KR200216493Y1 - The duct supporting equipment - Google Patents

The duct supporting equipment Download PDF

Info

Publication number
KR200216493Y1
KR200216493Y1 KR2020000027451U KR20000027451U KR200216493Y1 KR 200216493 Y1 KR200216493 Y1 KR 200216493Y1 KR 2020000027451 U KR2020000027451 U KR 2020000027451U KR 20000027451 U KR20000027451 U KR 20000027451U KR 200216493 Y1 KR200216493 Y1 KR 200216493Y1
Authority
KR
South Korea
Prior art keywords
pipe
concrete
formwork
tube
design
Prior art date
Application number
KR2020000027451U
Other languages
Korean (ko)
Inventor
김우진
Original Assignee
김우진
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김우진 filed Critical 김우진
Priority to KR2020000027451U priority Critical patent/KR200216493Y1/en
Application granted granted Critical
Publication of KR200216493Y1 publication Critical patent/KR200216493Y1/en

Links

Abstract

이 고안은 관 부설라인상의 기층(11) 위에 관을 기초콘크리트 두께(t)만큼 부상시키기 위한 관 부상체(1)를 배열하고, 관 부상체(1)에 관 이음단(15a)을 안착시켜 관을 기층(11)위에 기초콘크리트 두께(t)만큼 부상시켜 배열하고, 공간부(3)에서 관의 이음부에 이음칼라(9)를 설치하고, 부상시킨 관의 좌우에 거푸집을 조립하고, 거푸집 내에 콘크리트를 타설하여 일체형 콘크리트가(10) 관의 저면과 측면을 지지하게 하며, 콘크리트 양생 후 거푸집을 해체하는 과정으로 구성되는 관 가설 지지체에 관한 고안이다. 이 고안에 의하면 거푸집 조립인력과 콘크리트 타설 인력과 콘크리트 타설 장비를 각각 1회 투입하는 것으로 관의 부설을 완료함으로써 공기를 단축하고, 숙련공이 아니더라도 거푸집을 조립할 수 있고, 거푸집 조립을 정확히 할 수 있고, 거푸집 조립시의 부자재 비용을 줄이고, 거푸집의 순환사이클을 단축하고, 기초콘크리트와 측면콘크리트를 일체화되어 하수의 누수를 보다 감소시키고, 제 위치에 맞게 정확하게 관을 부설할 수 있다.This design arranges a tube floating body (1) for floating the tube by the base concrete thickness (t) on the base layer (11) on the pipe laying line, and seats the pipe joint (15a) on the tube floating body (1). Arrange the tubes by floating them on the base layer 11 by the basis concrete thickness (t), install the joint collars 9 at the joints of the tubes in the space 3, and assemble the formwork on the left and right sides of the tubes. The concrete is placed in the formwork to support the bottom and side of the integrated concrete (10) tube, it is a design for a pipe temporary support consisting of the process of dismantling the formwork after concrete curing. According to this design, it is possible to shorten the air by completing the laying of the pipe by inputting the form assembly manpower, concrete placing manpower and concrete placing equipment once, and to assemble formwork even without skilled workers, and to assemble formwork accurately, It is possible to reduce the cost of subsidiary materials when assembling formwork, shorten the circulation cycle of formwork, integrate the foundation concrete and the side concrete, reduce the leakage of sewage, and lay the pipe correctly in place.

Description

관 가설장치 { The duct supporting equipment }Pipe construction device {The duct supporting equipment}

이 고안은 관 가설장치에 관한 고안이다. 이 고안에서 관이라 함은 하수용, 빗물 배수용 흄관(원심력 철근콘크리트관) 등 지하에 매설되는 관으로서 표1의 관을 포함한다.This design is a design related to the pipe construction device. In this design, the term "pipe" includes pipes of Table 1, which are buried underground, such as sewage pipes for sewage and rainwater drainage (centrifugal reinforced concrete pipes).

<표 1>TABLE 1

표2는 현행 철도용 관 부설 M당 단가표이다. 이 단가표는 국내 관급 시공 시방서의 관 부설 단계 및 단가와 대체로 같다.Table 2 shows the unit cost table per M for existing railway pipes. This unit price chart is generally the same as the level of pipe installation and unit price in the domestic government construction specification.

<표 2>TABLE 2

종래의 관 부설 시공 방법을 도1 (A),(B)를 인용하여 설명하면 다음과 같다.The conventional pipe laying method will be described with reference to FIGS. 1 (A) and (B) as follows.

먼저 관 부설라인을 따라 지반을 굴착하고 막돌과 잔돌로 관 부설 구배에 맞추어 기층(11)을 조성한 후 기층 위에 기초콘크리트(12)와 관 측면콘크리트(13)를 2단계로 타설한다. 1차 기초콘크리트(12)는 거푸집(14)을 막돌 기층(11)위에 조립한 후 상부가 평평하게 타설한다. 거푸집 조립은 설계상의 기초콘크리트(12)라인 양변으로 거푸집을 이어 세우고 거푸집 내측과 외측에 거푸집 버팀을 세운다. 조립된 거푸집 내에 기초콘크리트(12)를 타설 하고 어느 정도 양생되면 거푸집(14)의 내측 버팀을 제거하고 흄관(15)을 배열한다. 흄관(15)의 배열은 기초콘크리트(12)위에 흄관(15)을 굴려 넣어 늘어놓으면서 흄관(15)의 양단 이음부를 좌우로 이동시켜 부설 라인에 맞추고 또한 높이를 조절하여 기울기를 정렬한다. 라인과 높이 조절에 지렛대 곡괭이 등 수동 공구를 사용한다. 흄관(15)이 배열되면 흄관(15)을 중심으로 조립된 거푸집 버팀을 정렬하거나 보강하고 흄관(15) 양편에 측면콘크리트(13)를 타설한다. 측면콘크리트(13)가 어느 정도 양생되면 거푸집을 해체하여 회수하고 흄관 이음부에 관이음 모르터(16)를 시공한 다음 검사를 끝내고 매설한다. 또한 부설되는 관이 도1(C)와 같이 두줄 이상인 경우 관과 관 사이에 속메우기 콘크리트(17)를 타설한다.First, the ground is excavated along the pipe laying line, and the base layer 11 is formed in accordance with the pipe laying gradient with the makdol and the remnants, and then the foundation concrete 12 and the tube side concrete 13 are poured on the base layer in two steps. The primary foundation concrete 12 is formed by placing the formwork 14 on the membrane base 11, and the top is poured flat. Formwork assembly forms the formwork on both sides of the basic concrete line (12) in the design and forms the formwork on the inside and outside of the formwork. Placing the foundation concrete 12 in the assembled form and curing to some extent, remove the inner brace of the form 14 and arrange the fume pipe 15. The arrangement of the fume pipe 15 is arranged by rolling the fume pipe 15 on the foundation concrete 12 to move the joints of both ends of the fume pipe 15 to the left and right to the laying line, and also adjust the height to align the slope. Use manual tools such as levers and pickaxes to adjust the line and height. When the fume pipe 15 is arranged, align or reinforce the mold support assembled around the fume pipe 15 and pour the side concrete 13 on both sides of the fume pipe 15. When the side concrete 13 is cured to some extent, the formwork is dismantled and recovered, and the pipe joint mortar 16 is constructed in the fume pipe joint, and then the inspection is completed and buried. In addition, when the pipe to be laid is more than two lines as shown in Figure 1 (C) is poured concrete 17 between the pipe and the pipe.

도2의 콘크리트관은 관주면의 일부에 평면부(15b)를 형성한 관이다. 도2의 관은 주로 현장 제작 콘크리트관으로서 제작과 시공이 불편하지만 관 측면콘크리트 타설시 기초콘크리트(12)와 관(15)의 사이에 공간부를 남기지 않고 충진되는 이점이 있다. 도2의 관의 부설 시공법은 도1, 도2에서 설명된 관의 부설 시공방법과 같다.The concrete pipe of FIG. 2 is a pipe in which a flat portion 15b is formed on a part of the pipe circumferential surface. The pipe of FIG. 2 is mainly inconvenient to manufacture and construct as a concrete produced in the field, but there is an advantage in that it is filled without leaving a space between the base concrete 12 and the pipe 15 when the concrete is placed on the side of the pipe. The installation method of the pipe of FIG. 2 is the same as the installation method of the pipe demonstrated in FIG.

위에서 살펴본 관 부설 시공법은 표2의 단가표에 나타난 바와같이 기초콘크리트와 관 측면콘크리트를 2차에 걸처 타설하는 관 부설시공법으로서, 완성된 관 부설 구축물을 종단적으로 관찰할 때 두 콘크리트 층 사이에 시공이음이 생기고, 기초콘크리트와 흄관 사이에도 콘크리트의 미 충진 공간부가 발생하는 관 부설 시공법이고 동시에 아래와 같이 공정관리가 불합리한 시공법인 것이다.The pipe laying method described above is a pipe laying method for placing foundation concrete and pipe side concrete over a secondary stage, as shown in the unit price table of Table 2, and it is a joint between two concrete layers when longitudinally observing the completed pipe laying structure. This is the construction method of pipe laying where the unfilled space part of concrete is generated between the foundation concrete and the fume pipe, and at the same time, the process management is unreasonable construction method as follows.

즉, 종래의 관 부설 시공법은 기초콘크리트와 관 측면콘크리트를 2단계로 타설 하게 됨으로써, 공기가 길어지고, 거푸집 조립인력과 콘크리트 타설 인력과, 콘크리트 타설 장비를 각각 2차에 걸처 투입하게 되고, 동시에 거푸집 조립시의 부자재 비용이 커지고, 숙련공에의 해 거푸집이 조립되며, 거푸집의 순환사이클이 커지므로 관 부설비용이 증가되는 것이다.In other words, in the conventional pipe laying method, the foundation concrete and the pipe side concrete are cast in two stages, and the air becomes longer, and the form assembly manpower, the concrete placing manpower, and the concrete placing equipment are put into the second stage, respectively. The cost of subsidiary materials during assembly of the formwork increases, the formwork is assembled by skilled workers, and the circulation cycle of the formwork increases, thus increasing the use of pipe fittings.

이 고안의 목적은 기층 상부에 관을 가설 상태로 배열하고 기초콘크리트 부분과 측면콘크리트 부분을 일체로 타설 할 수 있게 하는 관 가설장치를 제공함에 있다.The object of the present invention is to provide a pipe construction apparatus for arranging pipes on a substrate base and placing the foundation concrete parts and side concrete parts integrally.

더 나아가 이 고안은 기초콘크리트 부분과 측면콘크리트 부분 사이에 수평 시공이음이 생기지 아니하게 함은 물론 공사기간을 단축하고, 투입인력을 감소하고, 숙련공이 아니더라도 거푸집을 조립할 수 있고, 콘크리트 타설시 편압이 발생되지 않고, 공사장비의 이용 효율을 높이고, 공사자재를 절약하며, 거푸집 조립시의 부자재 비용을 줄이고, 거푸집의 순환사이클을 단축하고, 더 나아가 수평 시공이음이 없는 콘크리트로 관을 지지하여 누수율을 감소시키며, 제 위치에 맞게 관을 정확하게 관을 부설할 수 있게 하는 관 가설장치를 제공하고자 하는 것이다.Furthermore, this design not only eliminates horizontal construction joints between the foundation concrete and side concrete parts, but also shortens the construction period, reduces the manpower, and assembles the formwork even if the worker is not skilled. Improves the utilization efficiency of construction equipment, saves construction materials, reduces the cost of subsidiary materials when assembling formwork, reduces the circulation cycle of formwork, and further supports the pipe with concrete without horizontal construction joints to improve the leak rate. It is to provide a pipe hypothesis to reduce, and to allow the pipe to be placed accurately in place.

도1(A),(B),(C)는 종래 흄관의 시공도1 (A), (B), (C) is a construction diagram of a conventional fume pipe

도2(A),(B)는 종래 일주 평면 콘크리트관의 시공도Figure 2 (A), (B) is a construction diagram of a conventional one-round flat concrete pipe

도3은 서포팅블록 세트의 사사도3 is a perspective view of a supporting block set;

도4(A),(B)는 도3 블록에 시공상태도Figure 4 (A), (B) is a construction state diagram in Figure 3 block

도5(A),(B)는 다른 실시예 서포팅 블록에 의한 시공상태도Figure 5 (A), (B) is a construction state by the supporting block of another embodiment

도6은 도3 관 부상체를 사용하는 경우 거푸집 조립 상태도Figure 6 is a form assembly state when using the Figure 3 pipe floating body

<도면 주요 부호의 설명><Description of Drawing Major Symbols>

1:관 부상체 3:공간부 9:이음칼라 15:관1: Tube Floating Body 3: Space 9: Joint Color 15: Tube

이 고안을 첨부도면에 따라서 상세하게 설명하면 다음과 같다.This invention is described in detail according to the accompanying drawings as follows.

도3은 관 부상체(1)로서 콘크리트 거푸집 연결요소 예로서 앵커(a)를 포함하고 동시에 서포팅블록(g)으로 구성한 이 고안 관 가설장치의 실시 예이다.FIG. 3 is an embodiment of this design pipe placing apparatus including an anchor (a) as a concrete formwork connecting element (1) as a pipe floating body (1) and simultaneously comprising a supporting block (g).

도3에서 관의 양단 이음단을 안착시켜 관을 기초콘크리트 두께(t) 만큼 기층 위로 부상시키는 콘크리트 서포팅블록(g)과 지지블록(i)으로 관 부상체(1)를 구성한다. 기층위(11)에 서포팅블록을 배열 할 때 대응된 서포팅블록(g)의 사이에 간격을 두어 이음칼라 삽입 공간부(3)를 구성한다. 관 지지용 테이퍼(h)를 형성한 지지블록(i)을 서포팅블록(g)의 좌우에 배열하여 관 지지체(5)를 구성한다.In FIG. 3, the pipe floating body 1 is composed of a concrete supporting block g and a supporting block i that mount the joints at both ends of the pipe to float the pipe up the base by the thickness t of the base concrete. When arranging the supporting blocks on the base layer 11, a space between the corresponding supporting blocks g is provided to form the joint color insertion space 3. A support block (i) having a taper (h) for pipe support is arranged on the left and right sides of the supporting block (g) to form a pipe support (5).

서포팅블록(g)과 지지블록(i)의 상면을 원호 곡면으로 구성하여 부상되는 관의 안정을 도모한다.The upper surface of the supporting block (g) and the support block (i) is composed of an arc curved surface to stabilize the floating pipe.

도4(A),(B)는 도3 관 부상체의 시공 상태도이다. 두개의 서포팅블록(g) 상부에 관(15)의 대응하는 이음단을 안착하고 있으며, 칼라(9)는 공간부(3)에서 관이음부를 덮고 있다. 또한 철선(j)으로 서포팅블록(g)을 묶어 테이퍼(h)가 관의 저부 양측에 밀착됨으로써 가설된 관은 지극히 안정된 상태가 되었다. 관이 가설되면 거푸집(14)을 조립하고 기초콘크리트 부분과 측면콘크리트 부분이 일체화되게 콘크리트(10)를 타설 한다.4 (A) and 4 (B) show construction states of the pipe floating body of FIG. 3. A corresponding joint end of the tube 15 is seated on top of the two supporting blocks g, and the collar 9 covers the tube joint in the space 3. In addition, the supporting pipe g was bundled with the iron wire j, and the taper h was brought into close contact with both sides of the bottom of the pipe, so that the hypothesized pipe became extremely stable. When the pipe is installed, the mold 14 is assembled and the concrete 10 is poured so that the foundation concrete portion and the side concrete portion are integrated.

도5는 단른 실시예로서 서포팅블록과 지지블록이 일체화된 타입의 관 부상체(1)이다.FIG. 5 is a tube floating body 1 of the type in which the supporting block and the support block are integrated in a single embodiment.

도5의 관부상체(1)는 콘크리트 거푸집 연결요소로서 예컨데 결속 철선(j)이나 앵커(a)를 포함하고 동시에 관(15)의 양단 이음단을 안착시켜 관(15)을 기초콘크리트 두께(t) 만큼 기층 위로 부상시키는 콘크리트 서포팅블록(m)과 그 양단의 지지블록(n)으로 관 부상체(1)를 구성하고, 기층(11)위에 관 부상체(1)를 배열 할 때 두 부상체(1)의 서포팅블록(m) 사이에 간격을 두어 이음칼라 삽입 공간부(3)를 구성하고, 양쪽의 지지블록(n)에 조절간격(p)을 유지하도록 대응하는 관 지지용 테이퍼(o)를 형성함으로써 관 지지체(5)를 구성한다.The tubular superstructure 1 of FIG. 5 includes, for example, a binding wire j or an anchor a as a concrete formwork connecting element, and at the same time seats the two ends of the pipe 15 to form a foundation concrete thickness t. When the tube floating body (1) is composed of the concrete supporting block (m) and the supporting block (n) at both ends, and the tube floating body (1) is arranged on the base (11), the two floating bodies Pipe support taper (o) corresponding to the spaced between the supporting blocks (m) of (1) to form the joint collar insertion space (3) and to maintain the adjustment interval (p) on both support blocks (n) The pipe support 5 is formed by forming ().

도5의 관 부상체 시공은 대응하는 서포팅블록(m)의 상부에 관(15)의 대응하는 이음단을 안착한다. 칼라(9)는 공간부(3)에서 관이음부를 덮고 있다. 관을 라인에 따라 정렬할 때 서포팅블록(m) 좌우에서 이동시키고 관 좌우의 조절간격(p)에 막돌 등 지지체(q)를 끼워 관을 고정한 다음 거푸집(14)을 조립하고 거푸집 내에 기초콘크리트 부분과 측면콘크리트 부분이 일체화되는 콘크리트를 타설한다.The tube floatation construction of FIG. 5 seats the corresponding joint end of the tube 15 on top of the corresponding supporting block m. The collar 9 covers the pipe joint in the space 3. When arranging the tube along the line, move the support block (m) from left and right, and fix the tube by inserting a support (q) such as a membrane stone into the control gap (p) on the left and right side of the tube, then assemble the formwork (14) and the base concrete part in the formwork. The concrete is poured with the side concrete parts.

관 부설이 2 이상의 열로서 부설되는 경우 도4, 도5의 관 가설 장치는 2열 이상의 관을 부설할 수 있도록 관 가설장치를 연속 배열하여 사용한다.When the pipe laying is laid in two or more rows, the pipe placing apparatus of FIGS. 4 and 5 uses a continuous arrangement of pipe placing devices so as to lay two or more rows of pipes.

관 가설장치가 선행하여 또는 하나씩 부설되면 작업 장비를 이용하여 가설장치 상부에 흄관의 양단을 안착시킨다. 이미 가설장치를 관 부설 라인을 따라 일치시켰으므로 흄관을 가설장치의 상부에 안착하는 것 만으로 흄관의 정렬이 정확하게 이루어진다. 다만 흄관 이음단을 관 가설장치에 안착시킬 때 이음 칼라(9)를 흄관의 이음부에 삽입한다.If the pipe placing device is installed in advance or one by one, work equipment is used to seat both ends of the fume pipe on the top of the placing device. The installation of the fume pipe is precisely aligned by simply placing the fume pipe on the upper part of the installation device because the fitting device is already matched along the pipe laying line. However, when the fume pipe joint is seated on the pipe construction device, the joint collar (9) is inserted into the joint of the fume pipe.

가설장치 위에 흄관이 안착된 후 흄관의 좌우에 거푸집(14)을 조립한다. 거푸집 조립요령은 종래와 같으나 이 고안에서 다음과 같이 시공함으로써 숙련공이 아닌 일반 노동력으로 부자재를 적게 사용하면서 신속하게 조립할 수 있다.After the fume pipe is placed on the hypothesis device, the formwork 14 is assembled on the left and right sides of the fume pipe. Forming instructions are the same as in the prior art, but the construction as follows in the design can be quickly assembled while using less subsidiary materials in general labor than skilled workers.

즉, 도6(A)는 타이볼트(22)를 사용하여 거푸집(14)을 조립한 예이다. 타이볼트(22) 일측에 걸림부(23)가 형성되어있고, 타측에 너트(24) 체결용 나사부(25)와 절단 홈(26)이 형성되어 있다. 거푸집(14)을 조립할 때 걸림부(23)를 서포팅블록(g,m)에 구비한 연결요소 예컨데 결속 철선(j)이나 앵커(a)에 걸고 거푸집(14)을 관통시킨 외측 나사부(25)에 너트(24)를 채워 거푸집(14)을 조립한다. 이와 같이 타이볼트(22)를 관 부상체(1) 등에 연계하여 거푸집을 조립한다. 이와 같이 타이볼트를 사용하면 숙련공이 아니더라도 거푸집(14)의 조립을 신속하고 정확하게 할 수 있다. 거푸집을 탈형 한 후 콘크리트 측면으로 돌출되는 볼트(22)의 돌출부는 절단홈(26)에서 절단하여 제거할 수 있다.That is, FIG. 6 (A) shows an example in which the formwork 14 is assembled using the tie bolts 22. As shown in FIG. A locking portion 23 is formed at one side of the tie bolt 22, and a threaded portion 25 for fastening the nut 24 and a cutting groove 26 are formed at the other side. When assembling the formwork 14, the outer threaded portion 25 through which the engaging portion 23 is provided on the supporting blocks g and m, for example, the fastening wire j or the anchor a, and the formwork 14 is penetrated. Assemble the formwork (14) by filling the nut (24). In this way, the formwork is assembled by connecting the tie bolt 22 to the pipe floating body 1 or the like. In this way, if the tie bolts are used, the assembling of the formwork 14 can be performed quickly and accurately even if the skilled worker is not. After demolding the formwork, the protrusion of the bolt 22 protruding toward the concrete side can be removed by cutting in the cutting groove 26.

도6(B),(C)는 타이띠철(32)을 사용하여 거푸집을 조립한 예이다. 타이띠철(32)의 일측에 걸림부(33)를 만들고, 타측에 삼각핀(34)의 결합구멍(35)과 절단 홈(36)을 형성하고 있다. 타이띠철(32)을 사용하여 거푸집을 조립하자면 걸림부(33)를 천선(j)이나 앵커(a) 등에 걸고 거푸집(14)을 관통시킨 외측 구멍(35)에 삼각핀(34)를 끼워 거푸집을 조립한다. 마찬가지로 타이 띠철을 사용하면 숙련공이 아니더라도 거푸집(14) 신속하고 정확하게 조립 할 수 있다.6 (B) and 6 (C) show an example of assembling the formwork using the tie-iron 32. A locking portion 33 is formed on one side of the tie strip iron 32, and a coupling hole 35 and a cutting groove 36 of the triangular pin 34 are formed on the other side. To assemble the formwork using the tie strip iron 32, the triangular pin 34 is inserted into the outer hole 35 through which the catch portion 33 is hung on the cloth line j or the anchor a, and the formwork 14 is passed through. Assemble Likewise, if you use tie strips, even if you are not skilled workers, the formwork 14 can be assembled quickly and accurately.

상기와 같이 거푸집(10)이 조립이 완료되면 기층(11) 위에 기초콘크리트 부분과 측면콘크리트 부분을 일체형 콘크리트(10)로서 타설 하고 콘크리트 양생 후 거푸집을 해체하는 것이다.When the formwork assembling 10 is completed as described above, the foundation concrete portion and the side concrete portion is poured on the base layer 11 as an integrated concrete 10 and the formwork is dismantled after curing of concrete.

이 고안은 상술한 콘크리트 관 가설장치 외에도 주철재 관 가설장치, 합성수지재 관 가설 장치 등 다양한 재료에 의한 관 가설 장치를 사용할 수 있다.This design can be used in addition to the above-mentioned concrete pipe construction apparatus pipe casting apparatus made of a variety of materials, such as cast iron pipe construction apparatus, synthetic resin pipe construction apparatus.

상기 콘크리트 타설시 측면콘크리트의 높이가 너무 높을 경우 일시에 콘크리트를 주입하면 관이 부상할 우려가 있다. 이 경우 묽은 콘크리트가 부상력을 소실 할때 까지 일정 시간의 간격을 두고 콘크리트를 2차에 걸쳐 주입하거나 관 부상체와 관을 철선으로 결속한 후 콘크리트를 타설한다.If the height of the side concrete is too high when the concrete is poured, there is a fear that the pipe is injured when concrete is injected at a time. In this case, the concrete is poured into the secondary at intervals of a certain time until the thin concrete loses the flotation force, or the pipe floating body and the pipe are bound together with steel wire and then the concrete is poured.

상기와 같이 이 고안은 기층 상부에 관을 가설 상태로 배열하고 기초콘크리트 부분과 측면콘크리트 부분을 일체로 타설 할 수 있게 하는 관 가설장치를 제공하는 것으로서, 이 고안에 의하면 기초콘크리트 부분과 측면콘크리트 부분 사이에 수평 시공이음이 생기지 아니하게 함은 물론 공사기간을 단축하고, 투입인력을 감소하고, 숙련공이 아니더라도 거푸집을 조립할 수 있고, 콘크리트 타설시 편압이 발생되지 않고, 공사장비의 이용 효율을 높이고, 공사자재를 절약하며, 거푸집 조립시의 부자재 비용을 줄이고, 거푸집의 순환사이클을 단축하고, 더 나아가 수평 시공이음이 없는 관지지 콘크리트를 제공하여 하수의 누수를 감소시키며, 제 위치에 맞게 관을 정확하게 관을 부설할 수 있게 하는 관 가설장치를 제공하는 것이다.As described above, the present invention is to provide a pipe construction apparatus for arranging the tube in the upper part of the base layer and placing the foundation concrete portion and the side concrete portion integrally. According to this design, the foundation concrete portion and the side concrete portion It is possible not only to create horizontal joints, but also to shorten the construction period, reduce the input manpower, assemble formwork even without skilled workers, do not generate pressure during concrete placement, and improve the use efficiency of construction equipment. It saves construction materials, reduces the cost of subsidiary materials when assembling formwork, shortens the circulation cycle of formwork, and further reduces the leakage of sewage by providing pipe support concrete without horizontal construction joints. It is to provide a pipe construction device that can be installed in the pipe.

Claims (1)

부설되는 관(15)의 이음단을 기층(11) 위에서 기초콘크리트 두께(t)만큼 부상시키고 거푸집을 조립하여 기초콘크리트 부분과 측면콘크리트 부분을 일체형콘크리트(10)로 타설 할 수 있도록 콘크리트 서포팅블록과 관 지지블록으로 관 부상체(1)를 구성하고, 상기 관 부상체(1)를 배열할 때 간격을 띄워 이음칼라(32) 수용 공간부(3)를 구성하고, 상기 관 지지체에 관 지지용 테이퍼를 형성한 관 가설장치.Floating end of the pipe (15) to be laid on the base layer (11) by the basis concrete thickness (t) and assembling the formwork concrete foundation block and the side concrete part to be cast as an integral concrete (10) and A pipe support block constitutes a pipe floating body (1), spaced apart when arranging the pipe floating body (1) to form a joint collar (32) receiving space (3), for supporting the pipe on the pipe support Tapered pipe temporary device.
KR2020000027451U 2000-09-30 2000-09-30 The duct supporting equipment KR200216493Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020000027451U KR200216493Y1 (en) 2000-09-30 2000-09-30 The duct supporting equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020000027451U KR200216493Y1 (en) 2000-09-30 2000-09-30 The duct supporting equipment

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR2020000024333U Division KR200211191Y1 (en) 2000-08-28 2000-08-28 The duct supporting equipment

Publications (1)

Publication Number Publication Date
KR200216493Y1 true KR200216493Y1 (en) 2001-03-15

Family

ID=73089443

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020000027451U KR200216493Y1 (en) 2000-09-30 2000-09-30 The duct supporting equipment

Country Status (1)

Country Link
KR (1) KR200216493Y1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100437718B1 (en) * 2002-02-15 2004-06-30 안병원 Working method for draining a penetrated water while constructing a bridge
CN113235418A (en) * 2021-05-12 2021-08-10 山西省交通科技研发有限公司 Construction method of integrated prefabricated drainage structure for bridge

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100437718B1 (en) * 2002-02-15 2004-06-30 안병원 Working method for draining a penetrated water while constructing a bridge
CN113235418A (en) * 2021-05-12 2021-08-10 山西省交通科技研发有限公司 Construction method of integrated prefabricated drainage structure for bridge

Similar Documents

Publication Publication Date Title
US10458093B2 (en) On-site manhole casting system
US10968594B1 (en) Manhole rehabilitation system
KR20070077824A (en) Construction method of precast concrete box culvert with bolt connecting structure
KR100808676B1 (en) Method of constructing for hume pipe underground
CN216131506U (en) Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure
KR101566229B1 (en) Manufacturing equipment for Manhole using various connecting pipe, manufacturing method for the same and connecting method for the manhole with a connecting pipe
KR200216493Y1 (en) The duct supporting equipment
CN110629617A (en) Combined type bottom-plate-free box type roadbed and roadbed construction method
CN218236612U (en) Reinforced concrete pipeline repairing device
CN115898469A (en) Tunnel secondary lining construction method
KR100386914B1 (en) The duct construction method with the duct supporting equipment and The duct supporting equipment
KR200211191Y1 (en) The duct supporting equipment
KR100836512B1 (en) Duct repairing material, repairing structure, and repairing method
CN110552378A (en) Underground space roof subsides post-cast strip and seals structure in advance
CN213418235U (en) Prefabricated assembled FRP pipe-concrete-steel pipe combination column
KR102190480B1 (en) Implant pile pressing apparatus in architecture foundation system and a universal implant piling method
CN206973068U (en) A kind of through-flooring is pre-buried to use the pre-buried adapter of flexible interface adjusting center
KR200417474Y1 (en) Support pipe
KR200342265Y1 (en) Hume concrete pipe connection structure
KR102518907B1 (en) Manhole Block Manufacturing Method
JPH1146432A (en) Case for wire underground conduit and manhole structure for the pipeline
KR102206046B1 (en) Crack guidance device and method for constructing joints of drainage structure using same
CN214144646U (en) Laminated slab cantilever frame pre-embedding device, building component finished product and cantilever frame structure
CN111270708B (en) Sump leakage plugging device and sump leakage plugging method
KR100377690B1 (en) A valve room structure and method of constructing valve room

Legal Events

Date Code Title Description
U106 Divisional application of utility model
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20020627

Year of fee payment: 3

LAPS Lapse due to unpaid annual fee