KR101948026B1 - Pre-stressed concrete (psc) beam producing method for forming steel reinforcement assembly by connecting prefabricated segments of steel reinforcement assembly in construction field - Google Patents
Pre-stressed concrete (psc) beam producing method for forming steel reinforcement assembly by connecting prefabricated segments of steel reinforcement assembly in construction field Download PDFInfo
- Publication number
- KR101948026B1 KR101948026B1 KR1020180051823A KR20180051823A KR101948026B1 KR 101948026 B1 KR101948026 B1 KR 101948026B1 KR 1020180051823 A KR1020180051823 A KR 1020180051823A KR 20180051823 A KR20180051823 A KR 20180051823A KR 101948026 B1 KR101948026 B1 KR 101948026B1
- Authority
- KR
- South Korea
- Prior art keywords
- reinforcing bar
- assembly
- bar assembly
- reinforcing
- segments
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/28—Concrete reinforced prestressed
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
Description
본 발명은 PSC 빔 제작방법에 관한 것으로, 보다 구체적으로, 프리스트레스트 콘크리트(Pre-Stressed Concrete: PSC) 교량의 시공을 위한 PSC 빔(Beam) 제작시, 현장과 떨어진 공장 등의 장소에서 철근조립대를 이용하여 복수의 철근조립체 세그먼트를 제작하여 운반하고, 현장에서 철근조립체 세그먼트를 결합한 철근조립체를 형성한 후에 콘크리트를 타설하는, 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에 관한 것이다.The present invention relates to a method of manufacturing a PSC beam, and more particularly, to a method of manufacturing a PSC beam for the construction of a pre-stressed concrete (PSC) bridge, A PSC beam fabrication method in which a plurality of rebar assembly segments are manufactured and transported and a reinforcing bar assembly is formed by combining the reinforcing bar assembly segments in the field and then the concrete is laid, .
최근 건설되는 콘크리트 교량은 PSC 빔을 이용하여 가설되며, 이러한 교량 가설공법의 경우, 지상에서 PSC 빔을 제작한 후에 가설현장으로 운반한다.Recently constructed concrete bridges are constructed using PSC beams. In the case of such a bridge construction method, the PSC beam is produced on the ground and then transported to the construction site.
도 1의 a)는 일반적인 PSC 빔 교량을 나타내는 측면도이고, 도 1의 b)는 PSC 빔을 나타내는 사시도이다.1 (a) is a side view showing a general PSC beam bridge, and Fig. 1 (b) is a perspective view showing a PSC beam.
도 1의 a)에 도시된 바와 같이, 교대 또는 교각(2) 위에 PSC 빔(1)의 양측 단부를 거치한 후, 상기 PSC 빔(1)과 일체화되도록 가로보를 형성하고, 이후, 슬래브 콘크리트(3)를 타설하여 교량을 건설하는 공법이다. 이러한 공법에 소요되는 PSC 빔(1)은, 도 1의 b)에 도시된 바와 같이, 기본적으로 I자형의 단면을 유지하면서 교축방향을 따라서 동일한 형태의 직선 형태를 이루도록 형성된다.As shown in Fig. 1 a), a beam is formed so as to be integrated with the
이와 같이 교량의 상부구조물로 널리 사용되고 있는 PSC 빔(10)은 길이가 표준화되어 있어 철근 가공 및 조립, 거푸집 설치, 콘크리트 타설 및 긴장력 도입 등 일련의 작업과정들이 동일한 패턴으로 반복적인 작업이 현장에서 이루어지고 있다.Since the length of the
한편, 도 2는 종래의 기술에 따른 철근콘크리트 빔 내부에 배근되는 철근조립체를 예시하는 도면이다.FIG. 2 is a view illustrating a reinforcing bar assembly disposed in a reinforced concrete beam according to a conventional technique.
철근조립체(4)는 다양한 직경과 형태를 가진 철근들이 서로 조립되어 길이방향으로 연장되도록 제작하게 되는데, 이러한 철근들은 단면력에 따라 그 형태 및 배치간격들이 정해지게 된다. 예를 들면, 도 2에 도시된 바와 같이 길이방향 주철근(4a)을 스트럽철근(4f)이 감싸도록 배근되고, 이러한 스트럽철근(4f)은 길이방향으로 서로 이격되어 길이방향 주철근(4a)에 결속된다.The
또한, 역시 U자형 띠철근(4c)이 길이방향 주철근(4a) 및 스트럽철근(4f)을 감싸도록 배근되며, 이러한 U자형 띠철근(4c)은 길이방향으로 서로 이격되고, 역시 길이방향 주철근(4c)에 의하여 결합된다. 또한, 용도에 따라 다른 부재철근(4b)들이 추가 배근되고, 다른 철근을 체결설치 하기 위한 환형 볼트(4e)가 설치되기도 한다.The U-shaped
이와 같이 철근콘크리트 빔 내부에 콘크리트에 의하여 마감되는 내부에 많은 철근들이 배근되며, 이러한 철근들의 배근은 숙련된 철근공들이 배근작업을 통해 완성되지만 대부분 인력에 의한 작업이기 때문에 품질관리가 어려울 수밖에 없게 된다.In this way, many reinforcing bars are placed inside the concrete inside the reinforced concrete beam, and the steel reinforcing bars are completed through the laying work of the reinforcing bars. However, quality control is inevitably difficult due to the work performed by most of the workers.
물론, 자동화된 설비를 구축할 수 있겠지만 요구되는 철근콘크리트 빔 단면이 다양하기도 하고, 소량 생산을 위하여 일일이 자동화된 설비를 이용할 경우, 사실상 많은 투자와 노력을 요구할 수밖에 없게 되어 크레인 운반과 같은 작업을 제외하고는 대부분의 조립작업은 작업자의 인력에 의존하고 있는 실정이다.Of course, it is possible to construct an automated facility, but the required cross-section of the reinforced concrete beam is various. In case of using automated equipment for small-scale production, it is necessary to invest a lot of effort and effort, Most assembly work depends on the workforce.
한편, 선행기술로서, 대한민국 등록특허번호 제10-1692356호에는 "단부리프트를 이용한 철근조립장치, 이를 이용한 철근조립체 제작방법 및 철근콘크리트빔"이라는 명칭의 발명이 개시되어 있는데, 도 3을 참조하여 설명한다.As a prior art, Korean Patent Registration No. 10-1692356 discloses an invention entitled " Rebar Assembly Device using End Lift, Rebar Assembly Method Using It and Reinforced Concrete Beam " Explain.
도 3은 종래의 기술에 따른 철근조립장치를 나타내는 사시도이다.3 is a perspective view showing a reinforcing bar assembling apparatus according to a conventional technique.
도 3을 참조하면, 종래의 기술에 따른 철근조립장치는 철근조립대(10), 철근조립빔(20), 단부리프트(30) 및 주철근운반 지지대(40)를 포함하여 구성된다.Referring to FIG. 3, a conventional rebar assembling apparatus includes a
철근조립대(10)는 공장 등에 있어 바닥판에 설치된 일종의 강재 베이스플레이트로서 상면 단부에는 양 단부리프트(30, 30a, 30b)가 수직으로 연장되도록 배치된다. 이러한 철근조립대(10)는 일측 단부리프트(30a) 측방으로부터 철근조립빔(20)에 주철근(51)을 탑재하여 양단부리프트(30, 30a, 30b) 사이에 진입시킬 수 있도록 철근조립빔의 연장길이를 고려하여 세팅된다.The
이에 따라, 일측 단부리프트(30a) 측방에서 주철근(51)을 탑재시킨 철근조립빔(20)이 진입할 수 있도록 철근조립대(10) 상면에는 롤러와 같은 슬라이딩수단(11)이 상면에 다수를 이격시켜 설치하게 된다. 이때, 상기 롤러 상면에서 슬라이딩 되면서 철근조립빔(20)이 철근조립대(10) 상면으로부터 이탈되지 않도록 롤러의 양 측방에는 이탈방지용 고정대(12)를 설치할 수 있다.A sliding means 11 such as a roller is provided on the upper surface of the
또한, 철근조립빔(20)은 상면에 띠철근(52)과 스트럽철근(53)이 얹어져 이격되어 세팅되도록 하는 지지대 역할을 하면서, 먼저 세팅된 띠철근(52)과 스트럽철근(53)에 주철근(51)을 운반할 수 있는 일종의 대차역할도 하게 된다. 이때, 상기 철근조립빔(20)은 H형강과 같은 강재빔(21)을 이용하고, 양 단부면은 단부마감판(22)이 형성되도록 하고, 강재빔(21)의 복부(125)에는 주철근운반지지대(40)가 장착시킨다.The reinforcing
또한, 타측 단부마감판(22)에는 고정홀(23)이 형성되어 있고, 일측은 힌지봉(24)이 형성되며, 이에 따라 타측 단부리프트(30b)에 장착된 회전판(31)의 고정핀(32)이 상기 고정홀(23)에 삽입되도록 하고, 일측 단부리프트(30a)에 형성된 힌지봉지지대(33)에 상기 힌지봉(24)이 안착된다.A
결국, 철근조립빔(20)은 철근조립대(10)의 롤러를 통해 좌우로 이동하면서 주철근(51)을 운반하고, 철근조립대(10)에 세팅된 띠철근(52), 스트럽철근(53)에 주철근(51)을 연결 조립할 수 있는 대차로서, 띠철근(52), 스트럽철근(53)을 주철근(51)에 연결 조립하기 위하여 필요한 노력을 줄여 작업자의 숙련에 따라 좌우되는 철근조립체(50) 제작의 품질을 용이하게 관리할 수 있다.The reinforcing
또한, 단부리프트(30)는 철근조립대(10)의 상면에 서로 이격되어 내측에 철근조립빔(20)이 위치하게 되며, 철근조립빔(20)의 양 단부를 상승 및 하강시킬 수 있도록 하면서, 철근조립체(50) 조립이 완료되면 철근조립빔(20)을 180도 회전시키는 기능을 가지게 된다.The end lifts 30 are spaced apart from each other on the upper surface of the reinforcing
이에 따라, 철근조립빔(20)이 진입하는 쪽의 일측 단부리프트(30a)는 철근조립빔(20)의 단부마감판(22)에 형성된 힌지봉(24)을 지지하는 힌지봉지지대(33)가 위치할 수 있도록 단부포스트(31a) 두개가 서로 횡방향으로 이격되어 마주보도록 배치시켜 철근조립빔(20)의 이동이 가능한 공간이 형성된다.The
주철근운반 지지대(40)는 철근조립빔(20)의 강재빔(21) 양 복부(25)에 장착시킨 회전붐대를 포함하여 형성된다. 이에 따라, 주철근(51)은 일측 단부리프트(30a)의 측방에 위치시킨 철근조립빔(20)의 주철근운반 지지대(40)에 미리 탑재하고, 주철근(51)이 주철근운반 지지대(40)에 탑재된 철근조립빔(20)이 양 단부리프트(30a, 30b) 사이로 이동하는 과정에서 함께 운반된다.The cast iron
종래의 기술에 따른 철근조립장치에 따르면, 철근콘크리트 빔 제작을 위한 철근조립체를 제작함에 있어서 품질관리가 용이하도록 하면서 숙련된 작업자가 아니더라도 용이하게 철근들을 배근하고 조립할 수 있다.According to the conventional reinforcing bar assembling apparatus, it is possible to easily assemble and assemble the reinforcing bars even when not a skilled worker, while making quality control easy in manufacturing a reinforcing bar assembly for producing a reinforcing concrete beam.
한편, 철근콘크리트 구조물은 다수의 종방향 철근과 횡방향 철근을 종횡으로 배근 및 고정하고, 이러한 철근들의 바깥쪽에 거푸집을 설치하며, 이러한 거푸집 내에 콘크리트를 타설 및 양생함으로써 시공된다.On the other hand, the reinforced concrete structure is constructed by longitudinally and horizontally arranging and securing a plurality of longitudinal reinforcing bars and transverse reinforcing bars, installing a mold outside the reinforcing bars, and pouring and curing concrete in these reinforcing bars.
이러한 철근의 배근은, 통상적으로 작업자가 직접 종방향 철근과 횡방향 철근을 배근 위치로 운반하여 배근하는 방식 또는 크레인을 이용하여 배근 위치로 운반한 후 작업자가 배근하는 방식 등이 있다.Such reinforcing steel rods are usually constructed by an operator manually transporting the longitudinal reinforcing bars and transverse reinforcing rods to the reinforcing rods, or a method in which the roving ropes are transported to a roping position using a crane.
이러한 철근 가공과 조립 공정은 현장에서 다수의 작업인력에 의하여 일일이 수작업으로 작업이 이루어지는 특성상 작업기간이 많이 소요되며, 특히, 숙련된 철근 작업인력의 수급이 갈수록 어려워지는 사회적 여건상 미숙련 작업인력의 현장 투입에 따른 생산성 저하 및 품질, 안전관리상의 문제, 인건비 상승에 따른 원가상승 등 현장 작업에 따른 문제가 갈수록 커지고 있는 형편이다.This reinforcing steel processing and assembling process requires a lot of work period due to the fact that the work is manually performed by a large number of workmen in the field. In particular, due to the social conditions in which the supply of skilled steelworkers becomes increasingly difficult, Problems related to field work such as productivity decrease due to input, quality, safety management problem, cost increase due to labor cost increase are increasing.
또한, 철근 가공 및 조립과 관련한 또 다른 방법으로 소정의 철근 가공, 즉, 철근을 도면대로 자르거나 굽히거나 하는 일련의 작업들만 공장에서 하고, 이와 같이 가공된 철근들을 현장으로 운반하여 현장에서는 조립하는 방법이 이루어지는 예도 있으나, 이러한 방법 역시 철근 가공을 제외한 대부분의 철근조립 과정들이 현장에서 이루어지기 때문에 상대적으로 많은 작업자와 시간이 소요되는 철근 조립작업의 반복으로 그다지 큰 비용절감과 공사기간 단축, 품질관리와 안전관리의 획기적인 개선 효과는 기대하기 어려운 형편이다.In addition, there is another method related to the processing and assembling of reinforcing bars. In the factory, only a series of operations for performing a predetermined reinforcing process, that is, cutting or bending the reinforcing bars according to the drawings, are carried out. However, since most of the rebar assembly processes except for the rebar are performed in the field, relatively large number of workers and time-consuming repetition of the rebar assembly operation are required to reduce the cost, shorten the construction period, And improvement of safety management are not expected to be expected.
또한, 전술한 도 3에 도시된 종래의 기술에 따른 철근조립장치에 의해 조립된 철근조립체의 경우, PSC 빔 제작을 위한 철근조립체에 적용하기 어렵다는 문제점이 있다. 즉, 종래의 기술에 따른 철근조립장치에 의해 조립된 철근조립체는 하나의 완성된 철근조립체이기 때문에 현장까지 운반하는 것이 용이하지 않고, 특히, PSC 빔과 같이 대형 구조물용 철근조립체인 경우, 공장에서 현장까지 이동시키는 것이 매우 어렵다는 문제점이 있다.In addition, in the case of the reinforcing bar assembly assembled by the reinforcing bar assembling apparatus according to the prior art shown in FIG. 3, it is difficult to apply the reinforcing bar assembly to the reinforcing bar assembly for manufacturing the PSC beam. That is, it is not easy to transport to the site because the reinforcing bar assembly assembled by the reinforcing bar assembly according to the prior art is a completed reinforcing bar assembly. In particular, in the case of a reinforcing bar assembly for a large structure such as a PSC beam, There is a problem that it is very difficult to move to the site.
전술한 문제점을 해결하기 위한 본 발명이 이루고자 하는 기술적 과제는, PSC 교량의 시공을 위한 PSC 빔 제작시, 현장과 떨어진 공장 등의 장소에서 철근조립대를 이용하여 복수의 철근조립체 세그먼트를 제작하여 운반하고, 현장에서 철근조립체 세그먼트를 결합한 철근조립체를 형성한 후에 콘크리트를 타설하여 PSC 빔을 제작할 수 있는, 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법을 제공하기 위한 것이다.In order to solve the above problems, the present invention provides a method of manufacturing a PSC beam for a PSC bridge, The present invention provides a method of manufacturing a PSC beam, in which a reinforcing bar assembly is formed by combining a reinforcing bar assembly segment in the field, and then a concrete is installed to form a PSC beam.
본 발명이 이루고자 하는 다른 기술적 과제는, 체결블록 또는 철근받침대와 결합하는 철근조립대를 이용하여 철근조립체 세그먼트를 조립함으로써 공장에서 철근조립체 세그먼트를 신속하면서도 정밀하게 조립 제작할 수 있는, 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법을 제공하기 위한 것이다.Another object of the present invention is to provide a method and system for assembling reinforcing assembly segments by assembling a reinforcing assembly segment using a reinforcing assembly assembly coupled with a fastening block or a rebar pedestal, To thereby form a reinforcing steel assembly.
전술한 기술적 과제를 달성하기 위한 수단으로서, 본 발명에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법은, a) 공장에서 철근조립체 세그먼트 제작을 위해 철근조립대 및 철근지지대를 배치하는 단계; b) 상기 철근조립대에 체결블록 또는 철근받침대를 체결하는 단계; c) 상기 체결블록 또는 철근받침대 상에 상기 철근조립체 세그먼트를 삽입하여 조립하는 단계; d) 철근조립체 세그먼트 운반장치를 이용하여 상기 철근조립체 세그먼트를 현장으로 운반하는 단계; e) 현장의 PSC 빔 제작대에 상기 철근조립체 세그먼트를 거치하고, 상기 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 단계; f) 상기 PSC 빔 제작대 상에 거푸집을 조립하고 콘크리트를 타설하는 단계; 및 g) 긴장재 정착장치를 설치하고, 긴장력을 도입하여 PSC 빔을 완성하는 단계를 포함하되, 공장에서 미리 제작된 다수의 철근조립체 세그먼트를 현장에 반입하여 현장에서 PSC 빔 제작대 상에서 서로 겹이음하여 원하는 연장 길이를 갖는 철근조립체를 형성하며, 상기 d) 단계의 철근조립체 세그먼트 운반장치는 하부 지지 방식의 철근조립체 인양장치로서, 상기 철근조립체 세그먼트를 하부에서 지지하여 운반하는 철근조립체 운반 프레임을 이용하며, 상기 철근조립체 운반 프레임은 철근조립대 내측에 배치된 철근지지대 사이의 브레이싱를 활용하되, 상기 철근지지대와 브레이싱 상면에 철근조립체 세그먼트가 하부지지방식으로 지지되도록 하면서, 철근조립체 세그먼트가 내측에 위치하여 폐합되도록 사각박스체 형태로 조립하게 된다.As a means for achieving the abovementioned technical object, a PSC beam manufacturing method for connecting a reinforcing assembly segment by connecting the reinforcing assembly segments in the field according to the present invention comprises the steps of: a) assembling a reinforcing bar assembly and a reinforcing bar support ; ≪ / RTI > b) fastening the fastening block or the reinforcing bar to the reinforcing bar assembly; c) inserting and assembling the bar assembly segment on the fastening block or bar support; d) transporting said rebar assembly segment to the field using a rebar assembly segment transport device; e) placing the reinforcing assembly segment on a site PSC beam building stand and connecting the reinforcing assembly segments to form a reinforcing assembly; f) assembling a mold on the PSC beam production site and casting concrete; And g) installing a taut fixer and completing the PSC beam by introducing a tension force, wherein a plurality of prefabricated rebar assembly segments are brought into the field and folded on the PSC beam production site in situ Wherein the rebar assembly segment conveying device in the step d) is a bottom supporting type lifting device for lifting a steel bar assembly using a steel bar assembly carrying frame for supporting and transporting the steel bar assembly segment from the bottom, , The reinforcing bar assembly carrying frame utilizes a bracing between the reinforcing bar supports located inside the reinforcing bar assembly so that the reinforcing bar assembly and segments are supported on the upper surface of the bracing in a lower supporting manner, So that they are assembled in the form of a rectangular box.
여기서, 상기 b) 단계의 체결블록은 슬롯형 제1 체결블록으로서, "ㄷ"자형 체결블록 볼록부를 형성하여 제1 철근조립대에 형성된 제1 철근조립대 체결홈에 삽입함으로써 제1 체결블록과 제1 철근조립대가 레일처럼 이동할 수 있다.In this case, the fastening block in step b) is a slot-type first fastening block, and the " C " fastening block convex part is formed and inserted into the first reinforcing bar assembly fastening groove formed in the first reinforcing bar assembly, The first reinforcing assembly can move like a rail.
여기서, 상기 b) 단계의 체결블록은 슬롯형 제2 체결블록으로서, 상기 제2 체결블록 하단의 폭이 넓게 제2 체결블록 볼록부를 형성하여 제2 철근조립대에 형성된 제2 철근조립대 체결홈에 삽입함으로써, 상기 제2 체결블록과 제2 철근조립대와 체결시 일체감을 확보하며, 철근 조립 후 제2 철근조립대에서 철근을 분리할 경우, 상기 제2 체결블록의 하단부와 제2 철근조립대가 맞물려 스토퍼 역할을 하여 제2 철근조립대에서 상기 제2 체결블록의 이탈을 방지할 수 있다.In this case, it is preferable that the fastening block in step b) is a slot-type second fastening block, and the second fastening block convex part is formed at a lower width of the lower end of the second fastening block, To secure a sense of unity at the time of tightening with the second fastening block and the second reinforcing bar assembly, and when the reinforcing bars are separated from the second reinforcing bar assembly after the rebar assembly, the lower end of the second fastening block and the second reinforcing bar assembly So that the second fastening block can be prevented from departing from the second reinforcing bar assembly.
여기서, 상기 b) 단계의 철근받침대는 "ㄷ"자형 제1 철근받침대 볼록부가 형성된 제1 철근받침대로서 간격조절부재를 사용하여 간격을 조절하며, 상기 "ㄷ"자형 제1 철근받침대 볼록부를 제1 철근조립대에 형성된 제1 철근조립대 체결홈에 삽입함으로써 상기 제1 철근받침대와 제1 철근조립대가 레일처럼 이동할 수 있다.Here, the reinforcing bar in step b) is a first reinforcing bar having a first reinforcing bar convex portion formed therein, the gap being adjusted using a gap adjusting member, and the first reinforcing bar convex portion of the " The first reinforcing bar support and the first reinforcing bar assembly can be moved like a rail by inserting the first reinforcing bar assembly into the first reinforcing bar assembly fastening groove formed in the reinforcing bar assembly.
여기서, 상기 b) 단계의 철근받침대는 하단부 확장형 제2 철근받침대 볼록부가 형성된 제2 철근받침대로서 간격조절부재를 사용하여 간격을 조절하며, 상기 하단부 확장형 제2 철근받침대 볼록부를 제2 철근조립대에 형성된 제2 철근조립대 체결홈에 삽입함으로써 상기 제2 철근받침대를 제2 철근조립대와 체결시 일체감을 확보하며, 철근 조립 후 제2 철근조립대에서 철근을 분리할 경우, 상기 제2 철근받침대의 하단부와 제2 철근조립대가 맞물려 스토퍼 역할을 하여 제2 철근조립대에서 상기 제2 철근받침대의 이탈을 방지할 수 있다.Here, the reinforcing bar in step b) may be a second reinforcing bar having a convex portion of the lower expandable second reinforcing bar, adjusting the gap using a gap adjusting member, and pressing the convex portion of the lower expanding second reinforcing bar to the second reinforcing bars The second reinforcing bar assembly is inserted into the formed second reinforcing bar assembly engaging groove to secure a sense of unity when the second reinforcing bar assembly is fastened to the second reinforcing bar assembly. When the reinforcing bars are separated from the second reinforcing bar assembly after assembling the reinforcing bars, The second reinforcing bar assembly is engaged with the lower reinforcing bar assembly and serves as a stopper to prevent the second reinforcing bar assembly from being separated from the second reinforcing bar assembly.
삭제delete
삭제delete
여기서, 상기 e) 단계의 PSC 빔 제작대는 상기 철근조립체 세그먼트의 연결 오차를 최소화하도록 직선 거치대로 구성하는 것이 바람직하다.Preferably, the PSC beam manufacturing stage of the step e) is configured as a straight holder so as to minimize a connection error of the reinforcing bar assembly segment.
여기서, 상기 e) 단계의 PSC 빔 제작대는 상기 철근조립체 세그먼트를 직선으로 체결할 수 있는 가이드 프레임 방식의 PSC 빔 제작대이거나 또는 가이드 고정핀을 이용하여 L형 가이드를 고정하는 L형 가이드 방식의 PSC 빔 제작대일 수 있다.Here, the PSC beam production stand of step e) may be a guide frame type PSC beam production stand capable of linearly fastening the steel reinforcing assembly segments or an L-type guide type PSC beam production stand for fixing the L- Beam fabrication unit.
본 발명에 따르면, PSC 교량의 시공을 위한 PSC 빔 제작시, 현장과 떨어진 공장 등의 장소에서 철근조립대를 이용하여 복수의 철근조립체 세그먼트를 제작하여 간편하게 운반할 수 있고, 현장에서 철근조립체 세그먼트를 결합한 철근조립체를 형성한 후에 콘크리트를 타설하고 긴장력을 도입함으로써 PSC 빔을 용이하게 제작할 수 있다.According to the present invention, a plurality of rebar assembly segments can be manufactured and transported using a rebar assembly stand at a place such as a factory apart from the site when manufacturing a PSC beam for constructing a PSC bridge, and the rebar assembly segment The PSC beam can be easily manufactured by pouring concrete and introducing a tension force after forming the combined reinforcing bar assembly.
본 발명에 따르면, 체결블록 또는 철근받침대와 결합하는 철근조립대를 이용하여 철근조립체 세그먼트를 조립함으로써 공장에서 철근조립체 세그먼트를 신속하면서도 정밀하게 조립 제작할 수 있고, 현장에서 철근조립체 세그먼트를 용이하게 연결할 수 있다.According to the present invention, it is possible to quickly and precisely assemble and fabricate the rebar assembly segments in the factory by assembling the rebar assembly segments using the rebar assembly blocks that are coupled to the fastening blocks or the rebar pedestals, have.
본 발명에 따르면, 현장에서의 작업자 투입 및 작업시간을 획기적으로 줄임으로써 공기 단축은 물론, 보다 경제적이면서도 품질이 높은 PSC 빔을 제작할 수 있다.According to the present invention, it is possible to manufacture a PSC beam that is economical as well as high in quality as well as shortening of air by drastically reducing worker input and work time in the field.
도 1의 a)는 일반적인 PSC 빔 교량을 나타내는 측면도이고, 도 1의 b)는 PSC 빔을 나타내는 사시도이다.
도 2는 종래의 기술에 따른 철근콘크리트 빔 내부에 배근되는 철근조립체를 예시하는 도면이다.
도 3은 종래의 기술에 따른 철근조립장치를 나타내는 사시도이다.
도 4는 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 제작되는 PSC 빔을 나타내는 도면이다.
도 5는 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법의 동작흐름도이다.
도 6은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에 적용되는 이동식 철근 조립용 철근조립대를 나타내는 도면이다.
도 7은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에 적용되는 철근조립대와 체결되는 슬롯형 체결블록을 나타내는 도면이다.
도 8은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에 적용되는 철근조립대와 체결되는 하단부 확장형 체결블록을 나타내는 도면이다.
도 9는 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에 적용되는 철근조립대와 체결되는 슬롯형 철근받침대를 나타내는 도면이다.
도 10은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에 적용되는 철근조립대와 체결되는 하단부 확장형 철근받침대를 나타내는 도면이다.
도 11은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에서 상부 매달기 방식의 철근조립체 인양장치를 나타내는 도면이다.
도 12는 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에서 하부 지지 방식의 폐합형 운반 프레임을 나타내는 도면이다.
도 13은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에서 철근조립체 세그먼트 운반 과정을 나타내는 도면이다.
도 14는 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에서 가이드 프레임 방식의 PSC 빔 제작대에 철근조립체 세그먼트를 거치하는 것을 나타내는 단면도이다.
도 15는 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에서 가이드 프레임 방식의 PSC 빔 제작대에 철근조립체 세그먼트를 직선으로 결합하는 것을 나타내는 도면이다.
도 16은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에서 L형 가이드 방식의 PSC 빔 제작대에 철근조립체 세그먼트를 거치하는 것을 나타내는 도면이다.
도 17은 도 16에 도시된 L형 가이드 방식의 PSC 빔 제작대를 구체적으로 나타내는 도면이다.1 (a) is a side view showing a general PSC beam bridge, and Fig. 1 (b) is a perspective view showing a PSC beam.
FIG. 2 is a view illustrating a reinforcing steel assembly that is placed inside a reinforced concrete beam according to a conventional technique.
3 is a perspective view showing a reinforcing bar assembling apparatus according to a conventional technique.
Figure 4 is a view of a PSC beam fabricated to form a rebar assembly by connecting the rebar assembly segments in situ in accordance with an embodiment of the present invention.
5 is an operational flow diagram of a method of fabricating a PSC beam to form a rebar assembly by connecting a rebar assembly segment at a site in accordance with an embodiment of the present invention.
FIG. 6 is a view illustrating a reinforcing bar assembly for a movable reinforcing bar assembly applied to a method of manufacturing a PSC beam, in which a reinforcing bar assembly is formed by connecting reinforcing assembly segments at a site according to an embodiment of the present invention.
FIG. 7 is a view showing a slot-type fastening block which is fastened to a reinforcing bar assembly applied to a method of manufacturing a PSC beam to form a steel frame assembly by connecting the steel frame assembly segments in the field according to an embodiment of the present invention.
FIG. 8 is a view illustrating a lower-end expandable fastening block engaged with a reinforcing bar assembly applied to a method of manufacturing a PSC beam to form a reinforcing bar assembly by connecting the reinforcing bar assembly segments in the field according to an embodiment of the present invention.
FIG. 9 is a view showing a slot-type reinforcing bar supported by a reinforcing bar assembly applied to a method of manufacturing a PSC beam to form a reinforcing bar assembly by connecting the reinforcing bar assembly segments in the field according to an embodiment of the present invention.
FIG. 10 is a view illustrating a lower-end extended reinforcing bar coupled to a reinforcing bar assembly applied to a method of manufacturing a PSC beam to form a reinforcing bar assembly by connecting the reinforcing bar assembly segments in the field according to an embodiment of the present invention.
FIG. 11 is a view showing a device for lifting a reinforcing bar assembly in an upper suspension method in a method of manufacturing a PSC beam, in which a reinforcing bar assembly is formed by connecting reinforcing assembly segments at a site according to an embodiment of the present invention.
FIG. 12 is a view showing a combined transportation frame of a lower support type in a method of manufacturing a PSC beam in which a reinforcing bar assembly is formed by connecting reinforcing assembly segments at a site according to an embodiment of the present invention.
FIG. 13 is a view illustrating a process of transporting a steel bar assembly segment in a PSC beam manufacturing method of forming a steel bar assembly by connecting the steel bar assembly segments in the field according to an embodiment of the present invention.
FIG. 14 is a cross-sectional view illustrating the mounting of a reinforcing bar assembly segment on a guide frame type PSC beam producing stand in a method of manufacturing a reinforcing bar assembly by connecting the reinforcing bar assembly segments in the field according to an embodiment of the present invention.
FIG. 15 is a view illustrating a method of linearly connecting a reinforcing bar assembly segment to a guide frame type PSC beam producing stand in a method of manufacturing a reinforcing bar assembly by connecting reinforcing bar assembly segments in the field according to an embodiment of the present invention.
FIG. 16 is a view showing a step of mounting a reinforcing bar assembly segment on a PSC beam producing stand of an L-shaped guide type in a method of manufacturing a PSC beam by connecting a reinforcing bar assembly segment at a site according to an embodiment of the present invention.
17 is a diagram specifically showing a PSC beam production stand of the L-type guide system shown in Fig. 16. Fig.
아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings, which will be readily apparent to those skilled in the art. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In order to clearly illustrate the present invention, parts not related to the description are omitted, and similar parts are denoted by like reference characters throughout the specification.
명세서 전체에서, 어떤 부분이 어떤 구성요소를 "포함"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다. Throughout the specification, when an element is referred to as " comprising ", it means that it can include other elements as well, without excluding other elements unless specifically stated otherwise.
[철근조립체 세그먼트를 이용하여 제작되는 PSC 빔(100)][
도 4는 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 제작되는 PSC 빔을 나타내는 도면이다.Figure 4 is a view of a PSC beam fabricated to form a rebar assembly by connecting the rebar assembly segments in situ in accordance with an embodiment of the present invention.
도 4의 a)에 도시된 바와 같이, 공장에서 철근조립체 세그먼트(110a, 110b, 110c) 제작하여 운반하고, 이후, 도 4의 b)에 도시된 바와 같이, 현장에서 철근조립체 세그먼트(110a, 110b, 110c)를 연결하여 철근조립체(110)를 형성하며, 이후, 도 4의 c)에 도시된 바와 같이, 현장에서 거푸집을 조립한 후, 콘크리트를 타설하고 긴장력을 도입하여 PSC 빔(100)을 완성한다.As shown in Figure 4a), the steel
본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 제작되는 PSC 빔(100)의 경우, 공장과 같은 특정 장소에서 일정 규격으로 미리 PSC 빔용 철근조립체 세그먼트(110a, 110b, 110c)를 조립하고, 이렇게 제작된 소정의 철근조립체 세그먼트(110a, 110b, 110c)를 현장으로 운반하여 조립을 완료하고, 이후, 거푸집 설치 및 콘크리트 타설, 긴장력 도입으로 PSC 빔(100)을 제작할 수 있다.In the case of a
이하, 도 5 내지 도 17을 참조하여, 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법을 구체적으로 설명한다.5 to 17, a method of manufacturing a PSC beam for forming a reinforcing bar assembly by connecting reinforcing assembly segments at a site according to an embodiment of the present invention will be described in detail.
[현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법][Method of making PSC beam forming reinforcing assembly by connecting reinforcing assembly segments in the field]
도 5는 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법의 동작흐름도이다.5 is an operational flow diagram of a method of fabricating a PSC beam to form a rebar assembly by connecting a rebar assembly segment at a site in accordance with an embodiment of the present invention.
도 5를 참조하면, 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법은, 먼저, 공장에서 철근조립체 세그먼트(110a, 110b, 110c) 제작을 위해 철근조립대(210) 및 철근지지대(220)를 배치한다(S110).Referring to FIG. 5, a PSC beam manufacturing method for connecting a rebar assembly segment at a site according to an exemplary embodiment of the present invention to form a rebar assembly includes firstly assembling the
다음으로, 상기 철근조립대(210)에 체결블록(230) 또는 철근받침대(240)를 체결한다(S120).Next, the tightening block 230 or the reinforcing bar 240 is fastened to the reinforcing bar assembly 210 (S120).
다음으로, 상기 체결블록(230) 또는 철근받침대(240) 상에 상기 철근조립체 세그먼트(110a, 110b, 110c)를 삽입하여 조립한다(S130). 이에 따라, 철근 조립용 철근조립대(210)를 사용하여 소정 규격의 철근조립체 세그먼트(110a, 110b, 110c)를 공장에서 신속하면서도 정밀하게 조립할 수 있다.Next, the reinforcing
다음으로, 철근조립체 세그먼트 운반장치를 이용하여 상기 철근조립체 세그먼트(110a, 110b, 110c)를 현장으로 운반한다(S140). 이때, 상기 철근조립체 세그먼트 운반장치는 공장에서 각각 조립된 철근조립체 세그먼트(110a, 110b, 110c)를 현장으로 안전하게 운반할 수 있다.Next, the steel
다음으로, 현장의 PSC 빔 제작대(290)에 상기 철근조립체 세그먼트(110a, 110b, 110c)를 거치하고, 상기 철근조립체 세그먼트(110a, 110b, 110c)를 연결하여 철근조립체(110)를 형성한다(S150). 즉, 공장에서 미리 제작된 다수의 철근조립체 세그먼트(110a, 110b, 110c)를 현장에 반입하여 현장에서 PSC 빔 제작대(290) 상에서 서로 겹이음하여 원하는 연장 길이를 갖는 철근조립체(110)를 형성할 수 있다.Next, the reinforcing
다음으로, 상기 PSC 빔 제작대(290) 상에 거푸집을 조립하고 콘크리트를 타설한다(S160).Next, the mold is assembled on the PSC
다음으로, 긴장재 정착장치를 설치하고, 긴장력을 도입하여 PSC 빔 교량용 PSC 빔(100)을 완성한다(S170).Next, a tensional material fixing device is installed, and a
따라서 PSC 교량용 PSC 빔(100) 제작시, 기존에는 현장에서 철근 가공 및 조립 등 모든 작업이 이루어지지만, 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법은, 현장과 떨어진 공장 등과 같은 장소에서 소정의 철근조립체 세그먼트(110a, 110b, 110c)를 제작하고, 이를 현장으로 운반하여 철근조립체 세그먼트(110a, 110b, 110c)를 결합하여 철근조립체(110)를 형성함으로써 PSC 빔(100)을 용이하게 제작할 수 있다.Therefore,
한편, 도 6은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에 적용되는 이동식 철근 조립용 철근조립대를 나타내는 도면으로서, 도 6의 a)는 이동식 철근 조립용 철근조립대를 나타내는 사시도이고, 도 6의 b)는 도 6의 a)에 도시된 A 영역을 구체적으로 나타내는 도면이다.6 is a view showing a reinforcing bar assembly for a movable reinforcing bar assembly applied to a method of manufacturing a PSC beam in which a reinforcing bar assembly is formed by connecting reinforcing assembly segments at a site according to an embodiment of the present invention. 6 is a perspective view showing a reinforcing bar assembly for movable rebar assembly, and FIG. 6B is a view specifically showing area A shown in FIG. 6A.
도 6의 a) 및 b)에 도시된 바와 같이, 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에 적용되는 이동식 철근 조립용 철근조립대(210)를 양측에 배치하고, 그 사이에 철근지지대(220)를 배치한 후, 그 상부에 철근을 삽입 체결하여 철근조립체 세그먼트(110a)를 형성하게 된다.6 (a) and 6 (b), a mobile steel reinforcing
이때, 도 6의 b)에 도시된 바와 같이, 양측에 배치된 상기 철근조립대(210)에 체결블록 또는 철근받침대가 삽입되며, 상기 체결블록 또는 철근받침대에 소정 간격마다 형성된 홈에 철근을 삽입하게 된다. 이때, 상기 철근지지대(220)는 철근을 지지하도록 소정 간격으로 배치될 수 있다.6 (b)), a fastening block or a reinforcing bar is inserted into the reinforcing
한편, 도 7은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에 적용되는 철근조립대와 체결되는 슬롯형 체결블록을 나타내는 도면이고, 도 8은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에 적용되는 철근조립대와 체결되는 하단부 확장형 체결블록을 나타내는 도면이다.7 is a view showing a slot type fastening block to be fastened to a reinforcing bar assembly applied to a method of manufacturing a PSC beam to form a steel frame assembly by connecting the steel frame assembly segments in the field according to the embodiment of the present invention. FIG. 5 is a view illustrating a lower end extended type fastening block which is fastened to a reinforcing bar assembly applied to a PSC beam manufacturing method for forming a reinforcing steel assembly by connecting the reinforcing assembly segments at the site according to an embodiment of the present invention.
도 7 및 도 8을 참조하면, 블록 체결식 철근조립장치로서, 1.0~2.0m 정도의 길이를 갖는 제1 및 제2 체결블록(230a, 230b)에 철근 위치(S = 200~400㎜)에 각각 제1 및 제2 철근조립대 체결홈(211a, 211b)을 형성하여 상기 철근조립대(210a, 210b) 길이에 대응하여 소정 개수의 제1 및 제2 체결블록(230a, 230b)을 체결함으로써, 블록 체결 방식의 철근조립장치를 완성한다,Referring to FIGS. 7 and 8, a block-type reinforcing bar assembly device is provided in which first and
이때, 제1 및 제2 체결블록(230a, 230b) 내에서 철근 간격을 설정할 수 있으므로, 별도의 철근 간격 조절장치가 필요하지 않게 되며, 또한, 철근 간격에 따라 1~3개의 체결블록(230a, 230b)을 사용할 수 있다.At this time, since the spacing of the reinforcing bars can be set within the first and second tightening blocks 230a and 230b, a separate reinforcing gap adjusting device is not required, and one to three
도 7은 제1 체결블록(230a)인 슬롯형 체결블록에 "ㄷ"자형 체결블록 볼록부(231a)를 형성하여 제1 철근조립대 체결홈(211a)에 삽입함으로써 제1 체결블록(230a)과 제1 철근조립대(210a)가 레일처럼 이동할 수 있다.7 shows a state in which the "U" shaped fastening block
구체적으로, 도 7의 a)는 제1 철근조립대(210a)에 형성된 제1 철근조립대 체결홈(211a)에 제1 체결블록(230a)인 슬롯형 체결블록을 삽입하는 것을 나타내고, 도 7의 b)는 제1 철근조립대(210a)에 제1 체결블록(230a)이 삽입된 상태를 나타내며, 도 7의 c)는 제1 체결블록(230a)인 슬롯형 체결블록을 구체적으로 나타내고, 도 7의 d)는 도 7의 b)에 도시된 B 영역을 구체적으로 나타낸다.7A shows insertion of a slot-like fastening block as a
또한, 도 8은 제2 체결블록(230b)인 슬롯형 체결블록에 하단의 폭을 넓게 제2 체결블록 볼록부(231b)를 형성하여 제2 철근조립대 체결홈(211b)에 삽입함으로써, 상기 제2 체결블록(230b)과 제2 철근조립대(210b)와 체결시 일체감을 확보할 수 있다. 이때, 철근 조립 후 제2 철근조립대(210b)에서 철근을 분리할 경우, 상기 제2 체결블록(230b)의 하단부와 제2 철근조립대(210b)가 맞물려 스토퍼 역할을 하여 제2 철근조립대(210b)에서 상기 제2 체결블록(230b)의 이탈을 방지할 수 있다.8 shows a state in which the second fastening block
구체적으로, 도 8의 a)는 제2 철근조립대(210b)에 형성된 제2 철근조립대 체결홈(211b)에 제2 체결블록(230b)인 슬롯형 체결블록을 삽입하는 것을 나타내고, 도 8의 b)는 제2 철근조립대(210b)에 제2 체결블록(230b)이 삽입된 상태를 나타내며, 도 8의 c)는 제2 체결블록(230b)인 슬롯형 체결블록을 구체적으로 나타내고, 도 8의 d)는 도 8의 b)에 도시된 C 영역을 구체적으로 나타낸다.Specifically, FIG. 8A shows insertion of a slot-shaped fastening block as a
한편, 도 9는 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에 적용되는 철근조립대와 체결되는 슬롯형 철근받침대를 나타내는 도면이고, 도 10은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에 적용되는 철근조립대와 체결되는 하단부 확장형 철근받침대를 나타내는 도면이다.9 is a view showing a slot-type reinforcing bar supported by a reinforcing bar assembly applied to a method of manufacturing a PSC beam to form a reinforcing bar assembly by connecting the reinforcing bar assembly segments in the field according to an embodiment of the present invention. FIG. 5 is a view illustrating a lower-side expandable reinforcing bar attached to a reinforcing bar assembly applied to a method of manufacturing a PSC beam to form a reinforcing bar assembly by connecting the reinforcing bar assembly segments in the field according to an embodiment of the present invention.
도 9 및 도 10을 참조하면, 간격 조절식 철근조립장치로서, 개개의 철근받침대(240a, 240b)에 별도의 간격조절부재(250)를 연결함으로써, 간격을 고정시킬 수 있고, 이때, 철근 간격에 따라 1~3개의 간격조절부재(250)를 사용할 수 있다.Referring to FIGS. 9 and 10, it is possible to fix the gap by connecting a separate
도 9는 제1 철근받침대(240a)에 "ㄷ"자형 제1 철근받침대 볼록부(241a)를 형성하여 제1 철근조립대 체결홈(211a)에 삽입함으로써 상기 제1 철근받침대(240a)와 제1 철근조립대(210a)가 레일처럼 이동할 수 있다.9 shows a state where the first reinforcing
구체적으로, 도 9의 a)는 제1 철근조립대 체결홈(211a)이 형성된 제1 철근조립대(210a)가 "ㄷ"자형 제1 철근받침대 볼록부(241a)가 형성된 제1 철근받침대(240a)에 삽입되는 것을 나타내며, 도 9의 b)는 제1 철근조립대(210a)에 제1 철근받침대(240a)가 삽입된 상태를 나타내며, 도 9의 c)는 도 9의 a)에 도시된 D 영역을 구체적으로 나타내며, 도 9의 d)는 도 9의 b)에 도시된 E 영역을 구체적으로 나타내며, 제1 철근받침대(240a)가 간격조절부재(250)에 의해 간격이 조절되는 것을 나타낸다.Specifically, FIG. 9A shows a first reinforcing
또한, 도 10은 제2 철근받침대(240b) 하단의 폭을 넓게 하여 제2 철근조립대(210b)와 체결시 일체감을 확보할 수 있다. 이때, 철근 조립 후 제2 철근조립대(210b)에서 철근을 분리할 경우, 상기 제2 철근받침대(240b) 하단부와 상기 제2 철근조립대(210b)가 맞물려 스토퍼 역할을 함으로써 상기 제2 철근조립대(210b)에서 상기 제2 철근받침대(240b)의 이탈을 방지할 수 있다.10, the width of the lower end of the second reinforcing
구체적으로, 도 10의 a)는 제2 철근조립대 체결홈(211b)이 형성된 제2 철근조립대(210b)가 하단부 확장형 제2 철근받침대 볼록부(241b)가 형성된 제2 철근받침대(240b)에 삽입되는 것을 나타내며, 도 10의 b)는 제2 철근조립대(210b)에 제2 철근받침대(240b)가 삽입된 상태를 나타내며, 도 10의 c)는 도 10의 a)에 도시된 F 영역을 구체적으로 나타내며, 도 10의 d)는 도 10의 b)에 도시된 G 영역을 구체적으로 나타내며, 제2 철근받침대(240b)가 간격조절부재(250)에 의해 간격이 조절되는 것을 나타낸다.10A illustrates a second reinforcing
한편, 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에서, 철근조립체 세그먼트 운반장치는 공장에서 제작 조립된 철근조립체 세그먼트(110a, 110b, 110c)를 안전하게 이송차량에 상차하고 운반하여 현장의 PSC 빔 제작대에 하차시킬 수 있다.Meanwhile, in the PSC beam manufacturing method of forming the reinforcing bar assembly by connecting the reinforcing bar assembly segments in the field according to the embodiment of the present invention, the reinforcing bar assembly segment conveying device includes the reinforcing
도 11은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에서 상부 매달기 방식의 철근조립체 인양장치를 나타내는 도면으로서, 도 11의 a)는 철근조립체 세그먼트(110a, 110b, 110c)를 인양하는 철근조립체 인양장치(260)를 나타내며, 도 11의 b)는 도 11의 a)에 도시된 H 영역을 구체적으로 나타내며, 도 11의 c)는 흔들림 방지장치(261)에 삽입된 인양고리(263)를 나타낸다.11 is a view showing an apparatus for lifting a reinforcing bar assembly in an upper suspension manner in a method of manufacturing a PSC beam by connecting reinforcing assembly segments at a site according to an embodiment of the present invention, 11 (b) shows the H region shown in FIG. 11 (a) in detail, and FIG. 11 (c) shows a structure for lifting the rebounding
도 11에 도시된 바와 같이, 상부 매달기 방식의 철근조립체 인양장치(260)는 철근조립체 세그먼트(110a, 110b, 110c)를 상부에 매달아 운반하는 장치로서, 흔들림 방지장치(261), 브레이싱(262), 인양고리(263) 및 인양로프(264)를 구비한다.As shown in FIG. 11, the upper suspension type
상부 매달기 방식의 철근조립체 인양장치(260)는 한 면의 일부가 폐합되지 않는 강재 바(Bar)로 형성되는 흔들림 방지장치(261)에 다수의 인양고리(263)를 삽입 및 이동 설치한 후, 철근조립체 세그먼트(110a, 110b, 110c)를 인양할 수 있다.A plurality of lifting hooks 263 are inserted and moved to the
한편, 도 12는 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에서 하부 지지 방식의 폐합형 운반 프레임을 나타내는 도면으로서, 도 12의 a)는 철근조립체 세그먼트(110a, 110b, 110c)가 철근조립대(210) 및 철근지지대(220) 상에 결합된 것을 나타내고, 도 12의 b)는 철근조립체 운반 프레임(270)을 나타내며, 도 12의 c)는 인양장치(260)를 이용하여 상기 철근조립체 세그먼트(110a, 110b, 110c)가 안착된 철근조립체 운반 프레임(270)을 인양하는 것을 나타낸다.12 is a view showing a combined transportation frame of a lower supporting type in a method of manufacturing a PSC beam in which a reinforcing bar assembly is formed by connecting reinforcing assembly segments at a site according to an embodiment of the present invention. The
도 12에 도시된 바와 같이, 하부 지지 방식의 철근조립체 인양장치는 철근조립체 세그먼트(110a, 110b, 110c)를 하부에서 지지하여 운반하는 철근조립체 운반 프레임(270)으로서, 상기 철근조립대(210) 내측에 배치된 철근지지대(220)를 활용할 수 있다. 즉, 상기 철근조립체 세그먼트(110a, 110b, 110c)의 제작이 완료된 후, 상기 철근지지대(220)를 폐합되게 조립하여 철근조립체 운반 프레임(270)으로 인양할 수 있다. 즉, 철근조립대(210) 내측에 배치된 철근지지대(220) 사이의 브레이싱(271)를 활용하되, 상기 철근지지대(220)와 브레이싱(271) 상면에 철근조립체 세그먼트(110a, 110b, 110c)가 하부지지방식으로 지지되도록 하면서, 철근조립체 세그먼트(110a, 110b, 110c)가 내측에 위치하여 폐합되도록 사각박스체 형태로 조립되고 있음을 알 수 있다.As shown in FIG. 12, the lower supporting type lifting device for lifting a reinforcing bar assembly includes a reinforcing frame
한편, 도 13은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에서 철근조립체 세그먼트 운반 과정을 나타내는 도면이다.FIG. 13 is a view illustrating a process of transporting a steel bar assembly segment in a method of manufacturing a PSC beam to form a steel bar assembly by connecting the steel bar assembly segments in the field according to an embodiment of the present invention.
도 13의 a)는 공장에서 철근조립체 세그먼트(110a, 110b, 110c)를 제작한 후, 철근조립체 운반 프레임(270)으로 인양하여 이송차량(280)에 상차하는 것을 나타내며, 도 13의 b)는 이송차량(280)을 이용하여 현장까지 철근조립체 세그먼트(110a, 110b, 110c)를 이동시키는 것을 나타내고, 도 13의 c)는 현장에 도착한 이송차량(280)에서 PSC 빔 제작대(290)의 소정 위치로 철근조립체 세그먼트(110a, 110b, 110c)를 하차 및 거치하는 것을 나타낸다.Figure 13a shows that the steel
한편, 현장에서 철근조립체 세그먼트(110a, 110b, 110c)를 연결하여 철근조립체(110)를 형성할 경우, 철근조립체 세그먼트(110a, 110b, 110c)의 연결 오차를 최소화하도록 PSC 빔 제작대(290)를 직선 거치대로 구성한다.Meanwhile, when the reinforcing
도 14는 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에서 가이드 프레임 방식의 PSC 빔 제작대에 철근조립체 세그먼트를 거치하는 것을 나타내는 단면도이고, 도 15는 가이드 프레임 방식의 PSC 빔 제작대에 철근조립체 세그먼트를 직선으로 결합하는 것을 나타내는 도면이다.14 is a cross-sectional view showing that a reinforcing bar assembly segment is mounted on a guide frame type PSC beam producing stand in a method of manufacturing a reinforcing bar assembly by connecting the reinforcing bar assembly segments in the field according to the embodiment of the present invention, Is a view showing that the reinforcing assembly segment is linearly coupled to the guide frame type PSC beam producing stand.
도 14 및 도 15에 도시된 바와 같이, 가이드 프레임 방식의 PSC 빔 제작대(290a)는 종방향 각재(291), 횡방향 각재(292), 하부 거푸집용 철판(293) 및 가이드 프레임(294)을 포함하며, 다수의 철근조립체 세그먼트(110a, 110b, 110c)를 직선으로 체결할 수 있다.As shown in Figs. 14 and 15, the PSC
한편, 도 16은 본 발명의 실시예에 따른 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법에서 L형 가이드 방식의 PSC 빔 제작대에 철근조립체 세그먼트를 거치하는 것을 나타내는 도면이고, 도 17은 도 16에 도시된 L형 가이드 방식의 PSC 빔 제작대를 구체적으로 나타내는 도면이다.Meanwhile, FIG. 16 is a view illustrating a method of manufacturing a PSC beam by connecting a reinforcing bar assembly segment at a site according to an embodiment of the present invention, and mounting a reinforcing bar assembly segment on a PSC beam building plate of an L-type guide system And FIG. 17 is a diagram specifically showing a PSC beam production zone of the L-type guide system shown in FIG.
도 16의 a)는 종방향 각재 상에 횡방향 각재를 거치한 것을 나타내며, 도 16의 b)는 횡방향 각재 상에 하부 거푸집용 철판 및 L형 가이드를 설치하는 것을 나타내는 도면이다. 또한, 도 17의 a)는 도 16에 도시된 I 영역의 상세도이고, 도 17의 b)는 측면도이다.Fig. 16 (a) shows a transverse directional beam member mounted on a vertical directional beam member, and Fig. 16 (b) shows the provision of a lower formwork steel plate and an L-shaped guide on a transverse directional beam member. 17A is a detailed view of the I region shown in FIG. 16, and FIG. 17B is a side view.
도 16 및 도 17에 도시된 바와 같이, L형 가이드 방식의 PSC 빔 제작대(290b)는 종방향 각재(291), 횡방향 각재(292), 하부 거푸집용 철판(293), L형 가이드(295) 및 가이드 고정핀(296)을 포함하며, 다수의 철근조립체 세그먼트(110a, 110b, 110c)를 직선으로 체결할 수 있고, 이때, L형 가이드(295)는 가이드 고정핀(296)을 이용하여 고정시킬 수 있다.16 and 17, the PSC
즉, L형 가이드 방식의 PSC 빔 제작대(290b)는 L형 가이드(295) 및 가이드 고정핀(296)을 사용하여 철근조립체 세그먼트110a, 110b, 110c)를 직선으로 정렬할 수 있고, PSC 빔 형성시 피복 두께를 확보할 수 있다.That is, the PSC beam production stand 290b of the L-shaped guide system can linearly align the steel
결국, 본 발명의 실시예에 따르면, PSC 교량의 시공을 위한 PSC 빔 제작시, 현장과 떨어진 공장 등의 장소에서 철근조립대를 이용하여 복수의 철근조립체 세그먼트를 제작하여 간편하게 운반할 수 있고, 현장에서 철근조립체 세그먼트를 결합한 철근조립체를 형성한 후에 콘크리트를 타설하고 긴장력을 도입함으로써 PSC 빔을 용이하게 제작할 수 있다.As a result, according to the embodiment of the present invention, it is possible to manufacture a plurality of reinforcing bar assembly segments by using the reinforcing bar assembly at a place such as a factory apart from the field, and to easily carry the PSC beam for the construction of the PSC bridge, The PSC beam can be easily manufactured by pouring concrete and introducing a tensile force after forming the reinforcing steel assembly in which the reinforcing assembly segments are combined.
또한, 본 발명의 실시예에 따르면, 체결블록 또는 철근받침대와 결합하는 철근조립대를 이용하여 철근조립체 세그먼트를 조립함으로써 공장에서 철근조립체 세그먼트를 신속하면서도 정밀하게 조립 제작할 수 있고, 현장에서 철근조립체 세그먼트를 용이하게 연결할 수 있다. 이에 따라, 현장에서의 작업자 투입 및 작업시간을 획기적으로 줄임으로써 공기 단축은 물론, 보다 경제적이면서도 품질이 높은 PSC 빔을 제작할 수 있다.Also, according to the embodiment of the present invention, it is possible to assemble the rebar assembly segments by using the reinforcing bars assembled with the fastening blocks or the rebar pedestals, so that the rebar assembly segments can be assembled quickly and precisely in the factory, Can be easily connected. Accordingly, it is possible to manufacture a PSC beam which is economical as well as high in quality as well as shortening of air by drastically reducing worker input and work time in the field.
전술한 본 발명의 설명은 예시를 위한 것이며, 본 발명이 속하는 기술분야의 통상의 지식을 가진 자는 본 발명의 기술적 사상이나 필수적인 특징을 변경하지 않고서 다른 구체적인 형태로 쉽게 변형이 가능하다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시예들은 모든 면에서 예시적인 것이며 한정적이 아닌 것으로 이해해야만 한다. 예를 들어, 단일형으로 설명되어 있는 각 구성 요소는 분산되어 실시될 수도 있으며, 마찬가지로 분산된 것으로 설명되어 있는 구성 요소들도 결합된 형태로 실시될 수 있다.It will be understood by those skilled in the art that the foregoing description of the present invention is for illustrative purposes only and that those of ordinary skill in the art can readily understand that various changes and modifications may be made without departing from the spirit or essential characteristics of the present invention. will be. It is therefore to be understood that the above-described embodiments are illustrative in all aspects and not restrictive. For example, each component described as a single entity may be distributed and implemented, and components described as being distributed may also be implemented in a combined form.
본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is defined by the appended claims rather than the detailed description and all changes or modifications derived from the meaning and scope of the claims and their equivalents are to be construed as being included within the scope of the present invention do.
100: PSC 빔
110: 철근조립체
110a, 110b, 110c: 철근조립체 세그먼트
210: 철근조립대
210a: 제1 철근조립대
211a: 제1 철근조립대 체결홈
210b: 제2 철근조립대
211b: 제2 철근조립대 체결홈
220: 철근지지대
230: 체결블록(슬롯형 체결블록)
230a: 제1 체결블록
231a: 제1 체결블록 볼록부
230b: 제2 체결블록
231b: 제2 체결블록 볼록부
240a: 제1 철근받침대
241a: 제1 철근받침대 볼록부
240b: 제2 철근받침대
241b: 제2 철근받침대 볼록부
250: 간격조절부재
260: 철근조립체 인양장치
261: 흔들림 방지부재
262: 브레이싱
263: 인양고리
264: 인양로프
270: 철근조립체 운반 프레임
280: 이송차량
290: PSC 빔 제작대
290a: 제1 PSC 빔 제작대
290b: 제2 PSC 빔 제작대
291: 종방향 각재
292: 횡방향 각재
293: 하부 거푸집용 철판
294: 가이드 프레임
295: L형 가이드
296: 가이드 고정핀100: PSC beam
110: Reinforcing assembly
110a, 110b, 110c: Reinforcing assembly segment
210:
210a: first reinforcing bar assembly
211a: First reinforcing assembly assembly fastening groove
210b: second reinforcing bar assembly
211b: second reinforcing bar assembly fastening groove
220: Reinforcement support
230: fastening block (slot-type fastening block)
230a: first fastening block
231a: first fastening block convex portion
230b: second fastening block
231b: second fastening block convex portion
240a: first reinforcing bar
241a: first reinforcing bar convex portion
240b: second reinforcing bar
241b: second reinforcing bar convex portion
250:
260: Reinforcement assembly lifting device
261:
262: Bracing
263: Lifting ring
264: Lifting rope
270: Reinforcing assembly transport frame
280: Transport vehicle
290: PSC beam production stand
290a: first PSC beam production stand
290b: second PSC beam production stand
291: Longitudinal groove
292:
293: Iron plate for lower formwork
294: Guide frame
295: L type guide
296: Guide pin
Claims (10)
b) 상기 철근조립대(210)에 체결블록(230) 또는 철근받침대(240)를 체결하는 단계;
c) 상기 체결블록(230) 또는 철근받침대(240) 상에 상기 철근조립체 세그먼트(110a, 110b, 110c)를 삽입하여 조립하는 단계;
d) 철근조립체 세그먼트 운반장치를 이용하여 상기 철근조립체 세그먼트(110a, 110b, 110c)를 현장으로 운반하는 단계;
e) 현장의 PSC 빔 제작대(290)에 상기 철근조립체 세그먼트(110a, 110b, 110c)를 거치하고, 상기 철근조립체 세그먼트(110a, 110b, 110c)를 연결하여 철근조립체(110)를 형성하는 단계;
f) 상기 PSC 빔 제작대(290) 상에 거푸집을 조립하고 콘크리트를 타설하는 단계; 및
g) 긴장재 정착장치를 설치하고, 긴장력을 도입하여 PSC 빔(100)을 완성하는 단계를 포함하되,
공장에서 미리 제작된 다수의 철근조립체 세그먼트(110a, 110b, 110c)를 현장에 반입하여 현장에서 PSC 빔 제작대(290) 상에서 서로 겹이음하여 원하는 연장 길이를 갖는 철근조립체(110)를 형성하며,
상기 d) 단계의 철근조립체 세그먼트 운반장치(270)는 하부 지지 방식의 철근조립체 인양장치로서, 상기 철근조립체 세그먼트(110a, 110b, 110c)를 하부에서 지지하여 운반하는 철근조립체 운반 프레임을 이용하며, 상기 철근조립체 운반 프레임(270)은 철근조립대(210) 내측에 배치된 철근지지대(220) 사이의 브레이싱(271)를 활용하되, 상기 철근지지대(220)와 브레이싱(271) 상면에 철근조립체 세그먼트(110a, 110b, 110c)가 하부지지방식으로 지지되도록 하면서, 철근조립체 세그먼트(110a, 110b, 110c)가 내측에 위치하여 폐합되도록 사각박스체 형태로 조립된 것임을 특징으로 하는 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법.a) disposing a reinforcing bar 210 and a reinforcing bar 220 for fabrication of the reinforcing assembly segments 110a, 110b and 110c at the plant;
b) fastening the fastening block 230 or the reinforcing bar 240 to the reinforcing bar assembly 210;
c) inserting and assembling the reinforcing bar assembly segments (110a, 110b, 110c) on the coupling block (230) or the reinforcing bar support (240);
d) transporting said rebar assembly segments (110a, 110b, 110c) to the field using a rebar assembly segment transport device;
e) forming the reinforcing bar assembly 110 by mounting the reinforcing assembly segments 110a, 110b and 110c on the field PSC beam building block 290 and connecting the reinforcing assembly segments 110a, 110b and 110c, ;
f) assembling a mold on the PSC beam manufacturing stand (290) and casting concrete; And
g) installing a tensioning fixture and introducing a tension force to complete the PSC beam 100,
A plurality of prefabricated rebar assembly segments 110a, 110b, 110c are brought into the field and folded together on the PSC beam production stand 290 in situ to form a reinforcing assembly 110 having a desired extension length,
The rebar assembly segment transport device 270 in the step d) is a lower lifting type rebar assembly lifting device. The rebar assembly lifter uses a reinforcing bar assembly carrying frame for supporting and transporting the rebar assembly segments 110a, 110b, and 110c from the bottom, The reinforcing bar assembly carrying frame 270 utilizes a bracing 271 between the reinforcing bar supports 220 disposed inside the reinforcing bar assembly 210 and includes a reinforcing bar assembly 210, (110a, 110b, 110c) are supported in a lower supporting manner and are assembled in the form of a rectangular box so that the reinforcing assembly segments (110a, 110b, 110c) are positioned inside and closed. To form a reinforcing steel assembly.
상기 b) 단계의 체결블록(230)은 슬롯형 제1 체결블록(230a)으로서, "ㄷ"자형 체결블록 볼록부(231a)를 형성하여 제1 철근조립대(210a)에 형성된 제1 철근조립대 체결홈(211a)에 삽입함으로써 제1 체결블록(230a)과 제1 철근조립대(210a)가 레일처럼 이동하는 것을 특징으로 하는 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법.The method according to claim 1,
The fastening block 230 of the step b) is formed as a slot-type first fastening block 230a, and a " C " fastening block convex portion 231a is formed and the first reinforcing bar assembly And the first fastening block 230a and the first reinforcing rod assembly 210a are moved like a rail by inserting the first fastening block 230a and the first reinforcing rod assembly 210a into the fastening groove 211a so as to form a PSC beam Way.
상기 b) 단계의 체결블록(230)은 슬롯형 제2 체결블록(230b)으로서, 상기 제2 체결블록(230b) 하단의 폭이 넓게 제2 체결블록 볼록부(231b)를 형성하여 제2 철근조립대(210b)에 형성된 제2 철근조립대 체결홈(211b)에 삽입함으로써, 상기 제2 체결블록(230b)과 제2 철근조립대(210b)와 체결시 일체감을 확보하며, 철근 조립 후 제2 철근조립대(210b)에서 철근을 분리할 경우, 상기 제2 체결블록(230b)의 하단부와 제2 철근조립대(210b)가 맞물려 스토퍼 역할을 하여 제2 철근조립대(210b)에서 상기 제2 체결블록(230b)의 이탈을 방지하는 것을 특징으로 하는 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법.The method according to claim 1,
The coupling block 230 of the step b) is a slot-type second coupling block 230b and the second coupling block convex portion 231b is formed to have a wide width at the lower end of the second coupling block 230b, Is inserted into the second reinforcing bar assembly coupling groove 211b formed in the assembly base 210b to secure a sense of unity when fastened to the second coupling block 230b and the second reinforcing bar assembly 210b, When separating the reinforcing bar from the two reinforcing bars 210b, the lower end of the second connecting block 230b and the second reinforcing bar assembly 210b are engaged with each other to serve as a stopper, 2 fastening block 230b is prevented from being separated from the reinforcing bar assembly 230b.
상기 b) 단계의 철근받침대(240)는 "ㄷ"자형 제1 철근받침대 볼록부(241a)가 형성된 제1 철근받침대(240a)로서 간격조절부재(250)를 사용하여 간격을 조절하며, 상기 "ㄷ"자형 제1 철근받침대 볼록부(241a)를 제1 철근조립대(210a)에 형성된 제1 철근조립대 체결홈(211a)에 삽입함으로써 상기 제1 철근받침대(240a)와 제1 철근조립대(210a)가 레일처럼 이동하는 것을 특징으로 하는 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법.The method according to claim 1,
The reinforcing bar 240 of the step b) is a first reinforcing bar 240a having a 'C' shaped first reinforcing bar convexity 241a formed therein, and the gap is adjusted using the gap adjusting member 250, Shaped first reinforcing bar convex portion 241a is inserted into the first reinforcing bar assembly coupling groove 211a formed in the first reinforcing bar assembly 210a so that the first reinforcing bar support 240a and the first reinforcing bar assembly 240a ' (210a) is moved like a rail. ≪ RTI ID = 0.0 > 31. < / RTI >
상기 b) 단계의 철근받침대(240)는 하단부 확장형 제2 철근받침대 볼록부(241b)가 형성된 제2 철근받침대(240b)로서 간격조절부재(250)를 사용하여 간격을 조절하며, 상기 하단부 확장형 제2 철근받침대 볼록부(241b)를 제2 철근조립대(210b)에 형성된 제2 철근조립대 체결홈(211b)에 삽입함으로써 상기 제2 철근받침대(240b)를 제2 철근조립대(210b)와 체결시 일체감을 확보하며, 철근 조립 후 제2 철근조립대(210b)에서 철근을 분리할 경우, 상기 제2 철근받침대(240b)의 하단부와 제2 철근조립대(210b)가 맞물려 스토퍼 역할을 하여 제2 철근조립대(210b)에서 상기 제2 철근받침대(240b)의 이탈을 방지하는 것을 특징으로 하는 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법.The method according to claim 1,
The reinforcing bar 240 of the step b) is a second reinforcing bar 240b having a second reinforcing bar protruding portion 241b formed on the lower end of the reinforcing bar 240 and the interval adjusting member 250 is used to adjust the interval, The second reinforcing bar support protrusion 240b is inserted into the second reinforcing bar assembly 210b by inserting the two reinforcing bar protrusion 241b into the second reinforcing bar assembly coupling groove 211b formed in the second reinforcing bar assembly 210b. The lower end of the second reinforcing bar support 240b and the second reinforcing bar assembly 210b are engaged with each other to serve as a stopper when the reinforcing bars are assembled and the reinforcing bars are separated from the second reinforcing bar assembly 210b. And preventing the second reinforcing bar assembly (240b) from being separated from the second reinforcing bar assembly (210b) by connecting the reinforcing bar assembly segments in situ to form a reinforcing bar assembly.
상기 e) 단계의 PSC 빔 제작대(290)는 상기 철근조립체 세그먼트(110a, 110b, 110c)의 연결 오차를 최소화하도록 직선 거치대로 구성하는 것을 특징으로 하는 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법.The method according to claim 1,
The PSC beam production stand 290 of step e) is configured as a straight stand so as to minimize a connection error between the reinforcing assembly segments 110a, 110b and 110c. Forming a PSC beam.
상기 e) 단계의 PSC 빔 제작대(290)는 상기 철근조립체 세그먼트(110a, 110b, 110c)를 직선으로 체결할 수 있는 가이드 프레임(294) 방식의 PSC 빔 제작대(290a)이거나 또는 가이드 고정핀(296)을 이용하여 L형 가이드(295)를 고정하는 L형 가이드 방식의 PSC 빔 제작대(290b)인 것을 특징으로 하는 현장에서 철근조립체 세그먼트를 연결하여 철근조립체를 형성하는 PSC 빔 제작방법.9. The method of claim 8,
The PSC beam manufacturing stand 290 of the step e) may be a PSC beam manufacturing stand 290a of a guide frame 294 type that can linearly fasten the reinforcing bar assembly segments 110a, 110b and 110c, Shaped PSC beam manufacturing stand (290b) for fixing the L-shaped guide (295) by using a plurality of reinforcing bars (296).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020180051823A KR101948026B1 (en) | 2018-05-04 | 2018-05-04 | Pre-stressed concrete (psc) beam producing method for forming steel reinforcement assembly by connecting prefabricated segments of steel reinforcement assembly in construction field |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020180051823A KR101948026B1 (en) | 2018-05-04 | 2018-05-04 | Pre-stressed concrete (psc) beam producing method for forming steel reinforcement assembly by connecting prefabricated segments of steel reinforcement assembly in construction field |
Publications (1)
Publication Number | Publication Date |
---|---|
KR101948026B1 true KR101948026B1 (en) | 2019-05-02 |
Family
ID=66581515
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020180051823A KR101948026B1 (en) | 2018-05-04 | 2018-05-04 | Pre-stressed concrete (psc) beam producing method for forming steel reinforcement assembly by connecting prefabricated segments of steel reinforcement assembly in construction field |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101948026B1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112813836A (en) * | 2020-12-31 | 2021-05-18 | 中铁二十局集团第六工程有限公司 | Cast-in-place box girder construction method |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000104404A (en) * | 1998-09-30 | 2000-04-11 | Mamoru Kuroki | Reinforcement work execution method and temporary reinforcement assembly jig used for the method |
KR100257928B1 (en) | 1998-04-08 | 2000-06-01 | 이태수 | Method for manufacturing a reinforcing bar assembly |
JP2000254747A (en) * | 1999-03-05 | 2000-09-19 | Okumura Corp | REINFORCING BAR PREASSEMBLY OF OUTER SHELL PCa COLUMN AND ASSEMBLING DEVICE |
KR100595376B1 (en) | 1999-04-16 | 2006-07-03 | 정경옥 | Zig assembly for preparing iron bar mesh, process for preparing iron bar mesh using the said zig assembly, and process for construction utilizing the iron bar mesh |
KR20080020727A (en) | 2006-08-29 | 2008-03-06 | 동방엔지니어링 주식회사 | Costruction die for steel reinforcing |
JP2009190820A (en) * | 2008-02-13 | 2009-08-27 | Shimizu Corp | Lifting tool and lifting method of reinforcing bar |
KR101305913B1 (en) | 2011-06-27 | 2013-09-09 | 동도산업 주식회사 | Rebar jig for psm box girder mould |
KR20140017410A (en) * | 2012-07-30 | 2014-02-11 | 주식회사 정우비엔씨 | Steel reinforcement transfer device |
KR20140142555A (en) * | 2013-06-04 | 2014-12-12 | 김근택 | Pre-tension psc girder and its manufacturing method |
KR101565598B1 (en) | 2014-05-30 | 2015-11-03 | 서보산업 주식회사 | An iron bar transporting bracket and method for fiting the same |
KR101692356B1 (en) | 2016-07-22 | 2017-01-17 | 이호석 | Reinforcing bar assembler apparaus using end-lift and reinforcing bar assembling method and concrete beam therewith |
KR101722084B1 (en) | 2016-05-10 | 2017-04-03 | 김범준 | Process of Bar Assembly |
-
2018
- 2018-05-04 KR KR1020180051823A patent/KR101948026B1/en active
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100257928B1 (en) | 1998-04-08 | 2000-06-01 | 이태수 | Method for manufacturing a reinforcing bar assembly |
JP2000104404A (en) * | 1998-09-30 | 2000-04-11 | Mamoru Kuroki | Reinforcement work execution method and temporary reinforcement assembly jig used for the method |
JP2000254747A (en) * | 1999-03-05 | 2000-09-19 | Okumura Corp | REINFORCING BAR PREASSEMBLY OF OUTER SHELL PCa COLUMN AND ASSEMBLING DEVICE |
KR100595376B1 (en) | 1999-04-16 | 2006-07-03 | 정경옥 | Zig assembly for preparing iron bar mesh, process for preparing iron bar mesh using the said zig assembly, and process for construction utilizing the iron bar mesh |
KR20080020727A (en) | 2006-08-29 | 2008-03-06 | 동방엔지니어링 주식회사 | Costruction die for steel reinforcing |
JP2009190820A (en) * | 2008-02-13 | 2009-08-27 | Shimizu Corp | Lifting tool and lifting method of reinforcing bar |
KR101305913B1 (en) | 2011-06-27 | 2013-09-09 | 동도산업 주식회사 | Rebar jig for psm box girder mould |
KR20140017410A (en) * | 2012-07-30 | 2014-02-11 | 주식회사 정우비엔씨 | Steel reinforcement transfer device |
KR20140142555A (en) * | 2013-06-04 | 2014-12-12 | 김근택 | Pre-tension psc girder and its manufacturing method |
KR101565598B1 (en) | 2014-05-30 | 2015-11-03 | 서보산업 주식회사 | An iron bar transporting bracket and method for fiting the same |
KR101722084B1 (en) | 2016-05-10 | 2017-04-03 | 김범준 | Process of Bar Assembly |
KR101692356B1 (en) | 2016-07-22 | 2017-01-17 | 이호석 | Reinforcing bar assembler apparaus using end-lift and reinforcing bar assembling method and concrete beam therewith |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112813836A (en) * | 2020-12-31 | 2021-05-18 | 中铁二十局集团第六工程有限公司 | Cast-in-place box girder construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106906955B (en) | Shear wall integral prefabricated reinforcement mesh structure and construction method thereof | |
KR101692356B1 (en) | Reinforcing bar assembler apparaus using end-lift and reinforcing bar assembling method and concrete beam therewith | |
KR101959333B1 (en) | Pre-stressed concrete (psc) beam producing method for forming steel reinforcement assembly by connecting prefabricated segments of steel reinforcement assembly in construction field | |
JPH11181725A (en) | Method for constructing horizontal beam of main tower made of concrete | |
KR100920202B1 (en) | Connecting Method of Girder with Integrated Slab and Horizontal Moving Method of Girder | |
CN210316690U (en) | Roof elevator machine room structure | |
KR101948026B1 (en) | Pre-stressed concrete (psc) beam producing method for forming steel reinforcement assembly by connecting prefabricated segments of steel reinforcement assembly in construction field | |
KR101665121B1 (en) | Method of manufacturing composite girder for bridge | |
KR100767388B1 (en) | Segment girder construction method for bridge | |
US5976442A (en) | Apparatus and method to manufacture cast panels | |
JP2000045231A (en) | Erection method for arch bridge | |
KR100631029B1 (en) | Precasted concrete plate assembly and the construction method using thereof | |
JP2006063718A (en) | Method of constructing overhung bridge using corrugated steel plate web | |
JP3940212B2 (en) | Construction method of horizontal beams for concrete main tower. | |
CN112681150B (en) | Prefabricated hoisting system for box-type arch bridge and construction method | |
KR102155645B1 (en) | Formwork for the PC Deck that can be placed at the Exact Position, the Manufacturing Method of the PC Deck using the same and the PC Deck | |
KR101291517B1 (en) | Composite girder construction method using t shape steel plate | |
JP6449637B2 (en) | Building construction method | |
KR100597872B1 (en) | Construction method for bridge using a jig apparatus | |
KR102004316B1 (en) | Reinforcing method of concrete slab | |
JP4204603B2 (en) | Construction method of concrete structure | |
KR100403989B1 (en) | Bridge slab construction method and precast concrete plate applied therein | |
KR101907976B1 (en) | Jig bracket for reinforcing bar lifting and moving and reinforcing bar construction method therewith | |
CN113027132A (en) | Concrete stepped pouring method for subway slope section plate | |
CN111778856A (en) | Construction method of main tower steel bar |