KR102561586B1 KR1020220070138A KR20220070138A KR102561586B1 KR 102561586 B1 KR102561586 B1 KR 102561586B1 KR 1020220070138 A KR1020220070138 A KR 1020220070138A KR 20220070138 A KR20220070138 A KR 20220070138A KR 102561586 B1 KR102561586 B1 KR 102561586B1
Authority
KR
South Korea
Prior art keywords
slope reinforcement
reinforcement panel
improved
panel unit
unit
Prior art date
Application number
KR1020220070138A
Other languages
Korean (ko)
Inventor
안성훈
Original Assignee
주식회사 정성이엔씨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 정성이엔씨 filed Critical 주식회사 정성이엔씨
Priority to KR1020220070138A priority Critical patent/KR102561586B1/en
Application granted granted Critical
Publication of KR102561586B1 publication Critical patent/KR102561586B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/205Securing of slopes or inclines with modular blocks, e.g. pre-fabricated
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/025Retaining or protecting walls made up of similar modular elements stacked without mortar
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

본 발명은 상부와 하부에 각각 대응하는 형상으로 상부홀(111)과 하부돌기(113)가 형성되고,
측면과 반대쪽 측면에 각각 대응하는 형상으로 측면돌기(121)와 측면홀(123)이 형성되며,
사면(S) 정면에 다수개가 상하좌우로 적층되어 옹벽체를 구성하는 것을 특징으로 하는 개량형 사면 보강 패널 유닛(100)을 제공한다.
그리고 상기 개량형 사면 보강 패널 유닛(100) 정면에는 후면으로 관통하는 네일체관통홀(120)이 형성되고,
사면(S)에 네일링된 네일(AC)의 타단이 상기 네일체관통홀(120)에 체결되는 것을 특징으로 하는 개량형 사면 보강 패널 유닛(100)을 제공한다.
더불어 상기 측면돌기(121)에서 상기 측면홀(123)을 관통하는 보강재설치홀(130)이 형성되고,
상기 개량형 사면 보강 패널 유닛(100) 다수개가 옆으로 배치될 때,
다수개의 상기 개량형 사면 보강 패널 유닛(100) 상호간에 상기 보강재설치홀(130)을 관통하며 보강재(1000)가 설치되는 것을 특징으로 하는 특징으로 하는 개량형 사면 보강 패널 유닛(100).
In the present invention, upper holes 111 and lower protrusions 113 are formed in shapes corresponding to the upper and lower parts, respectively,
Side protrusions 121 and side holes 123 are formed in shapes corresponding to the side and the opposite side, respectively,
Provides an improved slope reinforcement panel unit 100, characterized in that a plurality of them are stacked up, down, left and right on the front of the slope (S) to form a retaining wall.
In addition, a nail body through hole 120 penetrating the rear side is formed on the front side of the improved slope reinforcement panel unit 100,
An improved slope reinforcement panel unit (100) is provided, characterized in that the other end of the nail (AC) nailed to the slope (S) is fastened to the nail body through hole (120).
In addition, a reinforcement installation hole 130 penetrating the side hole 123 is formed in the side projection 121,
When the plurality of the improved slope reinforcement panel units 100 are placed sideways,
Improved slope reinforcement panel unit (100), characterized in that the reinforcement member (1000) is installed between the plurality of improved slope reinforcement panel units (100) passing through the reinforcement installation hole (130).

Figure R1020220070138
Figure R1020220070138

Description

개량형 사면 보강 패널 유닛 및 이를 이용한 사면 보강 구조{the improved panel unit for reinforcing slope and the reinforcing slope structure using the same}{the improved panel unit for reinforcing slope and the reinforcing slope structure using the same}

본 발명은 절개지 또는 사면 보강을 위한 옹벽구조에 관한 것으로, 더욱 상세하게는 철근콘크리트로 선제작된 경량화된 옹벽구조물인 개량형 사면 보강 패널 유닛을 설치한 후, 패널 유닛 상호간을 강선으로 상호 연결하여 결합하고 네일링하므로, 외관이 미려하고 작업성 및 안정성 증가 효과가 우수한 개량형 사면 보강 패널 유닛 및 이를 이용한 사면 보강 구조에 관한 것이다. The present invention relates to a retaining wall structure for incision or slope reinforcement, and more particularly, after installing an improved slope reinforcement panel unit, which is a lightweight retaining wall structure prefabricated of reinforced concrete, and then connecting the panel units to each other with steel wires. Since it is nailed and nailed, it relates to an improved slope reinforcement panel unit with a beautiful appearance and excellent workability and stability increase effect and a slope reinforcement structure using the same.

산지가 많은 우리나라에서 도로, 주택단지, 수로, 제방 등의 각종 토목공사에서는 산의 일부를 절개하는 것은 필수적으로, 이에 따른 붕괴를 방지하기 위하여 옹벽구조물을 설치한다.In Korea, where there are many mountains, it is essential to cut a part of a mountain in various civil engineering works such as roads, housing complexes, waterways, and embankments, and retaining wall structures are installed to prevent collapse.

이러한 절개지 또는 사면(S)에서의 종래의 옹벽공사는 현장타설 콘크리트가 일반적이었는데, In the conventional retaining wall construction in such an incision or slope (S), cast-in-place concrete was common,

이 경우 거푸집 설치 및 해체의 어려움과 경제성과 공기 등에 문제가 많아, 영구앵커와 프리케스트형식의 옹벽구조물을 병용한 공법이 많이 적용되고 있다.In this case, there are many problems with the difficulty of installing and dismantling the formwork, economic feasibility, and air, so a method using a permanent anchor and a precast retaining wall structure is widely applied.

이러한 공법의 종래방법은 등록특허 제 10-0525156호를 예로 들면, The conventional method of this method is, for example, in Registered Patent No. 10-0525156,

㉠ 원지반을 절토하여 사면을 형성하고, ㉠ the original ground is cut to form a slope,

㉡ 소정간격으로 사면에 매설홀을 천공하여 앵커를 그라우팅으로 고정하고, ㉡ Buried holes are drilled on the slope at predetermined intervals to fix anchors with grouting,

㉢ 프리케스트형식의 옹벽구조물을 설치하고, ㉢ Install a retaining wall structure in the form of a precast,

㉣ 옹벽구조물의 배면과 절토된 사면 사이에 콘크리트를 타설하고, ㉣ Pour concrete between the back of the retaining wall structure and the cut slope,

㉤ 콘크리트 경화후에 옹벽구조물 전면에서 앵커를 인장하여 옹벽구조물이 사면을 가압함으로서 붕괴를 방지한다.㉤ After the concrete has hardened, anchors are pulled from the front of the retaining wall structure to prevent collapse by pressurizing the slope of the retaining wall structure.

이러한 종래의 옹벽구조물은 자체만으로 구조적 기능을 갖춘 프리케스트 구조물(Full-PC라 함)로 무거워 절개지에서의 설치에 어려움이 많고, 옹벽구조물의 배면과 절토된 사면 사이에 타설되는 콘크리트는 옹벽구조물보다도 많은 물량이 소요됨에도 불구하고 구조적인 기능이 없는 충진만을 목적으로 하기 때문에 비효율적이다.Such a conventional retaining wall structure is a precast structure (referred to as Full-PC) that has structural functions by itself, and is heavy, making it difficult to install in an incised area, and the concrete poured between the back of the retaining wall structure and the cut slope is more Despite the large quantity required, it is inefficient because it is aimed only at filling without structural function.

또한, 시공 완료 후 패널에 내력(집중호우, 쐐기파괴)이 작용하는 경우, 패널간의 결합력이 없어 국부적 파손 내지 무너져 내리는 현상이 발생되는 문제점이 있다.In addition, when internal forces (heavy rain, wedge breakage) act on the panels after completion of construction, there is a problem in that local damage or collapse occurs due to lack of bonding force between the panels.

이에 합리적인 구조형태를 이루면서 경량화하여 작업성이 경제적으로 효과적인 기술이 필요하다.Therefore, it is necessary to develop a technology that is economically effective in workability by achieving a reasonable structure and light weight.

[문헌 1] 대한민국 등록특허 제0372821호 '절토사면의 블럭식 수동보강방법', 2003년 02월 06일[Document 1] Republic of Korea Patent No. 0372821 'Block type manual reinforcement method of cut slope', February 06, 2003 [문헌 2] 대한민국 등록특허 제2006305호 '절토사면 및 성토지 옹벽용 블럭 구조물', 2019년 07월 26일[Document 2] Republic of Korea Patent Registration No. 2006305 'Block structure for cut slope and embankment wall', July 26, 2019

본 발명은 상기한 바와 같은 종래의 제반 문제점을 해소하기 위해서 제시되는 것이다. 그 목적은 종래의 옹벽구조물이 중량의 프리케스트 구조물(Full-PC)로 제작되어 설치에 어려움이 있는 것을 개선하여 경량화하고 시공성이 개선된 개량형 사면 보강 패널 유닛 및 이를 이용한 사면 보강 구조를 제공하고자 한다.The present invention is presented in order to solve the various conventional problems as described above. The purpose is to provide an improved slope reinforcement panel unit with light weight and improved workability by improving the difficulty in installation due to the conventional retaining wall structure being made of a heavy precast structure (Full-PC) and a slope reinforcement structure using the same. .

상기한 기술적 과제를 해결하기 위해 본 발명은 상부와 하부에 각각 대응하는 형상으로 상부홀(111)과 하부돌기(113)가 형성되고,In order to solve the above technical problem, the present invention has an upper hole 111 and a lower protrusion 113 formed in a shape corresponding to the upper and lower parts,

측면과 반대쪽 측면에 각각 대응하는 형상으로 측면돌기(121)와 측면홀(123)이 형성되며, Side protrusions 121 and side holes 123 are formed in shapes corresponding to the side and the opposite side, respectively,

사면(S) 정면에 다수개가 상하좌우로 적층되어 옹벽체를 구성하는 것을 특징으로 하는 개량형 사면 보강 패널 유닛(100)을 제공한다.Provides an improved slope reinforcement panel unit 100, characterized in that a plurality of them are stacked up, down, left and right on the front of the slope (S) to form a retaining wall.

그리고 상기 개량형 사면 보강 패널 유닛(100) 정면에는 후면으로 관통하는 네일체관통홀(120)이 형성되고,In addition, a nail body through hole 120 penetrating the rear side is formed on the front side of the improved slope reinforcement panel unit 100,

사면(S)에 네일링된 네일(AC)의 타단이 상기 네일체관통홀(120)에 체결되는 것을 특징으로 하는 개량형 사면 보강 패널 유닛(100)을 제공한다.An improved slope reinforcement panel unit (100) is provided, characterized in that the other end of the nail (AC) nailed to the slope (S) is fastened to the nail body through hole (120).

더불어 상기 측면돌기(121)에서 상기 측면홀(123)을 관통하는 보강재설치홀(130)이 형성되고,In addition, a reinforcement installation hole 130 penetrating the side hole 123 is formed in the side projection 121,

상기 개량형 사면 보강 패널 유닛(100) 다수개가 옆으로 배치될 때, When the plurality of the improved slope reinforcement panel units 100 are placed sideways,

다수개의 상기 개량형 사면 보강 패널 유닛(100) 상호간에 상기 보강재설치홀(130)을 관통하며 보강재(1000)가 설치되는 것을 특징으로 하는 특징으로 하는 개량형 사면 보강 패널 유닛(100).Improved slope reinforcement panel unit (100), characterized in that the reinforcement member (1000) is installed between the plurality of improved slope reinforcement panel units (100) passing through the reinforcement installation hole (130).

본 발명에 따르면 다음과 같은 효과가 기대된다.According to the present invention, the following effects are expected.

첫째, 종래의 옹벽구조물이 중량의 프리케스트 구조물(Full-PC)로 설치에 어려움이 있는 것을 개선하여 경량화하고 시공성이 개선된 개량형 사면 보강 패널 유닛 및 이를 이용한 사면 보강 구조를 제공한다.First, the existing retaining wall structure is a heavy precast structure (Full-PC), which is difficult to install, to provide an improved slope reinforcement panel unit that is lightweight and has improved workability and a slope reinforcement structure using the same.

둘째, 기성의 옹벽구조가 국부적 파괴에 대처가 안되는 것을 개선하여 국부적 파괴에 대응이 가능한 개량형 사면 보강 패널 유닛 및 이를 이용한 사면 보강 구조를 제공한다.Second, an improved slope reinforcement panel unit capable of coping with local destruction by improving existing retaining wall structures that cannot cope with local destruction and a slope reinforcement structure using the same are provided.

셋째, 전면에 차별화된 문양을 제공할 수 있는 개량형 사면 보강 패널 유닛 및 이를 이용한 사면 보강 구조를 제공한다.Third, an improved slope reinforcement panel unit capable of providing a differentiated pattern on the front side and a slope reinforcement structure using the same are provided.

넷째, 보강제에 계측장치를 설치하여 유지관리를 제공할 수 있는 개량형 사면 보강 패널 유닛 및 이를 이용한 사면 보강 구조를 제공한다.Fourth, an improved slope reinforcement panel unit capable of providing maintenance by installing a measuring device on the reinforcement and a slope reinforcement structure using the same are provided.

도 1은 본 발명의 개량형 사면 보강 패널 유닛 및 이를 이용한 사면 보강 구조의 단면도를 도시한 것이다.
도 2는 본 발명의 개량형 사면 보강 패널 유닛 상호간의 결합관계를 도시한 것이다.
도 3은 본 발명의 개량형 사면 보강 패널 유닛의 정면도, 측면도, 평면도를 도시한 것이다.
도 4는 본 발명의 개량형 사면 보강 패널 유닛을 이용한 사면 보강 구조에 보강재를 적용한 실시예이다.
도 5는 본 발명의 개량형 사면 보강 패널 유닛을 이용한 사면 보강 구조에 보강재를 적용한 다른 실시예이다.
도 6은 본 발명의 개량형 사면 보강 패널 유닛을 이용한 사면 보강 구조에 보강재를 적용한 다른 실시예의 시공방법을 도시한 것이다.
도 7은 도 6의 완성된 모습을 도시한 것이다.
도 8은 본 발명의 개량형 사면 보강 패널 유닛을 이용한 사면 보강 구조에 보강재를 적용한 다른 실시예의 시공방법을 도시한 것이다.
도 9는 도 8의 완성된 모습을 도시한 것이다.
도 10은 본 발명의 개량형 사면 보강 패널 유닛을 이용한 사면 보강 구조에 보강재를 적용한 다른 실시예이다.
1 is a cross-sectional view of an improved slope reinforcement panel unit of the present invention and a slope reinforcement structure using the same.
Figure 2 shows the coupling relationship between the improved slope reinforcement panel units of the present invention.
3 shows a front view, a side view, and a plan view of an improved slope reinforcement panel unit of the present invention.
4 is an embodiment in which reinforcement is applied to a slope reinforcement structure using an improved slope reinforcement panel unit of the present invention.
5 is another embodiment in which reinforcement is applied to a slope reinforcement structure using an improved slope reinforcement panel unit of the present invention.
6 shows a construction method of another embodiment in which a reinforcing material is applied to a slope reinforcement structure using an improved slope reinforcement panel unit of the present invention.
FIG. 7 shows a completed state of FIG. 6 .
8 shows a construction method of another embodiment in which a reinforcing material is applied to a slope reinforcement structure using an improved slope reinforcement panel unit of the present invention.
Figure 9 shows the completed appearance of Figure 8.
10 is another embodiment in which reinforcement is applied to a slope reinforcement structure using an improved slope reinforcement panel unit of the present invention.

이하 첨부한 도면과 함께 상기와 같은 본 발명의 개념이 바람직하게 구현된 실시예를 통하여 본 발명을 더욱 상세하게 설명한다. Hereinafter, the present invention will be described in more detail through an embodiment in which the concept of the present invention as described above is preferably implemented in conjunction with the accompanying drawings.

도 1은 본 발명의 개량형 사면 보강 패널 유닛 및 이를 이용한 사면 보강 구조의 단면도를 도시한 것이다.1 is a cross-sectional view of an improved slope reinforcement panel unit of the present invention and a slope reinforcement structure using the same.

도 2는 본 발명의 개량형 사면 보강 패널 유닛 상호간의 결합관계를 도시한 것이다.Figure 2 shows the coupling relationship between the improved slope reinforcement panel units of the present invention.

도 3은 본 발명의 개량형 사면 보강 패널 유닛의 정면도, 측면도, 평면도를 도시한 것이다.3 shows a front view, a side view, and a plan view of an improved slope reinforcement panel unit of the present invention.

도 4는 본 발명의 개량형 사면 보강 패널 유닛을 이용한 사면 보강 구조에 보강재를 적용한 실시예이다.4 is an embodiment in which reinforcement is applied to a slope reinforcement structure using an improved slope reinforcement panel unit of the present invention.

도 5는 본 발명의 개량형 사면 보강 패널 유닛을 이용한 사면 보강 구조에 보강재를 적용한 다른 실시예이다.5 is another embodiment in which reinforcement is applied to a slope reinforcement structure using an improved slope reinforcement panel unit of the present invention.

도 6은 본 발명의 개량형 사면 보강 패널 유닛을 이용한 사면 보강 구조에 보강재를 적용한 다른 실시예의 시공방법을 도시한 것이다. 6 shows a construction method of another embodiment in which a reinforcing material is applied to a slope reinforcement structure using an improved slope reinforcement panel unit of the present invention.

도 7은 도 6의 완성된 모습을 도시한 것이다.FIG. 7 shows a completed state of FIG. 6 .

도 8은 본 발명의 개량형 사면 보강 패널 유닛을 이용한 사면 보강 구조에 보강재를 적용한 다른 실시예의 시공방법을 도시한 것이다. 8 shows a construction method of another embodiment in which a reinforcing material is applied to a slope reinforcement structure using an improved slope reinforcement panel unit of the present invention.

도 9는 도 8의 완성된 모습을 도시한 것이다.Figure 9 shows the completed appearance of Figure 8.

도 10은 본 발명의 개량형 사면 보강 패널 유닛을 이용한 사면 보강 구조에 보강재를 적용한 다른 실시예이다.10 is another embodiment in which reinforcement is applied to a slope reinforcement structure using an improved slope reinforcement panel unit of the present invention.

본 발명의 개량형 사면 보강 패널 유닛(100)은 상부와 하부에 각각 대응하는 형상으로 상부홀(111)과 하부돌기(113)가 형성되고,The improved slope reinforcement panel unit 100 of the present invention has upper holes 111 and lower protrusions 113 formed in corresponding shapes at the top and bottom, respectively,

측면과 반대쪽 측면에 각각 대응하는 형상으로 측면돌기(121)와 측면홀(123)이 형성되며, Side protrusions 121 and side holes 123 are formed in shapes corresponding to the side and the opposite side, respectively,

사면(S) 정면에 다수개가 상하좌우로 적층되어 옹벽체를 구성하는 것을 특징으로 한다.It is characterized in that a plurality of them are stacked up, down, left and right on the front of the slope (S) to form a retaining wall.

그리고 상기 개량형 사면 보강 패널 유닛(100) 정면에는 후면으로 관통하는 네일체관통홀(120)이 형성되고,In addition, a nail body through hole 120 penetrating the rear side is formed on the front side of the improved slope reinforcement panel unit 100,

사면(S)에 네일링된 네일(AC)의 타단이 상기 네일체관통홀(120)에 체결되는 것을 특징으로 한다.It is characterized in that the other end of the nail (AC) nailed to the slope (S) is fastened to the nail body through hole (120).

또한 상기 측면돌기(121)에서 상기 측면홀(123)을 관통하는 보강재설치홀(130)이 형성되고,In addition, a reinforcement installation hole 130 penetrating the side hole 123 is formed in the side projection 121,

상기 개량형 사면 보강 패널 유닛(100) 다수개가 옆으로 배치될 때, When the plurality of the improved slope reinforcement panel units 100 are placed sideways,

다수개의 상기 개량형 사면 보강 패널 유닛(100) 상호간에 상기 보강재설치홀(130)을 관통하며 보강재(1000)가 설치되는 것을 특징으로 하는 특징으로 한다.It is characterized in that the reinforcing material 1000 is installed between the plurality of the improved slope reinforcing panel units 100 while passing through the reinforcing material installation hole 130.

도 2는 본 발명의 개량형 사면 보강 패널 유닛 상호간의 결합관계를 도시한 것이고, 도 3은 본 발명의 개량형 사면 보강 패널 유닛의 정면도, 측면도, 평면도를 도시한 것이다.2 shows a coupling relationship between the improved slope reinforcement panel units of the present invention, and FIG. 3 shows a front view, a side view, and a plan view of the improved slope reinforcement panel unit of the present invention.

도시된 바와 같이,As shown,

상기 개량형 사면 보강 패널 유닛(100)은 상하좌우 적층되는 과정에서,In the process of stacking the improved slope reinforcement panel unit 100 up, down, left and right,

측면돌기(121)와 측면홀(123)이 상호간에 맞물리고,The side protrusion 121 and the side hole 123 are mutually engaged,

상부홀(111)과 하부돌기(113)가 상호간에 맞물려 강한 체결력을 형성하게 된다.The upper hole 111 and the lower protrusion 113 are engaged with each other to form a strong fastening force.

그리고 사면(S)에 네일링된 네일(AC)의 타단이 상기 개량형 사면 보강 패널 유닛(100)에 형성된 상기 네일체관통홀(120)에 체결되는데,In addition, the other end of the nail AC nailed to the slope S is fastened to the nail body through hole 120 formed in the improved slope reinforcement panel unit 100.

상기 네일(AC)의 인장력을 상시 체크하는 계측기(300)가 상기 네일(AC) 중단 또는 타단에 설치될 수 있다.A measuring instrument 300 that constantly checks the tensile force of the nail AC may be installed at the middle or other end of the nail AC.

중앙통제실에서는 상기 계측기(300)의 신호를 받아 상기 네일(AC)의 인장력 정상 여부를 상시 확인하고 상기 네일(AC)의 인장력을 상시 점검하게 된다.The central control room receives a signal from the measuring instrument 300 and constantly checks whether or not the tensile force of the nail AC is normal, and constantly checks the tensile force of the nail AC.

상기 사면(S) 정면과 상기 개량형 사면 보강 패널 유닛(100) 배면 사이에는 뒤채움재(BF)가 타설된다.A backfill material (BF) is placed between the front surface of the slope (S) and the rear surface of the improved slope reinforcement panel unit (100).

상기 뒤채움재(BF)는 절토된 흙이나 골재 등을 선택적으로 이용할 수 있으며, 레벨을 달리하여 하부와 상부에 각각 골재와 흙을 부설할 수 있다.As the backfill material (BF), cut soil or aggregate may be selectively used, and aggregate and soil may be laid in the lower part and the upper part, respectively, at different levels.

상기 개량형 사면 보강 패널 유닛(100)은 PC, 합성수지 등 구조적 성능이 확보된 소재라면 무엇이든 이용이 가능하다.The improved slope reinforcement panel unit 100 may use any material such as PC or synthetic resin, as long as structural performance is secured.

보통 옹벽체에 이용되는 블록은 자체 자중이 많이 확보되야 하나,Blocks usually used for retaining walls should have a lot of their own weight,

본 발명에 사용되는 상기 개량형 사면 보강 패널 유닛(100)은 합성수지 등 자중이 작은 것이라도 상기 네일(AC)와 보강재(1000)로 인하여 충분히 구조적 성능을 발휘하게 된다.The improved slope reinforcement panel unit 100 used in the present invention exhibits sufficient structural performance due to the nail AC and the reinforcing material 1000 even if it is made of synthetic resin or the like having a small weight.

상기 개량형 사면 보강 패널 유닛(100)은 상기 측면돌기(121)에서 상기 측면홀(123)을 관통하는 보강재설치홀(130)이 횡으로 형성된다.In the improved slope reinforcement panel unit 100, a reinforcement installation hole 130 penetrating the side hole 123 is formed in the side protrusion 121 laterally.

따라서 상기 개량형 사면 보강 패널 유닛(100) 다수개가 옆으로 배치될 때, Therefore, when a plurality of the improved slope reinforcement panel units 100 are placed sideways,

다수개의 상기 개량형 사면 보강 패널 유닛(100) 상호간에 상기 보강재설치홀(130)을 관통하며 보강재(1000)가 설치된다.The reinforcing materials 1000 are installed between the plurality of improved slope reinforcing panel units 100 passing through the reinforcing material installation holes 130.

상기 보강재(1000)는 포스트텐션이 가능한 강연선을 이용하는 것이 바람직하다. 왜냐하면 상기 개량형 사면 보강 패널 유닛(100) 배면에서 작용하는 토압에 대응하여 상기 개량형 사면 보강 패널 유닛(100) 상호간의 벌어짐을 방지해야 하기 때문이다.It is preferable to use a post-tensionable stranded wire as the reinforcing material 1000 . This is because it is necessary to prevent the improved slope reinforcement panel unit 100 from opening between each other in response to the earth pressure acting on the rear surface of the improved slope reinforcement panel unit 100 .

도 4는 2개의 상기 개량형 사면 보강 패널 유닛(100) 상호간을 연결한 실시예이고,4 is an embodiment in which two of the improved slope reinforcement panel units 100 are connected to each other,

도 5는 5개의 상기 개량형 사면 보강 패널 유닛(100) 상호간을 연결한 실시예이다. 5 is an embodiment in which five of the improved slope reinforcement panel units 100 are connected to each other.

이와 같이 상기 개량형 사면 보강 패널 유닛(100) 개수에 무관하게 상기 보강재(1000)를 관통하여 설치할 수 있다.In this way, regardless of the number of the improved slope reinforcement panel units 100, it can be installed through the reinforcement member 1000.

보다 구체적으로 도 4에서,More specifically in Figure 4,

제1방식으로,in the first way,

2개의 상기 개량형 사면 보강 패널 유닛(100)을 먼저 횡으로 설치한 후 상기 보강재(1000) 일단을 정착구(1010)로 고정한 후 타단을 당겨 포스트텐션을 부여한 후 타단에 정착구(1010)를 고정할 수 있다.After installing the two improved slope reinforcement panel units 100 horizontally first, fixing one end of the reinforcing material 1000 to the anchorage 1010, pulling the other end to apply post tension, and then fixing the anchorage 1010 to the other end. there is.

다른 제2방식으로,In another second way,

1개의 상기 개량형 사면 보강 패널 유닛(100)을 먼저 설치한 후 상기 보강재(1000) 일단을 정착구(1010)로 고정한 후 타단을 노출시킨 후,After installing one of the improved slope reinforcement panel units 100 first, fixing one end of the reinforcing material 1000 to the anchorage 1010 and exposing the other end,

상기 보강재(1000) 타단을 다른 상기 개량형 사면 보강 패널 유닛(100)의 상기 보강재설치홀(130)을 관통시키면서 상기 다른 상기 개량형 사면 보강 패널 유닛(100)을 설치하고, Installing the other improved slope reinforcement panel unit 100 while passing the other end of the reinforcement member 1000 through the reinforcement installation hole 130 of the other improved slope reinforcement panel unit 100,

마지막으로 상기 보강재(1000) 타단을 당겨 포스트텐션을 부여한 후 타단에 정착구(1010)를 고정할 수 있다. Finally, after applying post-tension by pulling the other end of the reinforcing material 1000, the anchorage 1010 may be fixed to the other end.

도 6은 본 발명의 개량형 사면 보강 패널 유닛을 이용한 사면 보강 구조에 보강재를 적용한 다른 실시예의 시공방법을 도시한 것이고, 도 7은 도 6의 완성된 모습을 도시한 것이다.6 shows a construction method of another embodiment in which a reinforcing material is applied to a slope reinforcement structure using an improved slope reinforcement panel unit of the present invention, and FIG. 7 shows a completed state of FIG. 6 .

그리고 도 8은 본 발명의 개량형 사면 보강 패널 유닛을 이용한 사면 보강 구조에 보강재를 적용한 다른 실시예의 시공방법을 도시한 것이고, 도 9는 도 8의 완성된 모습을 도시한 것이다.And FIG. 8 shows a construction method of another embodiment in which a reinforcing material is applied to a slope reinforcement structure using an improved slope reinforcement panel unit of the present invention, and FIG. 9 shows a completed state of FIG. 8 .

도 6 내지 9에 도시된 실시예는 도시된 바와 같이,As shown in the embodiments shown in Figures 6 to 9,

상기 개량형 사면 보강 패널 유닛(100)에 상기 보강재설치홀(130)을 레벨을 달리하여 다수개 형성한 것으로써,
레벨을 달리하는 다수개의 상기 보강재설치홀(130)에 상술한 제2방식을 교차하여 적용하여 상기 보강재(1000)를 설치한 것이다.
부연하면, 상기 개량형 사면 보강 패널 유닛(100)에서 상기 보강재설치홀(130)은 2개 이상이 각각 레벨을 달리하여 수평으로 형성되며,
준비된 2개의 상기 개량형 사면 보강 패널 유닛(100)을 각각 제1유닛(100-1)과 제2유닛(100-2)으로 명명할 때,
상기 제1유닛(100-1)의 어느 한 레벨의 상기 보강재설치홀(130)에 설치된 상기 보강재(1000) 일단을 정착구(1010)로 고정하고 타단을 노출시키고,
상기 제2유닛(100-2)의 다른 레벨의 상기 보강재설치홀(130)에 상기 보강재(1000) 일단을 정착구(1010)로 고정하고 타단을 노출시킨 후,
상기 제1유닛(100-1)에서 노출된 상기 보강재(1000)를 상기 제2유닛(100-2)의 어느 한 레벨의 상기 보강재설치홀(130)을 관통하여 타단을 당겨 포스트텐션을 부여한 후 상기 제2유닛(100-2)에 정착구(1010)로 고정하므로,
다수개의 상기 개량형 사면 보강 패널 유닛(100) 상호간을 다수개의 상기 정착구(1010)가 중첩되어 포스트텐션을 부여하며 결속하는 것을 특징으로 한다.
By forming a plurality of reinforcement installation holes 130 at different levels in the improved slope reinforcement panel unit 100,
The reinforcing material 1000 is installed by crossing and applying the above-described second method to the plurality of reinforcing material installation holes 130 having different levels.
In other words, in the improved slope reinforcement panel unit 100, two or more reinforcement installation holes 130 are formed horizontally at different levels,
When naming the two prepared slope reinforcement panel units 100 as the first unit 100-1 and the second unit 100-2, respectively,
One end of the reinforcing material 1000 installed in the reinforcing material installation hole 130 of any one level of the first unit 100-1 is fixed to the anchorage 1010 and the other end is exposed,
After fixing one end of the reinforcing material 1000 to the reinforcing material installation hole 130 of the second unit 100-2 with an anchorage 1010 and exposing the other end,
The reinforcing material 1000 exposed in the first unit 100-1 is passed through the reinforcing material installation hole 130 of any one level of the second unit 100-2 and the other end is pulled to give post-tension. Since the anchorage 1010 is fixed to the second unit 100-2,
It is characterized in that the plurality of anchorages 1010 are overlapped with each other to provide post-tension and bind the plurality of the improved slope reinforcement panel units 100 to each other.

삭제delete

도 6 및 7에 도시된 실시예가 상기 보강재설치홀(130)을 상단과 중단에 형성한 것이라면,If the embodiment shown in FIGS. 6 and 7 is to form the reinforcement installation hole 130 at the top and the middle,

도 8 및 9에 도시된 실시예는 상기 보강재설치홀(130)을 상단과 하단에 형성한 것이다.In the embodiment shown in FIGS. 8 and 9, the reinforcement installation holes 130 are formed at the top and bottom.

도 10은 본 발명의 개량형 사면 보강 패널 유닛을 이용한 사면 보강 구조에 보강재를 적용한 다른 실시예이다.10 is another embodiment in which reinforcement is applied to a slope reinforcement structure using an improved slope reinforcement panel unit of the present invention.

도 10의 설치예는 횡으로 적층되는 개량형 사면 보강 패널 유닛(100) 상호간에 레벨차를 달리하여 설치될 경우,In the installation example of FIG. 10, when the horizontally stacked improved slope reinforcement panel units 100 are installed with different level differences between each other,

레벨차를 달리하여 형성된 상기 보강재설치홀(130)을 이용하여, 상기 보강재(1000)를 설치한 것이다.The reinforcing material 1000 is installed using the reinforcing material installation hole 130 formed by varying the level difference.

본 발명은 상기에서 언급한 바와 같이 바람직한 실시예와 관련하여 설명되었으나, 본 발명의 요지를 벗어남이 없는 범위 내에서 다양한 수정 및 변형이 가능하며, 다양한 분야에서 사용 가능하다. Although the present invention has been described in relation to the preferred embodiments as mentioned above, various modifications and variations are possible within the scope without departing from the gist of the present invention, and can be used in various fields.

따라서 본 발명의 청구범위는 이건 발명의 진정한 범위 내에 속하는 수정 및 변형을 포함한다.Accordingly, the claims of this invention include the modifications and variations which fall within the true scope of this invention.

S: 사면
AC: 네일
BF: 뒤채움재
100: 개량형 사면 보강 패널 유닛
100-1: 제1유닛
100-2: 제2유닛
111: 상부홀
113: 하부돌기
121: 측면돌기
123: 측면홀
120: 네일체관통홀
130: 보강재설치홀
300: 계측기
1000: 보강재
1010: 정착구
S: pardon
AC: Nail
BF: backfill material
100: improved slope reinforcement panel unit
100-1: 1st unit
100-2: second unit
111: upper hole
113: lower protrusion
121: side protrusion
123: side hole
120: nail body through hole
130: reinforcement installation hole
300: instrument
1000: stiffener
1010: anchorage

Claims (3)

상부와 하부에 각각 대응하는 형상으로 상부홀(111)과 하부돌기(113)가 형성되고, 측면과 반대쪽 측면에 각각 대응하는 형상으로 측면돌기(121)와 측면홀(123)이 형성되며, 사면(S) 정면에 다수개가 상하좌우로 적층되어 옹벽체를 구성하는 개량형 사면 보강 패널 유닛(100)을 이용한 것으로,
상기 개량형 사면 보강 패널 유닛(100) 정면에는 후면으로 관통하는 네일체관통홀(120)이 형성되고, 사면(S)에 네일링된 네일(AC)의 타단이 상기 네일체관통홀(120)에 체결되는 것을 특징으로 하며,
상기 측면돌기(121)에서 상기 측면홀(123)을 관통하는 보강재설치홀(130)이 형성되고, 상기 개량형 사면 보강 패널 유닛(100) 다수개가 옆으로 배치될 때, 다수개의 상기 개량형 사면 보강 패널 유닛(100) 상호간에 상기 보강재설치홀(130)을 관통하며 보강재(1000)가 설치되는 것을 특징으로 하되,
상기 개량형 사면 보강 패널 유닛(100)에서 상기 보강재설치홀(130)은 2개 이상이 각각 레벨을 달리하여 수평으로 형성되며,
준비된 2개의 상기 개량형 사면 보강 패널 유닛(100)을 각각 제1유닛(100-1)과 제2유닛(100-2)으로 명명할 때,
상기 제1유닛(100-1)의 어느 한 레벨의 상기 보강재설치홀(130)에 설치된 상기 보강재(1000) 일단을 정착구(1010)로 고정하고 타단을 노출시키고,
상기 제2유닛(100-2)의 다른 레벨의 상기 보강재설치홀(130)에 상기 보강재(1000) 일단을 정착구(1010)로 고정하고 타단을 노출시킨 후,
상기 제1유닛(100-1)에서 노출된 상기 보강재(1000)를 상기 제2유닛(100-2)의 어느 한 레벨의 상기 보강재설치홀(130)을 관통하여 타단을 당겨 포스트텐션을 부여한 후 상기 제2유닛(100-2)에 정착구(1010)로 고정하므로,
다수개의 상기 개량형 사면 보강 패널 유닛(100) 상호간을 다수개의 상기 정착구(1010)가 중첩되어 포스트텐션을 부여하며 결속하는 것을 특징으로 하는 개량형 사면 보강 패널 유을 이용한 사면 보강 구조.
Upper holes 111 and lower projections 113 are formed in shapes corresponding to the upper and lower parts, and side projections 121 and side holes 123 are formed in shapes corresponding to the side and the opposite side, respectively. (S) Using the improved slope reinforcement panel unit 100, which is stacked vertically and horizontally on the front side to form a retaining wall,
A nail body through hole 120 penetrating the rear side is formed on the front side of the improved slope reinforcing panel unit 100, and the other end of the nail AC nailed to the slope S is passed through the nail body through hole 120. characterized in that it is fastened,
A reinforcement installation hole 130 penetrating the side hole 123 is formed in the side protrusion 121, and when a plurality of the improved slope reinforcement panel units 100 are arranged sideways, the plurality of the improved slope reinforcement panels It is characterized in that the reinforcing material 1000 is installed between the units 100 through the reinforcing material installation hole 130,
In the improved slope reinforcement panel unit 100, two or more reinforcement installation holes 130 are formed horizontally at different levels,
When naming the two prepared slope reinforcement panel units 100 as the first unit 100-1 and the second unit 100-2, respectively,
One end of the reinforcing material 1000 installed in the reinforcing material installation hole 130 of any one level of the first unit 100-1 is fixed to the anchorage 1010 and the other end is exposed,
After fixing one end of the reinforcing material 1000 to the reinforcing material installation hole 130 of the second unit 100-2 with the anchorage 1010 and exposing the other end,
The reinforcing material 1000 exposed in the first unit 100-1 is passed through the reinforcing material installation hole 130 of any one level of the second unit 100-2 and the other end is pulled to give post-tension. Since the anchorage 1010 is fixed to the second unit 100-2,
A slope reinforcement structure using an improved slope reinforcement panel type, characterized in that a plurality of the improved slope reinforcement panel units 100 are overlapped with a plurality of anchorages 1010 to give post-tension and bind.
삭제delete 삭제delete
KR1020220070138A 2022-06-09 2022-06-09 the improved panel unit for reinforcing slope and the reinforcing slope structure using the same KR102561586B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020220070138A KR102561586B1 (en) 2022-06-09 2022-06-09 the improved panel unit for reinforcing slope and the reinforcing slope structure using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020220070138A KR102561586B1 (en) 2022-06-09 2022-06-09 the improved panel unit for reinforcing slope and the reinforcing slope structure using the same

Publications (1)

Publication Number Publication Date
KR102561586B1 true KR102561586B1 (en) 2023-07-31

Family

ID=87458365

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020220070138A KR102561586B1 (en) 2022-06-09 2022-06-09 the improved panel unit for reinforcing slope and the reinforcing slope structure using the same

Country Status (1)

Country Link
KR (1) KR102561586B1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR980002478A (en) * 1998-01-14 1998-03-30 박병영 Construction Method of Block Reinforced Earth Retaining Wall
JP2000309929A (en) * 1999-04-28 2000-11-07 Kensetsu Kiso Eng Co Ltd Earth retaining wall
KR100372821B1 (en) 1999-09-20 2003-02-20 윤남식 Passive reinforced nail wall for cutting slope
KR101622190B1 (en) * 2015-08-03 2016-05-18 그린이엔지 주식회사 Slate pannel and retaining wall using the same
KR102006305B1 (en) 2018-12-24 2019-08-01 (주)지성이씨에스 Block structure for retaining wall of cut-slope and back-filing side

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR980002478A (en) * 1998-01-14 1998-03-30 박병영 Construction Method of Block Reinforced Earth Retaining Wall
JP2000309929A (en) * 1999-04-28 2000-11-07 Kensetsu Kiso Eng Co Ltd Earth retaining wall
KR100372821B1 (en) 1999-09-20 2003-02-20 윤남식 Passive reinforced nail wall for cutting slope
KR101622190B1 (en) * 2015-08-03 2016-05-18 그린이엔지 주식회사 Slate pannel and retaining wall using the same
KR102006305B1 (en) 2018-12-24 2019-08-01 (주)지성이씨에스 Block structure for retaining wall of cut-slope and back-filing side

Similar Documents

Publication Publication Date Title
KR100799358B1 (en) Combined retaining wall and method for constructing thereof
KR101023660B1 (en) Retaining Wall using Anchor and Concrete Panel and its Construction Method
KR100640716B1 (en) Precast concrete block for cantilever retaining wall and construction method using the same
US5551810A (en) Retaining wall with an outer face and method of forming the same
JP2007530833A (en) Reinforced soil retaining wall system and construction method
KR101105092B1 (en) A precast retaining panel and construction method of the same with half pc type backfill
KR101027800B1 (en) Prefabricated revet construction and method for constructing the same
KR20110033650A (en) Method for underground roadway using slurry wall method
US20210017755A1 (en) Composite wall and methods of constructing a composite wall
KR102561586B1 (en) the improved panel unit for reinforcing slope and the reinforcing slope structure using the same
KR101194043B1 (en) Prefabricated Revet Construction and Method for Constructing the same
CN106223477A (en) A kind of precast reinforced concrete structure method of attachment
KR102111153B1 (en) Retaining Wall Panel Structure using PC Strand
KR102511425B1 (en) the half precast concrete type retaining wall structure
KR200420394Y1 (en) Precast concrete block for cantilever retaining wall
KR102352069B1 (en) A reinforcing support system of retaining wall block for excellent seismic performance and the contruction method thereof
KR100919921B1 (en) Retaining Wall using Panel and Constructing Method thereof
KR100317701B1 (en) a reinforcement land method of construction to using tires
KR102079676B1 (en) Method and apparatus for cascading retaining wall using anchor panel
KR200223114Y1 (en) A structure reinforcing for retaining wall for inclined plane which to cut off a rock wall
KR100964721B1 (en) Block for road extension
KR102388496B1 (en) Extension panel of cut retaining wall and its construction method
JPH09203053A (en) Precast reinforced concrete foundation structure
JP3710434B2 (en) Widening road
KR20110103087A (en) Power transmission manhole

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant