Prior art keywords
pipe
piping
existing
mortar
mortar layer
Prior art date
Application number
KR1020010020048A
Other languages
Korean (ko)
Other versions
KR100414801B1 (en
Inventor
김근수
Original Assignee
김근수
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김근수 filed Critical 김근수
Priority to KR10-2001-0020048A priority Critical patent/KR100414801B1/en
Publication of KR20020079260A publication Critical patent/KR20020079260A/en
Application granted granted Critical
Publication of KR100414801B1 publication Critical patent/KR100414801B1/en

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/12Tube and panel arrangements for ceiling, wall, or underfloor heating
    • F24D3/14Tube and panel arrangements for ceiling, wall, or underfloor heating incorporated in a ceiling, wall or floor
    • F24D3/149Tube-laying devices
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B41/00After-treatment of mortars, concrete, artificial stone or ceramics; Treatment of natural stone
    • C04B41/0018Coating or impregnating "in situ", e.g. impregnating of artificial stone by subsequent melting of a compound added to the artificial stone composition
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F2290/00Specially adapted covering, lining or flooring elements not otherwise provided for
    • E04F2290/02Specially adapted covering, lining or flooring elements not otherwise provided for for accommodating service installations or utility lines, e.g. heating conduits, electrical lines, lighting devices or service outlets
    • E04F2290/023Specially adapted covering, lining or flooring elements not otherwise provided for for accommodating service installations or utility lines, e.g. heating conduits, electrical lines, lighting devices or service outlets for heating

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Ceramic Engineering (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Materials Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Organic Chemistry (AREA)
  • Thermal Sciences (AREA)
  • Civil Engineering (AREA)
  • Floor Finish (AREA)

Abstract

PURPOSE: A method for exchanging piping with grooving method and piping structure is provided to perform the piping operation quickly and minimize dusts and noise during the process. CONSTITUTION: A method for exchanging piping with a grooving method is composed of steps of an existing piping detecting step for finding the piping position, an existing piping drain step for removing the water remaining in the existing piping, a piping position indicating step for indicating the piping position to install the piping in a constant interval, a wet paper installation step for laying the wet paper on the portion of the bottom surface on which a cutting edge passes, a linear piping grooving step for making grooves in proper depth and width to form a mortar layer, a both ends connection piping grooving step for connecting both ends after the linear grooving step, a piping installation step for installing the piping at the piping grooves, a moisture supplying step to the piping groove for preventing the moisture in new mortar layer from being absorbed in the existing mortar layer by providing the moisture for existing mortar layer having the piping groove, a solution applying step for preventing the moisture in new mortar layer from being absorbed in the existing mortar layer by applying the solution in the piping grooves, a mortar filling step for filling the piping grooves with cement, and a finishing step for smoothly finishing the surface of the filled cement to be coplanar with the surface of the existing mortar layer.

Description

홈파기공법 배관파이프 교체방법 및 그 방법으로 시공된 배관구조{a piping to change method by groove digging method of construction and the hypocaust floor structure got fromit}Substituting pipe pipe replacement method and pipe structure constructed by the method {a piping to change method by groove digging method of construction and the hypocaust floor structure got fromit}

본 발명은 본인이 선출원한 특허등록출원 제99-30668호인 홈파기공법에 의한 온돌파이프 교체방법 및 그로부터 얻어진 온돌바닥구조에서 발전하여 보다 진보된 신규한 홈파기공법에 의한 홈파기공법 배관파이프 교체방법 및 그 방법으로 시공된 배관구조에 관한 것으로, 더욱 상세하게는 온돌파이프나 수도관, 배수관등을 고장으로 교체하여야 하거나 이들 배관이 노후되어서 전면적으로 교체하여야 할때 기존의 미장몰탈층에 새로운 배관파이프를 배관할 부분만을 콘크리트절단기로 배관파이프의 직경에 알맞도록 적당한 깊이와 넓이로 절단하고 파내어서 요홈을 형성한후, 여기에 새로운 배관파이프를 삽입하여 배관하고 급결 시멘트를 이용하여 기존의 미장몰탈층의 상면과 일치하도록 배관된 요홈을 메워서 단시간 내에 마감몰탈하는 아주 간단한 방법으로 배관파이프를 교체하도록 한 홈파기공법 배관파이프 교체방법 및 그 방법으로 시공된 배관구조에 관한 것이다.The present invention is a method for replacing an ondol pipe by a grooving method, which is a patent registration application No. 99-30668, which is filed by the applicant, and a grooving method using a more advanced new grooving method by replacing the ondol floor structure obtained therefrom. And it relates to the piping structure constructed in that way, more specifically, the on-pipe pipe, water pipe, drain pipe, etc. to replace the failure or when these pipes are old and replaced all over the new plaster pipe to the existing plaster mortar layer Only the part to be piped is cut and cut into a suitable depth and width to fit the pipe pipe's diameter with a concrete cutter to form a groove, and then a new pipe pipe is inserted into the pipe and the cement is used for the existing plaster mortar layer. Very simple to fill and finish mortar in a short time by filling the grooves piped to match the upper surface The grooving method pipe pipe replacement method for replacing the pipe pipe by the method and the pipe structure constructed by the method.

우리나라를 비롯한 중국의 일부는 온돌문화권으로서 옛부터 바닥면을 데워서 주거하는 습관을 가지고 생활하고 있는바, 최초에는 토굴이나 주거지의 바닥면에 모닥불을 피워서 바닥면을 데우고 습기를 제거하여 이용하다가 여기서 발전한 것이 주거지의 바닥에 온돌판(구둘)을 깔고 아궁이로 불을 지펴서 온돌을 가열하는 방법으로 그 연료가 목재에서 석탄 →기름 →가스 순의 고급 연료로 변화되면서 온돌가열방법 또한 연료가 많이 사용되고 지속적인 난방이 어려운 직접가열 방식에서 벗어나 온돌 바닥면에 온돌 배관을 하고 그 배관 내부에 가열된 온수를 순환시켜서 온돌을 가열하는 순환수를 이용한 간접가열 방식으로 발전되어 실생활에 많은 편리함을 주고 있는 실정이다.Some of China, including Korea, have been living with the habit of warming the floor and living in the ondol culture area.In the beginning, a bonfire was burned on the floor of a crypt or residence to heat the floor and remove moisture. The method of heating the ondol by laying ondol plates (shoes) on the floor of a residential area and burning them with a firewood is used to heat the ondol heating method as the fuel is changed from wood to coal → oil → gas. It is a situation that it is developed indirect heating method using circulating water that heats the ondol by circulating the heated hot water inside the ondol floor and circulating the heated hot water inside the ondol floor, which is difficult to be heated directly.

따라서 최근에는 주거용 건축물의 바닥면의 일측으로 수도관과 배수관을 배관한 다음, 1차로 열손실을 방지하는 단열재로 단열하여 열손실을 최소화 한후 그 위에에 난방수를 데워주는 보일러와 연결된 온돌파이프를 난방에 알맞은 간격으로 배관하고 상기한 배관을 미장몰탈층으로 덮어서 마감 하는 방법으로 온돌바닥을 시공하였는바, 이와 같은 건물 배관을 시공후 사용하던중 이상이 발생하거나, 오랜기간이 경과하여 배관된 파이프가 노후가 되면 가족의 건강과 직결되는 관계로 즉시 새로운 온돌파이프로 교체하여야만 한다.Therefore, in recent years, water pipes and drain pipes are piped to one side of the floor of a residential building, and then heat is insulated with an insulating material that prevents heat loss first, thereby minimizing heat loss, and heating the ondol pipe connected to the boiler that warms the heating water thereon. The underfloor was constructed in such a way that the pipes were spaced at a suitable interval and the above-mentioned pipes were covered with a plaster mortar layer to finish the pipes. When they are old, they should be replaced with new ondol pipes as they are directly related to their family's health.

이에 기존의 온돌파이프교체방법을 살펴보면 첫째로는 낡고 이상이 있는 기존온돌파이프(30)가 설치된 기존바닥몰탈층(10)을 깨어 기존의온돌파이프(30)와 기존바닥몰탈층(10)을 전부 들어낸후 새로운 온돌파이프를 적당한 간격으로 배열하고 그 상면에 미장몰탈층을 형성하여서 새로운 온돌파이프로 교체하거나, 둘째로는 내부에 낡은 온돌파이프가 설치된 기존바닥몰탈층(10)을 원형그대로 둔 상태에서 기존바닥몰탈층(10) 상면에 온돌파이프를 올려놓고 새롭게 마감몰탈층을 형성하는 새로운 온돌파이프로 시공하는 방법이 사용되고 있으나, 전자의 경우에는 미장몰탈층의 특성상 표면이 매우 튼튼하여 이를 깨어서 들어내기가 매우 힘들고 번거로웠음은 물론 이때의 충격으로 인한 건축물의 균열등 안전에도 문제가 있었으며, 소음과먼지를 심하게 유발하며, 건축물쓰레기가 다량으로 방출되어 이를 치워야 하므로 온돌파이프의 교체작업시 시간이 많이 걸리고 비용또한 많이 소요되며, 건축물 쓰레기가 다량으로 발생하여 환경오염의 원인이 되는 등 많은 문제점이 있었다.In this regard, the existing method of replacing the ondol pipe firstly breaks the existing floor mortar layer 10 in which the old ondol pipe 30 is installed, which is old and abnormal, and completely removes the existing ondol pipe 30 and the existing floor mortar layer 10. After lifting, arrange new ondol pipes at appropriate intervals and form a plaster mortar layer on the upper surface and replace them with new ondol pipes, or, secondly, with the existing floor mortar layer 10 having old ondol pipes installed therein. A method of constructing a new ondol pipe that puts an ondol pipe on the upper surface of an existing bottom mortar layer 10 and forms a new finishing mortar layer is used. However, in the former case, the surface of the plaster mortar layer is very strong, so it is broken out. Was very difficult and cumbersome, and there were also problems with safety, such as cracks in buildings due to the impact. Balhamyeo, it will clean up construction waste is released in large quantities, so consuming replacement of the floor heating pipe work also takes a lot of time, money and had a lot of problems, such as the construction waste that causes pollution to occur in large quantities.

그리고 후자의 경우에는 미장몰탈층을 깬다음 전부를 들어내는 번거로움은 전혀 없으나 이는 낡은 온돌파이프가 설치된 기존의 미장몰탈층상면에 새로운 온돌파이프가 배열된 마감몰탈층을 형성하는 관계로 전체 바닥면의 두께가 상당히 두꺼워져 그만큼 중량이 많이 나가기 때문에 건축물자체에 무리한 하중이 작용하여 건축물 전체의 수명에 막대한 영향을 끼치게됨으로써 안전사고의 위험이 뒤따를 수 밖에 없었으며, 배관후 건물의 천정이 낮아져서 건물을 사용하는데 불편함이 뒤따르는 등, 문제점이 있었다.In the latter case, there is no hassle of breaking the plaster mortar layer and lifting all of them, but this is because the finishing mortar layer with the new ondol pipe is arranged on the existing plaster mortar layer where the old ondol pipe is installed. As the thickness of the material is considerably thicker, the weight is so heavy that the unreasonable load acts on the building itself, which greatly affects the life of the whole building, which inevitably leads to the risk of safety accidents. There was a problem, such as the inconvenience followed.

본 발명은 상기와 같은 문제점을 고려하여 안출된 본인의 선출원 발명인 특허등록출원 제99-30668호의 기술내용을 개량하여 더욱 완벽하게 진보 시킴으로서, 기존의 낡은 배관파이프를 새로운 파이프로 교체하는 작업을 더욱 신속하게 하는 것은 물론, 기존 배관 관로를 미연에 탐지하여 기존 배관라인을 거의 완벽하게 제거하고 새로운 배관설계를 함으로써 배관후 난방효과를 극대화 하며, 홈파기작업능률을 향상시키고, 습식포를 이용하여 홈파기작업시 발생하는 물이나 분진을 흡수하여 작업환경과 실내환경을 청결하게 유지토록 하며, 시공이 완료된후 기존의 바닥과 새로이 시공한 바닥면이 서로 완벽하게 접착되어 갈라지지 않도록 함에 그 목적을 둔 것이다.The present invention improves more completely by improving the technical contents of the patent application No. 99-30668, which is the applicant's prior invention, which has been made in view of the above problems, so that the work of replacing the old pipe pipe with a new pipe more quickly. In addition, the existing pipe line is detected in advance, and the existing pipe line is almost completely removed and the new pipe design is designed to maximize the heating effect after the pipe, improve the digging efficiency, and use the wet cloth to dig the pipe. Its purpose is to absorb the water or dust generated during work to keep the working environment and the indoor environment clean and to prevent the existing floor and the newly constructed floor from being completely adhered to each other after construction is completed. .

도1은 본 발명을 실시하기위한 공정의 흐름도.1 is a flow chart of a process for practicing the present invention.

도2는 본 발명을 실시하기 위하여 직선홈파기공정을 실시한 예시도.Figure 2 is an exemplary view of performing a linear grooving process to implement the present invention.

도3은 본 발명을 실시하기 위하여 곡선홈파기공정을 실시한 예시도.Figure 3 is an exemplary view of carrying out a curved grooving process to implement the present invention.

도4는 본 발명을 완성한 온돌구조를 나타낸 예시도.Figure 4 is an exemplary view showing an ondol structure completing the present invention.

♣도면의 주요 부분에 대한 부호의 설명♣♣ Explanation of symbols for the main parts of the drawing

10: 기존바닥몰탈층. 30: 기존배관.10: Existing bottom mortar layer. 30: Existing piping.

100: 배관홈. 200: 새로운몰탈. 300: 배관파이프.100: piping groove. 200: new mortar. 300: piping pipe.

상기와 같은 목적을 달성하기 위한 본 발명은 기존에 배관된 기존배관(30)에 뜨거운 물을 넣어 열감지로 관로를 탐지하거나 기존배관(30)이 동파이프등 금속일때는 금속탐지기를 이용하여 기존배관(30)의 위치를 정확하게 찾아내는 기존배관관로 탐사공정과, 기존배관(30)에 잔여하는 물을 콤프레샤를 이용한 고압의 에어로 불어서 제거 하거나, 진공펌프를 이용하여 고압으로 흡입하는 방법으로 제거하는 기존배관배수공정과, 시공하고자 하는 기존바닥몰탈층(10)에 배관위치를 정확하게 선정하여 먹줄 등으로 표시 함으로서 배관의 간격이 일정하게 시공하도록 표시하는 배관위치표시공정과, 스폰지나 부직포에 적당량의 물을 먹여서 만든 습식포를 시공하고자 하는 기존바닥몰탈층(10)의 커팅날이 지나가는 부위에 깔아주는 습식포설치공정과, 배관을 하기에 알맞게 폭은 배관파이프(300)의 외경에 플러스공차로 형성되고 깊이는 배관파이프(300)가 매몰되고 그 위에 적당한 몰탈두께를 형성할 수있도록 직선으로 홈을파는 직선배관홈파기공정과, 직선홈파기를 끝마친 양단을 배관을 하기에 알맞게 폭은 배관파이프(300)의 외경에 플러스공차로 형성되고 깊이는 배관파이프(300)가 매몰되고 그 위에 적당한 몰탈두께를 형성할 수있도록 곡선으로 홈을파서 연결하는 양단연결배관홈파기공정과, 상기한 공정에서 적당한 폭과 깊이로 형성된 배관홈(100)에 설비하고자하는 배관파이프(300)를 깊숙히 끼워넣어서 설치하는 배관파이프설치공정과, 배관홈(100)을 형성한 기존의 기존바닥몰탈층(10)에 충분히 물을주어 수분을 머금게 함으로서 배관파이프(300) 주변에 새로운 몰탈을 채워서 충전할 때 새로운 몰탈에 함유된 수분을 기존바닥몰탈층(10)이 흡수하지 못하도록 하는 배관홈수분공급공정과, 충분히 물을먹은 기존의 몰탈의 배관홈(100) 내면에 수용액을 발라주어 기존바닥몰탈층(10)의 모세공을 막아주어 새로운 몰탈을 배관홈(100)에 충진시 새로운 몰탈의 수분이 기존의 몰탈층으로 흡수되지 않게 하는 수분이탈방지용 수용액도포공정과, 상기 배관파이프(300)가 배관된 배관홈(100)에 급결시멘트를 개어서 시멘트가 경화작용을 시작하기전에 충진하는 몰탈충진공정과, 상기한 방법으로 배관홈(100)에 충진된 급결시멘트의 표면을 기존바닥몰탈층(10)과 일치하도록 매끄럽게 마감하는 마감처리공정으로 이루어지며, 이와같은 방법으로 기존의 건축물 바닥층에 배관된 기존배관파이프(30)의 내부가비어있고 곡선배관홈이 직선배관홈 보다 크게 형성하여서 그 내부에 배관파이프(300)를 삽입설치하고, 상기 배관파이프(300)가 설치된 매몰홈(100)에 급결시멘트를 채워서 배관파이프(300)가 묻히도록 배관구조를 형성하는 것으로, 이를 각 공정별로 실시되는 실시예를 상세히 설명하면 다음과 같다.In order to achieve the above object, the present invention puts hot water into an existing pipe 30 that is previously piped to detect a pipe by heat detection or when an existing pipe 30 is a metal such as a copper pipe, an existing pipe using a metal detector. Existing pipe line exploration process to accurately locate the position (30) and existing pipes to remove the residual water in the existing pipe (30) by blowing with high pressure air using a compressor, or by suctioning at a high pressure using a vacuum pump. Piping position display process to display the pipe space uniformly by selecting the piping position on the existing floor mortar layer 10 to be installed and marking it with a feed line, and a suitable amount of water to the sponge or nonwoven fabric Wet cloth installation process and piping to the cutting blade of the existing bottom mortar layer (10) to install the wet fabric made by feeding the piping The width of the pipe pipe 300 is formed with a positive tolerance on the outer diameter of the pipe pipe 300, and the depth is a straight pipe grooving process in which the pipe pipe 300 is buried in a straight line so that the pipe pipe 300 is buried and a suitable mortar thickness is formed thereon. The width is formed with a positive tolerance in the outer diameter of the pipe pipe 300 and the depth is grooved in a curve so that the pipe pipe 300 is buried and an appropriate mortar thickness can be formed thereon so as to fit the both ends of the grooved pipe. A pipe pipe installation process for deeply inserting the pipe pipe 300 to be installed in the pipe groove 100 to be installed in the pipe groove 100 formed at a suitable width and depth in the above-described process. Fill the existing mortar layer (10) with sufficient water to fill the existing floor mortar layer (10) to form a new mortar when filling the new mortar around the piping pipe (300) Capillary of the existing bottom mortar layer (10) by applying an aqueous solution to the pipe groove water supply process to prevent the existing floor mortar layer (10) to absorb the moisture, and the inside of the pipe groove (100) of the existing mortar sufficiently ate water Blocking the ball when filling the new mortar into the pipe groove 100, the new water mortar to prevent the moisture from being absorbed into the existing mortar layer coating process of water escape, and the pipe pipe 300 is pipe piping (100) Mortar filling process to fill the cement before the hardening operation is started, and smoothly finish the surface of the cement to be filled in the pipe groove 100 in the above manner so as to coincide with the existing floor mortar layer 10. The interior of the existing pipe 30 is emptied and the curved pipe groove is formed larger than the straight pipe groove in this way. Inserting and installing the pipe pipe 300, filling the fastening cement in the buried groove 100 is installed in the pipe pipe 300 to form a pipe structure so that the pipe pipe 300 buried, it is carried out for each process An example will be described in detail as follows.

"기존배관관로 탐사공정""Existing pipeline exploration process"

기존에 배관된 관로에 뜨거운 물을 넣어 열감지로 관로를 탐지하거나 배관이 동 파이프등 금속일때는 금속탐지기를 이용하여 기존배관의 위치를 정확하게 찾아낸다.Hot water is inserted into the existing pipeline to detect the pipeline by heat detection, or when the pipeline is made of metal such as copper pipe, use a metal detector to accurately locate the existing pipeline.

이렇게 하는데에는 첫째; 기존의 배관과 작업하는 위치가 일치 함으로서 발생하는 작업공구의 마모와 작업방해 등의 요인으로 작업능률이 저하되는 것을 방지하기위하여 기존의 배관을 피해서 공사하기에 유리하도록 하기 위함이며, 둘째; 기존의 배관이 고르게 되었을 때는 기존의 배관위치를 정확하게 파내어 기존의 배관을 제거하고 새로운 배관을 함으로서 건물의 바닥면을 보호하고 배관후 기존의 배관을 따라 열량이 누설되는 것을 방지하므로 열률이 저하되는 것을 바지하기 위함이며, 세째; 기존의 배관이 동파이프 등 고가의 재생가능한 소재일 경우 회수 할 수 있으며, 네째; 바닥면에 함께시공된 수도관 등 을 손상시키지 않기위한 것이다.To do this firstly; In order to prevent the work efficiency from being deteriorated due to the wear of work tools and the interruption of work caused by the coincidence of working position with the existing pipe, it is advantageous to avoid the existing pipe work. When the existing pipe is uniform, the existing pipe position is accurately dug to remove the existing pipe, and the new pipe is installed to protect the floor of the building and to prevent heat leakage along the existing pipe. For pants, third; If the existing pipe is an expensive renewable material such as copper pipe can be recovered, fourth; The purpose is not to damage the water pipes, etc. which are installed together on the floor.

"기존배관배수공정""Existing Pipe Drainage Process"

기존의 배관에 잔여하는 물을 콤프레샤를 이용한 고압의 에어로 불어서 제거 하거나, 진공펌프를 이용하여 고압으로 흡입하는 방법으로 제거한다.Water remaining in the existing pipe is removed by blowing with high pressure air using a compressor, or by suctioning at a high pressure using a vacuum pump.

이와같이 하는 데에는 첫째; 시공중 기존의 배관에 들어있는 물이 누수되어 작업환경이나 실내환경을 더럽히는 것은 물론, 바닥면으로 스며들어 아래층으로 누수됨으로서 아래층의 천정을 더럽히는 문제점을 방지하기 위함이고, 둘째; 시공후 기존의 파이프에 남아있는 물이 서서히 증발하면서 방바닥에 습기가 차는 원인이 되는것을 방지하기 위함이다.There are first things to do in this way; It is to prevent the problem of polluting the ceiling of the lower floor by leaking water in the existing pipe during construction, as well as polluting the working environment or indoor environment, as well as seeping into the floor and leaking to the lower floor. This is to prevent the water remaining in the existing pipe after construction and slowly evaporate the moisture on the floor.

"배관위치표시공정""Plumbing position display process"

시공하고자 하는 배관위치를 정확하게 선정하여 먹줄 등으로 표시 함으로서 배관의 간격이 일정하게 시공하도록 표시하는 것이다.By selecting the pipe position to be installed correctly and marking it with a webbing line, it is to mark the pipe space uniformly.

"습식포설치공정""Wet cloth installation process"

스폰지나 부직포에 적당량의 물을 먹여서 만든 습식포를 시공하고자 하는 바닥면의 커팅날이 지나가는 부위에 깔아준다.Apply a wet cloth made by feeding an appropriate amount of water to a sponge or non-woven fabric and apply it to the area where the cutting blade on the bottom passes.

이때 습식포의 두께는 홈파기 작업시 사용하는 물의 량에 따라 다르게 하여서 작업시 톱날에 공급되는 물을 흡수하도록 하는것이 가장중요하다.At this time, it is most important that the thickness of the wet cloth varies depending on the amount of water used during the digging process to absorb the water supplied to the saw blade during the work.

상기와 같이 습식포를 깔아주는 것은, 첫째; 홈파기 작업의 하나인 커팅작업시 톱날에 공급되는 물을 흡수하여 작업용수가 바닥면(방열층, 단열층)으로 스며드는것을 방지하기 위함이고, 둘째; 커팅작업시 발생하는 분진 등의 미세한 먼지를 흡수하여 작업환경을 청결하게함은 물론, 작업먼지가 실내를 오염시키는 것을 최소화 하고, 작업에 사용하는 기계의 오염을 최소화하여 기계의 사용수명을 연장시키기 위한 것이다.To spread the wet cloth as described above, first; In order to prevent water from penetrating to the bottom surface (heat insulation layer, heat insulation layer) by absorbing the water supplied to the saw blade during the cutting operation, one of the slotting operation, second; Absorbs fine dust such as dust generated during cutting operations to clean the work environment, minimizes work dust from contaminating the room, and minimizes contamination of the machine used for work, thus extending the service life of the machine. It is for.

"직선배관홈파기공정""Linear pipe grooving process"

본 공정은 직선작업을 위하여 장비의 직선이동을 안내하는 레일을 설치하는 레일설치공정과, 상기한 레일을 따라 이동 하면서 난방 바닥면을 배관에 용이한 크기(폭은 배관파이프가 끼워지는정도의 크기)로 절단하는 절단공정과, 절단된 부위를 해머드릴이나 정으로 떼어내거나 스크레이퍼로 파서 알맞은 깊이(배관파이프가 매몰되고 그 위에 적당한 몰탈두께를 형성할 수 있는 크기)로 홈을파는 공정으로 이루어진다.This process is a rail installation process that installs a rail to guide the linear movement of the equipment for straight line work, and a size that is easy to pipe the heating floor to the pipe while moving along the above rail (width is the size that fits the pipe pipe). ), And cutting the cut portion with a hammer drill or chisel, or digging with a scraper to dig a groove to a suitable depth (size to allow the pipe pipe to be buried and form a suitable mortar thickness thereon).

여기서 장비의 종류는 크게 한정되지 않고 바닥면을 절단하고 파낼수 있는것이면 어떤 것이든 무방하다. 그러므로 전문적인 장비가 아닌 핸드그라인드나, 핸드드릴을 사용할 수 도있다. 그리고 장비의 직선이동을 안내하는 레일역시 기존에 많이 쓰이는 H빔이나 기타 장비의 이동을 안내할 수 있는 장비이면 무관하다.The type of equipment is not limited to any type of equipment, as long as it can cut and dig the floor. Therefore, you can use non-professional equipment such as hand grind or hand drill. And the rail that guides the linear movement of the equipment is also irrelevant as long as it can guide the movement of H-beams or other equipment that is used a lot.

"양단연결배관홈파기공정""End Connection Pipe Groove Process"

본 공정은 상기 직선홈파기를 끝마친 양단을 곡선으로 홈을파서 연결하기 위한것으로, 곡선작업을 위하여 장비의 곡선이동을 안내하는 레일을 설치하거나 외측을 서로 연결되도록 직선으로 절단하는 레일을 레일설치공정과, 상기한 레일을 따라 이동 하면서 난방 바닥면을 배관에 용이한 크기(폭은 배관파이프의 크기보다 약2배정도의 크기)로 곡선으로 절단하거나 외측은 직선으로 절단하고 내측은 삿갓 또는 타원형으로 절단하는 절단공정과, 절단된 부위를 해머드릴이나 정으로 떼어내거나 스크레이퍼로 파서 알맞은 깊이(배관파이프가 매몰되고 그 위에 적당한 몰탈두께를 형성할 수 있는 크기)로 배관홈을파는 공정으로 이루어진다.This process is to connect the both ends of the straight grooved groove in a curved groove, install a rail for guiding the curved movement of the equipment for the curve work or rail mounting process for cutting the rail in a straight line to be connected to each other And, while moving along the above-mentioned rails, the heating bottom is cut into curves (width is about twice as large as the size of the pipe pipe) in a pipe or the outside is cut in a straight line and the inside is cut in a hat or oval. The cutting process is carried out, and the cut part is removed by a hammer drill or a chisel, or dug with a scraper to dig a pipe groove at a suitable depth (size to allow the pipe pipe to be buried and form a suitable mortar thickness thereon).

여기서 장비의 종류는 크게 한정되지 않고 바닥면을 절단하고 파낼수 있는것이면 어떤 것이든 무방하다. 그러므로 전문적인 장비가 아닌 핸드그라인드나, 핸드드릴을 사용할 수 도있다. 그리고 장비의 곡선이동을 안내하는 레일역시 기존에 많이 쓰이는 H빔이나 기타 장비의 이동을 안내할 수 있는 장비이면 무관하다.The type of equipment is not limited to any type of equipment, as long as it can cut and dig the floor. Therefore, you can use non-professional equipment such as hand grind or hand drill. And the rail that guides the curve movement of the equipment is also irrelevant as long as it can guide the movement of H-beam or other equipment that is used a lot.

그리고 핸드머신을 이용하여 홈파기 작업을 할 때는 배관이 구부러지는 오서리의 안쪽부분에는 관이 충분히 구부러 지도록 많이 떼어내면 작업이 용이하다.And when grooving using a hand machine, it is easy to remove a lot of pipes in the inner part of the auspicious pipe where the pipe is bent enough to bend.

"배관파이프설치공정""Pipe pipe installation process"

상기한 공정에서 적당한 폭과 깊이로 형성된 배관홈에 설비하고자하는 배관파이프를 깊숙히 끼워넣어서 설치한다.In the above-described process, the pipe pipes to be installed are inserted deeply and installed in the pipe grooves formed with a suitable width and depth.

이때 배관파이프의 외경과 배관홈의 폭이 거의 일치하므로 배관파이프가 홈에 끼어서 고정되므로 별도의 배관파이프 고정수단이 필요하지 않다.At this time, since the outer diameter of the pipe pipe and the width of the pipe grooves almost coincide, the pipe pipe is clamped in the groove so that no additional pipe pipe fixing means is required.

" 배관홈수분공급공정""Plumbing Home Water Supply Process"

배관홈을형성한 기존의 바닥몰탈층에 충분히 물을주어 수분을 머금게 함으로서 배관파이프 주변에 새로운 몰탈을 채워서 충전할 때 새로운 몰탈에 함유된 수분을 기존의 몰탈층이 흡수하지 못하도록 하는 것이다.By filling enough water to the existing bottom mortar layer that formed the pipe grooves, the existing mortar layer prevents the existing mortar layer from absorbing the moisture contained in the new mortar when filling the new mortar around the pipe pipe.

이때 물을 너무 많이 주게되면 기존의 몰탈층이 흡수하고 남은 물이 단열층으로 스며들어 부작용을 일으킬 염려가 있으므로 조심하여야 하며, 만약 물을 너무 작게 주면 새로운 몰탈을 충진시 새로운 몰탈에 함유된 수분이 기존의몰탈로 흡수되면서 새로운몰탈이 급격히 수축되어 기존의몰탈과 새로운몰탈의 사이에 크랙이 생기는 원인이 된다.At this time, if too much water is absorbed by the existing mortar layer, and the remaining water may seep into the insulation layer, which may cause side effects. If water is too small, the moisture contained in the new mortar when filling the new mortar will be Absorbed by the mortar of the new mortar shrinks rapidly, causing a crack between the existing mortar and the new mortar.

"수분이탈방지용 수용액도포공정""Aqueous coating solution for moisture escape prevention"

충분히 물을먹은 기존의 몰탈의 배관홈 내면에 수용액을 발라주어 기존의 몰탈층의 모세공을 막아주어 새로운 몰탈을 배관홈에 충진시 새로운 몰탈의 수분이 기존의 몰탈층으로 흡수되지 않게 한다.Applying an aqueous solution to the inner surface of the pipe mortar of the existing mortar that has been sufficiently watered to block the capillary hole of the existing mortar layer so that when the new mortar is filled into the pipe groove, the moisture of the new mortar is not absorbed into the existing mortar layer.

이때 사용되는 수용액은 기존의 몰탈층에 형성되어있는 미세한 모세공을 막아줄 수 있는 수용성 수용액이나 기타 기존의 몰탈층과 화합할 수 있는 수용성 화합물이면 모두 사용할 수 있으며, 여기에 접착제를 섞어서 처리하면 기존의 몰탈층과 새로운 몰탈층이 보다 완벽하게 접착된다.The aqueous solution used at this time can be used as long as it is an aqueous solution that can block the fine capillary formed in the existing mortar layer or any other water-soluble compound that can be combined with the existing mortar layer. The mortar layer and the new mortar layer are more perfectly bonded.

이와같이 기존몰탈층의 배관홈 내면에 수용액을 바르는 것은 기존의 몰탈층에 미세한 모세공이 막히어서 새로운 몰탈을 충진시 모세관 현상으로 새로운 몰탈의 수분이 기존의 몰탈층에 형성된 모세공을 통하여 흡수되어 새로운 몰탈의 미세량이 아탈되면서 급격히 수축되어서 기존의 몰탈층과 새로운 몰탈 사에에 틈새가 발생하는 것을 미연에 방지하므로 기존의 몰탈층과 새로운 몰탈층이 서로 일체가 되어 하나가 되게 되는 것이다.Applying an aqueous solution to the inner surface of the pipe groove of the existing mortar layer is a capillary phenomenon when the new mortar is filled because the fine capillary is blocked in the existing mortar layer. As the fine amount of the attrition shrinks rapidly and prevents a gap between the existing mortar layer and the new mortar layer, the existing mortar layer and the new mortar layer become one with each other.

"몰탈충진공정""Mortal Filling Process"

상기한 공정이 완료되면 배관파이프가 배관된 배관홈에 급결시멘트를 개어서 시멘트가 경화작용을 시작하기전에 충진한다.When the above process is completed, the fastening cement is opened in the pipe groove to which the pipe pipe is piped and filled before the cement starts to harden.

이때 주의하여야 할 것은 급결시멘트가 경화작용을 일으키기전에 배관홈에 채우는 것이 중요하다.It should be noted that it is important to fill the pipe grooves before the hardened cement hardens.

"마감처리공정""Finishing process"

상기한 방법으로 배관홈에 충진된 급결시멘트가 완전히 경화가 되기전에 금속미장칼이나 헤라 등을 이용하여표면을 매끄럽게 마감하고, 그래도 표면의 거친 부분이 있으면, 완전히 경화된 이후에 연마석이나 가타 연마제로 표면을 갈아내어서 마감처리를 한다.Finish the surface smoothly using metal plaster or hera before the hardened cement filled in the pipe groove is hardened by the above method. Grind the surface and finish.

상기한 공정으로 완성된 본 발명은 기존의 건축물 바닥층에 배관된 기존 배관파이프의 내부가비어있고 곡선배관파이프매몰홈이 직선배관매몰홈 보다 크게 형성하여서 그 내부에 배관파이프를 삽입설치하고, 상기 배관파이프가 설치된 매몰홈에 급결시멘트를 채워서 배관파이프가 묻히도록 배관구조를 형성한다.The present invention completed in the above process is empty the inside of the existing piping pipe piped to the existing floor of the building and the curved pipe pipe investment groove is formed larger than the straight pipe investment groove to insert the pipe pipe therein, the pipe Fill the fastening cement into the buried groove where the pipe is installed to form the pipe structure so that the pipe pipe is buried.

상기와 같은 본 발명은 배관파이프가 고장나거나 낡아서 교체하고자 할 때 기존의 미장몰탈층을 전부 들어내지 않고 배관파이프가 배관되는 부위만을 배관파이프의 직경에 알맞도록 적당한 깊이와 넓이를 갖는 요홈으로 파내고, 새로운 배관을 하고서 새로운 몰탈과 기존의 몰탈 사이가 갈라지지 않도록 처리한후, 급속히 경화되는 급결시멘트로 배관파이프가 배관된 배관홈을 충진하여 시공을 마감함으로서 신속한 배관작업이 이루어져 공사기간이 기존의 공법으로 7일정도 걸려야 하는것이 단하루만에 끝나는 것은 물론이고, 작업시 먼지나 소음발생을 최소화 하여 기타 자업이 보다 아주 간단한 방법으로 신속하면서도 견고하게 온돌파이프의 교체작업을 할 수 있음은 물론 시공비용이 절감되며 건축물자체에도 과중한 하중을 주지 않게 된다.In the present invention as described above, when the pipe pipe is broken or worn out, the existing pipeless mortar layer is not lifted out, but only the portion where the pipe pipe is piped into a groove having a suitable depth and width to suit the diameter of the pipe pipe. After the new piping is processed to prevent the cracking between the new mortar and the existing mortar, the rapid hardening of the cement pipe fills the pipe grooved with the piping pipe and finishes the construction. Not only does it take about 7 days to finish in a single day, but it also minimizes the occurrence of dust and noise when working, so that other workers can change their ondol pipes quickly and firmly in a simpler way. The cost is reduced and the building itself is not overburdened.

그리고 온돌파이프의 교체작업시 미장몰탈층을 깨내는 것이 아니라 요홈부분만 절단함으로 해서 건축물의 바닥에 심한 충격을 주지 않아도 되므로 충격으로 인한 건물의 균열등이 발생할 염려가 전혀 없음은 물론 충격소음을 줄여 주는등 안심하고 공사를 할 수 있는등 온돌파이프를 교체하는 공사에서는 없어서는 아니될 매우 획기적인 발명이다.In addition, it is not necessary to break the mortar layer at the time of replacing the ondol pipe, but by cutting only the groove part, so that the floor of the building does not have to be severely impacted. It is a very innovative invention that is indispensable in constructions that replace ondol pipes, such as giving construction works with confidence.

Claims (2)

기존에 배관된 관로에 뜨거운 물을 넣어 열감지로 관로를 탐지하거나 배관이 동 파이프등 금속일때는 금속탐지기를 이용하여 기존배관의 위치를 정확하게 찾아내는 기존배관관로 탐사공정과,Existing pipe line exploration process that inserts hot water into the existing pipe line to detect the pipe line by heat detection, or when the pipe is metal such as copper pipe, accurately locates the existing pipe using a metal detector; 기존의 배관에 잔여하는 물을 콤프레샤를 이용한 고압의 에어로 불어서 제거 하거나, 진공펌프를 이용하여 고압으로 흡입하는 방법으로 제거하는 기존배관배수공정과,Existing pipe drainage process of removing residual water in the existing pipe by blowing with high pressure air using a compressor or by suctioning at high pressure using a vacuum pump, 시공하고자 하는 배관위치를 정확하게 선정하여 먹줄 등으로 표시 함으로서 배관의 간격이 일정하게 시공하도록 표시하는 배관위치표시공정과,Piping position display process to display the pipe space uniformly by selecting the pipe position to be constructed accurately and marking it with a feed line, etc. 스폰지나 부직포에 적당량의 물을 먹여서 만든 습식포를 시공하고자 하는 바닥면의 커팅날이 지나가는 부위에 깔아주는 습식포설치공정과,Wet cloth installation process that spreads wet cloth made by feeding appropriate amount of water to sponge or nonwoven fabric on the part where cutting edge of the bottom surface is going to be installed, 배관을 하기에 알맞게 폭은 배관파이프의 외경에 플러스공차로형성되고 깊이는 배관파이프가 매몰되고 그 위에 적당한 몰탈두께를 형성할 수있도록 직선으로 홈을파는 직선배관홈파기공정과,The straight pipe grooving process, in which the width is formed with a plus tolerance in the outer diameter of the pipe pipe and the depth is grooved in a straight line so that the pipe pipe is buried and a suitable mortar thickness is formed thereon. 직선홈파기를 끝마친 양단을 배관을 하기에 알맞게 폭은 배관파이프의 외경에 플러스공차로형성되고 깊이는 배관파이프가 매몰되고 그 위에 적당한 몰탈두께를 형성할 수있도록 곡선으로 홈을파서 연결하거나 외측은 직선으로 절단하여 연결하고 내측은 삿갓형으로 절단하여 파내므로서 양단을 연결하는 배관홈을 형성하는 양단연결배관홈파기공정과,The width is formed with positive tolerances on the outer diameter of the pipe pipe and the depth is connected to the pipe so that the pipe is buried and the appropriate mortar thickness is formed on the outside of the pipe pipe. Connecting and cutting both ends of the pipe to form a pipe groove connecting both ends by cutting and digging in a straight line and digging inside 상기한 공정에서 적당한 폭과 깊이로 형성된 배관홈에 설비하고자하는 배관파이프를 깊숙히 끼워넣어서 설치하는 배관파이프설치공정과,A pipe pipe installation step of inserting a pipe pipe to be installed deeply into a pipe groove formed at a suitable width and depth in the above-described process; 배관홈을형성한 기존의 바닥몰탈층에 충분히 물을주어 수분을 머금게 함으로서 배관파이프 주변에 새로운 몰탈을 채워서 충전할 때 새로운 몰탈에 함유된 수분을 기존의 몰탈층이 흡수하지 못하도록 하는 배관홈수분공급공정과,Plumbing groove moisture supply that prevents the existing mortar layer from absorbing the moisture contained in the new mortar by filling the new mortar around the pipe pipe by filling the existing floor mortar layer with sufficient water to fill the water. Fair, 충분히 물을먹은 기존의 몰탈의 배관홈 내면에 수용액을 발라주어 기존의 몰탈층의 모세공을 막아주어 새로운 몰탈을 배관홈에 충진시 새로운 몰탈의 수분이 기존의 몰탈층으로 흡수되지 않게 하는 수분이탈방지용 수용액도포공정과,Applying an aqueous solution to the inner surface of the pipe mortar of the existing mortar that has been sufficiently watered to block the capillary hole of the existing mortar layer so that when the new mortar is filled into the pipe groove, the moisture of the new mortar is not absorbed into the existing mortar layer. Prevention aqueous solution coating process, 상기 배관파이프가 배관된 배관홈에 급결시멘트를 개어서 시멘트가 경화작용을 시작하기전에 충진하는 몰탈충진공정과,A mortar filling process of filling a cement before the hardening operation by opening a quick cement in the pipe groove to which the pipe pipe is piped; 상기한 방법으로 배관홈에 충진된 급결시멘트의 표면을 기존의몰탈층과 일치하도록 매끄럽게 마감하는 마감처리공정으로 이루어짐을 특징으로하는 홈파기공법 배관파이프 교체방법.Grooving method pipe pipe replacement method characterized in that it consists of a finishing process to smoothly finish the surface of the fastened cement filled in the pipe groove in accordance with the above method to match the existing mortar layer. 건축물의 바닥층에 새로이 배관을 함에 있어서,In newly piped to the floor of the building, 기존의 건축물 바닥층에 배관된 기존 배관파이프의 내부가비어있고 곡선배관파이프매몰홈이 직선배관매몰홈 보다 크게 형성하여서 그 내부에 배관파이프를 삽입설치하고, 상기 배관파이프가 설치된 매몰홈에 급결시멘트를 채워서 배관파이프 가 묻히도록 배관구조를 구성함을 특징으로하는 홈파기공법 배관파이프 교체방법으로 시공된 배관구조.The inside of the existing plumbing pipe that is piped to the floor of the existing building is hollow and the curved piping pipe groove is formed to be larger than the straight piping investment groove, so that the pipe pipe is inserted into the inside of the pipe. Piping structure constructed by grooving method pipe pipe replacement method characterized by constructing piping structure to fill the pipe pipe by filling it.
KR10-2001-0020048A 2001-04-14 2001-04-14 a piping to change method by groove digging method of construction and the hypocaust floor structure got fromit KR100414801B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2001-0020048A KR100414801B1 (en) 2001-04-14 2001-04-14 a piping to change method by groove digging method of construction and the hypocaust floor structure got fromit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2001-0020048A KR100414801B1 (en) 2001-04-14 2001-04-14 a piping to change method by groove digging method of construction and the hypocaust floor structure got fromit

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020010021870U Division KR200261668Y1 (en) 2001-07-19 2001-07-19 a piping to change method by groove digging method of the hypocaust floor structure got fromit

Publications (2)

Publication Number Publication Date
KR20020079260A true KR20020079260A (en) 2002-10-19
KR100414801B1 KR100414801B1 (en) 2004-01-16

Family

ID=27701128

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2001-0020048A KR100414801B1 (en) 2001-04-14 2001-04-14 a piping to change method by groove digging method of construction and the hypocaust floor structure got fromit

Country Status (1)

Country Link
KR (1) KR100414801B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20210148604A (en) * 2020-06-01 2021-12-08 김근수 Building piping replacement construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20210148604A (en) * 2020-06-01 2021-12-08 김근수 Building piping replacement construction method

Also Published As

Publication number Publication date
KR100414801B1 (en) 2004-01-16

Similar Documents

Publication Publication Date Title
CN104790595A (en) Construction method for adjustable tile hanging system of pitched roof
CN113323440A (en) Concrete gap repairing and anti-seepage treatment method
NO335635B1 (en) Device for removing loose-bore material
CN207959289U (en) Structure is repaired in a kind of leak for basement post-pouring zone position
KR20020079260A (en) a piping to change method by groove digging method of construction and the hypocaust floor structure got fromit
KR100414802B1 (en) a piping to change method by groove digging method of construction and the hypocaust floor structure got fromit
CN103556825B (en) The construction method of preserved pipeline sleeve pipe in a kind of high building structure layer concrete
KR200261668Y1 (en) a piping to change method by groove digging method of the hypocaust floor structure got fromit
KR200444865Y1 (en) Closeing Tool for Penetration Sleeve
CN204419202U (en) A kind of tunnel slot repair structure
JP3885422B2 (en) Buried structure and construction method in Japanese-style toilet repair
KR20020079258A (en) a piping to change method by groove digging method of construction and the hypocaust floor structure got fromit
KR102391541B1 (en) Building piping replacement construction method
CN106223497A (en) A kind of operational approach of Applying Steel Structures To A Villa integrated system
CN207685959U (en) A kind of floor when construction for Super High intercepts water drainage arrangement
KR102197844B1 (en) How to replace ondol floor piping using cutting method
KR102408861B1 (en) Building piping replacement construction method
KR101091797B1 (en) Exchanging method of bottom pipe and thereof structure
CN113914540B (en) Construction method for reserving and embedding electromechanical wire pipes in block wall
CN104747798A (en) Drainage pipe installation construction method for kitchens or bathrooms
CN215518920U (en) Underground floor seepage maintenance structure
CN114293807B (en) Plugging method for basement concrete dynamic cracks
JP7312391B2 (en) Slab penetrating unit and drain pipe connection structure using the same
CN220645338U (en) Expansibility concrete floor crack repair structure
RU2725347C1 (en) Method of device of cutoff waterproofing at reconstruction of buildings and structures for reconstruction and re-profiling of industrial enterprises

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121031

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20131119

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20141202

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20151222

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20181231

Year of fee payment: 16

FPAY Annual fee payment

Payment date: 20191212

Year of fee payment: 17