KR20060134754A - Partial coating waterproof tunnel and there of method - Google Patents

Partial coating waterproof tunnel and there of method Download PDF

Info

Publication number
KR20060134754A
KR20060134754A KR1020050054683A KR20050054683A KR20060134754A KR 20060134754 A KR20060134754 A KR 20060134754A KR 1020050054683 A KR1020050054683 A KR 1020050054683A KR 20050054683 A KR20050054683 A KR 20050054683A KR 20060134754 A KR20060134754 A KR 20060134754A
Authority
KR
South Korea
Prior art keywords
layer
waterproof
tunnel
coating
waterproofing
Prior art date
Application number
KR1020050054683A
Other languages
Korean (ko)
Inventor
김인태
황현주
Original Assignee
김인태
황현주
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김인태, 황현주 filed Critical 김인태
Priority to KR1020050054683A priority Critical patent/KR20060134754A/en
Publication of KR20060134754A publication Critical patent/KR20060134754A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Abstract

A partially waterproof-coated tunnel and a construction method of the same are provided to facilitate the construction regardless of a sectional shape of the tunnel, and achieve a single-cell tunnel structure without requiring lining concrete. A partially waterproof-coated rock tunnel(100) comprises a reinforcing shotcrete layer(110), a water drain member(120), a waterproof coating layer(130), a water drain part, and a waterproof coating layer protection shotcrete layer(140). The rock tunnel is divided into a leaking section requiring waterproofing, and a non-leaking section not requiring waterproofing. The reinforcing shotcrete layer is formed on an inner surface of the rock tunnel. The water drain member is attached to the leaking section. The waterproof coating is formed on the water drain member. The waterproof coating layer protection shotcrete layer is formed on the waterproof coating layer. A construction method for the rock tunnel comprises the steps of setting a waterproof construction area, forming the reinforcing shotcrete layer, attaching the water drain member, forming the waterproof coating layer, and forming the waterproof coating layer protection shotcrete layer.

Description

부분 도막방수 터널 및 그 시공방법{PARTIAL COATING WATERPROOF TUNNEL AND THERE OF METHOD}Partial coating waterproof tunnel and construction method {PARTIAL COATING WATERPROOF TUNNEL AND THERE OF METHOD}

도 1은 종래 이중셀 방수터널의 폭방향 종단면도.1 is a longitudinal cross-sectional view of a conventional double-cell waterproof tunnel.

도 2는 종래 이중셀 방수터널의 길이방향 부분 종단면도.Figure 2 is a longitudinal longitudinal cross-sectional view of a conventional double-cell waterproof tunnel.

도 3은 종래 이중셀 방수터널의 배수부재 및 방수시트 체결부 단면도.Figure 3 is a cross-sectional view of the drainage member and waterproof sheet fastening of the conventional double-cell waterproof tunnel.

도 4 내지 도 9는 종래 이중셀 방수터널의 시공 공정을 보인 것이며, 각 도면에서 (a)는 폭방향, (b)는 길이방향으로 각각 절단하여 보인 단면도로서,4 to 9 show the construction process of the conventional double-cell waterproof tunnel, and in each drawing (a) is a cross-sectional view cut in the longitudinal direction, respectively (b) in the longitudinal direction,

도 4 (a),(b)는 터널 굴착 후 숏크리트한 형태를 보인 단면도.Figure 4 (a), (b) is a cross-sectional view showing a shotcrete after the tunnel excavation.

도 5 (a),(b)는 숏크리트 벽면에 배수부재를 설치하는 과정을 보인 단면도.Figure 5 (a), (b) is a cross-sectional view showing a process of installing the drain member on the shotcrete wall.

도 6 (a),(b)는 배수부재 위에 방수시트를 설치하는 과정을 보인 단면도.Figure 6 (a), (b) is a cross-sectional view showing a process of installing a waterproof sheet on the drain member.

도 7 (a),(b)는 방수시트의 손상 여부를 조사하는 기밀시험 과정을 보인 단면도.Figure 7 (a), (b) is a cross-sectional view showing the airtight test process for examining the damage of the waterproof sheet.

도 8 (a),(b)는 방수층을 보호하기 위한 라이닝 콘크리트를 타설하는 과정을 보인 단면도.Figure 8 (a), (b) is a cross-sectional view showing a process of pouring lining concrete for protecting the waterproof layer.

도 9 (a),(b)는 종래에 주로 건설되는 터널공법인 NATM 터널공법을 설명하기 위한 단면도.Figure 9 (a), (b) is a cross-sectional view for explaining the NATM tunnel method which is a tunnel method mainly constructed conventionally.

도 10은 본 발명의 일 실시예에 의한 부분 도막방수 공법으로 시공되는 방수터널을 폭방향으로 절단하여 보인 종단면도.10 is a longitudinal cross-sectional view of the waterproof tunnel is cut in the width direction is constructed by a partial film waterproofing method according to an embodiment of the present invention.

도 11은 본 발명의 일 실시예에 의한 부분 도막방수 공법으로 시공되는 방수터널을 길이방향으로 절단하여 보인 부분 종단면도.FIG. 11 is a partial longitudinal cross-sectional view of a waterproof tunnel constructed by a partial coating waterproof method according to an embodiment of the present invention in a longitudinal direction;

도 12 내지 도 15는 본 발명의 일 실시예에 의한 부분 도막방수 공법의 요부를 보인 도면으로서,12 to 15 is a view showing the main portion of the partial film waterproofing method according to an embodiment of the present invention,

도 12는 암반터널의 심도에 따라 지표수와 지하수 영향을 받는 얕은 심도영역과 깊은 심도영역의 영역 구분도.FIG. 12 is a view illustrating a region of shallow and deep depth regions affected by surface water and groundwater according to depth of rock tunnels. FIG.

도 13은 암반터널의 깊은 심도영역 영역에서의 방수구간 설정도.13 is a view illustrating a waterproof section in a deep depth region of a rock tunnel.

도 14는 방수구간에서 비방수구간으로 물의 이동과 확산을 방지하기 위한 부분 도막방수층의 단부 구조를 보인 확대 단면도.14 is an enlarged cross-sectional view showing the end structure of the partial coating waterproof layer for preventing the movement and diffusion of water from the waterproof section to the non-waterproof section.

도 15는 도막방수층의 배수 구조를 보인 단면도.15 is a cross-sectional view showing a drainage structure of the coating waterproof layer.

도 16 (a),(b)는 터널에서 배수되는 용수를 집수하여 유도배수하는 배수구조의 일예를 보인 정면도 및 종단면도.Figure 16 (a), (b) is a front view and a longitudinal sectional view showing an example of a drainage structure for collecting and inducing drainage of the water drained in the tunnel.

도 17 (a),(b)는 터널에서 배수되는 용수를 집수하여 유도배수하는 배수구조의 다른 예를 보인 정면도 및 종단면도.Figure 17 (a), (b) is a front view and a longitudinal sectional view showing another example of a drainage structure for collecting and inducing drainage of water drained from the tunnel.

도 18 내지 도 21은 본 발명의 일 실시예에 의한 부분 도막방수 공법의 공정을 보인 것이며, 각 도면에서 (a)는 폭방향, (b)는 길이방향으로 각각 절단하여 보인 단면도로서,18 to 21 are views showing the process of the partial coating waterproofing method according to an embodiment of the present invention, in each drawing (a) is a cross-sectional view cut in the width direction, (b) in the longitudinal direction, respectively,

도 18은 터널 굴착 후 숏크리트하는 과정을 보인 단면도.18 is a cross-sectional view showing a process of shotcrete after the excavation of the tunnel.

도 19는 숏크리트 벽면에 배수부재를 설치하는 과정을 보인 단면도.19 is a cross-sectional view showing a process of installing a drain member on the shotcrete wall.

도 20은 배수부재 위에 도막방수 뿜칠작업을 하는 과정을 보인 단면도.20 is a cross-sectional view showing a process of spraying the coating film waterproof on the drain member.

도 21은 도막방수층 보호를 위하여 숏크리트하는 과정을 보인 단면도.FIG. 21 is a cross-sectional view illustrating a process of shotcreting for protecting a coating waterproof layer; FIG.

도 22는 본 발명의 다른 실시예에 의한 부분 도막방수 공법으로 시공되는 방수터널을 폭방향으로 절단하여 보인 종단면도.Figure 22 is a longitudinal cross-sectional view of the waterproof tunnel cut in the width direction constructed by a partial film waterproofing method according to another embodiment of the present invention.

도 23은 본 발명의 다른 실시예에 의한 부분 도막방수 공법으로 시공되는 방수터널을 길이방향으로 절단하여 보인 부분 종단면도.FIG. 23 is a partial longitudinal cross-sectional view of a waterproof tunnel constructed by a partial coating waterproof method according to another embodiment of the present invention in a longitudinal direction;

도 24 내지 도 28은 본 발명의 또 다른 실시예에 의한 부분 도막방수 공법을 설명하기 위한 도면으로서, 24 to 28 are views for explaining a partial coating waterproofing method according to another embodiment of the present invention,

도 24는 부분 도막방수 공법으로 시공되는 방수터널을 폭방향으로 절단하여 보인 종단면도.24 is a longitudinal cross-sectional view of the waterproof tunnel constructed by the partial coating waterproofing method by cutting in the width direction.

도 25는 부분 도막방수 공법으로 시공되는 방수터널을 길이방향으로 절단하여 보인 종단면도.25 is a longitudinal sectional view of the waterproof tunnel constructed by the partial film waterproofing method by cutting in the longitudinal direction.

도 26은 도 25의 요부 확대 단면도.26 is an enlarged cross-sectional view of the main portion of FIG. 25;

도 27 (a),(b)는 배수부재 일체형 방수도막 위에 2차로 방수도막을 형성하는 과정을 보인 방수터널의 폭방향 종단면도 및 길이방향 부분 종단면도.Figure 27 (a), (b) is a longitudinal longitudinal cross-sectional view and a longitudinal longitudinal cross-sectional view of the waterproof tunnel showing a process of forming a waterproof coating film on the second drainage integral waterproof coating.

도 28은 도 27 (b)의 요부 확대 단면도.FIG. 28 is an enlarged sectional view of a main portion of FIG. 27 (b); FIG.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

100 : 암반 터널 101 : 얕은 심도영역100: rock tunnel 101: shallow depth area

102 : 깊은 심도영역 110 : 보강 숏크리트층102: deep depth area 110: reinforced shotcrete layer

120 : 배수부재 130 : 도막 방수층120: drainage member 130: coating film waterproof layer

130' : 일체형 도막 배수부재 130a : 1차 도막 방수층130 ': integral coating film drainage member 130a: primary coating film waterproofing layer

130b : 2차 도막 방수층 131 : 누수 차단부130b: secondary coating waterproof layer 131: water leakage blocking unit

140 : 방수층 보호 숏크리트층 150 : 배수부140: waterproof layer protective shotcrete layer 150: drain

151 : 유공관 152 : 배수관151: Merit pipe 152: Drain pipe

153 : 연결관 154 : 여과재153 connector 154 filter medium

180 : 라이닝 콘크리트층 C : 경계심도180: lining concrete layer C: boundary depth

D1 : 누수영역 D2 : 비누수영역D1: leaking area D2: soapy area

본 발명은 부분 도막방수 터널 및 그 시공방법에 관한 것으로, 특히 터널내의 누수 혹은 누수예상 구간에 대해서만 부분적으로 방수를 실시하고 비방수구간으로 물의 확산이나 이동을 방지함으로써, 터널내의 구간별 부분방수공법의 적용이 가능하며, 도막 방수재 도포(뿜칠)에 의한 작업방법으로 터널의 단면이나 형상에 구애받지 않고, 방수층 표면에 숏크리트 취부가 용이하도록 하여 라이닝 콘크리트가 필요 없는 단일셀 터널구조 형태의 시공이 가능토록 하여 터널공사비 절감 및 시공효율을 증대시킬 수 있도록 한 부분 도막방수 터널 및 그 시공방법에 관한 것이다.The present invention relates to a partial coating waterproof tunnel and its construction method, and in particular, by partially waterproofing only the leaked or expected leakage section in the tunnel and preventing the diffusion or movement of water in the unsealed section, the partial waterproofing method in each section in the tunnel It is possible to apply the coating material waterproofing, and it is possible to apply the shotcrete on the surface of the waterproof layer without the lining concrete by allowing the installation of shotcrete on the surface of the waterproof layer regardless of the cross section or shape of the tunnel. The present invention relates to a partial coating waterproof tunnel and its construction method to reduce tunnel construction cost and increase construction efficiency.

일반적으로 산악지형 또는 지하심부의 암반 영역을 관통하여 건설되는 터널 공사는 암반의 절리나 균열 등의 불연속면을 통하여 지하수와 지표수가 터널내로 유출되는 것을 방지하기 위해 방수공사를 실시하고 있으며, 굴착된 터널의 벽면에 숏크리트를 타설하고, 이 숏크리트 위에 부직포와 방수시트를 부착한 후, 이를 보호를 위한 콘크리트 라이닝을 설치하는 이중셀 터널구조로 시공하고 있다.In general, the tunnel construction, which penetrates the rocky areas of the mountainous or subterranean core, performs waterproofing to prevent the groundwater and surface water from leaking into the tunnel through discontinuities such as rock joints or cracks. After the shotcrete is placed on the wall, the non-woven fabric and the waterproof sheet are attached to the shotcrete, and then it is constructed as a double-cell tunnel structure in which concrete lining for protection is installed.

이하, 도면에 의하여 설명하면 도 1 내지 도 9는 종래 이중셀 방수터널 및 그 시공 공정을 설명하기 위한 도면으로서, 도 1에는 종래 이중셀 방수터널의 폭방향 종단면도가 도시되고, 도 2에는 종래 이중셀 방수터널의 길이방향 부분 종단면도가 도시되어 있으며, 도 3에는 종래 이중셀 방수터널의 부직포 및 방수시트 체결부 단면도가 도시되어 있다.1 to 9 are views for explaining a conventional double-cell waterproof tunnel and its construction process, Figure 1 is a longitudinal longitudinal cross-sectional view of a conventional double-cell waterproof tunnel, Figure 2 is a conventional A longitudinal longitudinal cross-sectional view of a dual cell waterproof tunnel is shown, and FIG. 3 is a cross-sectional view of a nonwoven fabric and a waterproof sheet fastening portion of a conventional double cell waterproof tunnel.

이에 도시한 바와 같이, 종래 이중셀 방수터널은 굴착된 터널(1)의 내주면에 숏크리트층(2)이 타설되고, 이 숏크리트층(2)에 투수층의 부직포(3)와 수지계통의 방수시트(4)가 체결부재(10)로 부착되고, 이 위에 라이닝 콘크리트층(5)이 타설된 구성으로 되어 있다.As shown in the drawing, in the conventional double-cell waterproof tunnel, a shotcrete layer 2 is placed on the inner circumferential surface of the excavated tunnel 1, and the non-woven fabric 3 of the water-permeable layer and the resin-based waterproof sheet are disposed on the shotcrete layer 2. 4) is attached to the fastening member 10, on which the lining concrete layer 5 is poured.

도 4 내지 도 9은 종래 이중셀 방수터널의 시공 공정을 보인 것이며, 각 도면에서 (a)는 폭방향, (b)는 길이방향으로 각각 절단하여 보인 단도면로서, 도 4 (a),(b)에는 터널 굴착 후 숏크리트한 형태를 보인 단면도, 도 5 (a),(b)에는 숏크리트 벽면에 부직포를 설치하는 과정을 보인 단면도, 도 6 (a),(b)에는 부직포 위에 방수시트를 설치하는 과정을 보인 단면도가 각각 도시되고, 도 7 (a),(b)에는 방수시트의 손상 여부를 조사하는 기밀시험 과정을 보인 단면도, 도 8 (a),(b)에는 방수층을 보호하기 위한 라이닝 콘크리트를 타설하는 과정을 보인 단면도가 각각 도시되어 있으며, 도 9 (a),(b)에는 종래에 주로 건설되는 터널공법인 NATM 터널공법을 설명하기 위한 단면도가 도시되어 있다.4 to 9 show the construction process of the conventional double-cell waterproof tunnel, in each drawing (a) is a cross-sectional view cut in the width direction, (b) in the longitudinal direction, respectively, Figure 4 (a), ( b) is a cross-sectional view showing the shotcrete after the excavation of the tunnel, Figure 5 (a), (b) is a cross-sectional view showing the process of installing a nonwoven fabric on the shotcrete wall, Figure 6 (a), (b) a waterproof sheet on the nonwoven fabric Cross-sectional view showing the installation process is shown, respectively, Figure 7 (a), (b) is a cross-sectional view showing the airtight test process to investigate the damage of the waterproof sheet, Figure 8 (a), (b) to protect the waterproof layer Sections showing the process of pouring lining concrete for each is shown, Figure 9 (a), (b) is shown a cross-sectional view for explaining the NATM tunnel method, which is a tunnel method that is mainly constructed conventionally.

이에 도시한 바와 같이 종래 이중셀 방수터널의 방수공법은 도 4 (a),(b)와 같이 굴착된 터널(1)의 내주면에 숏크리트층(2)을 타설한다.As shown in the related art, the waterproofing method of the conventional double-cell waterproof tunnel places the shotcrete layer 2 on the inner circumferential surface of the tunnel 1 excavated as shown in FIGS. 4 (a) and 4 (b).

이어서 도 5 (a),(b)와 같이 상기 숏크리트층(2)에 투수층의 부직포(3)를 부착한다.Subsequently, the nonwoven fabric 3 of the permeable layer is attached to the shotcrete layer 2 as shown in FIGS. 5 (a) and 5 (b).

이어서 도 6 (a),(b)와 같이 상기 부직포(3) 위에 수지계통의 방수시트(4)를 도 3의 체결부재(10)로 부착하면 불룩불룩한 형태의 불투수층인 방수막이 형성이 된다.Subsequently, as shown in FIGS. 6A and 6B, when the resin-based waterproof sheet 4 is attached onto the nonwoven fabric 3 with the fastening member 10 of FIG. 3, a waterproof film that is a water-impermeable layer having a bulging shape is formed.

이때 방수시트(4)의 접합부는 7㎝이상 겹이음하여 전기특수용접기를 이용하여 현장이음작업을 실시하고, 상기 체결부재(10)에는 예를 들어 와셔형태의 란델(11)과 못(12)이 이용되며, 터널(1) 전면에 걸쳐 방수시트(4)를 설치하면서 다수개의 란델(11)을 못(12)으로 고정하여 방수시트(4)를 부착한다.At this time, the joint portion of the waterproof sheet 4 is overlapped by 7 cm or more to perform a field joint using an electric special welding machine, and the fastening member 10 has, for example, a washer-shaped landel 11 and a nail 12. This is used, while installing a waterproof sheet 4 over the front of the tunnel (1) to secure a plurality of Landel 11 with a nail 12 to attach the waterproof sheet (4).

이후, 도 7 (a),(b)와 같이 무거운 방수시트(4)로 인하여 처짐이 발생되므로 시공중에 찢어지는 등의 손상이 발생되기 쉬우므로 콤푸레샤(40)를 이용하여 방수막의 내부로 압축공기를 분사하여 접합부의 손상을 확인하는 기밀시험을 실시한다.Since the deflection occurs due to the heavy waterproof sheet 4 as shown in FIGS. 7 (a) and 7 (b), it is easy to cause damage such as tearing during construction. Therefore, the compressed air is compressed into the waterproof membrane using the compressor 40. Airtight test is carried out to confirm the damage of the joint by spraying.

그리고, 도 8 (a),(b)와 같이 방수시트(4)의 방수막 위에 라이닝 콘크리트층(5)을 20cm∼40cm의 두께로 타설하여 형성한다.Then, as shown in Fig. 8 (a), (b) is formed by pouring the lining concrete layer 5 to a thickness of 20cm to 40cm on the waterproof film of the waterproof sheet (4).

현재 주로 건설되는 국내 터널공법은 도 9 (a),(b)와 같이 숏크리트층(2)과 록볼트(30)를 이용하여 터널을 보강하는 NATM 터널공법이므로, 라이닝 콘크리트층 (5)은 하중분담보다는 방수층의 보호가 주목적이며, 기존 방수시트(4)에 의한 방수방법은 라이닝 콘크리트층(5)이 필수적인 이중셀 터널구조 형식으로 시행되어야 하는 것이다.Currently, the domestic tunnel method, which is mainly constructed, is NATM tunnel method for reinforcing the tunnel using the shotcrete layer 2 and the rock bolt 30 as shown in FIGS. 9 (a) and 9 (b). The protection of the waterproof layer is more important than the sharing, and the waterproofing method by the existing waterproof sheet 4 is to be implemented in the form of a double cell tunnel structure in which the lining concrete layer 5 is essential.

도면에서 미설명 부호 30은 이동식 받침대를 보인 것이고, 50은 라이닝 콘크리트층(4)을 형성하기 위한 거푸집을 보인 것이다.In the figure, reference numeral 30 denotes a movable pedestal, and 50 denotes a form for forming the lining concrete layer 4.

이와 같은 종래의 이중셀 방수터널 시공법은 암반터널의 누수영역과 비누수영역을 구분함이 없이 암반터널의 내면에 부직포와 방수시트를 전면적으로 부착하여 방수막을 형성하고, 이 방수층 위에 방수층의 보호를 위해 라이닝 콘크리트층을 타설하여 형성하는 것으로 방수막의 내부로 압축공기를 분사하여 방수막의 손상을 확인하기 위한 번거로운 시험을 하여야 하므로 시공 과정과 절차가 복잡하게 되고 시공 기일이 오래 걸리는 문제점이 있다.In the conventional double cell waterproof tunnel construction method, a non-woven fabric and a waterproof sheet are attached to the inner surface of the rock tunnel to form a waterproof membrane without distinguishing between the leakage zone and the soap water zone of the rock tunnel, and the protection of the waterproof layer on the waterproof layer is achieved. In order to form the lining concrete layer in order to spray compressed air into the waterproof membrane to perform a cumbersome test to confirm the damage of the waterproof membrane, there is a problem that the construction process and procedures become complicated and the construction period takes a long time.

또한 방수시트 외부에서는 물의 이동이 전구역으로 자유롭게 이동되는 방수공법의 특성 때문에 누수가 발생되지 않는 구역에 대해서도 방수공사를 불가피하게 시행하여야 하므로 방수층 보호를 위하여 20cm∼40cm 두께의 라이닝 콘크리트층을 설치하여야 하므로 터널의 전구간에 대한 전면 방수공사의 시행으로 시공 효율성과 경제성이 떨어지게 될 뿐 아니라, 시공 기일이 더욱 지연되는 등의 많은 문제점을 내재하고 있었다.In addition, due to the characteristics of the waterproofing method in which the movement of water freely moves to the entire area outside the waterproof sheet, waterproof construction must be inevitably performed even in areas where water does not occur. Therefore, a lining concrete layer having a thickness of 20 cm to 40 cm must be installed to protect the waterproof layer. Implementing the entire waterproofing work for all the tunnels has not only lowered the construction efficiency and economic efficiency, but also has many problems such as delayed construction time.

본 발명은 상기한 바와 같은 종래의 문제점 및 결함을 해소하기 위하여 창안한 것으로, 터널 내부의 누수구간에만 방수를 실시하고, 방수를 실시하지 않은 비누수구간으로 물의 이동이나 확산을 차단하여 종래의 터널 전구간에 걸친 전면 방수 시행하는 비효율성을 제거하고 구간별로 부분방수 시행이 가능토록 하며, 도포 시공방법을 채택함으로써 터널의 다양한 단면이나 형상에 구애받지 않고 시공이 용이하게 되는 부분 도막방수 터널 및 그 시공방법을 제공하고자 함에 목적이 있다. The present invention was devised to solve the above problems and defects as described above, and provides a waterproofing section only in the leaking section inside the tunnel, and blocks the movement or diffusion of water into a soapy section that is not waterproofing. Partial waterproofing tunnel and its construction that makes it easy to install regardless of the various cross sections or shapes of the tunnel by eliminating the inefficiency of waterproofing the entire surface and allowing partial waterproofing by section. The purpose is to provide a method.

위와 같은 목적을 달성하기 위하여 본 발명에 의한 부분 도막방수 터널은 암반 터널의 내주면이 방수가 필요한 누수영역과 방수가 필요하지 않는 비누수영역으로 구분되고, 상기 암반 터널의 내주면에 보강 숏크리트층이 형성되며, 상기 누수영역에 배수부재가 부착되고, 이 배수부재 위에 도막 방수재가 도포되어 도막 방수층이 형성되며, 상기 배수부재와 도막 방수층의 양측면 하단부에 배수를 위한 배수부가 설치되고, 상기 도막 방수층 위에 상기 도막 방수층 보호를 위한 방수층 보호 숏크리트층이 형성되어 구성된다.In order to achieve the above object, the partial coating waterproof tunnel according to the present invention is divided into a water leakage area that requires waterproofing and an inner circumferential surface of a rock tunnel, and a water-repellent area that does not require waterproofing, and a reinforcement shotcrete layer is formed on an inner circumferential surface of the rock tunnel. And a drainage member is attached to the leaking area, and a coating film waterproofing material is coated on the draining member to form a coating film waterproofing layer, and a drainage part for drainage is installed at both lower ends of the draining member and the coating film waterproofing layer. A waterproofing layer protective shotcrete layer for protecting the coating waterproofing layer is formed.

상기 암반 터널은 경계심도에 따라 경계심도 외부의 지표수 영향에 의해 누수되는 얕은 심도영역과, 경계심도 내부의 지하수 영향으로 누수되는 깊은 심도영역으로 구분됨과 아울러, 얕은 심도영역이 누수영역으로 구분되고, 깊은 심도영역은 지하수가 누수되는 누수영역과, 누수되지 않는 비누수영역으로 구분되어 구성된다.The rock tunnel is divided into a shallow depth area that is leaked by the surface water effect outside the boundary depth and a deep depth area that is leaked by the groundwater effect inside the boundary depth, and the shallow depth area is divided into the leakage area according to the boundary depth. The deep depth zone is divided into a leakage zone in which groundwater leaks and a non-leakage soap zone.

상기 도막 방수층은 부직포와 같은 배수부재에 도막 방수재가 도포되어 1차 도막 방수층이 일체로 형성된 배수부재 일체형 도막 배수부재가 상기 누수영역의 보강 숏크리트층 위에 부착되며, 이 일체형 도막 배수부재 위에 도막 방수재가 도포되어 2차 도막 방수층 형성됨으로써 1차 도막 방수층과 2차 도막 방수층의 이중구조로 형성될 수도 있다.The coating film waterproofing layer is coated with a drainage member such as a nonwoven fabric, and a coating member waterproofing member integrally formed with a drainage member having a primary coating layer waterproofing layer is attached to the reinforcement shotcrete layer of the leaking area. The coating may be applied to form a second waterproofing layer, thereby forming a dual structure of a first waterproofing layer and a second waterproofing layer.

상기 도막 방수층은 얕은 심도영역과, 깊은 심도영역의 누수영역에서 비누수영역으로 물의 이동이나 확산을 방지하기 위해서 배수부재의 양단부 외부로 누수 차단부가 확장 형성되어 터널의 노출된 내주면에 접합된 구성된다.The coating layer is composed of a shallow depth region, and a leakage blocking portion is formed outside the both ends of the drainage member to prevent the movement or diffusion of water from the leakage region of the deep depth region to the soapy region and bonded to the exposed inner peripheral surface of the tunnel. .

또한 본 발명에 의한 부분 도막방수 터널의 시공방법은 상기 암반 터널을 경계심도에 따라 경계심도 외부의 지표수 영향에 의해 누수되는 얕은 심도영역과, 경계심도 내부의 지하수 영향으로 누수되는 깊은 심도영역으로 구분함과 아울러, 얕은 심도영역을 누수영역으로 구분하고, 깊은 심도영역은 지하수가 누수되는 누수영역과, 누수되지 않는 비누수영역으로 구분 설정하는 방수 시공영역 설정단계와, 상기 암반 터널의 내주면에 보강 숏크리트층을 형성하는 보강 숏크리트층 형성단계와, 상기 얕은 심도영역과, 깊은 심도영역의 누수영역에 배수부재를 부착하는 배수부재 부착단계와, 상기 배수부재 위에 도막 방수재를 도포하여 도막 방수층을 형성하는 도막 방수층 형성단계와, 상기 도막 방수층 위에 상기 도막 방수층 보호를 위한 방수층 보호 숏크리트층을 형성하는 방수층 보호 숏크리트층 형성단계를 포함하여 구성된다.In addition, according to the present invention, a method of constructing a partial coating waterproof tunnel is classified into a shallow depth area leaked by surface water effects outside the boundary depth and a deep depth area leaked by groundwater effects inside the boundary depth according to the boundary depth. In addition, the shallow depth area is divided into a leaking area, and the deep depth area is a watertight construction area setting step of dividing the groundwater into a leaking area and a non-leaking soapy water area, and reinforcing the inner circumferential surface of the rock tunnel. A step of forming a reinforcement shotcrete layer for forming a shotcrete layer, a step of attaching a drainage member to the drainage region of the shallow depth region and a deep depth region, and forming a waterproofing layer by coating a coating film waterproofing material on the drainage member Forming a waterproof layer and protecting the waterproof layer to protect the waterproof layer on the waterproof layer It is configured to include a protective waterproof layer shotcrete layer forming step of forming a concrete floor.

그리고 상기 도막 방수층 형성단계에서는 시공 현장의 외부 공장에서 배수부재에 도막 방수재를 도포하여 1차 도막 방수층이 일체로 형성된 배수부재 일체형 도막 배수부재를 제조하는 도막 배수부재 제조단계와, 이 일체형 도막 배수부재를 시공 현장에 반입하여 상기 얕은 심도영역과, 깊은 심도영역의 누수영역에 일체형 도막 배수부재를 부착하는 도막 배수부재 부착단계와, 상기 일체형 도막 배수부재 위에 도막 방수재를 도포하여 2차 도막 방수층을 형성함으로써 이중구조의 도막 방수층을 형성하는 도막 방수층 형성하는 과정으로 실시할 수도 있다.In the coating film waterproofing layer forming step, the coating film waterproofing material is applied to the drainage member at an external factory at the construction site to manufacture a coating member drainage member for manufacturing a drainage member integrated film drainage member in which the primary coating film waterproofing layer is integrally formed. Coating film drainage member attaching the integrated film drainage member to the shallow depth region and the water leakage region of the deep depth region, and coating a film waterproofing material on the integrated film drainage member to form a secondary coating film waterproofing layer. It can also be carried out by the process of forming a coating film waterproof layer which forms the coating film waterproof layer of a dual structure.

상기 도막 방수재에는 (주)아텍스에서 보급하고 있는 폴리톱(POLYTOP)을 이용하는 것이 바람직하다.As the coating film waterproofing material, it is preferable to use a polytop (POLYTOP) which is supplied by ATEX.

이와 같은 본 발명에 의한 부분 도막방수 터널 및 그 시공방법은 장소가 협소한 터널 공사 특성과 용도에 따라 다양한 변화단면 및 변곡점 등의 특수한 단면과 작업조건에 구애받지 않는 뿜칠형 방수방법을 적용하므로 시공이 용이하고 작업여건에 관계없이 시공이 가능한 장점을 가지고 있어 시공효율을 증대시킬 수 있다.Such a partial coating waterproof tunnel and its construction method according to the present invention is applied because it is applied to a special cross-section, such as a variety of cross-sections and inflection points and spraying type waterproofing method regardless of the working conditions according to the tunnel construction characteristics and uses of the narrow place It is easy and can be installed regardless of working conditions, so it is possible to increase construction efficiency.

이하, 본 발명을 첨부한 도면에 실시예를 들어 상세히 설명하면 다음과 같다. Hereinafter, with reference to the accompanying drawings, the present invention will be described in detail as follows.

도 10은 본 발명의 일 실시예에 의한 부분 도막방수 공법으로 시공되는 방수터널을 폭방향으로 절단하여 보인 종단면도이고, 도 11은 본 발명의 일 실시예에 의한 부분 도막방수 공법으로 시공되는 방수터널을 길이방향으로 절단하여 보인 부분 종단면도이다.10 is a longitudinal cross-sectional view of the waterproof tunnel constructed by the partial coating waterproofing method according to an embodiment of the present invention cut in the width direction, Figure 11 is a waterproof construction of the partial coating waterproofing method according to an embodiment of the present invention Partial longitudinal sectional view of the tunnel cut longitudinally.

먼저 도 10 및 도 11에 도시한 바와 같이 굴착된 암반 터널(100)의 내주면이 후술한 바와 같이 방수가 필요한 누수영역과 방수가 필요하지 않는 비누수영역으로 구분되고, 상기 암반 터널(100)의 내주면에 보강 숏크리트층(110)이 형성되며, 상기 누수영역(D1)에 부직포와 같은 배수부재(120)가 부착되고, 이 배수부재(120) 위 에 도막 방수재가 뿜칠로 도포되어 도막 방수층(130)이 형성되며, 상기 배수부재(120)와 도막 방수층(130)의 양측면 하단부에 배수를 위한 배수부(150)가 설치되고, 상기 도막 방수층(130) 위에 상기 도막 방수층(130) 보호를 위한 방수층 보호 숏크리트층(140)이 형성되어 구성된다.First, as shown in FIGS. 10 and 11, the inner circumferential surface of the excavated rock tunnel 100 is divided into a water leakage area that requires waterproofing and a soap water area that does not need waterproofing, as described below. A reinforcement shotcrete layer 110 is formed on an inner circumferential surface, and a drainage member 120 such as a nonwoven fabric is attached to the leaking area D1, and a coating film waterproofing material is sprayed on the drainage member 120 to spray the coating film waterproofing layer 130. ) Is formed, and the drainage part 150 for drainage is installed at both lower ends of the drainage member 120 and the coating film waterproofing layer 130, and the waterproofing layer for protecting the coating waterproofing layer 130 on the coating waterproofing layer 130. The protective shotcrete layer 140 is formed.

도면에서 150은 상기 도막 방수층(120)과 방수층 보호 숏크리트층(140)의 하부에 형성되는 배수부를 보인 것이다.In FIG. 150, the drainage portion formed at the bottom of the coating layer waterproof layer 120 and the waterproof layer protective shotcrete layer 140 is illustrated.

상기 도막 방수재에는 (주)아텍스에서 보급하고 있는 폴리톱(POLYTOP)을 이용하는 것이 바람직하며, 이 폴리톱은 폴리우레아(Polyurea) 탄성물질로 이소시아네이트 프리폴리머(Isocyanate prepolymer)인 A제와 아민(Amine)계 혼합물인 B제로 구성되어있고, A제와 B제를 가열, 혼합, 고압 분사하여 피착면에 분사하면 순간적으로 완전히 접착되면서 높은 인장강도와 신장성능을 지니며 방수와 방청, 그리고 내화학성이 뛰어난 매우 탄력적이고 매끈한 도막이 형성된다. 특히 내마모성, 내충격성, 내수성, 내약품성이 우수하고 시공 시에 도막의 두께를 자유롭게 조절할 수 있으며 콘크리트 뿐 만 아니라 철판, 알루미늄 등 다양한 피착면에 우수한 접착력을 나타낸다.It is preferable to use a polytop (POLYTOP), which is widely used in Attex Co., Ltd. for the coating film waterproofing material, and the polytop is a polyurea elastomer and isocyanate prepolymer A and an amine (Amine) system. It is composed of B agent which is a mixture. When A and B agent are heated, mixed and sprayed on the surface by spraying with high pressure, they are completely adhered instantly and have high tensile strength and elongation performance. An elastic and smooth coating film is formed. In particular, it has excellent abrasion resistance, impact resistance, water resistance, chemical resistance, and can freely control the thickness of the coating film during construction, and shows excellent adhesion to various adhered surfaces such as iron plate and aluminum as well as concrete.

폴리톱은 분사 3초 후부터 경화가 시작되어 1분 이내에 경화가 완료되어 도막 위를 걸을 수 있으며, 수직면이나 경사면뿐만 아니라 천정면까지도 시공이 가능하다.The polytops begin to cure after 3 seconds of spraying and can be cured within 1 minute to walk on top of the coating, and can be applied to ceilings as well as vertical or inclined surfaces.

폴리톱 시공에서 최상의 품질을 얻기 위해서는 A제와 B제를 적절하게 혼합하고 부피비로 일정하게 1:1로 도장할 수 있는 고온, 고압의 충돌 혼합식 스프레이 장비가 필요하고, A제와 B제의 점도를 알맞게 조절하는 것이 중요하다.In order to obtain the best quality in polytop construction, high-temperature, high-pressure collision-mixing spray equipment is required to properly mix agent A and agent B and to paint at a constant volume ratio of 1: 1. It is important to adjust the viscosity appropriately.

그리고, 폴리우레아는 이소시아네이트 프리폴리머와 특수 혼합된 폴리에테르아민(Polyetheramine)이 연쇄적으로 반응하여 생성되는 것으로 분자구조 내에 우레아 결합을 가지고 있는 고분자 물질을 말하며, 수지의 반응성이 매우 빨라 3 - 10초 이내의 겔 타임(Gel-time)을 갖는 초속경화형이다(경화속도는 조절이 가능하다).In addition, polyurea refers to a polymer material having a urea bond in its molecular structure, which is produced by a chain reaction of an isocyanate prepolymer and a specially mixed polyetheramine. The reactivity of the resin is very fast within 3 to 10 seconds. It is a super fast curing type with a gel-time of (hardening speed is adjustable).

폴리톱 반응의 구조식은 다음 반응식1과 같다.The structural formula of the polytop reaction is shown in Scheme 1 below.

Figure 112005033548934-PAT00001
Figure 112005033548934-PAT00001

최근에도 이 폴리우레아 수지에 대한 신기술 개발 및 연구가 활발히 진행 중으로, 사용목적에 따라 폴리우레아 스프레이 탄성체를 여러 가지 상업적 응용분야에 폭 넓게 적용할 수 있으며, 콘크리트, 섬유, 목재, 폼 재코팅 등이 이 응용분야에 속한다.Recently, new technology development and research on this polyurea resin have been actively conducted, and polyurea spray elastomers can be widely applied to various commercial applications according to the purpose of use, and concrete, fiber, wood, foam recoating, etc. Belongs to this application.

위와 같은 폴리톱은 외부로부터 완전히 차단된 도막 방수층이 형성되어 뛰어난 방수, 방청효과가 있고, 다양한 인장강도와 신장율, 높은 부착강도, 내화학성, 내마모성, 내충격성, 내수성, 및 용출성안전등이 우수하며, 열안정성 및 내후성이 우수하고, 다양한 물성을 갖는 탄성체("예" 연질형 ~ 경질형)를 제조할 수 있으며, 여러 가지 상업적 응용분야에 폭넓게 적용할 수 있고, 반응성이 균일하여 코팅직후 표면위에 습도와 낮은기온의 영향을 받지 않으므로 작업의 용이성하며, 표면의 청소가 용이하고 시공면이 연결부위 없이 마무리 등의 특징이 있다.The polytop has the excellent waterproofing and rust prevention effect by forming the waterproofing layer of the film completely blocked from the outside, and has excellent tensile strength, elongation rate, high adhesion strength, chemical resistance, abrasion resistance, impact resistance, water resistance, and dissolution safety. It has excellent thermal stability and weather resistance, and can produce elastomers (eg, "soft" to "hard") having various physical properties, and can be widely applied to various commercial applications. It is easy to work because it is not affected by humidity and low temperature, and it is easy to clean the surface.

도 12 내지 도 15는 본 발명의 일 실시예에 의한 방수터널을 보인 도면으로서, 도 12에는 암반터널의 심도에 따라 지표수와 지하수 영향을 받는 얕은 심도영역과 깊은 심도영역의 영역 구분도가 도시되고, 도 13에는 암반터널의 깊은 심도영역 영역에서의 방수구간 설정도가 도시되어 있다. 12 to 15 are views illustrating a waterproof tunnel according to an embodiment of the present invention, in FIG. 12 is a diagram showing a region of shallow depth and deep depth areas affected by surface water and groundwater according to the depth of a rock tunnel. FIG. 13 shows a waterproof section setting diagram in a deep depth region region of a rock tunnel.

이하 본 발명을 상세하게 설명하기 전에 도 12 및 도 13을 참조하여 암반 내에 설치되는 터널(100)의 누수현상을 살펴보면 암반내의 물이 유입되는 현상은 절리, 균열, 파쇄대등의 불연속면으로 투수층에 저수된 지하수가 유입되는 현상과 지표면의 지표수가 불연속면의 틈을 따라 터널내로 유입되는 현상으로 구분된다.Before describing the present invention in detail with reference to Figures 12 and 13 to look at the leakage of the tunnel 100 is installed in the rock is a phenomenon in which water is introduced into the rock is stored in the permeable layer as a discontinuous surface, such as joints, cracks, crushing zone Groundwater flows into the tunnel and groundwater flows into the tunnel along the discontinuities.

따라서 도 12와 같이 암반 터널(100)은 터널의 영역적 특성에 따라 결정되는 경계심도(C), 예를 들어 심도 50m인 지점을 기준으로 얕은 심도영역(101)과 깊은 심도영역(102) 으로 구분되며, 경계심도(C) 50m이내의 얕은 심도영역(101)의 경우는 암반의 불연속면이 지표와 개구되어 있을 가능성이 높기 때문에 지표수 영향을 받을 수 있는 누수가능 영역이며, 경계심도(C)가 50m이상인 깊은 심도영역(102)의 경우는 암반의 치밀성으로 투수계수가 낮아 암반 내에 저수된 지하수만 불연속면에 따라 유출되는 현상으로 터널굴착 공사 중에 누수개소에 대한 육안 식별 이 가능한 영역이다.Accordingly, as shown in FIG. 12, the rock tunnel 100 is divided into a shallow depth region 101 and a deep depth region 102 based on a boundary depth C determined according to a regional characteristic of the tunnel, for example, a depth of 50 m. In the case of the shallow depth region 101 within 50 m of the boundary depth C, the discontinuity surface of the rock is likely to be open to the surface, and thus, it is a leaky region that may be affected by the surface water. In the case of the deep depth area 102 of 50 m or more, the permeability coefficient is low due to the rock density, and only the groundwater stored in the rock flows out along the discontinuous surface, which is a region that can be visually identified for leaks during tunnel excavation work.

이와 같이 본 발명은 암반 터널(100)의 내부를 경계심도(C)에 따라 지표수 영향으로 누수되는 얕은 심도영역(101)과 지하수 영향으로 누수되는 깊은 심도영역(102)으로 구분함과 아울러, 상기 얕은 심도영역(101)을 누수영역(D1)으로 구분하고, 상기 깊은 심도영역(102)을 지하수가 누수되는 누수영역(D1)과, 누수되지 않는 비누수영역(D2)으로 구분하여, 상기 깊은 심도영역(102)의 누수영역(D1)만을 선정하여 부분적으로 방수공사를 시행하는 것을 특징으로 한다.As described above, the present invention divides the interior of the rock tunnel 100 into a shallow depth region 101 leaked by the surface water effect and a deep depth region 102 leaked by the groundwater effect according to the boundary depth C. The shallow depth region 101 is divided into a leakage region D1, and the deep depth region 102 is divided into a leakage region D1 through which groundwater leaks and a non-leakage soap region D2. Selecting only the leakage area (D1) of the depth area 102 is characterized in that to perform a partial waterproof construction.

도 14에는 방수구간에서 비방수구간으로 물의 이동과 확산을 방지하기 위한 부분 도막방수층의 단부 구조를 보인 확대 단면도가 도시되고, 도 15에는 도막방수층의 배수 구조를 보인 단면도가 도시되어 있다.14 is an enlarged cross-sectional view showing the end structure of the partial coating waterproof layer to prevent the movement and diffusion of water from the waterproof section to the non-waterproof section, and FIG. 15 is a cross-sectional view showing the drainage structure of the coating film waterproof layer.

이하, 도 10 내지 도 15를 함께 참조하면, 본 발명에 의한 부분 도막방수 터널은 암반 터널(100)의 내부를 경계심도(C)에 따라 경계심도(C) 외부의 지표수 영향에 의해 누수되는 얕은 심도영역(101)과, 경계심도(C) 내부의 지하수 영향으로 누수되는 깊은 심도영역(102)으로 구분함과 아울러, 얕은 심도영역(101)을 누수영역(D1)으로 구분하고, 깊은 심도영역(102)은 지하수가 누수되는 누수영역(D1)과, 누수되지 않는 비누수영역(D2)으로 구분 설정하며, 상기 터널(100)의 내주면에 보강 숏크리트층(110)을 하고, 상기 얕은 심도영역(101)과, 깊은 심도영역(102)의 누수영역(D1)에 배수부재(120)를 부착하며, 이 배수부재(120) 위에 도막 방수층(130)을 형성하고, 이 도막 방수층(130) 위에 상기 도막 방수층(130) 보호를 위한 방수층 보호 숏크리트층(140)을 형성하여 구성된다.Hereinafter, referring to FIGS. 10 to 15, in the partial coating waterproof tunnel according to the present invention, the interior of the rock tunnel 100 may be shallow due to surface water influence outside the boundary depth C according to the boundary depth C. The depth area 101 is divided into a deep depth area 102 that leaks due to the groundwater effect inside the boundary depth C, and the shallow depth area 101 is divided into a leakage area D1, and the deep depth area is separated. Reference numeral 102 is set by dividing the ground water leakage area (D1) and the non-water leakage area (D2), the reinforcement shotcrete layer 110 on the inner peripheral surface of the tunnel 100, the shallow depth area And a drain member 120 is attached to the water leakage region D1 of the deep depth region 102, and the coat waterproof layer 130 is formed on the drain member 120, and the coat waterproof layer 130 is It is configured by forming a waterproof layer protective shotcrete layer 140 for protecting the coating film waterproof layer 130.

그리고 상기 도막 방수층(130)은 도 14와 같이 얕은 심도영역(101)과, 깊은 심도영역(102)의 누수영역(D1)에서 비누수영역(D2)으로 물의 이동이나 확산을 방지하기 위해서 도 14와 같이 배수부재(120)의 양단부 외부로 누수 차단부(131)를 확장 형성하여 터널(100)의 노출된 내주면에 직접 접합되도록 구성된다.In addition, the coating film waterproofing layer 130 may have a shallow depth region 101 as shown in FIG. 14, and a water diffusion layer D1 of the deep depth region 102 to prevent the movement or diffusion of water from the water leakage region D1 to the soap water region D2. As shown in the drawing, the leakage blocking part 131 is formed to extend outside the both ends of the drain member 120 to be directly joined to the exposed inner circumferential surface of the tunnel 100.

여기서 상기 누수 차단부(131)는 폭(d)을 0.5m∼1.0m의 범위로 형성되고, 도막두께 2mm∼4㎜이상으로 형성하는 것이 바람직하다.Here, the water leakage blocking unit 131 is preferably formed with a width d in a range of 0.5 m to 1.0 m, and a coating film thickness of 2 mm to 4 mm or more.

상기 도막 방수층(130)의 누수 차단부(131)는 도포로 겹칠을 하여 배수부재(120) 양단부가 터널(100)의 내주면과 일체화로 되도록 형성된 방수층이므로 깊은 심도영역(102)의 비누수영역(D2)으로 물의 이동과 확산을 방지토록 하며, 얕은 심도영역(101)과, 깊은 심도영역(102)의 누수영역(D1)의 암반에서 배출되는 물은 도막 방수층(130) 내부의 배수부재(120)에 의해 형성되는 배수층을 통하여 터널(100)의 하단부로 흘러 도 15와 같이 터널(100)의 양측면 하단부에 설치된 배수부(150)로 집수되어 배수관(152)으로 배수된다.The water leakage blocking portion 131 of the waterproof layer 130 is overlapped by coating so that both ends of the drain member 120 are formed to be integrated with the inner circumferential surface of the tunnel 100, so that the water-absorbing region of the deep depth region 102 is formed. D2) to prevent the movement and diffusion of water, and the water discharged from the rock of the shallow depth region 101 and the leakage region D1 of the deep depth region 102 is the drain member 120 inside the waterproofing layer 130 of the coating film. Flow through the drainage layer formed by the lower end of the tunnel 100 flows into the drain 150 installed in the lower end of both sides of the tunnel 100 as shown in Figure 15 is drained to the drain pipe 152.

상기 배수부(150)는 배수부재(120)와 도막 방수층(130)과 양측 하단부 내부에 다수개의 구멍이 주면에 형성된 유공관(151)이 배수부재(120) 내부로 삽입됨과 아울러 주위에 여과재(154)가 충진되고, 상기 배수부재(120)와 도막 방수층(130)의 하단부가 유공관(151)을 감싸는 형태로 절곡되어 부착되며, 유공관(151)과 배수관(152)의 사이에 복수개의 연결관(153)이 연결된 구성으로 되어 있다.The drainage part 150 includes a drainage member 120, a coating layer waterproofing layer 130, and a perforated tube 151 having a plurality of holes formed in a main surface inside both bottom ends thereof, and inserted into the drainage member 120. ) Is filled, the lower end of the drain member 120 and the coating layer waterproof layer 130 is bent and attached to surround the perforated pipe 151, a plurality of connecting pipes (between the perforated pipe 151 and the drain pipe 152) 153 is connected.

도면에서 미설명 부호 160은 퇴수거를 보인 것이고, 161은 퇴수거(160)와 배수관(152)을 연결하는 연결관을 보인 것이다.In the drawings, reference numeral 160 denotes a drainage strip, and 161 shows a connection pipe connecting the drainage strip 160 and the drain pipe 152.

도 16 (a),(b)는 터널에서 배수되는 용수를 집수하여 유도배수하는 배수구조의 일예를 보인 정면도 및 종단면도가 각각 도시되고, 도 17 (a),(b)에는 터널에서 배수되는 용수를 집수하여 유도배수하는 배수구조의 다른 예를 보인 정면도 및 종단면도가 각각 도시되어 있다.16 (a) and 16 (b) show a front view and a longitudinal cross-sectional view showing an example of a drainage structure for collecting and inducing drainage of water drained from a tunnel, and FIGS. 17 (a) and 17 (b) show drainage in a tunnel. A front view and a longitudinal cross-sectional view showing another example of a drainage structure for collecting and inducing drainage of water to be drawn are shown.

본 발명에 의한 암반 부분 도막방수 터널을 시공함에 있어서 모든 도포형 방수자재는 습윤한 면은 시공이 가능하나, 흐르는 용수에 대해서는 시공이 불가능한 점을 보완하기 위해서, 터널내부의 용수개소에 대해서는 도 16 및 도 17에 도시한 바와 같이 통상 유도배수방법의 유도 배수수단(170)을 실시한 후 시공하게 되며, 도 16에 도시된 유도 배수수단(170)은 터널(100)의 암반의 용수부에 천공을 하여 호스나 관(171)을 삽입시키고 이 삽입관(171)들을 연결관(172)으로 연결하여 배수로(173)로 배수시키는 형태로 적용하거나, 도 17에 도시된 바와 같이 터널(100)의 벽면에 흐르는 물은 반달형태의 호스관(174)을 부착하고 호스관(174)들을 연결부(175)로 연결하여 배수로(173)로 연결시키는 형태로 적용한다.In the construction of the rock partial waterproofing tunnel according to the present invention, in order to compensate for the fact that all coated type waterproofing materials can be constructed on the wet surface, the construction is impossible for flowing water. And the construction is performed after the induction drainage means 170 of the normal induction drainage method, as shown in Figure 17, the induction drainage means 170 shown in Figure 16 to puncture the water in the rock of the tunnel 100 Insert a hose or pipe 171 and connect the insertion pipes 171 to the connection pipe 172 to drain to the drain 173, or as shown in Figure 17 the wall surface of the tunnel 100 The water flowing in is applied in the form of attaching the hose pipe 174 in the form of a half moon and connecting the hose pipes 174 to the connection portion 175 to the drainage path 173.

도 18 내지 도 21은 본 발명의 일 실시예에 의한 부분 도막방수 공법의 공정을 보인 것이며, 각 도면에서 (a)는 폭방향, (b)는 길이방향으로 각각 절단하여 보인 단면도로서, 도 18에는 터널 굴착 후 숏크리트하는 과정을 보인 단면도가 도시되고, 도 19에는 숏크리트 벽면에 배수부재를 설치하는 과정을 보인 단면도가 도시되어 있으며, 도 20에는 배수부재 위에 도막방수 뿜칠작업을 하는 과정을 보인 단면도가 도시되고, 도 21에는 도막방수층 보호를 위하여 숏크리트하는 과정을 보인 단면도가 도시되어 있다.18 to 21 are views showing a process of the partial coating waterproofing method according to an embodiment of the present invention, in each drawing (a) is a cross-sectional view cut in the width direction, (b) in the longitudinal direction, respectively, Figure 18 The cross-sectional view showing the process of shotcrete after the excavation of the tunnel is shown, Figure 19 is a cross-sectional view showing the process of installing the drain member on the shotcrete wall, Figure 20 is a cross-sectional view showing a process of spraying the coating film on the drain member FIG. 21 is a cross-sectional view illustrating a process of shotcreting for protecting a coating waterproof layer.

이하, 도 10 내지 도 17, 그리고 도 18 내지 도 21을 참조하여 설명하면 본 발명에 의한 부분 도막방수 터널 시공방법은 도 12 내지 도 14와 같이 암반 터널(100)의 내부를 경계심도(C)에 따라 지표수 영향으로 누수되는 경계심도(C) 외부의 얕은 심도영역(101)과, 지하수 영향으로 누수되는 경계심도(C) 내부의 깊은 심도영역(102)으로 구분하고, 깊은 심도영역(102)을 지하수가 누수되는 누수영역(D1)과, 누수되지 않는 비누수영역(D2)으로 구분 설정하는 방수 시공영역 설정단계와, 도 18과 같이 상기 암반 터널(100)의 내주면에 보강 숏크리트층(110)을 형성하는 보강 숏크리트층 형성단계와, 도 19와 같이 상기 얕은 심도영역(101)과, 깊은 심도영역(102)의 누수영역(D1)에 배수부재(120)를 부착하는 배수부재 부착단계와, 도 20과 같이 상기 배수부재(110) 위에 도막 방수재를 도포하여 도막 방수층(130)을 형성하는 도막 방수층 형성단계와, 도 21과 같이 상기 도막 방수층(130) 위에 상기 도막 방수층(130) 보호를 위한 방수층 보호 숏크리트층(140)을 형성하는 방수층 보호 숏크리트층 형성단계를 포함하여 구성된다.Hereinafter, referring to FIGS. 10 to 17 and FIGS. 18 to 21, the method for constructing a partial coating waterproof tunnel according to the present invention may have a boundary depth C inside the rock tunnel 100 as shown in FIGS. 12 to 14. And the deep depth zone 102 outside the boundary depth C leaked by the surface water effect, and the deep depth zone 102 inside the boundary depth C leaked by the groundwater effect. The waterproof construction area setting step of setting the ground water to the water leakage area (D1) and the non-water leakage area (D2), and the reinforced shotcrete layer 110 on the inner circumferential surface of the rock tunnel 100 as shown in FIG. Forming a reinforcement shotcrete layer; attaching the drainage member 120 to the shallow depth region 101 and the leakage region D1 of the deep depth region 102 as shown in FIG. 19; 20, the coating film waterproof material on the drain member 110 as shown in FIG. A waterproofing layer protective shotcrete layer forming a waterproofing layer protective shotcrete layer 140 for protecting the coating waterproofing layer 130 on the coating waterproofing layer 130 as shown in FIG. 21; It comprises a forming step.

이하 이와 같은 본발명에 의한 부분 도막방수 터널의 시공예를보다 구체적으로 설명하면 본 발명을 실시함에 있어서는 먼저 도 12 및 도 13과 같이 암반 터널(100)의 내부를 경계심도(C)에 따라 지표수 영향으로 누수되는 경계심도(C) 외부의 얕은 심도영역(101)과, 지하수 영향으로 누수되는 경계심도(C) 내부의 깊은 심도영역(102)으로 구분하고, 깊은 심도영역(102)을 지하수가 누수되는 누수영역(D1)과, 누수되지 않는 비누수영역(D2)으로 구분 설정하는 방수 시공영역 설정하다.Hereinafter, the construction of the partial coating waterproof tunnel according to the present invention will be described in more detail. According to the present invention, first, the surface water of the rock tunnel 100 according to the boundary depth C will be described with reference to FIGS. 12 and 13. The shallow depth zone 101 outside the boundary depth C leaked by the impact, and the deep depth zone 102 inside the boundary depth C leaked by the groundwater impact, are divided into the deep depth zone 102. The waterproof construction area is divided into a water leakage area D1 and a non-water leakage area D2.

예를 들어 경계심도(C) 50m이내의 얕은 심도영역(101)의 경우는 암반의 불연 속면이 지표와 개구되어 있을 가능성이 높기 때문에 지표수 영향을 받을 수 있으므로 누수가능 영역으로 선정해서 방수공사를 시행하며 또한 경계심도(C) 50m이상의 깊은 심도영역(102)의 경우는 암반의 치밀성으로 투수계수가 낮아 암반 내에 저수된 지하수만 불연속면에 따라 유출되는 현상으로 터널굴착 공사 중에 누수개소에 대한 육안 및 측정 장비에 의해 식별이 가능하다. 따라서 깊은 심도영역(102)의 누수개소를 식별하여 누수영역(D1)과 비누수영역(D2)으로 구분한다.For example, the shallow depth zone 101 within 50m of boundary depth (C) is likely to be affected by surface water because the discontinuous surface of the rock is likely to be open to the surface, so it may be affected by surface water. In the case of the deep depth area 102 with a boundary depth (C) of 50m or more, the permeability coefficient is low due to the rock density, and only the groundwater stored in the rock flows along the discontinuous surface. It can be identified by the equipment. Therefore, the leakage point of the deep depth area 102 is identified and divided into the leakage area D1 and the soap water area D2.

이어서 도 18과 같이 암반 터널(100)의 내주면에 보강 숏크리트층(110)을 통상의 숏크리트 장비(20)를 이용하여 타설하여 형성한다.Subsequently, as shown in FIG. 18, the reinforcement shotcrete layer 110 is formed on the inner circumferential surface of the rock tunnel 100 by using the conventional shotcrete equipment 20.

이와 같이 보강 숏크리트층(110)을 형성한 후, 터널내부의 용수개소에 대해서는 필요에 따라 도 16 및 도 17에 도시한 바와 같이 통상 유도배수방법의 유도 배수수단(170)을 설치한 후 다음 단계를 실시한다.After the reinforcement shotcrete layer 110 is formed in this way, water in the tunnel is provided with induction drainage means 170 of the induction drainage method as shown in FIGS. Is carried out.

이어서 도 19와 같이 위에서 구분 설정된 얕은 심도영역(101)과, 깊은 심도영역(102)의 누수영역(D1)에 상기 보강 숏크리트층(110) 위로 투수층의 배수부재(120)를 밀착시켜서 압정 혹은 못과 같은 체결부재로 고정시킨다.Subsequently, as shown in FIG. 19, the shallow depth region 101 set above and the water leakage region D1 of the deep depth region 102 are brought into close contact with the drainage member 120 of the water permeable layer on the reinforcement shotcrete layer 110. Fix it with a fastening member such as

이후 도 20과 같이 도막 방수재 분사장비(70)로 2액형 분사용 폴리우레아 탄성물질을 A액과 B액을 혼합하여 배수부재(120) 표면에 고압분사 시키면 도막 방수재가 2분 이내에 고결되어 도막 방수층(130)이 형성된다.After the high pressure spray on the surface of the drain member 120 by mixing the A- and B-component polyurea elastic material for two-component spraying with the coating film waterproofing material spraying equipment 70 as shown in Figure 20, the coating film waterproofing material is solidified within 2 minutes 130 is formed.

이 도막 방수층(130)은 도막두께 2㎜ㅁ0.3㎜를 표준으로 하여 누수량에 따라 도막의 두께는 조절하여 시행한다.The coating film waterproof layer 130 has a coating film thickness of 2 mm 0.3 0.3 mm as a standard, and the thickness of the coating film is adjusted according to the amount of leakage.

또한 상기 도막 방수층(130)은 얕은 심도영역(101)과, 깊은 심도영역(102)의 누수영역(D1)에서 비누수영역(D2)으로 물의 이동이나 확산을 방지하기 위해서 도 14와 같이 배수부재(120)의 양단부 외부로 누수 차단부(131)를 확장 형성하여 터널(100)의 노출된 내주면에 직접 접합되도록 구성된다.In addition, the coating film waterproof layer 130 is a drainage member as shown in FIG. 14 to prevent the movement or diffusion of water from the shallow depth region 101 and the leak region D1 of the deep depth region 102 to the soap water region D2. The leakage blocking part 131 is formed to extend outward from both ends of the 120 to be directly joined to the exposed inner circumferential surface of the tunnel 100.

여기서 상기 누수 차단부(131)는 폭(d)을 0.5m∼1.0m의 범위로 형성되고, 도막두께 2mm∼4㎜이상이상으로 형성하는 것이 바람직하다.Here, the leakage blocking portion 131 is preferably formed with a width d in a range of 0.5 m to 1.0 m, and a coating film thickness of 2 mm to 4 mm or more.

이와 같이 도막 방수층(130)을 형성하는 단계에서 터널(100)의 양측 하단부에는 도 15와 같이 배수부(150)를 설치하여 얕은 심도영역(101)과, 깊은 심도영역(102)의 누수영역(D1)의 암반에서 배출되는 물은 도막 방수층(130) 내부의 배수부재(120)에 의해 형성되는 배수층을 통하여 터널(100)의 하단부로 흘러 양측 하단부의 배수부(150)로 집수되어 배수관(152)으로 배수되도록 한다.Thus, in the step of forming the coating layer waterproof layer 130, the drainage portion 150 is installed at both lower ends of the tunnel 100 as shown in FIG. 15, so that the shallow depth region 101 and the leakage region of the deep depth region 102 ( Water discharged from the rock of D1) flows through the drainage layer formed by the drainage member 120 inside the waterproofing layer 130 to the lower ends of the tunnels 100 and is collected into the drainage parts 150 at both lower ends of the drain pipe 152. To drain).

이때 상기 배수부(150)는 배수부재(120)와 도막 방수층(130)과 양측 하단부 내부에 다수개의 구멍이 주면에 형성된 유공관(151)을 배수부재(120) 내부로 삽입함과 아울러 주위에 여과재(154)를 충진하고, 상기 배수부재(120)와 도막 방수층(130)의 하단부가 유공관(151)을 감싸는 형태로 절곡하여 부착하며, 유공관(151)과 배수관(152)의 사이에 복수개의 연결관(153)을 연결하여 구성한다.At this time, the drainage portion 150 is inserted into the drainage member 120, the coating layer waterproof layer 130 and the air hole pipe 151 formed in the main surface of the plurality of holes in the lower end of both sides into the drainage member 120 and the filter material around Filled 154, the lower end of the drain member 120 and the coating film waterproof layer 130 is bent and attached in a form surrounding the perforated pipe 151, a plurality of connections between the perforated pipe 151 and the drain pipe 152 It is configured by connecting the pipe (153).

이어서 도 21과 같이 상기 도막 방수층(130) 위에 상기 도막 방수층(130) 보호를 위한 방수층 보호 숏크리트층(140)을 숏크리트 장비(20)로 20mm∼45mm의 두께로 형성하여 부분 도막방수 터널의 시공을 완료한다.Subsequently, as shown in FIG. 21, a waterproofing layer protective shotcrete layer 140 for protecting the coating waterproofing layer 130 is formed to have a thickness of 20 mm to 45 mm using the shotcrete equipment 20 to protect the coating waterproofing layer 130. To complete.

도 22는 본 발명의 다른 실시예에 의한 부분 도막방수 공법으로 시공되는 방수터널을 폭방향으로 절단하여 보인 종단면도이고, 도 23은 본 발명의 다른 실시예 에 의한 부분 도막방수 공법으로 시공되는 방수터널을 길이방향으로 절단하여 보인 부분 종단면도로서, 이에 도시한 바와 같이 본 발명의 일 실시예에 의한 시공된 부분 도막방수 터널은 도 10 내지 도 15와 같이 암반 터널(100)의 내주면에 보강 숏크리트층(110)을 형성한 후 누수영역에 배수부재(120)를 부착하고 도막 방수재를 분사 도포하여 도막 방수층(130)을 일연체로 형성하여 누수영역의 방수를 완벽하게 차단할 수 있는 것이므로 도막 방수층(130) 위로 방수층 보호 숏크리트층(140)을 20mm∼45mm의 두께로만 형성하여도 암반 터널(100)의 내주면을 전체적으로 완벽하게 방수할 수 있게 되는 것이나, 도 22 및 도 23과 같이 암반 터널(100)의 양측면 하측부에 필요에 따라 라이닝 콘크리트층(180)을 형성할 수 있으며, 이와 같이 라이닝 콘크리트층(180)을 형성하면 벽면의 내구성이 보다 증가된다.22 is a longitudinal cross-sectional view of the waterproof tunnel constructed by the partial coating waterproofing method according to another embodiment of the present invention by cutting in the width direction, Figure 23 is a waterproof construction of the partial coating waterproofing method according to another embodiment of the present invention Partial longitudinal cross-sectional view shown by cutting the tunnel in the longitudinal direction, the construction of the partial coating waterproof tunnel according to an embodiment of the present invention as shown in Figure 10 to 15 as shown in the reinforcement shotcrete on the inner peripheral surface of the rock tunnel 100 After the layer 110 is formed, the drainage member 120 is attached to the leaking area, and the coating film waterproofing material is sprayed and applied to form the coating film waterproofing layer 130 as a single body so that the waterproofing of the leaking area can be completely blocked. 130) Even if the waterproof layer protection shotcrete layer 140 is formed only with a thickness of 20mm to 45mm, it is possible to completely waterproof the entire inner circumferential surface of the rock tunnel 100, As shown in FIGS. 22 and 23, lining concrete layers 180 may be formed on both sides of the lower side of the rock tunnel 100 as necessary. The lining concrete layer 180 may be formed to increase durability of the wall surface. .

도 24 내지 도 28은 본 발명의 또 다른 실시예에 의한 부분 도막방수 공법을 설명하기 위한 도면으로서, 도 24에는 부분 도막방수 공법으로 시공되는 방수터널을 폭방향으로 절단하여 보인 종단면도가 도시되고, 도 25에는 부분 도막방수 공법으로 시공되는 방수터널을 길이방향으로 절단하여 보인 종단면도가 도시되어 있으며, 도 26에는 도 25의 요부 확대 단면도가 도시되어 있다.24 to 28 are views for explaining a partial film waterproofing method according to another embodiment of the present invention, Figure 24 is a longitudinal cross-sectional view of the waterproof tunnel cut in the width direction constructed by the partial film waterproofing method is shown FIG. 25 illustrates a longitudinal cross-sectional view of a waterproof tunnel constructed by a partial coating waterproof method in a longitudinal direction, and FIG. 26 illustrates an enlarged cross-sectional view of a main part of FIG. 25.

그리고 도 27 (a),(b)에는 배수부재 일체형 방수도막 위에 2차로 방수도막을 형성하는 과정을 보인 방수터널의 폭방향 종단면도 및 길이방향 부분 종단면도가 도시되고, 도 28에는 도 27 (b)의 요부 확대 단면도가 도시되어 있다.27 (a) and 27 (b) show a longitudinal longitudinal cross-sectional view and a longitudinal partial cross-sectional view of a waterproof tunnel showing a process of forming a secondary waterproof coating on the drainage member integrated waterproof coating, and FIG. An enlarged cross-sectional view of the main portion of b) is shown.

상술한 바와 같이 본 발명에 의한 암반 부분 도막방수 터널을 시공함에 있어서 모든 도포형 방수자재는 습윤한 면은 시공이 가능하나, 흐르는 용수에 대해서는 시공이 불가능한 점을 보완하기 위해서, 터널내부의 용수개소에 대해서는 도 16 및 도 17에 도시한 바와 같이 통상 유도배수방법의 유도 배수수단(170)을 실시한 후 시공하는 방법과, 도 24 내지 도 28에 도시된 바와 같은 다른 실시예의 형태로 시공하는 방법이 있다.As described above, in the construction of the partial rock waterproofing tunnel according to the present invention, all coated type waterproofing materials can be constructed on a wet surface, but in order to compensate for the impossibility of construction for flowing water, the water points inside the tunnel. As shown in FIGS. 16 and 17, a method of constructing the induction drainage means 170 of the induction drainage method and the method of constructing another embodiment as shown in FIGS. 24 to 28 are shown. have.

도 22 내지 도 25에 도시된 본 발명의 또 다른 실시예에 의한 부분 도막방수 터널은 암반 터널(100)의 내부를 경계심도(C)에 따라 지표수 영향으로 누수되는 경계심도(C) 외부의 얕은 심도영역(101)과, 지하수 영향으로 누수되는 경계심도(C) 내부의 깊은 심도영역(102)으로 구분하고, 깊은 심도영역(102)을 지하수가 누수되는 누수영역(D1)과, 누수되지 않는 비누수영역(D2)으로 구분하며, 상기 터널(100)의 내주면에 보강 숏크리트층(110)을 하고, 배수부재(120)에 도막 방수재를 도포하여 1차 도막 방수층(130a)이 일체로 형성된 배수부재 일체형 도막 배수부재(130')를 상기 얕은 심도영역(101)과, 깊은 심도영역(102)의 누수영역(D1)에 부착함과 아울러, 이 일체형 도막 배수부재(130') 위에 도막 방수재를 도포하여 2차 도막 방수층(130b)을 형성하여 1차 도막 방수층(130a)과 2차 도막 방수층(130b)의 이중구조로된 도막 방수층(130)을 형성하며, 이 도막 방수층(130) 위에 상기 도막 방수층(130) 보호를 위한 방수층 보호 숏크리트층(140)을 형성하여 구성된다.22 to 25 is a partial coating waterproof tunnel according to another embodiment of the present invention is shallow outside the depth of the boundary (C) that leaks inside the rock tunnel 100 due to the surface water effect according to the boundary depth (C) The depth area 101 is divided into a deep depth area 102 inside the boundary depth C leaked by the groundwater effect, and the deep depth area 102 is leaked area D1 through which groundwater leaks, and is not leaked. It is divided into a soap water area (D2), the reinforcement shotcrete layer 110 on the inner circumferential surface of the tunnel 100, and the coating film waterproofing material is applied to the drainage member 120, the first coating film waterproofing layer (130a) integrally drained The member integral coating film draining member 130 'is attached to the shallow depth region 101 and the leak region D1 of the deep depth region 102, and a coating film waterproofing material is placed on the integral coating film draining member 130'. By coating to form a secondary coating waterproofing layer (130b) to the primary coating waterproofing layer (130a) and secondary The coating film waterproof layer 130 having a double structure of the coating film waterproof layer 130b is formed, and the waterproof film protective shotcrete layer 140 for protecting the coating film waterproof layer 130 is formed on the film waterproof layer 130.

이와 같은 본 발명의 또 다른 실시예에 의한 부분 도막방수 터널의 시공방법은 도 12 및 도 14와 같이 암반 터널(100)의 내부를 경계심도(C)에 따라 지표수 영향으로 누수되는 경계심도(C) 외부의 얕은 심도영역(101)과, 지하수 영향으로 누수되는 경계심도(C) 내부의 깊은 심도영역(102)으로 구분하고, 깊은 심도영역 (102)을 지하수가 누수되는 누수영역(D1)과, 누수되지 않는 비누수영역(D2)으로 구분 설정하는 방수 시공영역 설정단계와, 도 18과 같이 상기 암반 터널(100)의 내주면에 보강 숏크리트층(110)을 형성하는 보강 숏크리트층 형성단계와, 시공 현장의 외부 공장에서 배수부재(120)에 도막 방수재를 도포하여 1차 도막 방수층(130a)이 일체로 형성된 배수부재 일체형 도막 배수부재(130')를 제조하는 도막 배수부재 제조단계와, 이 일체형 도막 배수부재(130')를 시공 현장에 반입하여 도 24 및 도 25와 같이 상기 얕은 심도영역(101)과, 깊은 심도영역(102)의 누수영역(D1)에 일체형 도막 배수부재(130')를 부착하는 도막 배수부재 부착단계와, 도 27과 같이 상기 일체형 도막 배수부재(130') 위에 도막 방수재를 도포하여 2차 도막 방수층(130b)을 형성함으로써 이중구조의 도막 방수층(130)을 형성하는 도막 방수층 형성단계와, 도 21과 같이 상기 도막 방수층(130) 위에 상기 도막 방수층(130) 보호를 위한 방수층 보호 숏크리트층(140)을 형성하는 방수층 보호 숏크리트층 형성단계를 포함하여 구성된다. In the construction method of the partial coating waterproof tunnel according to another embodiment of the present invention as described above with reference to Figure 12 and 14 boundary depth (C) is leaked due to the surface water effect according to the boundary depth (C) in the rock tunnel 100 ) Into a shallow depth region (101) outside, and a deep depth region (102) inside the boundary depth (C) leaked by the groundwater effect, and the deep depth region (102) and a leaking region (D1) where groundwater is leaked; A waterproof construction area setting step of dividing and setting the non-leaking soapy water area (D2), and a step of forming a reinforcement shotcrete layer (110) on the inner circumferential surface of the rock tunnel (100) as shown in FIG. 18; The coating film drainage member manufacturing step of applying the coating film waterproofing material to the drainage member 120 at an external factory in the construction site to manufacture the drainage member integrated film drainage member 130 'in which the primary coating film waterproofing layer 130a is integrally formed; The coating film draining member (130 ') A coating film drainage member attaching step of attaching the integrated film drainage member 130 'to the shallow depth region 101 and the leakage region D1 of the deep depth region 102 as shown in FIGS. And a coating layer waterproofing step of forming a coating layer waterproofing layer 130 having a dual structure by coating a coating layer waterproofing material on the unitary coating layer draining member 130 'as shown in FIG. 27 to form a secondary coating layer waterproofing layer 130b. A waterproof layer protective shotcrete layer forming step of forming a waterproof layer protective shotcrete layer 140 for protecting the coating film waterproofing layer 130 is formed on the coating film waterproofing layer 130 as described above.

이와 같은 본 발명의 또 다른 실시예에 의한 부분 도막방수 터널의 시공방법은 시공 현장의 외부 공장에서 제조된 일체형 도막 배수부재(130')를 시공 현장에 반입하여 암반 터널(100)의 보강 숏크리트층(110)에 부착시킨 후, 시공 현장에서 일체형 도막 배수부재(130')의 표면에 도막 방수재를 도포하여 2차 도막 방수층(130b)을 형성함으로써 이중구조의 도막 방수층(130)을 형성하는 과정을 제외한 그 외 다른 구성 및 작용은 상기한 일 실시예와 동일하다.In the construction method of the partial coating waterproof tunnel according to another embodiment of the present invention, the reinforced shotcrete layer of the rock tunnel 100 is brought into the construction site by an integral coating drainage member 130 'manufactured at an external factory at the construction site. After attaching to the (110), the process of forming the coating layer waterproof layer 130 of the dual structure by forming a secondary coating layer waterproof layer (130b) by applying a coating film waterproofing material on the surface of the integrated coating film draining member (130 ') at the construction site Except for the other configurations and operations are the same as the above-described embodiment.

현재 주로 건설되는 국내 터널공법은 상술한 바와 같이 주로 숏크리트 록볼 트만으로 터널을 보강하는 NATM 터널공법이므로, 콘크리트 라이닝은 하중분담보다는 방수층의 보호가 주목적이며, 기존 방수시트에 의한 방수방법은 콘크리트 라이닝이 필수적인 이중셀 터널구조 형식으로 시행되는 반면에, 본 발명공법은 처짐이 적은 일체형 방수형태이므로 방수층 표면에 숏크리트 취부가 가능함으로써, 단일셀 터널구조 형태와 이중셀 터널구조 형태를 모두 충족시킬 수가 있어 터널공법에 발전을 기여할 수가 있으며, 기존 이중셀 터널구조 형태는 누수 등의 하자발생시에 누수지점 확인이 불가하여 유지보수가 곤란하였으나, 단일셀 터널구조 형태에서는 누수지점 확인과 유지보수가 간편하고 터널의 콘크리트 라이닝이 불필요하므로 막대한 량의 콘크리트 타설로 인한 공사비 절감과 공기단축이 효과가 있다.Currently, the domestic tunnel method, which is mainly constructed, is NATM tunnel method that mainly reinforces the tunnel with only shotcrete rock bolts as described above. Therefore, the concrete lining is mainly intended to protect the waterproof layer rather than the load sharing. While the present invention is implemented in the form of an essential double cell tunnel structure, the present invention method is a one-piece waterproof type with less deflection, so that shotcrete can be mounted on the surface of the waterproof layer, thereby satisfying both the single cell tunnel structure and the double cell tunnel structure. It can contribute to the development of the construction method, and the existing double cell tunnel structure is difficult to maintain due to the fact that it is impossible to check the leakage point when a defect such as water leakage occurs.However, in the single cell tunnel structure, it is easy to check and maintain the leakage point. Enormous amount of cones because no concrete lining is required Cost savings and shortening due to the placement agent is effective.

또한, 터널공사는 장소가 협소한 특성과 용도에 따라 다양한 변화단면 및 변곡점 등의 특수한 단면과 작업조건에 구애받지 않는 뿜칠형 방수방법을 적용하므로 시공이 용이하고 작업여건에 관계없이 시공이 가능한 장점을 가지고 있어 시공효율을 증대시킬 수 있다.In addition, the tunnel construction is easy to construct and can be applied regardless of working conditions because it applies a special cross-section such as various changing cross sections and inflection points and a spraying type waterproofing method regardless of the working conditions depending on the narrow characteristics and uses of the place. It can increase the construction efficiency.

본 발명에 의한 부분 도막방수 터널 및 그 시공방법은 터널방수공법은 기존 방수공법에 비하여 터널의 구간별 누수 혹은 누수예상 구역에만 선택적으로 시행할 수 있는 부분방수가 가능한 이점이 있다.The partial coating waterproof tunnel and its construction method according to the present invention has the advantage that the tunnel waterproofing method can be selectively performed only on the leakage or leakage area for each section of the tunnel compared to the existing waterproofing method.

또한 도포형 방수방법이므로 단면의 형상이나 작업조건에 제약을 받지 않고 간편하게 시공이 가능하다.In addition, since it is a coating type waterproofing method, it can be easily installed without being restricted by the shape of the cross section or the working conditions.

또한 터널공사에서 콘크리트 라이닝이 없는 단일셀 터널구조 형식이 가능하 여 유지관리와 보수작업이 용이한 이점이 있다.In addition, it is possible to maintain and repair a single cell tunnel structure without concrete lining in tunnel construction.

또한 공사기간이 단축되고 작업이 콘크리트 라이닝이 불필요하여 부분방수가 가능하므로 경제적인 이점이 있다.In addition, there is an economic advantage because the construction period is shortened and the work is partially waterproof because concrete lining is unnecessary.

Claims (12)

암반 터널(100)의 내주면이 방수가 필요한 누수영역(D1)과 방수가 필요하지 않는 비누수영역(D2)으로 구분되고, 상기 암반 터널(100)의 내주면에 보강 숏크리트층(110)이 형성되며, 상기 누수영역(D1)에 배수부재(120)가 부착되고, 이 배수부재(120) 위에 도막 방수재가 도포되어 도막 방수층(130)이 형성되며, 상기 배수부재(120)와 도막 방수층(130)의 양측면 하단부에 배수를 위한 배수부(150)가 설치되고, 상기 도막 방수층(130) 위에 상기 도막 방수층(130) 보호를 위한 방수층 보호 숏크리트층(140)이 형성되어 구성된 것을 특징으로 하는 부분 도막방수 터널.The inner circumferential surface of the rock tunnel 100 is divided into a water leakage area D1 that requires waterproofing and a soap water area D2 that does not need waterproofing, and a reinforcement shotcrete layer 110 is formed on the inner circumferential surface of the rock tunnel 100. The drainage member 120 is attached to the leakage region D1, and a coating waterproofing material is coated on the draining member 120 to form a coating waterproofing layer 130, and the draining member 120 and the coating waterproofing layer 130. Drainage part 150 for drainage is installed at the lower end of both sides of the, and the partial coating waterproof, characterized in that the waterproof layer protection shotcrete layer 140 for protecting the coating film waterproofing layer 130 is formed on the coating film waterproofing layer 130 tunnel. 제 1 항에 있어서, 상기 암반 터널(100)이 경계심도(C)에 따라 경계심도(C) 외부의 지표수 영향에 의해 누수되는 얕은 심도영역(101)과, 경계심도(C) 내부의 지하수 영향으로 누수되는 깊은 심도영역(102)으로 구분됨과 아울러, 얕은 심도영역(101)이 누수영역(D1)으로 구분되고, 깊은 심도영역(102)은 지하수가 누수되는 누수영역(D1)과, 누수되지 않는 비누수영역(D2)으로 구분되어 구성된 것을 특징으로 하는 부분 도막방수 터널.2. The shallow depth zone 101 according to claim 1, wherein the rock tunnel 100 leaks due to surface water influence outside the boundary depth C according to the boundary depth C, and the groundwater effect inside the boundary depth C. The deep depth area 102 is divided into a deep depth area 102, and the shallow depth area 101 is divided into a leak area D1, and the deep depth area 102 is a leak area D1 in which groundwater is leaked and is not leaked. Partial membrane waterproof tunnel, characterized in that divided into a non-soap water region (D2). 제 2 항에 있어서, 상기 터널(100)의 내주면에 보강 숏크리트층(110)이 되고, 배수부재(120)에 도막 방수재가 도포되어 1차 도막 방수층(130a)이 일체로 형성된 배수부재 일체형 도막 배수부재(130')가 상기 누수영역(D1)에 부착되며, 이 일체형 도막 배수부재(130') 위에 도막 방수재가 도포되어 2차 도막 방수층(130b) 형성됨으로써 1차 도막 방수층(130a)과 2차 도막 방수층(130b)의 이중구조로된 도막 방수층(130)이 형성되고, 이 도막 방수층(130) 위에 상기 도막 방수층(130) 보호를 위한 방수층 보호 숏크리트층(140)이 형성되어 구성된 것을 특징으로 하는 부분 도막방수 터널.According to claim 2, wherein the reinforcement shotcrete layer 110 on the inner circumferential surface of the tunnel 100, the coating film waterproofing material is applied to the drainage member 120, the primary coating film waterproofing layer 130a integrally formed drainage member coating film drainage A member 130 'is attached to the leakage region D1, and a coating film waterproofing material is coated on the integrated coating film draining member 130' to form a secondary coating film waterproofing layer 130b, thereby forming a primary coating film waterproofing layer 130a and a secondary film. The coating film waterproof layer 130 having a dual structure of the coating film waterproof layer 130b is formed, and the waterproof layer protective shotcrete layer 140 for protecting the coating film waterproof layer 130 is formed on the film waterproof layer 130. Partial membrane waterproof tunnel. 제 1 항 내지 제 3 항 중 어느 한 항에 있어서, 상기 도막 방수층(130)은 얕은 심도영역(101)과, 깊은 심도영역(102)의 누수영역(D1)에서 비누수영역(D2)으로 물의 이동이나 확산을 방지하기 위해서 배수부재(120)의 양단부 외부로 누수 차단부(131)가 확장 형성되어 터널(100)의 노출된 내주면에 접합된 구성을 특징으로 하는 부분 도막방수 터널.The water coating layer 130 according to any one of claims 1 to 3, wherein the coating layer 130 is formed of a shallow depth region 101 and a water leakage region D2 from a leakage region D1 of the deep depth region 102. Partial film waterproof tunnel, characterized in that the leakage blocking portion 131 is formed to extend to the outside of both ends of the drain member 120 to prevent movement or diffusion bonded to the exposed inner peripheral surface of the tunnel (100). 제 1 항 내지 제 3 항 중 어느 한 항에 있어서, 상기 배수부(150)는 배수부재(120)와 도막 방수층(130)과 양측 하단부 내부에 다수개의 구멍이 주면에 형성된 유공관(151)을 배수부재(120) 내부로 삽입함과 아울러 주위에 여과재(154)를 충진하고, 상기 배수부재(120)와 도막 방수층(130)의 하단부가 유공관(151)을 감싸는 형태로 절곡하여 부착하며, 유공관(151)과 배수관(152)의 사이에 복수개의 연결관(153)을 연결하여 구성된 것을 특징으로 하는 부분 도막방수 터널.According to any one of claims 1 to 3, The drainage portion 150 drains the hole 120 151 formed in the main surface of the drain member 120, the coating film waterproofing layer 130 and a plurality of holes in the lower end of both sides Inserted into the member 120 and filled with a filter material 154 around the bent, the lower end of the drain member 120 and the coating film waterproofing layer 130 is bent and attached in a form surrounding the perforated pipe 151, the perforated pipe ( Partial coating waterproof tunnel, characterized in that configured by connecting a plurality of connecting pipes (153) between the 151 and the drain pipe (152). 제 1 항 내지 제 3 항 중 어느 한 항에 있어서, 암반 터널(100)의 양측면 하측부에 상기 방수층 보호 숏크리트층(140)의 외측으로 라이닝 콘크리트층(180)을 형성하여 구성된 것을 특징으로 하는 부분 도막방수 터널. The portion according to any one of claims 1 to 3, wherein the lining concrete layer 180 is formed outside the waterproof layer protective shotcrete layer 140 on both lower sides of the rock tunnel 100. Coating waterproof tunnel. 제 1 항 내지 제 3 항 중 어느 한 항에 있어서, 상기 방수층 보호 숏크리트층(140)은 20mm∼45mm의 두께로 형성되어 구성된 것을 특징으로 하는 부분 도막방수 터널. The partial coating waterproof tunnel according to any one of claims 1 to 3, wherein the waterproof layer protective shotcrete layer (140) is formed to have a thickness of 20 mm to 45 mm. 제 1 항 내지 제 3 항 중 어느 한 항에 있어서, 상기 도막 방수층(130)은 2액형 분사용 폴리우레아 탄성물질인 도막 방수재를 도포하여 형성된 구성을 특징으로 하는 부분 도막방수 터널.The partial coating waterproof tunnel according to any one of claims 1 to 3, wherein the coating waterproof layer 130 is formed by applying a coating waterproof material which is a two-component spray polyurea elastic material. 제 1 항 내지 제 3 항 중 어느 한 항에 있어서, 상기 배수부재(120)는 부직포인 것을 특징으로 하는 부분 도막방수 터널.The partial coating waterproof tunnel according to any one of claims 1 to 3, wherein the drain member (120) is a nonwoven fabric. 제 4 항에 있어서, 상기 누수 차단부(131)는 폭(d)을 0.5m∼1.0m의 범위로 형성되고, 도막두께 2mm∼4㎜이상으로 형성되어 구성된 것을 특징으로 하는 부분 도막방수 터널.The partial coating waterproof tunnel according to claim 4, wherein the leakage blocking part (131) is formed with a width (d) in a range of 0.5 m to 1.0 m, and formed with a film thickness of 2 mm to 4 mm or more. 상기 암반 터널(100)을 경계심도(C)에 따라 경계심도(C) 외부의 지표수 영향에 의해 누수되는 얕은 심도영역(101)과, 경계심도(C) 내부의 지하수 영향으로 누 수되는 깊은 심도영역(102)으로 구분함과 아울러, 얕은 심도영역(101)을 누수영역(D1)으로 구분하고, 깊은 심도영역(102)은 지하수가 누수되는 누수영역(D1)과, 누수되지 않는 비누수영역(D2)으로 구분 설정하는 방수 시공영역 설정단계와, 상기 암반 터널(100)의 내주면에 보강 숏크리트층(110)을 형성하는 보강 숏크리트층 형성단계와, 상기 얕은 심도영역(101)과, 깊은 심도영역(102)의 누수영역(D1)에 배수부재(120)를 부착하는 배수부재 부착단계와, 상기 배수부재(110) 위에 도막 방수재를 도포하여 도막 방수층(130)을 형성하는 도막 방수층 형성단계와, 상기 도막 방수층(130) 위에 상기 도막 방수층(130) 보호를 위한 방수층 보호 숏크리트층(140)을 형성하는 방수층 보호 숏크리트층 형성단계를 포함하여 구성된 것을 특징으로 하는 부분 도막방수 터널의 시공방법.The depth of the rock tunnel 100 which is leaked by the surface water influence outside the boundary depth C according to the boundary depth C, and the deep depth which is leaked by the groundwater effect inside the boundary depth C. In addition to the area 102, the shallow depth area 101 is divided into a water leakage area D1, and the deep depth area 102 is a water leakage area D1 through which groundwater is leaked, and a non-water leakage area. (D2) the waterproof construction area setting step of setting, the reinforced shotcrete layer forming step of forming a reinforcement shotcrete layer 110 on the inner circumferential surface of the rock tunnel 100, the shallow depth area 101, and deep depth A drainage member attaching step of attaching the drainage member 120 to the leaking area D1 of the region 102, and a coating layer waterproofing layer forming step of forming a coating layer waterproofing layer 130 by applying a coating layer waterproofing material on the drainage member 110; On top of the coating waterproof layer 130 to protect the coating waterproof layer 130 Construction method of a partial coating waterproof tunnel, characterized in that it comprises a step of forming a waterproof layer protective shotcrete layer forming a waterproof layer protective shotcrete layer (140). 제 1 항에 있어서, 암반 터널(100)의 내부를 경계심도(C)에 따라 지표수 영향으로 누수되는 경계심도(C) 외부의 얕은 심도영역(101)과, 지하수 영향으로 누수되는 경계심도(C) 내부의 깊은 심도영역(102)으로 구분하고, 깊은 심도영역(102)을 지하수가 누수되는 누수영역(D1)과, 누수되지 않는 비누수영역(D2)으로 구분 설정하는 방수 시공영역 설정단계와, 상기 암반 터널(100)의 내주면에 보강 숏크리트층(110)을 형성하는 보강 숏크리트층 형성단계와, 시공 현장의 외부 공장에서 배수부재(120)에 도막 방수재를 도포하여 1차 도막 방수층(130a)이 일체로 형성된 배수부재 일체형 도막 배수부재(130')를 제조하는 도막 배수부재 제조단계와, 이 일체형 도막 배수부재(130')를 시공 현장에 반입하여 상기 얕은 심도영역(101)과, 깊은 심도영역(102)의 누수영역(D1)에 일체형 도막 배수부재(130')를 부착하는 도막 배수부재 부착단계와, 상기 일체형 도막 배수부재(130') 위에 도막 방수재를 도포하여 2차 도막 방수층(130b)을 형성함으로써 이중구조의 도막 방수층(130)을 형성하는 도막 방수층 형성단계와, 상기 도막 방수층(130) 위에 상기 도막 방수층(130) 보호를 위한 방수층 보호 숏크리트층(140)을 형성하는 방수층 보호 숏크리트층 형성단계를 포함하여 구성된 것을 특징으로 하는 부분 도막방수 터널의 시공방법.The shallow depth region 101 outside the boundary depth C that leaks inside the rock tunnel 100 due to the surface water effect according to the boundary depth C, and the boundary depth C that leaks due to the groundwater effect. And a waterproof construction area setting step of dividing the deep depth area 102 into an inside, and dividing the deep depth area 102 into a leakage area D1 where groundwater leaks and a non-leak water area D2. Reinforcing shotcrete layer forming step of forming a reinforcement shotcrete layer 110 on the inner circumferential surface of the rock tunnel 100 and the primary coating film waterproofing layer 130a by applying a coating film waterproofing material to the drain member 120 at an external factory at the construction site A coating film drainage member manufacturing step of manufacturing the integrally formed drainage member integral coating film drainage member 130 ', and bringing the integrated coating film drainage member 130' into the construction site to produce the shallow depth region 101 and a deep depth. Integral to the leak area D1 of the area 102 A coating film draining member attaching step for attaching the film draining member 130 'and a coating film waterproofing layer 130 having a dual structure by forming a secondary coating film waterproofing layer 130b by applying a coating film waterproofing material on the integrated coating film draining member 130'. And a waterproof layer protective shotcrete layer forming step of forming a waterproof layer protective shotcrete layer 140 for protecting the coating waterproofing layer 130 on the coating waterproofing layer 130. Construction method of coating waterproof tunnel.
KR1020050054683A 2005-06-23 2005-06-23 Partial coating waterproof tunnel and there of method KR20060134754A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050054683A KR20060134754A (en) 2005-06-23 2005-06-23 Partial coating waterproof tunnel and there of method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050054683A KR20060134754A (en) 2005-06-23 2005-06-23 Partial coating waterproof tunnel and there of method

Publications (1)

Publication Number Publication Date
KR20060134754A true KR20060134754A (en) 2006-12-28

Family

ID=37813084

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050054683A KR20060134754A (en) 2005-06-23 2005-06-23 Partial coating waterproof tunnel and there of method

Country Status (1)

Country Link
KR (1) KR20060134754A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100819822B1 (en) * 2006-10-18 2008-04-07 연일화섬공업(주) Water proof construction method for tunnel using union water proof sheet
KR100969513B1 (en) * 2009-12-30 2010-07-12 코오롱건설주식회사 A method for construting tunel using polyamide fiber having two layer for reinforcing
CN102434176A (en) * 2011-10-11 2012-05-02 宁波市瑞通新材料科技有限公司 Preparation method of waterproof fireproof insulation compound plate for tunnel
CN110410144A (en) * 2019-07-18 2019-11-05 中交第二公路勘察设计研究院有限公司 A kind of waterproof/drainage structure of shield tunnel
CN110700857A (en) * 2019-09-30 2020-01-17 交通运输部公路科学研究所 Composite tunnel supporting system and construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100819822B1 (en) * 2006-10-18 2008-04-07 연일화섬공업(주) Water proof construction method for tunnel using union water proof sheet
KR100969513B1 (en) * 2009-12-30 2010-07-12 코오롱건설주식회사 A method for construting tunel using polyamide fiber having two layer for reinforcing
CN102434176A (en) * 2011-10-11 2012-05-02 宁波市瑞通新材料科技有限公司 Preparation method of waterproof fireproof insulation compound plate for tunnel
CN110410144A (en) * 2019-07-18 2019-11-05 中交第二公路勘察设计研究院有限公司 A kind of waterproof/drainage structure of shield tunnel
CN110700857A (en) * 2019-09-30 2020-01-17 交通运输部公路科学研究所 Composite tunnel supporting system and construction method

Similar Documents

Publication Publication Date Title
CN110878700B (en) Tunnel waterproof structure and construction method thereof
CN105297743B (en) A kind of ground-connecting-wall defect seepage stops discharge structure and its construction method
CN106703084A (en) Waterproofing treatment method and system of construction joint structure of plane and elevation structure junction areas of basement
CN109488371B (en) Waterproof system of full-enclosed waterproof station and dynamic setting and quantity-limiting drainage method
EA035065B1 (en) Method for installation and laying of a waterproof liner on a bottom of a water basin or canal, waterproof liner and waterproof panel for installation on a bottom of a water basin or canal
KR101186104B1 (en) Method for repairing expansion joint part between concrete structures using inducing conduct pipe
CN107327308A (en) A kind of Railway Tunnel waterproof method
KR20060134754A (en) Partial coating waterproof tunnel and there of method
KR101017117B1 (en) Method and device for waterproofing steel pipe loop structure by a water drainage process for constructing underground structure by non-excavation
JP3753729B1 (en) Tunnel waterproof structure
CN107524174A (en) A kind of diaphragm wall I-shaped steel joint provided with water expandable waterstop
CN107345406B (en) waterproof sealing method for deformation joint of pipe gallery
KR101200016B1 (en) Method of constructing underground structure using steel pipe loop structure employing a water drainage process and water drainage type underground structure constructed using the same
KR101316718B1 (en) A tunnel waterproofing construction method
KR101005581B1 (en) Expansion joint structure for tunnel
KR100929362B1 (en) Water-proofing method for underground concrete structure
CN111119927A (en) Tunnel three-dimensional waterproof and drainage system and construction technology
KR20100042441A (en) Inducing waterproof structure of underground diaphragm wall
KR100866505B1 (en) Guide apparatus for water leakage of inner tunnel equipped with environmentally-friendly antibacterial guide panel for water leakage and its guide method thereof
CN210660137U (en) Shield constructs end ring beam and section of jurisdiction seam crossing seepage maintenance structure
CN211368801U (en) Tunnel engineering seam waterproof construction
KR100956144B1 (en) High elastic composite waterproof sheet
KR100454605B1 (en) High-density and pressurization repair method about new/old concrete joint part
JP7215251B2 (en) Synthetic segment
CN112459130A (en) Drainable externally-adhered water stop with adhesion timeliness and application

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application
J201 Request for trial against refusal decision
J501 Disposition of invalidation of trial
J501 Disposition of invalidation of trial