KR101783439B1 - Stability apparatus for ground having prestressed stiffener - Google Patents

Stability apparatus for ground having prestressed stiffener Download PDF

Info

Publication number
KR101783439B1
KR101783439B1 KR1020160145162A KR20160145162A KR101783439B1 KR 101783439 B1 KR101783439 B1 KR 101783439B1 KR 1020160145162 A KR1020160145162 A KR 1020160145162A KR 20160145162 A KR20160145162 A KR 20160145162A KR 101783439 B1 KR101783439 B1 KR 101783439B1
Authority
KR
South Korea
Prior art keywords
thread
stiffener
ground
insertion hole
guide member
Prior art date
Application number
KR1020160145162A
Other languages
Korean (ko)
Inventor
김철환
김중석
김중영
Original Assignee
주식회사 스팅이앤씨
김철환
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 스팅이앤씨, 김철환 filed Critical 주식회사 스팅이앤씨
Priority to KR1020160145162A priority Critical patent/KR101783439B1/en
Application granted granted Critical
Publication of KR101783439B1 publication Critical patent/KR101783439B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • E02D5/801Ground anchors driven by screwing
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/15Geometrical or physical properties including at least a hinge
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1671Shapes helical or spiral
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0034Steel; Iron in wire form
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

The present invention relates to a ground reinforcing apparatus using a prestressed stiffener which maximizes a restricting force with respect to displacement of the ground; thereby preventing an accident due to falling rocks due to a collapse or sliding of the ground. According to an embodiment of the present invention, the ground reinforcing apparatus using the prestressed stiffener comprises: a stiffener, a traction part, an expansion part, and a fixated part. The stiffener has a first screw thread formed on an outer circumference of a front end thereof and has a second screw thread formed on the outer circumference of a rear end thereof. The traction part has a coupling member having a third screw thread formed on an inner circumference of a front side thereof to be coupled to the second screw thread through a screw; has a sawtooth type-multistage expansion guide member formed on a rear side thereof having a conical shape; and has a fourth screw thread formed on the outer circumference between the coupling member and the sawtooth type-multistage expansion guide member. The expansion part is positioned outside the sawtooth type-multistage expansion guide member, and has a multi-expansion sawtooth groove formed on the inner circumference thereof in such a manner to be expanded in a multi-stage as approaching from the front side to the rear side and in contact with the sawtooth type-multistage expansion guide member, and has a plurality of grip protrusions formed on the outer circumference thereof to protrude in a direction of the fourth screw thread and inserted and fixated to an insertion hole. The fixed part has a fifth screw thread formed on the inner circumference thereof to selectively be coupled to the fourth screw thread through a screw in a state where the traction part penetrates the inside thereof to be positioned, and is connected by the sawtooth type-multistage expansion guide member and a connector.

Description

프리스트레스 보강재를 이용한 지반보강장치{STABILITY APPARATUS FOR GROUND HAVING PRESTRESSED STIFFENER}BACKGROUND OF THE INVENTION Field of the Invention [0001] The present invention relates to a ground reinforcement for a prestress reinforcement,

개시된 내용은 지반의 붕괴 및 낙석방지와 터널굴착면의 내부단면형성을 위한 보강공사에 사용되는 프리스트레스 보강재를 이용한 지반보강장치에 관련된다.The disclosed contents relate to a ground reinforcement apparatus using a prestressed stiffener used for reinforcement work for preventing the collapse of the ground and preventing the fall of the ground and forming the inner section of the tunnel excavation surface.

본 명세서에서 달리 표시되지 않는 한, 이 섹션에 설명되는 내용들은 이 출원의 청구항들에 대한 종래 기술이 아니며, 이 섹션에 포함된다고 하여 종래기술이라고 인정되는 것은 아니다.Unless otherwise indicated herein, the contents set forth in this section are not prior art to the claims of this application and are not to be construed as prior art to be included in this section.

일반적으로 건축, 토목 등의 건설현장에서 지반을 굴착하거나 절토, 성토하면서 발생하는 수직 또는 경사진 지반 지반은 불안정하여 붕괴 또는 낙석의 위험성이 있다. 따라서 안정된 지반이라고 하더라도 예상치 못한 원인으로 인한 사고를 예방하기 위해서 지반 보강공사가 시행된다.Generally, the vertical or inclined ground that is generated when excavating, cutting, or embanking the ground in the construction site such as construction or civil engineering is unstable, and there is a risk of collapse or fallout. Therefore, even if the ground is stable, ground reinforcement works will be implemented to prevent accidents caused by unexpected causes.

이러한 지반의 붕괴나 낙석 위험을 방지하기 위한 보강공사로는 크게 어스앵커(earth anchor)공법에 의한 보강공사와, 소일네일링(soil-nailing)공법과 록볼트(rockbolt)공법에 의한 보강공사로 나뉠 수 있다.Reinforcing works to prevent the collapse or fall of the ground are largely reinforced by earth anchor method, soil-nailing method and rockbolt method. It can be divided.

어스앵커 공법은 타이백(tie-back)공법이라고도 하는데, 흙막이 벽에 구멍을 뚫어 철근이나 PC강선을 집어넣은 다음, 모르타르를 그라우팅(grouting) 처리하고 후면에 앵커를 만들어 흙막이 벽을 잡아매는 공법이다. The earth anchor method is also called tie-back method, which is a method of drilling a hole in the earth retaining wall, inserting a reinforcing steel or a PC steel wire, grouting the mortar, and anchoring the back wall to hold the earth retaining wall.

또한, 소일네일링 공법은 흙속에 보강재를 삽입하여 안정을 도모하는 지반보강공법의 하나로 보강재를 프리스트레스 처리 없이 좁은 간격으로 지반에 삽입하여 지반 자체의 전체 강도를 증대시키는 공법이며, 록볼트 공법 또한 소일네일링 공법과 같은 방법으로 지반을 보강하는 공법이다.In addition, the soil nailing method is a method of reinforcing the ground by inserting stiffener into the soil and inserting the stiffener into the ground at a narrow interval without prestressing to increase the overall strength of the ground itself. It is a method to reinforce the ground in the same way as the nailing method.

이와 같은 어스앵커 공법이나 소일네일링 공법과 록볼트 공법은 공사도중 또는 공사가 마무리되고 난 후에 일어날 수 있는 지반의 변위가 억제되게 함으로써 지반의 붕괴 혹은 낙석발생이 방지되게 하는 효과가 발휘된다.The earth anchor method, the soil nailing method, and the rock bolt method have an effect of preventing the collapse of the ground or the occurrence of rockfall by suppressing the displacement of the ground which may occur during construction or after completion of the construction.

그런데 이러한 종래의 지반보강공법에서 지반에 삽입되는 보강재가 철근, 강선, 강봉과 같은 막대 형상으로 이루어져 있어 지반에 형성된 구멍 내에 모르타르가 그라우팅 처리가 된다 하더라도 지반 내부에 견고하게 고정 및 지지되지 못해 그라우팅의 상태나 시간경과에 따라 지반의 변위에 대한 억제력이 유지되지 못하는 단점이 있었다.However, in the conventional ground reinforcement method, since the reinforcing material inserted into the ground is formed into a rod shape such as a steel bar, a steel wire, and a steel bar, even if the mortar is subjected to grouting in the hole formed in the ground, And there is a disadvantage that the restraining force against the displacement of the ground can not be maintained according to the state or time elapse.

1. 대한민국 특허공개 제10-2006-0100790호(2006.09.21)1. Korean Patent Publication No. 10-2006-0100790 (2006.09.21) 2. 대한민국 특허공개 제10-2014-0124198호(2014.10.24)2. Korean Patent Publication No. 10-2014-0124198 (Apr. 24, 2014) 3. 대한민국 특허공개 제10-2001-0086663호(2001.09.15)3. Korean Patent Publication No. 10-2001-0086663 (September 15, 2001)

삽입구멍 내에 삽입되는 보강재의 단부가 견인시 확장되게 하여 고정력이 최대화되게 하고, 프리스트레스 처리될 수 있게 보강재가 견인된 상태에서 지반 측에 고정될 수 있는 프리스트레스 보강재를 이용한 지반보강장치를 제공하고자 한다.The present invention is to provide a ground reinforcement apparatus using a prestressing reinforcement which is capable of being extended when the stiffener is inserted into the insertion hole to maximize the clamping force and fixed to the ground in a state where the stiffener is pulled so as to be prestressed.

하나의 실시 예로서 개시된 내용은 후방 측은 지반에 굴착 형성된 삽입구멍 내부에 삽입되고 전방 측은 상기 삽입구멍의 외부로 노출되며 전단 외주연에는 제 1 나사산이, 후단 외주연에 제 2 나사산이 각각 형성된 보강재와, 상기 보강재의 후단 측에 결합 된 상태로 상기 삽입구멍 내에 위치되되 전방에는 상기 보강재의 후단이 삽입되어 나사결합 될 수 있도록 그 내주연에 상기 제 2 나사산과 나사결합 되는 제 3 나사산이 형성된 결합부재가 구비되고, 후방에는 전방에서 후방으로 갈수록 다단으로 확장되는 톱니형 다단확장유도부재가 원추형상으로 형성되며, 상기 결합부재와 상기 톱니형 다단확장유도부재 사이의 외주연에는 제 4 나사산이 형성된 견인부와, 상기 톱니형 다단확장유도부재의 외부에 위치되되 내주연에는 상기 톱니형 다단확장유도부재에 면접되는 다단확장톱니홈이 전방에서 후방으로 갈수록 다단으로 확장되게 형성되고, 외주연에는 상기 제 4 나사산 방향으로 돌출된 다수의 파지돌기가 형성되어 상기 보강재가 전방 측으로 견인될 때 상기 톱니형 다단확장유도부재가 전방으로 이동됨에 따라 다단으로 확장되면서 상기 파지돌기가 상기 삽입구멍 내부에 삽입 고정되는 확장부와, 상기 견인부가 그 내부에 관통 위치된 상태로 상기 제 4 나사산과 선택적으로 나사결합 될 수 있도록 그 내주연에 제 5 나사산이 형성되고, 상기 톱니형 다단확장유도부재와 커넥터에 의해 연결되는 고정부가 포함되는 프리스트레스 보강재를 이용한 지반보강장치에 대해 기술하고 있다.In the disclosed embodiment, the rear side is inserted into the insertion hole formed on the ground and the front side is exposed to the outside of the insertion hole, and the first thread is formed on the outer periphery of the shearing and the second thread is formed on the outer periphery of the rear end And a third screw thread formed on the inner circumference of the first screw thread so as to be screwed with the second screw thread so that the rear end of the stiffener can be inserted and screwed in front of the insert hole in a state of being coupled to the rear end side of the stiffener. Wherein a plurality of serration-type multi-stage extension guide members are formed in a conical shape extending from the front to the rear in a multi-step manner, and a fourth thread is formed on an outer periphery between the coupling member and the multi- And an outer periphery of the sawtooth multi-stage expansion induction member, And a plurality of grip protrusions protruding in the fourth thread direction are formed on the outer circumference of the plurality of grip protrusions so that when the stiffener is pulled toward the front side, An enlarged portion in which the gripping protrusion is inserted and fixed in the insertion hole while being extended in a multi-stage as the multi-stage expanding guide member is moved forward; and an enlarged portion in which the gripping portion is inserted into the insertion hole, And a fifth screw thread is formed on the inner periphery thereof so as to be able to be engaged with the threaded multi-stage extension guide member, and the fixing portion connected by the connector is connected to the toothed multi-stage extension guide member.

이상에서와 같은 프리스트레스 보강재를 이용한 지반보강장치에 의하면, 삽입구멍 내부로 삽입되는 보강재의 단부에 견인 여부에 따라 방사상 확장되는 확장부가 구비되어 있어 보강재가 삽입구멍 내부에 견고하게 지지 될 수 있고, 확장부에 의해 그 후단이 지지 된 상태에서 전방 측으로 견인된 보강재는 프리스트레스 상태가 되고 이 상태에서 보강재가 지반에 고정됨으로써 지반의 변위에 대한 억제력이 극대화되어 지반의 붕괴 또는 슬라이딩에 따른 낙석사고가 방지될 수 있는 탁월한 장점을 갖는다.According to the ground reinforcing apparatus using the prestress reinforcement as described above, the reinforcing member can be firmly supported in the insertion hole by the radially expanding portion provided at the end of the reinforcing member inserted into the insertion hole, The stiffener pulled to the front side in the state where the rear end is supported by the part becomes a prestressed state and the stiffener is fixed to the ground in this state to maximize the restraining force against the displacement of the ground to prevent the falling rock caused by the collapse or sliding of the ground It has an excellent advantage.

도 1은 개시된 내용의 일 실시 예에 따른 프리스트레스 보강재를 이용한 지반보강장치의 사시도.
도 2는 개시된 내용의 일 실시 예에 따른 프리스트레스 보강재를 이용한 지반보강장치의 작동 단면도.
도 3은 개시된 내용의 일 실시 예에 따른 프리스트레스 보강재를 이용한 지반보강장치의 사용상태도.
1 is a perspective view of a ground reinforcement apparatus using a prestressing reinforcement according to an embodiment of the disclosure;
2 is an operational cross-sectional view of a ground reinforcement apparatus using a prestressing stiffener according to an embodiment of the disclosure.
FIG. 3 is a use state view of a ground reinforcement apparatus using a prestressing reinforcement according to an embodiment of the disclosure; FIG.

개시된 내용의 이점 및 특징, 그리고 그것들을 달성하는 방법은 첨부되는 도면과 함께 상세하게 후술되어 있는 실시 예들을 참조하면 명확해질 것이다. 그러나 개시된 내용은 이하에서 개시되는 실시 예들에 한정되는 것이 아니라 서로 다른 다양한 형태로 구현될 수 있으며, 단지 본 실시 예들은 개시된 내용의 개시가 완전하도록 하고, 개시된 내용이 속하는 기술분야에서 통상의 지식을 가진 자에게 개시된 내용의 범주를 완전하게 알려주기 위해 제공되는 것이며, 개시된 내용은 청구항의 범주에 의해 정의될 뿐이다. 명세서 전체에 걸쳐 동일 도면부호는 동일 구성 요소를 지칭한다.Brief Description of the Drawings The advantages and features of the disclosed subject matter, and how to accomplish them, will become apparent with reference to the embodiments described in detail below with reference to the accompanying drawings. It is to be understood, however, that the disclosure is not limited to the embodiments set forth herein, but may be embodied in many different forms and should not be construed as limited to the embodiments set forth herein, But is provided only to fully disclose the scope of the disclosure to those with ordinary skill in the art, and the disclosure is only defined by the scope of the claims. Like numbers refer to like elements throughout.

개시된 내용의 실시 예들을 설명함에 있어서 공지 기능 또는 구성에 대한 구체적인 설명이 개시된 내용의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명을 생략할 것이다. 그리고 후술 되는 용어들은 개시된 내용의 실시 예에서의 기능을 고려하여 정의된 용어들로서 이는 사용자, 운용자의 의도 또는 관례 등에 따라 달라질 수 있다. 그러므로 그 정의는 본 명세서 전반에 걸친 내용을 토대로 정류기내려져야 할 것이다.The detailed description of known functions and configurations incorporated herein will be omitted when it may obscure the subject matter of the present disclosure. It is to be understood that both the foregoing general description and the following detailed description of the present invention are exemplary and explanatory and are intended to provide further explanation of the invention as claimed. Therefore, the definition should be based on the contents of this specification.

도 1에서 도 3은 개시된 내용에 따른 하나의 실시 예를 도시하고 있다. 도 1은 사시도이고, 도 2는 작동도이며, 도 3은 사용상태도이다.Figures 1 to 3 illustrate one embodiment according to the teachings of the present invention. Fig. 1 is a perspective view, Fig. 2 is an operational view, and Fig. 3 is a state of use.

이하에는 도 1 및 도 2를 참조하여 개시된 내용의 일 실시 예에 따른 프리스트레스 보강재를 이용한 지반보강장치(1)의 구성부재와 그 연결관계에 대해서 상세하게 설명하기로 한다.Hereinafter, the constituent members of the ground reinforcing apparatus 1 using the prestressing reinforcement according to an embodiment of the present invention with reference to FIGS. 1 and 2 will be described in detail.

먼저, 도 1을 참조하면, 보강재(100)는 선형의 막대형상으로 형성되며 강선을 사용시에는 별도의 결합장치로 구성된다. 그리고 그 양단은 지반 내부와 지반에 적층 시공되는 블록에 프리스트레스 상태로 연결 고정되어 지반의 붕괴, 낙석 발생과 같은 사고가 방지되게 하는 역할을 한다.First, referring to FIG. 1, the stiffener 100 is formed into a linear rod shape, and when the steel wire is used, it is formed of a separate coupling device. Both ends of the ground are connected and fixed in a block that is built up in the ground and in the ground so as to prevent accidents such as the collapse of the ground and the occurrence of rockfall.

이러한 보강재(100)는 그 후방 측이 지반에 굴착 형성된 삽입구멍(800) 내부에 삽입되고 전방 측은 상기 삽입구멍(800)의 외부로 노출된다. 이때 그 전단 외주연에는 제 1 나사산(110)이, 후단 외주연에 제 2 나사산(120)이 각각 형성된다. The stiffener 100 is inserted into the insertion hole 800 where the rear side thereof is excavated on the ground, and the front side is exposed to the outside of the insertion hole 800. At this time, a first thread 110 is formed on the outer periphery of the front end, and a second thread 120 is formed on the outer periphery of the rear end.

전술한 보강재(100)는 견인과 동시에 그 후방 측이 삽입구멍(800) 내에 고정되고 이 상태에서 전방 측이 추후에 설명될 라이너스크류 유닛(500)에 의해서 고정됨으로써 프리스트레스 상태로 설치된다. 이와 같은 보강재(100)는 지반의 전반적인 상태를 고려해 다양한 두께 및 길이로 가공되며, 보강재(100) 외에 강선 또는 강봉이 사용될 수도 있다.The above-described reinforcing member 100 is installed in a prestressed state by being fixed within the insertion hole 800 while its rear side is fixed by the liner screw unit 500 to be described later. The reinforcing member 100 may be manufactured to have various thicknesses and lengths in consideration of the overall condition of the ground. In addition to the reinforcing member 100, a steel wire or a steel bar may be used.

한편, 전술한 보강재(100)의 후단 측에는 견인부(200)가 결합 되는데, 이 견인부(200)는 보강재(100)의 견인 여부에 따라 추후에 설명될 확장부(300)가 확장되게 하는 역할을 한다. 이러한 확장부(300)는 보강재(100)에 결합 된 상태로 삽입구멍(800) 내에 위치되되 전방에는 보강재(100)의 후단이 삽입되어 나사결합 될 수 있도록 그 내주연에 제 2 나사산(120)과 나사결합 되는 제 3 나사산(211)이 형성된 결합부재(210)가 구비된다. 그리고 후방에는 전방에서 후방으로 갈수록 다단으로 확장되는 톱니형 다단확장유도부재(220)가 원추형상으로 형성된다. 또한, 결합부재(210)와 톱니형 다단확장유도부재(220) 사이의 외주연에는 제 4 나사산(230)이 형성된다.The traction unit 200 is coupled to the rear end of the stiffener 100. The traction unit 200 extends the expansion unit 300 to be described later depending on whether the stiffener 100 is pulled or not . The enlarged portion 300 is positioned in the insertion hole 800 in a state of being coupled to the stiffener 100 and a second thread 120 is provided on the inner circumference of the enlarged portion 300 so that the rear end of the stiffener 100 can be inserted and screwed. And a coupling member 210 having a third thread 211 threadedly engaged with the coupling member 210. In the rear, a sawtooth multi-stage extension guide member 220 is formed in a conical shape extending from the front to the rear in a multistage manner. In addition, a fourth thread 230 is formed on the outer circumference between the coupling member 210 and the sawtooth multi-stage extension guide member 220.

이때 제 2 나사산(120)과 제 3 나사산(211)은 오른 방향으로 결합 되는데, 이는 추후에 설명될 제 4 나사산(230)과 제 5 나사산(410)은 왼 방향으로 나사결합 되기 때문이다. 즉, 보강재(100)와 고정부(400)는 제 4 나사산(230)과 제 5 나사산(410)의 나사결합이 해제되는 방향으로 회전되면서 견인되는데, 이때 제 2 나사산(120)과 제 3 나사산(211)의 나사결합이 함께 해제되는 것이 방지되게 하기 위함이다. 그리고 전술한 톱니형 다단확장유도부재(220)는 보강재(100)의 견인시 확장부(300) 내에서 전진되며 확장부(300)를 확장시킨다. 이를 위해서 그 외주연은 다단으로 확장되는 경지반을 갖는다. 또한, 제 4 나사산(230)은 보강재(100) 삽입시 고정부(400)가 위치 고정되게 하는 역할을 한다.At this time, the second thread 120 and the third thread 211 are coupled to each other in the right direction because the fourth thread 230 and the fifth thread 410 to be described later are screwed to the left. That is, the stiffener 100 and the fixing part 400 are pulled while being rotated in the direction in which the threaded connection between the fourth thread 230 and the fifth thread 410 is released. At this time, the second thread 120 and the third thread So that the threaded engagement of the threaded portion 211 is prevented from being released together. The sawtooth multi-stage extension guide member 220 is advanced in the extension portion 300 when the stiffener 100 is pulled, and extends the extension portion 300. For this purpose, the other edge has a ground plane that extends into multiple stages. The fourth screw thread 230 serves to fix the fixing part 400 when the stiffener 100 is inserted.

다음으로, 도 2를 참조하면, 전술한 톱니형 다단확장유도부재(220) 외부에는 확장부(300)가 위치된다. 이 확장부(300)는 톱니형 다단확장유도부재(220)의 전진시 방사상 확장되면서 삽입구멍(800) 내부에 고정되어 보강재(100) 후방이 삽입구멍(800) 내에 견고하게 위치 고정되게 하는 역할을 한다. 이러한 확장부(300)는 그 내주연에 톱니형 다단확장유도부재(220)에 면접되는 다단확장톱니홈(310)이 전방에서 후방으로 갈수록 다단으로 확장되게 형성된다. 그리고 그 외주연에는 제 4 나사산(230) 방향으로 돌출된 다수의 파지돌기(320)가 형성된다. 따라서 보강재(100)가 전방 측으로 견인될 때 톱니형 다단확장유도부재(220)가 전방으로 이동됨에 따라 다단으로 확장되면서 파지돌기(320)가 삽입구멍(800) 내부에 삽입 고정된다. 이때 파지돌기(320)는 삽입구멍(800) 내부에 그 일부가 고정되고, 삽입구멍(800) 내에 그라우팅(900, grouting) 시공되는 부분에도 지지된다.Next, referring to FIG. 2, the extended portion 300 is positioned outside the sawtooth multi-stage extension guide member 220 described above. The extension portion 300 is radially expanded when the toothed multi-stage extension guide member 220 is advanced, and is fixed inside the insertion hole 800, so that the rear of the stiffener 100 is firmly fixed in the insertion hole 800 . The extension portion 300 is formed at the inner periphery of the extension portion 300 so that the multi-stage extended toothed grooves 310 are extended in a multi-step manner from the front to the back. And a plurality of grip protrusions 320 protruding in the direction of the fourth screw thread 230 are formed on the outer periphery thereof. Accordingly, when the stiffener 100 is pulled forward, the grip protrusion 320 is inserted and fixed in the insertion hole 800 while being extended in multiple stages as the sawtooth multi-stage extension guide member 220 is moved forward. At this time, the grip protrusion 320 is partly fixed to the inside of the insertion hole 800 and is also supported at a portion where the grouting (900) is applied in the insertion hole 800.

전술한 확장부(300)는 톱니형 다단확장유도부재(220)에 비해 그 길이가 길게 형성된다. 이는 보강재(100)의 견인시 톱니형 다단확장유도부재(220)가 확장부(300)의 후방에서 전방으로 충분히 이동되는 공간이 확보되어야 하기 때문이다. 따라서 고정부(400)가 제 4 나사산(230)에 나사결합 된 상태에서는 톱니형 다단확장유도부재(220)가 확장부(300)의 내측 후방에 위치되고, 보강재(100)가 견인됨에 따라 톱니형 다단확장유도부재(220)가 확장부(300) 내부에서 전방으로 서서히 이동되어 확장부(300)가 방사상 확장되게 한다. 이때 전술한 확장부(300)는 보강재(100)의 견인시 삼분할 되면서 방사상 확장되도록 보강재(100)의 길이 방향으로 절개선이 형성된다.The extended portion 300 is formed to have a longer length than the sawtooth multi-stage extension guide member 220. This is because it is necessary to secure a space in which the sawtooth multi-stage extension guide member 220 is sufficiently moved forward from the rear of the extension portion 300 when the stiffener 100 is pulled. Accordingly, in a state where the fixing portion 400 is screwed to the fourth thread 230, the sawtooth multi-stage extension guide member 220 is positioned on the inner rear side of the expansion portion 300, and as the stiffener 100 is pulled, Shaped multi-stage extension guide member 220 is gradually moved forward within the extended portion 300 so that the extended portion 300 is radially expanded. At this time, the enlargement 300 is formed in the lengthwise direction of the stiffener 100 so as to radially expand the stiffener 100 by three times when the stiffener 100 is pulled.

그리고 전술한 제 4 나사산(230)에는 고정부(400)가 선택적으로 나사결합 된다. 이 고정부(400)는 보강재(100) 삽입시 확장부(300)가 톱니형 다단확장유도부재(220) 측에서 임의로 이탈되지 않게 하는 역할을 한다. 이를 위해 고정부(400)와 톱니형 다단확장유도부재(220)는 커넥터(420)에 의해 연결되며, 내주연에는 제 4 나사산(230)과 나사결합되는 제 5 나사산(410)이 형성된다. 이때 전술한 커넥터(420)는 확장부(300)의 확장시 회동 될 수 있도록 그 양단이 상기 톱니형 다단확장유도부재(220) 및 고정부(400)와 각각 힌지 연결된다.The fixing portion 400 is selectively screwed to the fourth thread 230 described above. The fixing part 400 serves to prevent the extension part 300 from being detached from the sawtooth multi-stage extension guide member 220 when the reinforcing member 100 is inserted. To this end, the fixing portion 400 and the serrated multi-stage extension guide 220 are connected by a connector 420, and a fifth thread 410 is screwed to the fourth thread 230 on the inner circumference. At this time, both ends of the connector 420 are hingedly connected to the toothed multi-stage extension guide member 220 and the fixing portion 400 so that the connector 420 can be rotated when the extension portion 300 is extended.

따라서 보강재(100)가 삽입구멍(800) 내부에 삽입될 때에는 확장부(300)가 임의 확장되지 않고 톱니형 다단확장유도부재(220) 상에 정위치 될 수 있도록 제 5 나사산(410)이 제 4 나사산(230)과 나사결합 된 상태에서 삽입된다. 또한, 보강재(100)가 삽입구멍(800) 내에서 견인될 때에는 제 4 나사산(230) 및 제 5 나사산(410)의 나사결합이 해제되는 방향으로 회전되면서 지반에 굴착 형성된 삽입구멍(800)의 외부 방향으로 견인된다. 보강재(100)를 강선으로 사용할 때에는 별도의 결합구를 이용하여 지반보강장치에 나사로 조립하여 사용된다.When the reinforcing member 100 is inserted into the insertion hole 800, the fifth screw thread 410 is inserted into the insertion hole 800 so that the extension portion 300 can be positively positioned on the toothed multi- 4 thread 230 with a screw thread. When the stiffener 100 is pulled in the insertion hole 800, the threaded engagement of the fourth thread 230 and the fifth thread 410 is released in the direction of releasing the insertion hole 800 It is pulled outwardly. When the reinforcing member 100 is used as a steel wire, it is assembled by screwing it into a ground reinforcement apparatus by using a separate coupling hole.

이하에는 도 3을 참조하여 개시된 내용의 일 실시 예에 따른 프리스트레스 보강재를 이용한 지반보강장치(1)의 전체적인 시공방법에 대해서 상세하게 설명하기로 한다.Hereinafter, the overall construction method of the ground reinforcement apparatus 1 using the prestress reinforcement according to an embodiment of the present invention with reference to FIG. 3 will be described in detail.

먼저, 지반에 다수의 삽입구멍(800)을 굴착 시공하고, 삽입구멍(800) 내에 보강재(100)의 후방 측이 삽입되게 한다. 보강재(100) 후단에는 견인부(200)가 결합 되는데, 견인부(200)의 제 4 나사산(230)에는 고정부(400) 나사결합 된 상태로 위치되고, 견인부(200)의 톱니형 다단확장유도부재(220) 상에는 확장부(300)가 각각 위치된다.First, a plurality of insertion holes 800 are drilled in the ground, and the rear side of the reinforcing member 100 is inserted into the insertion holes 800. A trailing portion 200 is coupled to the rear end of the stiffener 100. The fixing portion 400 is screwed to the fourth thread 230 of the traction portion 200 and the sawtooth multi- An extension 300 is positioned on the extension guide member 220, respectively.

보강재(100)가 삽입되면 삽입구멍(800) 내부가 모르타르에 의해 그라우팅(900) 시공된다. 그라우팅(900) 시공된 부분의 양생이 시작되어 경화가 완료되기 전에 보강재(100)을 오른 방향으로 회전시키며 견인하게 되는데, 이때 왼 방향으로 나사결합된 제 4 나사산(230)과 제 5 나사산(410)이 서서히 분리된다.When the stiffener 100 is inserted, the inside of the insertion hole 800 is grouted 900 by mortar. The curing of the portion where the grouting 900 is applied is started and the reinforcing member 100 is rotated in the right direction before the hardening is completed. At this time, the fourth screw thread 230 and the fifth screw thread 410 ) Are gradually separated.

동시에, 톱니형 다단확장유도부재(220)가 확장부(300)의 후방에서 전방으로 견인되면서 확장부(300)가 방사상 확장된다. 또한, 확장부(300) 외측에 형성된 파지돌기(320)가 삽입구멍(800)의 내부에 견고하게 고정된다At the same time, the extended portion 300 is radially expanded while the serrated multi-stage extension guide member 220 is pulled forward from the rear of the extended portion 300. In addition, the holding protrusion 320 formed outside the extending portion 300 is firmly fixed to the inside of the insertion hole 800

고정부(400)의 제 5 나사산(410)과 견인부(200)의 제 4 나사산(230) 간의 나사결합이 완전히 해제되면 이때부터 보강재(100)는 회전 또는 회전되지 않는 상태로 견인되는데 확장부(300)가 더이상 확장되지 않을 때까지 견인된다.When the threaded connection between the fifth thread 410 of the fixing part 400 and the fourth thread 230 of the pulling part 200 is completely released, the stiffener 100 is pulled in a state in which it is not rotated or rotated. (300) is no longer extended.

견인이 마무리된 보강재(100)는 견인된 상태에서 라이너스크류 유닛(500)에 의해 지반 측에 고정되어 프리스트레스 상태로 설치된다. 여기서 라이너스크류 유닛(500)은, 보강재(100)가 그 중앙에 관통된 상태로 삽입구멍(800)이 형성된 지반에 면접 위치되는 지압판(510)과, 보강재(100)가 그 중앙에 관통된 상태로 지압판(510) 상에 면접 위치되는 라이너스크류(520)와, 라이너스크류(520) 외주연에 나사결합 되어 보강재(100)의 프리스트레스 상태로 고정되게 하는 고정너트(530)가 포함된다.The traction finished stiffener 100 is fixed to the ground side by the liner screw unit 500 in a pulled state and installed in a prestressed state. Here, the liner screw unit 500 includes a pressure plate 510 placed in an interfacial position where the insertion hole 800 is formed in a state where the reinforcing member 100 passes through the center thereof, and a state in which the reinforcing member 100 passes through the center thereof And a fixing nut 530 screwed to the outer periphery of the liner screw 520 to fix the stiffener 100 in a prestressed state.

이러한 라이너스크류 유닛(500)은 종래기술에 따른 라이너스크류와 동일한 것으로 하여 더 이상의 구체적인 설명은 명세서의 간략화를 위해서 생략하기로 한다.The liner screw unit 500 is the same as the liner screw according to the prior art, and the detailed description will be omitted for simplification of the description.

그라우팅(900) 시공된 부분이 완전히 경화되면 보강재(100)의 전방 측은 지반에 적층 시공되는 하나의 블록(700)에 관통 위치된다. 그리고 블록(700) 외부로 돌출된 보강재(100) 전단의 제 1 나사산(110)에는 블록(700)의 전면에 지지 고정되는 캡부재(600)가 나사결합된다.When the grouting portion 900 is completely cured, the front side of the reinforcing member 100 is positioned in a block 700 that is stacked on the ground. A cap member 600 secured to the front surface of the block 700 is screwed to the first thread 110 of the front end of the stiffener 100 protruding from the block 700.

이상에서와 같은 프리스트레스 보강재를 이용한 지반보강장치(1)는 삽입구멍(800) 내부로 삽입되는 보강재(100)의 단부에 견인 여부에 따라 방사상 확장되는 확장부(300)가 구비되어 있어 보강재(100)가 삽입구멍(800) 내부에 견고하게 지지 될 수 있고, 확장부(300)에 의해 그 후단이 지지 된 상태에서 전방 측으로 견인된 보강재(100)는 프리스트레스 상태가 되고 이 상태에서 보강재가 지반에 고정됨으로써 지반의 변위에 대한 억제력이 극대화되어 지반의 붕괴 또는 슬라이딩에 따른 낙석사고가 방지될 수 있다.The ground reinforcing apparatus 1 using the prestress reinforcement as described above is provided with an extension 300 extending radially depending on whether the reinforcing member 100 is inserted into the insertion hole 800 or not, Can be firmly supported in the insertion hole 800 and the stiffener 100 pulled to the front side in the state where the rear end thereof is supported by the extended portion 300 is in a prestressed state and in this state, The restraining force against the displacement of the ground is maximized, and the rockfall accident due to the collapse or sliding of the ground can be prevented.

개시된 내용은 예시에 불과하며, 특허청구범위에서 청구하는 청구의 요지를 벗어나지 않고 당해 기술자라면 통상의 지식을 가진 자에 의하여 다양하게 변경 실시될 수 있으므로, 개시된 내용의 보호범위는 상술한 특정의 실시 예에 한정되지 않는다.It will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined by the appended claims. But is not limited to the example.

1 : 프리스트레스 보강재를 이용한 지반보강장치
100 : 보강재
110 : 제 1 나사산
120 : 제 2 나사산
200 : 견인부
210 : 결합부재
211 : 제 3 나사산
220 : 톱니형 다단확장유도부재
230 : 제 4 나사산
300 : 확장부
310 : 다단확장톱니홈
320 : 파지돌기
400 : 고정부
410 : 제 5 나사산
420 : 커넥터
500 : 라이너스크류 유닛
510 : 지압판
520 : 라이너스크류
530 : 고정너트
600 : 캡부재
700 : 블록
800 : 삽입구멍
900 : 그라우팅
1: Ground reinforcement system using prestress reinforcement
100: Stiffener
110: First thread
120: Second thread
200:
210:
211: Third thread
220: serrated multi-stage extension guide member
230: fourth thread
300: Extension part
310: Multistage extended sawtooth groove
320:
400:
410: fifth thread
420: Connector
500: liner screw unit
510:
520: liner screw
530: Fixing nut
600: cap member
700: Block
800: Insertion hole
900: Grouting

Claims (9)

후방 측은 지반에 굴착 형성된 삽입구멍 내부에 삽입되고 전방 측은 상기 삽입구멍의 외부로 노출되며 전단 외주연에는 제 1 나사산이, 후단 외주연에 제 2 나사산이 각각 형성된 보강재;
상기 보강재의 후단 측에 결합 된 상태로 상기 삽입구멍 내에 위치되되 전방에는 상기 보강재의 후단이 삽입되어 나사결합 될 수 있도록 그 내주연에 상기 제 2 나사산과 나사결합 되는 제 3 나사산이 형성된 결합부재가 구비되고, 후방에는 전방에서 후방으로 갈수록 다단으로 확장되는 톱니형 다단확장유도부재가 원추형상으로 형성되며, 상기 결합부재와 상기 톱니형 다단확장유도부재 사이의 외주연에는 제 4 나사산이 형성된 견인부;
상기 톱니형 다단확장유도부재의 외부에 위치되되 내주연에는 상기 톱니형 다단확장유도부재에 면접되는 다단확장톱니홈이 전방에서 후방으로 갈수록 다단으로 확장되게 형성되고, 외주연에는 상기 제 4 나사산 방향으로 돌출된 다수의 파지돌기가 형성되어 상기 보강재가 전방 측으로 견인될 때 상기 톱니형 다단확장유도부재가 전방으로 이동됨에 따라 다단으로 확장되면서 상기 파지돌기가 상기 삽입구멍 내부에 삽입 고정되는 확장부; 및
상기 견인부가 그 내부에 관통 위치된 상태로 상기 제 4 나사산과 선택적으로 나사결합 될 수 있도록 그 내주연에 제 5 나사산이 형성되고, 상기 톱니형 다단확장유도부재와 커넥터에 의해 연결되는 고정부;가 포함되고,
상기 보강재의 전방 측은 지반에 적층 시공되는 하나의 블록에 관통 위치되고, 상기 블록 외부로 돌출된 상기 제 1 나사산에는 상기 블록의 전면에 지지 고정되는 캡부재가 나사결합되는 프리스트레스 보강재를 이용한 지반보강장치.
A reinforcing member having a rear side inserted into the insertion hole formed by excavating on the ground, a front side exposed to the outside of the insertion hole, a first thread on the outer periphery of the sheath and a second thread on the outer periphery of the rear end;
A coupling member having a third screw thread formed on the inner circumference thereof so as to be screwed with the second screw thread so that the rear end of the stiffener can be inserted and screwed in front of the insertion hole while being coupled to the rear end side of the stiffener Wherein a plurality of serration-type multi-stage extension guide members are formed in the rear portion of the guide member in a conical shape extending from the front to the rear in a multi-step manner, ;
And a plurality of multi-step enlarged tooth grooves formed on the outer circumference of the toothed multi-step expanding guide member to be inserted into the plurality of multi-step expanding guide members, the multi-step extended toothed grooves being extended in a plurality of steps from the front to the back, A plurality of grip protrusions protruding from the plurality of grip protrusions are formed, and when the stiffener is pulled forward, the grip protrusion is inserted and fixed in the insertion hole while being extended in multiple stages as the toothed multi-stage extension guide member is moved forward; And
A fixing portion having a fifth thread formed on an inner periphery thereof so as to be selectively threadedly engaged with the fourth thread in a state where the pulling portion is penetrated into the fixing portion, the fixing portion being connected to the serration multi- / RTI >
Wherein the front side of the reinforcing member is inserted through one block which is laminated on the ground, and the first thread protruding out of the block is provided with a reinforcing member using a prestress reinforcement which is screwed to a cap member, .
청구항 1에 있어서,
상기 확장부는 상기 보강재의 견인시 삼분할 되면서 방사상 확장되도록 상기 보강재의 길이 방향으로 절개선이 형성되는 것을 특징으로 하는 프리스트레스 보강재를 이용한 지반보강장치.
The method according to claim 1,
Wherein the extension is formed in the longitudinal direction of the reinforcing member so as to be radially expanded when the reinforcing member is pulled in three times.
청구항 2에 있어서,
상기 커넥터는 상기 확장부의 확장시 회동 될 수 있도록 그 양단이 상기 톱니형 다단확장유도부재 및 고정부와 각각 힌지 연결되는 것을 특징으로 하는 프리스트레스 보강재를 이용한 지반보강장치.
The method of claim 2,
Wherein both ends of the connector are hingedly connected to the toothed multi-stage extension guide member and the fixing unit, respectively, so that the connector can be pivoted when the extension unit is extended.
청구항 1에 있어서,
상기 고정부는 상기 보강재가 상기 삽입구멍 내부에 삽입될 때 상기 확장부가 임의 확장되지 않고 상기 톱니형 다단확장유도부재 상에 정위치 될 수 있도록 상기 제 5 나사산이 상기 제 4 나사산과 나사결합 된 상태에서 삽입되는 것을 특징으로 하는 프리스트레스 보강재를 이용한 지반보강장치.
The method according to claim 1,
Wherein the fixing portion is in a state in which the fifth thread is screwed with the fourth thread so that when the stiffener is inserted into the insertion hole, the extension is not arbitrarily expanded but can be positively positioned on the toothed multi- Wherein the prestressing reinforcement is inserted into the ground reinforcement.
청구항 4에 있어서,
상기 보강재는 상기 제 4 나사산 및 상기 제 5 나사산의 나사결합이 해제되는 방향으로 회전되면서 지반에 굴착 형성된 삽입구멍의 외부 방향으로 견인되는 것을 특징으로 하는 프리스트레스 보강재를 이용한 지반보강장치.
The method of claim 4,
Wherein the stiffener is pulled outwardly of an insertion hole formed in the ground while being rotated in a direction in which the threaded engagement of the fourth thread and the fifth thread is released.
청구항 5에 있어서,
상기 제 1 나사산 및 상기 제 3 나사산은 오른 방향으로 나사결합 되고, 상기 제 4 나사산과 상기 제 5 나사산은 왼 방향으로 나사결합 되는 것을 특징으로 하는 프리스트레스 보강재를 이용한 지반보강장치.
The method of claim 5,
Wherein the first thread and the third thread are screwed in the right direction and the fourth thread and the fifth thread are threaded in the left direction.
청구항 6에 있어서,
상기 보강재는 견인된 상태에서 라이너스크류 유닛에 의해 지반 측에 고정되어 프리스트레스 상태로 설치되는 것을 특징으로 하는 프리스트레스 보강재를 이용한 지반보강장치.
The method of claim 6,
Wherein the reinforcing member is fixed to the ground side by the liner screw unit in a pulled state and installed in a prestressed state.
청구항 7에 있어서 상기 라이너스크류 유닛은,
상기 보강재가 그 중앙에 관통된 상태로 상기 삽입구멍이 형성된 지반에 면접 위치되는 지압판;
상기 보강재가 그 중앙에 관통된 상태로 상기 지압판 상에 면접 위치되는 라이너스크류; 및
상기 라이너스크류 외주연에 나사결합 되어 상기 보강재의 프리스트레스 상태로 고정되게 하는 고정너트;가 포함되는 것을 특징으로 하는 프리스트레스 보강재를 이용한 지반보강장치.
The liner screw unit according to claim 7,
A screed plate placed in an interfacial state on a ground where the insertion hole is formed in a state where the reinforcing member passes through the center thereof;
A liner screw placed on the support plate in a state where the reinforcement member penetrates the center thereof; And
And a fixing nut screwed to the outer periphery of the liner screw to fix the stiffener in a prestressed state.
삭제delete
KR1020160145162A 2016-11-02 2016-11-02 Stability apparatus for ground having prestressed stiffener KR101783439B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160145162A KR101783439B1 (en) 2016-11-02 2016-11-02 Stability apparatus for ground having prestressed stiffener

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160145162A KR101783439B1 (en) 2016-11-02 2016-11-02 Stability apparatus for ground having prestressed stiffener

Publications (1)

Publication Number Publication Date
KR101783439B1 true KR101783439B1 (en) 2017-09-29

Family

ID=60035594

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160145162A KR101783439B1 (en) 2016-11-02 2016-11-02 Stability apparatus for ground having prestressed stiffener

Country Status (1)

Country Link
KR (1) KR101783439B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102540069B1 (en) * 2021-12-27 2023-06-05 한국건설기술연구원 Micropile equipped with a cone-shaped tip acupressure device considering the action distribution load during installation and its construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100961284B1 (en) * 2009-09-10 2010-06-03 주식회사 건화 Soil nailing apparatus and constructing method thereof
KR101299432B1 (en) * 2013-02-07 2013-08-29 김철환 Sting style anchor with sawtooth shaped wedge and construction method for the same

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100961284B1 (en) * 2009-09-10 2010-06-03 주식회사 건화 Soil nailing apparatus and constructing method thereof
KR101299432B1 (en) * 2013-02-07 2013-08-29 김철환 Sting style anchor with sawtooth shaped wedge and construction method for the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102540069B1 (en) * 2021-12-27 2023-06-05 한국건설기술연구원 Micropile equipped with a cone-shaped tip acupressure device considering the action distribution load during installation and its construction method

Similar Documents

Publication Publication Date Title
US8998541B2 (en) Rock bolt
KR100958696B1 (en) Pretention nailing method by using wedge force
KR100861938B1 (en) The earth anchor and construction method for use of that
US9732614B2 (en) Device, method and system for loading fixatives for rock bolts
KR100978629B1 (en) Soil nailing for reinforce slope and method for reinforce slope using thereof
KR101783439B1 (en) Stability apparatus for ground having prestressed stiffener
KR101471487B1 (en) multipurpose load dispersion style ground anchor assembly
KR101041362B1 (en) Earth anchor for reinforcing and stabilizing slopes and the ground stabilization method using the same
AU2016100070A4 (en) Grout Anchored Rock Bolt
KR20130029906A (en) An expanding device of frictional force
KR101000569B1 (en) Slope reinforcement nailing for road and housing area and method which uses them
KR100696309B1 (en) Anchor-nail Device for Slope-reinforcement-construction
KR101460180B1 (en) Nail connectors for soil nailing method
KR101547320B1 (en) Structure of Permanent Anchor
KR100871467B1 (en) Ground pressure anchor and constructing method thereof
US20180291582A1 (en) Anchor having fixing device at side of pressure plate to depress land slope and method of installing same
KR102225888B1 (en) Ground pressure type anchor with wedge having maximum expansion property for cross slope
KR100873738B1 (en) The earth anchor
KR102022906B1 (en) Anchor and construction method thereof
KR20150035122A (en) Drill Root Pile And Construction Method Thereof
KR102054994B1 (en) Cylindrical wedge anchor for reinforcing the ground and method for constructing this same
KR20190131339A (en) Slope reinforcement apparatus using steel reinforced bar with hitch nail
KR101017412B1 (en) Permanent anchor of friction bearing pressure type and constructing method thereof
KR100913320B1 (en) Multifunctional complex type anchor body
KR101771423B1 (en) Anchor body for slope reinforcement

Legal Events

Date Code Title Description
AMND Amendment
AMND Amendment
X701 Decision to grant (after re-examination)
GRNT Written decision to grant