KR19990015944U - Bogie for collecting sludge from sedimentation basin - Google Patents

Bogie for collecting sludge from sedimentation basin Download PDF

Info

Publication number
KR19990015944U
KR19990015944U KR2019970029314U KR19970029314U KR19990015944U KR 19990015944 U KR19990015944 U KR 19990015944U KR 2019970029314 U KR2019970029314 U KR 2019970029314U KR 19970029314 U KR19970029314 U KR 19970029314U KR 19990015944 U KR19990015944 U KR 19990015944U
Authority
KR
South Korea
Prior art keywords
rail
trolley
sedimentation basin
sludge
bogie
Prior art date
Application number
KR2019970029314U
Other languages
Korean (ko)
Other versions
KR200164423Y1 (en
Inventor
이정표
Original Assignee
이정표
주식회사 성보기전
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이정표, 주식회사 성보기전 filed Critical 이정표
Priority to KR2019970029314U priority Critical patent/KR200164423Y1/en
Publication of KR19990015944U publication Critical patent/KR19990015944U/en
Application granted granted Critical
Publication of KR200164423Y1 publication Critical patent/KR200164423Y1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D21/00Separation of suspended solid particles from liquids by sedimentation
    • B01D21/02Settling tanks with single outlets for the separated liquid
    • B01D21/04Settling tanks with single outlets for the separated liquid with moving scrapers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D21/00Separation of suspended solid particles from liquids by sedimentation
    • B01D21/18Construction of the scrapers or the driving mechanisms for settling tanks
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D21/00Separation of suspended solid particles from liquids by sedimentation
    • B01D21/24Feed or discharge mechanisms for settling tanks
    • B01D21/245Discharge mechanisms for the sediments

Landscapes

  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Removal Of Floating Material (AREA)
  • Platform Screen Doors And Railroad Systems (AREA)

Abstract

본 고안은, 침전지의 슬러지 수집용 대차에 대한 것으로서, 대차가 편심되지 않고 항상 평행을 유지하는 상태로 전후진이 이루어지고, 레일로부터 구동바퀴가 이탈되지 않도록 하기 위해, 침전지(100)내에 부설된 레일(200)상에서 전후진 이동자재토록 설치되어 바닥에 침전된 슬러지를 배출로(11)측으로 이송시켜주는 대차(300)에 있어, 상기 레일(200)은 정단면이 "ㄷ"자 형상으로 되고 침전지(100)의 양측 내벽(500)에 서로 평행하게 설치되며, 이 레일의 하측 수평부(201) 내면에 외주면이 접촉되어 회전되게 상기 대차(300)의 양측면 전후측에 각각 수직으로 축착되는 구동바퀴(310)들과, 상기 레일(200)의 내측 수직부(202) 내면에 외주면이 접촉되어 회전되게 대차(300)의 양측면 전후에 축착된 구동바퀴(310)들 사이에 위치하게 수평으로 축착되어 이 대차의 편심이동을 방지하여 주는 보조바퀴(320)들을 구비한 침전지의 슬러지 수집용 대차를 제공함에 있다.The present invention is for the sludge collection truck of the sedimentation basin, the rail is placed in the sedimentation basin 100 in order to prevent the driving wheel from being separated from the rail, and the forward and backward is made in the state that the balance is always eccentric and always parallel. In the trolley 300, which is installed to move forward and backward on the 200 and transfers the sludge settled on the floor to the discharge path 11 side, the rail 200 has a front end surface in the shape of "c" and the sedimentation basin. The driving wheels are installed on both inner walls 500 of parallel to each other in parallel to each other, and are vertically condensed on both front and rear sides of the trolley 300 so that the outer circumferential surface is in contact with the inner surface of the lower horizontal portion 201 of the rail. 310 and the outer circumferential surface of the inner vertical portion 202 of the rail 200 is contacted horizontally and horizontally condensed between the driving wheels 310 condensed before and after both sides of the trolley 300 so as to rotate. The balance of this balance A it is the balance for the sludge collected in the clarifier having the wheels 320 to provide that to avoid.

Description

침전지의 슬러지 수집용 대차Bogie for collecting sludge from sedimentation basin

본 고안은 침전지의 슬러지를 수집하는 대차에 관한 것으로, 대차가 전후 이동시 편심에 의해 레일에서 이탈되는 것을 방지하도록 한 것이다.The present invention relates to a trolley for collecting sludge in the sedimentation basin, and to prevent the trolley from being separated from the rail by an eccentricity when moving back and forth.

종래의 슬러지 제거장치인 대차는 실용신안공고 제97-3805호에서 보는 바와 같으며, 도 1은 종래의 슬러지 제거장치인 대차가 설치된 침전지의 개략적인 측면도로서,The conventional sludge removal apparatus is a bogie as shown in Utility Model Publication No. 97-3805, and FIG. 1 is a schematic side view of a sedimentation basin in which a conventional sludge removal apparatus is installed.

침전지(10)의 바닥면에는 후단으로부터 전방의 슬러지 배출로(11) 입구까지 레일(12)이 시설되어 있고.The rail 12 is provided in the bottom surface of the sedimentation basin 10 from the rear end to the entrance of the sludge discharge path 11 in front.

이 레일(12)상에는 대차(20)가 설치되어 구동모터(13)의 작동으로 정역회전되게 축착된 드럼(14)에 감겨지는 견인와이어(15)의 작동으로 전.후진된다.The trolley 20 is installed on the rail 12 and moved forward and backward by the operation of the traction wire 15 wound around the drum 14 which is constricted to be rotated forward and backward by the operation of the drive motor 13.

대차(20)의 전후면에는 제1,2스크레이퍼(30)(30')가 각각 축으로 착설되어 제1,2구동수단에 의해 회동된다.First and second scrapers 30 and 30 'are mounted on the front and rear surfaces of the trolley 20, respectively, and rotated by the first and second driving means.

제1스크레이퍼(30)는 축(31)에 의해 후면 중간부가 대차(20)의 전면에 축착되고, 제2스크레이퍼(30')는 축(31')에 의해 전면 상단부가 대차(20)의 후면에 축착되며, 이들 스크레이퍼(30,30')가 수직 상태일 때 그 하단이 침전지(10)의 바닥면에 접촉하게 된다.The first scraper 30 is affixed to the front surface of the trolley 20 by the shaft 31 and the second scraper 30 'is the rear end of the trolley 20 by the shaft 31' to the upper end of the trolley 20. When the scrapers 30 and 30 'are in a vertical state, their lower ends come into contact with the bottom surface of the sedimentation basin 10.

제1구동수단은 견인와이어(15)에 의해 동작되어 제1스크레이퍼(30)를 회동시켜 주며, 제2구동수단은 이 제1스크레이퍼(30)가 회동되면 함께 동작되어 제2스크레이퍼(30')를 동시에 회동시켜 주게 된다.The first driving means is operated by the traction wire 15 to rotate the first scraper 30, and the second driving means is operated together when the first scraper 30 is rotated to form the second scraper 30 '. Will rotate at the same time.

제1구동수단은, 대차(20)의 상부 중간위치에 축(40)으로 착설되며 견인와이어(15)의 하측에 한바퀴 정도로 감겨져 통과하게 걸어준 구동풀리(41)와 함께 회전되게 축(40)에 착설된 전동풀리(42) 및 대차(20)의 전면 상부 중간위치와 하부 중간위치에 각각 축착된 안내풀리(43)(43')들과 제1스크레이퍼(30)의 상단부 중간 위치에 고정착설한 가동풀리(44) 및 전동풀리(42)의 회전력을 가동풀리(44)에 전달하여 제1스크레이퍼(30)를 회동시켜 주는 전동와이어(45)로 구성된다.The first driving means, the shaft 40 is installed in the upper intermediate position of the trolley 20 and rotated together with the driving pulley 41 wound around the lower side of the towing wire 15 and walked therethrough. The guide pulleys 43 and 43 'fixed to the front upper middle position and the lower middle position of the electric pulley 42 and the trolley 20 mounted on the fixed position in the middle position of the upper end of the first scraper 30, respectively. It consists of an electric wire 45 which transmits the rotational force of the movable pulley 44 and the electric pulley 42 to the movable pulley 44 to rotate the first scraper 30.

또한,구동풀리(41)의 외측면에 적정간격으로 격리 착설한 제동핀(46) (46')들과, 이들 제동핀을 걸어주게 대차(20)의 소정위치에 착설한 제동판(47)으로 되는 제동수단을 설치하여 견인와이어(15)에 의해 구동풀리(41)가 정회전되면 제동핀(46)이 제동판(47)의 선단부 저면에 걸어지며, 반대로 역회전되면 제동핀(46')이 제동판(47)의 선단부 상면에 걸어지게 함으로써, 구동풀리(41)는 이들 제동핀(46)(46')이 제동판(47)에 선택적으로 걸어지는 범위내에서만 회전되게 제어된다.In addition, the braking pins 46 and 46 'which are segregated and installed on the outer surface of the driving pulley 41 at appropriate intervals, and the braking plate 47 which are installed at a predetermined position of the trolley 20 to hang these braking pins. When the driving pulley 41 is rotated forward by the traction wire 15 by installing the braking means, the braking pin 46 is walked on the bottom surface of the tip of the braking plate 47. On the contrary, the braking pin 46 ' ) Is driven to the upper surface of the distal end of the brake plate 47, the drive pulley 41 is controlled to rotate only within the range that these brake pins 46, 46 'is selectively engaged with the brake plate 47.

제동판(47)의 선단부 상.저면은 경사면으로 되게 형성하고 중간부분에는 장공들을 상하로 나란하게 설치하여 이들 장공을 통해 조정볼트를 대차(20)에 체결함으로써 제동판(47)의 위치를 장공의 길이 범위내에서 전후 이동시킬 수 있게 한다.The upper and lower ends of the brake plate 47 are formed to be inclined surfaces, and in the middle part, the long holes are installed side by side up and down, and the adjustment bolts are fastened to the trolley 20 through these holes to position the position of the brake plate 47. It can be moved back and forth within the length range of.

이렇게 하면, 제동핀(46)(46')들이 제동판(47)의 선단부 경사면에 걸어지는 범위가 조정되므로 제1스크레이퍼(30)의 회동범위가 조절된다.In this case, the range in which the brake pins 46 and 46 'are engaged on the inclined surface of the tip of the brake plate 47 is adjusted, so that the rotation range of the first scraper 30 is adjusted.

제2구동수단은, 선단의 제1스크레이퍼(30)의 후면 하부에 결속하고 후단은 제2스크레이퍼(30')의 하단부에 결속한 수개의 연동와이어(50)와 이들 와이어를 걸어주도록 대차(20)의 전면 하부 소정위치에 축착한 안내풀리(51)들로 구성된다.The second driving means is connected to the lower end of the first scraper 30 at the front end and the rear end of the second scraper 30 'to the lower end of the second interlocking wire 50 and the trolley 20 to hang these wires. The guide pulleys 51 are fixed to a predetermined position on the front lower portion of the front side.

한편, 레일(12)의 후단과 전단축 상면에는 제동편(60)(60')을 착설하여 대차(20)의 정위치까지 후진되면 제동편(60)이 뒷바퀴(21)의 앞쪽을 걸어주게 하고, 정위치까지 전진되면 제동편(60')이 앞바퀴(22)의 뒤쪽을 걸어주게 한다.On the other hand, in the rear end of the rail 12 and the upper end of the shear shaft is installed braking pieces (60) (60 ') and back to the correct position of the trolley 20, the braking piece (60) to walk the front of the rear wheel (21) And, if it is advanced to the right position, the braking piece (60 ') is to walk the rear of the front wheel (22).

또한, 제동편(60)은 앞쪽이 완만한 경사면으로 되게하고, 제동편(60')은 뒤쪽이 완만한 경사면으로 되게 함으로써 대차(20)가 후진시에는 뒷바퀴(21)가 전진시에는 앞바퀴(22)가 각기 제동편(60)(60')을 용이하게 넘어갈 수 있게 되어 있었다.In addition, the braking piece 60 makes the front face a gentle slope, and the braking piece 60 'makes the rear face a gentle slope, so that the rear wheel 21 moves forward when the truck 20 retreats. 22) could easily cross the braking pieces 60 (60 '), respectively.

그러나, 종래 대차(20)의 앞뒤바퀴(21,22)가 일자형태의 레일(12)에 설치되어 와이어(15,50)에 의해 이동시 대차(20)의 편심에 의해 레일(12)로부터 대차(20)의 앞뒤바퀴(21,22)가 이탈되는 경우가 많으며 이때에 대차(20)를 제 위치로 복구하기 위해 소요되는 시간 및 경비가 과다 사용 및 지출되는 문제점이 있었다.However, the front and rear wheels 21 and 22 of the conventional trolley 20 are installed on the rails 12 having a straight shape, and the trolley 20 is moved from the rails 12 by the eccentricity of the trolley 20 when moving by the wires 15 and 50. In many cases, the front and rear wheels 21 and 22 of 20 are separated, and there is a problem in that the time and expense required for restoring the balance 20 in place are excessively used and expended.

한편, 침전지(10)의 바닥부분에 상기 레일(12)을 침전지 바닥에 설치공사함에 있어, 콘크리트면이 수평으로 정확하게 맞지 않아 통상적으로 레일(12)을 수평하게 설치한 후 바닥면 전체에 마감몰탈작업을 하여야 하므로 설치공사 가격이 높아지고, 아울러 레일 높이 만큼 바닥이 높아져 침전지 전체의 체적이 감소하는 문제점이 있었다.On the other hand, when installing the rail 12 on the bottom of the sedimentation basin 10 in the installation work on the sedimentation basin, the concrete surface does not fit horizontally exactly, usually after installing the rail 12 horizontally mortar mortar on the entire bottom surface Since the work must be done, the installation cost is high, and the floor is raised by the height of the rail, thereby reducing the volume of the entire sedimentation basin.

본 고안은 종래의 슬러지 제거장치인 대차의 문제점을 개선하여 고안한 것으로서, 그 목적은 침전지 슬러지 제거장치의 대차가 편심에 의해 레일에서 이탈되지 않고 슬러지 수집이 원활하게 이루어지도록 하는 것이다.The present invention is designed to improve the problem of the conventional sludge removal device, the purpose of the sludge collection sludge removal device is to ensure that the sludge collection is made smoothly without being separated from the rail by the eccentricity.

또한, 본 고안의 다른 목적은 레일의 설치비용과 복구비를 낮출 수 있도록 설치하는 것이다.In addition, another object of the present invention is to install to reduce the installation cost and recovery cost of the rail.

본 고안의 이러한 목적들은 침전지의 측벽에 "ㄷ"자형 레일로 개선하여 설치하고, 이 레일에 삽입되어 회동되는 구동바퀴와 보조바퀴를 대차의 프레임 측면에 축착함으로서 달성된다.This object of the present invention is achieved by retrofitting and installing a "c" shaped rail on the side wall of the sedimentation basin, and affixing the driving wheel and the auxiliary wheel inserted into the rail to the frame side of the bogie.

도 1은 종래의 대차가 설치된 침전지의 개략적인 측면도,1 is a schematic side view of a sedimentation basin in which a conventional bogie is installed;

도 2는 본 고안의 대차가 레일에 설치된 상태를 보인 평면도,Figure 2 is a plan view showing a state in which the trolley of the present invention is installed on the rail,

도 3은 동 정면도,3 is a front view of the same,

도 4는 동 측면도,4 is a side view of the same,

도 5는 본 고안 대차의 구동바퀴와 보조바퀴가 레일에 결합된 상태를 보인 단면도,5 is a cross-sectional view showing a state in which the driving wheel and the auxiliary wheel of the present invention trolley is coupled to the rail,

도 6은 본 고안의 대차가 레일에 설치된 상태를 보인 분리 사시도.Figure 6 is an exploded perspective view showing a state in which the trolley of the present invention is installed on the rail.

*도면의 주요부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

100 : 침전지 200 : 레일100: settler 200: rail

210 : 레일지지대 300 : 대차210: rail support 300: bogie

310 : 구동바퀴 320 : 보조바퀴310: driving wheel 320: auxiliary wheel

400 : 스크레이퍼 500 : 내벽400: scraper 500: inner wall

이하, 본 고안의 구성을 도면에 의하여 상세히 설명하면 다음과 같다.Hereinafter, the configuration of the present invention in detail with reference to the drawings.

제2∼4도는 본 고안의 대차가 레일에 설치된 상태의 평면도, 정면도, 측면도를 보인 것으로, 침전지(100) 내에 부설된 레일(200)상에서 전후진 회동자재토록 설치되어 바닥에 침전된 슬러지를 배출로(11)측으로 이송시켜주는 대차(300)에 있어서, 상기 레일(200)은 정단면이 "ㄷ"자 형상으로 되고 침전지(100)의 양측 내벽(500)에 서로 평행하게 설치되며, 이 레일의 하측 수평부(201) 내면에 외주면이 접촉되어 회전되게 상기 대차(300)의 양측면 전후측에 각각 수직으로 축착되는 구동바퀴(310)들과, 상기 레일(200)의 내측 수직부(202) 내면에 외주면이 접촉되어 회전되게 대차(300)의 양측면 전후에 축착된 구동바퀴(310)들 사이에 위치하게 수평으로 축착되어 이 대차의 편심이동을 방지하여주는 보조바퀴(320)들을 구비되어 있다.2 to 4 are a plan view, a front view, and a side view of the truck of the present invention installed on the rail, and installed on the rails 200 installed in the sedimentation basin 100 so as to be rotated back and forth and settled on the floor. In the trolley 300 for transporting to the discharge path 11 side, the rail 200 has a front end surface of the "c" shape and is installed in parallel to each other on the inner wall 500 of both sides of the sedimentation basin 100. Driving wheels 310 which are vertically condensed on both front and rear sides of the trolley 300 so that the outer circumferential surface is in contact with the inner surface of the lower horizontal portion 201 of the rail, and the inner vertical portion 202 of the rail 200. ) Is provided with auxiliary wheels 320 which are horizontally condensed to be positioned between the driving wheels 310 which are condensed before and after both sides of the trolley 300 so that the outer circumferential surface is in contact with the inner surface to prevent eccentric movement of the trolley. have.

상기 대차(300)에는, 도 5와 같이, 구동면이 상기 레일(200)의 내측 하면과 맞닿으며 대차의 수평축에 축착되어 구동되는 구동바퀴와, 구동면이 상기 레일의 내측 수직면과 맞닿으며 대차의 수직축에 축착되어 대차(300)의 편심을 잡아주는 보조바퀴(320)가 구비되어 있다.In the trolley 300, as shown in FIG. 5, a driving wheel is brought into contact with the inner bottom surface of the rail 200 and is driven by being condensed on the horizontal axis of the trolley, and the driving surface is brought into contact with the inner vertical surface of the rail. Auxiliary wheel 320 is fixed to the vertical axis of the cart 300 to hold the eccentricity.

여기서, 대차(300)가 전후진시 스크레이퍼(400)가 침전지(100)의 바닥에 쌓인 슬러지를 밀어내게 되는데 대차(300)의 좌우측에 쌓인 슬러지의 양에 따라 대차가 한쪽으로 편심되어도 보조바퀴(320)가 레일(200)에 접촉회동함에 따라, 대차가 편심되지 않고 구동바퀴(310)가 원활하게 레일(200)을 따라 회동하게 된다.Here, when the trolley 300 moves forward and backward, the scraper 400 pushes the sludge accumulated on the bottom of the sedimentation basin 100, even if the trolley is eccentric to one side according to the amount of sludge accumulated on the left and right sides of the trolley 300. As the contact pivots on the rail 200, the bogie is not eccentric and the driving wheel 310 smoothly rotates along the rail 200.

이와 같이 본 고안 침전지의 슬러지 수집용 대차(300)는, 침전지(100) 양측 내벽(500)에 설치된 레일지지대(210)에 고정된 "ㄷ"자형 레일(200)과 이 레일(200)에 삽입되어 구동되는 구동바퀴(310)와 대차(300)의 편심을 잡아주는 보조바퀴(320)를 대차(300)의 양측 프레임에 축착함으로서, 대차(300)의 이동시 편심에 의해 레일(200)로부터 이탈되는 현상이 일어나지 않았으며, 또한 레일(200)을 침전지(100)의 바닥면에 설치하지 않고 침전지의 양측 내벽(500)에 설치된 레일지지대(210)에 설치함으로서, 침전지(100) 바닥 공사시 레일(200)의 높이 만큼의 공간을 더 확보할 수 있는 효과가 있으며, 레일(200) 설치에 구애받지 않고 바닥면 공사가 쉽게 이루어져 레일 설치 및 복구에 따른 시간 및 비용을 절감시키는 효과가 있다.Thus, sludge collection trolley 300 of the present invention sedimentation basin, the "c" shaped rail 200 fixed to the rail support 210 installed on both inner walls 500 of the sedimentation basin 100 and inserted into the rail 200. By driving the wheels 310 and the auxiliary wheels 320 which hold the eccentricity of the trolley 300 to both sides of the trolley 300, thereby being separated from the rail 200 by the eccentricity when the trolley 300 moves. The phenomenon does not occur, and also by installing the rail 200 on the rail support 210 installed on both inner walls 500 of the sedimentation basin without installing the bottom surface of the sedimentation basin 100, There is an effect that can secure more space as much as the height of 200, the floor work is easily made irrespective of the rail 200 installation has the effect of reducing the time and cost of rail installation and repair.

Claims (2)

침전지(100) 내에 부설된 레일(200)상에서 전후진 이동자재토록 설치되어 바닥에 침전된 슬러지를 배출로(11)측으로 이송시켜주는 대차(300)에 있어서, 상기 레일(200)은 정단면이 "ㄷ"자 형상으로 되고 침전지(100)의 양측 내벽(500)에 서로 평행하게 설치되며, 이 레일의 하측 수평부(201) 내면에 외주면이 접촉되어 회전되게 상기 대차(300)의 양측면 전후측에 각각 수직으로 축착되는 구동바퀴(310)들과, 상기 레일(200)의 내측 수직부(202) 내면에 외주면이 접촉되어 회전되게 대차(300)의 양측면 전후에 축착된 구동바퀴(310)들 사이에 위치하게 수평으로 축착되어 이 대차의 편심이동을 방지하여 주는 보조바퀴(320)들을 구비하여되는 것을 특징으로 하는 침전지의 슬러지 수집용 대차.In the trolley 300 which is installed to move forward and backward on the rail 200 installed in the sedimentation basin 100 to transfer the sludge deposited on the floor to the discharge path 11 side, the rail 200 has a front end face. It is formed in a "c" shape parallel to each other on the inner wall 500 of both sides of the sedimentation basin 100, the outer circumferential surface of the lower horizontal portion 201 of the rail in contact with the inner and outer sides of the bogie 300 to rotate Driving wheels 310 which are respectively vertically condensed to the outer wheels, and outer wheels contacting the inner circumferential surface of the inner vertical part 202 of the rail 200 in contact with each other, and the driving wheels 310 condensed before and after both sides of the trolley 300. Sludge collecting bogie of the sedimentation basin characterized in that it is provided with auxiliary wheels (320) which are horizontally squeezed in between to prevent eccentric movement of the bogie. 제1항에 있어서, 보조바퀴(320)는 복수로 축착 설치되는 것을 특징으로 하는 침전지의 슬러지 수집용 대차.The trolley for sludge collection of the sedimentation basin of claim 1, wherein the auxiliary wheel (320) is installed condensed in plurality.
KR2019970029314U 1997-10-22 1997-10-22 A rail-car for collecting deposited sludge KR200164423Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2019970029314U KR200164423Y1 (en) 1997-10-22 1997-10-22 A rail-car for collecting deposited sludge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2019970029314U KR200164423Y1 (en) 1997-10-22 1997-10-22 A rail-car for collecting deposited sludge

Publications (2)

Publication Number Publication Date
KR19990015944U true KR19990015944U (en) 1999-05-15
KR200164423Y1 KR200164423Y1 (en) 2000-01-15

Family

ID=19512362

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2019970029314U KR200164423Y1 (en) 1997-10-22 1997-10-22 A rail-car for collecting deposited sludge

Country Status (1)

Country Link
KR (1) KR200164423Y1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20180078579A (en) * 2016-12-30 2018-07-10 엔탑컨버전스 주식회사 Washing mechanism assembly of swash plate in settling tank for water treatment system
KR102126737B1 (en) * 2019-09-26 2020-06-25 주식회사 대성환경건설 Sludge collector for circular clarifier

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20180078579A (en) * 2016-12-30 2018-07-10 엔탑컨버전스 주식회사 Washing mechanism assembly of swash plate in settling tank for water treatment system
KR102126737B1 (en) * 2019-09-26 2020-06-25 주식회사 대성환경건설 Sludge collector for circular clarifier

Also Published As

Publication number Publication date
KR200164423Y1 (en) 2000-01-15

Similar Documents

Publication Publication Date Title
JP2002348081A (en) Conveyer for people provided with step bodies directly driven, and step body therefor
KR200164423Y1 (en) A rail-car for collecting deposited sludge
RU2514311C1 (en) Parking device
KR100889473B1 (en) Underwater carriage type sludge collector
KR200371397Y1 (en) Truck of sludge collector for prevention of derailment
KR970003804Y1 (en) Scrapping device in a settling basin
CN212561049U (en) Road surface leveling device for highway construction
CN212103562U (en) Road leveling device is used in municipal works construction
CN210598304U (en) Hydraulic parking equipment convenient to park
CN108221838B (en) Track removal of impurities, snow removing trolley
KR200359153Y1 (en) An underwater cart for sludge collector
KR100232721B1 (en) Apparatus for removing sludge in settling tank
KR930002433Y1 (en) Sludge remover
KR0138262Y1 (en) Sludge Removal Device of Sedimentation Basin
JP3900750B2 (en) Transportation equipment using mobile objects
CN218862221U (en) Embedded road parking device
KR0123310Y1 (en) Sludge scraper of sedimentation basin
JP2000070612A (en) Sludge scraping apparatus
KR100195791B1 (en) Parking apparatus
CN214763526U (en) Double-irrigation linkage mud scraper
CN219839062U (en) Prefabricated component conveying device
JPH071333Y2 (en) Vehicle towing device
KR101154020B1 (en) Apparatus charging battery of rail bike
KR200460499Y1 (en) Underwater cart for sludge collecting
KR970003805Y1 (en) Scrapping device in a settling basin

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20101006

Year of fee payment: 12

LAPS Lapse due to unpaid annual fee