KR102025327B1 - pipe layer adjustable boom length - Google Patents
pipe layer adjustable boom length Download PDFInfo
- Publication number
- KR102025327B1 KR102025327B1 KR1020130059691A KR20130059691A KR102025327B1 KR 102025327 B1 KR102025327 B1 KR 102025327B1 KR 1020130059691 A KR1020130059691 A KR 1020130059691A KR 20130059691 A KR20130059691 A KR 20130059691A KR 102025327 B1 KR102025327 B1 KR 102025327B1
- Authority
- KR
- South Korea
- Prior art keywords
- boom
- fixed
- pipe layer
- length
- detachably fixed
- Prior art date
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/62—Constructional features or details
- B66C23/64—Jibs
- B66C23/68—Jibs foldable or otherwise adjustable in configuration
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C2700/00—Cranes
- B66C2700/01—General aspects of mobile cranes, overhead travelling cranes, gantry cranes, loading bridges, cranes for building ships on slipways, cranes for foundries or cranes for public works
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66D—CAPSTANS; WINCHES; TACKLES, e.g. PULLEY BLOCKS; HOISTS
- B66D2700/00—Capstans, winches or hoists
- B66D2700/01—Winches, capstans or pivots
- B66D2700/0108—Winches, capstans or pivots with devices for paying out or automatically tightening the cable
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Jib Cranes (AREA)
Abstract
The present invention is to extend the working radius according to the working environment,
Boom length adjustable pipe layer according to an embodiment of the present invention,
Undercarriage;
An upper frame rotatably mounted on the lower running body and equipped with a cab and an engine compartment;
A boom adapter mounted at the front of the upper frame;
A boom pivotally fixed to the boom adapter by a boom cylinder rotatably fixed to the upper frame by a lower end;
A flag block detachably fixed to a first mounting member of a first center plate installed at an upper end of the boom and supporting a wire rope to lift and lower the hook;
A winch for elevating the hook by the wire rope wound around the winch roller according to a rotational direction of the winch motor mounted on the upper frame;
A connection plate detachably fixed to an upper portion of the boom, a left and right frame mounted opposite to the connection plate, a second center plate fixed to a predetermined position on an opposite surface of the left and right frames, and installed on the second center plate And a second mounting member in which a flag block separated from the first mounting member is detachably fixed, and is detachably connected to an upper end of the boom to adjust the boom length. To provide a boom-length adjustable pipe layer.
Description
The present invention relates to a pipe layer, and more particularly to a pipe layer with a boom length adjustable to extend the working radius according to the working environment.
Generally, a pipe layer (pipe layer) for transporting an oil pipeline to a buried place (an excavation groove formed to bury an oil pipeline) during an operation for embedding heavy chain oil pipelines (pipes for transferring oil, natural gas, etc.) and water pipelines. ). At this time, the pipe layer is configured to enable the basic operation (driving, swing, etc.) of the excavator, and is used by replacing the excavator working device (boom, arm, bucket, etc.) with a boom and winch.
Pipe layer according to the prior art shown in Figure 1,
Lower traveling
An upper frame (4) rotatably mounted on the lower traveling body (1), on which a cab cap (2) and an engine compartment (3) are mounted;
A boom adapter (5) mounted to the front of the upper frame (4);
The
A hook (10) lifted by a wire rope (9) supported by the sheave (8) fixed to the upper end of the boom (7);
And a
In the process of embedding oil pipes, water pipes, and the like having a large tube diameter by using the pipe layer as described above, the wire rope 9 wound on the winch roller by driving the
In the pipe layer of the prior art, the working radius is limited depending on the length of the boom during the pipe laying operation of lifting a heavy oil pipeline and moving it to a buried place, thereby reducing the work efficiency of expensive construction equipment.
Embodiments of the present invention relate to a boom length-adjusted pipe layer that allows for expansion of the working radius by means of a boom extension that is mounted according to operator intent or working environment.
Embodiments of the present invention relate to a boom length-adjusted pipe layer that provides convenience to the driver by reducing work time for mounting the boom extension at the boom end.
Boom length adjustable pipe layer according to an embodiment of the present invention,
Undercarriage;
An upper frame rotatably mounted on the lower running body and equipped with a cab and an engine compartment;
A boom adapter mounted at the front of the upper frame;
A boom pivotally fixed to the boom adapter by a boom cylinder rotatably fixed to the upper frame by a lower end;
A flag block detachably fixed to a first mounting member of a first center plate installed at an upper end of the boom and supporting a wire rope to lift and lower the hook;
A winch for elevating the hook by the wire rope wound around the winch roller according to a rotational direction of the winch motor mounted on the upper frame;
A connection plate detachably fixed to an upper portion of the boom, a left and right frame mounted opposite to the connection plate, a second center plate fixed to a predetermined position on an opposite surface of the left and right frames, and installed on the second center plate And a second mounting member in which a flag block separated from the first mounting member is detachably fixed, and is detachably connected to an upper end of the boom to adjust the boom length. To provide a boom-length adjustable pipe layer.
According to a preferred embodiment, the connecting plate is
It is in close contact with the fixing plate formed on the top of the boom to correspond to the connecting plate, characterized in that the removable plate is fixed to the fixing plate by a bolt fastened through the connecting plate and the fixing plate.
The left and right frames are
Characterized in that each pipe having a cross section corresponding to the boom cross section.
The boom extension structure
Pipe lugs formed on the left and right frames to face each other;
One side is detachably fixed to the upper surface of the boom, and the other side is foldably connected to the pipe lug; characterized in that it comprises a reinforcement member made with.
The bracket
Penetrating through the bracket is characterized in that the detachably fixed to the upper surface of the boom by a bolt fastened to the upper surface of the boom.
One embodiment of the present invention as described above has the following advantages.
Work efficiency can be improved as the working radius is extended by the boom extension which is detachably mounted according to the driver's intention or working environment.
In addition, it is possible to provide convenience and reliability to the driver by reducing the work time for mounting the boom extension structure at the boom end.
1 is a schematic diagram of a pipe layer according to the prior art,
Figure 2 is a perspective view of the boom extension structure, in the boom length adjustable pipe layer according to an embodiment of the present invention,
3 is a plan view of the boom extension structure, in the boom length adjustable pipe layer according to an embodiment of the present invention,
Figure 4 is a side view showing the boom length in the boom length adjustable pipe layer according to an embodiment of the present invention,
5 is a view showing the mounting of the boom extension in the boom length-adjustable pipe layer according to an embodiment of the present invention,
6 is a state diagram used of the boom length adjustable pipe layer according to an embodiment of the present invention.
Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings, which are intended to explain in detail enough to enable those skilled in the art to easily carry out the invention, and thus It is not intended that the technical spirit and scope of the invention be limited.
Boom length adjustable pipe layer according to an embodiment of the present invention shown in Figure 2 to 6,
Lower running body (1);
An upper frame (4) rotatably mounted on the lower traveling body (1), on which an cab cap (2) and an engine compartment (3) are mounted;
A boom adapter (5) mounted to the front of the upper frame (4);
A boom (7) rotated by a boom cylinder (6) having a lower end fixed to the boom adapter (5) by a fixing pin and rotatably fixed by a fixing pin on a lower end of the upper frame (4);
Removably fixed to the first mounting member 13 (
A
A connecting
In this case, preferably, the
The
The left and
Each pipe having a cross section corresponding to the cross section of the boom 7 (for example, a square pipe may be used) may be formed.
The
Pipe lugs 23 and 24 fixed by welding on the left and
One side is detachably fixed to the upper surface of the boom (7), the other side to the pipe lugs (23, 24) brackets (25, 26) that is foldably connected by a fixing pin (P); And (27).
The
It may be detachably fixed to the upper surface of the
At this time, the configuration except for the
Hereinafter, an example of using the boom length adjustable pipe layer according to an embodiment of the present invention will be described in detail with reference to the accompanying drawings.
2 to 6, the boom (7) by the
That is, in a state in which the connecting
The fixing
The
The
As shown in FIG. 4, the length of the
On the other hand, when the
Therefore, it is possible to extend the working radius by extending the length of the
On the other hand, as described above, when the pipe laying work to extend the length of the boom (7) by the
That is, in accordance with the working environment or the driver's intention that the work is not required to extend the length of the
One; Undercarriage
2; Cab Cap
3; Engine room
4; Upper frame
5; Boom adapter
6; Boom cylinder
7; Boom
8; Sieve
9; Wire rope
10; hook
11; winch
12; Oil pipe
13; First mounting member
14; Flag block
15; Connecting plate
16; Left frame
17; Right frame
18; 2nd center plate
19; Second mounting member
20; Boom extension
21; Fixed plate
22; volt
23,24; Pipe lugs
25,26; Bracket
27; Reinforcement member
Claims (5)
An upper frame rotatably mounted on the lower running body and equipped with a cab and an engine compartment;
A boom adapter mounted at the front of the upper frame;
A boom pivotally fixed to the boom adapter by a boom cylinder rotatably fixed to the upper frame by a lower end;
A flag block detachably fixed to a first mounting member of a first center plate installed at an upper end of the boom and supporting a wire rope to lift and lower the hook;
A winch for elevating the hook by the wire rope wound around the winch roller according to a rotational direction of the winch motor mounted on the upper frame;
A connection plate detachably fixed to an upper portion of the boom, a left and right frame mounted opposite to the connection plate, a second center plate fixed to a predetermined position on an opposite surface of the left and right frames, and installed on the second center plate And a second mounting member in which a flag block separated from the first mounting member is detachably fixed to the flag block, and a boom extension structure detachably connected to an upper end of the boom to adjust the boom length. Boom length adjustable pipe layer.
A boom length-adjustable pipe layer, which is in close contact with the fixing plate formed on the top of the boom so as to correspond to the connecting plate and is detachably fixed to the fixing plate by bolts fastened through the connecting plate and the fixing plate.
Boom length-adjusted pipe layer, characterized in that formed by each pipe having a cross section corresponding to the boom cross section.
Pipe lugs formed on the left and right frames to face each other;
A boom length-adjustable pipe layer, comprising a reinforcing member comprising: a bracket detachably fixed to one side of the upper surface of the boom and the other side to be foldably connected to the pipe lug.
A boom length-adjustable pipe layer, characterized in that is detachably fixed to the upper surface of the boom by a bolt fastened to the upper surface of the boom through the bracket.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020130059691A KR102025327B1 (en) | 2013-05-27 | 2013-05-27 | pipe layer adjustable boom length |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020130059691A KR102025327B1 (en) | 2013-05-27 | 2013-05-27 | pipe layer adjustable boom length |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20140139256A KR20140139256A (en) | 2014-12-05 |
KR102025327B1 true KR102025327B1 (en) | 2019-09-25 |
Family
ID=52459334
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020130059691A KR102025327B1 (en) | 2013-05-27 | 2013-05-27 | pipe layer adjustable boom length |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR102025327B1 (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10220921B1 (en) | 2017-10-26 | 2019-03-05 | Miller Towing Equipment, Inc. | Pipe-laying vehicle with rotator platform leveling system |
CN108408566B (en) * | 2018-05-17 | 2023-11-14 | 江苏凯斯智能装备科技有限公司 | Lifting appliance with lifting turnover lifting hook |
CN109205491B (en) * | 2018-11-19 | 2020-06-23 | 李雪峰 | Pipeline installation hoisting device for buried waste gas treatment tower |
CN112727111A (en) * | 2020-12-25 | 2021-04-30 | 重庆城市职业学院 | Scenic spot modular building construction equipment and use method |
CN117300573B (en) * | 2023-11-29 | 2024-02-06 | 山西继禹工程机械有限公司 | Mining equipment assembly disassembly and assembly vehicle |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4091936A (en) * | 1976-11-15 | 1978-05-30 | The Warner & Swasey Company | Apparatus for extending a boom assembly |
JPH11228076A (en) * | 1998-02-10 | 1999-08-24 | Komatsu Ltd | Device and method for changing number of winding time of wire rope for crane |
-
2013
- 2013-05-27 KR KR1020130059691A patent/KR102025327B1/en active IP Right Grant
Also Published As
Publication number | Publication date |
---|---|
KR20140139256A (en) | 2014-12-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR102025327B1 (en) | pipe layer adjustable boom length | |
US7896178B2 (en) | Industrial vehicle counterweight system | |
US20090260265A1 (en) | Accessory For Converting Excavators | |
US7845503B2 (en) | Pipe-laying machine | |
JP4679605B2 (en) | Hydraulic hose routing device for hanging grapple | |
JP5800848B2 (en) | Cylinder storage device, boom device and crawler crane | |
JP2016199345A (en) | Boom attaching/detaching device and attaching/detaching method | |
JP2007230747A (en) | Working method and working machine | |
CN107420114A (en) | A kind of Multifunctional aloft-work constructing device for constructing tunnel | |
JP5302928B2 (en) | Work machine front attachment | |
JP5367645B2 (en) | Working machine | |
JP2002194774A (en) | Method and device for detaching/attaching counter weight of construction machinery | |
JP5389682B2 (en) | Construction machinery | |
KR20090033606A (en) | Option pipe fixing device of excavator short swing radius type | |
JP2019044370A (en) | Construction machine | |
JP6816745B2 (en) | How to install construction machinery and winch body | |
CN207348867U (en) | A kind of Multifunctional aloft-work constructing device for constructing tunnel | |
CA2631480A1 (en) | Boom assembly suitable for pipelaying | |
JP2014214540A (en) | Hydraulic equipment arrangement configuration of compact double arm work machine | |
JP5439437B2 (en) | Electric working machine, power supply unit and moving method thereof | |
JP7052661B2 (en) | Piping structure for construction machinery and transformer lifters | |
JPH081189U (en) | Model steel beam gripping vehicle and model steel beam gripping device | |
JP2017197316A (en) | Assembling method of construction machine | |
JP6776740B2 (en) | How to attach / detach the winch to the work machine and the main body of the work machine | |
JP2005171696A (en) | Hanging attachment detaching device and handling machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant |