KR20020079707A - The facility of river in the civil center and method restoration of it - Google Patents

The facility of river in the civil center and method restoration of it Download PDF

Info

Publication number
KR20020079707A
KR20020079707A KR1020020058703A KR20020058703A KR20020079707A KR 20020079707 A KR20020079707 A KR 20020079707A KR 1020020058703 A KR1020020058703 A KR 1020020058703A KR 20020058703 A KR20020058703 A KR 20020058703A KR 20020079707 A KR20020079707 A KR 20020079707A
Authority
KR
South Korea
Prior art keywords
water
river
diameter pipe
facility
road
Prior art date
Application number
KR1020020058703A
Other languages
Korean (ko)
Other versions
KR100515189B1 (en
Inventor
한민호
Original Assignee
건양씨앤이 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 건양씨앤이 주식회사 filed Critical 건양씨앤이 주식회사
Priority to KR10-2002-0058703A priority Critical patent/KR100515189B1/en
Publication of KR20020079707A publication Critical patent/KR20020079707A/en
Application granted granted Critical
Publication of KR100515189B1 publication Critical patent/KR100515189B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B8/00Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
    • E02B8/04Valves, slides, or the like; Arrangements therefor; Submerged sluice gates
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • E02B9/02Water-ways
    • E02B9/06Pressure galleries or pressure conduits; Galleries specially adapted to house pressure conduits; Means specially adapted for use therewith, e.g. housings, valves, gates
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use
    • Y02A20/40Protecting water resources
    • Y02A20/402River restoration
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Revetment (AREA)

Abstract

PURPOSE: Installations for rivers in the downtown area and a restoration method for the rivers are provided to secure a constant amount of water of the rivers, and to protect park facilities within the terrace land on the river from a deluge. CONSTITUTION: An underwater bank(21) and a fish way(22) are installed at the upper stream region from which a restoration work of the rivers in the downtown area is started. A plurality of large diameter pipes(10) are installed on the bottom of rivers to circulate the water of the river and bypass the water in order to absorb excessive water flow during a deluge. Water taking facilities are connected to the lower ends of the large diameter pipes, and water pumping facilities(2) and sanitation facilities(1) are installed within the terrace land on the river.

Description

도심지 하천설비와 도심지하천 복원 공법{The facility of river in the civil center and method restoration of it}The facility of river in the civil center and method restoration of it}

본 발명은 도심지 하천복원 공법에 관한 것으로서, 상세히 설명하면, 도심지 하천복원이 시작되는 상류지역에 물막이 수중보 및 어도, 홍수시 과다 유량 흡입구, 하도밑에 설치한 하천수 재순환 및 홍수시 바이패스 통로내 하단부에 설치된 취수 시설, 그리고 고수부지에 설치된 양수장 및 자연정화 시설로 이루어진 설비 및 생태공원 생태학습장과 그 설비를 이용한 도심지 하천복원공법에 관한 것이다.The present invention relates to a downtown river restoration method, which will be described in detail, in the upper portion of the downtown river restoration begins, the water barrier and the estuary, the excess flow intake during flooding, river water recirculation installed under the road and the lower part of the bypass passage in the flood The present invention relates to a facility consisting of an intake facility installed, a pumping station and a natural purification facility installed on a sediment site, an ecological learning center of an ecological park, and an urban river restoration method using the facility.

국토의 도시화에 따라 토지 이용이 증대되고 하천유역에서의 생산활동이 증대되면서 하천은 이, 치수 기능만을 고려한 배수로 기능을 담당하는 하천이 되어왔으며, 대도시 하천의 고수부지 등은 하상주차장 또는 하상도로로서의 역할을 담당해왔다.특히 자연스럽게 사행하던 하천이 직강하되거나 복개되고 호안은 콘크리트로 변하였고 차집관거 설치 및 도심지역의 포장으로 인한 하천으로의 유입유량감소As urbanization of land has increased land use and production activities in river basins have increased, rivers have become rivers that serve as drainage channels that take into account only these and watershed functions. In particular, naturally flowing rivers have been descended or reclaimed, lakes have been converted to concrete, and the flow of water into the rivers has been reduced due to the installation of teahouses and pavement in urban areas.

등으로 인하여 하천은 자정능력을 상실한채 다양하게 천변에 서식하던 식생, 어류, 곤충 등은 사라져 갔다.The rivers lost their self-cleaning ability, and the vegetation, fish, and insects that lived on the banks of the river disappeared.

이러한 하천환경의 저하에 대한 복안으로 여러 공법이 유럽 및 일본, 한국에서 시도되고 있다. 그중 하나인 자연형 하천 복원 공법은 현재의 인위적인 하천을 생태적 자연기법을 도입하여 과거 자연 상태의 하천으로 복원하려는 공법이며, 더 이상 우리 주변의 자연환경을 사람위주로 개발하여 환경오염을 가중시키지도 않고 인간과 자연이 공존하는 환경을 창출하고자 하는 것이다.Various construction methods have been tried in Europe, Japan, and Korea to address the deterioration of the river environment. One of them, the Natural River Restoration Method, is a method to restore the current artificial rivers to the rivers of the past natural state by adopting ecological natural techniques, and further develops the natural environment around us and does not increase human pollution. It is to create an environment where nature and nature coexist.

현재 국내에 소개된 자연형 하천 복원공법은 크게 2가지로 나눌 수 있다. 하나는 독일 및 스위스에서 발달한 유럽형 공법으로 주로 자연재료(말뚝 및 식물재료등)를 이용하여 하천복원을 하는 공법이나 유럽에 비해 하상계수가 큰(일시적으로 큰 유량이 집중되는 비율을 나타낸 계수로 유럽에 비해 작게는 10배에서 크게는 50배까지 큼) 국내의 하천에서는 집중호우에 의해 유발된 홍수에 의해 복원된 시설이 유실되는 경우가 많아 국내에서의 적용은 거의 힘들다.그리고 국내와 같이 하상계수가 큰 일본에서 발전한 구조물 위주의 자연형 하천 복원 공법이 국내 하천에 많이 적용되고 있으나 인공구조물의 특성상 유럽형과 같은 섬세한 자연 생태계의 복원은 힘든 실정이다. 하천의 유량관리가 잘되고 있는 일본에 비해 갈수기에는 하천에 거의 물이 없는 국내의 사정상, 식생, 곤충 및 어류생태계를 복원하는 것은 거의 불가능하며 이의 대비책으로 상류에 댐 건설 및 도수관을 통한 다른 하천 용수의유입 및 지하수 양수를 통한 용수확보를 시도하고 있으나, 특히 지하수 양수를 통한 유량확보의 경우, 도시포장화로 인하여 도시 지반내 지하수가 고갈되고 있는 상황에서 대량의 지하수를 양수하기 때문에 대규모의 지반침하 현상을 불러올수 있다. 상류에 댐을 건설하는 방안 또한 2차적인 환경 파괴를 불러올 수 있기 때문에 자제해야하며 타하천에서의 유량도입 또한 취수원이 되는 타 하천의 환경저하를 불러올 수 있다. 또한 국내의 경우, 도심지내의 하천은 하수종말처리 시설에 의해 처리가 되지만, 도심지 상류에 위치한 하천수는 대개 오수처리가 되지 않은 채 도심지 하천으로 유입되기 때문에 도심지 하천의 복원시에는 이에 대한 대책도 강구할 필요가 있다. 본 개발자는 이러한 기존 공법의 문제점을 해결하여 한국형 도심지 하천에 적용 가능토록 한 하천복원 공법을 개발하였으며 개발된 신공법의 적용으로 인하여 보다 풍부한 자연환경의 도심내 회복를 가능토록 하였다.Currently, the natural river restoration method introduced in Korea can be divided into two types. One is the European method developed in Germany and Switzerland. It is a method that restores rivers mainly using natural materials (eg piles and plant materials). In domestic rivers, the facilities restored by floods caused by heavy rains are often lost in domestic rivers, making them difficult to apply in Korea. Although the structure-oriented natural river restoration method developed in Japan, which has a large coefficient, is widely applied to domestic rivers, it is difficult to restore the delicate natural ecosystem like the European type due to the nature of the artificial structure. Compared to Japan, which has better flow control in rivers, it is almost impossible to restore the vegetation, vegetation, insects, and fish ecosystems in the dry season with little water in the dry season. While attempting to secure water through inflow and groundwater pumping, in particular, in case of securing flow through groundwater pumping, a large amount of groundwater is pumped out due to urban groundwater draining a large amount of groundwater. Can be called The construction of dams upstream can also lead to secondary environmental destruction, so refrain from introducing them. Also, the introduction of flows from other streams can also lead to environmental degradation of other rivers. In Korea, however, streams in urban areas are treated by sewage treatment facilities, but river water located upstream of the city usually flows into downtown rivers without sewage treatment, so take countermeasures when restoring downtown rivers. There is a need. This developer has solved the problems of the existing construction method and developed a river restoration method that can be applied to the Korean urban streams. The application of the developed new construction method allows the urban restoration of a richer natural environment.

현재 국내에서 사용중인 하천 복원 공법은 식생호안공법과 구조물 블록공법의 2가지로 나눌 수 있다.The river restoration method currently used in Korea can be divided into vegetation protection method and structure block method.

식생호안공법을 설명하면, 자연형 하천 정비 공법은 현재의 인위적인 하천을 생태적 자연 기법을 도입하여 과거 자연 상태로의 하천으로 복원하려는 공법이며, 더 이상 우리 주변의 자연 환경을 사람 위주로 개발하여 환경오염을 가중시키지 않고 인간과 자연이 공존하는 자연을 창출하고자 하는 것이다. 이러한 환경복원운동은 유럽, 미국, 일본 등지에서 범국민적인 캠페인을 통하여 10여년전부터 실행해 왔으며 큰 성과를 거두고 있다. 특히 생태공학적 기술은 불안정한 구간에 식물공동체를 구축하는데 도움을 주며 생물학, 생태학과 공학적인 개념들이 함께 기능을 발휘하는 체계가 된다.When describing the vegetation protection method, the natural river maintenance method is a method to restore the current artificial river to the river to the past natural state by adopting ecological natural method, and furthermore, it develops environmental pollution by focusing on the natural environment around us. It is trying to create a nature where humans and nature coexist without adding weight. This environmental restoration movement has been carried out for more than 10 years through national campaigns in Europe, the United States, and Japan, and has achieved great results. In particular, eco-technologies help to build plant communities in unstable areas and become a system in which biology, ecology and engineering concepts work together.

생태공학은 단지 약한 것에 초점을 맞추기보다는 스스로를 보호하는 자생력을 이용하며, 일단 식생의 안정화가 구축되면 식생은 자발적 유지가 가능하다. 살아있는 식물들이 외부의 힘 (홍수나 유동사 퇴적에 의한 상태의 변화)에 의해 충격을 받았을 때 식물들은 재생과 적응이 쉽다. 그래서 동서양을 막론하고 수백년동안 사람들은 이러한 식물들의 안정화 특성을 이용하여 왔다.Ecological engineering uses self-sustaining power to protect itself rather than just focus on the weak, and once the vegetation stabilizes, the vegetation can be maintained voluntarily. When living plants are shocked by external forces (changes in state due to flooding or fluid deposition), they are easy to regenerate and adapt. Thus, for hundreds of years, people from both the East and the West have used the stabilizing properties of these plants.

자연형 하천 호안 정비공법은 하천환경 정비중 하천내에서 생태적으로 가장 중요한 역할을 담당하는 저수호안을 생태적으로 재생시키고자 하는 것이다.Natural river shore renovation method is to ecologically regenerate low water reservoir which plays the most important ecological role in the stream.

자연형 하천 호안 공법에 사용되는 주요재료는 자연석(원석 또는 깬돌), 목재(말뚝, 살아 있는 삽목이 가능한 나뭇가지 또는 죽은 가지.), 천연섬유(야자열매 섬유를 이용한 제품, 황마)등이 자연형 하천 공법이 발달된 유럽에서 쓰이는 주요 재료이다. 이들 재료중 자연석은 유한 자원이며, 목재 또한 사용후 다시 성장시키려면 적어도 수년에서 수십년이 소요되는 유한자원으로 볼 수 있다. 돌과 나무의 과다 사용은 자연이 회복할 여유를 주지 않는 또 다른 자연 파괴이며, 훼손된 부분을 회복시키려 다른곳을 파괴하는 빈곤의 악순환이 될 수 있다는 점에서 찾아낸 것이 천연섬유로 야자열매를 이용한 제품이 많이 사용되고 있다.The main materials used in natural river revetment include natural stone (stone or crushed stone), wood (pile, twigs or dead branches with live cutting), and natural fiber (products using coconut fiber, jute). It is the main material used in Europe where the type river process is developed. Of these materials, natural stone is a finite resource, and wood can also be regarded as a finite resource that requires at least several years or decades to grow again after use. The overuse of stones and trees is another natural destruction that nature cannot afford to recover, and it can be a vicious cycle of poverty that destroys others to restore damaged parts. This is used a lot.

그리고 하천에서의 치수기능과 환경기능은 어느 정도 상반된 면을 지니고 있다. 하천 생태계, 경관 및 친수성등 하천 환경 요소들은 호안재료에 따라 상당한 영향을 받으므로 자연형 하천 계획에 의해 이루어지는 하천정비는 달성목적에 따라 다양한 재료가 선택되어 질 수 있으므로 해당하천의 하도 및 지역특성등을 충분히 반영하고 홍수에도 견딜 수 있음은 물론 하천 생태계, 경관, 친수성등 여러 하천 환경 요소들의 보전 및 향상을 위하여 서로 비교 검토후 최적 재료를 선택하여 적용하거나 재료의 조합도 바람직하다.In addition, the dimensional and environmental functions in rivers have some contradictory aspects. Since river environment factors such as river ecosystem, landscape, and hydrophilicity are significantly affected by the shoreline materials, the river maintenance made by the natural river plan can be selected according to the purpose of accomplishment. In order to sufficiently reflect and tolerate flooding, and to preserve and improve various river environmental factors such as river ecosystem, landscape, and hydrophilicity, it is desirable to select and apply the optimal materials after comparing them with each other.

식생호안공법의 장점은 경관양호, 둔치의 건조화 방지, 다양한 식생기능, 생태계 보전기능-초본류와 함께 식물연쇄의 제 1차 생산자 역할을 하고, 조류나 소동물의 휴식과 먹이 획득의 장소 제공. 수질정화기능이 있으며, 단점으로는 하도접근 곤란, 지속적인 유지관리 필요하고, 콘크리트 블록에 비해 공사비가 비싸다, 내구성 저하, 시공시기의 제한 받는 점이다.The benefits of the vegetation protection method include the protection of landscape, prevention of drying out of the vulture, various vegetation functions, and ecosystem preservation functions-acting as the primary producers of plant chains together with herbaceous plants, and providing a place for resting and obtaining food for birds and small animals. There are water purification functions, and the disadvantages are difficult access to the roadway, continuous maintenance is required, and the construction cost is higher than that of concrete blocks, durability is lowered, and construction time is limited.

일반 자연형 하천복원 공법 시공예는 도 12에 도시된 바와 같다.General natural river restoration method construction example is as shown in FIG.

자연형 하천 정비시 문제점은 년중 식물 식재를 위한 시공 시기의 배려가 필요. 식물성장기 동안 이식할 경우 고사하는 식물의 양이 늘어나는 것이다.Problems in the maintenance of natural rivers require consideration of the time of construction for planting throughout the year. Transplanting during plant growth increases the amount of dead plants.

자연형 하천 공법은 아직 대부분이 품셈에 기재되어 있지 않아서 노임, 경비 및 재료비의 적응이 일정치 못해 설계 담당자나 공무원의 애로 사항이 되고 있으며, 이는 공사비 산출시 가격 상승의 원인이 되기도 하므로 이에 대한 정비가 필요하다. 자연형 하천 공사시 가장 일반적으로 사용되는 식물은 버드나무과의 갯버들, 버드나무 등과 벼과 식물의 갈대, 물억새등이다. 다행히 최근 일부 식물원에서 갈대, 물억새등은 재배하여 판매하고 있지만, 아직도 많은 양이 채취되고 있으며, 버드나무류는 거의 전량이 채취되고 있는 상황이다. 이는 자연 하천을 조성하기 위해 또 다른 환경파괴를 범하는 경우가 되므로 현재는 큰 문제가 없다 할지라도, 향후 공사가 늘어나면 큰 문제가 될 수 있으므로 이에 대한 대책이 필요하다.Since most of the natural river construction methods are not yet listed in the product, the adjustment of wages, expenses, and material costs is inconsistent, which is a problem for design managers and public officials. Is needed. The most commonly used plants in the construction of natural rivers are willow willows, willows, and reeds of rice plants. Fortunately, some botanical gardens have grown and sold reeds, pampas grass, etc., but a large amount is still collected, and almost all willows are collected. This is because it is another case of environmental destruction in order to create a natural river, but even if there is no big problem at present, it may be a big problem if the construction in the future increases.

돌 공사시 식재와 병행할 경우, 돌을 사용하는 공사는 돌 사이의 공극에 물고기와 저서 생물들의 서식처 및 피난처로 사용될 수 있는 공간이다. 그러나 평상시 수위선 이상의 지역은 돌틈 사이에 자연적으로 식물이 자생하려면 많은 시간이 소요될 뿐 아니라 붕괴의 한 원인이 될 수 있으며 경관적으로도 좋지 않으므로 평수위선 이상은 돌틈사이에 흙을 채워 버드나무류, 삽목, 잔디 식재 및 씨앗 뿌리기 등으로 녹화시키는 것으로 경관수나 치수적으로 좋다고 판단된다.In parallel with planting in stone construction, the construction using stone is a space that can be used as a habitat and refuge for fish and benthic creatures in the gaps between the stones. However, areas above the level line usually take a long time to grow naturally among the gaps, and may be a cause of collapse, and are not so scenic, so the level above the level level fills the soil between the gaps and willows, It is judged that it is good for the number of trees and the size of trees by cutting with cuttings, grass planting and seeding.

구조물 블록공법을 설명하면, 기존 콘크리트의 기능을 그대로 수행하면서, 물과 공기를 투과 시킬 뿐만 아니라 식물의 뿌리를 통과시켜 제방의 원지반에 정착하게 함으로써 제방의 원지반을 살리고(지렁이, 소곤충의 생존 확인)물속에 산소를 공급하며, 수중 생물의 서식공간을 확보해줌과 아울러 수생생태계와 육상생태계를 연결하여 줌으로써 풍부한 생태환경을 회복할 수 있다.When explaining the structure block method, while maintaining the function of the existing concrete, not only permeate water and air, but also allow the plant roots to pass through and settle on the base of the dike, saving the base of the dike (checking the survival of earthworms and small insects). By supplying oxygen in the water, securing the habitat for aquatic organisms, and connecting the aquatic and terrestrial ecosystems, the rich ecological environment can be restored.

구조물 블록공법의 장점으로는 하천의 생태적 다양성을 확보 제방부 전면에 식물이 생육하도록 하여 하천 생태계와 육상 생태계를 자연스럽게 연결하도록 하며 수중부에 다양한 수생식물이 생육하도록 하여, 어류, 양서류, 파충류 및 곤충류의 산란과 서식공간을 확보한다. 또한 식물이 정착될 뿐만 아니라 물과 산소를 투과시키므로 원지반에 지렁이를 포함한 다양한 소곤충과 미생물이 생육되고, 구조체로서 제방을 홍수로부터 보호하여 식생이 정착되어 블록과 제방을 일체화시키고 투수성 재료를 사용하여 제방이 받는 토압을 경감시켜 블록간의 마찰계수가 증가되며, 식물의 뿌리가 블록을 통과하여 제방에 정착되므로 견고하게 제방에 부착되는 것이다. 구조물 블록공법 시공예는 도13내지 도 17에 나타난 바와 같다.The advantage of the structure block method is to secure the ecological diversity of the rivers so that vegetation grows in front of the levees so that the river ecosystems and the land ecosystems can be naturally connected, and various aquatic plants grow in the water, and fish, amphibians, reptiles and insects Secure spawning and habitat space for In addition, plants not only settle, but also permeate water and oxygen to grow various insects and microorganisms including earthworms on the ground, and protect the levees from flooding as structures to settle vegetation to integrate blocks and levees and use permeable materials. By reducing the earth pressure received by the dike, the coefficient of friction between the blocks increases, and the roots of the plants pass through the block and settle on the dike so that they are firmly attached to the dike. Structure block construction method is as shown in Figure 13 to 17.

기타, 대한민국공개특허공보 공개번호 특2000-0007004호에는 중소하천의 어족보호와 양서류의 이동통로를 가진 낙차공과 호안의 시공방법이 기재되어 있고, 동 공보 공개번호 특2002-0059196호에는 환경복원을 위한 호소내 수생식물을 식재하기 위하여 장마철이나 폭우 등에 견딜 수 있는 자연형 하천복원과 하천 수변부의 수충부를 설치하여 침식방지 및 식물정착이 가능한 식생호안공법이 기술되어 있으며,In addition, Korean Laid-Open Patent Publication No. 2000-0007004 describes the construction method of free fall ball and revetment with protection of small and medium-sized rivers and passage of amphibians, and the public publication No. 2002-0059196 discloses environmental restoration. In order to plant the aquatic plants in the lake for the rainy season, natural river restoration that can withstand rainy seasons and heavy rains and vegetation protection methods that can prevent erosion and plant settlement are installed by installing water repellents in the riverside.

대한민국 등록특허공보 등록번호 10-0296515호에는 하천의 어족자원과 양서류를 보호할 수 잇는 친환경적인 하상 및 호안부재와 이를 이용한 하상 및 호안의 시공방법이 기재되어 있고,Republic of Korea Patent Publication No. 10-0296515 describes the eco-friendly riverbed and shore protection member that can protect the fish stocks and amphibians in the river and the construction method of the riverbed and lakeside using the same,

대한민국등록실용신안공보 등록번호 20-0283238호에는 동물들이 생활영역을 넓힐 수 있도록 도와주는 환경생태통로다리가 기재되어 있으며,Korean Utility Model Registration No. 20-0283238 describes an ecological pathway to help animals expand their lives.

동 공보 등록번호 20-0277591호에는 하천에 형성된 수중보의 적어도 한곳에 수로를 형성하여 어도를 구성하는 수중보용 어도장치에 있어서, 상기 수로의 양측벽면에 가이드홈을 형성하고 다수개의 어도가 형성된 어도불록과, 어도불록의 높이 변화에 대응하여 물의 출입이 가능하도록 출입공이 형성된 고무튜브로 이루어진 어도형성부와, 상기 수로의 양측벽면에 고정된 스크린망으로 구성된 하천의 수중보용 어도장치가 기술되어 있고, 동 공보 등록번호 20-0286652호에 자동수위조절이 가능한 수중보가 기술되어 있으나,The publication No. 20-0277591 discloses an underwater fishing device for forming a fishery by forming a waterway in at least one of the underwater beams formed in a river, wherein the guide grooves are formed on both sidewalls of the waterway, and a plurality of fishery blocks are formed. In addition, there is described a fishery forming apparatus for a river underwater consisting of a fishery forming portion made of a rubber tube formed with a hole to allow water in and out corresponding to a change in height of the fishery, and a screen net fixed to both side walls of the waterway. Publication No. 20-0286652 describes an underwater level control with automatic water level control,

상기와 같은 종래의 기술들은 한국의 하천지형에 맞지 않고, 또한 설치방법이 복잡하고 도심지에 단시간내에 설치하기 어려우며, 홍수시 대량의 물을 유출시키지 못하며, 친환경적이지 못한 문제점이 있어 왔다.Conventional techniques as described above are not suitable for the river topography of Korea, the installation method is complicated, difficult to install in a short time in the downtown, and do not spill a large amount of water during the flood, there has been a problem that is not environmentally friendly.

본 발명은 상기와 같은 문제점을 해결하고자, 본 출원인이 기출원한 발명의 명칭 : 대구경강관 압입추진공을 이용한 생태계 이동로 시공방법(출원번호 10-2002-0011899호)을 적용한 자연형 하천 복원 공법의 일종으로 현재의 인위적인 하천을 생태적 자연기법을 도입하여 과거 자연 상태의 하천으로 복원하려는 공법으로서, 자연환경을 사람위주로 개발하여 환경오염을 가중시키지도 않고 인간과 자연이 공존하는 환경을 창출하고자 하는 한국형 도심지 하천복원 공법을 제공하는 것을 목적으로 하는 것이다.The present invention, in order to solve the above problems, the applicant of the present invention filed by the applicant Applicant name: natural river restoration method applied to the ecological movement road construction method (application number 10-2002-0011899) using the Daegu diameter steel pipe indentation pusher It is a method to restore the current artificial rivers to the rivers of the past natural state by introducing ecological natural techniques.It is a Korean type that aims to create an environment where humans and nature coexist without aggravating environmental pollution by developing the natural environment around people. The purpose is to provide urban stream restoration methods.

도1은 본 발명의 도심지 하천복원 공법 전체상세도Figure 1 is a detailed view of the downtown river restoration method of the present invention

도2는 본 발명의 도심지 하천복원 공법 전체 정면상세도Figure 2 is a front view of the entire downtown river restoration method of the present invention

도3은 본 발명의 도심지 하천복원 공법 상류 측면상세도Figure 3 is a side view upstream of the downtown river restoration method of the present invention

도4는 본 발명의 도심지 하천복원 공법 상류 평면상세도Figure 4 is a plan view upstream of the downtown river restoration method of the present invention

도5는 본 발명의 도심지 하천복원 공법 상류 정면상세도5 is a front detail view of the downtown stream restoration method of the present invention;

도6은 본 발명의 도심지 하천복원 공법 중간부 평면상세도Figure 6 is a plan detail of the middle portion of the downtown river restoration method of the present invention

도7은 본 발명의 도심지 하천복원 공법 중간부 측면상세도Figure 7 is a side detail view of the middle portion of the downtown river restoration method of the present invention

도8은 본 발명의 도심지 하천복원 공법 중간부 정면상세도Figure 8 is a front detail view of the middle part of the downtown river restoration method of the present invention

도9는 본 발명의 도심지 하천복원 공법 하류 평면상세도Figure 9 is a plan view of the downstream downtown restoration method downstream of the present invention

도10은 본 발명의 도심지 하천복원 공법 하류 측면상세도Figure 10 is a side detail downstream of the downtown river restoration method of the present invention

도11은 본 발명의 도심지 하천복원 공법 하류 정면상세도11 is a front detail view of a downtown river restoration construction method of the present invention;

도12는 종래의 자연형 하천복원공법 상세도12 is a detailed view of the conventional natural river restoration method

도13내지 도17은 종래의 블록공법 상세도13 to 17 are detailed block diagrams of the related art.

도18는 본 발명의 제방도로에 설치된 터널식 야생동물 이동통로 평면상세도18 is a plan view of the tunnel-type wild animal movement passage installed on the embankment road of the present invention

도19은 본 발명의 제방도로에 설치된 터널식 야생동물 이동통로 측면상세도Figure 19 is a side view of the tunnel-type wildlife movement passage installed on the embankment road of the present invention

<도면의 부호설명><Description of the Drawings>

자연정화시설(1), 양수시설(2), 자연형 호안정비시설(3,6), 생태공원(4), 친환경형하상도로(5), 고수부지(7), 제방도로(8), 대구경파이프수로(10), 대구경파이프하류취수구연결관(10-1), 하도(11), 하천수(12,12'),하상토(13), 취수구(20,30), 수중보(21, 32), 어도(22,33), 취수관(23), 펌프(24), 생태공원용수공급관(25), 배수관 (26), 수문(31,50), 대구경외관(40), 내관(41), 유도철책(42), 조명장치 (43), 토양(44), 내관지지대(45), 배수로(46), 고무판(47), 패널(48), 방음벽(49), 제방(51), 터널식 야생동물 이동통로(52), 상류:A, 중앙부:B, 하류:C , 홍수위: x, 평수위: yNatural Purification Facility (1), Pumping Facility (2), Natural Reservoir Maintenance Facility (3,6), Ecological Park (4), Eco-Friendly River Top Road (5), Coriander Site (7), Dike Road (8), Large-diameter pipe canal (10), large-diameter pipe downstream inlet connection pipe (10-1), sewer (11), river water (12, 12 '), riverbed soil (13), water intake (20, 30), submerged (21, 32, fishery (22, 33), water intake pipe (23), pump (24), ecological park water supply pipe (25), drainage pipe (26), sluice gate (31, 50), Daegu external view (40), inner pipe (41) ), Guide rail (42), lighting device (43), soil (44), inner pipe support (45), drainage passage (46), rubber plate (47), panel (48), soundproof wall (49), bank (51), Tunnel Wildlife Driveway (52), Upstream: A, Center: B, Downstream: C, Flood Level: x, Ground Level: y

상기 목적을 달성하기 위하여 본 발명은 하천수(13)가 흐르는 하도(11)의 상하류지역에 물막이 수중보(21,32,) 및 어도(22,33)를 설치하여 물의 흐름을 일정하게 하고 물고기의 왕래를 자유롭게하였으며, 하천바닥 하부에 다수개의 대구경파이프수로(10)를 매설하여 하천수를 재순환하거나 홍수시 바이패스시켜 홍수시 과다 유량을 흡수하였고, 상기 대구경파이프수로(10)내 하단부에 연결된 취수시설과 고수부지(7)에 설치된 양수장(1)에 의해 물을 취수하여 자연정화 시설(2)을 이용하여 정화하였고, 상기 하도(11)의 양측지역의 경사면 호안에 설치된 자연형 호안정비시설(6)의 상부에는 일정면적을 형성된 하상도로(5)의 하부에 일정간격으로 생태공원(4)의 인공호수(또는 인공연못)과 연계하여 형성된 다수개의 터널식 야생동물 이동통로(52)를 설치하였으며, 상기 자연정화시설(1)에 의해 정화된 물을 자연정화시설(1)의 측면에 형성된 상기 생태공원(4)과, 배수관(26)에 의해 정수된 물을 하도(11)로 배출하였으며, 상기 생태공원(4) 및 고수부지(7)의 바깥쪽 측면에 경사면으로 형성된 자연형 호안정비시설(6)과, 상기 자연형호안정비시설(6)의 상부에 제방도로(8)로 이루어진 한국형 도심지 하천복원공법 및 그 설비에 관한 것이다.In order to achieve the above object, the present invention installs water barriers (21, 32, and fish) (22, 33) in the upstream and downstream regions of the river channel (11) through which the river water (13) flows to keep the flow of water constant The large-diameter pipe canal (10) was buried under the river bed to recirculate or bypass the flood water to absorb excess flow during flooding, and the water intake connected to the lower part of the large-diameter pipe canal (10). Water was collected by the water tank (1) installed at the facility and the ciliary site (7) and purified using a natural purification facility (2). In the upper part of 6), a plurality of tunnel-type wild animal moving passages 52 formed in connection with the artificial lake (or artificial pond) of the ecological park 4 at regular intervals were installed at the lower part of the lower road 5 having a predetermined area. , The water purified by the natural purification facility (1) discharged the water purified by the ecological park (4) and the drain pipe 26 formed on the side of the natural purification facility (1) to the sewer (11), Korean-style urban center consisting of a natural lake safety facility (6) formed on a slope on the outer side of the ecological park (4) and cilantro site (7), and a levee road (8) on the natural lake safety facility (6) It relates to the river restoration method and its facilities.

본 발명은 첫째, 홍수시 과다 유량 유입구 및 방출수문을 갖추면서 평수위시에는 하천수 재순환의 용도를 가지는 하류 취수구 및 상류 취수시설을 갖춘 대구경 파이프를 복원하고자 하는 도심지 하천의 하도밑에 설치하여 도심지 하천의 일정수량 확보 및 홍수시에 고수부지내의 생태공원 시설을 보호하고자 하였고,First, the present invention has a constant flow rate of urban streams by installing under a river stream to restore large diameter pipes having downstream intake and upstream intake facilities having the use of river water recirculation at the time of pyeongsu, while having excessive flow inlets and discharge gates during flooding. In order to protect the ecological park facilities in the site of the flood waters,

특히 상류에 풍부한 수량을 갖추지 못한 도심지 하천의 경우, 일정 유량을 확보해야하는 면에서 많은 곤란을 겪고 있는데 본 공법을 채용하게 되면 타하천에서의 용수도입 또는 지하수 양수를 사용한 용수 확보를 안해도 가능하며, 지하수 양수로 인한 도심지 지반 침하의 어려움을 겪지 않아도 되며,Especially in the case of urban rivers that do not have abundant water upstream, they have a lot of difficulties in securing a certain flow rate.If this method is adopted, it is not necessary to secure water by introducing water from other rivers or using groundwater pumping. You don't have to go through the subsidence of urban grounding

둘째, 재순환된 하천수를 상류의 강관파이프내 취수원에서 양수하여 일부는 자연정화 시설로, 일부는 복원된 하천으로 방류하는 시스템을 채택하였으며, 접촉산화시설 및 습생식물 정화 시설 등의 자연정화 시설을 거친 하천수는 고수부지에 만들어진 생태공원 및 생태학습장등을 순환하도록 하여 보다 깨끗한 수변 환경을 요구하는 많은 수생생물들이 도심지 복원 하천에 적응되도록 만들었다. 그리고 상류 및 하류의 수중보에 계단식 어도를 만들어 복원된 도심지 하천을 통해 상류에서 하류, 또는 하류에서 상류로 물고기의 이동이 자유롭게 하였으며,Second, the recycled river water was pumped from the intake pipe in the upstream steel pipe, so that some were discharged into natural purification facilities, and some were restored to restored rivers, and they went through natural purification facilities such as contact oxidation facilities and wet plant purification facilities. The streams have been circulated through ecological parks and eco-learning sites built on the grounds, allowing many aquatic creatures that require a cleaner waterfront environment to adapt to urban restoration rivers. In addition, the fish can be freely moved from the upstream to the downstream or the downstream to the upstream through the restored downtown river by creating a cascaded fishery on the upper and downstream underwater beams.

세 번째는 도심지의 과다한 교통량을 분산하기 위해 만든 하상도로 시설을 하천 복원의 명분으로 폐기 시키지 않은 채 복원된 하천과 생태공원과의 조화성을 중시한친환경 도로(서식 생물의 휴식을 위하여 야간 및 심야 통행 금지 및 야생동물 이동통로 설치 및 친자연적 울타리 설치등)로 재 가공하여 도심지내의 교통량 분산을 일정량 담당할 수 있도록 하였고,Third, eco-friendly roads that emphasize the harmony of restored rivers and ecological parks without discarding facilities that were created to disperse excess traffic in urban areas for the purpose of river restoration. Prohibits and installs wildlife movement passages, installs natural fences, etc.

넷 째, 복원된 도심지 하천내의 고수부지내에 생태공원 및 생태학습장을 설치하여 자연환경의 접촉이 어려운 도시민들에게 자연의 풍부한 휴식을 주며 어린이들에게는 자연의 소중함을 깨닫을수 있는 학습장이 되도록 하였다.Fourth, ecological parks and eco-learning sites were installed in the restored grounds in urban rivers to provide abundant rest for nature to city residents who have difficulty in contact with the natural environment and to be a learning place for children to realize the importance of nature.

그리고 이러한 시설물이 홍수시에 피해를 입지 않도록 하도밑에 설치된 홍수시 과다 유량 바이패스 (BY-PASS) 배출 대구경 파이프를 설치하였다.In order to prevent these facilities from being damaged during flooding, a large-diameter discharge pipe (BY-PASS) discharged under flooding was installed.

본 발명을 크게 3 부분으로 나누어 세부 설명을 할 수 있다.The present invention can be divided into three parts and described in detail.

첫째, 도심지 하천복원이 시작되는 상류지역의 물막이 수중보 및 어도, 홍수시 과다 유량 흡입구, 하도밑에 설치한 하천수 재순환 및 홍수시 바이패스 통로내 하단부에 설치된 취수 시설, 그리고 고수부지에 설치된 양수장 및 자연정화 시설로 이루어져 있으며,(도.3).Firstly, water barriers and fisheries in the upstream areas where urban river restoration begins, excessive flow intake during flooding, recirculation of river water installed under the sewers and intake facilities installed at the bottom of the bypass passages during flooding, and pumping stations and natural purification installed in the sediment site. It consists of facilities (Fig. 3).

우선 대구경 파이프로 이루어진 하천수 재순환 및 홍수시 바이패스 통로는First of all, the bypass passage for river water recycling and flooding

하수정화 처리를 거치지 않은 오염된 하천수가 흐르던 도심지 하도 아래의 심하게 부패된 하상토양을 굴착하여 폐기물처리장에 반출 처리후, 10년빈도 이상의 홍수 유량을 바이패스 처리할수 있는 관경의 대구경 파이프를 매설하고 깨끗한 하상토양을 충진하여 수생생물이 하천에 복원할 수 있는 환경을 만들어 준다.Excavate the badly decomposed bottom soils under the urban sewerage where the contaminated river water has not gone through the sewage treatment process and take them out to the waste treatment plant, and then bury large diameter pipes with diameters capable of bypassing flood flows over 10 years. Filling riverbed soils creates an environment in which aquatic life can be restored to rivers.

그리고 상류에서 흘려온 물은 일단 물막이 수중보를 통하여 물의 흐름을 일정하게 하며, 수중보에 설치되는 계단식 어도를 통하여 물고기의 왕래를 자유롭게 할 수있도록 한다.And the water flowing from the upstream once the water flow through the water basin, and the water flows through the stepped esophagus that is installed on the underwater beams to free the coming and going of the fish.

수중보 상류 양측지역의 호안에는 제방을 설치하여 홍수시의 과다 유량이 고수부지내의 양수장 시설 또는 자연 정화 시설에 피해를 주지 않도록 하였으며, 수중보 상류 10m 전방 지역에 수중보 보다 높게 설치한 홍수시 과다 유량 유입구로 홍수시의 과다 유량이 자유롭게 유도되도록 하였다.An embankment was installed on both sides of the upstream subwater basin to prevent the excess flow during flooding from damaging the pumping facility or natural purification facility in the reservoir site. Excessive flow rates during flooding were induced freely.

또한 하천수 재순환 및 홍수시 바이패스 통로내의 하단부에 설치된 취수시설을 통하여 양수된 하천수는 양수장에서 양을 조절 분리하여 일부는 자연정화 시설을 거친 후, 생태공원 및 생태학습장의 용수로 사용되도록 하였으며, 나머지 하천수는 복원된 하천 지역에 방류하여 하천 수량이 항상 일정량을 유지하도록 하였다.In addition, the river water pumped through the intake facility installed at the lower part of the bypass passage in case of river water recirculation and flooding is controlled and separated from the pumping station, and some of them go through the natural purification facility and then used as water for ecological parks and eco-learning sites. Has discharged to the restored river area so that the quantity of the river is always kept constant.

그리고 자연정화 시설에는 접촉산화식 정화시설 및 습생정화식물에 의한 정화지를 만들어 보다 깨끗한 물이 생태공원 및 생태학습장으로 유입되도록 하였다.In addition, natural purification facilities were made by catalytic oxidation purification plants and wetland purification plants to make clean water flow into eco-parks and eco-learning sites.

두번째는 복원 대상 도심지 하천의 중류지역으로 하천수가 흐르는 하도밑에는 하천수 재순환 및 홍수시 바이패스 수로용의 대구경 파이프를 매설하며, 하상토양은 깨끗한 토양으로 치환하여 충진한다.The second is the midstream of the stream to be restored, and under the river flows, large-diameter pipes for river water recirculation and bypass channels are flooded. Subsoil is filled with clean soil.

그리고 호안지역에는 자연성 호안 정비 재료를 이용하여 호안 복원정비를 실시하며 하천에서 제방까지 연결된 생태시스템을 갖추도록 한다.In the coastal areas, the coastal waters will be reconstructed and repaired by using natural revetment materials.

하상도로는 일정부분마다 터널식 야생동물 이동통로 (당사 기특허출원공법 <대구경강관 압입추진공을 이용한 생태계 이동로 시공방법 출원번호 10-2002-0011899> 적용 가능)을 생태공원의 호수와 연계 설치하여 하천지역 및 호안지역, 고수부지내의 생태공원 및 생태 학습장에로의 동물이동이 끊어지지 않도록 하였으며 야간 및 심야에 서식생물의 안정된 휴식을 위하여 차량 통행금지를 실시한다.In certain parts of Hasang-ro, tunnel-type wild animal movement passages (applicable to the company's patent application method <applicable to the method of construction of ecosystem movement path using Daegu light pipe indentation propulsion application application number 10-2002-0011899>) are installed in conjunction with the lake of the ecological park. The movement of animals to ecological parks and eco-learning sites in river areas, lakeside areas and cilantro areas is not interrupted, and vehicle traffic is prohibited to ensure stable rest of the habitats at night and at night.

또한 하상도로는 친환경적 도로로 부설하며 도로 양측에는 울타리를 설치하여 서식동물들이 차량으로 인한 피해를 입지 않도록 한다.In addition, riverbeds are laid as eco-friendly roads and fences are installed on both sides of the roads to prevent habitat animals from being damaged by vehicles.

그리고 고수 부지내에는 생태공원 및 생태 학습장을 설치하여 자연환경의 접촉이 어려운 도시민들에게 자연의 풍부한 휴식을 주며 특히 어린이들에게는 자연의 소중함을 깨닫을수 있는 학습장이 되도록 하였다.In addition, ecological parks and eco-learning centers have been set up in the Kosu site to provide abundant rest for nature to those in need of contact with the natural environment, and especially for children to learn the importance of nature.

세번째는 도심지 하천 복원이 끝나는 하류지역으로 물막이 수중보를 통하여 복원된 하천내의 유량이 일정하도록 하였으며, 수중보에는 계단식 어도를 설치하여 하류에서 올라오는 물고기들의 왕래를 자유롭도록 하였다.The third is the downstream area where urban stream restoration is completed, and the flow rate in the restored river through the submerged underwater basin is constant, and the underwater basin is provided with a cascading fishnet to freely move the fish coming from the downstream.

또한 수중보 전방 10m 의 상류지역에는 하천수 재순환 및 홍수시 바이패스 수로에 연결된 취수 파이프를 가진 취수구를 평수위 중간지점에 설치하여 수중보에 의해 저수된 하천수가 자연스럽게 하천수 재순환 통로로 흘려들도록 하였으며 이 취수구에는 수문을 설치하여 홍수시에는 하천수가 유입되지 못하도록 하여 홍수시의 하천수 역류현상을 차단하였다.In addition, in the upstream area of 10m in front of the submerged walkway, an intake port with a intake pipe connected to the bypass channel in case of water recirculation and flooding was installed at the middle point of the Pyeongsu level so that the streams stored by the submerged stream naturally flow into the river recirculation passage. The installation prevented the inflow of river water during flooding, thus preventing the backflow of river water during flooding.

그리고 하천수 재순환 및 홍수시 바이패스 수로 기능을 가지는 대구경 파이프는 수중보 하류지역의 하도에 노출되게 하였으며, 홍수시에는 수문을 개방하여 상류지역의 과다 유량을 대구경 파이프를 통하여 하류로 바이패스 시켜 복원된 하천의 피해를 최소화하도록 하였다.In addition, large-diameter pipes with a bypass channel function during river water recirculation and flooding were exposed to the sewer of the submerged downstream area.In the event of a flood, the floodgate was opened by bypassing the excess flow in the upstream area through the large-diameter pipe downstream. To minimize the damage.

이하 본 발명을 실시예를 참고하여 설명하면 다음과 같다.Hereinafter, the present invention will be described with reference to Examples.

실시예Example

제1공정1st process

하천수(13)가 흐르는 하도(11)의 양측지역의 경사면 호안에 도1내지 도3과 같이 자연형 호안정비시설(6)을 설치하여 홍수시의 과다 유량이 고수부지(7)내의 양수장(2) 또는 생태공원(4)에 피해를 주지 않도록 하였으며, 상기 자연형 호안정비시설(6)의 상부에는 일정면적을 형성시켜, 하상도로(5)를 설치하여 도시교통의 소통을 원활하게 하였으며, 상기 하상도로(5)의 바깥쪽 측면에는 생태공원(4) 및 고수부지(7)를 설치하여 시민들이 휴식과 운동을 할 수 있게 하였고, 상기 고수부지(7)의 상류 일측에 자연정화시설(1)을 설치하여, 양수장(2)에서 취수된 물을 정화시켜 하도(11)에 배출하며, 상 자연정화시설(1)의 측면에 형성된 생태공원(4)에 물을 공급하도록 하여 하천수를 정화시켰고, 상기 생태공원(4) 및 고수부지(7)의 바깥쪽 경사면 제방에는 자연형 호안정비시설(6)을 설치하여 홍수시의 과다 유량이 제방을 넘어 주택가에 피해를 주지 않도록 하였고, 상기 자연형호안정비시설(6)의 상부에는 제방도로(8)를 설치하여 도시교통의 소통을 원활하게 하였으며,A natural type lakeside maintenance facility (6) is installed on the slopes of both sides of the sewer (11) through which the river water (13) flows. ) Or ecological park (4) was not damaged, and a certain area was formed on the upper part of the natural recreational maintenance facility (6), and a riverbed (5) was installed to facilitate communication of city traffic. On the outer side of the riverbed (5), an ecological park (4) and a cilantro site (7) were installed to allow citizens to rest and exercise, and a natural purification facility (1) upstream of the cilantro site (1). ) To purify the water taken from the pumping station (2) to discharge to the sewer (11), and to supply the water to the ecological park (4) formed on the side of the phase natural purification facility (1) to purify the river water On the banks of the outer slopes of the ecological park (4) and coriander site (7), natural type lake rest The non-facilities (6) were installed to prevent excessive flow rate during flooding and damage to residential areas. The upper part of the natural relief service facility (6) installed a dike road (8) to communicate urban traffic. Smoothly,

친환경형 하상도로(5)는 일정부분마다 터널식 야생동물 이동통로(52)를 대구경강관 압입추진공을 이용한 생태계 이동로 시공방법에 따라 설치하였고, 상기에서 터널식 야생동물 이동통로(25)는 도18내지 도19에 도시된 바와 같이, 야생동물에게 환경적인 위화감을 주지 않기 위해 내관(41)의 내부에 친환경적인 접착재료를 이용하여 통나무 벽면 등의 패널(48)을 시공하고, 벽면 사이에 넝클등을 삽입하고, 일정조명을 위한 조명장치(43)를 내관(41) 천정 일측에 설치하며, 야생동물의 이동시 내관(41)의 바닥에서 오는 위화감을 줄이기 위해 토양(흙바닥)(44)을 설치한 다음,도로의 하단에 매설된 외관(40)의 양선단부에서 고수부지지역으로 약 5m 정도의 방음벽(49)을 설치하고, 야생동물을 상기와 같이 시공된 이동로로 유도하기 위하여 도로의 측면에서 고수부지안으로 2m 떨어져 설치한 상기와 같이 시공된 이동로의 선단부와 도로측면을 완만한 경사로 연결하는 유도철책을 설치하여 하천지역 및 호안지역, 고수부지내의 생태공원 및 생태 학습장에로의 동물이동이 끊어지지 않도록 하였고,Eco-friendly riverbed (5) was installed in accordance with the construction method of the ecosystem-type movement path using the tunnel-type wildlife movement passage 52 for each part, the tunnel-type wildlife movement passage 25 is shown in Figure 18 As shown in Figure 19, in order not to give a sense of environmental discomfort to the wild animals, the panel 48, such as the log wall surface using a environmentally friendly adhesive material inside the inner tube 41, the shank, etc. between the walls Inserting, and installing the lighting device 43 for constant lighting on one side of the inner tube (41) ceiling, and install the soil (dirt floor) 44 to reduce the discomfort coming from the bottom of the inner tube (41) during the movement of wild animals. Next, install a soundproof wall 49 of about 5 m from both ends of the exterior 40 buried at the bottom of the road to the coriander site area, and to guide the wildlife to the constructed moving path as described above. Coriander site in By installing guide rails that connect the front end of the moving road and the side of the road, which are installed 2m away, to the slope, the movement of animals to the ecological parks and eco-learning grounds in the river area, the coastal area and the reservoir is not broken. So that

제2공정2nd process

하수정화 처리를 거치지 않은 오염된 하천수가 흐르던 도심지 하도(11)의 바닥에 심하게 부패된 하상토양을 굴착하여 폐기물처리장에 반출 처리후, 10년빈도 이상의 홍수 유량을 바이패스 처리할 수 있는 관경의 대구경파이프수로(10)를 다수개 매설하고, 상기 대구경파이프수로(10)의 상부에 깨끗한 하상토(13)를 복토하여 수생생물이 하천에 복원할 수 있는 환경을 만들어 준 다음,Large diameter of diameter that can bypass flooding flow rate over 10 years after excavating severely depleted bottom soil at the bottom of urban sewer (11) where polluted river water that has not undergone sewage treatment is taken out to waste treatment plant A plurality of pipe channels 10 are embedded, and a clean river bed 13 is covered on the upper part of the large-diameter pipe channel 10 to create an environment in which aquatic organisms can be restored to the river.

하도(11) 상류(A)의 일측에 하도(11)의 바닥에 매설된 다수개의 대구경파이프수로 (10)의 상류측 말단부가 상부로 경사지게 연장되어 하천수(12)의 상부까지 돌출되게 설치하고, 저수된 하천수(12)가 자연스럽게 대구경파이프수로(10)로 흘려들도록 상기 다수개의 대구경파이프수로(10)의 상류측 말단부에 취수구(20)를 설치하였고, 상기 다수개의 대구경파이프수로(10)의 내부하부일측에 펌프(24)를 설치하여, 상기 펌프(24)에 연결된 취수관(23)을 통해 고수부지(7)에 설치된 양수장(2)에 취수관(23)을 통해 고수부지(7)에 설치된 양수장(2)에 취수토록 하고, 상기 양수장(2)에 일측에 형성되어 자연정화시설(1)을 통해 정화시킨 다음, 정수된 물을 배수관(26)을 통해 하도(11)로 배출시켜 하도(11)를 정화시키며,Upstream end of the plurality of large-diameter pipe channels 10 buried at the bottom of the underpass 11 at one side of the upstream 11 A extends inclined upward and is installed to protrude to the upper portion of the river water 12. In order to naturally flow into the large-diameter pipe channel 10, the intake port 20 is installed at the upstream end of the plurality of large-diameter pipe channel 10, and the plurality of large-diameter pipe channel ( The pump 24 is installed on the inner lower side of 10), and the cistern site is connected to the pumping station 2 installed in the cistern site 7 through the intake pipe 23 connected to the pump 24 through the intake pipe 23. Intake in the pumping station (2) installed in the (7), formed on one side in the pumping station (2) to purify through the natural purification facility (1), and then purified water through the drain pipe (26) To purify the roadway (11),

상기 다수개의 대구경파이프수로(10)의 취수구(20)를 중심으로 하류쪽 후방 10m 의 후방지역에 어도(22)가 경사지게 설치된 수중보(21)를 형성시켜By forming the underwater beam 21 inclined in the rear region 10 m downstream of the water intake port 20 of the plurality of large-diameter pipe canal (10) is inclined

상류에서 흘려온 물은 일단 물막이 수중보(21)를 통하여 물의 흐름을 일정하게 하며, 상기 수중보(21)에 설치되는 계단식 어도(22)를 통하여 물고기의 왕래를 자유롭도록 하였으며,Water flowing from the upstream once the flow of water through the water barrier 21 to maintain a constant flow, and freely coming and going fish through the stepped esophagus 22 installed in the underwater beam 21,

제3공정3rd process

상기 하도(11)의 하상토(13)의 하부에 매설된 다수개의 대구경파이프수로(10)의 하류측 일측에 수직으로 돌출되는 대구경파이프하류취수구연결관(10-1)을 형성시켜 하천수(13)의 수위까지 연장되게 하여 상기 대구경파이프하류취수구연결관(10-1)의 말단부에 설치된 취수구(30)입구에 수문(50)을 설치하여 대구경파이프수로(10)에 하천수(13)를 유입시켜 홍수시에는 하천수가 유입되지 못하도록 하여 홍수시의 하천수 역류현상을 차단하도록 하였으며,The large-diameter pipe downstream intake connection pipe 10-1 is formed to protrude perpendicularly to the downstream side of the plurality of large-diameter pipe channels 10 embedded in the lower portion of the lower soil 13 of the lower road 11 to form a river water ( 13) to extend the water level of the large diameter pipe downstream inlet port 10-1 of the water inlet 30 is provided in the inlet 30 is installed in the inlet 30 to install the river water (13) in the large diameter pipe channel 10 It prevented the inflow of river water during the flood, so as to block the backflow of the river water during the flood.

상기 다수개의 대구경파이프수로(10)의 하류 끝단부는 상부로 경사지게 연장되어 하천수(12)의 상부까지 돌출되어 설치한 후 끝단부에 다수개의 수문(31)을 설치하여 홍수시에 다수개의 대구경파이프수로(10)내에 바이패스된 물을 배출 또는 차단하게 하고, 상기 대구경파이프하류취수구연결관(10-1)과 수문(31)의 사이에 어도 (33)가 경사지게 설치된 수중보(32)를 형성시켜, 상류에서 흘려온 물은 일단 물막이 수중보(32)를 통하여 물의 흐름을 일정하게 하며, 상기 수중보(32)에 설치되는 계단식 어도(33)를 통하여 물고기의 왕래를 자유롭도록 한 한국형으로 도심지 하천을 복원하도록 시공하였다.The downstream ends of the plurality of large-diameter pipe canals 10 extend inclined upwardly to protrude to the upper portion of the river water 12, and then a plurality of large-diameter pipes are installed at the ends by flooding. Discharge or shut off the bypassed water in the waterway 10, and forms an underwater beam 32 inclined by an airway 33 between the large diameter pipe downstream inlet connection pipe 10-1 and the water gate 31. The water flowing from the upstream, once the water flow through the submersible submersible (32) to the constant flow, and through the stepped esophagus (33) installed in the submerged beams (32) in the Korean-style to free the traffic of the city stream It was constructed to restore.

이하 본 발명을 도면을 참고하여 설명하면 다음과 같다.Hereinafter, the present invention will be described with reference to the drawings.

도1은 본 발명의 도심지 하천복원 공법 전체상세도, 도2는 본 발명의 도심지 하천복원 공법 전체 정면상세도, 도3은 본 발명의 도심지 하천복원 공법 상류 측면상세도, 도4는 본 발명의 도심지 하천복원 공법 상류 평면상세도, 도5는 본 발명Figure 1 is a detailed view of the downtown river restoration method of the present invention, Figure 2 is a full front detail of the downtown river restoration method of the present invention, Figure 3 is a downtown side restoration method upstream side detail view of the present invention, Figure 4 is Downtown river restoration construction upstream plan detail view, Figure 5 is the present invention

의 도심지 하천복원 공법 상류 정면상세도, 도6은 본 발명의 도심지 하천복원 공법 중간부 평면상세도, 도7은 본 발명의 도심지 하천복원 공법 중간부 측면상세도, 도8은 본 발명의 도심지 하천복원 공법 중간부 정면상세도, 도9는 본 발명의 도심지 하천복원 공법 하류 평면상세도, 도10은 본 발명의 도심지 하천복원 공법 하류 측면상세도, 도11은 본 발명의 도심지 하천복원 공법 하류 정면상세도, 도12는 종래의 자연형 하천복원공법 상세도, 도13내지 도17은 종래의 블록공법 상세도, 도18는 본 발명의 제방도로에 설치된 터널식 야생동물 이동통로 평면상세도, 도19은 본 발명의 제방도로에 설치된 터널식 야생동물 이동통로 측면상세도를 도시한 것이며, 자연정화시설(1), 양수시설(2), 자연형 호안정비시설(3,6), 생태공원(4), 친환경형 하상도로(5), 고수부지(7), 제방도로(8), 대구경파이프수로(10), 대구경파이프하류취수구연결관(10-1), 하도(11), 하천수(12,12'),하상토(13), 취수구(20,30), 수중보(21, 32), 어도(22,33), 취수관(23), 펌프(24), 생태공원용수공급관(25), 배수관(26,27), 수문(31,50), 대구경외관(40), 내관(41), 유도철책(42), 조명장치(43), 토양(44), 내관지지대(45), 배수로(46), 고무판(47), 패널(48), 방음벽(49), 제방(51), 터널식야생동물 이동통로(52), 상류:A, 중앙부:B, 하류:C ,홍수위: x, 평수위: y를 나타낸 것임을 알 수 있다.The downtown river restoration method upstream front detail view of the downtown river restoration method of the present invention, Figure 6 is a plan view of the middle portion of the downtown river restoration method of the present invention, Figure 7 is the middle side detail view of the downtown river restoration method of the present invention, Figure 8 is a downtown river of the present invention 9 is a plan view of the downstream downtown restoration method of the present invention, FIG. 10 is a downstream side elevation view of the downtown river restoration method of the present invention, and FIG. 11 is a downstream view of the downtown river restoration method downstream of the present invention. Fig. 12 is a detailed view of a conventional natural river restoration method, Figs. 13 to 17 are detailed views of a conventional block method, and Fig. 18 is a detailed plan view of a tunnel-type wild animal moving passage installed on the embankment road of the present invention. Figure 3 shows a detailed view of the tunnel-type wildlife movement passage installed on the embankment road of the present invention, natural purification facility (1), pumping facility (2), natural lake safety facility (3, 6), ecological park (4) , Eco-friendly riverbed (5), high Site (7), embankment road (8), large diameter pipe waterway (10), large diameter pipe downstream inlet connection pipe (10-1), sewer (11), river water (12, 12 '), riverbed soil (13), Water intakes (20, 30), underwater beams (21, 32), fisheries (22, 33), intake pipes (23), pumps (24), ecological park water supply pipes (25), drain pipes (26, 27), sluice gates (31) 50, large diameter exterior 40, inner tube 41, guide rail 42, lighting device 43, soil 44, inner tube support 45, drainage 46, rubber plate 47, panel ( 48, the soundproof wall 49, the embankment 51, the tunnel-type wild animal moving passage 52, the upstream: A, the central portion: B, the downstream: C, the flood level: x, the surface water level: y can be seen that.

구조를 살펴보면 도1내지 도2와 같이 도심지 하천에 있어서, 바닥에 하상토(13)가 있으며 상기 하상토(13)의 상부에 하천수(12)가 흐르는 하도(11)와, 상기 하도(11)의 상,하류측에 형성된 수중보(21,32)와, 상기 하도(11)의 하부에 매설된 다수개의 대구경파이프수로(10)와, 상기 하도(11) 상,하류측의 수중보(21,32) 일측에 형성되어 있으며 상기 다수개의 대구경파이프수로(10)로 물을 유입시키는 취수구 (20,30)와, 상기 하도(11)의 최상부 양쪽에 경사면으로 형성된 제방에 형성된 자연형 호안정비시설(6)과, 상기 자연형 호안정비시설(6)의 상부에 형성된 하상도로(5)와, 상기 하상도로(5)의 바깥쪽 측면에 형성된 생태공원(4) 및 고수부지(7)와, 상기 생태공원(4) 및 고수부지(7)의 상류쪽 일측에 형성된 자연정화시설(1)과,Looking at the structure as shown in Figures 1 to 2 in the downtown rivers, there is a riverbed (13) at the bottom and the river water (12) flowing the river water 12 on the top of the riverbed (13), and the sewer (11) Submerged beams 21 and 32 formed on the upper and downstream sides of the pipes, a plurality of large-diameter pipe channels 10 embedded in the lower portion of the lower road 11, and the underwater beams 21, which are disposed on the lower and upper roads 11 and 12, respectively. 32) It is formed on one side and the water intake port (20, 30) for introducing water into the plurality of large diameter water pipe (10), and the natural lake safety facility formed on the embankment formed on both sides of the top of the channel 11 (6), a riverbed (5) formed on the upper part of the natural lake safety facility (6), an ecological park (4) and cilantro site (7) formed on the outer side of the riverbed (5), A natural purification facility (1) formed at an upstream side of the ecological park (4) and a cilantro site (7),

상기 친환경형 하상도로(5)의 하부에 일정간격으로 생태공원(4)의 인공호수(또는 인공연못)과 연계하여 형성된 다수개의 터널식 야생동물 이동통로(52)와,A plurality of tunnel-type wildlife movement passages 52 formed in association with an artificial lake (or artificial pond) of the ecological park 4 at a predetermined interval in the lower portion of the eco-type riverbed road 5,

상기 자연정화시설(1)의 측면에 형성된 상기 생태공원(4)에 물을 공급하는 생태공원용수공급관(25)과, 상기 자연정화시설(1)의 또다른 일측에 형성된 양수장(2)과, 상기 양수장(2)에 연결되어 있으며, 다수개의 대구경파이프수로(10)의 하부 일측에서 형성된 펌프(24)에 또다른 일측이 연결되어 물을 취수하는 취수관(23)과, 상기 양수장(2)의 또다른 일측에 형성되어 자연정화시설(1)을 통해 정수된 물을 하도(11)로 배출하는 배수관(26)과, 상기 생태공원(4) 및 고수부지(7)의 바깥쪽 측면에 경사면으로 형성된 자연형 호안정비시설(6)과, 상기 자연형호안정비시설(6)의 상부에 형성된 제방도로(8)로 구성된 한국형 도심시 하천설비인 것이다.An ecological park water supply pipe (25) for supplying water to the ecological park (4) formed on the side of the natural purification facility (1), a pumping station (2) formed on the other side of the natural purification facility (1), Is connected to the pumping station (2), the other side is connected to the pump 24 formed at the lower one side of the plurality of large diameter water pipe (10) and the water intake pipe 23 and the pumping station (2) On the other side of the c) is formed on the drain pipe (26) for discharging the purified water through the natural purification facility (1) to the sewer (11), and on the outer side of the ecological park (4) and coriander site (7) It is a Korean urban urban river equipment consisting of a natural lake safety facility (6) formed by the slope and the embankment road (8) formed on the natural lake safety facility (6).

상기 상류(A)의 하도(11)를 살펴보면, 도3내지 도5에 나타난 바와 같이,Looking at the bottom 11 of the upstream (A), as shown in Figures 3 to 5,

하도(11)의 하상토(13)의 하부에 매설된 다수개의 대구경파이프수로(10)의 상류측일단이 상부로 경사지게 연장되어 하천수(12)의 상부까지 돌출되어 형성된 말단부와, 상기 다수개의 대구경파이프수로(10)의 말단부에 형성되어 있고 물을 유입또는 차단시키는 취수구(20)와, 상기 다수개의 대구경파이프수로(10)의 하부일측에서 형성된 펌프(24)와, 상기 펌프(24)에 연결되어 있으며 또다른 일측에는 양수장(2)에 연결되어 물을 취수하는 취수관(23)과, 상기 양수장(2)의 또다른 일측에 형성되어 자연정화시설(1)을 통해 정수된 물을 하도(11)로 배출하는 배수관(26)과,And a plurality of end portions formed by protruding upward one end of the plurality of large-diameter pipe channels 10 embedded in the lower portion of the lower soil soil 13 of the lower road 11 so as to protrude upward to the upper portion of the river water 12; A water intake port 20 formed at a distal end of the large-diameter pipe channel 10 and a pump 24 formed at one lower side of the plurality of large-diameter pipe channel 10 and the pump 24 Is connected to the other side of the intake pipe (2) is connected to the water intake pipe (23) and the water is formed on the other side of the pumping station (2) and purified water through the natural purification facility (1) Drain pipe (26) for discharging to the lower road (11),

상기 취수구(20)를 중심으로 하류쪽에 형성된 수중보(21)와, 상기 수중보(21)의 하류쪽 일측에 연결되어 형성된 어도(22)로 구성되어 있으며,Is composed of a submerged beam 21 formed on the downstream side around the intake port 20, and the fishery 22 formed connected to the downstream side of the submerged beam 21,

상기 하도(11)의 중앙부(B)를 살펴보면, 도6내지 도8에 나타난 바와 같이,Looking at the central portion (B) of the lower road 11, as shown in Figure 6 to 8,

상기 하도(11)에 흐르는 하천수(12)의 하부에 형성된 하상토(13)와, 상기 하상토(13)의 하부에 매설된 다수개의 대구경파이프수로(10)로 구성되어 있고,It is composed of a bottom soil 13 formed in the lower portion of the river water 12 flowing in the lower road 11, and a plurality of large diameter pipe water channel 10 embedded in the lower portion of the bottom soil 13,

상기 하도(11)의 하류(C)를 살펴보면, 도9내지 도11에 나타난 바와 같이 하도(11)의 하상토(13)의 하부에 매설된 다수개의 대구경파이프수로(10)의 하류측 일측에 수직으로 돌출되어 하천수(13)의 수위까지 연장되어 형성된 대구경파이프하류취수구연결관(10-1)과, 상기 대구경파이프하류취수구연결관(10-1)의 말단부에 형성된 대구경파이프수로(10)에 물을 유출입시키는 취수구(30)와, 상기 취수구(30)에 설치된 수문(50)과, 상기 다수개의 대구경파이프수로(10)의 하류 끝단부가 상부로 경사지게 연장되어 하천수(12)의 상부까지 돌출되어 형성되어 있으며, 상기 끝단부에다수개의 대구경파이프수로(10)내에 저장된 물을 배출 또는 차단하는 수문(31)과, 상기 대구경파이프하류취수구연결관(10-1)과 수문(31)의 사이에 형성된 수중보(32)와, 상기 수중보(32)에 형성된 어도(33)로 구성되어 있음을 알 수 있는 것이다.Looking at the downstream (C) of the lower road 11, as shown in Figures 9 to 11, one side of the downstream side of the plurality of large-diameter pipe channel 10 embedded in the lower portion of the lower soil 13 of the lower road 11 Large diameter pipe downstream inlet connection pipe 10-1 formed to protrude perpendicularly to the water level of the river water 13 and the large diameter pipe water channel 10 formed at the distal end of the large diameter pipe downstream intake pipe 10-1. Intake port 30 for flowing water in and out, the water gate 50 installed in the intake port 30, and the downstream ends of the plurality of large-diameter pipe channel 10 is inclined upwardly to the top of the river water (12) It is formed to protrude up to the end, the sluice 31 for discharging or blocking the water stored in the plurality of large diameter pipe channel 10, and the large diameter pipe downstream inlet connection pipe (10-1) and sluice (31) ) The underwater beam 32 formed between and the fishbone formed in the underwater beam 32 33).

상기에서 수중보(21,32)의 일측에 형성된 어도(22,33)는 통상 알려진 형태의 수중보에 경사지게 설치된 어도를 사용하였다The above-mentioned fishes 22 and 33 formed on one side of the underwater beams 21 and 32 used fishes installed inclined to the underwater beams of a generally known type.

본 발명의 하상도로(5)의 하부에 일정간격으로 다수개 설치된 터널식 야생동물 이동통로(52)는 도18 및 도19에 도시된 바와 같이, 내관(강관)(41) 양측면에 설치된 판넬(48)과, 상부 일측에 형성되어 관내로 빛을 발산하는 조명장치(43)와, 상기 내관(41)의 하부에 설치된 토양(44)과, 상기 토양(44)의 양단에 형성된 배수로(46)와, 상기 내관(41)의 외측하부와 외관(강관)(40)내부에 형성되어 내관(40) 지지하는 내관지지대(45)와, 상기 내관지지지대(45)상부와 내관(41)사이에 형성되어 내관 (41)을 보호하는 고무판(47)과, 상기와 같이 시공된 이동로의 선단부와 도로측면을 완만한 경사로 연결되어 설치된 유도철책(42)으로 구성된 제방도로용(8)의 터널식 야생동물 이동통로(52)인 것이다.The tunnel-type wild animal movement passages 52 installed at a plurality of intervals at a lower portion of the lower roadway 5 of the present invention, as shown in Figures 18 and 19, the inner panel (steel pipe) 41, the panel 48 is provided on both sides ), An illumination device 43 formed on one side of the upper part to emit light into the tube, a soil 44 disposed below the inner tube 41, a drainage path 46 formed at both ends of the soil 44, and And an inner tube support 45 formed inside the outer lower portion of the inner tube 41 and the exterior (steel pipe) 40 to support the inner tube 40 and between the upper portion of the inner tube support 45 and the inner tube 41. Tunnel type wildlife of the road dike (8) consisting of a rubber plate (47) for protecting the inner tube (41) and the guide rail (42) installed by connecting the front end of the moving path and the road side in a gentle slope as described above It is a moving passage (52).

상기와 같이 본 발명은 홍수시 과다 유량 유입구 및 방출수문을 갖추어 도심지 하천의 일정수량 확보 및 홍수시에 고수부지내의 생태공원 시설을 보호하고,As described above, the present invention is equipped with an excess flow inlet and discharge sluice during flooding to secure a certain amount of urban streams and to protect the ecological park facilities in the cistern site during flooding,

재순환된 하천수를 상류의 강관파이프내 취수원에서 양수하여 일부는 자연정화 시설로, 일부는 복원된 하천으로 방류하며, 상류 및 하류의 수중보에 계단식 어도를 만들어 복원된 도심지 하천을 통해 상류에서 하류, 또는 하류에서 상류로 물고기의이동이 자유롭게 하였고, 도심지의 과다한 교통량을 분산하기 위해 만든 하상도로 시설을 하천 복원하여 도심지내의 교통량 분산을 일정량 담당할수 있도록 하였으며, 복원된 도심지 하천내의 고수부지내에 생태공원 및 생태학습장을 설치하여 자연환경의 접촉이 어려운 도시민들에게 자연의 풍부한 휴식을 주며 어린이들에게는 자연의 소중함을 깨닫을 수 있는 학습장을 제공하는 장점이 있는 것이다.The recycled river water is pumped from the intake in the upstream steel pipe, some are discharged to the natural purification facilities, some are restored to the restored rivers, and cascaded estuaries are formed upstream and downstream, and upstream and downstream through the restored downtown rivers, or The free movement of fish from the downstream to the upstream, and the restoration of the riverbed facility created to disperse excess traffic in the downtown area to take charge of the distribution of traffic in the downtown area, and the ecological park and ecology in the reservoir of the restored downtown river. It has the advantage of providing a learning center that provides abundant rest of nature to the city residents who have difficulty in contact with the natural environment by setting up a learning center.

Claims (9)

하천수(13)가 흐르는 하도(11)의 양측지역의 경사면 호안에 설치된 자연형 호안정비시설(6)과, 상기 자연형 호안정비시설(6)의 상부에는 일정면적을 형성된 하상도로(5)와, 상기 하상도로(5)의 바깥쪽 측면에 설치된 생태공원(4) 및 고수부지(7)와, 상기 고수부지(7)의 상류 일측에 설치된 자연정화시설(1)과, 상기 자연정화시설(1)의 측면에 형성된 생태공원(4)과, 상기 생태공원(4) 및 고수부지(7)의 바깥쪽 경사면 제방에 설치된 자연형 호안정비시설(6)과, 상기 자연형호안정비시설 (6)의 상부에 제방도로(8)를 시공하는 도심지 하천복원공법에 있어서,The natural lake safety facility (6) installed on the slopes of both sides of the river channel (11) through which the river water (13) flows, and the lower road (5) having a predetermined area on the natural lake safety facility (6); , An ecological park (4) and a cilantro site (7) installed on the outer side of the lower road (5), a natural purification facility (1) installed upstream of the cilantro site (7), and the natural purification facility ( 1) an ecological park (4) formed on the side of the side, a natural lake restoring facility (6) installed on the bank of the outer slope of the ecological park (4) and the coriander site (7), and the natural lake restoring facility (6 In the downtown river restoration method to construct the embankment road 8 in the upper part of the 하천수(13)가 흐르는 하도(11)의 상하류지역에 물막이 수중보(21,32,) 및 어도(22,33)를 설치하여 물의 흐름을 일정하게 하고 물고기의 왕래를 자유롭게하였으며, 하천바닥 하부에 다수개의 대구경파이프수로(10)를 매설하여 하천수를 재순환하거나 홍수시 바이패스시켜 홍수시 과다 유량을 흡수하였고, 상기 대구경파이프수로(10)내 하단부에 연결된 취수시설과 고수부지(7)에 설치된 양수장(1)에 의해 물을 취수하여 자연정화 시설(2)을 이용하여 정화하였고, 상기 하도(11)의 양측지역의 경사면 호안에 설치된 자연형 호안정비시설(6)의 상부에는 일정면적을 형성된하상도로(5)의 하부에 일정간격으로 생태공원(4)의 인공호수(또는 인공연못)과 연계하여 형성된 다수개의 터널식 야생동물 이동통로(52)를 설치하였으며,Water barriers (21,32) and fisheries (22,33) were installed in the upstream and downstream regions of the riverway (11) where the river water (13) flowed to maintain a constant flow of water and to freely move fish. Two large-diameter pipe channels (10) were buried to recycle the river water or bypassed during flooding to absorb excess flow during flooding, and were installed at the water intake facility connected to the lower end of the large-diameter pipe channel (10) and the water reservoir (7). Water was collected by the pumping station (1) and purified using a natural purification facility (2), and a predetermined area was formed at an upper portion of the natural lake restoring facility (6) installed on the sloped lakes of both sides of the lower road (11). In the lower part of the lower road (5), a plurality of tunnel-type wildlife movement passages (52) formed in association with the artificial lake (or artificial pond) of the ecological park (4) were installed. 상기 자연정화시설(1)에 의해 정화된 물을 자연정화시설(1)의 측면에 형성된 상기 생태공원(4)과, 배수관(26)에 의해 정수된 물을 하도(11)로 배출하였으며, 상기 생태공원(4) 및 고수부지(7)의 바깥쪽 측면에 경사면으로 형성된 자연형 호안정비시설(6)과, 상기 자연형호안정비시설(6)의 상부에 제방도로(8)를 시공함을 특징으로 하는 도심지 하천복원공법.The water purified by the natural purification facility (1) discharged the water purified by the ecological park (4) and the drain pipe 26 formed on the side of the natural purification facility (1) to the sewer (11), The construction of a natural lake safety facility (6) formed on an inclined surface on the outer side of the ecological park (4) and the coriander site (7), and a levee road (8) on top of the natural lake safety facility (6) Downtown river restoration method characterized by. 청구항 1에 있어서, 상기 터널식 야생동물 이동통로(52)는 야생동물에게 환경적인 위화감을 주지 않기 위해 내관(41)의 내부에 친환경적인 접착재료를 이용하여 통나무, 벽면 등의 패널(48)을 시공하고, 벽면 사이에 넝클등을 삽입하고, 일정조명을 위한 조명장치(43)를 내관(41) 천정 일측에 설치하며, 야생동물의 이동시 내관(41)의 바닥에서 오는 위화감을 줄이기 위해 토양(흙바닥)(44)을 설치한 다음, 도로의 하단에 매설된 외관(40)의 양선단부에서 고수부지지역으로 약 5m 정도의 방음벽(49)을 설치하고, 도로의 측면에서 고수부지안으로 2m 떨어져 설치한 상기와 같이 시공된 이동로의 선단부와 도로측면을 완만한 경사로 연결하는 유도철책을 설치하여 시공함을 특징으로 하는 도심지 하천복원공법.The method of claim 1, wherein the tunnel-type wildlife movement passage 52 constructs a panel 48, such as logs, walls, using environmentally friendly adhesive material inside the inner tube 41 in order not to give an environmental discomfort to the wild animals. And, insert the shank, etc. between the walls, the lighting device 43 for constant lighting is installed on one side of the ceiling of the inner tube 41, to reduce the discomfort coming from the bottom of the inner tube 41 during the movement of the wildlife (soil) (Bottom) 44, and then installs a soundproof wall 49 of about 5m from the both ends of the exterior 40 buried at the bottom of the road to the cilantro site, and 2m away from the side of the road into the cilantro site. The urban stream restoration method, characterized in that the construction by installing a guide rail connecting the front end of the road and the side of the road in a gentle slope constructed as described above. 청구항 1에 있어서, 상기 대구경파이프수로(10)의 시공은 하수정화 처리를 거치지 않은 오염된 하천수가 흐르던 도심지 하도(11)의 바닥에 심하게 부패된 하상토양을 굴착하여 폐기물처리장에 반출 처리 한후, 10년빈도 이상의 홍수 유량을 바이패스 처리할수 있는 관경의 대구경파이프수로(10)를 다수개 매설하고, 상기 대구경파이프수로(10)의 상부에 깨끗한 하상토(13)를 복토하여 수생생물이 하천에 복원할 수 있는 환경을 만들어 준 다음, 하도(11) 상류(A)의 일측에 하도(11)의 바닥에 매설된 다수개의 대구경파이프수로(10)의 상류측 말단부가 상부로 경사지게 연장되어 하천수(12)의 상부까지 돌출되게 설치하고, 저수된 하천수(12)가 자연스럽게 대구경파이프수로(10)로 흘려들도록 상기 다수개의 대구경파이프수로(10)의 상류측 말단부에 취수구(20)를 설치하였고, 상기 다수개의 대구경파이프수로(10)의 내부하부일측에 펌프(24)를 설치하여, 상기 펌프(24)에 연결된 취수관(23)을 통해 고수부지(7)에 설치된 양수장(2)에 취수토록 시공한 다음, 상기 하도(11)의 하상토(13)의 하부에 매설된 다수개의 대구경파이프수로(10)의 하류측 일측에 수직으로 돌출되는 대구경파이프하류취수구연결관(10-1)을 형성시켜 하천수(13)의 수위까지 연장되게 하여 상기 대구경파이프하류취수구연결관(10-1)의 말단부에 취수구(30)를 설치하여 대구경파이프수로(10)에 물을 유입시키며, 상기 취수구(30) 입구에 수문(50)을 설치하여 홍수시에는 하천수가 유입되지 못하도록 하여 용수시의 하천수 역류현상을 차단도록 하였고,The method of claim 1, wherein the construction of the large-diameter pipe canal (10) excavated a heavily decomposed bottom soil on the bottom of the downtown sewer (11) through which the contaminated river water flows without the sewage purification treatment, and carried out to the waste treatment plant, A large number of large-diameter pipe canals 10 having a diameter capable of bypassing flood flows of 10 years or more are buried, and aquatic organisms are covered by covering the clean riverbed soil 13 above the large-diameter pipe canals 10. After creating a restorable environment in the stream, the upstream end portions of a plurality of large diameter pipe channels 10 buried at the bottom of the sewer 11 on one side of the upstream A of the sewer 11 are inclined upwardly. And installed to protrude to the upper portion of the river water 12, the intake port 20 in the upstream end portion of the plurality of large diameter pipe water channel 10 so that the stored river water 12 flows into the large diameter pipe water channel 10 naturally. Install The pump 24 is installed on the inner lower side of the plurality of large-diameter pipe channels 10, and the pumping station 2 installed in the cistern site 7 through the intake pipe 23 connected to the pump 24. Large diameter pipe downstream intake connector 10-protrudes vertically to one side of the downstream side of the plurality of large diameter pipe channels 10 embedded in the lower portion of the lower soil 13 of the lower road 11. 1) is formed to extend to the water level of the river water (13) to install a water inlet 30 in the distal end of the large diameter pipe downstream inlet connection pipe (10-1) to introduce water into the large diameter pipe water channel (10), The water gate 50 was installed at the entrance of the intake port 30 to prevent the flow of river water during flooding so as to block the flow of river water backflow during the water, 상기 다수개의 대구경파이프수로(10)의 하류 끝단부는 상부로 경사지게 연장되어 하천수(12)의 상부까지 돌출되어 설치한 후 끝단부에 다수개의 수문(31)을 설치하여 다수개의 대구경파이프수로(10)내에 저장된 물을 배출 또는 차단하게 시공함을 특징으로 하는 도심지 하천복원공법.The downstream ends of the plurality of large-diameter pipe canals 10 are inclined upwardly to protrude to the upper portion of the river water 12, and then a plurality of large-sized pipes 31 are installed at the ends. 10) Urban stream restoration method, characterized in that the construction to discharge or block the water stored in. 청구항 1에 있어서, 상기 양수장(2)의 시공은 양수된 물은 일측에 형성되어 자연정화시설(1)을 통해 양수된 물을 정화시킨 다음, 정수된 물을 배수관(26)을 통해 하도(11)로 배출시켜 하도(11)를 정화시키도록 시공하고, 상기 수중보(21)의 시공은 다수개의 대구경파이프수로(10)의 취수구(20)를 중심으로 하류쪽 후방 10m 의 후방지역에 어도(22)가 경사지게 설치된 수중보(21)를 설치도록 시공하여, 상류에서 흘려온 물은 일단 물막이 수중보(21)를 통하여 물의 흐름을 일정하게 하며, 상기 수중보(21)에 설치되는 계단식 어도(22)를 통하여 물고기의 왕래를 자유롭도록 하였으며, 또다른 수중보(32)는 상기 대구경파이프하류취수구연결관(10-1)과 수문(31)의 사이에 어도(33)가 경사지게 설치된 수중보(32)를 설치하여 상류에서 흘려온 물은 일단 물막이 수중보(32)를 통하여 물의 흐름을 일정하게 하며, 상기 수중보(32)에 설치되는 계단식 어도(33)를 통하여 물고기의 왕래를 자유롭도록 시공함을 특징으로 하는 도심지 하천공법.The method of claim 1, wherein the construction of the pumping station (2) is pumped water is formed on one side to purify the water pumped through the natural purification facility (1), and then purified water through the drain pipe (26) The subsurface (21) is constructed so as to purify the sewer (11), and the construction of the underwater beam (21) is based on the water inlet (20) of the plurality of large-diameter pipe channels (10) in the rear region 10 m downstream of the downstream ( Construction to install the submerged beams 21 are installed to be inclined, the water flowing upstream once the water flow through the submerged underwater beams 21, the water flow through the stairwell 22 is installed on the underwater beams 21 To free the traffic of the fish through, another underwater beam 32 is installed between the large diameter pipe downstream inlet connection pipe 10-1 and the water gate 31 by installing an underwater beam 32 to be inclined Water flowing from the upstream once passes through the water basin (32) The stream of the downtown method, characterized in that the constant flow of the trough, construction to freely come and go fish through the cascading fish (33) installed in the underwater beam (32). 한국형 도심지 하천설비에 있어서, 바닥에 하상토(13)가 있으며 상기 하상토(13)의 상부에 하천수(12)가 흐르는 하도(11)와, 상기 하도(11)의 상,하류측에 형성된 수중보(21,32)와, 상기 하도(11)의 하부에 매설된 다수개의 대구경파이프수로(10)와, 상기 하도(11) 상,하류측의 수중보(21,32) 일측에 형성되어 있으며 상기 다수개의 대구경파이프수로(10)로 물을 유입시키는 취수구(20,30)와, 상기 하도(11)의 최상부 양쪽에 경사면으로 형성된 제방에 형성된 자연형 호안정비시설(6)과, 상기 자연형 호안정비시설(6)의 상부에 형성된 하상도로(5)와, 상기 하상도로(5)의 바깥쪽 측면에 형성된 생태공원(4) 및 고수부지(7)와, 상기 생태공원(4) 및 고수부지(7)의 상류쪽 일측에 형성된 자연정화시설(1)과,In the Korean urban river equipment, there is a bottom soil (13) at the bottom and the river channel (12) through which the river water (12) flows on the top of the bottom soil (13), and an underwater beam formed on the upper and downstream sides of the channel (11) (21,32), a plurality of large-diameter pipe canal (10) embedded in the lower portion of the lower road 11, and the submersible beams (21, 32) on one side of the upper and downstream of the lower road (11) Water intake ports 20 and 30 for introducing water into a plurality of large-diameter pipe channels 10, natural lake safety facilities 6 formed on the embankment formed on both sides of the top of the channel 11, and the natural type The riverbed road 5 formed in the upper part of the shoreline maintenance facility 6, the ecological park 4 and the coriander site 7 formed in the outer side of the riverbed road 5, the ecological park 4 and the coriander A natural purification facility (1) formed on one side of an upstream side of the site (7), 상기 친환경형 하상도로(5)의 하부에 일정간격으로 생태공원(4)의 인공호수(또는 인공연못)과 연계하여 형성된 다수개의 터널식 야생동물 이동통로(52)와,A plurality of tunnel-type wildlife movement passages 52 formed in association with an artificial lake (or artificial pond) of the ecological park 4 at a predetermined interval in the lower portion of the eco-type riverbed road 5, 상기 자연정화시설(1)의 측면에 형성된 상기 생태공원(4)에 물을 공급하는 생태공원용수공급관(25)과, 상기 자연정화시설(1)의 또다른 일측에 형성된 양수장(2)과, 상기 양수장(2)에 연결되어 있으며, 다수개의 대구경파이프수로(10)의 하부 일측에서 형성된 펌프(24)에 또다른 일측이 연결되어 물을 취수하는 취수관(23)과, 상기 양수장(2)의 또다른 일측에 형성되어 자연정화시설(1)을 통해 정수된 물을 하도(11)로 배출하는 배수관(26)과, 상기 생태공원(4) 및 고수부지(7)의 바깥쪽 측면에 경사면으로 형성된 자연형 호안정비시설(6)과, 상기 자연형호안정비시설(6)의 상부에 형성된 제방도로(8)로 구성되어 있음을 특징으로 하는 도심지 하천설비임.An ecological park water supply pipe (25) for supplying water to the ecological park (4) formed on the side of the natural purification facility (1), a pumping station (2) formed on the other side of the natural purification facility (1), Is connected to the pumping station (2), the other side is connected to the pump 24 formed at the lower one side of the plurality of large diameter water pipe (10) and the water intake pipe 23 and the pumping station (2) On the other side of the c) is formed on the drain pipe (26) for discharging the purified water through the natural purification facility (1) to the sewer (11), and on the outer side of the ecological park (4) and coriander site (7) It is a downtown river facility characterized in that it consists of a natural lake safety facility (6) formed by the slope and the embankment road (8) formed on top of the natural lake safety facility (6). 청구항 5에 있어서, 하도(11)의 바닥에 형성된 하상토(13)의 하부에 매설된 다수개의 대구경파이프수로(10)의 상류측일단은, 상부로 경사지게 연장되어 하천수(12)의 상부까지 돌출되어 형성된 말단부와, 상기 다수개의 대구경파이프수로(10)의 말단부에 형성되어 있고 물을 유입또는 차단시키는 취수구(20)와, 상기 다수개의 대구경파이프수로(10)의 하부일측에서 형성된 펌프(24)와, 상기 펌프(24)에 연결되어 있으며 또다른 일측에는 양수장(2)에 연결되어 물을 취수하는 취수관(23)과, 상기 양수장(2)의 또다른 일측에 형성되어 자연정화시설(1)을 통해 정수된 물을 하도(11)로 배출하는 배수관(26)과,The upstream end of the plurality of large-diameter pipe channels 10 buried in the lower part of the lower soil 13 formed at the bottom of the lower road 11 is inclined upwardly to the upper part of the river water 12. A protruding end portion, a water intake port 20 formed at a distal end of the plurality of large-diameter pipe channels 10, and a pump formed at a lower side of the plurality of large-diameter pipe channels 10; And a water intake pipe 23 connected to the pump 24 and connected to the pump station 2 to collect water, and formed on another side of the pump station 2 to purify the water. A drain pipe 26 for discharging the purified water through the facility 1 to the sewerage system 11, 상기 취수구(20)를 중심으로 하류쪽에 형성된 수중보(21)와, 상기 수중보(21)의 하류쪽 일측에 연결되어 형성된 어도(22)로 구성되어 있음을 특징으로 하는 도심지 하천설비.Downtown river equipment, characterized in that consisting of the waterway (21) formed on the downstream side around the intake port (20), and the fishery (22) formed connected to the downstream side of the underwater beam (21). 청구항 5에 있어서, 상기 하도(11)의 하상토(13)의 하부에 매설된 다수개의 대구경파이프수로(10)의 하류측일단은, 일측에 수직으로 돌출되어 하천수(13)의 수위까지 연장되어 형성된 대구경파이프하류취수구연결관(10-1)과, 상기 대구경파이프하류취수구연결관(10-1)의 말단부에 형성된 대구경파이프수로(10)에 물을 유입시키는 취수구(30)와, 상기 취수구(30)에 설치된 수문(50)과, 상기 다수개의 대구경파이프수로(10)의 하류 끝단부가 상부로 경사지게 연장되어 하천수(12)의 상부까지 돌출되어 형성되어 있으며, 상기 끝단부에 다수개의 대구경파이프수로(10)내에 저장된 물을 배출 또는 차단하는 수문(31)과, 상기 대구경파이프하류취수구연결관 (10-1)과 수문(31)의 사이에 형성된 수중보(32)와, 상기 수중보(32)에 형성된 어도(33)로 구성되어 있음을 특징으로 하는 도심지 하천설비.The downstream end of the plurality of large-diameter pipe channels 10 embedded in the lower soil 13 of the sewer 11 protrudes perpendicularly to one side and extends to the water level of the river water 13. A large diameter pipe downstream intake port connecting pipe 10-1 and a large diameter pipe water inlet 10 formed at the distal end of the large diameter pipe downstream inlet connection pipe 10-1, and the water inlet 30 The water gate 50 installed in the intake port 30 and the downstream ends of the plurality of large-diameter pipe channels 10 are inclined upwardly to protrude to the upper portion of the river water 12, and a plurality of end portions A water gate 31 for discharging or blocking water stored in the large-diameter pipe channel 10, an underwater beam 32 formed between the large-diameter pipe downstream inlet connection pipe 10-1 and the water gate 31, and the underwater beam It is characterized by consisting of an island 33 formed in the (32) Downtown River facility. 청구항 5에 있어서, 상기 하상도로(5)의 하부에 일정간격으로 설치된 터널식 야생동물 이동통로(52)는 내관(강관)(41) 양측면에 설치된 판넬(48)과, 상부 일측에 형성되어 관내로 빛을 발산하는 조명장치(43)와, 상기 내관(41)의 하부에 설치된 토양(44)과, 상기 토양(44)의 양단에 형성된 배수로(46)와, 상기 내관(41)의 외측하부와 외관(강관)(40)내부에 형성되어 내관(40) 지지하는 내관지지대(45)와, 상기 내관지지지대(45)상부와 내관(41)사이에 형성되어 내관(41)을 보호하는 고무판 (47)과, 상기와 같이 시공된 이동로의 선단부와 도로측면을 완만한 경사로 연결되어 설치된 유도철책(42)으로 구성되어 있음을 특징으로 하는 도심지 하천설비.The method according to claim 5, Tunnel-type wildlife movement passage 52 installed at a predetermined interval in the lower portion of the lower road 5 is a panel 48 provided on both sides of the inner pipe (steel pipe) 41, and formed on one side of the upper into the pipe An illumination device 43 for emitting light, a soil 44 disposed below the inner tube 41, a drainage passage 46 formed at both ends of the soil 44, an outer lower portion of the inner tube 41, An inner tube support 45 formed inside the outer tube (40) and supporting the inner tube 40, and a rubber plate formed between the upper portion of the inner tube support 45 and the inner tube 41 to protect the inner tube 41 ( 47), and urban river equipment, characterized in that consisting of the guide rail 42 is installed connected to the slope of the road side and the road side of the construction of the moving path constructed as described above. 한국형 도심지하천복원 공법에 있어서,In the Korean urban underground restoration method, 제1공정1st process 하천수(13)가 흐르는 하도(11)의 양측지역의 경사면 호안에 도1내지 도3과 같이 자연형 호안정비시설(6)을 설치하여 홍수시의 과다 유량이 고수부지(7)내의 양수장(2) 또는 생태공원(4)에 피해를 주지 않도록 하였으며, 상기 자연형 호안정비시설(6)의 상부에는 일정면적을 형성시켜, 하상도로(5)를 설치하여 도시교통의 소통을 원활하게 하였으며, 상기 하상도로(5)의 바깥쪽 측면에는 생태공원(4) 및 고수부지(7)를 설치하여 시민들이 휴식과 운동을 할 수 있게 하였고, 상기 고수부지(7)의 상류 일측에 자연정화시설(1)을 설치하여, 양수장(2)에서 취수된 물을 정화시켜 하도(11)에 배출하며, 상 자연정화시설(1)의 측면에 형성된 생태공원(4)에 물을 공급하도록 하여 하천수를 정화시켰고, 상기 생태공원(4) 및 고수부지(7)의 바깥쪽 경사면 제방에는 자연형 호안정비시설(6)을 설치하여 홍수시의 과다 유량이 제방을 넘어 주택가에 피해를 주지 않도록 하였고, 상기 자연형호안정비시설(6)의 상부에는 제방도로(8)를 설치하여 도시교통의 소통을 원활하게 하였으며,A natural type lakeside maintenance facility (6) is installed on the slopes of both sides of the sewer (11) through which the river water (13) flows. ) Or ecological park (4) was not damaged, and a certain area was formed on the upper part of the natural recreational maintenance facility (6), and a riverbed (5) was installed to facilitate communication of city traffic. On the outer side of the riverbed (5), an ecological park (4) and a cilantro site (7) were installed to allow citizens to rest and exercise, and a natural purification facility (1) upstream of the cilantro site (1). ) To purify the water taken from the pumping station (2) to discharge to the sewer (11), and to supply the water to the ecological park (4) formed on the side of the phase natural purification facility (1) to purify the river water On the banks of the outer slopes of the ecological park (4) and coriander site (7), natural type lake rest The non-facilities (6) were installed to prevent excessive flow rate during flooding and damage to residential areas. The upper part of the natural relief service facility (6) installed a dike road (8) to communicate urban traffic. Smoothly, 친환경형 하상도로(5)는 일정부분마다 터널식 야생동물 이동통로(52)를 대구경강관 압입추진공을 이용한 생태계 이동로 시공방법에 따라 설치하였고, 상기에서 터널식 야생동물 이동통로(25)는 야생동물에게 환경적인 위화감을 주지 않기 위해 내관(41)의 내부에 친환경적인 접착재료를 이용하여 통나무 벽면 등의 패널(48)을 시공하고, 벽면 사이에 넝클등을 삽입하고, 일정조명을 위한 조명장치(43)를 내관 (41) 천정 일측에 설치하며, 야생동물의 이동시 내관(41)의 바닥에서 오는 위화감을 줄이기 위해 토양(흙바닥)(44)을 설치한 다음, 도로의 하단에 매설된 외관(40)의 양선단부에서 고수부지지역으로 약 5m 정도의 방음벽(49)을 설치하고, 야생동물을 상기와 같이 시공된 이동로로 유도하기 위하여 도로의 측면에서 고수부지안으로 2m 떨어져 설치한 상기와 같이 시공된 이동로의 선단부와 도로측면을 완만한 경사로 연결하는 유도철책을 설치하여 하천지역 및 호안지역, 고수부지내의 생태공원 및 생태 학습장에로의 동물이동이 끊어지지 않도록 하였고,The eco-friendly riverbed (5) was installed according to the construction method of the ecosystem-type movement path using the tunnel-type wild animal movement passage 52 for each part, and the tunnel-type wildlife movement passage 25 was wild animal. In order not to give environmental discomfort to the interior of the inner tube 41, using the environment-friendly adhesive material to construct a panel 48 such as log wall, insert the shank, etc. between the walls, the lighting device for constant lighting ( 43) is installed on one side of the ceiling of the inner pipe (41), and the soil (soil bottom) 44 is installed to reduce the discomfort coming from the bottom of the inner pipe (41) during the movement of the wildlife, and then buried at the bottom of the road ( The soundproof wall 49 of about 5m is installed from the end of both ends to the coriander site, and 2m away from the side of the road into the coriander site in order to guide wild animals to the constructed moving path. This install the tip of the installation, go to the induction of a gradual ramp connecting the road side fence was not to break the movement of animals in the ecological park and river ecology learning center for doing local and regional revetment, gosubu, 제2공정2nd process 하도(11)의 바닥에 심하게 부패된 하상토양을 굴착하여 폐기물처리장에 반출 처리 한후에, 10년빈도 이상의 홍수 유량을 바이패스 처리할 수 있는 관경의 대구경파이프수로(10)를 다수개 매설하고, 상기 대구경파이프수로(10)의 상부에 깨끗한 하상토(13)를 복토하여 수생생물이 하천에 복원할 수 있는 환경을 만들어 준 다음,After digging the badly decomposed bottom soil at the bottom of the roadway 11 and carrying it out to a waste treatment plant, a plurality of large-diameter pipe canals 10 of a diameter capable of bypassing flood flows of 10 years or more are buried. By covering the clean riverbed 13 on the upper part of the large-diameter pipe canal 10 to create an environment in which aquatic life can be restored to the river, 하도(11) 상류(A)의 일측에 하도(11)의 바닥에 매설된 다수개의 대구경파이프수로 (10)의 상류측 말단부가 상부로 경사지게 연장되어 하천수(12)의 상부까지 돌출되게 설치하고, 저수된 하천수(12)가 자연스럽게 대구경파이프수로(10)로 흘려들도록상기 다수개의 대구경파이프수로(10)의 상류측 말단부에 취수구(20)를 설치하였고, 상기 다수개의 대구경파이프수로(10)의 내부하부일측에 펌프(24)를 설치하여, 상기 펌프(24)에 연결된 취수관(23)을 통해 고수부지(7)에 설치된 양수장(2)에 취수토록 하고, 상기 양수장(2)에 양수된 물은 일측에 형성되어 자연정화시설(1)을 통해 양수된 물을 정화시킨 다음 정수된 물을 배수관(26)을 통해 하도(11)로 배출시켜 하도(11)를 정화시키며, 상기 다수개의 대구경파이프수로(10)의 취수구(20)를 중심으로 하류쪽 후방 10m 의 후방지역에 어도(22)가 경사지게 설치된 수중보(21)를 설치하였으며,Upstream end of the plurality of large-diameter pipe channels 10 buried at the bottom of the underpass 11 at one side of the upstream 11 A extends inclined upward and is installed to protrude to the upper portion of the river water 12. In order to naturally flow into the large-diameter pipe channel 10, the inlet 20 is installed at the upstream end of the plurality of large-diameter pipe channels 10, and the plurality of large-diameter pipe channels A pump 24 is installed at one inner lower side of the pump 10 so as to be withdrawn to the pumping station 2 installed at the cistern site 7 through a water intake pipe 23 connected to the pump 24, and the pumping station 2 is connected to the pump 24. Water pumped in is formed on one side to purify the water pumped through the natural purification facility (1) and then purifies the waterway (11) by discharging the purified water to the sewer (11) through the drain pipe (26), 10 m rearward downstream of the inlet 20 of the plurality of large-diameter pipe channels 10 The even in 22 was installed obliquely installed submerged weir 21, 제3공정3rd process 상기 하도(11)의 하상토(13)의 하부에 매설된 다수개의 대구경파이프수로(10)의 하류측 일측에 수직으로 돌출되는 대구경파이프하류취수구연결관(10-1)을 형성시켜 하천수(13)의 수위까지 연장되게 하여 상기 대구경파이프하류취수구연결관(10-1)의 말단부에 설치된 취수구(30)입구에 수문(50)을 설치하여 대구경파이프수로(10)에 하천수(13)를 유입시켜 홍수시에는 하천수가 유입되지 못하도록 하여 홍수시의 하천수 역류현상을 차단하도록 하였으며, 상기 다수개의 대구경파이프수로(10)의 하류 끝단부는 상부로 경사지게 연장되어 하천수(12)의 상부까지 돌출되어 설치한 후 끝단부에 다수개의 수문(31)을 설치하여 다수개의 대구경파이프수로(10)내에 저장된 물을 배출 또는 차단하게 하고, 상기 대구경파이프하류취수구연결관(10-1)과 수문(31)의 사이에 어도(33)가 경사지게 설치된 수중보(32)를 설치 시공함을 특징으로 하는 도심지 하천복원공법.The large-diameter pipe downstream intake connection pipe 10-1 is formed to protrude perpendicularly to the downstream side of the plurality of large-diameter pipe channels 10 embedded in the lower portion of the lower soil 13 of the lower road 11 to form a river water ( 13) to extend the water level of the large diameter pipe downstream inlet port 10-1 of the water inlet 30 is provided in the inlet 30 is installed in the inlet 30 to install the river water (13) in the large diameter pipe channel 10 The inflow of the river water was prevented from flowing during the flood, thereby preventing the backflow of the river water during the flood. The downstream ends of the plurality of large-diameter pipe channels 10 were inclined upwardly and protruded to the upper part of the river 12. After installation, a plurality of water gates 31 are installed at the end to discharge or block water stored in the plurality of large diameter pipe channels 10, and the large diameter pipe downstream inlet connection pipe 10-1 and the water gate 31 Degree in between (33) The urban river restoration method, characterized in that the construction of the submarine (32) installed inclined).
KR10-2002-0058703A 2002-09-27 2002-09-27 The facility of river in the civil center and method restoration of it KR100515189B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2002-0058703A KR100515189B1 (en) 2002-09-27 2002-09-27 The facility of river in the civil center and method restoration of it

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2002-0058703A KR100515189B1 (en) 2002-09-27 2002-09-27 The facility of river in the civil center and method restoration of it

Publications (2)

Publication Number Publication Date
KR20020079707A true KR20020079707A (en) 2002-10-19
KR100515189B1 KR100515189B1 (en) 2005-09-16

Family

ID=27728490

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2002-0058703A KR100515189B1 (en) 2002-09-27 2002-09-27 The facility of river in the civil center and method restoration of it

Country Status (1)

Country Link
KR (1) KR100515189B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100721897B1 (en) * 2005-11-03 2007-05-28 조남열 River purification structure
CN110117987A (en) * 2019-04-02 2019-08-13 无锡市政设计研究院有限公司 A kind of running water pumping plant of black and odorous water regulation
CN114656115A (en) * 2022-04-25 2022-06-24 中交上海航道勘察设计研究院有限公司 River channel ectopic rapid filtering method and system
CN115142382A (en) * 2022-07-29 2022-10-04 重庆交通大学 Landscape water supplementing system and method applied to source-head type river channel

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101349463B1 (en) * 2013-07-05 2014-01-16 현대건설주식회사 Riverbed structure having accelerating flow path for preventing accumulation

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4437431A (en) * 1981-11-06 1984-03-20 Koch David L Method and apparatus for diversion of downstream migrating anadromous fish
JP3626231B2 (en) * 1995-01-20 2005-03-02 ランデス株式会社 Structure to prevent animals from entering the motorway
JP3490917B2 (en) * 1998-11-17 2004-01-26 国土交通省九州地方整備局長 Stair type fishway equipment
KR100321942B1 (en) * 1999-04-26 2002-02-04 이정희 Water storage tower used as fish road
US6394699B1 (en) * 1999-07-28 2002-05-28 Norman R. Neufeld Apparatus for reduced flow fish passage
KR20000063599A (en) * 2000-07-19 2000-11-06 박이동 The natural sewage disposal facilities of river
KR100423662B1 (en) * 2000-09-25 2004-03-24 주식회사 오이코스 System of the purification river water with biological contact oxidation type to install on any natural river banks and water sides
KR100442523B1 (en) * 2002-03-06 2004-07-30 건양씨앤이 주식회사 The method for construction using pressure-input propulsion of ecosystem travel load

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100721897B1 (en) * 2005-11-03 2007-05-28 조남열 River purification structure
CN110117987A (en) * 2019-04-02 2019-08-13 无锡市政设计研究院有限公司 A kind of running water pumping plant of black and odorous water regulation
CN110117987B (en) * 2019-04-02 2024-03-22 华昕设计集团有限公司 Running water pump station for black and odorous water body remediation
CN114656115A (en) * 2022-04-25 2022-06-24 中交上海航道勘察设计研究院有限公司 River channel ectopic rapid filtering method and system
CN115142382A (en) * 2022-07-29 2022-10-04 重庆交通大学 Landscape water supplementing system and method applied to source-head type river channel
CN115142382B (en) * 2022-07-29 2024-05-07 重庆交通大学 Landscape water supplementing system and method applied to source type river

Also Published As

Publication number Publication date
KR100515189B1 (en) 2005-09-16

Similar Documents

Publication Publication Date Title
KR101668095B1 (en) Sustainable structured biotop system using wetland, pond and settling pond structure adopting multi-cells and multi-lanes
CN110396979A (en) A kind of ecological restoring method of city river
CN107739098B (en) Method for purifying water quality and restoring water ecology of polluted urban internal lake
CN112695586A (en) Sponge city water circulating system
KR20160139594A (en) cyclic-typed restoring system for the ecological environment
CN108867541A (en) A kind of black smelly river body ecology synthesis repairing and treating system
CN211972073U (en) Urban ecological river cross section
KR100444972B1 (en) Constructed wetland system and method for controlling wastewater and nonpoint pollution source adopting multi-cells
KR100515189B1 (en) The facility of river in the civil center and method restoration of it
CN112194254A (en) Near-natural estuary wetland construction method with uniform water distribution
JP2001224243A (en) Artificial virescence method and artificial verdant land
CN215562338U (en) Multi-stage storage-regulation hydrophilic ecological bank protection structure based on existing vertical retaining wall
CN214883415U (en) Landscape stack way type ecological revetment structure based on existing vertical retaining wall
KR0147724B1 (en) Revetment method for making the curve point of natural type watercourse
Cotterell Fish passage in streams
CN211621506U (en) Combined ecological drainage channel structure
CN212506106U (en) Stepped ecological revetment structure
KR0147723B1 (en) A revetment method for making natural type watercourse
CN110984059A (en) Construction method and application of coastal estuary wetland protection and restoration system
CN220704425U (en) Ecological water purification type revetment
CN220813664U (en) Ecological frame of artificial fish reef and ecological transformation system of seawall
CN113356325B (en) Comprehensive treatment method for water ecological environment of landscape water area
CN214613898U (en) Hydrophilic seton step type ecological bank protection structure based on existing vertical retaining wall
Peay MINIMISING LOSS OF CRAYFISH AND HABITATDURING WORKS ON WATERCOURSES
Rickard et al. River Weirs–Good Practice Guide Guide-Section A

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20080909

Year of fee payment: 4

LAPS Lapse due to unpaid annual fee