KR20030077498A - A drain at slope - Google Patents

A drain at slope Download PDF

Info

Publication number
KR20030077498A
KR20030077498A KR1020030059726A KR20030059726A KR20030077498A KR 20030077498 A KR20030077498 A KR 20030077498A KR 1020030059726 A KR1020030059726 A KR 1020030059726A KR 20030059726 A KR20030059726 A KR 20030059726A KR 20030077498 A KR20030077498 A KR 20030077498A
Authority
KR
South Korea
Prior art keywords
coupling
frame
slope
plate
side walls
Prior art date
Application number
KR1020030059726A
Other languages
Korean (ko)
Other versions
KR100561716B1 (en
Inventor
박이근
Original Assignee
박이근
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박이근 filed Critical 박이근
Priority to KR1020030059726A priority Critical patent/KR100561716B1/en
Publication of KR20030077498A publication Critical patent/KR20030077498A/en
Application granted granted Critical
Publication of KR100561716B1 publication Critical patent/KR100561716B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B13/00Irrigation ditches, i.e. gravity flow, open channel water distribution systems
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B5/00Artificial water canals, e.g. irrigation canals
    • E02B5/02Making or lining canals
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines

Abstract

PURPOSE: A side gutter is provided to prevent the breaking of the ground and a landslide by securing the safety of a slope. CONSTITUTION: The side gutter composed of a base plane(A1) and both sidewalls(A2) comprises the steps of forming cover hanging projections(A3) on the upper sides of both sidewalls(A2), fitting a portion of a bearing-coupling bar(A5) to a hole(A4) of a drainpipe(A), placing vertical frames(B2) which is formed vertically on a horizontal frame(B1) perpendicular to a backing frame(B3) on the remaining projected bearing-coupling bar(A5), forming a coupling projection(B5) and a coupling groove(B6) on the vertical frame(B2), and coupling many holes penetrated under the vertical frames(B2) of the inclined bearing plate(B) attached with woven fabrics(B7) on the backside of a perforated plate(B4).

Description

측구{A DRAIN AT SLOPE}Side ball {A DRAIN AT SLOPE}

본 발명은 도로 사면, 터널 입갱부, 택지조성 등의 절·성토 토목공사에 있어서 강우시 사면 하부 지반 내로 우수의 유입을 방지하는 원활한 배수로를 확보하는 사면 안전대책공법으로서, 누구나 손쉽게 시공할 수 있고 시공 후에도 사면의 안전성을 확보해 주는 산마루 측구에 관한 것이다.The present invention is a slope safety measures to secure a smooth drainage to prevent the inflow of rainwater into the lower slopes during rainfall in road slopes, tunnel tunnels, housing site construction, etc., anyone can easily construct It relates to the ridge side opening that ensures the safety of the slope even after construction.

종래 산마루 측구의 기본적인 구조는 그 용도와 형태, 제작 재료 등에 따라다양하게 구분되는데, PE 제품의 경우에는 도1a와 같이 본체(101), 바닥재(102), 걸림판(103), 본체보강재(104), 바닥보강재(105), 수밀보강바닥이음재(106), 버팀재(107), 수밀보강이음재(108)으로 구성된다.Conventionally, the basic structure of the ridged side opening is variously classified according to its use, form, and manufacturing material. In the case of PE products, as shown in FIG. 1A, the main body 101, the flooring material 102, the locking plate 103, and the main body reinforcement material 104 are provided. ), The bottom reinforcement 105, the watertight reinforcement bottom joints 106, the support material 107, the watertight reinforcement joints (108).

그러나, 콘크리트 제품의 경우에는 도1b와 같이 바닥부(201)와 양측벽부(202)로 구성되고 일측에 연결결합부(203)가 형성된 구조로서 그 구성이 비교적 간단하다. 각 구성별 특징은 본체와 바닥재는 우수를 흘려 보내기 위한 용도로 누수와 부력으로부터의 보호를 위한 장치가 대개 포함되어 있고, 기존 제품을 구성하는 부분품의 재질에 있어서 바닥재는 본체와 다른 재질인 보강섬유 혼합콘크리트로 제작되고 있으며, 버팀대와 바닥보강재는 측구의 사용목적에 부합하기 위하여 그 형태를 보존 유지하기 위한 재질이면 가능하고, 수밀보강이음재는 측구에 자연집수로 배수되는 과정에서의 누수를 방지하기 위하여 사용되므로 방수성 물질이 적합하다.However, in the case of concrete products, as shown in Figure 1b is composed of a bottom portion 201 and both side wall portion 202 and a coupling coupling portion 203 formed on one side of the structure is relatively simple. The characteristics of each component are that the main body and the flooring material are used to drain the rainwater, and a device for protecting against leakage and buoyancy is usually included, and the flooring material is a reinforcing fiber which is different from the main body in the material of the parts constituting the existing product. It is made of mixed concrete, and the brace and floor reinforcement can be made of material to preserve its shape in order to meet the purpose of the side opening, and the watertight reinforcing joint material prevents water leakage in the process of draining to the side. Waterproof material is suitable because it is used.

이상과 같은 기존 측구의 시공방법을 설명하면, 먼저 측구설치를 위해 소요공간을 굴착 , 측구의 설치(기성제품 또는 현장타설 콘크리트 제작), 굴착부의 측구 설치 후 잉여 굴착부 되메우기와 다짐 실시 순으로 시공된다.When explaining the construction method of the existing side hole as described above, first excavate the required space for the installation of the side hole, installation of the side hole (made of ready-made products or cast-in-place concrete), and construction of the excavation part backfilling and compaction do.

그러나, 기존 측구제품 및 현장타설 측구를 설치하는 일련의 시공공정에서는 측구 측벽부 상단까지만 되메움 할 수 있고 측구 하부 및 주변지반의 되메움토의 다짐이 원활하게 이뤄질 수 없기 때문에, 강우시 상부 사면의 지표면을 따라 흘러 내려온 우수가 측구 내로 전량 유입되지 못하고 주변지반의 세굴로 인해 측구와 지반의 연결부에서 단차가 발생하여 우수의 상당량이 측구 측면부와 하부를 통해 사면 하부 지반 내로 유입되게 된다. 우수가 사면 내로 유입되면 지반의 단위중량이 증가되고, 지반의 강도가 저하되어 사면 전체의 안전율이 크게 떨어지므로 사면의 붕괴를 위협하게 된다.However, in the series of installation process for installing existing side products and field casting side outlets, only the top side of the side wall part can be backfilled, and the backfill of the bottom side and surrounding ground cannot be made smoothly. Rainfall that flows down the surface of the ground cannot flow into the sidewalls, and scours in the surrounding grounds cause a step at the connections between the sideways and the grounds, and a considerable amount of rainwater flows into the lower slopes through the sidewalls and the bottoms. When rainwater flows into the slope, the unit weight of the ground increases, the strength of the ground decreases, and the safety factor of the slope decreases significantly, thereby threatening the collapse of the slope.

이러한 문제점으로 인하여 측구 시공시에 작업자에게 충분히 숙지시키고 있으나, 작업자의 이해부족과 이론적 배경 결핍으로 인한 시공의 불확실성 등으로 측구가 올바르게 설치되지 않을 뿐만 아니라 측구 주변에 실시한 식생 등도 주변지반의 세굴로 인해 무용지물이 되는 등 완전한 시공관리가 부족한 것이 현실이다.Due to these problems, they are fully familiar with the workers during construction of the sideways, but the side openings are not installed correctly due to the uncertainty of construction due to the lack of understanding of the worker and the lack of theoretical background. The reality is that there is a lack of complete construction management such as becoming useless.

특히 현재 권장하고 있는 현장 타설의 경우, 높은 사면과 대규모 사면의 경우에는 시공이 거의 불가능하고 공기와 많은 인력이 소모될 뿐만 아니라 필요에 따라 절취사면 상부로 현장타설용 장비를 이동하여야 하는 등 원활한 작업마저 어려운 경우가 대부분이며 기존 측구의 시공 후의 문제는 강우시 경사면으로부터 흘러 내려오는 우수의 대부분이 측구로 유입되지만, 측구주변의 약한 지반을 우선적으로 세굴시키고, 또한 다짐이 원활하지 않아 측구 주변지반의 침식이 유발되어 측구와 지반의 연결부에 단차가 발생하게 된다.Particularly, in the case of the currently recommended on-site casting, it is almost impossible to construct high and large slopes, it consumes a lot of air and manpower, and it is necessary to move the equipment for on-site casting to the upper part of the cut-off slope as needed. In most cases, the problem after the construction of existing sidewalls is that most of the rainwater flowing down from the slopes during rainfall falls into the sideways, but the weak ground around the sideways is preferentially scoured and the compaction is not smooth. Erosion is triggered and a step occurs in the connection between the side port and the ground.

이러한 현상으로 우수는 결국 측구 하부로 유입되고 이는 사면을 이루는 지반의 단위중량을 증가시키고, 지반강도는 저하시켜 사면의 붕괴가 유발되는 매몰사고로 이어지게 된다.As a result, rainwater eventually flows into the lower side of the mouth, which increases the unit weight of the ground which forms the slope, and decreases the ground strength, which leads to the burial accident that causes the slope to collapse.

본 발명은 기존 측구 설치 후 발생하는 제 문제점들을 해결하기 위한 측구에관한 것으로서, 상부사면쪽의 측구벽 상단에 유공벽과 세립분 유실을 방지시켜줄 배수용 매트(부직포)를 간단하게 현장에서 조립·설치해두고 유공벽 상단까지 되메움 높이를 증가시켜 둠으로써 향후 측구 주변지반의 침식·세굴, 다짐 등에 의해서도 측구와 지반의 연결부에 단차가 발생하지 않도록 하여 대형의 사면붕괴 사고를 방지하자는 것에 그 목적이 있을 뿐만 아니라 또 다른 목적으로는 기존에 설치된 측구에 유공벽과 배수용 매트를 현장에서 간단하게 부착 시공하고, 토사 되메움 및 식생을 추가 실시함으로써 동일한 효과를 얻을 수 있어 기존 시공된 측구의 보수·보강대책으로도 활용될 수 있어 기존의 사면에 대한 측구의 안정확보대책으로서도 적용할 수 있는 그 활용성이 크게 기대되는 측구를 제공함에 목적이 있다.The present invention relates to a side opening for solving the problems occurring after the existing side opening installation, drainage mat (non-woven fabric) to prevent the loss of perforated wall and fine grains on the upper side of the side wall of the upper slope simply assembled on site The purpose is to prevent the large slope collapse by preventing the step between the side port and the ground due to the erosion, scour, and compaction of the surrounding ground in the future by increasing the backfill height to the top of the perforated wall. As well as other purposes, the same effect can be obtained by simply attaching the perforated wall and drainage mat to the existing side of the site and adding the soil backfill and vegetation. It can also be used as a reinforcement measure, which can be applied as a measure to secure the stability of the existing slopes. It aims to provide a gutter which is largely expected utilization.

도 1a는 종래 합성수지재의 측구Figure 1a is a side opening of a conventional synthetic resin material

도 1b는 종래 콘크리트재의 측구1b is a side opening of a conventional concrete material

도 2a는 본 발명에 의한 측구 분해도Figure 2a is an exploded view of the side opening according to the present invention

도 2b는 본 발명에 따른 조립된 측구의 측단면도2b is a side cross-sectional view of an assembled side mouth according to the invention

도 3a는 본 발명에 따른 다른 실시예의 측구 분해도Figure 3a is an exploded view of another embodiment of the present invention

도 3b는 본 발명에 따른 다른 실시예에 의한 측구의 측단면도Figure 3b is a side cross-sectional view of the side opening according to another embodiment according to the present invention

도 4는 본 발명에 의한 측구의 설치 상태도Figure 4 is an installation state of the side opening according to the present invention

본 발명은 도로 사면, 터널 입갱부, 택지조성 등의 절·성토 토목공사에 있어서 강우시 사면 하부 지반 내로 우수의 유입을 방지하여 원활한 배수로를 확보하므로서 사면안전을 보장할 수 있는 측구로서 도2a 및 도 2b에 나타난 바와 같이 저면(A1)과 양측벽(A2)으로 구성되고 양측벽(A2)의 상부내측으로 뚜껑걸림턱(A3)이 형성되어 있고 일측벽(A2) 상면에는 일정 간격으로 구멍(A4)이 뚫어져 있는 배수관(A)의 구멍(A4)에 지지결합봉(A5)의 일부분이 끼워져 결합되고 나머지의 돌출된 지지결합봉(A5)에 수평프레임(B1)에 수직으로 형성된 여러 개의 수직프레임(B2)이 받임프레임(B3)과 직교되게 구성되므로서 나머지 구획부에는 유공판(B4)으로 형성되어 있고 좌우 양측에 있는 수직프레임(B2) 각각에는 결합돌출부(B5)와 결합홈(B6)이 형성되어 있으며 유공판(B4) 뒷면에는 부직포(B7)가 부착된 경사면 지지판(B)의 수직프레임(B2) 바로 아래에 뚫어져 있는 여러 개의 구멍(B2')을 끼워 결합시킨 측구라 할 수 있다.The present invention is to prevent the inflow of rainwater into the lower slopes during rainfall in road slopes, tunnel openings, housing site construction, etc. as a side opening that can ensure the slope safety while ensuring a smooth drainage channel 2a and As shown in Figure 2b is composed of a bottom surface (A1) and both side walls (A2), and the lid engaging jaw (A3) is formed in the upper inner side of both side walls (A2), and the upper surface of one side wall (A2) at regular intervals ( A portion of the support coupling rod A5 is fitted into the hole A4 of the drain pipe A through which A4 is drilled, and a plurality of verticals formed perpendicular to the horizontal frame B1 to the remaining protruding support coupling rod A5. Since the frame B2 is orthogonal to the receiving frame B3, the remaining partitions are formed of perforated plates B4, and the coupling protrusions B5 and the coupling grooves B6 are formed on each of the vertical frames B2 on both left and right sides. ) Is formed on the back of the perforated plate (B4) Non-woven fabric may be combined into a number of grid-side hole (B2 ') with drilled directly below the vertical frame (B2) of the inclined support plate (B) of (B7) is attached.

본 발명의 또 다른 실시예로는 도3a 및 도3b에서와 같이 저면(C1)과 양측벽(C2)으로 구성되고 양측벽(C2)의 상부 내측으로 뚜껑걸림턱(C3)이 형성되어 있고 상부 경사면쪽으로 향하는 측벽(C2)의 외측면에 수개의 볼트(C4)가 고정되어 있는 배수관(C)의 볼트(C4)에 상하측 수평프레임(D1, D2)에 수직으로 형성된 여러 개의 수직프레임(D3)으로 구성된 구획부에는 유공판(D4)으로 형성되고 좌우 양측 수직프레임(D3)의 상판부에는 각각 결합돌출부(D5)와 결합홈(D6)이 형성되어 있으며 수직프레임(D3)의 하반부의 각각에는 2개의 결착공(D7)이 뚫어져 있고 유공판(D4)의 일측면에 부직포(D8)를 접착시킨 경사면지지판(D)에 형성된 결착공(D7)을 끼워 넣어 너트(C4')로 결착 결합시켜서 되는 측구라 할 수 있다.In another embodiment of the present invention, as shown in Figures 3a and 3b is composed of a bottom surface (C1) and both side walls (C2), the capping jaw (C3) is formed in the upper inner side of both side walls (C2) and the upper Several vertical frames (D3) formed perpendicular to the upper and lower horizontal frames (D1, D2) on the bolts (C4) of the drain pipe (C) in which several bolts (C4) are fixed to the outer side of the side wall (C2) toward the inclined surface The partition portion is formed of a perforated plate (D4) is formed in the upper plate of the left and right vertical frame (D3) engaging projections (D5) and engaging grooves (D6) are formed in each of the lower half of the vertical frame (D3) Two binding holes D7 are drilled and the binding holes D7 formed on the inclined surface support plate D to which the nonwoven fabric D8 is bonded to one side of the perforated plate D4 are inserted into the binding holes D7. It can be called a side ball.

앞의 실시예는 배수관(A)에 형성된 구멍(A4)과 경사지지판(B)에 형성된 구멍(B2')에 지지결합봉(A5)으로 연결하는 수단이고 후자는 배수관 외측면에 고정시킨 볼트를 경사지지판(B)의 수직프레임 하반부에 형성된 결착공을 끼워 넣어 너트로 결착하는 수단이다.The previous embodiment is a means for connecting the support A5 to the hole A4 formed in the drain pipe A and the hole B2 'formed in the inclined support plate B. The latter uses a bolt fixed to the outer surface of the drain pipe. It is a means for inserting the binding hole formed in the lower half of the vertical frame of the inclined support plate (B) to bind with a nut.

이상에서 배수관(A)은 통상 사용되는 콘크리트재 또는 프라스틱재가 될 수 있고 경사면 지지판(B)은 합성수지재로 일체로 성형한 것이 경비, 설치면에서 유리하며 지지결합봉은 철재, 부직포는 물이 쉽게 통과할 수 있는 것이 좋다.The drain pipe (A) can be a concrete or plastic material that is commonly used, and the inclined surface support plate (B) is formed integrally with synthetic resin material, which is advantageous in terms of security and installation, and the support coupling rod is made of steel, and the nonwoven fabric passes easily through water. It is good to be able to.

이와 같은 측구의 시공방법은 우선 배수관 설치를 위해 경사면을 가로질러배수관 크기와 시공성르 고려하여 일정크기의 도랑을 굴착하고 배수관을 설치 또는 현장타설한 후 상부 경사면측 배수관(A)의 측벽(A2)에 있는 구멍(A4)에 지지결합봉(A5)의 일부를 끼워 넣고 나머지 부분에 경사지지판(B)에 형성된 여러 개의 구멍(B2')을 끼워 경사면 지지판을 설치 연결한 다음 굴착부의 측구 설치 후 잉여 굴착부 되메우기와 상부 경사면측의 경사면 지지판(B)에 토사를 채우면서 다짐을 실시한 후 식생을 실시하면 시공이 끝난다. (도4a 및 도4b는 본 발명에 의한 측구의 설치 상태도)The construction method of the side opening first excavates a trench of a certain size in consideration of the drainage pipe size and construction characteristics to install the drainage pipe and installs or installs the drainage pipe, and then the side wall (A2) of the upper inclined side drain pipe (A) Insert a part of the support coupling rod (A5) into the hole (A4) in the hole, and then insert the inclined surface support plate by inserting several holes (B2 ') formed in the inclined support plate (B) in the remaining part, and after installing the side opening of the excavation part, surplus Construction is completed when the vegetation is carried out after filling the excavation portion and compacting the earth and sand on the inclined support plate (B) on the upper inclined surface side. (4a and 4b is an installation state diagram of the side opening according to the present invention)

이와 같은 측구는 배수로의 상부 경사면쪽의 측벽에 경사면 지지판에 설치되어 있어 경사면 지지판에 거의 경사면 지지판 높이만큼 토사로 메움 다짐하므로서 강우시 경사면에서 흘러 내려오는 물이 배수로의 측벽과 경사면과의 경계부를 침식할 수 없게 되어 배수로의 저면이나 주위에 세굴이 발생되지 않으며 또한 부직포가 부착된 경사면 지지판은 또한 상부 경사면으로 흘러 내려오는 물흐름의 세기를 약화시켜 부직포를 통해 배수로로 물이 스며 흘러 들어오게끔 하므로서 지반붕괴 및 산사태를 방지할 수 있다.This side port is installed on the inclined support plate on the side wall of the upper slope of the drainage channel, so that the slope is filled with earth and sand by the height of the inclined support plate, so that water flowing down from the inclined surface during the rainfall erodes the boundary between the side wall of the drain and the slope. This prevents scour from occurring at the bottom or around the drainage channel, and the nonwoven fabric-inclined support plate also weakens the strength of the water flowing down the upper slope, causing water to seep into the drain through the nonwoven fabric. Ground collapse and landslides can be prevented.

본 발명에 의한 측구는 강우시에도 경사면에서 측구로 유입되는 우수가 측구 하부지반으로 스며들지 않아 사면의 붕괴를 방지할 수 있게 되어 대형 매몰사고 등을 미연에 방지할 수 있게 된다.The side opening according to the present invention can prevent the collapse of the slope because rainwater that flows from the inclined surface into the side opening does not penetrate into the lower side of the ground, even in the case of rain, it is possible to prevent a large investment accident.

유공벽 높이만큼 토사를 채움하여 시공해 둠으로써, 시공시 다소 불량하게측구 주변지반이 다짐되었다 할지라도 상부 경사면에서 흘러내리는 우수는 지표면을 따라 유공벽을 통하여 측구 내로 유입되기 때문에 측구 주변지반이 유실되고, 하부지반으로 우수가 유입되는 현상을 방지할 수 있다.By filling the soil by the height of the perforated wall, even though the surrounding ground was compacted somewhat poorly during construction, the rainwater flowing down from the upper slope flows into the side opening through the perforated wall along the surface, so the surrounding ground is lost. And it can prevent the phenomenon that rainwater flows into the lower ground.

또한, 유공벽 배면에는 배수용 매트를 설치해 두기 때문에 세립분의 토사가 유실되는 것을 방지할 수 있어 우수에 의한 토사유실을 최소화할 수 있으며, 이는 사면의 녹화에도 큰 도움이 되므로 환경친화적인 측구라 할 수 있다.In addition, since the drainage mat is installed on the rear surface of the perforated wall, it is possible to prevent the sediment of fine grains from being lost, thereby minimizing the loss of soil due to rainwater, which is very helpful for the greening of slopes. can do.

그리고, 본 시공방법에서 유공벽을 배면토사보다 약간 높게 시공해 둠으로써 상부사면으로부터 굴러 내려온 토사, 작은 돌멩이 등이 측구 배수로를 막아 배수를 지연·불량하게 만드는 것을 방지할 수 있게 되어 측구의 유지관리에도 큰 도움이 될 뿐만 아니라 그 시공방법이 간단한데 비하여 그 기능은 우수하므로 사면의 안전대책공법으로서 적용성이 높은 측구라 할 수 있다.In this construction method, by constructing the perforated wall slightly higher than the back soil, it is possible to prevent the soil, small stones, etc., rolled down from the upper slope to prevent the drainage from delaying and poorly draining the drainage drainage. Not only is it a great help, but its construction method is simple, but its function is excellent, so it can be said to be a highly applicable side ball as a safety countermeasure method of slope.

Claims (2)

저면(A1)과 양측벽(A2)으로 구성되고 양측벽(A2)의 상부내측으로 뚜껑걸림턱(A3)이 형성되어 있고 일측벽(A2) 상면에는 일정 간격으로 구멍(A4)이 뚫어져 있는 배수관(A)의 구멍(A4)에 지지결합봉(A5)의 일부분이 끼워져 결합되고 나머지의 돌출된 지지결합봉(A5)에 수평프레임(B1)에 수직으로 형성된 여러 개의 수직프레임(B2)이 받임프레임(B3)과 직교되게 구성되므로서 나머지 구획부에는 유공판(B4)으로 형성되어 있고 좌우 양측에 있는 수직프레임(B2) 각각에는 결합돌출부(B5)와 결합홈(B6)이 형성되어 있으며 유공판(B4) 뒷면에는 부직포(B7)가 부착된 경사면 지지판(B)의 수직프레임(B2) 바로 아래에 뚫어져 있는 여러 개의 구멍(B2')을 끼워 결합시킨 측구.A drain pipe composed of a bottom surface A1 and both side walls A2 and a lid catching jaw A3 is formed inside the upper side of both side walls A2, and a hole A4 is drilled at a predetermined interval on the upper surface of one side wall A2. A portion of the support coupling rod A5 is fitted into the hole A4 of (A), and a plurality of vertical frames B2 are formed on the remaining protruding support coupling rod A5 perpendicular to the horizontal frame B1. Since it is configured to be orthogonal to the frame (B3), the remaining partitions are formed of the perforated plate (B4), and each of the vertical frame (B2) on both left and right coupling protrusions (B5) and coupling grooves (B6) are formed and Side side of the plate (B4) is fitted with a plurality of holes (B2 ') that are drilled just below the vertical frame (B2) of the inclined surface support plate (B) attached to the non-woven fabric (B7). 저면(C1)과 양측벽(C2)으로 구성되고 양측벽(C2)의 상부 내측으로 뚜껑걸림턱(C3)이 형성되어 있고 상부 경사면쪽으로 향하는 측벽(B2)의 외측면에 수개의 볼트(C4)가 고정되어 있는 배수관(C)의 볼트(C4)에 상하측 수평프레임(D1, D2)에 수직으로 형성된 여러 개의 수직프레임(D3)으로 구성된 구획부에는 유공판(D4)으로 형성되고 좌우 양측 수직프레임(D3)의 상판부에는 각각 결합돌출부(D5)와 결합홈(B6)이 형성되어 있으며 수직프레임(D3)의 하반부의 각각에는 2개의 결착공(D7)이 뚫어져 있고 유공판(D4)의 일측면에 부직포(D8)를 접착시킨 경사면지지판(D)에 형성된 구성(D7)을 끼워 넣어 너트(C4')로 결착 결합시켜서 되는 측구.Several bolts C4 are formed on the outer surface of the side wall B2, which is composed of a bottom surface C1 and both side walls C2, and is formed with a lid catching jaw C3 inside the upper side of both side walls C2, and faces toward the upper inclined surface. Is formed of a perforated plate (D4) in the partition portion consisting of a plurality of vertical frames (D3) formed perpendicular to the upper and lower horizontal frames (D1, D2) to the bolt (C4) of the drain pipe (C) to which is fixed Coupling protrusions D5 and coupling grooves B6 are formed in the upper plate portion of the frame D3, respectively, and two binding holes D7 are drilled in each of the lower half portions of the vertical frame D3, and one of the perforated plates D4 is formed. A side opening formed by inserting a configuration (D7) formed on an inclined surface support plate (D) to which a nonwoven fabric (D8) is attached to a side surface, and binding with a nut (C4 ').
KR1020030059726A 2003-08-28 2003-08-28 A drain at slope KR100561716B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020030059726A KR100561716B1 (en) 2003-08-28 2003-08-28 A drain at slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020030059726A KR100561716B1 (en) 2003-08-28 2003-08-28 A drain at slope

Publications (2)

Publication Number Publication Date
KR20030077498A true KR20030077498A (en) 2003-10-01
KR100561716B1 KR100561716B1 (en) 2006-03-20

Family

ID=32388599

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020030059726A KR100561716B1 (en) 2003-08-28 2003-08-28 A drain at slope

Country Status (1)

Country Link
KR (1) KR100561716B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100758560B1 (en) * 2006-08-17 2007-09-13 주식회사 계림폴리콘 Presloped precast trench structure
KR200448790Y1 (en) * 2009-10-28 2010-05-20 김흥진 Water channel
KR100965522B1 (en) * 2010-03-04 2010-06-24 주식회사 비엔디코퍼레이션 Reinforcement material for slope ditch and slope ditch structure using the same
KR200457803Y1 (en) * 2011-05-27 2012-01-03 주식회사 이케이 코프레이션 Mat with anti-insect

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100758560B1 (en) * 2006-08-17 2007-09-13 주식회사 계림폴리콘 Presloped precast trench structure
KR200448790Y1 (en) * 2009-10-28 2010-05-20 김흥진 Water channel
KR100965522B1 (en) * 2010-03-04 2010-06-24 주식회사 비엔디코퍼레이션 Reinforcement material for slope ditch and slope ditch structure using the same
KR200457803Y1 (en) * 2011-05-27 2012-01-03 주식회사 이케이 코프레이션 Mat with anti-insect

Also Published As

Publication number Publication date
KR100561716B1 (en) 2006-03-20

Similar Documents

Publication Publication Date Title
KR101023660B1 (en) Retaining Wall using Anchor and Concrete Panel and its Construction Method
KR101105092B1 (en) A precast retaining panel and construction method of the same with half pc type backfill
KR101886151B1 (en) Retaining wall structure and construction method thereof
KR100491410B1 (en) Drainage structure of an incline area
CN110258622B (en) Pile plate type retaining wall and construction method thereof
KR100753556B1 (en) De-pressure drainage method and the system
KR100665984B1 (en) The construction method of basement self drainage
KR100561716B1 (en) A drain at slope
JP5975726B2 (en) Ground structure and ground improvement method
CN113445539B (en) Limited filling tire wall and construction method thereof
JP2000144769A (en) Method of landslide protection work for preparing housing lot
CN213173779U (en) Cutting slope protection structure
KR102192445B1 (en) Retaining Wall System usable as building underground wall and Method for constructinging the same
CN210658431U (en) Pile plate type retaining wall
KR20180040095A (en) Construction method for soil retaining wall using cap slab
KR101334749B1 (en) Vegetation block in tiers for retaining wall and method for construction of retaining wall using the same
KR100370930B1 (en) The method of setting up a drain at slant face
KR101021112B1 (en) Constructing wall block
KR200223114Y1 (en) A structure reinforcing for retaining wall for inclined plane which to cut off a rock wall
KR100665985B1 (en) The construction method of basement self drainage
JP3059034U (en) Water collection and penetration joint basin for rainwater etc.
JP3709550B2 (en) Concrete retaining wall
CN217026767U (en) Existing culvert structure is striden on open cut tunnel
KR101653722B1 (en) A structure for drainage and this method using the same
CN215715242U (en) Variable cross-section T-shaped pile board wall structure

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130218

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20140212

Year of fee payment: 9

FPAY Annual fee payment
FPAY Annual fee payment

Payment date: 20160309

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20180420

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20190411

Year of fee payment: 14