KR200387364Y1 - steel well foundation equipment - Google Patents

steel well foundation equipment Download PDF

Info

Publication number
KR200387364Y1
KR200387364Y1 KR20-2005-0007094U KR20050007094U KR200387364Y1 KR 200387364 Y1 KR200387364 Y1 KR 200387364Y1 KR 20050007094 U KR20050007094 U KR 20050007094U KR 200387364 Y1 KR200387364 Y1 KR 200387364Y1
Authority
KR
South Korea
Prior art keywords
well
wall
caisson
steel
reinforcing bar
Prior art date
Application number
KR20-2005-0007094U
Other languages
Korean (ko)
Inventor
조기현
Original Assignee
(주)삼도기술
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)삼도기술 filed Critical (주)삼도기술
Priority to KR20-2005-0007094U priority Critical patent/KR200387364Y1/en
Application granted granted Critical
Publication of KR200387364Y1 publication Critical patent/KR200387364Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater

Abstract

본 고안은 해상대형크레인이 진입할 수 없는 강이나 저수지, 하구언(둑) 등에서 복수의 롯트(하부, 중간, 상부 우물통케이슨)를 소형크레인으로 제작, 운반, 설치하여 강재우물통기초를 시공할 수 있는 강재우물통기초 시공 설비에 관한 것이다. The present invention can construct the base of steel wells by manufacturing, transporting and installing a plurality of lots (lower, middle, upper well caissons) as small cranes in rivers, reservoirs, estuaries, etc., where marine large cranes cannot enter. The present invention relates to a steel water well foundation construction facility.

Description

강재우물통기초 시공 설비{steel well foundation equipment}Steel well foundation equipment

본 고안은 해상대형크레인이 진입할 수 없는 강이나 저수지, 하구언(둑) 등에서 복수의 롯트(하부, 중간, 상부 우물통케이슨)를 소형크레인으로 제작, 운반, 설치하여 강재우물통기초를 시공할 수 있는 강재우물통기초 시공 설비에 관한 것이다. The present invention can construct the base of steel wells by manufacturing, transporting and installing a plurality of lots (lower, middle, upper well caissons) as small cranes in rivers, reservoirs, estuaries, etc., where marine large cranes cannot enter. The present invention relates to a steel water well foundation construction facility.

바다, 강, 하천 등에서 시공하는 교량의 기초형식은 직접기초, 말뚝기초, 우물통기초, 케이슨기초 등이 있다. 이 중 가장 많이 사용되는 기초는 우물통기초로서, 콘크리트우물통기초, 강재우물통으로 나누어진다. 수심이 얕은 경우에는 축도를 하여 콘크리트우물통기초를 시공하고, 수심이 깊은 경우(5m 이상)에는 강재우물통케이슨을 육상에서 제작한 후, 1500톤급 이상의 해상대형크레인(3)으로 현장위치까지 운반한 후 강재우물통케이슨을 한번에 설치한다(한국공개특허공보 제1999-42532호 참조). The basic types of bridges constructed at sea, rivers, rivers, etc. include direct foundations, pile foundations, well well foundations, and caisson foundations. The most commonly used foundation is well well base, which is divided into concrete well base and steel well base. If the water depth is shallow, construct the concrete well base with a shaft, and if the water depth is deep (more than 5m), the steel well caisson is manufactured on land and then transported to the site with a large marine crane (3) of 1500 tons or more. After installing steel well bucket caisson at a time (see Korean Patent Publication No. 1999-42532).

즉, 강재우물통케이슨 1개의 높이는 1.5 내지 2m 이고 그 무게는 150톤~200톤 정도이다. 따라서, 5m 이상의 수심에 설치하기 위해서는 적어도 강재우물통케이슨 복수의 롯트 예컨대 3개를 볼트 조립하거나 (수밀성 확보를 위해) 용접하여 서로 결합시켜야 한다. 이 결합된 일체형 강재우물통케이슨(1)의 무게는 그 높이에 따라 다르나 평균 600톤 이상이다. 이 무거운 강재우물통케이슨(1)을 운반하기 위한 해상대형크레인으로는 적어도 1000톤급 이상이 되어야 한다(도 1 참조). 현재 해상대형크레인으로는 삼성호 3000톤, 설악호 2000톤, 대림호 1500톤 등이 있다. That is, the height of one steel well caisson is 1.5 to 2m and the weight is about 150 to 200 tons. Therefore, in order to install at a depth of 5m or more, at least a plurality of steel well caisson lots, such as three, should be bolted together or welded (to ensure watertightness) to be joined to each other. The combined integral steel well caisson 1 has a weight of 600 tons or more depending on its height. The offshore large crane for transporting this heavy steel well caisson 1 shall be at least 1000 tonnes or more (see Fig. 1). Currently, there are 3,000 tons of Samsung cranes, 2000 tons of Seorak and 1500 tons of Daelim.

이 1000톤급 이상의 해상대형크레인은 저수지, 하천의 상류지역 또는 시화호, 영상강호 등의 제방내부 해안에 진입할 수 없다는 한계가 있다. 그래서, 해상대형크레인을 분리, 이동, 재조립하여 설치하는 비용이 예컨대 대략 7,8억 정도 소요되는 것으로 파악되고 있다. There is a limit that the marine oversize crane of more than 1000 tons cannot enter the reservoir, the upper area of the river, or the inner shore of the embankment such as the Sihwa Lake and the Image River. Therefore, it is understood that the cost of separating, moving, and reassembling marine large cranes is, for example, about 780 million.

본 고안은 전술한 문제를 해결하기 위하여 안출된 것으로, 해상대형크레인이 진입할 수 없는 지역에서 운반, 설치가 용이하고 비용이 저렴한 소형크레인으로 강재우물통케이슨의 기초를 시공할 수 있는 강재우물통기초 시공 설비를 제공함에 그 목적이 있다. The present invention was devised to solve the above-mentioned problems. The construction of the steel well container base can be used to construct the foundation of the steel water well caisson as a small crane that is easy to carry, install and inexpensive in an area where marine large cranes cannot enter. The purpose is to provide the equipment.

전술한 목적을 달성하기 위한 본 고안의 강재우물통기초 시공 설비는 제1내벽, 제1외벽, 상기 제1내벽과 상기 제1외벽의 하단을 연결하는 바닥, 상기 제1내벽과 상기 제1외벽 사이의 제1격벽에 제1철근이 배근된 제1우물통케이슨; 상기 제1우물통케이슨에 설치되는 제2우물통케이슨을 포함하여 이루어진다. Steel well ventilation foundation construction equipment of the present invention for achieving the above object is a first inner wall, the first outer wall, a floor connecting the lower end of the first inner wall and the first outer wall, between the first inner wall and the first outer wall A first well caisson where the first reinforcing bar is disposed in the first partition of the first well; It comprises a second well caisson installed in the first well caisson.

이 구성에 의하면, 해상대형크레인이 진입할 수 없는 지역에서 운반, 설치가 용이하고 비용이 저렴한 소형크레인으로 강재우물통케이슨의 기초를 시공할 수 있다. According to this configuration, it is possible to construct the foundation of the steel water well caisson with a small crane that is easy to transport, install and inexpensive in an area where marine large cranes cannot enter.

전술한 구성에서, 상기 제2우물통케이슨은 상기 제1내벽에 설치되는 제2내벽과, 상기 제1외벽에 설치되는 제2외벽과, 상기 제1철근에 연결되는 제2철근으로 구성되는 것이 바람직하고, 이때, 상기 철근간의 연결은 각각의 철근에 형성된 수나사와, 이 수나사와 나사 체결되는 커플링에 의해 이루어지면, 연결이 신속하고 견고하여 물 위에서의 작업성을 향상시킬 수 있다. In the above-described configuration, the second well barrel caisson is composed of a second inner wall installed on the first inner wall, a second outer wall provided on the first outer wall, and a second reinforcing bar connected to the first reinforcing bar. Preferably, the connection between the reinforcing bar is made by the male screw formed on each of the reinforcing bars and the coupling screwed to the male screw, the connection is fast and robust to improve the workability on the water.

또한, 상기 제1우물케이슨의 상기 제1내벽에 튜브가 설치되고, 상기 제2우물통케이슨에 제3우물통케이슨이 설치되되, 상기 제3우물통케이슨은 상기 제2내벽에 설치되는 제3내벽과, 상기 제2외벽에 설치되는 제3외벽과, 상기 제2철근에 커플링에 의해 연결되는 제3철근으로 구성되는 것이 바람직하다. In addition, a tube is installed on the first inner wall of the first well caisson, a third well caisson is installed on the second well caisson, the third well caisson is a third installed on the second inner wall Preferably, the inner wall, the third outer wall provided on the second outer wall, and the third rebar connected to the second reinforcing bar by a coupling.

이하, 본 고안의 바람직한 실시예를 첨부한 도면에 따라 설명한다. Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings.

도 2는 본 고안의 바람직한 실시예에 따른 강재우물통케이슨 중 하부우물통케이슨을 육상에서 제작하여 소형크레인으로 기초위치까지 이동하여 설치하는 상태를 도시한 도이고, 도 3a 내지 도 3d는 하부우물통케이슨에 중간우물통케이슨의 설치 순서를 도시한 도이고, 도 4는 하부/중간우물통케이슨의 격벽에 콘크리트를 타설하는 도이고, 도 5는 강재우물통케이슨을 설치한 후 그 내부를 채우는 단계를 도시한 도이고, 도 6은 본 고안에 따른 강재우물통기초 시공 공법을 도시한 플로 차트이다. 2 is a view showing a state in which the lower well bucket caisson of the steel well bucket caisson according to a preferred embodiment of the present invention is installed on the land to move to the base position with a small crane, Figure 3a to 3d is a lower well bucket 4 is a view showing the installation procedure of the intermediate well caisson in the caisson, Figure 4 is a diagram for placing concrete on the partition wall of the lower / middle well caisson, Figure 5 is a step of filling the interior after installing the steel well caisson. Figure 6 is a flow chart illustrating a steel water well foundation construction method according to the present invention.

본 실시예의 강재우물통기초 시공 공법은 먼저, 육상에서 슈를 갖는 하부우물통케이슨을 제작한다(S10). 하부우물통케이슨(10)은 도 2 및 도 3a에 도시한 바와 같이, 하부내벽(11), 하부외벽(13), 하부내벽(11)과 하부내벽(13)의 하단에 경사지게 설치되는 바닥(15)으로 이루어진 슈를 갖는 원통형상의 강재슈하부케이슨으로 구성되는 것이 바람직하다. 또한, 하부내벽(11)과 하부외벽 사이의 하부격벽에는 L형강의 간격보강재(17)가 하부내벽(11)과 하부외벽(13)에 용접되고, 철근(18,19)이 배근되어 있는 것이 바람직하다. Steel well base construction method of the present embodiment, first, to produce a lower well caisson having a shoe on the land (S10). As shown in FIGS. 2 and 3A, the lower well barrel caisson 10 has a bottom inclined at a lower end of the lower inner wall 11, the lower outer wall 13, the lower inner wall 11, and the lower inner wall 13 ( It is preferable that it consists of the cylindrical steel shoe lower caisson which has the shoe which consists of 15). In addition, in the lower partition wall between the lower inner wall 11 and the lower outer wall, the gap reinforcing material 17 of the L-shaped steel is welded to the lower inner wall 11 and the lower outer wall 13, and the reinforcing bars 18 and 19 are disposed. desirable.

이 하부우물통케이슨(10)은 높이가 20m인 경우 180톤 정도이기 때문에, 150톤 또는 200톤의 소형크레인(5)에 의해서도 양중이 가능하기 때문에, 우물통기초 현장에 설치할 수 있다(S13). 즉, 현장의 수면 위에 하부우물통케이슨(10)을 띄워 놓는다. 이 띄워 놓은 상태에서 하부우물통케이슨(10)의 흘수(吃水; 선체가 물에 잠기는 깊이) 상태를 고려하여, 튜브(20)를 설치하는 것이 바람직하다(S12). 즉, 하부우물통케이슨(10)의 길이는 종래의 완성된 강재우물통케이슨(1)의 길이보다 짧은 상태로 현장의 수면에 놓이기 때문에, 긴 경우보다 가라않을 위험이 높기 때문이다. 이 튜브(20)는 하부내벽(11)의 내주면에 체결부재(21)에 의해 설치되는 것이 바람직하다. 예컨대, 체결부재(21)로는 하부내벽(11)의 고리와 튜브의 훅으로 구현할 수 있다. 한편, 하부우물통케이슨(10)을 현장에 설하기 전에, 하상을 정리하고 가이드파일(7)을 설치할 수 있다. Since the lower well caisson 10 is about 180 tons when the height is 20 m, it can be lifted by the small crane 5 of 150 to 200 or 200 tons, so that it can be installed at the well well base site (S13). . That is, float the lower well caisson 10 on the surface of the field. It is preferable to install the tube 20 in consideration of the draft state of the lower well barrel caisson 10 in the floating state (S12). That is, because the length of the lower well caisson 10 is placed on the surface of the site in a state shorter than the length of the conventional completed steel well caisson 1, because there is a high risk of not going down than the long case. This tube 20 is preferably provided by the fastening member 21 on the inner peripheral surface of the lower inner wall (11). For example, the fastening member 21 may be implemented by the hook of the lower inner wall 11 and the hook of the tube. On the other hand, before installing the lower well caisson 10 in the field, it is possible to arrange the lower bed and install the guide pile (7).

하부우물통케이슨(10)을 현장에 설치한 후 그 위에 중간우물통케이슨(30)을 설치한다(S14). 중간우물통케이슨(30)은 중간내벽(31)을 하부내벽(11)에 용접 또는 볼트 조립한 후(도 3b), 중간수직철근(38)을 하부수직철근(18)에 연결하고(도 3c), 중간외벽(33)을 하부외벽(13)에 용접 또는 볼트 조립하여(도 3d) 설치된다. 철근(18)과 철근(38)의 연결방식은 겹이음, 압접, 커플링으로 이루어지는데, 본 실시예에서는 원통형너트인 커플링(40)으로 구현되어, 작업성을 향상시킬 수 있다. 즉, 암나사가 형성된 커플링(40)을 회전시키면, 수직철근(18)(38)에 가공된 수나사와 나사 체결되어 간단히 연결된다. 또한, 수직철근(38)에 수평철근(39)을 배근하는 것이 바람직하다. 또한, 중간내벽(31)이 분할원통인 경우, 원주방향용접 뿐 아니라 길이방향용접도 행하면 된다. After installing the lower well caisson 10 in the field and install the intermediate well caisson 30 thereon (S14). The intermediate well caisson 30 welds or bolts the intermediate inner wall 31 to the lower inner wall 11 (FIG. 3B), and then connects the intermediate vertical reinforcement 38 to the lower vertical reinforcing bar 18 (FIG. 3C). ), The intermediate outer wall 33 is welded or bolted to the lower outer wall 13 (FIG. 3D). Connection method of the reinforcing bar 18 and the reinforcing bar 38 is composed of overlapping, pressure welding, coupling, in this embodiment is implemented by the coupling 40, which is a cylindrical nut, can improve the workability. That is, when the female threaded coupling 40 is rotated, the male thread machined to the vertical bars 18 and 38 is screwed and simply connected. In addition, it is preferable to reinforce the horizontal reinforcement 39 to the vertical reinforcement 38. In the case where the intermediate inner wall 31 is a divided cylinder, not only the circumferential welding but also the longitudinal welding may be performed.

중간우물통케이슨(30)이 설치된 후 튜브(20)를 제거한다(S15). 튜브(20)를 제거한 후 흘수를 고려하여 가라앉지 않도록 적당한 높이로 격벽(12, 32)에 콘크리트를 타설한다(S16). After the intermediate well caisson 30 is installed to remove the tube (20) (S15). After removing the tube 20, the concrete is poured into the partitions 12 and 32 to a suitable height so as not to sink in consideration of the draft (S16).

그 다음, 필요한 경우 중간우물통케이슨(30)에 상부우물통케이슨(50)을 설치하여(S17), 강재우물통케이슨조립체(100)를 형성한다. 상부우물통케이슨(50)의 설치는 중간우물통케이슨(30)의 설치와 동일하므로 자세한 설명은 생략한다. Then, if necessary, the upper well caisson 50 is installed in the intermediate well caisson 30 (S17) to form a steel well caisson assembly 100. Since the installation of the upper well caisson 50 is the same as the installation of the intermediate well caisson 30, a detailed description thereof will be omitted.

강재우물통케이슨조립체(100)가 형성된 후, 도 4에 도시한 바와 같이, 점진적으로 침하하도록 격벽에 콘크리트를 타설한다(S18). 침하된 강재우물통케이슨(100)의 내부 굴착을 반복하여 지지층에 도달시킨다(S19). 필요한 경우, 단계(S19) 전에 상부우물통케이슨(50)의 상단에 거푸집을 설치하고 콘크리트 타설하여 벽체를 형성시킨 후, 내부굴착을 행할 수 있다. After the steel well barrel caisson assembly 100 is formed, as shown in Figure 4, the concrete is poured into the partition wall to gradually sink (S18). The internal drilling of the sinking steel well caisson 100 is repeated to reach the support layer (S19). If necessary, after installing the formwork on the upper end of the upper well caisson 50 before the step (S19) to form a wall by placing concrete, it can be carried out internal drilling.

강재우물통케이슨(100)이 지지층에 도달한 후, 강재우물통케이슨의 내부를 채우는데, 먼저 지지층과 강재우물통케이슨(100)간의 수밀을 위한 수중콘크리트를 지지층에 타설한 후 양수하고, 도 5에 도시한 바와 같이 콘크리트(또는 모래)를 타설하여 속채움을 완료한다(S20). After the steel well bucket caisson 100 reaches the support layer, it fills the interior of the steel well bucket caisson, first pouring the concrete for the watertight between the support layer and the steel well bucket caisson 100 on the support layer and pumping, as shown in FIG. As described above, the concrete (or sand) is poured to complete the filling (S20).

이와 같이, 강재우물통케이슨(100)의 일부를 구성하는 하부우물통케이슨(10)을 육상에서 제작하여 현장에 설치한 후 그 위에 중간우물통케이슨(30)과 상부우물통케이슨(50)의 점진적 설치가 가능하여, 내륙의 강이나 저수지, 시화호나 영산강호의 둑에 분해 조립 필요없이 진입할 수 있는 소형크레인으로 작업할 수 있다. 따라서, 분해 조립에 따른 비용과 시간을 현저히 절약할 수 있다. As described above, the lower well caisson 10 constituting a part of the steel well caisson 100 is manufactured on the ground and installed on the site, and then the middle well caisson 30 and the upper well caisson 50 thereon. It can be installed to work with small cranes that can enter inland rivers, reservoirs, banks of Sihwa Lake or Yeongsan River without disassembly and assembly. Therefore, the cost and time for disassembly and assembly can be remarkably saved.

본 고안에 따른 강재우물통기초 시공 설비는 전술한 실시예에 국한되지 않고 본 고안의 기술 사상이 허용하는 범위 내에서 다양하게 변형하여 실시할 수 있다. Steel well base construction equipment according to the present invention is not limited to the above embodiment can be carried out in a variety of modifications within the range allowed by the technical idea of the present invention.

이상의 설명으로부터 명백하듯이, 본 고안에 의하면 다음과 같은 효과가 있다. As apparent from the above description, the present invention has the following effects.

첫째, 강재우물통케이슨을 복수로 나누어 설치함으로써, 현장에서 소형크레인으로 충분히 양중 작업이 가능하여, 해상대형크레인이 진입할 수 없는 저수지나 둑에서 부대비용(해상대형크레인의 분해, 조립과 그 반대)을 발생시키지 않고 시공할 수 있다. First, by installing multiple steel well caissons, it is possible to carry out heavy lifting work with small cranes in the field, so that additional costs are required in reservoirs or banks where marine large cranes cannot enter (disassembly, assembly of marine large cranes and vice versa). Can be constructed without generating

둘째, 하부우물통케이슨의 내주면에 튜브를 설치함으로써, 상대적으로 길이가 짧은 하부우물통케이슨의 가라않을 높은 위험을 배제시킬 수 있다. Second, by installing a tube on the inner circumferential surface of the lower well caisson, it is possible to eliminate the high risk of the lower well caisson of relatively short length.

셋째, 철근간의 연결은 커플링에 의해 행해짐으로써, 철근간의 연결을 신속하고 견고히 연결하여 물 위에서 작업성을 향상시킬 수 있다. Third, the connection between the reinforcing bar is performed by the coupling, it is possible to improve the workability on the water by connecting the connection between the reinforcing bar quickly and firmly.

도 1은 종래 육상에서 일체로 제작된 강재우물통케이슨을 해상대형크레인으로 기초위치까지 이동하여 설치하는 상태를 도시한 도. 1 is a view showing a state in which a steel well barrel caisson manufactured integrally on a conventional land and installed by moving to a base position by a large marine crane.

도 2는 본 고안의 바람직한 실시예에 따른 강재우물통케이슨 중 하부우물통케이슨을 육상에서 제작하여 소형크레인으로 기초위치까지 이동하여 설치하는 상태를 도시한 도. 2 is a view showing a state in which the lower well bucket caisson of the steel well bucket caisson according to a preferred embodiment of the present invention is installed on the land to move to the base position with a small crane.

도 3a 내지 도 3d는 하부우물통케이슨에 중간우물통케이슨의 설치 순서를 도시한 도. Figures 3a to 3d is a view showing the installation procedure of the intermediate well caisson in the lower well caisson.

도 4는 하부/중간우물통케이슨의 격벽에 콘크리트를 타설하는 상태를 도시한 도. Figure 4 is a view showing a state in which concrete is poured on the partition wall of the lower / middle well caisson.

도 5는 강재우물통케이슨을 설치한 후 그 내부를 채우는 단계를 도시한 도. Figure 5 is a view showing the step of filling the interior after installing the steel well caisson.

도 6은 본 고안에 따른 강재우물통기초 시공 공법을 도시한 플로 차트. Figure 6 is a flow chart showing the steel well ventilation foundation construction method according to the present invention.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

10 : 하부(제1)우물통케이슨 20 : 튜브10: lower (first) well caisson 20: tube

30 : 중간(제2)우물통케이슨 40 : 커플링30: middle (second) well bucket caisson 40: coupling

50 : 상부(제3)우물통케이슨 100 : 강재우물통케이슨50: upper (third) water well caisson 100: steel water well caisson

Claims (3)

제1내벽, 제1외벽, 상기 제1내벽과 상기 제1외벽의 하단을 연결하는 바닥, 상기 제1내벽과 상기 제1외벽 사이의 제1격벽에 제1철근이 배근된 제1우물통케이슨; 상기 제1우물통케이슨에 설치되는 제2우물통케이슨을 포함하여 이루어진 강재우물통기초 시공 설비. A first well barrel caisson in which a first reinforcing bar is disposed on a first inner wall, a first outer wall, a floor connecting a lower end of the first inner wall and the first outer wall, and a first partition wall between the first inner wall and the first outer wall. ; Steel well cylinder foundation construction equipment comprising a second well caisson installed in the first well caisson. 제 1항에 있어서, 상기 제2우물통케이슨은 상기 제1내벽에 설치되는 제2내벽과, 상기 제1외벽에 설치되는 제2외벽과, 상기 제1철근에 연결되는 제2철근으로 구성되고, According to claim 1, wherein the second well caisson is composed of a second inner wall is installed on the first inner wall, a second outer wall provided on the first outer wall, and a second reinforcing bar connected to the first reinforcement , 상기 철근간의 연결은 각각의 철근에 형성된 수나사와, 이 수나사와 나사 체결되는 커플링에 의해 이루어지는 것을 특징으로 하는 강재우물통기초 시공 설비. The connection between the reinforcing bar is a steel well ventilation foundation construction equipment, characterized in that made by a male screw formed in each of the reinforcing bars, the coupling is screwed with the male screw. 제 2항에 있어서, 상기 제1우물케이슨의 상기 제1내벽에 튜브가 설치되고, The method of claim 2, wherein a tube is installed on the first inner wall of the first well caisson, 상기 제2우물통케이슨에 제3우물통케이슨이 설치되되, The third well caisson is installed in the second well caisson, 상기 제3우물통케이슨은 상기 제2내벽에 설치되는 제3내벽과, 상기 제2외벽에 설치되는 제3외벽과, 상기 제2철근에 커플링에 의해 연결되는 제3철근으로 구성되는 것을 특징으로 하는 강재우물통기초 시공 설비. The third well caisson is composed of a third inner wall is installed on the second inner wall, a third outer wall is installed on the second outer wall, and a third reinforcing bar connected by coupling to the second reinforcing bar Steel well ventilation foundation construction equipment.
KR20-2005-0007094U 2005-03-16 2005-03-16 steel well foundation equipment KR200387364Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2005-0007094U KR200387364Y1 (en) 2005-03-16 2005-03-16 steel well foundation equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2005-0007094U KR200387364Y1 (en) 2005-03-16 2005-03-16 steel well foundation equipment

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020050021825A Division KR100768552B1 (en) 2005-03-16 2005-03-16 steel well foundation construction and equipment

Publications (1)

Publication Number Publication Date
KR200387364Y1 true KR200387364Y1 (en) 2005-06-17

Family

ID=43688680

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2005-0007094U KR200387364Y1 (en) 2005-03-16 2005-03-16 steel well foundation equipment

Country Status (1)

Country Link
KR (1) KR200387364Y1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102169627B1 (en) * 2020-09-09 2020-10-23 김용재 Installation method of concrete sinker for floating structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102169627B1 (en) * 2020-09-09 2020-10-23 김용재 Installation method of concrete sinker for floating structure

Similar Documents

Publication Publication Date Title
US9567720B2 (en) Offshore platform for a marine environment
KR101134780B1 (en) Underwater Base for Seawater Bridge Column
KR100819624B1 (en) Waterproof open caisson assembly and concrete foundation construction method using the same
CN109914399B (en) Environment-friendly pile foundation construction method
CN104775446A (en) Cylindrical pier for fixing water structure and mounting and constructing method of cylindrical pier
KR101211811B1 (en) Cast in concrete pile With precast type Caisson
WO2015135471A1 (en) Hollow cylindrical pier for fixing offshore platform structure to bed and method of installing and constructing same
CN103015456A (en) Rapid pit-in-pit form erecting method in foundation slab of buried concrete structure
CN104389318A (en) Reinforced concrete-steel structure hybrid gravity foundation for offshore wind power and construction method thereof
CN102561371A (en) Steel caisson enclosure structure at island-tunnel combination part
KR100714179B1 (en) Concrete Well Construction Method Using Weight Reducing Method and Concrete Well Thereof
KR100768552B1 (en) steel well foundation construction and equipment
KR101256274B1 (en) Reverse Drill Method With precast type Caisson and Jacket
CN114718103A (en) Water closing construction method for water accumulation pit affected by seawater tide
KR20010096389A (en) Construction Method of Direct Foundation for using Caisson
CN104762942B (en) Fixed platform soft soil foundation seabed, aquatic building ocean fixed installation construction method
KR200387364Y1 (en) steel well foundation equipment
KR102078934B1 (en) Base supporting structure for bridge type floating structure and method of constructing the same
JP2006194031A (en) Pillar construction method
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
KR200232748Y1 (en) Steel caisson working a basic constructing of bridge
CN109629587B (en) Steel caisson pile body structure for bank abrupt slope and construction method
CN112962641A (en) Construction method for dismantling riverbank cofferdam structure
KR20020081530A (en) Well form for the base operation of pier and it&#39;s operation method
CN110552360A (en) Double-row steel pipe pile cofferdam construction method

Legal Events

Date Code Title Description
U107 Dual application of utility model
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20060308

Year of fee payment: 3

EXTG Extinguishment