KR200392674Y1 - Auger crane for winding electric wire - Google Patents

Auger crane for winding electric wire Download PDF

Info

Publication number
KR200392674Y1
KR200392674Y1 KR20-2005-0013421U KR20050013421U KR200392674Y1 KR 200392674 Y1 KR200392674 Y1 KR 200392674Y1 KR 20050013421 U KR20050013421 U KR 20050013421U KR 200392674 Y1 KR200392674 Y1 KR 200392674Y1
Authority
KR
South Korea
Prior art keywords
wire
winding
crane
reused
present
Prior art date
Application number
KR20-2005-0013421U
Other languages
Korean (ko)
Inventor
심재길
Original Assignee
심재길
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 심재길 filed Critical 심재길
Priority to KR20-2005-0013421U priority Critical patent/KR200392674Y1/en
Application granted granted Critical
Publication of KR200392674Y1 publication Critical patent/KR200392674Y1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G11/00Arrangements of electric cables or lines between relatively-movable parts
    • H02G11/02Arrangements of electric cables or lines between relatively-movable parts using take-up reel or drum

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Storage Of Web-Like Or Filamentary Materials (AREA)

Abstract

본 고안은 권선용 오가크레인에 관한 것으로, 더욱 상세하게는 폐전선 철거 작업시 및 재사용 전선 철거 작업시 사용되는 권선용 오가크레인에 관한 것이다. The present invention relates to a winding oga crane, and more particularly to a winding oga crane used in the waste wire demolition work and reusable wire demolition work.

본 고안은 전주 굴착용 스크류 및 전선 권선기를 선택적으로 결합할 수 있는 결합부와; 상기 결합부에 결합되며, 일정한 길이로 절단된 폐전선 또는 재사용 전선이 그 외주에 감기도록 원기둥의 드럼 모양을 갖고 상기 폐전선 또는 재사용 전선이 권선되도록 하는 전선 권선기를 구비하는 권선용 오거크레인을 제공한다.The present invention and the coupling portion that can selectively couple the electric pole drilling screw and wire winding machine; It is coupled to the coupling portion, and provides a winding auger crane having a wire-shaped winding machine for winding the closed wire or reused wire having a cylindrical drum shape so that the closed wire or reused wire cut to a predetermined length is wound around the outer periphery thereof. .

Description

권선용 오가크레인{AUGER CRANE FOR WINDING ELECTRIC WIRE}AUGER CRANE FOR WINDINGS {AUGER CRANE FOR WINDING ELECTRIC WIRE}

본 고안은 권선용 오가크레인에 관한 것으로, 더욱 상세하게는 폐전선 철거 작업시 및 재사용 전선 철거 작업시 사용되는 권선용 오가크레인에 관한 것이다. The present invention relates to a winding oga crane, and more particularly to a winding oga crane used in the waste wire demolition work and reusable wire demolition work.

일반적으로, 전주(電柱)는 전신, 전화, 전등 등의 전선을 지지하는 기둥으로, 주로 교류 배전 선로의 지지물로서 사용되는 것이며, 목주, 철근콘크리트주, 철주(鐵柱) 등이 있다. 전주에는 고압 및 저압 배전선이 병가(倂架)되는 것이 많으며, 이로 인해 상단 가까이에 완목 또는 금속제의 래크를 고정하고 이것에 애자를 장착하여 전선을 지지한다. 또한, 전선의 지상 높이의 최저에 대해서는 규정값이 있으며, 또 전선의 상호간격도 충분히 취해야 하는데 이런 것으로부터 전주의 높이나 완목의 치수가 정해진다. In general, electric poles are pillars that support electric wires such as telegraphs, telephones, electric lights, and the like, and are mainly used as a support for AC distribution lines, such as wooden poles, reinforced concrete poles, and iron poles. In the electric pole, high-voltage and low-voltage distribution lines are often left sick, and thus, hardwood or metal racks are fixed near the top and insulators are mounted to support the wires. In addition, there is a prescribed value for the minimum of the ground height of the electric wire, and the mutual clearance of the electric wire must also be sufficiently taken. From this, the height of the pole and the dimensions of the timber are determined.

한편, 전주 사이를 연결하는 전선의 철거 작업을 할 경우, 일반적으로 전선의 정해져 있는 소정의 위치에서만 전선의 절단이 가능하게 되어 있다. 따라서, 종래 전주 사이를 연결하고 있는 전선의 철거 작업을 행할 경우에는, 전선의 정해진 위치에서 전선의 절단을 행한 다음, 전선 철거를 위하여 철거 작업을 수행하는 작업자들에 의해 인력으로 전선을 되감기할 필요가 있었다. On the other hand, when carrying out the removal work of the electric wire which connects between electric poles, in general, the electric wire can be cut | disconnected only in the predetermined | prescribed predetermined position of an electric wire. Therefore, in the case of dismantling the electric wires connected between conventional poles, it is necessary to rewind the electric wires by manpower by workers who perform the electric dismantling work for electric wire dismantling after cutting the electric wires at the fixed positions of electric wires. There was.

이와 같은 작업을 하게 되면, 전선의 철거 작업시에 전선을 되감는 작업에 많은 인력이 투입될 뿐만 아니라, 도로나 인도 주변에서 전선 철거 작업을 행할 경우에는 전선 철거를 행하는 동안에 도로 변에 주차되어 있는 차량이나 인도를 통행하고 있는 보행자의 안전에 위험을 불러 올 소지가 많으며, 나아가 이들의 안전을 보장하기 위해서 교통을 통제하는 인원이 배치되어야만 하는 문제점을 갖고 있었다. This work not only puts a lot of manpower into rewinding the wires during the demolition of the wires, but also when parked around the roads or sidewalks, they are parked alongside the roads during the demolition of the wires. There are many risks to the safety of vehicles and pedestrians passing through the road, and furthermore, there is a problem that personnel to control traffic must be arranged to ensure their safety.

본 고안은 상기와 같은 문제점을 해결하기 위해 만들어진 것으로, 전주의 전선 철거 작업시에 인력에 의하여 전선을 되감을 경우 발생하는 불필요한 인력 낭비를 방지할 수 있을 뿐만 아니라, 철거 작업이 진행되고 있는 도로 변의 주차 차량의 안전 및 그 주위를 통행하고 있는 보행자의 안전을 확보할 수 있으며, 철거한 전선을 균일하게 한(1) 드럼씩으로 되감기하는 것이 가능하여 철거 전선의 운반이나 재사용 전선의 운반을 용이하게 만드는 권선용 오가크레인을 제공하는 것을 목적으로 한다. The present invention has been made to solve the above problems, and can not only prevent unnecessary waste of personnel caused by rewinding the electric wire by personnel during the electric wire demolition work of the week, as well as changing the road side where the demolition work is in progress. It is possible to secure the safety of the parking vehicle and the safety of pedestrians traveling around it, and to rewind the demolished wires to uniform (1) drums, making it easy to carry the demolition wires or carry the reusable wires. It is an object to provide an organocrane for winding.

본 고안에 따르면, 전주 굴착용 스크류 및 전선 권선기를 선택적으로 결합할 수 있는 결합부와; 상기 결합부에 결합되며, 일정한 길이로 절단된 폐전선 또는 재사용 전선이 그 외주에 감기도록 원기둥의 드럼 모양을 갖고 상기 폐전선 또는 재사용 전선이 권선되도록 하는 전선 권선기를 구비하는 권선용 오거크레인을 제공한다. According to the present invention, the coupling portion that can selectively couple the electric pole drilling screw and wire winding machine; It is coupled to the coupling portion, and provides a winding auger crane having a wire-shaped winding machine for winding the closed wire or reused wire having a cylindrical drum shape so that the closed wire or reused wire cut to a predetermined length is wound around the outer periphery thereof. .

이하 첨부된 도면을 참조하여, 본 고안의 바람직한 실시예를 상세히 설명하기로 한다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정해서 해석되어서는 아니되며, 고안자는 그 자신의 고안을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 고안의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다. 따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 고안의 가장 바람직한 일 실시예에 불과할 뿐이고, 본 고안의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들을 대체할 수 있는 다양한 균등물과 변경 및 변형예들이 있을 수 있음을 이해하여야 한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. Prior to this, the terms or words used in this specification and claims should not be construed as being limited to their usual or dictionary meanings, and the inventors will properly describe the concept of terms in order to best explain their own design. Based on the principle that it can be defined, it should be interpreted as meaning and concept corresponding to the technical idea of the present invention. Therefore, the embodiments described in the present specification and the configuration shown in the drawings are only one of the most preferred embodiments of the present invention, and do not represent all of the technical ideas of the present invention, which can be replaced at the time of the present application. It should be understood that there may be various equivalents, modifications, and variations.

이하에서, 첨부된 도면을 참조하여, 본 고안에 따른 실시예에 대하여 설명하도록 한다. Hereinafter, with reference to the accompanying drawings, it will be described an embodiment according to the present invention.

도 1은 권선용 오가크레인을 나타내는 도면이다. 본 고안의 일 실시예에 따른 권선용 오가크레인(100)은 전주 굴착용 스크류(도시하지 않음) 및 전선 권선기(10)를 선택적으로 결합할 수 있는 결합부(20)와, 상기 결합부(20)에 결합되며 일정한 길이로 절단된 폐전선 또는 재사용 전선이 그 외주에 감기도록 원기둥의 드럼 모양을 갖고 상기 폐전선 또는 재사용 전선이 권선되도록 하는 전선 권선기(10)를 구비한다. 1 is a view showing an organ crane for winding. Oga crane 100 for winding according to an embodiment of the present invention is a coupling portion 20 that can selectively couple the electric pole drilling screw (not shown) and the wire winding machine 10, and the coupling portion 20 And a wire winding machine (10) having a cylindrical drum shape such that a closed wire or reused wire cut to a predetermined length is wound around the periphery thereof, and the closed wire or reused wire is wound.

전선 권선기(10)는 법규에 의해 정해져 있는 소정의 길이로 절단된 폐전선 또는 재사용 전선이 그 외주에 감기도록 권선할 수 있으며, 오가크레인(100)이 좌우회전이 가능하기 때문에 이와 같은 회전력을 이용하여 전선 권선이 가능하게 된다. The wire winding machine 10 may be wound so that the closed wire or reused wire cut to a predetermined length determined by law may be wound around its outer circumference, and the oga crane 100 may be rotated left and right to use such rotational force. This enables wire winding.

또한, 전선 권선기(10)는 그 모양이 원기둥 모양으로 도면 상에 도시되어 있지만, 이에 한정되는 것은 아니며 원기둥은 물론이고 다각형 모양이 될 수도 있다는 것은 당업자에게 자명한 사실이다. In addition, although the shape of the wire winding machine 10 is shown in the drawings in the shape of a cylinder, it is apparent to those skilled in the art that the present invention is not limited thereto and may be a polygon as well as a cylinder.

결합부(20)는 전주 굴착용 스크류(도시하지 않음) 및 전선 권선기(10)를 선택적으로 결합할 수 있는 부분이다. 전주 굴착용 스크류와 전선 권선기(10) 및 결합부(20) 사이의 결합은 다양한 결합 방법이 가능함은 물론이다. Coupling portion 20 is a portion that can selectively couple the electric pole drilling screw (not shown) and the wire winding machine (10). The coupling between the electric pole drilling screw and the wire winding machine 10 and the coupling unit 20 is a variety of coupling methods are possible, of course.

또한, 전선 권선기(10)와 결합부(20)를 제외한 오가크레인(100)의 나머지 부분은 일반적인 오가크레인의 구성 및 기능을 따르게 된다. In addition, the remaining portion of the organocrane 100 except for the wire winding machine 10 and the coupling portion 20 will follow the configuration and function of the general organocrane.

다음으로 이와 같은 권선용 오가크레인을 사용하여 폐전선 또는 재사용 전선을 권선하는 방법에 대하여 알아 보기로 한다. Next, a method of winding a closed wire or a reusable wire by using the Oga crane for winding will be described.

도 2는 권선용 오가크레인을 사용한 권선 방법을 나타내는 플로우차트이다. Fig. 2 is a flowchart showing a winding method using a winding oga crane for winding.

본 고안의 일 실시예에 따른 권선용 오가크레인을 사용한 권선 방법은, 일정한 길이로 절단된 폐전선 또는 재사용 전선의 일단을 전선 권선기(10)에 결합하는 단계(S100)와, 상기 폐전선 또는 재사용 전선의 일단이 결합된 전선 권선기(10)를 작동하여 상기 전선 권선기(10)의 외주에 폐전선 또는 재사용 전선을 권선하는 단계(S200)를 구비한다. Winding method using the winding Ogacrane according to an embodiment of the present invention, the step of coupling one end of the closed wire or reused wire cut to a predetermined length to the wire winding machine 10 (S100), the closed wire or reused wire It is provided with a step (S200) of winding a closed wire or reused wire on the outer circumference of the wire winding machine 10 by operating the wire winding machine 10, one end of which is coupled.

단계 S100에서는 법규에 의하여 정해져 있는 소정의 길이로 절단된 폐전선 또는 재사용 전선의 일단을 전선 권선기에 결합하게 되며, 그 이후 단계 S200에서는 일단이 결합된 폐전선 또는 재사용 전선을 권선하게 된다. In step S100, one end of the closed wire or reused wire cut to a predetermined length determined by the law is coupled to the wire winding machine, and then, in step S200, the closed wire or reused wire that is coupled to one end is wound.

다음으로, 종래에 인력으로 전선 철거 작업을 하는 경우와 상기에서 설명한 권선용 오가크레인을 이용하여 전선 철거 작업을 하는 경우를 각각 표를 통하여 비교하여 보도록 한다. Next, the case of the wire demolition work by the conventional manpower and the case of the wire demolition work using the above-described Oga crane for winding will be compared through the table respectively.

(표 1)Table 1

항목Item 인력 되감기Rewind 오가크레인을 이용한 권선장치Winding device using organ crane 인력manpower 많은 인원(3~4명)Large number of people (3-4 people) 적은 인원(오가크레인 기사 1명Small number of people (1 Oga Crane article 되감는 양Rewinding amount 한정(30m/1인)Limited (30m / 1 person) 무한정(전선 1드럼, 600m)Infinity (1 wire drum, 600m) 당길수 있는 경간Pull Span 한정(30m/1인)Limited (30m / 1 person) 무한정(전선 1드럼, 600m)Infinity (1 wire drum, 600m) 공사 속도Construction speed 느림(약200/1인, 600m)Slow (approx. 200m per person, 600m) 빠름(약 20분/600m)Fast (approximately 20 minutes / 600m) 운영비Operating costs 인부 인건비만큼 소요Labor cost as much as labor 기존 오가크레인 비용 그대로Existing Oga Crane Cost 운반carrying 되감기가 불균등하여 부피가 커지고 운반에 애로 사항 있음Uneven rewinding results in bulky and difficult transport 전선 1드럼으로운반하기에 용이함Easy to transport with 1 wire drum

상기 표1에서 알 수 있는 것과 같이, 종래 인력에 의해 전선 철거 작업을 하는 경우와 비교하여 본 고안의 일 실시예에 따른 경우에는, 인력의 낭비를 줄일 수 있어서 인건비를 절감할 수 있을 뿐만 아니라, 되감는 양이나 당길 수 있는 경간이 무한정일 뿐만 아니라 공사 속도가 현저히 빨라지게 되어서 철거 작업이 매우 용이하게 이루어진다. 또한, 오가크레인을 이용하여 철거한 경우, 전선 1드럼으로 깔끔하게 철거됨으로 인해 철거 이후 운반도 현저히 용이하게 된다. As can be seen in Table 1, when compared to the case of the electric wire demolition work by the conventional manpower according to an embodiment of the present invention, it is possible to reduce the labor cost by reducing the waste of manpower, Not only is the amount of rewinding and the span that can be pulled indefinitely, but also the construction speed is remarkably high, making the demolition work very easy. In addition, in the case of dismantling using the Ogacrane, since the wire is neatly dismantled by one drum, it is also remarkably easy to carry after dismantling.

다음으로, 종래에 인력으로 재사용 전선을 철거하는 작업을 행하는 경우와 권선용 오가크레인을 이용하여 재사용 전선을 철거하는 작업을 행하는 경우를 각각 표를 통하여 비교해 보도록 한다. Next, the case of performing the work of dismantling the reused wire by the conventional manpower and the case of dismantling the reused wire by using the Oga crane for winding to compare through the table respectively.

(표 2)Table 2

항목Item 인력 되감기Rewind 오가크레인을 이용한 권선장치Winding device using organ crane 인력manpower 많은 인원(약 20명 소요)Large number of people (around 20 people) 적은 인원(오가크레인 기사 1명)Small number of people (1 Oga Crane article) 재사용 전선 되감기Rewind the reused wire 전선 손상의 우려Fear of wire damage 전선 손상이 없음No wire damage 되감는 양Rewinding amount 한정(2~3경간, 80~120m)Limited (2 ~ 3 span, 80 ~ 120m) 무한정(전선 1드럼, 600m)Infinity (1 wire drum, 600m) 당길 수 있는 경간Pullable Span 한정(2~3경간, 80~120m)Limited (2 ~ 3 span, 80 ~ 120m) 무한정(전선 1드럼, 600m)Infinity (1 wire drum, 600m) 공사속도Construction speed 느림(약 60분/600m)Slow (approx. 60 minutes / 600m) 빠름(약 20분/600m)Fast (approximately 20 minutes / 600m) 운영비Operating costs 인부 인건비만큼 소요Labor cost as much as labor 기존 오가크레인 비용 그래도Original Oga Crane Cost 안전성safety 불균일한 장력의 과도한이도로 안정상 위험함Dangerous for stability due to excessive degree of uneven tension 균일한 장력으로 이도확보할 수 있고 안전성 확보Can secure ear with uniform tension and ensure safety 현실성Reality 재사용하기 위해 인력 충원은 불합리Recruiting manpower to reuse is unreasonable 인력충원없이 기존 인원 및 장비로 가능함Possible to use existing personnel and equipment without adding manpower

상기 표 2에서 알 수 있는 것과 같이, 종래 인력에 의해 재사용 전선 철거 작업을 하는 경우와 비교하여 본 고안의 일 실시예에 따른 경우에는, 인력의 낭비를 줄일 수 있어서 인건비를 절감할 수 있을 뿐만 아니라, 되감는 양이나 당길 수 있는 경간이 무한정일 뿐만 아니라 공사 속도가 현저히 빨라지게 되어서 철거 작업이 매우 용이하게 이루어진다. 또한, 오가크레인을 이용하여 철거한 경우, 전선 1드럼으로 깔끔하게 철거됨으로 인해 철거 이후 운반도 현저히 용이하고, 재사용시에도 용이하게 재사용이 가능하게 된다. 그리고, 인력 충원없이도 기존 오가크레인 기사 1명으로도 모든 작업이 가능하게 되는 효과가 있다. As can be seen in Table 2, when compared to the case of dismantling the reused wire by the conventional manpower according to an embodiment of the present invention, it is possible to reduce the labor cost to reduce the waste of manpower In addition, the amount of rewinding and the length of the pullable can be infinite, as well as the construction speed is remarkably high, making the demolition work very easy. In addition, when the demolition using the Oga Crane, since it is neatly dismantled by a wire 1 drum it is significantly easy to transport after demolition, it is easy to reuse when reuse. In addition, there is an effect that all work can be done with one existing Oga Crane article without recruiting personnel.

상기한 바와 같이, 본 고안은 인원 낭비를 줄이며, 공사가 진행되는 도로 주변의 차량 안전 및 보행자 안전에 바람직하다는 것을 잘 알 수 있다. As described above, the present invention reduces the waste of personnel, it can be seen that it is preferable for vehicle safety and pedestrian safety around the road where construction is in progress.

마지막으로, 도 3은 본 고안의 일 실시예에 따른 권선용 오가크레인을 실제로 작업에 적용한 경우를 나타낸 사진이다. Finally, Figure 3 is a photograph showing a case in which the winding Oga Crane according to an embodiment of the present invention actually applied to the work.

이상과 같이, 본 고안은 비록 한정된 실시예와 도면에 의해 설명되었으나, 본 고안은 이것에 의해 한정되지 않으며 본 고안이 속하는 기술 분야에서 통상의 지식을 가진 자에 의해 본 고안의 기술 사상과 아래에 기재될 특허 청구범위의 균등 범위 내에서 다양한 수정, 변경 및 변형이 가능함은 물론이다.As described above, although the present invention has been described by way of limited embodiments and drawings, the present invention is not limited thereto and is intended by those skilled in the art to which the present invention pertains. Of course, various modifications, changes and variations are possible within the equivalent scope of the claims to be described.

본 고안에 따르면, 인원 낭비를 최소화하여 인건비를 현저히 절감할 수 있을 뿐만 아니라, 공사가 진행되고 있는 도로 주변의 차량 안전에 만전을 기할 수 있으며, 또한 공사가 진행되고 있는 인도 주변의 보행자의 안전에도 만전을 기할 수 있으며, 폐전선이나 재사용 전선을 바닥에 떨어지지 않고 되감기하는 것이 가능하다. 나아가, 인력이 아닌 오가크레인을 이용하여 철거를 하게 됨으로써, 깔끔하게 1드럼씩 철거를 행할 수 있다는 장점을 갖고 있다. According to the present invention, it is possible to minimize the waste of personnel by minimizing the waste of personnel, and to ensure the safety of vehicles around roads under construction, and also to the safety of pedestrians around India where construction is underway. It is possible to make sure, and it is possible to rewind the waste wire or reused wire without falling to the floor. Furthermore, since the demolition is carried out by using Ogacrain rather than manpower, it has the advantage of being able to perform demolition by one drum neatly.

도 1은 권선용 오가크레인을 나타내는 도면,1 is a diagram showing an organ crane for winding,

도 2는 권선용 오가크레인을 사용한 권선 방법을 나타내는 플로우차트,2 is a flowchart showing a winding method using an organocrane for winding;

도 3은 본 고안의 일 실시예에 따른 권선용 오가크레인을 실제로 작업에 적용한 경우를 나타낸 사진이다. 3 is a photograph showing a case in which the oga crane for windings according to an embodiment of the present invention is actually applied to a work.

*도면의 주요 부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings

10 전선 권선기 10 wire winding machine

20 결합부 20 coupling

100 권선용 오가크레인 Oga Crane for 100 winding

Claims (1)

전주 굴착용 스크류 및 전선 권선기를 선택적으로 결합할 수 있는 결합부와;A coupling part for selectively coupling the electric pole drilling screw and the wire winding machine; 상기 결합부에 결합되며, 일정한 길이로 절단된 폐전선 또는 재사용 전선이 그 외주에 감기도록 원기둥의 드럼 모양을 갖고 상기 폐전선 또는 재사용 전선이 권선되도록 하는 전선 권선기를 구비하는 Coupled to the coupling portion, and has a wire-shaped winding machine for winding the closed wire or reused wire having a cylindrical drum shape so that the closed wire or reused wire cut to a predetermined length is wound around the periphery 권선용 오거크레인. Auger crane for winding.
KR20-2005-0013421U 2005-05-12 2005-05-12 Auger crane for winding electric wire KR200392674Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2005-0013421U KR200392674Y1 (en) 2005-05-12 2005-05-12 Auger crane for winding electric wire

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2005-0013421U KR200392674Y1 (en) 2005-05-12 2005-05-12 Auger crane for winding electric wire

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020050039555A Division KR20060116938A (en) 2005-05-12 2005-05-12 Auger crane for winding electric wire and method using the same

Publications (1)

Publication Number Publication Date
KR200392674Y1 true KR200392674Y1 (en) 2005-08-17

Family

ID=43693875

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2005-0013421U KR200392674Y1 (en) 2005-05-12 2005-05-12 Auger crane for winding electric wire

Country Status (1)

Country Link
KR (1) KR200392674Y1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101091131B1 (en) 2008-02-22 2011-12-12 김용균 auger crane for winding wire
KR102466919B1 (en) 2022-07-04 2022-11-14 김완영 Auger crane for dust protection

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101091131B1 (en) 2008-02-22 2011-12-12 김용균 auger crane for winding wire
KR102466919B1 (en) 2022-07-04 2022-11-14 김완영 Auger crane for dust protection

Similar Documents

Publication Publication Date Title
CN104947604B (en) A kind of fast quick change frame construction method of high-speed railway 900t concrete box girders
KR200392674Y1 (en) Auger crane for winding electric wire
ATE513100T1 (en) METHOD FOR REPLACING A MAST AND SYSTEM COMPRISING A MAST
JP2003253623A (en) Rebuilding construction method for bridge beam
CN204334248U (en) Motor stator casing coil inserting apparatus
JP6223701B2 (en) Heavy lifting tool
CN104909312A (en) Electric operating vehicle
JP3765096B2 (en) Bridge construction replacement method
CN206707400U (en) A kind of security enclosure of transforming plant device
CN107355085A (en) The guard method of reserved steel bar at the top of a kind of structural column
KR20060116938A (en) Auger crane for winding electric wire and method using the same
CN107217862A (en) A kind of outer protection network supporting construction and outer protection net construction method
CN203833394U (en) Labor-saving winding tool flexible in winding and unwinding
CN204059953U (en) Hang mould prefab form
CN103178462B (en) Insulated angle lifting platform for live working
KR20130010573A (en) Folding streetlights
KR101065514B1 (en) wire-changing device inside of electric pole andnon-power-failure power distribution method
CN205355669U (en) Power transmission line construction is with supplementary cross arm
CN204754778U (en) Assistance -localization real -time and mobile device of construction of adaptation transmission line rock stock
KR20190095831A (en) The Movable Temporary Arm 2 Apparatus And Method Using In Uninterruptible Work In The Power Distribution Lines
JP6626599B1 (en) Floor slab cutting device
CN210885083U (en) Cable trench cover carrying device
CN109082993A (en) Town road Rapid-Repair structure and its construction method
CN103669219B (en) Many limbs height pier is with sliding construction equipment
CN206076831U (en) A kind of quick transition assembled lifts crossing frame certainly

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20060714

Year of fee payment: 3

LAPS Lapse due to unpaid annual fee