KR20010019079A - Precast steel Plate &Concrete Pile Structure of Semi Down Wall Construction System - Google Patents
Precast steel Plate &Concrete Pile Structure of Semi Down Wall Construction System Download PDFInfo
- Publication number
- KR20010019079A KR20010019079A KR1019990035297A KR19990035297A KR20010019079A KR 20010019079 A KR20010019079 A KR 20010019079A KR 1019990035297 A KR1019990035297 A KR 1019990035297A KR 19990035297 A KR19990035297 A KR 19990035297A KR 20010019079 A KR20010019079 A KR 20010019079A
- Authority
- KR
- South Korea
- Prior art keywords
- plate
- retaining wall
- steel
- pile
- steel pipe
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/28—Prefabricated piles made of steel or other metals
- E02D5/285—Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0007—Production methods using a mold
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
본 발명은 가설 흙막이 토류벽 구축과 단계별 굴토 공사와 역타설 구조물의 동시에 축조할 때 주변 지반의 침하현상을 억제하기 위한 간이 역타설 옹벽 축조용 프리케스트 강말뚝 및 이를 이용한 옹벽구축공법에 관한 것이다.The present invention relates to a precast steel pile for the construction of a simple reverse casting retaining wall for suppressing the settlement of the surrounding ground when constructing a temporary soil wall and constructing step-by-step earthwork and reversal structure at the same time, and a retaining wall construction method using the same.
도심 건물에 근접한 현장에서의 굴착공사로 인해 발생하는 주변지반과 구조물 침하에 따른 공사관련 민원의 해소를 위한 역타설 공사는 통상 지중 연속벽을 흙막이 옹벽으로 활용하는데, 이는 암반층이 조기에 형성된 지반에서는 부적합하다.In the case of reverse casting for resolving civil complaints related to the ground caused by the excavation work on the site near the urban building and the settlement of the structure, the underground continuous wall is usually used as the retaining wall. Inadequate
이 점을 고려하여 가설 토류벽으로 역타설 구축하는 선행기술이 본인에 의한 특허 제115877호의 가설 흙막이 벽체를 영구 벽체용으로 시공하는 장치 및 시공 방법의 경제적인 천공 단면에 맞춰 선정되는 합성 엄지말뚝은 소요 단면 계수, 또는 허용응력이 작기 때문에 토류벽에 작용하는 수평력이 크게 증가되는 근린 생활층과 기계실 같은 지하층의 층간 높이가 높은 경우에는 엄지말뚝의 간격을 좁혀 시공하거나 영구지지 빔/슬래브 역타설 구조물 이외의 별도의 가설 버팀(지지)물을 추가로 설치하여 외부 역타설 옹벽을 굴착 단계별로 끊어서 치는 방법으로 축조하지만 공기가 지연되어 공가원가의 상승요인이 되어 왔다.Considering this point, the prior art for reversing the construction of temporary earthwalls is based on the economical perforated cross section of the device and construction method for constructing temporary wall of temporary wall of Patent No. 115877 for permanent wall. If the height of the interlaminar floors of neighboring living floors and machinery rooms where the horizontal force acting on the earth wall is greatly increased due to the small cross-sectional coefficients or small allowable stresses is high, the gap between the thumb piles should be narrowed or other than the permanent support beam / slab reverse casting structure. The construction of additional backing braces by breaking additional external retaining retaining walls by cutting them at each stage of excavation, but the delay of air has been a factor in the increase of cost.
또, 가설 흙막이 토류벽을 이용하여 굴착 단계별로 토류벽을 지지하는 영구 콘크리트 구조의 역타설지지 빔/슬래브를 구축 한 후에 기초 층부터 순타 외부옹벽을 단계별로 구분 시공하는, 통상의 역타설 빔/슬래브를 선시공한 후 외부 옹벽을 후시공하고, 선시공 빔/슬래브에 일체화된 옹벽의 수직 철근의 위 아래 이음길이를 고려하여 미리 절단된 옹벽의 수직 이형철근을 빔/슬래브의 이형철근을 배근할 때 함께 조립하여 콘크리트를 타설하는 것은 후속 시공한 외부옹벽이 층마다 두 곳의 철근이음이 발생하기 때문에 공사비가 증가한다.In addition, after constructing a permanent concrete supporting beam / slab of permanent concrete structure supporting the earth wall by excavation stage using the temporary earthquake earth wall, a normal reverse casting beam / slab that separates the outer retaining wall step by step from the foundation layer is constructed. After pre-installation, post-install the external retaining wall, and assemble the vertically deformed rebar of the pre-cut retaining wall together with the reinforcing bar / slab's deformed rebar in consideration of the up and down joint length of the vertical reinforcement of the retaining wall integrated with the pre-construction beam / slab. Placing concrete increases the cost of construction because the subsequent retaining walls generate two reinforcing bars per floor.
그리고 통상의 H-형강제 말뚝과 역타설지지용 빔 슬래브 구조물을 일체화하여 정착시키는 스터드 보울트의 수평 부착은 용접할 때의 높은 열을 받은 스터드 보울트가 순간적으로 녹아서 용접시 용해된 쇳물이 아래로 흘러내리는 접합 불량이 생기기 때문에 스터브 보울트의 수평 부착은 추가로 보강 용접해야되는 단점도 있다.In addition, the horizontal attachment of the stud bolts for fixing the H-shaped steel piles and the beam slab structure for back-pouring integrally is fixed. The stud bolts subjected to high heat during welding instantly melt, and the molten water flows down during welding. The horizontal attachment of the stub bolts has the disadvantage that additional reinforcement welding is required because of poor joining.
한편, 가설 토류벽을 이용하여 영구 콘크리트 구조의 역타설지지 빔/슬래브를 구축한 후 기초층부터 외부옹벽을 구분 시공하는 통상의 가설 토류벽용 역타설 시공 엄지말뚝은 지반 천공홀에 진동해머로 타입하더라도 고강도 잔유물(왕사) 위에 정착되기 때문에 역타설 하중의 재하로 인한 침하변형이 발생하여 역타설 빔/슬래브 구조물에 심각한 균열이 발생하기 십상이다.On the other hand, even if the construction of the reverse casting support beam / slab of the permanent concrete structure using the temporary earth wall, and then the external retaining wall to separate the foundation wall from the foundation layer, even if the thumb pile is a type of vibration hammer in the ground drilling hole Since it is settled on high-strength residues (wangs), settlement deformation is caused by loading of reverse casting loads, and serious cracking occurs in the reverse casting beam / slab structure.
또, 실용신안등록 제35446호에 있어서의 흙막이 토류판용 스페이서는 가변기능이 부족하여 엄지말뚝의 수직도가 불량한 경우 각기 다른 변형유격이 발생하여 효율성이 눈에 띌 정도로 저하되는 단점이 있다.In addition, the spacer for earthenware earth plate in the Utility Model Registration No. 35446 has a disadvantage in that the efficiency is noticeably lowered because different deformation gaps occur when the verticality of the thumb pile is poor due to the lack of the variable function.
본 발명은 가설 흙막이 토류벽 구축과 단계별 굴토 공사와 역타설 구조물의 동시에 축조할 때 주변 지반의 침하현상을 억제할 수 있는 강말뚝을 제공하려는 것이다.The present invention is to provide a steel pile that can suppress the settlement of the surrounding ground when the construction of the temporary earthen wall wall and the construction of the step-by-step excavation and reversal structure at the same time.
상기 목적을 달성하기 위해서는 첫째, 흙막이 토류벽에 작용하는 수평 응력에 충분한 대응력을 갖는 엄지말뚝은 설치 간격 또는 지지간격을 좁히지 않고 말뚝 단면을 축소하더라도 높이가 높은 외부옹벽 구조물의 안정된 구축, 둘째 엄지 말뚝용 지반 천공홀의 천공 잔류물이 부상하여 엄지말뚝의 정착을 도움으로써 침하가 배제되는 가설흙막이 토류벽의 기능과 함께 역타설 구조의 안정된 구축, 셋째 역타설용 말뚝으로 활용하는 외부옹벽과 지지 빔/슬래브의 수직 철근의 이음량을 통상의 가설 토류벽 역타설 시공에 비해 절반으로 줄이는 공기단축 및 원가 절감과, 넷째 엄지말뚝의 수직도 불량이 원인이 되어 구조물의 계획 단면을 과다하게 침범한 경우라도 설계에 준하는 구조물의 정밀한 축조, 다섯째 엄지말뚝이 역타설 옹벽 내부에 존치되는 구조로 철근 콘크리트 옹벽을 철골 콘크리트 옹벽으로의 구조개선, 여섯째 개착식 굴토공사의 통상의 엄지말뚝 규격에 준하는 스트리트용 엄지말뚝 또는 어스 앵커용 엄지말뚝으로 대체하면 엄지말뚝의 버팀지지의 통상적인 높이인 1.8∼2.5m를 적어도 4.5m 이상 늘려서 매 층마다 한 곳의 지지로써 구조물의 축조효율을 향상시킬 수 있는 엄지말뚝으로 더욱 경제적인 지하구조물을 안전하고도 신속하게 구축할 수 있어야 한다. 본 발명은 이를 구현한 것이다.In order to achieve the above object, first, the thumb pile having a sufficient coping force to the horizontal stress acting on the earth wall earth wall is stable construction of the high external retaining wall structure even if the pile section is reduced without narrowing the installation interval or support interval, second thumb pile The construction of the reinforcement structure and the stabilization of the reinforcing structure and the external retaining wall and supporting beams / slabs used as the pile for the reversal placement Even if the projected section of the structure is excessively violated due to the shortening of airtightness and cost, which reduces the joint volume of the vertical reinforcing bar by half compared with the normal temporary earth wall reversal construction, and the poor verticality of the thumb pile, Precise construction of the structure, with the fifth thumb pile retained inside the retaining wall When the reinforced concrete retaining wall is replaced with a steel thumb retaining structure, a street thumb pile or earth anchor thumb pile that conforms to the normal thumb pile standard of the sixth type of burial construction, 1.8, which is the normal height of the support of the thumb pile It should be possible to build more economically underground structures safely and quickly with thumb piles that can increase the construction efficiency of the structure with one support for each floor by increasing ˜2.5m to at least 4.5m. The present invention implements this.
도 1은 역타설 흙막이용 Pc-강 말뚝의 단면도1 is a reverse casting Pc for -Section of the river stakes
도 2는 도 1의 A-a 선 단면도2 is a cross-sectional view taken along the line A-a of FIG.
도 3은 도 1의 B-b 선 단면도3 is a cross-sectional view taken along the line B-b of FIG.
도 4는 도 1의 C-c 선 단면도4 is a cross-sectional view taken along the line C-c of FIG.
도 5는 강말뚝의 인장력 보강 단면도5 is a cross-sectional view of reinforcing the tensile strength of the steel pile
도 6은 강말뚝의 전단력 보강 단면도6 is a sectional view of reinforcing shear force of steel pile
도 7 내지 도 13은 상기 강말뚝을 이용하여 역타설 작업공정별 축조순서도7 to 13 is a construction sequence diagram of the reverse casting work process using the steel pile
<도면의 주요 부분에 대한 부호의 설명><Description of the code | symbol about the principal part of drawing>
1 : 강관 2 : 상부 정착판1: steel pipe 2: upper fixing plate
3 : 둘레 받침판 4 : 하부 정착판3: circumferential support plate 4: lower fixing plate
5 : 보울트 6 : 걸고리5: bolt 6: hook
7 : 이형 철근 8 : 케플러7: deformed bar 8: Kepler
9 : 그라우팅 주입관 10 : 콘크리트 투입구9: grouting injection pipe 10: concrete inlet
11 : 지반 천공홀 12 : 그라우팅11: ground drilling hole 12: grouting
13 : 역타설 빔/슬래브 14 : 외부 역타설 옹벽13: Reversal Beam / Slab 14: External Reversal Retaining Wall
15 : 가설 토류벽(판) 16 : 이음 보강판15: temporary earth wall (plate) 16: joint reinforcement plate
17 : 가변 간격제 18 : 스터드 볼트17: variable spacer 18: stud bolt
19 : 강말뚝 20 : 보강판19: steel pile 20: reinforcement plate
21 : 고강도 콘크리트 22 : 와이어 로우프21: high strength concrete 22: wire rope
23 : 가변형 매달기 빔/슬래브 거푸집틀23: variable hanging beam / slab formwork
24 : 순타 외부옹벽24: outer wall
도 1에서, 역타설 흙막이용 강말뚝(19)은-형 강관(1)을 소정의 사용길이에 적합하게 용접하여 이은 다음에 강관(1)과 동일한 단면상에서 서로 엇갈리게 작용하는 인장력과 압축력을 가장 경제적인 방법으로 보강하기 위하여 상기 강관(1)의 내부에서 인장력이 작용하는 부분에 국한시켜 보강판(20)을 덧붙여 보강하고, 전단력이 작용하는 부위는 스터드 보울트(18)로 상기 보강판(20)의 양단부를 보강한다.In Fig. 1, the steel pile 19 for backwashing mudstone is The inner part of the steel pipe (1) in order to reinforce in a most economical way the welded steel pipe (1) suitable for a predetermined length of use, and then reinforce the tensile and compressive forces that intersect on the same cross section as the steel pipe (1) Reinforced by adding a reinforcement plate 20 to the portion where the tensile force acts in, and the site where the shear force acts to reinforce both ends of the reinforcement plate 20 with a stud bolt 18.
또 다른 압축력이 작용하는 부분은 건너뛰어서 고강도 콘크리트(21)로 충진하여 지하 다층 구조와 동일한 방법으로 반복 보강하여 강말뚝(19)을 형성하기 위하여 소정의 상기 강관(1)을 소정의 사용길이에 적합하도록 연결할 때에는 먼저 맞대기 용접부위인 강관(1)의 단부를 V컷팅 맞대기 용접하고 연마하여 이음부를 중심으로 강관(1)의 이음부에 보강판(16)을 덧붙인 강말뚝(19)을 구성하기 위하여 강관(1) 상단의 양측 정착판(2)과 하부 정착판(4)을 용접, 정착시킨다.The portion of the compressive force is skipped and filled with high-strength concrete 21 and repeatedly reinforced in the same manner as the underground multi-layer structure to form the steel pile 19 at a predetermined use length. In order to make a proper connection, first, the V-cutting butt welds and polishes the end of the butt welded steel pipe 1 to form a steel pile 19 having a reinforcing plate 16 attached to the joint of the steel pipe 1 around the joint. Both fixing plates 2 and the lower fixing plate 4 on the upper end of the steel pipe 1 are welded and fixed.
도 2에서, 상기한 강말뚝(19)의 상부 정착판(2)의 외곽을 관통하는 역타설 옹벽용 수직 이형철근(7)을 매다는 용도로 활용하기 위하여 철근 이음용 케플러(8)를 부착한다.In FIG. 2, a kepler 8 for reinforcing bars is attached to be used for suspending vertical deformed reinforcing bars 7 for reverse pouring retaining walls that penetrate the outer fixing plate 2 of the steel pile 19. .
도 3에서, 상기 강관(1)의 내부에서 필요 부분을 보강판(20)으로 보강하기 위하여 걸고리(6)와 스터드 보울트(18)를 부착한 보강판(20)의 걸고리(6)에 와이어 로우프(22)에 걸어서 강관(1)의 내부로 끌어 들이고 설치할 지점에 맞춘 후에 강관(1)의 외부에서 보강판(20) 부위에 나사공을 천공하여 보울트(5)를 체결하고, 강관(1)의 내부에서 필요한 부분을 보강판(20)과 스터드 보울트(18)로 보강한다.In FIG. 3, a wire rope is attached to the hook 6 of the reinforcing plate 20 to which the hook 6 and the stud bolt 18 are attached to reinforce the necessary portion inside the steel pipe 1 with the reinforcing plate 20. (22) is hooked into the inside of the steel pipe (1) and aligned with the point to be installed, and then screwing the bolt (5) by drilling a screw hole in the reinforcement plate 20 portion from the outside of the steel pipe (1), the steel pipe (1) Reinforcement of the necessary portion inside the reinforcement plate 20 and the stud bolt 18.
또 다른 부분은 건너뛰는 형태로 강관(1)의 내부로 보강판(20)을 끌어들일 때 이용한 와이어 로우프(22)의 타단을 당기면 강판 걸고리(6)에서 벗겨지므로 와이어 로우프(22)를 재활용할 수 있다.Another part of the wire rope 22 can be recycled because the other end of the wire rope 22 used to pull the reinforcing plate 20 into the inside of the steel pipe 1 is peeled off from the steel plate hook 6. have.
도 4에서, 외부옹벽(14) 내측의 상기 강말뚝(19) 지지용 빔/슬래브(13)를 축조하기 위하여, 강말뚝(19)에 외부옹벽(14)의 수직 이형 철근(7)을 역타설 매달기용으로 하고 각관 둘레 받침판(3)과 케플러(8)로 매달아 받쳐 빔/슬래브(13) 콘크리트 치기와 단계별 굴토공사에 따라 차기 층 역타설 구조물 축조에 이용하므로써 강말뚝(19)에 지지 빔/슬래브(13)의 구조물 정착용 스터드 보울트(18)가 부실시공될 확율이 큰 수평부착을 피하고 역타설 구조물의 정착은 외부옹벽(14)의 이형철근(7)과 둘레 받침판(3) 및 케플러(8)를 이용하여 매달기 때문에 안전하고 또한 간편 신속하게 축조할 수가 있다.In FIG. 4, in order to construct the beam / slab 13 for supporting the steel pile 19 inside the outer retaining wall 14, the vertically shaped reinforcing bar 7 of the outer retaining wall 14 is reversed to the steel pile 19. Supporting beams on steel piles (19) by placing them on the pedestal (3) and the Kepler (8) for the purpose of pour-in, and for supporting the beam / slab (13) for the construction of the next layer reversal structure according to concrete striking and stepwise excavation. Avoiding horizontal attachment with a high probability that the stud bolts 18 for fixing the structure of the slab 13 will be misplaced, and fixing of the reversal structure can be carried out using the deformed reinforcing bar 7 of the outer retaining wall 14 and the circumferential plate 3 and Kepler. Since (8) is used for hanging, it is possible to construct safely and simply and quickly.
이 때, 둘레 받침판(3)은 굴착단계별로 외부옹벽(14,24)의 내측 두께변화를 수용하는 이형 철근(7)의 배근위치를 자유로이 행할 수 있는 둘레 받침판(3)으로 된 이중 정착구조이다.At this time, the circumferential support plate (3) is a double fixing structure consisting of a circumferential support plate (3) capable of freely performing the reinforcement position of the deformed reinforcing bar (7) to accommodate the change in the inner thickness of the outer retaining walls (14, 24) for each excavation step. .
도 6에서, 보강판(20)으로 보강된 상기 강관(1)을 180°회전시켜 상대편 내측에 엇갈리게 인장력이 작용하는 부분에 국한시키고 동일 방법으로 보강판(20)에 스터드 보울트(18)를 부착하여 전단응력을 보강, 고강도 콘크리트(21)를 충진하므로 강말뚝(19)은 단면계수와 단면 2차 모우멘트가 현저히 증가하여 휨과 전단에 대한 내력이 월등하며, 이 강말뚝(19)의 상/하부 정착판(2/4)을 관통하는 하부 그라우팅 주입관(9)을 설치하고 지반 천공홀(11)에 건입하여 천공 잔류물 위에 강말뚝(19)이 정착될 때에는 침하변형이 우려되지만 하부 그라우팅 주입관(9)으로 압축공기를 주입하여 천공 잔류물을 부상시키면서 지반 천공홀(11)의 하단부에 그라우팅을 충진하면 강말뚝(19)은 안정된 정착상태로 유지되고 또 다른 내부 투입구(10)로 강관(1)의 내부를 고강도 콘크리트로 충진하여 양생한다.In FIG. 6, the steel pipe 1 reinforced by the reinforcing plate 20 is rotated 180 ° to be limited to a portion in which the tensile force is applied to the inside of the opposite side, and the stud bolt 18 is attached to the reinforcing plate 20 in the same manner. As the steel pile 19 is remarkably increased in section modulus and cross-sectional secondary moment, the strength of bending and shear is superior, and the strength of the steel pile 19 is increased. When the lower grouting injection pipe 9 penetrates the lower fixing plate 2/4 and is inserted into the ground drilling hole 11 and the steel pile 19 is fixed on the drilling residue, Injecting compressed air into the grouting injection tube 9 while filling the grouting in the lower end of the ground drilling hole 11 while floating the drilling residues, the steel pile 19 is maintained in a stable fixing state and another internal inlet 10 The inside of the furnace steel pipe (1) is made of high strength concrete Fill and cure.
도 7 내지 도 13는 상기 강말뚝(19)을 이용하여 건축물을 축조하는 작업을 단계별로 나타낸 것으로서, 그림의 좌측은 외부 역타설 옹벽(14)이고 우측은 순타 외부옹벽(14)을 구축하는 공정도이다.7 to 13 illustrate the step-by-step of the construction of the building using the steel pile 19, the left side of the figure is a process diagram for constructing the external reinforcing retaining wall 14 and the right side of the smooth outer retaining wall 14. to be.
먼저, 지반 천공홀(11)에 강말뚝(19)을 건입하고, 이 강말뚝(19)을 관통한 하부 그라우팅 주입관(9)으로 압축공기를 주입하여 침전된 천공 잔류물을 부상시키면서 그라우팅(12)을 충진하여 지반 천공홀(11)의 하단에 괸 고강도 천공 잔류물과 시멘트 밀크가 압축공기에 의해 교반 정착구근을 형성하게 된다.First, the steel pile 19 is inserted into the ground drilling hole 11, and compressed air is injected into the lower grouting injection tube 9 penetrating the steel pile 19, while the precipitated puncture residue is raised to grout ( 12) and the high-strength drilling residue and cement milk at the bottom of the ground drilling hole 11 to form a stirring fixing bulb by the compressed air.
강말뚝(19)의 내부에도 콘크리트를 충진하여 양생시킨 후에 지상 1층 빔/슬래브를 축조하기 위한 지반을 굴착 정리하여 버림 콘크리트를 타설하고 먹 선긋기를 한 후 가변형 매달기 빔/슬래브 거푸집 틀(23)을 조립하여 지상 1층 빔/슬래브 콘크리트를 타설하고 보양하여 설계강도가 발현된 후 지하 1층 굴토작업과 함께, 강말뚝(19)의 배면에 가설 흙막이 토류벽을 구축하는 굴토공사용 횡널 토류판을 설치하여 가설 흙막이 토류벽(15)과 차후 외부옹벽(14) 구축용 거푸집으로 공용하기 위하여 강말뚝(19)의 배면과 외부옹벽(14) 거푸집 공용 토류판 사이에 가변 간격제(17)로 변화유격을 형성한다. 가변 간격제(17)는 몸통과 외관으로 구분되며, 외관은 몸통을 감싸 전,후진하는 스크류로 수직도가 불량한 엄지말뚝의 배면에서 변화유격을 확보하여 구조물을 설계와 동일한 형상으로 축조한다.After filling and curing concrete in the steel pile 19, excavating and arranging the ground for building the first floor beam / slab above the ground, casting concrete and drawing the cast line, and then hanging the hanging beam / slab formwork (23). ) Assemble and reinforce the ground-floor beam / slab concrete to build and reinforce the design strength, and then develop the ground strength. Variable gap (17) is provided between the back of the steel pile (19) and the external retaining wall (14) formwork common earth plate in order to install the temporary earthenware earth wall (15) and the formwork for building the external retaining wall (14). Form. The variable spacer 17 is divided into a body and an exterior, and the exterior is constructed with the same shape as the design by securing a change clearance at the back of the thumb pile having a poor verticality with a screw that moves forward and backwards around the body.
강말뚝(19)의 배면과 토류판 사이에 가변 간격제(17)로 변화유격을 형성한 다음 가변 간격제(17)들 사이로 외부옹벽(14)의 외부측 수평 철근을 배근하고 콘크리트 치기한다. 외부옹벽(14)의 철근 피복을 형성하는 토류판 가변 간격제(17)에 의하여 강말뚝(19)의 철골이 외부옹벽(14)의 내부에 설치되므로 철골 구조에 의해 개선된 외부옹벽(14)의 지지는 가변형 매달기 빔/슬래브 거푸집틀(23)을 지하 1층 빔/슬래브(13) 위치로 내려서 지상 1층 슬래브(13)에 정착하고 지하 1층 빔/슬래브(13)의 콘크리트를 타설하여 보양하면서, 가변형 매달기 빔/슬래브 거푸집틀(23) 아래쪽에서는 굴토 작업대기 없이 연속 굴착과 함께 외부 역타설 옹벽(14)을 함께 축조할 수도 있고 또는 차후에 별도로 기초층부터 순차적으로 순타 외부옹벽(24)을 구축할 수 있다. 굴착에 따른 연약 지반의 분포상태와 지하수위의 변화 및 주변 민원발생 여건에 따라서 선택적으로 적용하는 것이 원칙이고, 지하 1층은 연약지반에 위치할 수도 있으므로 가설 토류벽(15)의 지반 보강 차수 그라우팅 설명과 도면 표기는 생략한다.A variable clearance is formed by the variable spacer 17 between the rear surface of the steel pile 19 and the earth plate, and then the horizontal horizontal reinforcing bar of the outer retaining wall 14 is disposed between the variable spacers 17 and concrete-pumped. Since the steel frame 19 is installed inside the outer retaining wall 14 by the earth plate variable spacer 17 forming the reinforcing bar of the outer retaining wall 14, the outer retaining wall 14 is improved by the steel structure. The support is lowered to the first floor slab (13) above the ground by placing the variable hanging beam / slab formwork (23) to the location of the first floor beam / slab (13) and placing the concrete of the first floor beam / slab (13). While retaining, the variable suspended beam / slab formwork 23 may be constructed together with the external reversal retaining wall 14 together with continuous excavation without a pit excavation stand, or subsequently in turn from the base layer separately. ) Can be built. The principle is to apply selectively according to the distribution status of the soft ground, excavation of groundwater level and surrounding civil complaints due to the excavation, and the first basement may be located in the soft ground, so the ground reinforcement order grouting of the temporary earth wall 15 is explained. And drawing notation are omitted.
강말뚝(19)의 배면에 가설 흙막이 토류벽(15)과 외부옹벽(14) 거푸집 공용 횡널 토류판을 설치하면서 가변형 매달기 빔/슬래브 거푸집 틀(23) 아래에서는 굴착 중장비의 작업대기없이 연속적으로 지하 2층에 대한 동시 굴착작업을 실시한다.Under the variable hanging beam / slab formwork (23), while installing the temporary earthenware earth wall (15) and the external retaining wall (14) formwork on the back of the river pile (19), the basement 2 is continuously operated without waiting for excavation heavy equipment. Simultaneous excavation of the layers is carried out.
가변형 매달기 빔/슬래브 거푸집 틀(23)을 지하 2층으로 내려서 지하 1층에 정착하고 강말뚝(19)의 지하 2층 역타설지지 빔/슬래브(13)를 구축한 후 같은 요령으로 지하 3층에 대한 굴토작업과 가설 흙막이 토류벽(15)의 설치 및 지하 3층용 역타설 빔/슬래브(13) 구축하고, 굴착면을 정리한 후 기초 바닥 콘크리트 치기한 다음에 가변형 매달기 빔/슬래브 거푸집틀(23)을 해체하여 지상으로 반출한다.The variable hanging beam / slab formwork (23) is lowered to the basement 2 floor and settled in the basement 1 floor, and the basement 2 floor reverse casting support beam / slab (13) of the river pile (19) is constructed. Construction and installation of temporary soil wall (15) and reversal beam / slab (13) for the basement 3rd floor, after digging the excavation surface, striking the foundation floor concrete, and then the variable hanging beam / slab formwork Dismantle (23) and take it out to the ground.
이상 설명한 바와 같은 본 발명은 가설 흙막이 토류벽으로 철골조 외부 역타설 옹벽을 구축하는데 효과적인 Pc-강말뚝으로 토압이 크게 작용하면서도 층간 높이가 높은 지하층에 역타설 구조물을 시공할 때 가설 토류벽에 작용하는 수평력에 충분한 대응력을 갖도록-형 강관의 내부 필요부분을 강판과 스터드-보울트, 고강도 콘크리트로 보강하여 단면계수, 단면 2차 모우멘트를 증가시킴으로서 휨과 전단에 대한 내력이 대폭 증가돼 역타설 흙막이 엄지말뚝의 설치간격 또는 지지간격을 넓히거나 엄지말뚝의 단면적을 효과적으로 축소시킬 수가 있다.As described above, the present invention is effective for constructing a steel frame external retrocast retaining wall as a temporary earthenware earth wall. -When the reverse pile is installed in the basement with high interlayer height while the earth pressure acts as a river pile, it has sufficient response to the horizontal force acting on the temporary earth wall. -The internal necessary part of the type steel pipe is reinforced with steel plate, stud-bolt, and high-strength concrete to increase the section modulus and cross-sectional secondary moment, which greatly increases the strength of bending and shear, so that the installation spacing or support of the backstacking pile It can increase the spacing or reduce the cross section of the thumb pile effectively.
또, 상기 강말뚝을 지반 천공홀에 건입하여 천공 역타설 흙막이용-강관과 상기 강말뚝의 외부 그라우팅 주입관으로 압축공기를 주입하여 천공 잔류물을 부상시키면서 시멘트 그라우팅 밀크를 충진하여 지반 천공홀의 하단부 구근을 형성함으로서 강말뚝을 튼튼하게 정착시켜 시종 안정감있게 유지시킬 수가 있다.In addition, the river pile is built into the ground drilling hole for drilling reverse casting -Compressed air is injected into the steel pipe and the external grouting injection pipe of the steel pile to fill the cement grouting milk while floating the perforated residue to form the bottom bulb of the ground perforated hole so that the steel pile can be firmly settled and kept stable all the time. have.
또한 상기한 강말뚝의 배면과 외부옹벽 거푸집 공용 토류판과 유격형성용 가변 간격제의 변화유격을 형성하므로써 엄지말뚝의 수직도가 불량한 경우일지라도 토류판의 수직도 유지가 용이하므로 설계대로 구조물을 축조하기가 한결 용이하다.In addition, it is easy to maintain the verticality of the earth plate even if the verticality of the thumb pile is poor by forming a variable play between the back surface of the steel pile, the common earth plate formwork and the variable spacer for forming the gap, so that it is easy to construct the structure as designed. It is easy.
특히 토압이 세고 역타설 층고가 높은 외부옹벽과 빔/슬래브 구조물을 구축함에 있어서, 상기한 강말뚝의 상부 정착판에서 옹벽의 수직 이형 철근을 역타설용 매달기 철근으로 활용하고 받침판과 케플러로 매달아 받쳐서 콘크리트 치기함으로서 강말뚝에 지지 빔/슬래브 구조물 정착용 수평부착형 스터드 보울트의 부실시공을 우려하지 않고도 역타설 구조물을 확실히 매달아 정착시켜서 안전하고 간편하게 축조하기 위하여 상기 강말뚝의 상부 정착판에서 옹벽의 수직 이형 철근을 역타설용 매달기 철근으로 활용하여 받침판과 케플러로 매달아 받치고 빔/슬래브 구조물을 축조한 후 외부옹벽을 기초층부터 별도로 시공하거나 또는 굴착단계별로 역타설 시공하더라도 외부옹벽의 수직 철근이음 개소를 절반으로 줄일 수 있다.In particular, when constructing external retaining wall and beam / slab structure with high earth pressure and high reversal floor height, the vertical reinforcing bar of the retaining wall is used as the reinforcing reinforcing reinforcing bar in the upper fixing plate of the steel pile and hung with the supporting plate and Kepler. Supporting the retaining wall in the upper fixing plate of the steel pile in order to securely and easily build the suspended casting structure without worries about the secondary construction of the horizontally mounted stud bolt for fixing the support beam / slab structure to the steel pile by supporting the concrete Vertical reinforcing bars are used as vertical reinforcing bars to be suspended by supporting plates and Kepler, and the beam / slab structure is constructed. We can cut point in half.
그리고 상기한 강말뚝과 토류판 가변 간격제, 매달기 철근, 받침판, 케플러 가변형 매달기 빔/슬래브 거푸집틀 등을 효과적으로 이용할 수 있기에 가설 흙막이 토류벽의 강말뚝이 역타설 옹벽 내부에 존치시킬 수 있고, 이에 따라 철근 콘크리트 옹벽이 철골 콘크리트 옹벽으로의 구조개선이 이뤄진다.And since the river pile and the earth plate variable spacer, the hanging reinforcement, the backing plate, the Kepler variable hanging beam / slab formwork can be effectively used, the steel pile of the temporary earthquake earth wall can be maintained inside the inverted retaining wall. Reinforced concrete retaining wall is structural improvement to steel concrete retaining wall.
게다가 강말뚝과 토류판 가변간격제를 이용하므로 강말뚝의 수직도가 불량하더라도 역타설 옹벽의 수직도를 완벽하게 형성하는 토류판 가변 간격제의 가변 기능이 있으므로 강말뚝의 수직도와 무관하게 가설 토류벽의 수직도를 형성하여 역타설 옹벽의 완벽한 수직도를 이룰 수가 있다.In addition, since the steel pile and the earth plate variable spacing are used, there is a variable function of the earth plate variable spacer which perfectly forms the verticality of the reverse casting retaining wall even if the verticality of the steel pile is poor. A can be formed to achieve a perfect vertical angle of the backpouring retaining wall.
또, 가변형 매달기 빔/슬래브 거푸집틀 아래에서 굴토 작업대기시간없이 연속적으로 굴착작업을 수행할 수 있으므로 역타설 구조물을 안전하고도 신속하게 구축할 수 있으며, 개착식 굴토공사의 통상 규격인 스트러트용 엄지말뚝 또는 어스 앵커용 강말뚝으로 대체할 경우에는 통상의 버팀 지지 높이인 1.8∼2.5m를 최소한 4.5m 이상 늘어나 매층마다 한 곳의 지지로 가설 토류벽의 효율성을 올릴 수 있는 가설 토류벽용 엄지말뚝으로 사용하는데 조금도 부족함이 없으므로 굴착공사로 인한 주변침하를 억제하는데 매우 효과적이다.In addition, the excavation work can be carried out continuously under the variable hanging beam / slab formwork without the excavation waiting time, so that the inverse casting structure can be constructed safely and quickly. When replacing with a pile of thumb or a steel anchor, a temporary pile wall thumb pile that can increase the efficiency of the temporary earth wall with one support for each floor is increased by at least 4.5m, which is a normal support height of 1.8 to 2.5m. There is no shortage of use, so it is very effective in suppressing the surrounding settlement caused by excavation work.
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1019990035297A KR20010019079A (en) | 1999-08-24 | 1999-08-24 | Precast steel Plate &Concrete Pile Structure of Semi Down Wall Construction System |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1019990035297A KR20010019079A (en) | 1999-08-24 | 1999-08-24 | Precast steel Plate &Concrete Pile Structure of Semi Down Wall Construction System |
Publications (1)
Publication Number | Publication Date |
---|---|
KR20010019079A true KR20010019079A (en) | 2001-03-15 |
Family
ID=19608556
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1019990035297A KR20010019079A (en) | 1999-08-24 | 1999-08-24 | Precast steel Plate &Concrete Pile Structure of Semi Down Wall Construction System |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR20010019079A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561402A (en) * | 2010-12-22 | 2012-07-11 | 中国二十冶集团有限公司 | Treatment method for construction joint between top plate and wall of individual underground civil air defense project constructed by covered top-down excavation method |
CN110258640A (en) * | 2019-07-11 | 2019-09-20 | 吉林大学 | A kind of construction method of the overlapping wall system of covered back-digging |
CN115434363A (en) * | 2022-09-30 | 2022-12-06 | 武汉誉城千里建工有限公司 | Retaining wall construction method suitable for repeated excavation and backfilling working condition |
CN115478548A (en) * | 2022-11-04 | 2022-12-16 | 中铁九局集团第一建设有限公司 | Expansive soil cutting slope expansion-reduction earthquake-resistant disaster-prevention combined retaining structure and construction method |
-
1999
- 1999-08-24 KR KR1019990035297A patent/KR20010019079A/en not_active Application Discontinuation
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561402A (en) * | 2010-12-22 | 2012-07-11 | 中国二十冶集团有限公司 | Treatment method for construction joint between top plate and wall of individual underground civil air defense project constructed by covered top-down excavation method |
CN102561402B (en) * | 2010-12-22 | 2014-06-25 | 中国二十冶集团有限公司 | Treatment method for construction joint between top plate and wall of individual underground civil air defense project constructed by covered top-down excavation method |
CN110258640A (en) * | 2019-07-11 | 2019-09-20 | 吉林大学 | A kind of construction method of the overlapping wall system of covered back-digging |
CN110258640B (en) * | 2019-07-11 | 2020-07-03 | 吉林大学 | Construction method of superposed wall system for cover-excavation top-down construction |
CN115434363A (en) * | 2022-09-30 | 2022-12-06 | 武汉誉城千里建工有限公司 | Retaining wall construction method suitable for repeated excavation and backfilling working condition |
CN115434363B (en) * | 2022-09-30 | 2023-06-02 | 武汉誉城千里建工有限公司 | Retaining wall construction method suitable for repeated excavation backfill working condition |
CN115478548A (en) * | 2022-11-04 | 2022-12-16 | 中铁九局集团第一建设有限公司 | Expansive soil cutting slope expansion-reduction earthquake-resistant disaster-prevention combined retaining structure and construction method |
CN115478548B (en) * | 2022-11-04 | 2024-05-10 | 中铁九局集团第一建设有限公司 | Expansion soil cutting side slope expansion-reducing anti-seismic disaster-preventing combined retaining structure and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105735325B (en) | A kind of intensive permanent support assembled basement structure system and construction method | |
KR100951097B1 (en) | Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket | |
CN109356173A (en) | A kind of pin-connected panel anchor bolt frame girder construction and its construction method | |
CN106759439B (en) | Tower crane foundation for foundation pit and construction method thereof | |
KR20090094971A (en) | Under ground top-down method | |
CN108612110A (en) | A kind of Deep Foundation Pit of Metro Stations combined type construction method for supporting | |
CN112177012A (en) | Precast concrete non-primary support system with lattice columns for foundation pit engineering and construction method | |
KR102286225B1 (en) | Method for constructing underground structure busing PC integrating method without support | |
KR101631447B1 (en) | Top-Down method of underground structure using the CFT and the Composite Beam | |
CN212801564U (en) | Foundation ditch steel sheet pile supporting construction | |
CN113417300A (en) | Slope support system and construction method thereof | |
CN113697640A (en) | Finished hoistway of integrally assembled elevator added in existing multi-story building and construction method | |
KR20110052360A (en) | Downward construction method of underground structure that enables continuous basement wall using non-wale and diaphragm action of concrete slab | |
KR101210368B1 (en) | Uniting Method of Temporary earth wall with basement exterior Wall using Couplers and Bolts. | |
CN117166510A (en) | Deep large-diameter open caisson construction method | |
KR100390369B1 (en) | Construction method of arch structure of subway or common duct in excavating process | |
CN214940212U (en) | Deep foundation pit supporting device | |
KR20010019079A (en) | Precast steel Plate &Concrete Pile Structure of Semi Down Wall Construction System | |
KR100462236B1 (en) | panel for external underground wall of building, structure and construction method using the same | |
KR200263526Y1 (en) | Hanging semi down up system | |
CN113585336A (en) | Quick construction method of sinking type concrete mixing station in soft foundation environment | |
KR200219236Y1 (en) | A mold assembly for reinforced concrete girders execution | |
KR100592397B1 (en) | storey spacing support ssoldier pile soil retaining wall | |
KR960016755B1 (en) | Working method and working apparatus of underground structure | |
CN220726302U (en) | Shallow bias tunnel hole entering structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E601 | Decision to refuse application | ||
E601 | Decision to refuse application |