KR102557752B1 - Pre-drilling and positioning method for installation of jacket foundation - Google Patents

Pre-drilling and positioning method for installation of jacket foundation Download PDF

Info

Publication number
KR102557752B1
KR102557752B1 KR1020210049710A KR20210049710A KR102557752B1 KR 102557752 B1 KR102557752 B1 KR 102557752B1 KR 1020210049710 A KR1020210049710 A KR 1020210049710A KR 20210049710 A KR20210049710 A KR 20210049710A KR 102557752 B1 KR102557752 B1 KR 102557752B1
Authority
KR
South Korea
Prior art keywords
perforation
penetration
jacket
foundation structure
pile
Prior art date
Application number
KR1020210049710A
Other languages
Korean (ko)
Other versions
KR20220143318A (en
Inventor
김현일
김동준
이상휴
최윤호
Original Assignee
현대건설주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 현대건설주식회사 filed Critical 현대건설주식회사
Priority to KR1020210049710A priority Critical patent/KR102557752B1/en
Publication of KR20220143318A publication Critical patent/KR20220143318A/en
Application granted granted Critical
Publication of KR102557752B1 publication Critical patent/KR102557752B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/0008Methods for grouting offshore structures; apparatus therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/06Constructions, or methods of constructing, in water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/727Offshore wind turbines

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Foundations (AREA)

Abstract

본 발명은 자켓 기초구조물 선천공 거치 시공방법 및 이를 이용한 자켓 기초구조물에 관한 것이다. 이를 위하여, 해저 지반의 특정 설치 위치에 설치되는 자켓 기초구조물에 있어서, 관입부가 삽입되기 이전에, 설치 위치에 관입부와 대응되도록 복수개가 선천공 시공되는 천공부;를 포함하고, 관입부는 천공부에 삽입되어 자켓부가 설치 위치에 거치되는 것을 제공할 수 있다. The present invention relates to a pre-drilling installation method for a jacket foundation structure and a jacket foundation structure using the same. To this end, in the jacket foundation structure installed at a specific installation location on the seabed, before the penetration portion is inserted, a plurality of perforations are pre-drilled to correspond to the penetration portion at the installation location; The penetration portion is inserted into the perforation portion to provide that the jacket portion is mounted at the installation location.

Description

자켓 기초구조물 선천공 거치 시공방법 및 이를 이용한 자켓 기초구조물{Pre-drilling and positioning method for installation of jacket foundation}Pre-drilling and positioning method for installation of jacket foundation

본 발명은 자켓 기초구조물 선천공 거치 시공방법 및 이를 이용한 자켓 기초구조물에 관한 것이다.The present invention relates to a pre-drilling installation method for a jacket foundation structure and a jacket foundation structure using the same.

일반적으로 해상 구조물은 해저에 고정되는 기초를 가지고 해상에 설치될 수 있는 다양한 구조물을 말하며, 대표적으로는 해상 풍력발전 장치, 해상 석유시추 플랫폼과 같은 Oil 이나 Gas의 생산 구조물, 해양과학기지 구조물, 항만 구조물 등이 있다. 이러한 해상 구조물은 해저에 고정되는 기초구조물 위에 안착되어 고정되며, 기초구조물은 통상 해저에 고정되어 기초 구조를 형성하는 기초구조물 및 이러한 기초구조물의 상단에 상부구조물을 설치하기 위한 데크를 포함하며, 데크 상에는 상부구조물이 설치된다. 도 1은 해상풍력발전의 기초구조물의 예시를 도시한 모식도이다. 도 1에 도시된 바와 같이, 기초구조물은 그 형상에 따라 모노파일(monopile)형, 트라이포드(tripod)형, 돌핀(dolphin)형, 자켓(jacket)형, 부유식 구조 등으로 구분된다. 이 중에서 자켓형은 기초구조물에 수평으로 작용하는 파력에 대해 비교적 안정적인 구조를 가지고, 지반정리가 최소로 요구되며, 소구경 Pile로도 시공이 가능하여 선호도가 높은 형식에 해당된다. In general, offshore structures refer to various structures that can be installed on the sea with foundations fixed to the seabed. Representative examples include offshore wind power generators, oil and gas production structures such as offshore oil drilling platforms, marine science base structures, and harbor structures. Such an offshore structure is seated and fixed on a foundation structure fixed to the seabed, and the foundation structure is usually fixed to the seabed to form a foundation structure and a deck for installing an upper structure on top of the foundation structure. An upper structure is installed on the deck. 1 is a schematic diagram showing an example of a basic structure of offshore wind power generation. As shown in FIG. 1, the foundation structure is classified into a monopile type, a tripod type, a dolphin type, a jacket type, a floating structure, and the like according to its shape. Among them, the jacket type has a relatively stable structure against the wave force acting horizontally on the foundation structure, requires minimal ground clearance, and can be constructed with small-diameter piles, so it corresponds to a highly preferred type.

자켓형 기초구조물과 관련하여, 도 2는 자켓 기초구조물을 도시한 모식도이다. 도 2에 도시된 바와 같이, 일반적인 자켓형 기초구조물이 적용된 기초구조물은 강관으로 구성된 레그를 해저면에 세우고, 레그와 레그 사이에 브레이스 부재를 설치하여 입체 트러스 구조를 형성하며, 레그를 해저에 고정하기 위해 파일이 추가로 설치되는 형태이다. 자켓형 기초구조물은, 일반적으로 4개의 레그(Leg) 및 레그 사이를 연결하는 복수개의 브레이스(Brace)로 구성되고, 이러한 레그는 말뚝(Pile)에 의해 지반에 지지되도록 구성될 수 있다. Regarding the jacketed foundation structure, FIG. 2 is a schematic diagram showing the jacketed foundation structure. As shown in FIG. 2, the foundation structure to which a general jacket-type foundation structure is applied is a type in which legs made of steel pipes are erected on the sea floor, brace members are installed between legs to form a three-dimensional truss structure, and piles are additionally installed to fix the legs to the sea floor. A jacketed foundation structure is generally composed of four legs and a plurality of braces connecting between the legs, and these legs may be configured to be supported on the ground by piles.

일반적인 자켓형 기초구조물의 시공은 설치 위치의 지반 정리 단계, 바지선 등을 이용한 자켓 기초구조물 운송 단계, 예정 위치에 자켓 거치 단계, 파일 항타 단계, 자켓-파일 연결부 용접 및 그라우팅 단계로 진행된다.The construction of a general jacket type foundation structure proceeds in the following steps: ground preparation at the installation location, transportation of the jacket foundation structure using a barge, etc., installation of the jacket at the intended location, pile driving, welding and grouting of the jacket-pile connection.

대한민국 공개특허, 공개번호 10-2015-0077787, 부력탱크를 이용한 해상풍력 자켓 기초구조물 시공 방법, 주식회사 포스코건설Republic of Korea Patent Publication No. 10-2015-0077787, Offshore wind power jacket basic structure construction method using buoyancy tank, POSCO E&C 대한민국 공개특허, 공개번호 10-2015-0077748, 수직 레그가 형성된 자켓 기초구조물의 시공방법, 주식회사 포스코건설Republic of Korea Patent Publication No. 10-2015-0077748, construction method of jacket foundation structure with vertical legs formed, POSCO E&C Co., Ltd.

일반적인 경우, 해저 지반에 토사층이 존재하므로 자켓을 거치 후 파일을 즉시 설치하여 외력에 대한 안정성을 후속 작업이 가능한 수준 이상으로 확보할 수 있다. 그러나, 해저면에 암반이 노출되거나 충분한 두께의 토사층이 존재하지 않는 조건(국내에서는 대표적으로 제주도 연안 지역과 같은 조건)에서는 자켓 거치 후 파일의 즉시 설치가 불가하고 암반 굴착 등의 작업이 수행되어야 한다. 따라서, 파일의 설치가 완료되기 전까지 기간이 증가되며 그만큼 자켓 기초구조물이 외력(파력, 조력, 풍하중 등)에 의하여 전도되거나 활동이 발생할 위험성이 높아지는 문제가 있었다. 파일의 설치가 완료되기 이전 자켓 기초구조물의 임시 거치 기간 동안의 안정성을 확보하기 위한 기존의 방법은 별도의 고정용 지그를 설치하거나, 바닥면에 버림 콘크리트를 타설하는 방법 등이 있었다. In general, since there is a layer of soil on the seabed, it is possible to secure stability against external forces to a level that allows subsequent work by immediately installing piles after passing through the jacket. However, under conditions where bedrock is exposed on the seabed or soil layer of sufficient thickness does not exist (typically in Korea, conditions such as the coastal area of Jeju Island), piles cannot be installed immediately after the jacket is mounted, and work such as bedrock excavation must be performed. Therefore, the period until the installation of the pile is completed increases, and there is a problem that the jacket foundation structure is overturned by external force (wave force, tidal force, wind load, etc.) or the risk of activity increases. Existing methods to secure stability during the temporary standing period of the jacket foundation structure before the pile installation is completed include installing a separate fixing jig or pouring cast-off concrete on the floor.

구체적으로, 도 3은 기존의 임시 거치 방법 중 자켓 고정용 지그를 활용하는 시공 방법을 도시한 모식도이다. 도 3에 도시된 바와 같이, 기존의 임시 거치 방법으로는 자켓 고정용 지그 설치 및 제거의 공정 추가로 인해 공기 및 공사비가 증대되는 문제가 있었다. 또한, 도 4는 기존의 임시 거치 방법 중 퇴적층 준설 및 버림 콘크리트 타설 방법을 도시한 모식도이다. 도 4에 도시된 바와 같이, 기존 공법 적용 시 파일 고정을 위해 자켓 기초구조물의 Leg can 하단부까지 버림 콘크리트 타설이 필요하나, 해저 지반의 EL(Elevation Level)이 불규칙하기 때문에 자켓 호기별로 상이한 시공이 필요하여 시공성이 다소 떨어지게 되는 문제가 있었다. Specifically, FIG. 3 is a schematic diagram showing a construction method using a jig for fixing a jacket among existing temporary mounting methods. As shown in FIG. 3 , the existing temporary mounting method has a problem in that time and construction costs increase due to the addition of the process of installing and removing the jig for fixing the jacket. In addition, FIG. 4 is a schematic diagram showing a method of dredging a sedimentary layer and pouring abandoned concrete among existing temporary mounting methods. As shown in FIG. 4, when applying the existing method, pouring concrete is required to the lower end of the leg can of the jacket foundation structure to fix the pile, but since the EL (Elevation Level) of the seabed ground is irregular, different construction is required for each jacket unit. There was a problem that the workability was somewhat lowered.

따라서, 본 발명의 목적은, 설치 위치 시공 오차 최소화를 위한 시공 난이도 저감, 해저면 암반층의 경우 추가 지그 설치/제거 공정 배제, EL에 따른 시공성 제약이 해소된 자켓 기초구조물 선천공 거치 시공방법 및 이를 이용한 자켓 기초구조물을 제공하는데에 있다. Therefore, an object of the present invention is to reduce the construction difficulty for minimizing installation position construction errors, to eliminate additional jig installation/removal processes in the case of seabed rock layers, and to provide a pre-drilled installation method for jacket foundation structures in which workability constraints according to EL are resolved, and a jacket foundation structure using the same.

이하 본 발명의 목적을 달성하기 위한 구체적 수단에 대하여 설명한다.Hereinafter, specific means for achieving the object of the present invention will be described.

본 발명의 목적은, 해저 지반의 특정 설치 위치에 설치되는 자켓 기초구조물에 있어서, 상기 자켓 기초구조물의 본체로서, 브레이스 및 레그를 포함하는 자켓부; 상기 레그의 하부에 구성되고, 길이방향이 상기 자켓부의 하방으로 구성되는 관입부; 및 상기 관입부가 삽입되기 이전에, 상기 설치 위치에 상기 관입부와 대응되도록 복수개가 선천공 시공되는 천공부;를 포함하고, 상기 관입부는 상기 천공부에 삽입되어 상기 자켓부가 상기 설치 위치에 거치되는 것을 특징으로 하는, 선천공 거치를 이용한 자켓 기초구조물을 제공하여 달성될 수 있다.An object of the present invention is to provide a jacket foundation structure installed at a specific installation location on the seabed, comprising: a jacket portion including braces and legs as a main body of the jacket foundation structure; a penetrating portion disposed at a lower portion of the leg and extending in a longitudinal direction downward of the jacket portion; And before the penetration portion is inserted, a plurality of perforations are pre-drilled to correspond to the penetration portion at the installation position, wherein the penetration portion is inserted into the perforation portion and the jacket portion is mounted at the installation position.

또는, 상기 해저 지반은 암반층을 의미하는 것을 특징으로 할 수 있다. Alternatively, the seafloor ground may be characterized in that it means a bedrock layer.

또는, 상기 천공부 내측과 상기 관입부 사이의 공간에 시공된 그라우트인 제1그라우팅부;를 더 포함하고, 상기 제1그라우팅부는, 상기 관입부가 상기 천공부에 삽입되어 임시 거치된 이후에 시공되는 것을 특징으로 할 수 있다. Alternatively, a first grouting part, which is a grout installed in a space between the inside of the perforation part and the penetration part, may be further included, and the first grouting part may be constructed after the penetration part is inserted into the perforation part and temporarily held.

또는, 상기 천공부 내측과 상기 관입부 사이의 공간에 시공된 그라우트인 제1그라우팅부; 상기 관입부를 관통하여 상기 천공부의 바닥면에 타설되는 핀파일; 및 상기 핀파일 내부 공간에 시공되는 그라우트, 상기 핀파일 외측과 상기 해저 지반 사이 공간에 시공되는 그라우트 또는 상기 핀파일 외측과 상기 관입부 내측 사이의 공간에 시공되는 그라우트를 포함하는 제2그라우팅부;를 더 포함하고, 상기 제1그라우팅부는, 상기 관입부가 상기 천공부에 삽입되어 임시 거치된 이후에 시공되며, 상기 제1그라우팅부가 시공된 이후에 상기 핀파일이 시공되고, 상기 핀파일이 시공된 이후에 상기 제2그라우팅부가 시공되는 것을 특징으로 할 수 있다. Alternatively, a first grouting part that is a grout applied to the space between the inside of the perforation part and the intrusion part; A pin file that penetrates the penetration portion and is poured on the bottom surface of the perforation portion; and a second grouting part including grout applied to the inner space of the fin pile, grout applied to the space between the outside of the fin pile and the seafloor ground, or grout applied to the space between the outside of the fin pile and the inside of the penetrating part, wherein the first grouting part is constructed after the penetrating part is inserted into the perforation and temporarily held, the fin pile is constructed after the first grouting part is constructed, and the fin pile is constructed after the fin pile is constructed. It may be characterized in that the second grouting part is constructed.

또는, 상기 관입부 외측에 상기 관입부를 감싸도록 구성되고, 나선형 띠철근과 기둥주근으로 구성된 철근 보강 또는 철근 선타설 보강으로 구성되는 보강재; 및 상기 천공부 내측과 상기 관입부 사이의 공간에 시공된 그라우트인 제1그라우팅부;를 더 포함하고, 상기 제1그라우팅부는, 상기 관입부가 상기 천공부에 삽입되어 임시 거치된 이후에 시공되며, 상기 관입부, 상기 보강재 및 상기 천공부를 일체화 하는 것을 특징으로 할 수 있다. Alternatively, a reinforcing material configured to surround the penetration portion outside the penetration portion and composed of reinforcing bar reinforcement or reinforcing bar line casting reinforcement composed of spiral strip reinforcement and column main bars; and a first grouting part, which is a grout applied to a space between an inside of the perforation part and the penetration part, wherein the first grouting part is constructed after the penetration part is inserted into the perforation part and temporarily held, and the penetration part, the reinforcing material, and the perforation part are integrated.

또는, 상기 설치 위치 중 상기 해저 지반의 EL(Elevation Level)이 가장 높은 위치에 시공된 상기 천공부에 가장 먼저 상기 관입부가 일부 삽입되고, 상기 자켓부가 횡방향으로 회전되어 상기 천공부에 상기 관입부의 위치가 연직 방향으로 일치되도록 조정된 뒤, 상기 천공부에 상기 관입부가 삽입되어 상기 자켓부가 상기 설치 위치에 설치되는 것을 특징으로 할 수 있다. Alternatively, the penetration part is first partially inserted into the perforation constructed at the highest elevation level (EL) of the seabed ground among the installation positions, and the jacket part is rotated in the transverse direction to the perforation. After the position is adjusted to match the perforation part in the vertical direction, the penetration part is inserted into the perforation part, and the jacket part is installed at the installation position.

또한, 상기 관입부의 외측, 내측 또는 하단에 상기 관입부의 수직방향으로 돌출 구성되는 플랜지부; 및 상측은 상기 플랜지부에 수직으로 체결되고, 하측은 상기 천공부의 하부 지반을 지지하도록 구성되며, 상기 관입부의 길이방향으로 길이가 연장되거나 수축되도록 구성되는 승하강 모듈;을 더 포함하고, 상기 승하강 모듈의 연장 또는 수축에 의해 상기 천공부의 상기 하부 지반에 대한 상기 관입부의 상하 위치가 조정되고, 상기 플랜지부와 상기 승하강 모듈은 상기 관입부의 내부 공간이 종방향으로 개방되도록 구성되는 것을 특징으로 할 수 있다. In addition, the flange portion configured to protrude in the vertical direction of the penetration portion on the outside, inside or bottom of the penetration portion; and an elevating module having an upper side vertically fastened to the flange portion, a lower side configured to support the lower ground of the perforation portion, and configured to extend or contract in length in the longitudinal direction of the penetration portion. The elevational position of the penetration portion relative to the lower ground of the perforation portion is adjusted by extension or contraction of the elevating module, and the flange portion and the elevating module are configured such that an internal space of the penetration portion is opened in a longitudinal direction.

또한, 상기 천공부는 상기 관입부의 길이보다 깊은 깊이로 과천공 시공되고, 상기 천공부의 하부 지반에 되메움 시공 또는 버림 콘크리트 타설 시공되는 세부조정부;를 더 포함하며, 상기 세부조정부 시공을 통하여 상기 관입부의 레벨링 또는 수직도 조절을 수행하는 것을 특징으로 할 수 있다. In addition, the perforation part is over-drilled to a depth greater than the length of the penetration part, and further includes a detailed adjustment part in which backfilling or abandoned concrete is poured into the ground below the perforation part.

본 발명의 다른 목적은, 해저 지반의 특정 설치 위치에 설치되는 자켓 기초구조물에 있어서, 상기 자켓 기초구조물의 본체로서, 브레이스 및 레그를 포함하는 자켓부; 및 상기 레그의 하부에 구성되고, 길이방향이 상기 자켓부의 하방으로 구성되는 관입부;및 를 포함하고, 상기 관입부는, 상기 관입부가 삽입되기 이전에 상기 설치 위치에 상기 관입부에 대응되도록 복수개가 선천공 시공된 천공부에 삽입되어 상기 자켓부가 상기 설치 위치에 거치되는 것을 특징으로 하는, 선천공 거치를 이용한 자켓 기초구조물을 제공하여 달성될 수 있다. Another object of the present invention is to provide a jacket foundation structure installed at a specific installation location on the seabed, as a main body of the jacket foundation structure, comprising: a jacket portion including braces and legs; and a penetrating part formed at the lower part of the leg and having a longitudinal direction below the jacket part; and including, wherein the penetrating part is inserted into a plurality of pre-drilled perforated parts to correspond to the penetrating part at the installation position before the penetrating part is inserted, and the jacket part is mounted at the installation position.

본 발명의 다른 목적은, 해저 지반의 특정 설치 위치에 설치되는 자켓 기초구조물의 본체로서, 브레이스 및 레그를 포함하는 자켓부; 및 상기 레그의 하부에 구성되고, 길이방향이 상기 자켓부의 하방으로 구성되는 관입부;를 포함하는 자켓 기초구조물의 시공방법에 있어서, 상기 설치 위치에 상기 관입부와 대응되도록 복수개 선천공 시공하여 천공부를 생성하는 선천공 단계; 및 상기 관입부를 상기 천공부에 삽입하여 상기 자켓부를 상기 설치 위치에 거치하는 임시 거치 단계;를 포함하는, 자켓 기초구조물의 선천공 거치 시공방법을 제공하여 달성될 수 있다.Another object of the present invention is a main body of a jacket foundation structure installed at a specific installation location on the seabed ground, comprising: a jacket portion including braces and legs; and a penetrating portion formed at a lower portion of the leg and having a lengthwise direction lower than the jacket portion, wherein a plurality of pre-drilling is performed to correspond to the penetrating portion at the installation location to create a perforated portion; It can be achieved by providing a pre-drilled mounting construction method for a jacket foundation structure, including; and a temporary mounting step of inserting the penetration part into the perforation part and mounting the jacket part at the installation position.

또는, 상기 해저 지반은 암반층을 의미하는 것을 특징으로 할 수 있다. Alternatively, the seafloor ground may be characterized in that it means a bedrock layer.

또는, 상기 임시 거치 단계 이후에, 상기 천공부 내측과 상기 관입부 사이의 공간에 제1그라우팅부를 시공하는 제1그라우팅 단계;를 더 포함하는 것을 특징으로 할 수 있다. Alternatively, the method may further include a first grouting step of constructing a first grouting part in a space between the inside of the perforation part and the intrusion part after the temporary mounting step.

또는, 상기 임시 거치 단계 이후에, 상기 천공부 내측과 상기 관입부 사이의 공간에 제1그라우팅부를 시공하는 제1그라우팅 단계; 핀파일을 상기 관입부를 관통하여 상기 천공부의 바닥면에 타설하는 파일 시공 단계; 및 상기 핀파일 내부 공간, 상기 핀파일 외측과 상기 해저 지반 사이 공간 또는 상기 핀파일 외측과 상기 관입부 내측 사이의 공간에 제2그라우팅부를 시공하는 제2그라우팅 단계;를 더 포함하는 것을 특징으로 할 수 있다. Alternatively, after the temporary mounting step, a first grouting step of constructing a first grouting part in the space between the inside of the perforation part and the intrusion part; A pile construction step of pouring a pin pile through the penetration part to the bottom surface of the perforation part; and a second grouting step of constructing a second grouting part in a space inside the fin pile, a space between the outside of the fin pile and the seafloor ground, or a space between the outside of the fin pile and the inside of the penetration part.

또는, 상기 임시 거치 단계 이전에, 나선형 띠철근과 기둥주근으로 구성된 철근 보강 또는 철근 선타설 보강으로 구성되는 보강재를 상기 관입부 외측에 상기 관입부를 감싸도록 구성하는 보강 단계; 를 더 포함하고, 상기 임시 거치 단계 이후에, 상기 천공부 내측과 상기 관입부 사이의 공간에 제1그라우팅부를 시공하는 제1그라우팅 단계;를 더 포함하며, 상기 제1그라우팅부는, 상기 관입부, 상기 보강재 및 상기 천공부를 일체화 하는 것을 특징으로 할 수 있다. Alternatively, prior to the temporary installation step, a reinforcing step of configuring a reinforcing material composed of reinforcing bars composed of spiral strip reinforcing bars and column main bars or reinforcing bar line casting reinforcement to surround the intrusion portion outside the intrusion portion; and a first grouting step of constructing a first grouting part in a space between the inside of the perforation part and the penetration part after the temporary mounting step, wherein the first grouting part integrates the penetration part, the reinforcing material, and the perforation part.

또는, 상기 임시 거치 단계는, 상기 설치 위치 중 상기 해저 지반의 EL(Elevation Level)이 가장 높은 위치에 시공된 상기 천공부에 가장 먼저 상기 관입부를 일부 삽입하고, 상기 자켓부를 횡방향으로 회전하여 상기 천공부에 상기 관입부의 위치가 연직 방향으로 일치되도록 조정한 뒤, 상기 천공부에 상기 관입부를 삽입하여 상기 자켓부를 상기 설치 위치에 거치하는 것을 특징으로 할 수 있다. Alternatively, the temporary mounting step may include first partially inserting the penetration part into the perforation constructed at the highest elevation level (EL) of the seafloor ground among the installation positions, rotating the jacket part in the horizontal direction, adjusting the position of the penetration part to match the perforation part in the vertical direction, and then inserting the penetration part into the perforation part to mount the jacket part at the installation position.

또는, 상기 자켓 기초구조물은 상기 관입부의 외측, 내측 또는 하단에 상기 관입부의 수직방향으로 돌출 구성되는 플랜지부; 및 상측은 상기 플랜지부에 수직으로 체결되고, 하측은 상기 천공부의 하부 지반을 지지하도록 구성되며, 상기 관입부의 길이방향으로 길이가 연장되거나 수축되도록 구성되는 승하강 모듈;을 더 포함하고, 상기 플랜지부와 상기 승하강 모듈은 상기 관입부의 내부 공간이 종방향으로 개방되도록 구성되며, 상기 임시 거치 단계 이후에, 상기 승하강 모듈의 연장 또는 수축을 수행하여 상기 천공부의 상기 하부 지반에 대한 상기 관입부의 상하 위치를 조정하여 상기 자켓 기초구조물의 수직도를 미세조정하는 수직도 미세조정 단계;를 더 포함하는 것을 특징으로 할 수 있다. Alternatively, the jacket base structure may include a flange portion protruding in a vertical direction of the penetration portion at an outer side, an inside side, or a lower end of the penetration portion; and an elevating module, the upper side of which is vertically fastened to the flange portion, the lower side of which is configured to support the lower ground of the perforation portion, and the elevating module configured to extend or contract in the longitudinal direction of the penetration portion, wherein the flange portion and the elevating module are configured to open the internal space of the penetration portion in the longitudinal direction, and after the temporary mounting step, the elevating module is extended or contracted to adjust the vertical position of the penetration portion with respect to the lower ground of the perforation portion. It may be characterized in that it further comprises; verticality fine-adjustment step of fine-tuning the verticality.

또한, 상기 자켓 기초구조물의 상기 천공부는 상기 관입부의 길이보다 깊은 깊이로 과천공 시공되고, 상기 천공부의 하부 지반에 되메움 시공 또는 버림 콘크리트 타설 시공되는 세부조정부를 더 포함하며, 상기 선천공 단계 이후에, 상기 천공부의 하부 지반에 상기 세부조정부 시공을 통하여 상기 관입부의 레벨링 또는 수직도 조절을 수행하는 세부조정 단계;를 더 포함하는 것을 특징으로 할 수 있다. In addition, the perforation part of the jacket foundation structure is over-drilled to a depth greater than the length of the penetration part, and further includes a detailed adjustment part in which backfilling or discarded concrete is poured into the ground below the perforation part. After the pre-piercing step, a detailed adjustment step of leveling or adjusting the verticality of the penetration part through the construction of the detailed adjustment part in the ground below the perforation part; may be characterized in that it further comprises.

상기한 바와 같이, 본 발명에 의하면 이하와 같은 효과가 있다.As described above, the present invention has the following effects.

첫째, 본 발명의 일실시예에 따르면, 자켓 기초구조물의 관입부를 천공부 내 관입 이후에 위치를 조정하게 되므로, 설치 위치 시공 오차 최소화를 위한 시공 난이도가 저감되는 효과가 발생된다. First, according to one embodiment of the present invention, since the position of the penetration part of the jacket base structure is adjusted after penetration into the perforation part, the effect of reducing the construction difficulty for minimizing the installation position construction error occurs.

둘째, 본 발명의 일실시예에 따르면, 해저면 암반층에 자켓 기초를 시공하는 경우 추가 지그 설치/제거 공정이 배제되는 효과가 발생된다. Second, according to one embodiment of the present invention, when constructing the jacket foundation on the seabed rock layer, an additional jig installation/removal process is excluded.

셋째, 본 발명의 일실시예에 따르면, 해저 지반의 EL(Elevation Level)에 따른 시공성 제약이 해소되는 효과가 발생된다. 해저면 암반층에 기존 공법 적용 시, 파일 고정을 위해 버림 콘크리트 타설이 필요하나, 해저 지반의 EL이 불규칙하기 때문에 시공성이 다소 떨어지게 되는 문제가 있다. 본 발명의 일실시예에 따르면, 천공부의 그라우트가 파일을 고정하기 때문에 추가적인 고정 작업이 불필요해지고, 이에 따라 해저 지반의 EL에 따른 시공성 제약이 해소되는 효과가 발생된다. Thirdly, according to one embodiment of the present invention, the effect of dissolving the constructability constraints according to the EL (Elevation Level) of the seabed ground is generated. When applying the existing method to the seabed rock layer, it is necessary to pour cast concrete to fix the pile, but there is a problem that the workability is somewhat lowered because the EL of the seabed ground is irregular. According to one embodiment of the present invention, since the grout of the perforation part fixes the pile, additional fixing work is unnecessary, and thus, the effect of solving the workability restriction according to the EL of the seabed ground occurs.

넷째, 본 발명의 일실시예에 따르면, 해저 암반층 선천공 후 자켓 임시 거치 시, 자켓 기초구조물의 시공 중 전도 및 활동에 대한 안정성 확보할 수 있으며, 구조물을 정확한 위치에 거치도 가능해지는 효과가 발생된다. Fourth, according to one embodiment of the present invention, when the jacket is temporarily mounted after the pre-drilling of the seabed bedrock layer, the stability of the jacket base structure during construction can be ensured, and the structure can be mounted at the correct position.

다섯째, 본 발명의 일실시예에 따르면, 자켓 기초구조물의 레그 외부가 주변 암반과 선(先)그라우팅 시공되어 있으므로, 파일 주변의 그라우팅 유출이 방지되는 효과가 발생된다. 도 5는 기존의 일반 공법에 따라 레그 하단과 암반 사이의 밀폐 작업을 도시한 모식도이다. 도 5와 같이, 기존의 일반 공법에 따르면, 자켓 기초구조물의 레그 하단과 암반 사이에서 그라우트가 유출되는 것을 방지하기 위하여 Rubber Pad(도 5의 a), 반구 Rubber(도 5의 b), Rubber packing(도 5의 c), 그라우트 유출 최소화 작업(도 5의 d) 등을 이용한 밀폐 시공이 별도로 필요하게 되며, 이는 추가적인 밀폐 작업으로서 공기 증가 및 시공성 저하의 문제를 야기하고 있었다. Fifth, according to one embodiment of the present invention, since the outside of the leg of the jacket foundation structure is pre-grouted with the surrounding bedrock, an effect of preventing outflow of grouting around the pile is generated. 5 is a schematic diagram showing a sealing operation between the bottom of a leg and a bedrock according to a conventional general method. As shown in FIG. 5, according to the existing general method, in order to prevent the leakage of grout between the bottom of the leg of the jacket foundation structure and the bedrock, rubber pad (Fig. 5a), hemispherical rubber (Fig. 5b), rubber packing (Fig. 5c), and grout leakage minimization work (Fig.

여섯째, 본 발명의 일실시예에 따르면, 파일 시공 이전 단계에서도 자켓 기초구조물의 안정성을 확보할 수 있으며, 최소한의 암반층 천공을 통해 자켓 기초구조물을 정확한 위치에 거치 및 고정시킬 수 있으며, 천공 작업을 자켓 기초구조물 제작 혹은 운송 단계에 수행하여 공기에 영향을 미치지 않도록 시공이 가능한 효과가 발생된다. Sixth, according to one embodiment of the present invention, the stability of the jacket foundation structure can be secured even in the stage before pile construction, and the jacket foundation structure can be mounted and fixed in an accurate position through the minimum drilling of the rock layer, and the drilling operation is performed in the manufacturing or transportation stage of the jacket foundation structure, so that the construction can be performed so as not to affect the air.

한편, 본 발명에서 얻을 수 있는 효과는 이상에서 언급한 효과들로 제한되지 않으며, 언급하지 않은 또 다른 효과들은 아래의 기재로부터 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 명확하게 이해될 수 있다.On the other hand, the effects obtainable in the present invention are not limited to the effects mentioned above, and other effects not mentioned can be clearly understood by those skilled in the art from the description below.

본 명세서에 첨부되는 다음의 도면들은 본 발명의 바람직한 실시예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 그러한 도면에 기재된 사항에만 한정되어 해석되어서는 아니 된다.
도 1은 해상풍력발전의 기초구조물의 예시를 도시한 모식도,
도 2는 자켓 기초구조물을 도시한 모식도,
도 3은 기존의 임시 거치 방법 중 자켓 고정용 지그를 활용하는 시공 방법을 도시한 모식도,
도 4는 기존의 임시 거치 방법 중 퇴적층 준설 및 버림 콘크리트 타설 방법을 도시한 모식도,
도 5는 기존의 일반 공법에 따라 레그 하단과 암반 사이의 밀폐 작업을 도시한 모식도,
도 6은 본 발명의 일실시예에 따른 자켓 기초구조물 선천공 거치 시공방법을 도시한 흐름도,
도 7은 본 발명의 일실시예에 따른 선천공 단계(S10)를 도시한 모식도,
도 8은 본 발명의 일실시예에 따른 선천공 단계(S10)의 세부조정부(되메움 시공 또는 버림 콘크리트 타설 시공) 시공을 도시한 모식도,
도 9, 10은 본 발명의 일실시예에 따른 임시 거치 단계(S20)를도시한 모식도,
도 11은 본 발명의 제1변형예에 따라 외측 플랜지와 승하강 모듈이 구성된 모식도이고,
도 12는 본 발명의 제2변형예에 따라 하측 또는 내측 플랜지와 승하강 모듈이 구성된 모식도
도 13은 본 발명의 일실시예에 따른 천공부 그라우팅 단계(S30)를 도시한 모식도,
도 14는 본 발명의 일실시예에 따른 파일 시공 단계(S40)를 도시한 모식도,
도 15는 본 발명의 일실시예에 따른 파일 그라우팅 단계(S50)를 도시한 것,
도 16은 본 발명의 일실시예에 따른 보강 단계를 도시한 것이다.
The following drawings attached to this specification illustrate preferred embodiments of the present invention, and together with the detailed description of the invention serve to further understand the technical idea of the present invention, the present invention is limited to those described in the drawings. It should not be construed.
1 is a schematic diagram showing an example of a basic structure of offshore wind power generation;
2 is a schematic diagram showing a jacket basic structure;
3 is a schematic diagram showing a construction method using a jig for fixing a jacket among existing temporary mounting methods;
4 is a schematic diagram showing a sedimentary dredging and discarded concrete pouring method among existing temporary mounting methods;
Figure 5 is a schematic diagram showing the sealing operation between the lower leg and the bedrock according to the existing general method;
6 is a flow chart showing a pre-drilling installation method for a jacket foundation structure according to an embodiment of the present invention;
7 is a schematic diagram showing a pre-piercing step (S10) according to an embodiment of the present invention;
8 is a schematic diagram showing the construction of the detailed adjustment part (backfill construction or abandoned concrete pouring construction) of the pre-drilling step (S10) according to an embodiment of the present invention;
9 and 10 are schematic diagrams showing the temporary mounting step (S20) according to an embodiment of the present invention;
11 is a schematic diagram showing the configuration of an outer flange and an elevating module according to a first modified example of the present invention;
Figure 12 is a schematic diagram of the configuration of the lower or inner flange and the lifting module according to the second modified example of the present invention
13 is a schematic diagram showing a perforation grouting step (S30) according to an embodiment of the present invention;
14 is a schematic diagram showing a pile construction step (S40) according to an embodiment of the present invention;
15 shows a pile grouting step (S50) according to an embodiment of the present invention;
16 illustrates a reinforcement step according to an embodiment of the present invention.

이하 첨부된 도면을 참조하여 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자가 본 발명을 쉽게 실시할 수 있는 실시예를 상세히 설명한다. 다만, 본 발명의 바람직한 실시예에 대한 동작원리를 상세하게 설명함에 있어서 관련된 공지기능 또는 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명을 생략한다.Hereinafter, an embodiment in which a person skilled in the art can easily practice the present invention will be described in detail with reference to the accompanying drawings. However, in the detailed description of the operating principle of the preferred embodiment of the present invention, if it is determined that a detailed description of a related known function or configuration may unnecessarily obscure the subject matter of the present invention, the detailed description will be omitted.

또한, 도면 전체에 걸쳐 유사한 기능 및 작용을 하는 부분에 대해서는 동일한 도면 부호를 사용한다. 명세서 전체에서, 특정 부분이 다른 부분과 연결되어 있다고 할 때, 이는 직접적으로 연결되어 있는 경우뿐만 아니라, 그 중간에 다른 소자를 사이에 두고, 간접적으로 연결되어 있는 경우도 포함한다. 또한, 특정 구성요소를 포함한다는 것은 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라, 다른 구성요소를 더 포함할 수 있는 것을 의미한다.In addition, the same reference numerals are used for parts having similar functions and actions throughout the drawings. Throughout the specification, when a specific part is said to be connected to another part, this includes not only the case where it is directly connected but also the case where it is indirectly connected with another element interposed therebetween. In addition, including a specific component does not exclude other components unless otherwise stated, but means that other components may be further included.

자켓 기초구조물 선천공 거치 시공방법Pre-drilled installation method for jacket foundation structure

도 6은 본 발명의 일실시예에 따른 자켓 기초구조물 선천공 거치 시공방법을 도시한 흐름도이다. 도 6에 도시된 바와 같이, 본 발명의 일실시예에 따른 자켓 기초구조물 선천공 거치 시공방법은, 선천공 단계(S10), 임시 거치 단계(S20), 자켓 관입부 그라우팅 단계(S30), 파일 시공 단계(S40), 파일 그라우팅 단계(S50)를 포함할 수 있다. 6 is a flow chart showing a method for installing pre-drilling of a jacket foundation structure according to an embodiment of the present invention. As shown in FIG. 6, the pre-drilling installation method for the jacket base structure according to an embodiment of the present invention may include a pre-drilling step (S10), a temporary mounting step (S20), a jacket penetration grouting step (S30), a pile construction step (S40), and a pile grouting step (S50).

선천공 단계(S10)는 자켓 기초구조물(10)의 설치 위치를 선천공하여 천공부(1)를 생성하는 단계이다. 도 7은 본 발명의 일실시예에 따른 선천공 단계(S10)를 도시한 모식도이다. 도 7에 도시된 바와 같이, 자켓 기초구조물(10)의 각 관입부(13)의 설치 위치에 관입부(13) 직경보다 넓은 직경으로 선천공 시공하여 천공부(1)를 생성할 수 있다. 예를 들어, 천공부(1)의 직경(w)은 관입부(13) 직경의 1.1배 내지 2배로 구성될 수 있고, 천공부(1)의 깊이(h)는 관입부(13) 길이보다 깊게 구성될 수 있다. 이때, 천공부(1)의 깊이(h)는 시공 환경이나 시공 상황에 따라 관입부(13) 길이보다 얕게 구성되는 것도 가능하다. 본 발명의 일실시예에 따른 천공부(1)의 선천공 시공에 의해 자켓 거치 시의 안정성이 크게 증대되는 효과가 발생된다. 특히, 구조물 높이 대비 특정 수준 이하의 깊이를 가지는 shallow한 천공부(1)의 선천공 시공만으로도 자켓 거치 시의 충분한 안정성을 확보할 수 있는 효과가 발생된다. 이때, 천공부(1)의 직경(w)이 과다하게 넓은 경우에는 자켓 레그와 그라우트 간 접합력이 저하되어 안정성이 저하되는 문제가 발생되고, 천공부(1)의 깊이(h)가 지나치게 깊은 경우에는 암반 굴착에 대한 공기가 길어지게 되는 문제가 발생된다. The pre-drilling step (S10) is a step of pre-drilling the installation position of the jacket base structure 10 to create the perforated part 1. 7 is a schematic diagram showing a pre-piercing step (S10) according to an embodiment of the present invention. As shown in FIG. 7 , the perforation part 1 may be created by performing pre-drilling with a diameter wider than the diameter of the penetration part 13 at the installation position of each penetration part 13 of the jacket base structure 10 . For example, the diameter w of the perforation part 1 may be 1.1 to 2 times the diameter of the penetration part 13, and the depth h of the perforation part 1 may be deeper than the length of the penetration part 13. At this time, it is also possible that the depth (h) of the perforation (1) is configured to be shallower than the length of the penetration part (13) according to the construction environment or construction conditions. The pre-perforated construction of the perforation part 1 according to an embodiment of the present invention has the effect of greatly increasing the stability during jacket mounting. In particular, the effect of securing sufficient stability when mounting the jacket is generated only by the pre-drilling construction of the shallow perforation part 1 having a depth below a certain level compared to the height of the structure. At this time, when the diameter (w) of the perforation part (1) is excessively wide, the bonding force between the jacket leg and the grout is lowered, resulting in a decrease in stability, and when the depth (h) of the perforation part (1) is too deep, a problem in that the air for rock excavation becomes long occurs.

천공부(1)의 깊이(h)와 관련하여, 천공부(1)의 선천공 시공 시 관입부(13) 길이보다 깊게 시공(과천공)한 후 하부 지반에 되메움 시공 또는 버림 콘크리트 타설 시공 등을 포함하는 세부조정부를 시공하여 레벨링(레벨 세부조정) 혹은 자켓 구조물 수직도 세부조정을 수행하도록 구성될 수 있다. 도 8은 본 발명의 일실시예에 따른 선천공 단계(S10)의 세부조정부(되메움 시공 또는 버림 콘크리트 타설 시공) 시공을 도시한 모식도이다. 도 8에 도시된 바와 같이, 천공부(1)의 선천공 시공 시 관입부(13) 길이보다 깊게 시공(과천공, H1, H2, EL(-)d)한 후 하부 지반에 되메움 시공 또는 버림 콘크리트 타설 시공 등을 포함하는 세부조정부(100)를 시공하여 계획고(h1, h2, EL(-)c)까지 레벨링(레벨 세부조정) 혹은 자켓 구조물 수직도 세부조정을 수행하도록 구성될 수 있다. 이에 따르면, 선천공 후 저렴한 비용으로 천공부(1)의 깊이를 세부조정할 수 있게 되므로, 굴착만으로 천공부(1)의 깊이(h)를 정교하게 시공하는 방법에 비해 비용, 공기, 시공 난이도의 측면에서 상대적으로 이득이 발생되는 효과가 있다. Regarding the depth (h) of the perforation part (1), when the pre-drilling part (1) is constructed deeper than the length of the penetration part (13) (over-drilling), it can be configured to perform leveling (level fine adjustment) or verticality fine adjustment of the jacket structure by constructing a detailed adjustment part including backfilling or discarding concrete pouring in the lower ground. 8 is a schematic diagram showing the construction of the detailed adjustment part (backfill construction or abandoned concrete pouring construction) of the pre-drilling step (S10) according to an embodiment of the present invention. As shown in FIG. 8, during the pre-drilling construction of the perforation part 1, after the construction (over-drilling, H1, H2, EL(-)d) deeper than the length of the penetration part 13, the lower ground is backfilled or discarded. It can be configured to perform leveling (level fine adjustment) or verticality fine adjustment of the jacket structure by constructing the detailed adjustment unit 100 including concrete pouring construction, etc. According to this, since it is possible to fine-tune the depth of the perforation part 1 at low cost after pre-drilling, cost, time, and construction difficulty compared to the method of elaborately constructing the depth h of the perforation part 1 only by excavation There is an effect of generating a relative benefit in terms of difficulty.

또한, 천공부(1) 중 EL이 가장 높은 설치 위치에 시공되는 천공부(1)의 깊이(h)가 가장 깊게 구성될 수 있다. 각 관입부(13)에 대응되는 설치 위치에서 해저 지반의 EL(Elevation Level)이 EL (-)a, EL (-)b로 상이하더라도 천공부(1)의 바닥면 수심(EL (-)c)이 동일하도록 각 천공부(1)의 깊이(h1,h2)는 달리 시공될 수 있다. 천공부(1)의 시공 위치는 자켓 기초구조물(10)의 설치 위치에서 특정 수준 이상의 오차가 발생되지 않도록 GPS 등의 장비를 활용하여 정확한 위치를 천공하도록 구성될 수 있다. 기존의 일반 공법으로는 자켓 기초구조물(10)을 해저면에 거치할 때 설치 위치 위에 정확하게 거치하여야 하는 문제가 있어서 시공 상의 난이도가 있었는데, 본 발명의 일실시예에 따른 선천공 단계(S10)에 따르면, 자켓 기초구조물 자체를 설치 위치 위에 정확하게 거치하는 기존의 시공 방법보다 더 낮은 시공 난이도로 설치 위치에 선천공 시공 수행할 수 있는 효과가 발생된다.In addition, the depth h of the perforation part 1 constructed at the installation position where the EL is the highest among the perforation part 1 may be configured to be the deepest. Even if the EL (Elevation Level) of the seafloor ground is different from EL (-)a and EL (-)b at the installation location corresponding to each penetration part 13, the bottom surface water depth (EL (-)c) of the perforation part 1 is the same. The construction position of the perforation unit 1 may be configured to perforate an accurate position using equipment such as GPS so that an error of more than a certain level does not occur in the installation position of the jacket basic structure 10. In the existing general construction method, there was a problem in that the jacket foundation structure 10 should be accurately placed on the installation position when mounting the jacket foundation structure 10 on the sea floor, so there was a difficulty in construction.

임시 거치 단계(S20)는 자켓 기초구조물(10)의 각 관입부(13)를 천공부(1)에 삽입하여 임시거치하는 단계이다. 도 9, 10은 본 발명의 일실시예에 따른 임시 거치 단계(S20)를도시한 모식도이다. 도 9, 10에 도시된 바와 같이, 본 발명의 일실시예에 따른 임시 거치 단계(S20)는 자켓 기초구조물(10)의 각 관입부(13)를 천공부(1)에 삽입하여 임시거치하도록 구성될 수 있다. 도 9는 자켓 기초구조물의 레그에서 연장되는 형태의 관입부가 구성되는 경우를 도시한 것이고, 도 10은 자켓 기초구조물의 레그의 측부에 Pile Sleeve의 형태로 관입부가 구성되는 경우를 도시한 것이다. 도 9, 10에 도시된 바와 같이, 본 발명의 범위는 다양한 관입부 형태를 가지는 자켓 기초구조물에 대한 시공 방법을 포함할 수 있지만, 설명의 편의를 위하여 이하에서는 레그(12) 단부에서 관입부(13)가 연장되는 형태를 기초로 기술하였다. 기존의 일반 공법으로는 자켓 기초구조물을 해저면에 거치할 때 설치 위치 위에 정확하게 거치하여야 하는 문제가 있어서 시공 상의 난이도가 있었는데, 본 발명의 일실시예에 따른 임시 거치 단계(S20)에 따르면, 자켓 기초구조물의 관입부(13)가 상대적으로 너비가 넓은 천공부(1)에 삽입되기만 하면 됨으로써 시공 난이도가 크게 저감되는 효과가 발생된다. 자켓 기초구조물(10)의 임시 거치는 크레인 바지선과 같은 Setting Barge가 활용될 수 있다. The temporary mounting step (S20) is a step of inserting each penetration part 13 of the jacket basic structure 10 into the perforation part 1 and temporarily placing it thereon. 9 and 10 are schematic diagrams showing the temporary mounting step (S20) according to an embodiment of the present invention. As shown in FIGS. 9 and 10 , in the temporary mounting step (S20) according to an embodiment of the present invention, each inlet portion 13 of the jacket base structure 10 is inserted into the perforated portion 1 to be temporarily installed. FIG. 9 shows a case where the intrusion part is formed extending from the leg of the jacket foundation structure, and FIG. 10 shows a case where the penetration part is formed in the form of a pile sleeve on the side of the leg of the jacket foundation structure. As shown in FIGS. 9 and 10, the scope of the present invention may include a construction method for a jacket base structure having various intrusion shapes, but for convenience of description, the following intrusion portion 13 is extended from the end of the leg 12. It has been described based on the form. In the existing general construction method, there was a problem in that the jacket foundation structure must be accurately placed on the installation position when mounting the jacket foundation structure on the sea floor, so there was difficulty in construction. A setting barge, such as a crane barge for temporary support of the jacket foundation structure 10, may be utilized.

특히, 본 발명의 일실시예에 따른 임시 거치 단계(S20)는, 해저 지반의 EL(Elevation Level)이 가장 높은 설치 위치의 천공부(1)에 가장 먼저 자켓 기초구조물(10)의 특정 관입부(13)를 일부 삽입하고, 삽입된 특정 관입부(13)를 축으로 자켓 기초구조물(10)을 횡방향으로 회전하여 각 천공부(1)에 각 관입부(13)의 위치가 연직 방향으로 일치되도록 조정한 뒤, 각 천공부(1)에 각 관입부(13)를 삽입하도록 구성될 수 있다. 이에 따르면, 자켓 기초구조물(10)을 해저면에 거치할 때 정확한 설치 위치에 거치하기 위한 난이도가 크게 저감되는 효과가 발생된다. In particular, in the temporary mounting step (S20) according to an embodiment of the present invention, a specific penetration part 13 of the jacket basic structure 10 is first partially inserted into the perforation part 1 at the installation position where the elevation level (EL) of the seabed ground is highest, and the jacket basic structure 10 is rotated in the transverse direction around the inserted specific penetration part 13 to adjust the position of each penetration part 13 to each perforation part 1 in the vertical direction. After that, it may be configured to insert each penetration part 13 into each perforation part 1. According to this, when the jacket base structure 10 is mounted on the sea floor, the difficulty of mounting the jacket base structure 10 at the correct installation position is greatly reduced.

또한, 자켓 기초구조물(10)의 임시 거치 시 수직도 미세 조정을 위한 본 발명의 변형예와 관련하여, 도 11은 본 발명의 제1변형예에 따라 외측 플랜지와 승하강 모듈이 구성된 모식도이고, 도 12은 본 발명의 제2변형예에 따라 하측 또는 내측 플랜지와 승하강 모듈이 구성된 모식도이다. 도 11 및 12에 도시된 바와 같이, 본 발명의 변형예에 따른 관입부(13)의 구성에 따르면, 각 관입부(13)의 하단에 플랜지부(130)와 승하강 모듈(131)이 구성될 수 있다. 플랜지부(130)는 관입부(13)의 외측, 내측 또는 하단에 관입부의 수직방향으로 돌출 구성되어 승하강 모듈(131)의 상측을 지지하도록 구성될 수 있다. 승하강 모듈(131)은 상측이 플랜지부(130)를 통해 관입부(13)를 지지하도록 플랜지부(130)에 수직으로 체결되고, 하측이 천공부(1)의 하부지반을 지지하도록 구성되며, 관입부(13)의 길이방향으로 길이가 연장되거나 수축되어 천공부(1)의 하부 지반에 대한 관입부(13)의 상하 위치를 조정하도록 구성될 수 있다. 또한, 플랜지부(130)와 승하강 모듈(131)은, 관입부(13) 상측으로 핀파일(30)이 삽입되어 길이방향으로 관통되기 위해 관입부(13)의 내부 공간이 종방향으로 개방되도록 구성될 수 있다. 이때, 승하강 모듈(131)은 유압식 잭, 공압식 잭, 기계식 잭, 볼트 등의 승하강 수단으로 구성될 수 있다. 본 발명의 변형예에 따른 플랜지부(130) 및 승하강 모듈(131)에 따르면, 좀더 미세한 수직도 조절 등이 필요한 경우, 혹은 되메움 등으로 수직도 조절이 어려움 지형인 경우, 자켓 기초구조물(10)의 임시 거치 이후 정교한 수직도 조절이 가능해지는 효과가 발생된다. 이에 따르면, 천공부(1)의 선천공 시공 시 깊이(h)에 대한 공정 정교도가 요구되지 않게 되므로, 공정 난이도가 저감되고 공기가 단축되는 효과가 발생된다. In addition, in relation to the modified example of the present invention for fine adjustment of the verticality when the jacket foundation structure 10 is temporarily mounted, FIG. 11 is a schematic diagram in which the outer flange and the elevating module are configured according to the first modified example of the present invention, and FIG. 12 is a schematic diagram showing the lower or inner flange and the lifting module configured according to the second modified example of the present invention. As shown in FIGS. 11 and 12, according to the configuration of the penetration part 13 according to the modified example of the present invention, the flange part 130 and the elevating module 131 can be configured at the lower end of each penetration part 13. The flange portion 130 may be configured to protrude from the outside, inside, or bottom of the penetration portion 13 in the vertical direction of the penetration portion to support the upper side of the elevating module 131 . The elevating module 131 is vertically fastened to the flange portion 130 so that the upper side supports the penetration portion 13 through the flange portion 130, and the lower side is configured to support the lower ground of the perforation portion 1. The length of the penetration portion 13 may be extended or contracted in the longitudinal direction to adjust the vertical position of the penetration portion 13 with respect to the lower ground of the perforation portion 13. In addition, the flange portion 130 and the elevating module 131 may be configured such that the internal space of the penetrating portion 13 is opened in the longitudinal direction so that the pin file 30 is inserted into the penetrating portion 13 and penetrates in the longitudinal direction. At this time, the lifting module 131 may be composed of lifting means such as a hydraulic jack, a pneumatic jack, a mechanical jack, and a bolt. According to the flange portion 130 and the elevating module 131 according to the modified example of the present invention, when more fine verticality adjustment is required, or in the case of terrain where verticality adjustment is difficult due to backfilling, etc., the jacket base structure 10 After temporary installation, precise verticality adjustment is possible. According to this, since the precision of the process for the depth (h) is not required during the pre-drilling construction of the perforation part (1), the process difficulty is reduced and the period is shortened.

천공부 그라우팅 단계(S30)는 자켓 기초구조물(10)의 임시 고정을 위하여 천공부(1) 내측과 관입부(13)의 사이를 그라우팅하여 제1그라우팅부(20)를 생성하는 단계이다. 도 13은 본 발명의 일실시예에 따른 천공부 그라우팅 단계(S30)를 도시한 모식도이다. 도 13에 도시된 바와 같이, 본 발명의 일실시예에 따른 천공부 그라우팅 단계(S30)에 따르면, 자켓 기초구조물(10)의 임시 고정을 위하여 천공부(1)와 관입부(13)의 사이를 그라우팅하여 제1그라우팅부(20)를 생성하도록 구성될 수 있다. 이에 따르면, 자켓 기초구조물(10)의 관입부(13) 외부가 주변 암반과 선(先)그라우팅 시공되어 있으므로, 파일 그라우팅 단계(S50)에서 별도의 추가 작업 없이도 파일 주변의 그라우트 유출이 방지되는 효과가 발생된다.Grouting the perforation part ( S30 ) is a step of creating the first grouting part 20 by grouting between the inside of the perforation part 1 and the penetration part 13 to temporarily fix the jacket base structure 10 . 13 is a schematic diagram showing a perforation grouting step (S30) according to an embodiment of the present invention. As shown in FIG. 13, according to the grouting step (S30) of the perforation part according to an embodiment of the present invention, the first grouting part 20 may be created by grouting between the perforation part 1 and the penetration part 13 to temporarily fix the jacket base structure 10. According to this, since the outside of the penetration part 13 of the jacket base structure 10 is pre-grouted with the surrounding bedrock, the effect of preventing the outflow of grout around the piles without additional work in the pile grouting step (S50) is generated.

파일 시공 단계(S40)는 핀파일(30)의 근입부를 굴착하고, 자켓 기초구조물(10)의 관입부(13) 또는 레그(12)를 통해 핀파일(30)을 삽입하며, 해머 등을 이용한 핀파일(30) 항타를 통해 천공부(1)의 바닥면에 핀파일(30)을 타설하는 단계이다. 자켓 기초구조물(10)의 관입부(13)가 Pile Sleeve 형태로 레그(12) 측부에 구성되는 경우에는 관입부(13)를 통해 핀파일(30)을 삽입하며, 자켓 기초구조물(10)의 관입부(13)가 레그(12)에서 연장되도록 구성되는 경우에는 레그(12) 및 관입부(13)를 통해 핀파일(30)을 삽입하도록 구성될 수 있다. 도 14는 본 발명의 일실시예에 따른 파일 시공 단계(S40)를 도시한 모식도이다. 도 14에 도시된 바와 같이, 본 발명의 일실시예에 따른 파일 시공 단계(S40)에 따르면, 자켓 기초구조물 임시 거치 후 지그 설치와 같은 별다른 추가 공정 없이 곧바로 핀파일(30)을 타설할 수 있게 되므로 공기가 단축되는 효과가 발생된다. In the pile construction step (S40), the inlet of the pin pile 30 is excavated, the pin pile 30 is inserted through the penetration part 13 or the leg 12 of the jacket foundation structure 10, and the pin pile 30 is driven using a hammer. When the penetration part 13 of the jacket base structure 10 is configured on the side of the leg 12 in the form of a pile sleeve, the pin pile 30 is inserted through the penetration part 13, and when the penetration part 13 of the jacket base structure 10 is configured to extend from the leg 12, the pin pile 30 may be inserted through the leg 12 and the penetration part 13. 14 is a schematic diagram showing a pile construction step (S40) according to an embodiment of the present invention. As shown in FIG. 14, according to the pile construction step (S40) according to an embodiment of the present invention, the fin pile 30 can be poured immediately without any additional process such as jig installation after the temporary mounting of the jacket foundation structure. The effect of shortening the air is generated.

파일 그라우팅 단계(S50)는 파일 시공 단계(S40)에서 시공된 핀파일(30) 내부, 핀파일(30)과 해저 지반(주로 암반) 사이의 공간, 핀파일(30)과 자켓 기초구조물(10)의 관입부(13) 사이의 공간을 그라우팅하여 제2그라우팅부(21)를 생성하는 단계이다. 도 15는 본 발명의 일실시예에 따른 파일 그라우팅 단계(S50)를 도시한 것이다. 도 15에 도시된 바와 같이, 파일 그라우팅 단계(S50)는 핀파일(30) 내부, 핀파일(30)과 해저 지반(주로 암반) 사이의 공간, 핀파일(30)과 자켓 기초구조물(10)의 관입부(13) 사이의 공간을 그라우팅하도록 구성될 수 있다. The pile grouting step (S50) is a step of generating the second grouting portion 21 by grouting the inside of the pin pile 30 constructed in the pile construction step (S40), the space between the pin pile 30 and the seabed ground (mainly rock mass), and the space between the pin pile 30 and the penetration part 13 of the jacket foundation structure 10. 15 illustrates a file grouting step (S50) according to an embodiment of the present invention. As shown in FIG. 15, the pile grouting step (S50) is the inside of the pin pile 30, the space between the pin pile 30 and the seabed ground (mainly rock mass), and the pin pile 30 and the jacket foundation structure. It may be configured to grout the space between the penetration part 13 of 10.

추가적으로, 본 발명의 일실시예에 따른 자켓 기초구조물 선천공 거치 방법은, 자켓 기초구조물(10) 제작 시에 보강 단계를 더 포함할 수 있다. 보강 단계는 선조립 철근 등의 보강재(40)를 자켓 기초구조물(10)의 관입부(13) 외측에 보강하는 단계이다. 도 16은 본 발명의 일실시예에 따른 보강 단계를 도시한 것이다. 도 16에 도시된 바와 같이, 본 발명의 일실시예에 따른 보강 단계에 따르면, 자켓 기초구조물(10)의 관입부(13)와 천공부(1)의 사이 공간에 선조립 철근 등의 보강재(40)가 구성되게 되므로, 천공부 면적이 넓은 경우에도 그라우트 시 인발에 대한 저항성을 향상하여 안정성이 확보되는 효과가 발생된다. 본 발명의 일실시예에 따른 보강재(40)는 나선형 띠철근과 기둥주근으로 구성된 철근 보강 또는 철근/선타설 보강으로 구성될 수 있다. Additionally, the method for mounting the pre-drilled jacket base structure according to an embodiment of the present invention may further include a reinforcement step when manufacturing the jacket base structure 10 . The reinforcing step is a step of reinforcing reinforcing materials 40 such as pre-assembled reinforcing bars to the outside of the penetration part 13 of the jacket basic structure 10. 16 illustrates a reinforcement step according to an embodiment of the present invention. As shown in FIG. 16, according to the reinforcing step according to an embodiment of the present invention, since the reinforcing material 40 such as pre-assembled reinforcing bars is configured in the space between the penetration part 13 and the perforation part 1 of the jacket basic structure 10, even when the area of the perforation part is wide, the effect of securing stability by improving resistance to pulling out during grout occurs. The reinforcing material 40 according to an embodiment of the present invention may be composed of reinforcing bars composed of spiral strip reinforcing bars and column main bars or reinforcing bars/line casting reinforcement.

선천공 거치를 이용한 자켓 기초구조물Jacket foundation structure using pre-drilled mounting

도 16에 도시된 바와 같이, 본 발명의 일실시예에 따른 선천공 거치를 이용한 자켓 기초구조물(10)은, 천공부(1), 자켓부, 관입부(13), 핀파일(30), 제1그라우팅부(20), 제2그라우팅부(21)로 구성될 수 있다. 설명의 편의를 위하여, 자켓 기초구조물에 포함되는 트랜지션 피스(Transition Piece), 워크 플랫폼(Work Platform), 보트랜딩(Boat Landing) 등의 구성은 설명을 생략하지만, 본 발명의 범위를 한정하지는 않는다. As shown in FIG. 16, the jacket basic structure 10 using pre-drilling mounting according to an embodiment of the present invention includes a perforation part 1, a jacket part, a penetration part 13, a pin pile 30, and a first grouting part 20 and a second grouting part 21. For convenience of description, descriptions of components such as a transition piece, a work platform, and a boat landing included in the jacket basic structure are omitted, but the scope of the present invention is not limited.

천공부(1)는, 자켓 기초구조물(10)의 각 관입부(13)의 설치 위치에 관입부(13) 직경보다 넓은 직경으로 선천공 시공하여 구성되는 굴착부를 의미한다. 예를 들어, 천공부(1)의 직경(w)은 관입부(13) 직경의 1.1배 내지 2배로 구성될 수 있고, 천공부(1)의 깊이(h)는 관입부(13) 길이보다 깊게 구성될 수 있다. 이때, 천공부(1)의 깊이(h)는 시공 환경이나 시공 상황에 따라 관입부(13) 길이보다 얕게 구성되는 것도 가능하다. The drilling part 1 means an excavation part configured by performing pre-drilling with a diameter wider than the diameter of the penetrating part 13 at the installation position of each penetrating part 13 of the jacket basic structure 10. For example, the diameter w of the perforation part 1 may be 1.1 to 2 times the diameter of the penetration part 13, and the depth h of the perforation part 1 may be deeper than the length of the penetration part 13. At this time, it is also possible that the depth (h) of the perforation (1) is configured to be shallower than the length of the penetration part (13) according to the construction environment or construction conditions.

천공부(1)의 깊이(h)와 관련하여, 천공부(1)의 선천공 시공 시 관입부(13) 길이보다 깊게 시공(과천공, H1, H2, EL(-)d)한 후 하부 지반에 되메움 시공 또는 버림 콘크리트 타설 시공 등을 포함하는 세부조정부(100)를 시공하여 계획고(h1, h2, EL(-)c)까지 레벨링(레벨 세부조정) 혹은 자켓 구조물 수직도 세부조정을 수행하도록 구성될 수 있다. Regarding the depth (h) of the perforation part (1), when the pre-drilling part (1) is constructed deeper than the length of the penetration part (13) (over-drilling, H1, H2, EL(-)d), it is possible to perform leveling (level fine adjustment) or verticality adjustment of the jacket structure by constructing the detailed adjustment part 100 including backfilling or abandonment concrete pouring in the lower ground to the planned height (h1, h2, EL(-)c). .

또한, 천공부(1) 중 EL이 가장 높은 설치 위치에 시공되는 천공부(1)의 깊이(h)가 가장 깊게 구성될 수 있다. 또한, 각 관입부(13)에 대응되는 설치 위치에서 해저 지반의 EL(Elevation Level)이 EL (-)a, EL (-)b로 상이하더라도 천공부(1)의 바닥면 수심(EL (-)c)이 동일하도록 각 천공부(1)의 깊이(h1,h2)는 달리 시공될 수 있다.In addition, the depth h of the perforation part 1 constructed at the installation position where the EL is the highest among the perforation part 1 may be configured to be the deepest. In addition, even if the EL (Elevation Level) of the seafloor ground is different from EL (-)a and EL (-)b at the installation location corresponding to each penetration part 13, the bottom surface water depth (EL (-)c) of the perforation part 1 The depths h1 and h2 of each perforation part 1 can be constructed differently.

자켓부는, 브레이스(11, Brace)와 레그(12, Leg)로 구성되는 자켓 기초구조물(10)의 본체를 의미한다. 자켓부에는 트랜지션 피스(Transition Piece), 워크 플랫폼(Work Platform), 보트랜딩(Boat Landing) 등이 구성될 수 있고, 자켓부의 상부에는 해상구조물이 설치될 수 있다. The jacket portion refers to the main body of the jacket basic structure 10 composed of braces 11 and legs 12 . A transition piece, a work platform, a boat landing, and the like may be configured in the jacket portion, and an offshore structure may be installed on the upper portion of the jacket portion.

관입부(13)는, 자켓 기초구조물(10)의 레그 하부에 구성되고, 길이방향이 상기 자켓부의 하방으로 구성되어 천공부(1)에 관입되는 구성을 의미한다. The penetrating part 13 is formed in the lower part of the leg of the jacket base structure 10, and the longitudinal direction is formed in the lower part of the jacket part and penetrates into the perforated part 1.

핀파일(30)은, 자켓 기초구조물(10)의 관입부(13)를 통해 타설되는 파일을 의미한다. 핀파일(30)의 근입부를 굴착하고, 자켓 기초구조물(10)의 레그 또는 관입부(13)를 통해 핀파일(30)을 삽입하며, 핀파일(30) 항타를 통해 천공부(1)의 바닥면에 핀파일(30)을 타설하여 구성될 수 있다. 자켓 기초구조물(10)의 관입부(13)가 Pile Sleeve 형태로 레그(12) 측부에 구성되는 경우에는 관입부(13)를 통해 핀파일(30)을 삽입하며, 자켓 기초구조물(10)의 관입부(13)가 레그(12)에서 연장되도록 구성되는 경우에는 레그(12) 및 관입부(13)를 통해 핀파일(30)을 삽입하도록 구성될 수 있다. The pin pile 30 means a pile that is poured through the penetration part 13 of the jacket base structure 10. Excavate the inlet part of the pin pile 30, insert the pin pile 30 through the leg or penetration part 13 of the jacket base structure 10, and drive the pin pile 30 to the bottom surface of the perforation part 1. It can be configured by pouring the pin pile 30. When the penetration part 13 of the jacket base structure 10 is configured on the side of the leg 12 in the form of a pile sleeve, the pin pile 30 is inserted through the penetration part 13, and when the penetration part 13 of the jacket base structure 10 is configured to extend from the leg 12, the pin pile 30 may be inserted through the leg 12 and the penetration part 13.

제1그라우팅부(20)는, 천공부(1) 내측과 관입부(13) 사이의 공간에 시공된 그라우트를 의미할 수 있다. 제1그라우팅부(20)에 의하면 관입부(13) 및 천공부(1)가 일체화될 수 있고, 나아가 보강재(40)도 함께 일체화될 수 있다. The first grouting part 20 may refer to grout applied to a space between the inside of the perforation part 1 and the penetration part 13 . According to the first grouting part 20, the penetration part 13 and the perforation part 1 can be integrated, and furthermore, the reinforcing material 40 can also be integrated together.

제2그라우팅부(21)는, 핀파일(30) 내부 공간에 시공된 그라우트, 핀파일(30) 외측과 해저 지반(암반) 사이 공간에 시공된 그라우트 및 핀파일(30) 외측과 자켓 기초구조물(10)의 관입부(13) 내측 사이의 공간에 시공된 그라우트를 의미할 수 있다. The second grouting part 21 may mean grout applied to the inner space of the pin pile 30, grout applied to the space between the outside of the pin pile 30 and the seabed ground (rock), and grout applied to the space between the outside of the pin pile 30 and the inside of the penetration part 13 of the jacket foundation structure 10.

추가적으로, 본 발명의 일실시예에 따른 선천공 거치를 이용한 자켓 기초구조물(10)은, 관입부(13) 외측에 보강재(40)를 더 포함할 수 있다. 본 발명의 일실시예에 따른 보강재(40)는 나선형 띠철근과 기둥주근으로 구성된 철근 보강 또는 철근/선타설 보강으로 구성될 수 있다. 본 발명의 일실시예에 따르면 자켓 기초구조물(10)의 관입부(13)와 천공부(1)의 사이 공간에 선조립 철근 등의 보강재(40)가 구성되게 되므로, 천공부 면적이 넓은 경우에도 그라우트 시 인발에 대한 저항성을 향상하여 안정성이 확보되는 효과가 발생된다. Additionally, the jacket base structure 10 using the pre-drilling installation according to an embodiment of the present invention may further include a reinforcing material 40 outside the penetration part 13 . The reinforcing material 40 according to an embodiment of the present invention may be composed of reinforcing bars composed of spiral strip reinforcing bars and column main bars or reinforcing bars/line casting reinforcement. According to one embodiment of the present invention, since the reinforcing material 40, such as pre-assembled reinforcing bars, is configured in the space between the penetration part 13 and the perforation part 1 of the jacket basic structure 10, even when the area of the perforation part is wide, resistance to pulling out during grout is improved to ensure stability.

이상에서 설명한 바와 같이, 본 발명이 속하는 기술 분야의 통상의 기술자는 본 발명이 그 기술적 사상이나 필수적 특징을 변경하지 않고서 다른 구체적인 형태로 실시될 수 있다는 것을 이해할 수 있을 것이다. 그러므로 상술한 실시예들은 모든 면에서 예시적인 것이며 한정적인 것이 아닌 것으로서 이해해야만 한다. 본 발명의 범위는 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 등가 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함하는 것으로 해석되어야 한다.As described above, those skilled in the art to which the present invention pertains will be able to understand that the present invention can be embodied in other specific forms without changing its technical spirit or essential features. Therefore, the above-described embodiments should be understood as illustrative in all respects and not restrictive. The scope of the present invention is indicated by the claims to be described later rather than the detailed description, and all changes or modifications derived from the meaning and scope of the claims and equivalent concepts should be construed as being included in the scope of the present invention.

1: 천공부
10: 자켓 기초구조물
11: 브레이스
12: 레그
13: 관입부
20: 제1그라우팅부
21: 제2그라우팅부
30: 핀파일
40: 보강재
100: 세부조정부
130: 플랜지부
131: 승하강 모듈
1: perforation
10: jacket substructure
11: Brace
12: leg
13: penetration
20: first grouting part
21: second grouting part
30: pin file
40: stiffener
100: detailed adjustment unit
130: flange part
131: lifting module

Claims (17)

해저 지반의 특정 설치 위치에 설치되는 자켓 기초구조물에 있어서,
상기 자켓 기초구조물의 본체로서, 브레이스 및 레그를 포함하는 자켓부;
상기 레그의 하부에 구성되고, 길이방향이 상기 자켓부의 하방으로 구성되는 관입부; 및
상기 관입부가 삽입되기 이전에, 상기 설치 위치에 상기 관입부와 대응되도록 복수개가 선천공 시공되어 상기 관입부 직경의 1.1배 내지 2배의 직경으로 구성되는 천공부;
상기 천공부 내측과 상기 관입부 사이의 공간에 시공된 그라우트인 제1그라우팅부;
상기 관입부를 관통하여 상기 천공부의 바닥면에 타설되는 핀파일; 및
상기 핀파일 내부 공간에 시공되는 그라우트, 상기 핀파일 외측과 상기 해저 지반 사이 공간에 시공되는 그라우트 및 상기 핀파일 외측과 상기 관입부 내측 사이의 공간에 시공되는 그라우트를 포함하는 제2그라우팅부;
를 포함하고,
상기 제1그라우팅부는, 상기 관입부가 상기 천공부에 삽입되어 임시 거치된 이후에 시공되며,
상기 제1그라우팅부가 시공된 이후에 상기 핀파일이 시공되고, 상기 핀파일이 시공된 이후에 상기 제2그라우팅부가 시공되고,
상기 관입부는 상기 천공부에 삽입되어 상기 자켓부가 상기 설치 위치에 거치되되, 상기 설치 위치 중 상기 해저 지반의 EL(Elevation Level)이 가장 높은 위치에 시공된 상기 천공부에 가장 먼저 상기 관입부가 일부 삽입되고, 삽입된 상기 관입부를 축으로 상기 자켓부가 횡방향으로 회전되어 상기 천공부에 상기 관입부의 위치가 연직 방향으로 일치되도록 조정된 뒤, 상기 천공부에 상기 관입부가 삽입되어 상기 자켓부가 상기 설치 위치에 설치되되, 상기 설치 위치 중 EL이 가장 높은 위치에 시공되는 천공부의 깊이가 가장 깊게 구성되는 것을 특징으로 하는,
선천공 거치를 이용한 자켓 기초구조물.
In the jacket foundation structure installed at a specific installation location on the seabed ground,
As a main body of the jacket basic structure, the jacket portion including braces and legs;
a penetrating portion disposed at a lower portion of the leg and extending in a longitudinal direction downward of the jacket portion; and
Before the inlet is inserted, a plurality of pre-drilled constructions to correspond to the inlet at the installation location, and a perforation having a diameter 1.1 to 2 times the diameter of the inlet;
a first grouting part, which is a grout applied to the space between the inside of the perforation part and the penetration part;
A pin file that penetrates the penetration portion and is poured on the bottom surface of the perforation portion; and
A second grouting unit including grout applied to the inner space of the fin pile, grout applied to the space between the outside of the fin pile and the seabed ground, and grout applied to the space between the outside of the fin pile and the inside of the penetration part;
including,
The first grouting part is constructed after the penetrating part is inserted into the perforation part and temporarily held,
The fin pile is constructed after the first grouting part is constructed, and the second grouting part is constructed after the pin pile is constructed,
The penetration part is inserted into the perforation part and the jacket part is installed at the installation position, but the penetration part is first partially inserted into the perforation part constructed at the highest elevation level (EL) of the seafloor ground among the installation positions, and the jacket part is rotated in the transverse direction around the inserted penetration part to adjust the position of the penetration part to the perforation part in the vertical direction. Characterized in that the depth of the perforation constructed at the highest position is the deepest,
Jacket foundation structure using pre-drilled mounting.
제1항에 있어서,
상기 해저 지반은 암반층을 의미하는 것을 특징으로 하는,
선천공 거치를 이용한 자켓 기초구조물.
According to claim 1,
Characterized in that the seabed ground means a bedrock layer,
Jacket foundation structure using pre-drilled mounting.
제1항에 있어서,
상기 관입부를 관통하여 상기 천공부의 바닥면에 타설되는 상기 핀파일은,
상기 관입부가 파일 슬리브(Pile Sleeve) 형태로 레그의 측부에 구성되는 경우에는 상기 관입부를 관통하여 상기 천공부의 바닥면에 타설되고,
상기 관입부가 레그에서 연장되도록 구성되는 경우에는 레그 및 관입부를 관통하여 상기 천공부의 바닥면에 타설되는
선천공 거치를 이용한 자켓 기초구조물.
According to claim 1,
The pin pile passing through the penetration part and being poured on the bottom surface of the perforation part,
When the penetration part is formed on the side of the leg in the form of a pile sleeve, it penetrates the penetration part and is poured into the bottom surface of the perforation part,
When the penetration part is configured to extend from the leg, the leg and the penetration part are poured into the bottom surface of the perforation part.
Jacket foundation structure using pre-drilled mounting.
삭제delete 제1항에 있어서,
상기 관입부 외측에 상기 관입부를 감싸도록 구성되고, 나선형 띠철근과 기둥주근으로 구성된 철근 보강 또는 철근 선타설 보강으로 구성되는 보강재
를 더 포함하고,
상기 제1그라우팅부는, 상기 관입부가 상기 천공부에 삽입되어 임시 거치된 이후에 시공되며, 상기 관입부, 상기 보강재 및 상기 천공부를 일체화 하는 것을 특징으로 하는,
선천공 거치를 이용한 자켓 기초구조물.
According to claim 1,
A reinforcing material configured to surround the penetration portion outside the penetration portion and composed of reinforcing bar consisting of spiral strip reinforcing bars and column main bars or reinforcing bar line casting reinforcement
Including more,
The first grouting part is constructed after the penetration part is inserted into the perforation part and temporarily held, and the penetration part, the reinforcing material, and the perforation part are integrated.
Jacket foundation structure using pre-drilled mounting.
삭제delete 제1항에 있어서,
상기 관입부의 외측, 내측 또는 하단에 상기 관입부의 수직방향으로 돌출 구성되는 플랜지부; 및
상측은 상기 플랜지부에 수직으로 체결되고, 하측은 상기 천공부의 하부 지반을 지지하도록 구성되며, 상기 관입부의 길이방향으로 길이가 연장되거나 수축되도록 구성되는 승하강 모듈;
을 더 포함하고,
상기 승하강 모듈의 연장 또는 수축에 의해 상기 천공부의 상기 하부 지반에 대한 상기 관입부의 상하 위치가 조정되고,
상기 플랜지부와 상기 승하강 모듈은 상기 관입부의 내부 공간이 종방향으로 개방되도록 구성되는 것을 특징으로 하는,
선천공 거치를 이용한 자켓 기초구조물.
According to claim 1,
A flange portion configured to protrude in a vertical direction of the inlet portion on the outside, inside, or bottom of the inlet portion; and
an elevating module having an upper side vertically fastened to the flange unit, a lower side supporting the lower ground of the perforation unit, and extending or contracting in length in the longitudinal direction of the penetration unit;
Including more,
The vertical position of the penetration part with respect to the lower ground of the perforation part is adjusted by extension or contraction of the elevating module,
Characterized in that the flange portion and the elevating module are configured such that the internal space of the intrusion portion is opened in the longitudinal direction.
Jacket foundation structure using pre-drilled mounting.
제1항에 있어서,
상기 천공부는 상기 관입부의 길이보다 깊은 깊이로 과천공 시공되고,
상기 천공부의 하부 지반에 되메움 시공 또는 버림 콘크리트 타설 시공되는 세부조정부;
를 더 포함하며,
상기 세부조정부 시공을 통하여 상기 관입부의 레벨링 또는 수직도 조절을 수행하는 것을 특징으로 하는,
선천공 거치를 이용한 자켓 기초구조물.
According to claim 1,
The perforation is over-perforated at a depth greater than the length of the penetration,
A detailed adjustment unit for backfilling or discarding concrete pouring in the lower ground of the perforation unit;
Including more,
Characterized in that the leveling or verticality adjustment of the penetration part is performed through the construction of the detailed adjustment part.
Jacket foundation structure using pre-drilled mounting.
삭제delete 해저 지반의 특정 설치 위치에 설치되는 자켓 기초구조물의 본체로서, 브레이스 및 레그를 포함하는 자켓부; 및 상기 레그의 하부에 구성되고, 길이방향이 상기 자켓부의 하방으로 구성되는 관입부;를 포함하는 자켓 기초구조물의 시공방법에 있어서,
상기 관입부가 삽입되기 이전에, 상기 설치 위치에 상기 관입부와 대응되도록 복수개 선천공 시공하여 상기 관입부 직경의 1.1배 내지 2배의 직경으로 구성되는 천공부를 생성하는 선천공 단계;
상기 관입부를 상기 천공부에 삽입하여 상기 자켓부를 상기 설치 위치에 거치하는 임시 거치 단계;
상기 천공부 내측과 상기 관입부 사이의 공간에 제1그라우팅부를 시공하는 제1그라우팅 단계;
핀파일을 상기 관입부를 관통하여 상기 천공부의 바닥면에 타설하는 파일 시공 단계; 및
상기 핀파일 내부 공간, 상기 핀파일 외측과 상기 해저 지반 사이 공간 및 상기 핀파일 외측과 상기 관입부 내측 사이의 공간에 제2그라우팅부를 시공하는 제2그라우팅 단계;
를 포함하되,
상기 임시 거치 단계에 있어서, 상기 설치 위치 중 상기 해저 지반의 EL(Elevation Level)이 가장 높은 위치에 시공된 상기 천공부에 가장 먼저 상기 관입부가 일부 삽입되고, 삽입된 상기 관입부를 축으로 상기 자켓부가 횡방향으로 회전되어 상기 천공부에 상기 관입부의 위치가 연직 방향으로 일치되도록 조정된 뒤, 상기 천공부에 상기 관입부가 삽입되어 상기 자켓부가 상기 설치 위치에 설치되되, 상기 설치 위치 중 EL이 가장 높은 위치에 시공되는 천공부의 깊이가 가장 깊게 구성되는 것을 특징으로 하는,
자켓 기초구조물의 선천공 거치 시공방법.
A main body of a jacket foundation structure installed at a specific installation location on the seabed ground, comprising: a jacket portion including braces and legs; In the construction method of the jacket foundation structure including;
Before the inlet is inserted, a pre-drilling step of constructing a plurality of pre-drilled holes corresponding to the inlet at the installation location to create a perforation having a diameter 1.1 to 2 times the diameter of the inlet;
a temporary mounting step of inserting the penetration part into the perforation part and placing the jacket part at the installation position;
a first grouting step of constructing a first grouting part in a space between an inner side of the perforation part and the penetration part;
A pile construction step of pouring a pin pile through the penetration part to the bottom surface of the perforation part; and
a second grouting step of constructing a second grouting part in a space inside the fin pile, a space between the outside of the fin pile and the seafloor ground, and a space between the outside of the fin pile and the inside of the penetration part;
Including,
In the temporary mounting step, the penetration part is first partially inserted into the perforation constructed at the highest elevation level (EL) of the seafloor ground among the installation positions, and the jacket part is rotated in the transverse direction around the inserted penetration, so that the position of the penetration part is aligned with the perforation in the vertical direction. characterized in that it consists of
Pre-drilled installation method of jacket foundation structure.
제10항에 있어서,
상기 해저 지반은 암반층을 의미하는 것을 특징으로 하는,
자켓 기초구조물의 선천공 거치 시공방법.
According to claim 10,
Characterized in that the seabed ground means a bedrock layer,
Pre-drilled installation method of jacket foundation structure.
제10항에 있어서,
상기 파일 시공 단계에 있어서, 상기 핀파일은,
상기 관입부가 파일 슬리브(Pile Sleeve) 형태로 레그의 측부에 구성되는 경우에는 상기 관입부를 관통하여 상기 천공부의 바닥면에 타설되고,
상기 관입부가 레그에서 연장되도록 구성되는 경우에는 레그 및 관입부를 관통하여 상기 천공부의 바닥면에 타설되는
자켓 기초구조물의 선천공 거치 시공방법.
According to claim 10,
In the pile construction step, the pin pile,
When the penetration part is formed on the side of the leg in the form of a pile sleeve, it penetrates the penetration part and is poured into the bottom surface of the perforation part,
When the penetration part is configured to extend from the leg, the leg and the penetration part are poured into the bottom surface of the perforation part.
Pre-drilled installation method of jacket foundation structure.
삭제delete 제10항에 있어서,
상기 임시 거치 단계 이전에,
나선형 띠철근과 기둥주근으로 구성된 철근 보강 또는 철근 선타설 보강으로 구성되는 보강재를 상기 관입부 외측에 상기 관입부를 감싸도록 구성하는 보강 단계;
를 더 포함하고,
상기 제1그라우팅부는, 상기 관입부, 상기 보강재 및 상기 천공부를 일체화 하는 것을 특징으로 하는,
자켓 기초구조물의 선천공 거치 시공방법.
According to claim 10,
Prior to the temporary mounting step,
A reinforcing step of configuring a reinforcing material composed of reinforcing bars composed of spiral strip reinforcing bars and column main bars or reinforcing bar line cast reinforcement to surround the intrusion portion outside the intrusion portion;
Including more,
The first grouting part is characterized in that the penetration part, the reinforcing material and the perforation part are integrated.
Pre-drilled installation method of jacket foundation structure.
삭제delete 제10항에 있어서,
상기 자켓 기초구조물은 상기 관입부의 외측, 내측 또는 하단에 상기 관입부의 수직방향으로 돌출 구성되는 플랜지부; 및 상측은 상기 플랜지부에 수직으로 체결되고, 하측은 상기 천공부의 하부 지반을 지지하도록 구성되며, 상기 관입부의 길이방향으로 길이가 연장되거나 수축되도록 구성되는 승하강 모듈;을 더 포함하고, 상기 플랜지부와 상기 승하강 모듈은 상기 관입부의 내부 공간이 종방향으로 개방되도록 구성되며,
상기 임시 거치 단계 이후에,
상기 승하강 모듈의 연장 또는 수축을 수행하여 상기 천공부의 상기 하부 지반에 대한 상기 관입부의 상하 위치를 조정하여 상기 자켓 기초구조물의 수직도를 미세조정하는 수직도 미세조정 단계;
를 더 포함하는 것을 특징으로 하는,
자켓 기초구조물의 선천공 거치 시공방법.
According to claim 10,
The jacket base structure includes a flange portion protruding in the vertical direction of the penetration portion at the outer, inner side, or lower end of the penetration portion; And an elevating module having an upper side vertically fastened to the flange portion, a lower side configured to support the lower ground of the perforated portion, and configured to extend or contract in length in the longitudinal direction of the penetration portion, wherein the flange portion and the elevating module are configured such that the internal space of the penetration portion is opened in the longitudinal direction,
After the temporary mounting step,
a verticality fine-adjustment step of finely adjusting the verticality of the jacket foundation structure by performing an extension or contraction of the elevating and descending module to adjust the vertical position of the penetration part with respect to the lower ground of the perforation part;
Characterized in that it further comprises,
Pre-drilled installation method of jacket foundation structure.
제10항에 있어서,
상기 자켓 기초구조물의 상기 천공부는 상기 관입부의 길이보다 깊은 깊이로 과천공 시공되고, 상기 천공부의 하부 지반에 되메움 시공 또는 버림 콘크리트 타설 시공되는 세부조정부를 더 포함하며,
상기 선천공 단계 이후에,
상기 천공부의 하부 지반에 상기 세부조정부 시공을 통하여 상기 관입부의 레벨링 또는 수직도 조절을 수행하는 세부조정 단계;
를 더 포함하는 것을 특징으로 하는,
자켓 기초구조물의 선천공 거치 시공방법.
According to claim 10,
The perforation of the jacket foundation structure further includes a detailed adjustment unit in which the perforation is over-perforated to a depth greater than the length of the penetration, and the ground under the perforation is backfilled or abandoned concrete is poured,
After the pre-perforation step,
A detailed adjustment step of performing leveling or verticality adjustment of the penetration part through the construction of the detailed adjustment part in the ground below the perforation part;
Characterized in that it further comprises,
Pre-drilled installation method of jacket foundation structure.
KR1020210049710A 2021-04-16 2021-04-16 Pre-drilling and positioning method for installation of jacket foundation KR102557752B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210049710A KR102557752B1 (en) 2021-04-16 2021-04-16 Pre-drilling and positioning method for installation of jacket foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210049710A KR102557752B1 (en) 2021-04-16 2021-04-16 Pre-drilling and positioning method for installation of jacket foundation

Publications (2)

Publication Number Publication Date
KR20220143318A KR20220143318A (en) 2022-10-25
KR102557752B1 true KR102557752B1 (en) 2023-07-21

Family

ID=83804011

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210049710A KR102557752B1 (en) 2021-04-16 2021-04-16 Pre-drilling and positioning method for installation of jacket foundation

Country Status (1)

Country Link
KR (1) KR102557752B1 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000017647A (en) * 1998-07-01 2000-01-18 Kansai Electric Power Co Inc:The Installation method of underwater structure

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5179615A (en) * 1974-08-14 1976-07-12 Shoichi Sasaki KINZOKUSEIRENYOKAIJOZOSAIZAI
JP3702433B2 (en) * 1995-05-17 2005-10-05 大成建設株式会社 Leg installation device for floating structures
GB0902289D0 (en) * 2009-02-12 2009-03-25 Marine Current Turbines Ltd Methods for installing pin-piled jacket type structures at sea
KR20150077787A (en) 2013-12-30 2015-07-08 주식회사 포스코건설 Method of jacket structure launching for Sea wind power generator
KR20150077748A (en) 2013-12-30 2015-07-08 주식회사 포스코건설 Construction method of jacket structure

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000017647A (en) * 1998-07-01 2000-01-18 Kansai Electric Power Co Inc:The Installation method of underwater structure

Also Published As

Publication number Publication date
KR20220143318A (en) 2022-10-25

Similar Documents

Publication Publication Date Title
US9567720B2 (en) Offshore platform for a marine environment
CN108086340B (en) Open caisson construction structure and construction method thereof
US20110305523A1 (en) Support structure for use in the offshore wind farm industry
JP5278828B2 (en) How to install the jacket
KR101043606B1 (en) Net type support device of monopile for supporting seaside or seabed soft ground
WO2015135471A1 (en) Hollow cylindrical pier for fixing offshore platform structure to bed and method of installing and constructing same
DK2700750T3 (en) Pile FOR OFFSHORE STRUCTURES AND METHOD FOR CONSTRUCTION OF A pile FOR OFFSHORE STRUCTURES
CN105714833A (en) Construction method of steel plate pile open caisson support
JP6454674B2 (en) Construction method of water stop working space
KR102185234B1 (en) Pre-piling template using spudcan and installation method of offshore structure using thereof
JP6792240B2 (en) Scuttling prevention device for steel pipe piles, scuttling prevention structure and scuttling prevention method
CN110284515A (en) A kind of inclined uncovered rock riverbed pile base construction method
JP7174639B2 (en) Substructure of foundation for offshore wind power generation and construction method for substructure of foundation for offshore wind power generation
KR102521885B1 (en) Offshore wind farm structure installed by jacking method and its construction method
KR100975988B1 (en) The Method for Constructing Underwater Structure
Malhotra Design and construction considerations for offshore wind turbine foundations
KR101544640B1 (en) Suction Foundation Assembly, Construction Method for Adjusting Horizontality and Offshore Wind Power System using the same
KR102557752B1 (en) Pre-drilling and positioning method for installation of jacket foundation
JP2020128672A (en) Installation method of mono-pile foundation for offshore wind power generation and mono-pile foundation for offshore wind power generation
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
CN114215093B (en) Construction method of bearing platform foundation
KR102392135B1 (en) Pre-filing construction apparatus and construction method of offshore jacket foundation structure
JP2001348888A (en) Method and device for constructing underwater foundation structure
CN109137946B (en) Rapid positioning and stabilizing construction method for double-wall steel cofferdam of turbulent rock riverbed
JP4475116B2 (en) Vertical shaft structure and its construction method

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant