KR20020011270A - Arch structure of subway or common duct in excavating process of constructing and method of constructing the same - Google Patents

Arch structure of subway or common duct in excavating process of constructing and method of constructing the same Download PDF

Info

Publication number
KR20020011270A
KR20020011270A KR1020000044648A KR20000044648A KR20020011270A KR 20020011270 A KR20020011270 A KR 20020011270A KR 1020000044648 A KR1020000044648 A KR 1020000044648A KR 20000044648 A KR20000044648 A KR 20000044648A KR 20020011270 A KR20020011270 A KR 20020011270A
Authority
KR
South Korea
Prior art keywords
formwork
roof
wall
club
haunch
Prior art date
Application number
KR1020000044648A
Other languages
Korean (ko)
Other versions
KR100390369B1 (en
Inventor
강예석
이순호
Original Assignee
이순호
고윤철
주식회사 경호엔지니어링 종합건축사사무소
강성동
(주)강호엔지니어링건축사사무소
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이순호, 고윤철, 주식회사 경호엔지니어링 종합건축사사무소, 강성동, (주)강호엔지니어링건축사사무소 filed Critical 이순호
Priority to KR10-2000-0044648A priority Critical patent/KR100390369B1/en
Publication of KR20020011270A publication Critical patent/KR20020011270A/en
Application granted granted Critical
Publication of KR100390369B1 publication Critical patent/KR100390369B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

PURPOSE: An arch structure and its construction method of a subway and a common duct are provided to minimize a bending moment of a structure, to restrain the application of forces except a compressive force, and to use a mobile support. CONSTITUTION: A construction method of an arch structure comprises the steps of forming a base unit(22) in the underground space; forming a haunch unit(23) on the base unit; forming a wall unit(24) on the haunch unit using a mobile support for supporting an inner mold of a wall unit; and forming a roof unit(25) using another mobile support for supporting an inner mold of a roof. By using the mobile supports, construction efficiency and quality of a structure are improved. Further, period of construction work and costs are saved.

Description

개착(開鑿)식으로 시공되는 지하철 및 공동구의 아치형 구조 및 그 시공 방법{Arch structure of subway or common duct in excavating process of constructing and method of constructing the same}Arch structure of subway or common duct in excavating process of constructing and method of constructing the same}

본 발명은 개착(開鑿)식으로 시공되는 지하철 및 공동구의 아치형 구조 및 그의 시공 방법에 관한 것이다. 보다 구체적으로는, 지하철 및 공동구의 개착식 시공에서, 구조물 단면 형상이 단순하여 이동식 동바리를 사용할 수 있고 휨모멘트가 거의 발생하지 않으며 축방향 압축력만이 작용하는 아치형 구조 및 그를 시공하는 방법에 관한 것이다.TECHNICAL FIELD The present invention relates to an arched structure of a subway and a public sphere, and a construction method thereof. More specifically, it relates to an arched structure and a method of constructing the structure of the subway and the public sphere, which has a simple cross-sectional shape, which allows the use of mobile clubs, almost no bending moment, and axial compressive force. .

통상적으로 개착식 공법은 지하 구조물이 설치되는 깊이가 약 18m 이하일 때, 터널공법보다 공사비용과 공기 면에서 유리하기 때문에 지하철 공사 및 공동구공사에서 널리 활용되고 있다. 그러나 굴착 후 축조되는 지하철 및 공동구 구조는 라멘식 박스형 구조에 한정되어 왔다. 따라서 되메우기 후 토압, 수압, 및 활하중에 의해 발생하는 휨모멘트를 지지하기 위해서 철근량을 증가시키고 헌치, 기둥 및 거더 등을 만듦으로써 구조물 내부 단면이 매우 복잡해진다. 복잡한 단면 형상에 따라, 거푸집 작업시 이동식 동바리를 사용할 수 없을 뿐 아니라 철근 배근 공정도 복잡하여 시공성이 저하되고 장기간의 공기가 요구된다. 또한, 철근량 과다로 콘크리트 타설시 골재 투입이 원할치 못하게 되어 밀실한 콘크리트 품질 확보에 어려움이 있다.In general, when the installation method is about 18m or less in the depth of the underground structure is installed, it is widely used in subway construction and joint construction because it is advantageous in terms of construction cost and air than the tunnel method. However, the construction of the subway and hollow ball structure after the excavation has been limited to the ramen box structure. Therefore, the cross section of the structure becomes very complicated by increasing the amount of reinforcing bars and creating haunches, columns and girders to support the bending moments generated by earth pressure, hydraulic pressure, and live load after backfilling. According to the complicated cross-sectional shape, not only can not use a movable copper bar when formwork, but also the rebar reinforcement process is complicated, the workability is reduced and long-term air is required. In addition, when the concrete is poured due to the excessive amount of reinforcement, it is difficult to secure tight concrete quality due to the unwanted input of aggregate.

본 발명은 휨모멘트가 거의 발생하지 않고 축방향 압축력만이 작용하는 단순한 단면의 구조를 채용함으로써 이동식 동바리를 사용할 수 있게 하여 시공성을 향상시키고 철근량 및 단면두께를 감소시켜 자재비를 절감하고 나아가 우수한 시공 품질을 제공할 수 있는 개착식으로 시공되는 지하철 및 공동구의 아치형 구조와 그의 시공 방법이다.The present invention adopts a simple cross-section structure in which bending moment is hardly generated and only axial compressive force is applied, which enables the use of movable copper clubs, thereby improving workability and reducing material costs by reducing rebar amount and cross-sectional thickness, and further improving construction quality. It is an arched structure of the subway and the public sphere that can be provided as a detachable construction and its construction method.

본 발명의 목적은 개착(開鑿)식으로 시공되는 지하철 및 공동구에서, 구조물에 휨모멘트가 거의 발생하지 않고 축방향 압축력만이 작용하게 하고 단순한 단면 형상으로 이동식 동바리를 사용 가능하게 하는 아치형 구조와 그의 시공방법을 제공하는 것이다.An object of the present invention is an arcuate structure and its arcuate structure, in which subways and hollow spheres are constructed in a detachable manner so that the bending moment is hardly generated in the structure and only the axial compressive force is applied and the movable club can be used in a simple cross-sectional shape. It is to provide a construction method.

제1도는 본 발명의 아치형 구조물의 완성된 구간과 가시설 상태를 동시에 나타낸 단면도이다.1 is a cross-sectional view showing the completed section of the arcuate structure of the present invention and the provisional state at the same time.

제2도는 본 발명의 아치형 구조물의 기초부 시공 단면도이다.2 is a cross-sectional view of the foundation of the arch structure of the present invention.

제3도는 본 발명의 아치형 구조물의 헌치부 시공 단면도이다.3 is a cross-sectional view of the haunch portion construction of the arch structure of the present invention.

제4도는 본 발명의 아치형 구조물의 벽체부 시공 단면도이다.4 is a cross-sectional view of the wall portion construction of the arch structure of the present invention.

제5도는 본 발명의 아치형 구조물의 지붕부 시공 단면도이다.5 is a cross-sectional view of the roof construction of the arch structure of the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

11 : 지반 12 : 앵글11: ground 12: angle

13 : 수평버팀보(strut) 14 : 복공판13 horizontal strut 14 perforated plate

15, 15` : 잭 16 : 브라켓15, 15`: Jack 16: Bracket

17 : 엄지말뚝(측벽 PILE) 18 : 어스 앙카17: Thumb pile (side wall PILE) 18: Earth anchor

19 : 수직 쐐기화타 21 : 아치형 구조물19: vertical wedges 21: arched structure

22 : 아치형 구조물 기초부 23 : 아치형 구조물 헌치부22: arched structure foundation 23: arched structure haunting unit

24 : 아치형 구조물 벽체부 25 : 아치형 구조물 지붕부24: arch structure wall portion 25: arch structure roof portion

26 : 바닥 방수부26: bottom waterproof

31 : 벽체부 내부 거푸집 지지용 이동식 동바리31: movable club for supporting formwork inside the wall

32 : 지붕부 내부 거푸집 지지용 이동식 동바리32: movable club for supporting formwork inside roof

33, 33` : 타워 동바리 34 : 잭 서포트33, 33`: Tower Dong 34: Jack Support

35 : 바퀴 36 : 동바리 하단 지지대35: wheel 36: bottom support

41 : 레일 42, 42` : 로프41: rail 42, 42`: rope

43 : 콘크리트 타설 구멍 44 : 거푸집 진동기43: concrete pouring hole 44: formwork vibrator

45 : 되메우기한 부분45: backfill

본 발명의 구체예의 도면에 따라 설명한다.It demonstrates according to drawing of the specific example of this invention.

제1도 내지 제3도와 같이, 본 발명이 실시되는 지하 공간에 흙막이 가시설을 설치하는 과정 및 방법은 다음과 같다. 먼저 엄지말뚝(17)을 2 m 간격으로 소정 깊이까지 설치하고, 굴착작업을 진행하면서 굴착깊이가 일정 깊이에 도달할 때마다 흙막이 가시설을 설치하고 그 깊이까지의 가시설이 완성되면 다시 굴착작업을 진행하고 상기 단계를 반복하여 설계된 소정 깊이까지 굴착을 진행한다. 상기 흙막이 가시설을 구성하는 2단 수평 버팀보(13)의 수평 간격은 상기의 엄지말뚝(17)과 동일 간격인 2m 로 설치한다. 그런데 1단 및 2단 수평 버팀보 간의 설치 간격과 동일하게 2단 및 3단 수평 버팀보를 설치하게 되면, 본 발명의 아치형 구조물 지붕부(25)를 시공할 때, 상기 3단 수평 버팀보를 해체해야 한다. 그러한 경우 흙막이 벽체에서 수평 지지부재가 없는 영역이 넓어져 상기 벽체에 가해지는 토압을 지지하기가 어렵게 된다. 따라서 상기 3단 버팀보가 설치될 위치에 2단 수평 버팀보를 이용하여 수직 화타쐐기(19)를 상기 엄지말뚝(17)과 용접하여 설치하거나 상기 수직 화타쐐기(19) 대신 어스 앙카(18)를 설치한다. 상기 수직 화타쐐기(19)나 상기 어스 앙카(18)는 수평으로 가로지르는 부재가 아니므로 가시설 해체없이 상기 아치형 구조물 지붕부(25)를 시공할 수 있다.As shown in Figures 1 to 3, the process and method for installing the temporary housing in the basement space is implemented as follows. First, the thumb pile 17 is installed to a predetermined depth at intervals of 2 m, and when the excavation depth reaches a certain depth while the excavation work is carried out, the earthquake temporary facility is installed. And repeat the above steps to proceed with the excavation to the designed depth. The horizontal spacing of the two-stage horizontal braces 13 constituting the earthenware temporary installation is installed at the same distance as the thumb pile 17, 2m. However, if the two-stage and three-stage horizontal braces are installed in the same manner as the installation interval between the first and second stage braces, the three-stage horizontal braces should be dismantled when constructing the arch structure roof portion 25 of the present invention. . In such a case, the area without the horizontal support member in the retaining wall becomes wide, making it difficult to support the earth pressure applied to the wall. Therefore, by using a two-stage horizontal brace in the position where the three-stage braces will be installed by installing a vertical weeding wedge 19 with the thumb pile 17 or install an earth anchor 18 instead of the vertical weeding wedge 19. do. Since the vertical wedges 19 or the earth anchors 18 are not horizontally transverse members, the arcuate structure roof 25 may be constructed without dismantling the temporary equipment.

제1도와 같이, 본 발명은 굴착된 지반(11) 위에 설치되는 기초부(22); 상기 기초부(22) 양단부 위에 설치되는 헌치부(23); 상기 헌치부(23) 위에 헌치부(23)와 외각선을 맞추어 설치되는 벽체부(24); 및, 상기 벽체부(24) 위에 벽체부(24)의 두께와 일치되도록 설치되는 원형의 지붕부(25);를 포함하는 개착식으로 시공되는 지하철 및 공동구의 아치형 구조(21) 및 그의 시공 방법이다.As shown in FIG. 1, the present invention includes: a base portion 22 installed on an excavated ground 11; Haunting unit 23 is installed on both ends of the base portion 22; A wall portion 24 installed on the haunch portion 23 in line with the haunch portion 23 and an outer line; And a circular roof portion 25 installed on the wall portion 24 so as to match the thickness of the wall portion 24. to be.

본 발명이 실시되는 곳의 지질, 하중 조건, 또는 시공 조건에 따라, 상기 기초부(22)의 단면 형상은 상하부면이 모두 평평하게 형성되거나, 상부면은 평평하고 하부면은 원형으로 형성되는 아치형 인버트(invert)이고, 상기 벽체부(24)는 단면 형상이 수직으로 형성되는 반아치형이거나 바깥쪽으로 경사지게 형성되는 마제(馬蹄)형 아치이거나 외부로 볼록한 곡면으로 형성되는 원형 아치일 수 있다.Depending on the geology, loading conditions, or construction conditions where the present invention is practiced, the cross-sectional shape of the base portion 22 is formed in both the upper and lower surfaces are flat, or the upper surface is flat and the lower surface is formed in an arch shape Inverted (invert), the wall portion 24 may be a semi-arch shaped cross-sectional shape is formed vertically, a horse-shaped arch formed to be inclined outwardly or a circular arch formed to the outer convex curved surface.

제2도 내지 제5도와 같이, 터파기와 흙막이 가시설 설치 작업을 완료한 지반(11) 위를 바닥방수(26)한 후, 본 발명의 기초부(22) 철근을 배근하고 거푸집을 설치하고 콘크리트를 타설하여 상기 기초부(22)를 형성하는 1단계; 상기 기초부(22)의 거푸집을 해체하고 기초부(22)의 철근과 연결하여 본 발명의 헌치부(23) 철근을 배근하고 거푸집을 설치하고 콘크리트를 타설하여 상기 헌치부(23)를 형성하는 2단계; 상기 헌치부(23)의 거푸집을 해체하고 헌치부(23)를 방수하고 헌치 외각부(45)를 되메우는 3단계; 본 발명의 벽체부(24)가 설치될 위치 주변의 가시설을 해체하고 벽체부 내부 거푸집 지지용 이동식 동바리(31)를 설치하고 상기 동바리의 잭서포트(34)와 일체화된 내부 거푸집을 설치하고 상기 헌치부(23)의 철근과 연결하여 벽체부(24)의 철근을 배근하고 외부 거푸집을 설치하고 콘크리트를 타설하여 상기 벽체부(24)를 형성하는 4단계; 상기 벽체부(24)의 거푸집을 해체하고 상기 이동식 동바리(31)를 이동시키고 벽체부(24)를 방수하고 벽체 외각부를 되메우는 5단계; 본 발명의 지붕부(25)가 설치될 위치 주변의 가시설을 해체하고 상기 지붕부 지지용 이동식 동바리(32)를 설치하고 상기 동바리의 잭 서포트(34)와 일체화된 내부 거푸집을 설치하고 벽체부(24)의 철근과 연결하여 상기 지붕부 철근을 배근하고 외부 거푸집을 설치하고 콘크리트를 타설하여 상기 지붕부(25)를 형성하는 6단계; 및, 상기 지붕부(25)의 거푸집을 해체하고 방수하고 되메우기를 하는 7단계; 를 포함하고, 상기 각 단계는 시공 구간별로 연속하여 행해진다.2 to 5, after waterproofing (26) on the ground (11) on the ground and completed the temporary installation of the temporary equipment and earthenware, reinforcing the base portion 22 of the present invention, install the formwork and concrete 1 step of forming the base portion 22 by pouring; Dismantling the formwork of the base portion 22 and connecting with the reinforcing bar of the base portion 22 to reinforce the reinforcing portion 23 reinforcement of the present invention, install the formwork and cast concrete to form the haunch portion 23 Step 2; Disassembling the formwork of the haunch (23), waterproofing the haunch (23) and backfill the haunch outer portion (45); Dismantling the provisional facility around the location of the wall portion 24 of the present invention and installing a movable club for supporting the formwork inside the wall, and installing an internal formwork integrated with the jack support 34 of the club and the old 4 steps of forming the wall portion 24 by connecting the reinforcement of the tooth 23 to reinforce the reinforcement of the wall portion 24, installing an external formwork, and placing concrete; Disassembling the formwork of the wall part 24, moving the movable club 31, waterproofing the wall part 24, and backfilling the wall outer part; Dismantle the provisional facilities around the location of the roof portion 25 of the present invention, install the movable club 32 for the roof support, and install the internal formwork integrated with the jack support 34 of the club, and the wall part ( Step 6 is connected to the reinforcement of the 24 to reinforce the roof reinforcement, install the external formwork and cast the concrete to form the roof portion 25; And, seven steps of dismantling the formwork of the roof portion 25, waterproof and backfill; Includes, each step is performed successively for each construction section.

제4도 및 제5도와 같이, 상기 4단계의 벽체부 내부 거푸집 지지용 이동식 동바리(31)는 다리부의 단부에 바퀴(35)가 달려있고 상기 벽체부(24)와 동일한 높이이고, 작업원 및 자재 이동시 지장이 없도록 로프(42`)로 들어올려 고정시켰다가 콘크리트 타설시 상기 로프(42`)를 내리고 잭(15`)을 조여 고정하는 하단 지지대(36)가 설치되어있는 타워 동바리(33); 와 상기 타워 동바리(33)와 일방 단부를 용접등으로 접합시킨 다수개의 잭 서포트(34); 를 포함하고, 상기 6단계의 지붕부 내부 거푸집 지지용 이동식 동바리(32)는 다리부의 단부에 바퀴(35)가 달려있고 본 발명의 지붕부(25)에 설치되는 내부 거푸집을 지지할 수 있는 높이의 타워 동바리(33`) 와 상기 타워 동바리(33`)와 일방 단부를 용접 등으로 접합시킨 다수개의 잭 서포트(34)를 포함한다.As shown in FIGS. 4 and 5, the movable club 31 for supporting the formwork inside the wall portion of the fourth stage has a wheel 35 at the end of the leg portion and is the same height as the wall portion 24. The tower club (33) is provided with a lower support (36) for lifting and fixing with a rope (42`) so that there is no problem during material movement, and then lowering the rope (42`) and tightening the jack (15`) when concrete is placed. ; And a plurality of jack supports 34 in which the tower club 33 and one end are joined by welding or the like; Includes, the movable roof for supporting the inner formwork of the roof of the six stages 32 is a height that can support the inner formwork is installed on the roof portion of the present invention with the wheel 35 is attached to the end of the leg portion And a plurality of jack supports 34 in which the tower clubs 33 'and the tower clubs 33' and one end thereof are joined by welding or the like.

전술한 4단계의 외부 거푸집은 상기 구조물의 벽체부(24) 바로 위의 수평버팀보(13) 하부 레일(41)에 매달린 로프(42)와 연결하여 이동시키는 일체형 이동식 거푸집이거나 인력(人力)으로 이동시키는 낱개(piece)형 거푸집이고, 또 전술한 6단계의 외부 거푸집은 상기 구조물 지붕부(25) 바로 위의 수평버팀보(13) 하부 레일(41)에 매달린 로프(42)와 연결되어 이동시키는 이동식 거푸집이다. 그리고 상기 6단계의 외부 거푸집 높이의 1/3, 2/3 지점 및 천단부에 콘크리트 타설 구멍(43)을 상기 구조물(21)의 종방향으로 일정하게 설치하고 콘크리트 타설 후 공극이 생기지 않도록 상기 천단부의 구멍(43)은 위쪽으로 돌출되게 테두리 처리를 한다.The external formwork of the above-described four stages is an integrated movable formwork or gravity moving connected to the rope 42 suspended from the horizontal rail 13 and the lower rail 41 just above the wall portion 24 of the structure. It is a piece-shaped formwork, and the above-described six-step formwork is movable to move in connection with the rope 42 suspended on the lower rail 41 of the horizontal support 13 just above the roof portion 25 of the structure. It is a formwork. In addition, the concrete placing holes 43 are uniformly installed in the longitudinal direction of the structure 21 at one-third, two-thirds, and the top ends of the heights of the external formwork of the six steps, and the voids are not formed after the concrete is placed. The negative hole 43 is edged to protrude upward.

본 발명으로 개착(開鑿)식으로 시공되는 지하철 및 지하 공동구를 휨모멘트가 거의 발생하지 않고 축방향 압축력만이 작용하는 아치형 구조로 축조함으로써, 철근량 및 단면두께를 감소시킴은 물론, 구조물 형상을 단순화하여 이동식 동바리 이용이 가능토록 하였고, 이에 따라 시공성 향상, 공기단축을 통한 공사비용 절감과 우수한 시공 품질을 제공하게 되었다.According to the present invention, by constructing the subway and underground hollow spheres to be constructed in an open manner with an arch structure in which almost no bending moment is generated and only an axial compression force is applied, the amount of rebar and the cross-sectional thickness are reduced, as well as the structure shape is simplified. Therefore, it is possible to use mobile clubs, thereby improving construction performance, reducing construction costs through air shortening, and providing excellent construction quality.

Claims (5)

굴착된 지반(11) 위에 설치되는 기초부(22);A foundation 22 installed on the excavated ground 11; 상기 기초부(22) 양단부 위에 설치되는 헌치부(23);Haunting unit 23 is installed on both ends of the base portion 22; 상기 헌치부(23) 위에 헌치부(23)와 외각선을 맞추어 설치되는 벽체부(24); 및,A wall portion 24 installed on the haunch portion 23 in line with the haunch portion 23 and an outer line; And, 상기 벽체부(24) 위에 벽체부(24)의 두께와 일치되도록 설치되는 원형의 지붕부(25);A circular roof portion 25 installed on the wall portion 24 so as to match the thickness of the wall portion 24; 를 포함하는 것을 특징으로 하는 개착(開鑿)식으로 시공되는 지하철 및 공동구의 아치형 구조(21).Arched structure (21) of the subway and the public sphere to be constructed in an attached manner characterized in that it comprises a. 제1항에서, 상기 기초부(22)는 시공되는 곳의 지질, 하중 조건, 또는 시공 조건에 따라, 단면 형상이 상하부면 모두 평평하게 형성되거나, 상부면은 평평하고 하부면은 원형으로 형성되는 아치형 인버트(invert)이고, 상기 벽체부(24)는 단면 형상이 수직으로 형성되는 반아치형이거나, 바깥쪽으로 경사지게 형성되는 마제(馬蹄)형 아치이거나, 외부로 볼록한 곡면으로 형성되는 원형 아치인 것을 특징으로 하는 개착식으로 시공되는 지하철 및 공동구의 아치형 구조(21).According to claim 1, wherein the base portion 22 is formed in the cross-sectional shape of both the upper and lower surfaces are flat, or the upper surface is flat and the lower surface is formed in a circular shape depending on the geology, load conditions, or construction conditions of the construction site It is an arcuate invert (invert), the wall portion 24 is a semi-arch shaped cross-sectional shape is formed vertically, or horseshoe arch formed to be inclined outward, or is a circular arch formed in the outer convex surface Arched structure (21) of the subway and the public sphere to be constructed as a detachable. 굴착된 지반(11) 위를 바닥 방수(26)한 후 제1항 및 제2항의 기초부(22)의 철근을 배근하고 거푸집을 설치하고 콘크리트를 타설하여 상기 기초부(22)를 형성하는 1단계;1 to form the foundation part 22 by reinforcing the reinforcing bar of the foundation part 22 of claim 1 and claim 2, and then installing the formwork and placing concrete after the bottom waterproofing 26 on the excavated ground (11). step; 상기 기초부(22)의 거푸집을 해체하고 기초부(22)의 철근과 연결하여 제1항의 헌치부(23)의 철근을 배근하고 거푸집을 설치하고 콘크리트를 타설하여 상기 헌치부(23)를 형성하는 2단계;The formwork of the base part 22 is dismantled and connected to the reinforcing bar of the base part 22 to reinforce the reinforcing bar of the haunting part 23 of claim 1, to form the formwork, and to cast the concrete to form the haunch part 23. Two steps; 상기 헌치부(23)의 거푸집을 해체하고 헌치부(23)를 방수하고 헌치 외각부(45)를 되메우는 3단계;Disassembling the formwork of the haunch (23), waterproofing the haunch (23) and backfill the haunch outer portion (45); 제1항 및 제2항의 벽체부(24)가 설치될 위치 주변의 가시설을 해체하고 벽체부 내부 거푸집 지지용 이동식 동바리(31)를 설치하고 상기 이동식 동바리의 잭서포트(34)와 일체화된 내부 거푸집을 설치하고 상기 헌치부(23)의 철근과 연결하여 상기 벽체부(24)의 철근을 배근하고 외부 거푸집을 설치하고 콘크리트를 타설하여 상기 벽체부(24)를 형성하는 4단계;Dismantling the provisional facilities around the location of the wall portion 24 of claim 1 and 2 and installing a movable club (31) for supporting the formwork inside the wall and integrated with the jack support 34 of the movable club Step 4 is installed to connect with the reinforcing bar of the haunch (23) to reinforce the reinforcement of the wall portion 24, install the external formwork and cast concrete to form the wall portion (24); 상기 벽체부(24)의 거푸집을 해체하고 상기 이동식 동바리(31)를 이동시키고 벽체부(24)를 방수하고 벽체 외각부를 되메우는 5단계;Disassembling the formwork of the wall part 24, moving the movable club 31, waterproofing the wall part 24, and backfilling the wall outer part; 제1항의 지붕부(25)가 설치될 위치 주변의 가시설을 해체하고 지붕부 지지용 이동식 동바리(32)를 설치하고 상기 이동식 동바리의 잭 서포트(34)와 일체화된 내부 거푸집을 설치하고 상기 벽체부(24)의 철근과 연결하여 상기 지붕부(25) 철근을 배근하고 외부 거푸집을 설치하고 콘크리트를 타설하여 상기 지붕부를 형성하는 6단계; 및,Dismantling the provisional facilities around the location of the roof portion 25 of claim 1, install a movable club 32 for supporting the roof, and install an internal formwork integrated with the jack support 34 of the movable club. Step 6 is connected to the reinforcing bar of the roof (25) to reinforce the reinforcing bar, install the external formwork and cast the concrete to form the roof; And, 상기 지붕부(25)의 거푸집을 해체하고 방수하고 되메우기를 하는 7단계;7 steps of dismantling the formwork of the roof portion 25, waterproofing and backfilling; 를 포함하고, 상기 각 단계는 시공 구간별로 연속하여 행해짐을 특징으로 하는 개착식으로 시공되는 지하철 및 공동구의 아치형 구조(21) 시공방법.Including, wherein each step is a construction of the arched structure of the subway and the public sphere to be constructed in a detachable manner, characterized in that is carried out successively for each construction section. 제3항에서, 상기 4단계의 벽체부 내부 거푸집 지지용 이동식 동바리(31)는 다리부의 단부에 바퀴(35)가 달려있고 상기 벽체부(24)와 동일한 높이이고, 로프(42`)로 들어 올려 고정시켰다가 콘크리트 타설시 상기 로프(42`)를 내린 후 잭(15`)으로 조여서 고정하는 하단 지지대(36)가 설치되어 있는 타워 동바리(33); 와 상기 타워 동바리(33)와 일방 단부를 용접등으로 접합시킨 다수개의 잭 서포트(34);를 포함하고, 상기 6단계의 지붕부 내부 거푸집 지지용 이동식 동바리(32)는 다리부의 단부에 바퀴(35)가 달려있고 상기 지붕부(25)에 설치되는 내부 거푸집을 지지할 수 있는 높이의 타워 동바리(33`); 와 상기 타워 동바리(33`)와 일방 단부를 용접등으로 접합시킨 다수개의 잭 서포트(34);를 포함하는 것을 특징으로 하는 개착식으로 시공되는 지하철 및 공동구의 아치형 구조(21) 시공방법.4. The movable club 31 for supporting the formwork inside the wall part of the fourth step has a wheel 35 at the end of the leg and is flush with the wall part 24, and is lifted by a rope 42 '. A tower club (33) having a lower support (36) for fixing by lifting and fixing and then tightening with a jack (15`) after lowering the rope (42`) when concrete is poured; And a plurality of jack supports 34 in which one end is joined to the tower club 33 by welding or the like, and the movable club 32 for supporting formwork in the roof part of the sixth step includes a wheel ( A tower club 33 'having a height of 35 to which it can support an internal formwork installed in the roof part 25; And a plurality of jack supports (34) for joining the tower portion (33`) and one end thereof by welding or the like; and an arch structure (21) for constructing a subway and a public sphere. 제3항에서, 상기 4단계의 벽체부 외부 거푸집은 벽체부(24) 바로 위의 수평버팀보(13) 하부 레일(41)에 매달린 로프(42)와 연결되어 이동시킬 수 있는 일체형이동식 거푸집이거나 인력(人力)으로 이동시키는 낱개(piece)형 거푸집이고, 상기 6단계의 지붕부 외부 거푸집은 지붕부(25) 바로 위의 수평버팀보(13) 하부 레일(41)에 매달린 로프(42)와 연결되어 이동시킬 수 있는 거푸집이며 거푸집 높이의 1/3, 2/3 지점 및 천단부에 콘크리트 타설 구멍(43)을 상기 구조물의 종방향으로 일정하게 설치하고 상기 천단부의 구멍(43)은 위쪽으로 돌출되게 테두리 처리가 된 것을 특징으로 하는 개착식으로 시공되는 지하철 및 공동구의 아치형 구조(21) 시공방법.The wall formwork of the fourth step is an integrally movable formwork or attraction that is connected to the rope 42 suspended on the lower rail 41 of the horizontal support 13 just above the wall 24. It is a piece-shaped formwork to move in (人力), the outer formwork of the roof of the six stages is connected to the rope 42 suspended on the lower rail 41 of the horizontal brace 13 directly above the roof portion 25 It is a movable formwork, and the concrete placing hole 43 is uniformly installed in the longitudinal direction of the structure at 1/3, 2/3 point and the top end of the formwork height, and the hole 43 of the top end is projected upward. Construction method of the arched structure of the subway and the public sphere that is constructed as a detachable, characterized in that the edge treatment.
KR10-2000-0044648A 2000-08-01 2000-08-01 Construction method of arch structure of subway or common duct in excavating process KR100390369B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2000-0044648A KR100390369B1 (en) 2000-08-01 2000-08-01 Construction method of arch structure of subway or common duct in excavating process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2000-0044648A KR100390369B1 (en) 2000-08-01 2000-08-01 Construction method of arch structure of subway or common duct in excavating process

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020000022061U Division KR200208830Y1 (en) 2000-08-02 2000-08-02 Arch structure of subway or common duct in excavating process of constructing

Publications (2)

Publication Number Publication Date
KR20020011270A true KR20020011270A (en) 2002-02-08
KR100390369B1 KR100390369B1 (en) 2003-07-07

Family

ID=19681295

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2000-0044648A KR100390369B1 (en) 2000-08-01 2000-08-01 Construction method of arch structure of subway or common duct in excavating process

Country Status (1)

Country Link
KR (1) KR100390369B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101725149B (en) * 2009-12-15 2011-01-26 中铁二局股份有限公司 Construction method of long open-cut tunnel
KR101640449B1 (en) * 2015-12-21 2016-07-18 우경기술주식회사 Construction method for open cutting in tunnel portal area
CN106120855A (en) * 2016-08-23 2016-11-16 青岛城建集团有限公司 A kind of subway open-cut station arch is without rod structure and construction thereof
KR101687308B1 (en) * 2015-10-27 2016-12-26 주식회사 한라 arch tunnel construction method using divided type lining form
CN113236296A (en) * 2021-04-25 2021-08-10 中铁二局第二工程有限公司 Arch pier body preservation method for subway station arch cover construction

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101437842B1 (en) * 2012-07-10 2014-09-04 한국철도기술연구원 Low depth tunnel construction method using variable mould system
KR101455202B1 (en) 2013-07-23 2014-10-28 주식회사 인터컨스텍 Construction method of an underground structure using lower member installed temporary system
CN111322089A (en) * 2020-02-28 2020-06-23 西南交通大学 Vault prefabricated assembled tunnel and construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR830000986U (en) * 1982-02-09 1983-09-22 Weon Mo Park Cigarette case for sea-bathing
JPH0745799B2 (en) * 1990-02-07 1995-05-17 日本サミコン株式会社 Method and apparatus for installing precast plate for tunnel
KR100200333B1 (en) * 1995-03-23 1999-06-15 윤기철 Form for tunnel
KR19980081945A (en) * 1998-08-06 1998-11-25 정희정 Expandable formwork for tunnel construction.
JP2000204888A (en) * 1999-01-12 2000-07-25 Ishikawajima Constr Materials Co Ltd Pit mouth tunnel and its construction method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101725149B (en) * 2009-12-15 2011-01-26 中铁二局股份有限公司 Construction method of long open-cut tunnel
KR101687308B1 (en) * 2015-10-27 2016-12-26 주식회사 한라 arch tunnel construction method using divided type lining form
KR101640449B1 (en) * 2015-12-21 2016-07-18 우경기술주식회사 Construction method for open cutting in tunnel portal area
CN106120855A (en) * 2016-08-23 2016-11-16 青岛城建集团有限公司 A kind of subway open-cut station arch is without rod structure and construction thereof
CN113236296A (en) * 2021-04-25 2021-08-10 中铁二局第二工程有限公司 Arch pier body preservation method for subway station arch cover construction
CN113236296B (en) * 2021-04-25 2023-08-18 中铁二局第二工程有限公司 Arch leg rock mass preservation method for subway station arch cover method construction

Also Published As

Publication number Publication date
KR100390369B1 (en) 2003-07-07

Similar Documents

Publication Publication Date Title
KR101630235B1 (en) Precast truss wall structure and construction method of underground structure using thereof
JP3644605B2 (en) Reverse driving method of underground structure under road surface.
JP2002256573A (en) Foundation for existing foundation reinforcing steel tower and construction method for it
KR20090094971A (en) Under ground top-down method
CN105715068A (en) Underpinning and reinforcing structure for seismic isolation bearing of existing brick-concrete structure and construction method for underpinning and reinforcing structure
KR100775767B1 (en) Top-down method using the vertical steel bar for the src column
KR100390369B1 (en) Construction method of arch structure of subway or common duct in excavating process
KR20060096706A (en) Deck suspension top-down method of sub-structure
CN210288419U (en) Reverse column diagonal bracing reinforcing system for large-span reverse foundation pit
KR20100109654A (en) Prestressed concrete girder with plural steel wires disposed at shear surface of tension port, manufacturing method thereof, and assembling bridge construction method using the same
KR200208830Y1 (en) Arch structure of subway or common duct in excavating process of constructing
KR100500143B1 (en) Constructing method for hollow section extension of pier to ensure water flow section and struction thereof
RU2123091C1 (en) Foundation for metal column, method of foundation construction and alignment
CN213571600U (en) Bridge underpins bearing structure
KR200390421Y1 (en) Top-down substructure by deck suspension
JP3644606B2 (en) Installation method of formwork support in reverse placement method
KR20210119935A (en) Underground structure using strut and method construturing the same
KR200219236Y1 (en) A mold assembly for reinforced concrete girders execution
JP3208100U (en) Scaffolding device for construction of underground structures
AU2016102393A4 (en) A Method of constructing a column, a tunnel, and a tunnel made from the method
KR200263281Y1 (en) Apparatus for reinforcing a construction by enlarging its&#39; size
KR20040051182A (en) Temporary soil sheathing using prestress and pile thereof
KR20030006681A (en) Apparatus and method for reinforcing a construction by enlarging its&#39; size
CN220550564U (en) Assembled prestressing force foundation ditch backplate
KR20010019079A (en) Precast steel Plate &amp;Concrete Pile Structure of Semi Down Wall Construction System

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130516

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20140513

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20150528

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20160520

Year of fee payment: 14

FPAY Annual fee payment

Payment date: 20170519

Year of fee payment: 15

FPAY Annual fee payment

Payment date: 20180518

Year of fee payment: 16

FPAY Annual fee payment

Payment date: 20190522

Year of fee payment: 17