KR102336874B1 - Constructing Method of Underwater Tunnel with Tethering Tunnel Modules, and Underwater Tunnel Constructed by such Method - Google Patents

Constructing Method of Underwater Tunnel with Tethering Tunnel Modules, and Underwater Tunnel Constructed by such Method Download PDF

Info

Publication number
KR102336874B1
KR102336874B1 KR1020200040059A KR20200040059A KR102336874B1 KR 102336874 B1 KR102336874 B1 KR 102336874B1 KR 1020200040059 A KR1020200040059 A KR 1020200040059A KR 20200040059 A KR20200040059 A KR 20200040059A KR 102336874 B1 KR102336874 B1 KR 102336874B1
Authority
KR
South Korea
Prior art keywords
precast
tunnel module
tunnel
precast tunnel
concave groove
Prior art date
Application number
KR1020200040059A
Other languages
Korean (ko)
Other versions
KR20210122980A (en
Inventor
진병무
김제춘
김유석
김웅구
이종필
배경태
김경오
서경원
김용직
Original Assignee
(주)대우건설
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)대우건설 filed Critical (주)대우건설
Priority to KR1020200040059A priority Critical patent/KR102336874B1/en
Publication of KR20210122980A publication Critical patent/KR20210122980A/en
Application granted granted Critical
Publication of KR102336874B1 publication Critical patent/KR102336874B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water
    • E02D29/07Tunnels or shuttering therefor preconstructed as a whole or continuously made, and moved into place on the water-bed, e.g. into a preformed trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water
    • E02D29/073Tunnels or shuttering therefor assembled from sections individually sunk onto, or laid on, the water-bed, e.g. in a preformed trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

본 발명은 프리캐스트 콘크리트로 이루어진 프리캐스트 터널모듈을 마감블록과 가이드 체인을 이용하여 순차적으로 수중의 정확한 위치까지 침설시켜서 결합하고 정해진 위치에서 안정적으로 테더링(tethering)하여 고정시킴으로써 수중터널을 구축하게 되는 "마감블록과 가이드 케이블을 이용한 프리캐스트 터널모듈의 침설 및 테더링 구성의 수중터널 시공방법" 및 이러한 시공방법에 의해 구축된 "수중터널"에 관한 것이다. The present invention builds an underwater tunnel by immersing and combining precast tunnel modules made of precast concrete sequentially to the correct position in the water using a finishing block and a guide chain, and stably tethering and fixing them at a fixed position. It relates to "underwater tunnel construction method of immersion and tethering configuration of precast tunnel module using closing block and guide cable" and "underwater tunnel" constructed by this construction method.

Figure R1020200040059
Figure R1020200040059

Description

마감블록과 가이드 체인을 이용한 프리캐스트 터널모듈의 침설 및 테더링 구성의 수중터널 시공방법 및 이에 의해 구축된 수중터널{Constructing Method of Underwater Tunnel with Tethering Tunnel Modules, and Underwater Tunnel Constructed by such Method} Constructing Method of Underwater Tunnel with Tethering Tunnel Modules, and Underwater Tunnel Constructed by such Method}

본 발명은 차량이나 보행자가 통행할 수 있는 터널을 수중에 시공하는 방법과, 이러한 시공방법에 의해 구축된 수중터널에 관한 것으로서, 구체적으로는 프리캐스트 콘크리트 부재로 제작된 터널모듈("프리캐스트 터널모듈")을 마감블록과 가이드 체인을 이용하여 순차적으로 수중의 정확한 위치까지 침설시켜서 테더링(Tethering)함으로써, 프리캐스트 터널모듈을 정해진 위치에서 수밀하면서도 안정적으로 고정시켜서 수중터널을 구축하게 되는 "마감블록과 가이드 체인을 이용한 프리캐스트 프리캐스트 터널모듈의 침설 및 테더링 구성의 수중터널 시공방법" 및 이러한 시공방법에 의해 구축된 "수중터널"에 관한 것이다. The present invention relates to a method of constructing a tunnel through which vehicles or pedestrians can pass underwater, and an underwater tunnel constructed by such a construction method, and specifically, a tunnel module made of a precast concrete member (“precast tunnel”). By tethering the module") by sequentially submerging it to the correct position in the water using a closing block and guide chain, the precast tunnel module is watertightly and stably fixed at a fixed position to build an underwater tunnel. It relates to an underwater tunnel construction method of immersion and tethering configuration of a precast precast tunnel module using blocks and guide chains, and an “underwater tunnel” constructed by such a construction method.

차량이나 보행자의 통행을 위하여 물속에 구축되는 수중터널을 시공함에 있어서 수중터널을 이루는 터널모듈을 수중터널의 일측에서 전방(수중터널이 진행하는 방향)으로 순차적으로 압출시키는 방식이 대한민국 등록특허 제10-0797795호 등에 의해 제안되어 있다. 이에 대한 대안으로서 최근에는 공장에서 프리캐스트 콘크리트 구조물의 형태로 사전 제작된 프리캐스트 터널모듈을 수면에 부유시켜 현장으로 이송한 후, 프리캐스트 터널모듈을 수중으로 침설시켜서 이미 설치되어 있던 수중터널의 기설부분과 연결하는 방식으로 프리캐스트 터널모듈을 연속적으로 결합하여 수중터널을 시공하는 방안이 제안되었다. In constructing an underwater tunnel to be built in water for the passage of vehicles or pedestrians, the method of sequentially extruding the tunnel module constituting the underwater tunnel from one side of the underwater tunnel to the front (the direction in which the underwater tunnel proceeds) is the Republic of Korea Patent No. 10 -0797795 et al. As an alternative to this, recently, a precast tunnel module pre-fabricated in the form of a precast concrete structure in a factory is floated on the water surface and transported to the site, and then the precast tunnel module is immersed in the water to install the already installed underwater tunnel. A method of constructing an underwater tunnel by continuously combining precast tunnel modules in a way that connects to the parts has been proposed.

수중터널의 경우, 작용하는 부력이 수중터널의 자중보다 큰 것이 일반적이므로 수중터널이 부유하지 않도록 수중에서 안정적으로 고정시키는 것이 매우 중요하다. 일반적으로는 수중터널이 연장되는 방향 즉, 종방향으로 소정 간격을 두고 고정 케이블을 이용하여 수중터널의 본체와 수중 지반 사이를 연결하여 수중터널의 위치를 고정하게 된다. 이와 같이 고정 케이블을 이용하여 수중터널을 안정적으로 고정하는 것을 "테더링(Tethering)"이라고 부른다. 종래에는 프리캐스트 터널모듈이 수중에 침설되어 기설부분과 접합될 때마다 잠수 인력이 투입되어 고정 케이블을 프리캐스트 터널모듈에 결합하는 방식으로 테더링을 수행하였다. 그런데 수중터널은 상당한 수심(水深) 위치에 구축되므로 테더링을 위하여 잠수인력을 투입하는 것은 상당한 작업시간과 비용을 유발하게 될 뿐만 아니라 안전사고의 발생 가능성도 높아지는 단점이 있다. In the case of an underwater tunnel, it is common that the acting buoyancy force is greater than the self-weight of the underwater tunnel, so it is very important to stably fix it in the water so that the underwater tunnel does not float. In general, the position of the underwater tunnel is fixed by connecting the body of the underwater tunnel and the underwater ground using a fixed cable at a predetermined interval in the direction in which the underwater tunnel extends, that is, in the longitudinal direction. In this way, stably fixing the underwater tunnel using a fixed cable is called “tethering”. In the related art, whenever a precast tunnel module is submerged in water and joined to an existing part, a diving manpower is input to perform tethering in such a way that a fixed cable is coupled to the precast tunnel module. However, since the underwater tunnel is built at a considerable depth of water, the input of diving personnel for tethering not only causes considerable work time and cost, but also has the disadvantage of increasing the possibility of a safety accident.

프리캐스트 터널모듈은 기설부분에 높은 정밀도로 접합 연결되어야 하며, 이를 위해서는 수중으로 침설되는 프리캐스트 터널모듈을 정확한 연결위치에 배치하고 정렬시키는 것이 매우 중요하다. 그러나 종래 기술에서는 프리캐스트 터널모듈을 수중으로 침설시켜서 정확한 연결위치에 배치하고 정렬하는 작업 역시 잠수인력에 의존하고 있는 바, 위에서 언급한 바와 같은 많은 시간과 비용 발생의 문제 및 안전사고 위험의 문제가 존재한다. The precast tunnel module should be connected to the existing part with high precision. However, in the prior art, the task of immersing the precast tunnel module underwater, arranging and arranging it at the correct connection position also depends on the diving manpower. exist.

대한민국 등록특허공보 제10-0797795호(2008. 01. 24. 공고)Republic of Korea Patent Publication No. 10-0797795 (published on Jan. 24, 2008)

본 발명은 위와 같은 종래 기술의 한계를 극복하기 위하여 개발된 것으로서, 부유시켜 현장으로 이송된 프리캐스트 터널모듈을 침설시켜서 수중터널의 기설부분과 연결 접합하고 고정 케이블을 이용하여 테더링하여 수중터널을 시공함에 있어서, 가이드 체인을 이용하여 프리캐스트 터널모듈을 정확한 연결접합 위치로 유도하여 정렬시킴과 동시에, 마감블록을 이용하여 정해진 위치에서 프리캐스트 터널모듈을 테더링함으로써 프리캐스트 터널모듈의 침설 및 테더링 작업을 수행할 때 잠수인력의 투입을 최소화시켜서 그에 따른 비용 발생, 공기 장기화, 안전사고 발생 위험 등을 줄이고 시공오차를 최소화하여 정밀한 시공이 가능하게 하며 시공 효율성을 증대시킬 수 있는 수중터널 시공기술을 제공하는 것을 목적으로 하는 것이다. The present invention was developed to overcome the limitations of the prior art as described above, and by immersing a precast tunnel module that was floated and transported to the site, connected to the existing part of the underwater tunnel, and tethered using a fixed cable to form an underwater tunnel. In construction, the precast tunnel module is guided and aligned to the correct connection joint position using a guide chain, and at the same time, the precast tunnel module is immersed and tethered at a fixed position using a closing block. Underwater tunnel construction technology that minimizes the input of diving manpower when performing the derring work, reduces costs, prolonged construction period, and the risk of safety accidents, enables precise construction by minimizing construction errors, and increases construction efficiency is intended to provide

위와 같은 과제를 달성하기 위하여 본 발명에서는, 프리캐스트 터널모듈을 수면으로 부유시켜 이송시킨 후 침설하여, 이미 수중에 구축되어 있던 기설부분에 연결 접합하고, 후속하는 프리캐스트 터널모듈을 순차적으로 연속 접합시켜서 수중터널을 구축하는 수중터널 시공방법으로서, 프리캐스트 터널모듈을 수면으로 부유시켜 이송시킨 후 침설하여, 이미 수중에 구축되어 있던 기설부분에 연결 접합하고, 후속하는 프리캐스트 터널모듈을 순차적으로 연속 접합시켜서 수중터널을 구축하는 수중터널 시공방법으로서, 상단에는 마감블럭이 구비되어 있는 테더링용 고정 케이블을 기설부분의 전방에 설치하고, 마감블럭에는 가이드 체인을 연결하며, 가이드 체인을 프리캐스트 터널모듈에 연결하는 단계; 가이드 체인을 감아서 프리캐스트 터널모듈을 수중 침설시켜서 기설부분의 전방에서 접합 위치에 정렬 배치시키는 단계; 및 기설부분과 프리캐스트 터널모듈을 수밀하게 일체로 연결 결합하고, 마감블럭을 프리캐스트 터널모듈에 수밀한 상태로 일체화되도록 고정 결합하여 프리캐스트 터널모듈을 고정 케이블에 의해 테더링하는 단계를 포함하며; 프리캐스트 터널모듈에는 오목홈부가 형성되어 있고, 오목홈부에는 볼트공이 형성되어 있으며, 마감블럭의 상단부는 오목홈부에 대응되는 형상을 가지며, 마감블럭의 상면에는 결합볼트가 돌출 구비되어 있고, 가이드 체인은 프리캐스트 터널모듈을 관통하여 프리캐스트 터널모듈의 내부에서 체인권취기에 감겨 있으며; 체인권취기의 작동에 의해 가이드 체인이 감겨져서 프리캐스트 터널모듈이 침설되며, 침설된 프리캐스트 터널모듈이 기설부분의 전방에 정렬배치되면 마감블럭의 상단부가 오목홈부의 내면에 밀착되도록 끼워져서 수밀상태를 이루고, 결합볼트는 볼트공을 관통하여 프리캐스트 터널모듈의 내부로 돌출되며, 돌출된 결합볼트에 너트부재가 체결 고정됨으로써 프리캐스트 터널모듈이 고정 케이블에 의해 테더링되는 것을 특징으로 하는 수중터널 시공방법이 제공된다. In order to achieve the above object, in the present invention, the precast tunnel module is floated on the surface of the water, transported, and then submerged, connected and joined to the existing part already built in the water, and the subsequent precast tunnel module is sequentially joined continuously. As an underwater tunnel construction method that constructs an underwater tunnel through As an underwater tunnel construction method to construct an underwater tunnel by splicing, a fixed cable for tethering equipped with a finishing block is installed in front of the existing part at the top, a guide chain is connected to the finishing block, and the guide chain is used in a precast tunnel connecting to the module; immersing the precast tunnel module underwater by winding the guide chain to align and arrange the precast tunnel module at the joint position in front of the existing part; and tethering the precast tunnel module by means of a fixed cable by watertightly connecting the existing part and the precast tunnel module together, and fixing the finishing block to be integrated with the precast tunnel module in a watertight state. ; A concave groove is formed in the precast tunnel module, a bolt hole is formed in the concave groove, the upper end of the finishing block has a shape corresponding to the concave groove, and a coupling bolt is protruded from the upper surface of the finishing block, and a guide chain passes through the precast tunnel module and is wound on the chain winder inside the precast tunnel module; The guide chain is wound by the operation of the chain winder and the precast tunnel module is immersed, and when the precast tunnel module is aligned and placed in front of the existing part, the upper end of the finishing block is fitted so that it is in close contact with the inner surface of the concave groove and is watertight. Underwater, characterized in that the precast tunnel module is tethered by a fixed cable by fastening and fixing the nut member to the protruding coupling bolt, and the coupling bolt penetrates the bolt hole and protrudes into the inside of the precast tunnel module. A tunnel construction method is provided.

또한 본 발명에서는 상기한 수중터널 시공방법에 의해 시공되어 구축된 수중터널이 제공된다. In addition, the present invention provides an underwater tunnel constructed and constructed by the above-described underwater tunnel construction method.

상기한 본 발명의 수중터널 및 그 시공방법에 있어서, 고정 케이블은 마감블럭을 관통하여 마감블럭과 결합되며; 오목홈부의 바닥면에는 고정 케이블이 삽입되는 케이블관통공이 관통 형성되어 있으며; 마감블럭의 상단부가 오목홈부의 내면에 밀착되도록 끼워지면, 고정 케이블의 단부는 케이블관통공을 지나서 프리캐스트 터널모듈의 내부로 돌출되며; 프리캐스트 터널모듈의 내부로 돌출된 고정 케이블의 단부가 긴장 정착됨으로써 고정 케이블에는 긴장력이 도입되는 구성을 가질 수 있고, 더 나아가 가이드 체인의 하단은 결합볼트에 결합되어 있어서, 가이드 체인은 오목홈부의 볼트공을 통과하여 프리캐스트 터널모듈의 내부로 진입되는 구성을 가질 수도 있다. In the underwater tunnel and its construction method of the present invention, the fixed cable passes through the closing block and is combined with the closing block; A cable through hole into which a fixed cable is inserted is formed through the bottom surface of the concave groove; When the upper end of the closing block is fitted to the inner surface of the concave groove, the end of the fixed cable protrudes through the cable through hole into the inside of the precast tunnel module; Since the end of the fixed cable protruding into the inside of the precast tunnel module is tensioned and fixed, a tension force is introduced to the fixed cable. It may have a configuration in which it enters the inside of the precast tunnel module through the bolt hole.

본 발명에서는 부유시켜 현장으로 이송된 프리캐스트 터널모듈을 침설시켜서 수중터널의 기설부분과 접합 연결하여 수중터널을 시공함에 있어서, 프리캐스트 터널모듈이 수중에 투입되어 기설부분의 전방에 정렬될 때까지 가이드 체인에 의해 가이드되면서 침설되므로 프리캐스트 터널모듈이 해류 등에 의해 유실되지 않고 정확한 접합 위치에 용이하게 정렬시킬 수 있을 뿐만 아니라, 프리캐스트 터널모듈의 테더링 또한 용이하게 수행할 수 있는 바, 프리캐스트 터널모듈의 침설 및 테더링 과정에 잠수인력을 투입하지 않거나, 적어도 잠수 인력의 투입을 최소화시킬 수 있게 되며, 그에 따라 비용 절감 및 공기 단축의 효과를 발휘할 수 있게 되고 안전사고 발생 위험도 크게 감소시킬 수 있게 되는 장점이 있다. In the present invention, in constructing an underwater tunnel by immersing the floating and transported precast tunnel module to the site and connecting it to the existing part of the underwater tunnel, until the precast tunnel module is put into the water and aligned in front of the existing part As it is immersed while being guided by the guide chain, the precast tunnel module can be easily aligned at the correct joint position without being lost due to currents, etc., and tethering of the precast tunnel module can be easily performed. No diving manpower is put in the immersion and tethering process of the tunnel module, or at least the input of diving manpower can be minimized. There are advantages to being.

또한 본 발명에서는 프리캐스트 터널모듈이 접합 목표 위치까지 침설되어 기설부분과 접합되면서 가이드 체인으로 인하여 프리캐스트 터널모듈에 존재하는 구멍이 마감블럭에 의해 수밀하게 마감됨과 동시에 프리캐스트 터널모듈이 고정 케이블에 의해 매우 견고하게 안정적으로 테더링되므로 그만큼 시공효율성 향상 효과 및 공기 단축 효과가 배가되는 장점이 있다. In addition, in the present invention, the precast tunnel module is immersed to the bonding target position and joined to the existing part, the hole existing in the precast tunnel module is closed watertight by the closing block due to the guide chain, and at the same time, the precast tunnel module is attached to the fixed cable. Since it is tethered very firmly and stably, there is an advantage in that the effect of improving the construction efficiency and shortening the construction period is doubled.

특히, 본 발명에서는 고정 케이블을 이용하여 프리캐스트 터널모듈을 테더링하기 위하여 마감블럭을 프리캐스트 터널모듈에 수밀하게 결합 고정하는 작업을 프리캐스트 터널모듈의 내부에서 수행할 수 있으므로 그만큼 작업이 수월하게 이루어질 수 있고 시공 효율이 크게 향상되는 효과가 발휘된다.In particular, in the present invention, in order to tether the precast tunnel module using a fixed cable, the operation of watertightly coupling and fixing the finishing block to the precast tunnel module can be performed inside the precast tunnel module, so the operation can be performed easily. This can be achieved and the effect of greatly improving the construction efficiency is exhibited.

도 1 내지 도 3은 각각 본 발명에 따른 시공방법에 따라 수중터널을 구축하는 과정을 순차적으로 보여주는 개략적인 측면도이다.
도 4 및 도 5는 각각 가이드 체인의 상단부를 프리캐스트 터널모듈에 연결 결합하는 과정을 순차적으로 보여주는 프리캐스트 터널모듈의 개략적인 종방향의 단면도이다.
도 6 및 도 7은 각각 프리캐스트 터널모듈을 수중으로 가라앉혀서 기설부분의 전방에서 접합하는 것을 순차적으로 보여주는 개략적인 측면도이다.
도 8은 고정 케이블의 상부에 구비된 마감블럭에 대한 개략적인 사시도이다.
도 9는 도 8에 도시된 마감블럭의 개략적인 정면도이다.
도 10은 마감블럭이 결합되는 오목홈부가 보이도록 도시한 프리캐스트 터널모듈의 개략적인 사시도이다.
도 11의 (a) 및 (b)는 각각 오목홈부에서의 도 10에 표시된 화살표 E-E 및 F-F에 따른 개략적인 프리캐스트 터널모듈의 부분 단면도이다.
도 12는 마감블럭이 프리캐스트 터널모듈에 고정 결합되어 프리캐스트 터널모듈이 고정 케이블에 의해 테더링된 상태를 보여주는 도 5에 대응되는 개략적인 종방향의 단면도이다.
도 13은 프리캐스트 터널모듈이 테더링된 상태일 때의 마감블럭과 오목홈부의 결합 상태를 보여주는 도 11의 (a)에 대응되는 개략적인 프리캐스트 터널모듈의 부분 단면도이다.
도 14는 고정 케이블이 서로 교차된 상태로 프리캐스트 터널모듈이 테더링되어 있는 실시예에 대한 도 12에 대응되는 개략적인 종방향의 단면도이다.
1 to 3 are schematic side views sequentially showing the process of constructing an underwater tunnel according to the construction method according to the present invention, respectively.
4 and 5 are schematic longitudinal cross-sectional views of the precast tunnel module sequentially showing the process of connecting and coupling the upper end of the guide chain to the precast tunnel module, respectively.
6 and 7 are schematic side views sequentially showing that the precast tunnel module is submerged in water and joined at the front of the existing part, respectively.
8 is a schematic perspective view of a closing block provided on an upper portion of a fixed cable.
9 is a schematic front view of the closing block shown in FIG.
10 is a schematic perspective view of a precast tunnel module showing a concave groove to which a finishing block is coupled;
11(a) and 11(b) are partial cross-sectional views of a schematic precast tunnel module according to arrows EE and FF indicated in FIG. 10 in a concave groove, respectively.
12 is a schematic longitudinal cross-sectional view corresponding to FIG. 5 showing a state in which the finishing block is fixedly coupled to the precast tunnel module and the precast tunnel module is tethered by a fixed cable.
13 is a schematic partial cross-sectional view of the precast tunnel module corresponding to FIG. 11 (a) showing the coupling state of the closing block and the concave groove when the precast tunnel module is in a tethered state.
FIG. 14 is a schematic longitudinal cross-sectional view corresponding to FIG. 12 for an embodiment in which the precast tunnel module is tethered with fixed cables intersecting each other.

이하, 본 발명의 바람직한 실시예를 첨부한 도면을 참조하여 설명한다. 본 발명은 도면에 도시된 실시예를 참고로 설명되었으나 이는 하나의 실시예로서 설명되는 것이며, 이것에 의해 본 발명의 기술적 사상과 그 핵심 구성 및 작용이 제한되지 않는다. 참고로 본 명세서에서는 수중터널이 연장되는 방향을 "종방향"이라고 기재하는데, 특히 수중터널에 프리캐스트 터널모듈이 점차로 접합되어서 수중터널이 연장되어 가는 방향을 "전방(前方)"이라고 기재하고, 이와 반대되는 방향을 "후방"이라고 기재한다. Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings. Although the present invention has been described with reference to the embodiment shown in the drawings, which is described as one embodiment, the technical idea of the present invention and its core configuration and operation are not limited thereby. For reference, in this specification, the direction in which the underwater tunnel extends is described as "longitudinal direction". In particular, the direction in which the underwater tunnel extends as the precast tunnel module is gradually joined to the underwater tunnel is described as "front", The opposite direction is described as "rear".

본 발명에 따른 수중터널은, 종방향으로 소정 길이를 가지는 프리캐스트 터널모듈(2)을 그 전방에서 순차적으로 수밀한 상태로 일체 연결함으로써 구축된다. 도 1에는 본 발명에 따른 시공방법에 따라 수중터널을 구축하는 과정에서 수중에 기설부분(1)이 설치되어 있는 상태를 보여주는 개략적인 측면도가 도시되어 있다. 도 1에 도시된 것처럼 수중터널을 구축할 때 수중에는 기설부분(1)이 정해진 종방향 수중터널 선형을 가지도록 설치되어 있는데, 하단이 수중 지반에 고정되어 있는 고정 케이블(3)이 수중터널의 기설부분(1)에 결합됨으로써 기설부분(1)이 고정 케이블(3)에 의해 테더링되어 있다. 기설부분(1)의 전방에는 새로 침설될 프리캐스트 터널모듈(2)을 고정시키기 위한 또다른 고정 케이블(3)이 프리캐스트 터널모듈(2)가 침설되어 배치될 위치에 맞추어서 수중 지반에 고정 설치되어 있다. 새로 침설되는 프리캐스트 터널모듈(2)을 테더링하여 고정시키기 위한 고정 케이블(3)의 상단에는 마감블럭(4)이 구비되어 있다. 고정 케이블(3)에 마감블럭(4)을 설치함에 있어서, 고정 케이블(3)이 마감블럭(4)을 수밀하게 관통하는 형태가 될 수 있다. 이 경우, 후술하는 것처럼 프리캐스트 터널모듈(2)에 마감블럭(4)을 결합한 후, 프리캐스트 터널모듈(2)의 내부에서 고정 케이블(3)의 길이를 조정함으로써 고정 케이블(3)에 도입되는 장력을 조절하는 작업을 매우 용이하게 수행할 수 있게 된다. The underwater tunnel according to the present invention is constructed by integrally connecting the precast tunnel modules 2 having a predetermined length in the longitudinal direction sequentially from the front in a watertight state. 1 is a schematic side view showing a state in which the existing part 1 is installed in the water in the process of constructing an underwater tunnel according to the construction method according to the present invention. As shown in Figure 1, when constructing an underwater tunnel, the existing part (1) is installed to have a predetermined longitudinal underwater tunnel alignment, and the fixed cable (3) whose lower end is fixed to the underwater ground is the underwater tunnel. By being coupled to the existing part (1), the existing part (1) is tethered by a fixed cable (3). In front of the existing part (1), another fixed cable (3) for fixing the precast tunnel module (2) to be newly immersed is fixed to the underwater ground in accordance with the position where the precast tunnel module (2) is to be immersed and placed. has been A closing block 4 is provided at the upper end of the fixing cable 3 for fixing the newly immersed precast tunnel module 2 by tethering. In installing the closing block 4 on the fixed cable 3 , the fixed cable 3 may be in the form of penetrating the closing block 4 watertightly. In this case, after coupling the closing block 4 to the precast tunnel module 2 as described below, the length of the fixed cable 3 is adjusted inside the precast tunnel module 2 to be introduced into the fixed cable 3 . It becomes possible to perform the operation of adjusting the tension to be very easily.

마감블럭(4)에는 가이드 체인(5)이 연결되어 있는데, 도 1에 예시된 것처럼 가이드 체인(5)의 상단에 제1부표(51)를 결합 설치하여 제1부표(51)가 수면에 부유하게 만들 수 있다. 이와 같이 제1부표(51)를 이용하게 되면 가이드 체인(5)의 상단 위치를 쉽게 파악할 수 있게 되고, 가이드 체인(5)의 상단이 수면 부근에 존재하게 만들 수 있게 되어 후술하는 것처럼 가이드 체인(5)을 프리캐스트 터널모듈(2)에 연결하는 작업을 수면에서 쉽게 수행할 수 있게 되는 장점이 있다. A guide chain 5 is connected to the closing block 4, and as illustrated in FIG. 1, a first buoy 51 is coupled and installed on the upper end of the guide chain 5 so that the first buoy 51 floats on the water surface. can make it In this way, when the first buoy 51 is used, the upper position of the guide chain 5 can be easily grasped, and the upper end of the guide chain 5 can be made to exist near the water surface, so that as will be described later, the guide chain ( 5) has the advantage of being able to easily perform the operation of connecting the precast tunnel module 2 to the surface of the water.

필요에 따라서는 고정 케이블(3)에도 보조적인 제2부표(52)를 더 연결할 수도 있다. 부재번호 50은 제2부표(52)와 고정 케이블(3)을 연결하기 위한 연결선(50)이다. 가이드 체인(5)을 프리캐스트 터널모듈(2)에 연결하기 전의 상태에서 가이드 체인(5)이 늘어져 있는 상태가 될 수 있고, 그로 인하여 가이드 체인(5)과 결합된 제1부표(51)가 정해진 위치에서 상당 범위 밖으로 벗어나 있게 될 수도 있는데, 이 경우 작업자가 무작정 제1부표(51)에만 의지하여 새로 침설될 프리캐스트 터널모듈(2)을 이송하게 되면 잘못된 위치로 가게 되는 경우가 발생할 수도 있다. 그렇지만 위와 같이 고정 케이블(3)에 보조적인 제2부표(52)를 연결해두면 제2부표(52)에 의해 고정 케이블(3)의 위치를 파악할 수 있게 되고 작업자는 제2부표(52)를 이용하여 정확한 위치로 프리캐스트 터널모듈(2)을 이송할 수 있게 된다. 필요에 따라서는 제1부표(51)와 제2부표(52)를 서로 연결해둘 수 있으며, 이 경우 제1부표(51)가 과도하게 엉뚱한 범위에 위치하게 되는 것을 효과적으로 방지될 수 있다. If necessary, an auxiliary second buoy 52 may be further connected to the fixed cable 3 . Reference number 50 is a connecting line 50 for connecting the second buoy 52 and the fixed cable 3 . In the state before the guide chain 5 is connected to the precast tunnel module 2, the guide chain 5 may be in a dangling state, whereby the first buoy 51 coupled to the guide chain 5 is It may be out of a considerable range from the fixed position. In this case, if the operator recklessly relies on the first buoy 51 to transfer the precast tunnel module 2 to be newly immersed, it may lead to a wrong position. . However, if the auxiliary second buoy 52 is connected to the fixed cable 3 as above, the position of the fixed cable 3 can be grasped by the second buoy 52 , and the operator uses the second buoy 52 . Thus, it is possible to transport the precast tunnel module 2 to an accurate location. If necessary, the first buoy 51 and the second buoy 52 can be connected to each other, and in this case, the first buoy 51 can be effectively prevented from being excessively positioned in the wrong range.

수중터널을 이루는 프리캐스트 터널모듈(2)은 차량이나 사람이 통행할 수 있는 중공(中空)을 가지도록 육상 내지 선박 위에서 프리캐스트 콘크리트 부재로 사전 제작되어, 수면에 부유된 상태로 예인선박에 의해 시공현장에서 가이드 체인(5)의 상단부가 위치하는 곳으로 이송된다. 프리캐스트 터널모듈(2)이 시공현장으로 이송되면, 수면을 향하여 연장된 가이드 체인(5)의 상단부를 프리캐스트 터널모듈(2)에 연결 결합한다. 도 2에는 도 1에 도시된 상태에 후속하여 프리캐스트 터널모듈(2)이 시공현장으로 이송된 상태를 보여주는 개략적인 측면도가 도시되어 있고, 도 3에는 도 2에 후속하여 가이드 체인(5)의 상단부를 프리캐스트 터널모듈(2)에 연결 결합한 상태를 보여주는 개략적인 측면도가 도시되어 있다. 도 4 및 도 5에는 각각 가이드 체인(5)의 상단부를 프리캐스트 터널모듈(2)에 연결 결합하는 과정을 순차적으로 보여주는 프리캐스트 터널모듈(2)의 개략적인 종방향의 단면도가 도시되어 있다. The precast tunnel module 2 constituting the underwater tunnel is pre-fabricated as a precast concrete member on land or on a ship to have a hollow through which vehicles or people can pass, and is suspended on the water surface by a towing vessel. It is transferred to a place where the upper end of the guide chain 5 is located at the construction site. When the precast tunnel module (2) is transported to the construction site, the upper end of the guide chain (5) extending toward the water surface is connected to the precast tunnel module (2). 2 is a schematic side view showing a state in which the precast tunnel module 2 is transported to the construction site following the state shown in FIG. 1, and in FIG. A schematic side view showing a state in which the upper end is connected to the precast tunnel module 2 is shown. 4 and 5 are schematic longitudinal cross-sectional views of the precast tunnel module 2 sequentially showing the process of connecting and coupling the upper end of the guide chain 5 to the precast tunnel module 2, respectively.

도면에 도시된 것처럼 고정 케이블(3)과 마감블럭(4), 그리고 가이드 체인(5)은 프리캐스트 터널모듈(2)을 종방향으로 바라보았을 때, 좌우측의 양측에 각각 설치되며, 프리캐스트 터널모듈(2)의 중공 내부에는 체인권취기(M)가 구비될 수 있다. 우선, 도 4에 도시된 것처럼 일단이 체인권취기(M)에 감겨져 있는 유도선(誘導線)(54)의 타단부를 프리캐스트 터널모듈(2)의 밖으로 뽑아내어 가이드 체인(5)의 상단에 연결한다. 가이드 체인(5)을 제1부표(51)와 분리시키고 체인권취기(M)를 작동시켜 유도선(54)을 감으면, 유도선(54)이 체인권취기(M)에 의해 감기면서 가이드 체인(5)의 상단이 프리캐스트 터널모듈(2)을 관통한 후 도 5에 도시된 것처럼 체인권취기(M)에 감기게 된다. As shown in the drawing, the fixed cable 3, the closing block 4, and the guide chain 5 are respectively installed on both sides of the left and right when the precast tunnel module 2 is viewed in the longitudinal direction, and the precast tunnel A chain winder (M) may be provided inside the hollow of the module (2). First, as shown in FIG. 4 , the other end of the guide wire 54 having one end wound around the chain winder M is pulled out of the precast tunnel module 2 and the upper end of the guide chain 5 is pulled out. connect to When the guide chain (5) is separated from the first buoy (51) and the chain winder (M) is operated to wind the guide wire (54), the guide wire (54) is guided while being wound by the chain winder (M). After the upper end of the chain 5 passes through the precast tunnel module 2, it is wound around the chain winder M as shown in FIG.

도 4 및 도 5에 예시된 것처럼, 프리캐스트 터널모듈(2)의 단면을 상하로 분할할 수 있고, 프리캐스트 터널모듈(2)이 용이하게 가라앉을 수 있게 하기 위하여 상부는 수밀상태로 만들어서 건식(乾式) 공간이 되도록 하고 하부는 물이 유입되어 채울 수 있는데, 도면에 도시된 실시예에서는 체인권취기(M)가 물이 채워진 하부의 공간에 배치되어 있다. 필요에 따라서는 체인권취기(M)가 상부의 건식공간에 위치할 수도 있다. As illustrated in FIGS. 4 and 5, the cross section of the precast tunnel module 2 can be divided up and down, and the upper part is made watertight so that the precast tunnel module 2 can be easily submerged and dried. (乾式) to become a space and the lower part can be filled with water inflow, and in the embodiment shown in the figure, the chain winder (M) is arranged in the lower space filled with water. If necessary, the chain winder M may be located in the upper dry space.

위와 같이 가이드 체인(5)이 감겨져 있는 상태의 체인권취기(M)를 작동시켜서 가이드 체인(5)을 더욱 감게 되면 도 5에 도시된 것처럼 가이드 체인(5)의 길이가 줄어들면서 프리캐스트 터널모듈(2)은 기설부분(1)과의 접합 위치를 향하여 수중으로 침설된다. 도 6에는 도 3에 도시된 상태에 후속하여 가이드 체인(5)의 길이 감소에 의해 프리캐스트 터널모듈(2)이 침설되는 것을 보여주는 개략적인 측면도가 도시되어 있고, 도 7에는 수중으로 가라앉은 프리캐스트 터널모듈(2)이 기설부분(1)의 전방에서 접합 위치에 정렬 배치되고 접합되는 상태를 보여주는 개략적인 측면도가 도시되어 있다. 도 7에 도시된 것처럼 프리캐스트 터널모듈(2)이 기설부분(1)의 전방에 정렬 배치된 후에는 기설부분(1)과 프리캐스트 터널모듈(2)을 수밀하게 일체로 연결 결합하고, 이에 후속하여 또는 이와 병행하여 마감블럭(4)을 프리캐스트 터널모듈(2)에 수밀한 상태로 일체화되도록 고정 결합한다. When the guide chain 5 is further wound by operating the chain winder M in the state in which the guide chain 5 is wound as above, the length of the guide chain 5 is reduced as shown in FIG. 5 and the precast tunnel module (2) is submerged in water toward the joint position with the existing part (1). 6 is a schematic side view showing that the precast tunnel module 2 is submerged by the reduction in the length of the guide chain 5 following the state shown in FIG. A schematic side view is shown showing a state in which the cast tunnel module 2 is aligned and bonded at the bonding position in front of the existing part 1 . As shown in FIG. 7, after the precast tunnel module 2 is arranged in front of the existing part 1, the existing part 1 and the precast tunnel module 2 are watertightly integrally connected and coupled, Subsequently or in parallel, the finishing block 4 is fixedly coupled to the precast tunnel module 2 in a watertight state.

마감블럭(4)이 견고하게 프리캐스트 터널모듈(2)에 고정 결합됨으로써, 기설부분(1)과 접합된 프리캐스트 터널모듈(2)은 마감블럭(4)과 결합된 고정 케이블(3)에 의해 매우 안정적으로 테더링된 상태가 된다. 이렇게 접합된 프리캐스트 터널모듈은 이제 새로운 기설부분이 되는 것이며, 새로운 프리캐스트 터널모듈을 다시 준비하여 위와 같은 방식으로 침설시키고 접합하며 마감블럭(4)을 프리캐스트 터널모듈에 일체로 결합함으로써 프리캐스트 터널모듈을 고정 케이블에 의해 테더링하는 과정을 반복 수행함으로써 수중터널을 구축하게 된다. As the closing block 4 is firmly fixedly coupled to the precast tunnel module 2, the precast tunnel module 2 bonded to the existing part 1 is connected to the fixed cable 3 coupled to the closing block 4 It becomes a very stable tethered state. The precast tunnel module joined in this way is now a new existing part, and a new precast tunnel module is prepared again, immersed in the same way as above, and joined. By repeating the process of tethering the tunnel module with a fixed cable, an underwater tunnel is built.

본 발명에서는 이와 같이 프리캐스트 터널모듈(2)이 접합 목표 위치까지 수중으로 침설되어 수중터널의 기설부분(1)의 전방에 정렬될 때까지 가이드 체인(5)에 의해 가이드되면서 안전하게 접합 위치까지 침설되므로, 프리캐스트 터널모듈(2)의 침설 작업이 용이하게 이루어지고, 특히 프리캐스트 터널모듈(2)이 해류 등에 의해 유실되는 것을 방지할 수 있으며, 더 나아가 프리캐스트 터널모듈(2)의 침설과정에 잠수인력을 투입하지 않거나, 적어도 잠수 인력의 투입을 최소화시킬 수 있게 된다. 따라서 본 발명에 의하면 프리캐스트 터널모듈(2)의 침설 및 테더링 작업에 소요되는 비용을 크게 절감할 수 있게 되고 공기를 단축할 수 있음은 물론이며 안전사고 발생 위험도 크게 감소시킬 수 있게 된다. 특히, 프리캐스트 터널모듈(2)이 접합 목표 위치까지 침설되어 기설부분(1)과 접합되면서, 고정 케이블(3)에 결합되어 있는 마감블럭(4)이 프리캐스트 터널모듈(2)에 수밀하게 결합 고정됨으로써 프리캐스트 터널모듈(2)이 고정 케이블(3)에 의해 매우 견고하게 안정적으로 테더링되므로 그만큼 공기 단축의 효과가 배가된다. In the present invention, as described above, the precast tunnel module 2 is immersed in the water to the joint target position and is guided by the guide chain 5 until it is aligned in front of the existing part 1 of the underwater tunnel, and it is safely immersed to the joint position. Therefore, the immersion operation of the precast tunnel module 2 is facilitated, and in particular, it is possible to prevent the precast tunnel module 2 from being lost due to currents, etc., and furthermore, the immersion process of the precast tunnel module 2 It is possible to minimize the input of diving manpower, or at least the input of diving manpower. Therefore, according to the present invention, it is possible to greatly reduce the cost required for immersion and tethering of the precast tunnel module 2, shorten the construction period, and also greatly reduce the risk of safety accidents. In particular, as the precast tunnel module 2 is immersed to the bonding target position and joined to the existing part 1 , the closing block 4 coupled to the fixed cable 3 is watertightly attached to the precast tunnel module 2 . Since the precast tunnel module (2) is tethered very securely and stably by the fixing cable (3) by being coupled and fixed, the effect of shortening the period of time is doubled.

무엇보다도 고정 케이블(3)을 이용하여 프리캐스트 터널모듈(2)을 테더링하기 위하여 마감블럭(4)을 프리캐스트 터널모듈(2)에 수밀하게 결합 고정하는 작업을 프리캐스트 터널모듈(2)의 내부에서 수행할 수 있으므로, 그만큼 작업이 수월하게 이루어질 수 있고 시공 효율이 크게 향상되는 효과가 발휘된다. 도 4 및 도 5에 예시한 것처럼 프리캐스트 터널모듈(2)의 단면 하부에 물이 채워져 있더라도, 프리캐스트 터널모듈(2)을 기설부분(1)에 수밀하게 일체로 연결 결합한 후 프리캐스트 터널모듈(2)에 채워져 있던 물을 인위적으로 배수함으로써 프리캐스트 터널모듈(2)의 내부를 건식공간으로 만들 수 있다. 이 경우에는 마감블럭(4)을 프리캐스트 터널모듈(2)에 수밀하게 결합 고정하는 작업을 프리캐스트 터널모듈(2) 내부의 건식 공간에서 수행할 수 있으므로 작업의 효율성이 더욱 극대화되는 장점이 있다. Above all, in order to tether the precast tunnel module (2) using a fixed cable (3), the work of watertight coupling and fixing the closing block (4) to the precast tunnel module (2) is performed on the precast tunnel module (2) Since it can be carried out inside the As illustrated in FIGS. 4 and 5 , even when water is filled in the lower portion of the cross section of the precast tunnel module 2 , the precast tunnel module 2 is integrally connected to the existing part 1 in a watertight manner and then the precast tunnel module By artificially draining the water filled in (2), the inside of the precast tunnel module (2) can be made into a dry space. In this case, since the operation of watertight coupling and fixing of the finishing block 4 to the precast tunnel module 2 can be performed in the dry space inside the precast tunnel module 2, there is an advantage in that the efficiency of the operation is further maximized. .

다음에서는 마감블럭(4)의 상세 구성과, 마감블럭(4)을 프리캐스트 터널모듈(2)에 수밀하게 결합 고정함으로써 침설된 프리캐스트 터널모듈(2)을 테더링하는 구성에 대해 상세히 설명한다. Next, the detailed configuration of the closing block 4 and the configuration of tethering the submerged precast tunnel module 2 by watertight coupling and fixing the closing block 4 to the precast tunnel module 2 will be described in detail. .

도 8에는 고정 케이블(3)의 상부에 구비된 마감블럭(4)에 대한 개략적인 사시도가 도시되어 있고, 도 9에는 도 8에 도시된 마감블럭(4)의 개략적인 정면도가 도시되어 있다. 도 10에는 마감블럭(4)이 결합되는 오목홈부(20)가 보이도록 도시한 프리캐스트 터널모듈(2)의 개략적인 사시도가 도시되어 있다. 도 11의 (a)에는 오목홈부(20)에서 도 10에 표시된 화살표 E-E에 따른 개략적인 프리캐스트 터널모듈(2)의 부분 단면도가 도시되어 있고, 도 11의 (b)에는 오목홈부(20)에서 이에 직교하는 방향인 화살표 F-F에 따른 개략적인 프리캐스트 터널모듈(2)의 부분 단면도가 도시되어 있다. 8 is a schematic perspective view of the closing block 4 provided on the upper portion of the fixing cable 3 is shown, FIG. 9 is a schematic front view of the closing block 4 shown in FIG. 10 is a schematic perspective view of the precast tunnel module 2 showing the concave groove 20 to which the closing block 4 is coupled is shown. 11 (a) is a partial cross-sectional view of the schematic precast tunnel module 2 along the arrow EE shown in FIG. 10 in the concave groove 20, and in FIG. 11 (b) the concave groove 20. A schematic partial cross-sectional view of the precast tunnel module 2 is shown along the arrow FF, which is a direction orthogonal thereto.

앞서 언급한 것처럼 가이드 체인(5)의 상단은 프리캐스트 터널모듈(2)을 관통하여 체인권취기(M)에 감기므로 프리캐스트 터널모듈(2)에는 가이드 체인이 관통하게 될 구멍이 형성된다. 그런데 높은 수압에서도 수중터널의 내부가 수밀한 건식 공간을 유지하기 위해서는 프리캐스트 터널모듈에 형성된 구멍이 완전하게 밀봉될 필요가 있다. 또한 프리캐스트 터널모듈(2)의 안정적인 테더링을 위해서는 고정 케이블(3)이 견고하게 프리캐스트 터널모듈(2)에 결합되어야 한다. 마감블럭(4)은 위와 같은 기능을 모두 발휘하도록 고정 케이블(3)의 상단에 구비되는 부재로서, 마감블럭(4)은 그 상면이 프리캐스트 터널모듈(2)과 밀착하여 조립 결합된다. As mentioned above, since the upper end of the guide chain 5 passes through the precast tunnel module 2 and is wound around the chain winder M, a hole through which the guide chain will pass is formed in the precast tunnel module 2 . However, in order to maintain a watertight dry space inside the underwater tunnel even at high water pressure, the hole formed in the precast tunnel module needs to be completely sealed. In addition, for stable tethering of the precast tunnel module 2 , the fixed cable 3 should be firmly coupled to the precast tunnel module 2 . The closing block 4 is a member provided at the upper end of the fixed cable 3 to exhibit all of the above functions, and the closing block 4 is assembled and coupled with its upper surface in close contact with the precast tunnel module 2 .

프리캐스트 터널모듈(2)에서 마감블럭(4)의 상면이 밀착되는 부분에는 오목홈부(20)가 형성되어 있다. 도면에 도시된 것처럼 프리캐스트 터널모듈(2)의 두께 일부가 줄어들어서 오목하게 파여 있는 오목홈부(20)가 형성되는 것이다. 따라서 마감블럭(4)은 상단의 일부가 오목홈부(20)의 오목한 형상에 정확하게 끼워져서 오목홈부(20)를 채우게 되며, 마감블럭(4)의 상면은 오목홈부(20)의 평평한 바닥면에 밀착하게 된다. 도면에 도시된 실시예의 경우, 오목홈부(20)는 평평한 바닥면과, 상기 바닥면을 둘러싸는 경사면으로 이루어져서 프리캐스트 터널모듈의 두께 깊이로 갈수록 단면적이 작아지는 다각 뿔대 형태의 오목한 형상을 가지고 있는 바, 오목홈부(20)에 끼워지는 마감블럭(4)의 상부 역시 이에 정확하게 부합되도록 평평한 정면과 경사진 측면을 가지는 형태로 이루어진다. In the precast tunnel module (2), a concave groove (20) is formed in the portion to which the upper surface of the finishing block (4) is in close contact. As shown in the drawing, a portion of the thickness of the precast tunnel module 2 is reduced to form a concave groove 20 having a concave groove. Therefore, a part of the upper end of the closing block 4 is accurately fitted into the concave shape of the concave groove 20 to fill the concave groove 20, and the upper surface of the closing block 4 is on the flat bottom surface of the concave groove 20. become close In the case of the embodiment shown in the drawings, the concave groove 20 has a concave shape in the form of a polygonal truncated truncated cone that is composed of a flat bottom surface and an inclined surface surrounding the bottom surface so that the cross-sectional area becomes smaller as the thickness of the precast tunnel module increases. The bar, the upper part of the closing block 4 fitted into the concave groove 20 is also formed in a form having a flat front and an inclined side so that it is precisely matched thereto.

앞서 언급한 것처럼 마감블럭(4)은 고정 케이블(3)의 상단에 구비되는데, 도면의 실시예의 경우, 마감블럭(4)에는 중앙관통공(42)이 형성되어 있어서, 고정 케이블(3)은 중앙관통공(42)에 삽입되어 마감블럭(4)을 관통하고, 마감블럭(3)의 상면 밖으로 돌출된 고정 케이블(3)의 단부에는 체결마감재(33)가 결합되어 있는 구성을 가지고 있다. 도면에는 도시를 생략하였지만, 마감블럭(4)의 하면에는 마감블럭(4)이 고정 케이블(3)을 따라 하강하지 못하게 하는 스톱퍼가 설치될 수도 있다. 이와 같이 고정 케이블(3)이 마감블럭(4)을 관통하는 형태로 마감블럭(4)이 고정 케이블(3)에 구비되는 경우, 후술하는 바와 같이 고정 케이블(3)을 프리캐스트 터널모듈(2)의 내부에서 긴장하여 그 단부를 정착하는 것이 용이하며, 그에 따라 고정 케이블(3)에 의한 프리캐스트 터널모듈의 테더링을 더욱 견고하고 안정적으로 이룰 수 있게 되는 장점이 발휘된다. 특히, 이러한 구성에서는 필요할 때 고정 케이블(3)의 길이를 조정할 수 있게 되는 장점이 있다. 그러나 마감블럭(4)을 고정 케이블(3)에 결합하는 방식은 위와 같은 구성에 한정되지 않으며, 용접이나 매립 압착 등과 같이 기타 다양한 방식을 이용할 수도 있다. As mentioned above, the closing block 4 is provided at the upper end of the fixed cable 3, in the case of the embodiment of the drawing, the closing block 4 has a central through hole 42 formed therein, so the fixed cable 3 is a central pipe It is inserted into the through hole 42 and penetrates the closing block 4, and the end of the fixed cable 3 protruding out of the upper surface of the closing block 3 has a configuration in which the fastening finishing material 33 is coupled. Although not shown in the drawings, a stopper may be installed on the lower surface of the closing block 4 to prevent the closing block 4 from descending along the fixed cable 3 . When the closing block 4 is provided in the fixed cable 3 in such a way that the fixed cable 3 passes through the closing block 4, the fixed cable 3 is connected to the precast tunnel module 2 as described later. ), it is easy to fix the end by tensioning the inside, and accordingly, the advantage of being able to achieve the tethering of the precast tunnel module by the fixed cable 3 more firmly and stably is exhibited. In particular, this configuration has the advantage of being able to adjust the length of the fixed cable (3) when necessary. However, the method of coupling the closing block 4 to the fixed cable 3 is not limited to the above configuration, and various other methods such as welding or buried pressing may be used.

마감블럭(4)의 상면에는 결합볼트(40)가 돌출된 형태로 일체 구비되어 있다. 결합볼트(40)는 복수개로 구비될 수 있다. 또한 마감블럭(4)에는 프리캐스트 터널모듈(2)의 침설을 유도하기 위한 가이드 체인(5)이 연결 구비된다. 도 10 내지 도 12에 도시된 바와 같이 마감블럭(4)의 상면이 밀착하게 되는 오목홈부(20)의 평평한 바닥면에는 결합볼트(40)가 삽입 관통되는 볼트공(22)이 형성되는데, 도면에 예시된 것처럼 가이드 체인(5)의 하단을 결합볼트(40)의 단부에 결합하게 되면, 볼트공(22)을 가이드 체인(5)이 관통하는 구멍으로도 활용할 수 있게 되며, 그에 따라 가이드 체인(5)이 관통할 구멍을 별도로 프리캐스트 터널모듈(2)에 형성할 필요가 없으며, 프리캐스트 터널모듈(2)에 형성해야 하는 구멍의 수를 줄일 수 있다. 물론 가이드 체인(5)의 하단이 마감블록(4)의 상면에서 임의 위치에 결합되어 있는 경우에는 가이드 체인(5)이 관통할 구멍이 오목홈부(20)에 추가로 관통 형성된다. 오목홈부(20)의 바닥면에는 고정 케이블(3)이 삽입되는 케이블관통공(23)이 관통 형성되어 있다. A coupling bolt 40 is integrally provided on the upper surface of the closing block 4 in a protruding form. A plurality of coupling bolts 40 may be provided. In addition, the closing block 4 is provided with a guide chain 5 for inducing the immersion of the precast tunnel module 2 is connected. 10 to 12, a bolt hole 22 through which the coupling bolt 40 is inserted is formed on the flat bottom surface of the concave groove 20 to which the upper surface of the finishing block 4 is in close contact, as shown in FIGS. When the lower end of the guide chain 5 is coupled to the end of the coupling bolt 40 as illustrated in, the bolt hole 22 can also be used as a hole through which the guide chain 5 passes, and accordingly, the guide chain (5) It is not necessary to separately form a hole through the precast tunnel module (2), it is possible to reduce the number of holes to be formed in the precast tunnel module (2). Of course, when the lower end of the guide chain 5 is coupled to an arbitrary position on the upper surface of the closing block 4 , a hole through which the guide chain 5 will pass is additionally formed through the concave groove 20 . A cable through hole 23 into which the fixed cable 3 is inserted is formed through the bottom surface of the concave groove 20 .

도 12에는 마감블럭(4)이 프리캐스트 터널모듈(2)에 고정 결합되어 프리캐스트 터널모듈(2)이 고정 케이블(3)에 의해 테더링된 상태를 보여주는 도 5에 대응되는 개략적인 종방향의 단면도가 도시되어 있고, 도 13에는 이와 같이 프리캐스트 터널모듈(2)이 고정 케이블(3)에 의해 테더링된 상태일 때의 마감블럭(4)과 오목홈부(20)의 결합 상태를 보여주는 도 11의 (a)에 대응되는 개략적인 프리캐스트 터널모듈(2)의 부분 단면도가 도시되어 있다. 도 12 및 도 13에 도시된 것처럼, 프리캐스트 터널모듈(2)이 고정 케이블(3)에 의해 테더링될 때에, 마감블럭(4)은 프리캐스트 터널모듈(2)에 밀착되는데, 구체적으로 마감블럭(4)의 상부가 오목홈부(20) 내에 위치하여 완전히 밀착된다. 이 때, 결합볼트(40)는 프리캐스트 터널모듈(2)을 관통하도록 볼트공(22)에 삽입되어 단부가 프리캐스트 터널모듈(2)의 내부로 돌출된다. 이렇게 돌출된 결합볼트(40)에 너트부재(44)가 체결됨으로써 견고하게 고정된다. 고정 케이블(3)과 체결마감재(33)는 케이블관통공(23)에 단순히 삽입되어 위치할 수도 있지만, 고정 케이블(3)의 단부 역시 케이블관통공(23)을 지나서 프리캐스트 터널모듈(2)의 내부로 돌출될 수 있다. 마감블럭(4)의 상면 밖으로 돌출된 고정 케이블(3)의 단부에 체결마감재(33)가 임시로 결합되어 있는 경우, 고정 케이블(3)이 케이블관통공(23)에 삽입되었을 때 체결마감재(33)도 케이블관통공(23) 내에 위치하게 된다. 12 is a schematic longitudinal direction corresponding to FIG. 5 showing a state in which the closing block 4 is fixedly coupled to the precast tunnel module 2 and the precast tunnel module 2 is tethered by the fixed cable 3 . is shown, and FIG. 13 shows the coupling state of the closing block 4 and the concave groove 20 when the precast tunnel module 2 is tethered by the fixed cable 3 as described above. A partial cross-sectional view of the schematic precast tunnel module 2 corresponding to (a) of FIG. 11 is shown. 12 and 13, when the precast tunnel module 2 is tethered by the fixed cable 3, the closing block 4 is in close contact with the precast tunnel module 2, specifically, the finish The upper portion of the block (4) is located in the concave groove (20) and is completely in close contact. At this time, the coupling bolt 40 is inserted into the bolt hole 22 so as to penetrate the precast tunnel module 2 , and the end protrudes into the precast tunnel module 2 . The nut member 44 is fastened to the protruding coupling bolt 40 so as to be firmly fixed. The fixed cable 3 and the fastening finishing material 33 may be simply inserted into the cable through hole 23, but the end of the fixed cable 3 also passes through the cable through hole 23 and the precast tunnel module (2) may protrude into the When the fastening finish material 33 is temporarily coupled to the end of the fixed cable 3 protruding out of the upper surface of the closing block 4, the fastening finish material (3) when the fixed cable 3 is inserted into the cable through hole (23) 33) is also located in the cable through hole (23).

고정 케이블(3)의 단부가 케이블관통공(23)을 지나서 프리캐스트 터널모듈(2)의 내부로 돌출된 경우, 고정 케이블(3)의 돌출된 단부에 단순한 체결부재(43)를 체결하여 고정 케이블(3)을 고정시킬 수도 있지만, 고정 케이블(3)의 단부를 긴장장치 등으로 물어서 당긴 후 정착장치를 고정 케이블(3)의 단부에 체결하여 정착시킴으로써 고정 케이블(3)에 긴장력을 도입하는 것도 바람직하다. 이와 같이 고정 케이블(3)에 긴장력이 도입되는 경우에는 더욱 견고하고 안정적으로 프리캐스트 터널모듈(2)을 테더링시킬 수 있게 된다. When the end of the fixed cable 3 passes through the cable through hole 23 and protrudes into the precast tunnel module 2, a simple fastening member 43 is fastened to the protruding end of the fixed cable 3 to fix it. It is also possible to fix the cable 3, but after pulling the end of the fixed cable 3 with a tension device, etc. It is also desirable In this way, when tension is introduced into the fixed cable 3 , the precast tunnel module 2 can be tethered more firmly and stably.

무엇보다도 위와 같은 구성에서는 마감블럭(4)의 상부의 볼록한 부분 전체가 오목홈부(20)의 오목한 내면 전체에 완전히 밀착되며, 그에 따라 우수한 수밀성이 발휘된다는 장점이 있다. 또한 위에서 설명한 결합볼트(40)에 너트부재(44)를 체결하는 작업, 고정 케이블(3)의 단부에 체결부재(43)를 체결하거나 고정 케이블(3)을 긴장하여 정착하는 작업을 프리캐스트 터널모듈(2)의 내부에서 수행하게 되는 바, 프리캐스트 터널모듈(2) 외부의 고압 환경으로 잠수 인력을 투입하지 않거나 적어도 최소화시킬 수 있게 되고, 그만큼 안전사고 발생 위험을 줄이고 시간 및 비용을 절감할 수 있게 되는 장점이 발휘된다. Above all, in the above configuration, the entire convex portion of the upper portion of the finishing block 4 is completely in close contact with the entire concave inner surface of the concave groove portion 20, and thus excellent watertightness is exhibited. In addition, the work of fastening the nut member 44 to the coupling bolt 40 described above, the work of fastening the fastening member 43 to the end of the fixed cable 3 or fixing the fixed cable 3 by tensioning the precast tunnel As it is performed inside the module (2), it is possible to avoid or at least minimize the input of diving personnel into the high-pressure environment outside the precast tunnel module (2), thereby reducing the risk of safety accidents and saving time and money. The advantages of being able to

도 14에는 고정 케이블(3)이 서로 교차된 상태로 프리캐스트 터널모듈(2)이 테더링되어 있는 실시예에 대한 도 12에 대응되는 개략적인 종방향의 단면도가 도시되어 있다. 프리캐스트 터널모듈(2)을 고정 케이블(3)에 의해 테더링을 함에 있어서, 도 12에 도시된 것처럼 한 쌍의 마감블럭(4)을 각각 프리캐스트 터널모듈(2)의 양측에 결합하여 한 쌍의 고정 케이블(3)이 서로 교차하지 않고 프리캐스트 터널모듈(2)의 양측에 위치하게 할 수도 있지만, 이와 달리 도 14에 도시된 것처럼 고정 케이블(3)이 서로 교차된 상태로 설치되어 프리캐스트 터널모듈(2)이 테더링될 수 있는 것이다. FIG. 14 is a schematic longitudinal cross-sectional view corresponding to FIG. 12 for an embodiment in which the precast tunnel module 2 is tethered with the fixed cables 3 crossed with each other. In tethering the precast tunnel module 2 with the fixed cable 3, a pair of closing blocks 4 are coupled to both sides of the precast tunnel module 2 as shown in FIG. The pair of fixed cables 3 may be positioned on both sides of the precast tunnel module 2 without intersecting each other, but in contrast, as shown in FIG. 14 , the fixed cables 3 are installed in a crossed state, The cast tunnel module 2 can be tethered.

1: 기설부분
2: 프리캐스트 터널모듈
3: 고정 케이블
4: 마감블럭
5: 가이드 체인
1: Existing part
2: Precast tunnel module
3: Fixed cable
4: Closing block
5: guide chain

Claims (4)

프리캐스트 터널모듈(2)을 수면으로 부유시켜 이송시킨 후 침설시켜, 이미 수중에 구축되어 있던 기설부분(1)에 연결 접합하고, 후속하는 프리캐스트 터널모듈을 순차적으로 연속 접합시켜서 수중터널을 구축하는 수중터널 시공방법으로서,
상단에 마감블럭(4)이 구비되어 있는 테더링용 고정 케이블(3)을 기설부분(1)의 전방에 설치하고, 마감블럭(4)에는 가이드 체인(5)을 연결하며, 가이드 체인(5)의 상단에 제1부표(51)를 결합 설치하여 제1부표(51)가 수면에 부유하게 만들고, 고정 케이블(3)에도 연결선(50)을 연결하고 연결선(50)에 보조적인 제2부표(52)를 연결하여 제2부표(52)도 수면에 부유하게 만드는 단계;
프리캐스트 터널모듈(2)을 수면으로 부유시켜 이송시킨 후에는 프리캐스트 터널모듈(2)의 내부에 구비된 체인권취기(M)에 감겨 있는 유도선(54)의 타단부를 프리캐스트 터널모듈(2)의 밖으로 뽑아내어 가이드 체인(5)의 상단에 연결하고 가이드 체인(5)을 제1부표(51)와 분리시키고, 체인권취기(M)의 작동에 의해 유도선(54)을 당겨서 가이드 체인(5)의 상단이 프리캐스트 터널모듈(2)을 관통하여 체인권취기(M)에 감기게 만들어서 가이드 체인(5)의 길이를 줄임으로써 프리캐스트 터널모듈(2)을 수중 침설시켜서 기설부분(1)의 전방에서 접합 위치에 정렬 배치시키는 단계; 및
기설부분(1)과 프리캐스트 터널모듈(2)을 수밀하게 일체로 연결 결합하고, 마감블럭(4)을 프리캐스트 터널모듈(2)에 수밀한 상태로 일체화되도록 고정 결합하여 프리캐스트 터널모듈(2)을 고정 케이블(3)에 의해 테더링하는 단계를 포함하며;
프리캐스트 터널모듈(2)에는 오목하게 파여 있는 오목홈부(20)가 형성되어 있고, 오목홈부(20)에는 볼트공(22)이 형성되어 있으며, 마감블럭(4)의 상단부는 오목홈부(20)에 대응되는 형상을 가지며, 마감블럭(4)의 상면에는 결합볼트(40)가 돌출 구비되어 있고;
체인권취기(M)의 작동에 의해 가이드 체인(5)이 감겨져서 프리캐스트 터널모듈(2)가 침설되어서 기설부분(1)의 전방에 정렬배치되면, 마감블럭(4)의 상단부가 오목홈부(20)의 내면에 밀착되도록 끼워져서 수밀상태를 이루고, 결합볼트(40)는 볼트공(22)을 관통하여 프리캐스트 터널모듈(2)의 내부로 돌출되며, 돌출된 결합볼트(40)에 너트부재(44)가 체결 고정됨으로써 프리캐스트 터널모듈(2)이 고정 케이블(3)에 의해 테더링되며;
오목홈부(20)는 프리캐스트 터널모듈(2)의 두께 일부가 줄어들어서 오목하게 파여 있도록 형성된 것인데, 오목홈부(20)는 평평한 바닥면과, 상기 바닥면을 둘러싸는 경사면으로 이루어져서 프리캐스트 터널모듈의 두께 깊이로 갈수록 단면적이 작아지는 다각 뿔대 형태의 오목한 형상을 가지고 있으며;
마감블럭(4)의 상부는 오목홈부(20)의 오목한 형상에 대응되는 형상의 볼록한 부분을 가지고 있어서, 마감블록(4)의 상부를 이루는 볼록한 부분이 오목홈부(20)에 끼워져서 내면에 밀착되는 형태로 오목홈부(20)를 채우게 되고;
고정 케이블(3)은 마감블럭(4)을 관통하여 마감블럭(4)과 결합되며;
오목홈부(20)의 바닥면에는 고정 케이블(3)이 삽입되는 케이블관통공(23)이 관통 형성되어 있으며;
마감블럭(4)의 상단부가 오목홈부(20)의 내면에 밀착되도록 끼워지면, 고정 케이블(3)의 단부는 케이블관통공(23)을 지나서 프리캐스트 터널모듈(2)의 내부로 돌출되며;
프리캐스트 터널모듈(2)의 내부로 돌출된 고정 케이블(3)의 단부를 긴장장치로 물어서 당긴 후 긴장장치를 고정 케이블(3)의 단부에 체결하여 정착시킴으로써 고정 케이블(3)이 긴장된 상태로 정착됨으로써 고정 케이블(3)에는 긴장력이 도입되는 구성을 가지는 것을 특징으로 하는 수중터널 시공방법.
The precast tunnel module (2) is floated on the surface of the water, transported, and then submerged to connect to the existing part (1) that has already been built in the water, and the following precast tunnel modules are sequentially and successively joined to construct an underwater tunnel. As an underwater tunnel construction method,
A fixing cable for tethering (3) equipped with a closing block (4) at the top is installed in front of the existing part (1), and a guide chain (5) is connected to the closing block (4), and the guide chain (5) ), the first buoy 51 is coupled to the upper end of the buoy to make the first buoy 51 float on the water surface, and the connecting line 50 is also connected to the fixed cable 3, and the second buoy is auxiliary to the connecting line 50. connecting (52) to make the second buoy (52) also float on the water surface;
After floating the precast tunnel module 2 to the water surface and transporting it, the other end of the guide wire 54 wound around the chain winder M provided inside the precast tunnel module 2 is connected to the precast tunnel module. Pull out of (2), connect it to the upper end of the guide chain (5), separate the guide chain (5) from the first buoy (51), and pull the guide wire (54) by the operation of the chain winder (M) By reducing the length of the guide chain 5 by making the upper end of the guide chain 5 penetrate the precast tunnel module 2 and wound around the chain winder M, the precast tunnel module 2 is immersed in the water to make the existing aligning the abutment position at the front of the part (1); and
The precast tunnel module ( 2) tethering by means of a fixed cable (3);
The precast tunnel module (2) is provided with a concave groove (20) which is dug into a concave groove (20), a bolt hole (22) is formed in the concave groove (20), and the upper end of the closing block (4) is a concave groove (20). ) has a shape corresponding to, the upper surface of the closing block (4) is provided with a coupling bolt (40) protruding;
When the guide chain 5 is wound by the operation of the chain winder M and the precast tunnel module 2 is submerged and arranged in front of the existing part 1, the upper end of the closing block 4 is a concave groove part. It is fitted to the inner surface of the 20 to form a watertight state, and the coupling bolt 40 penetrates the bolt hole 22 and protrudes into the precast tunnel module 2, and is attached to the protruding coupling bolt 40. As the nut member 44 is fastened and fixed, the precast tunnel module 2 is tethered by the fixing cable 3 ;
The concave groove 20 is formed so that a part of the thickness of the precast tunnel module 2 is reduced and is dug concave. The concave groove 20 is composed of a flat bottom surface and an inclined surface surrounding the bottom surface. has a concave shape in the form of a polygonal truncated truncated cone whose cross-sectional area becomes smaller as the thickness increases;
The upper portion of the closing block 4 has a convex portion of a shape corresponding to the concave shape of the concave groove portion 20, so that the convex portion constituting the upper portion of the closing block 4 is fitted into the concave groove portion 20 and is in close contact with the inner surface. to fill the concave groove 20 in the form that becomes;
The fixing cable 3 passes through the closing block 4 and is coupled to the closing block 4 ;
A cable through hole 23 into which the fixed cable 3 is inserted is formed through the bottom surface of the concave groove 20;
When the upper end of the closing block 4 is fitted in close contact with the inner surface of the concave groove 20, the end of the fixed cable 3 passes through the cable through hole 23 and protrudes into the precast tunnel module 2;
After pulling the end of the fixed cable 3 protruding into the inside of the precast tunnel module 2 with a tension device, fasten the tension device to the end of the fixed cable 3 and fix it, so that the fixed cable 3 is in a tense state. An underwater tunnel construction method, characterized in that it has a configuration in which tension is introduced to the fixed cable (3) by being fixed.
삭제delete 제1항에 있어서,
가이드 체인(5)의 하단은 결합볼트(40)에 결합되어 있어서, 가이드 체인(5)은 오목홈부(20)의 볼트공(22)을 통과하여 프리캐스트 터널모듈(2)의 내부로 진입되는 것을 특징으로 하는 수중터널 시공방법.
The method of claim 1,
The lower end of the guide chain 5 is coupled to the coupling bolt 40, so that the guide chain 5 passes through the bolt hole 22 of the concave groove 20 and enters the inside of the precast tunnel module 2 Underwater tunnel construction method, characterized in that.
차량이나 사람이 통행할 수 있는 중공(中空)을 가지는 프리캐스트 터널모듈을 수중에서 순차적으로 연결하여 구축된 수중터널로서,
청구항 1 또는 청구항 3의 방법에 의해 시공되어 복수개의 프리캐스트 터널모듈이 일체화되어 연결된 구조를 가지는 것을 특징으로 하는 수중터널.
As an underwater tunnel constructed by sequentially connecting precast tunnel modules having a hollow space through which vehicles or people can pass,
An underwater tunnel constructed by the method of claim 1 or 3, characterized in that it has a structure in which a plurality of precast tunnel modules are integrated and connected.
KR1020200040059A 2020-04-02 2020-04-02 Constructing Method of Underwater Tunnel with Tethering Tunnel Modules, and Underwater Tunnel Constructed by such Method KR102336874B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200040059A KR102336874B1 (en) 2020-04-02 2020-04-02 Constructing Method of Underwater Tunnel with Tethering Tunnel Modules, and Underwater Tunnel Constructed by such Method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200040059A KR102336874B1 (en) 2020-04-02 2020-04-02 Constructing Method of Underwater Tunnel with Tethering Tunnel Modules, and Underwater Tunnel Constructed by such Method

Publications (2)

Publication Number Publication Date
KR20210122980A KR20210122980A (en) 2021-10-13
KR102336874B1 true KR102336874B1 (en) 2021-12-09

Family

ID=78150836

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200040059A KR102336874B1 (en) 2020-04-02 2020-04-02 Constructing Method of Underwater Tunnel with Tethering Tunnel Modules, and Underwater Tunnel Constructed by such Method

Country Status (1)

Country Link
KR (1) KR102336874B1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000027208A (en) * 1998-07-07 2000-01-25 Kajima Corp Underwater moving method and device for underwater structure
JP2002327445A (en) 2001-05-02 2002-11-15 Taisei Corp Construction method of underwater tunnel
KR102066578B1 (en) 2019-03-07 2020-01-15 (주)대우건설 Constructing Method of Underwater Tunnel with Image Processing Alignment and Precast Segments, and Underwater Tunnel Constructed by such Method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0786232B2 (en) * 1992-02-20 1995-09-20 正照 新村 Underwater mooring equipment
JPH0748851A (en) * 1993-08-09 1995-02-21 Mitsui Constr Co Ltd Underwater tunnel
KR100797795B1 (en) 2007-04-13 2008-01-24 재단법인서울대학교산학협력재단 A floating type of underwater bridge and the construction method of the floating type of underwater bridge
KR101059297B1 (en) * 2009-03-27 2011-08-24 김준모 Construction method of cutlery tunnel

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000027208A (en) * 1998-07-07 2000-01-25 Kajima Corp Underwater moving method and device for underwater structure
JP2002327445A (en) 2001-05-02 2002-11-15 Taisei Corp Construction method of underwater tunnel
KR102066578B1 (en) 2019-03-07 2020-01-15 (주)대우건설 Constructing Method of Underwater Tunnel with Image Processing Alignment and Precast Segments, and Underwater Tunnel Constructed by such Method

Also Published As

Publication number Publication date
KR20210122980A (en) 2021-10-13

Similar Documents

Publication Publication Date Title
US6082391A (en) Device for hybrid riser for the sub-sea transportation of petroleum products
KR101211491B1 (en) Submerged floating tunnel with cable-stayed super long-span and construction method thereof
US7430979B2 (en) Method of transporting an elongate member
ES2967419T3 (en) Floating wind turbine support
KR102336874B1 (en) Constructing Method of Underwater Tunnel with Tethering Tunnel Modules, and Underwater Tunnel Constructed by such Method
US6682266B2 (en) Tension leg and method for transport, installation and removal of tension legs pipelines and slender bodies
BRPI0910535B1 (en) inertial transition duct element, subsea rigid duct and rigid end fitting method of a rigid duct
US4351624A (en) File and jacket construction method and apparatus
JP5166778B2 (en) How to build a pontoon
US9045205B2 (en) Floatable boat ramp
KR102382702B1 (en) Constructing Method of Underwater Tunnel with Tethering Tunnel Modules with Blocks, and Underwater Tunnel Constructed by such Method
RU2483969C1 (en) Dismountable lifting pontoon
EP2329098B1 (en) Methods and associated apparatus of constructing and installing rigid riser structures
KR102403753B1 (en) Constructing Method of Underwater Tunnel with Tethering Tunnel Modules, and Underwater Tunnel Constructed by such Method
KR102260350B1 (en) Submerged floating tunnel mooring device and its mooring method
US3766743A (en) Underwater pipeline installation
JPS5843534B2 (en) Offshore joining method for concrete floating bodies
KR100789986B1 (en) Method for laying pipe line on bottom of the sea
US20140314493A1 (en) Method for installing a self-supporting tower for extracting hydrocarbons
CN217260591U (en) Structure of floating platform on water
ES2695308B2 (en) Anchoring system and method of installing a seafloor anchoring system
US408748A (en) Buoyant subaqueous tunnel for railways
GB1589839A (en) Anchor and method of installation thereof
SU1283486A1 (en) Set of pipeline sections for transportation to place of laying
RU2035350C1 (en) Vertical floating column

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right