KR200305893Y1 - Devise constructing the scaffold for shipbuilding - Google Patents

Devise constructing the scaffold for shipbuilding Download PDF

Info

Publication number
KR200305893Y1
KR200305893Y1 KR20-2002-0036377U KR20020036377U KR200305893Y1 KR 200305893 Y1 KR200305893 Y1 KR 200305893Y1 KR 20020036377 U KR20020036377 U KR 20020036377U KR 200305893 Y1 KR200305893 Y1 KR 200305893Y1
Authority
KR
South Korea
Prior art keywords
clamp
temporary
ship
scaffolding
protrusion
Prior art date
Application number
KR20-2002-0036377U
Other languages
Korean (ko)
Inventor
박동석
Original Assignee
박동석
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박동석 filed Critical 박동석
Priority to KR20-2002-0036377U priority Critical patent/KR200305893Y1/en
Application granted granted Critical
Publication of KR200305893Y1 publication Critical patent/KR200305893Y1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63CLAUNCHING, HAULING-OUT, OR DRY-DOCKING OF VESSELS; LIFE-SAVING IN WATER; EQUIPMENT FOR DWELLING OR WORKING UNDER WATER; MEANS FOR SALVAGING OR SEARCHING FOR UNDERWATER OBJECTS
    • B63C5/00Equipment usable both on slipways and in dry docks
    • B63C5/02Stagings; Scaffolding; Shores or struts
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B71/00Designing vessels; Predicting their performance
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B73/00Building or assembling vessels or marine structures, e.g. hulls or offshore platforms
    • B63B73/40Building or assembling vessels or marine structures, e.g. hulls or offshore platforms characterised by joining methods
    • B63B73/43Welding, e.g. laser welding
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B73/00Building or assembling vessels or marine structures, e.g. hulls or offshore platforms
    • B63B73/40Building or assembling vessels or marine structures, e.g. hulls or offshore platforms characterised by joining methods
    • B63B73/49Building or assembling vessels or marine structures, e.g. hulls or offshore platforms characterised by joining methods by means of threaded members, e.g. screws, threaded bolts or nuts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/06Consoles; Brackets
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/08Scaffold boards or planks
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B2/00Friction-grip releasable fastenings
    • F16B2/02Clamps, i.e. with gripping action effected by positive means other than the inherent resistance to deformation of the material of the fastening
    • F16B2/06Clamps, i.e. with gripping action effected by positive means other than the inherent resistance to deformation of the material of the fastening external, i.e. with contracting action
    • F16B2/065Clamps, i.e. with gripping action effected by positive means other than the inherent resistance to deformation of the material of the fastening external, i.e. with contracting action using screw-thread elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B2221/00Methods and means for joining members or elements
    • B63B2221/02Methods and means for joining members or elements by welding
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B2221/00Methods and means for joining members or elements
    • B63B2221/08Methods and means for joining members or elements by means of threaded members, e.g. screws, threaded bolts or nuts
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63CLAUNCHING, HAULING-OUT, OR DRY-DOCKING OF VESSELS; LIFE-SAVING IN WATER; EQUIPMENT FOR DWELLING OR WORKING UNDER WATER; MEANS FOR SALVAGING OR SEARCHING FOR UNDERWATER OBJECTS
    • B63C5/00Equipment usable both on slipways and in dry docks
    • B63C5/02Stagings; Scaffolding; Shores or struts
    • B63C2005/025Stagings, or scaffolding, i.e. constructions providing temporary working platforms on slipways, in building or repair docks, or inside hulls

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Optics & Photonics (AREA)
  • Ladders (AREA)

Abstract

본 고안은 선박을 건조시에 가설발판을 설치하는데 사용하는 선박건조용 가설발판 설치대에 관한 것으로, 더욱 상세하게는 건조(建造)중인 선박건조물에 용접작업을 하거나 도색작업을 하는 등 선박을 건조하는데 필요로 하는 각종 작업을 수행하기 위하여 선박건조물에 가설발판을 설치하기 위하여 사용되는 가설발판 설치대를 선박구조물의 수평돌출대나 또는 수직돌출대에 착탈식으로 고정설치하는 클램프와, 가설발판을 걸어서 설치하는 사다리형태의 발판걸이대를 분리 구성함으로서, 가설발판 설치대의 설치작업이 안전하고 간편하게 이루어질 수 있도록 하기 위한 것이다.The present invention relates to a temporary construction scaffolding platform for ship construction used to install a temporary scaffold when a ship is constructed, and more particularly, to dry a ship by welding or painting a ship building under construction. Clamps for attaching removable scaffolds used to install temporary scaffolds on ship structures in order to carry out various necessary work on horizontal or vertical ramps of ship structures, and ladders for hanging temporary scaffolds By separating and configuring the scaffolding stand of the type, it is to ensure that the installation work of the temporary scaffolding installation stand is made safe and simple.

본 고안은 선박건조물(1)의 수평돌출대(2) 및 수직돌출대(3)에 클램핑 고정되는 클램프(6)와 가설발판(5)을 걸어서 설치하는 사다리형태의 발판걸이대(7)로 이루어지는 가설발판 설치대(8)에 있어서, 상기 클램프(6)와 발판걸이대(7)가 서로 분리되게 구성되며, 상기 클램프(6)는 "ㄷ"자형으로 형성된 클램프본체(9)의 양측에 "ㄷ"자형으로 형성되어 클램프본체(9)의 상하면과 후면을 감싸는 형태로 보강대(11)가 일체로 형성되고, 클램프본체(9)의 상면에는 클램프본체(9)로 삽입되는 수평돌출대(2) 및 수직돌출대(3)를 클램핑하는 고정볼트(10)가 체결되며, 클램프본체(9)의 저면에는 한쌍의 걸이구멍(12)이 형성된 걸이대(13)가 하향 형성되고, 상기 발판걸이대(7)는 양측 지지봉(7b) 사이에 다수개의 걸이부(7a)가 간격을 두고 설치되며, 양측 지지봉(7b)의 상부에 상기 걸이구멍(12)에 걸어지는 걸고리부(14)가 절곡되게 형성된 것을 특징으로 한다.The present invention consists of a ladder-type scaffolding rack (7) that is installed by hanging the clamp 6 and the temporary scaffolding (5) clamped to the horizontal protrusion (2) and the vertical protrusion (3) of the ship building (1) In the temporary scaffold mounting table (8), the clamp (6) and the footrest rack 7 is configured to be separated from each other, the clamp (6) is "C" on both sides of the clamp body (9) formed in the "C" shape "C" The reinforcing bar 11 is formed integrally in a shape of being shaped to surround the upper and lower surfaces and the rear surface of the clamp body 9, and the horizontal protrusion 2 inserted into the clamp body 9 on the upper surface of the clamp body 9 and The fixing bolt 10 for clamping the vertical protrusion 3 is fastened, and the bottom of the clamp main body 9 has a hook 13 formed with a pair of hook holes 12 downwardly, and the footrest 7 Is provided with a plurality of hooks (7a) spaced between the two support rods (7b), the upper portion of the both support rods (7b) Characterized in that the hanging loop portion 14 that walking on two yoke 12 formed to be bent.

Description

선박건조용 가설발판 설치대{Devise constructing the scaffold for shipbuilding}Installation constructing the scaffold for shipbuilding

본 고안은 선박을 건조시에 가설발판을 설치하는데 사용하는 선박건조용 가설발판설치대에 관한 것으로, 더욱 상세하게는 건조(建造)중인 선박건조물에 용접작업을 하거나 도색작업을 하는 등 선박을 건조하는데 필요로 하는 각종 작업을 수행하기 위하여 선박건조물에 가설발판을 설치하기 위하여 사용되는 가설발판 설치대를 선박구조물의 수평돌출대나 또는 수직돌출대에 착탈식으로 고정설치하는 클램프와 가설발판을 걸어서 설치하는 사다리형태의 발판걸이대를 분리 구성함으로서, 가설발판 설치대의 설치작업이 안전하고 간편하게 이루어질 수 있도록 하기 위한 것이다.The present invention relates to a temporary construction scaffolding platform for ship construction used to install a temporary scaffold when a ship is constructed. More specifically, the construction of a ship, such as welding or painting work on a building under construction. Ladder type to install the temporary scaffolding platform used to install the temporary scaffold on the ship's building to be detachably fixed to the horizontal or vertical platform of the ship's structure and to install the temporary scaffold. By separating and configuring the scaffolding stand, the installation work of the temporary scaffolding installation to ensure that the safe and easy to make.

일반적으로 선박을 건조할 때는 여러 가지 형태로 제작된 다수의 철판을 용접으로 결합 설치하여 선박의 기본 형태를 제작하며, 선박의 형태가 갖추어진 뒤에는 초기 단계에서 제작된 선체에 각종 설비를 설치하여 선박을 제작하게 되는데, 본 고안에서는 선체를 제작하는 과정에서 선체의 선박건조물에 용접작업을 하거나 도색작업을 하는 등 선박을 건조하는데 필요로 하는 각종 작업을 수행하기 위하여 선박건조물에 가설발판을 설치하는 경우에 사용되는 가설발판 설치대에 관한 것이므로, 가설발판 설치대에 대해서만 살펴보기로 한다.In general, when a ship is built, a plurality of steel plates manufactured in various forms are welded and installed to manufacture a basic shape of the ship. After the ship is prepared, various types of equipment are installed on the hull manufactured at an early stage. In the present invention, in the process of manufacturing the hull in the case of installing a temporary scaffold on the ship building in order to perform various tasks required to dry the ship, such as welding work or painting work on the ship building of the hull As it relates to the temporary scaffolding mounting platform used in the present invention, only the temporary scaffold mounting platform will be described.

위에서와 같이 제작되어지는 선박건조물은 철판을 용접하여 제작되는 다수의 대형 블록들이 용접결합에 이루어지고, 이렇게 제작되는 선박건조물에는 난간이나 발판과 같이 작업자를 보호하기 위한 보호수단이 마련되어 있지 않으며, 여러 군데에 수평으로 돌출되는 수평돌출대와 수직으로 돌출되는 수직돌출대가 형성되게 되어 이들 수평돌출대와 수직돌출대에 작업자의 안전을 위한 난간이나 발판을 착탈식으로 설치하게 된다.Ship building is manufactured as above is a large number of large blocks made by welding a steel plate is made in the welding combination, the ship building is manufactured is not provided with a protective means for protecting workers, such as railings or scaffolding, The horizontal protrusions projecting horizontally and the vertical protrusions projecting vertically are formed in the places, so that the handrails or scaffolds for the safety of workers can be detachably installed on the horizontal protrusions and the vertical protrusions.

상기와 같이 선박건조물에 설치되는 종래의 가설발판 설치대(8)는 도 1에 도시되어 있는 바와 같이 다수의 걸이부(7a)가 간격을 두고 사다리형태로 설치되는 발판걸이대(7)와, 선박건조물(1)의 수평돌출대(2)나 수직돌출대(3)에 클램프식으로 설치되는 클램프(6)로 이루어지며, 상기 클램프(6)는 "ㄷ"자형의 클램프본체(9)의 상부 양측에 고정볼트(10)가 나사식으로 관통되게 설치되며, 이러한 클램프본체(9)의 중앙부 외측에는 "ㄷ"자형태로 형성된 클램프본체(9)의 외부를 감싸는 보강대(11)가 용접으로 결합 설치되어 있다.As shown in FIG. 1, the conventional temporary scaffolding mounting table 8 installed on the ship building as described above is provided with a scaffolding rack 7 having a plurality of hook portions 7a arranged in a ladder shape at intervals, and the ship building. (1) consists of a clamp (6) which is installed in a clamp type on the horizontal projection (2) or vertical projection (3), the clamp 6 is the upper both sides of the "c" shaped clamp body (9) Fixing bolt 10 is installed to be penetrated through the screw type, and the reinforcing rod 11 surrounding the outside of the clamp body 9 formed in the "c" shape on the outside of the central portion of the clamp body 9 is coupled to the welding installation It is.

그리고, 상기 클램프(6)의 클램프본체(9) 후면 양측에는 발판걸이대(7)의 양측 선단부가 용접으로 고정 결합되며, 클램프본체(9)의 저면과 클램프본체(9)의 저면과 근접한 발판걸이대(7)의 선단부에는 또 다른 보강대(11a)가 고정 결합되어 있다.In addition, both ends of the footrest holder 7 are fixedly welded to both sides of the rear surface of the clamp body 9 of the clamp 6, and the footrest table adjacent to the bottom surface of the clamp body 9 and the bottom surface of the clamp body 9. Another reinforcing rod 11a is fixedly coupled to the tip end portion of (7).

이와 같이 구성된 종래의 가설발판 설치대(8)를 이용하여 건조중인 선박건조물(1)에 가설발판(5)을 설치하고자 하는 경우에는 도 2 및 도 1의 (가)(나)에서 보는 바와 같이 선박건조물(1)에 돌출되게 설치된 수평돌출대(2)에 클램프(6)의 클램프본체(9)를 끼운 뒤에, 고정볼트(10)를 체결하여 클램프본체(9)의 내측으로 삽입된 수평돌출대(2)가 고정되게 한다.When the temporary scaffold 5 is to be installed on the ship building 1 being constructed using the conventional temporary scaffold mounting stand 8 configured as described above, the vessel as shown in FIGS. 2 and 1 (a) (b) After inserting the clamp main body 9 of the clamp 6 into the horizontal protruding table 2 protruding to the building 1, the horizontal protruding table inserted into the clamp main body 9 by tightening the fixing bolt 10. Let (2) be fixed.

위에서와 같이 클램프본체(9)로 수평돌출대(2)를 삽입시킨 상태로고정볼트(10)를 체결함에 따라 가설발판 설치대(8)는 선박건조물(1)에 수직으로 고정 설치되게 되며, 타측에 또 다른 가설발판 설치대(8)를 위와 동일한 방법으로 고정 설치한 뒤에 발판걸이대(7)의 걸이부(7a)에 가설발판(5)의 지지바(4)를 걸쳐 놓으면 양측 선박건조물(1) 사이에 가설발판(5)이 수평방향으로 설치되어 작업자는 어렇게 설치된 가설발판(5)에 올라서서 필요로 하는 각종 작업을 실시할 수 있게 되는 것이다.As the fixing bolt 10 is fastened in a state where the horizontal protrusion 2 is inserted into the clamp body 9 as above, the temporary scaffolding mounting stand 8 is fixed to the ship building 1 vertically and is installed on the other side. After another temporary scaffolding mounting bracket 8 is fixedly installed in the same manner as above, the support bar 4 of the temporary scaffolding 5 is placed on the hook portion 7a of the scaffolding rack 7 so that both shipbuildings (1) Temporary scaffolding 5 is installed in the horizontal direction between the worker is to be able to climb on the temporary scaffolding 5 installed in this way to perform various tasks required.

그런데, 종래의 가설발판 설치대(8)는 사다리형태의 발판걸이대(7)가 클램프(6)의 하단에 용접으로 결합되어 일체형을 이루고 있으며, 현재 사용중인 것의 길이는 2m 정도이고 무게는 15kg 정도의 무게로 제작되어 있기 때문에 그 무게가 무거우며 길이가 비교적 긴 편이다.By the way, the conventional temporary scaffolding mounting bracket 8 is a ladder-shaped scaffolding rack 7 is joined to the lower end of the clamp 6 by welding to form an integrated, the length of the current being used is about 2m and weight of about 15kg Because it is made of weight, its weight is heavy and its length is relatively long.

위에서와 같이 무거우면서 길이가 긴 가설발판 설치대(8)를 낭떠리지와 같이 높고 안전수단이 마련되어 있지 않은 곳에서 설치해야 하므로, 설치작업이 매우 불편하고 어려워서 추락사고의 위험성이 있었다.Heavy and long temporary scaffolding stand (8) as above should be installed in a place without high safety, such as a cliff, because the installation work is very inconvenient and difficult, there was a risk of falling accident.

또한, 종래의 가설발판 설치대(8)는 하측에 사다리형태로 길이가 긴 발판걸이대(7)가 일체로 고정되어 있어서, 클램프(6)는 상측에 고정되고 하측의 발판걸이대(7)는 하측으로 늘어 트려지는 형태로만 설치가 가능하여 가설발판 설치대(8)를 수평방향으로 설치해야 하는 경우가 있어도 수평방향으로는 설치할 수 없는 사용상의 한계를 지니고 있었다.In addition, the conventional temporary scaffolding mounting stand 8 is fixed to the lower side of the long scaffolding stand 7 is integrally fixed, the clamp 6 is fixed to the upper side and the lower scaffolding stand 7 to the lower side The installation could only be performed in a stretched form, and thus the temporary mounting platform 8 had a limitation in use which could not be installed in the horizontal direction.

본 고안은 상기의 문제점을 해결하기 위하여 상측의 클램프와 하측의 발판걸이대를 분리구성하여 클램프의 설치작업이 안전하고 간편하도록 하고, 클램프가 분리되어 있음에 따라 클램프를 수직방향이나 수평방향을 가리지 않고 설치가 가능하도록 한 것을 기술적 과제로 한다.In order to solve the above problems, the present invention separates the upper clamp and the lower footrest stand so that the installation of the clamp is safe and simple. As the clamp is separated, the clamp does not cover the vertical or horizontal direction. It is a technical subject to make installation possible.

상기의 목적을 달성하기 위한 본 고안은 선박건조물의 수평돌출대 및 수직돌출대에 클램핑 고정되는 클램프와 가설발판을 걸어서 설치하는 사다리형태의 발판걸이대가 서로 분리되게 구성되며, 상기 클램프는 "ㄷ"자형으로 형성된 클램프본체의 양측에 클램프본체의 상하면과 후면을 감싸는 형태로 보강대가 일체로 형성되고, 클램프본체의 상면에는 클램프본체로 삽입되는 수평돌출대 및 수직돌출대를 클램핑하는 고정볼트가 체결되며, 클램프본체의 저면에는 한쌍의 걸이구멍이 형성된 걸이대가 하향 형성되고, 상기 발판걸이대는 양측 지지봉 사이에 다수개의 걸이부가 간격을 두고 설치되며, 양측 지지봉의 상부에 상기 걸이구멍에 걸어지는 걸고리부가 절곡되게 형성된 것을 특징으로 한다.The present invention for achieving the above object is configured to be clamped to the horizontal protrusion and vertical protrusion of the ship building and the ladder-type footrest rack is installed to hang the temporary scaffold is separated from each other, the clamp is "c" Reinforcing bars are integrally formed on both sides of the clamp body formed in the shape of the clamp body so as to surround the upper and lower surfaces of the clamp body, and fixing bolts for clamping the horizontal protrusion and the vertical protrusion that are inserted into the clamp body are fastened to the upper surface of the clamp body. On the bottom of the clamp main body, a pair of hooks formed with a pair of hook holes is formed downward, and the footrest rack is provided with a plurality of hooks at intervals between the supporting rods on both sides, and a hook portion bent on the hook hole on both upper support rods is bent. Characterized in that formed.

도 1의 (가)(나)는 종래 가설발판 설치대의 전부와 일부를 나타내는 사시도.1 (a) (b) is a perspective view showing all and part of a conventional temporary scaffolding mounting stage.

도 2는 종래 가설발판 설치대의 사용상태를 나타내는 측단면도.Figure 2 is a side cross-sectional view showing a state of use of the conventional temporary scaffolding installation.

도 3은 본 고안에 따른 가설발판 설치대를 나타내는 요부발췌 분리사시도.Figure 3 is an exploded perspective view of the lumbar excavation showing the temporary scaffold mounting stand according to the present invention.

도 4는 본 고안의 일사용상태를 나타내는 사시도.Figure 4 is a perspective view showing a working state of the present invention.

도 5의 (가)(나)는 본 고안의 일사용상태와 다른 사용상태를 나타내는 측단면도.Figure 5 (a) (b) is a side cross-sectional view showing a different use state than the working state of the present invention.

도 6은 본 고안의 주요 구성요소인 클램프의 다른 사용예를 나타내는 사시도이다.6 is a perspective view showing another example of use of the clamp which is the main component of the present invention.

〈도면의 주요 부분에 대한 부호의 설명〉<Explanation of symbols for main parts of drawing>

1 : 선박건조물 2 : 수평돌출대 3 : 수직돌출대1: Ship building 2: Horizontal protrusion 3: Vertical protrusion

4 : 지지바 5 : 가설발판 6 : 클램프4 support bar 5 temporary scaffold 6 clamp

7 : 발판걸이대 8 : 가설발판 설치대 9 : 클램프본체7: scaffolding rack 8: temporary scaffolding mounting table 9: clamp body

10 : 고정볼트 11 : 보강대 12 : 걸이구멍10: fixing bolt 11: reinforcing rod 12: hook hole

13 : 걸이대 14 : 걸고리부 15 : 와이어13 hanger 14: hook portion 15: wire

이하 본 고안에 따른 선박건조용 가설발판설치대에 대하여 첨부된 도면 도 3 내지 도 6을 참고하여 설명하면 다음과 같다.Hereinafter, with reference to the accompanying drawings, Figures 3 to 6 for the ship construction temporary scaffolding installation according to the present invention.

도 3은 본 고안에 따른 가설발판 설치대(8)를 나타내는 요부발췌 분리사시도이고, 도 4는 본 고안의 일사용상태를 나타내는 사시도이며, 도 5의 (가)(나)는 본 고안의 일사용상태와 다른 사용상태를 나타내는 측단면도이고, 도 6은 본 고안의 주요 구성요소인 클램프의 다른 사용예를 나타내는 사시도이다.3 is an exploded perspective view showing the excavated footrest mounting stand 8 according to the present invention, Figure 4 is a perspective view showing the working condition of the present invention, Figure 5 (a) (b) is the daily use of the present invention Figure 6 is a side cross-sectional view showing a different state of use, Figure 6 is a perspective view showing another example of use of the clamp which is the main component of the present invention.

본 고안에 의한 선박건조용 가설발판설치대는 선박건조물(1)에 수평 및 수직으로 설치되어 있는 수평돌출대(2) 및 수직돌출대(3)에 클램핑 고정되는 클램프(6)와, 가설발판(5)을 걸어서 설치하는 사다리형태의 발판걸이대(7)가 서로 분리되게 구성되어 있다.Ship construction temporary scaffolding mounting according to the present invention is a clamp (6) clamped to the horizontal protrusions (2) and vertical protrusions (3) which are installed horizontally and vertically on the ship building (1), and a temporary scaffolding ( 5) The ladder-shaped scaffolding stand 7 which is installed by hanging is configured to be separated from each other.

상기 클램프(6)는 도 3에서 보는 바와 같이 "ㄷ"자형으로 형성된 클램프본체(9)의 양측에 "ㄷ"자형으로 형성되어 클램프본체(9)의 상하면과 후면을 감싸는 형태로 보강대(11)가 일체로 형성되고, 클램프본체(9)의 상면에는 클램프본체(9)로 삽입되는 수평돌출대(2) 및 수직돌출대(3)를 클램핑하는 고정볼트(10)가 관통되게 체결되며, 클램프본체(9)의 저면에는 한쌍의 걸이구멍(12)이 형성된 걸이대(13)가 하향 형성되어 있다.The clamp 6 is formed in a "c" shape on both sides of the clamp body (9) formed in the "c" shape as shown in Figure 3 to surround the upper and lower surfaces and the rear surface of the clamp body (9) (11) Is integrally formed, and the fixing bolt 10 for clamping the horizontal protrusion 2 and the vertical protrusion 3 inserted into the clamp body 9 is fastened to the upper surface of the clamp body 9 through the clamp. On the bottom of the main body 9, a hanger 13 on which a pair of hangers 12 are formed is formed downward.

그리고, 상기 발판걸이대(7)는 도 3 및 도 4에서 보는 바와 같이 양측 지지봉(7b) 사이에 다수개의 걸이부(7a)가 간격을 두고 설치되며, 양측 지지봉(7b)의 상부에 상기 걸이구멍(12)에 걸어지는 걸고리부(14)가 절곡되게 형성되어 있다.In addition, as shown in FIGS. 3 and 4, the scaffolding stand 7 is provided with a plurality of hooks 7a spaced apart from each other between the supporting rods 7b, and the hook hole is formed on the upper sides of the supporting rods 7b. Hook portion 14 to be hooked to (12) is formed to be bent.

상기와 같이 구성되어 있는 본 고안의 설치 및 작용 관계를 도 3 내지 도 6을 참고하여 설명하면 다음과 같다.If described with reference to Figures 3 to 6 the installation and working relationship of the present invention is configured as described above.

건조중인 선박에 용접이나 도색등의 작업을 수행하고자 하는 경우에는 작업자의 안전한 작업을 위하여 가설발판을 설치하는데, 도 4 및 도 5의 (가)에서와 같이 선박건조물(1)에 수평으로 설치된 수평돌출대(2)에 가설발판 설치대(8)를 설치하는 경우와, 도 5의 (나)와 같이 선박건조물(1)에 수직으로 설치된 수직돌출대(3)에 가설발판 설치대(8)를 설치하는 경우가 있는데, 수평돌출대(2)에 가설발판 설치대(8)를 설치하는 예부터 먼저 설명한다.If you want to perform work such as welding or painting on the ship under construction, install a temporary scaffold for the safe operation of the worker, horizontally installed horizontally on the ship building (1) as shown in Figs. In the case of installing the temporary scaffold mounting bracket 8 on the protrusion 2 and installing the temporary scaffold mounting bracket 8 on the vertical protrusion 3 installed perpendicular to the ship building 1 as shown in FIG. Although there is a case, it will be described first from the example of installing the temporary scaffolding mounting platform (8) on the horizontal protrusion (2).

도 4 및 도 5의 (가)에서 보는 바와 같이 선박건조물(1)에 수평으로 설치된 수평돌출대(2)에 가설발판 설치대(8)를 설치하고자 하는 경우에는 클램프(6)의 개구된 클램프본체(9)를 선박건조물(1)의 수평돌출대(2)에 끼운 뒤에 클램프본체(9) 상측의 고정볼트(10)를 체결시키면, 고정볼트(10)의 끝단부가 수평돌출대(2)의 상면을 조여주어 클램프본체(9)의 하판부분과 고정볼트(10)의 끝단부 사이에서 견고하게 고정되어 클램프(6)가 선박건조물(1)의 수평돌출대(2)에 견고하게 고정되게 된다.As shown in (a) of FIG. 4 and FIG. 5, when the temporary scaffold mounting stand 8 is to be installed on the horizontal protrusion 2 installed horizontally on the ship building 1, the clamp main body of the clamp 6 is opened. (9) is inserted into the horizontal protrusion (2) of the ship building (1), and then tighten the fixing bolt (10) above the clamp body (9), the end of the fixing bolt (10) of the horizontal protrusion (2) Tighten the upper surface to be firmly fixed between the lower plate portion of the clamp body (9) and the end of the fixing bolt 10 so that the clamp (6) is firmly fixed to the horizontal protrusion (2) of the ship building (1) .

상기와 같이 클램프(6)를 선박건조물(1)의 수평돌출대(2)에 고정 설치한 뒤에는 클램프(6)의 하측에 하향 설치된 걸이대(13)의 걸이구멍(12)에 사다리형태로 형성된 발판걸이대(7)의 상단 걸고리부(14)를 끼워 넣으면서 걸면, 발판걸이대(7)의 걸고리부(14)가 클램프(6)의 걸이구멍(12)에 걸려서 발판걸이대(7)가 클램프(6)의 하측에 매달리게 설치되는 것이며, 타측에도 가설발판 설치대(8)을 설치하였던과 동일하게 또 다른 가설발판 설치대(8)를 설치한다.After the clamp 6 is fixed to the horizontal protrusion 2 of the ship building 1 as described above, the scaffold formed in a ladder shape in the hook hole 12 of the hanger 13 installed downward in the lower side of the clamp 6. When the upper hook portion 14 of the hanger 7 is inserted, the hook 14 of the footrest 7 is caught by the hook hole 12 of the clamp 6 so that the footrest 7 is clamped. It is to be installed on the lower side of the installation, and the other side is installed another temporary scaffolding mounting stand (8) in the same way as the temporary scaffolding mounting bracket (8).

위에서와 같이 서로 대응하는 부분에 가설발판 설치대(8)를 각각 설치한 뒤에는 4 및 도 5의 (가)에서 보는 바와 같이 지지바(4)를 양측 발판걸이대(7)의 걸이부(7a)에 걸쳐지게 올려놓고 그 상부에 가설발판(5)을 설치하면 가설발판(5)의 설치가 완료되는 것이며, 상기 걸이부(7a)에 걸쳐지게 올려놓은 지지바(4)를 철사등의 와이어로 묶으면 더욱더 안정되게 설치할 수 있는 것이다.After installing the temporary scaffolding mounting brackets 8 at the portions corresponding to each other as described above, as shown in Figs. 4 and 5 (a), the support bars 4 are attached to the hook portions 7a of the both side mounting racks 7. If you put it up and install the temporary scaffold 5 on the upper part, the installation of the temporary scaffold 5 is completed, and the support bar 4 placed on the hanger 7a is bundled with a wire such as a wire. If you can install more stable.

다음은 도 5의 (나) 및 도 6에 도시된 경우에 대한 설명으로 수평돌출대(2)에 가설발판 설치대(8)를 설치하는 것은 도 4 및 도 5의 (가)의 경우에 설치하는것과 동일하게 설치하고, 수직돌출대(3)에 클램프(6)를 설치하는 것은 클램프(6)의 개구된 클램프본체(9)를 선박건조물(1)에 수직방향으로 설치된 수직돌출대(3)에 삽입시킨 상태에서 고정볼트(10)를 체결하여 클램프(6)를 수직돌출대(3)에 견고하게 고정시킨다.The following is a description of the cases shown in (b) and 6 of FIG. 5 to install the temporary scaffolding mounting platform 8 on the horizontal protrusion 2 to be installed in the case of (a) of FIG. Installing in the same manner as the above, and installing the clamp 6 on the vertical protrusion (3) is the vertical protrusion (3) provided with the clamp body (9) opened in the vertical direction to the ship building (1) The clamp 6 is firmly fixed to the vertical protrusion 3 by fastening the fixing bolt 10 in the inserted state.

상기와 같이 클램프(6)를 수직돌출대(3)에 고정설치하면 클램프(6)는 보강대(11) 부분이 상하방향으로 위치하게 되며, 이렇게 보강대(11) 부분이 상하로 위치된 상태에서 도 6에 도시된 바와 같이 클램프(6)의 상부측 보강대(11)의 상부에 지지바(4)를 올려놓은 상태로 클램프(6)와 지지바(4)를 철사등의 와이어(15)로서 묶어서 지지바(4)의 일측단이 수직돌출대(3)에 설치된 클램프(6)에 고정시킬 수 있게 되고, 타측은 발판걸이대(7)의 걸이부(7a) 올려놓고 와이어로 고정시킨 뒤에 지지바(4)의 상면에 가설발판(5)을 설치하면 가설발판의 설치가 완료되게 되는 것이다.When the clamp 6 is fixed to the vertical protrusion 3 as described above, the clamp 6 is positioned in the up and down direction of the reinforcing bar 11, and thus the reinforcing bar 11 is positioned up and down. As shown in FIG. 6, the clamp 6 and the support bar 4 are bundled together with wires 15 such as wires while the support bar 4 is placed on the upper side reinforcement 11 of the clamp 6. One end of the support bar (4) can be fixed to the clamp (6) installed on the vertical protrusion (3), and the other side is put on the hook portion (7a) of the footrest rack (7) and fixed with wire and then the support bar When the temporary scaffold 5 is installed on the upper surface of (4), the installation of the temporary scaffold is completed.

상기와 같이 본 고안의 선박건조용 가설발판설치대는 상측의 클램프와 하측의 발판걸이대를 분리구성하여 클램프의 부피와 무게가 대폭 축소된 상태가 되므로 클램프의 설치작업이 안전하고 간편하게 이루어지는 잇점과, 클램프가 분리되어 있음에 따라 클램프를 수직방향이나 수평방향을 가리지 않고 설치가 가능하여 발판걸이대를 사용하지 않고 클램프만으로도 가설발판을 설치할 수 있는 효과가 있는 것이다.As described above, the temporary construction scaffold installation stand for ship construction of the present invention separates the upper clamp and the lower scaffolding stand so that the volume and weight of the clamp are greatly reduced. Since the clamp can be installed without covering the vertical or horizontal direction, it is effective to install the temporary scaffolding with only the clamp without using the scaffolding stand.

또한, 본 고안의 클램프는 보강대가 클램프본체의 양측에 클램프본체를 감싸는 형태로 설치되어 강도가 향상되는 장점이 있고, 클램프를 녹이슬지 않는 스텐레스스틸로 제작하므로 수명이 오래가는 효과와 특히 고정볼트와 고정볼트가 체결되는 암나사부가 부식되지 않으므로 고정볼트를 조이고 푸는 작업이 원활하게 이루어지는 효과를 아울러 지니고 있는 것이다.In addition, the clamp of the present invention has the advantage that the reinforcing rod is installed in the form of wrapping the clamp body on both sides of the clamp body, the strength is improved, and the clamp is made of stainless steel that does not rust, so the effect of long life and especially fixing bolts Since the female thread to which the fixing bolt is fastened does not corrode, it has the effect of smoothing and loosening the fixing bolt.

Claims (1)

본 고안은 선박건조물(1)의 수평돌출대(2) 및 수직돌출대(3)에 클램핑 고정되는 클램프(6)와 가설발판(5)을 걸어서 설치하는 사다리형태의 발판걸이대(7)로 이루어지는 가설발판 설치대(8)에 있어서,The present invention consists of a ladder-type scaffolding rack (7) that is installed by hanging the clamp 6 and the temporary scaffolding (5) clamped to the horizontal protrusion (2) and the vertical protrusion (3) of the ship building (1) In the temporary scaffold mounting stand 8, 상기 클램프(6)와 발판걸이대(7)가 서로 분리되게 구성되며,The clamp 6 and the footrest rack 7 are configured to be separated from each other, 상기 클램프(6)는 "ㄷ"자형으로 형성된 클램프본체(9)의 양측에 클램프본체(9)의 상하면과 후면을 감싸는 보강대(11)가 일체로 형성되고, 클램프본체(9)의 상면에는 클램프본체(9)로 삽입되는 수평돌출대(2) 및 수직돌출대(3)를 클램핑하는 고정볼트(10)가 관통되게 체결되며, 클램프본체(9)의 저면에는 한쌍의 걸이구멍(12)이 형성된 걸이대(13)가 하향 형성되고,The clamp 6 is integrally formed with a reinforcing bar 11 surrounding the upper and lower surfaces and the rear surface of the clamp main body 9 on both sides of the clamp main body 9 formed in a "c" shape, and clamps on the upper surface of the clamp main body 9. The fixing bolt 10 clamping the horizontal protrusion 2 and the vertical protrusion 3 inserted into the main body 9 are fastened to each other, and a pair of hook holes 12 are formed at the bottom of the clamp body 9. The formed hanger 13 is formed downward, 상기 발판걸이대(7)는 양측 지지봉(7b) 사이에 다수개의 걸이부(7a)가 간격을 두고 설치되며, 양측 지지봉(7b)의 상부에 상기 걸이구멍(12)에 걸어지는 걸고리부(14)가 절곡되게 형성된 것을 특징으로 하는 선박건조용 가설발판설치대.The footrest rack 7 is provided with a plurality of hook portions 7a at intervals between the support rods 7b on both sides, and the hook portion 14 hanging on the hook hole 12 on the upper sides of the support rods 7b. Ship construction temporary scaffolding installation characterized in that the bent.
KR20-2002-0036377U 2002-12-05 2002-12-05 Devise constructing the scaffold for shipbuilding KR200305893Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2002-0036377U KR200305893Y1 (en) 2002-12-05 2002-12-05 Devise constructing the scaffold for shipbuilding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2002-0036377U KR200305893Y1 (en) 2002-12-05 2002-12-05 Devise constructing the scaffold for shipbuilding

Publications (1)

Publication Number Publication Date
KR200305893Y1 true KR200305893Y1 (en) 2003-03-03

Family

ID=49401917

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2002-0036377U KR200305893Y1 (en) 2002-12-05 2002-12-05 Devise constructing the scaffold for shipbuilding

Country Status (1)

Country Link
KR (1) KR200305893Y1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200465246Y1 (en) 2012-08-16 2013-02-07 전진흥 scaffolding equipment
KR200486124Y1 (en) 2017-04-11 2018-04-04 대명테크 주식회사 Footrest for shipbuilding
KR200488890Y1 (en) * 2017-12-12 2019-04-01 삼성중공업 주식회사 Apparatus for fixing scaffold
KR20200000857U (en) 2018-10-22 2020-05-04 대명테크 주식회사 Step frame for high place work
KR102577567B1 (en) * 2022-12-23 2023-09-12 한화시스템 주식회사 Lunching apparatus of underwater vehicle and lunching method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200465246Y1 (en) 2012-08-16 2013-02-07 전진흥 scaffolding equipment
KR200486124Y1 (en) 2017-04-11 2018-04-04 대명테크 주식회사 Footrest for shipbuilding
KR200488890Y1 (en) * 2017-12-12 2019-04-01 삼성중공업 주식회사 Apparatus for fixing scaffold
KR20200000857U (en) 2018-10-22 2020-05-04 대명테크 주식회사 Step frame for high place work
KR102577567B1 (en) * 2022-12-23 2023-09-12 한화시스템 주식회사 Lunching apparatus of underwater vehicle and lunching method thereof

Similar Documents

Publication Publication Date Title
US4805735A (en) Scaffolding net system
KR200305893Y1 (en) Devise constructing the scaffold for shipbuilding
JP2009108473A (en) Hanging scaffold erection method for elevated structure
KR200389693Y1 (en) Fabricated scaffold for working in the block of a hull
JP6783011B1 (en) Suspended scaffolding
KR200409977Y1 (en) Hanger way bridge checking supporter
CA2268946A1 (en) Securing device for a supporting bar
KR200413590Y1 (en) Scaffold and construction structure thereof
CN211229470U (en) Multi-point suspension scaffold
JP4057957B2 (en) Ladder fitting for manhole
JP3672151B2 (en) Wire rope type suspension ladder equipment
JP2021075967A (en) Suspended scaffolding
JPH0542504U (en) Bracket for fixing scaffold skirting boards
KR200336394Y1 (en) A tool for fixing the bedplate
JP3485534B2 (en) Scaffolding protection device, scaffolding pipe device and scaffolding device
KR0151942B1 (en) Build-up type scaffolding
JP3470162B2 (en) Wiring and piping material holder and wiring and piping material holder body
KR200291504Y1 (en) Scaffold support devic for construction
JP4148631B2 (en) Suspension scaffold for steel construction
CN218521619U (en) A assembled support for bridge construction
JP2000314234A (en) Device of mounting cargo receiving stage for single tube scaffolding
KR100460230B1 (en) Scaffold support devic for construction
JPH0748866Y2 (en) Scaffolding structure for cable laying
JP2739400B2 (en) Working scaffold for deep foundation
KR200343844Y1 (en) A hanger for installed cable

Legal Events

Date Code Title Description
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20090120

Year of fee payment: 7

LAPS Lapse due to unpaid annual fee