 구성을 취할 수 있으므로, 상술한 바와 같은 부재의 변형 방지효과를 더욱 크게 얻을 수 있다.In the case of taking such a structure, a combination of the thumb pile guide member 100 and the guide member 500 for the masonry member is placed on the bottom surface of the pit part 2 formed by the first pit work, and the guide member during the second pit work. Since the type of configuration can be taken while guiding the thumb pile 200 and the retaining member 300 through the respective through holes 101 and 501, the deformation preventing effect of the member as described above can be obtained even more.

엄지말뚝(200) 및 그 가이드부재(100)의 경우와 마찬가지로, 흙막이부재용 가이드부재(500)의 흙막이부재 가이드용 관통공(501)에는 흙막이부재용 가이드부재(500)와 흙막이부재(300) 사이의 마찰을 저감하기 위한 마찰저감수단(400)이 더 구비된 구조를 취하는 것이 바람직하며, 그 구체적 구성은 상술한 바와 같다.As in the case of the thumb pile 200 and the guide member 100, the guide member 500 and the earth member 300 are provided in the through hole 501 for the earth guide member of the guide member 500. It is preferable to take the structure further provided with friction reducing means 400 for reducing the friction between, the specific configuration is as described above.

엄지말뚝 가이드부재(100)과 흙막이부재용 가이드부재(500)는 도 6에 도시된 바와 같이 일체형 구조를 취할 수도 있고, 도 7에 도시된 바와 같이 착탈가능한 구 조를 취할 수도 있다.The thumb pile guide member 100 and the guide member 500 for the masonry member may have an integral structure as shown in FIG. 6, or may have a detachable structure as shown in FIG. 7.

시공의 용이성 측면에서는 후자의 구조를 취하는 것이 보다 바람직한데, 이와 같이 흙막이부재용 가이드부재(500)가 엄지말뚝 가이드부재(100)에 착탈가능하게 장착되는 구성을 취하는 경우, 상호 대향하는 엄지말뚝 가이드부재(100)의 측부와 흙막이부재용 가이드부재(500)의 측부에는 가이드부재 결합수단(510)이 형성되는 것이 필요하다.In view of ease of construction, it is more preferable to take the latter structure. In this case, when the guide member 500 for the masonry member is taken to be detachably mounted to the thumb pile guide member 100, the thumb pile guides which face each other are opposed to each other. It is necessary that the guide member coupling means 510 is formed on the side of the member 100 and the side of the guide member 500 for the earth retaining member.

이러한 가이드부재 결합수단(510)은 다양한 구조를 취할 수 있으며, 도 7 및 도 8에서는 엄지말뚝 가이드부재(100)의 측부에 돌출형성된 가이드레일(511)과; 가이드레일(511)이 삽입되도록, 흙막이부재용 가이드부재(500)의 측부에 형성된 가이드홈(512)을; 포함하는 실시예를 도시하고 있다.The guide member coupling means 510 may take various structures, and the guide rail 511 protruding from the side of the thumb pile guide member 100 in FIGS. 7 and 8; A guide groove 512 formed at the side of the guide member 500 for the earth retaining member so that the guide rail 511 is inserted therein; An example embodiment is shown.

나아가, 관로형성용 굴토부(2)가 굴곡되거나 구불구불한 구성을 취하게 되는 경우에도 용이한 작업을 수행하기 위해서는, 도 8에 도시된 바와 같이, 엄지말뚝 가이드부재(100)와 흙막이부재용 가이드부재(500)의 상호간 절곡 구동이 가능하도록, 가이드레일(511) 및 가이드홈(512)의 단면이 원형인 구조를 취하는 것이 바람직하다.Furthermore, in order to perform an easy operation even when the conduit forming convex part 2 is bent or twisted, as shown in FIG. 8, the thumb pile guide member 100 and the earthing member are used. In order to enable the bending of the guide member 500 to each other, it is preferable to take a structure having a circular cross section of the guide rail 511 and the guide groove 512.

한편, 본 발명에 의한 관로공사용 간이 흙막이 구조물의 경우에도 종래의 구조와 마찬가지로, 도 9에 도시된 바와 같이, 굴토부(2)의 양측면에 상호 대향하도록 설치된 한 쌍의 엄지말뚝 가이드부재(100) 또는 엄지말뚝(200) 사이에 간격유지부재(600)가 더 구비된 구조를 취하는 것이 구조적 안정성 측면에서 바람직하다.On the other hand, in the case of a simple earthquake structure for the pipeline construction according to the present invention, as shown in Figure 9, as shown in Figure 9, a pair of pile pile guide member 100 installed to face each other side of the excavation (2) Or it is preferable in terms of structural stability to take a structure that is further provided with a spacing member 600 between the thumb pile (200).

이러한 구조를 취하는 경우, 도 10 내지 도 12에 도시된 바와 같이, 별도의 간격유지부재 결합용부재(700)가 더 구비된 구조를 취하는 것이 바람직한데, 이 간격유지부재 결합용부재(700)는 엄지말뚝 가이드부재(100) 심부의 엄지말뚝 가이드용 관통공(101)에 상하방향 구동이 가능하도록 엄지말뚝(200)과 함께 삽입되며, 간격유지부재(600)의 단부와 결합되는 구성을 취한다.When taking such a structure, as shown in Figures 10 to 12, it is preferable to take a structure that is further provided with a separate spacing member coupling member 700, this spacing holding member coupling member 700 is The thumb pile guide member 100 is inserted together with the thumb pile 200 so as to be able to be driven up and down in the thumb pile guide through-hole 101 of the core portion, and takes a configuration that is coupled with the end of the gap maintaining member 600. .

굴토부(2)의 측면에 작용하는 토압은 하부로 내려갈수록 증대하는 것이므로, 도 12에 도시된 바와 같이, 상부의 엄지말뚝 가이드부재(100) 상호간의 간격을 유지하기 위한 간격유지부재(600) 뿐만 아니라, 하부의 엄지말뚝(200) 상호간에도 간격유지부재(600)가 장착되는 것이 구조적 안정성 측면에서 바람직하다.Since the earth pressure acting on the side of the pit part 2 increases as it goes downward, as shown in FIG. 12, the gap maintaining member 600 for maintaining a gap between the upper thumb pile guide members 100 is shown. In addition, it is preferable in terms of structural stability that the gap maintaining member 600 is also mounted between the lower thumb pile 200.

그러나, 파이프의 설치작업을 위해서는 설치되었던 하부 간격유지부재의 해체작업이 필요한데, 종래의 구조에 있어서는 그 하부 간격유지부재의 임시 설치 및 해체 작업에 많은 수고와 비용이 소요되므로 이를 생략하는 것이 일반적이었고, 그로 인하여 흙막이 구조물의 구조적 안정성이 문제시되어 왔다.However, dismantling of the lower space keeping member that was installed is required for the installation work of the pipe. In the conventional structure, since it requires a lot of labor and cost for temporary installation and dismantling of the lower space keeping member, it was generally omitted. Therefore, the structural stability of the retaining structure has been a problem.

또한, 굴토 작업과 파이프 설치작업은 동시에 진행되는 것이 아니므로, 굴토 작업 및 흙막이 구조물의 설치 후 소정 시간 동안, 흙막이 구조물이 하부 간격유지부재가 설치되지 않은 상태로 존재하게 되는데, 시간의 경과와 함께 토압의 증대가 있는 경우, 대단히 위험한 응력 상태가 발생할 수 있다는 점에서 더욱 큰 문제로 지적되어 왔다.In addition, since the gulting work and the pipe installation work are not performed at the same time, for a predetermined time after the gulting work and the installation of the masonry structure, the masonry structure is present without the lower space keeping member is installed. Increasing earth pressure has been pointed out as a further problem in that extremely dangerous stress states can occur.

이에 비해, 본 발명의 경우, 간격유지부재(600)와 결합되는 간격유지부재 결합용부재(700)가 엄지말뚝 가이드부재(100)에 엄지말뚝(200)과 함께 삽입되어 별도로 상하방향 구동이 가능한 구조를 취하므로, 도 12a에 도시된 바와 같이 간격유지 부재(600)가 굴토부(2)의 하부를 지지하는 구조를 취하다가, 파이프(10)의 설치 작업시에는 도 12b에 도시된 바와 같이 간격유지부재 결합용부재(700)의 상향 구동에 의해 간격유지부재(600)를 상승시킬 수 있으므로 파이프(10)의 설치 작업을 위한 공간의 확보가 매우 용이하게 이루어지도록 한다.On the contrary, in the present invention, the gap holding member coupling member 700 coupled with the gap holding member 600 is inserted together with the thumb pile 200 in the thumb pile guide member 100 to be driven up and down separately. Since the structure, the space maintaining member 600 as shown in Figure 12a takes a structure supporting the lower portion of the pit portion 2, as shown in Figure 12b during the installation work of the pipe 10 Since the gap holding member 600 may be raised by the upward driving of the gap holding member coupling member 700, the space for the installation work of the pipe 10 may be secured very easily.

간격유지부재(600)를 소정 높이에 위치시키기 위해서는, 간격유지부재 결합용부재(700)가 소정 위치에서 고정되는 것이 필요하므로, 간격유지부재 결합용부재(700)를 엄지말뚝(200)에 고정하는 결합용부재 고정수단(710)이 더 구비된 구조를 취하는 것이 바람직하다.In order to position the spacing holding member 600 at a predetermined height, the spacing holding member coupling member 700 needs to be fixed at a predetermined position, so that the spacing holding member coupling member 700 is fixed to the thumb pile 200. It is preferable to take a structure that the coupling member fixing means 710 is further provided.

여기서, 결합용부재 고정수단(710)은 간격유지부재 결합용부재(700)를 엄지말뚝(200)에 대하여 착탈가능하게 고정하는 구조이면 어느 것이나 관계없으며, 도 10 및 도 11에서는, 엄지말뚝(200) 및 간격유지부재 결합용부재(700)에 각각 형성된 관통공(711a,711b)과; 복수의 관통공(711a,711b)에 함께 체결되는 볼트(712)를; 포함하는 실시예에 의해 구현된 경우를 도시하고 있다.Here, the coupling member fixing means 710 is any structure as long as the structure for detachably fixing the spacer maintaining member 700 for the thumb pile 200, in Figure 10 and 11, the thumb pile ( 200 and through-holes (711a, 711b) formed in the space maintaining member coupling member 700, respectively; Bolts 712 fastened together to the plurality of through holes 711a and 711b; The case implemented by the including embodiment is shown.

엄지말뚝 가이드부재(100)의 엄지말뚝 가이드용 관통공(101)에도 엄지말뚝 가이드부재(100)와 간격유지부재 결합용부재(700) 사이의 마찰을 저감하기 위한 마찰저감수단(400)이 더 구비된 구조를 취하는 것이 바람직하며, 그 구체적 내용은 상술한 바와 같다.In addition, the thumb pile guide through-hole 101 of the thumb pile guide member 100 further includes a friction reducing means 400 for reducing friction between the thumb pile guide member 100 and the space keeping member coupling member 700. It is preferable to take the provided structure, the details of which are as described above.

또한, 엄지말뚝 가이드부재(100)의 엄지말뚝 가이드용 관통공(101)에 함께 삽입되어 구동하는 엄지말뚝(200)과 간격유지부재 결합용부재(700) 사이에도 마찰을 저감하기 위한 간격유지부재 마찰저감수단(800)이 더 구비된 구조를 취하는 것 이 바람직한데, 이러한 간격유지부재 마찰저감수단(800)은 도 11에 도시된 바와 같이 엄지말뚝(200) 또는 간격유지부재 결합용부재(700)의 상호 대향면에 롤러부재(810)를 설치하는 구조 등에 의해 구현될 수 있다.In addition, the gap holding member for reducing the friction between the thumb pile 200 and the gap holding member coupling member 700 which is inserted and driven together in the thumb pile guide through-hole 101 of the thumb pile guide member 100 It is preferable to take the structure further provided with a friction reducing means 800, such a gap holding member friction reducing means 800 is a thumb pile 200 or a gap holding member coupling member 700 as shown in FIG. It may be implemented by a structure such as installing the roller member 810 on the mutually opposite surface of the).

한편, 흙막이부재(300)는 엄지말뚝(200)에 비해 상면이 길게 형성된 구조를 취하므로, 정확한 타입 작업이 어렵다는 문제점이 있었다.On the other hand, since the blocking member 300 has a structure in which the upper surface is formed longer than the thumb pile 200, there was a problem that the correct type work is difficult.

이에 비해, 본 발명에 의한 흙막이 구조물의 경우, 흙막이부재용 가이드부재(500)의 흙막이부재 가이드용 관통공(501)에 장착되는 흙막이 부재(300)를 복수의 조각흙막이부재(300a,300b)에 의해 구성함으로써, 위와 같은 문제점을 해결할 수 있도록 한다.On the other hand, in the case of the earth block structure according to the present invention, the earth block member 300 mounted in the earth block member guide through hole 501 of the earth block member guide member 500 is provided with a plurality of pieces of earth block members 300a and 300b. By this configuration, it is possible to solve the above problems.

즉, 도 13에 도시된 바와 같이, 상하방향으로 상대구동이 가능하도록 형성된 복수의 조각흙막이부재(300a,300b)와; 그 복수의 조각흙막이부재(300a,300b)의 상호 결합면에 형성된 자유이탈방지수단(310)을; 포함하는 구조를 취하는 경우, 도 14에 도시된 바와 같이 각 부재별 타입 작업이 가능하므로, 종래와 같이 흙막이부재가 일체로 형성된 경우에 비해 용이하고 정확한 타입 작업이 가능해진다.That is, as shown in Figure 13, a plurality of pieces of earthing members 300a, 300b formed so as to be relative to drive in the vertical direction; Free separation preventing means (310) formed on the mutual coupling surface of the plurality of pieces of earthing members (300a, 300b); In the case of including the structure, as shown in Figure 14, since each type of work is possible, as compared to the case where the earthen board member is formed integrally as in the prior art, it is possible to work accurately and accurately.

여기서, 자유이탈방지수단(310)은 복수의 조각흙막이부재(300a,300b) 상호간 상하방향의 자유이탈이 방지되도록 하는 구조이면 어느 것이나 관계없으며, 도 13에서는 조각흙막이부재(300)의 측면에 상하방향으로 형성된 장공(311)과; 그 장공(311)에 삽입되도록, 조각흙막이부재(300)의 측면에 형성된 돌부(312)를; 포함하는 실시예를 도시하고 있다.Here, the free release preventing means 310 may be any structure so as to prevent the free separation of the plurality of pieces of mud members 300a, 300b in the vertical direction between each other, and in FIG. 13 up and down the side of the piece mud members 300 A long hole 311 formed in a direction; A protrusion 312 formed on the side surface of the piece earthing member 300 so as to be inserted into the long hole 311; An example embodiment is shown.

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설 명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.Since the above is merely described with respect to some of the preferred embodiments that can be implemented by the present invention, the scope of the present invention, as is well known, should not be construed as limited to the above embodiments, the present invention described above All of the technical ideas together with the technical idea of the base will be included in the scope of the present invention.

본 발명은 시공이 용이하고 안전하면서도, 자재의 재활용률을 증대시킬 수 있도록 하는 효율적인 구조의 관로공사용 간이 흙막이 구조물을 제공한다.The present invention provides a simple earth block structure for the pipeline construction of an efficient structure that is easy and safe to construct, and to increase the recycling rate of the material.

Claims (20)

지반(1)의 터파기 작업에 의해 형성된 관로공사용 굴토부(2)의 측면붕괴를 방지하기 위하여 설치되는 관로공사용 간이 흙막이 구조물에 있어서,In the conduit construction simple earth block structure that is installed to prevent the side collapse of the conduit gulting part 2 formed by the excavation of the ground (1), 심부에 상하방향으로 엄지말뚝 가이드용 관통공(101)이 형성되고, 측부에 상부 흙막이부재 결합부(110)가 형성됨과 아울러, 상기 굴토부의 측면에 인접하여 소정 간격을 두고 설치되는 복수의 엄지말뚝 가이드부재(100)와;The through-hole 101 for the thumb pile guide is formed in the core portion in the vertical direction, and the upper retaining member coupling portion 110 is formed in the side portion, and a plurality of thumbs installed at predetermined intervals adjacent to the side surface of the pit portion A pile guide member 100; 상기 엄지말뚝 가이드용 관통공(101)에 삽입되어 하측 토체에 근입되도록 설치됨과 아울러, 측부에 하부 흙막이부재 결합부(210)가 형성된 복수의 엄지말뚝(200)과;A plurality of thumb piles 200 which are inserted into the through-holes 101 for the thumb pile guide so as to be inclined to the lower soil body, and have a lower retaining member coupling part 210 formed at a side thereof; 상기 복수의 엄지말뚝 가이드부재(100)의 상부 흙막이부재 결합부(110) 및 상기 복수의 엄지말뚝(200)의 하부 흙막이부재 결합부(210) 사이에 결합되는 흙막이부재(300)를;An earth retaining member 300 coupled between an upper earth retaining member engaging portion 110 of the plurality of thumb pile guide members 100 and a lower earth retaining member engaging portion 210 of the plurality of thumb stakes 200; 포함하는 관로공사용 간이 흙막이 구조물.Pipeline simple earthquake structure containing. 제1항에 있어서,The method of claim 1, 상기 엄지말뚝(200) 및 엄지말뚝 가이드부재(100)는 H형 구조이고, The thumb pile 200 and the thumb pile guide member 100 is H-shaped structure, 상기 상부 흙막이부재 결합부(110) 및 하부 흙막이부재 결합부(210)는 상기 H형 구조의 측부에 형성된 흙막이부재 가이드홈(111,211)인 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.The upper retaining member engaging portion 110 and the lower retaining member engaging portion 210 is a simple earthquake structure for pipeline construction, characterized in that the guide member 111, 211 formed in the side of the H-shaped structure. 제1항에 있어서,The method of claim 1, 상기 엄지말뚝 가이드부재(100)의 엄지말뚝 가이드용 관통공(101)에는 상기 엄지말뚝 가이드부재(100)와 상기 엄지말뚝(200) 사이의 마찰을 저감하기 위한 마찰저감수단(400)이 더 구비된 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.The thumb pile guide through-hole 101 of the thumb pile guide member 100 is further provided with a friction reducing means 400 for reducing the friction between the thumb pile guide member 100 and the thumb pile 200. A simple earthquake structure for pipeline use. 제3항에 있어서,The method of claim 3, 상기 마찰저감수단(400)은 The friction reducing means 400 is 상기 엄지말뚝 가이드부재(100)의 내면에 설치된 롤러부재(410)인 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.Simplified earth construction structure for a pipeline engineer, characterized in that the roller member 410 installed on the inner surface of the thumb pile guide member 100. 제4항에 있어서,The method of claim 4, wherein 상기 롤러부재(410)를 상기 엄지말뚝(200) 측으로 압박하기 위한 롤러부재 압박수단(420)이 더 구비된 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.The roller member pressing means for pressing the roller member 410 toward the thumb pile 200 side further comprises a simple earthquake structure for a public use. 제5항에 있어서,The method of claim 5, 상기 롤러부재 압박수단(420)은The roller member pressing means 420 is 상기 엄지말뚝 가이드부재(100)에 형성된 볼트 삽입공(421)과;A bolt insertion hole 421 formed in the thumb pile guide member 100; 상기 볼트 삽입공(421)에 결합되어 상기 롤러부재(410)를 상기 엄지말뚝(200) 측으로 압박하는 볼트(422)를; A bolt 422 coupled to the bolt insertion hole 421 to press the roller member 410 toward the thumb pile 200; 포함하는 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.Pipeline simple earthquake structure for use. 제1항에 있어서,The method of claim 1, 상기 엄지말뚝 가이드부재(100)의 측부에는 On the side of the thumb pile guide member 100 심부에 상하방향으로 흙막이부재 가이드용 관통공(501)이 형성된 흙막이부재용 가이드부재(500)가 결합된 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.A simple earth block structure for pipe line construction, characterized in that the guide member 500 for the earth block member formed with a through hole 501 for the earth guide member in the vertical direction. 제7항에 있어서,The method of claim 7, wherein 상기 흙막이부재용 가이드부재(500)가 상기 엄지말뚝 가이드부재(100)에 착탈가능하게 장착되도록, 상호 대향하는 상기 엄지말뚝 가이드부재(100)의 측부와 상기 흙막이부재용 가이드부재(500)의 측부에는 가이드부재 결합수단(510)이 형성된 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.The side of the thumb pile guide member 100 and the side of the guiding member guide member 500 that face each other so that the guide member 500 for the makjae member detachably mounted to the thumb pile guide member 100. There is a guide member coupling means 510 is a simple earthquake structure for use by a pipeline engineer. 제8항에 있어서,The method of claim 8, 상기 가이드부재 결합수단(510)은The guide member coupling means 510 is 상기 엄지말뚝 가이드부재(100)의 측부에 돌출형성된 가이드레일(511)과;A guide rail 511 protruding from the side of the thumb pile guide member 100; 상기 가이드레일(511)이 삽입되도록, 상기 흙막이부재용 가이드부재(500)의 측부에 형성된 가이드홈(512)을; 포함하는 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.A guide groove 512 formed at a side of the guide member 500 for the earth retaining member so that the guide rail 511 is inserted therein; Pipeline simple earthquake structure for use. 제9항에 있어서,The method of claim 9, 상기 엄지말뚝 가이드부재(100)와 흙막이부재용 가이드부재(500)의 상호간 절곡 구동이 가능하도록, 상기 가이드레일(511) 및 가이드홈(512)의 단면이 원형인 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.Simplified earth barriers for pipeline workers, characterized in that the cross-section of the guide rail 511 and the guide groove 512 is circular so that the thumb pile guide member 100 and the guide member 500 for the masonry member can be mutually bent. structure. 제7항에 있어서,The method of claim 7, wherein 상기 흙막이부재용 가이드부재(500)의 흙막이부재 가이드용 관통공(501)에는 상기 흙막이부재용 가이드부재(500)와 상기 흙막이부재(300) 사이의 마찰을 저감하기 위한 마찰저감수단(400)이 더 구비된 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.In the through-hole 501 of the earthing member member of the guide member 500 for the earthing member, friction reducing means 400 for reducing friction between the earthing member guide member 500 and the earthing member 300 is provided. Pipe construction simple earthquake structure for use, characterized in that further provided. 제1항에 있어서,The method of claim 1, 상기 굴토부(2)의 양측면에 상호 대향하도록 설치된 한 쌍의 상기 엄지말뚝 가이드부재(100) 또는 상기 엄지말뚝(200) 사이에는 간격유지부재(600)가 더 구비된 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.Simple between the pair of the thumb pile guide member 100 or the thumb pile 200 installed to face each other on both sides of the gulto part 2, characterized in that the interval maintaining member 600 is further provided. Climbing structures. 제12항에 있어서,The method of claim 12, 상기 엄지말뚝 가이드부재(100) 심부의 엄지말뚝 가이드용 관통공(101)에 상하방향 구동이 가능하도록 상기 엄지말뚝(200)과 함께 삽입됨과 아울러, 상기 간격유지부재(600)의 단부와 결합되도록 설치된 간격유지부재 결합용부재(700)가 더 구 비된 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.The thumb pile guide member 100 is inserted together with the thumb pile 200 so as to be able to be driven up and down in the thumb pile guide through hole 101 of the core portion, and coupled to the end of the spacing member 600. The simple earth block structure for a pipeline engineer, characterized in that the installed space maintaining member coupling member 700 is further provided. 제13항에 있어서,The method of claim 13, 상기 엄지말뚝 가이드부재(100)의 엄지말뚝 가이드용 관통공(101)에는 상기 엄지말뚝 가이드부재(100)와 상기 간격유지부재 결합용부재(700) 사이의 마찰을 저감하기 위한 마찰저감수단(400)이 더 구비된 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.In the thumb pile guide through hole 101 of the thumb pile guide member 100, friction reducing means 400 for reducing friction between the thumb pile guide member 100 and the gap holding member coupling member 700 is provided. ) Simple earthquake structure for use by ducts, characterized in that it is further provided. 제13항에 있어서,The method of claim 13, 상기 간격유지부재 결합용부재(700)를 상기 엄지말뚝(200)에 고정하는 결합용부재 고정수단(710)이 더 구비된 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.The simple earth gasket structure for a pipeline engineer, characterized in that the coupling member holding means for fixing the gap holding member 700 for the thumb pile 200 is further provided. 제15항에 있어서,The method of claim 15, 상기 결합용부재 고정수단(710)은The coupling member fixing means 710 is 상기 엄지말뚝(200) 및 간격유지부재 결합용부재(700)에 각각 형성된 관통공(711a,711b)과;Through-holes (711a, 711b) formed in the thumb pile 200 and the gap holding member 700, respectively; 상기 복수의 관통공(711a,711b)에 함께 체결되는 볼트(712)를;Bolts 712 fastened together to the plurality of through holes 711a and 711b; 포함하는 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.Pipeline simple earthquake structure for use. 제13항에 있어서,The method of claim 13, 상기 엄지말뚝(200)과 간격유지부재 결합용부재(700) 사이의 마찰을 저감하기 위한 간격유지부재 마찰저감수단(800)이 더 구비된 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.The simple earth block structure for a pipeline engineer, characterized in that the gap holding member friction reducing means 800 is further provided to reduce the friction between the thumb pile 200 and the gap holding member coupling member 700. 제17항에 있어서,The method of claim 17, 상기 간격유지부재 마찰저감수단(800)은The gap maintaining member friction reducing means 800 is 상기 엄지말뚝(200) 또는 상기 간격유지부재 결합용부재(700)의 상호 대향면에 설치된 롤러부재(810)인 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.The thumb pile 200 or the roller member 810 installed on the mutually opposing surfaces of the spacing member coupling member 700, characterized in that the pipe construction simple earthquake structure for use. 제7항에 있어서,The method of claim 7, wherein 상기 흙막이부재(300)는The earth blocking member 300 is 상하방향으로 상대구동이 가능하도록 형성된 복수의 조각흙막이부재(300a,300b)와;A plurality of pieces of soil blocking members (300a, 300b) formed to allow relative driving in the vertical direction; 상기 복수의 조각흙막이부재(300a,300b)의 상호 결합면에 형성된 자유이탈방지수단(310)을;Free separation preventing means (310) formed on the mutual coupling surface of the plurality of pieces of earthing members (300a, 300b); 포함하는 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.Pipeline simple earthquake structure for use. 제19항에 있어서,The method of claim 19, 상기 자유이탈방지수단(310)은The free departure prevention means 310 상기 조각흙막이부재(300)의 측면에 상하방향으로 형성된 장공(311)과;A long hole 311 formed in a vertical direction on a side surface of the carving mud member 300; 상기 장공(311)에 삽입되도록, 상기 조각흙막이부재(300)의 측면에 형성된 돌부(312)를;A protrusion 312 formed at a side surface of the piece earthing member 300 so as to be inserted into the long hole 311; 포함하는 것을 특징으로 하는 관로공사용 간이 흙막이 구조물.Pipeline simple earthquake structure for use.
KR1020050103032A 2005-10-31 2005-10-31 Temporary retaining wall structure for water works KR100744192B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050103032A KR100744192B1 (en) 2005-10-31 2005-10-31 Temporary retaining wall structure for water works

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050103032A KR100744192B1 (en) 2005-10-31 2005-10-31 Temporary retaining wall structure for water works

Publications (2)

Publication Number Publication Date
KR20070046378A true KR20070046378A (en) 2007-05-03
KR100744192B1 KR100744192B1 (en) 2007-08-01

Family

ID=38271736

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050103032A KR100744192B1 (en) 2005-10-31 2005-10-31 Temporary retaining wall structure for water works

Country Status (1)

Country Link
KR (1) KR100744192B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924450A (en) * 2019-12-18 2020-03-27 湖北工业大学 Method for protecting existing viaduct friction pile in pit under foundation pit excavation condition
KR102244505B1 (en) 2020-10-15 2021-04-23 이원식 Self-supporting Type Sheeting Structure and Method for Sheeting Construction using the same
KR102244507B1 (en) 2020-10-15 2021-04-26 이원식 Self-supporting Type Earth Retaining Wall
KR20230135339A (en) * 2022-03-16 2023-09-25 윤영근 Eco double soil retaining panel for easy collection

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012523512A (en) * 2009-04-07 2012-10-04 エマニュエル、ノベルト、アルフォンソ Pile system
CN108442382B (en) * 2018-03-06 2020-06-16 中铁十一局集团城市轨道工程有限公司 In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
KR102101586B1 (en) * 2019-11-19 2020-04-16 박준성 System for excavation of sewage pipe

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200258867Y1 (en) 2001-09-11 2001-12-28 주식회사 건화엔지니어링 A steel pile vertical guide equipment
KR200354783Y1 (en) 2004-03-25 2004-07-01 주식회사 도우엔지니어즈 Steel bar of adhere to roller
KR100533612B1 (en) 2005-09-02 2005-12-06 주식회사 유신건축종합건축사사무소 Structure of panel easy using foundation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924450A (en) * 2019-12-18 2020-03-27 湖北工业大学 Method for protecting existing viaduct friction pile in pit under foundation pit excavation condition
KR102244505B1 (en) 2020-10-15 2021-04-23 이원식 Self-supporting Type Sheeting Structure and Method for Sheeting Construction using the same
KR102244507B1 (en) 2020-10-15 2021-04-26 이원식 Self-supporting Type Earth Retaining Wall
KR20230135339A (en) * 2022-03-16 2023-09-25 윤영근 Eco double soil retaining panel for easy collection

Also Published As

Publication number Publication date
KR100744192B1 (en) 2007-08-01

Similar Documents

Publication Publication Date Title
KR100744192B1 (en) Temporary retaining wall structure for water works
KR100891949B1 (en) Temporary retaining wall structure for water supply and drainage works in low depth
KR100882831B1 (en) Reformed sheet plate and the method of installation of the same
KR101861805B1 (en) H omitted
KR100959300B1 (en) Structure for temporary retaining wall
KR20080026013A (en) Soil guard structure and establishment method
KR100977206B1 (en) A retaining wall structure for using slide rail and installation method
KR101572561B1 (en) Steel assembly for Pile
KR101888737B1 (en) Prefabricated shoring structure
KR101103782B1 (en) Temporary retaining wall structure for water works
KR101382609B1 (en) Earths wall for groundprotection and Construction Method thereof
KR100935006B1 (en) Temporary retaining wall structure for water supply and drainage works in high depth
KR101448216B1 (en) Retaining wall with multiple pile
KR20110098597A (en) Guide frame for h-steel
KR101809006B1 (en) Reformed sheet plate and the method of installation of the same
KR20130131836A (en) Earths wall for groundprotection and construction method thereof
KR200393051Y1 (en) Structure of assembling temporary panel for retaining wall
KR20090101993A (en) Soil guard structure and establishment method
KR101388478B1 (en) Arch-shaped retaining panel
KR200389267Y1 (en) Box type trench shoring apparatus
KR101939892B1 (en) Apparatus of sheathing for easy dismantling sheathing walls using multistage sheathing rail and dismantling method thereof
KR200396174Y1 (en) Steel earth plate for easy installation and dismantling
JP2010185239A (en) Earth retaining wall and construction method thereof
KR101569899B1 (en) Soil retaining plate
KR20180072305A (en) shaped steel beam and the structure using it

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee