JP2000204888A - Pit mouth tunnel and its construction method - Google Patents

Pit mouth tunnel and its construction method

Info

Publication number
JP2000204888A
JP2000204888A JP11005816A JP581699A JP2000204888A JP 2000204888 A JP2000204888 A JP 2000204888A JP 11005816 A JP11005816 A JP 11005816A JP 581699 A JP581699 A JP 581699A JP 2000204888 A JP2000204888 A JP 2000204888A
Authority
JP
Japan
Prior art keywords
tunnel
wellhead
elements
concrete
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11005816A
Other languages
Japanese (ja)
Inventor
Mitsuo Saito
光男 斉藤
Satoji Hori
聡次 堀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ishikawajima Kenzai Kogyo Co Ltd
Ishikawajima Construction Materials Co Ltd
Original Assignee
Ishikawajima Kenzai Kogyo Co Ltd
Ishikawajima Construction Materials Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ishikawajima Kenzai Kogyo Co Ltd, Ishikawajima Construction Materials Co Ltd filed Critical Ishikawajima Kenzai Kogyo Co Ltd
Priority to JP11005816A priority Critical patent/JP2000204888A/en
Publication of JP2000204888A publication Critical patent/JP2000204888A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To construct a pit mouth tunnel easily without increasing a cost. SOLUTION: Box-shaped long elements 15 are installed on a foundation 13, and the side parts of the elements 15 are connected to each other in order for assembly. When connecting the elements 15, a PC steel wire is disposed on fixing piece parts of side plates 21 on the outside of 2nd to 4th elements 15 and locking piece parts 33 formed on supporting plates 31 of the foundation 13, and tensed for supporting. While the elements 15 are assembled, concrete is filled into the elements to fill concrete into the entire elements 15 in which the side parts connected to each other form truss parts 22 in order to construct a side wall part 12a with elements 15 formed integrally with concrete. Precast boards 51 assembled in arch shape by butting them with each other are installed on the upper end part of the side wall part 12a so as to construct a roof part 12b.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、トンネル端部に
構築されて、トンネルの出入口を構成する坑口トンネル
及びその構築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a wellhead tunnel constructed at an end of a tunnel and constituting an entrance and exit of the tunnel, and a method for constructing the tunnel.

【0002】[0002]

【従来の技術】従来より、トンネルを構築する工法とし
て、地盤に掘削穴をあけ、この掘削穴に、内面からアン
カーを打ち込んでコンクリートを吹き付け、さらに、内
面に二次覆工を施す工法が知られている。
2. Description of the Related Art Conventionally, as a method of constructing a tunnel, there has been known a method of drilling an excavation hole in the ground, driving an anchor into the excavation hole and spraying concrete, and further performing a secondary lining on the inner surface. Have been.

【0003】ところで、上記のようにトンネルを構築す
る場合、図11に示すように、その坑口は落石等の危険
を有する切り刃であるため、このトンネル1の坑口2
に、周囲に張り出すウイング3を構築して地盤Gの土止
めを行っていた。
When a tunnel is constructed as described above, as shown in FIG. 11, the wellhead is a cutting edge having a risk of falling rocks.
Then, a wing 3 that protrudes around was constructed to block the ground G.

【0004】ところで、この土止め用のウイング3は、
その構築に多大な手間及び危険を要するため、図12に
示すように、坑口2から数10mの長さの不安定な地山
部分に、トンネル1から延長させた坑口トンネル4を構
築することが行われている。
[0004] By the way, the wings 3 for retaining the earth are
Since a great deal of trouble and danger is required for the construction, as shown in FIG. 12, it is necessary to construct a wellhead tunnel 4 extending from the tunnel 1 in an unstable ground part having a length of several tens of meters from the wellhead 2. Is being done.

【0005】この坑口トンネル4を構築するには、ま
ず、坑口トンネル4の内面を形成する内型枠を支保工に
よって支持し、この内型枠の外側に配筋を配設し、さら
に、その外側に外型枠を支持し、内型枠と外型枠との間
へコンクリートを打設していた。また、上記現場打ちに
代わる構築工法として、図13及び図14に示すよう
に、成形型によって成形されたプレキャスト版5を、現
場にて互いに突き合わせてアーチ型に組み立てて坑口ト
ンネル4を構築する工法がある。
[0005] In order to construct this wellhead tunnel 4, first, an inner formwork forming the inner surface of the wellhead tunnel 4 is supported by a support, and a reinforcing bar is arranged outside the inner formwork. The outer formwork was supported on the outside, and concrete was cast between the inner formwork and the outer formwork. As a construction method that replaces the above-mentioned in-situ casting, as shown in FIGS. 13 and 14, a precast plate 5 formed by a molding die is butted together at the site and assembled into an arch shape to construct a wellhead tunnel 4. There is.

【0006】[0006]

【発明が解決しようとする課題】ところで、現場打ちに
て坑口トンネル4を構築する場合、内型枠、外型枠の設
置、撤去等極めて煩雑な作業を要するという問題があ
り、また、この場合、これら型枠を支持する支保工が必
要であるため、その支保工の設置、撤去作業にも多大な
労力を要するという問題があった。
In the case of constructing the tunnel 4 by casting in the field, there is a problem that extremely complicated operations such as installation and removal of the inner formwork and the outer formwork are required. However, since a supporter for supporting these forms is required, there is a problem that a great deal of labor is required for installation and removal of the supporter.

【0007】また、プレキャスト版5を用いる場合、こ
のプレキャスト版5は、安定した構造とするためには、
3分割以下とする必要があるため、プレキャスト版5の
小型化には限度があり、これにより、プレキャスト版5
の大型化が避けられず、製造、運搬、設置等が困難とな
ってしまうという問題があった。
When the precast plate 5 is used, the precast plate 5 needs to have a stable structure.
Since it is necessary to reduce the size of the precast plate 5 to three or less, the miniaturization of the precast plate 5 is limited.
However, there is a problem that manufacturing, transportation, installation, and the like become difficult due to the inevitable increase in size of the device.

【0008】この発明は、上記事情に鑑みてなされたも
ので、コストアップを招くことなく、容易にかつ短期間
にて構築することが可能な坑口トンネル及びその構築方
法を提供することを目的としている。
The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a wellhead tunnel that can be easily and quickly constructed without increasing the cost, and a method of constructing the tunnel. I have.

【0009】[0009]

【課題を解決するための手段】上記目的を達成するため
に、請求項1記載の坑口トンネルは、トンネル端部に構
築されて、このトンネルの出入口を構成する坑口トンネ
ルであって、内部に鉄筋が配設された箱形に形成され、
側部同士が互いに接合されて組み立てられる長尺エレメ
ント内にコンクリートを充填してなる一対の互いに平行
に設けられた側壁部と、該側壁部の上部に、互いにトン
ネル周方向へ突き合わせて組み立てられるプレキャスト
版からなる天井部とから構成されていることを特徴とし
ている。
In order to achieve the above object, a wellhead tunnel according to claim 1 is a wellhead tunnel constructed at an end of the tunnel and constituting an entrance and exit of the tunnel, and has a reinforcing steel bar therein. Is formed in a box shape in which
A pair of parallel side walls provided by filling concrete in a long element whose side parts are joined together and assembled, and a precast assembled by abutting each other on the upper side of the side wall in the tunnel circumferential direction. It is characterized by being composed of a ceiling made of a plate.

【0010】このように、側部同士を接合することによ
り組み立てられた箱形の長尺エレメント内にコンクリー
トが充填された側壁部と、この側壁部の上端部に設けら
れたプレキャスト版とからなる構造であるので、型枠を
用いて現場打ちコンクリートにより構築するものと比較
して、型枠及び型枠を支持する支保工が不要とされ、こ
れにより、型枠及び支保工の設置、撤去等の極めて煩雑
な作業がなくされる。
[0010] As described above, the side wall is formed by joining the side parts together and is filled with concrete in a box-shaped long element, and the precast plate provided at the upper end of the side wall. Since the structure is used, compared with the construction using cast-in-place concrete using a formwork, the formwork and the supporting structure for supporting the formwork are not required, thereby setting and removing the formwork and the supporting structure. This eliminates the need for complicated work.

【0011】請求項2記載の坑口トンネルは、請求項1
記載の坑口トンネルにおいて、前記エレメントが、互い
に接合される側部がトラス構造とされ、互いに接合され
たエレメント同士にわたって前記コンクリートが充填さ
れていることを特徴としている。
The wellhead tunnel according to the second aspect is the first aspect.
The wellhead tunnel according to any one of the preceding claims, characterized in that the elements are connected to each other in a truss structure, and the concrete is filled over the elements connected to each other.

【0012】つまり、エレメント同士の接合側がトラス
構造とされて、互いのエレメント同士にわたってコンク
リートが充填された一体構造であるので、高強度化が図
られる。
That is, since the joining side of the elements has a truss structure and is an integrated structure in which the elements are filled with concrete, the strength is enhanced.

【0013】請求項3記載の坑口トンネルの構築方法
は、トンネル端部に構築されて、このトンネルの出入口
を構成する坑口トンネルの構築方法であって、内部に鉄
筋が配設された箱形の長尺エレメントの側部同士を互い
に接合して組み立て、これらエレメント内にコンクリー
トを充填して一体化させることにより、一対の側壁部を
互いに平行に構築し、これら側壁部の上端に、トンネル
周方向へ突き合わされるプレキャスト版を組み立てて天
井部を構築することを特徴としている。
According to a third aspect of the present invention, there is provided a method of constructing a wellhead tunnel constructed at an end of a tunnel and constituting an entrance and exit of the tunnel, wherein a box-shaped rebar is provided inside. By joining the side parts of the long element to each other and assembling them, filling these elements with concrete and integrating them, a pair of side wall parts is constructed parallel to each other, and the upper end of these side wall parts is placed in the tunnel circumferential direction. It is characterized by assembling a precast version that is matched to the ceiling to construct the ceiling.

【0014】このように、エレメントの側部同士を互い
に接合して組み立てて、エレメント内にコンクリートを
充填することにより、極めて容易に、内部にコンクリー
トが充填されたエレメントからなる側壁部が構築され、
さらに、側壁部の上端にプレキャスト版を組み立てるこ
とにより、容易に坑口トンネルが構築される。これによ
り、型枠を用いて現場打ちコンクリートにより坑口トン
ネルを構築する場合と比較して、型枠及び型枠を支持す
る支保工を不要とすることが可能となり、これにより、
型枠及び支保工の設置、撤去等の極めて煩雑な作業がな
くされ、工期短縮が図られる。
As described above, by joining the side parts of the element to each other and assembling them, and filling the element with concrete, it is possible to extremely easily construct the side wall composed of the element filled with concrete inside.
Further, by assembling the precast plate on the upper end of the side wall portion, the wellhead tunnel is easily constructed. This makes it possible to eliminate the need for a formwork and a shoring for supporting the formwork, as compared with a case where a wellhead tunnel is constructed from cast-in-place concrete using the formwork.
Extremely complicated work such as installation and removal of the formwork and the shoring is eliminated, and the construction period is shortened.

【0015】請求項4記載の坑口トンネルの構築方法
は、請求項3記載の坑口トンネルの構築方法において、
前記エレメントを、予め構築した基礎部分から順に接合
してアーチ型に組み立てる際に、前記エレメントの外面
と前記基礎部分とをPC鋼線によって連結し、該PC鋼
線を緊張させることにより前記エレメントを支持するこ
とを特徴としている。
According to a fourth aspect of the present invention, there is provided the method of constructing a wellhead tunnel according to the third aspect.
When the element is joined in order from a pre-constructed base portion to assemble into an arch shape, the outer surface of the element and the base portion are connected by a PC steel wire, and the PC steel wire is tensioned to connect the element. It is characterized by support.

【0016】このように、エレメントを外側からPC鋼
線によって引っ張ることにより支持しながら組み上げる
ので、内側からの支持が不要とされ、内側での支保工が
不要とされる。つまり、内側の支保工が不要とされるの
で、例えば、既設のトンネルに施工する場合にも、内側
に保護用枠等を設置して車両の走行車線を保護すること
により、交通を開放してエレメントの組み立てを行うこ
とができる。
As described above, since the element is assembled while being supported by being pulled by the PC steel wire from the outside, the support from the inside is unnecessary, and the support work on the inside is unnecessary. In other words, since the inner support is not required, for example, even in the case of construction in an existing tunnel, by opening a protective frame and the like inside to protect the traveling lane of the vehicle, to open the traffic Element assembly can be performed.

【0017】請求項5記載の坑口トンネルの構築方法
は、請求項3記載の坑口トンネルの構築方法において、
前記エレメントを、トンネル内周面に沿ってアーチ型に
配設した鋼材からなる支持部材に支持させながら予め構
築した基礎部分から順に接合して組み立てることを特徴
としている。
According to a fifth aspect of the present invention, there is provided a method of constructing a wellhead tunnel according to the third aspect.
The invention is characterized in that the elements are joined by assembling in order from a previously constructed base portion while being supported by a support member made of a steel material arranged in an arch shape along the inner peripheral surface of the tunnel.

【0018】このように、トンネル内周面に沿ってアー
チ型に配設した鋼材からなる支持部材に支持させるの
で、エレメントの組み立て作業の容易化を図ることがで
き、特に、新規のトンネルに構築する場合に有利であ
る。
As described above, since the support member made of a steel material arranged in an arched shape along the inner peripheral surface of the tunnel is supported, the work of assembling the elements can be facilitated. It is advantageous when

【0019】請求項6記載の坑口トンネルの構築方法
は、請求項3〜5のいずれか1項記載の坑口トンネルの
構築方法において、互いに接合させる側部がトラス構造
とされた前記エレメントを組み立て、これらエレメント
内にコンクリートを充填することを特徴としている。
According to a sixth aspect of the present invention, there is provided the method for constructing a wellhead tunnel according to any one of the third to fifth aspects, wherein the elements to be joined to each other have a truss structure. It is characterized in that concrete is filled in these elements.

【0020】つまり、互いに接合させる側部がトラス構
造とされたエレメントを用いるので、エレメント内にコ
ンクリートを充填することにより、極めて容易に、組み
立てたエレメントの内部全体にコンクリートが行き渡
り、エレメント同士が確実に一体化された高強度の側壁
部を有する坑口トンネルが構築される。
In other words, since elements having a truss structure on the sides to be joined to each other are used, by filling the elements with concrete, it is very easy to spread the concrete throughout the assembled elements and to ensure that the elements are connected to each other. A wellhead tunnel having a high-strength side wall integrated into the tunnel is constructed.

【0021】[0021]

【発明の実施の形態】以下、本発明の坑口トンネル及び
その構築方法の実施の形態を図によって説明する。図1
及び図2において、符号11は、坑口トンネルである。
この坑口トンネル11は、アーチ型に構築された坑口本
体12と、この坑口本体12の両端が設置された基礎1
3と、これら基礎13同士の間に設けられた底版部14
とから概略構成されている。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view showing an embodiment of a wellhead tunnel and a method for constructing the same according to the present invention. FIG.
2 and FIG. 2, reference numeral 11 denotes a wellhead tunnel.
The wellhead tunnel 11 has an arched wellhead body 12 and a foundation 1 on which both ends of the wellhead body 12 are installed.
3 and a bottom plate portion 14 provided between the foundations 13.
It is schematically composed of

【0022】坑口本体12は、その両側部が側壁部12
aとされ、中間部が天井部12bとされており、側壁部
12aの内周面には、化粧板16が設けられている。側
壁部12aは、図3にも示すように、側部同士が周方向
へ互いに接合された箱形の複数の長尺エレメント15か
ら構成されており、これら側部同士が互いに接合された
エレメント15には、その内部全体に、コンクリートC
が充填されて一体化されている。
The wellhead body 12 has side walls 12 on both sides.
a, an intermediate portion is a ceiling portion 12b, and a decorative plate 16 is provided on an inner peripheral surface of the side wall portion 12a. As shown in FIG. 3, the side wall portion 12a is composed of a plurality of box-shaped long elements 15 whose side portions are joined to each other in the circumferential direction, and the element 15 whose side portions are joined to each other. In the entire interior, concrete C
Are filled and integrated.

【0023】図4にも示すように、エレメント15は、
互いに対向させて設けられた一対の側板21と、これら
側板21同士の間に設けられ、これら側板21同士を、
間隔をあけた状態に接合するトラス部22とから構成さ
れている。このエレメント15の両側板21の幅寸法
は、内側が小さく、外側が大きくされている。つまり、
各エレメント15の側部同士を接合させた際に、全体的
に多角形型のアーチ型に組み立てられるようになってい
る。
As shown in FIG. 4, the element 15 is
A pair of side plates 21 provided facing each other, and provided between these side plates 21, these side plates 21 are
And a truss portion 22 joined at an interval. The width dimension of both side plates 21 of the element 15 is small on the inside and large on the outside. That is,
When the side parts of the elements 15 are joined together, they can be assembled into a polygonal arch as a whole.

【0024】なお、最上部に接合させるエレメント15
は、側壁部12aの上部が略水平となるように、外側の
側板21の幅寸法が、内側よりも小さくされている。ま
た、これらエレメント15の側板21には、その上部
に、鉤形に形成された継手部材23が設けられ、下部
に、継手部材23が係合可能な突起部24が設けられて
いる。
The element 15 to be joined to the uppermost part
The width of the outer side plate 21 is smaller than that of the inner side so that the upper part of the side wall part 12a is substantially horizontal. Further, the side plate 21 of each of the elements 15 is provided with a joint member 23 formed in a hook shape at an upper portion thereof, and a projection 24 with which the joint member 23 can be engaged is provided at a lower portion thereof.

【0025】即ち、エレメント15の上部に、他のエレ
メント15を接合する場合に、下方側のエレメント15
に対して軸方向へずらした状態にて上方側のエレメント
15を載せ、その後、上方のエレメント15を、ずらし
た方向と逆へスライドさせることにより、上方のエレメ
ント15の突起部24が、下方のエレメント15の継手
部材23に係合されるようになっている。
That is, when another element 15 is joined to the upper part of the element 15, the lower element 15
The upper element 15 is placed in a state shifted in the axial direction with respect to, and then the upper element 15 is slid in a direction opposite to the shifted direction, so that the projection 24 of the upper element 15 is moved downward. It is adapted to be engaged with the joint member 23 of the element 15.

【0026】なお、継手部材23を側板21の下部に設
け、突起部24を側板21の上部に設け、これらを互い
に係合させるようにしても良い。そして、上記構成のエ
レメント15には、その内部に、カゴ型の鉄筋25が配
設されてユニット化されている。
The joint member 23 may be provided below the side plate 21 and the projection 24 may be provided above the side plate 21 so that they are engaged with each other. And, the element 15 having the above configuration is provided with a cage-type reinforcing bar 25 therein to form a unit.

【0027】基礎13には、上方へ延出されたアンカー
筋26が設けられており、これらアンカー筋26によっ
て基礎13に坑口本体12が固着されている。また、基
礎13には、坑口本体12の下端部における外周側に、
長手方向へわたって支持板31が立設されている。
The foundation 13 is provided with anchor bars 26 extending upward, and the wellhead body 12 is fixed to the foundation 13 by the anchor bars 26. Also, on the foundation 13, on the outer peripheral side at the lower end of the wellhead body 12,
A support plate 31 stands upright in the longitudinal direction.

【0028】この支持板31には、図5に示すように、
凹部32が形成された複数の係止片部33が軸方向へ間
隔をあけて設けられている。これら係止片部33は、軸
方向へ3つずつ一組とされ、それぞれ第1係止片部33
a、第2係止片部33b、第3係止片部33cとされて
いる。
As shown in FIG. 5, the support plate 31
A plurality of locking pieces 33 having the recesses 32 are provided at intervals in the axial direction. The locking pieces 33 are formed as a set of three in the axial direction, and each of the locking pieces 33 is a first locking piece 33.
a, a second locking piece 33b and a third locking piece 33c.

【0029】坑口本体12を構成するエレメント15の
内の下から2段目のエレメント15の外側の側板21に
は、前記第1係止片部33a、第2係止片部33b、第
3係止片部33cと同一軸方向位置に、コマ部材34が
設けられており、さらに、第1係止片部33aと同一軸
方向位置には、コマ部材34の上方に、前記係止片部3
3と略同一形状に形成された定着片部35が設けられて
いる。
The first locking piece 33a, the second locking piece 33b, and the third locking member 33 are provided on the side plate 21 outside the second lowermost element 15 of the elements 15 constituting the wellhead main body 12. The top member 34 is provided at the same axial position as the stop piece portion 33c, and further, at the same axial direction position as the first locking piece portion 33a, above the top member 34, the locking piece portion 3 is provided.
A fixing piece 35 having substantially the same shape as that of the fixing piece 3 is provided.

【0030】また、エレメント15の内の下から3段目
のエレメント15の外側の側板21には、前記第2係止
片部33b、第3係止片部33cと同一軸方向位置に、
コマ部材34が設けられており、さらに、第2係止片部
33bと同一軸方向位置には、コマ部材34の上方に、
定着片部35が設けられている。
The outer side plate 21 of the third element 15 from the bottom of the element 15 is provided at the same axial position as the second locking piece 33b and the third locking piece 33c.
A top member 34 is provided, and at the same axial position as the second locking piece 33b, above the top member 34,
A fixing piece 35 is provided.

【0031】さらに、エレメント15の内の下から4段
目のエレメント15の外側の側板21には、前記第3係
止片部33cと同一軸方向位置に、コマ部材34が設け
られており、また、第3係止片部33cと同一軸方向位
置には、コマ部材34の上方に、定着片部35が設けら
れている。
Further, on the side plate 21 outside the fourth element 15 from the bottom of the element 15, a top member 34 is provided at the same axial position as the third locking piece 33c. A fixing piece 35 is provided above the top member 34 at the same axial position as the third locking piece 33c.

【0032】そして、上記係止片部33と定着片部35
との間には、後述する組み立て用PC鋼線41が配設さ
れるようになっており、このPC鋼線41の一端側に設
けられた定着用ナット41aが定着片部35に係止さ
れ、他端側に設けられた緊張用ナット41bが係止片部
33に係止されるようになっている。ここで、このPC
鋼線41は、両端部におねじが形成されており、このお
ねじに前記定着用ナット41a及び緊張用ナット41b
が螺合されるようになっている。
The locking piece 33 and the fixing piece 35
A fixing PC steel wire 41 to be described later is arranged between the fixing member 35 and a fixing nut 41a provided at one end of the PC steel wire 41. The tensioning nut 41 b provided on the other end side is locked by the locking piece 33. Here, this PC
The steel wire 41 has threads formed at both ends, and the fixing nut 41a and the tensioning nut 41b
Are screwed together.

【0033】なお、上記のように構成された坑口トンネ
ル11の坑口本体12内には、周方向へわたってかつ軸
方向へ間隔をあけて図示しないPC鋼線が配設され、こ
のPC鋼線によって周方向へプレストレスが導入されて
いる。
In the wellhead main body 12 of the wellhead tunnel 11 configured as described above, a PC steel wire (not shown) is disposed so as to extend in the circumferential direction and at intervals in the axial direction. This introduces a prestress in the circumferential direction.

【0034】天井部12bは、プレキャスト版51から
構成されたもので、各プレキャスト版51の一端が、互
いに接合される接合端51aとされ、例えば、ボルト・
ナット等によって締結固定されている。これらプレキャ
スト版51は、高強度コンクリートから成形されてその
厚さが薄くされている。
The ceiling portion 12b is composed of a precast plate 51. One end of each precast plate 51 is a joint end 51a to be joined to each other.
It is fastened and fixed by nuts and the like. These precast plates 51 are formed from high-strength concrete and have a reduced thickness.

【0035】また、天井部12bの両端を構成するプレ
キャスト版51の他端部は、側壁部12aの上端との連
結端51bとされている。この連結端51bは、外周方
向へ突出したフランジ部52が形成されてその厚さが側
壁部12aの厚さと略同一とされており、この連結端5
1bのフランジ部52には、トンネル軸線方向へ間隔を
あけて複数の連通孔53が形成されている。
The other end of the precast plate 51, which constitutes both ends of the ceiling 12b, is a connection end 51b with the upper end of the side wall 12a. The connecting end 51b is formed with a flange portion 52 protruding in the outer peripheral direction and has a thickness substantially equal to the thickness of the side wall portion 12a.
A plurality of communication holes 53 are formed in the flange portion 1b at intervals in the tunnel axis direction.

【0036】そして、この連通孔53には、側壁部12
bの上端に立設された連結筋54が挿通されている。な
お、この連結筋54は、その上端部が、プレキャスト版
51のフランジ部52の上方に突出されており、この突
出された部分にナット50が螺合されて締結固定されて
いる。
The communication hole 53 has a side wall 12.
A connecting bar 54 erected at the upper end of b is inserted. The connecting bar 54 has an upper end protruding above the flange portion 52 of the precast plate 51, and a nut 50 is screwed and fastened to the protruding portion.

【0037】次に、上記坑口トンネル11を構築する場
合について、図6を参照して説明する。 (側壁部12aの構築) (1)まず、基礎13を構築し、この基礎13の支持板
31に合わせて、一段目のエレメント15を配設し、こ
のエレメント15内にコンクリートCを充填する。 (2)次に、このエレメント15の上部に、2段目のエ
レメント15を、軸方向へずらした状態に載置させた
ら、この2段目のエレメント15をずらした方向と逆方
向へスライドさせる。
Next, the construction of the wellhead tunnel 11 will be described with reference to FIG. (Construction of Side Wall 12a) (1) First, a foundation 13 is constructed, a first-stage element 15 is arranged in accordance with a support plate 31 of the foundation 13, and concrete C is filled in the element 15. (2) Next, when the second-stage element 15 is placed on the upper part of the element 15 so as to be shifted in the axial direction, the second-stage element 15 is slid in a direction opposite to the direction in which the second-stage element 15 is shifted. .

【0038】このようにすると、この2段目のエレメン
ト15の側板21の下方側に設けられた突起部24が、
1段目のエレメント15の側板21の上方側に設けられ
た継手部材23に係合され、これら1段目のエレメント
15と2段目のエレメント15とが互いに接合される。
In this way, the projection 24 provided below the side plate 21 of the second stage element 15
The first-stage element 15 and the second-stage element 15 are engaged with each other by being engaged with a joint member 23 provided above the side plate 21 of the first-stage element 15.

【0039】(3)上記のように、2段目のエレメント
15を1段目のエレメント15に接合させたら、図6に
示すように、2段目のエレメント15の外側の側板21
に設けられた定着片部35に、PC鋼線41の一端部に
固定された定着用ナット41aを係止させ、基礎13の
支持板31に設けられた第1係止片部33aに、PC鋼
線41の他端部に螺合された緊張用ナット41bを係止
させる。
(3) As described above, when the second-stage element 15 is joined to the first-stage element 15, as shown in FIG.
The fixing nut 41a fixed to one end of the PC steel wire 41 is locked to the fixing piece 35 provided on the base 13 and the first locking piece 33a provided on the support plate 31 of the foundation 13 is fixed to the PC by the PC. The tension nut 41b screwed to the other end of the steel wire 41 is locked.

【0040】(4)次いで、他端部に螺合された緊張用
ナット41bをさらにねじ込み、PC鋼線41を緊張さ
せる。このようにすると、2段目のエレメント15が、
PC鋼線41によって外側から引っ張られて支持され、
この2段目のエレメント15の内側への倒れ込みが防止
される。
(4) Next, the tension nut 41b screwed to the other end is further screwed in to tension the PC steel wire 41. In this case, the element 15 in the second stage is
It is supported by being pulled from the outside by the PC steel wire 41,
The second stage element 15 is prevented from falling inside.

【0041】また、このとき、PC鋼線41は、2段目
のエレメント15の外側の側板21に設けられたコマ部
材34に当接することによりその当接部分が湾曲され、
このPC鋼線41が、1段目、2段目のエレメント15
同士の接合部分と接触することなく緊張される。これに
より、このPC鋼線41の緊張力が確実に2段目のエレ
メント15に作用することとなる。
At this time, when the PC steel wire 41 comes into contact with the top member 34 provided on the outer side plate 21 of the second stage element 15, the contact portion is curved,
This PC steel wire 41 is used for the element 15 of the first and second stages.
They are tensed without coming into contact with their joints. This ensures that the tension of the PC steel wire 41 acts on the second-stage element 15.

【0042】(5)この状態において、2段目のエレメ
ント15内にコンクリートCを充填する。 (6)その後、2段目のエレメント15の上部に、3段
目のエレメント15を、前述と同様に、軸方向へずらし
た状態に載置させ、この3段目のエレメント15をずら
した方向と逆方向へスライドさせる。
(5) In this state, the concrete C is filled in the second stage element 15. (6) After that, the third-stage element 15 is placed on the upper part of the second-stage element 15 in the axially displaced state in the same manner as described above, and the third-stage element 15 is displaced. And slide in the opposite direction.

【0043】このようにすると、この3段目のエレメン
ト15の側板21の下方側に設けられた突起部24が、
2段目のエレメント15の側板21の上方側に設けられ
た継手部材23に係合され、これら2段目のエレメント
15と3段目のエレメント15とが互いに接合される。
In this manner, the projection 24 provided below the side plate 21 of the third stage element 15
The second-stage element 15 and the third-stage element 15 are engaged with each other by being engaged with a joint member 23 provided above the side plate 21 of the second-stage element 15.

【0044】(7)このように、3段目のエレメント1
5を2段目のエレメント15に接合させたら、3段目の
エレメント15の外側の側板21に設けられた定着片部
35に、PC鋼線41の一端部に固定された定着用ナッ
ト41aを係止させ、基礎13の支持板31に設けられ
た第2係止片部33bに、PC鋼線41の他端部に螺合
された緊張用ナット41bを係止させる。
(7) Thus, the third stage element 1
5 is joined to the second-stage element 15, a fixing nut 41 a fixed to one end of the PC steel wire 41 is attached to the fixing piece 35 provided on the side plate 21 outside the third-stage element 15. The tension nut 41b screwed to the other end of the PC steel wire 41 is locked to the second locking piece 33b provided on the support plate 31 of the base 13.

【0045】(8)次いで、他端部に螺合された緊張用
ナット41bをさらにねじ込み、PC鋼線41を緊張さ
せる。このようにすると、3段目のエレメント15が、
PC鋼線41によって外側から引っ張られて支持され、
この3段目のエレメント15の内側への倒れ込みが防止
される。
(8) Next, the tension nut 41b screwed to the other end is further screwed in to tension the PC steel wire 41. In this case, the third stage element 15
It is supported by being pulled from the outside by the PC steel wire 41,
The third stage element 15 is prevented from falling inside.

【0046】また、このとき、PC鋼線41は、3段
目、2段目のエレメント15のそれぞれの外側の側板2
1に設けられたコマ部材34に当接することによりその
当接部分が湾曲され、このPC鋼線41が、2段目、3
段目のエレメント15同士及び1段目、2段目のエレメ
ント15同士の接合部分と接触することなく緊張され
る。これにより、このPC鋼線41の緊張力が確実に3
段目のエレメント15に作用することとなる。
At this time, the PC steel wire 41 is connected to the outer side plate 2 of each of the third-stage and second-stage elements 15.
When the PC steel wire 41 is in contact with the top member 34 provided in the first stage, the contact portion is bent,
It is tensed without coming into contact with the joints between the elements 15 in the first stage and between the elements 15 in the first and second stages. This ensures that the tension of the PC steel wire 41 is 3
It acts on the element 15 of the stage.

【0047】(9)この状態において、3段目のエレメ
ント15内にコンクリートCを充填する。 (10)さらに、3段目のエレメント15の上部に、4
段目のエレメント15を、前述と同様に、軸方向へずら
した状態に載置させ、この4段目のエレメント15をず
らした方向と逆方向へスライドさせる。
(9) In this state, the concrete C is filled in the third stage element 15. (10) Further, 4
The stage element 15 is placed in a state shifted in the axial direction in the same manner as described above, and the fourth stage element 15 is slid in the direction opposite to the direction shifted.

【0048】このようにすると、この4段目のエレメン
ト15の側板21の下方側に設けられた突起部24が、
3段目のエレメント15の側板21の上方側に設けられ
た継手部材23に係合され、これら3段目のエレメント
15と4段目のエレメント15とが互いに接合される。
In this way, the projection 24 provided below the side plate 21 of the fourth stage element 15
The third-stage element 15 is engaged with a joint member 23 provided above the side plate 21 of the third-stage element 15, and the third-stage element 15 and the fourth-stage element 15 are joined to each other.

【0049】(11)このように、4段目のエレメント
15を3段目のエレメント15に接合させたら、4段目
のエレメント15の外側の側板21に設けられた定着片
部35に、PC鋼線41の一端部に固定された定着用ナ
ット41aを係止させ、基礎13の支持板31に設けら
れた第3係止片部33cに、PC鋼線41の他端部に螺
合された緊張用ナット41bを係止させる。
(11) As described above, when the fourth stage element 15 is joined to the third stage element 15, the fixing piece 35 provided on the side plate 21 outside the fourth stage element 15 The fixing nut 41a fixed to one end of the steel wire 41 is locked, and screwed to the third locking piece 33c provided on the support plate 31 of the base 13 to the other end of the PC steel wire 41. The tension nut 41b is locked.

【0050】(12)次いで、他端部に螺合された緊張
用ナット41bをさらにねじ込み、PC鋼線41を緊張
させる。このようにすると、4段目のエレメント15
が、PC鋼線41によって外側から引っ張られて支持さ
れ、この4段目のエレメント15の内側への倒れ込みが
防止される。
(12) Next, the tension nut 41b screwed to the other end is further screwed in to tension the PC steel wire 41. In this way, the fourth stage element 15
Is pulled from the outside by the PC steel wire 41 and is supported, so that the fourth stage element 15 is prevented from falling inside.

【0051】また、このとき、PC鋼線41は、4段
目、3段目、2段目のエレメント15のそれぞれの外側
の側板21に設けられたコマ部材34に当接することに
よりその当接部分が湾曲され、このPC鋼線41が、3
段目、4段目のエレメント15同士、2段目、3段目の
エレメント15同士及び1段目、2段目のエレメント1
5同士の接合部分と接触することなく緊張される。これ
により、このPC鋼線41の緊張力が確実に4段目のエ
レメント15に作用することとなる。
At this time, the PC steel wire 41 comes into contact with the top member 34 provided on the outer side plate 21 of each of the fourth, third, and second stage elements 15, thereby causing the contact. The section is curved, and this PC steel wire 41
Elements 15 of the fourth and fourth stages, elements 15 of the second and third stages, and elements 1 of the first and second stages
It is tensed without coming into contact with the joint between the five. This ensures that the tension of the PC steel wire 41 acts on the fourth stage element 15.

【0052】(13)この状態において、4段目のエレ
メント15内にコンクリートCを充填する。 (14)コンクリートCが硬化したら、予め周方向へわ
たってエレメント15内に挿通させたPC鋼線(図示
略)を緊張させることにより、プレストレスが導入され
て高強度化された側壁部12aを完成させ、その内周面
側に化粧版16を貼り付ける。なお、各エレメント15
の端部は、充填するコンクリートCが流出しないように
閉鎖しておく。
(13) In this state, the concrete C is filled in the fourth stage element 15. (14) When the concrete C has hardened, the PC steel wire (not shown) inserted in the element 15 in advance in the circumferential direction is tensioned, so that the side wall 12a to which the prestress is introduced and the strength is increased. After completion, the decorative plate 16 is attached to the inner peripheral surface side. Each element 15
Is closed so that the concrete C to be filled does not flow out.

【0053】(天井部12bの構築) (15)次に、上記のようにして構築した側壁部12a
の上端に、プレキャスト版51を設置する。つまり、プ
レキャスト版51の連結端51bを構成するフランジ部
52に形成された連通孔53に、側壁部12aの上端に
設けられた連結筋54を挿通させながら連結端51bを
側壁部12a上へ載せ、このプレキャスト版51の接合
端51a同士を互いに突き合わせ、ボルト・ナットによ
って接合させる。
(Construction of Ceiling Part 12b) (15) Next, the side wall part 12a constructed as described above
A precast plate 51 is set at the upper end of the plate. That is, the connecting end 51b is placed on the side wall 12a while the connecting bar 54 provided at the upper end of the side wall 12a is inserted into the communication hole 53 formed in the flange 52 constituting the connecting end 51b of the precast plate 51. The joining ends 51a of the precast plate 51 are abutted against each other and joined by bolts and nuts.

【0054】さらに、連結筋54にナット50を螺合さ
せ、プレキャスト版51のフランジ部52を側壁部12
aの上端部に締結固定する。
Further, a nut 50 is screwed into the connecting bar 54, and the flange 52 of the precast plate 51 is attached to the side wall 12.
a.

【0055】(16)基礎13同士の間に、底版部14
を構築し、さらに、坑口本体12の内面に化粧板16を
貼り付けることにより坑口トンネル11を完成させ、そ
の後、坑口トンネル11を埋め戻す。なお、エレメント
15同士の組み立て時に用いたPC鋼線41は、坑口ト
ンネル11の完成後に取り外し、他の坑口トンネルの構
築時に用いる。また、この坑口本体12の内側での底版
部14の構築等の作業は、坑口本体12の構築時に並行
して行うことができる。
(16) Between the foundations 13, the bottom slab 14
Then, the decorative tunnel 16 is adhered to the inner surface of the wellhead main body 12 to complete the wellhead tunnel 11, and then the wellhead tunnel 11 is backfilled. In addition, the PC steel wire 41 used at the time of assembling the elements 15 is removed after the completion of the wellhead tunnel 11 and used at the time of building another wellhead tunnel. The work such as the construction of the bottom plate portion 14 inside the wellhead main body 12 can be performed in parallel with the construction of the wellhead main body 12.

【0056】このように、上記の坑口トンネル11によ
れば、側部同士を接合することによりアーチ型に組み立
てられた箱形の長尺エレメント15内に、コンクリート
Cを充填した側壁部12aと、これら側壁部12aの上
端部に設けたプレキャスト版51とから構成されたもの
であるので、型枠を用いて現場打ちコンクリートにより
構築するものと比較して、型枠及び型枠を支持する支保
工を不要とすることができ、これにより、型枠及び支保
工の設置、撤去等の極めて煩雑な作業をなくすことがで
きる。また、エレメント15の長さを長くすることによ
り、坑口トンネル11の長さを、極めて容易に長くする
ことができる。
As described above, according to the above-described wellhead tunnel 11, the side wall portion 12a filled with concrete C is filled in the box-shaped long element 15 assembled in an arch shape by joining the sides. Since it is composed of the precast plate 51 provided at the upper end portion of the side wall portion 12a, it is possible to provide a formwork and a support structure for supporting the formwork in comparison with those constructed by cast-in-place concrete using the formwork. Can be dispensed with, thereby making it possible to eliminate extremely complicated operations such as installation and removal of the formwork and the shoring. In addition, by increasing the length of the element 15, the length of the wellhead tunnel 11 can be extremely easily increased.

【0057】さらには、エレメント15同士の接合側が
トラス構造のトラス部22とされ、互いのエレメント1
5同士にわたってコンクリートCが充填された一体構造
であるので、側壁部12aの高強度化を図ることができ
る。
Further, the joining side of the elements 15 is a truss portion 22 of a truss structure, and
Since it is an integral structure in which the concrete C is filled over each other, the strength of the side wall portion 12a can be enhanced.

【0058】また、この坑口トンネル11を構築する構
築方法によれば、エレメント15の側部同士を互いに接
合してエレメント15内にコンクリートCを充填するこ
とにより側壁部12aを構築し、これら側壁部12aの
上部にてプレキャスト版51を互いに突き合わせて取り
付けることにより、極めて容易に、側部がエレメント1
5からなる側壁部12aからなり、中間部がプレキャス
ト版51からなる坑口トンネル11を構築することがで
きる。
According to the construction method for constructing the wellhead tunnel 11, the side walls 12a are constructed by joining the sides of the elements 15 to each other and filling the element 15 with the concrete C. By mounting the precast plates 51 against each other at the upper part of the element 12a, it is very easy to
The wellhead tunnel 11 composed of the side wall part 12 a composed of the precast plate 51 and the intermediate part composed of the precast plate 51 can be constructed.

【0059】つまり、前述したように、型枠を用いて現
場打ちコンクリートにより坑口トンネルを構築する場合
と比較して、型枠及び型枠を支持する支保工を不要とす
ることができ、これにより、型枠及び支保工の設置、撤
去等の極めて煩雑な作業をなくすことができ、工期短縮
を図ることができ、しかも、エレメント15の長さを長
くすることにより、極めて容易に坑口トンネル11の長
さを長くすることができる。
That is, as described above, the formwork and the support for supporting the formwork can be dispensed with, as compared with the case where the wellhead tunnel is constructed by cast-in-place concrete using the formwork. In addition, it is possible to eliminate extremely complicated work such as installation and removal of the formwork and the shoring work, to shorten the construction period, and to increase the length of the element 15 so that the wellhead tunnel 11 can be extremely easily mounted. The length can be lengthened.

【0060】また、両側部を構成する側壁部12aと、
これら側壁部12aの上端に連結されて坑口本体12の
上部を構成する天井部12bとから構成され、この天井
部12bが互いに突き合わされて接合されるプレキャス
ト版51から構成されているので、坑口本体12全部
を、互いに突き合わされて接合されるプレキャスト版か
ら構成した場合と比較して、プレキャスト版51を大幅
に小型化させることができる。
Further, a side wall portion 12a forming both side portions,
And a ceiling portion 12b which is connected to the upper end of the side wall portion 12a and constitutes the upper portion of the wellhead main body 12. Since the ceiling portion 12b is formed of the precast plate 51 which is abutted and joined to each other, the wellhead body As compared with the case where all the members 12 are formed of precast plates joined to each other by abutting each other, the precast plate 51 can be significantly reduced in size.

【0061】これにより、プレキャスト版51の成形用
型枠及び内部に配設する鉄筋等の小型化を図ることがで
きるとともに、大型の天井クレーンも不要となり、設備
費及び製造費の低コスト化を図ることができる。また、
プレキャスト版51の小型化に伴い、積み荷の大きさ、
積載重量の制限があるトラックにて、これらプレキャス
ト版51を容易に積載して運搬することができる。
As a result, it is possible to reduce the size of the mold for forming the precast plate 51 and the reinforcing bars provided inside the precast plate 51, as well as to eliminate the need for a large overhead crane, thereby reducing equipment and manufacturing costs. Can be planned. Also,
With the miniaturization of the precast plate 51, the size of the cargo,
These precast plates 51 can be easily loaded and transported on a truck having a limited loading weight.

【0062】しかも、工場、現場において、広大なスト
ックヤードも不要とすることができ、さらには、現場に
おける大型クレーン等の重機も不要となり、現場での制
約を緩和させることができる。また、エレメント15を
外側の側板21からPC鋼線41によって引っ張ること
により支持しながらアーチ型に組み上げるので、内側か
らの支持を不要とすることができ、内側での支保工を不
要とすることができる。
Moreover, a large stock yard is not required in a factory or on-site, and heavy equipment such as a large crane is not required on-site, so that restrictions on the on-site can be eased. Further, since the element 15 is assembled in an arch shape while being supported by being pulled from the outer side plate 21 by the PC steel wire 41, it is possible to eliminate the need for support from the inside, and to eliminate the need for support on the inside. it can.

【0063】つまり、内側の支保工が不要とされるの
で、例えば、既設のトンネルに施工する場合にも、図7
に示すように、内側に保護用枠61を設置して車両Sの
走行車線を保護することにより、交通を開放してエレメ
ント15の組み立てを行うことができる。
In other words, since the inner shoring is not required, for example, even when the tunnel is installed in an existing tunnel, FIG.
As shown in (1), by installing a protection frame 61 inside to protect the traveling lane of the vehicle S, it is possible to open the traffic and to assemble the element 15.

【0064】しかも、互いに接合させる側部がトラス構
造のトラス部22とされたエレメント15を用いるの
で、コンクリートCを充填することにより、極めて容易
に、エレメント15同士にわたってその内部にコンクリ
ートCを充填させることができ、エレメント15同士が
確実に一体化された高強度の側壁部12aを有するアー
チ型の坑口トンネル11を構築することができる。
Moreover, since the elements 15 having the truss portions 22 of the truss structure are used at the side portions to be joined to each other, the concrete C is filled with the concrete C very easily over the elements 15 by filling the concrete C. Thus, it is possible to construct the arched wellhead tunnel 11 having the high-strength side wall 12a in which the elements 15 are surely integrated.

【0065】また、エレメント15同士を、その長手方
向へ間隔をあけて設けた係合部材23と突起部24とを
係合させるものであるので、上下のエレメント15同士
をずらした状態にて接合側の側部同士を当接させて、ず
らした方向と逆方向へスライドさせることにより、極め
て容易に、それぞれのエレメント15の係合部材23と
突起部24とを互いに係合させて、これらエレメント1
5同士を連結させることができる。
Further, since the engaging members 23 and the projections 24 provided at intervals in the longitudinal direction of the elements 15 are engaged with each other, the upper and lower elements 15 are joined while being shifted from each other. By making the side portions of the side contact each other and sliding in the direction opposite to the shifted direction, the engaging member 23 of each element 15 and the protruding portion 24 can be very easily engaged with each other, 1
5 can be connected to each other.

【0066】また、エレメント15の端部を斜めに切断
しておくことにより、極めて容易に、坑口トンネル11
の端部を、図8に示すように、側方の地盤の傾斜に合わ
せて斜めにした、いわゆる竹割り構造とすることができ
る。
Also, by cutting the end of the element 15 obliquely, the wellhead tunnel 11
As shown in FIG. 8, a so-called bamboo split structure in which the end is inclined in accordance with the inclination of the ground on the side can be employed.

【0067】また、図9に示すものは、基礎13、底版
部14に代えて、基礎部分と底版部分とを一体化させた
インバート62を構築し、このインバート62の基礎部
分に坑口本体12を支持させたもので、この構造の坑口
トンネル11によれば、地盤の悪い場所にも容易に坑口
トンネル11を構築することができる。
In FIG. 9, instead of the foundation 13 and the bottom plate portion 14, an invert 62 in which the base portion and the bottom plate portion are integrated is constructed, and the wellhead main body 12 is attached to the base portion of the invert 62. According to the wellhead tunnel 11 having this structure, the wellhead tunnel 11 can be easily constructed even in a place with bad ground.

【0068】なお、このインバート62の部分を、エレ
メント15と同様な複数のエレメントによって構築して
も良い。つまり、エレメントを水平方向へ互いに接合さ
せ、その内部にコンクリートを充填することにより、エ
レメントをコンクリートによって一体化させてインバー
トとしても良い。
The portion of the invert 62 may be constructed by a plurality of elements similar to the element 15. That is, the elements may be joined to each other in the horizontal direction and the interior thereof may be filled with concrete, so that the elements may be integrated with concrete to form an invert.

【0069】また、上記の例では、平板状の側板21を
有するエレメント15を用いたが、アーチ形状に合わせ
て側板21を湾曲させたエレメント15を用いても良い
ことは勿論である。なおまた、上記の例では、PC鋼線
41の両端側におねじを形成し、これらおねじに定着用
ナット41a、緊張用ナット41bを螺合させたが、一
端側はねじ構造とすることなく、単に定着片部35へ係
止可能な係止部を設けた構造でも良い。
In the above example, the element 15 having the flat side plate 21 is used. However, the element 15 in which the side plate 21 is curved in accordance with the arch shape may be used. In the above example, screws are formed on both ends of the PC steel wire 41, and the fixing nut 41a and the tension nut 41b are screwed to these male screws, but one end has a screw structure. Instead, a structure in which a locking portion that can be simply locked to the fixing piece 35 may be provided.

【0070】また、上記のエレメント15を用いた坑口
トンネル11の他の構築方法として、特に、新規のトン
ネルの坑口トンネル11を構築する場合は、図10に示
すように、内面側における軸方向の複数箇所に、アーチ
型にH鋼等の鋼材を組み立てた支持部材63を設置し、
この支持部材63に支持させながら、エレメント15を
組み立ててコンクリートCを充填して、坑口本体12を
構築することも可能である。
As another method of constructing the wellhead tunnel 11 using the above-described element 15, especially when constructing a wellhead tunnel 11 of a new tunnel, as shown in FIG. At a plurality of locations, support members 63 in which steel materials such as H steel are assembled in an arch shape are installed,
It is also possible to construct the wellhead main body 12 by assembling the element 15 and filling with the concrete C while supporting the support member 63.

【0071】[0071]

【発明の効果】以上、説明したように、本発明の坑口ト
ンネル及びその構築方法によれば、下記の効果を得るこ
とができる。請求項1記載の坑口トンネルによれば、側
部同士を接合することにより組み立てられた箱形の長尺
エレメント内にコンクリートが充填された側壁部と、こ
の側壁部の上端にプレキャスト版を突き合わせた天井部
とから構成されたものであるので、型枠を用いて現場打
ちコンクリートにより構築するものと比較して、型枠及
び型枠を支持する支保工が不要とされ、これにより、型
枠及び支保工の設置、撤去等の極めて煩雑な作業をなく
すことができる。また、エレメントの端部に傾斜を付け
て、坑口トンネルの端部を竹割り構造とすることもでき
る。
As described above, according to the wellhead tunnel and the method of constructing the same according to the present invention, the following effects can be obtained. According to the wellhead tunnel according to the first aspect, the precast plate is abutted against the side wall portion filled with concrete in the box-shaped long element assembled by joining the side portions to each other, and the upper end of the side wall portion. Since it is composed of a ceiling part, compared with the construction using cast-in-place concrete using a formwork, a formwork and a shoring for supporting the formwork are not required. Extremely complicated work such as installation and removal of the shoring works can be eliminated. In addition, the ends of the elements may be inclined so that the ends of the wellhead tunnel have a bamboo split structure.

【0072】請求項2記載の坑口トンネルによれば、エ
レメント同士の接合側がトラス構造とされて、互いのエ
レメント同士にわたってコンクリートが充填された一体
構造とされた側壁部を有するので、高強度化を図ること
ができる。
According to the wellhead tunnel according to the second aspect, the joining side of the elements has a truss structure, and the side walls have an integrated structure in which concrete is filled over the elements, so that the strength is increased. Can be planned.

【0073】請求項3記載の坑口トンネルの構築方法に
よれば、エレメントの側部同士を互いに接合して組み立
てて、エレメント内にコンクリートを充填することによ
り、内部にコンクリートが充填されたエレメントからな
る側壁部を構築し、さらに、側壁部の上部にプレキャス
ト版を突き合わせて配設することにより、極めて容易に
坑口トンネルを構築することができる。これにより、型
枠を用いて現場打ちコンクリートにより坑口トンネルを
構築する場合と比較して、型枠及び型枠を支持する支保
工を不要とすることができ、これにより、型枠及び支保
工の設置、撤去等の極めて煩雑な作業をなくすことがで
き、工期短縮が図られる。
According to the method for constructing a wellhead tunnel according to the third aspect of the present invention, the elements are assembled by joining the sides of the elements to each other, and the element is filled with concrete, whereby the element is made of an element filled with concrete. By constructing the side wall portion and arranging the precast plate on the upper portion of the side wall portion, the wellhead tunnel can be constructed extremely easily. Thereby, compared with the case of constructing a wellhead tunnel by cast-in-place concrete using the formwork, it is possible to eliminate the need for the formwork and the shoring for supporting the formwork. Extremely complicated work such as installation and removal can be eliminated, and the construction period can be shortened.

【0074】請求項4記載の坑口トンネルの構築方法に
よれば、エレメントを外側からPC鋼線によって引っ張
ることにより支持しながら組み上げるので、内側からの
支持を不要とすることができ、内側での支保工を不要と
することができる。つまり、内側の支保工が不要とされ
るので、例えば、既設のトンネルに施工する場合にも、
内側に保護用枠等を設置して車両の走行車線を保護する
ことにより、交通を開放してエレメントの組み立てを行
うことができる。
According to the method of constructing a wellhead tunnel according to the fourth aspect, the element is assembled while being supported by being pulled from the outside by the PC steel wire, so that the support from the inside can be eliminated, and the support on the inside can be eliminated. Work can be eliminated. In other words, since the inner shoring is not required, for example, when constructing an existing tunnel,
By installing a protective frame or the like inside to protect the traveling lane of the vehicle, it is possible to open the traffic and to assemble the element.

【0075】請求項5記載の坑口トンネルの構築方法に
よれば、トンネル内周面に沿ってアーチ型に配設した鋼
材からなる支持部材に支持させるので、エレメントの組
み立て作業の容易化を図ることができ、特に、新規のト
ンネルに構築する場合に有利である。
According to the method for constructing a wellhead tunnel according to the fifth aspect, the element is supported by the support member made of a steel material arranged in an arched shape along the inner peripheral surface of the tunnel, thereby facilitating the assembling work of the element. This is particularly advantageous when constructing a new tunnel.

【0076】請求項6記載の坑口トンネルの構築方法に
よれば、互いに接合させる側部がトラス構造とされたエ
レメントを用いるので、エレメント内にコンクリートを
充填することにより、極めて容易に、組み立てたエレメ
ントの内部全体にコンクリートを行き渡らせることがで
き、エレメント同士が確実に一体化された高強度の側壁
部を有するアーチ型の坑口トンネルを構築することがで
きる。
According to the method for constructing a wellhead tunnel according to the sixth aspect, since the elements to be joined to each other have the truss structure, the elements are extremely easily assembled by filling the elements with concrete. Concrete can be spread all over the inside of the inside, and an arched wellhead tunnel having a high-strength side wall portion in which elements are surely integrated can be constructed.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の実施の形態の坑口トンネルの構成及
び構造を説明する坑口トンネルの斜視図である。
FIG. 1 is a perspective view of a wellhead tunnel illustrating a configuration and a structure of a wellhead tunnel according to an embodiment of the present invention.

【図2】 本発明の実施の形態の坑口トンネルの構成及
び構造を説明する坑口トンネルの断面図である。
FIG. 2 is a cross-sectional view of the wellhead tunnel illustrating the configuration and structure of the wellhead tunnel according to the embodiment of the present invention.

【図3】 本発明の実施の形態の坑口トンネルの構成及
び構造を説明する坑口トンネルの一部の断面図である。
FIG. 3 is a cross-sectional view of a part of the wellhead tunnel illustrating a configuration and a structure of the wellhead tunnel according to the embodiment of the present invention.

【図4】 本発明の実施の形態の坑口トンネルの構成及
び構造を説明する坑口トンネルに用いられるエレメント
の斜視図である。
FIG. 4 is a perspective view of an element used in the wellhead tunnel for describing a configuration and a structure of the wellhead tunnel according to the embodiment of the present invention.

【図5】 本発明の実施の形態の坑口トンネルの構成及
び構造を説明する支持板に設けられた係止片部の平面図
である。
FIG. 5 is a plan view of a locking piece provided on a support plate for explaining the configuration and structure of the wellhead tunnel according to the embodiment of the present invention.

【図6】 本発明の実施の形態の坑口トンネルの構築方
法を説明する組み立て途中の坑口トンネルの一部の断面
図である。
FIG. 6 is a cross-sectional view of a part of the wellhead tunnel during assembly for explaining the method of constructing the wellhead tunnel according to the embodiment of the present invention.

【図7】 本発明の実施の形態の坑口トンネルの構築方
法によって既設のトンネルに坑口トンネルを構築する場
合を説明する坑口トンネルの断面図である。
FIG. 7 is a cross-sectional view of a wellhead tunnel for explaining a case of building a wellhead tunnel in an existing tunnel by the method for building a wellhead tunnel according to the embodiment of the present invention.

【図8】 本発明の実施の形態の坑口トンネルの端部の
構造を説明する坑口トンネルの斜視図である。
FIG. 8 is a perspective view of a wellhead tunnel illustrating an end structure of the wellhead tunnel according to the embodiment of the present invention.

【図9】 本発明の他の実施の形態の坑口トンネルの構
成及び構造を説明する坑口トンネルの断面図である。
FIG. 9 is a sectional view of a wellhead tunnel illustrating a configuration and a structure of a wellhead tunnel according to another embodiment of the present invention.

【図10】 本発明の実施の形態の坑口トンネルの他の
構築方法を説明する坑口トンネルの断面図である。
FIG. 10 is a sectional view of a wellhead tunnel illustrating another method for constructing the wellhead tunnel according to the embodiment of the present invention.

【図11】 一般的なトンネルの構築方法を説明するト
ンネルが構築された地盤の断面図である。
FIG. 11 is a cross-sectional view of a ground where a tunnel is constructed, illustrating a general tunnel construction method.

【図12】 坑口トンネルの従来技術を説明する坑口ト
ンネルを有するトンネルが構築された地盤の断面図であ
る。
FIG. 12 is a cross-sectional view of the ground where a tunnel having a wellhead tunnel is described, illustrating a conventional technique of the wellhead tunnel.

【図13】 坑口トンネルの従来技術を説明する坑口ト
ンネルを有するトンネルが構築された地盤の断面図であ
る。
FIG. 13 is a cross-sectional view of the ground where a tunnel having a wellhead tunnel is described, illustrating a conventional technique of the wellhead tunnel.

【図14】 坑口トンネルの従来技術を説明する坑口ト
ンネルの斜視図である。
FIG. 14 is a perspective view of a wellhead tunnel for explaining a conventional technique of the wellhead tunnel.

【符号の説明】[Explanation of symbols]

11 坑口トンネル 12a 側壁部 12b 天井部 13 基礎 15 エレメント 21 外側の側板(外面) 22 トラス部(トラス構造) 25 鉄筋 41 PC鋼線 51 プレキャスト版 63 支持部材 C コンクリート DESCRIPTION OF SYMBOLS 11 Well tunnel 12a Side wall part 12b Ceiling part 13 Foundation 15 Element 21 Outer side plate (outer surface) 22 Truss part (truss structure) 25 Reinforcing bar 41 PC steel wire 51 Precast plate 63 Support member C Concrete

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 トンネル端部に構築されて、このトンネ
ルの出入口を構成する坑口トンネルであって、 内部に鉄筋が配設された箱形に形成され、側部同士が互
いに接合されて組み立てられる長尺エレメント内にコン
クリートを充填してなる一対の互いに平行に設けられた
側壁部と、 該側壁部の上部に、互いにトンネル周方向へ突き合わせ
て組み立てられるプレキャスト版からなる天井部とから
構成されていることを特徴とする坑口トンネル。
1. A wellhead tunnel constructed at an end of a tunnel and constituting an entrance and exit of the tunnel, formed in a box shape having a reinforcing bar disposed inside, and assembled by joining side parts to each other. It is composed of a pair of parallel side walls formed by filling concrete in a long element, and a ceiling part made of a precast plate that is assembled on top of the side wall parts by abutting each other in a tunnel circumferential direction. Wellhead tunnel.
【請求項2】 前記エレメントは、互いに接合される側
部がトラス構造とされ、互いに接合されたエレメント同
士にわたって前記コンクリートが充填されていることを
特徴とする請求項1記載の坑口トンネル。
2. The wellhead tunnel according to claim 1, wherein said elements are connected to each other in a truss structure, and said concrete is filled over said elements.
【請求項3】 トンネル端部に構築されて、このトンネ
ルの出入口を構成する坑口トンネルの構築方法であっ
て、 内部に鉄筋が配設された箱形の長尺エレメントの側部同
士を互いに接合して組み立て、これらエレメント内にコ
ンクリートを充填して一体化させることにより、一対の
側壁部を互いに平行に構築し、これら側壁部の上端に、
トンネル周方向へ突き合わされるプレキャスト版を組み
立てて天井部を構築することを特徴とする坑口トンネル
の構築方法。
3. A method of constructing a wellhead tunnel constructed at an end of a tunnel and constituting an entrance and exit of the tunnel, wherein side parts of a box-shaped long element in which a reinforcing bar is disposed are joined to each other. By assembling and filling these elements with concrete and integrating them, a pair of side walls are constructed parallel to each other, and at the upper ends of these side walls,
A method for constructing a wellhead tunnel, comprising assembling a precast plate that is to be abutted in a circumferential direction of the tunnel to construct a ceiling.
【請求項4】 前記エレメントを、予め構築した基礎部
分から順に接合してアーチ型に組み立てる際に、前記エ
レメントの外面と前記基礎部分とをPC鋼線によって連
結し、該PC鋼線を緊張させることにより前記エレメン
トを支持することを特徴とする請求項3記載の坑口トン
ネルの構築方法。
4. An outer surface of the element and the base portion are connected to each other by a PC steel wire when the elements are sequentially joined from a pre-constructed base portion and assembled in an arch shape, and the PC steel wire is strained. 4. The method according to claim 3, wherein the element is supported by the support.
【請求項5】 前記エレメントを、トンネル内周面に沿
ってアーチ型に配設した鋼材からなる支持部材に支持さ
せながら予め構築した基礎部分から順に接合して組み立
てることを特徴とする請求項3記載の坑口トンネルの構
築方法。
5. The assembly according to claim 3, wherein the elements are joined in order from a pre-established base portion while being supported by a support member made of a steel material arranged in an arch shape along the inner peripheral surface of the tunnel. The method of constructing a wellhead tunnel as described.
【請求項6】 互いに接合させる側部がトラス構造とさ
れた前記エレメントを組み立て、これらエレメント内に
コンクリートを充填することを特徴とする請求項3〜5
のいずれか1項記載の坑口トンネルの構築方法。
6. The element as claimed in claim 3, wherein said elements having a truss structure on the side to be joined to each other are assembled, and said elements are filled with concrete.
The method for constructing a wellhead tunnel according to any one of the above items.
JP11005816A 1999-01-12 1999-01-12 Pit mouth tunnel and its construction method Pending JP2000204888A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11005816A JP2000204888A (en) 1999-01-12 1999-01-12 Pit mouth tunnel and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11005816A JP2000204888A (en) 1999-01-12 1999-01-12 Pit mouth tunnel and its construction method

Publications (1)

Publication Number Publication Date
JP2000204888A true JP2000204888A (en) 2000-07-25

Family

ID=11621619

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11005816A Pending JP2000204888A (en) 1999-01-12 1999-01-12 Pit mouth tunnel and its construction method

Country Status (1)

Country Link
JP (1) JP2000204888A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100390369B1 (en) * 2000-08-01 2003-07-07 주식회사 경호엔지니어링 종합건축사사무소 Construction method of arch structure of subway or common duct in excavating process
JP2005126917A (en) * 2003-10-21 2005-05-19 Techno Pro Kk Bamboo split type entrance of steel construction
CN102966365A (en) * 2012-05-16 2013-03-13 山西晋城无烟煤矿业集团有限责任公司 Novel air bridge construction method
KR101655217B1 (en) * 2016-06-08 2016-09-07 우경기술주식회사 Construction method for open cutting in tunnel portal area
JP2018122067A (en) * 2017-01-30 2018-08-09 博彬 上村 Arch-shaped concrete stand
CN113565539A (en) * 2021-07-29 2021-10-29 中铁隧道集团一处有限公司 Construction method for preventing initial support side from rebounding of cantilever type cast-in-place side wall of tunnel
WO2023138033A1 (en) * 2022-01-21 2023-07-27 中交四航局第一工程有限公司 Short-bench construction method for weak surrounding rock section of super-large-section tunnel

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100390369B1 (en) * 2000-08-01 2003-07-07 주식회사 경호엔지니어링 종합건축사사무소 Construction method of arch structure of subway or common duct in excavating process
JP2005126917A (en) * 2003-10-21 2005-05-19 Techno Pro Kk Bamboo split type entrance of steel construction
CN102966365A (en) * 2012-05-16 2013-03-13 山西晋城无烟煤矿业集团有限责任公司 Novel air bridge construction method
CN102966365B (en) * 2012-05-16 2015-04-08 山西晋城无烟煤矿业集团有限责任公司 Novel air bridge construction method
KR101655217B1 (en) * 2016-06-08 2016-09-07 우경기술주식회사 Construction method for open cutting in tunnel portal area
JP2018122067A (en) * 2017-01-30 2018-08-09 博彬 上村 Arch-shaped concrete stand
CN113565539A (en) * 2021-07-29 2021-10-29 中铁隧道集团一处有限公司 Construction method for preventing initial support side from rebounding of cantilever type cast-in-place side wall of tunnel
CN113565539B (en) * 2021-07-29 2023-12-15 中铁隧道集团一处有限公司 Construction method for preventing primary support side rebound of tunnel cantilever type cast-in-situ side wall
WO2023138033A1 (en) * 2022-01-21 2023-07-27 中交四航局第一工程有限公司 Short-bench construction method for weak surrounding rock section of super-large-section tunnel

Similar Documents

Publication Publication Date Title
JP6448817B2 (en) PC truss wall structure and construction method thereof
KR101964678B1 (en) Combination structure of pile and copping and girder and method of construction
KR20130113315A (en) A building structure
KR101749959B1 (en) Assembly type arch structure and method for constructing it
JP2008127873A (en) Block out flask, and recess forming method using the same
KR20100125652A (en) A mold for apartment
JP2000204888A (en) Pit mouth tunnel and its construction method
JP6865550B2 (en) How to build silo roof and silo roof structure
JP2006299660A (en) Temporary receiving construction method and temporary receiving structure
KR20200136127A (en) Deck plate wall installation method using underground pavement
KR102296982B1 (en) Transfer Structure Construction Method Using U-shaped Steel Girder
JP3037912B2 (en) Power transmission tower foundation construction method and pillar formwork
JP3044459B2 (en) Tower structure construction method
KR101482523B1 (en) Nodular Box Girder, and Nodular Box Girder Bridge and Constructing Method thereof
KR100557334B1 (en) A Dismonuting Stair Form
JP3878546B2 (en) Construction method of cross girder integrated concrete slab
JPH08135247A (en) Placing form for hopper and construction method of hopper frame using the same
JP2008274567A (en) Circular steel pipe prefabricated bridge and its construction method
JP2002332691A (en) Joint construction between column and beam
JP2000129633A (en) Erection method for bridge floor slab
JP2001146756A (en) Earth-retaining wall and rc synthetic structure
JPH084196A (en) Panel for building
KR102296206B1 (en) Sectionally devided precast culvert box
JP2600531B2 (en) Foundation structure for steel column and its construction method
JPH0483051A (en) Construction of reinforced concrete staircase and staircase handrail precast concrete panel and staircase step form using for this

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20051202

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070921

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20071106

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20080408