KR20030022753A - an urgent fender wall of tires and an installation method of that - Google Patents

an urgent fender wall of tires and an installation method of that Download PDF

Info

Publication number
KR20030022753A
KR20030022753A KR1020020077657A KR20020077657A KR20030022753A KR 20030022753 A KR20030022753 A KR 20030022753A KR 1020020077657 A KR1020020077657 A KR 1020020077657A KR 20020077657 A KR20020077657 A KR 20020077657A KR 20030022753 A KR20030022753 A KR 20030022753A
Authority
KR
South Korea
Prior art keywords
wall
unit
emergency
walls
tires
Prior art date
Application number
KR1020020077657A
Other languages
Korean (ko)
Inventor
최원영
Original Assignee
최원영
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 최원영 filed Critical 최원영
Priority to KR1020020077657A priority Critical patent/KR20030022753A/en
Publication of KR20030022753A publication Critical patent/KR20030022753A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • E02B3/106Temporary dykes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/205Securing of slopes or inclines with modular blocks, e.g. pre-fabricated
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B2201/00Devices, constructional details or methods of hydraulic engineering not otherwise provided for
    • E02B2201/04Devices, constructional details or methods of hydraulic engineering not otherwise provided for using old tires for hydraulic engineering
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0001Rubbers
    • E02D2300/0003Car tires

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Revetment (AREA)

Abstract

PURPOSE: An installation method for a prefabricated emergency wall using waste tires is provided to install an emergency wall rapidly and firmly. CONSTITUTION: The installation method for a prefabricated emergency wall using waste tires comprises the steps of leveling the ground on an installation site, installing unit walls(5) in two lines, forming an emergency wall by filing up a space between an inside of a tire and a wall of a facing tire with earthy materials(10), spreading a vinyl sheet(8) on a front line and woven fabrics(9) on a rear line, attaching unit walls(5) on the vinyl sheet(8) and the woven fabrics(9) in a line, and letting ropes pass through perforated holes of tires of the unit walls(5) continuously, then binding together.

Description

폐타이어를 이용한 긴급 조립식 방재벽 및 이를 이용한 설치방법{an urgent fender wall of tires and an installation method of that}Urgent fender wall of tires and an installation method of that}

본 발명은 폐타이어를 이용한 긴급 조립식 방재벽 및 이를 이용한 설치방법에 관한 것으로서, 특히 홍수로 인한 범람위기 또는 제방유실 등 비상상황 발생시에 긴급하게 물, 토사 등의 유입을 차단할 수 있도록 폐타이어로 미리 만들어 놓은 소규모 벽체들을 비상상황 발생시 장비로 옮겨서 조립식으로 방재벽체를 설치하고타이어 벽체 내부에 장비를 사용하여 토사를 충진함으로써 튼튼한 방재벽을 신속하게 설치할 수 있는 긴급 조립식 방재벽에 관한 것이다.The present invention relates to an emergency prefabricated disaster prevention wall using waste tires and an installation method using the same. In particular, in the event of an emergency situation such as flooding crisis or levee loss due to flooding, the waste tires may be urgently blocked in advance to prevent inflow of water and earth and sand. It is about an emergency prefabricated barrier wall that can install sturdy barrier walls quickly by moving the small walls that have been made to the equipment in case of emergency and installing the barrier wall prefabricated and filling the soil with the equipment inside the tire wall.

우리나라는 지구온난화로 강우량이 증가하고 있으며 태풍이 자주오며 지역에 따라서는 게릴라성 호우가 내리고 있다. 또한 유역의 도시화로 첨두 홍수량이 증가하고 있다.In Korea, rainfall is increasing due to global warming, typhoons are frequent, and guerilla rains are falling in some regions. In addition, peak flooding is increasing due to urbanization of the watershed.

이렇게 증가된 홍수량은 제방을 붕괴시키고 범람하여 많은 피해를 일으키고 있다. 많은 양의 강우, 태풍으로 인한 폭우 등은 하천의 유량을 증가시킬 뿐만 아니라 식생상태가 나쁜 산지, 절개지 사면 등에서 산사태를 유발하여 강우와 함께 많은 토사와 유목이 하류로 흐르게 된다.This increased flooding causes the dams to collapse and flood, causing a lot of damage. A large amount of rainfall and heavy rain caused by typhoons not only increase the flow rate of the river, but also cause landslides in bad vegetation and inclined slopes, so that much soil and driftwood flows downstream along with the rainfall.

이러한 지역의 하류하천은 토사와 유목으로 수로가 막혀서 하천물이 범람하여 주변지역이 침수되고 토사에 의해 매몰되게 된다.The downstream rivers in these areas are channeled by soil and driftwood, flooding the rivers and flooding the surrounding area and buried by soil.

이와 같은 홍수에 의한 피해를 방지하기 위해서는 댐을 건설하고 하천의 제방을 정비하는 등 많은 비용과 시간이 필요하게 된다.In order to prevent such flood damage, a lot of money and time are required, such as building a dam and maintaining a river bank.

그러나 홍수에 의한 피해는 무차별적이며 인명과 재산상의 피해가 크므로 재해를 예방하기 위한 다각적인 노력이 필요하다.However, the damage caused by flooding is indiscriminate, and the damage to life and property is so great that various efforts are needed to prevent the disaster.

특히, 홍수로 인한 범람위기가 발생하면 무엇보다도 긴급하게 홍수벽을 설치하는 등 범람을 막기 위한 노력이 필요하며 그러나 불가항력적으로 범람이 되었을 때에는 물길 차단벽 등을 설치하여 그 피해지역의 확산을 막기 위한 노력이 필요하다.In particular, if a flooding crisis occurs due to flooding, it is necessary to put an effort to prevent flooding, such as urgently installing a flood wall.However, when it is inevitably flooded, water barriers are installed to prevent the spread of the affected area. Effort is required.

또한, 범람으로 유실된 제방, 도로 등의 신속한 응급복구가 필요하다.In addition, there is a need for rapid emergency repair of flooded dikes and roads.

현재 이러한 긴급 상황 발생시 범람을 막기 위해 할 수 있는 방법은 모래포대 등으로 홍수벽을 설치하는 방법이 있다.Currently, a way to prevent flooding in the event of such an emergency is to install flood walls with sand bags.

그러나 이 방법은 시간이 많이 소요되고 홍수벽이 약해서 범람을 막아내지 못하는 등 재해에 대한 예방 역할을 못하고 있으며 단지 모래포대 이용방법은 피해발생 후 제방복구 등의 응급복구 방법으로 이용되고 있다.However, this method is time-consuming and the flood wall is weak to prevent flooding, and it does not play a role in preventing disasters. The sand bag is only used as an emergency recovery method such as levee recovery after damage.

이와 같이 모래포대를 이용한 긴급 홍수벽의 설치나 응급복구 방법은 모래포대속에 토사류 투입이 어렵고 토사가 충진된 모래포대를 인력으로 운반하여 제방 등을 축조해야 하므로 포대를 크게 만들 수 없어서 속도가 느리고 인력이 많이 소요되며 이에 따라서 시간이 많이 소요되어서 긴급한 상황에 대한 대처효과가 적은 문제점이 있었다.As described above, the emergency flood wall installation or emergency recovery method using sand bags is difficult to put soil into sand bags, and sand bags filled with soil are transported by manpower to build embankments. This takes a lot of time and accordingly takes a lot of time to cope with the urgent situation was less effective.

또한 모래포대로 무너진 제방 등을 응급복구 할 경우 포대간의 결속력이 없으므로 제방의 안전도를 고려할 때 높이 쌓기가 어려우며 만약 제방고를 높이 쌓을 때에는 하부를 넓게 쌓아야 하므로 많은 모래포대가 필요하게 된다.In addition, there is no binding force between bags in case of emergency recovery of a damaged dike etc. with sand bags, so it is difficult to build high considering the safety of dikes.

이와 같이 모래포대를 이용한 수해 예방 및 수해시 응급복구 방법은 많은 인력과 시간이 소요되며 또한 제방의 안전성이 크지 않아서 실제 상황에서 잘 적용이 안되는 문제점이 있었다.As described above, the method of preventing and repairing floods using sand bags takes a lot of manpower and time, and the safety of the levees is not so great that there is a problem that cannot be applied in actual situations.

본 발명은 이러한 문제점들을 해소하기 위한 것으로서 본 발명의 목적은 첫째, 홍수로 하천이나 저수지의 수위가 상승하여 범람위기가 닥쳤을 때 범람을 방지하기 위하여 설치하는 긴급 홍수벽 및 범람시 물길이나. 토사를 차단하는 긴급 차단벽을 신속하고 튼튼하게 설치할 수 있고, 둘째, 제방유실, 도로유실 등 홍수로 인한 피해 발생 후 응급복구를 신속하고 효과적으로 실시할 수 있는 방재벽체를 제공하는데 그 목적이 있다.The present invention is to solve these problems, the object of the present invention is first, the emergency flood wall and flooding waterway to install to prevent flooding when the flooding crisis hits the water level of the river or reservoir due to the flood. The purpose of the present invention is to provide emergency barriers that can quickly and effectively install earthquake barriers to block soil, and secondly, to quickly and effectively perform emergency repairs after flood damage such as levees and roads.

상기의 목적 달성을 위한 본 발명은, 비슷한 크기의 폐타이어들을 모아서 일측면부를 절개하고 트레드면을 2개소 이상 등간격으로 천공하여 구멍을 형성토록한 후 이 폐타이어들을 절개부위가 위를 향하고 천공구멍이 같은 위치에 오도록 포개어 다수층의 높이로 원통형태로 쌓고 이 원통다수를 일렬로 붙여서 벽을 만들고 각 원통내부에서 유연성이 있으며 내구성과 강도가 큰 로프를 사용하여 천공구멍으로 상하좌우에 맞닿은 폐타이어들을 8자 형태로 교차 결속하여 일정크기의 소규모 단위벽체를 미리 다수 만들어 놓고 이 소규모 벽체를 수해 발생이 예상되는 취약지역 인근에 비축한 후 비상상황 발생시 현장으로 운반하여 장비를 사용하여 소규모 단위벽체들을 적층시켜서 방재 벽체로 이루어지도록 조립식으로 설치한 후 벽체 뒤쪽에 수직으로 비닐시트 또는 부직포를 설치하고 또한 장비를 사용하여 벽체 내부에 토사를 충진하여 방재벽을 매우 신속하고 튼튼하게 설치함으로써 그 목적이 달성된다.In order to achieve the above object, the present invention collects waste tires of similar size and cuts one side portion, and drills the tread surface at two or more equal intervals to form a hole, and then cuts the waste tires upwards and drills them. Stacked in a cylindrical shape at the height of multiple layers by stacking the holes in the same position, and attaching many cylinders in a row to make a wall, and using the rope with flexible, durable and high-strength inside each cylinder. The tires are cross-bonded in the form of eight letters to make a number of small unit walls of a certain size in advance, and the small walls are stored near the vulnerable area where it is expected to occur and transported to the site in case of emergency. To install them prefabricated so that they form a disaster prevention wall and then perpendicular to the back of the wall. The purpose is achieved by installing vinyl sheets or non-woven fabrics and by using equipment to fill the soil inside the walls with very fast and robust installation of disaster prevention walls.

도1은 본발명인 타이어를 이용한 단위벽체 조립 종단면도1 is a longitudinal cross-sectional view of unit wall assembly using the present invention tires

도2는 본발명에 따른 가공된 타이어의 사시도2 is a perspective view of a processed tire according to the present invention;

도3은 본발명에 따른 가공된 타이어의 단면도3 is a cross-sectional view of a processed tire according to the present invention.

도4는 본발명에 따른 밀착3열벽의 단면도Figure 4 is a cross-sectional view of the three close contact wall according to the present invention

도5는 본발명에 따른 이격2열벽 단면도Figure 5 is a cross-sectional view of two spaced apart two columns according to the present invention

도6은 본발명에 따른 1열벽 단면도Figure 6 is a one-walled cross section according to the present invention

도7은 본발명에 따라 긴급 홍수벽에 이용되어 밀착다열벽 방법으로 설치된Figure 7 is used in the emergency flood wall in accordance with the present invention installed in a close multi-row method

상태도State diagram

도8은 본발명에 따라 긴급 홍수벽에 이용되어 이격2열벽 방법으로 설치된Figure 8 is used in the emergency flood wall in accordance with the present invention is installed in the spaced two-wall method

상태도State diagram

도9는 본발명에 따라 제방 응급 복구에 이용되어 이격2열벽 방법으로 설치된Figure 9 is used for emergency repair of the embankment in accordance with the present invention is installed in a spaced two-wall method

상태의 단면도Profile of status

도10은 본발명에 따라 물길 긴급 차단벽에 이용된 상태의 구성도Figure 10 is a block diagram of a state used in the emergency road blocking wall according to the present invention

도11은 본발명에 따라 토사 긴급 차단벽에 이용된 상태의 구성도11 is a configuration diagram of the state used in the earth and sand emergency barrier in accordance with the present invention

도12는 본발명에 따라 도로복구 차단벽에 이용되어 보강재가 내설시켜 1열벽Figure 12 is used in the road restoration barrier wall according to the present invention, the reinforcement is built in the first row wall

방법으로 설치된 상태의 단면도Section installed in the way

도13은 본발명에 따라 도로복구 차단벽에 이용되어 보강재가 불필요한 1열벽Figure 13 is a one-row wall unnecessary for reinforcement used in the road repair blocking wall according to the present invention

방법으로 설치된 상태의 단면도Section installed in the way

도14는 본발명에 따라 교각 응급 설치에 이용된 상태의 구성도Figure 14 is a block diagram of a state used for the emergency installation of piers according to the present invention

도15는 본발명에 따라 제방호안에 설치된 상태의 구성도Figure 15 is a configuration diagram of the state installed in the protection in accordance with the present invention

도16은 본발명에 따라 제방 보강 차수벽으로 이용된 상태의 구성도Figure 16 is a schematic view of the state used as the embankment reinforcement order wall in accordance with the present invention

<도면중 주요 부분에 대한 부호 설명><Description of Signs for Main Parts in Drawings>

1. 폐타이어 2. 구멍1. Waste tire 2. Hole

3. 절개부 4. 로프3. Incision 4. Rope

5. 단위벽체 6. 운반용 고리5. Unit wall 6. Carrying ring

7. 뒤집기용 고리 8. 비닐시트7. Flip collar 8. Vinyl sheet

9. 부직포 10. 토사9. Nonwovens 10. Earth and sand

11. 타이로프 12. 보강재 로프11.tie rope 12.reinforcement rope

본발명인 방재벽체를 구성하기 위한 소규모 단위벽체의 구성을 첨부된 도면에 의하여 상세히 살펴보면 다음과 같다.Looking at the configuration of the small unit wall for constituting the disaster prevention wall of the present invention in detail by the accompanying drawings as follows.

도1 내지 도3에 도시된 바와같이 비슷한 크기의 폐타이어(1)들을 모아서 일측면부를 절개하고 트레드면을 2개소 이상 등간격으로 천공하여 구멍(2)을 형성토록한 후 이 폐타이어들을 절개부위(3)가 위를 향하고 천공구멍(2)이 같은 위치에 오도록 포개어 다수층의 높이로 원통형태로 쌓고 이 원통다수를 일렬로 붙여서 벽을 만들되 상하좌우에 맞닿은 각 폐타이어들의 천공구멍(2)으로 내구성과 강도가 큰 로프(4)를 8자 형태로 교차 결속하여 일정크기의 소규모 단위벽체(5)로 구성한다.As shown in Figs. 1 to 3, waste tires 1 of similar size are collected and one side portion is cut and perforated two or more places at equal intervals to form holes 2 to cut the waste tires. Perforated holes (2) are piled up in a cylindrical shape at the height of a plurality of layers, with the parts (3) facing up and the perforated holes (2) at the same position. ), The rope 4 having high durability and strength is cross-bonded in the form of eight characters to form a small unit wall 5 having a predetermined size.

상기 소규모 단위벽체(5)의 소정위치 상하부에는 장비로 운반이 가능하도록 운반용 고리(6)를 형성한 구성이다.Above and below the predetermined position of the small unit wall 5 is a configuration in which a transport ring 6 is formed to be transported by equipment.

본발명인 방재벽을 구성하기 위한 소규모 단위벽체(5)(일명 소규모 타이어 벽체라고 함)를 보다 구체적으로 제작과정을 설명하면 다음과 같다.The small unit wall 5 (also called small tire wall) for constituting the disaster prevention wall of the present invention will be described in more detail as follows.

단위벽체 제작에 사용하는 폐타이어들은 측면부를 절개하지 않고도 사용할 수 있으나 타이어 내부에 토사충진이 용이하고 벽체 해체시 토사제거가 용이하도록 폐타이어의 일측면부 또는 양측면부를 절개하여 제거하며 또한 타이어들간의 결속을 위하여 트레드면에 균등한 간격으로 2개이상의 구멍을 천공한다.Waste tires used for the production of unit walls can be used without cutting off the side parts, but they can be removed by cutting one side or both sides of the waste tires for easy soil filling inside the tire and easy soil removal when dismantling the wall. To do this, drill two or more holes at equal intervals on the tread surface.

구멍을 많이 뚫어서 묶을수록 단위벽체가 견고해진다.The more holes drilled and bundled, the stronger the unit wall is.

단위벽체 제작에 있어서는 비슷한 크기의 폐타이어들을 사용하며 단위벽체의 크기는 클수록 방재벽 설치시간을 단축할 수 있으나 토사충진 및 제거의 용이성, 운반 및 설치 편리성 등을 고려하여 결정한다.In the production of unit walls, waste tires of similar size are used, and the larger the unit wall size is, the shorter the installation time of the barrier wall can be shortened, but it is decided in consideration of the ease of soil filling and removal, convenience of transportation and installation.

예로서 승용차 타이어를 사용할 경우 도1에 도시된 바와같이 높이는 3개층, 길이는 5열을 갖는 단위벽체의 조립방법은 다음과 같다.As an example, when using a car tire, as shown in FIG. 1, a method of assembling a unit wall having three heights and five rows is as follows.

① 크기가 비슷한 폐타이어(1)들을 모아서 일측면부를 절개하고 중심각이 90도 되도록 4곳에 구멍(2)을 뚫는다.① Collect waste tires (1) of similar size and cut one side and drill holes (2) in four places so that the center angle is 90 degrees.

② 이렇게 가공된 타이어 3개를 절개된 측면부가 위를 향하고 좌우 천공 위치가 일직선상에 위치하도록 포개어 원통형태로 쌓는다.② The three processed tires are stacked in a cylindrical shape with the cut side faces upward and the left and right drilling positions are in a straight line.

③ 타이어 3개가 적층되어 형성된 원통형태 5개를 일직선상으로 붙여서 좌우 천공구멍(2)이 서로 맞닿도록 쌓는다.(3) Attach the five cylindrical shapes formed by stacking three tires in a straight line to stack the left and right boring holes 2 in contact with each other.

④ 각 원통 내부에서 맨 아래 타이어(1)의 서로 맞닿은 좌우 천공구멍(2)으로 각각 유연하며 내구성과 강도가 큰 로프(4)를 통과시키고 그 위 상부 타이어의 비드선을 포함하여 원형으로 감싸서 상부 타이어의 천공구멍으로 교차 통과시키고 반복하여 그 다음 3번째층 타이어의 비드선을 원형으로 감싸서 6개의 타이어들을 8자 형태로 결속하고 양 로프를 묶는다.④ Pass the flexible, durable and strong ropes 4 through the left and right boring holes 2 of the bottom tires 1, which are in contact with each other, inside the cylinders, and wrap them in a circle including the bead lines of the upper tires. Cross the tires through the perforations of the tires and repeat, then wrap the bead lines of the third layer tires in a circle to bind the six tires in an eight-character shape and tie both ropes together.

⑤ 1번째 원통과 2번째 원통 또 4번째 원통과 5번째 원통의 맞닿은 최상부 타이어들의 천공구멍(2)으로 로프(4)를 연속 통과시켜서 벽체 상부에 묶어서 운반용 고리(6)를 만든다.⑤ A rope (4) is continuously passed through the rope (4) through the perforation holes (2) of the uppermost tires abutting the first cylinder, the second cylinder, and the fourth cylinder and the fifth cylinder to form a carrying ring (6).

⑥ 맨하부 타이어들의 천공구멍으로는 로프(4)를 이용하여 뒤집기용 고리(7)를 설치한다.⑥ Install the reversing ring (7) using the rope (4) as the hole of the bottom tires.

이와같이 제작된 본발명인 단위벽체를 이용하여 사용되는 긴급 조립식 방재벽의 용도는 다음과 같다.The use of the emergency prefabricated disaster barrier used by using the unit wall of the present invention manufactured as described above is as follows.

(1) 재난 긴급 방재용(1) Disaster emergency emergency

하천이나 저수지의 수위상승으로 범람위험시 설치하는 긴급 홍수벽Emergency flood wall installed in case of danger of flooding due to rising water level in rivers or reservoirs

하천이나 저수지의 범람 예상시 또는 범람시 설치하는 긴급 물길 차단벽Emergency waterway barrier wall installed when the river or reservoir is expected to overflow

산사태 발생 우려지역 또는 발생지역에 설치하는 긴급 토사 차단벽Emergency earth and sand barriers installed in landslide-prone areas or outbreak areas

(2) 재난 응급 복구용(2) disaster recovery

하천이나 저수지 제방 붕괴시 응급 복구용 방재벽Emergency recovery barriers in the event of a river or reservoir embankment collapse

홍수로 인한 유실도로 복구용 방재벽Barriers to recover lost roads due to flooding

홍수로 인한 교량파괴시 응급 교각 복구용 방재벽Emergency Pier Recovery Barrier in case of Bridge Destruction due to Flood

임시 성토용 방재벽Temporary Fill Barriers

(3) 건설공사 가시설용(3) For construction facilities

가물막이 공사용 벽체Wall for construction

하천 및 수로 물길차단벽체River and waterway barriers

임시 물탱크, 저류지, 침사지 축조용 벽체Temporary water tanks, reservoirs, settlement walls

임시 성토용 벽체Temporary Fill Walls

등의 용도로 이용하면 된다.It may be used for such purposes.

상기 벽체의 설치 방법에 대하여 자세히 설명하면 다음과 같다.The installation method of the wall will be described in detail as follows.

벽체를 설치하기 위해서는 먼저 설치장소의 지반을 평탄하게 정지하고 단위벽체를 장비로 들어서 계획선에 안치시킨다.In order to install the wall, the ground of the installation site should be stopped evenly, and the unit wall is lifted into the equipment and placed on the planned line.

벽체는 수직으로 설치하여야 하며 가능한 범위에서 수평이 되도록 설치한다.Walls should be installed vertically and level to the extent possible.

벽체 설치방법에는 밀착다열벽 방법, 이격2열벽 방법 및 1열벽 방법이 있다.The wall installation method includes a close multi-row method, a spaced two-row method, and a single-row method.

방재벽의 용도와 장소에 따라서 방재벽 설치시간의 촉박성, 충진토사 확보방법, 설치높이, 설치장소의 넓이, 차량진입 등 설치장소의 여건 등을 고려하여 설치방법을 선정한다.According to the purpose and location of the barrier, the installation method should be selected in consideration of the tightness of the barrier installation time, the method of securing the filling soil, the height of the installation, the width of the installation site, and the conditions of the installation location such as entering the vehicle.

(1) 밀착다열벽 방법(1) tight multi-wall method

밀착다열벽 방법은 차수벽이나 토사차단벽으로 활용된다.The close multi-wall method is used as a barrier or soil barrier.

도4에 도시된 바와같이 단위벽체(5)를 사용하여 타이어 벽체를 2열이상 밀착하여 붙여서 벽체를 설치하며 차수벽으로 쓸때는 벽체 사이에 비닐시트(8)를 끼우고 토사 차단벽은 비닐시트(8)를 끼우지 않고 벽체 내부와 사이 공간에 토사를 충진한다.As shown in Figure 4, using the unit wall (5) to attach the tire wall in close contact with two or more rows to install the wall, when used as a barrier wall sandwiching the vinyl sheet (8) between the walls and the earth and sand barrier wall is a vinyl sheet ( 8) Fill the soil inside the space between the wall and without inserting it.

먼저 설치장소의 지반을 평탄하게 정지하고 맨 앞에 설치될 단위벽체(5)를 감쌀 수 있도록 바닥에 비닐시트(8)를 길게 깔고 단위벽체(5)를 비닐시트(8)가 1/3정도 깔리도록 비닐시트 위에 일렬로 높여서 설치한다.First, the ground of the installation place is stopped flat and the vinyl sheet 8 is laid long on the floor so as to wrap the unit wall 5 to be installed at the front, and the unit wall 5 is covered with 1/3 of the vinyl sheet 8. Install it in line with the plastic sheet.

단위벽체(5)간의 종방향 수평연결방법은 맞닿은 단위벽체들의 양쪽 외곽부 맨 위쪽 타이어의 천공구멍(2)으로 로프(4)를 연속하여 통과시켜서 함께 묶는다.In the longitudinal horizontal connection method between the unit walls 5, the rope 4 is successively passed through the perforation holes 2 of the top tires on both outer sides of the unit walls, which are joined together and tied together.

그러나 시간이 매우 촉박할 때는 단위벽체들간의 종방향 수평연결을 생략하며 시간적 여유가 있을 때에는 단위벽체에 기결속되어 있는 양쪽 외곽부 결속로프를 제거하고 맞닿은 양쪽 단위벽체의 6개 타이어들을 모두 로프로 결속하여 견고성을 배가시킨다.However, when the time is very short, the longitudinal horizontal connection between the unit walls is omitted, and when time permits, the two outer tie ropes attached to the unit walls are removed, and all six tires of the unit walls contacted with ropes are removed by rope. Bind to double the robustness.

바닥의 비닐시트(8)로 단위벽체(5) 뒷면을 감싸 올리고 비닐시트(8) 뒤쪽에 단위벽체(5)를 밀착시켜서 2열 또는 3열로 벽체를 설치하고 단위벽체간 수평연결을 실시한다.Wrap the back of the unit wall (5) with the vinyl sheet (8) at the bottom, and attach the unit wall (5) in close contact with the back of the vinyl sheet (8) to install the wall in two or three rows and to perform horizontal connection between the unit walls.

방재벽의 높이가 높을 때에는 단위벽체를 위로 올려서 수직으로 더 쌓으며 이때 상하단 위벽체간의 연결은 현장의 상황에 따라서 시간적 여유가 있으면 맞닿은 상하 단위벽체의 맨위와 맨아래 타이어의 천공구멍으로 로프를 통과시켜 함께 묶고 시간적 여유가 없으면 수직연결을 생략한다.When the height of the disaster prevention wall is high, the unit wall is lifted up to be stacked vertically. At this time, the connection between the upper and lower upper walls is made by passing the rope through the upper and lower tire perforations of the upper and lower unit walls, which are in contact with each other, if there is time. Bundle together and omit vertical connections if you do not have time.

(2) 이격2열벽 방법(2) spaced two-heat wall method

도5에 도시된 바와같이 단위벽체(5)를 사용하여 타이어 벽체를 일정한 간격을 띄우고 평행하게 2열로 설치하고 타이어 원통내부와 마주선 타이어 벽체사이에 공간에 토사(10)를 충진하여 방재벽을 만든다.As shown in FIG. 5, the unit walls 5 are used to install the tire walls in two rows in parallel and at regular intervals, and fill the earth and sand 10 in the space between the inside of the tire cylinder and the tire wall facing the disaster prevention wall. Make.

먼저 설치장소의 지반을 평탄하게 정지하고 제방과 평행하게 일정한 간격을 띄우고 전열에 비닐시트(8)를 깔고 후열에는 부직포(9)를 깔고 비닐시트(8)와 부직포(9)위에 단위벽체(5)를 일렬로 붙여서 설치한다.First, the ground of the installation site is stopped flat, spaced at regular intervals parallel to the embankment, the vinyl sheet (8) is laid on the heat transfer, the nonwoven fabric (9) is laid on the heat transfer, and the unit wall (5) is placed on the vinyl sheet (8) and the nonwoven fabric (9). Install in a line.

단위벽체(5)간의 종방향 수평연결방법은 맞닿은 단위벽체(5)들의 양쪽 외곽부 맨위쪽과 바로 아래쪽 타이어(1)의 천공구멍(2)으로 로프(4)를 연속 통과시켜서 함께 묶는다.In the longitudinal horizontal connection method between the unit walls 5, the ropes 4 are continuously passed through the top of the outer periphery of the abutment of the unit walls 5 and the boring holes 2 of the tire 1 immediately below, and tied together.

그러나 시간이 매우 촉박할 때는 단위벽체들간의 종방향 수평연결을 생략하며 시간적 여유가 있을 때에는 단위벽체에 기결속되어 있는 양쪽 외곽부 결속로프를 제거하고 맞닿은 양쪽 단위벽체의 8개 타이어들을 모두 로프로 결속하여 견고성을 배가시킨다.However, when the time is very short, the longitudinal horizontal connection between the unit walls is omitted, and when there is time, the two outer binding ropes attached to the unit walls are removed, and the eight tires on both sides of the unit walls are connected by ropes. Bind to double the robustness.

비닐시트(8)와 부직포(9)로 단위벽체(5)의 뒷면을 감싸 올리고 흐르지 않도록 상부에서 고정시킨다.The back of the unit wall (5) is wrapped with a vinyl sheet (8) and a nonwoven fabric (9) and fixed at the top so as not to flow.

한편, 마주선 단위벽체(5)들 간에는 벽체 중간 타이어에 천공된 구멍을 이용하여 비닐시트(8)와 부직포(9)에 구멍을 뚫고 타이로프(11)로 상호단위벽체를 연결하여 벽체가 뒤로 넘어지지 않도록 한다.Meanwhile, between the opposing unit walls 5, holes are formed in the vinyl sheet 8 and the nonwoven fabric 9 using holes drilled in the middle tire of the wall, and the mutual unit walls are connected by tie ropes 11 so that the wall is backward. Do not fall.

방재벽의 높이가 높을 때에는 단위벽체를 위로 올려서 2~3개 층을 수직으로 쌓으며 그 이상 높이에서는 상부로 가면서 단차를 주어 마주선 단위벽체간 이격거리를 좁혀서 설치한다.When the height of the disaster prevention wall is high, the unit wall is raised upward and two or three floors are stacked vertically. If the height of the disaster barrier is higher, the gap between the unit walls facing each other is narrowed by giving a step to the upper part.

단위벽체간 수직연결은 현장상황에 따라서 연결하거나 또는 생략한다.Vertical connections between unit walls may be omitted or omitted depending on site conditions.

(3) 1열벽 방법(3) 1 heat wall method

도6에 도시된 바와같이 뒤채움 토사가 있는 제방, 도로 등 성토지역에 설치하는 옹벽식 벽체 설치 방법으로서, 바닥 기초를 평탄하게 정지하고 기초바닥에 부직포(9)를 길게 깔고 그 위에 단위벽체(5)를 일렬로 붙여서 설치한다.As shown in FIG. 6, a retaining wall installation method is provided in a fill area such as a levee, a road, and a backfilled soil, and stops the floor foundation flat and lays a nonwoven fabric 9 on the foundation floor. Install 5) in a row.

단위벽체간 수평연결 방법은 맞닿은 단위벽체들의 양쪽 외곽부 맨위쪽과 바로 아래쪽 타이어의 천공구멍으로 로프를 연속하여 통과시켜서 함께 묶는다.The horizontal connection method between the unit walls is tied together by successively passing the rope through the perforation holes of the tires immediately above and at the top of both outer sides of the contact unit walls.

그러나 시간이 매우 촉박할 때는 단위벽체들간의 종방향 수평연결을 생략하며 시간적 여유가 있을 때에는 단위벽체에 기결속되어 있는 양쪽 외곽부 결속로프를 제거하고 맞닿은 양쪽 단위벽체의 8개 타이어들을 모두 로프로 결속하여 견고성을 배가시킨다.However, when the time is very short, the longitudinal horizontal connection between the unit walls is omitted, and when there is time, the two outer binding ropes attached to the unit walls are removed, and the eight tires on both sides of the unit walls are connected by ropes. Bind to double the robustness.

바닥의 부직포로 단위벽체 뒷면을 감싸 올리고 흐르지 않도록 상부에서 고정시키고 부직포에 구멍을 뚫고 벽체중간구멍에 보강재로프(12)로 묶는다.Wrap the back of the unit wall with a nonwoven fabric at the bottom and fix it at the top so that it does not flow, drill a hole in the nonwoven fabric and tie it with a reinforcement rope 12 in the middle hole of the wall.

벽체내부에 토사를 충진하고 뒤채움토사를 충진한다.Fill the soil inside the wall and fill the backfill soil.

뒤채움 토사를 충진할 때 보강재 로프(12)를 토사층에 묻으면서 충진한다.When filling the backfilling soil, the reinforcement rope 12 is filled while filling the soil layer.

1열벽은 설치높이와 현장여건에 따라서 일체화된 수직벽이나 또는 단차를 주는 계단식 수직벽으로 설치하며 단위벽체간 수직연결은 현장 상황에 따라서 연결하거나 또는 생략한다.One row wall is to be installed either as an integrated vertical wall or stepped vertical wall depending on the installation height and site conditions. Vertical connection between unit walls is connected or omitted depending on the site situation.

벽체내부 토사 충진방법How to fill soil inside the wall

단위벽체(5)는 평탄한 지역에 안치하면 토사를 충진하지 않은 상태에서도 자립하므로 벽체내 토사 충진 작업을 쉽게 할 수 있다.When the unit wall 5 is placed in a flat area, the unit walls 5 are self-supporting even when the soil is not filled, so that the soil filling work in the wall can be easily performed.

본 긴급 조립식 방재벽에서는 방재벽 설치시간단축을 위하여 장비를 사용하여 수직형태의 단위벽체 원통상부에 토사를 부어서 충진하여 망치로 타이어 표면을 두드려서 원통내부로의 토사충진이 잘되도록 하는 등 인력으로 충진작업을 마무리한다.In this emergency prefabricated barrier wall, the equipment is used to shorten the installation time of the barrier wall by filling earth and sand in the vertical cylindrical unit wall, and filling it with manpower. Finish the work.

각 원통내부에는 토사가 충만할수록 좋으나 시급성에 따라서 토사를 충진하며 일부원통에 토사가 약간 부족하여도 타이어 벽체는 자체가 자립하므로 비닐시트에 의하여 차수가 되며 부직포에 의하여 흡출이 방지되므로 벽체는 안전성에 큰 문제가 없다.It is better to fill the soil inside each cylinder, but it is better to fill the soil according to the urgency. Even though some soil is lacking in some cylinders, the tire wall itself is self-supporting, so it is ordered by vinyl sheet and prevented by the nonwoven fabric. There is no big problem.

방재벽 해체방법Dismantling method of barrier

비상상황이 종료되어 방재벽을 해체할 때에는 단위벽에간 연결로프를 끊고 장비로 단위벽체를 넘어뜨리고 고리로 들어 올려서 단위벽체와 토사를 분리한다.When dismantling the disaster barrier after the emergency is over, break the connecting rope between the unit walls, overturn the unit wall with the equipment, and lift it up with a ring to separate the unit wall and the soil.

주변의 토사를 치우고 청소하여 토사가 제거된 단위벽체는 세척한 후 보관하여 재사용하며 찌그러지거나 느슨해진 단위벽체는 분해하여 다시 조립한다.Clean and store the unit walls from which the soil is removed by removing and cleaning the surrounding soil. Reuse and reassemble the unit walls that are crushed or loosened.

이와같이 본발명인 소규모 타이어 벽체를 이용하여 설치된 긴급 조립식 방재벽은 수해를 방지하고 수해 발생시에는 그 피해를 줄이며 또한 응급복구를 신속히 하기 위한 방재시설로서 긴급 조립식 방재벽의 가장 중요한 장점은 신속성과 견고성 및 차수성이다.As such, the emergency prefabricated barrier wall installed using the small tire wall of the present invention is a disaster prevention facility for preventing floods, reducing damage in the event of a flood, and for quick emergency recovery. Mercury.

신속한 방재벽 설치를 위해서는 폐타이어를 가공하여 미리 소규모 방재용 타이어 벽체를 다수 만들어 놓고 재해발생이 우려되는 취약지역 인근에 이 소규모 벽체를 비축하여 놓았다가 비상상황 발생시 소규모 벽체를 장비로 이동하고 안치하여 방재벽을 조립식으로 설치하고 또한 벽체 내부의 토사 충진 작업도 장비를 사용함으로써 신속한 방재벽 설치가 가능하다.For fast disaster prevention wall installation, many tires for small disaster prevention tires are made in advance by processing waste tires, and this small wall is stored near the vulnerable area where a disaster is likely to occur. It is possible to install the barriers quickly by using the prefabricated barriers and using the equipment for earth and sand filling inside the walls.

한편, 견고한 방재벽 설치에 있어서는 벽체를 타이어로 사용하므로 견고성이 확보된다.On the other hand, in the installation of a solid disaster prevention wall, since the wall is used as a tire, robustness is secured.

타이어는 고무가 주성분으로써 내구성과 인장강도가 크고 화학적으로 안정되어 있는 소재이다.Tires are made of rubber and are chemically stable with high durability and tensile strength.

소규모 타이어 벽체는 벽체를 구성하는 모든 타이어들이 고탄소강이 들어있는 비드선 부위나 트레드면이 로프로 결속되어 벽체 전체가 일체화 되어 있으며 이 벽체 내부와 주변공간 외부에 토사류를 충진 하고 흡출 방지용 부직포를 설치함으로써 타이어로 구성된 방재벽은 견고성이 크다.In small tire wall, all tires that make up the wall are tied to the bead line or the tread surface where high carbon steel is contained by rope, and the whole wall is integrated. As a result, the disaster prevention wall made of tires has high rigidity.

또한 차수성 확보를 위하여 타이어 벽체 뒷면에 수직으로 비닐시트를 설치하고 토사를 충진함으로써 차수성이 확보된다.In addition, by securing the water-repellency, by installing a vinyl sheet vertically on the back of the tire wall and filling the soil.

긴급 조립식 방재벽은 소규모 타이어 벽체를 다수 미리 만들어 놓고 이들을수해발생이 예상되는 취약지역 인근에 비축한 후 비상시 현장으로 옮겨서 장비를 사용하여 벽체를 현장여건에 맞도록 조립식으로 설치하고 또한 장비를 사용하여 벽체내부와 주변공간에 토사를 충진하여 설치한다.Emergency prefabricated barrier wall is made by making a number of small tire walls in advance and stocking them near the vulnerable area where it is expected to occur, and then moving to the site in case of emergency and using the equipment to assemble the wall to fit the site conditions. Install the earth and sand in the wall and surrounding space.

본 발명의 또다른 실시예들을 첨부된 도면을 참조하면서 상세히 설명하면 다음과 같다.Another embodiment of the present invention will be described in detail with reference to the accompanying drawings as follows. same.

(1) 긴급 홍수벽(1) emergency flood wall

도7에 도시된 바와같이 하천이나 저수지에서 수위상승으로 범람위기시 설치하는 긴급 홍수벽으로서 제방의 둑마루를 평탄하게 정지한 후 단위벽체를 하천과 평행하게 설치하되 상황이 긴급한 지역에서는 밀착다열벽 방법으로 홍수벽을 설치하고 제내지쪽 벽체 뒤쪽에 토사 등을 쌓는다.As shown in Figure 7 is an emergency flooding wall installed during flooding crisis in rivers or reservoirs as the water level rises, after stopping the embankment of the embankment flat, install the unit wall in parallel with the stream, but in the urgent region close contact This method installs a flood wall and piles up soil on the back of the inner wall of mine.

한편, 도8에 도시된 바와같이 홍수벽 설치시간이 어느정도 여유가 있거나 다열로 쌓기에 단위벽체가 부족할 때는 이격2열벽 방법으로 홍수벽을 설치한다.On the other hand, as shown in Figure 8 when the flood wall installation time to some extent or when the unit wall is insufficient to stack in a multi-row, the flood wall is installed in a spaced two-row method.

홍수벽의 높이는 현장 상황에 맞추어 단위벽체를 1단 또는 2단 수직으로 연결하여 설치한다.The height of flood wall is to be installed by connecting unit wall vertically with 1st stage or 2nd stage according to the site situation.

(2) 붕괴제방 응급복구(2) Emergency recovery of collapsed embankment

도9에 도시된 바와같이 무너진 제방의 바닥을 평탄하게 정지한 후 단위벽체를 제방의 중심위치에서 이격2열벽 방법으로 설치한다.As shown in Fig. 9, after the bottom of the collapsed bank is stopped evenly, the unit wall is installed in a spaced two-row manner at the center of the bank.

제방축조높이에 따라서 하부층에서는 마주선 벽체의 이격거리를 넓게 하고상부로 가면서 단차가 생기도록 이격거리를 좁혀서 설치하여 제방의 안전도를 높힌다.According to the dike construction height, the lower floor increases the separation distance of the facing wall and installs by narrowing the separation distance so as to make a step toward the upper part.

타이어 벽체를 응급복구된 제방을 영구제방으로 사용하고자 할 때는 외부에 토사를 더 덮고 호안공을 피복한다.If the tire wall is to be used as a permanent embankment, cover the soil with additional earthwork and cover the revetment.

(3) 물길 긴급 차단벽(3) waterway emergency barrier

도10에 도시된 바와같이 홍수로 범람시 물길이 흘러서 수로형태가 될 수 있는 도로, 하천, 골짜기 등에 설치하는 물길차단 방재벽으로서 설치지점의 바닥을 평탄하게 정지하고 단위벽체로 물 흐름을 차단할 수 있도록 밀착다열 방법 또는 이격2열벽 방법으로 차단벽을 설치한다.As shown in FIG. 10, as a water barrier blocking wall installed in roads, rivers, valleys, etc., which may be in the form of waterways when flooding is caused by flooding, the floor of the installation site may be stopped evenly and the water flow may be blocked by the unit wall. The barrier wall should be installed by the close multi-row method or the spaced two-row method.

차단벽 좌우공간이 단위벽체로 차단이 어려울 때에는 이곳을 모래포대 등으로 막는다.When the left and right spaces of the barrier wall are difficult to block with unit walls, cover them with sand bags.

차단벽의 높이는 현장상황에 따라서 단위벽체를 1단 또는 2단으로 설치한다.The height of the barrier wall is to be installed in one or two stages depending on the site situation.

(4) 토사 긴급 차단벽(4) earth and sand emergency barriers

도11에 도시된 바와같이 산지, 절개지 등 산사태 발생 우려가 있는 경사지 하부지역이나 산간계곡에 단위벽체를 설치하여 토사를 차단하는 방재벽이나 사방 댐으로서 방재벽의 규모는 발생가능 토사량과 외력의 크기 등을 고려하여 결정한다.As shown in FIG. 11, a unit wall is installed in a lower area of a slope or a mountain valley where there is a risk of landslides such as a mountain or an incision. Determine the size and the like.

설치지점의 바닥을 평탄하게 정지하고 단위벽체를 밀착다열 방법으로 쌓되현장여건에 따라서 단위벽체를 외력이 가해지는 방향에 대하여 종방향 또는 횡방향으로 쌓는다.The floor of the installation site is stopped evenly and the unit walls are stacked in a close multi-row method. Depending on the site conditions, the unit walls are stacked in the longitudinal or transverse direction with respect to the direction of external force.

토사 긴급 차단벽이나 사방댐은 차단벽으로서의 안전도가 크도록 하부는 단위벽체를 넓게 설치하고 상부로 갈수록 단차를 주어 좁게 설치한다.In case of earth and sand emergency barriers or four-sided dams, unit walls are installed at the lower part of the unit so that the safety of the barriers is large.

본 토사 긴급 차단벽은 도로의 절개지 사면에 토석 방지벽으로 사용가능하다.The earth and sand emergency barrier can be used as a soil barrier on the cut slope of the road.

(5) 유실도로 응급복구(5) Emergency Road Recovery

도12 내지 도13에 도시된 바와같이 하천변이나 경사지에 설치된 도로가 홍수로 유실되었을 때 단위 벽체를 옹벽형태로 성토지역에 설치하는 방재벽으로서 바닥을 정지한 후 단위 벽체를 1열벽 방법으로 설치한다.As shown in FIGS. 12 to 13, when a road installed on a riverside or a slope is lost due to a flood, a unit wall is installed in a fill area in the form of a retaining wall, and the unit wall is installed by a one-row wall method after stopping the floor. .

성토높이나 경사도 등 현장여건에 따라서 일체화된 수직벽 또는 계단식 수직벽으로 한다.The vertical wall or stepped vertical wall is to be integrated depending on the site conditions such as fill height and slope.

계단식 수직벽에서는 경사도, 토질 등을 고려하여 보강재를 생략할 수 있다.In the stepped vertical wall, reinforcement may be omitted in consideration of slope, soil, etc.

(6) 유실 교량 응급 복구(6) Lost Bridge Emergency Recovery

도14에 도시된 바와같이 중소규모 하천에 설치된 교량이 홍수로 파괴되었을때 하천 유량이 줄어든 후 단위벽체가 교각 역할을 할 수 있도록 적당한 간격으로 설치하는 방재벽으로서 단위벽체(5)를 밀착2역벽 방법으로 설치하거나 4각형의 이격2열벽 방법으로 설치한다.As shown in Fig. 14, when the bridges installed in the small and medium-sized rivers are destroyed by flooding, the unit wall 5 is closely attached to the unit wall 5 as a disaster prevention wall installed at appropriate intervals so that the unit wall acts as a pier after the stream flow rate is reduced. Install in a square or two-wall spaced apart.

교각의 높이가 높을 때에는 단위벽체(5)를 위로 올려서 수직으로 더 쌓으며 이때 단위벽체간 상하연결은 반드시 로프를 결속하여 유체력으로 단위벽체가 분리되지 않도록 한다.When the height of the pier is high, the unit wall (5) is raised up and stacked further vertically, and the vertical connection between the unit walls must bind the rope so that the unit wall is not separated by the fluid force.

(7) 건설공사 가시설용 벽체(7) Walls for temporary construction work

건설공사 현장에서 가물막이 시설, 물길차단시설, 물저장시설, 저류지, 침사지 등 임시로 설치하는 차수용 가시설의 벽체 축조방법으로서 단위벽체와 비닐시트를 사용하여 밀착다열벽 방법, 이격2열벽 방법으로 차수용 벽체를 설치하거나 성토가 필요한 옹벽시설, 가도 등의 가시설에 1열벽 방법, 이격2열벽 방법으로 벽체를 설치한다.As a wall construction method for temporary temporary installations such as barriers, water barriers, water storage facilities, reservoirs, and settlements at construction sites, the unit walls and vinyl sheets are used to provide a close multi-wall method and spaced two-wall method. Walls should be installed in a single-row method or spaced two-row method in temporary facilities such as retaining walls or fillets.

(8) 제방호안 및 차수벽(8) Protective Measures and Order Walls

도15에 도시된 바와같이 하천이나 저수지의 제방에서 호안이 필요한 비탈면에 부직포(9)를 깔고 단위벽체(5)를 1열벽 방법으로 뉘여서 설치하고 단위벽체내부에 토사나 자갈을 충진하여 호안기능을 갖도록 할 수 있다.As shown in Fig. 15, the nonwoven fabric 9 is laid on the slope of the river or reservoir on the banks of the banks, and the unit walls 5 are installed in a single-row manner, and the soil and gravel are filled in the unit walls. It can be to have.

또한 비탈면에 단위벽체를 수직으로 세우고 벽체내부에 토사를 충진하여 호안을 만들수도 있다.In addition, it is possible to make a revetment by erecting a unit wall vertically on a slope and filling soil inside the wall.

한편, 도16에 도시된 바와같이 투수계수가 큰 하천변 토사로 축조된 제방을 보강하는 방법으로서 제방 앞부분을 절개하거나 새로 축조할 제방의 제체내에 단위벽체를 이용하여 밀착다열벽 방법으로 벽체를 설치하고 벽체사이에 비닐시트를 수직으로 끼우고 벽체내 토사를 충진하여 차수성를 증가시켜서 제방을 보강할 수 있다.On the other hand, as shown in Figure 16 as a method of reinforcing the dike built by the riverbed soil with a high permeability coefficient, the wall is installed by a close multi-wall method using a unit wall in the dike of the dike to cut the front part of the dike or newly built And it is possible to reinforce the levee by inserting the vinyl sheet vertically between the walls and filling the soil in the walls to increase the order.

이상과 같이 본 발명은 상술한 특성의 바람직한 실시예에 한정되지 아니하며 청구범위에서 청구하는 본 발명의 요지에 벗어남이 없이 당해 발명에 속하는 분야에서 통상의 지식을 가진 자라면 누구나 다양한 변경 실시가 가능한 것이다.As described above, the present invention is not limited to the preferred embodiment of the above-described characteristics, and various changes can be made by any person having ordinary skill in the art without departing from the gist of the present invention claimed in the claims. .

이상에서 살펴본 본발명의 효과를 살펴보면Looking at the effects of the present invention discussed above

(1) 단위벽체를 미리 만들어 놓고 장비를 사용하여 조립식으로 설치하므로(1) Since the unit wall is made in advance and is prefabricated using equipment,

신속히 방재벽을 축조할 수 있고You can quickly build a barrier

(2) 초단시간내 방재벽을 축조함으로서 재난을 예방할 수 있으며 재난시에는(2) Disaster prevention can be prevented by building a barrier in a very short time.

피해를 줄일 수 있으며Can reduce damage

(3) 단위벽체가 일정크기의 규모를 가지고 있으며 스스로 자립하며 경량이므(3) The unit wall has a certain size and is self-supporting and lightweight.

로 벽체축조가 용이하고Easy to build walls

(4) 벽체 외부명의 타이어는 충격, 세굴, 부식, 마모로부터 강하며 단위벽체(4) Tires outside the wall are strong against impact, scour, corrosion and abrasion.

를 상호 결속하고 벽체내부에 토사를 충진하고 흡출방지용 부직포를 설Bind to each other, fill the soil inside the wall, and set up the

치함으로써 벽체가 튼튼하며The wall is strong

(5) 벽체의 형태와 규모변경이 용이하므로 각종 용도에 적용할 수 있고(5) It is easy to change the shape and scale of the wall, so it can be applied to various uses.

(6) 차수용 벽체에서 벽체뒷면에 비닐 시트를 수직으로 설치할 수 있으므로(6) Since the vinyl sheet can be installed vertically on the back side of the wall

완벽한 차수가 가능하며Perfect order is possible

(7) 제방 등의 복구시 수직으로 벽체를 형성하므로 토량이 절약되고 현장토(7) Since the wall is formed vertically when the levee is restored, the amount of soil is saved and the soil is

의 적용이 가능하고Is applicable

(8) 타이어의 유연성, 로프의 신장율 및 충진재의 자중에 의하여 벽체의 굴(8) Wall oysters due to the flexibility of the tires, the elongation of the rope and the weight of the filler

요성이 커서 홍수로 지반 함몰시 변형된 지반에 빨리 순응되어 제방의Because of its large nature, it quickly adapts to the deformed ground when the ground is flooded.

기능을 유지하며Maintaining functionality

(9) 복구후 외력증가시 붕괴위험이 적으며 제방붕괴시 단위벽체가 일체화 되(9) There is little risk of collapse when the external force increases after restoration, and unit walls are integrated when the bank collapses.

어 있으며 타어어의 유연성으로 2차 피해를 줄일 수 있고And the flexibility of the other languages can reduce secondary damage

(10) 제방에서 긴급용 벽체를 영구용 벽체로 사용할 수 있으며 이때 제방의(10) An emergency wall can be used as a permanent wall in a levee,

차수기능이 커지며The order function is getting bigger

(11) 단위벽체는 사용 후 충진토사를 제거하여 재사용하므로 반영구적으로(11) The unit wall is semi-permanently because it removes the reclaimed soil after use and reuses it.

사용가능한 효과가 있는 것이다.There is a usable effect.

Claims (6)

비슷한 크기의 폐타이어(1)들을 모아서 일측면부를 절개하고 트레드면을 2개소 이상 소정간격으로 천공하여 구멍(2)을 형성토록한 후 이 폐타이어들을 절개부 위(3)가 위를 향하고 천공구멍(2)이 같은 위치에 오도록 포개어 다수층의 높이로 원통형태로 쌓고 이 원통 다수를 일렬로 붙여서 벽을 만들되 상하좌우에 맞닿은 각 폐타이어들의 천공구멍(2)으로 내구성과 강도가 큰 로프(4)를 8자 형태로 교차 결속하여 일정크기의 소규모 단위벽체(5)로 구성하는 한편, 상기 소규모 단위벽체(5)의 소정위치 상하부에는 장비로 운반이 가능하게 함과 동시에 뒤집기를 할 수 있도록 운반용 고리(6)와 뒤집기용 고리(7)를 형성함을 특징으로하는 폐타이어를 이용한 긴급 조립식 방재벽Collect the waste tires (1) of similar size and cut one side portion, and drill the tread surface at least two places at predetermined intervals to form a hole (2), and then cut the waste tires (3) upwards and drilled them. The holes (2) are stacked in the same position, stacked in a cylindrical shape at the height of a plurality of layers, and a plurality of cylinders are lined up to form a wall. 4) cross-binding in the form of eight characters to form a small unit wall (5) of a predetermined size, while at the same position upper and lower portions of the small unit wall (5) to be transported by the equipment and at the same time to be turned over. Emergency prefabricated disaster prevention wall using waste tires, characterized by forming a carrying ring 6 and a turning ring 7 설치장소의 지반을 평탄하게 정지한 후 바닥에 비닐시트(8)를 길게 깔고 그 위에 비닐시트(8)가 1/3정도 깔리도록 상기 청구항1의 단위벽체(5)를 일렬로 설치한 다음 상기 바닥의 비닐시트(8)로 단위벽체(5) 뒷면을 감싸 올리고 비닐시트(8) 뒤쪽에 단위벽체(5)를 밀착시켜서 2열 또는 3열로 벽체를 설치하는 한편, 상기 단위벽체(5)간 로프(4)로 결속하여 수평연결을 한다음 상기 단위벽체(5)내에 토사 (10)를 충진시켜 이루어짐을 특징으로하는 폐타이어를 이용한 긴급 조립식 방재벽 설치방법After stopping the ground of the installation place flatly, install the vinyl sheet 8 on the floor for a long time, and install the unit walls 5 of the claim 1 in such a way that the vinyl sheet 8 is spread over about 1/3. Wrap the back of the unit wall (5) with the vinyl sheet (8) at the bottom and attach the unit wall (5) to the back of the vinyl sheet (8) to install the wall in two or three rows, while between the unit walls (5) The method of installing an emergency prefabricated disaster prevention wall using waste tires, which is made by binding with a rope 4 to make a horizontal connection and then filling the soil 10 into the unit wall 5. 먼저 설치장소의 지반을 평탄하게 정지하고 제방과 평행하게 상기 청구항1의 단위벽체(5)를 일정한 간격을 띄워서 평행하게 2열로 설치하고 타이어 원통내부와 마주선 타이어 벽체사이에 공간에 토사(10)를 충진하여 방재벽을 만들되 전열에 비닐시트(8)를 깔고 후열에는 부직포(9)를 깐 다음 상기 비닐시트(8)와 부직포(9)위에 단위벽체(5)를 일렬로 붙인 후 맞닿은 단위벽체(5)들의 양쪽 외곽부 맨위쪽과 바로 아래쪽 타이어(1)의 천공구멍(2)으로 로프(4)를 연속 통과시켜 함께 묶어서 이루어짐을 특징으로하는 폐타이어를 이용한 긴급 조립식 방재벽 설치방법First, the ground of the installation site is stopped flat and the unit walls 5 of claim 1 are installed in two rows in parallel with a predetermined interval in parallel to the embankment, and the earth and sand 10 in the space between the inside of the tire cylinder and the facing tire wall. To make a disaster prevention wall, but put a vinyl sheet (8) on the heat transfer and a non-woven fabric (9) on the heat transfer, and then attach the unit walls (5) on the vinyl sheet (8) and the nonwoven fabric (9) in a row, and then contact the unit walls. Emergency prefabricated disaster prevention wall installation method using a waste tire, characterized in that the rope (4) through a continuous through the rope (4) through the top of the outer periphery of the both sides of the (5) and tie together together 바닥 기초를 평탄하게 정지하고 기초바닥에 부직포(9)를 길게 깔고 그 위에 상기 청구항1의 단위벽체(5)를 일렬로 붙여서 설치한 다음 맞닿은 단위벽체들의 양쪽 외곽부 맨위쪽과 바로 아래쪽 타이어의 천공구멍(2)으로 로프(4)를 연속하여 통과시켜서 함께 묶는 한편, 상기 단위벽체(5)내에 토사(10)를 충진시켜 이루어짐을 특징으로하는 폐타이어를 이용한 긴급 조립식 방재벽 설치방법The base of the floor is stopped flat, the nonwoven fabric 9 is laid on the base, and the unit walls 5 of claim 1 are lined up, and then the top and bottom tires of both outer edges of the unit walls are contacted. A method for installing an emergency prefabricated disaster prevention wall using waste tires, which is made by continuously passing the rope 4 through the holes 2 and tying them together, while filling the soil 10 into the unit wall 5. 제3항에 있어서, 상기 마주선 단위벽체(5)들 간에는 벽체 중간 타이어에 천공된 구멍(2)을 이용하여 비닐시트(8)와 부직포(9)에 구멍을 뚫고 타이로프(11)로 상호 단위벽체(5)를 연결하여 벽체가 뒤로 넘어지지 않도록 함을 특징으로하는 폐타이어를 이용한 긴급 조립식 방재벽 설치방법According to claim 3, Between the opposing unit wall (5) using a hole (2) perforated in the middle wall of the wall of the vinyl sheet (8) and the nonwoven fabric (9) by a hole in the tie rope 11 mutually Emergency assembly type disaster prevention wall installation method using a waste tire, characterized in that the wall does not fall back by connecting the unit wall (5) 제4항에 있어서, 상기 단위벽체(5)의 후면에 보강재 로프(12)를 설치하여 뒤채움토사를 충진시킴을 특징으로하는 폐타이어를 이용한 긴급 조립식 방재벽 설치방법5. The method of claim 4, wherein the reinforcement rope 12 is installed on the rear surface of the unit wall 5 to fill the backfill soil. 5.
KR1020020077657A 2002-12-09 2002-12-09 an urgent fender wall of tires and an installation method of that KR20030022753A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020020077657A KR20030022753A (en) 2002-12-09 2002-12-09 an urgent fender wall of tires and an installation method of that

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020020077657A KR20030022753A (en) 2002-12-09 2002-12-09 an urgent fender wall of tires and an installation method of that

Publications (1)

Publication Number Publication Date
KR20030022753A true KR20030022753A (en) 2003-03-17

Family

ID=27729729

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020020077657A KR20030022753A (en) 2002-12-09 2002-12-09 an urgent fender wall of tires and an installation method of that

Country Status (1)

Country Link
KR (1) KR20030022753A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102017113B1 (en) 2018-11-27 2019-09-02 박광명 Objects Internet-based industrial pouch

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR940011743A (en) * 1992-11-25 1994-06-21 유원남 Waste tire assembly wall, manufacturing method and using method
JPH08165659A (en) * 1994-12-13 1996-06-25 Fujita Corp Retaining wall construction method
JPH11256601A (en) * 1998-03-13 1999-09-21 Goto Kensetsu Kk Used tire block containing timber from thinning and construction method of retaining wall and revetment making use thereof
KR20000041500A (en) * 1998-12-22 2000-07-15 최원영 Method of reinforcing earth using waste tire
KR20010000440A (en) * 2000-09-29 2001-01-05 양현승 Retaining wall constructed by used tire block
KR20020023080A (en) * 2000-09-22 2002-03-28 윤여원 Construction Method of Retaining Wall Using Waste Tires

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR940011743A (en) * 1992-11-25 1994-06-21 유원남 Waste tire assembly wall, manufacturing method and using method
JPH08165659A (en) * 1994-12-13 1996-06-25 Fujita Corp Retaining wall construction method
JPH11256601A (en) * 1998-03-13 1999-09-21 Goto Kensetsu Kk Used tire block containing timber from thinning and construction method of retaining wall and revetment making use thereof
KR20000041500A (en) * 1998-12-22 2000-07-15 최원영 Method of reinforcing earth using waste tire
KR20020023080A (en) * 2000-09-22 2002-03-28 윤여원 Construction Method of Retaining Wall Using Waste Tires
KR20010000440A (en) * 2000-09-29 2001-01-05 양현승 Retaining wall constructed by used tire block

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102017113B1 (en) 2018-11-27 2019-09-02 박광명 Objects Internet-based industrial pouch

Similar Documents

Publication Publication Date Title
US4784520A (en) Shoreline protecting system and apparatus
US5697736A (en) Seawalls and shoreline reinforcement systems
US20150050086A1 (en) Methods of and systems for controlling water flow, breaking water waves and reducing surface erosion along rivers, streams, waterways and coastal regions
CN112523233B (en) Construction method of water-through type river-blocking cofferdam
CN213805481U (en) Gabion retaining wall
CN212077787U (en) Water conservancy and hydropower engineering bank wall
CN210946536U (en) Protective structure of small dangerous rock falling stone
RU2228479C1 (en) Method of reinforcement of loose grounds of bases and slopes (versions) and geo-grate for realization of this method
JP3698629B2 (en) Transmission type dam unit and transmission type dam
KR20110046209A (en) Method Of Construction For Scour Prevension And Reinforcement Of Bridge Pier, And Structure Of The Same
KR100245048B1 (en) Reinforced soil structure
JP6676462B2 (en) Embankment reinforcement method
KR20030022753A (en) an urgent fender wall of tires and an installation method of that
CN209816577U (en) Coastal soft soil foundation riverside embankment widening structure
CN209989781U (en) Novel structure of silty-fine sand stratum flood control dam
CN107059888B (en) Reinforcing bar gabion side slope supporting construction
JP4892204B2 (en) How to strengthen disaster prevention
CN105696608B (en) Protect folding method in a kind of steel sheet-pile cofferdam Longkou
TW201016930A (en) Regulation method for river with the function of protecting bridge pier and dike, and with the function of forming sand and stone collecting specific area
US11555284B1 (en) Integrating articulated concrete blocks with gabion/reno cages
CN217325475U (en) Reinforced structure is restoreed to hydraulic retaining wall that collapses
CN214301341U (en) Water drainage channel crossing temporary road on anti-seepage film of garbage pile
CN220352732U (en) Water permeable body structure for protecting river side slope
RU2176700C1 (en) Method for protecting territory from flooding
KR102536278B1 (en) Embankment water stopping structure and the construction method thereof

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application