KR200270234Y1 - construction jack - Google Patents

construction jack Download PDF

Info

Publication number
KR200270234Y1
KR200270234Y1 KR2020010040875U KR20010040875U KR200270234Y1 KR 200270234 Y1 KR200270234 Y1 KR 200270234Y1 KR 2020010040875 U KR2020010040875 U KR 2020010040875U KR 20010040875 U KR20010040875 U KR 20010040875U KR 200270234 Y1 KR200270234 Y1 KR 200270234Y1
Authority
KR
South Korea
Prior art keywords
construction
jack
stiffener
prevent
run
Prior art date
Application number
KR2020010040875U
Other languages
Korean (ko)
Inventor
최갑상
Original Assignee
최갑상
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 최갑상 filed Critical 최갑상
Priority to KR2020010040875U priority Critical patent/KR200270234Y1/en
Application granted granted Critical
Publication of KR200270234Y1 publication Critical patent/KR200270234Y1/en

Links

Abstract

본 고안은 토건용 스티프너 잭에 관한 것으로, 상세하게는 미끄럼 방지구가 형성되 지지판을 간격 조절봉을 통해, 작동되는 스티프너 잭을 형성하여, 뛰장의 에이치 빔과 결합하여 사용할 수 있도록 하여, 뛰장 설치 후 에지치 빔이 받는 진동을 방지하고, 구조물 파손을 예방할 수 있으며, 구조물에 대한 수직, 수평 하중 발생시 안전하게 지지하여, 버팀대와 뛰장 사이 축력작용으로 인한 크리프 변형을 예방하여 주고, 스티프너 잭의 사용에 있어서, 편리하게 결합과 해체가 가능하여 설치를 용이하게 하여, 작업시간을 단축되므로 공사기간을 단축하여, 경제성을 가지는 효과가 있으며, 뛰장 사이에 용접시공을 생략할 수 있어, 에이치 빔의 손실 및 용접시공으로 인한 작업의 불편함을 해소하고, 가스(gas) 작업으로 인한 작업자의 안전성을 보장 받을 수 있도록 고안한 것이다.The present invention relates to a stiffener jack for construction, and in particular, an anti-slip opening is formed, and a support plate is formed through a gap adjusting rod to form a stiffener jack that is operated, so that it can be used in combination with the H-beam of the run, after installation of the runway It can prevent the vibration of the edge beam, prevent the structure breakage, and securely support the vertical and horizontal loads on the structure to prevent the creep deformation caused by the axial force between the brace and the run, and in the use of the stiffener jack It can be easily combined and dismantled, making it easy to install and shortening the working time, thus shortening the construction period, and having economical effect, and eliminating the welding construction between the runes. Eliminate work inconveniences caused by construction and guarantee worker safety due to gas work. It is devised so.

Description

토건용 스티프너 잭{construction jack}Construction stiffener jacks {construction jack}

본 고안은 토건용 스티프너 잭에 관한 것으로, 상세하게는 토목공사에 사용되는 에이치 빔에 결합되어, 횡방향 비틀림을 방지하는 보강재로 사용하는 것이다.The present invention relates to a stiffener jack for civil engineering, and in detail, is coupled to an H beam used in civil engineering, and is used as a reinforcement material to prevent lateral torsion.

지하철공사 및 토목공사의 지하 개착구간에서 굴착된 토사의 역류 및 풍괴를 방지하기 위해, 토사를 지지할 수 있도록 에이치(H) 빔으로서 뛰장을 설치하게 되며, 뛰장 에이치(H) 빔 사이에는 스터럭 잭을 설치하여 사용하고 있으나, 횡성 뛰장에 토압에서 발생된 힘의 응력이 발생되어 뛰장을 밀게 되어, 띠장과 버팀대를 이격시키는 문제점이 있었다.In order to prevent backflow and collapse of earth and sand excavated in underground openings of subway and civil engineering works, a run is installed as an H beam to support the soil, and between sturdy H beams. Although the jack is installed and used, the stress generated in the earth pressure in the transverse run is generated, pushing the run, there is a problem of separating the band and the brace.

상기와 같이 발생하는 문제점을 해결하기 위해, 띠장과 에이치 빔의 이격을 방지할 수 있도록 하는 고안이 안출되어 있으며, 띠장과 에이치 빔을 고정하여 주는 수단도 안출되어 있다.In order to solve the problems occurring as described above, the devised to prevent the separation of the strip and the H-beam has been devised, a means for fixing the strip and the H-beam has been devised.

그러나 종래의 고안들은 버팀대 뛰장을 고정하여 수단으로 사용할 수 있으나, 버팀대의 하중을 감당해야 하는 에이치 빔에 대하여는, 에이치 빔에 가해지는 응력으로 인해, 에이치 빔에 휨이 발생하거나 에이치 빔이 굴곡되는 문제점을 해결할 수 없었다.However, the conventional designs can be used as a means of fixing the brace jump, but for the H beam that must bear the load of the brace, due to the stress applied to the H beam, the H-beam bends or the H-beam is bent Couldn't solve it.

이러한 문제점은 에이치(H) 빔에 가해지는 응력으로 인해, 에이치 빔의 면이 굴곡되는 현상이 발생하여, 결과적으로는 띠장을 버팀대에서 이격시켜, 에이치 빔이 버팀대를 지지하지 못하게 되어, 굴착된 면이나 적재된 토사가 붕괴는 원인이 되는 것이다.This problem is caused by the stress applied to the H (H) beam, the surface of the H-beam bends, resulting in the separation of the band from the brace, the H-beam does not support the brace, the surface is excavated However, the loaded soil will cause collapse.

상기의 문제점을 해결하기 위해 종래의 방법은 뛰장으로 사용되는 에이치(H) 빔 상. 하부에 철판으로 절단된 스티프너를 용접시공하여 설치하므로, 힘의 발생 지점에 밀착시켜, 에이치 빔의 강도를 증대하는 것으로, 에이치 빔이 받는 응력을 해소하도록 하고 있으나, 이러한 시공방법은 매우 복잡하고 자재의 낭비를 초래하는 문제점이 있는 것이다.In order to solve the above problems, the conventional method is used on the H (H) beam. Since the stiffener cut by the steel plate is installed at the lower part, it is installed in close contact with the force generating point to increase the strength of the H beam, and the stress of the H beam is solved. There is a problem that causes waste.

이러한 에이치 빔을 이용한 스티프너의 시공방법은, 시공비가 상승하고 요인이 되며, 절단된 에이치 빔을 뛰장으로 사용되는 에이치 빔에 결합을 위해 용접시공을 함으로서 시공기간의 소요 및 용접시공시 가스 발생을 유발하여 환경파괴 및 가스로 인한 안전사고의 위험이 있으며, 시공 후 철거시에도 뛰장으로 사용되는 에이치 빔에 결합된 스티프너로 사용되는 에이치 빔을 해체하기 위해서는 결합된 스티프너 에이치 빔을 절단해야 하는 단점을 갖고 있으므로, 인건비의 상승요인, 자재손실, 폐자재 유발을 초래하는 문제점이 있는 것이다.The construction method of the stiffener using the H beam, the construction cost increases and becomes a factor, and by welding the bonded H-beam to the H-beam that is used as a jumping, causing the construction period and gas generation during welding construction There is a risk of safety accidents due to environmental destruction and gas, and the combined stiffener H-beams must be cut in order to dismantle the H-beams used as the stiffeners coupled to the H-beams, which are used as runners, even after dismantling. Therefore, there is a problem that causes a rise in labor costs, material loss, waste materials.

본 고안은 상기와 같은 문제점을 감안하여, 미끄럼 방지구가 형성되 지지판을 간격 조절봉을 통해, 작동되는 스티프너 잭을 형성하여, 뛰장의 에이치 빔과 결합하여 사용할 수 있도록 하여, 버팀대와 뛰장 사이의 축력작용으로 인한, 크리프 변형을 예방할 수 있도록 한 것으로, 첨부된 도면에 상세하게 설명하면 다음과 같다.The present invention, in view of the above problems, by forming a stiffener jack to operate the support plate through the gap adjusting rod, the anti-slip is formed, so that it can be used in combination with the H-beam of the run, the axial force between the brace and the run In order to prevent creep deformation due to the action, it will be described in detail in the accompanying drawings as follows.

도1은 본 고안의 분리 사시도1 is an exploded perspective view of the present invention

도2는 본 고안의 사시도2 is a perspective view of the present invention

도3은 본 고안의 작동 상태도Figure 3 is an operating state of the present invention

도4는 본 고안의 사용 상태도4 is a state diagram used in the present invention

도면의 주요부분에 대한 부분의 설명Description of the parts of the main parts of the drawings

1,1';미끄럼 방지구 2,2';나사부 3,3';간격 조절봉 내입구1,1 '; Non-slip 2,2'; Screw part 3,3 '; Spacing adjustment rod inlet

4,4';지지판 5,5';볼트 내입공 6,6';밑판4,4 '; Support plate 5, 5'; Bolt hole 6,6 '; Bottom plate

7;고정볼트 8,8';나사부 9;간격 조절봉 10;스티프너 잭7; Fixing bolt 8,8 '; Screw section 9; Spacing adjustment rod 10; Stiffener jack

미끄럼 방지구(1)(1')와 양방향 나사부(2)(2')가 형성된 간격 조절봉 내입구(3)(3')가 일체로 형성된 지지판(4)(4')에, 볼트 내입공(5)(5')이 형성되 밑판(6)(6')을 형성하여, 밑판(6)(6')의 볼트 내입공(5)(5')이 연통될 수 있도록 결합한 후, 고정볼트(7)와 양방향 나사부(8)(8')가 양측으로 형성된 간격 조절봉(9)으로 결합하여서 된 것이다.On the support plate 4, 4 'formed integrally with the gap adjusting rod inlet 3, 3' formed with the anti-slip 1, 1 'and the bidirectional threaded portion 2, 2', A hole 5, 5 'is formed to form a bottom plate 6, 6', and the bolt inlets 5, 5 'of the bottom plate 6, 6' are coupled so as to communicate with each other, and then fixed. The bolt 7 and the bidirectional threaded part 8, 8 'are combined by the gap adjusting rod 9 formed at both sides.

이와 같이 간격 조절봉(9)을 통해 지지판의(4)(4') 간격조절으로 사용되는 스티프너 잭(10)과 뛰장으로 사용되는 에이치 빔(11)의 결합을 다음과 같다.As described above, the coupling between the stiffener jack 10 used as the spacing and the h beam 11 used as the run through the gap adjusting rod 9 to adjust the spacing of the support plates 4 and 4 'is as follows.

본 고안은 도4에 표시된 바와 같이 뛰장 에이치 빔(11) 사이에 삽입되어 사용되는 것으로, 양측으로 형성된 지지판(4)(4')과 밑판(6)(6')을 에이치 빔(11)의 내부 면에 밀차되도록 내입한 상태에서, 간격 조절봉(9)에 형성된 넛트(12)를 이용하여 간격 조절봉(9)을 회전하여 주면, 양방향으로 형성된 나사부(8)(8')에 치합된 지지판(4)(4')의 양방향 나사부(2)(2')에 의해 지지판(4)(4')이 간격이 멀어지게 되어, 지지판(4)(4')이 에이치 빔(11)의 면에 완전히 밀착시켜, 에이치 빔(11)에 스티프너 잭(10)을 결합하는 것이다.The present invention is inserted and used between the jumping H beam 11, as shown in Figure 4, the support plate (4) (4 ') and the bottom plate (6) 6' formed on both sides of the H beam 11 When the gap adjusting rod 9 is rotated using the nut 12 formed on the gap adjusting rod 9 in a state in which the inner surface is pushed inwardly, it is fitted to the threaded portions 8 and 8 'formed in both directions. The bidirectional threaded portions 2 and 2 'of the support plates 4 and 4' cause the support plates 4 and 4 'to be spaced apart, so that the support plates 4 and 4' In close contact with the surface, the stiffener jack 10 is coupled to the H beam 11.

상기와 같은 방법으로 스티프너 잭(10)의 지지판(4)(4')이 에이침 빔(11)에 밀착될 때에, 지지판(4)(4')에 형성된 미끄럼 방지구(1)(1')는 스티프너 잭(10)을 에치이 빔(11)에 단단히 고정시키는 기능을 하여, 스티프너 잭(10)이 에이치 빔(11)에서 이탈되는 것을 방지할 수 있도록 한 것이다.When the support plates 4 and 4 'of the stiffener jack 10 are in close contact with the aid beam 11 in the above manner, the anti-slip tool 1 and 1' formed on the support plates 4 and 4 '. ) Serves to secure the stiffener jack 10 to the etch beam 11 to prevent the stiffener jack 10 from being separated from the H beam 11.

본 고안에서 밑판(6)(6')의 볼트 내입공(5)(5')은 양측으로 결합되는 밀판(6)(6')의 간격을, 일정간격으로 유격을 가질 수 있도록 타원으로 형성된 것이며, 간격 조절봉(9)과 지지판(4)(4')에 형성된 나사부(2)(2')(8)(8')는 양방향으로 형성되어, 간격 조절봉(9)의 회전방향으로 따라 서로 대향되게 움직일 수 있도록 한 것이다.In the present invention, the bolt inlets 5 and 5 'of the bottom plate 6 and 6' are formed in an ellipse so as to have a gap at a predetermined interval between the six plates 6 and 6 'coupled to both sides. And the threaded portions 2, 2 ', 8, 8' formed on the gap adjusting rod 9 and the support plates 4, 4 'are formed in both directions in the direction of rotation of the gap adjusting rod 9; So that they can move opposite each other.

이러한 양방향 나사부(2)(2')(4)(4')는 간격 조절봉(9)의 회전을 통해 지지판(4)(4')의 간격이 이격되거나 근접할 수 있도록 한 것으로, 에이치 빔(11)의 외형 상태에 따라 지지판(4)(4')의 간격을 조절하여 사용할 수 있도록 하는 것이다.The two-way threaded portion 2, 2 ', 4, 4' is to allow the spacing of the support plates 4, 4 'to be spaced apart or close by the rotation of the gap adjusting rod 9, H beam According to the appearance of the (11) it is to be used to adjust the interval of the support plate (4) (4 ').

상기에서 상세하게 설명한 바와 같이, 나사부(2)(2')(8)(8')가 형성된 간격 조절봉(9)에 의해 간격이 조절되면서, 에이치 빔(11)에 결합되는 스티프너 잭(10)의 사용은, 일반 토목공사, 지하철 공사 개착구간에 뛰장으로 사용되는 에이치 빔(11) 사이에 삽입하여 결합하므로, 뛰장의 설치 후 에지치 빔(11)이 받는 진동을 방지하므로, 구조물 파손을 예방할 수 있으며, 구조물에 대한 수직, 수평 하중 발생시 안전하게 지지하여, 버팀대와 뛰장 사이 축력작용으로 인한 크리프 변형을 예방하여 주며, 편리하게 결합과 해체가 가능하여 설치를 용이하게 하여, 작업시간을 단축되므로 공사기간을 단축하여, 경제성을 가지는 효과가 있으며, 뛰장 사이에 용접시공을 생략할 수 있어, 에이치 빔의 손실 및 용접시공으로 인한 작업의 불편함을 해소하고, 가스(gas) 작업으로 인한 작업자의 안전성을 보장 받을 수 있는 효과가 있는 것이다.As described in detail above, the stiffener jack 10 is coupled to the H beam 11 while the spacing is adjusted by the spacing adjusting rod 9 on which the screw portions 2, 2 ', 8, 8' are formed. ) Is inserted into and coupled between H beams 11 used as a runway in general civil construction and subway construction opening sections, thus preventing damage to the edge beam 11 after installation of the runway. It can be prevented and securely supported when vertical and horizontal loads occur on the structure, preventing creep deformation due to axial force between braces and runners, and can be easily combined and dismantled to facilitate installation and shorten working time. The construction period is shortened and it has the effect of economical efficiency, and the welding construction can be omitted between the runes, eliminating the inconvenience of work due to the loss of the H-beam and the welding construction, and the gas work. It is effective to ensure the safety of workers.

Claims (1)

미끄럼 방지구(1)(1')와 나사부(2)(2')가 형성된 간격 조절봉 내입구(3)(3')가 일체로 형성된 지지판(4)(4')에, 볼트 내입공(5)(5')이 형성되 밑판(6)(6')을 형성하여, 밑판(6)(6')의 볼트 내입공(5)(5')이 연통될 수 있도록 결합한 후, 고정볼트(7)와 양방향 나사부(8)(8')가 양측으로 형성된 간격 조절봉(9)으로 결합하여서 된 것을 특징으로 하는 스티프너 잭.Bolt-in hole on support plate 4, 4 'formed integrally with gap adjustment rod inlet 3, 3' with non-slip opening 1, 1 'and threaded portion 2, 2'. (5) (5 ') is formed to form the bottom plate (6) (6'), the bolt inlets (5) (5 ') of the bottom plate (6) (6') to be connected so as to communicate, and then fixed bolt A stiffener jack, characterized in that (7) and the bidirectional threaded portion (8) (8 ') is combined by the gap adjusting rod (9) formed on both sides.
KR2020010040875U 2001-12-29 2001-12-29 construction jack KR200270234Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020010040875U KR200270234Y1 (en) 2001-12-29 2001-12-29 construction jack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020010040875U KR200270234Y1 (en) 2001-12-29 2001-12-29 construction jack

Publications (1)

Publication Number Publication Date
KR200270234Y1 true KR200270234Y1 (en) 2002-03-29

Family

ID=73072200

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020010040875U KR200270234Y1 (en) 2001-12-29 2001-12-29 construction jack

Country Status (1)

Country Link
KR (1) KR200270234Y1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101498343B1 (en) * 2012-11-19 2015-03-03 (주)대성스틸랜드 Ground anchor head fixing syatem
KR101498121B1 (en) * 2012-11-16 2015-03-04 노연식 Buckling restrained stiffener using for retaining wall wale
KR101652682B1 (en) * 2016-01-13 2016-08-31 서경식 H-piece
KR102191745B1 (en) * 2020-06-11 2020-12-16 주식회사 에스씨티앤씨 H-beam reinforcement for earth-walled
KR20210044531A (en) * 2019-10-15 2021-04-23 주식회사 대한 H-beam reinforcement with corrosion prevention structure
KR20220048587A (en) 2020-10-13 2022-04-20 한국산업안전보건공단 Multi-stiffener for reinforcing shearing force of h-beam

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101498121B1 (en) * 2012-11-16 2015-03-04 노연식 Buckling restrained stiffener using for retaining wall wale
KR101498343B1 (en) * 2012-11-19 2015-03-03 (주)대성스틸랜드 Ground anchor head fixing syatem
KR101652682B1 (en) * 2016-01-13 2016-08-31 서경식 H-piece
KR20210044531A (en) * 2019-10-15 2021-04-23 주식회사 대한 H-beam reinforcement with corrosion prevention structure
KR102260395B1 (en) * 2019-10-15 2021-06-03 (주)대한 H-beam reinforcement with corrosion prevention structure
KR102191745B1 (en) * 2020-06-11 2020-12-16 주식회사 에스씨티앤씨 H-beam reinforcement for earth-walled
KR20220048587A (en) 2020-10-13 2022-04-20 한국산업안전보건공단 Multi-stiffener for reinforcing shearing force of h-beam

Similar Documents

Publication Publication Date Title
US7537417B2 (en) Corner connection for temporary shoring
KR100851062B1 (en) Magnetic attached jack stiffener
KR20120140318A (en) Variable stiffner jack for h-beam
KR20190115235A (en) Connecting Structure of Steel Pipe Strut
US6984092B1 (en) Corner connection for temporary shoring
KR100916546B1 (en) Underground temporary structure and constructing method thereof
KR101337001B1 (en) Connector assembly for steel pipe strut
KR200270234Y1 (en) construction jack
KR200393178Y1 (en) steut for engineering work
KR102080492B1 (en) Construction method for cantilever in steel composite girder bridge
JP7009724B2 (en) Column-beam frame repair method and repair column-beam frame
KR100714434B1 (en) A bracing for reinforcing support
KR100648409B1 (en) A method of construction for temporary retaining wall
KR100476842B1 (en) soldier beam installed according to axial force in excavating work
KR100646178B1 (en) temporary facilities using steel pipe
KR200393179Y1 (en) steut for engineering work
KR100534079B1 (en) Construction method of strut
KR101958768B1 (en) Structure for Constructing the Lagging Board using Strut Beam having Reinforcement Bar
KR20190012433A (en) Equipment for fixing struts of construction system support
KR101307821B1 (en) Underground soil retaining wall structure for activity space securement
KR200436405Y1 (en) Structure for constructing bracing for reinforcing support
KR200494035Y1 (en) Corner shoe jacks for stiffening steel
KR100657654B1 (en) H-type pile having a plurality of anchor-throughholes
KR200362177Y1 (en) Reinforcement structure for H-beam column
KR102554428B1 (en) Prestress wale structure for retaining wall and its construction method

Legal Events

Date Code Title Description
REGI Registration of establishment
T201 Request for technology evaluation of utility model
T701 Written decision to grant on technology evaluation
FPAY Annual fee payment

Payment date: 20110315

Year of fee payment: 10

EXPY Expiration of term