KR101897143B1 - The upper structure and a method of capping a continuous barrier wall construction for underground - Google Patents

The upper structure and a method of capping a continuous barrier wall construction for underground Download PDF

Info

Publication number
KR101897143B1
KR101897143B1 KR1020160078618A KR20160078618A KR101897143B1 KR 101897143 B1 KR101897143 B1 KR 101897143B1 KR 1020160078618 A KR1020160078618 A KR 1020160078618A KR 20160078618 A KR20160078618 A KR 20160078618A KR 101897143 B1 KR101897143 B1 KR 101897143B1
Authority
KR
South Korea
Prior art keywords
water
bentonite
cement
wall
mixture
Prior art date
Application number
KR1020160078618A
Other languages
Korean (ko)
Other versions
KR20180000528A (en
Inventor
박헌구
박상혁
Original Assignee
한국농어촌공사
유한회사 대진에스시비
박헌구
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국농어촌공사, 유한회사 대진에스시비, 박헌구 filed Critical 한국농어촌공사
Priority to KR1020160078618A priority Critical patent/KR101897143B1/en
Publication of KR20180000528A publication Critical patent/KR20180000528A/en
Application granted granted Critical
Publication of KR101897143B1 publication Critical patent/KR101897143B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/16Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

본 발명은 종래의 물과 시멘트 및 벤토나이트로 구성된 지중연속차수벽의 상부에 지중연속차수벽 및 제정부의 보호, 보강을 위한 폭 1.2∼1.5m의 캐핑을 시공하여 수리구조물에 대한 차수와 제체 안정성을 동시에 확보하도록 한 지중연속차수벽용 상부캐핑 구조 및 이의 시공방법을 제공하는데 그 목적이 있다.
상기한 목적을 달성하기 위한 본 발명에 따른 지중연속차수벽용 상부캐핑 구조는 소정의 물과 시멘트 및 벤토나이트를 혼합하여 구성된 차수벽(W)에 있어서, 상기 차수벽(W)의 상부에 소정의 폭과 두께 및 길이를 갖는 상부캐핑(T)이 형성됨을 특징으로 한다.
또한, 상기한 목적을 달성하기 위한 본 발명에 따른 지중연속차수벽용 상부캐핑 시공방법은 소정의 물과 시멘트 및 벤토나이트를 혼합하여 차수벽(W)을 시공하는 지중연속차수벽 시공방법에 있어서, 상기 차수벽(W)의 상부의 일정두께를 절취하는 단계; 상기 절취된 차수벽(W)의 양단에 거푸집(F)을 설치하는 단계; 상기 거푸집(F)에 물과 시멘트 및 벤토나이트로 구성된 상부캐핑 혼합물을 타설 및 양생하여 상부캐핑(T)을 형성하는 단계로 이루어짐을 특징으로 한다.
In the present invention, capping of 1.2 to 1.5 m in width is carried out for protecting and reinforcing underground continuous water walls and regulating parts on the upper part of the underground continuous water wall composed of conventional water, cement and bentonite, And an upper capping structure for an underground continuous water wall and a construction method thereof.
To achieve the above object, according to the present invention, there is provided an upper capping structure for an underground continuous water barrier wall, comprising: a water barrier wall formed by mixing predetermined water, cement and bentonite, And a top capping (T) having a length is formed.
According to another aspect of the present invention, there is provided a method for constructing an underground continuous water wall for mixing water with cement and bentonite to construct a water wall W, (W); Installing a mold (F) at both ends of the cut off water wall (W); And forming an upper capping (T) by placing and curing a top capping mixture composed of water, cement and bentonite in the mold (F).

Description

지중연속차수벽용 상부캐핑 구조 및 이의 시공방법{The upper structure and a method of capping a continuous barrier wall construction for underground}BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an upper capping structure for an underground continuous water wall,

본 발명은 지중연속차수벽용 상부캐핑 구조 및 이의 시공방법에 관한 것으로, 특히 수리구조물의 저수지, 하천제방, 해안 방조제, 쓰레기 매립당 등 전연장에 걸쳐 지중연속차수벽 시공 후, 상기 지중연속차수벽 및 제정부의 보호, 보강을 위한 폭 1.2∼1.5m의 캐핑을 시공하는 지중연속차수벽용 상부캐핑 구조 및 이의 시공방법에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an upper capping structure for an underground continuous water wall and a method of constructing the same, and more particularly, to an undercapacity continuous water wall, The present invention relates to an upper capping structure for an underground continuous water barrier wall and a method of constructing the capping structure for capping with a width of 1.2 to 1.5 m for protection and reinforcement of a cap.

여기서, 본 발명은 본 발명의 권리자인 대진SCB가 소유한 등록특허 제10-1179867호를 바탕으로 하여 개량한 발명임을 분명하게 명확하게 밝혀두는 바이다. (기, 여타 현장 시공완료와 동시, 현재 시공중인 현장에서 확인할 수 있다.)Here, the present invention is clearly made clear that the invention is based on the registered patent No. 10-1179867 owned by Daejin SCB, the owner of the present invention. (At the same time as completion of construction of other facilities, you can check it on the site currently under construction.)

일반적으로 차수벽 시공방법은 CIP공법, 고압분사주입(그라우팅)공법, 시트파일공법 등이 사용된다.Generally, a CIP method, a high pressure injection injection (grouting) method, a sheet pile method and the like are used for the water wall construction method.

여기서, 상기 CIP(Cast In Place)공법은 천공기로 지반을 굴착한 후, 상기 굴착공 내에 기조립된 철근 및 조골재를 채우고, 모르타르를 주입하여 현장에서 파일을 시공하는 공법으로 소형장비의 시공이 가능하고, 소음 및 진동이 적고 치환공법으로 강성 및 자립성은 우수하나 차수를 위한 공기 및 공사비가 증가되는 문제가 있다.Here, the CIP (Cast In Place) method is a method in which a foundation is excavated by a boring machine, a pre-assembled reinforced bar and coarse aggregate is filled in the excavation hole, and a mortar is injected to construct a pile on the site. , The noise and vibration are small, and the substitution method is excellent in stiffness and independence, but there is a problem that air for construction and construction cost are increased.

또한, 상기 고압분사주입(그라우팅)공법은 지중에 초고압수의 분사방식을 이용하여 지반을 절삭 파쇄시킴과 동시에 공극에 그라우트재를 충전하는 일종의 유도 주입공법으로 로드 선단에 제트노즐을 장착하여 지반 내에서 노즐이 회전하면 자동으로 일정하게 상승하면서 노즐로부터 고압의 주입재를 수평방향으로 분사하여 지반을 절단형태의 틈을 만들고 그곳에 주입재를 채워 넣는 방법으로 파쇄된 토사와 주입재의 혼합 경화에 의해 원추형의 고결재를 조성하는 공법이다.In addition, the high-pressure injection injection (grouting) method is a kind of induction injection method in which a ground is crushed by using an ultra-high-pressure water injection method in the ground and a cavity is filled with a grout material, and a jet nozzle is mounted on the rod end, The injected material of high pressure is injected horizontally from the nozzle while the nozzle is rotated constantly, and the gap of the cutting form is formed by injecting the injection material in the horizontal direction, and the injection material is filled therein. It is a method to make payment.

상기한 바와 같은 고압분사주입(그라우팅)공법은 지반에 관계없이 모든 토질에 적용할 수 있으나, 부속장비가 많고, 지중에 유속이 있는 자갈 전석층에서는 시공이 어려우며, 특히 시공비가 고가인 문제가 있다.The above-mentioned high-pressure injection injection (grouting) method can be applied to all kinds of soil regardless of the ground, but it is difficult to construct the gravel all-weather stone layer with many attached equipments and the flow rate in the ground, .

그리고 시트파일공법은 시트파일을 연속으로 연결하여 벽체를 형성하는 공법으로 차수성이 높아 연약지반에 적합한 공법이나 다른 공법에 비하여 특히 공사비가 많이 드는 문제점이 있다.In addition, the sheet file method is a method of forming a wall by continuously connecting sheet files, which has a high water repellency and thus has a problem in that the construction cost is particularly high as compared with a construction method suitable for a soft foundation or other construction methods.

이에, 상기한 바와 같은 제문제점을 해결하기 위해 등록특허 10-1179867 암반층 굴착버킷을 이용한 지중 차수벽 시공방법이 제안되었다. In order to solve the above-mentioned problems, a method of constructing an underground water wall using a rock layer excavation bucket has been proposed.

상기한 종래의 암반층 굴착버킷을 이용한 지중 차수벽 시공방법은 대상지반(G)을 심도있게 지질을 조사하여, 이 대상지반(G)이 어떠한 상태인지를 확인하고, 인근에 굴착기, 폰드, 시멘트 사이로, 벤토나이트 저장탱크, 이동식 물저장 탱크, 용적식 펌프, 혼합플랜트 등 각종 장비를 설치하여 지중 차수벽(W) 시공을 위한 준비를 시행하는 단계(S1); 상기 대상지반(G)을 소정의 통체(10)와; 상기 통체(10)의 선단에 다수 개가 일체로 연장 형성되는 삽날(20)과; 상기 통체(10)의 배면에 용접 설치됨과 동시에 첨단 형상으로 형성된 연장스틱(30)으로 구성된 암반층 굴착버킷(E)으로 일정한 폭과 깊이로 굴착하여 트렌치(T)를 형성하는 단계(S2); 상기 트렌치(T)에 벤토나이트(B)를 충전하는 단계(S3); 상기 벤토나이트(B)에 시멘트혼합물(C) 또는 토사혼합물(S)로 구성되는 뒷채움재를 충전하되, 상기 시멘트혼합물(C)은 물 1,000ℓ, 시멘트 200㎏, 벤토나이트 60kg으로 구성하여 충전하고, 상기 토사혼합물(S)은 굴착토사 50∼200㎏에 시멘트 25∼100㎏과 벤토나이트 15∼100㎏으로 구성하고, 이들 구성의 총중량에 물 35%를 첨가하여 제조하여, 이와 같이 제조된 토사혼합물(S)을 충전하는 단계(S4); 상기 뒷채움재를 일정시간 경화시키는 단계(S5)를 순차적으로 시행하여 차수벽(W)을 시공함을 특징으로 한다.In the method of constructing the underground water wall using the conventional rock slab excavation bucket, the geologic structure of the target ground G is investigated in depth to confirm the state of the target ground G, and the vicinity of the excavator, the pond, (S1) of installing various equipment such as a bentonite storage tank, a movable water storage tank, a positive displacement pump, and a mixed plant to prepare for installation of an underground water wall (W); The target ground G is divided into a predetermined cylinder 10; A blades (20) having a plurality of blades extending integrally at the tip of the cylinder (10); A step (S2) of forming a trench (T) by excavating at a predetermined width and depth with a rock layer excavation bucket (E) welded to the back surface of the cylinder (10) and composed of an extensional stick (30) formed in a tip shape; (S3) charging the trench (T) with bentonite (B); Wherein the bentonite (B) is filled with a backfill material composed of a cement mixture (C) or a soil mixture (S), the cement mixture (C) consisting of 1,000 liters of water, 200 kg of cement and 60 kg of bentonite, The above-mentioned gypsum mixture S is prepared by mixing 25 to 100 kg of cement and 15 to 100 kg of bentonite in 50 to 200 kg of excavated soil, adding 35% of water to the total weight of these constituents, S) (S4); And a step S5 of curing the backfill material for a certain period of time to sequentially construct the water-distributing walls W.

상기한 바와 같은 구성으로 이루어진 종래의 암반층 굴착버킷을 이용한 지중 차수벽 시공방법은 지중 차수벽을 시공한다는 측면에서는 별다른 문제점을 발견할 수는 없다.The method of constructing the underground water wall using the conventional rock layer excavation bucket having the above structure can not find any problem in terms of construction of the underground water wall.

그러나, 종래의 암반층 굴착버킷을 이용한 지중 차수벽 시공방법은 시공 후, 지중 차수벽 상부 및 제정부의 보호, 보강할 필요성이 제기되고, 또한 지중 차수벽의 제방침하, 유실, 변형 등이 발생되는 문제점이 있다.However, there is a problem in that a method of constructing an underground water wall using a conventional rock layer excavation bucket is required to protect and reinforce the underwater water wall upper part and the control part after the construction, and also the embankment, loss, and deformation of the underground water wall occur .

등록특허 10-1179867(등록일: 2012년08월30일)Registration No. 10-1179867 (Registration date: August 30, 2012)

이에, 본 발명은 상기한 바와 같은 제문제점을 해결하기 위해 안출된 것으로서, 종래의 물과 시멘트 및 벤토나이트로 구성된 지중연속차수벽의 상부에 지중연속차수벽 및 제정부의 보호, 보강을 제방침하, 유실, 변형 등을 위한 폭 1.2∼1.5m의 캐핑을 시공하여 수리구조물에 대한 차수와 안정성을 동시에 확보하도록 한 지중연속차수벽용 상부캐핑 구조 및 이의 시공방법을 제공하는데 그 목적이 있다.Accordingly, the present invention has been made to solve the above-mentioned problems, and it is an object of the present invention to provide an underground continuous water wall composed of water, cement and bentonite, A capping structure having a width of 1.2 to 1.5 m for deformation and the like, so that the degree and stability of the hydraulic structure can be ensured at the same time, and an object of the present invention is to provide a construction method of the upper capping structure.

상기한 목적을 달성하기 위한 본 발명에 따른 지중연속차수벽용 상부캐핑 구조는 소정의 물과 시멘트 및 벤토나이트를 혼합하여 구성된 차수벽(W)에 있어서, 상기 차수벽(W)의 상부에는 폭 1.5m 및 두께 0.5m, 길이는 1m 이상을 갖는 상부캐핑(T)이 형성되되, 상기 차수벽(W)은 물과 시멘트 및 벤토나이트의 혼합물로 구성되고, 상기 혼합물의 배합비는 물 1000ℓ에 시멘트 200㎏과 벤토나이트 60㎏으로 구성되며, 상기 상부캐핑(T)은 물과 시멘트 및 벤토나이트의 혼합물로 구성되고, 상기 혼합물의 배합비는 물 1000ℓ에 시멘트 400㎏과 벤토나이트 60㎏으로 구성되며, 상기 상부캐핑(T)은 하부의 차수벽(W)에 비하여 강도가 적어도 2배 이상으로 구성되며, 상기 상부캐핑(T)의 상부를 일정한 폭 및 두께로 완성 후, 일정 높이로 복토하여 원 지반 상태가 유지되도록 구성됨을 특징으로 한다.In order to achieve the above object, an upper capping structure for an underground continuous water barrier wall according to the present invention is a water barrier wall W formed by mixing predetermined water, cement and bentonite, wherein an upper portion of the water barrier wall W has a width of 1.5 m and a thickness And a length of at least 1 m. The water wall W is composed of a mixture of water, cement and bentonite, and the blending ratio of the mixture is 200 liters of water, 60 kg of bentonite And the upper capping T is composed of a mixture of water, cement and bentonite, and the mixing ratio of the mixture is composed of 400 kg of cement and 60 kg of bentonite in 1000 L of water, The upper capping T is formed to have a predetermined width and thickness, and then the surface of the upper capping T is covered with a certain height to maintain the state of the ground .

또한, 상기한 목적을 달성하기 위한 본 발명에 따른 지중연속차수벽용 상부캐핑 시공방법은 소정의 물과 시멘트 및 벤토나이트를 혼합하여 차수벽(W)을 시공하는 지중연속차수벽 시공방법에 있어서, 시멘트 및 벤토나이트의 혼합물로 구성되고, 상기 혼합물의 배합비는 물 1000ℓ에 시멘트 200㎏과 벤토나이트 60㎏으로 구성된 차수벽용 혼합물로 차수벽(W)을 시공하는 단계; 상기 차수벽(W)의 상부의 일정두께 40㎝를 절취하는 단계; 상기 절취된 차수벽(W)의 양단에 거푸집(F)을 설치하는 단계; 상기 거푸집(F)에 물과 시멘트 및 벤토나이트의 혼합물로 구성되고, 상기 혼합물의 배합비는 물 1000ℓ에 시멘트 400㎏과 벤토나이트 60㎏으로 구성된 상부캐핑 혼합물을 타설 및 양생시켜 폭 1.5m 및 두께 0.5m로 구성되고, 길이는 1m 이상으로 하부의 차수벽(W)에 비하여 강도가 적어도 2배 이상으로 구성된 상부캐핑(T)을 형성하는 단계; 상기 상부캐핑(T)의 상부를 일정한 폭 및 두께로 성토하는 단계로 이루어짐을 특징으로 한다. In accordance with another aspect of the present invention, there is provided a method of constructing an underground continuous water wall for mixing water, cement and bentonite to form a water wall W, , And the mixing ratio of the mixture is set to 1000 L of water, and a water wall W is formed as a mixture for a water wall consisting of 200 kg of cement and 60 kg of bentonite; Cutting a predetermined thickness of 40 cm on the upper part of the water wall W; Installing a mold (F) at both ends of the cut off water wall (W); The mixture of water, cement and bentonite in the mold (F) was blended with a mixture of cement and bentonite in 1000 liters of water. The upper capping mixture was poured and cured to have a width of 1.5 m and a thickness of 0.5 m Forming a top capping (T) having a length of at least 1 m and a strength at least two times higher than that of the lower wall (W); And filling the upper portion of the upper capping T with a predetermined width and thickness.

즉, 본 발명은 기존 지중 차수벽 상부를 일정부분 절취함과 동시에 차후 시공되는 상부캐핑과 재료분리 없이(차수벽+상부캐핑) 일체화 되도록 함을 특징으로 한다.That is, the present invention is characterized in that the upper part of the existing ground water wall is partially cut off, and the upper capping is integrated with the subsequent upper capping without separating the material (water wall + upper capping).

이상에서 설명한 바와 같이, 본 발명에 따른 지중연속차수벽용 상부캐핑 구조 및 이의 시공방법은 지중연속차수벽 및 제정부의 보호, 보강을 위한 상부캐핑에 의해 영구적인 벽체 시공이 가능하다.As described above, the upper capping structure for underground continuous water barrier wall and the construction method thereof according to the present invention are capable of permanent wall construction by the upper capping for protection and reinforcement of underground continuous water wall and regulating part.

도 1은 종래의 암반층 굴착버킷을 도시한 사시도,
도 2는 종래의 암반층 굴착버킷을 이용하여 지중 차수벽 시공을 위한 기본 개념도,
도 3은 종래의 암반층 굴착버킷을 이용하여 지중 차수벽을 시공하는 과정을 도시한 공정도,
도 4는 종래의 암반층 굴착버킷을 이용하여 시공된 차수벽을 도시한 예시도,
도 5는 본 발명에 따른 지중연속차수벽용 상부캐핑을 도시한 예시도,
도 6a ∼ 6d는 본 발명에 따른 지중연속차수벽용 상부캐핑을 시공하는 과정을 도시한 공정도.
1 is a perspective view showing a conventional rock layer excavation bucket,
2 is a basic conceptual diagram for constructing an underground water wall using a conventional rock layer excavation bucket,
3 is a process diagram showing a process of constructing an underground water wall using a conventional rock layer excavation bucket,
FIG. 4 is an exemplary view showing an installed water wall constructed using a conventional rock layer excavation bucket,
Fig. 5 is an illustration showing an upper capping for an underground continuous water barrier wall according to the present invention,
6A to 6D are process drawings showing a process of constructing upper capping for an underground continuous water wall according to the present invention.

이하, 본 발명을 첨부한 예시도면을 참조하여 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

도 5는 본 발명에 따른 지중연속차수벽용 상부캐핑을 도시한 예시도이다.5 is an exemplary view showing top capping for an underground continuous water barrier wall according to the present invention.

이 도면에 도시된 바와 같이, 본 발명에 따른 지중연속차수벽용 상부캐핑 구조는 소정의 물과 시멘트 및 벤토나이트를 혼합하여 구성된 차수벽(W)에 있어서, 상기 차수벽(W)의 상부에 소정의 폭과 두께 및 길이를 갖는 상부캐핑(T)이 형성된다.As shown in this drawing, the upper capping structure for an underground continuous water barrier wall according to the present invention is a water barrier wall W constructed by mixing predetermined water, cement and bentonite, and has a predetermined width An upper capping T having a thickness and a length is formed.

여기서, 상기한 차수벽(W)은 본 발명의 선행문헌인 등록특허 제10-1179867호에 기재되어 있음으로 더 이상의 설명은 생략한다.Here, the above-mentioned water barrier wall W is described in the prior art document 10-1179867 of the present invention, and the further explanation will be omitted.

다만, 본 발명에 따른 지중연속차수벽용 상부캐핑 구조는 종래의 차수벽에 상부캐핑을 시공한 구조 및 방법을 그 특허의 대상으로 한다.However, the upper capping structure for an underground continuous water barrier wall according to the present invention is a structure and a method for applying upper capping to a conventional water barrier wall.

여기서, 상기 차수벽(W)은 물과 시멘트 및 벤토나이트의 혼합물로 구성되고, 상기 혼합물의 배합비는 물 1000ℓ에 시멘트 200㎏과 벤토나이트 60㎏으로 구성된다.Here, the water wall W is composed of a mixture of water, cement and bentonite, and the blending ratio of the mixture is composed of 200 liters of cement and 60 kg of bentonite in 1000 liters of water.

또한, 상기 차수벽(W) 상에 타설되는 상부캐핑(T)은 물과 시멘트 및 벤토나이트의 혼합물로 구성되고, 상기 혼합물의 배합비는 물 1000ℓ에 시멘트 400㎏과 벤토나이트 60㎏으로 구성된다.Also, the upper capping T placed on the water wall W is composed of a mixture of water, cement and bentonite, and the blending ratio of the mixture is composed of 400 kg of cement and 60 kg of bentonite in 1000 L of water.

즉, 상기 상부캐핑(T)은 하부의 차수벽(W)에 비하여 강도가 적어도 2배 이상으로 구성된다.That is, the upper capping T has a strength at least twice as high as that of the lower wall W.

또한, 상기 상부캐핑(T)의 제원은 폭 1.5m 및 두께 0.5m로 구성되고, 길이는 1m 이상으로 구성된다.The upper capping T is made of 1.5 m wide and 0.5 m thick and has a length of 1 m or more.

이하, 상기한 바와 같은 구성으로 이루어진 본 발명에 따른 지중연속차수벽용 상부캐핑을 시공에 대해 설명한다.Hereinafter, the construction of the upper capping for an underground continuous water barrier wall constructed as described above according to the present invention will be described.

도 6a∼6d는 본 발명에 따른 지중연속차수벽용 상부캐핑을 시공하는 과정을 도시한 공정도이다.6A to 6D are process drawings illustrating a process of constructing upper capping for an underground continuous water barrier wall according to the present invention.

이들 도면에 도시된 바와 같이, 본 발명에 따른 지중연속차수벽용 상부캐핑 시공방법은 소정의 물과 시멘트 및 벤토나이트를 혼합하여 차수벽(W)을 시공하는 지중연속차수벽 시공방법에 있어서, 상기 차수벽(W)의 상부의 일정두께를 절취하는 단계; 상기 절취된 차수벽(W)의 양단에 거푸집(F)을 설치하는 단계; 상기 거푸집(F)설치 후 물과 시멘트 및 벤토나이트로 구성된 상부캐핑 혼합물을 타설 및 양생하여 상부캐핑(T)을 형성하는 단계로 이루어진다.As shown in these drawings, the method of constructing the upper capping for underground continuous water barrier wall according to the present invention is a method for constructing an underground continuous water barrier wall in which predetermined water, cement and bentonite are mixed to construct a water barrier wall W, Cutting a predetermined thickness of the upper portion of the substrate; Installing a mold (F) at both ends of the cut off water wall (W); After the mold (F) is installed, an upper capping mixture composed of water, cement and bentonite is placed and cured to form an upper capping (T).

여기서, 상기한 차수벽(W) 시공은 본 발명의 선행문헌인 등록특허 제10-1179867호에 기재되어 있음으로 더 이상의 설명은 생략한다.Here, the construction of the above-mentioned water-bearing wall W is described in the prior art document 10-1179867 of the present invention, and the further explanation will be omitted.

다만, 상기 차수벽(W) 시공시, 본 발명에서는 차수벽(W)의 재료는 시멘트 및 벤토나이트의 혼합물로 구성되고, 상기 혼합물의 배합비는 물 1000ℓ에 시멘트 200㎏과 벤토나이트 60㎏으로 구성된다.However, at the time of construction of the water barrier wall W, in the present invention, the material of the water barrier wall W is composed of a mixture of cement and bentonite, and the blending ratio of the mixture is composed of 200 kg of cement and 60 kg of bentonite in 1000 L of water.

또한, 상기 상부캐핑(T)은 물과 시멘트 및 벤토나이트의 혼합물로 구성되고, 상기 혼합물의 배합비는 물 1000ℓ에 시멘트 400㎏과 벤토나이트 60㎏으로 구성된다.Also, the upper capping T is composed of a mixture of water, cement and bentonite, and the blending ratio of the mixture is composed of 400 kg of cement and 60 kg of bentonite in 1000 L of water.

즉, 상기 상부캐핑(T)은 하부의 차수벽(W)에 비하여 강도가 적어도 2배 이상으로 구성된다.That is, the upper capping T has a strength at least twice as high as that of the lower wall W.

그리고, 상기 상부캐핑(T)의 제원은 폭 1.5m 및 두께 0.5m로 구성되고, 길이는 전체 연장길이로 구성된다.The upper capping T has a width of 1.5 m and a thickness of 0.5 m, and the length of the upper capping T is a total length of the extension.

한편, 상기 상부캐핑(T)의 상부를 일정한 폭 및 두께로 완성 후 일정 높이로 복토하여 원 지반 상태를 유지한다.On the other hand, the upper portion of the upper capping T is finished to have a certain width and thickness, and is then covered with a certain height to maintain the ground state.

즉, 본 발명에 따른 지중연속차수벽용 상부캐핑 시공방법은 시멘트 및 벤토나이트의 혼합물로 구성되고, 상기 혼합물의 배합비는 물 1000ℓ에 시멘트 200㎏과 벤토나이트 60㎏으로 구성된 차수벽용 혼합물로 차수벽(W)을 시공한다.That is, the upper capping method for underground continuous water wall according to the present invention is composed of a mixture of cement and bentonite, and the mixing ratio of the mixture is 1000 l of water, and is mixed with 200 kg of cement and 60 kg of bentonite. Construction.

이어서, 도 6a에 도시된 바와 같이, 상기 차수벽(W)의 상부의 일정두께 약 40㎝를 절취한다.Subsequently, as shown in FIG. 6A, a predetermined thickness of about 40 cm on the upper part of the water wall W is cut.

이어서, 도 6b에 도시된 바와 같이, 상기 절취된 차수벽(W)의 양단에 거푸집(F)을 설치한다.Subsequently, as shown in FIG. 6B, a mold F is installed at both ends of the cut off water wall W.

이어서, 도 6c에 도시된 바와 같이, 상기 거푸집(F) 내에 물과 시멘트 및 벤토나이트의 혼합물로 구성되고, 상기 혼합물의 배합비는 물 1000ℓ에 시멘트 400㎏과 벤토나이트 60㎏으로 구성된 상부캐핑 혼합물을 타설한다.Next, as shown in FIG. 6C, the mold F is composed of a mixture of water, cement and bentonite, and the mixture ratio of the mixture is 1000 liters of water, and a top capping mixture composed of 400 kg of cement and 60 kg of bentonite is laid .

이어서, 도 6d에 도시된 바와 같이, 상기 상부캐핑 혼합물을 양생시킨 후, 거푸집을 탈형하면, 폭 1.5m 및 두께 0.5m로 구성되고, 길이는 전 연장으로 구성된 상부캐핑(T)을 형성한다.Then, as shown in Fig. 6D, after curing the upper capping mixture, the mold is demoulded to form a top capping T consisting of 1.5 m wide and 0.5 m thick, the length of which is a full extension.

이어서, 상기 상부캐핑(T)의 완료 후 상부면을 현지토를 이용하여 복토하여 원지반 상태로 유지한다.After completion of the upper capping T, the upper surface is covered with a local soil so as to be maintained in a ground state.

이상에서 설명한 바와 같이, 본 발명에 따른 지중연속차수벽용 상부캐핑 시공방법은 종래의 물과 시멘트 및 벤토나이트로 구성된 지중연속차수벽의 상부에 지중연속차수벽 및 제정부의 보호(침하, 유실, 변형 등), 보강을 위한 폭 1.2∼1.5m의 캐핑을 시공하여 수리구조물에 대한 차수와 안정성을 동시에 확보할 수 있는 작용효과가 있다.As described above, the upper capping construction method for an underground continuous water barrier wall according to the present invention is characterized in that protection (subsidence, loss, deformation, etc.) of an underground continuous water barrier wall and a damper is performed on an upper part of an underground continuous water barrier wall composed of water, cement and bentonite, , And capping with a width of 1.2 to 1.5 m for reinforcement is installed to secure the degree and stability of the hydraulic structure at the same time.

본 발명의 명세서에 기재한 바람직한 실시예는 예시적인 것으로서 한정적인 것은 아니며, 본 발명의 범위는 첨부된 특허청구범위에 의해서 나타나 있고, 그들 특허청구범위의 의미중에 들어가는 모든 변형예는 본 발명에 포함되는 것이다.The preferred embodiments described in the specification of the present invention are intended to be illustrative, not limiting, and the scope of the present invention is indicated by the appended claims, and all modifications that come within the meaning of the claims are included in the present invention. .

10: 통체 20: 삽날
30: 연장스틱 B: 벤토나이트
C: 시멘트혼합물 E: 굴착버킷
F: 거푸집 G: 지반
S: 토사혼합물 T: 상부캐핑
W: 차수벽
10: cylinder 20: blade
30: Extension stick B: Bentonite
C: Cement mixture E: Excavation bucket
F: Form G: Ground
S: Soil mixture T: Upper capping
W:

Claims (7)

소정의 물과 시멘트 및 벤토나이트를 혼합하여 구성된 차수벽(W)에 있어서,
상기 차수벽(W)의 상부에는 폭 1.5m 및 두께 0.5m, 길이는 1m 이상을 갖는 상부캐핑(T)이 형성되되,
상기 차수벽(W)은 물과 시멘트 및 벤토나이트의 혼합물로 구성되고,
상기 혼합물의 배합비는 물 1000ℓ에 시멘트 200㎏과 벤토나이트 60㎏으로 구성되며,
상기 상부캐핑(T)은 물과 시멘트 및 벤토나이트의 혼합물로 구성되고,
상기 혼합물의 배합비는 물 1000ℓ에 시멘트 400㎏과 벤토나이트 60㎏으로 구성되며,
상기 상부캐핑(T)은 하부의 차수벽(W)에 비하여 강도가 적어도 2배 이상으로 구성되며,
상기 상부캐핑(T)의 상부를 일정한 폭 및 두께로 완성 후, 일정 높이로 복토하여 원 지반 상태가 유지되도록 구성됨을 특징으로 하는 지중연속차수벽용 상부캐핑구조.
In a water-receiving wall (W) formed by mixing predetermined water with cement and bentonite,
An upper capping T having a width of 1.5 m and a thickness of 0.5 m and a length of 1 m or more is formed on the upper part of the water wall W,
The water wall W is composed of a mixture of water, cement and bentonite,
The compounding ratio of the mixture is composed of 1000 kg of water, 200 kg of cement and 60 kg of bentonite,
The upper capping (T) consists of a mixture of water, cement and bentonite,
The blending ratio of the mixture is composed of 1000 kg of water, 400 kg of cement and 60 kg of bentonite,
The upper capping T has a strength at least twice as high as that of the lower wall W,
Wherein an upper portion of the upper capping (T) is finished to have a predetermined width and thickness, and is then covered with a predetermined height to maintain the original ground state.
삭제delete 삭제delete 소정의 물과 시멘트 및 벤토나이트를 혼합하여 차수벽(W)을 시공하는 지중연속차수벽 시공방법에 있어서,
시멘트 및 벤토나이트의 혼합물로 구성되고, 상기 혼합물의 배합비는 물 1000ℓ에 시멘트 200㎏과 벤토나이트 60㎏으로 구성된 차수벽용 혼합물로 차수벽(W)을 시공하는 단계;
상기 차수벽(W)의 상부의 일정두께 40㎝를 절취하는 단계;
상기 절취된 차수벽(W)의 양단에 거푸집(F)을 설치하는 단계;
상기 거푸집(F)에 물과 시멘트 및 벤토나이트의 혼합물로 구성되고, 상기 혼합물의 배합비는 물 1000ℓ에 시멘트 400㎏과 벤토나이트 60㎏으로 구성된 상부캐핑 혼합물을 타설 및 양생시켜 폭 1.5m 및 두께 0.5m로 구성되고, 길이는 1m 이상으로 하부의 차수벽(W)에 비하여 강도가 적어도 2배 이상으로 구성된 상부캐핑(T)을 형성하는 단계;
상기 상부캐핑(T)의 상부를 일정한 폭 및 두께로 성토하는 단계로 이루어짐을 특징으로 하는 지중연속차수벽용 상부캐핑 시공방법.
A method of constructing an underground continuous water wall (W) by mixing predetermined water, cement and bentonite to construct a water wall (W)
A mixture of cement and bentonite, and the mixing ratio of the mixture is in the range of 1000 L of water, and the water wall W is formed as a mixture for a water wall consisting of 200 kg of cement and 60 kg of bentonite;
Cutting a predetermined thickness of 40 cm on the upper part of the water wall W;
Installing a mold (F) at both ends of the cut off water wall (W);
The mixture of water, cement and bentonite in the mold (F) was blended with a mixture of cement and bentonite in 1000 liters of water. The upper capping mixture was poured and cured to have a width of 1.5 m and a thickness of 0.5 m Forming a top capping (T) having a length of at least 1 m and a strength at least two times higher than that of the lower wall (W);
And filling the upper portion of the upper capping (T) with a predetermined width and thickness.
삭제delete 삭제delete 삭제delete
KR1020160078618A 2016-06-23 2016-06-23 The upper structure and a method of capping a continuous barrier wall construction for underground KR101897143B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160078618A KR101897143B1 (en) 2016-06-23 2016-06-23 The upper structure and a method of capping a continuous barrier wall construction for underground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160078618A KR101897143B1 (en) 2016-06-23 2016-06-23 The upper structure and a method of capping a continuous barrier wall construction for underground

Publications (2)

Publication Number Publication Date
KR20180000528A KR20180000528A (en) 2018-01-03
KR101897143B1 true KR101897143B1 (en) 2018-09-11

Family

ID=61002369

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160078618A KR101897143B1 (en) 2016-06-23 2016-06-23 The upper structure and a method of capping a continuous barrier wall construction for underground

Country Status (1)

Country Link
KR (1) KR101897143B1 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007231552A (en) * 2006-02-28 2007-09-13 Sumitomo Forestry Co Ltd Construction method of foundation pile using recycled electric pole

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3447529B2 (en) * 1996-12-24 2003-09-16 清水建設株式会社 How to fill the cavity
KR101179867B1 (en) 2011-11-29 2012-09-06 유한회사 대진기건 bedrock excavation buckets and underground curtain wall construction method using the same
KR20140053485A (en) * 2012-10-26 2014-05-08 한국파라마운트 주식회사 Paramat and waterproofing method using it

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007231552A (en) * 2006-02-28 2007-09-13 Sumitomo Forestry Co Ltd Construction method of foundation pile using recycled electric pole

Also Published As

Publication number Publication date
KR20180000528A (en) 2018-01-03

Similar Documents

Publication Publication Date Title
JP6166264B2 (en) How to build a retaining wall
KR101545307B1 (en) Construction method of complex temporary facility with bottom grouting for weak ground
KR100762991B1 (en) Precast piling method injected with high-strength mortar
CN107740434B (en) Construction method for waterproof curtain of foundation pit with dam for broken sand pebbles and dolomite
CN105569071B (en) A kind of slip casting under water of cement-based material or mud jacking block ground mass foundation construction
JP5615236B2 (en) Shaft construction method and shaft structure of inclined ground
CN206070508U (en) Device for reinforcing foundation
CN108571000A (en) The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river
CN101008178B (en) Soft base processing construction process using excavating and stirring method
CN114575355A (en) Soil protection and descent construction method
KR102173079B1 (en) Composite phc pile for soil retaining wall
CN104328797B (en) High slope large curvy wall building construction engineering method
KR101372182B1 (en) Pre-support tunneling reinforced by in-situ soil mixed with cement
KR102113291B1 (en) Soil retaining wall using phc pile and construction method thererof
KR101897143B1 (en) The upper structure and a method of capping a continuous barrier wall construction for underground
KR101267688B1 (en) The shore protection construction method using a precast finish panel
KR101021913B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR100483350B1 (en) In place assembling top blocks and their reinforced complex foundation method
KR940002457B1 (en) Method and apparatus for increasing bearing capacity of soft soil and constructing cutoff wall
KR101179867B1 (en) bedrock excavation buckets and underground curtain wall construction method using the same
KR100948060B1 (en) Constructing method for arranging river bank using steel casing retaining wall
Andromalos et al. The application of various deep mixing methods for excavation support systems
JP4020858B2 (en) Manufacturing method for underground structures
JP6869862B2 (en) Wall construction method and wall
CN112176944A (en) Construction method of hydrophilic platform revetment structure

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E601 Decision to refuse application
J201 Request for trial against refusal decision
J301 Trial decision

Free format text: TRIAL NUMBER: 2017101000552; TRIAL DECISION FOR APPEAL AGAINST DECISION TO DECLINE REFUSAL REQUESTED 20170202

Effective date: 20180807

S901 Examination by remand of revocation
GRNO Decision to grant (after opposition)
GRNT Written decision to grant