KR20030047279A - Cost estimate method for construction project using historical cost data, auto cost estimate system and medium storing a computer program for performing there - Google Patents

Cost estimate method for construction project using historical cost data, auto cost estimate system and medium storing a computer program for performing there Download PDF

Info

Publication number
KR20030047279A
KR20030047279A KR1020010077733A KR20010077733A KR20030047279A KR 20030047279 A KR20030047279 A KR 20030047279A KR 1020010077733 A KR1020010077733 A KR 1020010077733A KR 20010077733 A KR20010077733 A KR 20010077733A KR 20030047279 A KR20030047279 A KR 20030047279A
Authority
KR
South Korea
Prior art keywords
project
cost
construction
database
labor
Prior art date
Application number
KR1020010077733A
Other languages
Korean (ko)
Inventor
오영석
김정섭
임인상
차태선
Original Assignee
주식회사 포스코건설
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 포스코건설 filed Critical 주식회사 포스코건설
Priority to KR1020010077733A priority Critical patent/KR20030047279A/en
Publication of KR20030047279A publication Critical patent/KR20030047279A/en

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PURPOSE: A method and system for estimating project expenses for a construction project using results data are provided to estimate an equipment cost and a construction cost at a project planning stage by converting expenses of a previous similar project into the current project expenses based on a results data of a previous construction project and correcting a time and a unit capacity. CONSTITUTION: If a project is selected out of a plurality of previous project results(S301), estimation information of the selected project is copied(S302). If at least one previous project result is selected, a weighted average value of a labor and a price according to each process is calculated from project result data of the selected project, and a project expenses application price database is created(S303). A basic estimation database is created by adding the copied estimation information of the selected project to the project expenses application price database. The created basic estimation database is corrected collectively adapted to requested contents and a characteristic(S304). After completing the correction, if the estimation data are different from new project, the estimation data are deleted, appended, or replaced(S305). A specification of a device is replaced, and an equipment cost is executed(S307). A construction cost is correct with respect to an item related to a construction only, and a construction cost is estimated(S308). An indirect cost is correct out of a construction project expenses(S309).

Description

실적데이타를 이용한 건설프로젝트용 사업비 견적 방법, 이를 수행하는 자동 견적시스템 및 기록매체{COST ESTIMATE METHOD FOR CONSTRUCTION PROJECT USING HISTORICAL COST DATA, AUTO COST ESTIMATE SYSTEM AND MEDIUM STORING A COMPUTER PROGRAM FOR PERFORMING THERE}Cost Estimation Method for Construction Projects Using Performance Data, Automatic Estimation System and Recording Media

본 발명은 건설 프로젝트의 사업비를 견적하는 방법에 관한 것으로, 보다 상세하게는 실제 사업에 들어가기전 사업기획단계에서 공사비 및 설비비의 견적을 정확하고 신속하게 견적하도록 하여 효율적인 프로젝트기획을 가능하게 한 실적데이타를 이용한 건설프로젝트용 사업비 견적 방법, 이를 수행하는 자동 견적시스템 및 기록매체에 관한 것이다.The present invention relates to a method for estimating the project cost of a construction project, and more specifically, to the project planning stage before the actual project to enter the project cost and equipment cost estimates accurately and quickly to enable efficient project planning data The project cost estimation method for the construction project using the, and the automatic estimation system and recording medium for performing the same.

일반적으로, 건설프로젝트의 사업비에 대하여 견적을 내는 경우, 건설프로젝트의 단계 및 용도에 따라서 견적의 종류가 결정되는데, 미국 코스트엔지니어링협회(AACE : Association of American Cost Engineering)는 견적방법에 따라서 견적의 종류를 개략견적, 예산견적, 상세견적으로 분류하고 있으며, 이 중에서 개략견적법은 건설 프로젝트의 타당성 및 규모가 결정되는 단계인 기획/계획 단계에서 수행하는 것으로, 과거의 유사한 프로젝트의 실제 자료를 바탕으로 견적자가 자신의 경험에 의지하여 판단하는 것이다.In general, in the case of estimating the project cost of a construction project, the type of quotation is determined according to the stage and use of the construction project, and the Association of American Cost Engineering (AACE) estimates the type of quotation according to the estimation method. Are classified into rough estimates, budget estimates, and detailed estimates. Among these, the rough estimate method is carried out at the planning / planning stage, in which the feasibility and scale of the construction project is determined, based on actual data of similar projects in the past. The estimator makes judgments based on his own experience.

더 구체적으로, 개략견적기법은 취득한 정보의 상세정보와 프로젝트의 특성을 고려하여, 단위단가법(Unit Estimate Method), 요소견적법(Factor estimate method), 변수견적법(Parameter Estimate Method), 및 비용지수법(Cost Index Estimatie Method)이 네가지 방법으로 구분하며, 그중 단위단가법은 기본 단위에대한 비용자료, 예를 들어 건물바닥의 단위 면적, 건물의 단위체적 등에 근거하여 비용을 산출하거나 건물의 용도 단위를 기준으로 하여 비용을 산출하는 것으로, 여기에서 기본 단위에 대한 비용은 과거의 유사한 프로젝트들의 비용자료를 토대로 산출된 비용공식에 의해 계산하는 것이다. 그리고, 요소견적법은 프로젝트의 사업비 혹은 공사비를 구성하는 각 요소에 대한 비용과 이의 기준요소에 대한 비용의 비율을 이용하여 개략견적가격을 산정하며, 기준요소의 비용이 산출되면 다른 요소에 대한 비용은 각 요소의 계수와 기준요소의 비용을 곱하여 산정하고, 프로젝트 전체의 비용은 모든 요소들에 대한 비용의 합으로 산출하는 것이다. 그리고, 변수견적법은 프로젝트의 규모 또는 범위에 영향을 주는 설계변수에 근거한 것으로, 즉 프로젝트의 건축, 토목, 설비, 전기 등 각 시스템에 대한 비용은 설계변수의 수량과 각 변수의 수량 단위에 대하여 견적된 시스템 비용을 곱하여 산출하며, 프로젝트의 전체 비용은 프로젝트를 구성하는 모든 시스템들의 비용을 합하여 산출한다. 마지막으로, 비용지수법은 다른 시간과 장소에서 공사금액을 지수를 사용하여 조정하는 것으로, 새로운 프로젝트의 공사비 견적에 참고하기 위해서, 과거에 수행된 유사 프로젝트 혹은 시설물의 공사비용을 지수를 사용하여 현재의 금전가치에 맞도록 환산한다. 이런 비용지수법은 건설장비 및 플랜트 설비의 비용을 견적하기 위하여 주로 사용한다.More specifically, the coarse estimating method takes into account the detailed information of the acquired information and the characteristics of the project, so that the unit estimate method, the factor estimate method, the parameter estimate method, and the cost The Cost Index Estimatie Method is divided into four methods. The unit cost method calculates costs based on cost data for basic units, for example, the unit area of a building floor, the unit volume of a building, or the unit of use of a building. The cost is calculated based on the cost baseline, where the cost for the base unit is calculated from the cost formula based on the cost data of similar projects in the past. In addition, the element estimate method estimates the rough estimate price using the ratio of the cost of each element constituting the project or construction cost of the project and the cost of the reference element, and when the cost of the reference element is calculated, the cost of other elements is calculated. Is calculated by multiplying the coefficients of each element by the cost of the reference element, and the overall project cost is the sum of the costs for all elements. In addition, the variable estimation method is based on design variables that affect the size or scope of the project, that is, the cost of each system such as the construction, civil engineering, facilities, and electricity of the project is determined by the number of design variables and the unit of quantity of each variable. It is calculated by multiplying the estimated system cost, and the total cost of the project is calculated by adding up the costs of all the systems that make up the project. Finally, the cost index method uses the index to adjust the construction cost at different times and places, and uses the index to calculate the cost of similar projects or facilities that have been carried out in the past to refer to the cost estimate for a new project. Convert to a value for money. This cost index method is mainly used to estimate the cost of construction equipment and plant equipment.

건설 프로젝트의 개략견적에서 가장 많이 이용되는 기법은 단위단가법이지만, 상기 방법들의 공통점은 과거의 실적데이타 중 프로젝트의 특성을 고려하여 신뢰할 수 있는 단위를 설정하여 과거의 공사비를 현재의 공사비로 변환하는 것으로,보다 구체적으로 개략견적가격을 산정하기 위해 시간과 단위용량의 보정을 하며, 비용지수법을 추가로 이용한다.The most widely used technique in the construction project estimate is the unit cost method, but the common method is to convert the past construction cost to the current construction cost by setting a reliable unit in consideration of the characteristics of the project among the past performance data. In order to calculate the rough estimate price more specifically, time and unit capacity are corrected and the cost index method is additionally used.

그러나, 이런 기존의 견적방법은 견적자가 개인적인 경험 및 숙달도에 의한 편리성에 따라서 상기 견적기법들을 독립적으로 활용하여 사용하기 때문에, 견적자의 숙련도에 따라 결과가 달라지며, 프로젝트의 특성과 규모를 고려한 종합적인 판단이 부족하다는 문제점이 있다.However, since the estimator uses the estimating techniques independently according to the convenience of personal experience and proficiency, the results vary depending on the skill of the estimator, There is a problem of lack of judgment.

그리고, 지금까지는 건설 프로젝트의 견적이 금액과 수량을 중심으로 수행되어 있기 때문에, 견적작업을 건설프로젝트가 결정된 후의 투찰가격 결정과 내부 예산 설정등에만 이용하고 있는 실정이며, 더하여, 이런 견적결과를 프로젝트 관리등의 기초자료로 활용하지 못하고 있다는 불합리한 점이 있었다.Until now, since estimates of construction projects have been carried out mainly on the amount and quantity, the estimates have been used only for determination of pricing and internal budget after construction projects have been decided. There was an unreasonable point that it could not be used as basic data for management.

더하여, 견적작업은 건설 프로젝트의 견적 작업을 완료하고 투찰하기 전에 입찰 전략에 의거하여 투찰가 의사 결정 프로세스를 별도로 수행하고 있기 때문에, 견적작업에 대해 소요되는 시간이 너무 길고, 투찰가 결정 과정에서 견적작업의 신뢰도가 저하되는 경향이 있으며, 더 나아가 투찰금액의 신뢰도 저하로 인하여 건설 공사 및 건설 기업의 부실을 초래하게 된다는 문제점이 발생한다.In addition, the bidding process takes too long to estimate, since the bidder's decision-making process is carried out separately according to the bidding strategy before the bidding project is completed and projected. There is a tendency that the reliability is lowered, and furthermore, a problem arises that the construction of a construction company and the construction company is inadequate due to the decrease in the reliability of the amount of the investment.

본 발명은 상술한 종래의 문제점을 해결하기 위하여 제안된 것으로서, 그 목적은 과거 건설프로젝트의 실적데이타를 근거로 과거 유사프로젝트의 사업비를 현재 사업비로 변환하고 시간과 단위용량을 보정하여 사업기획단계에서 설비비 및 공사비의 견적을 가능하도록 한 실적데이타를 이용한 건설프로젝트용 사업비 견적 방법과, 이를 수행하는 자동 견적시스템 및 기록매체를 제공하는 것이다.The present invention has been proposed to solve the above-mentioned conventional problems, the object of which is to convert the project cost of the past similar project to the current project cost and correct the time and unit capacity based on the performance data of the past construction project in the project planning stage. It is to provide a project cost estimation method for construction projects using performance data that enables the estimation of equipment costs and construction costs, and an automatic estimation system and recording medium for performing the same.

도 1은 본 발명에 따른 자동 견적 시스템의 개략구성을 보이는 블럭구성도이다.1 is a block diagram showing a schematic configuration of an automatic estimating system according to the present invention.

도 2는 본 발명에 따른 자동 견적시스템의 상세 구성을 보이는 블럭도이다.2 is a block diagram showing a detailed configuration of an automatic estimating system according to the present invention.

도 3은 본 발명의 견적방법에 의한 사업비 견적과정을 보이는 플로우챠트이다.3 is a flowchart showing a project cost estimation process according to the estimation method of the present invention.

도 4는 본 발명의 견적방법에 의한 공사비적용단가 데이타베이스 생성과정을 보이는 플로우챠트이다.4 is a flowchart showing a construction cost application cost database generation process according to the estimation method of the present invention.

도 5는 본 발명의 일실시예에 의한 실적 프로젝트의 복사화면을 보인 도면이다.5 is a view showing a copy screen of the performance project according to an embodiment of the present invention.

도 6a는 본 발명의 일실시예에 의한 용량보정화면을 보인 도면이다.6A is a view showing a capacity correction screen according to an embodiment of the present invention.

도 6b는 본 발명의 일실시예에 의한 지역보정화면을 보인 도면이다.6B is a view showing a region correction screen according to an embodiment of the present invention.

도 6c는 본 발명의 일실시예에 의한 시간보정화면을 보인 도면이다.6C is a diagram illustrating a time correction screen according to an embodiment of the present invention.

도 6d는 본 발명의 일실시예에 의한 노무비 시간보정화면을 보인 도면이다.6D is a view showing a labor cost time correction screen according to an embodiment of the present invention.

도 6e는 본 발명의 일실시예에 의한 생산성보정화면을 보인 도면이다.6E is a view illustrating a productivity correction screen according to an embodiment of the present invention.

도 7은 본 발명의 일실시예에 의한 설비비 견적화면을 보인 도면이다.7 is a view showing the equipment cost estimation screen according to an embodiment of the present invention.

도 8은 본 발명의 일실시예에 의한 공사비 견적화면을 보인 도면이다.8 is a view showing a construction cost estimation screen according to an embodiment of the present invention.

도 9는 본 발명의 일실시예에 의한 견적완료화면을 보인 도면이다.9 is a view showing a quotation completion screen according to an embodiment of the present invention.

도 10은 본 발명의 일실시예에 의한 설비비 시뮬레이션화면을 보인 도면이다.10 is a view showing the equipment cost simulation screen according to an embodiment of the present invention.

도 11은 본 발명의 일실시예에 의한 공사비 시뮬레이션화면을 보인 도면이다.11 is a view showing a construction cost simulation screen according to an embodiment of the present invention.

도 12은 본 발명의 일실시예에 의한 간접비 시뮬레이션화면을 보인 도면이다.12 is a view showing an overhead simulation screen according to an embodiment of the present invention.

도 13은 본 발명의 일실시예에 의한 시뮬레이션 후의 견적결과를 보인 도면이다.FIG. 13 is a view illustrating an estimation result after simulation according to an embodiment of the present invention. FIG.

*도면의 주요 부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

10 : 자동 견적 시스템10: automatic quotation system

11 : 컴퓨터11: computer

12 : 표시장치12: display device

15 : 기억장치15: storage device

211 : 프로젝트 실적 DB211: project performance DB

212 : 공사비 적용단가 DB212: Cost unit cost DB

213 : 보정계수 DB213: Correction Factor DB

214 : 견적 DB214: Quote DB

상술한 본 발명의 목적을 달성하기 위한 구성수단으로서, 본 발명에 의한 건설프로젝트용 사업비 견적 방법은As a construction means for achieving the above object of the present invention, the project cost estimation method for a construction project according to the present invention

다수의 과거 프로젝트 실적중 견적할 신규 프로젝트와 유사한 프로젝트를 선택하면 선택된 실적프로젝트의 견적정보를 복사하는 제1단계;A first step of copying quotation information of the selected performance project when selecting a project similar to a new project to be quoted among a plurality of past project results;

다수의 과거 프로젝트 실적중 하나이상을 선택하면 선택된 프로젝트의 공사 실적 자료로부터 각 공종별 노무공량과 적용단가의 가중평균치를 계산하고 프로젝트 실행지역의 실제 노무단가를 입력하여 노무공량 및 각종 단가자료인 공사비적용단가데이타베이스를 생성하는 제2단계;If one or more of the past project results are selected, the weighted average of labor capacity and applied unit price for each sector is calculated from the construction performance data of the selected project, and the actual labor unit price of the project execution area is input to apply the labor cost and various unit cost data. Generating a unit price database;

제1단계에서 복사된 실적프로젝트의 견적정보와 상기 제2단계에서 생성된 공사비적용단가데이타베이스의 단가정보를 합하여 기본 견적데이타베이스를 생성하는 제3단계;A third step of generating a basic estimating database by adding the quotation information of the performance project copied in the first step and the unit price information of the construction cost applying unit price database generated in the second step;

상기 제3단계에서 생성된 견적기본데이타를 신규 프로젝트의 요구사항 및 특성에 맞도록 일괄보정하는 제4단계;A fourth step of collectively correcting the quotation basic data generated in the third step to meet the requirements and characteristics of the new project;

제4단계에 의해 일괄보정이 완료된 후, 견적데이타와 신규프로젝트간에 차이가 존재하는 경우 상기 일괄보정된 견적데이타를 PBS단위로 삭제, 추가, 교체하는 제5단계;A fifth step of deleting, adding, and replacing the batch revised quote data in units of PBS when there is a difference between the quote data and the new project after the batch correction is completed by the fourth step;

견적자의 판단에 따라 기기의 사양 및 교체를 수행하여 설비비 견적을 실행하는 제6단계;A sixth step of performing an equipment cost estimate by performing a specification and a replacement of the device according to the judgment of the estimator;

설비가 아닌 공사에만 관련된 항목에 대한 공사비를 보정하여 공사비를 견적하는 제7단계; 및A seventh step of estimating the construction cost by correcting the construction cost for the item related only to the construction, not the facility; And

건설 사업비중 간접비를 보정하는 제8단계에 의해 프로젝트의 사업비를 견적하는 것을 특징으로 한다.It is characterized by estimating the project cost of the project by the eighth step of correcting the overhead of the construction project cost.

상기 제1단계에서의 유사 프로젝트의 복사시 공사비에서 각 항목의 노무공량과 단가정보는 복사되지 않는다.When copying a similar project in the first step, labor capacity and unit price information of each item are not copied from the construction cost.

그리고, 상기 제2단계에서 생성된 공사비적용단가 데이타베이스의 정보중 신규견적프로젝트로 전달되는 정보는 각 항목의 노무공량, 자재단가, 경비단가, 중기단가인 것을 특징으로 한다.In addition, the information delivered to the new estimate project among the information in the construction cost application unit price database generated in the second step is characterized in that the labor capacity, material unit cost, cost unit price, mid-term unit price of each item.

그리고, 상기 보정단계(제4단계)는 신규프로젝트의 용량에 맞춰 보정을 행하는 용량보정, 실적 프로젝트와 신규프로젝트의 건설시기에 따른 물가차이를 보정하는 시간보정, 실적프로젝트와 신규프로젝트와의 지역차이에 따른 각종 단가차이를 보정하는 지역보정, 지역및 국가별로 존재하는 건설 노동 생산성의 차이를 보정하는 생산성보정으로 이루어진다.In addition, the correction step (fourth step) is the capacity correction for the correction according to the capacity of the new project, the time correction to correct the price difference according to the construction time of the performance project and the new project, the regional difference between the performance project and the new project It consists of regional corrections to correct various unit cost differences, and productivity corrections to correct differences in construction labor productivity existing by region and country.

더하여, 상기 본 발명에 의한 견적방법은 제1단계에서 제8단계까지를 수행하여 신규프로젝트에 대한 견적이 완료된 후, 설비비, 공사비, 및 간접비의 견적금액을 조정하는 제9단계를 더 포함할 수 있으며, 그 조정은 보정계수의 변경을 통해 이루어진다.In addition, the method of estimating according to the present invention may further include a ninth step of performing the first to eighth steps to adjust the estimated amount of equipment costs, construction costs, and overhead costs after the quotation for the new project is completed. The adjustment is made by changing the correction factor.

그리고, 본 발명에 의한 견적방법에 있어서, 공사비적용단가 데이타베이스의 생성은In the estimating method according to the present invention, the generation of the cost database unit cost database is

다수의 과거 실적 프로젝트중 하나 이상을 선택하는 단계;Selecting one or more of a plurality of past performance projects;

선택된 실적 프로젝트들을 세부 항목별로 조합하여, 각종 단가 데이타베이스 및 노무공량 데이타베이스를 형성하는 단계;Combining the selected performance projects by sub-items to form various unit price databases and labor capacity databases;

신규 프로젝트의 지역에서의 실제 노무단가를 입력하여 노무단가데이타베이스를 형성하는 단계;Inputting the actual labor price in the region of the new project to form a labor price database;

상기 노무공량데이타베이스로부터 다수 노무공량을 평균하여 항목별 가중평균 노무량을 계산하는 단계;Calculating a weighted average amount of labor for each item by averaging a plurality of labor volumes from the labor capacity database;

상기 노무단가데이타베이스의 데이타를 이용하여 공종별 가중평균 노무단가를 계산하는 단계;Calculating a weighted average labor price per work type using the data of the labor price database;

상기 계산된 평균 노무량과 평균 노무단가를 곱하여 항목별 평균 노무단가를 계산하는 단계; 및Calculating the average labor price per item by multiplying the calculated average labor amount by the average labor price; And

상기 각종 단가 데이타베이스와 항목별 평균 노무단가를 적용하여 공사비 적용단가 데이타베이스를 생성하는 단계로 이루어지는 것을 특징으로 한다.It is characterized in that it comprises the step of generating a cost-cost unit cost database by applying the various unit cost database and the average labor price per item.

또한, 본 발명은 상술한 각 단계를 실행시키는 프로그램을 기록한 기록매체를 포함한다.The invention also includes a recording medium on which a program for executing each of the above-described steps is recorded.

더하여, 본 발명은 데이타 및 소프트웨어를 기억하는 기억부와 소프트웨어를 실행하기 위한 CPU 및 부팅및 작업을 위한 RAM 및 ROM을 포함한 컴퓨터로 구현된 자동견적시스템에 있어서,In addition, the present invention provides a computer-based automatic estimation system including a memory for storing data and software, a CPU for executing software, and a RAM and ROM for booting and working.

과거에 수행된 다수 프로젝트의 실제 견적데이타를 축적하여 보관하는 제1 데이타베이스;A first database for accumulating and storing actual estimate data of a plurality of projects performed in the past;

현재 견적할 프로젝트에 적용될 노무공량 및 각종 단가를 기억하는 제2데이타베이스;A second database for storing labor costs and various unit prices to be applied to the project to be estimated;

과거 프로젝트의 실적 자료를 현재 견적하는 프로젝트에 맞추어 보정하기 위한 다수의 보정지수를 저장하는 제3데이타베이스;A third database for storing a plurality of correction indices for correcting the historical data of past projects according to a project currently estimated;

현재 견적중인 프로젝트의 견적데이타를 저장하여 보관하는 제4데이타베이스;A fourth database for storing and storing estimate data of the project currently being estimated;

상기 제1데이타베이스로부터 한 프로젝트의 실적데이타를 복사하여 제4데이타베이스에 저장한 후, 상기 제1데이타베이스에 저장된 하나 이상의 실적데이타를 조합하여 각종 단가를 산출하여 제2데이타베이스에 저장하고, 제4데이타베이스로 복사된 실적데이타에 상기 제2데이타베이스의 단가를 적용하고 제3데이타베이스의 다수 보정지수를 적용하여 보정계산하여 신규프로젝트에 대한 사업비를 견적하는 견적처리부;After copying the performance data of one project from the first database and storing it in the fourth database, various unit prices are calculated by combining one or more performance data stored in the first database, and stored in the second database. An estimate processing unit applying the unit price of the second database to the performance data copied to the fourth database and calculating the correction by applying a plurality of correction indices of the third database to estimate the project cost for the new project;

상기 견적처리부에서 산출된 신규프로젝트의 견적금액을 지수보정법으로 조정하는 시뮬레이션부; 및A simulation unit for adjusting an estimate amount of the new project calculated by the quotation processing unit by an index correction method; And

견적완료된 신규프로젝트의 견적결과를 출력하는 출력부를 포함하여 이루어지는 것을 특징으로 한다.Characterized in that it comprises an output unit for outputting the estimate result of the estimated new project.

이하, 첨부한 도면을 참조하여 본 발명에 대하여 상세하게 설명한다.EMBODIMENT OF THE INVENTION Hereinafter, this invention is demonstrated in detail with reference to attached drawing.

도 1은 본 발명의 실시예에 의한 자동견적시스템(11)의 일예를 나타낸 개략구성도로서, 본 발명에 자동견적시스템(11)은, 과거 프로젝트의 실적데이타 및 견적처리에 필요한 공사비적용단가나 보정계수, 및 현재 견적처리된 결과데이타를 저장하는 기억부(15)로부터 데이타를 입력받아 선택된 과거 실적데이타에 근거하여 견적처리를 실행한 후 그 결과를 표시화면(12)에 시각적으로 표시하는 처리를 행하면서 상기 기억부(15)에 저장시키는 컴퓨터(11)로 구성된다. 그리고 상기 도면에 있어서, 14는 데이타 입력을 위한 키보드를, 13은 포인팅디바이스인 마우스를 나타낸다.1 is a schematic configuration diagram showing an example of an automatic estimation system 11 according to an embodiment of the present invention. The automatic estimation system 11 according to the present invention is a construction cost application cost required for historical data and estimate processing of past projects. A process of receiving the data from the storage unit 15 storing the correction coefficient and the result data which is currently quoted, performing the estimation process based on the selected past performance data, and then visually displaying the result on the display screen 12. It consists of the computer 11 which stores in the said memory | storage part 15, carrying out the following. In the figure, 14 denotes a keyboard for data input and 13 denotes a mouse which is a pointing device.

기억부(15)는, 컴퓨터(11) 내에 내장된 하드디스크를 이용하여도 좋지만, 여기에서는 네트워크를 통해서 컴퓨터(11)와 접속되어 있는 영상정보라이브러리나, 플로피디스크, CD-ROM, DVD등의 기록매체를 이용하는 것도 좋다. 또한, 기억부(15)는 과거실적데이타, 공사비적용단가, 보정계수 및 견적결과데이타를 서로 다른 기록매체에 분리하여 저장할 수도 있고, 하나의 기록매체에 함께 저장할 수 도 있다.The storage unit 15 may use a hard disk built into the computer 11, but here, a video information library, a floppy disk, a CD-ROM, a DVD, or the like connected to the computer 11 via a network is used. It is also possible to use a recording medium. In addition, the storage unit 15 may store the past performance data, the cost of construction cost, the correction coefficient and the estimation result data separately on different recording media, or may be stored together on one recording medium.

도 2는, 상기 도 1에 표시한 컴퓨터(11)의 블럭구성도이다. 컴퓨터(11)는, 다음에 상세하게 설명하는 소프트웨어에 기초하여 처리를 실행하는 CPU(201)와, 부팅프로그램등을 기억한 ROM(202)과, CPU(201)의 작업영역으로서 사용되는 RAM(203)과, 각종 입력조작을 행하기 위한 키보드(204) 및 마우스(205)와, 견적처리의 중간과정이나 처리결과를 표시하기 위한 표시화면(12)을 구비한 CRT나 액정 디스플레이등의 표시장치(206)와, 본 발명에 따른 자동 견적 처리를 실현하기 위한 견적소프트웨어(207)를 포함한 각종 어플리케이션 프로그램이나 데이타를 기억한 하드디스크(208)와, 도 1에 표시한 기억부(15)와 컴퓨터(11)을 접속하는 각종 드라이버, 네트워크어댑터등의 인터페이스부(209)와, 상기 각부를 접속하는 버스(210)를 적어도 구비하고 있다.FIG. 2 is a block diagram of the computer 11 shown in FIG. The computer 11 includes a CPU 201 that executes processing based on software described in detail below, a ROM 202 storing a booting program, and the like, and a RAM used as a work area of the CPU 201 ( 203, a keyboard 204 and a mouse 205 for performing various input operations, and a display device 12 such as a CRT or a liquid crystal display, which includes a display screen 12 for displaying an intermediate process or processing results of the quotation processing. 206, a hard disk 208 that stores various application programs or data including estimation software 207 for realizing automatic estimation processing according to the present invention, a storage unit 15 and a computer shown in FIG. Interface portions 209 such as various drivers and network adapters for connecting 11 and at least buses 210 for connecting the respective portions are provided.

그리고, 상기 견적처리관련 데이타를 저장하는 기억부(15)는 프로젝트실적DB(211)와, 공사비적용단가DB(212)와, 보정계수DB(213)와, 견적DB(214)로 구성된다.The storage unit 15 for storing the quotation processing related data includes a project performance DB 211, a construction cost application unit price 212, a correction coefficient DB 213, and a quotation DB 214.

상기 프로젝트실적DB(211)는 과거에 준공되었거나 현재 진행중인 건설 프로젝트의 실제 실적자료들을 축적하여 구축된 데이타베이스이다.The project performance DB 211 is a database built by accumulating actual performance data of a construction project that has been completed in the past or is currently in progress.

상기 공사비적용단가DB(212)는 자동견적시스템에서 견적할 프로젝트에 적용될 노무공량과 각종 단가의 산출을 목적으로 구성하는 데이타베이스로서, 견적자가 새로운 프로젝트에 적용될 노무공량과 각종 단가의 산출에 근거가 될 프로젝트들을 상기 프로젝트실적DB(211)로부터 적어도 하나 이상 선택하면, 선택된 과거프로젝트들의 노무공량과 각종 단가 실적 자료들의 가중평균치로부터 구성되는 것으로서, 이 데이타베이스 구성방법에 대해서는 차후에 설명한다.The construction cost application unit DB 212 is a database configured for the purpose of calculating the labor volume and various unit prices to be applied to the project to be estimated in the automatic estimation system, and the estimator is based on the calculation of labor volume and various unit prices to be applied to the new project. When at least one project to be selected is selected from the project performance DB 211, a weighted average value of labor volume and various unit price performance data of the selected past projects will be described later.

그리고, 상기 보정계수DB(213)는 프로젝트의 실적 자료를 새로운 프로젝트의 견적에 활용하기 위해 보정하는 작업에 이용되는 지수들을 축적해 놓은 데이타베이스로서, 용량, 시간, 지역, 및 생산성등 4종류의 보정에 관련된 지수들이 저장되어 있다.The correction coefficient DB 213 is a database that accumulates indices used to correct the project performance data for estimating a new project, and includes four types of capacity, time, region, and productivity. The indices related to the calibration are stored.

마지막으로, 상기 견적DB(214)는 상기 자동견적시스템(11)이 견적소프트웨어(207)에 의해 프로젝트실적DB(211), 공사비적용단가DB(212), 보정계수DB(213)의 데이타를 기반으로 생성된 견적 프로젝트 데이타를 저장하는 것으로, 견적프로세스에 의해 작업이 수행되며, 그 상세내역서를 작성하게 된다.Finally, the quotation DB 214 is based on the data of the project estimate DB 211, construction cost application unit cost DB 212, correction coefficient DB 213 by the automatic estimation system 11 estimate software 207 By storing the project data created by the project, the work is performed by the process of quotation, and the details are written.

이상의 도 1 및 도 2에 표시한 자동견적시스템(11)의 구성은, 어디까지나 일예를 표시한 것이고, 후술하는 실시예의 각 기능을 실현하는 것이 가능하다면, 어떠한 시스템구성이라도 가능하다.The configuration of the automatic estimation system 11 shown in Figs. 1 and 2 described above is merely an example, and any system configuration can be used as long as the functions of the embodiments described later can be realized.

상기, 견적소프트웨어(207)에 의해 수행되는 본 발명에 의한 사업비견적과정은 과거의 실적데이터중 프로젝트 특성을 고려하여 신뢰할 수 있는 단위를 설정하는 공사비적용단가 데이타베이스를 구축하며, 과거의 사업비를 현재의 사업비로 변환하고, 비용지수법을 이용한 시간과 단위용량의 보정을 행하여 보다 상세한 개략견적가격을 산정하는 것으로서, 견적자가 프로젝트 특성과 규모를 고려하여 여러 견적기법을 종합적으로 적용할 수 있도록 제공한다. 또한, 효율적인 프로젝트관리가 가능하도록 견적작업의 결과가 관리시스템에서 활용할 수 있도록 금액과 수량뿐만아니라 노무공량을 근거로 한 노무비자료를 산출하고, 이러한 견적작업을 근거로 하여 투찰가격을 시뮬레이션할 수 있는 의사결정프로세스를 제공하여 투찰금액 결정이 견적시스템에서 이루어질 수 있도록 함으로서, 견적작업의 신뢰도를 높히고 견적자의 판단을 시스템적으로 제공한다.The project cost estimation process according to the present invention performed by the estimation software 207 establishes a construction cost application cost database that sets a reliable unit in consideration of project characteristics among past performance data, and displays the current project cost. The cost estimate method is used to calculate the time and unit capacity, and then the estimated price estimate is more detailed. The estimator can apply various estimation techniques in consideration of the project characteristics and size. In addition, labor cost data based on labor volume as well as amount and quantity can be calculated so that the results of the estimation work can be utilized in the management system to enable efficient project management. By providing a decision making process, the determination of the amount of the investment can be made in the estimating system, thereby increasing the reliability of the estimating operation and providing the estimator's judgment systematically.

본 발명의 실적데이타를 이용한 건설프로젝트용 사업비 견적 방법을 견적작업프로세스와, 의사결정프로세스와, 공사비적용단가DB생성프로세스로 구분하여 설명한다.The project cost estimation method for a construction project using the performance data of the present invention will be described by dividing into a quotation work process, a decision making process, and a construction cost application unit cost DB generation process.

견적작업프로세스Quotation process

도 3은 본 발명의 사업비 견적방법에 있어서, 견적작업프로세스 과정을 보인 플로우챠트이다.3 is a flowchart showing the process of estimating work in the project cost estimating method of the present invention.

본 발명에 따른 견적시스템을 이용한 새로운 프로젝트에 대한 견적작업의 첫단계로서, 과거 수행되었던 프로젝트의 실적중 현재 계획하는 프로젝트와 유사한 프로젝트를 선택하여, 과거 프로젝트의 견적자료를 복사한다(S301,S302).As a first step of estimating a new project using the estimating system according to the present invention, a project similar to the currently planned project is selected from the results of the previous project, and the estimate data of the past project is copied (S301, S302). .

이는 상기 도 2의 구성에 있어서, 하드디스크(209)에 저장된 견적소프트웨어(207)가 기억부(15)의 프로젝트실적DB(211)에 저장된 다수의 프로젝트중 선택된 유사 프로젝트를 복사하는 기능을 수행한다.In the configuration of FIG. 2, the estimating software 207 stored in the hard disk 209 performs a function of copying a similar project selected from a plurality of projects stored in the project record DB 211 of the storage unit 15. .

도 5는 유사프로젝트복사단계의 화면표시상태에 대한 예를 보인 것으로서, 견적시스템 실행창(60)내에서, 메뉴의 프로젝트복사기능(도시생략)을 실행시키면, 실적프로젝트복사창(61)이 열리며, 상기 실적프로젝트복사창(61)에는 상부에 선택된 과거의 프로젝트(62)가 표시되고, 그 하부(63)에 선택된 프로젝트에 대한 실제 견적데이타가 나타나며, 이 선택된 유사 프로젝트의 견적데이타는 상기 도 2의 견적DB(214)에 새로이 계획되는 프로젝트의 견적기본데이타로 저장된다. 즉, 견적DB(214)로 복사된 프로젝트의 실적데이타는 신규 프로젝트의 견적작업에 대한 기본틀을 구성한다.5 shows an example of the screen display state of the similar project copying step. When the project copying function (not shown) of the menu is executed in the estimation system execution window 60, the performance project copying window 61 is opened. The past project 62 selected in the upper part of the historical project copy window 61 is displayed, and actual quotation data for the selected project is displayed in the lower part 63 of the previous project. 2 is stored in the quotation DB 214 as basic quotation data of the newly planned project. That is, the performance data of the project copied to the quotation DB 214 constitutes a basic framework for the estimation work of the new project.

프로젝트실적DB(211)로부터 선택복사되는 프로젝트는 새로 계획하는 프로젝트와 동일한 유형의 건설작업, 예를 들어 고로신설, 연주공장의 연주기 개조등 동일한 설비유형의 실적 리스트에서 견적할 프로젝트와 더 유사한 프로젝트범위를 갖는 것으로 선택된다.The project to be copied from the project performance DB 211 is a project range that is more similar to the project to be estimated from the list of performances of the same equipment type, such as construction work of the newly planned project, eg new construction of a blast furnace, modification of the instrument of a performance factory, etc. It is selected to have.

그리고, 상기 선택된 프로젝트의 실적 정보를 견적DB(214)로 복사할 때는, 공사비의 경우는 각 항목(COA)의 노무공량과 단가 정보를 제외한 모든 정보들이 복사되며, 설비비의 경우는 모든 정보가 복사된다.And, when copying the performance information of the selected project to the quotation DB (214), in the case of construction costs, all the information except the labor capacity and unit price information of each item (COA) is copied, in the case of equipment costs all information is copied do.

그 다음, 공사비적용단가DB(212)를 생성한다(S303). 즉, 신규 견적작업의 기본틀을 생성하는 유사 실적 프로젝트의 복사시, 제외되었던 노무공량 정보와 자재, 장비등의 각종 단가정보들이 공사비적용단가DB(212)의 생성을 통해 얻어지게 된다. 상기 공사비적용단가DB(212)는 견적자가 선택한 과거 프로젝트의 공사 실적 자료들로부터 각 공종(commodity)별 노무공량과 적용 단가의 가중 평균치를 계산하여 생성한다. 상기 공사비적용단가DB(212)의 생성작업은 다음에 더 상세하게 설명한다.Next, a construction cost application unit DB 212 is generated (S303). That is, various copies of labor volume information, materials, equipment, etc., which have been excluded at the time of copying the similar performance project generating the basic framework of the new estimation work, are obtained through the creation of the construction cost application unit price DB 212. The construction cost application unit price DB 212 is generated by calculating the weighted average value of the labor capacity and applied unit price for each commodity from the construction performance data of the past project selected by the estimator. The creation of the construction cost application unit price DB 212 will be described in more detail below.

상기와 같이 생성된 공사비적용단가DB(212)는 신규 프로젝트 견적에 이용되는데, 이때, 적용단가DB(212)에서 신규 프로젝트의 견적에 이용되는 정보는 견적 COA별(code of account:견적계정번호체계) 노무공량, 자재단가, 경비단가, 그리고 중기 단가등이다. 적용단가DB(212)의 생성시 노무단가는 제외되며, 이렇게 제공받은 정보는 신규 프로젝트 견적중 공사비 견적작업에 활용되며, 설비비 견적작업과는 무관하다. 본 발명에서 이용하는 견적계정번호체계는 해당 시설의 설비를 체게적으로 분류하는 설비분류체계(PBS:Physical Breakdown Structure)와 설비를 건설하는 공종을 상하 연관관계를 고려하여 분류한 공종분류체계(CBS : Commodity breakdown Structure)를 조합하여 사용하는 것으로, 견적의 종류에 따라 번호의 상세 정도를 달리하고 사업이 진행됨에 따라 견적계정번호의 숫자를 증가시킨다. 상기에서 설비분류체계는 일정 기준을 잡고, 사업의 업무범위에 따라서 선정하여 사용할 수 있다.The construction cost application unit price DB 212 generated as described above is used to estimate the new project, at this time, the information used in the estimate of the new project in the application unit price DB 212 is estimated by code of account (code of account: quote account number system) Labor cost, material unit cost, expense unit price, and mid-term unit price. The labor unit price is excluded when the application unit price DB 212 is generated, and the information provided in this way is used for estimating the construction cost of the new project estimate, and is not related to the equipment cost estimation work. Quotation account number system used in the present invention is classified into a physical breakdown structure (PBS: Physical Breakdown Structure) to classify the facilities of the facility and the work classification system in consideration of the vertical relationship between the construction work (CBS: Commodity breakdown structure) is used in combination, and the number of detail is changed according to the kind of quotation and the number of estimate account number is increased as the business progresses. In the above, the facility classification system can be selected and used according to the business scope of the project to set a certain standard.

상기와 같이, 공사비적용단가DB(212)가 생성되면, 유사 실적 프로젝트와 공사비 적용단가DB(212)로부터 전달된 정보들로 일단 견적과 관련된 모든 항목들의작성은 완료되어, 견적DB(214)에 담긴 과거 실적 프로젝트 자료들을 신규 견적하는 프로젝트의 요구사항이나 특성(플랜트의 용량 혹은 공사 수행예정시기나 지역특성등)에 맞도록 일괄적인 보정이 이루어진다(S304). 이 보정처리는 공사비와 설비비 모두에 적용되며, 적용되는 보정의 종류는 용량, 시간, 지역, 생산성등으로 구분할 수 있다. 이러한 보정은 적절한 보정계수의 적용으로 개략견적결과에 대한 오차를 줄이기 위한 것이다. 즉, 보정전의 견적자료의 상태는 과거 프로젝트의 실적정보들 중에 일부를 선별하고, 또는 조합하여 견적DB에 옮겨놓은 것에 불과하며, 실제 견적하려는 신규 프로젝트의 조건들이 반영되지 않은 상태이다. 따라서, 본 보정단계는 조합되어진 실적 자료에 보정을 적용하여, 새로이 계획되는 신규 프로젝트의 특성과 조건을 반영시키는 단계이다.As described above, when the construction cost application unit price DB 212 is generated, with the information transmitted from the similar performance project and construction cost application unit price DB 212 once the creation of all items related to the quotation is completed, the estimate DB (214) The collective correction is made according to the requirements or characteristics of the project (new plant capacity or when the project is scheduled to be performed or regional characteristics) for newly estimating the project data contained in the past (S304). This correction process is applied to both construction and equipment costs, and the types of corrections can be divided into capacity, time, region, and productivity. This correction is to reduce the error of the rough estimate result by applying the appropriate correction factor. In other words, the state of the estimate data before correction is only a part of the performance information of the past project is selected or combined and transferred to the estimate DB, and the conditions of the new project to be actually quoted are not reflected. Therefore, this correction step is to apply the correction to the combined performance data to reflect the characteristics and conditions of the newly planned new project.

상기 보정직전의 견적DB(214)에 저장된 견적정보의 상태를 보면, 각 COA별 물량은 유사 실적 프로젝트를 그대로 복사한 물량이며, 각 항목별 단가는 공사비적용 DB(212)를 구성하는 하나 이상의 과거 공사실적 자료들을 견적시점의 현재가로 전환하여 가중 평균값을 산출하였고, 상기 공사비적용DB(212)는 국내에서 수행되었던 공사들의 실적정보로만 구성한 것이다.Looking at the state of the quotation information stored in the estimate DB (214) immediately before the correction, the quantity of each COA is a quantity of a copy of the similar performance project as it is, and the unit price of each item is one or more past constituting the construction cost application DB (212) The weighted average value was calculated by converting the construction performance data into the current price at the time of estimation, and the construction cost application DB 212 is composed only of the performance information of the constructions performed in Korea.

앞서 서술한 바와 같이, 이때 이루어지는 보정은 1)용량보정, 2)시간보정, 3)지역보정, 4)생산성보정이며, 각 사업비 비목별 조정적용여부와 범위는 다음의 표 1과 같다.As described above, the corrections made at this time are 1) capacity correction, 2) time correction, 3) regional correction, and 4) productivity correction, and the application and scope of adjustment for each project item is shown in Table 1 below.

용량보정Capacity correction 시간보정Time compensation 지역보정Regional correction 생산성보정Productivity correction 공사비Construction cost 재료비material cost 수량에 적용Apply to quantity 단가에 적용Apply to unit price 단가에 적용Apply to unit price 적용 안함Do not apply 노무비labor cost 수량에 적용Apply to quantity 단가에 적용Apply to unit price 적용안함Not applicable 노무공량에 적용Applied to labor capacity 자재비Material cost 수량에 적용Apply to quantity 단가에 적용Apply to unit price 단가에 적용Apply to unit price 적용안함Not applicable 경비security 수량에 적용Apply to quantity 단가에 적용Apply to unit price 단가에 적용Apply to unit price 적용안함Not applicable 설비비Equipment cost 설비비Equipment cost 기기 단가 및 환산설치중량에 적용Applied to unit price and converted installation weight 단가에 적용Apply to unit price 단가에 적용Apply to unit price 적용안함Not applicable

보정은 국내 공사와 해외 공사시 그 적용에 차이가 있을 수 있다. 국내 공사의 견적은 생산성과 지역의 보정을 제외한 시간과 용량에 대한 보정만이 이루어지면 되지만, 해외 공사 견적은 기본틀이 되는 과거 실적이 국내 실적이므로, 용량, 시간, 지역, 및 생산성의 보정이 모두 이루어져야 한다.The correction may be different in domestic and overseas construction. Estimates for domestic construction only need to be corrected for time and capacity, excluding productivity and regional corrections.However, overseas construction estimates are based on the past performance, which is the basis for domestic construction. All must be done.

그리고, 보정을 위해 구축된 보정계수DB(213)는 지속적인 보정데이타의 갱신작업이 요구된다. 예를 들어, 시간 보정에 사용되는 물가지수의 경우, 각 국의 생산자물가지수는 매년 발표되는 값들로 갱신되어야 하며, 지역 보정을 위한 보정계수 또한 필요시 새로운 국가의 추가등이 필요하다. 이러한 보정계수DB(213)의 갱신은 보정을 통한 견적작업결과의 정확도를 높힐 수 있는 중요한 사항이 된다.The correction coefficient DB 213 constructed for correction requires continuous updating of correction data. For example, in the case of the price index used for time correction, the producer price index for each country needs to be updated with the annually released values, and the correction factor for regional correction also requires the addition of a new country. The update of the correction coefficient DB (213) is an important matter that can increase the accuracy of the estimation work result through the correction.

상기 보정단계(S304)를 1)용량보정, 2)시간보정, 3)지역보정, 4)생산성보정으로 구분하여 구체적으로 설명한다.The correction step S304 will be described in detail by dividing it into 1) capacity correction, 2) time correction, 3) regional correction, and 4) productivity correction.

1)용량보정1) Capacity correction

용량보정은 기기의 규모 혹은 사양의 변화에 따른 비용의 증감관계를 이용한 것으로, 새로이 도입하는 기기의 사양이나 플랜트의 규모에 따른 구입비와 공사비를 견적할 때 사용된다. 다시 말해서, 동일한 종류의 기기나 산업용 시설물이 규모(혹은 용량)만을 달리할 때 그 비용에 대한 개략견적을 수행하는 경우에 사용된다. 일반적으로 알려진 규모/비용관계(Power-factor model)에 근거하여, 비용-용량 지수를 계산하고, 비용-용량지수를 이용하여 보정된 비용을 산출한다. 비용과 용량간의 관계를 적용시 비용과 용량간의 관계를 적용시킬 수 있는 설비의 규모 또는 용량의 범위가 미리 정의되어야 하고, 그 범위내에서 정의가 이루어져야 한다. 비용과 용량간의 관계를 분석할 만한 충분한 데이터가 축적되지 않은 경우 일반적으로, 0.6이나 0.7이 비용-용량지수로서 사용된다. 본 발명에서는 축적된 실적자료가 충분치 않은 경우를 위해 비용-용량지수의 초기치로서 일괄적으로, 0.6의 비용-용량지수를 적용하게 한다. 그러나, 이는 확정된 값이 아니며, 견적자의 경험에 의한 판단으로부터 변경할 수 있다.Capacity correction is used to estimate the purchase and construction costs according to the specifications of the newly introduced equipment or the size of the plant. In other words, it is used when the same kind of equipment or industrial facility performs a rough estimate of the cost when it differs only in size (or capacity). Based on a generally known power-factor model, the cost-capacity index is calculated and the cost-capacity index is used to calculate the corrected cost. When applying the relationship between cost and capacity, the size or range of capacity to which the relationship between cost and capacity can be applied should be defined in advance, and within that range. Typically, 0.6 or 0.7 is used as the cost-capacity index if there is not enough data available to analyze the relationship between cost and capacity. In the present invention, for the case where the accumulated performance data is not sufficient, the cost-capacity index of 0.6 is collectively applied as the initial value of the cost-capacity index. However, this is not a fixed value and can be changed from the judgment by the estimator's experience.

이러한 용량보정의 이론적인 배경은 견적분야에서 일반적으로 알려져 있는 사항이므로, 구체적인 설명은 생략한다.Since the theoretical background of the capacity correction is generally known in the estimation field, a detailed description thereof will be omitted.

도 6a는 용량에 대한 보정의 화면표시상태를 보인 것으로, 선택된 과거 실적 프로젝트의 용량과 현재 견적할 프로젝트의 용량차이를 반영하기 위한 것으로, 0.6의 비용-용량지수를 도입하여 용량보정을 실행한다. 상기 화면에 도시된 바와 같이, 보정창에는 적용여부를 선택하는 선택버튼이 있어, 견적자가 적용여부를 선택할 수 있다.FIG. 6A shows a screen display state of capacity correction, which reflects the difference between the capacity of the selected past performance project and the capacity of the project to be estimated now. The capacity correction is performed by introducing a cost-capacity index of 0.6. As shown on the screen, the correction window has a selection button for selecting whether to apply, the estimator can select whether to apply.

2) 지역보정2) Regional correction

지역보정은 서로 지리적으로 위치가 다른 두 지역간의 상대적인 생산성, 임금, 자재비, 장비비, 운송비, 세금, 공사 관리비 등의 차이로 인해 발생하는 프로젝트 비용의 차이를 보정하는 것으로, 지역보정을 위해 일반적으로 알려진 지역 보정계수를 사용한다. 상기 지역보정계수는 지역A에서 프로젝트를 수행하는데 소용되는 비용을 공사가 수행되는 지역을 제외한 다른 모든 조건이 동일한 프로젝트를 수행한다는 가정 하에서 지역B에서 수행하는데 소용되는 비용으로 전환시키는 것이다. 이러한 지역보정계수는 건설분야에서 일반적으로 잘 알려져 있는 사항으로서, 본 시스템에서는 일단 과거 실적자료를 국내공사 자료들로만 구성한 후, 국내 지역간에는 지역차이가 크게 존재하지 않으므로, 해외 프로젝트의 견적시에만 적용되도록 하였다. 그러나, 이는 예를 든 것으로, 실적자료의 변경시 달라질 수 있다.Regional correction compensates for differences in project costs incurred due to differences in relative productivity, wages, materials, equipment, transportation, taxes, and construction management costs between two geographically displaced regions. Use local correction factors. The area correction factor converts the cost of performing the project in the area A into the cost of performing the area B under the assumption that all the conditions except the area in which the construction is carried out carry out the same project. This area correction factor is generally well known in the construction field. In this system, once the historical performance data is composed only of domestic construction data, there is no large regional difference between domestic regions, so it is applied only when estimating overseas projects. It was. However, this is an example and may change when the performance data changes.

그런데, 국가간 건설 프로젝트 수행 비용의 차이를 찾기는 쉽지 않으며, 본 실시예에서는 1997년 McConville, J. G가 발표한 연구논문("Cost comparison of pacific rim countries", AACE International Transactions, 1997)에 게재된 한국을 포함한 12개국의 지역 보정계수를 적용하였다. 그러나, 이는 고정되는 것이 아니며 새로운 연구가 이루어지면 더 오차를 줄일 수 있는 값으로 변경된다.However, it is not easy to find the difference in the cost of performing construction projects between countries, and in this example, it is published in a 1997 study published by McConville, J. G ("Cost comparison of pacific rim countries", AACE International Transactions, 1997). The regional correction factors of 12 countries including Korea were applied. However, this is not fixed and changes to values that can further reduce errors as new research is done.

자재비와 설비비를 포함한 총 사업비의 지역보정은 크게 일괄보정과 세부보정으로 나누어진다. 해외 공사에 사용될 기기 구입의 경우, 그 기기의 원 생산자의 지역에 따라 해당 지역 공급의 경우, 국내 생산후 운송의 경우, 그리고 제3지역 생산후 운송의 경우등과 같은 다양한 경우가 있을 수 있으며, 이에 따라 세부보정이 이루어진다. 이때, 운송비, 수입관세, 중개료, 환율등이 고려된다. 지역보정에 필요한 세부 사항은 견적자가 직접 반영시킨다. 본 시스템에서 이런 지역보정을 위한 지역보정계수도 새로운 국가의 추가 혹은 기존 보정계수값의 수정이 가능하다.Regional corrections of total project costs, including material and equipment costs, are largely divided into batch corrections and detailed corrections. In the case of purchase of equipment to be used for overseas construction, there may be various cases, such as supply of the region, domestic post-production transport, and third region post-production transport, depending on the region of the original producer of the device. This makes detailed corrections. Transportation costs, import duties, brokerage fees, exchange rates, etc. are considered. Details necessary for local correction shall be directly reflected by the estimator. In this system, the regional correction coefficients for these local corrections can also be added to new countries or modification of the existing correction coefficient values.

도 6b는 이상 설명한 지역보정 화면에 대한 표시예를 보인 것으로, 본 실시예에서는 해외공사의 경우만 적용하도록 국가별 보정계수를 구비하고, 견적자가 신규프로젝트의 공사국가를 선택하면 해당 국가의 적용지수가 하단에 나타나며, 그후 적용버튼을 선택함으로서, 상기 선택된 보정계수에 의한 지역보정을 실행하도록 한다.FIG. 6B shows a display example of the region correction screen described above. In the present embodiment, the correction factor for each country is applied to apply only for overseas construction, and when the estimator selects the construction country of the new project, the applicable index of the corresponding country Appears at the bottom, and then, by selecting the apply button, the region correction by the selected correction coefficient is executed.

3)시간보정3) Time correction

건설 프로젝트 견적의 시간보정은 일반적으로 비용지수 혹은 물가지수가 사용되는데, 비용지수는 시간의 흐름에 따른 물가의 변화와 차이를 표현한 값으로서, 보통 A 시점에서의 어떤 항목의 비용을 다른 시점 B에서의 비용으로 전환하고자 할때 사용되는 것이다. 이때, 두 시간대에서 해당 항목의 질과 양은 변하지 않고 동일하다고 가정되며, 비용지수는 시간에 따른 복합 비용의 변화를 나타낸다.The time correction of construction project estimates is usually a cost index or a price index. The cost index is a representation of the change and difference in prices over time. It is used to convert to the cost of. At this time, it is assumed that the quality and quantity of the items are the same in both time zones and the same, and the cost index indicates the change in complex costs over time.

상기 비용지수는 여러 기관에서 정기적으로 발표되는 자료, 대표적인 예로서 ENR(Engineering News-Record), CCI(Construction Cost Index)등의 해외 자료와, 대한건설협회의 건설공사비지수, 한국건설산업연구원의 건설물가지수등의 국내자료중에서, 견적결과에 대한 오차를 줄일 수 있는 자료를 선택하여 이용한다.The cost index is published regularly by various organizations, such as overseas news such as Engineering News-Record (ENR), Construction Cost Index (CCI), the construction cost index of the Korea Construction Association, and the construction of the Korea Institute of Construction Industry. From the domestic data such as price index, select and use the data to reduce the error on the estimation result.

본 시스템에서는 시간보정작업시, 생산자 물가지수를 적용시키는 것을 기본으로 하고, 좀더 세분화된 물가지수가 존재하는 경우, 이를 선별하여 적용할 수 있도록 한다. 도 6c는 년도별 생산자 물가지수를 이용하여 일괄적인 시간보정을 행하는 화면을 나타낸 것이고, 도 6d는 대한건설협회가 발표한 건설업 임금실태조사 결과를 바탕으로 노무비에 대한 시간보정을 행하는 화면을 도시한 것이다.In this system, the producer price index is applied during time correction, and if a more detailed price index exists, it can be selected and applied. FIG. 6C illustrates a screen for collectively performing time correction using the producer price index for each year, and FIG. 6D illustrates a screen for performing time correction for labor costs based on the results of a survey on wages in the construction industry announced by the Korea Construction Association. will be.

상기에서, 생산자물가지수나 건설공사비 지수를 이용한 시간보정작업시, 오차의 범위를 줄이기 위해 일정 시간(예를 들어, 4,5년)단위로 지수데이타를 갱신시켜야 한다.In the above, when time correction work using the producer price index or construction cost index, the index data should be updated by a certain time (for example, 4, 5 years) in order to reduce the error range.

본 발명에서는 각종 지수값들을 보정계수DB(213)에 입력하여 두고, 차후에 보정계수값의 추가 및 갱신이 가능하도록 한다.In the present invention, various index values are input to the correction coefficient DB 213, so that correction coefficient values can be added and updated later.

그리고, 신규 프로젝트의 공사 시점으로의 시간보정시 과거 수년간의 공사비 지수값들의 변화 추세를 분석하여 앞으로의 변화추세를 예측하는 시계열분석(time-series analysis)기법을 채용한다.In addition, time-series analysis is employed to predict the trend of future changes by analyzing the trend of changes in construction cost index values over the past several years.

3) 생산성 보정3) Productivity correction

각 국가 및 지역별로 존재하는 건설 노동 생산성의 차이는 프로젝트에 영향을 미치는 중요한 요소중의 하나로서, 견적시 고려되어야 한다. 본 발명의 생산성 보정에서는 노무비, 구체적으로 말하면 노무공량에 적용하는 것을 기본으로 하지만, 이는 변경 및 수정이 가능하다. 물론, 앞서 설명한 시간 및 지역보정계수에 노동생산성의 지역 및 시간별 변화나 차이가 일부 반영되어 있지만, 견적자의 판단에 따라 지역별 노동생산성의 보정을 추가로 적용할 수 있도록 선택기능을 부여한다. 생산상 보정계수는 1997년 발표된 Kenneth K. Humphreys의 자료("Sources of International Cost Data", Keynot Address Presented at the NORDNET '97 Confererence, "Quality in Project Management", Reykjavik, Iceland, 11 September 1997)를 이용한다. 이는 새롭게 연구된 자료가 발표된다면 변경될 것이다.Differences in construction labor productivity in each country and region are one of the important factors affecting the project and should be considered in the estimates. In the productivity correction of the present invention, it is basically applied to labor costs, specifically, labor capacity, but this can be changed and modified. Of course, the above-mentioned time and regional correction coefficients partially reflect regional and hourly changes or differences in labor productivity, but at the discretion of the estimator, the selection function is provided so that additional correction of regional labor productivity can be applied. The production correction factor is based on data from Kenneth K. Humphreys published in 1997 ("Sources of International Cost Data", Keynot Address Presented at the NORDNET '97 Confererence, "Quality in Project Management", Reykjavik, Iceland, 11 September 1997). I use it. This will change if new research data are published.

도 6e는 상술한 생산성 보정단계의 화면표시예를 보인 것으로서, 선택가능한 국가별 생산성 보정지수리스트와, 선택된 적용지수 표시부와, 적용여부를 선택하는버튼이 포함된 생산성보정창이 디스플레이된다.6E illustrates a screen display example of the above-described productivity correction step, in which a productivity correction window including a selectable country-specific productivity correction index list, a selected application index display unit, and a button for selecting whether to apply is displayed.

도 6f는 상술한 용량, 시간, 지역, 생상성등의 일괄보정을 실행시킨 후의 보정결과를 보이는 화면으로서, 보정후의 견적금액을 보여주며, 견적자가 검토후 견적금액이 적당치않다고 생각될 때, 즉, 보정이 잘못이루어졌을때 일괄보정작업 이전의 상태로 되돌아가 다시 보정작업을 할 수 있는 옵션을 제공한다. 도 5에 보인 보정전의 상태와 비교할 때, 총공량이 견적할 프로젝트에 맞춰 변경되고, 총사업비도 변경되었음을 알 수 있다.Fig. 6F is a screen showing the result of the correction after executing the collective correction of the above-mentioned capacity, time, region, and productivity, and shows the estimated amount after the correction, when the estimator thinks that the estimated amount is not appropriate after the review, that is, When the calibration is made incorrectly, it provides the option to go back to the state before the batch calibration. Compared with the state before the correction shown in Figure 5, it can be seen that the total volume is changed according to the project to be estimated, and the total project cost is also changed.

상술한 바와 같이, 일괄보정이 완료되면, 다음 단계로 견적데이타의 각 설비분할체계(PBS)에 따라 교체, 추가 및 삭제작업이 실행된다(S305).As described above, when the batch correction is completed, the replacement, addition and deletion operations are executed in accordance with each equipment division system (PBS) of the estimate data to the next step (S305).

일괄 보정이 완료된 후, 견적데이타의 상태와 신규 프로젝트의 범위(scope)에 차이가 존재할 경우, 본 단계를 통해 현재 견적데이타베이스의 자료에서 해당 PBS의 교체, 추가 및 삭제를 통해 새로운 프로젝트의 범위로 변환시킨다. 즉, 견적자의 판단에 의해 신규프로젝트와 근사해지도록 견적데이타베이스를 구성하는 PBS를 수정하거나, 다른 실적 프로젝트의 PBS와 교체할 수 있다. 실적데이타베이스로부터 가져오는 PBS가 새로운 견적 프로젝트의 PBS로 추가되어질 때는, 앞서 일괄보정에 적용되었던 모든 보정지수들이 동일하게 적용되어 보정된다(S306). PBS 교체는 견적하고자하는 프로젝트에 존재하는 PBS를 과거 프로젝트 실적으로부터 선택되어진 PBS로 교체되는 것으로서, 이때 선택된 견적프로젝트의 PBS가 삭제되어 새로운 PBS로 대체된다.After the batch calibration is completed, if there is a difference in the status of the quotation database and the scope of the new project, this step is used to change the scope of the new project by replacing, adding, and deleting the corresponding PBS from the current quotation database. Convert That is, the PBS constituting the estimating database may be modified to be approximated with the new project at the estimate of the estimator, or may be replaced with the PBS of another performance project. When the PBS imported from the performance database is added to the PBS of the new estimating project, all correction indices previously applied to the batch correction are equally applied (S306). The PBS replacement is to replace the PBS existing in the project to be quoted with the PBS selected from past project results. At this time, the PBS of the selected quotation project is deleted and replaced with a new PBS.

이상, 복사한 과거 프로젝트의 실적에 대략적인 보정작업이 모두 완료되면,이제부터 총사업비를 구성하는 실제 설비비의 견적 및 공사비의 견적, 간접비의 견적작업에 들어간다(S307, S308, S309).As described above, when all the rough corrections to the results of the past project have been completed, the process of estimating the actual equipment cost, the construction cost, and the overhead cost constituting the total project cost is now started (S307, S308, S309).

먼저, 설비비 견적은 개별상세견적으로서 견적자가 개별 기기들을 하나하나 견적해 나가도록 제공한다. 즉 본 시스템은 실적 프로젝트의 설비비 실적자료에 존재하는 기기의 정보들을 참조할 수 있는 자료를 여러가지 기준별로 분류 조회하거나, 분석할 수 있는 기능을 제공한다. 즉, 상기 초기단계(S301)부터 본 설비비견적단계(S307) 이전까지의 작업상태를 담은 견적DB(214)의 데이타를 기초로 설비비 견적이 수행되는데, 이때 견적은 상세견적과 개략견적 두가지 방식으로 실행될 수 있다. 설비비의 상세견적은 기기번호(Equipment Number)단위로 이루어지며, 견적자의 판단 및 필요에 따라서 기기의 사양을 교체 및 수정할 수있다. 그리고, 견적자가 용량 및 시간보정을 감안하여 실적 프로젝트의 설비비 정보를 분석하고 그 결과를 참고하여 설비비의 상세 견적을 수행할 수 있는 기능을 제공한다. 또한, 필요시에 변경된 항목에 대한 상세 보정작업을 수행할 수 있도록 한다. 그리고, 이러한 기기별 상세 견적에 의한 COA 변경이 필요한 경우 해당 COA를 변경수정할 수 있도록 한다.First, equipment cost estimates provide estimates for individual devices. In other words, this system provides the function to classify or analyze the data that can refer to the information of equipment existing in the facility cost performance data of the performance project by various criteria. That is, the equipment cost estimation is performed based on the data of the quotation DB 214 containing the operation state from the initial stage (S301) to the previous equipment non-estimate stage (S307), wherein the estimation is carried out in two ways: detailed estimate and rough estimate. Can be executed. Detailed estimates of equipment costs are made in units of Equipment Number, and the specifications of the equipment can be changed and modified as required by the estimator. In addition, the estimator provides the function to analyze the equipment cost information of the performance project in consideration of the capacity and time correction and refer to the result to perform detailed estimation of the equipment cost. In addition, it is possible to perform detailed corrections to the changed items when necessary. In addition, when a COA change is required based on the detailed quotation for each device, the COA can be modified.

도 7은 본 시스템에서 제공되는 설비비 견적화면을 보인 것으로서, 설비비 견적창 상부에 설비비견적을 위한 다수의 기능버튼을 보이고, 화면 좌측부에 견적DB(214)에 저장된 설비비의 목록을 보이고, 화면 우측 상부에는 과거의 실적정보가 나타나며, 화면 우측 하부에는 현재 견적하는 프로젝트에서의 설비정보표시 및 수정기능을 동시에 제공한다. 상기 도 7의 설비비견적화면을 통해, 견적자는 설비비를 기기별로 보정 수정하여 반영시킬 수 있다.7 shows the equipment cost estimation screen provided by the system, shows a plurality of function buttons for equipment cost estimation on the equipment cost estimation window, a list of equipment costs stored in the quotation DB 214 on the left side of the screen, and the upper right side of the screen. In the past, historical performance information is displayed, and at the bottom right of the screen, the facility information display and correction function of the project currently estimated are provided at the same time. Through the equipment cost estimate screen of FIG. 7, the estimator may reflect and correct the equipment cost by device.

그 다음, 공사비견적은 설비와 관계없이 공사에만 관련된 항목에 대한 것으로, 주로 벌크(bulk)성 자재에 대한 세부 견적작업을 말한다. 본 시스템에서 공사비 견적은 공사비 개별 항목의 수정 및 추가를 통해 상세 견적이 가능하도록 하며, 또한 프로젝트실적DB(211)로부터 복사한 실적자료에 다양한 종류의 보정을 통해 현재 견적하는 프로젝트의 특성을 반영하여 견적정보로 전환시키게 한다. 개별 견적자료를 보정하는 경우 보정계수의 변경을 통한 공사비 견적은 용량, 시간, 지역, 생산성 등 4가지의 보정 작업 모두가 가능하며, 용량 보정의 경우는 동일한 용량 보정 지수값을 가지는 모든 항목들에 대해 일괄적으로 보정작업이 이루어지도록 한다.Next, the construction cost estimate is for items related only to the construction regardless of the equipment, and mainly refers to the detailed estimation of bulk materials. In this system, the construction cost estimation can be made in detail by modifying and adding the construction cost individual items, and also reflects the characteristics of the project currently estimated through various kinds of corrections in the performance data copied from the project performance DB 211. Have them convert to quote information. When revising individual estimate data, the construction cost estimate by changing the correction factor is possible for all four types of corrections, such as capacity, time, area, and productivity.In the case of capacity correction, all items with the same capacity correction index value are used. The calibration work is done in a batch.

도 8는 상술한 공사비 견적화면의 일실시예를 보인 것으로서, 좌측에 공사목록을 보이고, 우측에는 선택된 공사에 대한 정보, 수량 및 공사 비용등을 보인다.8 shows an embodiment of the above-described construction cost estimation screen, showing a construction list on the left, information, quantity and construction costs for the selected construction on the right.

간접비는 설비비와 공사비에 관련되지 않은 금융비용등을 나타내는 것으로서, 앞서 실행된 유사프로젝트의 복사와 PBS의 교체, 추가를 통해 그리고 각종 보정작업을 통해 새로운 프로젝트의 간접비는 이미 견적DB(214)에 담겨지게 된다. 따라서, 상기 간접비견적단계(S309)에서는 상기 견적DB(214)의 간접비를 검토하여 조정한다.Overhead costs represent financial costs that are not related to equipment costs and construction costs.The overhead costs of new projects are already included in the quotation DB (214) through the copying of similar projects, replacement and addition of PBS, and various corrections. You lose. Therefore, in the indirect non-estimate step S309, the indirect cost of the quotation DB 214 is reviewed and adjusted.

마지막으로, 완료된 견적결과를 검토하여, 일부 항목을 조정한다(S310). 도 9은 본 시스템에서 보이는 견적결과 검토화면으로서, 상부에는 견적한 신규프로젝트에 대한 서지정보 및 견적된 총공량과 총사업비가 나타나고, 화면좌측에 사업내역이 나오며, 화면우측으로 선택된 부분에 대한 상세한 견적결과를 보인다. 견적자는 상기 도 9와 같은 화면을 보고 최종 검토를 수행하고, 일부 항목의 금액에 대한 조정도 할 수 있다.Finally, the completed estimate result is reviewed and some items are adjusted (S310). 9 is a screen for reviewing the estimation result shown in this system, in which the bibliographic information and the estimated total volume and total project cost for the new project estimated are shown, the project details appear on the left side of the screen, and the detailed quotation for the selected portion on the right side of the screen. Shows the result. The estimator may perform a final review by viewing the screen as shown in FIG. 9 and may adjust the amount of some items.

의사결정프로세스Decision Making Process

다음으로 총 견적금액에 대한 최종 조정을 행하는 의사결정프로세스에 대해서 설명한다.Next, a decision process for final adjustment of the total estimated amount will be described.

견적금액의 조정(simulation)이란 상술한 설비비, 공사비, 간접비의 견적작업이 완료된 후에 총 견적금액을 조정하는 작업으로서, 본 시스템에서는 보정계수의 변경을 이루어지도록 구현한다.Simulation of the estimated amount is an operation of adjusting the total estimated amount after the above-mentioned estimation of the facility cost, construction cost, and overhead cost is completed, and the system implements a change of the correction factor.

따라서, 견적자는 설비비와 공사비 항목에 적용되었던 보정계수들의 종류와 값을 다양하게 변경 적용하면서, 총 견적금액의 변화를 조정할 수 있다. 그리고, 간접비 조정은 기 적용 비율을 변경 적용하여 수행된다.Therefore, the estimator can adjust the change in the total quotation amount while variously applying and applying the types and values of the correction coefficients applied to the equipment cost and the construction cost item. In addition, the overhead adjustment is performed by changing the previously applied ratio.

도 10은 설비비에 대한 견적결과 시뮬레이션 화면을 보인 것으로서, 설비비 시뮬레이션 화면은 상부에 견적 프로젝트에 대한 정보가 표시되고, 그 하부의 좌측에는 공종별 금액이, 우측에는 선택된 공종에 대한 세부 기기별 사양이 나타난다. 그리고 하단라인에는 시뮬레이션을 위해 보정지수종류와, 원래의 보정지수값과, 새로 조정할 보정지수값이 표시된다. 견적자는 상기 새로 조정할 보정지수값을 기입한 후 적용시킴으로서, 설비비 견적이 조정할 수 있다.10 is a simulation result simulation screen for the equipment cost, the equipment cost simulation screen, the information on the estimation project is displayed on the upper part, the amount of each model is shown on the left side of the lower part, and the detailed device-specific specifications for the selected model is shown on the right side. . The bottom line shows the correction index type, the original correction index value, and the newly adjusted correction index value for the simulation. The estimator can adjust the equipment cost estimate by applying the new correction index value and then applying it.

도 11은 공사비에 대한 견적결과 시뮬레이션 화면을 보인 것으로서, 마찬가지로 상부에는 건설프로젝트의 정보가 나타나며, 그 하부 좌측에는 공종별 금액이,우측에는 선택된 공종에 대한 PBS단위의 상세정보가 나타난다. 도한 하부라인에 보정지수종류 및 이전 보정지수값, 새로 적용할 보정지수값을 표시하고 기입할 수 있도록 하여 보정지수의 조정으로 공사비를 조정해볼 수 있다.FIG. 11 shows a simulation result simulation screen for the construction cost. Similarly, the construction project information is displayed at the upper part, the amount of each type is shown at the lower left side, and detailed information of the PBS unit is selected at the right side. In addition, it is possible to adjust the construction cost by adjusting the correction index by displaying and entering the correction index type, the previous correction index value, and the newly applied correction index value in the lower line.

도 12는 간접비에 대한 견적결과를 시뮬레이션하는 화면을 보인 것으로서, 도시된 바와 같이, 간접비별 금액이 표시되고, 현 적용비율과 수정적용비율에 대한 표시가 있어, 적용비율을 조정함으로서, 간접비를 시뮬레이션해볼 수 있게 된다.12 is a screen for simulating the result of the estimation of the overhead costs, as shown, the amount of each overhead costs are displayed, there is a display for the current application rate and the correction application rate, by adjusting the application rate, by simulating the overhead costs You can try.

도 13은 시뮬레이션 작업후의 견적결과를 보인 것으로서, 도 6f에 보인 일괄보정후의 견적데이타에서 다소 조정되었음을 볼 수 있다.FIG. 13 shows the estimation result after the simulation operation, and it can be seen that the estimate data after the collective correction shown in FIG. 6F has been adjusted somewhat.

이상과 같은 견적 결과에 대한 조정과 검토가 완료되면, 완료된 프로젝트의 견적결과를 출력할 수 있도록 한다.When the adjustment and review of the above quotation results are completed, the quotation results of the completed project can be output.

공사비적용단가DB생성프로세스Construction Cost Application Unit DB Creation Process

앞서 견적작업프로세스에서 설명한 공사비적용단가DB생성 및 적용과정에 대하여 도 4의 플로우챠트를 참조하여 상세하게 설명한다.The construction cost application cost DB generation and application process described in the estimation work process will be described in detail with reference to the flowchart of FIG. 4.

프로젝트실적DB(211)에 기억된 다수의 과거 프로젝트 실적 중 하나 이상의 선택한다(S401).At least one of a plurality of past project records stored in the project record DB 211 is selected (S401).

그러면, 선택된 실적 프로젝트의 세부항목별로 조합되어(S402), 각종 단가데이타베이스와, 노무공량 데이타베이스를 형성하고, 해당 지역의 노무단가를 입력하여 노무단가데이타베이스가 만들어진다(S403~S405).Then, it is combined by the detailed items of the selected performance project (S402), various unit price databases and labor capacity database are formed, and labor unit prices are inputted to generate labor unit price databases (S403 to S405).

상기에서 노무공량데이타베이스의 데이타에 기초하여 항목별 가중 평균노무량이 계산되고(S406), 노무단가데이타베이스의 데이타에 기초하여 공종별로 가중평균노무단가가 계산된다(S407). 그 다음, 상기 계산된 노무량과 단가를 곱하여 항목별 평균노무단가를 계산한다(S408, S409).The weighted average labor amount for each item is calculated based on the data of the labor capacity database (S406), and the weighted average labor price per work is calculated based on the data of the labor price database (S407). Then, the average labor price for each item is calculated by multiplying the calculated labor amount by the unit price (S408, S409).

상기 생성된 각종 단가 데이타와, 항목별 평균노무단가가 함께 공사비적용단가데이타베스를 생성한다(S410).The various unit price data generated above and the average labor price per item are generated together to generate a unit cost data unit price (S410).

이상에서 설명한 바와 같이, 본 발명은 건설 프로젝트의 실적 자료를 체계적으로 구축할 수 있는 데이터베이스를 제공하고, 개략견적 작업에서의 신뢰도를 제고시키고, 다양한 견적기법을 시스템화하여 견적자가 견적작업에 소요되는 시간을 단축시키고, 견적작업의 데이터를 중앙집중적으로 관리할 수 있도록 하는 효과가 있다.As described above, the present invention provides a database that can systematically build the performance data of the construction project, improve the reliability in the rough estimate work, and systemize various estimating techniques to estimate the time required for estimating work It is effective to shorten the time and to centrally manage the data of the estimation work.

또한, 본 발명은 견적결과를 시물레이션하는 의사결정프로세스를 제공하여, 의사 결정 시간을 단축시키고, 투찰가격 결정을 한번에 할 수 있도록함으로서, 견적업무의 일관성 유지와 투찰가의 정확성을 제고시킬 수 있는 효과가 있다.In addition, the present invention provides a decision making process that simulates the results of quotations, thereby reducing the decision time and making the bidding price at once, thereby maintaining the consistency of the estimation work and improving the accuracy of the bidders. have.

더하여, 건설 프로젝트의 견적결과를 프로젝트 관리의 기초데이터로 활용할 수 있으므로 건설프로젝트의 효율적인 관리가 가능해 지는 우수한 효과가 있다.In addition, since the estimation result of the construction project can be used as basic data for project management, it is possible to effectively manage the construction project.

Claims (9)

다수의 과거 프로젝트 실적중 견적할 신규 프로젝트와 유사한 프로젝트를 선택하면 선택된 실적프로젝트의 견적정보를 복사하는 제1단계;A first step of copying quotation information of the selected performance project when selecting a project similar to a new project to be quoted among a plurality of past project results; 다수의 과거 프로젝트 실적중 하나이상을 선택하면 선택된 프로젝트의 공사 실적 자료로부터 각 공종별 노무공량과 적용단가의 가중평균치를 계산하여 노무공량 및 각종 단가자료인 공사비적용단가데이타베이스를 생성하는 제2단계;Selecting at least one of a plurality of past project results, calculating a weighted average of labor capacity and applied unit cost for each sector from the construction project data of the selected project to generate labor cost and various unit cost data; 제1단계에서 복사된 실적프로젝트의 견적정보와 상기 제2단계에서 생성된 공사비적용단가데이타베이스의 단가정보를 합하여 기본 견적데이타베이스를 생성하는 제3단계;A third step of generating a basic estimating database by adding the quotation information of the performance project copied in the first step and the unit price information of the construction cost applying unit price database generated in the second step; 상기 제3단계에서 생성된 견적기본데이타를 신규 프로젝트의 요구사항 및 특성에 맞도록 일괄보정하는 제4단계;A fourth step of collectively correcting the quotation basic data generated in the third step to meet the requirements and characteristics of the new project; 제4단계에 의해 일괄보정이 완료된 후, 견적데이타와 신규프로젝트간에 차이가 존재하는 경우 상기 일괄보정된 견적데이타를 설비분할체계(PBS)단위로 삭제, 추가, 교체하는 제5단계;A fifth step of deleting, adding, and replacing the batch-corrected estimate data by a PBS unit if there is a difference between the estimate data and the new project after the batch correction is completed by the fourth step; 견적자의 판단에 따라 기기의 사양 및 교체를 수행하여 설비비 견적을 실행하는 제6단계;A sixth step of performing an equipment cost estimate by performing a specification and a replacement of the device according to the judgment of the estimator; 설비가 아닌 공사에만 관련된 항목에 대한 공사비를 보정하여 공사비를 견적하는 제7단계; 및A seventh step of estimating the construction cost by correcting the construction cost for the item related only to the construction, not the facility; And 건설 사업비중 간접비를 보정하는 제8단계에 의해 프로젝트의 사업비를 견적하는 것을 특징으로 하는 실적데이타를 이용한 건설프로젝트용 사업비 견적 방법.A method of estimating a project cost for a construction project using performance data, comprising estimating the project cost of the project by an eighth step of correcting overhead costs among the construction project costs. 제 1 항에 있어서,The method of claim 1, 상기 제1단계에서의 유사 프로젝트의 복사시 공사비에서 각 항목의 노무공량과 단가정보는 복사되지 않는 것을 특징으로 하는 실적데이타를 이용한 건설프로젝트용 사업비 견적 방법.When the copy of the similar project in the first step, the labor cost and unit price information of each item is not copied from the construction cost project cost estimation method for the construction project using the performance data. 제 1 항에 있어서,The method of claim 1, 제2단계에서 생성된 공사비적용단가 데이타베이스의 정보중 신규견적프로젝트로 전달되는 정보는 각 항목의 노무공량, 자재단가, 경비단가, 중기단가인 것을 특징으로 하는 실적데이타를 이용한 건설프로젝트용 사업비 견적 방법.The information delivered to the new estimate project among the information in the construction cost application cost database created in the second stage is labor cost, material cost, expense cost, and medium price for each item. Way. 제 1 항에 있어서,The method of claim 1, 상기 보정단계(제4단계)는 신규프로젝트의 용량에 맞춰 보정을 행하는 용량보정, 실적 프로젝트와 신규프로젝트의 건설시기에 따른 물가차이를 보정하는 시간보정, 실적프로젝트와 신규프로젝트와의 건설지역차에 따른 차이를 보정하는 지역보정, 지역및 국가별로 존재하는 건설 노동 생산성의 차이를 보정하는 생산성보정으로 이루어지는 것을 특징으로 하는 실적데이타를 이용한 건설프로젝트용 사업비 견적 방법.The correction step (step 4) is a capacity correction for correcting the capacity of a new project, a time correction for correcting a price difference according to the construction time of the performance project and a new project, and a construction area difference between the performance project and the new project. Method for estimating project cost for construction project using performance data, characterized in that it consists of a regional correction to correct the difference according to, and a productivity correction to correct the difference of construction labor productivity existing by region and country. 제 1 항에 있어서, 상기 방법은The method of claim 1 wherein the method is 제1단계에서 제8단계까지를 수행하여 신규프로젝트에 대한 견적이 완료된 후, 설비비, 공사비, 및 간접비의 견적금액을 조정하는 제9단계를 더 포함하는 것을 특징으로 하는 실적데이타를 이용한 건설프로젝트용 사업비 견적 방법.After performing the first to eighth step to complete the quotation for the new project, and further comprising a ninth step of adjusting the estimated amount of equipment costs, construction costs, and overhead costs for the construction project using the performance data How do you estimate business expenses? 제 5 항에 있어서, 상기 제9단계의 조정은 보정계수의 변경을 통해 이루어지는 것을 특징으로 하는 실적데이타를 이용한 건설프로젝트용 사업비 견적 방법.The method of claim 5, wherein the adjustment of the ninth step is performed by changing a correction factor. 제 1 항에 있어서, 상기 제3단계에서 공사비적용단가 데이타베이스의 생성은The method of claim 1, wherein in the third step, creation of a cost-cost unit cost database is 다수의 과거 실적 프로젝트중 하나 이상을 선택하는 단계;Selecting one or more of a plurality of past performance projects; 선택된 실적 프로젝트들을 세부 항목별로 조합하여, 노무단가를 제외한 단가데이타베이스, 노무공량 데이타베이스를 형성하는 단계;Combining the selected performance projects by sub-items to form a unit price database excluding labor unit price and a labor volume database; 해당 지역의 노무단가를 입력하여 노무 단가데이타베이스를 형성하는 단계;Inputting a labor unit price in a corresponding region to form a labor unit price database; 상기 노무공량데이타베이스로부터 다수 노무공량을 평균하여 항목별 가중평균 노무량을 계산하는 단계;Calculating a weighted average amount of labor for each item by averaging a plurality of labor volumes from the labor capacity database; 상기 노무단가데이타베이스의 데이타를 평균하여 공종별 가중평균 노무단가를 계산하는 단계;Calculating a weighted average labor price per work by averaging the data of the labor price database; 상기 계산된 평균 노무량과 평균 노무단가를 곱하여 항목별 평균 노무단가를 계산하는 단계; 및Calculating the average labor price per item by multiplying the calculated average labor amount by the average labor price; And 상기 단계에서 입력된 노무단가와 상기 계산된 항목별 평균 노무단가를 적용하여 공사비 적용단가 데이타베이스를 생성하는 단계로 이루어지는 것을 특징으로 하는 실적데이타를 이용한 건설프로젝트용 사업비 견적 방법.The project cost estimation method for a construction project using the performance data comprising the step of generating a cost database unit cost by applying the labor price input in the step and the calculated average labor price per item. 제 1 항 내지 제 7 항중 어느 한 항에 기재된 방법을 실행시키는 프로그램을 기록한 기록매체.A recording medium on which a program for executing the method according to any one of claims 1 to 7 is recorded. 데이타 및 소프트웨어를 기억하는 기억부와 소프트웨어를 실행하기 위한 CPU 및 부팅및 작업을 위한 RAM 및 ROM을 포함한 컴퓨터로 구현된 자동견적시스템에 있어서,In a computer-based automatic estimation system including a memory for storing data and software, a CPU for executing software, and a RAM and ROM for booting and working, 과거에 수행된 다수 프로젝트의 실제 견적데이타를 축적하여 보관하는 제1 데이타베이스;A first database for accumulating and storing actual estimate data of a plurality of projects performed in the past; 현재 견적할 프로젝트에 적용될 노무공량 및 각종 단가를 기억하는 제2데이타베이스;A second database for storing labor costs and various unit prices to be applied to the project to be estimated; 과거 프로젝트의 실적 자료를 현재 견적하는 프로젝트에 맞추어 보정하기 위한 다수의 보정지수를 저장하는 제3데이타베이스;A third database for storing a plurality of correction indices for correcting the historical data of past projects according to a project currently estimated; 현재 견적중인 프로젝트의 견적데이타를 저장하여 보관하는 제4데이타베이스;A fourth database for storing and storing estimate data of the project currently being estimated; 상기 제1데이타베이스로부터 한 프로젝트의 실적데이타를 복사하여 제4데이타베이스에 저장한 후, 상기 제1데이타베이스에 저장된 하나 이상의 실적데이타를 조합하여 각종 단가를 산출하여 제2데이타베이스에 저장하고, 제4데이타베이스로복사된 실적데이타에 상기 제2데이타베이스의 단가를 적용하고 제3데이타베이스의 다수 보정지수를 적용하여 보정계산하여 신규프로젝트에 대한 사업비를 견적하는 견적처리부;After copying the performance data of one project from the first database and storing it in the fourth database, various unit prices are calculated by combining one or more performance data stored in the first database, and stored in the second database. An estimate processing unit applying a unit price of the second database to the performance data copied to the fourth database and calculating a correction by applying a plurality of correction indices of the third database to estimate the project cost for the new project; 상기 견적처리부에서 산출된 신규프로젝트의 견적금액을 지수보정법으로 조정하는 시뮬레이션부; 및A simulation unit for adjusting an estimate amount of the new project calculated by the quotation processing unit by an index correction method; And 견적완료된 신규프로젝트의 견적결과를 출력하는 출력부를 포함하여 이루어지는 것을 특징으로 하는 실적데이타를 이용한 건설프로젝트용 자동 견적시스템.Automatic estimating system for construction projects using the performance data, characterized in that it comprises an output unit for outputting the estimate result of the completed new project.
KR1020010077733A 2001-12-10 2001-12-10 Cost estimate method for construction project using historical cost data, auto cost estimate system and medium storing a computer program for performing there KR20030047279A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020010077733A KR20030047279A (en) 2001-12-10 2001-12-10 Cost estimate method for construction project using historical cost data, auto cost estimate system and medium storing a computer program for performing there

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020010077733A KR20030047279A (en) 2001-12-10 2001-12-10 Cost estimate method for construction project using historical cost data, auto cost estimate system and medium storing a computer program for performing there

Publications (1)

Publication Number Publication Date
KR20030047279A true KR20030047279A (en) 2003-06-18

Family

ID=29573913

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020010077733A KR20030047279A (en) 2001-12-10 2001-12-10 Cost estimate method for construction project using historical cost data, auto cost estimate system and medium storing a computer program for performing there

Country Status (1)

Country Link
KR (1) KR20030047279A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060065838A (en) * 2004-12-10 2006-06-14 주식회사 디디알소프트 Management method for integrating construction cost and process and recording media for storing program source thereof
KR100791951B1 (en) * 2006-05-25 2008-01-04 이훈영 Method for prediction using case based
KR101047514B1 (en) * 2008-01-03 2011-07-08 한국건설기술연구원 Record medium recording program for performing road construction cost estimation method
KR20200115038A (en) * 2019-03-26 2020-10-07 김재영 System for enterprise resource planning
KR20210007335A (en) 2019-07-11 2021-01-20 이영광 Method for bids servicing of overseas constructions and service system thereof
CN112669082A (en) * 2020-12-31 2021-04-16 大为国际工程咨询有限公司 Engineering cost analysis method and system for reducing repeated workload
WO2021080194A1 (en) * 2019-10-23 2021-04-29 주식회사 주택 System and method for calculating labor cost by construction material
CN113034190A (en) * 2021-03-30 2021-06-25 重庆渝高科技产业(集团)股份有限公司 Pricing management system for engineering project
KR20220080912A (en) * 2020-12-08 2022-06-15 주식회사 지인인더스 Apparatus and method for calculating the cost of building materials

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11232329A (en) * 1998-02-17 1999-08-27 I Cube:Kk Cost management system
KR20010007721A (en) * 2000-07-03 2001-02-05 최성태 method for providing the amount of contruction materials and a cost thereof via an internet
JP2001209671A (en) * 2000-01-25 2001-08-03 Tis Inc Housing business supporting system provided with three- dimensional information
KR20010109459A (en) * 2000-05-31 2001-12-10 사사키 가네요시 Construction supporting system
KR20020064510A (en) * 2001-02-02 2002-08-09 (주)새암건축 Building cost survey and analysis method using the actual cost

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11232329A (en) * 1998-02-17 1999-08-27 I Cube:Kk Cost management system
JP2001209671A (en) * 2000-01-25 2001-08-03 Tis Inc Housing business supporting system provided with three- dimensional information
KR20010109459A (en) * 2000-05-31 2001-12-10 사사키 가네요시 Construction supporting system
KR20010007721A (en) * 2000-07-03 2001-02-05 최성태 method for providing the amount of contruction materials and a cost thereof via an internet
KR20020064510A (en) * 2001-02-02 2002-08-09 (주)새암건축 Building cost survey and analysis method using the actual cost

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060065838A (en) * 2004-12-10 2006-06-14 주식회사 디디알소프트 Management method for integrating construction cost and process and recording media for storing program source thereof
KR100791951B1 (en) * 2006-05-25 2008-01-04 이훈영 Method for prediction using case based
KR101047514B1 (en) * 2008-01-03 2011-07-08 한국건설기술연구원 Record medium recording program for performing road construction cost estimation method
KR20200115038A (en) * 2019-03-26 2020-10-07 김재영 System for enterprise resource planning
KR20210007335A (en) 2019-07-11 2021-01-20 이영광 Method for bids servicing of overseas constructions and service system thereof
WO2021080194A1 (en) * 2019-10-23 2021-04-29 주식회사 주택 System and method for calculating labor cost by construction material
KR20220080912A (en) * 2020-12-08 2022-06-15 주식회사 지인인더스 Apparatus and method for calculating the cost of building materials
CN112669082A (en) * 2020-12-31 2021-04-16 大为国际工程咨询有限公司 Engineering cost analysis method and system for reducing repeated workload
CN112669082B (en) * 2020-12-31 2023-07-18 大为国际工程咨询有限公司 Construction cost analysis method and system for reducing repeated workload
CN113034190A (en) * 2021-03-30 2021-06-25 重庆渝高科技产业(集团)股份有限公司 Pricing management system for engineering project
CN113034190B (en) * 2021-03-30 2023-11-07 重庆渝高科技产业(集团)股份有限公司 Nuclear price management system for engineering project

Similar Documents

Publication Publication Date Title
Karsak et al. Product planning in quality function deployment using a combined analytic network process and goal programming approach
US20090043643A1 (en) Managerial decision support system and method
US7881958B2 (en) Business data analysis
JP6446308B2 (en) Production planning apparatus and production planning method
WO2008154734A1 (en) An investment analysis and planning system and method
Horngren et al. A managerial Emphasis
KR20030047279A (en) Cost estimate method for construction project using historical cost data, auto cost estimate system and medium storing a computer program for performing there
US10580087B2 (en) Budget-management-data creating method, budget-management-data creating apparatus, and recording medium
US7444307B2 (en) Process for calculating the economic value created by a business activity
US20130013474A1 (en) System and method for modifying an index-based hierarchal cost model of a complex system
Gold et al. Modeling demand in computerized business simulations
Rafke et al. Simulating fleet procurement in an Indonesian logistics company
Meza Financial crisis, fiscal policy, and the 1995 GDP contraction in Mexico
US8050958B2 (en) Systems and methods for planning demand for configurable products
Čečević et al. Accounting and Value Stream Costing for More Efficient Business Processes
US8024219B2 (en) Systems and methods for planning demand for a configurable product in a managed supply chain
Hamilton Cost management
JP4617926B2 (en) Sales production integrated plan data processing device, sales production integrated plan data processing method, and sales production integrated plan data processing program
JP2004102357A (en) Production volume calculating method, device, system and program, and recording medium
Kalu An algorithm for systems welfare interactive goal programming modelling
JP7098126B1 (en) Accounting equipment, accounting methods, and accounting programs
JP7100917B1 (en) Life plan utilization system, life plan utilization method, and life plan utilization program
Bangash et al. Inventory requirements planning at lucent technologies
CN108388990B (en) System and method for realizing conversion from mixed prediction to raw material prediction based on computer software
Svavarsson Evaluation of strategic it platform investments

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application