KR20060042491A - Backfill system of integral bridge and its construction method to minimize the backfill pressure and to prevent the approach slab from its settlement - Google Patents

Backfill system of integral bridge and its construction method to minimize the backfill pressure and to prevent the approach slab from its settlement Download PDF

Info

Publication number
KR20060042491A
KR20060042491A KR1020040091083A KR20040091083A KR20060042491A KR 20060042491 A KR20060042491 A KR 20060042491A KR 1020040091083 A KR1020040091083 A KR 1020040091083A KR 20040091083 A KR20040091083 A KR 20040091083A KR 20060042491 A KR20060042491 A KR 20060042491A
Authority
KR
South Korea
Prior art keywords
backfill
compaction
construction
road
earth pressure
Prior art date
Application number
KR1020040091083A
Other languages
Korean (ko)
Other versions
KR100733592B1 (en
Inventor
유성근
김영호
정재호
Original Assignee
유성근
김영호
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 유성근, 김영호 filed Critical 유성근
Priority to KR1020040091083A priority Critical patent/KR100733592B1/en
Publication of KR20060042491A publication Critical patent/KR20060042491A/en
Application granted granted Critical
Publication of KR100733592B1 publication Critical patent/KR100733592B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

본 발명은 일체식교대 교량에 있어서 배면 수동토압을 최소화하고 접속슬래브의 침하를 방지할 수 있는 교대 뒤채움부 구조 및 그 시공방법에 관한 것이다.The present invention relates to an alternating backfill portion structure and a construction method thereof that can minimize back manual earth pressure in an integral shift bridge and prevent settlement of the connecting slab.

이를 위해 본 발명에 따른 교대 뒤채움부 구조는 입자가 크고 입도가 불량한 골재를 뒤채움재로 사용하여 기시공된 교대와 도로성토부 사이에 형성되는 교대 뒤채움부의 교대측에 교대축과 평행하게 소정폭으로 다짐장비를 사용하지 않고 무다짐으로 시공되는 무다짐 뒤채움부와; 상기 무다짐 뒤채움부와 무다짐 뒤채움부 시공시 기시공된 도로성토부로부터 연장 시공되는 도로성토부를 분리하기 위한 분리막과; 연장 시공되는 도로성토부 중 상기 무다짐 뒤채움부에 인접하는 구간에 형성되는 다짐도가 낮은 전이부를 포함하는 것을 특징으로 한다.To this end, the alternating backfilling structure according to the present invention uses predetermined aggregates having a large particle size and poor particle size as the backfilling material. A compaction back filling portion which is constructed by compaction without using compaction equipment in width; Separation membrane for separating the road fill soil extending from the road fill soil construction when the compact backfill and the compact backfill portion construction; It characterized in that it comprises a transition portion having a low compaction degree formed in the section adjacent to the compacting backfill portion of the road fill soil to be extended construction.

일체식교대 교량, 무다짐 뒤채움, 배면 수동토압, 접속슬래브, 배수, 분리막Integrated Shift Bridge, Compact Backfill, Back Manual Earth Pressure, Connecting Slab, Drainage, Separator

Description

일체식교대 교량에 있어서 배면 수동토압의 최소화와 접속슬래브의 침하방지를 위한 교대 뒤채움부 구조 및 그 시공방법{Backfill system of integral bridge and its construction method to minimize the backfill pressure and to prevent the approach slab from its settlement}Backfill system of integral bridge and its construction method to minimize the backfill pressure and to prevent the approach slab from minimizing back manual earth pressure and preventing settlement of connecting slab in integral shift bridge its settlement}

도 1은 본 발명에 따른 무다짐 뒤채움 방법을 일체식교대 교량에 도입한 예를 도시한 단면도.1 is a cross-sectional view showing an example in which the compacting backfilling method according to the present invention is introduced into an integral shift bridge.

도 2a, 2b는 배수수단의 실시예.2a and 2b show an embodiment of the drainage means.

도 3a 내지 도 3e는 본 발명의 일실시예에 따른 교대 뒤채움 방법의 흐름도.3A-3E are flow charts of an alternate backfill method in accordance with one embodiment of the present invention.

도 4는 본 발명의 다른 실시예에 따른 교대 뒤채움 방법의 흐름도.4 is a flow chart of an alternate backfill method according to another embodiment of the present invention.

도 5는 일체식교대 교량의 예를 보인 단면도.5 is a cross-sectional view showing an example of an integral bridge.

도 6은 기존 조인트교량에 적용되는 뒤채움 방법을 일체식교대 교량에 적용한 예를 나타낸 단면도.Figure 6 is a cross-sectional view showing an example of applying the backfill method applied to the existing bridge bridge integral bridge.

<도면의 주요부분에 대한 부호설명><Code Description of Main Parts of Drawing>

10 : 뒤채움부 12 : 무다짐 뒤채움부10: backfill 12: compact backfill

14 : 분리막 16 : 전이부14 separator 16: transition part

18 : 기시공된 도로성토부 20 : 배수수단18: Road construction soil part 20: Drainage means

22 : 중공관 23 : 구멍 22: hollow tube 23: hole

24 : U자형 트렌치 25 : 자갈 또는 쇄석24: U-shaped trench 25: Gravel or crushed stone

26 : 부직포 또는 유공판26 nonwoven fabric or perforated plate

본 발명은 일체식교대 교량에 있어서 배면 수동토압을 최소화하고 접속슬래브의 침하를 방지할 수 있는 교대 뒤채움부 구조 및 그 시공방법에 관한 것이다.The present invention relates to an alternating backfill portion structure and a construction method thereof that can minimize back manual earth pressure in an integral shift bridge and prevent settlement of the connecting slab.

일체식교대 교량이란 도 5에 도시된 바와 같이 신축이음과 교량받침을 제거하고 상부구조와 교대를 일체로 시공한 무조인트교량(jointless bridge)의 한 종류를 말한다. Integrated bridges as shown in Figure 5 refers to a kind of jointless bridge (jointless bridge) to remove the expansion joint and the bridge support and to construct the superstructure and the shift integrally.

이러한 일체식교대 교량은 신축이음과 교량받침이 제거됨으로써 초기 건설 비용과 유지관리 비용이 적게 들고, 충격하중이 감소되며, 차량 주행성이 좋고, 시공이 편리한 잇점이 있다. Such integrated shift bridges have advantages of low initial construction cost and maintenance cost, reduced impact load, good vehicle running, and convenient construction by removing new joints and bridge supports.

그러나 일체식교대 교량은 주위 온도변화로 인한 상부구조의 신축이 교대변위를 유발시키고, 교대변위에 의해 발생한 배면 수동토압이 교대뿐만 아니라 교량 전체의 구조적 거동에 영향을 미치는 문제점이 있다. However, there is a problem that the integral shift bridge causes the displacement of the superstructure due to the change of the ambient temperature, and the back passive earth pressure generated by the shift displacement affects the structural behavior of the entire bridge as well as the shift.

즉, 일반 조인트교량의 경우에는 상부구조와 하부구조가 교량받침에 의해 분리되어 있으므로 교대에 작용하는 주동토압은 상부구조로 전달되지 않으나, 일체식교대 교량의 경우에는 상부구조와 하부구조가 일체로 되어 있으므로 주위 온도변화에 따른 상부구조의 신축에 의해 교대배면에 주동토압과 수동토압이 각각 발생할 수 있는데 특히, 수동토압은 주동토압에 비해 매우 큰 동압이므로 일체식교대의 수동토압에 대한 검토가 필요하다. That is, in the case of general joint bridges, since the superstructure and the substructure are separated by the bridge support, the main earth pressure is not transmitted to the superstructure, but in the case of the integral bridge bridge, the superstructure and the substructure are integrated. Due to the expansion of the superstructure according to the change of ambient temperature, the main earth pressure and the manual earth pressure can be generated on the alternating back surface respectively. In particular, the manual earth pressure is a much higher dynamic pressure than the main earth pressure. Do.

또한, 일체식교대 교량에서 배면토압은 교대 및 파일기초의 거동에 영향을 미칠 뿐만 아니라 상, 하부구조가 서로 구속되어 있으므로 상부구조의 단면내력을 변화시킨다. 즉, 배면토압의 크기가 증가함에 따라 상부구조와 교대의 접합부에 발생하는 부모멘트의 크기가 증가하게 되며 이러한 현상은 상부구조의 단면증가 요인이 되어 결과적으로 공사비의 증가를 초래하게 된다. 따라서 일체식교대 교량의 건설에 있어 배면 수동토압을 최소화할 수 있는 방안이 필요하다.In addition, the back earth pressure in the integral bridge bridge not only affects the behavior of the shift and pile foundation, but also changes the cross-sectional strength of the superstructure because the upper and lower structures are restrained from each other. That is, as the size of the back soil pressure increases, the size of the parent moment occurring at the junction of the superstructure and the shift increases, which causes the cross-sectional increase of the superstructure, resulting in an increase in construction cost. Therefore, there is a need to minimize the back passive earth pressure in the construction of integrated shift bridges.

도 6은 기존 조인트교량에 적용되는 뒤채움 방법을 일체식교대 교량에 적용한 예를 나타낸 단면도이다. Figure 6 is a cross-sectional view showing an example of applying the backfill method applied to the existing bridge bridge integral bridge.

도시된 바와 같이 기존의 뒤채움 방법은 교대(30)와 도로성토부(18)를 독립적으로 시공한 후 뒤채움부(10)를 시공하게 되는데, 도로성토부(18)의 경우 안식각을 확보하기 위해 경사시공을 수행하게 된다. As shown, the existing backfill method is to construct the backfill portion 10 after the shift 30 and the road fill portion 18 independently, to secure the angle of repose of the road fill portion 18. The slope construction is performed.

그리고 뒤채움재료로는 교대 구조물이 완성된 후 실시하는 뒤채움 작업시 교대(30)에 인접한 뒤채움부(10)의 경우 다짐장비의 사용이 용이하지 않는 동시에 도로성토부(18)와 비교시 급속다짐 시공을 하게 되므로 다짐작업이 용이하도록 입도분포가 좋은 도로 보조기층재(SB-1 또는 SB-2)를 사용하여 90% 다짐 규정이 적용되는 도로성토부(18)보다 강화된 95% 다짐이 되도록 시방서에 규정되어 있다.And as a backfill material, the backfill part 10 adjacent to the shift 30 is not easy to use the compaction equipment when the backfill work is carried out after the shift structure is completed, and compared with the road fill part 18. Rapid compaction construction allows for 95% compaction, which is stronger than roadfill soil 18, where 90% compaction rules are applied using road sub-base materials (SB-1 or SB-2) with good particle size distribution to facilitate compaction. It is prescribed in the specification as much as possible.

따라서 기존의 뒤채움 방법은 도로성토부(18)의 경사시공으로 인해 다량의 뒤채움재가 필요하게 되고 뒤채움부(10)와 접촉하는 접속슬래브(40)의 길이가 길어 지게 되는 문제점이 있다. Therefore, the conventional backfilling method requires a large amount of backfilling material due to the inclined construction of the road fill soil portion 18, and the length of the connecting slab 40 in contact with the backfilling portion 10 becomes long.

또한, 교량이 건설되는 동안 다져지고 공사차량 등의 하중으로 자연히 다져진 도로성토부(18)와 급속시공한 뒤채움부(10) 사이에는 다짐도의 차이가 발생하게 되고 따라서 뒤채움부(10) 상부에 자리하며 뒤채움부(10)에 의하여 지지되는 접속슬래브(40)는 공용시간이 증가함에 따라 침하가 발생하게 되며, 접속슬래브(40)의 침하가 발생한 경우 주행중인 차량에 의해 충격이 증대되고, 사용자의 승차감이 불량하며, 접속슬래브(40)를 계속적으로 유지관리하여야 하는 문제가 발생한다. In addition, there is a difference in compaction degree between the road fill soil portion 18 that is compacted during the construction of the bridge and naturally compacted by the load of the construction vehicle, etc., and the back fill portion 10 rapidly formed, and thus the upper portion of the back fill portion 10. The connection slab 40, which is located at and supported by the back filling unit 10, is settled as the common time increases, and when the settlement of the connection slab 40 occurs, the impact is increased by the vehicle being driven. , The user's riding comfort is poor, there is a problem that must maintain the connection slab 40 continuously.

본 발명은 상술한 종래 기술의 문제점을 감안하여 안출된 것으로, 교대 배면 수동토압을 최소화할 수 있는 교대 뒤채움부 구조 및 그 시공방법을 제공하는데 그 목적이 있다.The present invention has been made in view of the above-described problems of the prior art, and an object thereof is to provide an alternating back fill portion structure and a construction method thereof that can minimize alternating back manual earth pressure.

또한, 본 발명의 목적은 뒤채움부의 배수가 용이한 교대 뒤채움부 구조 및 그 시공방법을 제공하는데 있다.It is also an object of the present invention to provide an alternating backfill portion structure and a construction method thereof that are easy to drain the backfill portion.

또한, 본 발명의 목적은 뒤채움부와 접촉하는 접속슬래브의 길이를 줄여 접속슬래브의 침하를 방지할 수 있는 교대 뒤채움부 구조 및 그 시공방법을 제공하는데 있다. In addition, it is an object of the present invention to provide an alternating backfill structure and construction method that can reduce the length of the connection slab in contact with the backfill to prevent the settlement of the connection slab.

본 발명의 그 밖의 목적, 특정한 장점 및 신규한 특징들은 이하의 상세한 설명과 바람직한 실시예로부터 더욱 분명해질 것이다. Other objects, specific advantages and novel features of the invention will become more apparent from the following detailed description and the preferred embodiments.

이하, 본 발명의 바람직한 실시예를 첨부한 도면을 참조하여 상세히 설명한 다.Hereinafter, with reference to the accompanying drawings, preferred embodiments of the present invention will be described in detail.

도 1은 본 발명에 따른 무다짐 뒤채움 방법을 적용하여 시공한 교대 뒤채움부 구조를 나타낸 단면도로서, 본 발명에 따른 교대 뒤채움부는 무다짐 뒤채움부(12)와 전이부(16) 및 이들을 분리하는 분리막(14)으로 구성된다.1 is a cross-sectional view showing the structure of the alternating backfill portion constructed by applying the compaction backfill method according to the present invention, the alternating backfill portion according to the present invention is the compaction backfill portion 12 and the transition portion 16 and It consists of the separator 14 which isolates these.

교대 뒤채움부란 기시공된 교대(30)와 도로성토부(18) 사이에 형성되는 공간부를 말하고, 무다짐 뒤채움부(12)란 교대 뒤채움부의 교대(30)측에 교대축과 평행하게 소정폭(예컨데, 1m이하)으로 뒤채움재를 다짐장비를 사용하지 않고 무다짐으로 시공한 부분을 말한다. The alternating backfill portion refers to a space portion formed between the shifted construction 30 and the road fill portion 18, and the compacting backfill portion 12 is parallel to the shift axis on the alternating side 30 of the alternating backfill portion. Refers to the part where the backfill material is constructed by compacting without using compaction equipment with a predetermined width (for example, 1m or less).

무다짐 뒤채움부(12)에 채워지는 뒤채움재료로는 상용 재료공급 및 생산을 감안하여 도로 현장에서 대량으로 생산되는 도로 보조기층재(예를 들어, SB-1 또는 SB-2)로부터 간단하게 체가름의 조건을 변경하여 도로 현장에서 생산이 가능한 입도가 불량한 재료를 사용한다. The backfill material to be filled in the compaction backfill portion 12 can be easily obtained from a road auxiliary base material (for example, SB-1 or SB-2) produced in large quantities on the road site in consideration of commercial material supply and production. By changing the condition of sieving, we use materials with poor particle size that can be produced on the road site.

다음의 표 1은 본 발명의 무다짐 뒤채움부(12)에 적용된 뒤채움재(SB-3)의 입도기준을 기존 뒤채움재(SB-1,SB-2)로 사용되는 도로 보조기층재의 입도기준과 비교하여 나타낸 것으로, 본 발명에 적용된 뒤채움재는 기본적으로 공극을 극대화하는 동시에 공극의 틈을 채울 가능성이 있고 물이 유입되면 물과 함께 소실될 우려가 있는 작은 입경의 골재를 배제한 재료이다. Table 1 below is the particle size criteria of the road auxiliary base material used as the backfill material (SB-1, SB-2) as the particle size standard of the backfill material (SB-3) applied to the compacting backfill portion 12 of the present invention As compared with the present invention, the backfill material applied to the present invention is basically a material excluding a small particle size aggregate that is capable of filling gaps in the gap while maximizing voids and possibly losing with water when water is introduced.

입도 번호Granularity number 통과중량백분율(%)Passing weight percentage (%) 75mm75 mm 50mm50 mm 40mm40 mm 20mm20 mm 10mm10 mm No.4No.4 No.8No.8 No.10No.10 No.40No.40 No.200No.200 SB-1SB-1 100100 -- 70-10070-100 50-9050-90 -- 30-6530-65 -- 20-5520-55 5-255-25 2-102-10 SB-2SB-2 -- 100100 80-10080-100 55-10055-100 -- 30-7030-70 -- 20-5520-55 5-305-30 2-102-10 SB-3SB-3 -- 100100 -- -- -- 00 -- -- -- --

구체적으로는 뒤채움재는 중량백분률로 50mm체에 100% 통과하고, No.4체에 모두 남는 입도기준을 가지도록 하였다. 그 이유는 기본적으로 콘크리트 배합시 사용하는 최대 입경 50mm는 교반 성능 확보와 시공성을 위한 것으로 최대 골재 입경을 50mm로 하여 고르지 못한 입도 분포에서 교반성능과 현장에서 생산성이나 선정하는데 어려움이 없기 때문이며, No.4 미만의 골재는 입경이 5mm 이하로서 교대 뒤채움부에 유입수가 발생할 경우 물과 함께 유실된 우려가 크기 때문에 배제한 것이다. Specifically, the backfill material passed 100% of the 50mm sieve at a weight percentage and had a particle size standard remaining in all No. 4 sieves. The reason is that the maximum particle size of 50mm used in concrete mixing is for securing agitation performance and constructability. The maximum aggregate particle size is 50mm, which means that there is no difficulty in agitation performance and selection in the uneven particle size distribution and in the field. Aggregate less than 4 is excluded because the particle diameter is less than 5mm and there is a great risk of loss with water when inflow water occurs in the alternating backfill.

따라서 본 발명에 따른 뒤채움재(SB-3)는 입도가 불량함으로서 입자들 사이에는 모양과 크기가 다른 틈인 공극을 효율적으로 형성할 수 있다. 또한 공극은 공기로 채워져 있는데, 특히 액체 즉, 유입수의 통로로 중요한 구실을 하고 있으며 배면 수동토압이 발생할 경우 완충적 공간으로도 직접 간접으로 그 기능을 갖게 된다. Therefore, the backfill material (SB-3) according to the present invention is poor in particle size, it is possible to efficiently form voids of different shapes and sizes between the particles. In addition, the voids are filled with air, which plays an important role in the passage of liquid, that is, the influent, and has a direct and indirect function as a buffer space when the back passive earth pressure occurs.

한편, 구조적으로도 입도분포가 불량할 경우 내부 마찰각이 작아지므로 수동토압계수가 기존 재료에 비해 작고 따라서 배면 수동토압이 감소하게 되며 배수가 용이하게 된다. On the other hand, if the particle size distribution is poor in structure, the internal friction angle is small, so the manual earth pressure coefficient is smaller than that of the existing material, and thus the back manual earth pressure is reduced and drainage is easy.

이러한 뒤채움재는 무다짐 뒤채움부(12)에 그대로 채워넣거나 돌망태(13) 형태로 제작하여 쌓게 된다. Such backfill material is filled in the compacted backfill portion 12 as it is or is produced by stacking the gabion 13 form.

분리막(14)은 무다짐 뒤채움부(12)와 연장 시공되는 도로성토부를 분리하기 위한 수단으로서, 무다짐 뒤채움부(12)의 시공을 용이하게 하고 연장 시공되는 도로성토부의 토사가 무다짐 뒤채움부(12)로 유입되는 것을 막기 위해 설치한다. 재 료는 유기질 또는 무기질 재료로 토사의 유입은 방지하면서 지하수는 통과할 수 있는 것이라면 어느 것이라도 가능하며, 바람직하게는 부직포를 들 수 있다.Separation membrane 14 is a means for separating the compacted backfill 12 and the road-filled soil to be extended construction, facilitates the construction of the compacted backfill 12, and the soil filling of the road-filled soil to be extended construction It is installed to prevent the inflow into the back filling portion (12). The material may be any organic or inorganic material, as long as it can pass the groundwater while preventing the inflow of soil, and preferably non-woven fabric.

전이부(16)란 무다짐 뒤채움부(12)와 도로성토부(18) 사이에 형성되는 상대적으로 다짐도가 낮은 구간을 말하는데, 무다짐 뒤채움부(12)를 시공하면서 교대(30)와 인접한 구간에 연장 시공되는 도로성토부를 시공하는 과정에서 형성되며, 무다짐 뒤채움부(12)와 인접한 일부 구간(대략 0.5 ~ 1m)에만 형성된다.The transition part 16 refers to a section having a relatively low degree of compaction formed between the compaction backfill portion 12 and the road fill portion 18. The construction of the transition backfill portion 12 alternates with the construction 30. It is formed in the process of constructing the road fill section extending to the adjacent section, and is formed only in a portion (approximately 0.5 ~ 1m) adjacent to the compacting backfill 12.

한편, 뒤채움부(10)에는 배수수단(20)이 더 설치될 수 있는데, 배수수단(20)은 뒤채움부(10)의 교대(30)쪽 하단에 설치되는 지하수 배수설비를 말한다. On the other hand, the back-filling portion 10 may be further provided with a drainage means 20, the drainage means 20 refers to the groundwater drainage equipment is installed on the lower side of the alternate 30 of the back-filling portion (10).

배수수단(20)은 뒤채움부(10)의 배수가 양호하지 않을 경우 지하수위가 증가하여 토압을 증가시키므로 유입되는 지하수를 원활히 배수하기 위하여 이미 설명한 바와 같이 입도가 불량한 재료를 사용한 재료를 통과한 물을 손쉽게 배수하여 지하수위의 상승을 사전방지하기 위한 것이다.When the drainage means 20 does not have good drainage of the backfill 10, the groundwater level is increased to increase earth pressure. Thus, the drainage means 20 has passed through a material using a material having a poor particle size as described above to smoothly drain the incoming groundwater. It is to prevent the rise of the groundwater level by easily draining the water.

도 2a와 도 2b는 배수수단(20)의 실시예를 나타낸 것으로, 도 2a에 도시된 바와 같이, 상부 반단부에만 다수의 구멍(23)이 형성된 유공관(22)이나, 도 2b에 도시된 바와 같이, 공간부에 입자가 크고 균일한 형상을 가진 자갈 또는 쇄석(25)을 채워넣은 U-자형 트렌치(24)가 적용될 수 있다. 유공관(22)의 단면은 원형이나 사각형이 바람직하나 이에 한정되지 않으며, 구멍(23)의 형상 역시 원형, 타원형, 사각형, 삼각형, 마름모형 등이 바람직하나 이에 한정되지는 않는다. U-자형 트렌치(24)의 개구에는 토사유입을 방지하기 위한 수단으로 부직포 또는 유공판(26)을 설치할 수 있다.2A and 2B show an embodiment of the drainage means 20. As shown in FIG. 2A, the hole tube 22 having a plurality of holes 23 formed only in the upper half end thereof, or as shown in FIG. 2B. Likewise, a U-shaped trench 24 filled with gravel or crushed stone 25 having a large particle and a uniform shape in the space may be applied. The cross section of the perforated tube 22 is preferably a circle or a square, but is not limited thereto. The shape of the hole 23 is also preferably circular, elliptical, square, triangular, rhombus, etc., but is not limited thereto. The opening of the U-shaped trench 24 may be provided with a nonwoven fabric or a perforated plate 26 as a means for preventing soil inflow.

이하에서는 상기한 구조를 갖는 교대 뒤채움부의 시공방법을 도 3a 내지 도 3e를 참조하여 설명한다. Hereinafter, the construction method of the alternate backfill portion having the above-described structure will be described with reference to FIGS. 3A to 3E.

본 발명에 따른 교대 뒤채움부 시공방법은 배수수단 설치단계, 분리막 배치단계, 뒤채움재 시공단계, 도로성토부 다짐단계 및 뒤채움부 완성단계로 이루어진다.Alternate backfill portion construction method according to the present invention consists of drainage means installation step, separation membrane arrangement step, backfill material construction step, road fill soil compaction step and backfill part completion step.

구체적으로, 도 3a에 도시된 바와 같이, 먼저 교대(30)측에 인접한 뒤채움부(10)의 하단에 배수수단(20)을 설치하고(배수수단 설치단계), 기시공된 교대(30)와 도로성토부(18) 사이의 뒤채움부(10)에 분리막(14)을 배치한 후(분리막 배치단계), 교대(30) 배면으로부터 도로성토부(18) 방향으로 소정의 구간(약 1m 구간)에 일정 높이(대략 30cm)로 본 발명에 따른 뒤채움재를 무다짐으로 시공한다. 뒤채움재는 돌망태(13) 형태로 제작되어 단순히 적재할 수도 있다(뒤채움재 시공단계).Specifically, as shown in Figure 3a, first install the drainage means 20 at the lower end of the back-filling portion 10 adjacent to the shift 30 side (drainage means installation step), the pre-installed shift 30 After the separation membrane 14 is disposed on the backfill portion 10 between the road fill portion 18 (separation membrane arrangement step), a predetermined section (about 1 m from the alternating back surface 30 in the direction of the road fill portion 18). The backfill material according to the present invention is constructed with a certain height (about 30 cm) in the section). Backfill material is manufactured in the form of gabion 13 can be simply loaded (backfill material construction step).

다음으로, 도 3b에 도시된 바와 같이 분리막(14)을 세운 후 무다짐 뒤채움부(12) 시공 높이와 동일한 높이로 연장 시공되는 도로성토부를 성토하고 다짐한다(도로성토부 다짐단계). 이때, 연장 시공되는 도로성토부에는 기존 뒤채움재(SB-1,SB-2)가 사용되며, 무다짐 뒤채움부(12)와 인접한 연장 시공되는 도로성토부의 경우 교대에 충격이 가지 않도록 무진동 다짐을 하게 되고("A"부분) 그 외의 부분은 진동 다짐을 하게 된다("B"부분). 따라서 연장 시공되는 도로성토부 중에서 무진동 다짐 부분("A"부분)은 진동 다짐된 도로성토부("B"부분, 17) 및 무다짐 뒤채움부(12)와 다짐도의 차이를 갖는 전이부(16)가 되고, 진동 다짐된 도로성토부("B"부분)는 기존 도로성토부(18)와 거의 동일한 다짐도를 갖는 도로성토부(17)가 된 다. Next, as shown in FIG. 3B, after the separation membrane 14 is set up, the road fill area which is constructed to extend to the same height as the construction height of the compaction backfill part 12 is filled and compacted (road fill part compacting step). In this case, the existing backfill material (SB-1, SB-2) is used for the road fill section to be extended, and the vibration-free compaction to prevent the impact on the shift in the case of the road fill section adjacent to the compact backfill section 12 ("A" part) and other parts are vibrated ("B" part). Therefore, the non-vibratory compaction portion ("A" portion) of the extended fill soil portion ("A" portion) is a transition portion having a difference between the compaction degree and the compaction road fill portion ("B" portion, 17) and the compaction backfill portion 12 ( 16), the vibratory compacted road fill section ("B" portion) becomes a road fill section 17 having the same compaction degree as the existing road fill section 18.

다음으로, 도 3c 내지 3d에 도시된 바와 같이 상기한 뒤채움재 시공 및 도로성토부 다짐의 과정을 계획고에 도달할 때까지 반복함으로써(뒤채움부 완성단계) 뒤채움부의 시공이 완료되게 된다.Next, as shown in Figures 3c to 3d by repeating the process of the backfill material construction and road fill compaction until reaching the planned height (after filling part completion step) construction of the backfill is completed.

이렇게 교대 뒤채움부의 시공이 완료되면, 도 3e에 도시된 바와 같이 교량의 바닥판 슬래브(52)와 도로부(42) 사이에 접속슬래브(40)를 시공하여 서로 연결시키면 교량의 건설이 완료된다. 이때, 접속 슬래브(40)와 도로부(42) 사이에는 신축이음부(44)를 두고 신축이음부(44) 아래에는 슬리퍼 슬래브(46)를 설치한다.When the construction of the alternating backfill is completed, as shown in FIG. 3E, when the connecting slab 40 is connected between the bottom slab 52 and the road 42 of the bridge, the construction of the bridge is completed. At this time, the expansion joint 44 between the connection slab 40 and the road part 42, and the slipper slab 46 is installed below the expansion joint 44.

이상과 같은 방법으로 본 발명에서는 교대 구축시 시공된 기존 도로성토부(18)가 교대(30)와 근접한 위치까지 연장 시공되므로, 뒤채움부와 접촉하는 접속슬래브(40)의 길이가 짧아지게 된다. 즉, 종래의 경우에는 교대 구축시 시공된 기존 도로성토부와 교대 사이의 뒤채움부에 뒤채움재를 단순 시공하였으므로, 뒤채움부와 접촉하는 접속슬래브의 길이가 길어질 수 밖에 없었다(도 6 참조). 그러나 본 발명에서는 교대와 근접한 위치까지 도로성토부를 연장 시공함으로써 뒤채움부와 접촉하는 접속슬래브(40)의 길이가 짧아지게 된다. In the present invention as described above, since the existing road fill portion 18 constructed at the time of shift construction is extended to a position close to the shift 30, the length of the connecting slab 40 in contact with the back filling portion is shortened. . That is, in the conventional case, since the backfill material was simply constructed in the backfill portion between the existing road fill part and the shift, which was constructed at the time of shift construction, the length of the connecting slab in contact with the backfill portion was long (see FIG. 6). . However, in the present invention, the length of the connecting slab 40 in contact with the back filling portion is shortened by extending the road fill soil to a position close to the shift.

또한, 종래의 경우 도로성토부가 교대에서 대략 0.5m 떨어진 위치에서 1:1의 경사를 갖게 시공되므로 접속슬래브와 접촉하는 뒤채움부의 길이는 교대 높이에 따라 증가되는 문제점이 있으나, 본 발명에서는 교대 높이에 관계 없이 일정한 접촉길이를 얻을 수 있다. 그에 따라 사용되는 뒤채움재의 사용량을 줄일 수 있는 효과도 있다. In addition, in the conventional case, since the road fill site is constructed to have a tilt of 1: 1 at a position approximately 0.5 m away from the shift, the length of the back filling portion contacting the connecting slab is increased depending on the shift height, but in the present invention, the shift height is increased. Irrespective of the constant contact length can be obtained. There is also an effect that can reduce the amount of backfill material used.

한편, 돌망태 형태로 제작된 뒤채움재를 사용할 경우, 도 4에 도시된 바와 같이 돌망태(13) 형태로 제작된 뒤채움재를 뒤채움부를 계획고까지 시공하고 분리막(14)을 설치한 후 연장 시공되는 도로성토부를 성토하고 다짐하게 된다. 이때, 연장 시공되는 도로성토부에는 기존 뒤채움재(SB-1,SB-2)가 사용되며, 연장 시공되는 도로성토부 다짐의 경우, 무다짐 뒤채움부(12)와 인접한 도로성토부의 경우 교대에 충격이 가지 않도록 무진동 다짐을 하게 되고("A"부분) 그 외의 부분은 진동 다짐을 하게 된다("B"부분). 따라서 무진동 다짐 부분("A"부분)은 진동 다짐된 도로성토부("B"부분, 17) 및 무다짐 뒤채움부와 다짐도의 차이를 갖는 전이부(16)가 되고, 진동 다짐된 도로성토부("B"부분)는 기존 도로성토부(18)와 거의 동일한 다짐도를 갖는 도로성토부(17)가 된다. On the other hand, in the case of using the backfill material manufactured in the form of gabion, the backfill material produced in the form of the gabion 13, as shown in Figure 4 to the construction of the back filling portion to the planned height and installed after the separation membrane 14 The road fills and fills the area. At this time, the existing backfill material (SB-1, SB-2) is used for the road fill site to be extended, and in the case of road fill compaction to be extended, the road fill section adjacent to the compaction back fill section 12 is shifted. Vibration-free compaction ("A" part) and vibration-free compaction ("B" part) are performed to prevent impact. Therefore, the vibration free compaction portion ("A" portion) becomes a vibratory compacted road fill portion ("B" portion, 17) and a transition portion 16 having a difference between the compaction backfill portion and the compaction degree. The portion ("B" portion) becomes the road fill portion 17 having the same compaction degree as the existing road fill portion 18.

상술한 바와 같이 본 발명에 따르면, 기존 도로 현장에서 보조기층 생산 시설로부터 매우 손쉽게 생산 가능한 입도분포가 불량한 골재를 뒤채움재로 사용하므로서 교대배면의 배수가 용이하므로 지하수의 급격한 유입으로 인한 수압에 의해 토압의 증가가 없고 재료의 특성상 수동토압 계수가 작으므로 일체식교대 교량의 배면 수동토압을 효과적으로 줄일 수 있다.As described above, according to the present invention, it is easy to drain the alternating back surface by using the aggregate having a poor particle size distribution that can be produced very easily from the auxiliary base production facility in the existing road site as a backfill material, so that the earth pressure by the water pressure due to the rapid inflow of groundwater Since there is no increase in and the passive earth pressure coefficient is small due to the characteristics of the material, it is possible to effectively reduce the back manual earth pressure of the integral shift bridge.

또한, 무다짐 뒤채움부와 전이부의 길이는 기존 뒤채움부의 길이보다 매우 작으므로 접속슬래브의 길이를 기존 뒤채움방법에 비해 작게 할 수 있어 접속슬래브의 침하를 방지할 수 있다.In addition, since the length of the filling backfill portion and the transition portion is much smaller than the length of the existing backfilling portion, the length of the connecting slab can be made smaller than that of the existing backfilling method, thereby preventing settlement of the connecting slab.

비록 본 발명이 상기에서 언급한 바람직한 실시예와 관련하여 설명되어졌지 만 본 발명의 요지와 범위로부터 벗어남이 없이 다양한 수정이나 변형이 가능하다. 즉, 상기에서 언급한 실시예는 일체식교대 교량에 적용된 경우에 대해 설명되었지만 일반 조인트교량의 뒤채움에 적용할 경우에도 동일한 효과를 볼 수 있다. 따라서 특허청구범위는 본 발명의 요지에 속하는 어떠한 수정이나 변형도 포함할 것이다.Although the present invention has been described in connection with the preferred embodiments mentioned above, various modifications and variations are possible without departing from the spirit and scope of the invention. That is, the above-mentioned embodiment has been described with respect to the case of applying to the integral bridge bridge, but the same effect can be seen when applied to the backfill of the general joint bridge. Thus, the claims will cover any modifications or variations that fall within the spirit of the invention.

Claims (13)

일체식교대 교량의 교대 뒤채움부 구조에 있어서,In the shift backfill structure of the integral shift bridge, 입자가 크고 입도가 불량한 골재를 뒤채움재로 사용하여 기시공된 교대(30)와 도로성토부(18) 사이에 형성되는 교대 뒤채움부(10)의 교대(30)측에 교대축과 평행하게 소정폭으로 다짐장비를 사용하지 않고 무다짐으로 시공되는 무다짐 뒤채움부(12)와; Using the aggregate having a large particle size and poor particle size as the backfill material, parallel to the alternating axis on the side of the alternating backfill portion 10 formed between the alternating portion 30 and the road fill portion 18, which were previously constructed. A compaction back filling portion 12 that is constructed by compaction without using compaction equipment in a predetermined width; 상기 무다짐 뒤채움부(12)와 무다짐 뒤채움부(12) 시공시 기시공된 도로성토부(18)로부터 연장 시공되는 도로성토부를 분리하기 위한 분리막(14)과; Separation membrane (14) for separating the road filling portion extending from the road fill portion (18) that was initially installed during the compacting back filling portion (12) and the compacting back filling portion (12) construction; 연장 시공되는 도로성토부 중 상기 무다짐 뒤채움부(12)에 인접하는 구간에 형성되는 다짐도가 낮은 전이부(16);를 포함하는 것을 특징으로 하는 배면 수동토압의 최소화와 접속슬래브의 침하방지를 위한 교대 뒤채움부 구조.Minimizing the back passive earth pressure and preventing settlement of the connecting slab, comprising: a transition portion 16 having a low compaction degree formed in a section adjacent to the compacted backfill portion 12 of the road-filled soil to be extended and constructed. Shift backfill structure for the. 제 1 항에 있어서,The method of claim 1, 상기 뒤채움재는 중량백분률로 50mm체에 100% 통과하고, No.4체에 100% 남는 입도분포를 가진 것을 특징으로 하는 배면 수동토압의 최소화와 접속슬래브의 침하방지를 위한 교대 뒤채움부 구조.The backfill material passes 100% in a 50mm sieve at a percentage by weight, and has a particle size distribution that remains 100% in No. 4 sieves. Alternate backfill portions for minimizing back manual earth pressure and preventing settlement of the connecting slab . 제 1 항 또는 제 2 항에 있어서,The method according to claim 1 or 2, 상기 뒤채움재는 돌망태(13) 형태로 제작된 것을 특징으로 하는 배면 수동토 압의 최소화와 접속슬래브의 침하방지를 위한 교대 뒤채움부 구조.The backfill material is alternately backfilled structure for minimizing the back passive earth pressure and preventing settlement of the connecting slab, characterized in that the gabion (13) form. 제 3 항에 있어서,The method of claim 3, wherein 상기 뒤채움부(12)의 교대측 하단에는 배수수단(20)이 더 설치된 것을 특징으로 하는 배면 수동토압의 최소화와 접속슬래브의 침하방지를 위한 교대 뒤채움부 구조. Alternating lower end of the back filling portion 12, the drainage means 20 is characterized in that the alternate back filling portion structure for minimizing the back passive earth pressure and preventing the settlement of the connection slab. 제 4 항에 있어서,The method of claim 4, wherein 상기 배수수단(20)은 속이 비어 있는 관으로서 상부 반단부에만 다수의 구멍(23)이 형성된 중공관(22)인 것을 특징으로 하는 배면 수동토압의 최소화와 접속슬래브의 침하방지를 위한 교대 뒤채움부 구조. The drainage means 20 is a hollow tube 22, which is a hollow tube 22 having a plurality of holes 23 formed only at an upper half end thereof, and alternately back-filling for minimizing back manual earth pressure and preventing settlement of the connecting slab. Wealth structure. 제 4 항에 있어서, The method of claim 4, wherein 상기 배수수단(20)은 공간부에 입자가 크고 균일한 형상을 가진 자갈 또는 쇄석(25)이 채워진 U-자형 트렌치(24)인 것을 특징으로 하는 배면 수동토압의 최소화와 접속슬래브의 침하방지를 위한 교대 뒤채움부 구조.The drainage means 20 is a U-shaped trench 24 filled with gravel or crushed stone 25 having a large and uniform shape in the space portion, minimizing the back passive earth pressure and preventing settlement of the connecting slab. Shift backfill structure. 제 6 항에 있어서,The method of claim 6, 상기 트렌치(24)의 개방부에는 부직포(26) 또는 유공판이 설치된 것을 특징으로 하는 배면 수동토압의 최소화와 접속슬래브의 침하방지를 위한 교대 뒤채움부 구조.Alternate backfill portion structure for minimizing the back passive earth pressure and preventing settlement of the connecting slab, characterized in that the non-woven fabric 26 or the perforated plate is installed in the opening portion of the trench 24. 일체식교대 교량의 교대 뒤채움부 시공방법에 있어서,In the construction method of the shift backfill portion of the integral shift bridge, 교대(30)와 도로성토부(18) 사이의 교대 뒤채움부에 분리막(14)을 배치하는 분리막 배치단계와; A separation membrane arrangement step of disposing a separation membrane 14 at an alternating backfill portion between the shift 30 and the road fill portion 18; 교대(30)배면으로부터 도로성토부(18) 방향으로 소정 구간에 일정 높이로 상기 분리막(14)을 세우면서 일정 높이로 입자가 크고 입도가 불량한 뒤채움재를 무다짐으로 시공하거나, 입자가 크고 입도가 불량한 뒤채움재를 돌망태(13) 형태로 제작하여 단순히 적재하는 뒤채움재 시공단계와;Construction of the backfill material with a large particle size and poor particle size at a certain height while laying the separator 14 at a predetermined height in the direction of the road fill soil 18 from the rear surface of the alternating material 30 A backfill material construction step of simply manufacturing the poor backfill material in the form of a gabion (13); 무다짐 뒤채움부(12) 시공 높이와 동일한 높이로 연장 시공되는 도로성토부를 성토하고, 무다짐 뒤채움부(12)와 인접한 연장 시공되는 도로성토부의 경우 교대에 충격이 가지 않도록 무진동 다짐을 하고, 그 외의 부분은 진동 다짐을 하는 연장 시공되는 도로성토부 다짐단계와; After filling the road fillet which is extended to the same height as the construction height of the compaction backfill 12, and the roadfill site which is extended adjacent to the compaction backfill 12, the vibration-free compaction is made so as not to impact the shift. , And other parts of the road fill soil compaction step is extended to the compaction vibration; 상기 뒤채움재 시공단계와 연장 시공되는 도로성토부 다짐단계를 계획고에 도달할 때까지 반복하는 단계를 포함하는 것을 특징으로 하는 배면 수동토압의 최소화와 접속슬래브의 침하방지를 위한 교대 뒤채움부 시공방법.Alternate backfill construction for minimizing the back manual earth pressure and preventing settlement of the connecting slab, comprising the step of repeating the backfill construction step and the road fill site compaction step being extended to reach the planned height. Way. 제 8 항에 있어서,The method of claim 8, 상기 뒤채움재는 중량백분률로 50mm체에 100% 통과하고, No.4체에 100% 남는 입도분포를 가진 것을 특징으로 하는 배면 수동토압의 최소화와 접속슬래브의 침하 방지를 위한 교대 뒤채움부 시공방법.The backfill material is passed by 100% in a 50mm sieve at a weight percentage, and has a particle size distribution that remains 100% in No. 4 sieves, alternate backfill construction for minimizing the back manual earth pressure and preventing settlement of the connecting slab. Way. 제 8 항 또는 제 9 항에 있어서,The method according to claim 8 or 9, 상기 분리막(14)을 배치하기 전에 교대(30)측에 인접한 뒤채움부의 하단에 배수수단(20)을 설치하는 배수수단 설치단계를 더 포함하는 것을 특징으로 하는 배면 수동토압의 최소화와 접속슬래브의 침하방지를 위한 교대 뒤채움부 시공방법.Before disposing the separation membrane 14 further comprises the step of installing the drainage means for installing the drainage means 20 at the lower end of the back-filling portion adjacent to the alternating (30) side of minimizing the back passive earth pressure and the connection of the slab Alternate backfill construction method to prevent settlement. 일체식교대 교량의 교대 뒤채움부 시공방법에 있어서,In the construction method of the shift backfill portion of the integral shift bridge, 교대(30)와 도로성토부(18) 사이의 뒤채움부에 돌망태(13) 형태로 제작된 입자가 크고 입도가 불량한 뒤채움재를 뒤채움부 계획고까지 시공하는 단계와;Constructing a backfill material having a large and poor particle size in the form of a gabion 13 between the backfill portion 18 and the road fill portion 18 to the backfill portion plan; 분리막(14)을 설치하는 단계와;Installing a separator (14); 소정의 높이로 연장 시공되는 도로성토부를 성토하고, 무다짐 뒤채움부(12)와 인접한 연장 시공되는 도로성토부의 경우 교대(30)에 충격이 가지 않도록 무진동 다짐을 하고, 그 외의 부분은 진동 다짐을 하는 연장 시공되는 도로성토부를 다짐하는 단계와;Fill the road fill section extending to a predetermined height, and in the case of the road fill section extending adjacent to the compacting backfill section 12, make a vibration-free compaction so as not to impact the shift 30, and the other parts Compacting the road fill soil to be extended construction; 상기 연장 시공되는 도로성토부 성토·다짐을 계획고에 도달할 때까지 반복하는 단계를 포함하는 것을 특징으로 하는 배면 수동토압의 최소화와 접속슬래브의 침하방지를 위한 교대 뒤채움부 시공방법.Alternate backfill portion construction method comprising the step of repeating the embankment, compaction and compaction of the road to be extended construction until reaching the planned height. 제 11 항에 있어서,The method of claim 11, 상기 뒤채움재는 중량백분률로 50mm체에 100% 통과하고, No.4체에 100% 남는 입도분포를 가진 것을 특징으로 하는 배면 수동토압의 최소화와 접속슬래브의 침하방지를 위한 교대 뒤채움부 시공방법.The backfill material is passed by 100% in a 50mm sieve with a weight percentage, and has a particle size distribution that remains 100% in No. 4 sieves, alternate backfilling construction for minimizing the back manual earth pressure and preventing settlement of the connecting slab. Way. 제 11 항 또는 제 12 항에 있어서,The method according to claim 11 or 12, 상기 뒤채움재를 시공하기 전에 교대(30)측에 인접한 뒤채움부의 하단에 배수수단(20)을 설치하는 단계를 더 포함하는 것을 특징으로 하는 배면 수동토압의 최소화와 접속슬래브의 침하방지를 위한 교대 뒤채움부 시공방법.Shifting for minimizing the back passive earth pressure and preventing settlement of the connection slab, further comprising the step of installing the drainage means 20 at the bottom of the back filling portion adjacent to the shift 30 side before installing the back filling material. Backfill construction method.
KR1020040091083A 2004-11-09 2004-11-09 Backfill system of integral bridge and its construction method to minimize the backfill pressure and to prevent the approach slab from its settlement KR100733592B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040091083A KR100733592B1 (en) 2004-11-09 2004-11-09 Backfill system of integral bridge and its construction method to minimize the backfill pressure and to prevent the approach slab from its settlement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040091083A KR100733592B1 (en) 2004-11-09 2004-11-09 Backfill system of integral bridge and its construction method to minimize the backfill pressure and to prevent the approach slab from its settlement

Publications (2)

Publication Number Publication Date
KR20060042491A true KR20060042491A (en) 2006-05-15
KR100733592B1 KR100733592B1 (en) 2007-07-03

Family

ID=37148349

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040091083A KR100733592B1 (en) 2004-11-09 2004-11-09 Backfill system of integral bridge and its construction method to minimize the backfill pressure and to prevent the approach slab from its settlement

Country Status (1)

Country Link
KR (1) KR100733592B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102787557A (en) * 2012-09-02 2012-11-21 中铁二院工程集团有限责任公司 Drainage structure of high-speed railway bridge road connector
CN107905093A (en) * 2017-11-17 2018-04-13 福州大学 The multistage abutment construction and its construction method of soil sedimentation after improvement bridge platform
CN108677637A (en) * 2018-04-28 2018-10-19 中交三航局第三工程有限公司 A kind of roadbed filling method of precast concrete tube coupling reinforcement light soil
CN111827097A (en) * 2020-07-06 2020-10-27 上海崇明水利工程有限公司 Concatenation formula reinforced concrete bridge abutment structure

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101653606B1 (en) * 2015-09-25 2016-09-02 우경기술주식회사 Method for constructing integral abutment bridge
KR102148258B1 (en) * 2018-12-20 2020-08-26 에스오씨기술지주 주식회사 Temporory bridges using piles and geobags and its construction method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010000952A (en) * 2000-10-31 2001-01-05 지영호 Removal of Nitrogen in Waste Water using Plasma Device
KR100433653B1 (en) * 2000-11-30 2004-06-07 (주)한맥기술 Constructing method for the filling out abutement of bridge
KR100451059B1 (en) * 2001-12-08 2004-10-02 삼영플랜트주식회사 Method and apparatus for manufacturing agrregate
KR20020025856A (en) * 2001-12-28 2002-04-04 이기홍 Prevention of approach slab settlement by applying non-com paction abutment backfilling method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102787557A (en) * 2012-09-02 2012-11-21 中铁二院工程集团有限责任公司 Drainage structure of high-speed railway bridge road connector
CN107905093A (en) * 2017-11-17 2018-04-13 福州大学 The multistage abutment construction and its construction method of soil sedimentation after improvement bridge platform
CN107905093B (en) * 2017-11-17 2023-09-01 福州大学 Multistage bridge abutment structure for improving rear soil settlement of bridge abutment and construction method thereof
CN108677637A (en) * 2018-04-28 2018-10-19 中交三航局第三工程有限公司 A kind of roadbed filling method of precast concrete tube coupling reinforcement light soil
CN108677637B (en) * 2018-04-28 2020-12-08 中交三航局第三工程有限公司 Roadbed filling method for precast concrete pipe joint reinforced lightweight soil
CN111827097A (en) * 2020-07-06 2020-10-27 上海崇明水利工程有限公司 Concatenation formula reinforced concrete bridge abutment structure

Also Published As

Publication number Publication date
KR100733592B1 (en) 2007-07-03

Similar Documents

Publication Publication Date Title
US10753049B2 (en) Pavement systems with geocell and geogrid
KR100243393B1 (en) Reinforced structure of soft foundation for using cell frame-work and its construction method
JP6335569B2 (en) Ground preparation method and ground structure
CN107905089A (en) A kind of reinforcement platform back of the body for preventing bumping at bridge-head and its construction method
KR100733592B1 (en) Backfill system of integral bridge and its construction method to minimize the backfill pressure and to prevent the approach slab from its settlement
CN110670436A (en) Structure for preventing urban road subgrade from non-uniform settlement and construction method thereof
KR101327278B1 (en) Foundation construction
KR101761477B1 (en) Construction method of jointless bridge with reinforced earth retaining wall and spread bearing block
CN114232399B (en) Highway support for collapsible area and construction method thereof
CN110172885A (en) Highway Construction in Desert method
JPH0453205B2 (en)
RU2256747C2 (en) Method for forming interface between bridge roadway and embankment
US20060213146A1 (en) Method of making a flat foundation for a floor without substantial excavation and foundation made by said method
CN113463457B (en) Roadbed structure for penetrating through slurry section and construction method thereof
KR20020025856A (en) Prevention of approach slab settlement by applying non-com paction abutment backfilling method
KR100536429B1 (en) Block structure of inorganic porous material and laying method using that
CN217324799U (en) Prevent roadbed structure that subsides
KR960013592B1 (en) Working method of toy top type concrete pile framings foundation
CN213267356U (en) Roadbed built above high-water-content silt
KR102088320B1 (en) foundation reinforcement construction method using cutting PHC pile
CN112144357B (en) Vibration rolling device of bedding material spreading machine
CN213389569U (en) Asphalt road structure
Whyte The overriding aspects of the design of geosynthetic-reinforced pile supported embankments
CN211142682U (en) Structure for preventing urban road subgrade from non-uniform settlement
CN216193941U (en) Novel abutment structure

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
E902 Notification of reason for refusal
E601 Decision to refuse application
AMND Amendment
J201 Request for trial against refusal decision
B701 Decision to grant
GRNT Written decision to grant
N231 Notification of change of applicant
G170 Publication of correction
FPAY Annual fee payment

Payment date: 20130624

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20140620

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20150609

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20160607

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20170622

Year of fee payment: 11