KR20040100678A - Pipe material weight configuration method in power plant - Google Patents

Pipe material weight configuration method in power plant Download PDF

Info

Publication number
KR20040100678A
KR20040100678A KR1020030033097A KR20030033097A KR20040100678A KR 20040100678 A KR20040100678 A KR 20040100678A KR 1020030033097 A KR1020030033097 A KR 1020030033097A KR 20030033097 A KR20030033097 A KR 20030033097A KR 20040100678 A KR20040100678 A KR 20040100678A
Authority
KR
South Korea
Prior art keywords
weight
piping material
calculating
data
power plant
Prior art date
Application number
KR1020030033097A
Other languages
Korean (ko)
Inventor
김대중
Original Assignee
두산중공업 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 두산중공업 주식회사 filed Critical 두산중공업 주식회사
Priority to KR1020030033097A priority Critical patent/KR20040100678A/en
Publication of KR20040100678A publication Critical patent/KR20040100678A/en

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

PURPOSE: A method for fixing a weight of pipeline materials used in a power plant with an automatic calculation formulation is provided to accurately calculate the weight of each pipeline material and reduce time needed for calculation by inputting dimension data of the selected pipeline materials to a weight calculating formulation. CONSTITUTION: The pipeline material to calculate the weight is selected(S10). The dimension data of the selected pipeline material is inputted(S11). If all data is inputted to an input window, the weight calculating formulation is loaded(S13). The weight of the selected pipeline material is calculated/output by the loaded weight calculating formulation(S14).

Description

발전 설비에서의 배관자재 중량 설정 방법{PIPE MATERIAL WEIGHT CONFIGURATION METHOD IN POWER PLANT}PIPE MATERIAL WEIGHT CONFIGURATION METHOD IN POWER PLANT}

본 발명은 발전 설비의 배관자재에 관한 것으로, 특히 발전 설비에서의 배관 자재의 중량을 산출하는 경우, 선택된 배관 자재의 치수 데이터를 입력하면, 입력창의 모든 데이터를 입력하였는 지 여부를 확인하여, 이상이 없으면 로딩된 중량 산출 공식에 따라, 상기 선택된 배관 자재의 중량을 자동으로 산출하여 출력하는 발전 설비에서의 배관자재 중량 설정 방법에 관한 것이다.The present invention relates to the piping material of the power generation equipment, in particular, when calculating the weight of the piping material in the power generation equipment, inputting the dimensional data of the selected piping material, it is confirmed whether all the data in the input window has been entered, The absence of the present invention relates to a pipe material weight setting method in a power generation facility that automatically calculates and outputs the weight of the selected pipe material according to the loaded weight calculation formula.

일반적으로, 발전 설비에 사용되는 배관자재로는 엘보우(Elbow), 티(Tee), 리듀서(Reducer), 캡(Cap) 등이 있다.In general, piping materials used in power generation facilities include elbows, tees, reducers, caps, and the like.

엘보우는 관 속을 흐르는 유체의 방향을 갑자기 바꾸는 장소에 사용하는 관이음을 말하는 것으로, 가단주철 또는 청동 ·황동으로 만들어지는데, 관과 접속시키기 위해 그 양 끝에 암나사를 내어 90 °의 각도를 이루는 것이 보통이다.Elbow refers to a pipe used for a place that suddenly changes the direction of fluid flowing through a pipe. It is made of malleable iron or bronze and brass. is average.

이 밖에, 엘보우의 종류로는 45 °엘보우, 수나사 엘보우, 스트리트 엘보우, 45 °스트리트 엘보우, 다른지름 엘보우 등이 있다.Other types of elbows include 45 ° elbows, male elbows, street elbows, 45 ° street elbows, and other diameter elbows.

그리고, 티는 관을 흐르는 유체의 방향을 수직으로 바꾸기 위하여 사용하는 관이음으로, 영어 알파벳 'T' 모양을 하고 있으며, 리듀서는 지름이 서로 다른 관과 관을 접속하는 데 사용하는 관이음을 말하고, 캡은 관 끝이나 관 구멍을 막는 관이음을 말한다.In addition, the tee is a tube joint used to change the direction of the fluid flowing through the tube vertically, and has the shape of the English alphabet 'T', and the reducer is a tube joint used to connect tubes with different diameters. The cap is a tube that covers the end of the tube or the tube hole.

일반적으로, 발전 설비는 그 부피가 아주 크므로, 이에 사용되는 배관의 종류 및 수가 무수히 많고, 각 배관을 연결하는 배관자재 또한 무수히 많이 사용되고 있다.In general, since the power generation equipment is very large in volume, there are many types and numbers of pipes used therein, and a number of pipe materials connecting each pipe are also used.

즉, 배관의 종류, 크기에 따라 관이음 역할을 하는 배관자재의 종류와 크기도 달라지게 되는데, 발전 설비에 의해 발생하는 압력, 온도 및 외란 등에 견디는 지 여부를 결정하기 위하여는 각 종류별로 배관 및 그 배관자재의 중량을 산출할 필요가 있게 된다.In other words, the type and size of piping materials that act as pipe joints also vary depending on the type and size of the pipe.In order to determine whether to withstand the pressure, temperature and disturbance generated by the power generation facilities, It is necessary to calculate the weight of the piping material.

그런데, 상기와 같은 종래의 기술에 있어서, 발전설비에 있어서 배관자재의 중량을 산출하는 경우, 다양한 단품에 대하여 각 단품별로 중량을 산출하는 방법이 존재하지 않아, 규격화된 배관 자재의 중량을 기준으로 수작업으로 중량을 추정하여 산출함으로써, 그 결과에 오류가 발생할 가능성이 많을 뿐만 아니라, 수계산을 위하여 많은 시간이 소요되는 문제점이 있었다. .By the way, in the conventional technique as described above, in the case of calculating the weight of the piping material in the power generation equipment, there is no method of calculating the weight for each single product for various single products, and based on the weight of the standardized piping material By estimating and calculating the weight by hand, not only the error is likely to occur in the result, but also there is a problem that it takes a lot of time to calculate the number. .

따라서, 본 발명은 상기와 같은 종래의 문제점을 해결하기 위하여 제안한 것으로, 발전 설비에서의 배관 자재의 중량을 산출하는 경우, 선택된 배관 자재의 치수 데이터를 입력하면, 입력창의 모든 데이터를 입력하였는 지 여부를 확인하여, 이상이 없으면 로딩된 중량 산출 공식에 따라, 상기 선택된 배관 자재의 중량을 자동으로 산출하여 출력하도록 하는 방법을 제공함에 그 목적이 있다.Therefore, the present invention has been proposed to solve the above-described problems, and when calculating the weight of the piping material in the power generation equipment, inputting the dimensional data of the selected piping material, whether all the data of the input window is entered or not By checking, if there is no abnormality, the object of the present invention is to provide a method for automatically calculating and outputting the weight of the selected piping material according to the loaded weight calculation formula.

도1은 본 발명 발전 설비에서의 배관자재 중량 설정 방법의 동작과정을 보인 순서도.1 is a flow chart showing the operation of the piping material weight setting method of the present invention installation.

도2는 본 발명 발전 설비에서의 배관자재 중량 설정 방법을 구현한 장치의 구성을 보인 블록도.Figure 2 is a block diagram showing the configuration of a device implementing the method of setting the weight of the piping material in the power generation equipment of the present invention.

도3은 본 발명 발전 설비에서의 배관자재 중량 설정 방법에서, 엘보우의 중랴응ㄹ 산출하기 위한 입력창의 예를 보인 도.Figure 3 shows an example of an input window for calculating the weight of the elbow in the pipe material weight setting method of the present invention power plant.

***도면의 주요 부분에 대한 부호의 설명****** Description of the symbols for the main parts of the drawings ***

20 : 입력 수단 21 : 제어 수단20: input means 21: control means

22 : 저장 수단 23 : 출력 수단22: storage means 23: output means

이와 같은 목적을 달성하기 위한 본 발명은, 중량을 산출하고자 하는 배관 자재를 선택하여, 상기 선택된 배관 자재의 치수 데이터를 입력하는 단계와; 입력창의 모든 데이터를 입력하였는 지 여부를 확인하여, 이상이 없으면 중량 산출 공식을 로딩하는 단계와; 상기 로딩된 중량 산출 공식에 따라, 선택된 배관 자재의 중량을 산출하여 출력하는 단계를 포함하는 것을 특징으로 한다.The present invention for achieving the above object comprises the steps of selecting the piping material to be calculated by weight, inputting the dimension data of the selected piping material; Checking whether all data of the input window has been input, and if there is no abnormality, loading the weight calculation formula; And calculating and outputting the weight of the selected piping material according to the loaded weight calculation formula.

이하, 본 발명에 따른 일실시예를 첨부한 도면을 참조하여 상세히 설명하면 다음과 같다.Hereinafter, an embodiment according to the present invention will be described in detail with reference to the accompanying drawings.

도1은 본 발명 발전 설비에서의 배관자재 중량 설정 방법의 동작과정을 보인 순서도로서, 이에 도시한 바와 같이, 중량을 산출하고자 하는 배관 자재를 선택하는 단계(S10)와; 상기 선택된 배관 자재의 치수 데이터를 입력하는 단계(S11)와; 입력창의 모든 데이터를 입력하였는 지 여부를 확인하여, 이상이 없으면 중량 산출 공식을 로딩하는 단계(S12,S13)와; 상기 로딩된 중량 산출 공식에 따라, 선택된 배관 자재의 중량을 산출하여 출력하는 단계(S14)로 구성한다.Figure 1 is a flow chart showing the operation of the pipe material weight setting method in the power plant of the present invention, as shown in the step, selecting the piping material to calculate the weight (S10); Inputting dimension data of the selected piping material (S11); Checking whether all data of the input window has been input, and if there is no abnormality, loading the weight calculation formula (S12 and S13); According to the loaded weight calculation formula, the step of calculating and outputting the weight of the selected piping material (S14).

그리고, 도2는 본 발명을 구현한 장치의 구성을 보인 블록도로서, 입력 수단(20), 제어 수단(21), 저장 수단(22), 출력 수단(23)으로 구성한다.FIG. 2 is a block diagram showing the configuration of an apparatus embodying the present invention, and comprises an input means 20, a control means 21, a storage means 22, and an output means 23. As shown in FIG.

본 발명에서, 저장 수단(22)은 발전 설비에서 사용되는 각 배관자재에 대한 도면 정보, 중량산출에 필요한 데이터 항목에 대한 정보, 중량 산출 공식에 대한 정보를 기저장한 다음, 사용자가 중량 산출을 하고자 하는 경우 제어 수단(21)의 제어에 의해 상기 기저장된 정보를 로딩하여 선택된 배관자재의 중량을 산출하게된다.In the present invention, the storage means 22 stores the drawing information for each piping material used in the power generation equipment, the information on the data items necessary for weight calculation, the information on the weight calculation formula, and then the user calculates the weight. If desired, the previously stored information is loaded by the control of the control means 21 to calculate the weight of the selected piping material.

이하, 본 발명의 동작 과정을 살펴보면, 발전 설비에서 사용되는 각 배관자재의 중량을 산출하고자 하는 경우, 사용자는 입력 수단(20)을 통해 저장 수단(22)에 기저장된 각 배관자재에 대한 도면 정보 및 중량산출에 필요한 데이터 항목에 대한 정보를 로딩하게 한 다음, 먼저 중량을 산출하고자 하는 배관 자재를 선택하여(S10), 선택된 배관 자재의 치수 데이터를 입력한다(S11).Hereinafter, referring to the operation process of the present invention, if the user wants to calculate the weight of each piping material used in the power generation facility, the user is drawing information about each piping material pre-stored in the storage means 22 through the input means 20 And loading information on a data item required for weight calculation, first, selecting a piping material to calculate a weight (S10), and inputting dimension data of the selected piping material (S11).

통상적으로, 발전 설비에 사용되는 배관자재로는 엘보우(Elbow), 티(Tee), 리듀서(Reducer), 캡(Cap) 등이 있으므로, 사용자는 상기 배관자재 중 어느 하나의 원하는 항목을 선택하게 된다.In general, piping materials used in power generation facilities include elbows, tees, reducers, caps, and the like, so that the user selects any one of the piping materials. .

예를 들어, 사용자가 엘보우의 중량을 산출하고자 하는 경우, 도3과 같은 입력창이 출력 수단(23)을 통해 나타나는데, 상기 입력창은 선택된 배관자재의 중량을 계산하는 데 사용된 공식 및 그 결과값을 나타내는 영역(10), 상기 영역(10)에 기재된 각 인자에 대해 설명하는 영역(11), 선택된 배관자재의 치수 데이터를 입력하는 영역(12), 선택된 배관자재에 대한 도면 정보를 나타내는 영역(13)으로 구분된다.For example, if the user wants to calculate the weight of the elbow, an input window as shown in Fig. 3 is displayed through the output means 23, which input formula is used to calculate the weight of the selected piping material and the resulting value. A region 10 indicating the region, an region 11 describing each factor described in the region 10, an region 12 for inputting the dimension data of the selected piping material, and an region showing drawing information about the selected piping material ( 13).

즉, 사용자가 배관자재 중 엘보우를 선택하였으므로, 사용자는 입력 수단(20)을 통해 엘보우의 치수 데이터를 입력하는 영역(12)에 필요한 데이터를 입력하면, 제어 수단(21)은 모든 항목을 다 입력하였는지 여부를 확인하여(S12) 모든 항목에 대해 데이터 입력이 완료된 경우 상기 저장 수단(22)에 저장된 중량산출 공식을 로딩한 다음(S13), 중량을 산출하여 엘보우의 중량을 계산하는 데 사용된 공식 및 그 결과값을 나타내는 영역(10)에 해당 엘보우의 중량값을 출력한다(S14).That is, since the user has selected the elbow of the piping material, when the user inputs the necessary data in the area 12 for inputting the dimension data of the elbow through the input means 20, the control means 21 inputs all items. When the data input is completed for all items (S12), the weight calculation formula stored in the storage means 22 is loaded (S13), and then the formula used to calculate the weight of the elbow by calculating the weight. And outputs the weight value of the elbow to the region 10 representing the resultant value (S14).

여기서, 상기 입력창은 공식 및 그 결과값을 나타내는 영역(10)에 기재된 각 인자에 대한 설명을 영역(11)을 통해 표시하고, 해당 인자들이 나타내는 엘보우 도면 상의 위치를 선택된 배관자재에 대한 도면 정보를 나타내는 영역(13)을 통해 표시함으로써, 사용자의 이해를 돕고 있다.Here, the input window displays a description of each factor described in the region 10 representing the formula and the result value through the region 11, and the drawing information on the selected piping material for the position on the elbow drawing indicated by the corresponding factors. By displaying through the area 13 indicating, it is helpful for the user to understand.

이상에서 설명한 바와 같이, 본 발명은 발전 설비에서의 배관 자재의 중량을 산출하는 경우, 선택된 배관 자재의 치수 데이터를 입력하면, 입력창의 모든 데이터를 입력하였는 지 여부를 확인하여, 이상이 없으면 로딩된 중량 산출 공식에 따라, 상기 선택된 배관 자재의 중량을 산출하여 출력함으로써, 각 배관자재의 중량을 정확하게 산출함과 아울러, 중량 산출에 소요되는 시간을 절약하는 효과가 있다.As described above, in the present invention, when calculating the weight of the piping material in the power generation equipment, if the dimension data of the selected piping material is input, it is checked whether all the data of the input window is input, By calculating and outputting the weight of the selected piping material according to the weight calculation formula, it is possible to accurately calculate the weight of each piping material and save time required for the weight calculation.

Claims (1)

중량을 산출하고자 하는 배관 자재를 선택하여, 상기 선택된 배관 자재의 치수 데이터를 입력하는 단계와; 입력창의 모든 데이터를 입력하였는 지 여부를 확인하여, 이상이 없으면 중량 산출 공식을 로딩하는 단계와; 상기 로딩된 중량 산출 공식에 따라, 선택된 배관 자재의 중량을 산출하여 출력하는 단계를 포함하는 것을 특징으로 하는 발전 설비에서의 배관자재 중량 설정 방법.Selecting a piping material for which weight is to be calculated and inputting dimension data of the selected piping material; Checking whether all data of the input window has been input, and if there is no abnormality, loading the weight calculation formula; And calculating and outputting the weight of the selected piping material according to the loaded weight calculation formula.
KR1020030033097A 2003-05-23 2003-05-23 Pipe material weight configuration method in power plant KR20040100678A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020030033097A KR20040100678A (en) 2003-05-23 2003-05-23 Pipe material weight configuration method in power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020030033097A KR20040100678A (en) 2003-05-23 2003-05-23 Pipe material weight configuration method in power plant

Publications (1)

Publication Number Publication Date
KR20040100678A true KR20040100678A (en) 2004-12-02

Family

ID=37378037

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020030033097A KR20040100678A (en) 2003-05-23 2003-05-23 Pipe material weight configuration method in power plant

Country Status (1)

Country Link
KR (1) KR20040100678A (en)

Similar Documents

Publication Publication Date Title
RU2321880C2 (en) Flow speed measuring module and respective measuring method
Wood et al. Numerical methods for modeling transient flow in distribution systems
US8823751B2 (en) Size based display of piping systems
CN102622484B (en) Method for automatically and designing pipeline of power plant
CN112222690B (en) Method for establishing pipeline weld joint management information
US20190195722A1 (en) Piping Network Leak Detection System, as Well as Leak Detection Device and Leak Detection Method Used in Said System
CN108733012A (en) Meet the control system of production equipment energy consumption limitation in industrial gasses piping network
Hyde et al. Life estimation of pressurised pipe bends using steady-state creep reference rupture stresses
WO2013192247A1 (en) System and method for calculating and reporting maximum allowable operating pressure
Caputo et al. An inverse approach for piping networks monitoring
Turkowski et al. New criteria for the experimental validation of CFD simulations
Sharp et al. Optimizing the ASME Venturi recovery cone angle to minimize head loss
KR20040100678A (en) Pipe material weight configuration method in power plant
Lyons et al. Assessment of the applicability of failure frequency models for dense phase carbon dioxide pipelines
Camperos et al. Experimental study for detection of leaks in horizontal pipelines
JP2006244072A (en) In-plant state simulation method and system
WO2023175383A1 (en) A system and method for automated and integrated plant design
KR102373756B1 (en) Method and device for evaluating the support gap of piping
CA3153418A1 (en) Fluid pressure monitoring system using flow data
US6772103B1 (en) Method for selecting a parts kit detail
KR20220161582A (en) Piping material take off method of bidding stage with automation solutions
González et al. Leak estimation method for complex pipelines with branch junctions
US6578024B2 (en) Hierarchical relational definition system for defining an object and method therefor
CN105181043A (en) Intelligent monitoring type ultrasonic flow adjusting device and application method thereof
CN110362901B (en) Spacecraft pipeline data multiplexing method

Legal Events

Date Code Title Description
WITN Withdrawal due to no request for examination