KR102625646B1 - construction method for falling rock prevention fence using wire ring - Google Patents

construction method for falling rock prevention fence using wire ring Download PDF

Info

Publication number
KR102625646B1
KR102625646B1 KR1020210186302A KR20210186302A KR102625646B1 KR 102625646 B1 KR102625646 B1 KR 102625646B1 KR 1020210186302 A KR1020210186302 A KR 1020210186302A KR 20210186302 A KR20210186302 A KR 20210186302A KR 102625646 B1 KR102625646 B1 KR 102625646B1
Authority
KR
South Korea
Prior art keywords
wiring
net
beams
forming step
rope
Prior art date
Application number
KR1020210186302A
Other languages
Korean (ko)
Other versions
KR20230096629A (en
Inventor
나재술
Original Assignee
나재술
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 나재술 filed Critical 나재술
Priority to KR1020210186302A priority Critical patent/KR102625646B1/en
Publication of KR20230096629A publication Critical patent/KR20230096629A/en
Application granted granted Critical
Publication of KR102625646B1 publication Critical patent/KR102625646B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F7/00Devices affording protection against snow, sand drifts, side-wind effects, snowslides, avalanches or falling rocks; Anti-dazzle arrangements ; Sight-screens for roads, e.g. to mask accident site
    • E01F7/04Devices affording protection against snowslides, avalanches or falling rocks, e.g. avalanche preventing structures, galleries
    • E01F7/045Devices specially adapted for protecting against falling rocks, e.g. galleries, nets, rock traps
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16GBELTS, CABLES, OR ROPES, PREDOMINANTLY USED FOR DRIVING PURPOSES; CHAINS; FITTINGS PREDOMINANTLY USED THEREFOR
    • F16G11/00Means for fastening cables or ropes to one another or to other objects; Caps or sleeves for fixing on cables or ropes
    • F16G11/03Means for fastening cables or ropes to one another or to other objects; Caps or sleeves for fixing on cables or ropes incorporating resiliently-mounted members for attachment of the cable end
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

본 발명은 와이어링을 이용한 낙석방지책 시공방법에 관한 것으로, 와이어링로프로 다수개의 와이어링을 형성하되 상하를 결합고리로 연결하고 좌우를 체결클립으로 체결하여 와이어링넷을 형성하고 H빔 사이에 와이어링넷을 결합하는 와이어링넷 형성단계와, H빔 사이 상측에 횡으로 다수 가닥 설치하는 차단와이어로프를 형성하는 차단와이어로프 형성단계, 및 H빔 사이 차단망을 결합하는 완성단계로 구성하므로, 다수개의 와이어링으로 인하여 수축 및 팽창이 용이하여 낙석으로 인한 충격에너지를 효율적으로 흡수하여 낙석의 도로침입을 억제할 뿐만 아니라 시설을 보호함과 동시에 수명을 연장할 수 있으며 각각의 와이어링넷을 교체할 수 있어 훼손부위를 신속하게 교체할 수 있도록 함과 동시에 와이어링넷의 조립이 용이하고 견고한 결합상태를 유지하므로 비용을 최소화하면서도 고품위의 낙석방지책을 제공하므로 낙서방지효율을 향상시키는 것이다.The present invention relates to a method of constructing a rockfall prevention system using wiring. A plurality of wiring rings are formed with wiring ropes, the top and bottom are connected with coupling rings, and the left and right sides are fastened with fastening clips to form a wiring net, and a wire is placed between H beams. It consists of a wiring net forming step that combines ring nets, a blocking wire rope forming step that forms multiple blocking wire ropes installed horizontally on the upper side between H beams, and a completion step of combining blocking networks between H beams, so there are multiple The wiring makes it easy to contract and expand, effectively absorbing impact energy from falling rocks, preventing falling rocks from intruding into the road, protecting facilities and extending the lifespan, and each wiring net can be replaced. It allows quick replacement of damaged parts, makes it easy to assemble the wiring net, and maintains a solid connection, thereby minimizing costs and providing high-quality rockfall prevention measures, thereby improving graffiti prevention efficiency.

Description

와이어링을 이용한 낙석방지책 시공방법{construction method for falling rock prevention fence using wire ring} Construction method for falling rock prevention fence using wire ring}

본 발명은 와이어링을 이용한 낙석방지책 시공방법에 관한 것으로, 상세하게는 낙석으로부터 발생하는 충격에너지를 효율적으로 흡수하여 낙석의 도로 침입을 억제하는 와이어링을 이용한 낙석방지책에 관한 것이다.The present invention relates to a method of constructing a rockfall prevention measure using wiring, and more specifically, to a rockfall prevention measure using wiring that efficiently absorbs impact energy generated from falling rocks and suppresses the intrusion of fallen rocks into the road.

일반적으로 낙석이 우려되는 지역에는 낙석방지책을 설치하여 사면에서 발생할 수 있는 낙석으로부터 안전하게 도로를 확보할 수 있도록 하였다.In general, rockfall prevention measures were installed in areas where falling rocks were a concern to ensure roads were safe from falling rocks that could occur on slopes.

이러한 종래의 낙석방지책은 도로의 일측에 콘크리트 기초를 형성하고 여기에 일정간격으로 H-빔을 입설한 다음 H-빔에 피복철선으로된 차단망을 횡으로 길게 설치한 다음 이를 좌우 측에서 잡아당겨 팽팽한 상태에서 각각의 H-빔에 고정시키고 다시 횡으로 와이어로프를 다수층으로 형성하여 낙석을 차단하도록 하였다.This conventional rockfall prevention measure forms a concrete foundation on one side of the road, installs H-beams at regular intervals on this, and then installs a barrier net made of covered wire horizontally on the H-beams and then pulls it from the left and right sides. It was fixed to each H-beam in a taut state, and multiple layers of wire rope were formed laterally to block falling rocks.

그러나 이러한 종래의 낙석방지책은 낙석발생 후 복구할 때 횡으로 형성된 차단망과 와이어로프를 전체를 교체하여야 하므로 신속한 복구가 불가능하고 교체작업 또한 번거로울 뿐만 아니라 최초 시공할 때 시공기간이 장기간 소요될 뿐만 아니라 이로 인하여 코스트가 상승하는 문제점이 있었다.However, these conventional rockfall prevention measures require the entire horizontal barrier net and wire rope to be replaced when recovering after a rockfall, making rapid recovery impossible. Not only is the replacement work cumbersome, but the construction period is long at the time of initial construction. As a result, there was a problem of rising costs.

이로 인하여 본 출원인은 상기한 문제점을 해소하기 위하여 선출원한 특허 등록 제10-643664호(명칭: 네트를 이용한 낙석방지책)가 있으나 H-빔과 H-빔 사이에 개별적으로 설치하여 상기한 문제점을 해소하고 부분적으로 보수 및 설치할 수 있도록 하였으나 낙서에 따른 충격에너지를 흡수하여 도로 침입을 억제하는 데는 한계가 있어 지지력과 충격에너지를 보다 효율적으로 제어할 수 있는 기술의 개발이 지속적으로 요구되어 왔다.Due to this, the present applicant has previously applied for patent registration No. 10-643664 (name: Rockfall prevention measure using net) to solve the above-mentioned problem, but the above-mentioned problem is solved by installing it separately between H-beams and H-beams. However, there is a limit to preventing road intrusion by absorbing the impact energy caused by graffiti, so the development of technology that can control bearing capacity and impact energy more efficiently has been continuously required.

따라서 본 발명의 주목적은 낙석으로 발생하는 충격에너지를 효율적으로 흡수하여 낙석차단 효과를 극대화하므로 안전사고의 발생을 방지할 수 있도록 하는 와이어링을 이용한 낙석방지책 시공방법을 제공하는 데 있다.Therefore, the main purpose of the present invention is to provide a rockfall prevention construction method using wiring that efficiently absorbs the impact energy generated by falling rocks and maximizes the rockfall blocking effect, thus preventing the occurrence of safety accidents.

본 발명의 다른 목적은 지주 사이에 와이어로프를 단위개념으로 각각 설치하되 지지력을 극대화할 수 있도록 함과 동시에 간편하게 설치하므로 공사기간을 단축할 수 있도록 하는 와이어링을 이용한 낙석방지책 시공방법을 제공하는 데 있다.Another object of the present invention is to provide a rockfall prevention construction method using wiring, which installs wire ropes as a unit between struts to maximize bearing capacity and at the same time shortens the construction period by making installation simple. there is.

본 발명의 다른 목적은 낙석방지책의 훼손시 부분보수가 용이하고 이를 신속하게 보수할 수 있도록 하는 와이어링을 이용한 낙석방지책 시공방법을 제공하는 데 있다.Another object of the present invention is to provide a method of constructing a rockfall prevention measure using wiring, which allows for easy partial repair and rapid repair when the rockfall prevention measure is damaged.

상기한 목적을 달성하기 위하여 본 발명의 와이어링을 이용한 낙석방지책 시공방법은 와이어링로프로 다수개의 와이어링을 형성하되 상하를 결합고리로 연결하고 좌우를 체결클립으로 체결하여 와이어링넷을 형성하고 H빔 사이에 와이어링넷을 결합하는 와이어링넷 형성단계와, H빔 사이 상측에 횡으로 다수 가닥 설치하는 차단와이어로프를 형성하는 차단와이어로프 형성단계, 및 H빔 사이 차단망을 결합하는 완성단계로 구성함을 그 기술적 구성상 기본 특징으로 한다.In order to achieve the above object, the method of constructing a rockfall prevention system using wiring of the present invention forms a plurality of wirings with wiring ropes, connects the top and bottom with connecting rings, and fastens the left and right sides with fastening clips to form a wiring net. It consists of a wiring net forming step of combining wiring nets between beams, a blocking wire rope forming step of forming multiple blocking wire ropes installed horizontally on the upper side between H beams, and a completion step of combining blocking nets between H beams. This is a basic feature of its technical composition.

따라서 본 발명의 와이어링을 이용한 낙석방지책 시공방법은 다수개의 와이어링으로 인하여 수축 및 팽창이 용이하여 낙석으로 인한 충격에너지를 효율적으로 흡수하여 낙석의 도로침입을 억제할 뿐만 아니라 시설을 보호함과 동시에 수명을 연장할 수 있으며 각각의 와이어링넷을 교체할 수 있어 훼손부위를 신속하게 교체할 수 있도록 함과 동시에 와이어링넷의 조립이 용이하고 견고한 결합상태를 유지하므로 비용을 최소화하면서도 고품위의 낙석방지책을 제공하므로 낙서방지효율을 극대화하는 효과가 있는 것이다.Therefore, the rockfall prevention construction method using the wiring of the present invention is easy to contract and expand due to the multiple wiring, so it not only suppresses the intrusion of fallen rocks into the road by efficiently absorbing the impact energy caused by falling rocks, but also protects the facility. Lifespan can be extended and each wiring net can be replaced, allowing damaged parts to be replaced quickly. At the same time, wiring nets are easy to assemble and maintain a solid connection, providing high-quality rockfall prevention measures while minimizing costs. Therefore, it has the effect of maximizing graffiti prevention efficiency.

도 1 은 본 발명에 따른 와이어링을 이용한 낙석방지책 시공방법을 설명하기 위한 설치상태를 나타낸 사시도.
도 2 는 본 발명에 따른 와이어링을 이용한 낙석방지책 시공방법을 설명하기 위한 설치상태를 확대하여 나타낸 정면도.
도 3 은 본 발명에 따른 와이어링을 이용한 낙석방지책 시공방법을 설명하기 위한 와이어링넷을 나타낸 정면도.
도 4 는 본 발명에 따른 와이어링을 이용한 낙석방지책 시공방법을 설명하기 위한 와이어링넷을 나타낸 확대도.
도 5 는 본 발명에 따른 와이어링을 이용한 낙석방지책 시공방법을 설명하기 위한 체결클립 분리상태를 나타낸 사시도.
도 6 은 본 발명에 따른 와이어링을 이용한 낙석방지책 시공방법을 설명하기 위한 체결클립 결합상태를 나타낸 사시도.
도 7 은 본 발명에 따른 와이어링을 이용한 낙석방지책 시공방법을 설명하기 위해 나타낸 사시도.
Figure 1 is a perspective view showing the installation state to explain the construction method of rockfall prevention using wiring according to the present invention.
Figure 2 is an enlarged front view showing the installation state to explain the construction method of rockfall prevention using wiring according to the present invention.
Figure 3 is a front view showing a wiring net for explaining the method of constructing a rockfall prevention measure using wiring according to the present invention.
Figure 4 is an enlarged view showing a wiring net for explaining the method of constructing a rockfall prevention measure using wiring according to the present invention.
Figure 5 is a perspective view showing a state of separation of fastening clips to explain the method of constructing a rockfall prevention measure using wiring according to the present invention.
Figure 6 is a perspective view showing a fastening clip combination state to explain the construction method of rockfall prevention using wiring according to the present invention.
Figure 7 is a perspective view showing a method of constructing a rockfall prevention measure using wiring according to the present invention.

이하 첨부한 도면을 참조하면서 본 발명의 실시 예를 상세하게 설명하면 다음과 같다.Hereinafter, an embodiment of the present invention will be described in detail with reference to the attached drawings.

도 1 내지 도 7 에 나타낸 바와 같이, 본 발명의 와이어링을 이용한 낙석방지책(100)은 H빔(111)을 일정간격으로 세워 설치하는 지주 설치단계와; 상기 지주 설치단계가 완료되면, 와이어링로프(121)로 다수개의 와이어링(122)을 형성하되 상하를 결합고리(123)로 연결하고 좌우를 체결클립(140)으로 체결하여 와이어링넷(120)을 형성하고 H빔(111) 사이에 와이어링넷(120)을 결합하는 와이어링넷 형성단계와; 상기 와이어링넷 형성단계가 완료되면, H빔(111) 사이 상측에 횡으로 다수 가닥 설치하는 차단와이어로프(130)를 형성하는 차단와이어로프 형성단계; 및 상기 차단와이어로프 형성단계가 완료되면, H 빔(111) 사이 차단망(150)을 결합하는 완성단계로 구성한다.As shown in Figures 1 to 7, the rockfall prevention measure 100 using the wiring of the present invention includes a support installation step of erecting and installing H beams 111 at regular intervals; When the support installation step is completed, a plurality of wirings 122 are formed with the wiring rope 121, and the top and bottom are connected with coupling rings 123 and the left and right sides are fastened with fastening clips 140 to form a wiring net 120. A wiring net forming step of forming and combining the wiring net 120 between the H beams 111; When the wiring net forming step is completed, a blocking wire rope forming step of forming a plurality of blocking wire ropes 130 installed horizontally on the upper side between the H beams 111; And when the blocking wire rope forming step is completed, it consists of a completion step of combining the blocking net 150 between the H beams 111.

상기 지주 설치단계는 사면의 도로변 등에 설치하는 것으로, 콘크리트기단(114)에 H빔(111)의 하측 매설부(112)를 일정간격으로 견고하게 세워 다수개 설치하되 H빔(111)의 상측 절곡부(113)를 도로 측으로 기울어지도록 설치한다.The prop installation step is to install a plurality of lower embedded parts 112 of the H beam 111 on the concrete base 114 at regular intervals, and the upper side of the H beam 111 is bent. Part 113 is installed tilted toward the road.

상기 와이어링넷 형성단계는 와이어링로프(121)를 파형으로 형성하여 파형의 상측와 하측를 반원형으로 형성하되 이러한 파형을 순차적으로 연속 반복하여 형성하도록 하는 것으로, 제1열 와이어링로프(121)의 하부 반원 중심과 제2열 상부 반원 중심의 결합고리(123)로 연결하도록 하고 좌우 측을 교차하도록 하여 다수개의 와이어링(122)을 순차적으로 형성하도록 하되, 좌우 측을 교차부분을 체결클립(140)으로 체결하여 와이어링로프(121)에 와이어링(122)을 일정 간격으로 형성함이 바람직하다.The wiring net forming step is to form the wiring rope 121 into a wave shape, forming the upper and lower sides of the wave shape into a semicircular shape, and forming this wave shape by sequentially repeating the lower semicircle of the first row wiring rope 121. The center and the second row are connected by a connecting ring (123) at the center of the upper semicircle, and a plurality of wiring (122) is sequentially formed by crossing the left and right sides, and the intersection portions on the left and right sides are connected with fastening clips (140). It is preferable to fasten the wiring rope 121 to form the wiring 122 at regular intervals.

나아가, 제1,2열 와이어링로프(121)는 한 가닥으로 형성하여 절단부분을 최소화하도록 하되, 와이어링로프(121)를 제3열에서 임의의 제n열까지 상기와 같이 반복 형성하여 원하는 크기로 형성하도록 하거나 일정한 단위면적으로 형성하여 다양한 체결수단으로 연결하여 원하는 크기나 길이로 형성할 수 있도록 한다.Furthermore, the first and second row wiring ropes 121 are formed as a single strand to minimize the cut portion, but the wiring rope 121 is repeatedly formed as described above from the third row to an arbitrary nth row to achieve the desired size. It can be formed to a certain size or a certain unit area and connected with various fastening means to form a desired size or length.

더욱이, 상기와 같이 와이어링로프(121)로 다수개의 와이어링(122)을 원하는 사이즈로 형성한 다음 테두리에 외각와이어로프(125)를 체결하되 상기와 같이 결합고리(123)로 결합하거나 체결클립(140)으로 결합할 수 있으나 간격유지 등을 위해 체결클립(143)으로 결합함이 바람직하다.Moreover, as described above, a plurality of wiring rings 122 are formed to a desired size using the wiring rope 121, and then the outer wire rope 125 is fastened to the edge, but is combined with a connecting ring 123 or a fastening clip as described above. It can be coupled with (140), but it is preferable to be coupled with a fastening clip (143) to maintain the gap.

아울러 테두리에 형성시킨 외각와이어로프(125)에는 클립 등 통상의 결합수단(124)을 연결하여 H빔(111)에 와이어링넷(120)을 견고하게 결합할 수 있도록 하는 것이다.In addition, a conventional coupling means 124 such as a clip is connected to the outer wire rope 125 formed on the edge, so that the wiring net 120 can be firmly coupled to the H beam 111.

특히 체결클립(140)은 삽입용 결합홈(141)을 형성하여 사전에 와이어링로프(121)에 일정 간격으로 끼워 형성하되 좌우 한 쌍으로 형성하여 대응 면에 슬라이드돌기(142)와 슬라이드홈(143)을 형성하여 원활하고 견고하게 결합할 수 있도록 하는 것으로, 와이어링로프(121)를 좌우 교차 부분을 체결클립(140)으로 결합하여 견고하게 고정함과 동시에 원형의 와이어링(122)을 순차적으로 정확하게 형성할 수 있도록 할 뿐만 아니라 체결클립(140)을 직선상으로 슬라이딩시켜 결합하고 결합 후 원형 상태를 유지하는 와이어링(122)에 의해 분리 우려 없이 견고한 결합 상태를 유지할 수 있는 것이다.In particular, the fastening clip 140 is formed by forming a coupling groove 141 for insertion and inserted into the wiring rope 121 at regular intervals in advance, but is formed as a pair on the left and right, and has a slide protrusion 142 and a slide groove ( 143) is formed to enable smooth and solid connection, and the wiring rope 121 is firmly fixed by combining the left and right intersection parts with the fastening clip 140, and at the same time, the circular wiring 122 is sequentially connected. Not only can it be formed accurately, but it can also be coupled by sliding the fastening clip 140 in a straight line and maintain a solid coupling state without fear of separation by the wiring 122 that maintains its circular state after coupling.

상기 차단와이어로프 형성단계는 H빔(111)의 상부 측에 횡으로 다수 가닥의 형성하여 통상의 결합수단(131)으로 H빔(111)에 결합하도록 하되 와이어링넷(120)의 상측에 형성하도록 함이 바람직하다.In the step of forming the blocking wire rope, a plurality of strands are formed horizontally on the upper side of the H-beam 111 to be coupled to the H-beam 111 using a normal coupling means 131, but are formed on the upper side of the wiring net 120. It is desirable to do so.

상기 완성단계는 와이어링넷(120) 및 차단와이어로프(130)을 설치함과 동시에 통상의 차단망(150)과 함께 H빔(111)에 설치하도록 한다.In the completion step, the wiring net 120 and the blocking wire rope 130 are installed and simultaneously installed on the H beam 111 together with the normal blocking net 150.

이러한 본 발명의 작용을 설명하면 다음과 같다.The operation of the present invention is explained as follows.

먼저, 도로변 등 설치위치에 콘크리트기단(114)을 형성함과 동시에 H빔(111)을 세워 일정간격으로 다수개 설치하여 견고하게 고정시킨 다음 H빔(111) 사이에 설계에 따라 와이어링넷(120) 또는 와이어링넷(120)과 차단와이어로프(130)을 복합적으로 결합한다.First, a concrete base 114 is formed at an installation location such as a roadside, and at the same time, a plurality of H-beams 111 are erected at regular intervals to be firmly fixed, and then a wiring net 120 is installed between the H-beams 111 according to the design. ) or complexly combine the wiring net 120 and the blocking wire rope 130.

이때 와이어링넷(120) 또는 와이어링넷(120)과 차단와이어로프(130)를 차단망(150)과 함께 설치하는 것으로, 다수개의 와이어링(122)으로 인하여 수축 및 팽창이 용이하여 낙석으로 인한 충격에너지를 효율적으로 흡수하여 낙석의 도로침입을 억제할 뿐만 아니라 시설을 보호함과 동시에 수명을 연장할 수 있으며 각각의 와이어링넷(120)을 교체할 수 있어 파손이나 훼손부위를 신속하게 교체할 수 있도록 하는 것이다.At this time, the wiring net 120 or the wiring net 120 and the blocking wire rope 130 are installed together with the blocking net 150. Due to the multiple wiring 122, it is easy to contract and expand, resulting in shock due to falling rocks. By absorbing energy efficiently, it not only prevents falling rocks from entering the road, but also protects the facility and extends its lifespan. Each wiring net (120) can be replaced so that damaged or broken parts can be quickly replaced. It is done.

더욱이, 와이어링넷(120)의 조립이 용이하고 견고한 결합상태를 유지하므로 코스트를 최소화하면서도 최고의 낙서방지효율을 얻을 수 있는 것이다.Moreover, since the wiring net 120 is easy to assemble and maintains a solid connection, the highest anti-graffiti efficiency can be achieved while minimizing the cost.

이상의 설명은 본 발명을 예시적으로 설명한 것이고, 명세서에 게시된 실시 예는 본 발명의 기술사상을 한정하기 위한 것이 아니라 설명하기 위한 것이므로 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자라면 본 발명의 기술사상을 벗어나지 않는 범위에서 다양한 수정과 변형 또는 단계의 치환 등이 가능할 것이다. The above description is an illustrative description of the present invention, and the embodiments posted in the specification are not intended to limit the technical idea of the present invention, but are for illustrative purposes, so those skilled in the art will understand the present invention. Various modifications, transformations, or substitution of steps will be possible without departing from the technical idea of .

그러므로 본 발명의 보호범위는 청구범위에 기재된 사항에 의해 해석되고, 그와 균등한 범위 내에 있는 기술적 사항도 본 발명의 권리범위에 포함되는 것으로 해석되어야 할 것이다.Therefore, the scope of protection of the present invention should be interpreted based on the matters stated in the claims, and technical matters within the equivalent scope thereof should also be interpreted as being included in the scope of rights of the present invention.

100 : 낙석방지책 110 : 지주부
111 : H빔 112 : 매설부
113 : 절곡부 114 : 기초콘크리트
120 : 와이어링넷 121 : 와이어링로프
122 : 와이어링 123 : 결합고리
124 : 결합수단 125 : 외각와이어로프
130 : 차단와이어로프 131 : 결합수단
140 : 체결클립 141 : 결합홈
142 : 슬라이드돌기 143 : 슬라이드홈
150 : 차단망
100: Rockfall prevention measure 110: Holding part
111: H beam 112: Buried part
113: bent part 114: basic concrete
120: wiring net 121: wiring rope
122: wiring 123: coupling ring
124: Coupling means 125: Outer wire rope
130: Blocking wire rope 131: Coupling means
140: fastening clip 141: coupling groove
142: Slide projection 143: Slide groove
150: Blocking net

Claims (3)

와이어링을 이용한 낙석방지책(100)은 H빔(111)을 일정간격으로 세워 설치하는 지주 설치단계와; 상기 지주 설치단계가 완료되면, 와이어링로프(121)로 다수개의 와이어링(122)을 형성하되 상하를 결합고리(123)로 연결하고 좌우를 체결클립(140)으로 체결하여 와이어링넷(120)을 형성하고 H빔(111) 사이에 와이어링넷(120)을 결합하는 와이어링넷 형성단계와; 상기 와이어링넷 형성단계가 완료되면, H빔(111) 사이 상측에 횡으로 다수 가닥 설치하는 차단와이어로프(130)를 형성하는 차단와이어로프 형성단계; 및 상기 차단와이어로프 형성단계가 완료되면, H 빔(111) 사이 차단망(150)을 결합하는 완성단계로 구성하되,
상기 와이어링넷 형성단계는 와이어링로프(121)를 파형으로 형성하여 파형의 상측와 하측를 반원형으로 형성하되 이러한 파형을 순차적으로 연속 반복하여 형성하되, 제1열 와이어링로프(121)의 하부 반원 중심과 제2열 상부 반원 중심의 결합고리(123)로 연결하도록 하고 좌우 측을 교차하도록 하여 다수개의 와이어링(122)을 순차적으로 형성하도록 하며 좌우 측 교차부분을 체결클립(140)으로 체결하여 와이어링로프(121)에 와이어링(122)을 일정 간격으로 형성하도록 하고, 테두리에 외각와이어로프(125)를 체결한 다음 H빔(111) 사이에 와이어링넷(120)을 각각 결합하도록 구성하되, 체결클립(140)에 삽입용 결합홈(141)을 형성하여 와이어링로프(121)에 일정 간격으로 끼워 형성하되 좌우 한 쌍으로 형성하여 대응 면에 슬라이드돌기(142)와 슬라이드홈(143)을 형성하여 결합할 수 있도록 구성한 것을 특징으로 하는 와이어링을 이용한 낙석방지책 시공방법.
The rockfall prevention measure 100 using wiring includes a support installation step of erecting and installing H beams 111 at regular intervals; When the support installation step is completed, a plurality of wirings 122 are formed using wiring ropes 121, and the upper and lower parts are connected with coupling rings 123 and the left and right sides are fastened with fastening clips 140 to form a wiring net 120. A wiring net forming step of forming and combining the wiring net 120 between the H beams 111; When the wiring net forming step is completed, a blocking wire rope forming step of forming a plurality of blocking wire ropes 130 installed horizontally on the upper side between the H beams 111; And when the blocking wire rope forming step is completed, it consists of a completion step of combining the blocking net 150 between the H beams 111,
In the wiring net forming step, the wiring rope 121 is formed into a wave shape, and the upper and lower sides of the wave shape are formed into a semicircle. This wave shape is formed by sequentially repeating the shape, and the lower semicircular center of the first row wiring rope 121 is formed. It is connected to the connecting ring 123 at the center of the semicircle at the top of the second row, and a plurality of wiring 122 is formed sequentially by crossing the left and right sides. The wiring is connected by fastening the left and right intersection parts with fastening clips 140. The wiring 122 is formed on the rope 121 at regular intervals, the outer wire rope 125 is fastened to the edge, and the wiring net 120 is connected between the H beams 111, respectively. A coupling groove 141 for insertion is formed in the clip 140 and inserted into the wiring rope 121 at regular intervals, and is formed as a pair on the left and right to form a slide protrusion 142 and a slide groove 143 on the corresponding side. A rockfall prevention construction method using wiring, characterized in that it is configured so that it can be combined.
삭제delete 삭제delete
KR1020210186302A 2021-12-23 2021-12-23 construction method for falling rock prevention fence using wire ring KR102625646B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210186302A KR102625646B1 (en) 2021-12-23 2021-12-23 construction method for falling rock prevention fence using wire ring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210186302A KR102625646B1 (en) 2021-12-23 2021-12-23 construction method for falling rock prevention fence using wire ring

Publications (2)

Publication Number Publication Date
KR20230096629A KR20230096629A (en) 2023-06-30
KR102625646B1 true KR102625646B1 (en) 2024-01-15

Family

ID=86959831

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210186302A KR102625646B1 (en) 2021-12-23 2021-12-23 construction method for falling rock prevention fence using wire ring

Country Status (1)

Country Link
KR (1) KR102625646B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101712651B1 (en) * 2016-04-08 2017-03-22 선진기업 주식회사 Falling rock preventing fence using zigzag wire rope and method for constructing this same
JP2020159096A (en) * 2019-03-27 2020-10-01 株式会社テザック Rockfall prevention tool and rockfall prevention method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR0124435Y1 (en) * 1992-05-09 1998-12-15 윤종용 Lesin pack motor of lead wire holders
KR20040004884A (en) * 2002-07-05 2004-01-16 나종호 net for preventing a falling rock, using wire rope
KR101691547B1 (en) * 2014-09-18 2016-12-30 주식회사 수아이텍 Wirenet assembly for being adhered on rock and constructing method thereof

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101712651B1 (en) * 2016-04-08 2017-03-22 선진기업 주식회사 Falling rock preventing fence using zigzag wire rope and method for constructing this same
JP2020159096A (en) * 2019-03-27 2020-10-01 株式会社テザック Rockfall prevention tool and rockfall prevention method

Also Published As

Publication number Publication date
KR20230096629A (en) 2023-06-30

Similar Documents

Publication Publication Date Title
US8197156B2 (en) Shallow mounted fixed vehicle barrier device
KR102081865B1 (en) Tunnel type rockfall protection structure having variable pole part for shock absorbing
JP5005659B2 (en) Rock fall protection net structure
KR102429680B1 (en) falling rock prevention sturcture construction method using wire ring
US9163418B2 (en) Removable and re-useable construction safety barrier
JP5086871B2 (en) Covered slope protection method
JP6871681B2 (en) Front and rear two-tiered protective fence
JP6114537B2 (en) Rockfall protection device and rockfall protection method
JP5818213B2 (en) Guard fence and its construction method
JP7235940B2 (en) Earth and sand fall protection work and its construction method
KR102625646B1 (en) construction method for falling rock prevention fence using wire ring
KR102458257B1 (en) Sturcture for preventing falling rock using wire ring
JP5793633B1 (en) Protective fence
KR102625648B1 (en) falling rock prevention pence using wire ring
KR102104814B1 (en) Transparent light weight cantilever wind barrier with pedestrian safety handrail and vehicle falling protection system of bridge
JP4580776B2 (en) Wire rope type rockfall protection fence
KR101701220B1 (en) Road expansion structure and construction method thereof
KR101572504B1 (en) Separable fence for protecting from falling rocks
JP4410736B2 (en) Protective fence
JP2010168833A (en) Protective fence against rockfall or the like
KR101104124B1 (en) Prefab Rockfall Protection
JP6884477B2 (en) Guard for median strip
AU2017251724B2 (en) Track support system
KR102476908B1 (en) debris flow prevention sturcture construction method using wire ring
KR100870750B1 (en) Wire rope fixing structure of rockfall prevention measures

Legal Events

Date Code Title Description
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20211223

PA0201 Request for examination
E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20230630

Patent event code: PE09021S01D

PG1501 Laying open of application
E701 Decision to grant or registration of patent right
PE0701 Decision of registration

Patent event code: PE07011S01D

Comment text: Decision to Grant Registration

Patent event date: 20231229

GRNT Written decision to grant
PR0701 Registration of establishment

Comment text: Registration of Establishment

Patent event date: 20240111

Patent event code: PR07011E01D

PR1002 Payment of registration fee

Payment date: 20240111

End annual number: 3

Start annual number: 1

PG1601 Publication of registration