KR200434427Y1 - Sliding support device - Google Patents

Sliding support device Download PDF

Info

Publication number
KR200434427Y1
KR200434427Y1 KR2020060027350U KR20060027350U KR200434427Y1 KR 200434427 Y1 KR200434427 Y1 KR 200434427Y1 KR 2020060027350 U KR2020060027350 U KR 2020060027350U KR 20060027350 U KR20060027350 U KR 20060027350U KR 200434427 Y1 KR200434427 Y1 KR 200434427Y1
Authority
KR
South Korea
Prior art keywords
earth plate
support
coupling
pillars
sliding
Prior art date
Application number
KR2020060027350U
Other languages
Korean (ko)
Inventor
김상훈
Original Assignee
김상훈
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김상훈 filed Critical 김상훈
Priority to KR2020060027350U priority Critical patent/KR200434427Y1/en
Application granted granted Critical
Publication of KR200434427Y1 publication Critical patent/KR200434427Y1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • E02D17/083Shoring struts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

슬라이딩 버팀 장치를 개시한다. 본 고안은 굴토벽면의 붕괴된 토사의 유입을 방지하기 위하여 설치되는 슬라이딩 버팀 장치에 관한 것으로서, 종래의 흙막이 장치는 스트럿버팀대를 사용하여 흙막이벽을 지지하였는데 설치가 어려워 작업 속도가 느리고 토압을 견디지 못하고 종종 무너지는 문제점이 있었으나, 본 고안인 슬라이딩 버팀 장치는 좌우측면에 각기 하기 토류판이 삽입되는 슬라이드홈부가 형성되고 전면에 하기 결합구가 삽입되어 결합하는 삽입홈이 형성되어 토굴의 양 굴토벽면을 따라 마주보도록 다수 개가 설치되는 기둥과 상기 기둥 중 서로 마주보는 두 기둥을 지지하기 위한 지지대, 상기 지지대 양단에 결합하여 상기 지지대와 각각의 기둥을 결합하게 하는 부기카와 상기 부기카의 상단과 하단 좌우면에 각각 일체로 형성되어 상기 삽입홈을 따라 상기 부기카를 가이드시키는 롤러부를 포함하는 결합구로 이루어진 버팀 수단 및 상기 기둥 중 인접한 서로 다른 기둥 사이의 슬라이드홈부에 삽입적재되는 토류판을 포함하는 슬라이딩 버팀 장치를 특징으로 하여 설치 및 해제가 쉽고 작업속도가 빨라 경제성과 시공성을 높이고 결합구의 사용으로 기둥에 가해지는 힘을 분산시켜 안정성을 높이는 효과가 있다.A sliding brace device is disclosed. The present invention relates to a sliding brace device that is installed to prevent the inflow of collapsed soil of the oyster wall surface, the conventional earth block device using a strut brace to support the earth wall, the installation speed is difficult to withstand the earth pressure Although there was a problem that often collapses, the sliding support device of the present invention is formed on the left and right sides, respectively, the slide groove portion is inserted into the earth plate, and the insertion groove is formed by inserting the following coupling holes on the front side along the oyster wall surface of the crypt On the upper and lower left and right sides of the bugika and the bugika to be coupled to both ends of the support and the support for supporting two pillars facing each other of the pillars are installed to face each other, the pillars are installed so as to face each other Each one is formed integrally with the boogie car along the insertion groove Features a brace means comprising a coupling means comprising a roller to guide and a sliding brace device including a earth plate inserted into the slide groove between the adjacent adjacent ones of the pillars, easy to install and release, fast and economical workability It is effective to increase the stability by dispersing the force applied to the column by using a coupling tool.

흙막이벽, 토류판, 슬라이드, 지지대 Retaining wall, earth plate, slide, support

Description

슬라이딩 버팀 장치{SLIDING SUPPORT DEVICE}Sliding Brace Device {SLIDING SUPPORT DEVICE}

도 1은 본 고안 슬라이딩 버팀 장치의 구성을 설명하기 위한 도면.1 is a view for explaining the configuration of the subject innovation sliding support device.

도 2는 본 고안 슬라이딩 버팀 장치의 기둥을 설명하기 위한 도면.Figure 2 is a view for explaining the pillar of the present invention sliding brace device.

도 3은 본 고안 슬라이딩 버팀 장치의 버팀 수단을 설명하기 위한 도면.Figure 3 is a view for explaining the brace means of the present invention the sliding brace device.

도 4는 본 고안 슬라이딩 버팀 장치의 토류판을 설명하기 위한 도면.Figure 4 is a view for explaining the earth plate of the subject innovation sliding support device.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

100 : 기둥 101 : 고정공100: pillar 101: fixing hole

110 : 슬라이드홈부 120 : 삽입홈110: slide groove 120: insertion groove

130 : 보강바 140 : 몸체운송구130: reinforcing bar 140: body transport

141 : 운반고리 200 : 버팀 수단141: carrying ring 200: bracing means

210 : 결합구 211 : 부기카210: combiner 211: buggy

212 : 롤러부 220 : 지지대212: roller 220: support

300 : 토류판 301 : 외부토류판300: earth plate 301: external earth plate

302 : 내부토류판 310 : 커넥터302: internal earth plate 310: connector

본 고안은 슬라이딩 버팀 장치에 관한 것으로서, 보다 상세하게는 버팀 수단에 의해 지지되는 두 기둥 양측에 토류판을 삽입하여 굴토벽면을 지지함으로써 시공이 간단하고 경제적이며 공사환경에 구애받지 않고 설치되는 슬라이딩 버팀 장치에 관한 것이다.The present invention relates to a sliding brace device, more specifically, the sliding brace device is installed in a simple and economical construction regardless of the construction environment by supporting the oyster wall by inserting the earth plate on both sides supported by the brace means It is about.

굴착시 굴착면에 가설구조물을 축조하여 무너짐을 방지하고 주변 건물에 피해가 발생하지 않도록 하기 위해 흙막이를 설치하여 사용한다. 일반적으로 흙막이 공법은 H-Pile 및 토류판공법, 시트파일(SHEET PILE)공법, 주열식 흙막이공법, 슬러리월(SLURRY WALL)공법 등이 사용되는데, 토질 및 지반의 형태, 매설심도, 지하수위, 구조물 매설폭, 경제성 및 시공성, 현장주위 여건 등을 종합적으로 고려하여 공법을 채택한다. 본 고안은 H-Pile 및 토류판공법을 사용하는 장치의 문제점을 보완하기 위한 것으로, H-Pile 및 토류판공법을 간단히 설명하면 H-Pile(어미말뚝)을 일정한 간격으로 박고 굴착과 동시에 토류판을 사이에 끼워 흙막이벽을 설치하는 공법으로, 스트럿버팀대를 설치하여 흙막이벽을 지지한다. 상기와 같은 공법은 굴착 깊이가 깊고 굴착폭이 넓은 곳에 사용되며 시가지 및 굴착폭이 좁은 곳에서는 공사가 힘든 문제점이 있다. When excavation, construct temporary structure on the excavation surface to prevent collapsing and to prevent damage to nearby buildings. In general, the soil clogging method is H-Pile and earth plate method, sheet pile method, heat-sucking earthquake method, slurry wall method, etc. The construction method should be adopted in consideration of the burial width, economic feasibility and constructability, and the site surroundings. The present invention is to compensate for the problems of the device using the H-Pile and earth plate method, briefly explaining the H-Pile and the earth plate method, H-Pile (mother pile) is put at regular intervals and at the same time the earth plate In this way, the strut brace is installed to support the retaining wall. Such a method is used in a deep drilling depth and a wide excavation width, there is a problem that construction is difficult in the narrow area and excavation width.

또한, 천공 및 항타장비가 별도로 필요하고, 천공과 항타로 인한 소음이 발생하며 토류판 삽입시 전선줄 등의 공중장애물의 방해를 받아 시가지에서 작업이 불편하다. In addition, the drilling and driving equipment is required separately, noise is generated due to the drilling and driving, and the work is inconvenient in the urban area due to the interference of aerial obstacles such as wire cords when the earth plate is inserted.

이 공법에 사용되는 스트럿버팀대는 길이연장이 불가능하여 토굴의 폭에 유동적으로 대응할 수 없어 토굴의 폭이 넓거나 좁은 지역마다 제작을 달리해야하는 문제점이 있었고, 관 직경에 따라 스트럿버팀대를 상하로 자유롭게 이동시킬 수 없었다. The strut brace used in this method was not able to extend the length flexibly, so there was a problem that the fabrication had to be made differently in the wide or narrow area of the crypt, and the strut brace could move freely up and down according to the pipe diameter. Couldn't.

또한, 자체의 강성이 크지 않아 모양이나 부피가 변할 수 있고, 작업자가 직접 설치하기 때문에 작업이 어렵고 작업속도가 느려 경제성이 적을 뿐 아니라, 토류판을 제거하는 과정에서 토사가 붕괴하여 재해가 발생할 확률이 높다. In addition, since the rigidity of the product itself is not large, the shape or volume can be changed, and since the worker installs it directly, the work is difficult and economical due to the slow working speed. high.

따라서, 본 고안은 상기와 같은 문제점을 감안하여 안출된 것으로, 버팀 수단에 의해 지지되는 두 기둥 양측에 일자형 슬라이드홈부를 형성하고 굴토벽면을 지지하는 토류판을 삽입하여 설치가 간단하고 지지대의 연장이 가능하도록 양단에 결합공을 형성하며 기둥에 가해지는 힘을 분산시키는 결합구를 사용함으로써 안정성을 확보하는 슬라이딩 버팀 장치를 제공함에 목적이 있다.Therefore, the present invention has been devised in view of the above problems, and it is easy to install and extend the support by inserting the earth plate supporting the oyster wall surface by forming a linear slide groove on both sides supported by the support means. It is an object of the present invention to provide a sliding brace device that ensures stability by forming a coupling hole at both ends and using a coupling tool for dispersing the force applied to the pillar.

상기와 같은 목적을 달성하기 위하여 본 슬라이딩 버팀 장치는 좌우측면에 각기 하기 토류판(300)이 삽입되는 슬라이드홈부(110)가 형성되고 전면에 하기 결합구(210)가 삽입되어 결합하는 삽입홈(120)이 형성되어 토굴의 양 굴토벽면을 따라 마주보도록 다수 개가 설치되는 기둥(100)과 상기 기둥(100) 중 서로 마주보는 두 기둥(100)을 지지하기 위한 지지대(220)와 상기 지지대(220) 양단에 결합하여 상기 지지대(220), 각각의 기둥을 결합하게 하는 부기카(211)와 상기 부기카(211)의 상단과 하단 좌우면에 각각 일체로 형성되어 상기 삽입홈(120)을 따라 상기 부기카(211)를 가이드시키는 롤러부(212)를 포함하는 결합구(210)로 이루어진 버팀 수단(200)과 상기 기둥(100) 중 인접한 서로 다른 기둥(100) 사이의 슬라이드홈부(110)에 삽입적재되는 토류판(300)을 포함하는 것을 특징으로 한다.In order to achieve the above object, the sliding support device includes a slide groove 110 into which the earth plate 300 is inserted into the left and right sides, respectively, and an insertion groove 120 into which the following coupling holes 210 are inserted. The support 220 and the support 220 for supporting the two pillars (100) facing each other among the pillars 100 and the plurality of pillars 100 are installed to face each other along the oyster wall of the crypt is formed; Coupled to both ends of the support 220, the bugika 211 for coupling each of the pillars and the upper and lower left and right sides of the buggie 211 are formed integrally with each other along the insertion groove 120 On the slide groove portion 110 between the support means 200 made of a coupler 210 including a roller portion 212 for guiding the boogie car 211 and the adjacent different pillars 100 among the pillars 100. Specifically, including the earth plate 300 is inserted Gong.

여기에서, 상기 버팀 수단(200)의 지지대(220)는 양끝단에 다수의 결합공이 형성되어 다수 개가 나사결합하는 것을 특징으로 한다.Here, the support 220 of the brace means 200 is characterized in that a plurality of coupling holes are formed at both ends are screw-coupled.

또한, 다수의 토류판(300)이 서로 접하는 소정 부위에 외부결합핀공을 형성한 다수의 결합홈이 형성되는 것을 특징으로 하며 각 토류판(300)이 서로 접할 시 상측에 삽입된 토류판(300)의 결합홈과 하측에 삽입된 토류판(300)의 결합홈에 끼워져 연결되고 상기 외부결합핀공과 핀결합하도록 내부결합핀공이 형성된 커넥터(310)를 더 포함하는 것을 특징으로 한다.In addition, the plurality of earth plate 300 is characterized in that a plurality of coupling grooves formed with an external coupling pin hole is formed in a predetermined portion in contact with each other, the coupling of the earth plate 300 inserted in the upper side when each earth plate 300 is in contact with each other It is characterized in that it further comprises a connector 310 is inserted into the coupling groove of the earth plate 300 is inserted into the groove and the inner coupling pin hole is formed to pin the external coupling pin hole.

또한, 상기 기둥(100)은, 삽입홈에서 결합구(210)를 삽입한 영역을 제외한 삽입홈의 영역에 삽입되는 보강바(130)를 더 포함하는 것을 특징으로 하고 배면에 소정의 간격으로 다수의 고정공(101)이 형성되고 상기 고정공(101)과 보강바(130)를 관통하여 나사결합하는 것을 특징으로 한다.In addition, the pillar 100 is characterized in that it further comprises a reinforcement bar 130 is inserted into the region of the insertion groove except for the region in which the coupler 210 is inserted in the insertion groove and a plurality of at predetermined intervals on the rear surface. It is characterized in that the fixing hole 101 is formed and screwed through the fixing hole 101 and the reinforcing bar 130.

여기에서, 상기 기둥(100) 끝단에서 핀결합하여 고정설치되고 소정 부위에 고리형상의 운반고리(141)가 형성되는 몸체운송구(140)를 더 포함하는 것을 특징으로 한다.Here, it is characterized in that it further comprises a body transport port 140 is fixed to the pin coupling at the end of the pillar 100 and a ring-shaped transport ring 141 is formed in a predetermined portion.

이하 첨부된 도면을 참조하여 본 고안인 슬라이딩 버팀 장치를 상세히 설명하기로 한다.Hereinafter, the sliding support device according to the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 고안 슬라이딩 버팀 장치의 구성을 설명하기 위한 도면으로서, 상기 도 1에 도시된 바와 같이 본 고안 슬라이딩 버팀 장치는 기둥(100)과 결합구(210), 지지대(220)를 포함하는 버팀 수단(200)과 토류판(300)으로 구성된다. 상기 기둥(100)은 두 기둥(100)이 마주보는 형태로 다수 개가 설치되고 상기 지지대(220)는 상기 두 기둥(100)을 지지하며 상기 결합구(210)는 상기 지지대(220)와 각각의 기둥(100)을 결합하게 하고 상기 토류판(300)은 인접한 서로 다른 기둥(100) 사이에 삽입되어 토사의 유입을 막는다.1 is a view for explaining the configuration of the present invention sliding brace device, the present invention sliding brace device as shown in Figure 1 is a support including a pillar 100, the coupling sphere 210, the support 220 It consists of a means 200 and the earth plate 300. A plurality of pillars 100 are installed in a form in which two pillars 100 face each other, and the supporter 220 supports the two pillars 100, and the coupler 210 is connected to the supporter 220. The pillars 100 are coupled to each other, and the earth plate 300 is inserted between adjacent different pillars 100 to prevent inflow of soil.

이하, 본 고안 슬라이딩 버팀 장치에 대하여 도 2 내지 도 4에서 좀 더 상세히 설명한다.Hereinafter, the present invention the sliding bracing device will be described in more detail with reference to FIGS.

도 2는 본 고안 슬라이딩 버팀 장치의 기둥을 설명하기 위한 도면으로, 도 2(a)는 기둥의 사시도이고, 도2(b)는 기둥의 또다른 실시예를 나타내기 위한 도면이며, 도2(c)는 기둥에 설치되는 몸체운송구를 설명하기 위한 도면이다. Figure 2 is a view for explaining the pillar of the present invention the sliding brace device, Figure 2 (a) is a perspective view of the pillar, Figure 2 (b) is a view showing another embodiment of the pillar, Figure 2 ( c) is a view for explaining the body transport port installed in the pillar.

상기 도 2(a)에 도시된 바와 같이 상기 기둥(100)은 좌우측면에 각기 토류판이 삽입되는 슬라이드홈부(110)가 형성되고 전면에 결합구가 삽입되어 결합하는 삽 입홈(120)이 형성된다. 상기 슬라이드홈부(110)에는 토류판이 삽입적재되는데, 굴토벽면의 상부를 지지하는 토류판과 하부를 지지하는 토류판을 구분하는 레일분리대가 없는 일자형의 슬라이드홈부(110)이기 때문에 이물질이 슬라이드홈부(110)에 끼어서 상기 기둥(100)과 상기 토류판의 삽입과 분리를 방해하지 않는다. As shown in FIG. 2 (a), the pillar 100 has slide grooves 110 into which earth plates are inserted, respectively, on the left and right sides thereof, and insertion grooves 120 are formed to couple and couple the coupling holes to the front surface. . A soil plate is inserted and inserted into the slide groove 110, and the foreign matter is a slide groove 110 because there is no straight rail for separating the earth plate supporting the upper portion of the oyster wall and the earth plate supporting the lower portion. It does not interfere with the insertion and separation of the pillar 100 and the earth plate.

도 2(b)는 기둥의 또다른 실시예를 나타내기 위한 도면으로, 상기 도 2(b)에 도시된 바와 같이 상기 기둥(100)의 삽입홈(120)에 보강바(130)가 삽입된다. 상기 보강바(130)는 상기 삽입홈(120)의 폭에 대응하게 형성되어 상기 보강바(130)를 상기 삽입홈(120)에 삽입하였을 경우 삽입홈(120) 내에서 보강바(130)가 쉽게 이동하거나 흔들리지 않게 한다. 또한, 좌우측면에 삽입된 토류판에서 가해지는 힘과 버팀 수단이 미는 힘으로 인한 기둥(100)의 변형을 막는다. 상기 기둥(100)과 상기 보강바(130) 간의 고정을 위하여 상기 기둥(100) 배면에 소정의 간격으로 다수의 고정공(101)을 형성하고 상기 고정공(101)과 보강바(130)를 관통하여 나사결합한다. Figure 2 (b) is a view showing another embodiment of the pillar, as shown in Figure 2 (b) is a reinforcement bar 130 is inserted into the insertion groove 120 of the pillar 100. . The reinforcement bar 130 is formed to correspond to the width of the insertion groove 120, when the reinforcement bar 130 is inserted into the insertion groove 120, the reinforcement bar 130 in the insertion groove 120 Do not move or shake easily. In addition, it prevents the deformation of the pillar 100 due to the force applied by the earth plate inserted into the left and right sides and the pushing force. In order to fix the pillar 100 and the reinforcing bar 130, a plurality of fixing holes 101 are formed on the rear surface of the pillar 100 at predetermined intervals, and the fixing hole 101 and the reinforcing bar 130 are formed. Screw through.

상기 기둥(100)과 상기 보강바(130)를 고정하는 작업 후에 상기 기둥(100)은 크레인 등의 운송장치가 기둥을 들어올린 후 이동시키기 쉽도록 도 2(c)에 도시된 바와 같이 상기 기둥(100) 끝단에서 핀결합하여 고정설치되고 소정 부위에 고리형상의 운반고리(141)가 형성되는 몸체운송구(140)를 사용하여, 크레인 등 운송장치의 발 혹은 고리를 상기 운반고리(141)에 걸고 운송장치가 기둥(100)을 들어올려 이동시키는 것이 가능하다. 그리고 상기 기둥(100)의 하단부는 토굴의 하부에 용이하게 박힐 수 있도록 뾰족하게 형성될 수 있다. After fixing the pillar 100 and the reinforcing bar 130, the pillar 100 is the pillar as shown in FIG. 2 (c) so that a transport device such as a crane can lift and move the pillar. (100) Using the body transport port 140 is fixed to the end coupled to the pin and the ring-shaped transport ring 141 is formed in a predetermined portion, the transport ring 141 to the foot or ring of the transport device, such as a crane It is possible for the transport device to lift and move the column 100. And the lower end of the pillar 100 may be formed pointed to be easily embedded in the lower portion of the crypt.

도 3은 본 고안 슬라이딩 버팀 장치의 버팀 수단을 설명하기 위한 도면으로, 도 3(a)는 버팀 수단과 기둥 결합시의 평면도이고 도 3(b)는 버팀 수단의 결합구를 설명하기 위한 도면이며 도 3(c)는 버팀 수단의 지지대를 설명하기 위한 도면이다.Figure 3 is a view for explaining the brace means of the present invention the sliding brace device, Figure 3 (a) is a plan view when the brace means and the column coupling and Figure 3 (b) is a view for explaining the coupling of the brace means Fig. 3 (c) is a view for explaining the support of the holding means.

상기 도 3(a)에서는 보강바를 포함한 기둥(100)을 실시예로 든다. 도 3(a)에 도시된 바와 같이 상기 버팀 수단은 상기 기둥(100) 중 서로 마주보는 두 기둥(100)을 지지하기 위한 지지대(220)와, 상기 기둥(100)의 삽입홈에 삽입되어 결합하고 상기 지지대(220) 양단에 결합하여 상기 지지대(220)와 각각의 기둥(100)을 결합하게 하는 부기카(211)와 삽입홈을 따라 상기 부기카(211)가 상하로 자유롭게 이동이 가능하게 하는 롤러부(212)로 이루어진 결합구로 구성된다. 상기 결합구는 상기 지지대(220)를 각각의 기둥(100)에 결합하게 하는데 상단과 하단에 각기 지지대(220)를 결합시켜 두 기둥(100)에서 지지대(220)에 가해지는 힘을 분산시켜 주는 역할을 함으로써 안정성을 확보한다. In FIG. 3 (a), the pillar 100 including the reinforcing bar is exemplified. As shown in FIG. 3 (a), the support means is inserted into the support groove 220 for supporting the two pillars 100 facing each other of the pillars 100 and inserted into the insertion groove of the pillar 100 to be coupled. And a coupler to both ends of the supporter 220 to allow the supporter 211 and the respective pillars 100 to be coupled to each other and to allow the bookkeeper 211 to freely move up and down along the insertion groove. It consists of a coupler made of a roller portion 212 to. The coupler couples the support 220 to each of the pillars 100, and combines the supports 220 at the top and the bottom thereof to disperse the force applied to the supports 220 at the two pillars 100. By ensuring the stability.

도 3(b)는 버팀 수단의 결합구를 설명하기 위한 도면으로서, 결합구의 평면도이며 상기 결합구는 상기 삽입홈에 삽입되어 결합하는 부기카(211)와 상기 부기카(211)의 상단과 하단 좌우면에 롤러부(212)를 일체로 형성하여 상기 삽입홈을 따라 가이드되어 공사시에 관로에 설치되는 관 직경에 따라 결합구의 위치를 이동시키고 유동성이 확보되어 상기 결합구를 상기 삽입홈에 부드럽게 삽입하거나 해체하는 것이 가능하게 한다. 본 도에서는 상기 부기카(211)의 상단 좌우면에 각기 한 개씩의 롤러부(212)를 가지고 하단의 좌우면에 각기 두 개씩의 롤러부(212)를 가지 는 결합구를 실시예로 들어 먼저 삽입홈에 삽입되는 부기카(211)의 하부가 쉽게 삽입되도록 한다. Figure 3 (b) is a view for explaining the coupling of the holding means, a top view of the coupling is the coupling unit is inserted into the insertion groove and the bugika 211 and the upper and lower left and right of the bugika 211 The roller unit 212 is integrally formed on the surface to guide the guide along the insertion groove to move the position of the coupler according to the pipe diameter installed in the pipeline at the time of construction and ensure fluidity so that the coupler is gently inserted into the insertion groove. Or dismantle it. In this figure, a coupler having one roller unit 212 on each of the upper left and right sides of the buggy car 211 and two roller units 212 on each of the lower left and right sides is described as an example. The lower part of the buggies 211 to be inserted into the insertion groove is easily inserted.

또한, 상기 롤러부(212)는 상부에 브러쉬(213)를 부착하여 작업시 모래, 자갈, 돌들이 롤러부(212) 내부로 들어가는 것을 막으며 상기 결합구를 상기 삽입홈에서 해체시 상기 삽입홈에 이물질이 끼어있지 않게 털어내는 역할을 하여 해체 작업을 부드럽게 한다.In addition, the roller unit 212 is attached to the brush 213 on the top to prevent sand, gravel, stones from entering the roller unit 212 during the operation and the insertion groove when dismantling the coupler from the insertion groove Smooth out the dismantling work by shaking off foreign matters.

상기 도 3(c)는 상기 지지대의 또다른 실시예로, 양끝단에 다수의 결합공이 형성되어 다수 개가 나사결합하는 지지대(220)를 설명하기 위한 도면이다. 공사 환경과 공사 형태에 따라 서로 마주보는 두 기둥(100) 사이의 거리가 달라지는데, 이 거리에 맞추어 지지대(220)의 개수를 늘리거나 줄일 수 있도록 양끝단에 다수의 결합공을 형성하여 다수 개를 나사결합하여 지지대(220)의 길이를 조절한다.3 (c) is a view for explaining a support 220 in which a plurality of coupling holes are formed at both ends, and a plurality of screws are coupled to each other as an embodiment of the support. The distance between the two pillars 100 facing each other varies according to the construction environment and the construction type, and a plurality of coupling holes are formed at both ends to increase or decrease the number of the supports 220 according to the distance. By screwing to adjust the length of the support (220).

도 4는 본 고안 슬라이딩 버팀 장치의 토류판을 설명하기 위한 도면이다.4 is a view for explaining the earth plate of the present invention the sliding brace device.

상기 도 4에 도시된 바와 같이 상기 기둥 중 인접한 서로 다른 기둥 사이의 슬라이드홈부에 토류판이 삽입적재되는데, 상기 토류판은 슬라이드홈부 내 삽입되는 위치에 따라 외부토류판(301)과 내부토류판(302)으로 구분된다. As shown in FIG. 4, an earth plate is inserted into a slide groove between adjacent different columns among the pillars, and the earth plate is divided into an outer earth plate 301 and an inner earth plate 302 according to the position of the slide plate. do.

상기 외부토류판(301)은 토굴 내 설치시 굴토벽면에 인접한 슬라이드홈부의 외측에 삽입되는 토류판(300)으로, 사각형상의 판이며 양측의 전면과 배면에서 각기 돌출부가 형성되어 상기 슬라이드홈부(110)에 삽입될 시 상기 외부토류판(301)의 일측부부터 삽입이 가능하며, 상기 돌출부에 의해 슬라이드홈부(110)의 소정 영 역을 남겨 내부토류판(302)이 삽입적재되는 공간을 형성한다. The external earth plate 301 is an earth plate 300 inserted into the outside of the slide groove portion adjacent to the oyster wall when installed in the crypt, a rectangular plate is formed in each of the front and rear sides of the projections are formed in the slide groove 110 When it is inserted, it is possible to insert from one side of the external earth plate 301, leaving a predetermined area of the slide groove 110 by the protrusion to form a space in which the internal earth plate 302 is inserted.

상기 내부토류판(302)는 토굴 내 설치시 슬라이드홈부(110)의 내측에 삽입되는 토류판으로, 사각형상의 판이며 상기 외부토류판(301)이 삽입된 후에 삽입되고 상기 내부토류판(302)을 사용함으로써 토류판을 제거하는 작업을 할 경우, 내부토류판(302)을 먼저 제거하여 토류판 제거시 상부에 위치한 토류판을 우선 제거하여 굴토벽면의 상부가 무너져 생기는 안전사고에 대비한다. The inner earth plate 302 is a earth plate inserted into the slide groove 110 when installed in the crypt, a rectangular plate is inserted after the outer earth plate 301 is inserted into the earth plate by using the inner earth plate 302 In the case of the operation to remove, the internal earth plate 302 is removed first to remove the earth plate located at the top when removing the earth plate to prepare for a safety accident caused by the top of the oyster wall surface collapse.

그리고, 상기 도 4에 도시된 바와 같이 상기 토류판은 다수의 토류판이 서로 접하는 소정 부위에 외부결합핀공을 형성한 다수의 결합홈이 형성된다. 각 토류판이 서로 접할 시 상측에 삽입된 토류판의 결합홈과 하측에 삽입된 토류판의 결합홈에 끼워져 연결되는 커넥터(310)에는 상기 외부결합핀공과 핀결합하도록 내부결합핀공이 형성되어 상기 커넥터(310)와 상기 토류판을 고정시킨다.And, as shown in FIG. 4, the earth plate has a plurality of coupling grooves formed with external coupling pin holes at predetermined portions where the plurality of earth plates contact each other. When each earth plate is in contact with each other, the connector 310 is inserted into the coupling groove of the earth plate inserted in the upper side and the coupling groove of the earth plate inserted in the lower portion is connected to the connector 310 is formed with an internal coupling pin hole to pin-couple with the external coupling pin hole is the connector 310 ) And the earth plate.

상기 구성에 따라, 도 1 내지 도 4를 참고하여 본 고안 슬라이딩 버팀 장치의 시공 순서를 설명하자면, 먼저 굴삭 장비를 이용하여 토굴을 소정의 깊이만큼 굴착한 후, 양 굴토벽면을 따라 토류판(300)을 삽입하는데, 굴토벽면에 기대어 토류판(300)을 세우고 맞은 편 굴토벽면에 상기 토류판(300)과 마주보도록 토류판(300)을 세운 후 상기 토류판(300)과 마주보는 토류판(300) 사이의 길이를 측정하여 작업 폭을 확인하는 순서를 마치고 서로 마주보는 두 기둥(100)과 상기 두 기둥(100)을 지지하는 버팀 수단(200)으로 구성된 구조물을 삽입하는데, 상기 구조물이 각 기둥(100)의 일측 슬라이드홉부(110)가 양 굴토벽면에서 마주보는 토류 판(300)의 일측부를 수용하도록 연결한다. According to the above configuration, referring to the construction procedure of the present invention the sliding brace device with reference to Figures 1 to 4, first excavating the crypt by a predetermined depth using the excavation equipment, the earth plate 300 along both oyster wall surface To insert, the earth plate 300 is leaning against the oyster earth wall surface and the earth plate 300 to face the earth plate 300 on the opposite oyster earth wall surface and then the length between the earth plate 300 and the earth plate 300 facing After completion of the procedure to check the working width by measuring the inserting the structure consisting of two pillars (100) facing each other and the support means 200 for supporting the two pillars 100, the structure is one side of each pillar (100) The slide hop 110 is connected to receive one side of the earth plate 300 facing from both oyster wall surface.

구조물 삽입이 끝나면 굴토벽면의 상부를 지지하도록 외부토류판(301)을 각각 삽입하고, 굴삭장비가 소정 깊이를 굴착하고 외부토류판(301)과 상기 구조물을 압입한다. 또다시 소정 깊이를 굴착한 후 내부토류판(302)을 삽입하고 상기 구조물을 압입하며 굴착과 압입을 반복한다. After the structure is inserted, the external earth plate 301 is inserted to support the upper part of the oyster earth wall, and the excavation equipment excavates a predetermined depth and presses the external earth plate 301 and the structure. After digging a predetermined depth again, the inner earth plate 302 is inserted, the structure is pressed in, and the excavation and indentation are repeated.

상기 구조물을 압입할 시에 상기 결합구(210)의 롤러부(212)에 의해 버팀 수단(200)의 하강이 수월하고 관로 설치나 지하 매설작업을 위해 버팀 수단(200)을 용이하게 들어올리는 역할을 하여 삽입홈(120)을 따라 유동적으로 가이드되어 상기 구조물이 강압에 의해 일어나는 변형을 최소화할 수 있다. When press-fitting the structure, the roller portion 212 of the coupler 210 facilitates the lowering of the brace means 200 and easily lifts the brace means 200 for the installation of pipelines or underground works. By being guided fluidly along the insertion groove 120 it is possible to minimize the deformation caused by the step-down structure.

상기 토류판(300)의 기둥(100)이 삽입되지 않은 타측에 상기 구조물을 삽입하고 상기한 과정을 반복하여 본 고안 슬라이딩 버팀 장치를 설치한다. The structure is inserted into the other side of the earth plate 300 in which the pillar 100 is not inserted, and the above-described process is repeated to install the device of the present invention.

본 고안 슬라이딩 버팀 장치는 슬라이드홈부가 일자형으로 형성되어 토류판이 삽입적재될 경우 이물질이 슬라이드홈부와 토류판에 끼어서 조립과 해체를 방해하지 않으며, 설치시 굴토벽면의 상부를 지지하는 외부토류판이 슬라이드홈부에 삽입되는 작업이 측면에서 행해질 수 있도록 형성되어 전선줄 등의 공중장애물에 영향을 받지 않고 설치하여 시가지 등의 환경에서도 작업이 편리한 장점이 있다. The sliding support device of the present invention has a slide groove portion formed in a straight shape, and when the earth plate is inserted, foreign matter is caught in the slide groove and the earth plate so that it does not interfere with assembly and disassembly. Since the work to be inserted is formed so as to be performed from the side, there is an advantage that the work is convenient even in an environment such as a city area by being installed without being affected by air obstacles such as wire cords.

상기 기술한 바와 같이 지지대를 연장하여 연결할 수 있어 토굴의 폭에 제약받지 않고 버팀 수단이 설치어 굴토벽면을 지지하고, 토질 및 지반의 형태에 영향 받지 않고 설치될 수 있으며 설치 및 해제가 간단하여 작업속도를 빠르게 하는 효과가 있다.As described above, the support can be extended and connected so that the support means can be installed without being limited by the width of the crypt to support the oyster wall, and can be installed without being affected by the soil and the form of the ground. It has the effect of speeding up.

그리고, 부기카에 롤러부가 일체로 형성되어 관로에 설치되는 관 직경에 따라 삽입홈 내에 삽입된 결합구를 상하로 자유로이 이동시킬 수 있어 슬라이딩 버팀 장치의 조립 및 해체가 부드럽게 이루어짐이 가능하다.In addition, the roller unit is integrally formed in the buggy car, and the coupling tool inserted into the insertion groove can be freely moved up and down according to the pipe diameter installed in the pipeline, so that the assembly and disassembly of the sliding brace device can be performed smoothly.

또한, 천공 및 항타작업을 실시할 필요가 없으므로 이로 인한 소음 발생이 줄어들고 굴삭기만을 가지고 안전하고 신속하게 작업을 하는 효과가 있다.In addition, since there is no need to perform drilling and driving operations, the noise generated by this is reduced, and there is an effect of working safely and quickly with only an excavator.

그리고, 기둥에 삽입되는 보강바는 토굴과 토류판에서 가해지는 힘으로 인한 기둥의 변형을 막고 지지대에서 가해지는 힘에 대해서도 지탱하는 역할을 하여 강성을 높여주고 삽입홈에 삽입되는 결합구는 지지대에 가해지는 힘을 분산시켜 안정성을 높인다.In addition, the reinforcing bar inserted into the pillar prevents the deformation of the pillar due to the force applied from the crypt and the earth plate, and also supports the force applied from the support to increase the rigidity, and the coupling tool inserted into the insertion groove is applied to the support. Disperses the force to increase stability.

또한, 슬라이드홈부에 삽입되는 토류판은 굴토벽면의 상부와 하부를 지지하므로 토류판 제거시에 하부를 지지하는 내부토류판을 먼저 제거하여 상부 토사의 붕괴를 막아 안전성을 높이는 효과가 있다.In addition, since the earth plate inserted into the slide groove supports the upper and lower portions of the oyster earth wall surface, when the earth plate is removed, first, the internal earth plate supporting the lower part is removed to prevent the collapse of the upper soil, thereby improving safety.

따라서, 이상에서 살펴본 본 고안은 기재된 구체적인 예에 대해서만 상세히 설명되었으나 본 고안의 기술사상범위 내에서 다양한 변형 및 수정이 가능함은 당업자에게 있어서 명백한 것이며, 이러한 변형 및 수정이 첨부된 실용신안청구범위에 속함은 당연한 것이다.Therefore, the present invention as described above has been described in detail only for the specific examples described, but it is apparent to those skilled in the art that various modifications and changes are possible within the technical scope of the present invention, and such modifications and modifications belong to the appended utility model claims. Is a matter of course.

Claims (5)

좌우측면에 각기 하기 토류판(300)이 삽입되는 슬라이드홈부(110)가 형성되고 전면에 하기 결합구(210)가 삽입되어 결합하는 삽입홈(120)이 형성되어 토굴의 양 굴토벽면을 따라 마주보도록 다수 개가 설치되는 기둥(100);Slide grooves 110 into which the earth plate 300 is inserted are formed on the left and right sides thereof, and insertion grooves 120 are formed to be coupled to the following coupling holes 210 to the front to face each other along the oyster walls of the crypt. A plurality of pillars 100 are installed; 상기 기둥(100) 중 서로 마주보는 두 기둥을 지지하기 위한 지지대(220) 및 상기 지지대(220) 양단에 결합하여 상기 지지대(220)와 각각의 기둥을 결합하게 하는 부기카(211)와 상기 부기카(211)의 상단과 하단 좌우면에 각각 일체로 형성되어 상기 삽입홈(120)을 따라 상기 부기카(211)를 가이드시키는 롤러부(212)를 포함하는 결합구(210)로 이루어진 버팀 수단(200); 및The boogie car 211 and the boogie which are coupled to both ends of the support 220 and the support 220 to support the two pillars facing each other of the pillars 100 to couple the respective pillars with the support 220 Reinforcement means consisting of a coupling sphere 210 is formed integrally with the upper and lower left and right sides of the car 211, each of which comprises a roller portion 212 for guiding the boogie car 211 along the insertion groove 120 200; And 상기 기둥(100) 중 인접한 서로 다른 기둥 사이의 슬라이드홈부(110)에 삽입적재되는 토류판(300);을 포함하는 것을 특징으로 하는 슬라이딩 버팀 장치.Sliding bracing apparatus comprising a; earth plate 300 is inserted into the slide groove 110 between the adjacent different ones of the pillars (100). 제 1항에 있어서, 상기 버팀 수단(200)의 지지대(220)는According to claim 1, wherein the support 220 of the brace means 200 양끝단에 다수의 결합공이 형성되어 다수 개가 나사결합하는 것;을 특징으로 하는 슬라이딩 버팀 장치.Sliding brace device, characterized in that a plurality of coupling holes are formed at both ends to screw the plurality of. 제 1항에 있어서,The method of claim 1, 다수의 토류판(300)이 서로 접하는 소정 부위에 외부결합핀공을 형성한 다수의 결합홈이 형성되는 것을 특징으로 하며;Characterized in that a plurality of coupling grooves are formed in a predetermined portion in which a plurality of earth plate 300 is in contact with each other to form an external coupling pin hole; 각 토류판(300)이 서로 접할 시 상측에 삽입된 토류판(300)의 결합홈과 하측에 삽입된 토류판(300)의 결합홈에 끼워져 연결되고 상기 외부결합핀공과 핀결합하도록 내부결합핀공이 형성된 커넥터(310);를 더 포함하는 것을 특징으로 하는 슬라이딩 버팀 장치.When each earth plate 300 is in contact with each other, the connector is inserted into the coupling groove of the earth plate 300 inserted in the upper side and the coupling groove of the earth plate 300 inserted in the lower side, and the inner coupling pin hole is formed so as to pin-couple with the external coupling pin hole Sliding support device, characterized in that it further comprises (310). 제 1항에 있어서, 상기 기둥(100)은The method of claim 1, wherein the pillar 100 is 삽입홈에서 결합구(210)를 삽입한 영역을 제외한 삽입홈의 영역에 삽입되는 보강바(130)를 더 포함하는 것을 특징으로 하고;It characterized in that it further comprises a reinforcement bar 130 is inserted into the region of the insertion groove except the region in which the coupling sphere 210 is inserted in the insertion groove; 배면에 소정의 간격으로 다수의 고정공(101)이 형성되고 상기 고정공(101)과 보강바(130)를 관통하여 나사결합하는 것;을 특징으로 하는 슬라이딩 버팀 장치.A plurality of fixing holes 101 are formed at predetermined intervals on the rear surface and screwed through the fixing holes 101 and the reinforcing bar 130; Sliding brace device, characterized in that. 제 4항에 있어서,The method of claim 4, wherein 상기 기둥 끝단에서 핀결합하여 고정설치되고 소정 부위에 고리형상의 운반고리(141)가 형성되는 몸체운송구(140);를 더 포함하는 것을 특징으로 하는 슬라이딩 버팀 장치.Sliding support device, characterized in that it further comprises; a body transportation port 140 is fixed to the pin end is fixed at the end of the pillar is formed in a ring-shaped transport ring (141).
KR2020060027350U 2006-09-30 2006-09-30 Sliding support device KR200434427Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020060027350U KR200434427Y1 (en) 2006-09-30 2006-09-30 Sliding support device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020060027350U KR200434427Y1 (en) 2006-09-30 2006-09-30 Sliding support device

Publications (1)

Publication Number Publication Date
KR200434427Y1 true KR200434427Y1 (en) 2006-12-20

Family

ID=41782745

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020060027350U KR200434427Y1 (en) 2006-09-30 2006-09-30 Sliding support device

Country Status (1)

Country Link
KR (1) KR200434427Y1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100891949B1 (en) 2008-12-08 2009-04-08 엘에스씨산업기술 주식회사 Temporary retaining wall structure for water supply and drainage works in low depth
KR100935006B1 (en) * 2008-12-08 2010-01-06 엘에스씨산업기술 주식회사 Temporary retaining wall structure for water supply and drainage works in high depth
KR20200001283U (en) * 2020-06-10 2020-06-17 김대운 Earth retaining wall
CN112049119A (en) * 2020-08-14 2020-12-08 同济大学 Sliding type steel support erecting device
CN113957906A (en) * 2021-10-27 2022-01-21 福建省华舜水利水电工程有限公司 Pipeline anti-collapse supporting equipment for water conservancy construction
CN114837197A (en) * 2022-05-29 2022-08-02 赖细玉 Foundation pit supporting structure with foundation pit construction parameter measurement function

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100891949B1 (en) 2008-12-08 2009-04-08 엘에스씨산업기술 주식회사 Temporary retaining wall structure for water supply and drainage works in low depth
KR100935006B1 (en) * 2008-12-08 2010-01-06 엘에스씨산업기술 주식회사 Temporary retaining wall structure for water supply and drainage works in high depth
WO2010068013A2 (en) * 2008-12-08 2010-06-17 코오롱건설주식회사 Temporaty soil retaining wall structure for water supply and drainage works in low depth
WO2010068014A2 (en) * 2008-12-08 2010-06-17 코오롱건설주식회사 Temporary soil retaining wall structure for water supply and drainage works deep underground
WO2010068013A3 (en) * 2008-12-08 2010-10-21 코오롱건설주식회사 Temporaty soil retaining wall structure for water supply and drainage works in low depth
WO2010068014A3 (en) * 2008-12-08 2010-10-21 코오롱건설주식회사 Temporary soil retaining wall structure for water supply and drainage works deep underground
KR20200001283U (en) * 2020-06-10 2020-06-17 김대운 Earth retaining wall
KR200492803Y1 (en) * 2020-06-10 2020-12-14 김대운 Earth retaining wall
CN112049119A (en) * 2020-08-14 2020-12-08 同济大学 Sliding type steel support erecting device
CN112049119B (en) * 2020-08-14 2021-06-04 同济大学 Sliding type steel support erecting device
CN113957906A (en) * 2021-10-27 2022-01-21 福建省华舜水利水电工程有限公司 Pipeline anti-collapse supporting equipment for water conservancy construction
CN114837197A (en) * 2022-05-29 2022-08-02 赖细玉 Foundation pit supporting structure with foundation pit construction parameter measurement function
CN114837197B (en) * 2022-05-29 2023-11-10 中铁五局集团第二工程有限责任公司 Foundation pit supporting structure with measure foundation pit construction parameter

Similar Documents

Publication Publication Date Title
KR200434427Y1 (en) Sliding support device
KR20010064667A (en) Method of building underground structure
KR101396517B1 (en) Construction method of the underground tunnel and, structure for the slab construction
KR101408667B1 (en) Method of constructing new tunnel using pre-existing tunnel structure
KR20130114340A (en) Soil sheath apparatus and method thereof
KR101256938B1 (en) Retaining wall device
KR200389266Y1 (en) Slide rail type shoring apparatus
JP6068774B1 (en) Earth retaining prior construction method using adjustable erection
JP2012112104A (en) Tunnel leg reinforcing structure
KR101249660B1 (en) Earth pressure supporting method of walls trench applying construction of none- excavation underground structure
KR101753223B1 (en) Soil retaining panel assembly having soil retaining supporter
KR101426511B1 (en) A temporary skeleton system used in constructuring a underground structure of a building and a top down underground construction method using a temporary skeleton system
JP6387778B2 (en) Suspension jig used when building the core material of the underground continuous wall, the method of building the core material of the underground continuous wall, and the system for building the core material of the underground continuous wall
KR100959946B1 (en) Constructing method of loop structure by tension force and loop structure constructed by this
KR101060571B1 (en) Box type propulsion pipe connecting structure and construction method thereof
KR20130030340A (en) Structure of retaining wall and construction method for installing underground structures
KR101745570B1 (en) Panel assembly for soil retaining
KR200416567Y1 (en) Pile chamber type trench shoring apparatus
CN204898737U (en) Structure is propped to detachable trading in underground structure post -cast strip
JP3183635U (en) Square frame for earth retaining
KR200494035Y1 (en) Corner shoe jacks for stiffening steel
JP2015108262A (en) Reaction receiving member and positioning method for upper surface of permanent steel column
CN219137712U (en) Collapse-preventing safety device for shallow slotting construction
KR200431928Y1 (en) Supporting structure for being used to excavated ground
JP7356106B2 (en) How to erect structural pillars and the Yatco connection jig used for that method

Legal Events

Date Code Title Description
REGI Registration of establishment
T201 Request for technology evaluation of utility model
EXTG Extinguishment
T601 Decision on revocation of utility model registration