KR20050098338A - Structure of steel pipe applied to steel pipe roof construction method for building underground structure, and steel pipe roof structure therefor using the same, and steel roof construction method thereof - Google Patents

Structure of steel pipe applied to steel pipe roof construction method for building underground structure, and steel pipe roof structure therefor using the same, and steel roof construction method thereof Download PDF

Info

Publication number
KR20050098338A
KR20050098338A KR1020040023343A KR20040023343A KR20050098338A KR 20050098338 A KR20050098338 A KR 20050098338A KR 1020040023343 A KR1020040023343 A KR 1020040023343A KR 20040023343 A KR20040023343 A KR 20040023343A KR 20050098338 A KR20050098338 A KR 20050098338A
Authority
KR
South Korea
Prior art keywords
steel pipe
steel
flange
clasp
flanges
Prior art date
Application number
KR1020040023343A
Other languages
Korean (ko)
Other versions
KR100569703B1 (en
Inventor
김진수
Original Assignee
김진수
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김진수 filed Critical 김진수
Priority to KR1020040023343A priority Critical patent/KR100569703B1/en
Publication of KR20050098338A publication Critical patent/KR20050098338A/en
Application granted granted Critical
Publication of KR100569703B1 publication Critical patent/KR100569703B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them

Abstract

본 발명은 비개착공법이 요구되는 지중에 구조물을 축조하는 비개착 강관루프 공법에 적용되는 강관의 구조, 및 그를 적용한 강관루프 구조체에 관한 것이다. 강관의 외부 일측면에 상하 2개의 제1플랜지가 부착되고 타측면에는 타강관의 제1플랜지와 대응 연결되는 제2플랜지가 상하로 부착되고, 강관의 일측부 중앙부에는 걸쇠 고리가 형성되고, 타측 중앙부에는 타강관의 걸쇠고리와 연결되는 T자형 플랜지가 형성되고, 상기 강관의 양측면에 인접한 강관을 서로 결합하는 정착철물을 관통설치하기 위한 다수의 관통공이 형성된다. 플랜지의 끝단은 일자형으로 형성되고 플랜지끼리 상호 겹치거나 맞대기 형식으로 구성된다. 관통공을 관통한 정착철물은 인접한 강관에 형성된 정착철물 관통공을 관통하여 설치된다. 이후 강관의 내부 및 인접한 강관의 상하플랜지에 의해 형성되는 폐합공간에 몰탈이나 콘크리트를 충전한다. 이로써, 견고한 횡방향 강성으로 인해 별도의 횡방향 지지보의 설치없이 가설기둥만 설치하여 내부의 토공 작업이 가능하므로, 가설루프의 규모가 줄어들고 시공공정도 단순하게 된다. 토공작업시 루프구조체내에서 구분굴착을 실시하여 시공중 터널의 안전성을 확보하고, 구조물이 설치될 부위만을 선택적으로 굴착하여 구조물을 설치한 후 상부하중을 지탱하고 있는 잔여부에 대한 토공작업이 이루어지므로 시공 중에 지반변위억제와 안정성확보 뿐만 아니라 공기단축 및 시공비절감을 이룬다.The present invention relates to a structure of a steel pipe applied to an unattached steel pipe loop method for constructing a structure in a ground where a non-opening method is required, and a steel pipe loop structure to which the same is applied. Two first flanges are attached to one outer side of the steel pipe, and a second flange corresponding to the first flange of the other steel pipe is attached to the other side up and down, and a latch ring is formed at the central portion of one side of the steel pipe. The central portion is formed with a T-shaped flange connected to the clasp of the other steel pipe, and a plurality of through holes for penetrating the fixing hardware for coupling the steel pipe adjacent to both sides of the steel pipe to each other is formed. The ends of the flanges are formed in a straight line, and the flanges overlap each other or are butt-shaped. The fixing steel penetrating the through hole is installed through the fixing steel through hole formed in the adjacent steel pipe. After that, the mortar or concrete is filled in the closed space formed by the upper and lower flanges of the inner and adjacent steel pipes. Thus, due to the rigid lateral stiffness can be installed in the earthwork by installing only the temporary pillar without the installation of a separate lateral support beam, the size of the temporary roof is reduced and the construction process is simplified. During earthwork, segregation excavation is carried out in the roof structure to secure the safety of the tunnel during construction, and the excavation is carried out selectively to the site where the structure is to be installed. Therefore, it prevents ground displacement and ensures stability during construction, as well as shortens the air and reduces construction costs.

Description

지중 구조물을 축조하는 강관루프 공법에 적용되는 강관의 구조 및 그를 적용한 강관루프 구조체 및 그 강관루프공법{Structure of steel pipe applied to steel pipe roof construction method for building underground structure, and steel pipe roof structure therefor using the same, and steel roof construction method thereof}Structure of steel pipe applied to steel pipe roof construction method for building underground structure, and steel pipe roof structure therefor using the same, and steel roof construction method

본 발명은 기존 도로 및 철도 하부를 횡단해서 하수암거나 지하차도, 터널구조물 등을 설치해야 하는 경우 공사에 따른 지장물의 이전이 곤란하거나, 지장물 저촉, 차량 소통의 장애 등으로 개착이 불가능하여 비개착공법이 요구될 경우 지중에 구조물을 축조하는 강관루프공법에 적용되는 강관의 구조, 및 그를 적용한 강관루프구조체, 및 그 강관루프공법에 관한 것이다.The present invention is difficult to transfer obstacles due to construction when the sewage rock, underground roadway, tunnel structure, etc. must be installed across the existing roads and railways, or it is impossible to fix them due to obstacles, obstacles in vehicle communication, etc. The present invention relates to a structure of a steel pipe applied to a steel pipe loop method for constructing a structure in the ground, a steel pipe loop structure applied thereto, and a steel pipe loop method.

보다 상세하게는, 본 발명은 루프를 형성하는 강관과 강관의 측면연결부가 구조적 연속성을 확보할 수 있도록 각 강관의 외측부 상하단에 플랜지 및 외측중앙부에 걸쇠연결부를 구비하고 강관 외측면에 정착철물 관통설치용 관통공을 형성한 강관, 및 그 강관을 지중에 압입한 후 서로 연결시켜 강관의 내부를 통해 정착철물을 설치하여 형성되는 강관루프 구조체, 및 그 강관루프공법에 관한 것이다. 이렇게 축조된 루프 구조체의 견고한 횡방향 강성으로 인해 별도의 횡방향 지지보의 설치없이 가설기둥만 설치하여 내부의 토공 작업이 가능하도록 하여 강관루프공법을 적용할 때, 가설루프의 규모가 줄어들고 시공 공정도 단순하게 되는 효과가 있다.In more detail, the present invention is provided with a clasp connection at the upper and lower ends of the outer side of each steel pipe and the central portion of the outer side of each steel pipe to secure structural continuity to ensure the structural continuity of the steel pipe forming the loop and for fixing the installation through the steel pipe outer surface It relates to a steel pipe having a through-hole, and a steel pipe loop structure formed by installing the fixing iron through the inside of the steel pipe by pressing the steel pipe in the ground and connected to each other, and the steel pipe loop method. Due to the strong lateral stiffness of the constructed roof structure, the temporary roof can be installed by installing only temporary columns without installing additional lateral support beams. There is also the effect of being simplified.

일반적으로, 지중에 구조물을 축조하는 방식으로 개착 및 비개착에 의한 구조물 축조방식이 있다. 기존 도로 및 철도 하부를 횡단해서 하수암거나 지하차도, 터널구조물 등을 설치해야하는 경우 공사에 따른 지장물의 이전이 곤란하거나, 지장물 저촉, 차량 소통의 장애 등으로 개착이 불가능하여 비개착공법이 요구되는데, 비개착에 의한 구조물 축조공법에는 횡단하는 도로나 지장물의 양측으로 작업구 개념의 전진기지와 도달기지가 필수적이며, 대표적인 비개착식 지중구조물 축조공법으로는 함체견인공법과 강관루프공법 등을 들 수 있다.In general, there is a structure construction method by the attachment and non-attachment in a way to build the structure in the ground. If it is necessary to install sewage rocks, underground roadways, tunnel structures, etc. across existing roads and railways, it is difficult to transfer obstacles due to construction, or it is impossible to fix them due to obstacles and obstacles in vehicle communication. In the non-adhesive structure construction method, the forward base and the reaching base of the concept of the work tool are essential to both sides of the crossing road or obstacle, and the typical non-adhesive underground structure construction method includes the hamp dog artificial method and the steel pipe loop method. Can be mentioned.

함체견인공법은 함체가 통과할 지중에 미리 600mm내외의 함체지지용 가설용 강관을 전진기지에서 도달기지 방향으로 수평으로 압입 관통시킨 후 견인할 함체의 반대 측 도달기지로부터 지중을 횡단하여 이어진 다수의 P.C.강선을 현장에서 제작된 함체와 결속한 후, 견인하여 함체내의 내부토사를 제거하고, 이와 같은 견인과 굴착작업을 반복하여 지중에 구조물을 설치하는 공법이다. 이 공법은 함체추진시 함체의 추진하중이나 추진함체와 이미 지중에 설치된 가설강관과의 틈에 의해 함체 상부의 도로나 지장물에 침하가 발생할 우려가 있으며, 또한 함체가 미리 제작되어 견인 설치되므로 함체의 규모가 커지게 되면 견인에 제약이 따르게 되고 작업장의 규모가 큰 편이므로 심도가 깊은 지하공간에서의 작업이 곤란하다. 그리고 함체간의 연결부의 처리가 미흡하게 되면 누수 등이 발생할 우려가 있다. 이러한 함체견인공법의 단점 등에 의하여 비개착식 지중구조물 축조공법으로는 강관루프 공법이 많이 적용되는 편이다.The ship prosthesis method is to press-through a steel pipe for supporting the housing about 600mm in advance from the forward base to the reach base in the ground through which the ship will pass, and then cross the ground from the reach base on the opposite side of the ship to be towed. After binding the PC steel wire to the manufactured enclosure on the site, it is towed to remove the internal soil in the enclosure and to repeat the towing and excavation work to install the structure in the ground. In this method, the propulsion load of the enclosure or the gap between the propulsion vessel and the temporary steel pipe installed in the ground may cause settlement on the road or obstacles on the upper part of the enclosure. If the size of the larger the traction constraints and the larger size of the workplace is difficult to work in deep underground space. If the connection between the enclosures is insufficient, leakage may occur. Due to the drawbacks of such hull prosthesis method, steel pipe loop method is often applied as a non-removable underground structure construction method.

본 발명의 강관은 주로 비개착 방식의 루프 공법에 적용되는 것이므로, 기존의 비개착 강관루프 공법 및 강관루프 구조체에 대한 예를 설명함으로써 발명의 이해를 도모할 것이다.Since the steel pipe of the present invention is mainly applied to the loop method of the non-adhesive method, the present invention will be understood by explaining examples of the existing non-adhesive steel pipe loop method and the steel pipe loop structure.

이하 종래의 강관루프 공법 및 강관루프 구조체에 대하여 도 1 내지 도 5를 참조하여 설명하기로 한다. 종래의 강관루프 공법은 구조물이 형성될 지중에 미리 강관(1)을 순차적으로 압입 연결하여, 강관 루프를 형성하고, 강관 루프의 안쪽의 내부 토사를 전부 제거하고 구조물을 축조하게 되는데, 도 1에 도시된 바와 같이 굴착 시 발생하는 상부나 측면하중은 횡방향 지지보(4) 및 가설기둥(5)등의 가설재로 지지된다. Hereinafter, a conventional steel pipe loop method and a steel pipe loop structure will be described with reference to FIGS. 1 to 5. In the conventional steel pipe loop method, the steel pipe 1 is sequentially press-connected to the ground where the structure is to be formed, thereby forming a steel pipe loop, removing all the internal soil inside the steel pipe loop, and constructing the structure. As shown, the upper or side loads generated during the excavation are supported by temporary materials such as transverse support beams 4 and temporary columns 5.

강관루프의 축조과정을 설명하면 다음과 같다. 먼저 전진기지에서 조성할 구체의 크기를 고려하여 구체 외곽 면에 600-800mm 정도의 가설용 강관(1)을 수평 압입하고 강관 내에 콘크리트를 타설하여, 강관 루프를 형성한다(도 2). 전진기지로부터 구조물이 축조될 루프내부를 굴착하게 되는데 굴착은 상부하중과 측압에 대한 안전성을 고려하여 상층의 루프 강관 부위로부터 하향으로 단계별로 굴착이 이루어지게 된다. 굴착은 1차로 강관 루프하면을 3m내외의 심도로 굴착하게 되는데 루프에 사용된 강관(1)과 강관(1)은 도 6에 도시한 바와 같이 단순한 고리형태(2, 3)로 연결되어 있으므로, 강관루프 하면과 측면에 강관과 직각방향으로 H형 강재로 횡방향 지지보(4)를 설치하고 다수의 가설기둥(5)으로 받쳐, 전 구간에 걸쳐 하중을 지지시켜야 한다(도 3). 다시 말하면 기존의 강관루프는 도 6에 도시한 바와 같이, 강관 측면 중앙부에 한 쌍의 ?? 자형 고리(2)와 T 자형 걸쇠(3)가 부착된 요철의 연결구조로 기 압입된 강관들을 상호 고리형태로 연결하여 시공함으로써 하중에 견디는 역할보다는 강관의 위치 이탈을 방지하기 위한 개념에 불과하다.The construction process of the steel pipe loop is as follows. First, in consideration of the size of the sphere to be formed at the forward base base horizontally indented steel pipe (1) of about 600-800mm to the outer surface of the sphere and cast concrete in the steel pipe, to form a steel pipe loop (Fig. 2). From the forward base, the excavation is performed inside the loop where the structure is to be constructed. Excavation is excavated step by step downward from the upper part of the roof steel pipe considering the safety of the upper load and the side pressure. Excavation is primarily to excavate the bottom of the steel pipe loop with a depth of about 3m. Since the steel pipe (1) and the steel pipe (1) used in the loop is connected in a simple ring form (2, 3), as shown in Figure 6, The horizontal support beam 4 is installed with H-shaped steel in the direction perpendicular to the steel pipe at the bottom and side of the steel pipe loop, and is supported by a plurality of temporary columns 5 to support the load over the entire section (FIG. 3). In other words, as shown in FIG. 6, a conventional steel pipe loop has a pair of ?? It is a concept to prevent the deviation of the steel pipe rather than the role of bearing the load by connecting the steel pipes pre-indented in the form of mutual rings by connecting the concave-convex structure with the female ring (2) and the T-shaped clasp (3). .

따라서 상기 강관루프의 연결부간에 횡방향 강성을 확보할 수 없는 단점이 있다. 이에 따라서 횡방향 지지보(4)와 보다 많은 갯수의 가설기둥(5)이 설치되어야 하며, 지지보(4)만큼 이격되어 구조물이 설치되어야 하므로 가시설의 규모가 커지는 문제점이 있다. 이후 2차, 3차로 굴진하면서 이미 설치된 가설기둥(5)을 조심스럽게 하향으로 연장하여(5', 5") 구조물의 설치심도까지 내부의 토사 굴착을 완료한 후(도 4 및 도 5) 최종으로 상부슬래브(60), 벽체(65), 및 하부슬래브(80) 등을 위한 철근과 거푸집을 설치하고 콘크리트를 타설하여 도 5에 도시한 바와 같이 지중축조물의 구조체를 완성한다. 이렇게 축조되는 종래의 강관루프 공법은 이미 설치된 가설기둥을 굴착한 후, 설치심도까지 하향으로 연장 설치해야 하는 문제점으로 인해 시공 중 침하의 우려가 높고, 기존에 설치된 가설재(4, 5)와의 저촉문제로 공사 속도가 늦어진다.Therefore, there is a disadvantage that it is not possible to secure the lateral rigidity between the connecting portion of the steel pipe loop. Accordingly, the lateral support beam 4 and a larger number of temporary columns 5 should be installed, and the structure should be installed so as to be spaced apart by the support beam 4, thereby increasing the size of the temporary installation. After the 2nd and 3rd excavation, the installation pillars (5), which have already been installed, are carefully extended downward (5 ', 5 ") to complete the excavation of the earth and sand until the installation depth of the structure (FIGS. 4 and 5). By installing reinforcing bars and formwork for the upper slab 60, the wall 65, and the lower slab 80, and placing the concrete to complete the structure of the underground construction as shown in Figure 5. The steel pipe loop method has a high possibility of subsidence during construction due to the problem of digging the already installed temporary columns and extending them downward to the installation depth, and the speed of construction due to problems with existing installed temporary materials (4, 5). Late.

본 발명이 이루고자 하는 기술적 과제는 인접한 강관을 측부 상하의 플랜지 및 측부중앙부의 걸쇠연결부로 연결하고 횡방향의 인장력을 감당하게 되는 정착철물을 설치하고, 강관내부 및 상하 플랜지에 의해 형성되는 폐합공간에 몰탈 또는 콘크리트 타설토록 함으로써, 횡방향지지력을 확보하게 하는 강관구조를 제공함을 목적으로 한다.The technical problem to be achieved by the present invention is to connect the adjacent steel pipe to the upper and lower flanges and the clasp connection of the central portion of the side and to install a fixing hardware to bear the tension in the transverse direction, mortar in the closed space formed by the inner and upper flanges of the steel pipe Or it is intended to provide a steel pipe structure to ensure the lateral bearing capacity by placing concrete.

본 발명이 이루고자 하는 다른 기술적 과제는 횡방향 지지력을 향상시킨 강관루프를 이용한 지중 축조물 공사 시에 지중 축조물 공사의 규모나 심도에 관계없이 별도의 횡방향 지지보의 설치없이 가설 기둥만 설치하여 시공 가능하게 하여, 가설루프의 규모가 줄어들고 시공 공정도 단순하고 용이하게 될 수 있도록 하는 강관루프 구조체, 및 그를 이용한 강관루프공법을 제공함을 목적으로 한다.Another technical problem to be achieved by the present invention is to install by installing only the temporary pillars without the installation of a transverse support beam regardless of the scale or depth of construction of the underground construction work when constructing underground construction using a steel pipe loop with improved lateral bearing capacity It is an object of the present invention to provide a steel pipe loop structure, and a steel pipe loop method using the same, so that the scale of the temporary loop can be reduced and the construction process can be simple and easy.

본 발명은 상기 다른 기술적 과제를 달성하기 위하여, 지중에 구조물을 축조하는 강관루프 공법에 적용되는 강관에 있어서, 횡단할 도로나 지장물의 양측에 작업구를 설치한 후 설치될 구조물의 외곽선에 맞추어 순차적으로 압입 설치되는, 외부 일측면에 상하 2개의 제1플랜지가 부착되고 타측면에는 타강관의 제1플랜지와 대응 연결되는 제2플랜지가 상하로 부착되고, 강관의 일측부 중앙부에는 강관 압입시 이탈을 방지하기 위한 걸쇠 고리가 형성되고, 타측 중앙부에는 타강관의 걸쇠고리와 연결되는 걸쇠플랜지가 형성되고, 상기 강관의 양측면에 인접한 강관을 서로 결합하는 정착철물을 관통설치하기 위한 관통공이 다수개 형성되는 강관을 제공한다.The present invention, in order to achieve the above another technical problem, in the steel pipe applied to the steel pipe loop method for constructing the structure in the ground, sequentially installed in accordance with the outline of the structure to be installed after installing work tools on both sides of the road or obstacle to be traversed Up and down two first flanges are attached to the outer one side, which is press-fitted to the second side, and a second flange corresponding to the first flange of the other steel pipe is attached to the other side up and down, and at the central part of one side of the steel pipe when the steel pipe is press-fitted A clasp ring is formed to prevent the hook, and a clasp flange connected to the clasp of the other steel pipe is formed at the other central portion, and a plurality of through holes are formed to penetrate the fixing hardware for joining the steel pipes adjacent to both sides of the steel pipe to each other. To provide steel pipes.

바람직하기로는 상기 제1 및 제2 플랜지의 끝단은 일자형으로 형성되고 인접한 강관의 플랜지끼리 상호 겹치거나 맞대기 형식으로 결합하여 폐합공간을 형성함을 특징으로 한다.Preferably, the ends of the first and second flanges are formed in a straight shape, and the flanges of adjacent steel pipes are formed to overlap each other or combine in a butt shape to form a closed space.

본 발명은 상기 다른 기술적 과제를 달성하기 위하여, 지중에 구조물을 축조하는 강관루프 공법에 적용되는 강관루프 구조체에 있어서, 횡단할 도로나 지장물의 양측에 작업구를 설치한 후 외부 일측면에 상하 2개의 제1플랜지가 부착되고 타측면에는 타강관의 제1플랜지와 대응 연결되는 제2플랜지가 상하로 부착되고, 강관의 일측부 중앙부에는 걸쇠 고리가 형성되고, 타측 중앙부에는 타강관의 걸쇠고리와 연결되는 걸쇠플랜지가 형성되고, 상기 강관의 양측면에 인접한 강관을 서로 결합하는 정착철물을 관통설치하기 위한 관통공이 다수개 형성되는 강관을 준비하여, 설치될 구조물의 외곽선에 맞추어 순차적으로 압입 설치할 때, 상기 강관을 지중에 오거로 굴착을 병행하면서 한 강관의 걸쇠고리가 타강관의 걸쇠플랜지와 고리결합되고, 한 강관의 제1 플랜지가 타강관의 제2플랜지에 겹치거나 맞대기 형식으로 결합하여, 순차적으로 압입 설치하고, 정착철물 관통공을 통해 정착철물을 관통삽입하여 강관들을 연결시킨 후, 상기 강관내부 및 상기 플랜지에 의해 형성된 폐합공간에 콘크리트를 타설함으로써 이루어지는 강관루프 구조체를 제공한다.The present invention, in order to achieve the above another technical problem, in the steel pipe loop structure applied to the steel pipe loop method for constructing the structure in the ground, after installing work tools on both sides of the road or obstacle to be traversed, the upper and lower sides 2 Two first flanges are attached to the other side and a second flange corresponding to the first flange of the other steel pipe is attached up and down, and a clasp ring is formed at the central portion of one side of the steel pipe, and the clasp of the other steel pipe is formed at the other central portion. When the clasp flange is connected and the steel pipes are formed to have a plurality of through-holes for the installation of the fixing steel coupling the steel pipes adjacent to both sides of the steel pipe to each other, and sequentially press-fit installation in accordance with the outline of the structure to be installed, The steel pipe clasp is looped with the clasp flange of the other steel pipe while drilling the steel pipe into the auger in the ground. The first flange is overlapped with the second flange of the other steel pipe or coupled in a butt type, and then press-installed in sequence, and the steel pipes are connected by inserting the fixing hardware through the fixing steel through-hole, and then to the inside of the steel pipe and the flange It provides a steel pipe loop structure made by pouring concrete into the closed space formed by the.

본 발명은 상술한 기술적 과제를 달성하기 위하여, 지중에 구조물을 축조하기 위한 강관루프 공법에 있어서, 토공작업의 시공 전에 구조물의 안전성을 확보하기 위하여, 먼저 지중구조물의 크기에 맞추어 측부 상하 연결 플랜지와 중앙 걸쇠 연결부를 부착한 강관을 준비하여, 상호 인접한 상하플랜지의 유간을 맞추고, 강관끼리의 걸쇠 연결부를 연결하여 센터위치를 맞춘 채 압입하고, 상호 인접 강관의 상하 플랜지를 연결하여 폐합공간을 형성하고, 강관에 형성한 정착철물 설치용 관통공을 통하여 강관 내측으로부터 관통한 정착철물을 이용하여 인접 강관들을 연결하고, 상기 강관내부 및 강관 연결 플랜지에 의해 형성된 폐합공간에 몰탈이나 콘크리트를 타설하여 강관루프구조체를 형성하는 단계; 굴착을 통해 장비통로를 확보하는 단계; 장비통로를 확보한 후 횡방향지지보를 설치하지 않고 필요시 가설기둥만을 설치하는 단계; 필요시 가설용 파일을 설치하고 다음 굴착부위인 벽체와 기둥부에 장비를 투입하여 다음 굴착을 실시하는 단계; 및 상부 슬라브 및 좌우 벽체 기둥 등 구조물을 축조한 후 최종적으로 마지막 토공작업을 실시한 후 바닥슬라브를 축조하는 단계를 포함하는 강관루프공법을 제공한다.The present invention, in order to achieve the above technical problem, in the steel pipe loop method for constructing the structure in the ground, in order to ensure the safety of the structure before the construction of earthwork, first, in accordance with the size of the underground structure, Prepare a steel pipe with a central clasp connection, align the clearances of the upper and lower flanges adjacent to each other, connect the clasp connections between the steel pipes, press-fit and adjust the center position, and connect the upper and lower flanges of adjacent steel pipes to form a closed space. The steel pipe loop structure is formed by connecting adjacent steel pipes by using the fixing steel penetrated from the inside of the steel pipe through the fixing hole formed in the steel pipe, and pouring mortar or concrete into the closed space formed by the steel pipe connection flange. Forming a; Securing an equipment path through excavation; Installing only temporary pillars if necessary without securing the transverse support after securing the equipment passage; Installing the temporary piles if necessary and putting the equipment into the walls and the pillars, which are the next excavation sites, to perform the next excavation; And constructing a bottom slab after constructing a structure such as an upper slab and left and right wall pillars and finally performing a final earthwork.

이하 본 발명의 실시예에서는 비개착 강관루프 공법에 적용되는 강관구조 및 그를 적용한 강관루프 구조체, 및 그를 적용한 강관루프공법의 바람직한 실시예의 구성 및 작용을 상세히 설명하기로 한다. 그러나, 본 발명이 이에 반드시 제한되는 것은 아니고, 당업자에게 많은 변형 및 수정이 가능하다.In the following embodiments of the present invention will be described in detail the configuration and operation of the steel pipe structure applied to the non-adhesive steel pipe loop method and the steel pipe loop structure applied thereto, and the preferred embodiment of the steel pipe loop method applied thereto. However, the present invention is not necessarily limited thereto, and many modifications and variations are possible to those skilled in the art.

본 발명에서는 도 7 및 도 8을 참조하여 보다 상세히 설명한다.In the present invention will be described in more detail with reference to FIGS.

도 7은 본 발명의 제1 실시예에 따른 강관의 구조 및 강관의 연결관계를 도시한 것이다. 도 7의 상세 단면도에서, 강관의 양측부에 상하 플랜지가 부착되어 인접한 강관의 플랜지끼리 상호 맞대기 형식으로 결합되고, 중앙부 양측에 걸쇠고리 및 T자형 플랜지가 부착되어 인접한 강관끼리 상호 고리결합되어 강관 상호간의 일정위치를 확보하게 되고, 또한 다수의 정착철물 설치용 관통공이 형성되어 인접한 강관이 상호 관통결합됨을 도시하는 강관의 상호 연결관계가 도시되어 있다.7 illustrates a structure of a steel pipe and a connection relationship between steel pipes according to a first embodiment of the present invention. In the detailed cross-sectional view of Figure 7, the upper and lower flanges are attached to both sides of the steel pipe, the flanges of adjacent steel pipes are coupled to each other in the form of a butt, the clasp and T-shaped flanges are attached to both sides of the central portion and the adjacent steel pipes are mutually coupled to each other and the steel pipes mutually The interconnection relationship of the steel pipes is shown to secure a predetermined position of the steel pipe, and also show that a plurality of through-holes for fixing fixtures are formed so that adjacent steel pipes are mutually coupled.

도 7에 도시된 바와 같이, 강관(10)의 외부 일 측면에 제1 플랜지(12)가 상하로 부착되고 타 측면에는 인접한 강관의 제1 플랜지(12)와 맞대기 형식으로 연결되어 폐합공간(150)을 형성하는 제2 플랜지(100)가 상하로 부착되어 있다. 상기 제1 및 제2 플랜지(12, 100)의 끝단은 일자형으로 압입하기 좋은 구조로 형성된다. 그러나, 반드시 플랜지의 끝단이 일자형이어여 하는 것은 아니며, 압입하기 좋은 구조이면, ??자이던 ??자이던 관계없다. 또한, 강관의 일측부 중앙부에는 걸쇠 고리(20)가 형성되고, 타측 중앙부에는 타강관의 걸쇠고리(20)와 연결되는 T자형 플랜지(22)가 형성되고, 상기 강관(10)의 양측면의 상하부에는 인접한 강관을 서로 결합하는 정착철물(130)을 관통설치하기 위한 관통공(135)이 다수개 형성된다. 상기 관통공은 강관의 양측부의 상하에 구비될 수 있으나, 일측 또는 일부에만 구비될 수도 있다. 도시된 바와 같이, 정착철물(130)은 일단이 한 강관의 관통공(135) 관통한 후 다른 강관의 관통공(135)을 통과한 후 나사와 결합되는 구조로 되는 것이 바람직하나, 양단이 볼트헤드 구조 또는 나사구조로 이루어지는 대신에 볼트머리없는 구조이거나, 나사결합되지 않고 적어도 일측이 머리없는 텐션볼트형태의 정착철물이 관통공(135)에 관통결합되는 구조로 일어질 수도 있다.As shown in FIG. 7, the first flange 12 is vertically attached to one outer side of the steel pipe 10, and the other side of the steel pipe 10 is connected to the first flange 12 of the adjacent steel pipe in a butt type to close the closed space 150. The 2nd flange 100 which forms) is attached up and down. Ends of the first and second flanges 12 and 100 are formed to have a straight line indentation. However, the end of the flange does not necessarily have to be straight, and as long as the structure is easy to press in, it does not matter whether it is ?? or ??. In addition, the clasp ring 20 is formed in the central portion of one side of the steel pipe, the T-shaped flange 22 connected to the clasp 20 of the other steel pipe is formed in the other central portion, the upper and lower parts of both sides of the steel pipe 10 There are formed a plurality of through-holes 135 for penetrating the fixing hardware 130 for coupling adjacent steel pipes to each other. The through hole may be provided above and below both sides of the steel pipe, but may be provided only on one side or a part thereof. As shown, the fixing hardware 130 is one end of the through-hole 135 of one steel pipe after passing through the through-hole 135 of the other steel pipe is preferably a structure that is coupled to the screw, both ends of the bolt Instead of a head structure or a screw structure, a bolt headless structure may be formed, or a screw may be screwed and at least one side of a headless tension bolt type fixing hardware may be formed to be penetrated through the through hole 135.

한편, 강관(10)의 내부(15) 및 인접한 강관의 제1 및 제2 플랜지(12, 100)의 맞대기 이음에 의해 형성된 폐합공간(150)에 몰탈이나 콘크리트를 충전함으로써 상부 토사 하중을 보다 잘 지탱할 수 있는 일체화된 횡방향 연속 가설 루프구조체를 형성할 수 있도록 한다. On the other hand, by filling the mortar or concrete in the closed space 150 formed by the butt joint of the inner 15 of the steel pipe 10 and the first and second flanges 12, 100 of the adjacent steel pipe, the upper soil load is better It is possible to form an integral transverse continuous hypothesis loop structure that can be supported.

또한, 강관(10)의 중앙부에 부착된 T자형 플랜지(22)가 인접강관의 중앙부에 부착된 걸쇠 고리(20)에 걸리게 되어 강관의 압압시 압입에 따른 시공 중의 위치 이탈을 방지하게 된다. 여기서, 걸쇠 고리 및 T자형 플랜지는 걸쇠연결부를 형성하는데, T자형 플랜지는 반드시 T자형일 필요는 없으며, 일자형, ??자형 등 걸쇠고리에 걸리는 구조이면 관계없을 것이다.In addition, the T-shaped flange 22 attached to the central portion of the steel pipe 10 is caught by the latch ring 20 attached to the central portion of the adjacent steel pipe to prevent the positional deviation during construction due to the press-fitting of the steel pipe. Here, the clasp ring and the T-shape flange forms a clasp connection, the T-shaped flange does not necessarily have to be a T-shape, it does not matter if the structure is caught in a clasp, such as a straight, ??.

도 8은 본 발명의 제2 실시예에 따른 강관의 구조 및 강관의 연결관계를 도시한 것이다. 도 8의 상세 단면도에서, 강관의 양측부에 상하 플랜지가 부착되어 인접한 강관의 플랜지끼리 상호 겹치기 형식으로 결합되고, 중앙부 양측에 걸쇠고리 및 T자형 플랜지가 부착되어 인접한 강관끼리 상호 고리결합되고 다수의 정착철물 설치용 관통공이 형성되어 인접한 강관이 상호 관통결합됨을 도시하는 강관의 상호 연결관계가 도시되어 있다.8 illustrates a structure of a steel pipe and a connection relationship between steel pipes according to a second embodiment of the present invention. In the detailed cross-sectional view of Figure 8, the upper and lower flanges are attached to both sides of the steel pipe, the flanges of adjacent steel pipes are coupled to each other in the form of overlapping, the clasp and T-shaped flanges are attached to both sides of the central portion and adjacent steel pipes are mutually interlinked and a plurality of The interconnection relationship of the steel pipes is shown, which shows that the through-holes for installing the fixing steel are formed so that adjacent steel pipes are mutually connected.

도 8에 도시된 바와 같이, 강관(10)의 외부 일 측면에 제1 플랜지(12)가 상하로 부착되고 타 측면에는 인접한 강관의 제1 플랜지(12)와 겹치기 형식으로 연결되어 폐합공간(150)을 형성하는 제2 플랜지(100)가 상하로 부착되어 있다. 상기 제1 및 제2 플랜지(12, 100)의 끝단은 일자형으로 압입하기 좋은 구조로 형성된다. 그러나, 반드시 플랜지의 끝단이 일자형이어여 하는 것은 아니며, 압입하기 좋은 구조이면, ??자이던 ??자이던 관계없다. 또한, 강관의 일측부 중앙부에는 걸쇠 고리(20)가 형성되고, 타측 중앙부에는 타강관의 걸쇠고리(20)와 연결되는 T자형 플랜지(22)가 형성되고, 상기 강관(10)의 양측면에는 인접한 강관을 서로 결합하는 정착철물(130)을 관통설치하기 위한 관통공(135)이 다수개 형성된다. 상기 관통공은 강관의 양측부의 상하에 구비될 수 있으나, 일측 또는 일부에만 구비될 수도 있다. 여기에서도 마찬가지로, 도시된 바와 같이, 정착철물(130)은 일단이 한 강관의 관통공(135) 관통한 후 다른 강관의 관통공(135)을 통과한 후 나사와 결합되는 구조로 되는 것이 바람직하나, 양단이 볼트헤드 구조 또는 나사구조로 이루어지는 대신에 볼트머리없는 구조이거나, 나사결합되지 않고 적어도 일측이 머리없는 텐션볼트형태의 정착철물이 관통공(135)에 관통결합되는 구조로 일어질 수도 있다.As shown in FIG. 8, the first flange 12 is vertically attached to an outer side of the steel pipe 10, and the other side is connected to the first flange 12 of the adjacent steel pipe in an overlapping manner to form a closed space 150. The 2nd flange 100 which forms) is attached up and down. Ends of the first and second flanges 12 and 100 are formed to have a straight line indentation. However, the end of the flange does not necessarily have to be straight, and as long as the structure is easy to press in, it does not matter whether it is ?? or ??. In addition, a clasp ring 20 is formed at one central portion of the steel pipe, a T-shaped flange 22 connected to the clasp 20 of the other steel pipe is formed at the other central portion, adjacent to both sides of the steel pipe 10 A plurality of through-holes 135 for penetrating the fixing hardware 130 for coupling the steel pipes to each other is formed. The through hole may be provided above and below both sides of the steel pipe, but may be provided only on one side or a part thereof. Here as well, as shown, the fixing hardware 130 is one end of the through-hole 135 of one steel pipe after passing through the through-hole 135 of the other steel pipe is preferably a structure that is coupled to the screw Instead of the bolt head structure or the screw structure, both ends may be formed without a bolt head, or may have a structure in which a fixing bolt of a headless tension bolt type is not screwed and at least one side is penetrated through the through hole 135. .

물론 강관(10)의 내부(15) 및 인접한 강관의 제1 및 제2 플랜지(12, 100)의 겹치기 형식의 결합에 의해 형성된 폐합공간(150)에 몰탈이나 콘크리트를 충전함으로써 상부 토사 하중을 보다 잘 지탱할 수 있는 일체화된 횡방향 연속 가설 루프구조체를 형성할 수 있도록 한다. 여기에서도, 강관(10)의 중앙부에 부착된 T자형 플랜지(22)가 인접강관의 중앙부에 부착된 걸쇠고리(20)에 걸리게 되어 강관의 압압시 압입에 따른 시공 중의 위치 이탈을 방지하게 된다. 여기서, 걸쇠고리 및 T자형 플랜지는 걸쇠연결부를 형성하는데, T자형 플랜지는 반드시 T자형일 필요는 없으며, 일자형, ??자형 등 걸쇠고리에 걸리는 구조이면 관계없을 것이다.Of course, by filling mortar or concrete in the closed space 150 formed by the combination of the overlapping form of the inner 15 of the steel pipe 10 and the first and second flanges 12 and 100 of the adjacent steel pipe, the upper soil load is increased. It is possible to form an integrated transverse continuous hypothesis loop structure that can be well supported. Here, the T-shaped flange 22 attached to the central portion of the steel pipe 10 is caught by the clasp ring 20 attached to the central portion of the adjacent steel pipe to prevent the positional deviation during construction due to the press-fitting of the steel pipe. Here, the clasp and the T-shaped flange forms a clasp connection, the T-shaped flange does not necessarily have to be a T-shaped, it will not matter if the structure is caught in the clasp, such as straight, ??.

상술한 본 발명의 제1 및 제2 실시예에서와 같이, 본 발명에서 횡방향의 인장력을 지탱하는 개념은 주로 플랜지결합 및 걸쇠연결을 통하여 이루어지는 것은 아니라, 강관 설치 후 강관의 내부에서 측벽에 일정한 간격으로 설치된 정착철물 설치 관통공(135)을 통해 인접한 강관을 텐션볼트와 같은 정착철물(130)을 관통결합하여 강관을 상호 결합함으로써 대부분 이루어진다. 또한, 이렇게 연속강관의 설치를 완료한 후 강관의 내부(15) 및 인접강관의 플랜지들(12, 100)에 의해 형성된 폐합공간(150)에 몰탈이나 콘크리트를 충전하게 되면 강관루프구조체는 보다 큰 횡방향 강성을 갖는 구조가 되어 기존의 도 1에서와 같은 강관루프공법에서의 루프 밑에 설치하는 횡방향지지보(4)가 불필요하게 된다.As in the first and second embodiments of the present invention described above, the concept of sustaining the lateral tension in the present invention is not primarily made through flange coupling and shackle connection, but is fixed to the side wall in the interior of the steel pipe after the steel pipe is installed. Through the fixing steel installation through-holes 135 installed at intervals adjacent to the steel pipe through the fixing hardware 130, such as tension bolts are made by combining the steel pipes to each other. In addition, after completing the installation of the continuous steel pipe is filled with the mortar or concrete in the closed space 150 formed by the flanges (12, 100) of the inner pipe 15 and the adjacent steel pipe of the steel pipe loop structure is larger It becomes a structure with lateral rigidity, and the lateral support 4 installed below the loop in the steel pipe loop method as shown in FIG. 1 becomes unnecessary.

이하, 상술한 본 발명의 강관의 구조를 토대로 이루어지는 본 발명에 의한 강관루프 구조체에 대해서 첨부된 도 9를 참조하여 설명하기로 한다.Hereinafter, a steel pipe loop structure according to the present invention based on the structure of the steel pipe of the present invention described above will be described with reference to FIG. 9.

도 9에 도시한 바와 같이, 지중에 구조물을 축조하는 강관루프 공법에 적용되는 강관루프 구조체는 도 7 또는 도 8에 도시한 강관을 적용하여 구축되는 것으로, 우선 외부 일측면에 상하 2개의 제1플랜지(12)가 부착되고 타측면에는 타강관의 제1플랜지와 대응 연결되는 제2플랜지(100)가 상하로 부착되고, 강관의 일측부 중앙부에는 걸쇠 고리(20)가 형성되고, 타측 중앙부에는 타강관의 걸쇠고리(20)와 연결되는 T자형 플랜지(22)가 형성되고, 상기 강관의 양측면에 인접한 강관을 서로 결합하는 정착철물(130)을 관통설치하기 위한 관통공(135)이 다수개 형성되는 강관(10)을 준비하여, 그 후 횡단할 도로나 지장물의 양측에 작업구를 설치한 후 설치될 구조물의 외곽선에 맞추어 순차적으로 압입 설치함으로써 이루어진다. 이 때, 상기 강관을 지중에 오거로 굴착을 병행하면서 한 강관의 걸쇠고리(20)가 타강관의 T자형 플랜지(22)와 고리결합되어 상호 이탈을 방지하면서 센터를 맞추고, 또한 한 강관의 제1 플랜지(12)가 타강관의 제2플랜지(100)에 겹치거나 맞대기 형식으로 연결 고정하여, 순차적으로 압입 설치한 후, 정착철물 관통공(135)을 통해 정착철물(130)을 관통삽입하여 강관들을 연결시킨다. 그 다음, 상기 강관내부(15) 및 상기 플랜지들(12, 100)에 의해 형성된 폐합공간(150)에 콘크리트를 타설함으로써 이루어지는 강관루프 구조체를 구축한다.As shown in FIG. 9, the steel pipe loop structure applied to the steel pipe loop method for constructing a structure in the ground is constructed by applying the steel pipe shown in FIG. 7 or 8. The flange 12 is attached to the other side and the second flange 100 corresponding to the first flange of the other steel pipe is attached up and down, one side central portion of the steel pipe has a latch ring 20 is formed, the other side T-shaped flange 22 is connected to the clasp 20 of the other steel pipe is formed, a plurality of through-holes 135 for penetrating the fixing hardware 130 for joining the steel pipe adjacent to both sides of the steel pipe to each other After preparing the steel pipe 10 to be formed, and then install the work tool on both sides of the road or obstacle to be traversed is made by sequentially pressing in accordance with the outline of the structure to be installed. At this time, the steel pipe clasp ring 20 is coupled to the T-shaped flange 22 of the other steel pipe while the excavation to the auger in the ground at the same time to align the center while preventing mutual separation, and further 1, the flange 12 is connected to the second flange 100 of the other steel pipe in a fixed or overlapping manner, and then press-installed sequentially, and then through the fixing hardware 130 through the fixing hardware through-hole 135 Connect the steel pipes. Next, a steel pipe loop structure is constructed by pouring concrete into the closed space 150 formed by the steel pipe inner portion 15 and the flanges 12 and 100.

도 9에 도시한 바와 같이, 본 발명의 비개착 강관루프 공법에 의한 축조된 구조물도 종래의 공법과 마찬가지로 강관루프 구조체하에 상하부 슬래브(60, 80) 및 벽부(65)를 두고 있다. 그러나, 강관루프 구조체에 상부 하중에 견디기 위하여 횡방향지지보(도 5의 4)를 두고 있지 않다. 그 이유는 강관루프 구조체에 적용되는 강관의 구조가 인접한 강관들을 연결하기 위하여 플랜지(12, 100), 걸쇠고리(20) 및 T자형 플랜지(22)에 의해 연결되고, 정착철물(130)이 관통공(135)을 관통하여 연결되고, 강관내부(15) 및 플랜지들(12, 100)에 의해 형성된 폐합공간(150)에 타설된 콘크리트에 의해 일체화되어 횡방향 내하력을 키웠기 때문이다.As shown in Fig. 9, the structure constructed by the non-adhesive steel pipe loop method of the present invention also has upper and lower slabs 60 and 80 and a wall portion 65 under the steel pipe loop structure as in the conventional method. However, the steel pipe loop structure is not provided with lateral support (4 in FIG. 5) to withstand the upper load. The reason is that the steel pipe structure applied to the steel pipe loop structure is connected by the flanges 12 and 100, the clasp 20 and the T-shaped flange 22 to connect the adjacent steel pipes, and the fixing steel 130 penetrates. This is because it is connected through the ball 135 and is integrated by concrete placed in the closed space 150 formed by the steel pipe inner portion 15 and the flanges 12 and 100 to increase the transverse load capacity.

이에 따라서 본 발명의 강관을 사용하여 루프구조체를 축조하는 경우, 횡방향 지지보(4)가 필요없게되어 횡방향지지보가 점유한 높이만큼 가설 강관루프의 규모도 줄어들게 되고, 가설강재도 수적으로 적게 사용된다. 또한 루프구조체내의 토공작업에 있어서는 1차 토공작업에 의해 확보된 통로를 이용하여 장비를 투입하여, 벽체와 기둥부에 선택적으로 흙막이 가설용 파일을 설치하고, 2차로 토사를 제거하고 벽체, 기둥, 상부슬라브 등 구조물을 축조한 후 3차로 상부하중을 지탱하고 있는 잔여부에 대한 토공작업을 수행하고 하부슬라브를 축조하므로, 기존 강관루프공법의 루프 내부의 토사를 전부 제거하는 과정에서 불가피하게 발생하는 지반침하 등이 발생치 않아 시공 중의 안정성 확보 뿐만 아니라 가시설의 규모가 축소되어 시공 공기 단축 및 시공비 절감을 이룰 수 있다. Accordingly, when the roof structure is constructed using the steel pipe of the present invention, the transverse support 4 is not necessary, so that the size of the temporary steel pipe loop is reduced by the height occupied by the transverse support, and the number of temporary steels is also small. Used. In the earthwork work in the roof structure, the equipment is input by using the passage secured by the first earthwork work, and the soil and piles are selectively installed on the walls and the pillars, and the soil is removed secondly, and the walls, columns, After constructing the structure such as the upper slab, earthwork is performed on the remaining part supporting the upper load in the third order and the lower slab is constructed. Therefore, inevitably occurring in the process of removing all the soil inside the loop of the existing steel pipe loop method Since there is no ground subsidence, it not only secures stability during construction but also reduces the size of temporary facilities, which can shorten construction air and reduce construction costs.

본 발명에서는 강관루프 구조체를 지중 구조물의 축조시 먼저 상술한 구조의 강관을 지중구조물의 작업구에서 압입하여 형성하게 되는데, 이러한 강관루프 구조체 및 그를 적용한 비개착 강관루프 공법을 이하 첨부된 도면을 참조하여 설명하기로 한다.In the present invention, when constructing a steel pipe loop structure, the steel pipe of the above-described structure is first formed by pressing the steel pipe of the above-described structure in the working tool of the underground structure. Such a steel pipe loop structure and a non-adhesive steel pipe loop method using the same are described below with reference to the accompanying drawings. This will be described.

도 10 내지 도 15는 본 발명의 강관 및 강관루프구조체를 적용한 비개착 강관루프 공법의 시공 순서도이다. 시공순서를 통해 본 공법의 상세한 구성 및 작용을 설명하면 다음과 같다.10 to 15 is a construction flow chart of the non-adhesive steel pipe loop method applying the steel pipe and the steel pipe loop structure of the present invention. The construction and operation of the construction method in detail through the construction sequence is as follows.

도 10에 도시한 바와 같이, 제1단계로 상술한 구조의 강관을 압입하고 연결한 후 강관내부에 몰탈이나 콘크리트를 충전한다. 즉, 횡단할 도로나 지장물의 양측에 작업구를 설치한 후 설치될 구조물의 외곽선에 맞추어 플랜지(12, 100)가 달린 강관(10)을 걸쇠고리(20)와 T자형 플랜지(22)를 연결한 채 삽입하여 강관을 오거로 굴착을 병행하면서 압입한다. 압입된 강관 측벽의 정착철물 관통공(135)을 통해 정착철물(130)을 타강관과 관통결합시킨다. 그 후 강관 내부(15) 및 플랜지들(12, 100)에 의해 형성된 폐합공간(150)에 콘크리트 타설 또는 그라우팅을 실시한다.As shown in Figure 10, the first step is to press and connect the steel pipe of the structure described above and then filling the mortar or concrete in the steel pipe. That is, after installing work tools on both sides of the road or obstacle to be traversed, the clasp 20 and the T-shaped flange 22 connect the steel pipe 10 with the flanges 12 and 100 to the outline of the structure to be installed. Insert it together and press-fit the steel pipe to the auger at the same time. Through the fixing steel through-hole 135 of the side wall of the press-fitted steel pipe, the fixing steel 130 is penetrated with the other steel pipe. Thereafter, concrete pouring or grouting is performed to the closed space 150 formed by the steel pipe interior 15 and the flanges 12 and 100.

도 11에 도시한 바와 같이, 제2단계로 내부 1차 굴착을 하고 가설기둥(40)을 설치한다. 즉, 상기 형성된 강관루프 구조체의 하면을 소형장비가 진입할 수 있는 심도로 굴착하면서 상부 하중을 적당한 간격으로 H-빔(40)(가설기둥)을 설치하여 지지시킨다. 이때 횡방향 지지보는 설치하지 않는다.As shown in FIG. 11, the first primary drilling is performed in a second step, and a temporary pillar 40 is installed. That is, while excavating the lower surface of the formed steel pipe loop structure to the depth that small equipment can enter, the upper load is supported by installing the H-beam 40 (temporary column) at appropriate intervals. At this time, the transverse support is not installed.

도 12에 도시한 바와 같이, 제3단계로 확보된 작업공간을 이용하여 소형 장비를 진입시켜 벽체와 기둥부에 가설용 H-파일(50)을 설치한다. As shown in FIG. 12, a small piece of equipment is entered using a workspace secured in a third step to install a temporary H-pile 50 on a wall and a pillar.

도 13에 도시한 바와 같이, 제4단계로 2차 토공을 실시하면서 벽체 및 중간 기둥설치용 가시설(버팀보: 75)을 설치하고, 그 설치된 가시설 내에서 철근 및 거푸집을 조립하여 벽체(65) 및 상부 슬래브(60)를 축조한다.As shown in Fig. 13, while the second earthwork is carried out in the fourth step, the wall and the intermediate pillar mounting provision (vertical beam: 75) is installed, and the reinforcing bars and formwork are assembled in the installed provisional wall to form the wall 65 and the upper portion. The slab 60 is constructed.

도 14에 도시한 바와 같이, 제5단계로 3차로 내부 잔여 토사 제거 및 가시설을 철거 한 후 바닥 슬래브에 버팀보(70)를 설치하고, 콘크리트를 타설하여 바닥 슬래브(80)를 설치한다.As shown in Figure 14, in the fifth step after the removal of the remaining internal soil and sewage in the third installation, the support 70 is installed on the floor slab, and the concrete is poured to install the floor slab (80).

도 15에 도시한 바와 같이, 제6단계로 중앙벽체 및 슬래브 표면처리를 하고 현장정리를 하여, 원하는 지중 구조물의 축조를 완성한다.As shown in FIG. 15, in the sixth step, the central wall and the slab surface treatment are performed and the site is cleaned to complete the construction of the desired underground structure.

도 10 내지 도 15에 도시한 바와 같이, 본 발명의 강관 및 강관루프구조체를 적용한 비개착 강관루프 공법은 강관루프 구조체로 감싸진 내부 굴착에 있어서는 먼저 소형 장비가 진입할 수 있는 통로를 1차적으로 확보해서 소형 장비를 이용하여 벽체와 기둥이 설치될 부위에 흙막이 가설용 H말뚝을 설치하여 토류 가시설을 축조하고 필요에 따라서 2차, 3차 등의 다단계 토공을 실시 한 후 벽체와 기둥 및 슬래브를 형성하여 원하는 구조물을 조성하게 된다. 이로써, 구조물이 설치될 부위만을 선택적으로 굴착한 후 구조물을 설치하고 이후 상부하중을 지탱하고 있는 잔여부에 대한 토공작업이 이루어지므로 시공 중에 지반의 변위억제와 안정성을 확보 할 수 있다. 따라서 축조된 강관루프내의 토공 작업 시 1차, 2차 등의 단계별로 굴진하면서 기 설치된 기둥의 지지부를 굴착, 부재를 연결하고 루프내의 모든 토사를 제거한 후 구조물을 시공하는 기존 강관루프공법에서 발생하는 침하문제나 안정성 결여가 해소된다.As shown in Figures 10 to 15, the non-adhesive steel pipe loop method applying the steel pipe and the steel pipe loop structure of the present invention primarily in the passage for entering small equipment first in the internal excavation wrapped with the steel pipe loop structure Secure the earthwork facility by installing the H pile for the construction of the wall with the small equipment and install the earthquake temporary installation at the site where the wall and the pillar will be installed, and perform the multi-stage earthwork such as the second and third as needed. To form the desired structure. Thus, after excavating only the site where the structure is to be selectively installed, the structure is installed, and since the earthwork is performed on the remaining part supporting the upper load, it is possible to secure displacement suppression and stability of the ground during construction. Therefore, excavation in the first and second stages of earthwork in the constructed steel pipe loop, excavating the supporting part of the pre-installed column, connecting the members, removing all the soil in the loop, and then constructing the structure Settlement problems and lack of stability are solved.

또한 횡방향으로 인장력을 받을 수 있는 구조시스템은 도 7 또는 도 8에서와 같이 강관의 내부에서 측벽에 일정한 간격으로 설치된 정착철물 관통공(135)을 통해 정착철물(130)을 타강관과 관통결합시기고, 이어 강관내부(15)에 몰탈이나 콘크리트를 충전시키고 강관의 플랜지들(12, 100)에 의해 형성된 폐합공간(150)에 몰탈이나 그라우팅 액을 주입하여 충전시키면 횡방향 강성을 갖는 강관으로 합성된 구조체의 특성을 갖게 된다.In addition, the structural system capable of receiving a tensile force in the transverse direction through the fixing steel 130 through the fixing steel through-hole 135 installed at regular intervals on the side wall in the interior of the steel pipe as shown in Figure 7 or 8 through the other steel pipe Then, the mortar or concrete is filled in the inner steel pipe 15 and the mortar or grouting liquid is injected into the closed space 150 formed by the flanges 12 and 100 of the steel pipe to form a steel pipe having a transverse rigidity. It has the characteristics of the synthesized structure.

또한, 지금까지는 본 발명을 비개착 강관루프구조체, 그 강관구조에 한정하여 설명되었으나, 본 발명이 이에 제한되는 것은 아니고, 비개착식 뿐만 아니라 개착식 복공구조의 토공에도 적용될 수 있으며, 강관과 같은 강관 뿐만 아니라 형강도 사용될 수 있음을 이해하여야 한다. 또한 터널작업에도 이용될 수 있음은 당연하므로, 시공용도 및 대상에 관계없이 첨부된 청구범위에 포함되는 범위안에서 다양한 변형 및 수정이 가능함을 이해하여야 한다.In addition, the present invention has been described so far as being limited to the non-adhesive steel pipe loop structure and the steel pipe structure, but the present invention is not limited thereto, and may be applied to the earthwork of the non-adhesive as well as the open-type perforated structure, such as steel pipes. It is to be understood that section steel as well as steel pipe may be used. In addition, it should be understood that various modifications and changes can be made within the scope of the appended claims regardless of the purpose and purpose of construction.

상술한 바와 같이 본 발명에서는 강관과 강관의 연결부에 몰탈이나 콘크리트를 충전할 수 있는 폐합 공간의 형성이 가능하도록 강관의 상??하단 외측부에 서로 연결할 수 있는 플랜지(12, 100)가 부착되고, 인접한 강관의 압입시 이탈을 방지하기 위하여 걸쇠고리(20)와 T자형 플랜지(22)를 부착하고, 강관끼리의 횡방향 내하력을 증강시키기 위한 정착철물(130)을 관통연결하기 위한 관통공(135)을 형성하고, 강관의 내부 또는 연결부의 폐합공간에 콘크리트를 충전함으로써, 횡방향으로 결속력을 갖는 강 콘크리트 합성체 루프를 축조함으로써, 구조물 축조를 위한 내부의 토공 작업 시에는 루프 구조체의 횡방향 강성으로 인해 별도의 횡방향 지지보의 설치 없이 가설 기둥만 설치하여 토공작업이 가능하므로 가설루프의 규모가 줄어들고 시공공정도 단순하게 된다. As described above, in the present invention, flanges 12 and 100 are connected to upper and lower outer portions of the steel pipe so as to form a closed space for filling mortar or concrete in the connection portion between the steel pipe and the steel pipe, Through holes 135 for attaching the clasp 20 and the T-shaped flange 22 to prevent separation during indentation of adjacent steel pipes, and connecting the fixing hardware 130 to enhance the transverse load-bearing force between the steel pipes 135 By forming concrete in the closed space of the steel pipe or the connection part, and constructing a steel concrete composite loop having a binding force in the transverse direction, so that the lateral rigidity of the roof structure during internal earthwork for structure construction Due to this, earthwork can be done by installing only temporary columns without installing additional transverse support beams, thus reducing the size of temporary loops and simplifying the construction process. It is.

이로써, 루프구조체내의 토공작업에 있어서는 1차 토공작업에 의해 확보된 통로를 이용하여 천공장비를 투입, 벽체와 기둥이 축조될 부위에 선택적으로 흙막이 가설용 파일을 설치, 2차로 토사를 제거하고 구조물을 축조한 후 3차로 상부하중을 지탱하고 있는 잔여부에 대한 토공작업이 이루어지므로 기존 강관루프공법의 루프 내부의 토사를 전부 제거하는 과정에서 불가피하게 발생하는 지반침하 등이 발생치 않아 시공 중의 안정성 확보 뿐만 아니라 가시설의 규모가 축소되어 시공 공기 단축 및 시공비 절감을 이룰 수 있다. Thus, in the earthwork work in the roof structure, the drilling equipment is input by using the passage secured by the first earthwork work, and the soil pile is selectively installed at the site where the wall and the pillar will be constructed, and the soil is removed secondly. After the construction of earthwork, earthwork is carried out on the remaining part supporting the upper load in the third step, so ground sedimentation, which is inevitably generated in the process of removing all the soil inside the loop of the existing steel pipe loop method, does not occur In addition to securing the size of the facility, construction air can be shortened and construction costs can be reduced.

도 1은 기존 비개착 구조물 축조 공법을 설명하기 위한 일반도.1 is a general view for explaining a conventional non-attached structure construction method.

도 2 내지 도 5는 기존 강관루프 공법의 시공순서를 설명하기 위한 단면도.2 to 5 are cross-sectional views for explaining the construction procedure of the existing steel pipe loop method.

도 6은 기존 공법의 강관의 연결구조 상세도.Figure 6 is a detailed view of the connection structure of the steel pipe of the existing construction method.

도 7은 본 발명의 제1 실시예에 따라서, 강관의 양측부에 상하 플랜지가 부착되어 인접한 강관의 플랜지끼리 상호 맞대기 형식으로 결합되고, 중앙부 양측에 걸쇠고리 및 T자형 플랜지가 부착되어 인접한 강관끼리 상호 고리결합되고 다수의 정착철물 설치용 관통공이 형성되어 인접한 강관이 상호 관통결합됨을 도시하는 강관의 상호 연결관계를 도시한 상세 단면도이다.7 is a top and bottom flanges are attached to both sides of the steel pipe according to the first embodiment of the present invention, the flanges of adjacent steel pipes are coupled to each other in a mutually butt-type, and the clasp and T-shaped flanges are attached to both sides of the central portion adjacent steel pipes It is a detailed cross-sectional view showing the interconnection relationship of the steel pipes which are mutually coupled and a plurality of through-holes for the installation of fixing steel are formed so that adjacent steel pipes are mutually through.

도 8은 본 발명의 제2 실시예에 따라서, 강관의 양측부에 상하 플랜지가 부착되어 인접한 강관의 플랜지끼리 상호 겹치기 형식으로 결합되고, 중앙부 양측에 걸쇠고리 및 T자형 플랜지가 부착되어 인접한 강관끼리 상호 고리결합되고 다수의 정착철물 설치용 관통공이 형성되어 인접한 강관이 상호 관통결합됨을 도시하는 강관의 상호 연결관계를 도시한 상세 단면도이다.8 is a top and bottom flange is attached to both sides of the steel pipe according to the second embodiment of the present invention, the flanges of adjacent steel pipes are combined in a mutually overlapping form, the clasp and T-shaped flanges are attached to both sides of the central portion adjacent steel pipes It is a detailed cross-sectional view showing the interconnection relationship of the steel pipes which are mutually coupled and a plurality of through-holes for the installation of the fixing steel is formed so that adjacent steel pipes are mutually through.

도 9는 본 발명의 비개착 강관루프 구조체를 이용한 지중 구조물을 도시한 단면도.9 is a cross-sectional view showing an underground structure using an unattached steel pipe loop structure of the present invention.

도 10 내지 도 15는 본 발명의 비개착 강관루프 구조체를 이용한 지중 구조물의 축조 공법의 시공 순서도.10 to 15 is a construction flowchart of the construction method of the underground structure using the non-attached steel pipe loop structure of the present invention.

<도면의 주요부분에 대한 설명><Description of main parts of drawing>

10...강관, 12, 100...제1 및 제2 플랜지10 ... steel pipe, 12, 100 ... first and second flange

15...강관 내부, 20...걸쇠고리15 ... inside steel pipe, 20 ... clasp

22...T자형 플랜지, 40...가설기둥22 ... T-shaped flange, 40 ...

50...가설용 파일, 60...상부 슬래브50 ... hypothetical files, 60 ... upper slab

65...벽체, 70, 75...버팀보65 ... wall, 70, 75 ...

80...하부 슬래브, 130...정착철물80 ... lower slab, 130 ... fixed hardware

135...정착철물 관통공, 150...폐합공간135 ... fixed steel through hole, 150 ... closed space

Claims (4)

지중에 구조물을 축조하는 강관루프 공법에 적용되는 강관에 있어서, In the steel pipe applied to the steel pipe loop method for constructing the structure in the ground, 횡단할 도로나 지장물의 양측에 작업구를 설치한 후 설치될 구조물의 외곽선에 맞추어 순차적으로 압입 설치되는, 외부 일측면에 상하 2개의 제1플랜지가 부착되고 타측면에는 타강관의 제1플랜지와 대응 연결되는 제2플랜지가 상하로 부착되고, 강관의 일측부 중앙부에는 걸쇠 고리가 형성되고, 타측 중앙부에는 타강관의 걸쇠고리와 연결되는 걸쇠 플랜지가 형성되고, 상기 강관의 양측면에 인접한 강관을 서로 결합하는 정착철물을 관통설치하기 위한 관통공이 다수개 형성되는 강관.After the work tools are installed on both sides of the road or obstacle to be traversed, two first flanges are attached to one outer side and the first flange of the other steel pipe is attached to one side of the external pipe, which is sequentially press-fitted according to the outline of the structure to be installed. Correspondingly connected second flange is attached to the upper and lower sides, the clasp ring is formed in the central portion of one side of the steel pipe, the clasp flange is formed in the other central portion is connected to the clasp of the other steel pipe, the steel pipe adjacent to both sides of the steel pipe Steel pipes are formed with a plurality of through-holes for penetrating the fixing fixture to be combined. 제1항에 있어서, 인접한 강관의 플랜지끼리 상호 겹치거나 맞대기 형식으로 결합하여 폐합공간을 형성함을 특징으로 하는 강관.The steel pipe according to claim 1, wherein the flanges of adjacent steel pipes overlap each other or are joined in a butt type to form a closed space. 지중에 구조물을 축조하는 강관루프 공법에 적용되는 강관루프 구조체에 있어서, 횡단할 도로나 지장물의 양측에 작업구를 설치한 후 외부 일측면에 상하 2개의 제1플랜지가 부착되고 타측면에는 타강관의 제1플랜지와 대응 연결되는 제2플랜지가 상하로 부착되고, 강관의 일측부 중앙부에는 걸쇠 고리가 형성되고, 타측 중앙부에는 타강관의 걸쇠고리와 연결되는 걸쇠플랜지가 형성되고, 상기 강관의 양측면에 인접한 강관을 서로 결합하는 정착철물을 관통설치하기 위한 관통공이 다수개 형성되는 강관을 준비하여, 설치될 구조물의 외곽선에 맞추어 순차적으로 압입 설치할 때, 상기 강관을 지중에 오거로 굴착을 병행하면서 한 강관의 걸쇠고리가 타강관의 걸쇠플랜지와 고리결합되고, 한 강관의 제1플랜지가 타강관의 제2플랜지에 겹치거나 맞대기 형식으로 결합하여, 순차적으로 압입 설치하고, 정착철물 관통공을 통해 정착철물을 관통삽입하여 강관들을 연결시킨 후, 상기 강관내부 및 상기 플랜지에 의해 형성된 폐합공간에 몰탈이나 콘크리트를 타설함으로써 이루어지는 강관루프 구조체.In the steel pipe loop structure applied to the steel pipe loop method for constructing a structure in the ground, after installing work tools on both sides of the road or obstacle to be traversed, two first flanges are mounted on one side of the outer side and the other steel pipe on the other side. A second flange corresponding to the first flange of the upper and lower sides is attached up and down, and the clasp ring is formed in the central portion of one side of the steel pipe, the clasp flange is formed in the other central portion is connected to the clasp of the other steel pipe, both sides of the steel pipe When preparing a steel pipe formed with a plurality of through-holes for the installation of the steel fittings adjacent to the steel pipes adjacent to each other, and sequentially press-fitted to fit the outline of the structure to be installed, the steel pipes are drilled in parallel with the auger in the ground The clasp of the steel pipe is looped with the clasp flange of the other steel pipe, and the first flange of one steel pipe overlaps or meets the second flange of the other steel pipe. Combined in the form, press-installed sequentially, through the fixing hardware through-hole to connect the steel pipes through the connection of the steel pipes, steel pipe loop made by pouring mortar or concrete into the closed space formed by the inside of the steel pipe and the flange Structure. 지중에 구조물을 축조하기 위한 강관루프 공법에 있어서, In the steel pipe loop method for constructing the structure in the ground, 토공작업의 시공 전에 구조물의 안전성을 확보하기 위하여, 먼저 지중구조물의 크기에 맞추어 측부 상하 연결 플랜지와 중앙 걸쇠 연결부를 부착한 강관을 준비하여, 상호 인접한 강관끼리의 걸쇠 연결부를 연결하여 센터위치를 맞춘 채 압입하고, 상호 인접 강관의 상하 플랜지를 연결하여 폐합공간을 형성하고, 강관에 형성한 정착철물 설치용 관통공을 통하여 강관 내측으로부터 관통한 정착철물을 이용하여 인접 강관들을 연결하고, 상기 강관내부 및 강관 연결 플랜지에 의해 형성된 폐합공간에 몰탈이나 콘크리트를 타설하여 강관루프구조체를 형성하는 단계; In order to ensure the safety of the structure before the earthwork work, first prepare the steel pipes with side up and down connecting flanges and the center clasp connection according to the size of the underground structure, and then connect the clasp connections between adjacent steel pipes to adjust the center position. Press-fitting, connecting the upper and lower flanges of adjacent steel pipes to form a closed space, and connect the adjacent steel pipes using the fixing steel penetrated from the inside of the steel pipe through the through-hole for fixing fixtures formed in the steel pipe, and the inside of the steel pipe and Pouring mortar or concrete into the closed space formed by the steel pipe connecting flange to form a steel pipe loop structure; 굴착을 통해 장비통로를 확보하는 단계; Securing an equipment path through excavation; 장비통로를 확보한 후 횡방향지지보를 설치하지 않고 필요시 가설기둥만을 설치하는 단계; Installing only temporary pillars if necessary without securing the transverse support after securing the equipment passage; 필요시 가설용 파일을 설치하고 다음 굴착부위인 벽체와 기둥부에 장비를 투입하여 필요에 따라서 다음 굴착을 실시하는 단계; 및 Installing the temporary piles if necessary and putting the equipment into the wall and the pillar which are the next excavation site, and performing the next excavation as necessary; And 상부 슬라브 및 좌우 벽체 기둥 등 구조물을 축조한 후 최종적으로 토공작업을 실시한 후 바닥슬라브를 축조하는 단계를 포함하는 강관루프공법.Steel pipe roofing method comprising the step of building the bottom slab after the final earthwork after the construction of the upper slab and left and right wall pillars.
KR1020040023343A 2004-04-06 2004-04-06 Structure of steel pipe applied to steel pipe roof construction method for building underground structure, and steel pipe roof structure therefor using the same, and steel roof construction method thereof KR100569703B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040023343A KR100569703B1 (en) 2004-04-06 2004-04-06 Structure of steel pipe applied to steel pipe roof construction method for building underground structure, and steel pipe roof structure therefor using the same, and steel roof construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040023343A KR100569703B1 (en) 2004-04-06 2004-04-06 Structure of steel pipe applied to steel pipe roof construction method for building underground structure, and steel pipe roof structure therefor using the same, and steel roof construction method thereof

Publications (2)

Publication Number Publication Date
KR20050098338A true KR20050098338A (en) 2005-10-12
KR100569703B1 KR100569703B1 (en) 2006-04-10

Family

ID=37277802

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040023343A KR100569703B1 (en) 2004-04-06 2004-04-06 Structure of steel pipe applied to steel pipe roof construction method for building underground structure, and steel pipe roof structure therefor using the same, and steel roof construction method thereof

Country Status (1)

Country Link
KR (1) KR100569703B1 (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100753140B1 (en) * 2006-02-24 2007-09-04 원하종합건설 주식회사 Steel pipe roof assembly and the construction method for tunnel using thereof
KR100784201B1 (en) * 2006-02-03 2007-12-10 한미기초개발주식회사 Method for construction of tunnel
KR100806867B1 (en) * 2006-02-24 2008-02-22 원하종합건설 주식회사 Steel pipe roof assembly and the construction method for Tunnel using thereof
KR100813910B1 (en) * 2006-12-28 2008-03-18 윤인병 Pipe roof structure
CN101922293A (en) * 2009-06-09 2010-12-22 株式会社Ntsenc Method for installing waterproof steel plate in construction of underground tunnel
KR101011805B1 (en) * 2010-09-08 2011-02-07 김진수 Method of constructing underground structure crossing pile bases in a pile-based ground and underground structure constructed using the same
KR101415694B1 (en) * 2014-03-10 2014-07-04 김동수 Method of constructing new tunnel under the pre-existing structure with anchor for bearing buoyancy
KR101616505B1 (en) * 2015-07-27 2016-04-29 원화코퍼레이션(주) Side wall structure using retaining member and sub-concrete structure construction method therewith
KR102013783B1 (en) * 2019-01-08 2019-08-26 김성진 Steel pipe, underground structure and cast messer shield method
KR102048831B1 (en) * 2019-07-01 2019-11-26 주식회사 신승이앤씨 Non-excavation type tunnel structure using steel pipe loof and leading pipe and method of constructing thereof
KR102540940B1 (en) 2022-03-31 2023-06-08 강익희 Pipe roof method with expanded boring and steel pipe jointing and structure using of the same

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102064998B1 (en) 2017-07-07 2020-01-10 주식회사 뉴컨스텍 Slip reduction type side connection steel pipe and linear and curved line hybrid type tunnel construction using it
KR102494477B1 (en) 2022-04-26 2023-02-06 원하건설 주식회사 Steel tube for underground structure and construction method thereof

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100784201B1 (en) * 2006-02-03 2007-12-10 한미기초개발주식회사 Method for construction of tunnel
KR100753140B1 (en) * 2006-02-24 2007-09-04 원하종합건설 주식회사 Steel pipe roof assembly and the construction method for tunnel using thereof
KR100806867B1 (en) * 2006-02-24 2008-02-22 원하종합건설 주식회사 Steel pipe roof assembly and the construction method for Tunnel using thereof
KR100813910B1 (en) * 2006-12-28 2008-03-18 윤인병 Pipe roof structure
CN101922293A (en) * 2009-06-09 2010-12-22 株式会社Ntsenc Method for installing waterproof steel plate in construction of underground tunnel
CN101922293B (en) * 2009-06-09 2013-01-02 株式会社Ntsenc Method for installing waterproof steel plate in construction of underground tunnel
KR101011805B1 (en) * 2010-09-08 2011-02-07 김진수 Method of constructing underground structure crossing pile bases in a pile-based ground and underground structure constructed using the same
KR101415694B1 (en) * 2014-03-10 2014-07-04 김동수 Method of constructing new tunnel under the pre-existing structure with anchor for bearing buoyancy
KR101616505B1 (en) * 2015-07-27 2016-04-29 원화코퍼레이션(주) Side wall structure using retaining member and sub-concrete structure construction method therewith
KR102013783B1 (en) * 2019-01-08 2019-08-26 김성진 Steel pipe, underground structure and cast messer shield method
KR102048831B1 (en) * 2019-07-01 2019-11-26 주식회사 신승이앤씨 Non-excavation type tunnel structure using steel pipe loof and leading pipe and method of constructing thereof
KR102540940B1 (en) 2022-03-31 2023-06-08 강익희 Pipe roof method with expanded boring and steel pipe jointing and structure using of the same

Also Published As

Publication number Publication date
KR100569703B1 (en) 2006-04-10

Similar Documents

Publication Publication Date Title
KR101274974B1 (en) Earth retaining wall and construction method thereof
KR100569703B1 (en) Structure of steel pipe applied to steel pipe roof construction method for building underground structure, and steel pipe roof structure therefor using the same, and steel roof construction method thereof
KR100562158B1 (en) Steel pipe roof construction method for building underground structure, roof structure therefor, and structure of steel pipe therefor
KR100712593B1 (en) Construction method of pipe roof structures
KR20070075506A (en) Construction method of underground structure using concrete filled pipe roof and concrete wall
KR20090114863A (en) Parallelly connected iron tube and construction method for underground structure using the same
KR20110122310A (en) Construction method for basement structure without temporary structure
KR20060097891A (en) Pipe roof structures and construction method of pipe roof structures
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
KR100806867B1 (en) Steel pipe roof assembly and the construction method for Tunnel using thereof
KR100510092B1 (en) A one-piece type arch-shaped structure with the precast concrete pannel and the steel frame under the earth, and method for manufacturing it
KR100784201B1 (en) Method for construction of tunnel
KR200354467Y1 (en) Steel pipe roof structure for building underground structure
KR101118100B1 (en) Pipe roof structures and its construction method
KR101202182B1 (en) pipe roof structures and its construction method
KR200385542Y1 (en) Pipe roof structures
KR100987948B1 (en) Construction method for underground structure using prestressed beam and development structure, saddle used in the same
KR100509707B1 (en) None open cut tunnelling of arch type with hume pipe and con&#39;c rib
KR100813910B1 (en) Pipe roof structure
KR20060117746A (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR102310091B1 (en) Underground structure installation method that does not require the installation of temporary pillars
KR100753140B1 (en) Steel pipe roof assembly and the construction method for tunnel using thereof
JPS584094A (en) Method of constructing low road cross
KR20110034831A (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
KR100833700B1 (en) Pipe roof structures

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20110303

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20140318

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20170328

Year of fee payment: 14