KR102426266B1 - Outer scaffolding system construction method for tank - Google Patents

Outer scaffolding system construction method for tank Download PDF

Info

Publication number
KR102426266B1
KR102426266B1 KR1020210106274A KR20210106274A KR102426266B1 KR 102426266 B1 KR102426266 B1 KR 102426266B1 KR 1020210106274 A KR1020210106274 A KR 1020210106274A KR 20210106274 A KR20210106274 A KR 20210106274A KR 102426266 B1 KR102426266 B1 KR 102426266B1
Authority
KR
South Korea
Prior art keywords
spherical tank
scaffold
scaffolding
horizontal
module
Prior art date
Application number
KR1020210106274A
Other languages
Korean (ko)
Inventor
박창순
박상순
Original Assignee
(주)대도시스템
박상순
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)대도시스템, 박상순 filed Critical (주)대도시스템
Priority to KR1020210106274A priority Critical patent/KR102426266B1/en
Application granted granted Critical
Publication of KR102426266B1 publication Critical patent/KR102426266B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/36Scaffolds for particular parts of buildings or buildings of particular shape, e.g. for stairs, cupolas, domes
    • E04G1/362Scaffolds for particular parts of buildings or buildings of particular shape, e.g. for stairs, cupolas, domes specially adapted for tanks, silos or similar vessels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/001Safety or protective measures against falling down relating to scaffoldings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/08Scaffold boards or planks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/16Struts or stiffening rods, e.g. diagonal rods

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

The present invention relates to a construction method of an outer system scaffolding for a spherical tank, in which a system scaffolding module is assembled and installed in multi-stages in an octagonal horizontal ring shape on an outer circumferential surface of a spherical tank installed by using supports, and required materials such as a work platform are optimized to allow quick installation and disassembly. The outer system scaffolding for a spherical tank is horizontally assembled and installed by the system scaffolding module of an octagonal horizontal ring shape, and each of the eight system scaffolding modules is manufactured by combining vertical and horizontal scaffoldings and the optimized working platform with dimensions determined according to a diameter of the spherical tank for each stage.

Description

구형탱크용 외부시스템비계 시공방법{OUTER SCAFFOLDING SYSTEM CONSTRUCTION METHOD FOR TANK}Construction method of external system scaffolding for spherical tank {OUTER SCAFFOLDING SYSTEM CONSTRUCTION METHOD FOR TANK}

본 발명은 구형탱크용 외부시스템비계에 대한 것이다. 더욱 구체적으로 지주를 이용하여 설치된 구형탱크의 외주면에 시스템비계모듈을 8각형의 수평 링 형태로 다단 조립 설치하여, 작업발판등 소요자재를 최적화시켜 신속하게 설치 및 해체가 가능하여, 보다 경제적인 구형탱크용 외부시스템비계 시공방법에 관한 것이다.The present invention relates to an external system scaffold for a spherical tank. More specifically, the system scaffolding module is assembled and installed in multiple stages in the form of an octagonal horizontal ring on the outer circumferential surface of the spherical tank installed using a post to optimize the required materials such as a work platform to enable quick installation and dismantling, resulting in a more economical spherical shape. It relates to a method of constructing an external system scaffold for a tank.

도 1a 및 도 1b는 종래 구형탱크(10)의 외부 조립식 비계시스템의 예시도이다.Figures 1a and 1b is an exemplary view of the external prefabricated scaffolding system of the conventional spherical tank (10).

상기 구형탱크(10)는 내부가 빈 원형 볼 형태로서 내부에 유류 등을 저장하기 위한 강재구조물이며, 지반에 자립 설치하기 위하여 지주(20)를 바닥에 설치하고, 지주(20) 내측으로 구형탱크(10)가 고정되도록 설치하고 있음을 알 수 있다.The spherical tank 10 is a steel structure for storing oil, etc., in the form of a circular ball with an empty inside, and a pole 20 is installed on the floor to be installed independently on the ground, and a spherical tank inside the pole 20 It can be seen that (10) is installed so that it is fixed.

이때 도 1a를 참조하면, 구형탱크(10) 외주면을 따라 외부 비계시스템으로서 작업발판(30)이 다단으로 설치되고 있음을 알 수 있으며, 상기 작업발판(30)을 수평으로 설치하기 위하여 파이프 형태의 수직 및 비계(40)를 이용하고 있음을 알 수 있다.At this time, referring to FIG. 1A , it can be seen that the working scaffold 30 is installed in multiple stages as an external scaffolding system along the outer circumferential surface of the spherical tank 10, and in order to install the working scaffold 30 horizontally, the pipe-shaped It can be seen that the vertical and scaffolding 40 are used.

이때 도 1b에 의하면, 작업발판(30)을 구형탱크(10) 외주면에 설치하기 위하여 브라켓(50)을 상기 외주면에 다수를 설치하는 방법도 소개되어 있음을 알 수 있다.At this time, according to FIG. 1b, it can be seen that a method of installing a plurality of brackets 50 on the outer circumferential surface of the spherical tank 10 in order to install the working scaffold 30 on the outer circumferential surface of the spherical tank 10 is also introduced.

도 1c는 종래 구형탱크(10)의 외주면을 따라 설치되는 유지보수대차(61) 및 선회장치(62) 설치 예시도를 도시한 것이다.Figure 1c shows an example of the installation of the maintenance bogie 61 and the turning device 62 installed along the outer peripheral surface of the conventional spherical tank (10).

즉, 구형탱크(10)가 지주(20)에 의하여 시공된 이후에, 구형탱크(10) 외부면 도장 작업을 하거나, 유지보수 작업을 하기 위해 작업자가 작업할 수 있는 유지보수대차(61)를 설치함에 있어, 구형탱크(10) 외주면에 레일(63), 선회장치(62)를 설치한 후, That is, after the spherical tank 10 is constructed by the pole 20, the spherical tank 10 external surface painting work, or a maintenance bogie 61 that a worker can work for to perform maintenance work. In the installation, after installing the rail 63 and the turning device 62 on the outer peripheral surface of the spherical tank 10,

별도의 구동시스템을 이용하여 구형탱크(10) 외주면 외주면을 따라 유지보수대차(61)나 선회장치(62)가 이동 또는 선회 할 수 있도록 하고 있음을 알 수 있다.It can be seen that the maintenance bogie 61 or the turning device 62 can move or turn along the outer peripheral surface of the spherical tank 10 by using a separate driving system.

이에 종래 구형탱크(10) 외주면 유지보수 등을 위해서는 대차나 선회장치를 이용할 수 있으나, 이러한 대차나 선회장치는 작업자가 탑승하는 방식으로 작업 범위가 매우 제한적이기 때문에, 구형탱크(10) 외주면에 다수의 비계(40)를 이용하여 작업발판을 설치하여 작업자가 구형탱크(10) 외주면을 따라 작업하는 방법도 소개되어 있음을 알 수 있다.Therefore, conventionally, a bogie or a turning device can be used for maintenance of the outer peripheral surface of the spherical tank 10, but since the work range of such a bogie or a turning device is very limited in a way that an operator boards, a plurality of the spherical tank 10 It can be seen that a method of installing a work scaffold by using the scaffold 40 of the spherical tank 10 and working along the outer circumferential surface of the spherical tank 10 is also introduced.

하지만 이러한 비계(40)와 작업발판을 설치하는 방법은 도 1a 및 도 1b를 참조하면, 설치 및 해체작업이 복잡하고, 많은 비용이 소요 될 뿐만 아니라, 최적의 구조해석에 의한 경제적 접근 방법도 아니라는 한계가 있었다.However, referring to Figures 1a and 1b for the method of installing the scaffold 40 and the work scaffold, the installation and dismantling work is complicated and costly, and it is not an economical approach based on the optimal structural analysis. There were limits.

일본국 특개 제2002-242424호(발명의 명칭: 구형탱크의 선회발반장치, 공개일자: 2002년08월28일)Japanese Patent Application Laid-Open No. 2002-242424 (Title of the invention: Turning and launching device for spherical tank, publication date: August 28, 2002) 일본국 특개 제2001-63797호(발명의 명칭: 구형탱크 상반외면용 선회발반, 공개일자: 2001년03월13일)Japanese Patent Application Laid-Open No. 2001-63797 (Title of the invention: Slewing platform for upper and outer surface of spherical tank, publication date: March 13, 2001) 대한민국 등록실용신안 제20-0354692호(발명의 명칭: 구형 탱크의 외부 검사 및 보수용 조립식 비계시스템에서의 작업대 좌우 회전장치, 공개일자: 2004년07월05일)Republic of Korea Registered Utility Model No. 20-0354692 (Title of the invention: Worktable left and right rotation device in prefabricated scaffolding system for external inspection and repair of old tanks, publication date: July 05, 2004)

이에 본 발명은 구형탱크용 외부시스템비계를 설치함에 있어서, 작업발판과 수직수평비계의 종류와 크기를 최적화시킨 상태에서 구형탱크의 외주면에 작업자가 작업가능한 공간을 다단으로 설치하되, 구조적 안정성과 경제성을 확보할 수 있는 구형탱크용 외부시스템비계 시공방법 제공을 해결하고자 하는 기술적과제로 한다.Therefore, in the present invention, when installing the external system scaffolding for a spherical tank, the space where the operator can work is installed in multiple stages on the outer circumferential surface of the spherical tank in a state where the type and size of the working scaffold and the vertical and horizontal scaffold are optimized, but structural stability and economic feasibility It is a technical task to solve the provision of an external system scaffolding construction method for spherical tanks that can secure

또한, 본 발명은 구형탱크용 외부시스템비계를 다단 설치함에 있어서, 지주에 설치된 구형탱크에 설치 및 해체가 용이하도록 모듈화된 구형탱크용 외부시스템비계를 이용함으로서 보다 신속한 구형탱크용 외부시스템비계 시공방법 제공을 해결하고자 하는 기술적과제로 한다.In addition, the present invention provides a faster method of constructing an external system scaffold for a spherical tank by using an external system scaffold for a spherical tank that is modularized to facilitate installation and dismantling of the spherical tank installed on a post in multi-stage installation of an external system scaffold for a spherical tank. It is a technical task to be solved.

또한, 본 발명은 구형탱크용 외부시스템비계를 종래 설치방법과 달리 진보적인 시스템 비계를 이용하기 때문에 보다 구조화 설계가 가능한 구형탱크용 외부시스템비계 시공방법 제공을 해결하고자 하는 기술적과제로 한다.In addition, the present invention is a technical task to solve the provision of an external system scaffold for a spherical tank construction method for a spherical tank that can be more structured because it uses an advanced system scaffold unlike the conventional installation method.

상기 과제를 달성하기 위한 본 발명의 구형탱크용 외부시스템비계 시공방법은, (a) 구형탱크의 외주면의 직경에 따라 중심을 향하여 중심으로 갈수록 설치폭이 좁아지는 8개의 사다리꼴 형태로, 구형탱크의 각 단마다 8각형의 수평링 형태로 시스템비계모듈을 조립 설치하는 단계; (b) 상기 시스템비계모듈이 8각형의 수평 링 형태로 배치되어 지주, 구형탱크의 외주면 주위에 작업자에게 작업공간을 확보할 수 있도록 시스템비계모듈과 함께 작업발판을 조립 설치하는 단계; 및 (c) 상기 8개의 사다리꼴 형태로 조립 설치되는 시스템비계모듈을 수평으로 서로 연결시켜 시스템비계모듈의 파손이 다른 시스템비계모듈에 전달되지 않도록 시스템비계모듈과 함께 수평재를 설치하는 단계;를 포함하여, 각각 8개의 사다리꼴 형태의 시스템비계모듈은 각 단에 따른 구형탱크의 직경에 맞추어 치수가 정해진 작업발판과 수직수평비계를 조합하여 제작한 것을 이용하여 구조적 안정성을 사전에 검토하여 설치할 수 있도록 하게 된다.The method for constructing an external system scaffold for a spherical tank of the present invention for achieving the above object is, (a) in the form of eight trapezoids in which the installation width becomes narrower toward the center according to the diameter of the outer circumferential surface of the spherical tank, Assembling and installing a system scaffolding module in the form of an octagonal horizontal ring for each stage; (b) the system scaffold module is arranged in an octagonal horizontal ring shape, so as to secure a working space for the operator around the outer circumferential surface of the post and the spherical tank; and (c) installing the horizontal member together with the system scaffolding module so that the system scaffolding modules assembled and installed in the eight trapezoidal shape are horizontally connected to each other so that the damage of the system scaffolding module is not transmitted to other system scaffolding modules. , each of the eight trapezoidal system scaffolding modules can be installed by examining the structural stability in advance using a combination of a working scaffold and a vertical and horizontal scaffold whose dimensions are determined according to the diameter of the spherical tank at each stage. .

본 발명에 의하면, 구형탱크 하단으로부터 상단으로 갈수록 외주면의 직경이 일정하게 변경되기 때문에 구형탱크용 외부시스템비계를 8각형의 수평 링 형태의 시스템비계모듈로 수평 조립 설치하되, 각각 8개의 시스템비계모듈들은 각 단에 따른 구형탱크의 직경에 맞추어 치수가 정해진 최적의 작업발판과 수직수평비계를 조합하여 제작한 것을 이용하여 구조적 안정성을 충분히 사전에 검토하여 설치할 수 있어, 보다 효율적이고 경제적인 구형탱크용 외부시스템비계 시공방법 제공이 가능하게 된다.According to the present invention, since the diameter of the outer peripheral surface is constantly changed from the bottom to the top of the spherical tank, the external system scaffold for the spherical tank is horizontally assembled and installed as a system scaffold module in the form of an octagonal horizontal ring, but each of 8 system scaffolding modules The spherical tank is more efficient and economical because it can be installed by sufficiently examining the structural stability in advance by using a combination of the optimal working scaffold and vertical and horizontal scaffolding, the dimensions of which are determined according to the diameter of the spherical tank according to each stage. It becomes possible to provide an external system scaffolding construction method.

또한, 본 발명의 8개의 시스템비계모듈들은 각단에 있어 구형탱크와 지주에 대응하여 서로 수평재와 경사재를 구속하여 외부 하중에 대하여 개별적으로 저항할 수 있기 때문에, 보다 안정적인 구형탱크용 외부시스템비계 시공방법 제공이 가능하게 된다.In addition, since the eight system scaffolding modules of the present invention can individually resist external load by restraining the horizontal member and the inclined member to each other corresponding to the spherical tank and the pole at each stage, more stable external system scaffolding for the spherical tank method can be provided.

또한, 본 발명의 8개의 시스템비계모듈은 작업발판과 수직수평비계를 조합하여 제작한 것으로서 조립에 나아가 해체도 용이하기 때문에 자재회수율이 커지고, 신속한 구형탱크용 외부시스템비계 시공방법 제공이 가능하게 된다.In addition, since the eight system scaffolding modules of the present invention are manufactured by combining a working scaffold and a vertical and horizontal scaffold, the material recovery rate is increased because it is easy to assemble and dismantle, and it is possible to provide a quick construction method for an external system scaffold for a spherical tank. .

도 1a 및 도 1b는 종래 구형탱크의 외부 조립식 비계시스템의 예시도,
도 1c는 종래 구형탱크의 외주면을 따라 설치되는 유지보수대차 및 선회장치 설치 예시도,
도 2a 및 도 2b는 본 발명의 구형탱크용 외부시스템비계의 시공단면도 및 시스템비계모듈설치 예시도,
도 3a, 도 3b 및 도 3c 및 도 3d는 본 발명의 구형탱크용 외부시스템비계의 작업발판, 수직수평비계, 경사재, 수평재, 상단트러스의 예시도,
도 4a, 도 4b, 도 4c, 도 4d 및 도 4e는 본 발명의 구형탱크용 외부시스템비계의 시공순서도이다.
1A and 1B are exemplary views of an external prefabricated scaffolding system of a conventional spherical tank;
1c is an example of installation of a maintenance bogie and a turning device installed along the outer peripheral surface of a conventional spherical tank;
Figure 2a and Figure 2b is a construction sectional view of the external system scaffolding for a spherical tank of the present invention and an exemplary view of the system scaffold module installation,
3a, 3b and 3c and 3d are an exemplary view of a working scaffold, a vertical horizontal scaffold, a slope member, a horizontal member, and an upper truss of an external system scaffold for a spherical tank of the present invention;
Figure 4a, Figure 4b, Figure 4c, Figure 4d and Figure 4e is a construction flow chart of the external system scaffold for a spherical tank of the present invention.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those of ordinary skill in the art can easily implement them. However, the present invention may be embodied in various different forms and is not limited to the embodiments described herein. And in order to clearly explain the present invention in the drawings, parts irrelevant to the description are omitted, and similar reference numerals are attached to similar parts throughout the specification.

명세서 전체에서, 어떤 부분이 어떤 구성요소를 "포함"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다.Throughout the specification, when a part "includes" a certain component, it means that other components may be further included, rather than excluding other components, unless otherwise stated.

[ 본 발명의 구형탱크용 외부시스템비계(100)][External system scaffolding for spherical tank of the present invention (100)]

도 2a 및 도 2b는 본 발명의 구형탱크용 외부시스템비계(100)의 시공단면도 및 시스템비계모듈설치 예시도를 도시한 것이다.Figures 2a and 2b shows a construction sectional view of the external system scaffold 100 for a spherical tank of the present invention and an exemplary view of the system scaffold module installation.

상기 본 발명의 구형탱크용 외부시스템비계(100)는 도 2a를 참조하면 다수의 지주(210)에 구형탱크(220)의 외측이 일체로 고정되어 하단(230)은 지상으로부터 이격되어 위치하고, 상단(240)과 하단(230)에 걸쳐 외주면과 이격되어 다단(예컨대 제 1단 내지 제 18단)으로 구형탱크용 외부시스템비계(100)가 설치되도록 하게 된다.The external system scaffold 100 for a spherical tank of the present invention is, with reference to FIG. 2a, the outside of the spherical tank 220 is integrally fixed to a plurality of posts 210 so that the lower end 230 is located spaced apart from the ground, It is spaced apart from the outer peripheral surface over 240 and the lower end 230 so that the external system scaffold 100 for the spherical tank is installed in multiple stages (eg, the first stage to the 18th stage).

즉, 상기 구형탱크용 외부시스템비계(100)는 수직수평비계(130)에 의하여 설치된 작업발판(120)이 구형탱크(220)의 외주면을 감싸도록 수평 링 형태로 다단(1 내지 18단) 설치되도록 한 것임을 알 수 있다.That is, the external system scaffold 100 for the spherical tank is installed in multiple stages (1 to 18 stages) in a horizontal ring form so that the working scaffold 120 installed by the vertical horizontal scaffold 130 surrounds the outer circumferential surface of the spherical tank 220 . It can be seen that this was done.

이에, 도 2b에 의하면, 각단(예컨대, 1단,2단....18단)의 구형탱크용 외부시스템비계(100)는 8개의 시스템비계모듈(110)들이, 구형탱크(220)의 외주면의 직경에 대응하여 예컨대 사다리꼴 형태로 조립 설치하되, 전체적으로 8각형의 수평 링 형태로 수평 조립되고 있음을 알 수 있고, Accordingly, according to FIG. 2b , the external system scaffolding 100 for a spherical tank of each stage (eg, 1st stage, 2nd stage ... 18 stages) has eight system scaffolding modules 110 of the spherical tank 220 . In response to the diameter of the outer circumferential surface, for example, but assembled in a trapezoidal shape, it can be seen that as a whole, it is horizontally assembled in the form of an octagonal horizontal ring,

각각의 시스템비계모듈(110)은 수평재(150)와 경사재(140)를 이용하여 서로 구속되도록 하면서, 지주(210)에 구형탱크(220)에 연결 및 지지되도록 하고 있음을 알 수 있다.It can be seen that each system scaffolding module 110 is connected to and supported by the spherical tank 220 on the post 210 while constrained to each other using the horizontal member 150 and the inclined member 140 .

이때, 각 단에 있어 8개의 사다리꼴 형태로 시스템비계모듈(110)로 조립 설치하게 되면 개개의 8개의 시스템비계모듈(110)에 사용되는 작업발판(120)은 최소한의 개수로 조립 설치할 수 있어 작업발판(120)과 수직수평비계(130) 조립 개수를 최적화시킬 수 있게 되고,At this time, when assembling and installing the system scaffolding module 110 in the form of 8 trapezoids at each stage, the working scaffold 120 used for each of the 8 system scaffolding modules 110 can be assembled and installed with a minimum number of work. It is possible to optimize the number of assembly of the scaffold 120 and the vertical and horizontal scaffolding 130,

시스템비계모듈(110) 각각은 서로 분리되어 설치되기 때문에 특정 시스템비계모듈(110)의 파손이 다른 시스템비계모듈(110)에 영향이 전달되지 않도록 하는 장점이 있게 된다.Since each of the system scaffolding modules 110 is installed separately from each other, there is an advantage in that the damage of a specific system scaffolding module 110 does not affect the other system scaffolding modules 110 .

또한, 시스템비계모듈(110) 각각은 규격화된 작업발판(120)과 수직수평비계(130)를 이용하여 조립 제작 및 해체도 간단 해지기 때문에 구조적 설계를 단순화시켜 효과적인 품질관리 및 시공관리가 가능하게 된다.In addition, each of the system scaffolding modules 110 uses a standardized work scaffold 120 and vertical and horizontal scaffolding 130 to simplify assembly, manufacturing and dismantling, thereby simplifying the structural design to enable effective quality control and construction management. do.

이에 상기 본 발명의 구형탱크용 외부시스템비계(100)는 도 2a 및 도 2b와 같이 시스템비계모듈(110), 작업발판(120), 수직수평비계(130), 경사재(140), 수평재(150), 상단트러스(160)를 포함하게 된다.Accordingly, the external system scaffolding 100 for a spherical tank of the present invention is a system scaffolding module 110, a working scaffold 120, a vertical horizontal scaffolding 130, a slope member 140, a horizontal member as shown in FIGS. 2a and 2b ( 150), and the upper truss 160 is included.

상기 시스템비계모듈(110)은 도 2a 및 도 2b와 같이, 구형탱크(220)의 외주면의 직경에 따라 중심을 향하여 8개의 사다리꼴 형태(중심으로 갈수록 설치폭이 좁아지는 형태)로 조립 설치되어 각 단(도 2b의 경우 4, 13, 18단)마다 8각형의 수평링 형태로 조립 설치된 것으로서, 구형탱크(220) 외주면 전체에 수직수평비계(130)를 이용하여 작업발판(120)을 구형탱크(220)의 외주면에 이격되어 설치 및 해체될 수 있도록 한 것이다.The system scaffolding module 110 is assembled and installed in the form of eight trapezoids toward the center according to the diameter of the outer circumferential surface of the spherical tank 220 (the form of which the installation width becomes narrower toward the center), as shown in FIGS. 2a and 2b. As an octagonal horizontal ring for every stage (4, 13, and 18 stages in the case of FIG. 2b), the spherical tank 220 uses a vertical horizontal scaffold 130 on the entire outer peripheral surface of the spherical tank 220 to install the working scaffold 120 into the spherical tank. It is spaced apart from the outer peripheral surface of 220 so that it can be installed and dismantled.

이때 8개 각각의 시스템비계모듈(110)은 수평재(150)에 의하여 서로 수평 연결되어 구속되어 있음을 알 수 있다.At this time, it can be seen that each of the eight system scaffolding modules 110 are horizontally connected to each other by the horizontal member 150 and are constrained.

즉, 도 2a와 같이 구형탱크(220)를 기준으로 상하 이격되어 제 1단에서 제 18단으로 설치된 시스템비계모듈(110)이 설치되고 있지만, 도 2b에는 4단, 13단, 18단에 의한 시스템비계모듈(110)의 단면도가 대표적으로 도시되어 있다.That is, although the system scaffolding module 110 installed from the first stage to the 18th stage is installed vertically spaced apart from the spherical tank 220 as shown in FIG. 2A, in FIG. 2B, 4 stages, 13 stages, and 18 stages A cross-sectional view of the system scaffolding module 110 is shown representatively.

예컨대, 도 2b의 제 4단으로 설치되는 구형탱크용 외부시스템비계(100)는 8개의 시스템비계모듈(110)이 서로 수평 연결되어 구형탱크의 중심을 향하여 8각형의 수평링 형태로 배치되어 있음을 알 수 있다.For example, in the external system scaffolding 100 for a spherical tank installed in the fourth stage of FIG. 2b, eight system scaffolding modules 110 are horizontally connected to each other and arranged in the form of an octagonal horizontal ring toward the center of the spherical tank. can be found

이에 설치되어야 하는 전체 면적에 대응하여 8개의 시스템비계모듈(110) 각각은 1-3종류의 작업발판(120)만을 수직수평비계(130)로 연결하여 설치하면 되기 때문에 신속한 설치 및 해제가 가능하게 된다.In response to the total area to be installed, each of the eight system scaffolding modules 110 only needs to be installed by connecting only 1-3 types of work scaffolds 120 to the vertical and horizontal scaffolding 130, so that quick installation and release are possible. do.

다음으로 도 2b의 제 13단과 제 18단으로 구형탱크용 외부시스템비계(100)도 8개의 시스템비계모듈(110)이 서로 연결되어 구형탱크의 중심을 향하여 8각형의 수평링 형태로 배치되도록 함은 동일하고,Next, as the 13th and 18th stages of FIG. 2b, the external system scaffolding 100 for the spherical tank is also connected to the eight system scaffolding modules 110 to be arranged in the form of an octagonal horizontal ring toward the center of the spherical tank. is the same,

단지, 제 13단과 제 18단에 대응하는 구형탱크(220)의 직경은 차이가 있으므로 설치되는 수직수평비계(130)를 이용하여 작업발판(120)의 설치개수에만 차이가 있음을 알 수 있으며, However, since there is a difference in the diameter of the spherical tank 220 corresponding to the 13th and 18th stages, it can be seen that there is a difference only in the number of installations of the working scaffolding 120 using the vertical horizontal scaffolding 130 installed,

특히 제 18단의 경우 구형탱크(220)의 상단 주위까지 설치되는 것이기 때문에 가장 작업발판(120)의 설치개수 가장 많아지게 됨을 알 수 있다.In particular, in the case of the 18th stage, it can be seen that the installation number of the working scaffold 120 is the largest because it is installed up to the upper end of the spherical tank 220 .

이로서 시스템비계모듈(110)을 구성하는 작업발판(120)과 수직수평비계(130)는 각단에 따라 설치 수만 차이가 나도록 설계할 수 있어, 설계도 간단해지고, 구조적 해석도 용이하여 구조적 안전성 확보와 검증이 가능하게 되고, 작업자도 동일한 형태의 크기만 서로 일부 차이가 있을 뿐이므로 설치 및 해체 속도의 증진이 가능하여, 보다 경제적인 구형탱크용 외부시스템비계(100) 시공이 가능하게 된다.As a result, the working scaffold 120 and the vertical and horizontal scaffolding 130 constituting the system scaffold module 110 can be designed so that only the number of installations differs according to each stage, making the design simple and structural analysis easy to secure and verify structural safety. This is made possible, and since there is only a partial difference between the size of the same shape and size, it is possible to increase the speed of installation and dismantling, so that more economical construction of the external system scaffold 100 for a spherical tank is possible.

또한 각단의 시스템비계모듈(110)은 수평재(150)에 의하여 수평 결속은 되어있지만 서로 분리되어 설치되기 때문에 어느 1개의 시스템비계모듈(110)이 파손되더라도 나머지 7개의 시스템비계모듈(110)에는 큰 영향이 없어 보다 안정적인 상태가 되고, 예측할 수 없는 풍력이 발생하더라도 각각의 시스템비계모듈(110)은 구형탱크(220)의 중심을 향하도록 배치되어 있어 안정적으로 저항하면서도 주위의 시스템비계모듈(110)에 영향을 전달하지 않을 수 있게 된다.In addition, although the system scaffolding module 110 of each stage is horizontally bound by the horizontal member 150, since they are installed separately from each other, even if any one of the system scaffolding modules 110 is damaged, the remaining 7 system scaffolding modules 110 have a large It is in a more stable state without any influence, and even if an unpredictable wind force occurs, each system scaffold module 110 is arranged to face the center of the spherical tank 220, so that it resists stably and the surrounding system scaffold module 110 It is possible not to transmit the effect to

이러한 시스템비계모듈(110)은 후술되는 작업발판(120)을 수직수평비계(130), 경사재(140), 수평재(150), 상단트러스(160)를 설치하는 과정에서 구형탱크(220)의 외주면에 8개의 사다리꼴 형태로 설치되어 전체적으로는 8각형의 수평 링 형태로 설치된다.This system scaffold module 110 is a spherical tank 220 in the process of installing the working scaffold 120 to be described later with the vertical horizontal scaffold 130 , the inclined member 140 , the horizontal member 150 , and the upper truss 160 . It is installed in the form of eight trapezoids on the outer circumferential surface and is installed in the form of an octagonal horizontal ring overall.

다음으로 작업발판(120)은 도 2a와 도 2b와 같이, 시스템비계모듈(110) 각각이 8각형의 수평 링 형태로 배치되어 지주(210), 구형탱크(220)의 외주면 주위에 작업자에게 작업공간을 확보할 수 있도록 한 것으로서, 이러한 작업발판(120)은 시스템비계모듈(110) 설치 시 함께 설치하게 된다.Next, the work scaffold 120 is, as shown in FIGS. 2a and 2b, each of the system scaffolding modules 110 is arranged in the form of an octagonal horizontal ring, the post 210, the spherical tank 220 around the outer peripheral surface of the work to the operator In order to secure a space, such a work scaffold 120 is installed together when the system scaffolding module 110 is installed.

구형탱크용 외부시스템비계(100)에 사용되는 작업발판(120)의 크기에 따른 종류가 너무 많게 되면, 자재 수급과 작업자가 연결 시켜야 할 작업발판(120)의 대상이 많아지게 되므로 작업효율이 저하될 수밖에 없게 되고, 연결작업량도 많아지게 된다. 이에 본 발명은 각단의 시스템비계모듈(110)에서 설치 해야할 면적에 맞추어 다수의 작업발판을 제작하여 조달하는 것이 아니라,If there are too many types according to the size of the working scaffold 120 used in the external system scaffolding 100 for a spherical tank, the number of objects of the working scaffold 120 to be connected to the material supply and demand and the worker increases, so the working efficiency is lowered. It becomes inevitable, and the amount of connection work increases. Accordingly, the present invention does not manufacture and procure a plurality of work scaffolds according to the area to be installed in the system scaffolding module 110 of each stage,

8개의 시스템비계모듈(110) 각각은 1-3종류의 작업발판(120)만을 수직수평비계(130)로 연결하여 설치하도록 하였기 때문에, 본 발명은 작업발판(120)의 사용 효율성이 증진되어 설치 및 해체가 용이하고, 성능인증을 받은 검증된 작업발판(120)을 이용하면 되기 때문에 작업발판(120)의 설치개수를 최적화시킬 수 있게 된다.Since each of the eight system scaffolding modules 110 is installed by connecting only 1-3 types of working scaffolds 120 to the vertical and horizontal scaffolding 130, the present invention improves the use efficiency of the working scaffolds 120 and installs them. And it is possible to optimize the number of installations of the working scaffold 120 because it is easy to disassemble and use the verified working scaffold 120 that has received performance certification.

예컨대, 도 2b의 제 4, 13, 19단 모두 시스템비계모듈(110)에 사용되는 작업발판(120)은 모두 도 3a과 같이 [B400*1829] 크기의 제품만을 서로 연결하여 8각형의 수평 링 형태로 조립 설치하고 있음을 알 수 있다.For example, the 4th, 13th, and 19th stages of FIG. 2b all work scaffold 120 used for the system scaffolding module 110, as shown in FIG. 3a, only the [B400 * 1829] size products are connected to each other to form an octagonal horizontal ring It can be seen that the assembly is installed in the form.

도 3a에 의하면 본 발명의 구형탱크(200)에 사용되는 작업발판(120)의 크기별 종류를 개시하고 있는데, 폭은 모두 B400 제품을 사용하고, 연장 길이만 서로 다른 것들을 이용하고, 이러한 각각의 작업발판(120)은 서로 연결하여 필요한 작업발판(120)의 종류와 설치개수를 최적화시켜 8개의 시스템비계모듈(110)에 모두 이용할 수 있게 된다.According to FIG. 3a, the types of the working scaffolds 120 used in the spherical tank 200 of the present invention are disclosed for each size, and the widths are all B400 products, only the extension lengths are different, and each of these works The scaffolding 120 is connected to each other to optimize the type and number of installations of the required working scaffolding 120 so that it can be used for all eight system scaffolding modules 110 .

상기 수직수평비계(130) 및 경사재(140)는 도 2a와 도 2b를 참조하면 각 단의 시스템비계모듈(110)의 작업발판(120)을 설치하기 위해서 사용되는 가설자재로서 작업발판(120)은 수평판 형태이므로 수직수평비계(130)와 경사재(140)를 이용하여 각 단의 높이에 따라 입체형태로 설치되며, 역시 시스템비계모듈(110) 설치 시 함께 설치하게 된다.The vertical horizontal scaffold 130 and the inclined member 140 are temporary materials used to install the working scaffold 120 of the system scaffolding module 110 of each stage with reference to FIGS. 2A and 2B, and the working scaffold 120 is ) is in the form of a horizontal plate, so it is installed in a three-dimensional form according to the height of each stage using the vertical horizontal scaffold 130 and the inclined material 140, and is also installed when the system scaffold module 110 is installed.

구체적으로는 도 3b 및 도 3c에 의하면, 단관파이프 형태의 수직수평비계(130)가 경사재(140)에 의하여 연결되도록 하고 있으며, 수직수평비계(130)도 단위길이 제품을 서로 연결하는 방식으로 설치 및 해체가 가능하도록 하게 된다.Specifically, according to FIGS. 3b and 3c, the vertical horizontal scaffolding 130 in the form of a single pipe pipe is connected by the inclined material 140, and the vertical scaffolding 130 also connects the unit length products to each other. Installation and disassembly are possible.

경사재(140)의 경우 양 단부는 갈고리 형태로 형성되어 있어 수직수평비계(130)에 경사지게 걸어 설치하여 수직으로 연장되는 수직수평비계(130)를 서로 구속하여 안정성을 확보할 수 있도록 하고 있음을 알 수 있으며, 경사길이에 따라 종류가 달라질 뿐이다.In the case of the inclined material 140, both ends are formed in the form of hooks, so that they are installed by hanging on the vertical horizontal scaffolding 130 at an angle to restrain the vertically extending vertical scaffolding 130 to each other to ensure stability. It can be seen that, only the type is different depending on the length of the slope.

상기 수평재(150)는 도 2a 및 도 2b와 같이, 각 단의 시스템비계모듈(110)에 있어서, 8각형의 수평 링 형태로 설치되는 시스템비계모듈(110)를 수평으로 서로 연결시켜 주기 위한 것이라 할 수 있으며, 역시 시스템비계모듈(110) 설치 시 함께 설치하게 된다.The horizontal member 150 is for horizontally connecting the system scaffolding module 110 installed in the form of an octagonal horizontal ring in the system scaffolding module 110 of each stage as shown in FIGS. 2A and 2B. It can be done, and it will be installed together when the system scaffolding module 110 is installed.

이러한 수평재(150)로서 양 단부에 체결구가 형성된 단관 파이프를 이용할 수 있으며, 도 2b를 기준으로 하면 각각의 시스템비계모듈(110)의 측면을 서로 연결하는데 이용함으로서 서로 결속시켜 안정성을 확보할 수 있도록 하면서 8각형 수평 링 형태를 유지하는데 이용된다.As such a horizontal member 150, a single pipe pipe having fasteners formed at both ends can be used, and when referring to FIG. 2b, by using the side surfaces of each system scaffold module 110 to connect to each other, stability can be secured by binding them to each other. It is used to maintain the shape of an octagonal horizontal ring while maintaining the

즉, 시스템비계모듈(110) 각각은 서로 분리되어 설치되기 때문에 특정 시스템비계모듈(110)의 파손이 다른 시스템비계모듈(110)에 영향이 전달되지 않도록 하는 역할(전달되더라도 제한적으로 전달됨)을 상기 수평재(150)가 담당하게 된다.In other words, since each of the system scaffolding modules 110 is installed separately from each other, the role of preventing the damage of a specific system scaffolding module 110 from being transmitted to other system scaffolding modules 110 (even if delivered, it is transmitted limitedly). The horizontal member 150 is in charge.

상기 상단트러스(160)는 도 2a 및 도 3d와 같이, 구형탱크(220)의 상단(240)에는 통상 개구부가 형성되어 있어 이러한 개구부를 막지 않도록 하면서 시스템비계모듈(110)을 상단(240)에서 서로 안정적으로 연결해주기 위한 것으로서 수직수평비계(130)와 연결시켜 설치하면 되며 역시 시스템비계모듈(110) 설치 시 함께 설치하게 된다.The upper truss 160 has an opening at the upper end 240 of the spherical tank 220, as shown in FIGS. 2A and 3D, so as not to block the opening, and the system scaffolding module 110 from the upper end 240. In order to stably connect each other, it can be installed in connection with the vertical and horizontal scaffolding 130 , and also installed together when the system scaffolding module 110 is installed.

이와 같이 트러스부재로 상단트러스를 제작하게 되면, 작업 난간의 역할도 하게 되어 작업자가 개구부로 접근이 용이하게 되고 역시 설치 및 해체에 유리하게 된다.When the upper truss is manufactured with the truss member in this way, it also serves as a work rail, so that the operator can easily access the opening, which is also advantageous for installation and dismantling.

[ 본 발명의 구형탱크용 외부시스템비계(100) 시공방법 ][External system scaffolding 100 for spherical tank construction method of the present invention]

도 4a, 도 4b, 도 4c, 도 4d 및 도 4e는 본 발명의 구형탱크용 외부시스템비계(100)의 시공순서도이다.4a, 4b, 4c, 4d and 4e is a construction flow chart of the external system scaffold 100 for a spherical tank of the present invention.

상기 구형탱크용 외부시스템비계(100)의 시공방법은, 지주(210)에 의하여 바닥에 이격되어 설치된 구형탱크(220)의 외주면에 구형탱크용 외부시스템비계(100)를 상하 다단으로 8각형의 수평 링 형태로 설치하는 방법이라 할 수 있다.The construction method of the external system scaffold 100 for a spherical tank is to install the external system scaffold 100 for a spherical tank on the outer circumferential surface of the spherical tank 220 installed to be spaced apart from the floor by a post 210 in an octagonal shape in upper and lower stages. It can be said that it is a method of installing in the form of a horizontal ring.

이에 구형탱크용 외부시스템비계(100) 설치에 필요한 소요의 시스템비계모듈(110), 작업발판(120), 수직수평비계(130), 경사재(140), 수평재(150), 상단트러스(160)와 같은 가설자재를 준비하게 되는데, Accordingly, the required system scaffolding module 110, work scaffold 120, vertical horizontal scaffold 130, inclined member 140, horizontal member 150, upper truss 160 required for the installation of the external system scaffolding 100 for the spherical tank ) to prepare temporary materials such as

예컨대 제 1 내지 18단 각각에 소요되는 구형탱크용 외부시스템비계(100)의 가설자재의 개수는 다르지만 8개의 구형탱크용 외부시스템비계(100)을 각 단마다 조립 연결하는 것은 동일 하기 때문에 신속한 조립 설치가 가능하다.For example, although the number of temporary materials of the external system scaffold 100 for a spherical tank required for each of the first to 18 stages is different, assembling and connecting the eight external system scaffolding 100 for the spherical tank for each stage is the same, so quick assembly Installation is possible.

이에 도 4a는 도 2a에 의한 구형탱크(220)의 제 1단 내지 18단에 있어 제 1,2,3 단의 구형탱크용 외부시스템비계(100)의 설치단면도를 도시한 것이다.Accordingly, FIG. 4A shows an installation sectional view of the external system scaffold 100 for the spherical tank of the first, second, and third stages in the first to 18 stages of the spherical tank 220 according to FIG. 2A.

즉, 구형탱크(220)의 중간을 기준으로 하방쪽으로 갈수록 구형탱크의 직경은 작아지게 되므로 제 1단의 경우 수평재(150)로 연결된 8개의 사다리꼴 형태로 조립 설치되어 전체적으로 8각형의 수평 링 형태로 설치되며, 이는 앞서 살펴본 작업발판(120)의 설치개수만 위쪽 단들과 대비하여 증가할 뿐, 수직수평비계(130), 경사재(140), 수평재(150)를 이용하여 설치하는 작업으로 간단하게 설치할 수 있음을 알 수 있다.That is, the diameter of the spherical tank becomes smaller as it goes downward based on the middle of the spherical tank 220. In the case of the first stage, it is assembled and installed in the form of eight trapezoids connected by the horizontal member 150 to form an octagonal horizontal ring as a whole. It is installed, which only increases the number of installations of the working scaffold 120 as seen above compared to the upper stages, and is simply a work of installing using the vertical and horizontal scaffolding 130 , the inclined member 140 , and the horizontal member 150 . You can see that it can be installed.

이에 제 2,3단은 제 1단보다 구형탱크(220)의 직경이 커지게 되므로 수평재(150)로 연결된 8각형의 수평 링 형태로 설치하는 것은 동일하고, 작업발판(120)의 설치개수가 적어짐을 알 수 있다.Accordingly, the second and third stages have a larger diameter of the spherical tank 220 than the first stage, so it is the same to install in the form of an octagonal horizontal ring connected to the horizontal member 150, and the number of installations of the working platform 120 is It can be seen that less

다음으로 도 4b는 도 2a에 의한 구형탱크(220)의 제 1단 내지 18단에 있어 제 4,5,6,7,8,9단의 구형탱크용 외부시스템비계(100)의 설치단면도를 도시한 것이다.Next, Figure 4b is a cross-sectional view of the installation of the external system scaffold 100 for the spherical tank of the 4,5,6,7,8,9 stages in the 1st to 18th stages of the spherical tank 220 according to Fig. 2a. it will be shown

도 2a를 참조하면 제 4-9단의 경우 구형탱크(220)의 직경이 가장 커지는 부위이기도 하고, 지주(210)의 간섭도 포함된 구간이므로 수평재(150)로 연결된 8각형의 수평 링 형태로 설치하는 것은 동일하고, 작업발판(120)의 설치개수가 상대적으로 줄어들게 될 뿐임을 알 수 있다.Referring to Figure 2a, in the case of stage 4-9, the diameter of the spherical tank 220 is the largest, and since the section also includes the interference of the posts 210, it is in the form of an octagonal horizontal ring connected by a horizontal member 150. It can be seen that the installation is the same, and the number of installations of the working scaffold 120 is relatively reduced.

다음으로 도 4c, 도 4d, 도 4e는 구형탱크(220)의 제 1단 내지 18단에 있어 제 10,11,12,13,14,15,16,17,18단의 구형탱크용 외부시스템비계(100)의 설치단면도를 도시한 것이다.Next, FIGS. 4c, 4d, and 4e are external systems for spherical tanks of 10, 11, 12, 13, 14, 15, 16, 17, and 18 stages in the first to 18 stages of the spherical tank 220. It shows an installation sectional view of the scaffold 100 .

도 2a를 참조하면 제 10-18단은 구형탱크(220)의 개략 중간부에서 상단(240) 쪽에 해당하므로 다시 구형탱크(220)의 직경이 커지게 되고, 상대적으로 설치되는 작업발판(120)의 개수도 증가하게 되며, 수평재(150)로 연결된 8각형의 수평 링 형태로 설치하는 것은 동일하고, 구형탱크(220)의 단면으로 보았을 때 중심점(중심)으로 수렴되고 있음을 알 수 있다.Referring to Figure 2a, the 10th - 18th stage corresponds to the upper end 240 side in the schematic middle part of the spherical tank 220, so the diameter of the spherical tank 220 is increased again, and the working scaffold 120 is relatively installed. The number of is also increased, and it is the same to install in the form of an octagonal horizontal ring connected to the horizontal member 150, and it can be seen that the spherical tank 220 is converging to the central point (center) when viewed in cross section.

이에 도 2a와 같이 구형탱크(220)의 상단(240)에서는 상단트러스(160)를 이용하여 구형탱크용 외부시스템비계(100)를 완성 시키게 된다.Accordingly, as shown in FIG. 2a, the upper end 240 of the spherical tank 220 uses the upper truss 160 to complete the external system scaffold 100 for the spherical tank.

이에 작업자는 각 단마다 설치된 8각형의 수평 링 형태로 설치된 구형탱크용 외부시스템비계(100)의 작업발판(120)을 이용하여 구형탱크(220)의 외주면 보수, 보강을 실시하고, 완료되면 통상적으로는 바닥에서 제 1단부터 구형탱크용 외부시스템비계(100)을 설치하게 되므로, 역으로 상단(240)부터 구형탱크용 외부시스템비계(100)을 해체하게 된다.Accordingly, the operator performs repair and reinforcement of the outer peripheral surface of the spherical tank 220 by using the working scaffold 120 of the external system scaffold 100 for the spherical tank installed in the form of an octagonal horizontal ring installed at each stage, and when completed, the normal Since the external system scaffold 100 for the spherical tank is installed from the first stage at the bottom, the external system scaffold 100 for the spherical tank is dismantled from the top 240 in reverse.

즉, 작업발판(120)과 수직수평비계(130)는 체결식, 소켓식등 분리가 가능하도록 조립 설치되고, 이는 경사재(140), 수평재(150), 상단트러스(160)도 마찬가지이므로 최종 해체가 가능하게 된다.That is, the work scaffold 120 and the vertical horizontal scaffold 130 are assembled and installed so that they can be separated by a fastening type, a socket type, etc. disassembly is possible.

전술한 본 발명의 설명은 예시를 위한 것이며, 본 발명이 속하는 기술분야의 통상의 지식을 가진 자는 본 발명의 기술적 사상이나 필수적인 특징을 변경하지 않고서 다른 구체적인 형태로 쉽게 변형이 가능하다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시예들은 모든 면에서 예시적인 것이며 한정적이 아닌 것으로 이해해야만 한다. 예를 들어, 단일형으로 설명되어 있는 각 구성 요소는 분산되어 실시될 수도 있으며, 마찬가지로 분산된 것으로 설명되어 있는 구성 요소들도 결합된 형태로 실시될 수 있다.The above description of the present invention is for illustration, and those of ordinary skill in the art to which the present invention pertains can understand that it can be easily modified into other specific forms without changing the technical spirit or essential features of the present invention. will be. Therefore, it should be understood that the embodiments described above are illustrative in all respects and not restrictive. For example, each component described as a single type may be implemented in a distributed manner, and likewise components described as distributed may also be implemented in a combined form.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is indicated by the following claims rather than the above detailed description, and all changes or modifications derived from the meaning and scope of the claims and their equivalents should be interpreted as being included in the scope of the present invention. do.

100:구형탱크용 외부시스템비계
110:시스템비계모듈 120:작업발판
130:수직수평비계 140:경사재
150:수평재 160:상단트러스
210:지주 220:구형탱크
230:구형탱크의 하단 240:구형탱크의 상단
100: External system scaffolding for a spherical tank
110: system scaffold module 120: work scaffold
130: vertical and horizontal scaffolding 140: inclined material
150: horizontal member 160: upper truss
210: post 220: spherical tank
230: the bottom of the spherical tank 240: the top of the spherical tank

Claims (10)

삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete (a) 구형탱크(220)의 외주면의 직경에 따라 중심을 향하여 중심으로 갈수록 설치폭이 좁아지는 8개의 사다리꼴 형태로, 구형탱크(220)의 각 단마다 8각형의 수평링 형태로 시스템비계모듈(110)를 조립 설치하는 단계;
(b) 상기 시스템비계모듈(110)이 8각형의 수평 링 형태로 배치되어 지주(210), 구형탱크(220)의 외주면 주위에 작업자에게 작업공간을 확보할 수 있도록 시스템비계모듈(110)과 함께 작업발판(120)을 조립 설치하는 단계; 및
(c) 상기 8개의 사다리꼴 형태로 조립 설치되는 시스템비계모듈(110)를 수평으로 서로 연결시켜 시스템비계모듈(110)의 파손이 다른 시스템비계모듈(110)에 전달되지 않도록 시스템비계모듈(110)과 함께 수평재(150)를 설치하는 단계;를 포함하여,
각각 8개의 사다리꼴 형태의 시스템비계모듈(110)은 각 단에 따른 구형탱크의 직경에 맞추어 치수가 정해진 작업발판(120)과 수직수평비계(130)를 조합하여 제작한 것을 이용하여 구조적 안정성을 사전에 검토하여 설치할 수 있도록 하는 구형탱크용 외부시스템비계 시공방법.
(a) The system scaffolding module in the form of eight trapezoids in which the installation width becomes narrower toward the center according to the diameter of the outer circumferential surface of the spherical tank 220, and in the form of an octagonal horizontal ring at each stage of the spherical tank 220 Assembling and installing (110);
(b) the system scaffolding module 110 is arranged in the form of an octagonal horizontal ring so as to secure a working space for the operator around the outer peripheral surface of the post 210 and the spherical tank 220 and the system scaffolding module 110 and Assembling and installing the work platform 120 together; and
(c) the system scaffolding module 110 so that the damage of the system scaffolding module 110 is not transmitted to other system scaffolding modules 110 by horizontally connecting the system scaffolding modules 110 assembled and installed in the eight trapezoidal shape Including; installing the horizontal member 150 together with
Each of the eight trapezoidal system scaffolding modules 110 uses a combination of the working scaffold 120 and the vertical and horizontal scaffold 130 whose dimensions are determined according to the diameter of the spherical tank according to each stage to predict structural stability in advance. A method of constructing an external system scaffold for a spherical tank that can be reviewed and installed.
제7항에 있어서,
상기 (a)단계에서 구형탱크(220)의 외주면의 직경에 따라 중심을 향하여 중심으로 갈수록 설치폭이 좁아지는 8개의 사다리꼴 형태로, 구형탱크(220)의 각 단마다 8각형의 수평링 형태로 설치되는 시스템비계모듈(110)은,
구형탱크(220)의 중간부에서 상단(240)과 하단(230)으로 갈수록 설치되는 작업발판(120)의 개수가 증가하도록 하면서 구형탱크(220)의 중심으로 작업발판(120)이 수렴되도록 하는 구형탱크용 외부시스템비계 시공방법.
8. The method of claim 7,
In the step (a), according to the diameter of the outer peripheral surface of the spherical tank 220, in the form of eight trapezoids whose installation width becomes narrower toward the center according to the diameter of the outer circumferential surface of the spherical tank 220, in the form of an octagonal horizontal ring at each end of the spherical tank 220 The system scaffolding module 110 to be installed is,
From the middle of the spherical tank 220 to the upper end 240 and the lower end 230, the number of the working scaffolds 120 installed increases while the working scaffold 120 converges to the center of the spherical tank 220. How to construct an external system scaffold for a spherical tank.
제7항에 있어서,
상기 (c) 단계 이후에,
구형탱크(220)의 상단(240)에 상단트러스(160)를 이용하여 구형탱크용 외부시스템비계(100)를 완성 시며, 작업자는 각 단마다 설치된 8각형의 수평 링 형태로 설치된 구형탱크용 외부시스템비계(100)의 작업발판(120)을 이용하여 구형탱크(220)의 외주면 보수, 보강을 실시하고, 완료되면 상단(240)부터 구형탱크용 외부시스템비계(100)을 해체하는 구형탱크용 외부시스템비계 시공방법.
8. The method of claim 7,
After step (c),
Using the upper truss 160 on the upper end 240 of the spherical tank 220, the external system scaffold 100 for the spherical tank is completed, and the operator is installed in the form of an octagonal horizontal ring installed at each stage. For spherical tanks that repair and reinforce the outer peripheral surface of the spherical tank 220 using the working scaffold 120 of the system scaffold 100, and dismantle the external system scaffold 100 for the spherical tank from the upper end 240 when completed External system scaffold construction method.
제7항에 있어서,
상기 (a) 단계의 수평재(150)는,
양 단부에 체결구가 형성된 단관 파이프를 이용할 수 있으며, 각각의 시스템비계모듈(110)의 측면을 서로 연결하여 결속시켜 8각형 수평 링 형태를 유지하는 역할을 하며,
상기 (b) 단계의 작업발판(120)은 수직수평비계(130)를 이용하여 설치하며,
상기 수직수평비계(130)는 각 단의 시스템비계모듈(110)의 작업발판(120)을 설치하기 위해서 사용되는 가설자재로서, 경사재(140)를 이용하여 각 단의 높이에 따라 입체형태로 설치되도록 하며, 상기 경사재(140)는 상기 수직수평비계(130)에 경사지게 걸어 설치하여 수직으로 연장되는 수직수평비계(130)를 서로 구속하여 안정성을 확보할 수 있도록 양 단부는 갈고리 형태로 형성된 것을 이용하는 구형탱크용 외부시스템비계 시공방법.
8. The method of claim 7,
The horizontal member 150 of step (a) is,
A single pipe pipe having fasteners formed at both ends can be used, and the side surfaces of each system scaffold module 110 are connected to each other and bound to maintain an octagonal horizontal ring shape,
The working scaffold 120 of step (b) is installed using a vertical horizontal scaffold 130,
The vertical and horizontal scaffolding 130 is a temporary material used to install the working scaffold 120 of the system scaffolding module 110 of each stage, and is formed in a three-dimensional form according to the height of each stage by using the inclined material 140 . Both ends are formed in the form of hooks so as to secure stability by restraining the vertically extending vertical scaffolding 130 by hanging on the vertical horizontal scaffolding 130 obliquely and installing the inclined member 140 to each other. A method of constructing an external system scaffold for a spherical tank using
KR1020210106274A 2021-08-11 2021-08-11 Outer scaffolding system construction method for tank KR102426266B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210106274A KR102426266B1 (en) 2021-08-11 2021-08-11 Outer scaffolding system construction method for tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210106274A KR102426266B1 (en) 2021-08-11 2021-08-11 Outer scaffolding system construction method for tank

Publications (1)

Publication Number Publication Date
KR102426266B1 true KR102426266B1 (en) 2022-07-29

Family

ID=82606674

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210106274A KR102426266B1 (en) 2021-08-11 2021-08-11 Outer scaffolding system construction method for tank

Country Status (1)

Country Link
KR (1) KR102426266B1 (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001063797A (en) 1999-08-26 2001-03-13 Kashiwabara Painting Works Co Ltd Spiral scaffold for upper half semispherical outer surface of spherical tank
JP2002242424A (en) 2001-02-21 2002-08-28 Toho Gas Co Ltd Turning scaffold device of spherical tank
KR200354692Y1 (en) 2004-04-16 2004-07-05 유양기술 주식회사 Work party right and left rotaly apparatus in the prefabricated scaffolding system
JP2010121394A (en) * 2008-11-21 2010-06-03 Kajitani Industry Co Ltd Gondola for demolishing tower-like structure and method for demolishing tower structure using the gondola
JP2020007769A (en) * 2018-07-06 2020-01-16 株式会社新成工業 Expandable connector
CN112663927A (en) * 2020-07-24 2021-04-16 中国建筑第二工程局有限公司 Steel structure dome aerial work stepped operation platform and construction method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001063797A (en) 1999-08-26 2001-03-13 Kashiwabara Painting Works Co Ltd Spiral scaffold for upper half semispherical outer surface of spherical tank
JP2002242424A (en) 2001-02-21 2002-08-28 Toho Gas Co Ltd Turning scaffold device of spherical tank
KR200354692Y1 (en) 2004-04-16 2004-07-05 유양기술 주식회사 Work party right and left rotaly apparatus in the prefabricated scaffolding system
JP2010121394A (en) * 2008-11-21 2010-06-03 Kajitani Industry Co Ltd Gondola for demolishing tower-like structure and method for demolishing tower structure using the gondola
JP2020007769A (en) * 2018-07-06 2020-01-16 株式会社新成工業 Expandable connector
CN112663927A (en) * 2020-07-24 2021-04-16 中国建筑第二工程局有限公司 Steel structure dome aerial work stepped operation platform and construction method thereof

Similar Documents

Publication Publication Date Title
CN102605858B (en) Building structure and construction method
US8555600B2 (en) Method for mounting in sections an annular tower for wind power generator, heliostatic power generator or chimney composed from three concrete segments or more
CN102817484B (en) Heavy multifunctional combined supporting frame
US20100199597A1 (en) Multi-horizontal structure member forming method
CN104508215A (en) Nodal constructive system of rapid assembly for load bearing structures, buildings and artifacts of multi-purpose use
CA2595144A1 (en) Method of building a floor for a boiler cage
JP2006502330A (en) Methods and apparatus for precast and framed block element structures
KR102426266B1 (en) Outer scaffolding system construction method for tank
CN104358328B (en) All-steel four-steel pipe multistage mountable overlong buckling-restrained brace
CN106368317A (en) Prefabricated frame, slotted shear walls and frame-shear-wall structure
CN107013044A (en) The modularization installation method of lighting roof and the lowering or hoisting gear for installing lighting roof
KR101288744B1 (en) Scaffoldings for the Scrubber
CN109209004B (en) Construction method of ultrahigh welding type lattice tower
JP5701490B2 (en) Roof repair method and structure
CN116357143A (en) Tank room dome construction method based on BIM
CN102828616A (en) High-formwork support system for roof
JP6736226B2 (en) Structure and construction method of the structure constructed on the tower-shaped building
JP2010090633A (en) Prefabricated work platform for cylindrical concrete structure
CN210561738U (en) Assembled pier shaft construction protection system
JP4476096B2 (en) Construction method of large high-rise wind farm
CN104164889A (en) Demountable tower crane foundation
CA2576315C (en) Method of building a boiler frame
CN103088998B (en) Combination palace lattice scaffold and installing and dismantling method thereof
CN203225074U (en) Advertising board of net rack structure
KR102597764B1 (en) Dropping prevention net mounted with climbing system and method for mounting the same

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant