KR20060124101A - Precast slab track system and it's construction method - Google Patents

Precast slab track system and it's construction method Download PDF

Info

Publication number
KR20060124101A
KR20060124101A KR1020050045859A KR20050045859A KR20060124101A KR 20060124101 A KR20060124101 A KR 20060124101A KR 1020050045859 A KR1020050045859 A KR 1020050045859A KR 20050045859 A KR20050045859 A KR 20050045859A KR 20060124101 A KR20060124101 A KR 20060124101A
Authority
KR
South Korea
Prior art keywords
slab
slab frame
frame
precast
filler
Prior art date
Application number
KR1020050045859A
Other languages
Korean (ko)
Other versions
KR100706786B1 (en
Inventor
조봉종
이후삼
황보대성
Original Assignee
삼표이앤씨 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 삼표이앤씨 주식회사 filed Critical 삼표이앤씨 주식회사
Priority to KR1020050045859A priority Critical patent/KR100706786B1/en
Publication of KR20060124101A publication Critical patent/KR20060124101A/en
Application granted granted Critical
Publication of KR100706786B1 publication Critical patent/KR100706786B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/002Ballastless track, e.g. concrete slab trackway, or with asphalt layers
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B9/00Fastening rails on sleepers, or the like
    • E01B9/38Indirect fastening of rails by using tie-plates or chairs; Fastening of rails on the tie-plates or in the chairs
    • E01B9/44Fastening the rail on the tie-plate

Abstract

A precast slab track system and a construction method thereof are provided to secure the best quality through quality control for materials and manufacture in a factory, to minimize the crack width in a construction site and to reduce construction, maintenance and life cycle costs by reconstructing and repairing easily. A precast slab track system(PSTS) comprises: a foundation layer(100) for stabilization formed in the appointed thickness and width using concrete and provided with inclines; a slab frame(200) composed of an opening penetrated vertically, many fasteners projected to the right and left sides of the opening, a reinforcement unit of many vertical reinforcing bars and many horizontal reinforcing bars, and a drain groove retreated inward in the appointed size; filler(300) made of asphalt emulsion, cement, sand and additives and injected between the foundation layer and the slab frame through injection holes; a pair of long rails(400) installed on the fasteners of the slab frame at regular intervals; and a rail coupler(500) fixing the rails on the fasteners of the slab frame. A construction method for the precast slab track system comprises the steps of manufacturing a slab frame formed in the rectangular shape and provided with an opening and many fasteners, carrying the manufactured slab frame on a job site using a conveyor, forming a foundation layer for stabilization to have the appointed thickness and width by placing concrete, installing the slab frame on the foundation layer, placing filler between the foundation layer and the slab frame, installing rails on the slab frame at regular intervals and fixing the rails on fasteners of the slab frame using a rail fastener.

Description

프리케스트 슬래브 궤도 시스템 및 시공방법{Precast slab track system and it's construction method}Precast slab track system and it's construction method

도 1은 본 발명에 따른 프리케스트 슬래브 궤도 시스템을 도시한 사시도,1 is a perspective view of a precast slab track system in accordance with the present invention;

도 2는 본 발명에 따른 프리케스트 슬래브 궤도 시스템의 슬래브 프레임을 도시한 정면 사시도,2 is a front perspective view showing a slab frame of the precast slab track system according to the present invention;

도 3은 본 발명에 따른 프리케스트 슬래브 궤도 시스템의 슬래브 프레임을 도시한 저면 사시도,3 is a bottom perspective view illustrating a slab frame of the precast slab track system according to the present invention;

도 4는 본 발명에 따른 슬래브 프레임 내에 철근이 배근된 상태를 도시한 사시도,4 is a perspective view showing a state in which reinforcing bars in the slab frame according to the invention

도 5는 본 발명에 따른 프리케스트 슬래브 궤도 시스템에 충전재가 충전된 상태를 도시한 사시도,5 is a perspective view illustrating a state in which a filler is filled in a precast slab track system according to the present invention;

도 6은 본 발명에 따른 슬래브 프레임간의 연결시 제1연결방법에 의한 연결상태를 도시한 평면도,6 is a plan view showing a connection state by a first connection method when connecting between slab frames according to the present invention;

도 7은 본 발명에 따른 슬래브 프레임간의 제1연결방법에 의한 연결 1단계 상태를 도시한 평면도,7 is a plan view showing a connection step 1 state by a first connection method between the slab frame according to the present invention,

도 8은 본 발명에 따른 슬래브 프레임간의 제1연결방법에 의한 연결 2단계 상태를 도시한 평면도,8 is a plan view illustrating a two-stage connection state by a first connection method between slab frames according to the present invention;

도 9는 본 발명에 따른 슬래브 프레임간의 제1연결방법에 의한 연결 3단계 상태를 도시한 평면도,9 is a plan view showing a three-stage connection state by the first connection method between the slab frame according to the present invention,

도 10은 본 발명에 따른 슬래브 프레임간 제2연결방법에 의한 연결상태를 도시한 평면도,10 is a plan view illustrating a connection state by a second connection method between slab frames according to the present invention;

도 11은 본 발명에 따른 슬래브 프레임 내에 매입된 종방향, 횡방향 철근 간의 절연 상태를 도시한 평면도,11 is a plan view showing an insulating state between the longitudinal and transverse reinforcement embedded in the slab frame according to the present invention,

도 12는 본 발명에 따른 슬래브 프레임간의 제1, 제2연결방법의 시공절차를 도시한 평면도1.12 is a plan view illustrating a construction procedure of the first and second connection methods between the slab frame according to the present invention.

도 13은 본 발명에 따른 슬래브 프레임간의 제1, 제2연결방법의 시공절차를 도시한 측면도1,Figure 13 is a side view showing the construction procedure of the first, second connection method between the slab frame according to the present invention 1,

도 14는 본 발명에 따른 슬래브 프레임간의 제1, 제2연결방법의 시공절차를 도시한 평면도2,14 is a plan view illustrating a construction procedure of the first and second connection methods between the slab frames according to the present invention;

도 15는 본 발명에 따른 슬래브 프레임간의 제1, 제2연결방법의 시공절차를 도시한 측면도2.Figure 15 is a side view showing the construction procedure of the first, second connection method between the slab frame according to the present invention.

도 16은 본 발명에 따른 안정화 기초층과 슬래브 프레임간을 충전재로 주입하는 상태를 도시한 예시도.16 is an exemplary view showing a state of injecting between the stabilization base layer and the slab frame according to the present invention as a filler.

-도면의 주요부분에 대한 부호의 설명-Explanation of symbols on the main parts of the drawing

100: 안정화 기초층 200: 슬래브 프레임100: stabilization base layer 200: slab frame

210: 개구부 220: 체결구210: opening 220: fastener

230: 철근부 232: 종방향철근230: reinforcing bar 232: longitudinal rebar

234: 횡방향철근 240: 배수홈234: transverse rebar 240: drain groove

250: 이음부 252: 오목홈250: joint 252: concave groove

254: 돌출부 260: 균열유발줄눈254: protrusion 260: crack inducing joint

270: PVC관 280: 유공관270: PVC pipe 280: Perforated pipe

290: 강봉 300: 충전재290: steel bar 300: filling material

310: 주입구 400: 레일310: inlet 400: rail

500: 레일체결구 600: 스크류잭500: rail fastener 600: screw jack

PSTS: 프리케스트 슬래브 궤도 시스템PSTS: Precast Slab Track System

본 발명은 프리케스트 슬래브 궤도 시스템 및 시공방법에 관한 것으로, 특히 고속철도용 슬래브 궤도 구성품의 특성과 우리나라의 지반특성을 감안하여 현장조건에 적합한 프리케스트 슬래브 궤도 시스템 및 시공방법에 관한 것이다.The present invention relates to a precast slab track system and construction method, and in particular, to a precast slab track system and construction method suitable for field conditions in consideration of the characteristics of the slab track components for high-speed railway and the ground characteristics of Korea.

현재 선로의 대부분은 전통적인 도상궤도 형식임에도 불구하고, 최근 경향은 점차 슬래브 궤도의 부설이 늘어나는 실정이다.Although most of the current tracks are in the form of traditional trajectories, the recent trend is gradually increasing the laying of slab tracks.

슬래브 궤도의 장점은 궤도강도의 향상으로 레일 장대화 시 좌굴 저항력 증대로 인하여 내구성을 향상시키고, 축중에 의한 정위치 탈락을 최소화시키는 것이 다.The advantage of slab track is to improve the durability of track by increasing buckling resistance due to the increase of track strength and to minimize dropout due to load.

따라서 궤도의 선형유지 및 보수작업주기가 길어지며 궤도보수비 등의 감소로 유지 보수비용을 절약할 수 있다.Therefore, the linear maintenance and maintenance work cycle of the track is lengthened, and maintenance costs can be saved by reducing track maintenance costs.

또한, 궤도 구조특성상 낮은 시공기면과 저폭으로 인하여 좁은 곡률의 급곡선 만족과 최대한의 좁은 부지에 부설을 만족하면서도 선로구축물의 강성을 보완하므로 터널 단면과 교량 상판의 단면감소를 유도하여 건설비를 절감시킬 수 있다.In addition, due to the low construction surface and low width of the track structure, it satisfies the rapid curvature of the narrow curvature and the laying on the maximum narrow site, while compensating the rigidity of the track structure, thereby reducing the construction cost by inducing the reduction of the cross section of the tunnel and the bridge deck. Can be.

따라서, 열차운행 횟수 증가로 다량의 유지보수가 예상되는 구간, 터널 및 장대 교량구간 및 와전류 제동구간 등에서는 절대적인 강점을 가지는 궤도 구조이다.Therefore, it is an orbital structure having absolute strengths in sections in which a large amount of maintenance is expected due to an increase in the number of train operations, tunnels and long bridge sections, and eddy current braking sections.

이런 이류로 고속철도에서 운영경험이 많은 일본과 독일 및 이탈리아 등에서 지대한 관심을 보여 개발 실용화시켰으며 최근에는 콘크리트 시공기술 및 시공장비 발달로 소요 건설비가 하향화되어 경제성도 가지게 되었다.Due to these reasons, they showed great interest in Japan, Germany, Italy, etc., which have high operating experience in high-speed railway, and developed and put them into practical use. Recently, due to the development of concrete construction technology and construction equipment, the required construction cost has been lowered, resulting in economic efficiency.

지금까지 대부분의 슬래브 궤도는 지하철과 일부 시험궤도에만 한정되어 부설되어 왔지만 1960년대 이후 점차 고속 선에도 확대 적용되기 시작했다.Until now, most of the slab tracks have been laid on the subway and some test tracks, but since the 1960s, they have been gradually applied to high speed ships.

그 중에서도 시속 200km/h 이상의 고속 운행시 그 사용성이 검증된 시스템은 3-4개 시스템 정도이다.Among them, 3-4 systems have proven their usefulness at high speeds over 200km / h.

시속 300km/h의 영업 속도로 TGV가 운영하는 프랑스는 영업구간의 대부분이 자갈 도상궤도로 이루어져 있지만 산악지형이 많아 교량, 터널, 암거 등 토목구조물의 비율이 높은 독일, 일본, 이탈리아의 경우는 슬래브 궤도 부설에 매우 적극적이다.France, operated by TGV at an operating speed of 300 km / h, is mostly made of gravel orbits, but in Germany, Japan, and Italy, where the ratio of civil structures such as bridges, tunnels, and culverts is high because of the mountainous terrain, Very active in laying tracks.

현재 독일형 슬래브 궤도와 일본형 슬래브 궤도가 가장 부설실적이 많으며 고속에서의 내구성, 주행안정성 및 경제성이 검증되었다고 할 수 있다.At present, German slab tracks and Japanese slab tracks are the most laid, and the durability, driving stability and economic feasibility at high speed have been verified.

대표적인 고속철도용 슬래브 궤도로는 일본의 방진A형 슬래브 궤도와 독일식 레다형 궤도, 쥬블린 궤도가 있다.Typical high-speed rail slab tracks include Japan's anti-vibration A-type slab tracks, German redda tracks, and Jublin tracks.

일본의 슬래브궤도의 경우는 가장 많은 부설실적(2,700km)을 가지고 있다.In Japan, the slab track has the largest number of laid tracks (2,700km).

초기의 신간선인 山陽線(Sanyo)에서는 5%에만 불과하였던 슬래브궤도가 東北線(Tohoku)에서는 전 노선의 93%를 차지하고 있다.The slab orbit, which was only 5% on the first Shinkansen, Sanyo, accounts for 93% of the entire line on the Tohoku.

최근에 완공된 上越 신간선도 대부분(슬래브 궤도 255km, 자갈 도상궤도 15km로 89% 비율)이 콘크리트 슬래브 궤도로 시공된 바 있다.Most of the new Shinkansen completed recently (concrete slab track 255km, gravel trajectory 15km, 89% of the ratio) have been constructed as concrete slab tracks.

최근 영업속도는 275km/h, 궤도구조의 수정 없이도 300km/h의 속도로 운행할 수 있는 것으로 평가되고 있다.Recently, the operating speed is estimated at 275km / h and can operate at speeds of 300km / h without modification of the track structure.

독일의 경우는 1972년 독일의 레다(Rheda) 역에 첫 슬래브 궤도 부설 이후에는 후속적인 슬래브 궤도의 개발 및 적용이 저조한 실정이었다.In the case of Germany, the development and application of subsequent slab tracks was poor after the first slab track was laid at Rheda station in Germany in 1972.

그러나 1994년 1월 1일 독일의 DB-West와 DB-East가 합병하여 DB-AG로 변모한 이후, 철도의 경쟁력 향상을 위하여 사용에 거의 제한이 없고 저유지 슬래브 궤도를 모든 신설 고속선에 부설하는 것을 기본원칙으로 채택하였다.However, after the merger of DB-West and DB-East in Germany on January 1, 1994, it transformed into DB-AG, there are almost no restrictions on the use of railroads. As the basic principle.

이후 1997년에 하노버(Hanover)-베를린(Berlin) 고속철도선에서 대규모 생력화 궤도가 최초로 건설되었다.Later, in 1997, the first large-scale harnessing track was built on the Hanover-Berlin high-speed railway.

여기서는 콘크리트 생력화 궤도(연장거리 : 140km)와 아스팔트 생력화 궤도(연장거리 : 5km)가 모두 사용되었다.Here, concrete concrete tracks (extended distance: 140 km) and asphalt vitalized tracks (extended: 5 km) were used.

현재는 약 200km 연장의 고속 신선 쾰른선이 현재 건설중인데 거의 대부분이 연속적인 생력화 궤도로 구성된다.The high-speed new Cologne, which is about 200 km long, is currently under construction, almost all of which consist of continuous vitalized tracks.

이와 같은 많은 시험구간 건설을 통해 얻은 경험들을 토대로 기술적 발전을 이루어 왔다.Technological advances have been made based on the experience gained through the construction of many of these test intervals.

그동안 슬래브 궤도는 일반 토노반상, 터널, 교량, 역사 등에 다양한 구조물 상에 부설되었으며 부루즈부르그-하노버의 고속 신선에 뮐베르그(Muchlberg) 터널 외 3개소에서 300km/h 및 406km/h의 시험주행에 성공된 바 있다.In the meantime, the slab tracks were laid on various structures such as torn roads, tunnels, bridges, and history. It has been successful.

한편, 현장타설식 슬래브 궤도는 고비용의 공법으로부터 탈피하여 더욱 경제적인 궤도구조를 만들고자 하는 노력으로 3개 설계요소에서 1개 설계요소로 구조적인 단순화를 지향하고 있다.On the other hand, the cast-in-place slab track is aiming at structural simplification from three design elements to one design element in an effort to make a more economic track structure away from the expensive method.

즉, (a) 3개의 설계요소를 가진 (BTS층/ATS층, 침목, 충전 콘크리트나 매스틱 아스팔트와 같은 채움재) 매입식 공법에서 출발하여 (b) 2개의 설계요소를 가진 (BTS층/ATS층, 침목) 비매입식 공법(콘크리트 무타설 궤도)을 거쳐 (c) 단일체로 제조되는 하나의 설계요소를 가진(레일지점이 BTS층에 통합된 형태) 무침목 공법까지 시도되고 있는 상황이다.That is, (a) starting from a buried process with three design elements (BTS layer / ATS layer, sleeper, filling material such as filled concrete or mastic asphalt), and (b) two design elements (BTS layer / ATS). Layers, sleepers) A non-invasive process (concrete-free placing track) is being attempted to (c) a sleeper process with one design element made of a single piece (integrated rail points into the BTS layer).

이와 같은 설계요소의 단순성 지양 외에도 슬래브 궤도는 타 궤도에 비해 다른 기술특성을 필요로 하는데 이러한 시스템의 서로 다른 특성이 모여 하나의 조화된 시스템을 형성하는 것이 중요한 문제가 된다.In addition to avoiding the simplicity of such design elements, slab tracks require different technical characteristics than other tracks, and it is important to combine different characteristics of these systems to form a harmonized system.

즉, 레일패드, 체결구 등에는 일반 도상궤도와 다른 조건을 요구하고 있다. 3형식 궤도는 콘크리트 구체(트로프)를 가지고 있다.That is, rail pads, fasteners, and the like require different conditions from the general image orbit. Type 3 tracks have concrete spheres (troughs).

이러한 구체(trough)의 기능은 고속철도의 열차주행으로 인하여 증가된 동적 하중을 레일, 강봉(rod), 단침목으로 이루어진 격자(grid)형 구조를 통하여 불투수층, 또는 콘크리트 하부면에 하중분배를 시키게 된다.The function of the trough is to distribute the increased dynamic loads due to the high-speed railway trains to the impermeable layer or the concrete base through a grid structure consisting of rails, rods and single sleepers. .

또한, 시공시 장대레일을 결합하여 설치하는 특성으로 장대레일의 온도변화로부터 발생하는 수평력을 전달하기 위한 견고한 지지부를 제공한다.In addition, it provides a solid support for transmitting the horizontal force generated from the temperature change of the pole rail as a feature that is installed by combining the pole rail during construction.

구체가 있는 경우는 로드를 침목에 관통시켜 격자형 구조를 만들게 되며, 구체가 생략된 현장 타설 궤도는 침목 하부면에 철근을 배치시켜 축중에 의한 휨에 저항하게 된다.If there is a sphere, the rod penetrates the sleeper to create a lattice structure, and the in-field casting track, which omits the sphere, places rebar on the underside of the sleeper to resist bending by the shaft.

구체형 슬래브 궤도는 독일의 고속철도 노선에 가장 부설실적이 많으며 선형 유지 면에서도 좋은 평가를 받고 있다.Concrete slab tracks are the most established in the high-speed railway lines of Germany and are well received for their linear maintenance.

그러나 비구체형과 비교시 단면증가로 공사비의 상승요인이 발생하며 완벽한 시공이 안 되면 침목 하부의 불균질한 콘크리트 채움에 의한 균열발생의 가능성이 있으므로 최근에는 이를 생략한 단순체로의 시공도 이뤄지고 있다.However, in comparison with the non-spherical type, the increase of the cross section causes the cost of construction, and if it is not perfect, there is a possibility of cracking due to the inhomogeneous concrete filling of the lower part of the sleeper.

이 구체가 생략된다면 가장 구조적인 개선효과가 큰 것은 BTS(콘크리트지지)층내에 철근의 효율적인 배치이다.If this sphere is omitted, the most structural improvement is the efficient placement of rebar in the BTS (concrete support) layer.

콘크리트층 구조에서는 종방향 배근은 이음매가 없는 연속 콘크리트 층임을 감안하여 설계되어야 한다.In concrete struc- tures, longitudinal reinforcements are to be designed to allow seamless continuous concrete layers.

즉 콘크리트 경화와 온도하중에 대한 상부균열을 최소화시키기 위해서는 BTS층의 횡단면을 기준으로 0.8∼0.9%의 철근비를 만족해야 한다.In other words, in order to minimize the top crack for concrete hardening and temperature load, the rebar ratio of 0.8 ~ 0.9% should be satisfied based on the cross section of BTS layer.

이는 온도의 영향에 의한 균열을 억제하기 위한 것으로 ACI 318 규정에 근거 한 것이다.This is to prevent cracking under the influence of temperature and is based on ACI 318 regulations.

이로써 BTS층 상단면의 균열폭은 0.5mm 미만으로의 제한이 가능해진다.This makes it possible to limit the crack width of the top surface of the BTS layer to less than 0.5 mm.

일반적으로 독일 현장타설 슬래브의 경우 BTS층의 품질기준은 표면 프로파일 공차는 2mm에 콘크리트 품질등급 B35(콘크리트 28일 공칭강도가 40N/㎟이상)를 충족시켜야 하므로 차후 고강도 콘크리트를 이용한 시공이 요구된다.In general, in the case of the German cast-in-place slab, the quality standard of the BTS layer is that the surface profile tolerance must be 2mm and meet the concrete quality grade B35 (more than 40N / mm2 concrete 28 days nominal strength).

기술특성 중 고려해야 할 내용은 시공시 선형조정방식이다.One of the technical characteristics to consider is the linear adjustment method during construction.

이 방법에 의해 궤도의 수직궤도 틀림상태, 승차감상태, 부설비용이 결정되기 때문이다.This is because the vertical track trajectory, ride comfort, and auxiliary equipment are determined by this method.

슬래브궤도의 경우 일단 시공되면 궤도 두정면의 위치 상실은 없지만 잘못된 시공 오차는 그대로 유지되고 차후 수정이 거의 불가능하기 때문에 시공시 선형조정방법은 중요하게 된다.In the case of slab tracks, once the construction is done, there is no loss of the position of the orbital head surface, but the linear construction method becomes important in construction because wrong construction error is maintained and correction is almost impossible later.

국외 슬래브 궤도의 선형조정방법의 기술동향을 살펴보면 크게 다음과 같이 3가지 방법으로 분류될 수 있다.Looking at the technical trend of the linear adjustment method of the foreign slab track can be classified into three methods as follows.

(1) 침목에 스핀들(spindle) 내장한 형식(1) Spindle built into sleepers

이 방식은 침목 내에 수직, 수평조정 스핀들을 위치시키는 방법으로 트로프에 침목을 거치하고 광학 계측에 의해 5m당 2mm 오차 이내로 조정된 후 채움 콘크리트에 의해 충전된다.This method involves placing the sleeper on the trough by placing the spindle vertically and horizontally in the sleeper and adjusting it to within 2mm per 5m by optical measurement and then filling it with filled concrete.

스핀들의 설치는 침목 2개당 1조의 수직 스핀들을 설치해야 하므로 비용이 증대되지만 독일의 승차감 지수(Q-number) 평가결과 10-15 정도로 우수한 성능을 보였다.Spindle installation costs increased because one set of vertical spindles was installed per two sleepers, but the German Q-number evaluation showed a good performance of 10-15.

(2) 광학장비에 이한 자동화 침목 거치(2) Automated sleeper mounting with optical equipment

이 방법은 침목 거치용 빔 측면에 측점기준기를 좌우에 부착시켜 침목거치틀을 정밀한 조정에 의해 BTS층의 프레쉬 콘크리트 안으로 자동으로 유도하는 방식이다.This method is a method of attaching the stationary reference to the left and right sides of the sleeper mounting beam to guide the sleeper frame into the fresh concrete of the BTS layer by precise adjustment.

침목에 진동을 가해준 콘크리트 액상화층에 측점기준기를 이용해 침목을 정확한 곳에 거치하게 된다. A stationary reference is placed on the concrete liquefaction layer that caused the sleepers to vibrate to place the sleepers in the correct place.

이때 각각의 침목 설치주기에 필요한 카메라와 레이저 측정기가 있으며 기계 본체에는 사진작업계산기와 제어모니터가 설치되어 있다.At this time, a camera and a laser measuring device are required for each sleeper installation cycle, and a photo task calculator and a control monitor are installed in the main body of the machine.

침목 위치를 선정하기 위한 자동화 및 특수 진동기, 침목 유도프로그램이 개발돼야 하는 형식이다.An automated, special vibrator and sleeper guidance program should be developed to select sleeper locations.

(3) 조정틀에 의한 방법(3) Method by adjusting frame

조정틀에 의한 방법은 이전의 레다궤도의 수정형인 베를린 궤도에서 처음 사용되었다.The control method was first used in the Berlin orbit, a modified version of the previous LEDA orbit.

레일 하면을 기준점으로 하여 조정틀을 트로프에 좌우 3개씩의 스핀들 나사로 지지하여 선형을 조정하는 방식이다.It is a method of adjusting the linearity by supporting the adjusting frame with three left and right spindle screws on the trough with the rail as the reference point.

이와 같은 방식은 장대레일이 체결된 상태에서 부설된다.Such a method is laid while the pole rail is fastened.

레일 두부가 아닌 저면에 맞추는 준 탑-다운 방식이나 사용이 비교적 간편한 장점이 있다.It has a quasi top-down method that fits on the bottom of the rail rather than the head, but it is relatively easy to use.

이러한 방식은 HGT층(불투수층) 또는 터널 내부의 콘크리트층에 조정틀을 지지시키는데 조정틀 내부에 수직, 수평 조정나사를 위치시켜 궤도상면을 기준으로 선형을 조정한다.This method supports the adjusting frame on the HGT layer (impermeable layer) or the concrete layer inside the tunnel, and adjusts linearity based on the track surface by placing vertical and horizontal adjusting screws inside the adjusting frame.

이 방법은 침목에 스핀들을 생략시키고 조정틀에 의해서만 조정하게 되며, 슬래브 궤도를 단순화시킬 수 있는 장점이 있다.This method eliminates the spindle on the sleepers and adjusts only by the adjustment frame, which has the advantage of simplifying the slab trajectory.

완전한 탑-다운(Top-Down) 형식으로 조정틀이 수정되면 시공 오차 발생부는 감소하게 된다.If the adjustment frame is modified to a full top-down form, the construction error generating part is reduced.

결정된 궤도선형에 대하여 정량적으로 평가할 수 있는 방법 중에 하나가 궤도검측차량을 이용, 순서에 따른 궤도의 위치를 기록하는 승차감지수(Q-number)이다.One of the methods for quantitatively evaluating the determined track linearity is a ride-sensing index (Q-number) that records the position of tracks in order using track detection vehicles.

선로구조물의 운영시 안정적인 상태를 알기 위해 궤도틀림, 궤간 차이, 방향(곡률)을 고려, 일년에 최대 6회까지 측정된다.In order to know the stable condition of the track structure, it is measured up to 6 times a year considering the track distortion, gap difference and direction (curvature).

승차감 지수가 적을수록 보수가 필요 없다는 것을 뜻하며 승차감 지수가 커질수록 승차감 및 궤도상태가 나빠진다는 것을 의미하므로, 열차하중재하에 따른 궤도위치의 변화를 반영하는 지수라 할 수 있다.A smaller ride comfort index means no maintenance is required, and a larger ride comfort index means that the ride comfort and track condition worsens, and thus the index reflects a change in track position due to train loading.

고속철도 구간에서의 자갈도상 구조는 궤도위치의 상태가 별로 좋지 않은 경우, 마모현상을 뚜렷이 나타내고 있다.The gravel-shaped structure in the high-speed railway section shows the wear phenomenon when the track position is not very good.

독일의 승차감 분석자료에 의하면 일반적으로 자갈도상이 80∼100 정도를 나타낸다면 슬래브 궤도의 지수는 5-35 이내로 매우 적다.According to the German comfort analysis data, when the gravel road shows 80-100, the index of slab track is very small, within 5-35.

궤도 두정면으로부터 선형을 맞춰나가는 구체형 궤도인 경우, 구간의 승차감 지수는 10∼15를 나타낸다. 비매입식 공법도 20∼25로 우수하였다.In the case of a spherical track that fits linearly from the head of the track, the ride comfort index of the section is 10 to 15. The non-buried method was also excellent in 20-25.

이상에서는 고속철도 슬래브 궤도의 개발동향과 주요 기술요건을 설명하였다.In the above, the development trend of the high-speed railway slab track and the main technical requirements were explained.

일본에서는 계속적인 신간선에 슬래브 부설을 고려하고 있다.In Japan, slabs are being considered for continued Shinkansen.

유럽에서는 최근 독일이 고속화에 따라서 보수량의 증대에 대비책으로서 슬래브 궤도의 개발에 힘을 쏟고 있다.In Europe, Germany has recently focused on the development of slab tracks as a countermeasure against the increase in repairs due to high speeds.

특히 구 동서독 간의 교통망 정비를 위해 장래의 고속화를 염두에 두어 슬래브 궤도의 개발이 전개되고 있다.In particular, the development of slab tracks is being developed with the intention of speeding up the future to improve the transportation network between the East and West Germany.

현재 슬래브 궤도를 포함한 생력화 궤도를 위해 약 20사의 기업군이 특허화된 정도로서 약 30개의 궤도를 제안하고 있으며, 본격적인 채용을 위해 치열한 개발 경쟁이 실시되고 있는 상황이다.Currently, about 20 companies have been patented for the vitalization track including slab tracks, and about 30 tracks are being proposed, and fierce competition for development is in progress.

여기서, 우리나라는 경부고속철도(서울∼대구간) 일부 장대터널 구간에서 슬래브 궤도를 적용하였으며, 현재 건설중인 경부고속철도 2단계(대구∼부산 간) 구간은 전 구간을 슬래브 궤도로 설계 중에 있다.Here, Korea applied slab tracks in some long tunnel sections of the Gyeongbu high speed railroad (Seoul to Daegu), and the second phase of the Gyeongbu high speed railroad (between Daegu and Busan) is currently designing all sections as slab tracks.

그러나 현재 우리나라의 고속철도 차량과 시스템은 프랑스의 TGV 시스템을 도입, 운영하고 있으며, 프랑스는 고속철도 전 구간이 자갈도상으로 이루어져 있다.However, Korea's high-speed railway vehicles and systems are currently introducing and operating the French TGV system. In France, all sections of the high-speed railway consist of gravel roads.

그러나 상기한 프랑스 시스템에 슬래브 궤도를 도입할 경우에는 슬래브 궤도에 필수요소인 철근과 신호 시스템간의 저촉문제가 발생한다.However, when the slab track is introduced into the French system, a problem arises between the reinforcing bar and the signal system, which are essential elements of the slab track.

우리나라에서 도입한 프랑스 신호시스템인 UM71은 궤도회로 구간에 열차가 있는지를 자동으로 검지하기 위한 전기회로로 자동열차제어의 기본적인 필수 안전요소이며, 레일을 정보전송매체로 활용하여 열차검지, 지상설비의 신호정보를 운행 중인 열차에 전송, 레일절손 검지, 전차선 전류를 변전소로 귀선 등의 기능을 수행하고 있다.The UM71, a French signaling system introduced in Korea, is an electrical circuit that automatically detects the presence of trains in track circuit sections.It is a fundamental safety component of automatic train control.It uses rails as information transmission media for train detection and ground equipment. It transmits signal information to trains in operation, detects rail breakage, and returns the tramline currents to substations.

그러나 레일 상부에서 690㎜ 이내에 설치된 철근은 궤도회로 송신전압에 의해 간섭을 일으켜 신호시스템의 성능저하를 초래하는 문제가 있다.However, the reinforcing bar installed within 690 mm from the rail top has a problem of causing interference by the track circuit transmission voltage and causing performance degradation of the signal system.

이에, 본 발명은 상기한 바와 같은 제문제점을 해결하기 위해 안출된 것으로서, 국내 실정에 적합한 독자적인 슬래브 궤도를 개발하는 것을 주목적으로 하여, 고속철도와 일반철도에 두루 적용이 가능하며, 현장여건을 고려한 시공성이 향상되며, 생애비용(Life cycle cost) 측면에서의 경제성이 확보되며, 시스템의 고품질 확보뿐만 아니라 유지보수가 용이한 프리케스트 슬래브 궤도 시스템 및 시공방법을 제공하는데 그 목적이 있다.Accordingly, the present invention has been made to solve the problems described above, the main purpose is to develop a unique slab track suitable for the domestic situation, can be applied to high-speed railway and general railway, construction properties in consideration of site conditions The purpose is to provide improved and economical in terms of life cycle cost, to provide a high quality of the system as well as easy to maintain precast slab track system and construction method.

상기한 목적을 달성하기 위한 본 발명에 따른 프리케스트 슬래브 궤도 시스템은 콘크리트로 일정한 두께 및 폭을 가지며, 좌우측면에 일정한 경사면을 갖는 안정화 기초층과; 상기 안정화 기초층의 상면에 설치됨과 동시에 전체적으로 사각형 판상체로 이루어지되, 그 가운데에 사각형상의 개구부가 형성되며, 상기 개구부의 좌우 측으로 다수개의 체결구가 일체로 돌출 형성된 슬래브 프레임과; 상기 안정화 기초층과 슬래브 프레임간에 충전되며, 이들을 일체로 연결하는 충전재와; 상기 슬래브 프레임의 체결구상에 일정한 간격을 두고 한 쌍이 나란하게 일정한 길이를 갖고 고정 설치되는 레일과; 상기 레일을 슬래브 프레임의 체결구상에 고정하는 레일체결구로 구성됨을 특징으로 한다.Precast slab track system according to the present invention for achieving the above object is a stabilizing base layer having a predetermined thickness and width of the concrete, a constant slope on the left and right sides; A slab frame installed on an upper surface of the stabilization base layer and formed of a rectangular plate body as a whole, wherein a rectangular opening is formed in the center thereof, and a plurality of fasteners protrude integrally to the left and right sides of the opening; A filler which is filled between the stabilization base layer and the slab frame and connects them integrally; A rail fixedly installed on the fastener of the slab frame and having a predetermined length in parallel with a pair; Characterized in that the rail is configured to fasten the rail on the fastener of the slab frame.

또한, 상기한 목적을 달성하기 위한 본 발명에 따른 프리케스트 슬래브 궤도 시공방법은 공장에서 전체적으로 사각형 판상체로 이루어지되, 그 가운데에 사각형상의 개구부가 형성되며, 상기 개구부의 좌우측으로 다수개의 체결구가 일체로 돌출 형성된 슬래브 프레임을 제조하는 단계(Ⅰ); 상기 제조된 슬래브 프레임을 별도의 운반장치를 이용하여 설치할 위치로 슬래브 프레임을 이송하는 단계(Ⅱ); 지면으로부터 일정한 두께 및 폭을 가지며, 좌우측면에 일정한 경사면을 갖도록 콘크리트를 타설하여 안정화 기초층을 형성하는 단계(Ⅲ); 상기 안정화 기초층상에 슬래브 프레임을 설치하는 단계(Ⅳ); 상기 안정화 기초층과 슬래브 프레임간에 충전재를 충전하는 단계(Ⅴ); 상기 슬래브 프레임상에 일정한 간격을 두고 한 쌍이 나란하게 일정한 길이를 갖는 레일을 설치하는 단계(Ⅵ); 상기 레일을 슬래브 프레임의 체결구상에 레일체결구로 고정하는 단계(Ⅶ)로 이루어짐을 특징으로 한다.In addition, the precast slab track construction method according to the present invention for achieving the above object is made of a rectangular plate-like body as a whole in the factory, a rectangular opening is formed therein, a plurality of fasteners to the left and right sides of the opening Manufacturing an integrally formed slab frame (I); Transferring the slab frame to a position where the manufactured slab frame is to be installed using a separate conveying device (II); Forming a stabilization base layer by placing concrete to have a constant thickness and width from the ground and having a constant inclined surface on left and right sides (III); Installing a slab frame on the stabilization base layer (IV); (V) filling a filler between the stabilization base layer and the slab frame; (VI) installing rails having a predetermined length in parallel with each other at a predetermined interval on the slab frame; The rail is fastened to the fasteners of the slab frame characterized in that it consists of a step (Ⅶ).

이하, 본 발명을 첨부한 예시도면을 참조하여 상세히 설명한다.Hereinafter, with reference to the accompanying drawings, the present invention will be described in detail.

도 1은 본 발명에 따른 프리케스트 슬래브 궤도 시스템을 도시한 사시도이며, 도 2와 도 3 은 본 발명에 따른 프리케스트 슬래브 궤도 시스템의 슬래브 프레임을 도시한 정, 저면 사시도이며, 도 4는 본 발명에 따른 슬래브 프레임 내에 철근이 배근된 상태를 도시한 사시도이며, 도 5는 본 발명에 따른 프리케스트 슬래브 궤도 시스템에 충전재가 충전된 상태를 도시한 사시도이며, 도 6은 본 발명에 따른 슬래브 프레임간의 연결상태를 도시한 평면도이며, 도 7 내지 도 9는 본 발명에 따른 슬래브 프레임간의 연결 1단계 상태를 도시한 평면도이며, 도 10 과 도 11은 본 발명에 따른 슬래브 프레임 내에 매입된 종, 횡방향 연결철근의 절연 상태를 도시한 평면도이며, 도 12와 도 13은 본 발명에 따른 슬래브 프레임간의 제1, 제2연결방법의 시공절차를 도시한 평면도1 및 측면도1, 도 14와 도 15는 본 발명에 따른 슬래브 프레임간의 제1, 제2연결방법의 시공절차를 도시한 평면도2 및 측면도2이며, 도 16은 본 발명에 따른 안정화 기초층과 슬래브 프레임간을 충전재로 주입하는 상태를 도시한 예시도이다.1 is a perspective view showing a precast slab track system according to the present invention, Figures 2 and 3 are a front, bottom perspective view showing a slab frame of the precast slab track system according to the present invention, Figure 4 is a present invention 5 is a perspective view illustrating a state in which reinforcing bars are reinforced in a slab frame according to the present invention, and FIG. 5 is a perspective view illustrating a state in which a filler is filled in a precast slab track system according to the present invention, and FIG. 6 is between slab frames according to the present invention. 7 and 9 are plan views illustrating a connection stage 1 state between the slab frames according to the present invention, and FIGS. 10 and 11 are longitudinal and transverse directions embedded in the slab frame according to the present invention. 12 and 13 are plan views showing the construction procedure of the first and second connection methods between the slab frames according to the present invention. 1 and side views 1, 14 and 15 are a plan view 2 and a side view 2 showing the construction procedure of the first and second connection method between the slab frame according to the present invention, Figure 16 is a stabilization base layer according to the present invention and It is an exemplary figure which shows the state which injects between slab frames with a filler.

이들 도면에 도시된 바와 같이, 본 발명에 따른 프리케스트 슬래브 궤도 시스템(PSTS)은 콘크리트로 일정한 두께 및 폭을 가지며, 좌우측면에 일정한 경사면을 갖는 안정화 기초층(100)과; 상기 안정화 기초층(100)의 상면에 설치됨과 동시에 전체적으로 사각형 판상체로 이루어지되, 그 가운데에 사각형상의 개구부(210)가 형성되며, 상기 개구부(210)의 좌우 측으로 다수개의 체결구(220)이 일체로 돌출 형성된 슬래브 프레임(200)과; 상기 안정화 기초층(100)과 슬래브 프레임(200)간에 충전되며, 이들을 일체로 연결하는 충전재(300)와; 상기 슬래브 프레임(200)의 체결구(220)상에 일정한 간격을 두고 한 쌍이 나란하게 일정한 길이를 갖고 고정 설치되는 레일(400)과; 상기 레일(400)을 슬래브 프레임(200)의 체결구(220)상에 고정하는 레일체결구(500)로 구성된다. As shown in these figures, the precast slab track system (PSTS) according to the present invention comprises a stabilization base layer 100 having a constant thickness and width of concrete and a constant inclined surface on the left and right sides; It is installed on the upper surface of the stabilization base layer 100 at the same time made of a generally rectangular plate body, a rectangular opening 210 is formed in the middle, a plurality of fasteners 220 to the left and right sides of the opening 210 A slab frame 200 which protrudes integrally; A filler 300 which is filled between the stabilization base layer 100 and the slab frame 200 and connects them integrally; A rail 400 fixedly installed on the fastener 220 of the slab frame 200 at a predetermined interval and having a predetermined length in parallel with each other; It consists of a rail fastener 500 for fixing the rail 400 on the fastener 220 of the slab frame 200.

즉, 본 발명에 따른 프리케스트 슬래브 궤도 시스템(PSTS)은 안정화 기초층(100), 슬래브 프레임(200), 충전재(300), 레일(400) 및 레일체결구(500)가 유기적으로 결합되어 이루어진 구조이다.That is, in the precast slab track system (PSTS) according to the present invention, the stabilization base layer 100, the slab frame 200, the filler 300, the rail 400 and the rail fastener 500 is organically coupled Structure.

여기서, 상기 안정화 기초층(100)은 콘크리트로 일정한 두께 및 폭을 가지며, 좌우측면에 일정한 경사면을 갖는 구조부이다.Here, the stabilization base layer 100 is a structural part having a predetermined thickness and width of the concrete, a constant inclined surface on the left and right sides.

또한, 상기 슬래브 프레임(200)은 전체적으로 사각형 프리케스트 콘크리트 판상체로 이루어지되, 상기 사각형 판상체의 가운데에 사각형상으로 상면과 하면이 관통되게 트이는 개구부(210)와; 상기 개구부(210)의 좌우 측으로 다수 개가 일체로 돌출 형성되는 체결구(220)와; 상기 사각형 판상체의 내면에 다수개의 종방향철근(232)과 다수개의 횡방향철근(234)이 상호 교차되어 이루어지는 철근부(230)와; 상기 사각형 판상체의 바닥면에 일정한 크기로 내측으로 오목하게 형성된 배수홈(240)으로 구성된다.In addition, the slab frame 200 is made of a rectangular pre-cast concrete plate as a whole, the opening 210 through which the upper and lower surfaces penetrate the rectangular in the center of the rectangular plate; Fasteners 220 formed to integrally protrude from the left and right sides of the opening 210; A rebar portion 230 formed by crossing a plurality of longitudinal rebars 232 and a plurality of transverse rebars 234 on an inner surface of the rectangular plate-shaped body; It is composed of a drain groove 240 formed concave inward in a predetermined size on the bottom surface of the rectangular plate-like body.

여기서, 상기 슬래브 프레임(200)에 개구부(210)를 형성한 이유는 구조적인 강도를 가지면서도 경제적인 시공을 하기 위함이다.The reason why the opening 210 is formed in the slab frame 200 is to provide economical construction while having structural strength.

또한, 상기 슬래브 프레임(200)에는 그 측면에 슬래브 프레임(200)과 슬래브 프레임(200)간을 원활하게 연결하기 위해 일정한 길이의 종방향철근(232)이 다수 개 노출됨과 동시에 일정한 깊이로 내측으로 오목홈(252)이 형성된 이음부(250)로 구성된다. In addition, the slab frame 200 is exposed to a plurality of longitudinal reinforcing bars 232 of a predetermined length to smoothly connect between the slab frame 200 and the slab frame 200 on the side and at the same time inward to a certain depth Concave groove 252 is formed with a joint 250 is formed.

한편, 상기 슬래브 프레임(200) 내에는 부설되는 철근부(230)는 종방향철근(232)과 횡방향철근(234)이 교차되어 이루어지되, 각 교차부위의 종, 횡방향철근(232, 234)의 외주면에 PVC관(270)가 끼워진 구조로서, 이와 같은 PVC관(270)에 의해서 종방향, 횡방향철근(232, 234) 간 절연처리를 한다.On the other hand, the reinforcing bar 230 is placed in the slab frame 200 is made of the longitudinal reinforcing bars 232 and the transverse reinforcing bars 234 are crossed, the longitudinal, transverse reinforcing bars 232, 234 of each intersection PVC pipe 270 is fitted to the outer peripheral surface of the), by the PVC pipe 270 is insulated between the longitudinal, transverse reinforcing bars (232, 234).

즉, 상기 종방향철근(232)과 횡방향철근(234)의 접촉부는 전기 절연을 위하여 절연재인 PVC관(270)을 이용하여 절연시키며, 재료절감 및 전기절연에 영향을 주는 횡방향철근(234)을 최소한으로 설치한 구조이다.That is, the contact portion of the longitudinal reinforcing bars 232 and the transverse reinforcing bars 234 is insulated using the PVC pipe 270, which is an insulating material, for electrical insulation, and the transverse reinforcing bars 234 affecting material reduction and electrical insulation. It is the structure that installed minimum.

그리고 상기 체결구(220)간에는 슬래브 프레임(200)의 표면으로부터 교축방향으로 슬래브 프레임(200)의 균열발생이 최적의 판상구조를 이루도록 일정한 깊이 및 폭을 갖는 균열유발줄눈(260)이 다수 개 형성된 구조이다. In addition, a plurality of crack inducing joints 260 having a constant depth and width are formed between the fasteners 220 so that crack generation of the slab frame 200 is optimally formed in the axial direction from the surface of the slab frame 200. Structure.

또한, 상기 강봉(290)은 슬래브 프레임(200)마다 전기 절연을 하기 위하여 슬래브 프레임(200)에 영향을 미치지 않도록 슬래브 프레임(200)의 중앙부에서 절단한 구조이다.In addition, the steel bar 290 is a structure cut from the center portion of the slab frame 200 so as not to affect the slab frame 200 in order to electrically insulate each slab frame (200).

그리고 상기 슬래브 프레임(200)의 개구부(210)에 위치한 강봉(290)을 슬래브 프레임(200)의 단부내에 위치하도록 길이 조정을 하는 것이 바람직하다.And it is preferable to adjust the length so that the steel bar 290 located in the opening 210 of the slab frame 200 is located in the end of the slab frame 200.

상기한 바와 같은 슬래브 프레임(200)은 강화 콘크리트로 구성된 사각형 판상체의 종방향으로 연장되며, 전방 측면의 사각형 판상체 표면 위로 돌출하는 적어도 2개 이상의 강봉(290)을 구비하고, 상기 강봉(290)에 대해서 횡방향으로 연장되는 이론적 파괴점을 적어도 하나 이상을 형성하며, 판상체 내부 종ㆍ횡방향철근(232, 234)의 절연을 위하여 강봉(290)을 판상체 중앙부에서 절연시키고, 종방향철근(232)과 횡방향철근(234)의 접촉부를 절연시키며, 횡방향철근(234)을 최소화하기 위하여 판상체의 중앙부에 개구부(210)가 형성된 구조이다.The slab frame 200 as described above extends in the longitudinal direction of the rectangular plate body made of reinforced concrete, and has at least two steel bars 290 protruding above the rectangular plate body surface on the front side, and the steel bar 290 At least one theoretical break point extending laterally with respect to the cross-section), and the steel bar 290 is insulated from the center of the plate body to insulate the plate longitudinal and transverse reinforcing bars 232 and 234. Insulating the contact portion of the reinforcing bar 232 and the transverse rebar 234, the opening 210 is formed in the central portion of the plate to minimize the transverse rebar (234).

또한, 상기 충전재(300)는 안정화 기초층(100)과 슬래브 프레임(200)간에 주입하되, 아스팔트 유제, 시멘트, 모래, 첨가제를 주성분으로 하여 제조되며, 넓은 공극을 메워야 하므로 유동성이 좋아야 하며, 압축강도는 7∼15MPa, 건조수축되지 않아야 하며, 동결융해에 대한 저항성이 커야 한다.In addition, the filler 300 is injected between the stabilization base layer 100 and the slab frame 200, but is made of asphalt emulsion, cement, sand, additives as a main component, because it must fill a wide void, fluidity should be good, compression The strength should be 7 ~ 15MPa, not dry shrinkage, and high resistance to freeze-thawing.

또한, 충전재 주입시 충전재(300)의 흘러내림을 방지하기 위하여 별도의 특수한 거푸집을 슬래브 프레임(200)에 설치하고, 상기 거푸집에 충전재를 주입할 수 있도록 별도의 주입구(310)를 다수 개 설치한다.In addition, in order to prevent the filler 300 from flowing down when the filler is injected, a separate special formwork is installed in the slab frame 200, and a plurality of additional injection holes 310 are installed to inject the filler into the formwork. .

그리고 상기 레일(400)은 슬래브 프레임(200)의 체결구(220)상에 일정한 간격을 두고 한 쌍이 나란하게 일정한 길이를 갖고 고정 설치되는 고속철도용 장대레일(400)이다.And the rail 400 is a high-speed railway pole rail 400 is fixedly installed with a certain length side by side at a predetermined interval on the fastener 220 of the slab frame 200.

또한, 상기 레일체결구(500)는 슬래브 프레임(200)의 체결구(220)상에 레일(400)을 고정하는 장치이다. In addition, the rail fastener 500 is a device for fixing the rail 400 on the fastener 220 of the slab frame 200.

상기한 바와 같은 구성으로 이루어진 본 발명에 따른 프리케스트 슬래브 궤도의 시공에 대해 설명한다.The construction of the precast slab track according to the present invention having the configuration as described above will be described.

본 발명에 따른 프리케스트 슬래브 궤도 시공방법은 공장에서 전체적으로 사각형 판상체로 이루어지되, 그 가운데에 사각형상의 개구부(210)가 형성되며, 상기 개구부(210)의 좌우 측으로 다수개의 체결구(220)이 일체로 돌출 형성된 슬래브 프레임(200)을 제조하는 단계(Ⅰ); Precast slab track construction method according to the invention is made of a rectangular plate body as a whole in the factory, a rectangular opening 210 is formed in the middle, a plurality of fasteners 220 to the left and right sides of the opening 210 Manufacturing an integrally formed slab frame 200 (I);

상기 제조된 슬래브 프레임(200)을 별도의 운반장치를 이용하여 설치할 위치로 슬래브 프레임(200)을 이송하는 단계(Ⅱ);Transferring the slab frame 200 to a position where the manufactured slab frame 200 is to be installed by using a separate conveying device (II);

지면으로부터 일정한 두께 및 폭을 가지며, 좌우측면에 일정한 경사면을 갖도록 콘크리트를 타설하여 안정화 기초층(100)을 형성하는 단계(Ⅲ);(III) forming a stabilization base layer 100 by pouring concrete to have a constant thickness and width from the ground and to have a constant inclined surface on the left and right sides;

상기 안정화 기초층(100)상에 슬래브 프레임(200)을 설치하는 단계(Ⅳ);Installing a slab frame (200) on the stabilization base layer (100);

상기 안정화 기초층(100)과 슬래브 프레임(200)간에 충전재(300)를 충전하는 단계(Ⅴ);Filling (V) the filler 300 between the stabilization base layer 100 and the slab frame 200;

상기 슬래브 프레임(200) 상에 일정한 간격을 두고 한 쌍이 나란하게 일정한 길이를 갖는 레일(400)을 설치하는 단계(Ⅵ); 상기 레일(400)을 슬래브 프레임(200)의 체결구(220)상에 레일체결구(500)로 고정하는 단계(Ⅶ)를 순차적으로 시행하여 프리케스트 슬래브 궤도(PSTS)를 시공한다.Installing (VI) a rail having a predetermined length in parallel with each other at a predetermined interval on the slab frame (200); The rail 400 is fastened to the fasteners 220 of the slab frame 200 by the rail fasteners 500 to sequentially perform a precast slab track (PSTS).

여기서, 상기 슬래브 프레임(200)은 전체적으로 사각형 프리케스트 콘크리트 판상체로 제조하되, 상기 사각형 판상체의 가운데에 사각형상으로 상면과 하면이 관통되게 트이는 개구부(210)와; 상기 개구부(210)의 좌우 측으로 다수 개가 일체로 돌출 형성되는 체결구(220)와; 상기 사각형 판상체의 내면에 다수개의 종방향철근(232)과 다수개의 횡방향철근(234)이 상호 교차되어 이루어지는 철근부(230)와; 상기 사각형 판상체의 바닥면에 일정한 크기로 내측으로 오목하게 형성된 배수홈(240)과; 그 측면에 슬래브 프레임(200)과 슬래브 프레임(200)간을 연결하기 위해 일정한 길이의 종방향철근(232)이 다수 개 노출됨과 동시에 일정한 깊이로 내측으로 오목홈(252)이 형성된 이음부(250)와; 상기 사각형 판상체의 표면으로부터 교축방향으로 일정한 깊이 및 폭을 갖도록 다수 개가 형성된 균열유발줄눈(260)으로 이루어진다. Here, the slab frame 200 is made of a rectangular precast concrete plate as a whole, the opening 210 through which the top and bottom through the rectangular shape in the center of the rectangular plate body; Fasteners 220 formed to integrally protrude from the left and right sides of the opening 210; A rebar portion 230 formed by crossing a plurality of longitudinal rebars 232 and a plurality of transverse rebars 234 on an inner surface of the rectangular plate-shaped body; A drain groove 240 formed concave inwardly with a predetermined size on the bottom surface of the rectangular plate-shaped body; In order to connect the slab frame 200 and the slab frame 200 on the side thereof, a plurality of longitudinal reinforcing bars 232 of constant length are exposed and a concave groove 252 formed with a concave groove 252 inward at a constant depth. )Wow; It consists of a crack-induced joint 260 is formed a plurality of so as to have a constant depth and width from the surface of the rectangular plate-like body.

즉, 상기한 바와 같은 슬래브 프레임(200) 제조는 먼저 슬래브 프레임(200)에 해당하는 거푸집을 설치하고, 상기 거푸집 내에 철근을 보강하며, 프리스트레스를 주입하며, 콘크리트를 타설한 후, 진동다짐을 하는 한편, 양생시킨 후 거푸집을 탈형시켜 제조한다.That is, in the manufacture of the slab frame 200 as described above, first install the formwork corresponding to the slab frame 200, reinforcing the reinforcing steel in the formwork, injecting the prestress, and after pouring concrete, the vibration compacting On the other hand, it is prepared by demolding the formwork after curing.

여기서, 상기 철근부(230)에는 종횡으로 철근(232, 234)을 설치하되, 그 교차부위에 해당하는 종방향철근(232)과 횡방향철근(234)의 외주면에 PVC관(270)를 끼워서 절연처리한다.Here, the reinforcing bar 230 is provided with rebars 232 and 234 vertically and horizontally, by inserting the PVC pipe 270 on the outer circumferential surface of the longitudinal reinforcing bars 232 and the transverse reinforcing bars 234 corresponding to the intersections thereof. Insulate.

또한, 상기 슬래브 프레임(200)은 프리스트레스트 된 제품으로 제품의 품질확보 및 변형을 방지하기 위하여 양생 기간 동안 슬래브 프레임(200) 적치시 별도의 특수설비를 이용하여 적치한다.In addition, the slab frame 200 is a prestressed product is stacked using a separate special equipment when the slab frame 200 is placed during the curing period in order to prevent product quality and deformation.

그리고 공장에서 제조된 슬래브 프레임(200)은 현장으로 운송시 슬래브 프레임(200)이 운송중의 충격에 의하여 변형되지 않도록 별도의 특수설비가 구비된 운반차량을 이용하여 운송한다.In addition, the slab frame 200 manufactured in the factory is transported using a transport vehicle equipped with a separate special equipment so that the slab frame 200 is not deformed by the impact during transportation.

또한, 상기 슬래브 프레임(200)을 설치할 지면으로부터 일정한 두께 및 폭을 가지며, 좌우측면에 일정한 경사면을 갖도록 콘크리트를 타설하여 안정화 기초층(100)을 형성한 후 상기 안정화 기초층(100)상에 슬래브 프레임(200)을 설치한다.In addition, after the slab frame 200 has a predetermined thickness and width from the ground on which the slab frame 200 is to be installed, and the concrete is placed on the left and right sides to form a stabilization base layer 100, the slab on the stabilization base layer 100 is formed. The frame 200 is installed.

이때, 상기 슬래브 프레임(200)은 일정한 길이와 폭으로 이루어진 단위체들로서 이들을 연결하여 설치한다.At this time, the slab frame 200 is installed by connecting them as units consisting of a predetermined length and width.

여기서, 상기 슬래브 프레임(200)간의 연결은 크게 연결방법에 따라 두 가지로 대별된다.Here, the connection between the slab frame 200 is roughly divided into two types depending on the connection method.

슬래브 프레임(200)의 제1연결방법은 일정한 길이의 유공관(280)을 적어도 한 개 이상 슬래브 프레임(200)의 단부를 관통시켜 매입하여, 슬래브 프레임(200) 을 제조하고, 이를 현장에서 유공관(280)에 강봉(290)을 고정시켜 인접한 슬래브 프레임(200)간을 연결한다.The first connection method of the slab frame 200 is to embed the at least one hole tube 280 of a predetermined length through the end of the slab frame 200, to manufacture the slab frame 200, and the hole pipe ( 280 is fixed to the steel bar 290 to connect between the adjacent slab frame 200.

또한, 상기 슬래브 프레임(200) 내부에 적어도 한 개 이상의 유공관(280)을 삽입하여 슬래브 프레임(200)을 제조하고, 상기 유공관(280)에 강봉(290) 또는 강연선을 삽입하고, 슬래브 프레임(200)의 하부에 일정한 높이로 충전재(300)를 주입하고, 경화시킨 후 상기 강봉(290) 또는 강연선에 프리스트레스를 주입하며, 상기 유공관(280)내에 충전재(300)를 충전함과 동시에 이음부(250)에 무수축 그라우팅을 타설하여 상호 연결한다.In addition, the slab frame 200 by inserting at least one or more perforated pipe 280 inside the slab frame 200, and inserts a steel bar 290 or a stranded wire into the perforated pipe 280, the slab frame 200 Inject the filler 300 to a certain height in the lower portion, and after curing, the pre-stress is injected into the steel rod 290 or the stranded wire, while filling the filler 300 in the perforated pipe 280 and the joint portion 250 ), And connect to each other by pouring non-shrink grouting.

또한, 슬래브 프레임(200) 제2연결방법은 슬래브 프레임(200)과 슬래브 프레임(200)간을 연결하기 위해 각각의 슬래브 프레임(200)을 관통하는 4개의 종방향철근(232)끼리 연결하고, 개구부(210)에 위치된 짧은 2개의 종방향철근(232)끼리 연결한다.In addition, the second connecting method of the slab frame 200 is connected to the four longitudinal reinforcing bars 232 through each of the slab frame 200 to connect between the slab frame 200 and the slab frame 200, The two short longitudinal bars 232 positioned in the opening 210 connect to each other.

여기서, 상기 슬래브 프레임(200)간 전기절연은 슬래브 프레임(200)을 관통하는 종방향철근(232) 4개를 슬래브 프레임(200)마다 끊어주기 위하여 슬래브 프레임(200)의 중앙부에서 절연처리하며, 개구부(210)에 위치된 종방향철근(232) 2개를 짧게 설치한다.Here, the electrical insulation between the slab frame 200 is insulated at the center of the slab frame 200 to break the four longitudinal reinforcing bars 232 through the slab frame 200 for each slab frame 200, Two longitudinal reinforcing bars 232 located in the opening 210 are shortly installed.

즉, 슬래브 프레임(200)간 연결은 슬래브 프레임(200)을 관통하는 종방향철근(232)4개와 개구부(210)에 위치한 짧은 종방향철근(232) 2개 총 6개를 서로 연결하는 방식인 바,That is, the connection between the slab frame 200 is a method of connecting a total of six longitudinal reinforcing bars (232) through the slab frame 200 and a total of two short longitudinal reinforcing bars (232) located in the opening 210 to each other bar,

이때 전기절연을 위하여 슬래브 프레임(200)을 관통하는 종방향철근(232) 4 개를 슬래브 프레임(200)마다 끊어주기 위하여 슬래브 프레임(200) 중앙부에서 절연처리를 하는 것과 개구부(210)에 위치한 종방향철근(232) 2개를 짧게 설치하는 것이다.At this time, in order to break the four longitudinal reinforcing bars 232 through the slab frame 200 for each slab frame 200 for electrical insulation, the insulating treatment at the center of the slab frame 200 and the longitudinal position located in the opening 210 Short installation of two direction reinforcing bars (232).

한편, 상기한 바와 같은 제1, 2 연결방법으로 연결하는 슬래브 프레임(200)간을 연결에는 모두 아래와 같은 과정을 통해 시공한다.On the other hand, the slab frame 200 to be connected by the first and second connection methods as described above are all installed through the following process.

즉, 슬래브 프레임(200)간 연결시 각각의 슬래브 프레임(200) 아래에 충전재(300)를 부어 넣고, 상기 충전재(300)가 경화된 후에 슬래브 프레임(200)의 연결부분 양측단에 스크류잭(600)을 설치하고, 각각의 슬래브 프레임(200)의 종방향철근(232)끼리 연결하여, 일측의 슬래브 프레임(200)과 타측의 슬래브 프레임(200)을 연결한다.That is, when the slab frame 200 is connected between the pour the filler 300 under each slab frame 200, and after the filler 300 is cured, the screw jack (2) at both ends of the connecting portion of the slab frame 200 ( 600 is installed, and longitudinal reinforcing bars 232 of each slab frame 200 are connected to each other, thereby connecting the slab frame 200 on one side and the slab frame 200 on the other side.

또한, 슬래브 프레임(200)간 연결시 각각의 슬래브 프레임(200) 제조시 외부로 돌출부(254)가 형성된 슬래브 프레임(200)을 다수 개 제조하고, 상기 제조된 슬래브 프레임(200)들을 소정의 위치에 적당한 간격을 두고 배치하고, 상기 슬래브 프레임(200)의 아래에 충전재(300)를 타설하고, 타설된 충전재(300)가 경화된 후, 상기 슬래브 프레임(200)간의 종방향철근(232)을 상호 연결한다.In addition, when the slab frame 200 is connected between the slab frame 200 to manufacture a plurality of slab frame 200 with a protrusion 254 is formed outside when manufacturing each slab frame 200, the manufactured slab frame 200 to a predetermined position After placing at appropriate intervals, the filler 300 is poured under the slab frame 200, and after the poured filler 300 is cured, the longitudinal reinforcing bars 232 between the slab frames 200 are placed. Interconnect.

따라서, 상기한 바와 같은 방법으로 슬래브 프레임(200)을 연결함으로써 종래의 연결부분 안쪽으로 충전재(300)를 충전하고, 이 충전재(300)가 경화되는 과정을 생략할 수 있어서 시공속도를 향상시키는 장점이 있다.Therefore, by connecting the slab frame 200 in the same manner as described above to fill the filler 300 into the inside of the conventional connecting portion, the process of hardening the filler 300 can be omitted, thereby improving the construction speed There is this.

상기한 바와 같은 방법을 이용하여 슬래브 프레임(200)간을 연결한 후, 상기 슬래브 프레임(200)과 안정화 기초층(100) 사이에는 충전재(300)를 주입하되, 상기 슬래브 프레임(200)과 안정화 기초층(100) 사이의 측면을 일정한 재료로 밀봉하고, 상기 슬래브 프레임(200)에 충전재 주입구(310)와 공기구멍을 형성한 후, 충전재(300)를 주입한다.After connecting between the slab frame 200 by using the method as described above, while filling the filler 300 between the slab frame 200 and the stabilization base layer 100, and stabilized with the slab frame 200 Side surfaces between the base layers 100 are sealed with a constant material, and a filler injection hole 310 and an air hole are formed in the slab frame 200, and then the filler 300 is injected.

여기서, 상기한 충전재(300)는 각 재료를 현장에서 직접 배합하여 일정한 압력으로 안정화 기초층(100)과 슬래브 프레임(200) 사이에 주입하여 사용하는데 이때 각각의 재료를 계량하여 배합하며, 일정한 압력으로 충전재를 주입구(310)를 통하여 주입할 수 있는 특수장비를 사용하여 시공한다.Here, the filler 300 is used to directly mix each material in the field and inject between the stabilization base layer 100 and the slab frame 200 at a constant pressure, in which case each material is weighed and blended, and a constant pressure is used. It is constructed using a special equipment that can be injected through the injection hole 310 to the.

또한, 상기 슬래브 프레임(200)의 하부에 일정한 높이의 충전재(300)를 주입하되, 슬래브 프레임(200)에 전체적으로 주입하여, 강봉(290) 또는 강연선에 프리스트레스 주입시 슬래브 프레임(200) 전체에 걸쳐 균등하게 응력이 분포되도록 시공한다.In addition, while injecting the filler 300 of a certain height in the lower portion of the slab frame 200, the overall injection into the slab frame 200, when prestress injection into the steel bar 290 or the stranded wire throughout the slab frame 200 Construct so that the stress is distributed evenly.

한편, 슬래브 프레임(200)이 노후되거나 절단되었을 경우에는 슬래브 프레임(200)의 하면의 충전재(300)를 절단하고, 슬래브 프레임(200)의 이음부(250)를 절단하며, 유공관(280) 내부의 강봉(290) 또는 강연선을 제거한 후, 새로운 슬래브 프레임(200)과 강봉(290)을 설치하여 슬래브 프레임(200)을 교체 연결한다.On the other hand, when the slab frame 200 is aged or cut, the filler 300 of the lower surface of the slab frame 200 is cut, the joint portion 250 of the slab frame 200 is cut, and the hollow pipe 280 inside After removing the steel bar 290 or the stranded wire, install a new slab frame 200 and the steel bar 290 to connect the slab frame 200 replacement.

이상에서 설명한 바와 같이, 본 발명에 따른 프리케스트 슬래브 궤도 시스템 및 시공방법은 다음과 같은 효과가 있다.As described above, the precast slab track system and construction method according to the present invention has the following effects.

첫째, 본 발명은 품질면에서 공장에서 재료 및 제조에 대한 품질관리로 최상 의 품질을 확보할 수 있는 장점이 있다.First, the present invention has the advantage of ensuring the best quality by quality control for materials and manufacturing in the factory in terms of quality.

둘째, 본 발명은 현장타설에서 발생되는 균열폭0.5mm에 비하여 균열폭을 0.2mm로 최소화시킬 수 있는 장점이 있다.Secondly, the present invention has an advantage of minimizing the crack width to 0.2mm compared to the crack width of 0.5mm generated in the field casting.

셋째, 본 발명은 방향 및 레벨 등 시공 오차 발생시 재시공 및 보수가 용이한 장점이 있다.Third, the present invention has the advantage of easy reconstruction and repair when construction errors, such as direction and level.

넷째, 본 발명은 슬래브 궤도 시스템의 공사비 및 유지보수비를 절감할 수 있는 장점이 있다.Fourth, the present invention has the advantage of reducing the construction cost and maintenance cost of the slab track system.

다섯째, 본 발명은 타 궤도에 비하여 유지보수가 적어 생애비용(Life cycle cost) 면에서 유리한 이점이 있다. Fifth, the present invention has an advantage in terms of life cycle cost (life cycle cost) is less maintenance than other tracks.

여섯째, 본 발명은 시공 면에서 사전 제조으로 현장 작업량을 대폭 줄였으며, 충전재를 제외하고 일기(온도, 호우 등)의 영향을 받지 않아 공기단축이 가능하며, 일 작업량은 최대 700m/일, 평균 400m/일이 가능하며, 현장 공정이 감소하며, 시공장비도 감소하여, 대기오염 감소로 인한 보다 쾌적한 작업환경 제공하는 장점이 있다.Sixth, the present invention significantly reduced on-site work by pre-manufacturing in terms of construction, it is possible to shorten the air without being affected by weather (temperature, heavy rain, etc.) except for the filling material, the work amount is up to 700m / day, average 400m / Work is possible, field processes are reduced, construction equipment is also reduced, there is an advantage to provide a more comfortable working environment due to reduced air pollution.

일곱째, 본 발명은 지반 침하시 체결구로 정정이 불가능할 경우에도 레벨 조정이 가능한 장점이 있다. Seventh, the present invention has the advantage that the level can be adjusted even when correction is impossible with the ground fastener.

여덟째, 본 발명은 심각한 사고 발생으로 인한 슬래브 궤도 시스템 파손시 교체가 용이한 이점이 있다. Eighth, the present invention has the advantage of easy replacement when the slab track system breakage due to serious accidents.

아홉째, 본 발명은 슬래브 프레임 교체 후 충전재의 빠른 경화로 인하여 약 5시간 후 열차운행이 가능한 장점이 있다.Ninth, the present invention has the advantage that the train operation after about 5 hours due to the rapid curing of the filler after slab frame replacement.

Claims (15)

콘크리트로 일정한 두께 및 폭을 가지며, 좌우측면에 일정한 경사면을 갖는 안정화 기초층(100)과; Stabilization base layer 100 having a constant thickness and width of concrete, and having a constant inclined surface on the left and right sides; 상기 안정화 기초층(100)의 상면에 설치됨과 동시에 전체적으로 사각형 판상체로 이루어지되, 그 가운데에 사각형상의 개구부(210)가 형성되며, 상기 개구부(210)의 좌우 측으로 다수개의 체결구(220)이 일체로 돌출 형성된 슬래브 프레임(200)과; It is installed on the upper surface of the stabilization base layer 100 at the same time made of a generally rectangular plate body, a rectangular opening 210 is formed in the middle, a plurality of fasteners 220 to the left and right sides of the opening 210 A slab frame 200 which protrudes integrally; 상기 안정화 기초층(100)과 슬래브 프레임(200)간에 충전되며, 이들을 일체로 연결하는 충전재(300)와; A filler 300 which is filled between the stabilization base layer 100 and the slab frame 200 and connects them integrally; 상기 슬래브 프레임(200)의 체결구(220)상에 일정한 간격을 두고 한 쌍이 나란하게 일정한 길이를 갖고 고정 설치되는 레일(400)과; A rail 400 fixedly installed on the fastener 220 of the slab frame 200 at a predetermined interval and having a predetermined length in parallel with each other; 상기 레일(400)을 슬래브 프레임(200)의 체결구(220)상에 고정하는 레일체결구(500)로 구성됨을 특징으로 하는 프리케스트 슬래브 궤도 시스템.Precast slab track system, characterized in that consisting of a rail fastener 500 for fixing the rail 400 on the fastener 220 of the slab frame 200. 제 1항에 있어서, The method of claim 1, 상기 슬래브 프레임(200)은 전체적으로 사각형 프리케스트 콘크리트 판상체로 이루어지되, 상기 사각형 판상체의 가운데에 사각형상으로 상면과 하면이 관통되게 트이는 개구부(210)와;The slab frame 200 is generally made of a rectangular precast concrete plate body, the opening 210 through which the upper and lower surfaces penetrate in the center of the rectangular plate body; 상기 개구부(210)의 좌우 측으로 다수 개가 일체로 돌출 형성되는 체결구(220)과; Fasteners 220 formed to integrally protrude from the left and right sides of the opening 210; 상기 사각형 판상체의 내면에 다수개의 종방향철근(232)과 다수개의 횡방향철근(234)이 상호 교차되어 이루어지는 철근부(230)와;A rebar portion 230 formed by crossing a plurality of longitudinal rebars 232 and a plurality of transverse rebars 234 on an inner surface of the rectangular plate-shaped body; 상기 사각형 판상체의 바닥면에 일정한 크기로 내측으로 오목하게 형성된 배수홈(240)으로 구성됨을 특징으로 하는 프리케스트 슬래브 궤도 시스템.Precast slab track system, characterized in that consisting of drainage grooves 240 formed concave inwardly in a predetermined size on the bottom surface of the rectangular plate-shaped body. 제 1항 또는 제 2항에 있어서,The method according to claim 1 or 2, 상기 슬래브 프레임(200)에는 그 측면에 슬래브 프레임(200)과 슬래브 프레임(200)간을 연결하기 위해 일정한 길이의 유공관(280)이 다수 개 노출됨과 동시에 일정한 깊이로 내측으로 오목홈(252)이 형성된 이음부(250)로 구성됨을 특징으로 하는 프리케스트 슬래브 궤도 시스템.The slab frame 200 has a plurality of perforated pipes 280 of a predetermined length to expose between the slab frame 200 and the slab frame 200 on the side and at the same time the concave groove 252 inward to a certain depth Precast slab track system, characterized in that consisting of the formed joint (250). 제 1항 또는 제 2항에 있어서,The method according to claim 1 or 2, 상기 체결구(220)간에는 슬래브 프레임(200)의 표면으로부터 교축방향으로 일정한 깊이 및 폭을 갖는 균열유발줄눈(260)이 다수 개 형성됨을 특징으로 하는 프리케스트 슬래브 궤도 시스템.Precast slab track system between the fastener 220 is formed with a plurality of crack-induced joint 260 having a predetermined depth and width in the axial direction from the surface of the slab frame 200. 제 2항에 있어서, The method of claim 2, 상기 철근부(230)는 종방향철근(232)과 횡방향철근(234)이 교차되어 이루어지되, 각 교차부위의 종, 횡방향철근(232, 234)의 외주면에 PVC관(270)가 끼워진 것을 특징으로 하는 프리케스트 슬래브 궤도 시스템.The reinforcing portion 230 is made of the longitudinal reinforcing bars 232 and the transverse reinforcing bars 234, but the PVC pipe 270 is fitted to the outer peripheral surface of the longitudinal, transverse reinforcing bars (232, 234) of each intersection Precast slab track system, characterized in that. 공장에서 전체적으로 사각형 판상체로 이루어지되, 그 가운데에 사각형상의 개구부(210)가 형성되며, 상기 개구부(210)의 좌우 측으로 다수개의 체결구(220)이 일체로 돌출 형성된 슬래브 프레임(200)을 제조하는 단계(Ⅰ);The factory is made of a generally rectangular plate body, a rectangular opening 210 is formed in the center, and a plurality of fasteners 220 to the left and right sides of the opening 210 formed integrally protruded slab frame 200 is manufactured Step (I); 상기 제조된 슬래브 프레임(200)을 별도의 운반장치를 이용하여 설치할 위치로 슬래브 프레임(200)을 이송하는 단계(Ⅱ);Transferring the slab frame 200 to a position where the manufactured slab frame 200 is to be installed by using a separate conveying device (II); 지면으로부터 일정한 두께 및 폭을 가지며, 좌우측면에 일정한 경사면을 갖도록 콘크리트를 타설하여 안정화 기초층(100)을 형성하는 단계(Ⅲ);(III) forming a stabilization base layer 100 by pouring concrete to have a constant thickness and width from the ground and to have a constant inclined surface on the left and right sides; 상기 안정화 기초층(100)상에 슬래브 프레임(200)을 설치하는 단계(Ⅳ);Installing a slab frame (200) on the stabilization base layer (100); 상기 안정화 기초층(100)과 슬래브 프레임(200)간에 충전재(300)를 충전하는 단계(Ⅴ);Filling (V) the filler 300 between the stabilization base layer 100 and the slab frame 200; 상기 슬래브 프레임(200) 상에 일정한 간격을 두고 한 쌍이 나란하게 일정한 길이를 갖는 레일(400)을 설치하는 단계(Ⅵ); Installing (VI) a rail having a predetermined length in parallel with each other at a predetermined interval on the slab frame (200); 상기 레일(400)을 슬래브 프레임(200)의 체결구(220)상에 레일체결구(500)로 고정하는 단계(Ⅶ)로 이루어짐을 특징으로 하는 프리케스트 슬래브 궤도 시공방법.Precast slab track construction method comprising the step of fixing the rail 400 to the fastener 220 on the fastener 220 of the slab frame 200. 제 6항에 있어서,The method of claim 6, 상기 슬래브 프레임(200)과 슬래브 프레임(200) 간을 연결하기 위해 일정한 길이의 유공관(280)을 적어도 한 개 이상 슬래브 프레임(200)의 단부를 관통시켜 매입하여, 슬래브 프레임(200)을 제조하고, 이를 현장에서 유공관(280)에 강봉(290)을 고정시켜 인접한 슬래브 프레임(200)간을 연결함을 특징으로 하는 프리케스트 슬래브 궤도 시공방법.In order to connect the slab frame 200 and the slab frame 200 through the end of the at least one slab frame 200 by embedding at least one perforated pipe 280 of a constant length, to manufacture a slab frame 200 Precast slab track construction method characterized in that connecting the adjacent slab frame 200 by fixing the steel bar 290 to the perforated pipe 280 in the field. 제 6항 또는 제 7항에 있어서,The method according to claim 6 or 7, 상기 슬래브 프레임(200)과 슬래브 프레임(200) 간을 연결하기 위해 슬래브 프레임(200) 내부에 적어도 한 개 이상의 유공관(280)을 삽입하여 슬래브 프레임(200)을 제조하고, 상기 유공관(280)에 강봉(290) 또는 강연선을 삽입하고, 슬래브 프레임(200)의 하부에 일정한 높이로 충전재(300)를 주입하고, 경화시킨 후 상기 강봉(290) 또는 강연선에 프리스트레스를 주입하며, 상기 유공관(280)내에 충전재(300)를 충전함과 동시에 이음부(250)에 무수축 그라우팅을 타설하여 상호 연결함을 특징으로 하는 프리케스트 슬래브 궤도 시공방법.In order to connect the slab frame 200 and the slab frame 200, at least one hole tube 280 is inserted into the slab frame 200 to manufacture the slab frame 200, the hole tube 280 Insert the steel rod 290 or the stranded wire, injecting the filling material 300 to a predetermined height in the lower portion of the slab frame 200, and after curing, the prestress is injected into the steel rod 290 or the stranded wire, the hole pipe 280 Prefilled slab track construction method characterized in that the filling the filling material 300 and at the same time by connecting the non-shrink grouting to the joint portion (250). 제 6항 내지 제 8항 중 어느 한 항에 있어서, The method according to any one of claims 6 to 8, 상기 슬래브 프레임(200)을 교체시 슬래브 프레임(200)의 하면의 충전재(300)를 절단하고, 슬래브 프레임(200)의 이음부(250)를 절단하며, 유공관(280) 내부의 강봉(290) 또는 강연선을 제거한 후, 새로운 슬래브 프레임(200)과 강봉(290)을 설치하여 슬래브 프레임(200)을 교체 연결함을 특징으로 하는 프리케스트 슬래브 궤도 시공방법.When the slab frame 200 is replaced, the filler 300 of the lower surface of the slab frame 200 is cut, the joint 250 of the slab frame 200 is cut, and the steel bar 290 inside the perforated pipe 280. Or after removing the strand, the new slab frame 200 and steel bar 290 by installing a precast slab track construction method characterized in that the replacement of the slab frame 200 by connecting. 제 6항에 있어서,The method of claim 6, 상기 슬래브 프레임(200)과 안정화 기초층(100) 사이에 충전재(300)를 주입하되, 상기 슬래브 프레임(200)과 안정화 기초층(100) 사이의 측면을 일정한 재료로 밀봉하고, 상기 슬래브 프레임(200)에 주입구(310)를 통해 충전재(300)를 주입함을 특징으로 하는 프리케스트 슬래브 궤도 시공방법.Filling filler 300 is injected between the slab frame 200 and the stabilization base layer 100, the side surface between the slab frame 200 and the stabilization base layer 100 is sealed with a constant material, the slab frame ( Precast slab track construction method characterized by injecting the filling material 300 through the injection hole (310). 제 6항에 있어서,The method of claim 6, 상기 슬래브 프레임(200)과 슬래브 프레임(200)간을 연결하기 위해 각각의 슬래브 프레임(200)을 관통하는 4개의 종방향철근(232)끼리 연결하고, 개구부(210)에 위치된 짧은 2개의 종방향철근(232)끼리 연결함을 특징으로 하는 프리케스트 슬래브 궤도 시공방법.In order to connect the slab frame 200 and the slab frame 200, the four longitudinal reinforcing bars 232 passing through each slab frame 200 are connected to each other, and two short bells positioned in the opening 210 are connected. Precast slab track construction method characterized in that the direction reinforcing bars (232) are connected to each other. 제 11항에 있어서,The method of claim 11, 상기 슬래브 프레임(200)간 전기절연은 슬래브 프레임(200)을 관통하는 종방향철근(232) 4개를 슬래브 프레임(200)마다 끊어주기 위하여 슬래브 프레임(200)의 중앙부에서 절연처리하며, 개구부(210)에 위치된 종방향철근(232) 2개를 짧게 설치함을 특징으로 하는 프리케스트 슬래브 궤도 시공방법.Electrical insulation between the slab frame 200 is insulated from the center portion of the slab frame 200 to break the four longitudinal reinforcing bars 232 through the slab frame 200 for each slab frame 200, the opening ( Precast slab track construction method characterized in that two longitudinal reinforcing bars (232) located in the 210 is installed short. 제 6항 내지 제 12항 중 어느 한 항에 있어서,The method according to any one of claims 6 to 12, 상기 슬래브 프레임(200)과 슬래브 프레임(200)간을 연결하기 위해 각각의 슬래브 프레임(200) 아래에 충전재(300)를 부어 넣고, 상기 충전재(300)가 경화된 후에 슬래브 프레임(200)의 연결부분 양측 단에 스크류잭(600)을 설치하고, 각각의 슬래브 프레임(200)의 종방향철근(232)끼리 연결함을 특징으로 하는 프리케스트 슬래브 궤도 시공방법.In order to connect the slab frame 200 and the slab frame 200, the filler 300 is poured under each slab frame 200, and after the filler 300 is cured, the slab frame 200 is connected. Precast slab track construction method characterized in that the screw jack (600) is installed at both ends of the part, and the longitudinal reinforcing bars (232) of each slab frame (200) are connected to each other. 제 6항 내지 제 12항 중 어느 한 항에 있어서,The method according to any one of claims 6 to 12, 상기 슬래브 프레임(200)과 슬래브 프레임(200)간을 연결하기 위해 각각의 슬래브 프레임(200) 제조시 외부로 돌출부(254)가 형성된 슬래브 프레임(200)을 다수 개 제조하고, 상기 제조된 슬래브 프레임(200)들을 소정의 위치에 적당한 간격을 두고 배치하고, 상기 슬래브 프레임(200)의 아래에 충전재(300)를 타설하고, 타설된 충전재(300)가 경화된 후, 상기 슬래브 프레임(200)간의 종방향철근(232)을 상호 연결함을 특징으로 하는 프리케스트 슬래브 궤도. In order to connect the slab frame 200 and the slab frame 200 to manufacture a plurality of slab frame 200 is formed with a protrusion 254 to the outside at the time of manufacturing each slab frame 200, the manufactured slab frame After arranging (200) at a predetermined interval at a suitable position, and pouring the filler 300 under the slab frame 200, after the poured filler 300 is cured, between the slab frame 200 Precast slab trajectory characterized by interconnecting longitudinal reinforcing bars (232). 제 6항 또는 제 10항에 있어서,The method of claim 6 or 10, 상기 충전재(300)는 아스팔트유제, 시멘트, 모래, 첨가제를 주성분으로 하며, 압축강도는 7∼15MPa로 이루어짐을 특징으로 하는 프리케스트 슬래브 궤도.The filler 300 is composed of asphalt emulsion, cement, sand, additives as a main component, the precast slab track characterized in that the compressive strength is made of 7 ~ 15MPa.
KR1020050045859A 2005-05-31 2005-05-31 Precast slab track system and it's construction method KR100706786B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050045859A KR100706786B1 (en) 2005-05-31 2005-05-31 Precast slab track system and it's construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050045859A KR100706786B1 (en) 2005-05-31 2005-05-31 Precast slab track system and it's construction method

Publications (2)

Publication Number Publication Date
KR20060124101A true KR20060124101A (en) 2006-12-05
KR100706786B1 KR100706786B1 (en) 2007-04-11

Family

ID=37728889

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050045859A KR100706786B1 (en) 2005-05-31 2005-05-31 Precast slab track system and it's construction method

Country Status (1)

Country Link
KR (1) KR100706786B1 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100814959B1 (en) * 2007-05-08 2008-03-19 주성렬 Support for supporting rail joint for uniting
KR101114442B1 (en) * 2011-06-16 2012-02-24 강남훈 Method for manufacturing concrete block having three dimensions solid shape and method for laying concrete track using concrete block manufactured by the same method
KR20160014411A (en) 2014-07-29 2016-02-11 한국철도기술연구원 Rail bridge with slab track reducing rail-structure interaction
CN105984020A (en) * 2015-02-02 2016-10-05 任丘市永基建筑安装工程有限公司 Concrete box-type combined die rail mounting technology
CN106032029A (en) * 2015-03-09 2016-10-19 任丘市永基建筑安装工程有限公司 A combination die steel rail arrangement technology
CN106283960A (en) * 2016-10-17 2017-01-04 兰州理工大学 Sleeper and construction method thereof for non-fragment orbit Concrete Crack Control
KR20180086961A (en) 2017-01-24 2018-08-01 한국철도기술연구원 Rail bridge with slab track reducing rail-structure interaction
CN111877054A (en) * 2020-08-11 2020-11-03 北京城建设计发展集团股份有限公司 Prefabricated plate type track structure convenient for rapid construction and construction method thereof
KR102487875B1 (en) * 2021-10-01 2023-01-11 정명수 Sky bike

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101114444B1 (en) * 2011-03-23 2012-02-24 강남훈 Method for manufacturing prefabricated solid bed track having three dimensions solid shape and laying method of concrete solid bed track using prefabricated solid bed track manufactured by the same method
KR101114445B1 (en) * 2011-03-25 2012-02-24 강남훈 Method for manufacturing concrete block having three dimensions solid shape and method for laying track of automated guideway type light rail transit using concrete block manufactured by the same method
KR101405468B1 (en) * 2011-07-15 2014-06-11 강남훈 Method for manufacturing concrete block for railway track and method for laying railway track using concrete block manufactured by the same method
KR101132952B1 (en) * 2011-08-09 2012-04-09 주식회사 이알에스 Composite rail for tramcar and rail track using the rail
KR101625829B1 (en) 2015-08-13 2016-06-02 한국철도기술연구원 Direct fastened asphalt track using each wide sleeper and concrete slab panel having geotextile and horizontal-vertical movement restraining apparatus, and construction method for the same
KR101634127B1 (en) 2015-08-13 2016-06-29 한국철도기술연구원 Apparatus for restraining horizontal-vertical movement of wide sleeper and slab panel, and construction method for the same
KR20190078830A (en) 2017-12-27 2019-07-05 한국철도기술연구원 Derailment containment provision (dcp) for railway, and construction method for the same
KR102616318B1 (en) 2022-12-28 2023-12-22 삼표레일웨이 주식회사 Deep underground tunnel PST construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS51105704U (en) 1975-02-21 1976-08-24
JP2604476B2 (en) * 1989-10-24 1997-04-30 日本鉄道建設公団 How to build a slab track
DE19733909B4 (en) * 1997-08-05 2006-07-06 Max Bögl Bauunternehmung GmbH & Co. KG Prefabricated reinforced concrete precast slab and process for its production
KR20020069799A (en) * 2001-02-28 2002-09-05 주식회사 태명실업 RC-tie of a concrete-ballast track
DE10310754B4 (en) * 2003-01-28 2006-01-26 Naumburger Bauunion Gmbh & Co. Bauunternehmung Kg Method for producing a solid rail track; Fixed railroad track

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100814959B1 (en) * 2007-05-08 2008-03-19 주성렬 Support for supporting rail joint for uniting
KR101114442B1 (en) * 2011-06-16 2012-02-24 강남훈 Method for manufacturing concrete block having three dimensions solid shape and method for laying concrete track using concrete block manufactured by the same method
WO2012173297A1 (en) * 2011-06-16 2012-12-20 Kang Nam-Hun Method for manufacturing solid three-dimensional concrete block and method for laying concrete tracks using concrete block manufactured using the method
KR20160014411A (en) 2014-07-29 2016-02-11 한국철도기술연구원 Rail bridge with slab track reducing rail-structure interaction
CN105984020A (en) * 2015-02-02 2016-10-05 任丘市永基建筑安装工程有限公司 Concrete box-type combined die rail mounting technology
CN106032029A (en) * 2015-03-09 2016-10-19 任丘市永基建筑安装工程有限公司 A combination die steel rail arrangement technology
CN106283960A (en) * 2016-10-17 2017-01-04 兰州理工大学 Sleeper and construction method thereof for non-fragment orbit Concrete Crack Control
CN106283960B (en) * 2016-10-17 2018-01-05 兰州理工大学 Sleeper and its construction method for non-fragment orbit Concrete Crack Control
KR20180086961A (en) 2017-01-24 2018-08-01 한국철도기술연구원 Rail bridge with slab track reducing rail-structure interaction
CN111877054A (en) * 2020-08-11 2020-11-03 北京城建设计发展集团股份有限公司 Prefabricated plate type track structure convenient for rapid construction and construction method thereof
KR102487875B1 (en) * 2021-10-01 2023-01-11 정명수 Sky bike

Also Published As

Publication number Publication date
KR100706786B1 (en) 2007-04-11

Similar Documents

Publication Publication Date Title
KR100706786B1 (en) Precast slab track system and it's construction method
Esveld Recent developments in slab track
Michas Slab track systems for high-speed railways.
EP0170631B1 (en) Components for railway lines on pre-fabricated reinforced concrete slabs without ballast
WO2017185906A1 (en) Transitional structure for turnout and non-turnout zones in low-set, mid-to-low speed magnetic levitation lines
US9222225B2 (en) Pre-stressed concrete track slab of slab-type ballast-less track
AU752198B2 (en) Railway or tramway rail and rail fastening system
US4905896A (en) Railroad roadway for high speed rail-mounted vehicles
CN112941975B (en) Combined track slab, prefabricated slab track system and installation and construction method thereof
CN203411863U (en) Embedded rail
CN103352401B (en) Embedded type track
Tayabji et al. Concrete slab track state of the practice
Bastin Development of German non-ballasted track forms
CN105133493A (en) Embedded track structure suitable for middle-span and small-span bridge and construction method
KR101405468B1 (en) Method for manufacturing concrete block for railway track and method for laying railway track using concrete block manufactured by the same method
CN100360742C (en) Plated rail without ballast
RU2373317C2 (en) Prestressed reinforced concrete slab for railway roads
Ižvolt et al. Historical development and applications of unconventional structure of railway superstructure of the railway infrastructure of the Slovak Republic
RU2352705C1 (en) Method for installation of permanent way
CN110364958B (en) Method for laying cable duct on roadbed
CN111877054A (en) Prefabricated plate type track structure convenient for rapid construction and construction method thereof
CN114808556B (en) Prefabricated assembly frame formula track structure
CN211547089U (en) CRTS IV type track slab
CN219527338U (en) Segment-assembled turnout rail plate beam structure
US20240084515A1 (en) Method of installing a rail support arrangement

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130125

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20140220

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20160325

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20170330

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20180404

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20190404

Year of fee payment: 13